Offshore Workspace WP2 Task 7b Alternative Installation Methods
Offshore Workspace WP2 Task 7b Alternative Installation Methods
Offshore Workspace WP2 Task 7b Alternative Installation Methods
Written by:
Signature:
Date: 14-05-2002
version 0 1
No of pages 26 26+1
DOWEC-F1W1-xxx-yy-nnn/vv-C
Contents
1 2 INTRODUCTION.............................................................................................................................3 STARTING POINTS AND CONDITIONS .......................................................................................4 2.1 2.2 2.3 3 PROPOSED LOCATION.................................................................................................................4 NUMBER OF WIND TURBINES AND PLANNING ................................................................................4 DATA OF COMPONENTS ..............................................................................................................5
INSTALLATION ..............................................................................................................................5 3.1 OPTIONS FOR INSTALLATION .......................................................................................................5 3.2 INSTALLATION METHOD FOUNDATION MONO PILE .......................................................................6 3.2.1 Foundation Mono Pile by tilting Pontoon ..........................................................................6 3.2.2 Foundation Mono Pile by Svanen .....................................................................................9 3.3 INSTALLATION METHOD - OWEC ................................................................................................9 3.3.1 Preassembled OWECs ....................................................................................................9 3.3.2 Assembly on location by other ships ..............................................................................13 3.3.3 Assembly on location by Self elevating Platforms .........................................................13 3.4 OFFSHORE ASSEMBLY LOCATION ..............................................................................................13 3.4.1 Installation process .........................................................................................................13 3.4.2 General requirements .....................................................................................................14 3.4.3 Concepts.........................................................................................................................18 3.4.4 Concept I.........................................................................................................................18 3.4.5 Concept II........................................................................................................................21 3.4.6 Cost.................................................................................................................................25
Page 2 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Introduction
In WP1 task 12 installation of structure, a work method is described for building a wind farm at the location of site III. Site III is located about 20 km offshore. For installing OWECs relatively near shore it proved to be possible to completely built up the superstructure onshore and transport it by the Svanen to the site of the wind farm. Building a wind farm conform this installation method at he location of site VII, implicates that the sailing time of the Svanen will be that much that it will be difficult to install the desired amount of OWECs in the given time span. This document describes the use of an offshore workspace for assembly, and accommodation of working crew and eventually O&M crew. It also looks at the possibilities of sheltering the installation vessel Svanen during periods of unworkable sea conditions.
Page 3 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
The location of the wind park is 60 km offshore. For this report the DOWEC Site VII site is used. It is located in the North Sea west of Hoek van Holland (see map). Although the actual sailing distance of the site is 55 km for the purpose of the study it is assumed that the sailing distance is 60 km.
Figure 2.1-1: Location site VII approx. 60 km offshore of Hoek van Holland
2.2
This report is based on a total number of 80 turbines with a capacity of 6 MW each. The total number of turbines has to be installed in one year. The workability is based on DOWEC document DOWECF1W1-WB-01-047/00-C (Wind and Wave conditions).
Page 4 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
2.3
Data of components
Sizes and weights 6 MW hub height rotor diameter mast length water depth scour depth monopile diameter monopile top monopile length monopile wall thickness monopile toe depth transition piece top transition piece bottom transition piece length transition piece diameter transition piece wall thickness nacelle weight rotor weight blades weight mast weight Total weight OWEC transition piece weight monopile weight m m m m m m m m mm m m m m m mm ton ton ton ton ton ton ton 95 130 85 35 0 6 10 75 60 -65 10 0 10 6,42 60 203 91 111 316 721 94 659
3 Installation
3.1 Options for installation
The installation of 80 OWECs of 6 MW at a distance of 60 km results in a combination of problems. The main problem areas are how to install the big number of turbines in the required period of time. In the baseline case the Svanen was used to do the piling and the installation of the wind turbine of 2.75 MW. In this package the capacity of the Svanen in not sufficient to be able to install the whole park within the required time of on year (read one season). To solve the problem we need to; 1. Double the equipment as used in WP1 (baseline). 2. Break down the activities in smaller packages in order to spread the number of activities over more workflows. Ad 1. Double the equipment as used in WP1. The Sailing time for the 60 km location will be 60 km / 1.6 m/miles / 4 knots = 9.5 hours. This is from the Maasvlakte Harbour. This results in a total cycle time of the Svanen of 55.5 hours. (Att. Fair weather planning)
Page 5 of 25
14-05-02
Placing activities Svanen place anchors Svanen Activities by Svanen at on-shore yard Pick up foundation pile from shore Reposition Svanen Pick up Transition piece from shore Pick up J-tubes from shore Pick up windturbine from shore Sail to construction location Activities Svanen off-shore Placing windturbine Position Svanen and fix anchors Final positioning Saven Place windturbine Cleaning and coating touch-up Inspection by Consultant/Engineer Loosen anchors Placing foundation pile Relocate Svanen to next position (500 m) Pick-up foundation pile and place in template Final positioning and drive pile Install temporary works Prepare and pick up transition piece Place top structure and adjust Grouting preparation Grouting annulus Placing J-tube Pick-up J-tube assembly Place J-tube assembly Cleaning and coating touch-up Inspection by Consultant/Engineer Loosen anchors Sail back to harbour
Project: Dowec Svanen Fair Weather Date: 14-05-02 Task Split
55,5 hrs 5 hrs 17 hrs 2 hrs 1 hr 1 hr 0,5 hrs 3 hrs 9,5 hrs 38,5 hrs 12 hrs 4 hrs 1 hr 4 hrs 1 hr 1 hr 2 hrs 12 hrs 2 hrs 2 hrs 4 hrs 1 hr 1 hr 2 hrs 1 hr 2 hrs 14,5 hrs 1 hr 2 hrs 2 hrs 1 hr 2 hrs 9,5 hrs
Progress Milestone Summary Project Summary Page 1 External Tasks External Milestone Deadline
DOWEC-F1W1-xxx-yy-nnn/vv-C
Looking at the additional data from the DOWEC team it was clear that an availability of uninterrupted periods of 56 hours was 60 % during the spring and summer period. This results in a total project cycle time of 55,5 hours/ 0,6 * 80 turbines = 7400 hours. Taking an inefficiency factor of 20% the total number of hours needed is 8880 hours The available hours in the same period are 184 days = 4416 hours. By doubling the equipment the available production hours are 8832, which is just sufficient to finish the project in time. In this case the available work space on shore also has to be extended to at least 5 (1.67 times baseline area) temporary erection positions so that the onshore activities will match the production of the off shore activities. Ad 2. Break down the activities in smaller packages in order to spread the number of activities over more workflows Looking at the components of the total OWEC the following parts can be identified; Foundation pile Transition piece Mast Nacelle Rotor Blades A logical split can be laid at the top of the transition piece whereby the foundation installation procedure is separated from the mast and turbine. This results in two separate workflows with each having its own equipment. The separate workflows can be divided as various options; 1. Foundation 1. 2. 3. 4. 5. 2. Turbine mono pile tripod steel tripod concrete triple pile steel segmented mono pile
For this report we choose to look further into the solution whereby the foundation consists of a mono pile. We will also look at the methods for installing the OWEC pre-assembled as well as assembly on location.
3.2
DOWEC-F1W1-xxx-yy-nnn/vv-C
Page 7 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Depending on the sensitivity of the tilting pontoon for waves and wind the maximum wave height and wind speed for this operation can be determined. For the moment we assume a workability of 60 % (being equal to the base case). The whole proces will take 108 hours per cycle for 4 piles. This results in a total time of 20 * 108 hours / 0,6 = 3600 hours. Taking an inefficiency factor of 20 % the total time is 4320 hours which is within the set limits. (planning dpfw 60km piling by pontoon)
Page 8 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
3.3
Page 9 of 25
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
DOWEC-F1W1-xxx-yy-nnn/vv-C
Page 10 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
The maximum beam of the pontoon is limited to the distance between the legs of the Svanen, which is 22 m. For the reference OWEC this results in the pontoon being 22x67x4 meters. An alternative in order to omit the sliding of the OWEC from the shore position to the transport barge is to erect the OWEC on the barge. Instead of the sliding installation a heavier crane is now needed in order to be able to assemble the different components. If this is done it is sensible to consider using a gantry like crane so that the OWECs can be assembled in an industrial like assembly line. Where the transport pontoon is used as a building platform. The third option to install the preassembled OWECs is to transport several OWECs in per trip. This overcome the problem of transferring the load of the OWEC at open sea from the transport barge to the installation ship. However this means that the installation ship has to be purpose built for this solution. (Fig 3.3.1.1)
Page 11 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Page 12 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Page 13 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Element
Monopile, transitionpiece
Component
Foundation
System
Factory
Inland navigation
Europort
Transshipment seagoing barge
Seagoing barge
Wind farm
OWEC
Transshipment crane
Installation location
Page 14 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
The italic marked items are not taken into account. 1 Breakwater General design information For the design of a breakwater the following information is required: - Water depth; - Wave heights; - Frequency of occurrence of waves; - Wind data; - Soil data. Because this is a rough design for an indication of the cost of an offshore assembly location, Functionality Breakwaters are built along the offshore assembly location for different purposes namely: - Provide protection against waves; - Provide quieter water for ships to navigate and moor; - Guidance of currents in order to reduce the amount of scour protection. Types of breakwaters Generally speaking two different types of structures are used for breakwaters: - Rubble mound; - Monolithic. Many variations are possible based on the above-mentioned structures. Some of these variations are listed below. Composite Rubble mound front Permanent structure consisting of some form of monolithic vertical breakwater with a rubble mount form placed before and against it. Advantages: - Low reflection of waves; - Moderate material use; - Impervious to water and sediment; - Can provide quay facilities on lee side; - Can be built working from structure itself. Disadvantages: - Expensive form of new construction since it requires multiple construction techniques to be built.
Coastal Engineering, volume III Breakwater Design; edited by W.W. Massie, P.E.; January 1986; Technical University of Delft; The Netherlands. Page 15 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Figure 3.4-2: Composite - rubble mound front Composite vertical monolithic top A permanent structure consisting of a rubble mound base, surmounted by a monolithic vertical structure. Advantages: - Moderate use of material; - Adapts well to an uneven seafloor; - Provides a convenient promenade. Figure 3.4-3: Composite - vertical monolithic top Disadvantages: - Suffers from impact forces of largest waves; Reflects the largest waves that can damage the lower rubble mount portion; - Rubble mound must be carefully constructed in order to provide a good foundation for the monolithic top; - Destroyed when design conditions are exceeded. Monolithic porous front A permanent monolithic structure having a porous front wall which acts to absorb the oncoming wave energy. Advantages: - Uses relatively little material compared to rubble mound; - Less wave impact and reflection than conventional monolithic structures; - Needs little space; - Provides quay on lee side. Disadvantages: - Difficult to construct; - Need high quality concrete and workmanship; - Even seafloor needed; - Intolerant of settlement; - Foundation problems on fine sand; - Severe damage when design conditions exceeded. Monolithic sloping front A monolithic structure with the upper portion of the vertical face sloping back at an angle of about 45 degrees. Advantages: - Economical of material; - Rather quickly constructed; - Less wave impact and reflection if compared with conventional monolithic structures; - Needs little space; - Quay facilities can be provided on lee side. Disadvantages: - Needs even seafloor; - Intolerant of settlement; - Can have foundation problems on fine sand; - Severe damage if design condition exceeded. Monolithic sunken caisson A temporary structure floated into place and sunk and ballasted to form an initial breakwater. Often used to cut off currents so that it can then be buried in a permanent breakwater. Advantages: - Very quickly placed on the site; Page 16 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Can provide quay facilities on the lee side; Occupies little space; Uses little material; Provides promenade; Provides work road for later construction phases.
Disadvantages: - Size limited by towing limitations; - Easily damaged (often by moderate storm); - Foundation difficulties on fine sand bed; - Requires smooth seafloor. Rubble mound Pell mell artificial armour units A permanent breakwater consisting of layers of stone and gravel protected on the exposed surface by a layer of randomly placed artificial armour units. A massive structure may be incorporated in the crest to save material. Advantages: - Durable; - Flexible (accommodates settlement); - Easily adapted to irregular bathymetry; - Needs no large natural units; - Functions well even when severely damaged. Disadvantages: - Need factory for production of armour units; - Large quantities of material needed; - Needs under layer if built on sand; - Unsuited to soft ground. Rubble mound placed units Permanent structure similar to pell-mell unit placement, except that units are now individually placed in a precise pattern. A monolithic crest construction is usually used. Advantages: - Flexible (adapts to settlement); - Uses least material of rubble mount types; - Adapts well to irregular bathymetry; Disadvantages: - Armour units must be fabricated; - Needs much skill in construction; - Impossible to place armour under water; - Unsuited to very soft ground; - Needs under layer if it is built on sand. Rubble mound stone Permanent structure consisting of successive layers of stone. The exposed surface is covered with heavy armour stones. Advantages: - Very durable (resists severe attack well); - Functions even when severely damaged; - Adapts to ground settlement; - Uses natural common available materials; - Easily adapted to irregular bathymetry; - Construction possible with limited skilled labour; - Uses common construction equipment; - Materials are usually inexpensive; Disadvantages: - Uses the most material of all types; - Must be adapted for construction on sand; Page 17 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Conclusions: - Rubble mount structures are the most durable, and as such are best suited to extremely heavy wave attack; - Monolithic structures use less space and material; this is especially true in deeper water. For the design of the breakwater only these two types will be taken into account.
3.4.3 Concepts
For the design of the island two different concepts are presented. For both concepts breakwaters need to be constructed before the actual island can be built. Concept I is a permanent island and is made in a rather traditional way. Concept II is a temporary work island and built up out of prefabricated elements. This speeds up the building time and makes it easier to demolish or even replace the island at an other location.
Work area Breakwater Quay
II
3.4.4 Concept I
Concept I is a traditional made island. Work order: - Construction of breakwater; - Construction of quay; - Reclamation for work area; - Subsidence work area; - Infrastructure; - Installing building equipment. Breakwater It may be considered to use two different types of breakwater constructions. Directly adjacent to the work area a semi overtopping breakwater is required. Semi overtopping means that during the installation period from February till October it should be non overtopping. In wintertime when installation activities do not take place, a severe storm may overtop the breakwater. However the load acting may not damage the breakwater during this storm. The strength of the breakwater is designed to be able to withstand winter storms. The height however can be designed for wave heights occurring during installation periods. The other breakwater, providing quieter water conditions for mooring and transshipment activities, may be overtopping. Both breakwaters are of the type of rubble mount breakwaters. Rubble mount breakwater Almost every rubble mound breakwater is constructed in layers. Each layer of the breakwater must be designed in a way that the adjacent layer of finer material cannot escape by being washed through its voids. This also applies to the natural bottom material layer underneath the breakwater. If the bottom material consists of fine sand then a filter layer must be constructed. The outer layer must be designed to withstand the expected wave attacks. The choice of the construction material is largely determined
Page 18 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
by the availability in the quantities needed. A rather indescribable core material can be used to support the outer layer. Usually the cheapest available material is thrown in. Depending on the function on the leeside of the rubble mound breakwater an overtopping or a nonovertopping breakwater can be used. The less critical or important the activities on the lee side the more overtopping the breakwater may be.
Figure 3.4-5: Rubble mount breakwater Table 3-1: Cost estimate of rubble mount breakwater per meter length Fraction Primary armor 16 t Secondary armor 1-6 t Quarry run 300-1000 kg Filter gravel Type of placement Over crest Over crest Barge placed Over crest Barge placed Barge placed Volume 3 1 [m /m ] 380 100 575 30 1,240 385 Unit price [] 58 58 46.5 70 54 31 Total price [] 22,040 5,800 26,737 2,100 66,960 11,935 135,572
Monolithic breakwater As described in paragraph 0 there are a few different types of monolithic breakwaters. For a cost estimation it is decided to built up the monolithic breakwater out of caissons. These are built in a dry dock and floated to the site where they are ballasted and sunk in place. The cost, stated below, do not include the transport cost and the cost for the use of a dry dock facility.
1 10 m 0 m
Dimensions caisson: Length Width Height Cell width Wall thickness Amount concrete Mass Cost per caisson Cost per meter 60 20 30 10 0.5 6,300 15,750 4.25 70,800 [m] [m] [m] [m] [m] 3 [m ] [tons] [mln ] []
30 m
m 60
Figure 3.4-6: Global dimensions caisson Quay Because the work area consists of pumped up sand the quay construction should provide an embankment. Therefore the quay construction should be of a solid form. Because transhipment and mooring activities take place, the boundary at the waterside should be vertical. The following types of constructions can be used as a quay: - Cofferdam (a); - Caisson (b).
20 m
Page 19 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
a
Figure 3.4-7: Quay constructions
Ad. a: Production Two combi-walls (sheet piles + tubular piles) are placed in the wet. After connecting them with anchors the space between is filled with sand. Installation platform For the foundation of the installation platform there still needs to be constructed a pile foundation. Ad. b: Production The concrete caisson is built in a prefab yard somewhere onshore. It is towed to the site, ballasted and sunk in place. Installation platform The caisson is designed to provide a platform on which the installation procedures can take place. Advantages: Cofferdam Low cost; No even seafloor needed; Small equipment needed to produce. Large amount of offshore pile placement; Limited construction height; Extra foundation required for installation platform; Hard to dismantle. Caisson No extra foundation required for installation platform; Immediately functional after placing; Easy to dismantle and reuse. Even seafloor needed; Large equipment needed to produce; Prefab yard needed; High production cost.
Disadvantages:
Conclusion: A breakwater built up out of caissons is, for this water depth, cheaper than a rubble mount breakwater because it uses to much material. Therefore the breakwater will consist of caissons. It is not likely to built the quay with a cofferdam for the following reasons: The length of the tubular piles and sheet piles of the combi-wall need to be approx. 45 m. For the tubular piles this is no problem but the length of the sheet piles is limited to 30 m. This means that scour protection is needed at the toe of the cofferdam as shown in Figure 3.4-7a; To prevent extreme deformations of the combi-wall there need to be at least two levels of anchors for a height of 30 m. The lower level is situated below water level. Installing these anchors is extremely difficult. Therefore the quay will also be constructed out of caissons. Cost concept 1 Total work area: Backfill sand Quay: Caisson Breakwater: Total cost Approx. Dimension 240 x 120 220x100x30 3 1/m Amount 28,800 660,000 0.66 360 6 25.5 1,000 70.8 100 [m ] 3 [m ] [mln ] 1 [m ] # [mln ] 1 [m ] [mln ] [mln ]
2
Page 20 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
3.4.5 Concept II
Work order: - Construction of breakwater; - Placing jackets; - Placing deck boxes; - Installing building equipment.
Figure 3.4-8: Island consisting of prefabricated elements There are two different procedures for installing the deck bock: a. Floating; b. Lifting. In the following paragraphs a concrete deck caisson will be dimensioned for the floating installation procedure and an steel deck box will be dimensioned for the lifting procedure. Design calculations concrete deck caisson In order to get a global idea of the dimensions of the deck some design calculations are made for a deck caisson that is floated in place. The following aspects are taken into account: - Floatability; - Strength. Ad. 1 Floatability In order to float the deck caisson on top of the jacket a substantial free board is required as show in Figure 3.4-9.
Deck heigth (H) Free board (F) Quay heigth (Q) HAT LAT Clearance (C)
Figure 3.4-9:Required free board and clearance for floating installation The difference between HAT and LAT is 2m according to the terms of reference. Assuming that: - Installation of the deck caisson is carried out during a sea level of 50% of HAT (MSL +0.50m); - Minimum clearance 1.00 m; - Minimum quay height to HAT 2.00 m.
Page 21 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
2-3 hours
Figure 3.4-10: Installation windows floating installation Freeboard = Clearance + quay height Freeboard = 3.00 m. In order to create a freeboard of approx. 3 meters the following dimensions for the deck caisson are determined. Dimensions concrete deck caisson: Length 40 [m] Width 30 [m] Height 6 [m] Wall thickness 0.4-0.5 [m] 0.4 m 3 Amount concrete 1,400 [m ] 0.5 m 0.5 m 0.4 m Mass 3,500 [tons] Freeboard 3 [m] 10 m 10 m Cost 0.95 [mln ]
6m
40
30 m
Ad. 2 Strength It is assumed that some type of crawler crane or other crane carries out the installation on top of the deck caisson. The mass of the crane including its load is about 600 tons. Own weight: Crane load:
5m
30 m
5m
1 8
Stress: Deflection:
1 30 6 3 12 27 5.2 3 = 223 [m 4 ] ; 223 = 74 [m 3 ] 0 .5 6 M 145,000 10 3 = [N/mm 2 ] = 2.0 [N/mm 2 ] . W 74 3 3 3 Fl 6,000 10 30 = = 0.05 [m] 1 600 l 48EI 48 30,000 10 4 223 1 12
The deflection by own weight and the positive stress are compensated by post tensioning. The remaining deflection of 0.05m by the crane is acceptable for the span of 30m. Page 22 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Design calculation steel deck The main span of the steel deck will be built up out of trussed girders as shown in Figure 3.4-14. On top of the main girders, tangential to the main span, deck girders will spread the load of the crawler tracks. The load of each crawler track is spread over two main girders.
10 m Steel trussed girders
1.5 m 8.8 m
3m
6000 [kN] ; Crane load: During lifting operations this load is not equal spread over the two crawler tracks. It is assumed to be 75% and 25% per track. The maximum load per track is 4500 kN.
225 kN 0.75 m 300 kN/m' 225 kN 0.75 m
2,250 kN 10 m
450 kN/m'
2,250 kN 10 m
225 kN
2,250 kN
Figure 3.4-12: Critical load case deck girder Deck girders Max. bending moment: Allowable stress: Moment of resistance needed: Profile choice: Mass deck: Main girders
255 [kNm] ;
3.75 m
3.75 m
HE 450 B
5m
30 m
5m
Figure 3.4-14: Steel trussed girders Own weight girder: Assume: Top and bottom girder profile HE450B. Diagonals 75% of mass of top and bottom girder.
80 [ m ] 171 [ kg/m1 ] + 135 [ m ] 125 [ kg/m1 ] = 30.5 [ Ton/girder] = 7.6 [kN/m 1 ] ; 2 1 Max. bending moment: 8 ( 7.6 + 3 2.05) 30 + 0.5 28,125 = 14,100 [kNm] ;
Plain stress truss:
M = A [mm 2 ] ; 2z
Page 23 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
h H
HE 450 B
F z z F
2 M=1 8 450 2.5 = 350 [kNm]; M 350 10 6 W= = = 2,333 10 3 [mm 3 ] 150
Design calculation steel jacket The dimensions of the jacket are indicative and based on experience with these type of offshore constructions.
0m
10 m
10 m
Dimensions jacket: 1500.30 1000.20 400.10 Amount steel Mass Cost 160 120 180 32 250 0.35 [m] [m] [m] 3 [m ] [tons] [mln ]
22 - 27 m
20 m
Support reactions: Stress: Cost concept 2 Amount Breakwater: Caisson 1,000 70.8
1 6
[m ] [mln ] Page 24 of 25
DOWEC-F1W1-xxx-yy-nnn/vv-C
Quay: Floating Deck caisson Support jacket Quay: Lifting Steel deck Support jacket Finger piers Support jacket (3) Steel deck (3) Total cost (min)
160x30 4 5 5.55 160x30 4 5 8.75 3 1.0 1.0 2.0 78.4 / 81.6 78.4
3.4.6 Cost
Comparing the two concepts the following can be concluded: - Concept 2 seems to be less expensive than concept 1 - The material cost for an offshore assembly area are estimated to be approx. 80 mln Euro;
Page 25 of 25