Itt - (J+L) TI.v (T-JT) J: (Half Short-Circuits) .) )
Itt - (J+L) TI.v (T-JT) J: (Half Short-Circuits) .) )
Itt - (J+L) TI.v (T-JT) J: (Half Short-Circuits) .) )
2 February 1982 A PROTOTYPE OF MULTIPROCESSOR BASED DISTANCE RELAY J.C. BASTIDE, Non Member, IEEE P. BORNARD, Member, IEEE Electricite de France Clamart, France
491
Abstract - This paper concerns the design and realization of a digital relay for EHV systems. It describes the algorithm which has been used and the main principles of operation. Then it shows how a prototype has been built with four 16-bit microprocessors, to allow the simultaneous real-time computation of three apparent impedances. The hardware and software architecture are described. The paper also presents the results of the tests carried out on the relay: a tripping signal is sent within one period of 50 Hz for all faults (half a period for near-by short-circuits). Furthermore, single-phase tripping, directional discrimination and power-swing detection are provided. INTRODUCTION
The development of a digital distance relay is part of a large EDF scheme, the PANDOR project, the aim of which is to improve fault clearance times by increasing the speed of relays and circuit-breakers. On the other hand, an assessment of the digitalization of most of EHV substation equipments (protections, communications, automation devices...) is included in the scope of this project. The choice of a distance protection was made according to the present EDF's policy. In this respect, studies of digital differential relays are currently in progress for some particular problems such as multiple-end lines. Without reviewing the classical discussion about the pros and cons of digital relays [I] , [2] , it is useful to emphasize their main advantages which have guided us for the design of a prototype: - flexibility (which means a possibility of changing algorithms and logic), - fau lt-tolerance (which leads to a multiprocessor structure because of the present lack of fault-tolerant chips) - reduction of costs when included in an homogeneous design of all EHV substation equipments (which at the moment implies the use of microprocessors). The aim was to follow these three directions to realize a prototype giving a tripping signal within a 50 Hz period for all faults, within half a period for severe short-circuits, computing impedances with enough accuracy to allow a first zone of 80 % of the protected line, and providing single-phase tripping, directional discrimination and power-swing detection.
(3)
Writing equation (2) for m successive samples gives a relationship of the form:
M.
la]
[vi +
[e]
(4)
I(t)
(t)
[a
[e]
=
al
-e (t )
It
and
[v]
Il=
1I I
Lv
v(t
)]-
(tm)
L-
(t M)i
j I
=
(a*)= 0 a
(5)
(P..)
iI
m
j =0
A1 i (t-jT)
7 i(t-jT).i[t-(j+l)T] j =O0
(6)
m
(Pij)
m -I
j=0
=
7 i(t-jT). i [t-(j+l)TI
2, 7j=l i2(t-jT)
and M
lyv
[
m
(bi)
-
(t) + e (t) = R i (t) +L i (t) - Ti (t - T) () where T is the sampling period and e (t) represents the difference between the model of the line and the actual phenomena (noise, shunt capacitance, measurement errors). Equation (l) can be written:
v v
(b)
j =0
-
i(t-jT).v(t-jT)
(7)
(2)
j =
0 itt-(j+l)TI.v(t-jT)J
P22 b1 - P12b2
2
[ails given by a1 =P1 P22 81 SM 384-7 A paper recommended and approved by the IEEE Power System Relaying Committee of the IEEE Power Engineering Society for presentation at the IEEE PES Summer Meeting, Portland, Oregon, July 26-31, 1981. Manuscript submitted January 30, 1981; made available for printing April 22, 1981.
and
a2 X -
Pl
P12 2 1 12 ll 22
b2
-
R and L are obtained through equations (3). In steady-state conditions, R and L computed with the above
1982 IEEE
492
formula
are:
i R =R
Lo tg2
wT
(8)
the
inductance,cothe system pulsation. When v (t) = Vm sin (wt +q) + V sin (at +f) ~~~p and i (t) = Im sinwt, it can be shown that the maximum
m
and
Lo
are
actual
values
o'f
resistance
and
good speed-accuracy compromise large convergence speed for high current faults due to the use of squared values, and the lack of singularities the insensibility of the computed distance of a fault versus the system frequency shifts the smallness of errors induced by a saturation of the analog to digital converters, used to limit the range of currents. However, the number of arithmetical operations is rea-
were
relative
AR
errors on
R and L
are
given by
L
=
=max
Vp
Vm
IV kR and p cos ad
sin?
kL
To detect and trip correctly all the types of fault on an EHV network, it was decided to build a relay computing simultaneously 3 apparent line-impedances, from either the 3 phase - to - phase or the 3 phase - to - ground potential/current pairs. This solution allows a fast tripping decision to be taken due to the rapid choice of the pairs to be processed. A simplified flow-chart of the relay is given on figure 2.
I
I
1.2
1.0
06
zero-sequence detection
kes
currents
04
Computation of
compens ated
02
100
200
300
400
500
600
Figure
1:
kL coefficient
versus
Computation of
ground
the 3
phase-to->
apparent impedance
with T = 0,83 ms and mT = 15 ms For more complex input signal spectra, analytical studies become almost impossible, because of the non-linearity of the algorithm. It can be shown that the sensitivity of L to current harmonics increases slightly with their frequency. However, when comparing these performances to other algorithms, it must be beared in mind that this sort of spectrum studies implicitly assume the stationnarity of voltages and currents, which is not very realistic (in particular in the case of fault on an overloaded line).
Phase- selection|
directional
discriminatio
-
zone de termination
|power-swing detection
dispatch of tripping signals and/or information
Zero-sequence detection
In steady-state conditions, the relay computes the 3 impedances from phase-phase data. After each new set of samples, it reckons zero-sequence quantities, 3 I and 3- VO. If one of these two values exceeds a threshold cPuring two contiguoussets of samples, the 3 distance-units are commuted on phaseto-ground data (phase voltages and compensated currents i hae+ K IO). The threshold for 3 1 is in fact equal to the uar er of the maximum value of any phase current during the last 50 Hz period (with a minimum step to avoid commutation during no-load conditions).
This characteristic is shown on figure 3 in the (R, X) plan. It is a parallelogram to simplify the tripping criteria. The 82.50 angle is due to the use of a comparison between the computed absolute-value of R and the maximum fault-resis-
ing.
(24
Tripping characteristic
That is why a sampling frequency of 1200 Hz was chosen data in a 50 Hz period, 18 in the window). In conclusion, the main advantages which were found for
493
tance
the relay settings, one of the three downstream zones or the upstream zone (zone 4) is chosen.
Power-swing detection To prevent incorrect tripping during out-of-synchronism conditions or power-swings, the rate of change of the resistance is calculated whenever there is a presumption of phase to - phase or three-phase short-circuit. If this rate is not sufficient, the tripping signals are blocked, and a power-swing alarm is sent. This function is suppressed in the case of grounded faults.
Phase selection
The relay must provide single-phase tripping. In addition, in case of polyphase faults, it has to decide which of the three potential/current processed 'pairs is/are to be considered for direction and zone determination. When the distance units are fed with phase to - ground data, the P 1 matrix element (equation 6) is used. The reason for this is the ratio of P11 for a faulted phase on P11 for an healthy phase can be shown fo be always exceeding 4., whereas this ratio does not exceed 1.5 if it concerns two faulted phases.Finally, the criterion for phase selection between distance elements which have their impedance inside the tripping characteristic is: there is a single phase -to - ground fault on phase x if P11 of phase x is more terms are than 2.5 times P11 of the other phases (P calculated with compensated currents). In the case of polyphase faults, the potential/current pair used for directional and zone determination is the one which has the higher P11 (higher current).
The digital processing of distance relaying algorithms requires at least a 16 - bit CPU. As no 16 - bit currently available microprocessor was powerful enough to be used alone when the prototype studies started in 1979, and, on the other hand, to reach the targets set out in the introduction, a parallel processing approach was taken up. That is why the three-distance-unit relay is built from four INTEL SBC 86/12 A boards using the 8086 microprocessor. The different tasks are dispatched in order to minimize exchanges on the common bus (Intel's Multibus) and to avoid contention in sharing ressources. The general architecture is illustrated by figure 4. One master CPU synchonizes the whole relay, and processes the problems which concern several distance-elements: reading of the settings, sampling and preprocessing of data, phase selection, power-swing detection, sending of tripping orders and information. Three slave processors which are identical (same hardware and software) process the specific problems of one unit each (they compute impedances, direction, zone).
Directional discrimination
The direction of the fault (busbar-side or line-side) is computed as the sign of the inductance obtained from the following data: - the current of the selected phase - the corresponding memorized pre-fault voltage, shifted by two samples so that the directional reverse line in the (R, X) plan has a -30 angle with the R axis (see figure 3) to deal with the near resistive short-circuits. In the case of a fault appearing during a line energization (no pre-fault voltage), the short-circuit is always detected
as line-side
(downstream).
to the
Zone determination
According
value
of the computed
inductance of
The data acquisition system has six channels for the potentials and voltage-converted currents of the three phases. There is no galvanic coupling between the transducers and the relay owing to the use of optoelectronic linear isolation
494
amplifiers with their isolated DC to DC converting powersupplies (the whole tolerate 5kV surges). Adjustable gains give the six analog signals their correct output levels: the voltages saturate when the phase potentials overstep the lumped peak rated voltage, the currents saturate over 40 kA to limit their dynamic range. Then, there are six -monochip anti-aliasing filters (3 pole Butterworth type) with a cut-off frequency of 550 Hz, and a 0.7 ms delay at 50 Hz. The filters are followed by six sample-holds. The sampling operation is initiated by one of the programmable timers of the master CPU's board, which delivers a "start conversion" command every 0.833 ms. This output is sent to six hybrid 12-bit analog-to-digital converters (ADC), whose status information at once triggers the sample-holds. Less than 25us later, an "end-of-conversion" signal is sent as an interrupt to the master CPU which can read the sampled values through the parallel l/O ports directly connected to its
-
Communication between processors Specialized buses between the CPU's and their specific units greatly simplify the communication problems: the slaves don't have to access the common bus, and are hardwareprevented to do so, avoiding priority resolution schemes. Only the master processor uses the common bus, to write the next data in the slaves' double-port RAMs and to read the results of the calculations. The synchronization of the 4 CPUs is achieved by means of a command sent by the master as soon as the new data are ready in the slaves' memories. This signal, comparable to an interrupt, is driven to the TEST input of the 3 slave 8086's, causing the reactivation of these processors, previously stopped by a wait instruction at the end of the last processing loop. On the other hand, any slave can interrupt the master in the case of hardware breakdown (this function is described below).
extended data bus. Twelve-bit ADC are at present the most accurate that can be reasonably used in the severe environment of an EHV substation relaying-house. Thus, to solve the problem of the dynamic range of currents (from a few hundred amperes to about 180 kA for asymmetrical faults in a 63 kA substation), it was decided to saturate these signals for the values exceeding 40 kA. By that way, the quantization step is about 20 A (for the EHV line), and enough accuracy during steady-state conditions is kept. This solution has been found to be better than
Settings and orders The settings of the relay are provided by thumb-wheels inserted into the front-plane of the device. This type of settings has been kept to maintain a "classical" man-machine interface. Six parameters are available: the limits of the 3 downstream zones and the upstream zone, the maximum resistance of the detected faults and the earth coefficient
two parallel ADC on each channel (one for the low values and one for the large), because the algorithm correctly copes with electronically saturated currents.
(zo-zd)/3 zd
Distance units
Each of the 3 slave processors has to compute an impedance every 0.833 ms, with in particular a large number of signed multiplications and additions. The 8086 is too slow to perform all of them during the sampling period. So, to each slave board, a fast arithmetic element was added. This unit is designed from a monochip TRW hardware multiplier-accumulator, which reckons a 16 x 16 bit multiplication and may accumulate the result to a 35-bit register in less than 155 ns. All the decoding and control circuitry is provided, so that the use of the arithmetic unit is very easy for the programmer: the decoders recognize the type of operation which has to be performed (multiplication or preload of a 32bit value in the accumulation register) and the control circuits operate the multiplier and the interface chips (parallel l/O devices, drivers and latches). The command which causes accumulation to a previous result is software generated. For the communications between the slave CPU's and their arithmetic units, the common bus could not be used: the requests to access it would have been much too frequent, with wait times downgrading the multiplier's performances. Thus, a private bus was created for each unit by extending the onboard data bus and by slightly modifying the address decode logic of the.SBC 86/12 A boards. As a result, a signed 16 x 16 bit multiplication of two CPU registers, with the result stored in other CPU registers, is performed in 8.8ys. When the accumulation command is used, this time asymptotically decreases to 4.4,us. The resistance and inductance are obtained by processing terms of the form (ab cd)/(ef gh), where the different elements are 32-bit numbers, and that may induce computing accuracy problems. To avoid this, terms like ab-cd are calculated as 64-bit fixed-point numbers, then converted into pseudofloatting-point values with hexadecimal exponent (multiple of 4) and 28-bit (for numerators) or 16-bit (for denominator) mantissa. The only operations on these floatting-point numbers are the last two divisions, which can be done easily by an 8086's instruction without overflow problems because of the length of the mantissas and the fact impedance is assumed to be infinite (and his computation stopped) whenever the denominator has an exponent less or equal to 4 (which means a line-current RMS value less than about 300 A).
-
Twelve orders and information are issued by the protection: starting of the relay, 3 phase-tripping signals, 4 zones, 2 direction information, power-swing detection and an autotest output described below. They are transmitted to the other equipment through optoelectronic decoupling relays (2,5 kV insulation voltage, 5is commutation time).
Rack and power supply
The relay is made of 8 INTEL SBC's format boards: 4 CPU's, 2 boards for the 3 arithmetic units, one for the analog filters and one for data sampling and acquisition. The input isolation amplifiers and the output relays are on the back of the device, for evident dielectric reasons. Figure 5 shows the ecuipment without its front-olane.
rigure
View oi
1.e
relay kwitnouu1
irrint-pidile)
495
The
DC
to
different
supply voltages
a
necessary
are
obtained
by
DC converters from
24 V
A for
D~C supply
15 V.
with batteries:
currents
12
V,
fault inception can be chosen, and the phase sequentially interrupted by the breakers on zerocrossing. One of the used network configuration is show, on figure 6 (the protection was settled in P or P9).
of
are
The
angle
Figures
Future
tolerant the
7,
and
show
some
short-circuits
a
:
on
this
studies
will
be
conducted
to
obtain
fault-
simulated busbar
400
kV
performances)
out these
are
relay, which could operate (may be with downgraded even in the case of -major hardware faults, and multiprocessor structure is a good starting point to carry
concepts. As
a
system.
behind
ins.
fault at Bl
current).
performed by
to
use
implement
the
detect
most
of
failures, while
the
time
requiring only
not
chips.
them
All these
we can
LI- jl6kA
--711
methods
outline
:
will
be
listed
here,
but
among
watchdog
which delivers
an
interrupt
rt
retriggered by
are
1.5 millisecond
.known values
operands
redundant
are
of
are
or
mutually exclusive,
output
2.2
x
that
the
probability
f or is
random
nfssage
expect
to
be taken
into consideration
less than
Z1.3Ii7 11 .zI-_Vb
pha.eBt.p____
______
10
The data
acquisition subsystem
to
check-up
tests,
as we
replace
it in the future
part of digital
equipment general
is safe.
a
Whenever
reset
equipment is issued, the disfuctionning element is checked again, and, if still incorrect, the supply of the output opto relays is completely switched off (till the protection is repared) to prevent hazardous tripping. This "two stage?? failure processing avoids having to disconnect the relay
of the for transient faults.
L..2
Figure
Figure
much
7
:
3-phase
an
relay
in P
8 shows
a-c
phases
fault
on
the measurement
transducers of the
Thus, with a minimum additional hardware (7 including the watchdogs), most of failure problems
dealt with. About has occured
chips
can
PI protection.
the
In this
case
the currents
are
be
higher,
but
on
large asymmetry
time:
has
still
an
unfavouare
rable effect
the clearance
ins.
the
tripping
orders
issued in about 12
reliability,
since
it should be noted
of
that
no
breakdown in
the, construction
the
prototype
December 1979.
TESTS ON THE PROTOTYPE After the steady-state tests carried out for a software debugging purpose, two kinds of data were used to try the simulations on an analog model of EHV systems, and relay records of real faults on 400 kV lines and busbars (from digital fault recorders or analog magnetic tapes).
_~~~~~~~~"V
Analog simulation
An
analog model,
EDF's
Microre'seau
and
at
Clamart,
was
used to create
types, including
sequentially developping
tions. This model
and the lines
are
synchro-
'I; O;r
actual
rotating
a
machines of
kVA,
simulated
by
number of
pi-cells.
S cc -14 100MVA
T3
1.32
111lkm)
CQ
2
laL
(infinite bus)
Figure
On
: a
phases
fault at
PI relaying point
3/5
of the
figure 9, we can see a double line-to-earth fault at length of line T5 : the tripping time is 13 ms in this
IP
Figure
6
:
T5 (103km)I
of simulated network
case.
example
496
--,16kA~~~~~~~~~~~~~~~~N
record was reportered from the healthy circuit. During the first 4 cycles, the current-flow has the same direction than on the faulted circuit (which induces a "zone 2" tripping decision).
I'
;;z;
=4
.V"
-Zi
Figure 9
:a
tripping signals finish less than 4 ms after fault clearance. Table I gives the maximum tripping times mesured for
Table I
(angle of
line
on a double-circuit
Type of
faulIt
1 phase earth 2P 2 P.E. 3p P 1 P. E. 2P 2 P.E. 1 P. E. 2P 2 P.E. 3P I P.E. 2P 2 P.E. 3P
time (ins)
Tripping
3~ P
Then the remote breaker opens, and the current-flow reverses for 1.5 cycle, before the short-circuit clearance. At that time, the relay finds that impedance and direction do not converge any longer, and latches its orders and information. Next, 17 ms later, it sends a "zone 4"1 (upstream) tripping order which is latched for 25 ms after fault clearance, since the protected line is not switched out. Figure 11 has been chosen to illustrate the necessity for a relay not only to trip actual faults, but also to keep quite during transient conditions when it is not directly concerned.
??16
??13.5 "13.5
I?9
?9.5
"9.5
.-....--.-...-
10
As that could have been foreseen, it has been established that the two major parameters influencing the tripping time are the level of the short-circuit current (the speed of convergence increases with it) and the importance of the zerosequence quantities in the case of earthed faults (the commutation time to change phase-phase impedance-elements into phase-to-ground units has to be added to convergence time).
Figure 11: 3-phase busbar fault with the protected line opened
A 3-phase busbar short-circuit was initiated at Bayet 400 kV substation just behind the protected circuit, with the 110 km line opened at its remote end. Transient currents of over 1.5 kA peak at 580 Hz appeared, associated to a full drop of voltages :as required, no tripping order was issued. As a last stage in the relay tests, the prototype is beeing permanently installed (during the first term of 1981) in a relaying house of a 400 kV EDF's substation.
497
CONCLUSION
The used algorithm has given satisfactory results in the fields of speed, accuracy and ability to be implemented. It has allowed to achieve the aimed performances, but it must be beared in mind that it is only a part of a digital relay software. In particular, whether the speed of the protection is limited by the time required for the algorithm to compute the right impedance values, plus the delay to make sure that they are actually the right values (convergence tests), it is restricted as well by the choice of the data to be processed (commutation between phase-to-phase and phase-to-ground quantities). The prototype built to implement the software is a powerful machine, and its 4-processor architecture is well suited to relaying computation for 3-phase systems, but versatile enough to insure a good flexibility. Besides, the simple task distribution provides a fairly easy software debugging, and allows to expect successful developments in the field of hardware-fault tolerance. Furthermore, the cost of the equipment, if not yet economically competitive, is quite reasonable, despite of the fact it has been designed on the basis of hardware available in 1978. The permanent tests on the EDF's 400 kV system will permit to corroborate the good behaviour of the protection in a relaying-house environment.
REFERENCES
[Ii J.G. GILBERT, E.A. UDREN, and M. SACKIN "The development and selection of algorithms for relaying of transmission lines by digital computers".Power System Control and Protection.New-York: Academic Press, 1978, pp 83 - 126.
[21 B.J. CORY, G. DROMEY, and B.E. MURRAY "Systemes numeriques pour les protections". CIGRE 1976, report 34-08.
Chamb6ry (France) on May 1953.In 1975 he obtained the degree of Ing6nieur Diplomt from the Ecole Superieure
diesand Research Department Clamart, near Paris. P. Bornard is a CIGRE (1978) and IEEE (1981) member.
at
Jean-Claude Bastide was born in Paris (France) in 1936. He joined EDF in 1956. He is since 1964with the Studiesand Research Department, where he works on relays and automation devices.
zone to 80% of the line. Present practice is to set first zone for 90%. Do the authors have plans and techniques to improve the accuracy in order to meet this requirement?
Discussion W. D. Breingan, and M. M. Chen (General Electric Company, King of Prussia, PA): We would like to congratulate the authors on their paper describing their work with a digital relay. The presentation of the hardware and software aspects, which used a multiprocessing concept, is especially a welcome addition to the digital relaying literature. There are. several quesions concerning this paper: 1. We also used an algorithm based on the difference equation representation of the protected circuit. (See references below.) However, our algorithm is computationally simpler in that we solved the difference equation directly for resistance and inductance, rather than using matrix methods. This simpler algorithm gives steady state estimates of: R =Ro wt and T L = Lo tan Wt
As a whole, they give a better result than those given by the authors' equation (8). Would the authors comment on why the more complicated matrix algorithm results in more error than our simpler
7. In the test procesure, the authors state that the analog model was used to create hundreds of faults; a library of 50 actual faults is available. In Table I, there are only 16 tests listed. Do the authors have more complete results showing the ranges of test conditions, as well as the ranges of trip times for a wide range of
system conditions? 8. The authors use 3 sets of processing hardware to perform 3 identical R, L. determination for the 3 phases. Why did the authors choose this approach instead of preselecting (classifying) the fault type and doing one calculation? Also, did the authors study the effects of using data from the unfaulted phases on the calculation?
REFERENCES
algorithm? 2. There is some confusion on our part concerning the window size and its content. It is stated in the paper that the window uses 18 sample points which is 15 milliseconds for the given sampling frequency. Yet the test data indicates tripping times which include values from 9.0 to 14 milliseconds. This suggests that the authors may be using some pre-fault data in the matrix calculations. Is this the technique to obtain these shorter trip times? 3. We are intrigued by the technique for handling the range of fault currents. It appears to us, however, this approach may have computational problems. With the use of saturating analog to ditital converters, the incoming current signals will be constant (the saturated value). For constant currents, the Ps of the authors' equation (6) will be zero. This will lead to division by zero in the calculation of the a's. How do the authors handle this situation? 4. The authors' point of view on the aliasing filter is very interesting. We found in our work that the conventional requirement on antialiasing is not applicable. Have the authors done work on the effect of aliasing on the algorithm to justify their point of view? 5. Did the authors incorporate any special technique to handle the problem of high fault resistance and load flow? This situation results in severe alteration of apparent R and L, and may cause misoperation of the protection scheme using the algorithm. 6. The authors stated that they have enough accuracy to set the first
1. W. D. Breingan, M. M. Chen, and T. F. Gallen: "The Laboratory Investigation of a Digital System for the Protection of Transmission Lines". IEEE Transactions on Power Apparatus and Systems, Vol. PAS-98, No. 2, March/April 1979, pp. 350-368. 2. T. F. Gallen, W. D. Breingan, and M. M. Chen: "A Digital System for Directional-Comparison Relaying". IEEE Transactions on PAS - Vol. PAS-98, No. 3, May/June 1979, pp. 948-956. 3. M. M. Chen, W. D. Breingan, and T. F. Gallen: "Field Experience with a Digital System for Transmission Line Protection". IEEE Transactions on PAS - Vol. PAS-98, No. 5, September/October 1979, pp. 1796-1805.
498
R L'tg (wT/2) = RD These considerations show that the "error" factors (which come from the time quantization (T for dt) and from the cross products like i (t). i[t- T]) improve the relay characteristics. In fact, the interest of the matrix algorithm is to provide a better digital filtering, as well as a fast convergence speed. The impedances are computed at every sample (during any steadystate or fault.condition), with mobile sampling windows shifted by T. Of course, when a fault occurs, some pre-fault data are used in the matrix calculations. In case of a severe short-circuit, the convergence of the computed values is fast (it is checked as explained in the paper paragraph "Tripping characteristic") and a tripping order may be issued in times as short as 8 ms (0.4 cycle). To bring out difficulties due to the converter saturation, the current should be constant at the saturated value (i.e. greater than 40 KA) for 18 successive sample (/4 of a cycle). This is fortunately impossible on our system. An advantage of the mean-square algorithm is its ability to cope with saturated signals, so long as some samples have a different value. With practical signals, the algorithm avoids the problem of singularities. Yet, for obvious reasons related to software reliability, every denominator is checked before a division to prevent any overflow problem. The algorithm is a digital filter used to extract quantities at the system frequency (50 Hz). It is consequently important to avoid confusion between this frequency and its images near fe/2' and this implies an analog anti-aliasing filtering. But, for the other frequencies of the [0, fe/2] band, nothing should have to be requested if the algorithm was perfect (i.e. providing a perfect rejection). As actually these frequencies may induce some errors in the impedance computations, it would not be reasonnable to allow a large aliasing effect. An ideal design of the analog filters must include a study of the primary signal spectra and the effect of t-ransducers, as well as the algorithm response to non-fondamental frequencies. The problem of high resistance fault and load flow is generally a problem of discrimination between normal steady-state and fault conditions, especially in case of a bilateral supply of the shortcircuit. A possible future evolution of the relay could include a dynamically computed tripping characteristic, according to the load. But there is a limit inherent to impedance relaying, and the solution of this problem is probably the use of other devices such as zero-sequence or differential relays.
-
6 - The present practice on the French network for the setting of the first zone is 80Wo of the line, and that explains our choice. The improvement of the accuracy is not only a relay problem, but implies as well a good knowledge of the transducers performance during electromagnetic transients. This point is presently being investigated. 7 - The 16 tests appearing in Table I are the ones which have given the longest tripping time during short-circuits on the network illustrated by figure 6 in the following conditions: fault inception angle varying from 00 to 3600 (by 100), and loads from + 1200 MW to - 200 MW and + 600 MVar to - 600 MVar on the protected line. The minimum tripping time is 0.4 cycle and it is reached for severe short-circuits. In all cases, the tripping time is always less than 1 cycle. A full report will be published on the relay performance, including the real faults it has tripped in the Albertville 400 KV substation where it was installed on June 1981 (on 15 Sept. 1981, 25 short-circuits have been correctly detected). 8 - Several considerations have led to the choice of 3 sets of processing hardware to perform 3 identical R and L determination (notwithstanding the fact that the prototype does not aim at an industrialization of the very same architecture): First, classifying the fault before the beginning of any impedance computation induces delay of the tripping signal: this delay is the time needed to process the previous samples of the chosen phase, plus the time to check the convergence of the computed values (the classification of the fault in our case needs about 6 ms). This problem is still sharper in case of a developing short-circuit. Then, 3 impedance computations allow to check the results coherence, according to the relay autotest procedures. The meaning of the last part of the question does not appear very clear to us. As far as we understand it, we should answer that the data from unfaulted phases are not used to trip the relay, since, after the phase selection, only the quantities related to the faulty phase(s) are considered.
Manuscript received September 25, 1981.