Sand Drains
Sand Drains
Sand Drains
/Dia
as
0
z
00
00
.4
CD
c
-
. of drain (2r)
Fig. 10.20 Coordinate directions.
Equivalent radius
The effect of each sand. drain extends to the end of its equivalent radius, which
differs for square and triangular arrangements (see Fig. 10:19).
For a square system:
Area of square enclosed by grid = a
2
Area of equivalent circle of radiusR = a
2
i.e. 1l"R
2
= a
2
or R=O.564a.
Fora triangular system:
A hexagon is formed by bisecting the various grid lines joining adjacent
drains (Fig. 10.21). A typical hexagon is shown in the figure from which it is
seen that the base of triangle ABC, i.e. the line AB, = a/2.
Now
aa
= AB tan LCBA = 2tan 30 = 2J3
hence:
. I a a a
2
Area of tnangle ABC = 2x 2x 2J3 = 8J3
Fig. 10.21 Equivalent radius: triangular system.
380 Elements of Soil Mechanics
So that:
, a
2
Total area of the hexagon = 12 x 8y'3= 0.865a
2
Radius of the equivalent circle, R = 0.525a
Determination of consolid4tion rates from curves
Barron has produced curves which give the relationship between the degree of
consolidation due to radial flow only, Ur, and the corresponding radial time
factor, T
r
T _ Ch
t
r - 4R2
where t = time considered.
These curves are reproduced in Fig. 10.22 and it can be seen that they
involve the use of factor n. This factor is simply the ratio of the equivalent
radius to the sand drain radius.
R
n = - and should lie between 5 to 100
r
To determine U (for both radial and vertical drainage) for a particular time, t,
the procedure becomes:
(i) Determine U
z
from the normal consolidation curves of U
z
against T
z
(Fig. 10.4):
Cyt
T
z
= H2 where H = vertical drainage path
(ii) Determine U
r
from Barron's curves of U
r
against T
r
.
(iii) Determine resultant percentage consolidation, U, from:
1
U = 100 - 100 (100 - Uz)(lOO - Ur)
1---
.
-
-......:::
r---..
........
r-- ...
k
......
........
"
'"
"-
r-.
r-.
'\.
i"'\.
r-..
\
1\
t'-.....
"
t--.
o
10
20
;g
30
c: 40
o
50
:2
g 60
70
()
80
90
100
0.004 0.01 0.04 0.10 0.40 1.0
Time factor, T,
Fig. 10.22 Radial consolidation rates (after Barron, 1948).
Rate of Foundation SetUement 331
Smear effects
The curves in Fig. 10.22 are for idealised drains, perfectly installed, clean and
working correctly. Wells are often installed by driving cased holes and then
backfilling as the casing is withdrawn, a procedure that causes distortion and
remoulding in the adjacent soil. In varved clays (clays with sandwich type
layers of silt and sand within them) the finer and more impervious layers are
dragged down and smear over the more pervious layers to create a zone of
reducedpenneability around the perimeter of the drain. This smeared zone
reduces the rate of consolidation, and in situ measurements to .check on the
estimated settlement rate are necessary on all but the smallest of jobs.
Effectiveness of sand drains
Sand drains are particularly suitable for soft clays but have little effect on soils
with small primary but large secondary effects, such as peat. See Lake (1963).
EXAMPLE 10.7
A soft clay layer, m
v
= 2.5 x 10-
4
m
2
/kN; Cv = 0.187m
2
/month, is 9.2m thick
and overlies impervious shale. An embankment, to be constructed in six
months, will subject the centre of the layer to a pressure increase of 100 kN/m
2
.
It is expected that a roadway will be placed on top of the embankment one
year after the start of construction and maximum allowable settlement after
this is to be 25 mm.
Determine a suitable sand drain system to achieve the requirements.
Solution
2.5
Pc = mvdp2H = 10000 x 100 x 9.2 x 1000 = 230mm
,J
therefore, minimum settlement that must have occurred by the time the
roadway is constructed == 230 - 25 = 205 mm. i.e.
205
U = 230 = 90 per cent
Assume that settlement commences at half the construction time for the
embankment. Then time to reach U = 90 per cent = 12 - = 9 months.
T = cvt = 0.187 x 9 = 0020
z . H2 9.22 .
From Fig. 10.4 U
z
= 16 per cent.
Try 450 mm (0.45 m) diameter drains in a triangular pattern.
Select n = 10. Then
R/r = 10 and R = 2.25m
hence
2.25
a = 0.525 = 4.3m
382 Elements of Soil Mechanics
Select a grid spacing of 3m.
R = 0.525 x 3 = 1.575m
_ 1.575 _ 7
n - 0.225-
Cyt 0.187 x 9
T
r
= 4R2 = 4 X 1.5752 = 0.169
(Note that no value for Ch was
given so C
v
must be used)
From Fig. 10.22, U
r
= 66 per cent.
U = 100 1 ~ (100 - 16)(100 - 66)
= 71.4 per cent, which is not sufficient
Try a=2.25m; R= 1.18m; n= 5.25.
T = 0.187 x 9 = 0 302
r 4 X 1.18
2
'
From graph, U
r
= 90 per cent.
Total consolidation percentage = 100 - 1 ~ (100 -116)(100 - 90)
= 91.6%
The arrangement is satisfactory.
Obviously no sand drain system could be designed as quickly as this. The
object of the example is simply to illustrate the method. The question of
installation costs must be considered and several schemes would have to"'be
closely examined before a final arrangement could be decided upon.
Exercises
EXERCISE 10.1
A soil sample in an oedometer test experienced 30 per cent primary consolida-
tion after 10 minutes. How long would it take the sample to reach 80 per cent
consolidation?
Answer 80min
EXERCISE 10.2
A 5m thick clay layer has an average Cy value of 5.0 x 10-
2
mm
2
/min. If the
layer is subjected to a uniform initial excess pore pressure distribution,
determine the time it will take to reach 90 per cent consolidation (i) if drained
on both surfaces and (ii) if drained on its upper surface only.
Answer (i) 200 years, (ii) 800 years
Rate of Foundation Settlement 383
EXERCISE 10.3
In a consolidation test the following readings were obtained for a pressure
increment:
Sample thickness (mm)
16.97
16.84
16.76
16.61
16.46
16.31
16.15
16.08
16.03
15.98
15.95
Time (min)
o
I
4
1
4
9
16
25
36
49
64
81
(i) Determine the coefficient of consolidation of the sample.
(ii) From the point for U = 90 per cent on the test curve, establish the point
for U = 50 per cent and hence obtain the test value for tso. Check your
value from the formula
TsoH
2
tso=--
Cv
Answer Cy = 1.28 mm
2
/min, tso = 10.2min
EXERCISE 10.4
A sample in a consolidation test had a mean thickness of 18.1 mm during
a pressure increment of 150 to 290 kN/m
2
. The sample achieved 50 per cent
consolidation in 12.5 min. If the initial and final void ratios for the increment
were 1.03 and 0.97 respectively, determine a value for the coefficient ofperme-
ability of the soil.
Answer k = 2.78 X 10-
6
mm/min
EXERCISE 10.5
A 2m thick layer of clay, drained at its upper only, is subjected to a
triangular distribution of initial excess pore water pressure varying from
1000 kN/m
2
at the upper surface to 0.0 at the base. The Cy value of the clay is
1.8 x 10-
3
m
2
/month. By dividing the layer into 4 equal slices, determine,
numerically, the degree of consolidation after 4 years.
Note If the total time is split into increments, r = 0.494.
Answer U = 15 per cent