Lecture 13 Distribution ProtectionDistribution Protection
Lecture 13 Distribution ProtectionDistribution Protection
10
3
T
im
e
[
s
e
c
]
ELCT 751 DistributionProtection 40
10 100 1
10
3
1
10
4
0.01
0.1
10K tot clear
10K min melt
15K tot clear
15K min melt
Current [A]
Recloser-Fuse Coordination
Recloser feeding a fuse:
Fast operations of recloser should
protect entire downstream line
( f ibl ) f
ELCT 751 DistributionProtection 41
(as far as possible) from
temporary faults (fuse saving)
Fuse link should not be damaged
by fast operation
Recloser-Fuse Coordination
Recloser feeding a fuse:
Fuse saving
Fuse link should not be damaged
ELCT 751 DistributionProtection 42
by fast operation
Permanent fault should cause
fuse to blow on first delayed
operation
8
Recloser operation - fuse link heating
V pu
Ipu
1
0
0
If
t
t
OPEN OPEN OPEN LOCKS OUT
ELCT 751 DistributionProtection 43
CLOSED CLOSED CLOSED
FUSE SHOULD BLOW DURING ONE
OF THESE DELAYED OPERATIONS
FUSE LINK
TEMPERATURE
FUSE SHOULD NOT
BE DAMAGED HERE
Fuse link heating
Fuse link heats during the
recloser closed periods and
cools during the open periods
ELCT 751 DistributionProtection 44
cools during the open periods
If reclosing interval is longer than
link thermal time constant, link
may cool completely
Fuse link heating
If reclosing interval is shorter
than link thermal time constant,
link may not cool at all
ELCT 751 DistributionProtection 45
y
If detailed calculations are not
done, assume no cooling to be
conservative
Recloser-fuse coordination
Assume no cooling of fuse link
Assume recloser sequence is
2 2
ELCT 751 DistributionProtection 46
2A2B
two fast (A curve) followed by
two delayed (B curve) operations
Recloser-fuse coordination
Plot 2 times recloser A curve to
compare with fuse minimum
melt curve
ELCT 751 DistributionProtection 47
melt curve
Plot 2A+B to compare with fuse
maximum clearing time
Fuse and recloser time-current
curves showing coordination
TI ME
FUSE MAX CLEARI NG TI ME
FUSE MIN
MELT TI ME
ELCT 751 DistributionProtection 48
CURRENT
A
2 X A
2 X A + B
RECLOSER CURVES
COORDINATION RANGE
9
Recloser fuse coordination
Less conservative calculations can be
done
compare 1.75 times A curve to fuse link
min melt time
ELCT 751 DistributionProtection 49
min melt time
compare B to fuse link max clearing time
Calculate the actual cooling based on
thermal time constant of fuse link in
cutout and ambient temperature
Fuse-Recloser Coordination
Reclosers downstream of fuses
are not common
N t d d d t
ELCT 751 DistributionProtection 50
Not recommended and not
considered here
Fuse-Recloser Coordination
Exception: power fuse
protecting substation
transformer on HV side
Must coordinate with MV circuit
ELCT 751 DistributionProtection 51
Must coordinate with MV circuit
breaker and any downstream
reclosers
Considered in section on
substation protection
Recloser-Recloser Coordination
Use time-current curves to
coordinate
Hydraulically controlled units need
about 12 cycles of margin between
dj t it t di t
ELCT 751 DistributionProtection 52
adjacent unit to coordinate
If margin is 2-12 cycles the units
might operate simultaneously
If margin is less than 2 cycles, the
units will operate simultaneously
Recloser-Recloser Coordination
Electronically controlled units
are simply coordinated with
manufacturers time-current
curves:
ELCT 751 DistributionProtection 53
curves:
Maximum clearing time of
downstream (protecting) recloser
less than minimum response time
of upstream (protected) recloser
Reclosing Interval
Time from trip to reclose
Fixed by design of hydraulic
units: 1-2 sec
ELCT 751 DistributionProtection 54
units: 1 2 sec
Programmable in electronic units:
2 sec for example
10
Reclosing Interval
Programmable in electronic units
set from instantaneous to 60 sec
instantaneous is usually too fast to
allowtemporaryfaultstoclear
ELCT 751 DistributionProtection 55
allow temporary faults to clear
2 seconds is a common setting
longer settings, e.g. 5 sec, may aid
coordination with source-side
circuit breakers or fuses
Coordination of recloser with
station circuit breaker
Station circuit breaker may be
used, with overcurrent relay
ELCT 751 DistributionProtection 56
logic
Overcurrent relays tend to
integrate recloser times
Coordination of recloser with
station circuit breaker
Quick check is to compare relay
time-current curve to a
cumulative recloser time current
ELCT 751 DistributionProtection 57
cumulative recloser time current
curve (e.g., 2A+2B in time)
If check shows miscoordination
possible, perform detailed
calculation
Example relay-recloser
coordination
Electromechanical time overcurrent
relay: 0.60 second trip delay and
30 sec reset time
ELCT 751 DistributionProtection 58
Hydraulic recloser on 2A2B
sequence
At fault current: A curve gives
0.035 sec and B curve gives 0.20
sec.
Example relay-recloser
coordination
Disk travel:
Each A clearing: relay disk
0 035/0 60 or 5 8%
ELCT 751 DistributionProtection 59
0.035/0.60 or 5.8%
Each B clearing: relay disk
0.20/0.60 or 33.3%
Each 2 sec open time: relay disk
2/30 or -6.7%
Example (Continued)
Relay completely resets after
each fast (A curve) operation
Calculate total net travel until
lockout:
ELCT 751 DistributionProtection 60
33.3% - 6.7% + 33.3% = 60% <
100%
Relay contacts do not close
Coordination is correct
11
Example (Continued)
Repeat for 1 sec reclosing
interval
Now relay does not completely
reset after fast operations
ELCT 751 DistributionProtection 61
reset after fast operations
Net total relay travel:
5.8-3.3+5.8-3.3+33.3-3.3+33.3 =
68.3% <100%
Coordination is still achieved.
Electronic Devices
Electronically controlled reclosers
have more choices of time-current
curves and reclosing intervals
Electronic overcurrent relays have
ELCT 751 DistributionProtection 62
Electronic overcurrent relays have
more choices of time-current curves
and no disk to reset
Consult relay manufacturers data to
determine reset time (may be a setting)
Sectionalizer Coordination
Does not use time-current curves
Sectionalizer will coordinate with
upstream recloser or circuit breaker
if it is set for fewer counts than the
ELCT 751 DistributionProtection 63
total number of upstream device
operations
Example: four shot upstream
recloser coordinates with a three-
shot downstream sectionalizer
Sectionalizer Application
Two sectionalizers may be used
in series if the downstream
device is set to one fewer count
ELCT 751 DistributionProtection 64
device is set to one fewer count
than the upstream device
Recloser-sectionalizer-fuse
coordination:
Sectionalizer Application
Recloser-sectionalizer-fuse
coordination:
sectionalizer counts downstream
ELCT 751 DistributionProtection 65
fuse blowing
2A2B recloser: fuse blows during
first delayed operation,
sectionalizer arms for final count,
then locks out when fuse blows
Sectionalizer Application
Use 1A3B recloser for 3 shot
sectionalizer with downstream
fuse:
ELCT 751 DistributionProtection 66
fuse:
Fuse clears on second recloser
count, sectionalizer does not lock
out when fuse blows
12
Sectionalizer Application
Recloser-sectionalizer-recloser
is tricky:
Sectionalizer may count either
ELCT 751 DistributionProtection 67
Sectionalizer may count either
recloser
Can work with sectionalizer
voltage restraint to prevent
counting downstream operations
Effect of Distribution
Automation / Remote Control
Distribution automation and
remote control of switches is
ELCT 751 DistributionProtection 68
mostly outside of our scope
Except as it interacts with
overcurrent protection system
Effect of Distribution
Automation / Remote Control
Consider a typical radial feeder
arrangement with normally open
ELCT 751 DistributionProtection 69
g y p
tie switches and normally closed
sectionalizing switches
Look at feeder reconfiguration
Feeder 1
NO
Tie
CB1 S1
T12
Load break switch
ELCT 751 DistributionProtection 70
Feeder 2
Normal Operation
CB2 S2
Feeder 1
NO
Tie
CB1 S1
T12
ELCT 751 DistributionProtection 71
Feeder 2
Fault at X cleared by station breaker
CB1.
CB2 S2
NO
Tie
CB1 S1
T12
ELCT 751 DistributionProtection 72
Feeder 2
Operator opens S1 then closes T12
CB2 S2
13
Recloser Loop Scheme
Consider a recloser loop scheme:
Feeder use a sectionalizing recloser
Adjacent feeder backs up to normally
open tie recloser
l i l i b k
ELCT 751 DistributionProtection 73
Fault trips recloser or station breaker
If sectionalizing recloser loses voltage,
it trips after 60 second delay
If tie recloser loses voltage, it closes
after 70 second delay
Feeder 1
NO
Tie
CB1 R1
T12
Recloser
ELCT 751 DistributionProtection 74
Feeder 2
Normal Operation
CB2 R2
Feeder 1
NO
Tie
CB2
CB1 R1
R2
T12
ELCT 751 DistributionProtection 75
Feeder 2
Fault at X cleared by station breaker
CB1. R1 and T12 lose voltage.
C
NO
Tie
CB2
CB1 R1
R2
T12
ELCT 751 DistributionProtection 76
Feeder 2
60 seconds after R1 loses voltage, it
automatically opens, then after 10
more seconds, T12 closes.
C
Network Systems
Full network distribution systems
are rare, except for secondary
networks (downtown areas of
cities) and spot networks (large
ELCT 751 DistributionProtection 77
cities) and spot networks (large
buildings)
MV feeder circuits are radially
connected to network transformers
Transformer secondaries (LV)
networked
HV Bus
Substation
MV Feeders
Network Transformers
Network Protectors
ELCT 751 DistributionProtection 78
Loads
LV Network
SECONDARY NETWORK
14
Network Transformers
MV Feeders
HV Bus
Substation
ELCT 751 DistributionProtection 79
SPOT NETWORK
Network Protectors and Fuses
LV Network
Loads
Network Systems
The secondary and spot network
systems are quite flexible in
operation
If one transformer is out of service,
ELCT 751 DistributionProtection 80
,
the remaining units can supply the
load
If a fault occurs on a primary
feeder, the transformer will tend to
feed it
Network Protector
Network protector will disconnect
the transformer if it back-feeds the
MV system
Network protector will prevent
ELCT 751 DistributionProtection 81
p p
transformer from being
reconnected unless power will flow
in proper direction
Fuses are often used on network
systems too
Low-Voltage System
Overcurrent Protection
Devices used are fuses and air
circuit breakers, including:
Molded-case circuit breakers
I l t d i it b k
ELCT 751 DistributionProtection 82
Insulated-case circuit breakers
LV power circuit breakers
Time-current curves are used for
coordination in the same way as
already described.
Insulated-case circuit breakers
ELCT 751 DistributionProtection 83
Typical Low-Voltage
Circuit Breaker Time-
Current (Electronic Trip)
T
i
m
e
Long time pickup
Long time dela
ELCT 751 DistributionProtection 84
Current
Long time delay
Short time pickup
Short time delay
Instantaneous
15
T
i
m
e
Long time pickup
ELCT 751 DistributionProtection 85
Current
T
i
m
e
Long time delay
ELCT 751 DistributionProtection 86
Current
Short time delay
similar to long
time delay
T
i
m
e
Sh k
ELCT 751 DistributionProtection 87
Current
Short time pickup
T
i
m
e
ELCT 751 DistributionProtection 88
Current
Instantaneous
SHORT-TIME
PICKUP
SHORT-TIME
DELAY
LONG-TIME
PI CKUP LONG-TIME
PICKUP
LONG-TIME
DELAY
LONG-TIME
TIME
ELCT 751 DistributionProtection 89
INSTANTANEOUS
INSTANTANEOUS
SHORT-TIME
PICKUP
LONG TIME
DELAY
(SHORT-TIME
DELAY SIMILAR)
CURRENT
Coordination
As before, coordination is done
with time-current curves
In all overcurrent protection the
downstream device should trip
ELCT 751 DistributionProtection 90
p
and clear the fault
Before the fastest upstream device
begins operation
Before system damage becomes
excessive
16
Coordination
As before, coordination is
done with time-current curves
Compromise is sometimes
ELCT 751 DistributionProtection 91
Compromise is sometimes
required: Main purpose is to
protect system from short-
circuits
Where to go for more information
Application and Coordination of
Reclosers, Sectionalizers, and
Fuses, IEEE Tutorial 80EHO157-
ELCT 751 DistributionProtection 92
8-PWR
Distribution System Protection
Manual, Cooper Power Systems
Where to go for more information
Manufacturers web sites:
www.abb.com,
www.cooperpower.com,
wwwch cutler hammer com
ELCT 751 DistributionProtection 93
www.ch.cutler-hammer.com,
www.ge.com,
www.sandc.com,
www.siemenstd.com,
www.squared.com