The document is a letter from the Chief Engineer of the Maharashtra State Electricity Transmission Company requesting technical feasibility reports for connecting three proposed solar power projects to the electricity grid. It requests surveys of the three project sites in Osmanabad, Satara, and Gondia districts to identify possible evacuation routes and assess requirements for augmenting infrastructure. The letter provides details of the three developers and their proposed project capacities. It also lists information needed in the feasibility reports, including nearest substations, transmission line lengths and routes, and potential infrastructure upgrades required.
The document is a letter from the Chief Engineer of the Maharashtra State Electricity Transmission Company requesting technical feasibility reports for connecting three proposed solar power projects to the electricity grid. It requests surveys of the three project sites in Osmanabad, Satara, and Gondia districts to identify possible evacuation routes and assess requirements for augmenting infrastructure. The letter provides details of the three developers and their proposed project capacities. It also lists information needed in the feasibility reports, including nearest substations, transmission line lengths and routes, and potential infrastructure upgrades required.
The document is a letter from the Chief Engineer of the Maharashtra State Electricity Transmission Company requesting technical feasibility reports for connecting three proposed solar power projects to the electricity grid. It requests surveys of the three project sites in Osmanabad, Satara, and Gondia districts to identify possible evacuation routes and assess requirements for augmenting infrastructure. The letter provides details of the three developers and their proposed project capacities. It also lists information needed in the feasibility reports, including nearest substations, transmission line lengths and routes, and potential infrastructure upgrades required.
The document is a letter from the Chief Engineer of the Maharashtra State Electricity Transmission Company requesting technical feasibility reports for connecting three proposed solar power projects to the electricity grid. It requests surveys of the three project sites in Osmanabad, Satara, and Gondia districts to identify possible evacuation routes and assess requirements for augmenting infrastructure. The letter provides details of the three developers and their proposed project capacities. It also lists information needed in the feasibility reports, including nearest substations, transmission line lengths and routes, and potential infrastructure upgrades required.
Sub: Technical feasibility report for Solar Power Projects proposed by M/s. Kushal Solar Solutions in Dist.-Osmanabad, M/s. Radhey Energy Pvt. Ltd. in Dist. Satara & M/s. Revival Solutions in Dist. Gondia.
Ref: 1) M/s. Kushal Solar Solutions letter no. Nil Dtd. 13.11.2013, for Grid connectivity for 100 MW at Village: Chivari, Tal.-Tuljapur, Dist.-Osmanabad. 2) M/s. Radhey Energy Pvt. Ltd. letter no. 2011 Dtd. 19.11.2013, for Grid connectivity for 15 MW at Village: Nalavasti (Gondavale), Tal.-Man, Dist.-Satara. 3) M/s. Revival Solutions letter no. Nil Dtd. 20.11.2013, for Grid connectivity for 1 MW at F-33, MIDC, Mundipar, Tal. & Dist.-Gondia.
With reference to above subject, M/s. Kushal Solar Solutions, M/s. Radhey Energy Pvt. Ltd. & M/s. Revival Solutions has proposed to setup Solar Power Projects as detailed below. All these developers vide letters under reference 1 to 3 have requested to this office to submit the technical feasibility report for this projects.
Sr. No. Name of Developer Name of Site, Tal. & Dist. Capacity (MW) Name of Zone 1 M/s. Kushal Solar Solutions Village: Chivari, Tal.-Tuljapur, Dist.-Osmanabad 100 Aurangabad 2 M/s. Radhey Energy Pvt. Ltd. Village: Nalavasti (Gondavale), Tal.-Man, Dist.-Satara 15 Karad 3 M/s. Revival Solutions F-33, MIDC, Mundipar, Tal. & Dist.-Gondia 1 Nagpur
From: The Chief Engineer (State Transmission Utility) Prakashganga, 5 th floor / A Wing, Plot C -19, E - Block, BKC, Bandra (E), Mumbai: - 400051. Phone No.: (O) 022 - 2659 5176, (P) 022 2659 5175, Fax: 022 - 26591222 E-Mail Id: cestu@mahatransco.in, cestu@maharashtrastu.com To: The Chief Engineer EHV Construction cum O&M Zone, MSETCL, Aurangabad / Karad / Nagpur .
Sub: Technical feasibility report for Solar Power Projects proposed by M/s. Kushal Solar Solutions in Dist.-Osmanabad, M/s. Radhey Energy Pvt. Ltd. in Dist. Satara & M/s. Revival Solutions in Dist. Gondia. ------------------------------------------------------------------------------------------------------------------------------------------------------- Page 2 of 3
You are requested to carry out the joint survey along with representatives of M/s. Kushal Solar Solutions, M/s. Radhey Energy Pvt. Ltd. & M/s. Revival Solutions and inform to this office the various possible evacuation arrangements from the existing MSETCL network. The technical feasibility report should have information such as 1. Nearest MSETCLs Sub-station. 2. Present load and capacity of transformers. 3. Length of line from solar plant site to the MSETCLs Sub-station. 4. Availability of space at existing MSETCLs Sub-station for line bays and transformer bays and possibility of procurement of adjacent land for Bus extension. 5. Any augmentation in transformation capacity required. 6. Any EHV Line / Railway / Highway / Forest crossing etc. 7. Route proposed for Grid Connectivity. 8. Any ROW problems.
As the Solar generation is weak in nature & small in capacity, it is beneficial to evacuate the power directly to load centre i.e. at 33 KV level. Hence, please explore the possibility of connection at 33 KV level.
The technical feasibility report furnishing above details is to be submitted to this office within 15 days from the date of this letter.
Sd/- Chief Engineer State Transmission Utility
Copy to: 1. The Superintending Engineer, EHV Construction Circle, MSETCL, Aurangabad / Kolhapur / Nagpur. It is requested to carryout joint survey along with the representatives of M/s. Kushal Solar Solutions, M/s. Radhey Energy Pvt. Ltd & M/s. Revival Solutions respectively.
2. Mr. Avinash Kothari, Partner M/s. Kushal Solar Solutions 654, Mangalwar Peth, 1 st Floor, Kothari Market, Solapur 2. Mobile No.: 9762701947 Tel. No.: (0217) 2721947 E-Mail: avinash.kothari@ymail.com You are requested to approach to the MSETCLs Field Officials for joint site visit.
3. Mr. Sandeep Kadam, Director M/s. Radhey Energy Pvt. Ltd. G-40, LOD MIDC, Nera MIDC office, Satara 415004. Sub: Technical feasibility report for Solar Power Projects proposed by M/s. Kushal Solar Solutions in Dist.-Osmanabad, M/s. Radhey Energy Pvt. Ltd. in Dist. Satara & M/s. Revival Solutions in Dist. Gondia. ------------------------------------------------------------------------------------------------------------------------------------------------------- Page 3 of 3
Mobile No.: 9422400930 Tel. No.: (02162) 245444 Fax No.: (02162) 239330 E-Mail: sandeep.kadam@radheyenergy.com You are requested to approach to the MSETCLs Field Officials for joint site visit.
4. Mr. Milind Perju Kotangale, Proprietor M/s. Revival Solutions F-33, MIDC Industrial Area, Mundipar, Dist. Gondia. Mobile No.: 9637749024 E-Mail: milindp32@yahoo.co.in You are requested to approach to the MSETCLs Field Officials for joint site visit.
UNE-EN - 62231 2007 (EN) (1) Composite Station Post Insulators For Substations With A.C Voltages Greater Than 1000 V Up To 245kV - Definitions, Test Methods and Acceptance Crite