trd question answer
trd question answer
trd question answer
DP
ISOLATOR
CT
CIRCUIT BREAKER
LIGHTNING
ARRESTER
TRACTION
TRANSFORMER
25 kv
42 kv LIGHTNING
CT
ARRESTER
TO BURIED RAIL &
NEAREST RUNNING 25 kv CIRCUIT BREAKER
TRACK 25 kv CT
25 KV SP ISOLATOR 25 kv SP ISOLATOR
NORMALLY CLOSED 100 kva, 25 kv/240 VLT SUPPLY
25 kv SP ISOLATOR TRANSFORMER
25 kv CT
25 KV/110V PT
25 kv FEEDER CIRCUIT BREAKER
(PROTECTION)
25 kv SP ISOLATOR
25 kv BUS COUPLER
INTERRUPTOR
(NORMAL OPEN)
25 kv INTERRUPTOR
25 kv SP ISOLATOR
25 kv PT
SUB SECTIONING &
PARALLELING STATION (SSP)
42 KV LA STATION TYPE:
HEAVY DUTY
SECTOR
Explanation of TSS: 113 words
1. Traction transformer
Traction transformers step down the grid voltage to 25 kV for feeding the
overhead equipment (OHE). The present standard capacity is 21.6 MVA
(ONAN)/30.2 MVA (ONAF).
2. Current transformer: CTs are used for measuring and protection purposes. Cts
ratios are LV side: 750A/5A, 1500A/5A
HV side: 400/5A
3. Potential transformer: PTs are used for measuring and protection purposes.
PTs ratios are
LV side: 25kv/110v
4. Circuit breaker:
High voltage and high rupturing capacity switches with insulating and
extinguishing media SF6 are operated with 110v volt DC controlled with
protections
5. Lightning arrester: Ls are used as protection against surge voltages. LA settings
are:
LV side: 42kv
HV side: 96kv/120kv/198kv
PROTECTION SCHEME
132 KV
DPI
OCR
200-100/5 A CT IDMT REF
INST
132 KV
DP CB
120 KV LA
400/5 A CT
132/25 KV
DIFF
TRANSFORMER
1600/4.09 A CT
42 KV LA
CB
OCR
1500-750/5 A CT REF
IDMT
SPI
BC SPI
OCR
1500-750/5 A CT DPR WPC
INST
PT
FDR CB
SPI
PROTECTIVE RELAYS AT THE TRACTION SUB-STATION
FOR THE TRANSFORMER PROTECTION: 224 words
1. Differential relays: it is provided to protection against inter turn fault
Biased setting : 15% above full load current
High setting: 8 to 10 times of full load current (for protection against
high inrush current during energization)
2. IDMT over current Relays for the primary (HV) as well as for the
secondary (L.V) side and an instantaneous over current element:
these relays are provided to protect transformer against overloading
Instantaneous OCR: 8 to 10 times of full load current
IDMT settings
HV side: 120 % of full load current with time grading from LV side
LV side: 120% of full load current
4. High speed Inter tripping Relays: these relays are provided to isolate
the transformer from both side simultaneously on the basis of
operation of main protective relays
5. Buchcholz relay is a protection against internal fault of transformer in
which transformer oil decomposes resulting in gas formation.
Alarm: low level fault
Tripping: high level severe fault
6. Winding temperature indicator
Alarm 950 C
Tripping 1050 C
2 Chances of No Sometimes
stalling
assistant engine is
required
The function of ATD is to maintain a constant tension in OHE conductors i.e contact wire and
catenary's wire under varying temperature conditions, so that profile of OHE is maintained for
better current collection.
MECHANICAL ADVANTAGE:
Mechanical advantage or total tension on OHE conductors
Thus for a constant tension of 1000kg each for contact wire (T 1) and catenary wire(T2). Counter
weight for 3:1 ratio pulley block is 2000/3 I.e. 667 kg. Hence 665 kg has been chosen.
Counter Weight for 5:1 ratio pulley block is 2000/5 I.e 400kg.
Bearings get damaged due to ingress of dirt and moisture as well due to detoriation in grease,
drying of grease.
3.2 What are the various precautions followed for the parallel operation of Traction
Transformer?
Ans: For parallel operation of transformer following condition should be satisfied
Precautions
1. Preferable to parallel transformer with closest turn ratio and percentage impedence
2. Rating of both transformer be identical for dissimilar KVAR rating circulating current be
less than limit
3. Fault level on LV bus increases so switchgears should be suitably rated
4. Suitable protection to be provided to clear the fault
Causes of pantograph entanglement: 144 words
Pantograph side
OHE side
Other causes
1. Storm
2. Bird hitting
3. Monkey Electrocution
4. Tree branches/foreign materials on OHE
5. Theft
6. Track Defect
Necessity of earthing of electrical equipment system: 268 words
1. To protect men and materials from injury or damage due to over voltage and current.
2. To provide low resistance path to fault current to ensure prompt and consistent
operation of protective devices in case of ground faults.
Measurement of Earth Resistance:
1. Earth resistance is measured by earth tester.
2. E is the earth electrode under test and P & C are auxiliary electrodes.
3. Fix the electrode C at the distance of approx. 25 m from E and fix the electrode P at the
centre of the electrodes E and C.
4. Connect them as figure given below given figure. And Take readings
5. Take two more readings by changing the position of the electrode P and C.
6. Take min. 3 readings and average of them is the earth resistance
Earth Resistance:
System earthing
System earthing: it is provided to limit potential between phases with respect to Earth as a
protection against earth fault.
How the train operation has improved after conversion specially on NE and SE ghat
section
1. 20 minutes saved at IGP for change of traction
2. Average speed increased so running time reduced
3. Higher tonnage train operation with ac loco banker
What is the power factor? what are the cause of low power factor, effect of low power factor
and advantages of the improved power factor?.
ANS: 208 words
POWER FACTOR:
The cosine of the angle between voltage and current in an ac circuit is known as power factor.
The power factor can never be greater than unity.
In an ac circuit there is generally a phase difference between voltage and current.
Causes of low power factor
Most of the AC appliances have induction motors.
The transformers at low loads.
The industrial heating furnaces
Arc lamps
The synchronous motor
Effects of low power factor
For a given power the current drawn by the load at low power factor is large, hence the must
be larger.
Higher cost of generation and transmission
Higher losses low efficiency
Higher voltage drop
Large sizes of alternator and conductor size of transmission line.
Advantages of power factor improvement
The KW capacity of the prime movers is better utilized.
This increases the KW capacity of the alternators.
The KW capacity of transformers and the lines are increased.
The efficiency of every plant is increased.
The overall cost per unit is decreased.
The regulation of the line is increased.
Earthing: Each structure on either side of the crossing span supporting the transmission
line shall be earthed.
Short notes of 5/4 marks
The function of ATD is to maintain a constant tension in OHE conductors i.e contact wire and
catenary's wire under varying temperature conditions, so that profile of OHE is maintained for
better current collection.
MECHANICAL ADVANTAGE:
Mechanical advantage or total tension on OHE conductors
Thus for a constant tension of 1000kg each for contact wire (T 1) and catenary wire(T2). Counter
weight for 3:1 ratio pulley block is 2000/3 I.e. 667 kg. Hence 665 kg has been chosen.
Counter Weight for 5:1 ratio pulley block is 2000/5 I.e 400kg.
The objective being to ensure the safety of personnel and equipment under all
circumstances
1. No work shall be carried out on live electrical equipment. After making
equipment dead, it shall be effectively earthed, before work is started.
2. The responsibility devolving on different officials should be clearly defined
and only “authorized person” may work on electrical equipment.
3. The procedure for effecting shut down and resuming supply should be clear
cut and foolproof.
4. Machinery to ensure that the rules prescribed are actually observed by the
staff concerned.
5. As far as possible, repair work should be carried out during day light hours.
If work has to be done during night hours, sufficient artificial lighting should
be provided.
Objectives – 100% safety and 0% accidents.
.
1. Sometimes masts get out of plumb. They should be checked
2. This occurs due to erosion of earthwork on the outer side of the mast
3. Masts which are out of plumb in excess of 5 cm at a height of 1.85 m from
rail level.
4. Leaning of mast can be set right by releasing the OHE and pulling the mast
by a “Tirfor”.
5. The foundation must first be exposed on the side to which the mast is to be
pulled by the Tirfor.
6. The rear under side of the foundation should be packed and rammed with
pieces of stone until the foundation is fully supported
7. If necessary the newly packed part may be strengthened by pouring in
cement
Sectioning and Paralleling Post (SP)
These posts are situated approximately midway between feeding posts marking
the demarcating point of two zones fed from different phases from adjacent sub-
stations. At these posts, a neutral section is provided to make it impossible for the
pantograph of an electric locomotive or EMU train to bridge- the different Phases
of 25 kV supply, while passing from the zone fed from one sub-station to the next
one. Since the neutral section remains 'dead', warning boards are
provided in advance to warn and remind the Driver of an approaching electric
locomotive/EMU to open locomotive circuit breaker (DJ) before approaching the
'neutral section', to coast through it and then switch 'on' on the other side.
Special care is taken infixing the location of neutral sections, on level tangent
tracks far away from signals, level crossing gates etc. to ensure that the train
coasts through the, neutral section at a sufficiently high speed, to obviate the
possibility of its stopping and getting
stuck within the neutral section.
A paralleling interruptor is provided at each 'SP' to parallel the OHE of the up and
down tracks of a double track section.'bridging interruptors' are also provided to
permit one feeding post to feed beyond the sectioning post upto the next FP if its
25
kV supply is interrupted for some reasons. These bridging interruptors are
normally kept open and should only be closed after
taking special precautions as detailed in these rules.