Aj 601
Aj 601
Aj 601
SPECIFICATION
Client
Plant
Location
04184
AJ-601
Dept./Sect.
Project
Specification
THIS DOCUMENT/DRAWING IS THE PROPERTY OF ABB LUMMUS GLOBAL B.V. INCLUDING ALL PATENTED AND PATENTABLE FEATURES AND/OR CONFIDENTIAL INFORMATION AND ITS USE IS CONDITIONED UPON THE USERS AGREEMENT NOT TO REPRODUCE
THE DOCUMENT/DRAWING, IN WHOLE OR IN PART, NOR THE MATERIAL DESCRIBED THEREON, NOR TO USE THE DOCUMENT/DRAWING FOR ANY PURPOSE OTHER THAN AS SPECIFICALLY PERMITTED IN WRITING BY ABB LUMMUS GLOBAL B.V.
Doc. No.
DE-04184-AJ-0601
Rev. 0
Specification For:
PILING
AJ-601
2005-03-11
REV.
DATE
DESCRIPTION
JLE
PREPARED
GL
CHECKED
AJ-601.DOC
JLE
APPROVED
Page 1 of 1
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
INDEX
SECTION
PAGE
1.
GENERAL
1.1
SCOPE
1.2
DEFINITIONS
1.3
REGULATORY REQUIREMENTS
1.4
1.5
UNITS
1.6
SITE CONDITIONS
1.7
ENVIRONMENTAL CLASS
2.
SELECTION OF PILES
2.1
GENERAL
2.2
TYPE OF PILES
2.3
SPACING OF PILES
3.
GENERAL REQUIREMENTS
3.1
DESIGN
3.2
MARKING
3.3
HANDLING
3.4
3.5
STAKING OUT
4.
STEEL PILES
4.1
MATERIALS
4.2
SURFACE TREATMENT
10
AJ-601.DOC
Page 2 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
INDEX (Contd)
SECTION
PAGE
5.
10
5.1
MATERIALS
10
5.2
DESIGN OF REINFORCEMENT
10
5.3
FABRICATION
11
5.4
TOLERANCES
11
6.
11
6.1
MATERIALS
11
6.2
DESIGN OF REINFORCEMENT
12
6.3
FABRICATION
12
6.4
TOLERANCES
13
7.
13
7.1
GENERAL
13
7.2
MATERIALS
13
7.3
DESIGN OF REINFORCEMENT
13
7.4
TOLERANCES
13
8.
PREDRILLING
13
9.
PILE DRIVING
14
9.1
GENERAL
14
9.2
DRIVING EQUIPMENT
14
9.3
14
9.4
DRIVING PROCEDURE
15
9.5
16
AJ-601.DOC
Page 3 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
INDEX (Contd)
SECTION
PAGE
9.6
DRIVING TOLERANCES
17
9.7
17
9.8
PILE LENGTHENING
17
10.
PILE TESTING
18
10.1
GENERAL
18
10.2
PILE CAPACITIES
18
10.3
EQUIPMENT
19
10.4
INSTRUMENTATION
20
10.5
LOADING PROCEDURE
20
10.6
RESULTS
23
11.
23
11.1
GENERAL
23
11.2
DOCUMENTS
24
11.3
INSPECTION
24
AJ-601.DOC
Page 4 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
1.
GENERAL
1.1
SCOPE
1.1.1
This specification covers the minimum requirements for the design, materials, fabrication and
installation of driven and bored piles.
1.1.2
AK-601 Earthworks.
1.2
J-601
Civil/Structural Design.
DEFINITIONS
For the purpose of this specification, the following definitions shall hold:
Client
Contractor
Supplier
Shall
Is to be understood as mandatory.
Should
May be
1.3
REGULATORY REQUIREMENTS
1.3.1
The work covered in this specification shall comply with all relevant governmental and local
laws, specifications, regulations and standards.
1.3.2
For subjects not covered by regulations, codes and standards or specifications, the design,
material, fabrication and erection shall be based on good economical engineering practice,
subject to approval by client.
1.4
AJ-601.DOC
Page 5 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
1.4.1
1.4.2
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
IS:1200-Part 23
IS:1786
IS:2062
IS:5121
IS:8112
IS:10262
In case of conflict between above-mentioned codes and standards and this specification,
contractor shall inform client, who will advise.
Where European or American codes/standards are referred to in this specification, equivalent
local codes and standards may be substituted, subject to approval by client.
1.5
UNITS
1.5.1
Elevations
meter (m).
Dimensions
millimeter (mm).
Force
kilonewton (kN).
Mass
kilogram (kg).
Moment
Stress
Pressure
kilopascal (kPa).
Loadings
kilonewton/m (kN/m).
1.5.2
For simplification purposes, one (1) kg weight may be taken as equal to 10 N (0.010 kN).
1.6
SITE CONDITIONS
1.6.1
For general site and design data, refer to geotechnical investigation report.
AJ-601.DOC
Page 6 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
1.6.2
The geotechnical investigation report, including pile bearing and horizontal load capacities, shall
be supplied by client. Any additional geotechnical information and/or advice required by
contractor to carry out the work shall be obtained by contractor.
1.6.3
A suitably qualified surveyor should locate existing underground obstacles in the area of interest
to determine potential conflicts with piling.
Should such conflicts be found, works shall not proceed until client advises contractor regarding
methods to overcome these conflicts.
1.7
ENVIRONMENTAL CLASS
Applicable environmental class to be in accordance with local and governmental regulations.
2.
SELECTION OF PILES
2.1
GENERAL
2.1.1
The main function of bearing piles is to transfer the loads on a foundation to deeper (soil) strata
which are capable of carrying such loads, in such a way that:
The design and testing of piles shall take into account both short-term and long-term behavior of
the pile foundation.
2.2
TYPE OF PILES
2.2.1
The type of piles with regard to material (steel, cast-in-situ or precast concrete) and method of
installation shall be as called for on design drawings and as recommended by approved piling
specialist.
2.2.2
The type of pile to be used is defined by type of loading, the soil conditions, such as drivability
and corrosivity of soil, possibility of tension stresses in the pile due to heave and also the site
conditions, such as effect upon nearby plant and existing works.
Driven prefabricated piles shall be applied wherever possible.
2.2.3
The choice with regard to end bearing, friction, or partly friction and partly bearing type of piles
shall be determined in accordance with geotechnical data recommendations and shall be as
specified by the geotechnical investigation report.
2.2.4
If more than one type of pile is suitable in any particular condition, then the choice shall be
governed by relative costs.
2.2.5
Whatever type of pile is used, it should have the necessary strength when installed to transfer
the loads imposed on it to the soil.
2.2.6
Raked piles shall be avoided where possible and shall be provided to resist horizontal forces
where the latter cannot be resisted by piled foundations on vertical piles.
AJ-601.DOC
Page 7 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
2.2.7
Neutral earth resistance on pile caps, ground beams, etc., may be taken into account in
assessing the foundations ability to resist horizontal forces.
2.3
SPACING OF PILES
Rev.
Error:
The minimum center-to-center spacing of piles shall be as follows, unless otherwise specified in
the geotechnical investigation report:
For piles deriving their resistance from end bearing: not less than twice the least
width or diameter of the pile.
Piles deriving their resistance from both end bearing and skin friction: Not less
than three pile diameters.
3.
GENERAL REQUIREMENTS
3.1
DESIGN
3.1.1
The contractor is responsible for performing pile reinforcement calculations, all in accordance
with the applicable codes and regulations.
3.1.2
The contractor is responsible for obtaining all information required for the calculation of the pile
reinforcement. Calculations shall incorporate the following load cases and requirements:
Transport/fabrication of piles.
Additional load due to negative skin friction to be added to the design capacities
for each pile.
be:
Safety factor for pile capacity (including positive or negative skin friction) shall
Safety factor for lifting (in pile driving equipment) shall be 2.0 with pile tip on the
ground and 1.4 with pile tip on a lorry.
All safety factors shall be in accordance with the latest applicable codes and
regulations and shall be confirmed by the contractor.
3.1.3
AJ-601.DOC
Page 8 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
3.2
MARKING
3.2.1
After a prefabricated concrete pile has been cast, the date of casting, reference number, sizes
and where appropriate, the prestressing force shall be clearly inscribed on a label near the top.
3.2.2
Lifting and support point shall be indicated on the shaft of the piles.
3.2.3
Each prefabricated concrete pile shall be marked at intervals of 200 mm along the top 5 m of its
length before being driven.
3.2.4
Test piles shall be marked at intervals of 200 mm over the full length.
3.2.5
Each prefabricated concrete pile shall receive a color marking on top. Piles with standard
reinforcement shall get a green mark, while piles with extra reinforcement shall be marked in
purple.
HANDLING
3.3
3.3.1
The method and sequence of lifting, transporting from the factory to the construction site and
storing of piles shall be such that the piles are not damaged. Only the designed lifting and
support points shall be used.
During transport and storage, piles shall be stored on adequate supports located under the lifting
points of the piles.
3.3.2
Contractor has to prepare and submit handling procedures to client for approval before starting
the work.
3.3.3
Client shall inspect each pile when it is delivered on the construction site. Piles which are
damaged to such an extent that, in the opinion of client, their structural integrity is impaired or
likely to be impaired during the driving, will be rejected by client.
3.4
3.4.1
Storage facilities for piles must be installed on site as a part of the pile works. Upon receipt, piles
must be inspected by client, material receiving reports made and issued. In case of damage,
damaged piles shall be removed from construction site.
3.4.2
Piles shall not be stacked in more than four layers, with wooden cribbing installed so lower pile
is free from the ground.
3.4.3
All piles within a stack shall be in groups of the same type. Packings of uniform thickness shall
be provided between piles at the lifting points.
3.5
STAKING OUT
3.5.1
Contractor must stake out the locations of the piles. Stakes shall be numbered and color-coded
in accordance with the numbering on the piling drawings.
4.
STEEL PILES
AJ-601.DOC
Page 9 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
4.1
MATERIALS
4.1.1
All materials and work shall be in accordance with engineering specification JB-611.
4.1.2
Unless otherwise specified, grade of steel for H-profiles shall be weldable ordinary structural
steel of Grade Fe 410WB, all according to IS:2062 or BS EN 10025 (Grade Fe 430B). All
structural steel pipes shall be Grade Yst-240 to code IS:1161. Pipes shall be either seamless or
mill welded. Spiral-welded pipe is not acceptable. Section sizes and lengths shall be as indicated
on the drawings.
4.1.3
The grade of steel for splice plates, caps and driving points shall be the same as that of the steel
section. Connections should be all welded to the details shown on the drawings.
4.1.4
4.2
Protective coatings where required, shall be as indicated on the drawings. Length of coating shall be
indicated on the drawings.
SURFACE TREATMENT
Surfaces due to receive a protective coating shall be blast cleaned, prior to application of the
coating, which shall then be applied in accordance with the suppliers instructions. Areas
modified within the coated length, such as at cutoffs and at splices with plates welded, shall be
recoated using materials and methods compatible with the existing coating. Curing should be
allowed to take place before pile installation.
5.
5.1
MATERIALS
5.1.1
All materials and work shall be in accordance with engineering specification A-611.
5.1.2
The concrete mixes shall be in accordance with IS:456 and IS;10262. Concrete grade: M45.
5.1.3
5.1.4
5.1.5
Reinforcing quality shall be in accordance with IS:1786 with minimum characteristic yield
strength of 415 N/mm.
5.2
DESIGN OF REINFORCEMENT
5.2.1
The cover to reinforcement, including binding wire, shall not be less than 40 mm for fully
embedded piles in the ground and not less than 50 mm for piles installed in or above open
water.
5.2.2
The steel reinforcement shall be designed in such a way that the crack width of the concrete will
remain less than 0.2 mm under all loading conditions.
5.2.3
Local bars for resisting bending moments may be added but shall be so arranged as to avoid a
sudden discontinuity of the reinforcing steel which could lead to cracking during heavy driving.
AJ-601.DOC
Page 10 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
5.2.4
Lateral reinforcement which is of particular importance in resisting driving stresses, shall be not
less than 6 mm diameter, securely fixed to the main reinforcement.
Lateral reinforcement should be not less than 0.6% of the gross volume, applied over a distance
of three pile diameters from each end of the pile.
5.2.5
Lateral reinforcement in the body of the pile shall be not less than 0.2%, spaced at not more than
half the diameter of the pile. The transition between the close spacing near the ends and the
maximum spacing should be made gradually over a length equal to about three times the
diameter.
5.2.6
If joints to main longitudinal bars are required, they shall be staggered and preferably be made
by full penetration butt-welding.
5.3
FABRICATION
5.3.1
5.3.2
The quantities and sizes of the piles are as specified in the piling contract documents.
5.3.3
5.3.4
Corners and driving head of square piles shall have 25 mm chamfers unless otherwise called for
on design drawings.
5.3.5
5.3.6
5.3.7
An electric control wire in each pile shall be installed in order to ensure that pile is undamaged after
prefabrication, transport and installation.
5.3.8
Concrete shall be placed continuously for each pile to avoid cold joints.
5.3.9
5.3.10
5.4
TOLERANCES
The curvature along the axis of the pile shall not exceed 1 mm/m of length.
6.
6.1
MATERIALS
6.1.1
All materials and work shall be in accordance with engineering specification A-611.
6.1.2
The concrete mixes shall be in accordance with IS:456 and IS;10262. Concrete grade: M35
6.1.3
6.1.4
AJ-601.DOC
Page 11 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
6.1.5
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
Reinforcing Quality
For nonprestressed steel; according with IS:1786 with minimum characteristic yield
strength of 415 N/mm.
For prestressed steel; according to IS:1786 and IS:10790 Part 1, shall have a minimum
nominal tensile strength of 1500 N/mm.
6.2
DESIGN OF REINFORCEMENT
6.2.1
The cover to reinforcement, including binding wire, shall not be less than 40 mm for fully embedded
piles in the ground and not less than 50 mm for piles installed in or above open water.
6.2.2
The steel reinforcement shall be designed in such a way that the crack width of the concrete will
remain less than 0.05 mm under all loading conditions.
6.2.3
Local bars for resisting bending moments may be added but shall be so arranged as to avoid a
sudden discontinuity of the reinforcing steel which could lead to cracking during heavy driving.
6.2.4
Sufficient prestressing steel shall be provided in the form of high-tensile wire, strand or bar so that
the effective prestress after losses is sufficient to resist all loading conditions.
6.2.5
Under normal loading conditions tensile strength of prestressed reinforcement shall be 50% of the
maximum allowable tensile strength.
6.3
FABRICATION
6.3.1
6.3.2
The quantities and sizes of the piles are as specified in the piling contract documents.
6.3.3
6.3.4
Corners and driving head of square piles shall have 25 mm chamfers unless otherwise called for on
design drawings.
6.3.5
6.3.6
6.3.7
An electric control wire in each pile shall be installed in order to ensure that pile is undamaged after
prefabrication, transport and installation.
6.3.8
Concrete shall be placed continuously for each pile to avoid cold joints.
6.3.9
AJ-601.DOC
Page 12 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
6.3.10
6.4
TOLERANCES
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
The curvature along the axis of the pile shall not exceed 1 mm/m length.
7.
7.1
GENERAL
The types of piles to be used shall be selected on the basis of the site and loading conditions.
Contractor may propose alternatives to the types indicated on the design drawings.
7.2
MATERIALS
7.2.1
All materials and work shall be in accordance with engineering specification A-611.
7.2.2
The concrete mixes shall be in accordance with IS:456 and IS;10262. Concrete grade: M25
7.2.3
7.2.4
7.2.5
Reinforcing quality shall be in accordance with IS:1786, with minimum characteristic yield
strength of 415 N/mm.
7.3
DESIGN OF REINFORCEMENT
7.3.1
7.3.2
The steel reinforcement shall be designed in such a way that the crack width of the concrete will
remain less than 0.2 mm under all loading conditions.
7.3.3
The cover to reinforcement, including binding wire, shall not be less than 40 mm.
7.4
TOLERANCES
The curvature along the axis of the pile shall not exceed 1 mm/m length.
8.
PREDRILLING
8.1
In areas with underground obstacles of which the exact location is not known, predrilling should be
executed.
8.2
8.3
Drill diameter shall not exceed equivalent pile diameter. Diameter shall not exceed 400 mm.
AJ-601.DOC
Page 13 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
The average drill depth shall be not deeper than 5 m above toe elevation of the pile.
AJ-601.DOC
Page 14 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
9.
PILE DRIVING
9.1
GENERAL
9.1.1
A pile driving procedure, which includes the minimum blow count, description of load tests when
required, shall be established by contractor. No pile driving activities are allowed until approval is
received from client.
9.1.2
Piles shall not be driven until the concrete has achieved the specified characteristic strength.
9.1.3
Before the start of pile driving, the required excavation work shall be done in accordance with
engineering specification AK-601.
9.1.4
The installation of piles and the sequence of driving shall be in accordance with the relevant design
drawings and requirements.
9.1.5
Piles shall be driven vertically, except where noted on the design drawings.
9.1.6
Piles shall be driven within the tolerances set forth in subsection 9.6 of this specification.
9.1.7
9.2
DRIVING EQUIPMENT
9.2.1
Energy of the driving hammer shall be adjustable and set to the requirements for the pile type.
9.2.2
The contractor shall submit records of the type of rig and pile hammer he intends to use, indicating
weight, energy per blow, drop height, etc.
9.2.3
Pile driving and lifting equipment ensuring stability during handling, lifting and installing of the piles,
shall be strictly as stated in contractor's tender.
9.2.4
Driving of each pile shall start with new cushion material in the pile cap.
9.2.5
In hazardous areas, plastic dollies or other approved type shall be used for safety purposes.
9.3
9.3.1
The sequence of driving piles shall be as agreed with client before commencement of any work and
contractor may be requested by client to adjust its sequence.
9.3.2
In general, the first pile shall be driven close to the location of a CPT (if available).
9.3.3
If pile driving has to be carried out on a sloping surface, driving shall start at the higher parts.
9.3.4
Piles in a large group should be either driven progressively from one side to the other or outward
from the center of the group. The final driving sequence shall be determined after detailed piling
plan is available.
AJ-601.DOC
Page 15 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
9.4
DRIVING PROCEDURE
9.4.1
Each pile shall be driven continuously until the specified or approved set and/or depth has been
reached and to the minimum specified blow count and, if applicable, when the pile tip has reached
the bearing zone.
9.4.2
If refusal is encountered above the bearing zone, the pile driving system and/or installation
procedure shall be adjusted in order to achieve the specified depth.
9.4.3
If a pile does not meet the specified blow count, if applicable, within the bearing zone, driving shall
continue until the specified minimum blow count is achieved over a one meter interval. Alternatively,
these piles may be accepted if selective pile load tests do support that these piles have sufficient
capacity at the specified depths.
9.4.4
During driving of piles to a specified toe elevation, the piling specialist shall carry out a continuous
check of the behavior of each pile and he will calculate, if necessary, by using HILEY or other
approved formula, that each pile will reach the capacity required at the depth specified.
9.4.5
The penetration depth into the bearing soil layer, if applicable, shall be 3 x diameter of pile or 3 x the
dimension of a side in case of a square pile.
9.4.6
At all stages during driving the piles shall be adequately supported and restrained by means of
leaders, trestles, temporary supports or other guide arrangements to maintain position and
alignment and to prevent buckling. These arrangements shall be such that damage to the pile does
not occur.
9.4.7
To prevent damage to the pile during driving, the contractor shall ensure that the pile hammer is
properly centered over the pile, the steel cover (pile cap) over the pile head fits properly (20 mm ply
maximum), the wooden filling (two (2) layers of pinewood) has the proper thickness (120 mm at
least) and that this filling is replaced as required.
9.4.8
In case the pile drifts away during the driving, the pile hammer shall be recentered over the pile to
prevent unnecessary stresses.
9.4.9
Piles shall be driven only. Pulling, jetting, jacking of piles into the required position shall not be
permitted.
9.4.10
Where penetration of the pile is suddenly resisted by underground obstructions, such as buried
rocks, the pile contractor shall stop pile driving and bring this condition immediately to the attention
of client for resolution.
9.4.11
Where piles are of the driven type and the spacing and ground conditions are such that ground
heave is likely, the resulting amount of uplift and lateral movement of the piles shall be recorded by
means of levels and positions taken on each pile each day, over a period agreed between
contractor and client.
Piles which heave more than 25 mm shall be reseated to their original elevation.
9.4.12
An elevation shall be taken on each pile as soon as it has been driven and elevations shall again be
taken on all piles after completion of driving.
AJ-601.DOC
Page 16 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
9.5
9.5.1
Penetration and driving records shall be kept by the contractor and shall be supplied (daily) to the
client.
9.5.2
The pile installation log book records shall include, but not be limited to, the following information:
9.5.3
a.
b.
c.
Type of pile.
d.
Dimensions of pile.
e.
Date of manufacture.
f.
g.
h.
i.
j.
Reference elevation.
k.
l.
Make, type and weight of hammer, and suppliers rated energy per blow if applicable.
m.
Stroke of hammer.
n.
o.
For each pile nearest to a Cone Penetration Test (CPT) location, blow counts shall be
recorded over the total length of the pile, and these blow counts shall be presented in a
graph together with the relevant CPT.
p.
Special observations during pile driving, such as intervals in driving, crushing of the pile
material, replacement of casing, etc.
Extended length.
AJ-601.DOC
Page 17 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
9.6
DRIVING TOLERANCES
9.6.1
Piles shall be driven to the specified positions within the following tolerances:
Rev.
Error:
The maximum deviation from the specified slope shall not exceed 1%
(10 mm/m) of the pile length or any section of the length measured when the pile is
aboveground in the leads.
The contractor shall prepare a table showing the deviation of every pile from its exact required
position and forward this information to the client.
9.7
9.7.1
In case the location of a pile is outside the allowable tolerances, client will decide whether the pile
location is acceptable or if additional pile(s) have to be driven or structural modifications may be
required.
9.7.2
If a pile is damaged during pile driving activities, client will decide whether the pile can be repaired
or if the pile shall be cut off and abandoned. The decision of client shall be binding.
9.7.3
Damaged driven concrete piles shall be tested (when required) with the "Acoustic Wave Method",
executed by an approved geotechnical specialist.
9.8
PILE LENGTHENING
9.8.1
9.8.2
AJ-601.DOC
Page 18 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
10.
PILE TESTING
10.1
GENERAL
10.1.1
10.1.2
The results of the integrity tests shall be used as basis to decide on additional pile load tests or
replacement. Client's approval is to be obtained.
10.1.3
Tests shall be made both, before and during the schedule pile installation.
Types and pile tests are as follows:
Vertical compression
2 x working load.
Vertical tension
2 x working load.
Horizontal
2 x working load.
Vertical compression
1 x working load.
Vertical tension
1 x working load.
Horizontal
1 x working load.
Ultimate load tests should all be carried out on preliminary piles. Proof load tension tests should also
be carried out on preliminary piles. Other proof load tests should be carried out on working piles.
The locations of preliminary piles should be shown on the drawings. These should be finally cut off a
minimum of 300 mm below pile cap level.
10.2
PILE CAPACITIES
Pile capacities, i.e. allowable working loads should be confirmed by the ultimate load tests as
follows:
When determined or confirmed by a loading test, the allowable pile capacity should be 50%
of the ultimate load, but should in no case exceed the load which produces a net movement
of 0.3 mm per 10 kN of gross load applied.
The test should be arranged so that uplift pile capacities are measured simultaneously with
"vertical loading" capacities. Uplift capacities shall be determined as for above vertical
loads.
AJ-601.DOC
Page 19 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
Piles should be tested for lateral design capacity in accordance with the following
procedure:
The test load should be 200% of the proposed working lateral load on the pile and produce,
at first cycle, no more than 12 mm lateral movement. The lateral movement at the pile
cutoff elevation should be less than 5 mm when tested with the proposed working load.
10.3
EQUIPMENT
Contractor is responsible for the design, procurement and construction of all structural details
required for the tests.
Vertical compression or tension loads should be applied axially to the test piles, with care
taken to minimize eccentric loadings. A sufficiently strong test beam should be centered
over the test pile to achieve this, together with hydraulic jack.
Reaction System
For vertical compression loads the beam can be reacted against either
kentledge or neighboring tension pile.
For vertical tension loads the beams can be reacted against either preliminary
or working piles.
AJ-601.DOC
Page 20 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
10.4
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
INSTRUMENTATION
The main objective of the load tests is to derive load-displacement curves from the results.
Therefore during testing measurements should be taken for load, displacement and time.
Loads
Loads applied to the pile head can be monitored by one (1) of the following instruments:
Displacement
Variations in temperature should be monitored throughout the test, to ascertain the influence upon
test results. Equipment should be protected against weather conditions in an appropriate manner.
Instrumentation should be arranged in such a manner that it can be conveniently observed from a
single position.
Before the start of testing, calibration certification for instrumentation should be submitted to client.
10.5
LOADING PROCEDURE
Test piles should be of the same type and installed with the same equipment as working piles. Tests
should be carried out during the normal piling contract and with client's present and should not
require a separate mobilization.
10.5.1
AJ-601.DOC
Page 21 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
The following steps are proposed for loading to 1.5 working load:
0.25 - 0.50 - 0 0.50 - 0.75 - 0 0.75 - 1.00 - 0 1.00 - 1.25 - 0 1.25 - 1.50 - 0, etc., times the working load.
It might be necessary to unload to, for example, 0.1 times the working load instead of 0.0 to prevent
movement at the loading frame relative to the pile.
Working load is defined as the allowable load according to pile design plus
negative friction on compression piles if applicable.
Piles can be loaded up "regularly and reasonably fast". We recommend that the shortest of
the following criteria is applied for each "new" load.
Constant until pile head movement is smaller than 0.1 mm/20 minutes.
Method B
The pile should be progressively loaded as follows:
The load should be maintained at each stage for the period indicated or until movement under the
specific loads has ceased completely, whichever is the longer period.
Movement may be considered as ceased when it is continuing at no more than the following rates:
0.1 mm/20 minutes.
Rate of Loading
% of Working Load
25
50
75
100
75
50
25
0
100
125
150
175
Time
1 hour
1 hour
1 hour
6 hours
10 minutes
10 minutes
10 minutes
10 minutes
6 hours
1 hour
24 hours
1 hour
AJ-601.DOC
Page 22 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Rate of Loading
% of Working Load
200
175
150
125
100
75
50
25
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
Time
6 hours
10 minutes
10 minutes
10 minutes
10 minutes
10 minutes
10 minutes
10 minutes
*
*
*
Rate of Loading
% of Working Load
Time
50
100
150
100
50
0
10.5.3
1 hour
1 hour
6 hours
10 minutes
10 minutes
-
Rate of Loading
% of Working Load
50
100
150
100
50
0
Time
1 hour
1 hour
48 hours
10 minutes
10 minutes
-
AJ-601.DOC
Page 23 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
10.6
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
RESULTS
The settlement or movement of piles under test loads shall be measured and recorded on
completion of each loading stage and every three (3) hours where the load period exceeds
one (1) hour, but does not exceed twelve (12) hours, thereafter every twelve (12) hours.
All results should be forwarded to client in an agreed format.
Any necessary interpretation of test results will be made by client. Should test results warrant, client
may modify installation procedures and criteria, or the design load capacities of piles.
11.
11.1
GENERAL
11.1.1
The appointed contractor should ensure the quality of work in respect of both workmanship and
materials. There shall be an element of self-certification (quality plan) and this shall be formalized by
submissions to client. Specific requirements are as follows:
Method Statements.
Contractor should submit method statements (plans) for the following, fully detailing
equipment and materials to be used:
Pile installation.
Pile testing.
Workmanship.
Contractor should employ qualified personnel, fully experienced in the work to be carried
out.
11.1.2
Contractor shall submit certificates, before work starts, for all materials to be used in the works.
11.1.3
For steel piles certified mill tests reports shall be kept on file by the contractor for inspection by the
client.
11.1.4
For concrete piles (prefabricated and cast-in situ) material certificates shall be submitted for:
11.1.5
Cement.
Reinforcing steel.
Contractor shall cast sufficient concrete cylinders or cubes, depending on what the design has been
based and make the required tests as per the requirements stipulated in the applicable code. The
detailed record of the tests shall show the results that the specified concrete strength has been
reached. Copies of this record shall be submitted to the client within three working days.
AJ-601.DOC
Page 24 of 24
Plant
441
Location
Dept./Sect.
Doc. No.
Error:
Reference
Project
AJ-601
Specification
Rev.
Error:
11.1.6
If any test specimen fails to meet the specified concrete strength, contractor shall carry out new
tests for the already cast piles of the related batch. If the new tests fail again, contractor shall bring
this condition immediately to the attention of the client for resolution.
11.1.7
In the case of proprietary products, full catalogue details should be forwarded. For steel fabrication,
shop drawings should be submitted.
11.1.8
Contractor shall employ the services of an independent materials testing laboratory. A testing
program shall be agreed at the start of the contract. Test reports demonstrating compliance with the
specification shall be submitted to client upon completion of piling work. The test reports shall be the
property of the client.
11.2
DOCUMENTS
Piling contractor shall provide following documents:
Pile Logs.
Pile logs shall be submitted daily to the client (see also section 9).
Contractor shall submit a report of the pile tests carried out, the scope of which shall be
agreed with the client (see also section 10).
As-built Drawings
Contractor shall submit a marked-up drawing giving full details of actual piles installed.
11.3
INSPECTION
11.3.1
Client reserves the right of inspection of the work by the client during all phases of the work.
11.3.2
Contractor shall keep a competent representative at the work fully authorized to act for him and
receive such orders as may given for proper continuation of the work.
AJ-601.DOC
Page 25 of 24