BOP Discussion
BOP Discussion
BOP Discussion
Centralizes and hangs off (i.e., closes a set of pipe rams around the drill string and supports its weight)
the drill string in the wellbore7
Seals the annulus between the drill pipe and the casing to shut in the well8
Seals the well by completely closing off the wellbore if no pipe is in the hole10
Severs the casing or the drill pipe to seal the well in emergencies (e.g., loss of station keeping/
emergency disconnect)11
Annular BOP
Annular BOPs are located at the top of the BOP stack. While only one is required by regulation, two annular
BOPs were installed on the Deepwater Horizon LMRP.16 The Cameron DL Annular BOP has a donut like rubber
seal known as an elastomeric packing element, reinforced with steel ribs or inserts. The packing element is
situated in the annular BOP housing between the head and the top of the hydraulic piston. When the piston is
actuated, its upward movement forces the packing unit to constrict, sealing the annulus or open hole.17 Figure
3 is a cutaway view of a Cameron DL Annular BOP.
Riser Adapter
Flex Joint
Kill Line
Blue Pod
Yellow Pod
53.75 ft.
LMRP
Kill Line
Wellhead Connector
Riser
Flex Joint
Upper Annular
Lower Annular
LMRP Connector
ST Locks
Blind Shear Rams
Wellhead Connector
Head
Annular Element
(Elastomeric Packing Unit)
Annular Body
Piston
One (1) Cameron Upper Ram type TL double-body BOP with ST Locks and sequence valves fitted to
the upper cavity and with super shear bonnets fitted to the lower cavity:
Blind shear ram: shearing blind ram subassemblies19
Casing shear ram: super shear ram subassemblies20
One (1) Cameron Ram type TL BOP single unit with ST Locks and sequence valves:
Upper pipe ram: variable bore ram subassembly21
One (1) Cameron Lower Ram type TL double-body BOP with ST Locks and sequence valves on both
cavities:
Middle pipe ram: variable bore ram subassembly22
Lower pipe ram: variable bore test ram subassembly23
Ram BOP
A ram BOP essentially is a valve that uses a pair of opposing pistons and steel ram blocks. The ram blocks
extend through guide chambers (ram cavities) of the BOP housing (body) and extend (close) toward the center
of the BOP wellbore to halt returning flow, or are left retracted (open) to permit flow. The inner and top faces of
the ram blocks are fitted with elastomeric seals or packers that seal against the ram blocks, between each other,
against the drill pipe running though the wellbore, against the ram cavity, and against the wellbore.25 Outlets
at the sides of the BOP body are used for connection to choke and kill valves and piping.26 The three types of
rams, or ram blocks, in use on the Deepwater Horizon at the time of the incident were variable bore pipe rams
(VBRs), blind shear rams (BSRs), and casing shear rams (CSRs).27
Top Seals
VBR Packers
Bottom Ram
Figure 5 Typical Blind Shear Ram
Upper Ram
Lower Ram
Ram Block
ST Lock Body
Wellhead Connector
The wellhead connector is attached at the bottom of the BOP stack and is used to lock the BOP stack onto the
wellhead.34 A metal gasket ensures pressure integrity between the connector and the wellhead. Because the
connector is hydraulically actuated, the BOP stack can be remotely attached or released from the wellhead.
Associated Equipment
Deepwater Horizon Diverter System
The diverter is an integral part of the mud control system, directing drilling fluids returning from the well into the
mud processing system.35 When required, the diverter is closed and flow from the well is directed either to the
mud-gas separator (MGS) or through flow lines overboard away from the drilling rig. The Deepwater Horizon
diverter is rated for a maximum working pressure of 500 psi36 with a 14in. diameter line to the MGS, as well as
a 14in. diameter port and starboard overboard flow lines.37 See Figure 8.
Diverter Housing
Starboard Overboard
Line
Drilling Riser
Figure 8 Deepwater Horizon Diverter System
Moon Pool
Figure 10 Deepwater Horizon ABB Vetco Gray Riser with Buoyancy Modules
Primary
The primary means of operating the BOP was the electro-hydraulic/multiplex control system (MUX). The MUX
control system transmits electrical command signals to operate functions on the BOP. Commands from the
surface control panels are sent through cables to two subsea control pods located on the LMRP. The signals are
processed by the electronics located in the pods and converted to hydraulic signals that operate control valves
directing operating fluid to the BOP stack.43 Each control pod contains an assembly with two subsea electronic
modules (SEMs), two subsea transducer modules (STMs), pressure regulators, solenoid valves, subsea
hydraulic accumulators, and operating valves.44 The STMs monitor the hydraulic control system pressures and
the hydrostatic pressure acting on the BOP.45
Secondary
The four secondary means of BOP control included:
Auto-shear Function
The auto-shear mechanically activates the high-pressure shear circuit to close the blind shear rams and ST
Locks if the LMRP is unexpectedly disconnected from the BOP stack.50
Two subsea electronic modules (SEM A and SEM B) are located in each of the pods for a total of four
SEMs on the BOP stack.A
AMF cards (one per SEM, two per pod, and four in the BOP system)
A dedicated 9-volt (V) DC battery pack per AMF card (one per SEM, two per pod, and four in the BOP
system)
27V DC battery pack shared for both SEM A and B (one per pod and two in the BOP system)
Solenoid 103 is energized to activate the high-pressure shear circuit for 30 seconds when the AMF is
activated
Dedicated subsea hydraulic accumulators to operate the functions commanded by the AMF
system 52, B
Modifications
After the Deepwater Horizon BOP stack was commissioned in 2001 and went into service, a total of 20
modifications were made to improve operability and reliability based on recommendations by Transocean,
BP, and/or Cameron. The investigation team concluded that none of the modifications adversely impacted
the operation of the BOP at the time of the incident. A detailed review of the modifications may be found in
Appendix H.
Cameron and Transocean websites were consulted for engineering bulletins, product advisories, and product
alerts concerning the BOP equipment, of which a total of 314 were identified. Of these, 73 had been completed,
113 did not apply to the Deepwater Horizon, and 127 were for information purposes only. While the status of
A
B
When functions are activated from surface controls, the signal is sent to the SEMs to carry out the command by energizing the respective solenoid
valves. The solenoid valves have two operating coils individually connected to one of the two SEMs in the pod so that either SEM can operate the
valve.
Eight each 80-gallon accumulators, 6,000 psi working pressure
one advisory could not be determined, it was found that this advisory did not have an effect on the operation of
the BOP on April 20, 2010.
Maintenance
Transoceans conditioned-based maintenance philosophy is designed to:
Ensure the integrity of safety, environmental, and operations equipment to deliver the required
performance and reliability throughout the assets life cycle
Preserve the installations, facilities, equipment, machinery, and structures to maximize the useful
working life of assets in a cost-effective manner
Manage maintenance activities using standardized processes, focusing on critical equipment, and
planning the work to ensure that it is carried out in a timely manner
Ensure maintenance activities are completed by competent equipment owners and maintenance
personnel
Minimize non-productive operating time through proper planning, execution, evaluation and continuous
improvements to the maintenance system
The Deepwater Horizon BOP was operated in accordance with the maintenance requirements of the Transocean
Subsea Maintenance Philosophy document.53 This document outlines the type and timing of maintenance to
be performed, including preventive and corrective maintenance, component condition evaluation, function and
pressure testing, and major overhauls.
The investigation team reviewed the Transocean maintenance management system and identified 752 tasks for
the BOP and subsea equipment to be performed during the preceding 365-day period. On April 20, 2010, only
four of 752 tasks were overdue. These tasks were related to the following equipment: (1) BOP pipe ram cavities,
(2) BOP stack LMRP connector, (3) choke control unit on the drill floor, and (4) surface choke and kill piping.
These maintenance tasks are briefly summarized below, and a detailed review can be found in Appendix I.
1. The annual maintenance to be performed on the ram blocks (including the piston end, the hydraulic
bonnet studs, and the operating BOP body threads) required non-destructive testing (NDT), inspection,
and service of the ram blocks over a 365 day interval; this was due to commence in January 2010.54 This
work can only be carried out while the BOP is at the surface and would have been completed during
the between-well maintenance at the end of the Macondo well. The independent forensic analysis
performed by DNV confirmed that the BOP pipe rams closed during the response to the well-control
incident, and this outstanding maintenance task did not adversely affect the operation of the BOP.55
2. The maintenance task requiring surface testing and operation of the LMRP connector to determine
connector wear is performed at 180 day intervals and was due to be performed on March 30, 2010. This
work can only be carried out while the BOP is at the surface and would have been completed during
the between-well maintenance after the rig left the Macondo well.56 During the course of operations at
the well, the BOP stack was pressure tested at regular intervals, and those tests confirmed the integrity
of the connector. See Appendix J. The LMRP connector did not contribute to the incident.
3. BOP choke control maintenance is performed at seven-day intervals and was scheduled to be
completed on April 16, 2010.57 The BOP choke control unit was not used during the incident and had
no affect on the well control response.
4. High-pressure choke and kill piping from the choke manifold to the moon pool required inspection and
service at 30 day intervals. This planned maintenance procedure had been performed on March 19,
2010, and was scheduled for April 18, 2010.58 The BOP choke and kill piping had been inspected and
used successfully before the incident and did not contribute to the incident.
As noted, none of the outstanding maintenance tasks adversely affected the operation of the BOP during the
well-control response. Routine operation and testing of the BOP prior to the incident, post-incident intervention
and recovery, and investigations to date have confirmed that the identified items and the BOP were operating
satisfactorily.
Minor Leaks
Five minor leaks were identified in the Deepwater Horizon BOP control system: three identified and assessed
pre-incident and two identified during the post-incident ROV intervention. A detailed review of the five minor
leaks, which had no adverse impact on the functionality of the BOP, may be found in Appendix K, and are as
follows:
Identified Pre-Incident:
1. Leak on the test ram open-side function
2. Leak on the accumulator surge bottle on the upper annular BOP
3. Leak on the lower annular close function
Identified Post-Incident:
4. Leak on a hose fitting to the lock function on the ST Lock circuit.
5. Leak on the tubing from the blind shear ram ST Lock sequence valve to the blind shear ram ST
Lock chamber
1. The test ram is the lowermost ram and is used during function and pressure testing of the BOP stack;
it is not used for well control and, therefore, could not have impacted the events of April 20, 2010.
The Transocean subsea team reported the small volume test ram leak to BP as reflected in the BP
Daily Operations Reports of Feb. 23March 13, 2010.59 The operation report identified the leak as
being on the yellow pod, and the drill crew switched to the blue pod to stop the leak and allow further
investigation.
2. On Feb. 19, 2010, a Transocean senior subsea supervisor identified a leak in the upper annular BOP
close circuit at the hose fitting to the upper annular surge bottle. The leak was detectable but very
small; at a set pressure of 1,500 psi, the leak rate was determined to be 0.1 gallons per minute (gpm).60
A leak of this size would not have adversely affected the operation of the upper annular BOP.
3. Transoceans senior subsea engineer noted a leak in the close function of the lower annular and
confirmed that it was very small and that the annular BOP would still close when needed. The flow
rate of the leak was confirmed to be about 0.1 gpm. The leak appeared as a tick, or a brief flickering
indication, on the hydraulic fluid flow meter located on the BOP control panel. The flow indication
appeared only when the lower annular BOP was in the closed position, and the subsea team did not
identify any fluid leaking externally from the system.61 Such a leak would not and did not impede the
functionality of the lower annular BOP. The lower annular BOP was used for the negative pressure test
but was not used during the well-control incident.
4. During the post-incident response efforts, when the ROV operated the pipe ram function on the ROV
intervention panel, the intervention team noted a leak on the lock function on the ST Lock circuit for
the BOP rams. The team used an ROV to retighten the hose fitting.62 This leak did not prevent the ST
Locks from operating and would not have impacted the well-control response.
5. Transocean identified a leak on April 26, 2010, in the tubing connection that runs from the blind shear
ram ST Lock sequence valve to the ST Lock chamber.63 The leak was not apparent until the pressure
on the ST Lock was above 4,000 psi. The BOP ram must be approximately 90% closed for a sequence
valve to open, allowing fluid to pass through to the ST Lock locking function and creating the conditions
for a leak in this location. The existence of this leak confirmed that the shear ram on this bonnet was
closed. Further, based on the ROV video, this leak was small and would not have prevented the ST
Lock from functioning.64
The five leaks identified above had no adverse impact on the functionality of the BOP. The leaks were small in
volume and would not have impacted the closing or sealing capabilities of the BOP stack.
Testing
The BOP stack is regularly maintained and pressure tested.65 Tests include function tests every seven days
and comprehensive pressure tests every 14 days. Testing is performed to verify the pressure containment
capability of the various BOPs and to identify any malfunctions that may require the BOP stack to be retrieved
and repaired.
See Table 1 for a complete list of all tests performed on the BOP while on the Macondo location. The BOP
passed each of these tests. See also Appendix J.
Test Conducted
Test Date
References
February 5, 2010
February 6, 2010
February 9, 2010
February 9, 2010
March 1, 2010
Test Conducted
Test Date
References
March 4, 2010
March 4, 2010
Test Diverter
April 1, 2010
April 1, 2010
April 3, 2010
Table 1 (contd)
Test Conducted
Test Date
References
April 3, 2010
April 8, 2010
April 8, 2010
April 9, 2010
Table 1 (contd)
Closed the diverter packer (seal within the diverter housing just below the rig floor) and diverted the
flow to the MGS67
Closed the upper and middle variable bore rams (VBRs) at approximately 9:47 p.m.68
1 bbl is equal to 42 gallons, and a typical residential swimming pool is roughly 10,000 to 20,000
gallons.
Figure 11 Drill Pipe Tool Joint Lifted by Flow into Upper Annular
A tool joint is where two sections of pipe are threaded together, resulting in a larger diameter segment.
Figure 11 shows the drill pipe tool joint in the upper annular BOP element stack as a result of the upward force
from the flowing well.
At approximately 9:41 p.m., the drill crew directed flow to the trip tank to monitor the well and observed a rising
fluid level in the tank.72 The drill crew activated the upper annular BOP from the drill floor at approximately 9:43
p.m.73 During the 26 seconds required for the annular BOP to fully close,74 hydrocarbons and well debris flowed
with increasing velocity between the rubber annular BOP packing element and the drill pipe tool joint. This flow
eroded both components, carving a flow path for hydrocarbons through the annular BOP packing element and
into the riser.
Figure 12 depicts the erosion of the drill pipe and annular BOP during the initial attempt to shut in the well and
shows the eroded drill pipe recovered from the Deepwater Horizon riser at the NASA Michoud facility. The
distance between the upper and lower fingers of the annular element is 18 in., which corresponds to the section
of drill pipe shown in the figure.75 The contact with the lower fingers can be clearly identified on the tool joint. The
erosion on the upper section of the drill pipe aligns with the area of the upper fingers of the annular element.
Upper VBRs
No ROV intervention occurred to the upper VBRs post incident, which indicates the upper VBRs had
been closed by the drill crew prior to the post-incident ROV intervention.82
Radiographic surveys were completed by May 15, 2010, and indicated that the rams were closed and
the ST Locks were locked.83
When the yellow pod was re-deployed from the Q4000 oilfield service vessel and the upper VBRs close
function was activated on May 26, 2010, the flow count was 0.4 gallons, confirming that the VBRs were
closed. (Normal close volume is approximately 24 gallons.) This process was repeated a second time
to confirm.84
The upper VBRs were found closed during a video camera inspection of the BOP on board the Q4000
on Sept. 9, 2010.85
Middle VBRs
ROV intervention on May 5, 2010, cut the blue pod middle VBR close hose to the shuttle valve, installed
an ROV connection, and pressured the function with a subsea accumulator bank.86 The middle VBRs
pressured up immediately to 3,500 psi with no indication of flow, confirming the rams were closed
previously by the drill crew.
Radiographic surveys were completed by May 15, 2010, and indicated that the rams were closed and
that the ST Locks were locked.87
The middle VBRs were found closed during the BOP forensic inspection at NASA Michoud.88
The kill line was lined up with the BOP upper kill valves open to the wellbore. When the upper VBRs were closed, the kill line was isolated from the
well. At approximately 9:47 p.m., pressure in the kill line dropped rapidly and the pressure in the drill pipe increased rapidly, indicating that the VBRs
were closed
Figure 13 illustrates the path of return flow to the MGS after the diverter was closed.
Overboard Line
Gumbo Box
Diverter Housing
Overboard Line
Overboard Chute
Figure 13 Path of Return Flow after Diverter was Closed and then Overcome
Drilling Riser
Figure 13 Path of Return Flow after Diverter was Closed and then Overcome
E 5.5-in. drill pipe = 23.75 in.2 x 7,000 psi = 166,250 lb. lift.
F 5,750 psi surface pressure plus the hydrostatic pressure of seawater in the drill pipe.
G The Deepwater Horizon ST locks were not functioned as a standard practice when the BOP was subsea except for hurricane abandonment prior
to disconnect of the LMRP from the lower BOP stack. It was unlikely that the driller/toolpusher activated the ST Lock lock function after closing the
upper and middle VBRs. All functions on the MUX pods shifted to the vent position when power was lost to the pods. Closing pressure was then
vented to the upper and middle VBRs. The rams stay closed with the assistance of adequate wellbore pressure. The AMF system fired the HP
shear circuit locking the ST Locks behind the upper and middle VBRs moments after the power was lost to the pods. If the AMF had not fired, the
rams would have had to have been held closed by only the wellbore pressure for 33.5 hours until the auto-shear pin was cut by an ROV. When the
auto-shear pin was cut on April 22, 2010, at 7:30 a.m., there was no indication of fluid discharge from the control pods indicating that the BSR and
the ST Locks were already in the closed and locked position. If the BSR was still open, approximately 30 gallons of fluid would visibly discharge
from the open side of the BSR and ST Locks.
The AMF batteries registered acceptable voltage levels (8.85V for both 9V SEM battery packs and 26V
for the 27V battery pack).97
Solenoid 103 (for the HP shear circuit) did not function mechanically when activated with one SEM at
a time (two SEMs per pod). Solenoid 103 was replaced with a spare solenoid and taken into evidence
by the JIT investigation.
Solenoid 3A (for the upper annular regulator increase) did not function mechanically when activated
with one SEM at a time (two SEMs per pod). Solenoid 3A was replaced with a spare solenoid and taken
into evidence by the Joint Investigation Team.
The AMF system was re-tested and functioned as expected and designed.98
The yellow pod was lowered and latched to the Deepwater Horizon BOP on May 19, 2010. The pod was used
to operate functions remotely from the Q4000 on the rig BOP stack for 114 days up until the BOP was loaded
on the barge to be sent ashore on Sept. 10, 2010.
The yellow pod AMF system was tested at NASA Michoud on March 3, 2011, with the original solenoid 103
installed. Testing of the yellow pod produced the following findings:
The AMF batteries were still at acceptable voltage levels (8.67V for SEM A and 8.44V for SEM B 9V
battery packs, and 28.15V for the 27V pod battery pack).
Functioned every time with both SEM A and SEM B activated (direct activation of the Portable Electronic
At all times during the process, a representative from the U.S. Coast Guard and the Bureau of Ocean Energy Management, Regulation and
Enforcement (BOEMRE) was present to witness all work on the pod.
While technicians incorrectly described the E-cable and plug assembly as non-OEM supply, the parts
were in fact made by Camerons supplier. The E-cable and plug assembly were new when installed on
the yellow pod in February 2010, prior to deploying the BOP on the Macondo well.
Three functions of the AMF system were tested with SEM A and SEM B armed according to normal
operating conditions when the BOP is subsea. The AMF functioned as expected and designed each
time, functioning Solenoid 103 and pressurizing the pilot line to the HP shear circuit.99
Further testing of Solenoid 103 at NASA Michoud is ongoing at the time of publication of this report.
The AMF battery voltage levels were recorded at 8.87V for SEM A 9V, 0.142V for SEM B 9V battery
pack, and 7.61V for the 27V battery pack.102
The blue pod AMF system was tested and did not initiate the sequence (i.e., solenoid 103 was not
activated due to low 27V battery power).103
When 230V power was re-applied from the PETU to the pod, the AMF system initiated and completed
the sequence and activated solenoid 103.104
I At all times during the process, a representative from the U.S. Coast Guard and the BOEMRE was present to witness all work on
the pod.
ST Locks
Figure 16 Position of Blind Shear Rams and VBRs Following AMF Activation.
Ram Block
Locked Position
Figure 17 Blind Shear Ram ST Lock in Locked Position Following AMF Activation
The blue pod was lowered and latched to the Deepwater Horizon BOP on July 9, 2010. The pod was ready but
not used for the incident response. It was recovered with the BOP in September 2010.
The blue pod AMF system was tested at NASA Michoud on March 3, 2011, with the following results:
The AMF battery voltage levels were recorded at 8.90V for SEM A 9V battery, 8.61V for SEM B 9V and
0.71V for the 27V battery pack.105
It was determined by the NASA engineer at Michoud that the initial battery voltage readings taken in
July 2010 on the Discoverer Enterprise were incorrectly measured by the technician. The readings
taken on the pod at Michoud were verified three times and are correct.
The AMF system was tested and did not initiate the sequence.106
When 230V power was re-applied from the PETU to the pod, the AMF system completed the sequence
and activated solenoid 103.107
SEM A AMF processor was inactive, confirming that it had completed the sequence and shut down as
designed.
SEM B AMF processor was active, confirming that it had not completed the sequence due to a low
amperage 9V battery pack.
Further inspection of the blue pod AMF system is ongoing at NASA Michoud at the time of publication
of this report.
Voltage measurements taken on the blue pod 9V AMF batteries showed that they were at satisfactory voltage
levels; however, voltage tests alone are not indicative of the battery condition. The batteries must be tested
under load to determine whether sufficient energy remains to operate the AMF processor.
The timing for this event is known to be after the pipe parted and before the Deepwater Horizon sank.
The AMF activated the high pressure shear circuit minutes after the explosions and fires utilizing approximately 30 gallons of the stored fluid in
the eight 80-gallon accumulators mounted on the lower BOP. When the AMF vented off the high pressure shear circuit, 30 seconds after it was
activated, the remaining pressure in the accumulator bottles was preserved for use when the auto-shear plunger activated the high pressure shear
circuit.
testing of the rams, and the ram and annular packers, is performed in static conditions.118
If there is flow from the formation into the wellbore, the expansion of gas as it migrates up the wellbore will
displace the drilling mud through the BOP stack. A significant expansion of a gas influx will push the flow
velocities to a point where they exceed the capabilities of the BOP stack and may prevent ram and annular
BOP elements from effectively sealing the well. During high-velocity well flow conditions, when ram or annular
BOP elements are closing, the flow area in the bore of the BOP gradually is reduced, resulting in even higher
flow velocity and pressure.119
Sheared section of
drill pipe forced above
upper annular
The ram and annular BOPs do not close instantaneously to seal the wellbore. They are activated by hydraulic
fluid moving pistons and, therefore, take seconds to move from the open to closed position (16 seconds for
ram BOPs and 26 seconds for annular BOPs of the Deepwater Horizon BOP stack).120 When BOPs are closed
during high-velocity conditions, increased jetting pressure and fluid flow may damage the seals and prevent the
annulars, VBRs, and BSRs from sealing, thus preventing isolation of the wellbore flow. Leakage through ram
or annular BOP elements would continue to erode the BOP components and allow the influx of hydrocarbons
to continue.
The Deepwater Horizon BOP and MUX control system were fully operational at the time of the incident
and functioned as designed.
The equipment was maintained in accordance with Transocean requirements, and all implemented
modifications maintained or improved the performance of the BOP.
Minor leaks identified pre-incident did not adversely affect the functionality of the BOP.
Upon detection of the flowing well, the drill crew shut in the well by (1) closing the upper annular BOP;
(2) closing the diverter packer and diverting the flow to the mud-gas separator; and (3) closing the
upper and middle VBRs, which initially sealed the well.
The high flow rate of hydrocarbons from the well prevented the annular BOP element from sealing on
the drill pipe and subsequently eroded the drill pipe in the sealing area.
Increased pressure inside the drill pipe and external damage caused by erosion ruptured the drill pipe,
allowing hydrocarbons to flow up the riser. The drill pipe then parted as the Deepwater Horizon drifted
off location.
The explosions and fire severed the communication link between the BOP and the rig, preventing
activation of the BOP emergency disconnect system (EDS) from the toolpushers control panel.
The automatic mode function (AMF) operated as designed to close the blind shear rams following the
explosion.
High pressure bowed the drill pipe partially outside of the BSR shearing blades, trapping it between
the ram blocks and preventing the BSR from completely shearing the pipe, fully closing, and sealing.
Description
Length
234
XX
Bottom of upper annular element to the center of the blind shear ram
AA-1
Tool joint connection break at flow-wash end to the riser shear cut
111.5
AA-2
7.5
AA-3
Section recovered from inside the upper annular in the Deepwater Horizons LMRP
109
AA
BB
CC
234
43.5
42
142
142
420
XX
Section recovered from below the BSR and above the CSR
Center of the casing shear ram to the center of the lower test rams
Section recovered from below the CSR that extends to the lower test rams
Bottom of upper annular element to the center of the lower test rams
Tool joint connection to the start of the flow-wash damage on the tool joint
AA-1
Upper tool joint connection break at flow-wash end to riser shear cut
111.5
AA-2
7.5
AA-3
Section recovered from inside the upper annular in the Deepwater Horizons LMRP
109
BB
Section recovered from below the BSR and above the CSR
42
CC
Section recovered from below the CSR that extends to the lower test rams
142
DD
418
552
EE-1
Nominal Length of the Deepwater Horizons S-135 Drill Pipe = (+/- 6 inches)
Upper section recovered from the riser joint above the BOP
388
EE-2
Section recovered from inside the upper annular in the Deepwater Horizons LMRP
136
EE-3
27
EE
551
(inches)
EE
AA
DD
BB
CC
Figure 21 Drill Pipe Location in the BOP at the Time the BSR Cut the Pipe
1.
University of Texas, Petroleum Extension Service, A Primer of Oilwell Drilling, Seventh Edition, 2008, 184, 207, 223, 224.
2.
The University of Texas, Petroleum Extension Service, A Primer of Oilwell Drilling, Seventh Edition, 2008, 184188.
3.
The University of Texas, Petroleum Extension Service, A Primer of Oilwell Drilling, Seventh Edition, 2008, 52.
4.
The University of Texas, Petroleum Extension Service, A Primer of Oilwell Drilling, Seventh Edition, 2008, 186.
5.
Ibid.
6.
Ibid.
7.
American Petroleum Institute, Recommended Practices for Blowout Prevention Equipment Systems for Drilling Wells, RP 53,
Third Edition, March 1997, 3.1.42, 4.
8.
The University of Texas, Petroleum Extension Service, A Primer of Oilwell Drilling, Seventh Edition, 2008, 184, 186.
9.
Ibid.
10. Ibid.
11. The University of Texas, Petroleum Extension Service, A Primer of Oilwell Drilling, Seventh Edition, 2008, 184, 227.
12. American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, December 1997.
13. Testimony of Curt Kuchta, Hearing before the Deepwater Horizon Joint Investigation Team, May 27, 2010, 171:17172:4;
Testimony of Chris Pleasant, Hearing before the Deepwater Horizon Joint Investigation Team, May 28, 2010, 105:23106:7;
Testimony of Jimmy Harrell, Hearing before the Deepwater Horizon Joint Investigation Team, May 27, 2010, 10-1711:10.
14. Testimony of Jimmy Harrell, Hearing before the Deepwater Horizon Joint Investigation Team, May 27, 2010, 1222; Testimony
of Chris Pleasant, Hearing before the Deepwater Horizon Joint Investigation Team, May 28, 2010, 132:925; Testimony of Steve
Bertone, Hearing before the Deepwater Horizon Joint Investigation Team, June 20, 2010, 41:715.
15. Cameron, R&B Falcon Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September
2000, 1-16, 1-17; Vastar Resources Inc. and R&B Falcon Drilling Co., Exhibit B-2 of Drilling Contract RBS-8D, Semisubmersible
Drilling Unit, Contract No. 980249, Dec. 9, 1998, E.2.9, 33, E.3.2, 33.
16. Cameron, R&B Falcon Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September
2000, 17, 111.
17. American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, December 1997, 3.1.6, 4.
18. Cameron, R&B Falcon Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September
2000, 17, 18, 111.
19. Cameron, R&B Falcon Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September
2000, 37, 38, 334, 338.
20. Ibid.
21. Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September 2000, 310, 311, 337.
22. Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September 2000, 34, 35, 337.
23. Ibid.
24. ABB Vetco Gray, Databook, A-2.
25. American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, December 1997, 3.1.7, 4.
26. Cameron, R&B Falcon Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September
2000, 1-8, 1-11; Vastar Resources Inc. and R&B Falcon Drilling Co., Exhibit B-2 of Drilling Contract RBS-8D, Semisubmersible
Drilling Unit, Contract No. 980249, Dec. 9, 1998, 32, 33.
27. Cameron, R&B Falcon Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September
2000, 3-34, 3-37, 3-38.
28. American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, 5, December 1997, 3.1.56, 5.
29. Cameron, R&B Falcon Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September
2000, 3-37.
30. George Coltrin e-mail to Darrell Boudreaux, et. al., Oct. 19, 2004, BP-HZN-BLY00056058; Cameron Field Service Order 121096,
January 3, 2005, CAM_CIV_0011451; Change Proposal, Proposal No. SS-10, Deepwater Horizon, BOP Test Rams, Nov. 21,
2004.
31. American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, December 1997, 3.1.55, 5.
32. Cameron, Cameron Engineering Bulletin EB 852D, Rev. A1, Oct. 30, 1998, 7; IADC Deepwater Well Control Guidelines, First
Edition, October 1998, 3.1.2, 3-3.
33. Deepwater Horizon TL BOP Stack Operation & Maintenance Manual, Initial Release, Rev. A, September 2000, 1-7, 1-11.
34. ABB Vetco Gray, Field Service Manual for R&B Falcon RBS8D 21 HMF H Marine Riser System and Wellhead Connector
Manual, FSM00105, June 2000, 1, Part 1.1, Operating & Service Procedure 6192, BP-HZN-BLY00031145.
35. American Petroleum Institute, Recommended Practice for Diverter Systems Equipment and Operations, RP64, Second Edition,
November 2001, 5.1, 6-7.
36. Hydril, R&B Falcon RBS-8D Deepwater Horizon, Hydril S.O. 615911 P.O. 087 00014, FS 21x60-500 Diverter Housing, FS 21x60500 Diverter, FS 21x60-500 Handling Tool, June 23, 2010, 1-1 1-3, 3-5 (Table 3-2).
37. Hydril, R&B Falcon RBS-8D Deepwater Horizon Hydril S.O. 615911 P.O. 087-00014, June 23, 2000, 1-1 to 1-5.
38. American Petroleum Institute, Recommended Practice for Design, Selection, Operation and Maintenance of Marine Drilling Riser
Systems, 16Q (RP 16Q), First Edition, November 1, 1993, 2.4.1, 6, 7 (Figure 1-1).
39. Hydralift, Reading & Bates RBS8D Deepwater Horizon N-Line Drilling Riser Tensioner System Operation and Maintenance
Manual P/N HA13862, Rev. A, Initial Release, 10/06/00, Revision: B- As Builts, 10.06.00, 2, 2 of 8 (11 of 267).
40. ABB Vetco Gray, Field Service Manual for R&B Falcon RBS8D 21 HMF-H Marine Riser System and Wellhead Connector
Manual, FSM00105, June 2000, 2, 66, BP-HZN-BLY00031145, 210.
41. ABB Vetco Gray, Field Service Manual for R&B Falcon RBS8D 21 HMF-H Marine Riser System and Wellhead Connector
Manual, FSM00105, June 2000, 2, 66, BP-HZN-BLY00031145, 203.
42. ABB Vetco Gray, Field Service Manual for R&B Falcon RBS8D 21 HMF-H Marine Riser System and Wellhead Connector
Manual, FSM00105, June 2000, 2, Part 2.1, Operating & Service Procedure 6215, BP-HZN-BLY00031145, 210.
43. Cameron Controls, RBS8D Multiplex BOP Control System, R&B Falcon Deepwater Horizon, 139 or 56 of 79.
44. Cameron Controls, RBS8D Multiplex BOP Control System, R&B Falcon Deepwater Horizon, 130, or 50 of 79.
45. Cameron Controls, RBS8D Multiplex BOP Control System, R&B Falcon Deepwater Horizon, Vol. 1, 2000, 9.
46. Cameron, Emergency, Back Up and Deepwater Safety Systems, May 2004, 12.
47. Cameron, Emergency, Back Up and Deepwater Safety Systems, May 2004, 5.
48. American Petroleum Institute, Specification for Control Systems for Drilling Well Control Equipment and Control Systems for
Diverter Equipment, Spec 16D, Second Edition, 5.7.1, 37.
49. American Petroleum Institute, Specification for Control Systems for Drilling Well Control Equipment and Control Systems for
Diverter Equipment, Spec 16D, Second Edition, 5.8.3, 3940.
50. American Petroleum Institute, Specification for Control Systems for Drilling Well Control Equipment and Control Systems for
Diverter Equipment, Spec 16D, Second Edition, 5.9.2, 41.
51. See Appendix P; American Petroleum Institute, Specification for Control Systems for Drilling Well Control Equipment and Control
Systems for Diverter Equipment, Spec 16D, Second Edition, 5.9.3, 41.
52. Cameron Controls, RBS8D Multiplex BOP Control System, R&B Falcon Deepwater Horizon, Vol. 1, 2000, 77.
53. Subsea Maintenance Philosophy, Family 400, Recommended Practices HQS-OPS-RP-400-001, May 16, 2007.
54. 365 Day-Ram BOP NDT Job Plan Report, Oct. 16, 2009.
55. DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
85. Expro and Oceaneering video taken in the bore of the BOP on board the Q4000 - September 2010.
86. Preliminary BOP Function Timeline, May 11, 2010.
87. BP, Deepwater Horizon Accident Investigation Report, Sept. 8, 2010, BP-HZN-BLY0000001, 161162.
88. DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
89. Stress Engineering Services Inc. Structural Analysis of the Macondo #252 Work String.
90. Stress Engineering Services Inc. Structural Analysis of the Macondo #252 Work String.
91. Sperry Drilling Services data logs (drilling parameters), April 520, 2010.
92. DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
93. See Appendices H, I, K, N, and O. DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
94. Testimony of Curt Kuchta, Hearing before the Deepwater Horizon Joint Investigation Team, May 27, 2010, 171:17172:4;
Testimony of Chris Pleasant, Hearing before the Deepwater Horizon Joint Investigation Team, May 28, 2010, 105:23106:7;
Testimony of Jimmy Harrell, Hearing before the Deepwater Horizon Joint Investigation Team, May 27, 2010, 10-1711:10.
95. Testimony of Jimmy Harrell, Hearing before the Deepwater Horizon Joint Investigation Team, May 27, 2010, 1222; Testimony
of Chris Pleasant, Hearing before the Deepwater Horizon Joint Investigation Team, May 28, 2010, 132:925; Testimony of Steve
Bertone, Hearing before the Deepwater Horizon Joint Investigation Team, June 20, 2010, 41:715.
96. Cameron Controls, Daily Report Sheet, Subsea Pod Intervention, Horizon, BP, May 5, 2010, 1.
97. Cameron Controls, Daily Report Sheet, Subsea Pod Intervention, Horizon, BP, May 5, 2010, 3, 8.
98. Cameron Controls, Daily Report Sheet, Subsea Pod Intervention, Horizon, BP, May 5, 2010, 3.
99. See Appendices N and O; DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
100. Ibid.
101. Cameron Controls, Daily Report Sheet, Subsea Blue Pod Intervention, Horizon/BP, June 28, 2010.
102. Cameron Controls, Daily Report Sheet, Subsea Blue Pod Intervention, Horizon/BP, June 28, 2010.
103. Ibid.
104. Ibid.
105. See Appendix N; DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
106. Ibid.
107. Ibid.
108. See Appendices N and O; DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
109. See Appendix O; DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
110. See Appendix L; DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
111. Testimony of Daun Winslow, Hearing before the Deepwater Horizon Joint Investigation Team, Aug. 24, 2010, 13:1725.
112. See Appendix L; DNV, Forensic Examination of Deepwater Horizon Blowout Preventer, March 20, 2011.
113. Ibid.
114. The University of Texas, Petroleum Extension Service, A Primer of Oilwell Drilling, Seventh Edition, 2008, 184.
115. American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, December 1997, 4.5, 18, 4.5.1.2,
18; 4.7, 19.
116. American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, December 1997, 4.4.2.1,18;
American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, December 1997, 4, 6.
117. American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, December 1997, 4.4.4, 18.
118. American Petroleum Institute, Specification for Drill Through Equipment, 16A, Second Edition, December 1997, 4.5, 18, 4.5.1.2,
18; 4.7, 19.
119. Stress Engineering Services Inc., Hydraulic Analysis of Macondo #252 Well Prior to Incident of April 20, 2010.
120. Deepwater Horizon BOP Subsea Test, Well Num. MC 252 Macondo #1, Feb. 1011, 2010.