Srgew
Srgew
Srgew
Statement of Responsibility
This document is the joint responsibility of all group members signing below.
All group members have contributed to the production of this document; it is
their original work and has not been copied or adapted from other sources.
George Severns
Intesar Mahmood
Mike Lacey
..
Thomas Armstrong ..
Diana Sultanova
Henna Ashfaq
CONTENTS
EXECUTIVE SUMMARY
Fluvial sandstone reservoirs are a significant reservoir type that account for up to 30% of global remaining
hydrocarbon reserves. Since the development of the North Sea province commenced in the early 70s, numerous
large discoveries have been made in fluvial strata, all presenting unique complexities in terms of field development.
The Taminga A field is an offshore fluvial discovery in the UK sector of the North Sea, covering a total area of
approximately 17000 acres (10 km by 7 km.) As with any field development, the ultimate goal is to develop a plan
which maximises ultimate recovery within the confines of economics and physical limits.
The asset is a medium crude oil reservoir with a small gas cap, and with an average reservoir pressure close to
bubble point. Strategies were designed with maintaining the pressure above bubble point as a key priority, and
water injection as the principle method to achieve this.
The final optimized plan proposes a 20 year depletion plan, implementing a pattern drive water injection strategy,
potentially leading to recoveries of up to 27% equating to a cumulative oil production of 700 million bbl and 0.7 tcf
gas. The CAPEX required is estimated to be approximately US$ 4.5 bln, predicting a gross revenue of $38 bln of which
profit is expected to be $11 bln after tax and operating expenditure. The payback time is expected to be 5 years.
Economic evaluation and sensitivity analysis shows the project to be robust, presenting relatively low financial risk;
with a positive NPV and high IRR across a significant range of discount rates. Due to lack of well test data the
principle risks to the development remains to be production rate deliverability.
Proposal
The Taminga A field 20 Year development plan consists of:
-
Integrated subsea satellite system with individual wells tied back to platform through 2 manifolds
Artificial lift enabled 30 km subsea oil pipeline and 40 km gas pipeline linking platform to facilities on
mainland
1. DEVELOPMENT CONCEPT
The Taminga A Field consists of an anticlinal reservoir with a dome shaped trap, and a major fault (assumed to be
sealing) to the south, as a result of which reservoir volumes are compartmentalized between a large footwall
(Segment 1) and a smaller hanging wall (Segment 2). The main field development strategy focuses on initially
producing Segment 1 as it holds the most volumes (Table 2).
Development Strategy
The field is to be developed using 9 producing wells and 12 water injection wells, the locations of which are shown in
Figure 3. The drive mechanismTable
is a 1water
floodAassisted
aquifer drive. The injectors are placed in a peripheral
Taminga
Field Data
pattern to provide peripheral pressure support and raise the oil-water contact. The wells are to be drilled in three
sections, the
central
section from
the
platform and
a north
and
south
cluster,
to be drilled
from a
semisubmersible
drill
ship.
This
drilling
schedule
is
outlined
in the project
Reserves
schedule (Figure 6). Produced gasTable
is to2 be
sold asData
economic analysis showed this result in a higher NPV for the
project than reinjection. Segment 2 is a prospective area and currently has no distinct plans as the sealing capacity of
the fault is still unknown. Once real data an understanding of dynamic field behaviour has been established it will be
possible to decide the best course of action with regards its development. If the fault is non-sealing then there will
be natural flow and will not necessitate further development in the short term.
2. EXPORTING OPTIONS
There are two main export options available for oil: pipeline, tanker and one for the gas: pipeline. The development
proposes separate pipelines for oil and gas. Economic evaluation of the export options prove pipelines to be ideal for
both fluids, requiring the least capital expenditure, construction time, OPEX and export tariff costs. Furthermore
pipelines allow the option for choosing capacities to optimise infrastructure use and enables faster, reliable and
continuous hydrocarbon delivery to downstream point of sale.
PIPELINE
30 km 100-200 Mb/d Oil Pipeline
40 km 100-200 MMscf/day Gas Pipeline
3. MAP OF FIELD
Flank Fault
Segment 2
Main Fault
Segment 1
Producers
P1 E
P2 N
P3 W
P4 W
P5 SE
P6 SE
P7 SE
P8 E
P9 E
Water Injectors
I1 NE
I2 N
I3 N
I4 W
I5 SE
I6 SE
I7 N
I8 E
I9 E
I 10
I 11
I12 SE
Platform
Coordinates
X
Y
5614
8143
3658
7801
2154
6910
1554
5065
2587
1776
4050
2481
5135
3362
5714 5836
5978 6793
X
Y
6544 9206
5112 10131
2524
8936
839
6981
3472
1267
5480
2212
4772
7647
6364
4037
5045 5348
2406 4098
3919 6620
3156 2790
4417 6397
I2 N
I1 NE
I3 N
GOC
P2P2NN
P1 E
OWC
I7 N
I4 W
P3 W
P9 E
I11
P2 N
I8
I9 E
P4 W
P8 E
I10
P7 SE
I3 N
I6 SE
Producer
I12 SE
P6 SE
Water Injector
P5 SE
Platform (not to scale)
I5 SE
4. DRILLING PROGRAM
The drilling schedule has been planned through a systematic basis, with preserving reservoir pressure and long term
reservoir management in mind.
A total of 9 Producers and 12 Water Injectors are to be drilled via both the platform and the semi-submersible
drilling rig. The wells drilled by the semi-submersible rig are to be tied back to the platform through central flowlines
from two manifolds, one in the North and one in the South.
DESIGN
TIME
The peripheral producers are to be drilled initially in order to minimally affect the gas cap, followed by
peripheral water injectors. More injectors are to be drilled initially in order to sustain reservoir
pressure once later producers come on stream. Dynamic simulation indicates that this method
prevents the formation of a pressure sink at the centre of the field.
Drilling is expected to be completed within 3 years by 2019. All wells are within 5 km of the platform
and require approximately 90 days completing each. This project schedule (Figure 6) takes into
account the time required for post hook-up testing and data acquisition (cores, MWD, logs). The first
producers (P9, P2) are expected to come on stream in January 2017 after the hook-up phase.
The total drilling expenditure is expected to be approximately $ 1.2 bln
ECONOMICS
Opting for a semi-submersible drilling rig increases costs, however reduces the time required for
drilling completions (3 Years) and subsequently shortens payback period as it enables simultaneous
drilling of multiple wells (via platform and semi-sub).
In comparison platform drilling all wells requires 4-5 years for drilling completions and delays payback
with increased financial exposure. In the larger scale of costs considering full CAPEX, a semisubmersible does not incur significant added expenses and is justified by the time benefits.
A full breakdown of drilling expenditure is displayed in Figure 4
ERD (extended reach) was not considered due to the relative field structural simplicity and all wells
being less than 5 km from platform. ERD involves added technical complications in terms of
engineering design which is not necessary considering field simplicity. (Jahn et al 2008).
Wells
PLATFORM DRILLED
P3
P4
P8
P9
I4
I8
I9
I10
I11
Distance km
Drilling Cost
1.97
3.16
1.44
1.6
3.63
3
1.2
3
0.5
$54,000,000
$61,000,000
$47,000,000
$50,000,000
$63,000,000
$59,000,000
$44,000,000
$59,000,000
$45,000,000
Total
$482,000,000
Dep. Distance
1.9
1.1
2.1
1.4
1.3
1.6
Drilling Cost
$64,000,000
$58,000,000
$66,000,000
$61,000,000
$60,000,000
$62,000,000
Total
$371,000,000
Dep. Distance km
1.8
1.4
1.1
2
0.5
0.9
Drilling Cost
$64,000,000
$61,000,000
$59,000,000
$65,000,000
$56,000,000
$57,000,000
Total
$362,000,000
I1
I2
I3
I7
P1
P2
MANIFOLD SOUTH
I5
I6
I12
P5
P6
P7
$1,215,000,000
5. SUB-SEA
The proposed subsea infrastructure is satellites, with individual wells tied back to the rig production facility through a two
manifolds, North and South. The decision is based on preliminary economics suggesting it to be the infrastructure
requiring the least CAPEX and construction time, thereby reducing financial exposure.
Platform
Semi-submersible
P2
P1
P7
II
I6
II
P5
II
I5
II
P6
II
I3
II
I7
II
I1
II
I2
II
Figure 5 diagrammatically represents the facilities and subsea infrastructure of Taminga A field. 12 wells are connected to
satellites and tied back to north and south manifolds as part of clusters. The remaining wells are tied back straight to the
platform shown above.
Infrastructure
Flow Lines
Umbilicals
UTA
Production
Jumper
Satellite
Manifold
Cost
$5million/Km
This cost is driven by
material, diameter,
coating and length.
The subsea of Taminga A will be fitted with two manifolds. North manifold connected to the north cluster of wells
and the south manifold connected to the south cluster of wells. The drawback to developing subsea infrastructure is
manifolds is the high cost. This is justified however by a multitude of advantages which have the potential to
increase production, save time and finance.
Manifold Functions
Connection for 6 potential production or injection wells, separated into two production flowlines back to the
main platform.
Monitoring of individual wells dynamic performance in real time controlled onshore reducing living quarter
size.
Production and injection simultaneous capabilities (GE Energy, 2014)
Individual control of wells to mitigate problems associated with dry/damaged wells.
Pressure support for low or high-pressured reservoirs.
Dynamic information of flow, pressures temperature, which can be included in a data acquisition programme
Help to minimise the use of pipelines and risers, which can add huge amount of weight to the platforms and
lead to platform damage or increase platform costs. (Bai and Bai, 2005)
Reduction in the amount of umbilicals required to connect power, hydraulics.
An optimised subsea arrangement to mitigate against entanglement of umbilicals and flowlines.
A reduction in movement of a semisubmersible drill ship as 6 deviated wells can be drilled from one location
through a manifold before movement is required.
Temperature support to allow hydrocarbons to arrive at the platform above critical temperature.
Enables produced fluids to be distributed, control fluids, inject gas and EOR chemicals.
Provides support for other subsea infrastructure/maintenance equipment such as ROVs (Remotely Operated
Vehicle) the use of which is becoming ever increasing.
Helps to maintain valve and pipe work integrity.
Provide gas injection at the riser to reduce slug flow in flow line.
Can provides gas lift which lightens the fluid column and increases production rates.
Can control choke or killing of individual wells.
The additions of subsea manifolds are preferable in case for the need of EOR later in field life, they can be
designed to manage chemicals and other high temperature high pressure fluids.
The majority of the above capabilities are difficult to, or not possible to achieve through direct satellite to platform
tiebacks.
10
6. PROJECT SCHEDULE
The project schedule (Figure 6) incorporates all of the major development activities starting with the building and
installation of production and processing platform all the way to drilling and subsea completions. The oil and gas
pipelines are to be built during the last months of the build phase, at which time the semi-submersible drilling rig will
mobilise to field.
SEMI-SUB DRILED
PLATFORM DRILLED
First Oil
11
22 Month Plateau
Plateau rate: 150,000 -175,000 bopd
12
Oil Produced
(over 20 years)
P1
P2
P3
P4
P5
P6
P7
P8
P9
99 mmbbl
85 mmbbl
73 mmbbl
87 mmbbl
42 mmbbl
48 mmbbl
75 mmbbl
148 mmbbl
58 mmbbl
Percentage of
total field
production
14%
12%
10%
13%
6%
7%
10%
21%
8%
Non-discounted
revenue from oil
$6.9 billion
$6.0 billion
$5.1 billion
$6.1 billion
$2.9 billion
$3.4 billion
$5.2 billion
$10.3 billion
$4.1 billion
13
14
8. FACILITIES
The facilities decisions are based on the plateau rate which provides an optimal take-off from the field (Jahn et al
2008). They are also made with making optimal use of facility and infrastructure in mind to justify the CAPEX and
OPEX required. A steel jacket platform is suitable for the North Sea supporting the drilling rig, production, processing
and other facilities. The steel jacket is also ideal for the shallow water depth of the North Sea (approximately 150m).
Oil
Gas
Platform The facilities processing capacity is based on the total field volume
production rate inclusive of oil, water, gas. The plateau rate of 175,000 bopd
Liquids
Processing corresponds to a maximum reservoir volume production rate of approximate
380,000 bbl/day; therefore an installation (separation and treatment
systems) with a processing capacity of 400,000 bbl/day of fluids is
appropriate.
Water
Injection
Water
Treatment
100-200 Mb/day
100-200 MMscf/day
N/A
The field maximum water injection rate 200,000 bpd (oil equivalent). As a
safety for the possible addition of future infill injector wells a facility with
injection processing capacity of 250,000 bpd is recommended.
Seawater to be treated and injected into the reservoir. Produced water will be treated and disposed of
following regional legislation and guidelines.
UK North Sea water injection regulations necessitate intensive water treatment systems incorporating
the following:
-De-oiling
-Oxygen removal
-Particle content monitoring
-Bacterial treatment
-Scale inhibitor application
Cost
At $70,000/ tonne of steel, the fluid processing facilities will require an approximate investment total of
$ 1 bln.
15
Field development requires an environmental impact assessment and public consultation under UK and EU
legislation, international treaties and agreements. The Offshore Petroleum Production and Pipelines (Assessment of
Environmental Effects) Regulations 1999 necessitates consideration to external bodies and presented below.
Government and Local Council
Non-Government
- The produced and injected water to be subjected to intensive cleaning processes in line with Department of Energy
& Climate Change regulations.
-Safe disposal of waste fluids from drilling and other onsite operations.
- Cooperation with regional environmental and wildlife monitoring agencies to be maintained in order to ensure
minimal impact on surround ecosystem and habitat.
- Future implementation of secondary, tertiary recovery methods to be intensively risk assessed.
- Consideration to air quality, energy efficiency, chemical substances.
Data availability is limited and so this assessment is based on regional environmental surveys. An environmental site
study is recommended covering the following areas:
16
As a safety margin considering the fluctuating nature of oil price, the baseline scenario has been set to
$70 /bbl. Current spot price of Brent Crude is US $ 108.8 (EIA Spot Prices 17/04/14).
Gas Price
Ultimate
Expected
Recovery
715 MMbbl
CAPEX
Cos
$2,383,6
$1,215,0
$664,00
$120,00
$160,00
Total Capex
$4,542,6
Total Capex
$4,542,600,000
Tax
Corporation tax for UKCS field developments are 62% and this figure has been implemented into the
preliminary economics.
Discount
Rates
Variable discount rates have been applied to CAPEX, OPEX and net revenue to assess economic robustness
of the project. The current UK discount rate specified by the Cabinet Office Centre for Social Impact Bonds
is 3.5% for projects with duration ranging 0-30 years.
NPV
Net present values have been calculated at variable discount rates as an indicator of economic feasibility.
IRR
ECONOMIC ANALYSIS
A cashflow analysis based on the simulated production profile, with nominal and real values has been established
with consideration to uncertainties and their effect on NPV. At US$ 70/bbl and the current discount rate of 3.5% an
ultimate cash surplus (profit) of approximately $11 billion is expected, equating to a return on investment (ROI) of
140%. The post-tax NPV after 20 years is $13 billion which equates to an NPV/barrel of $22, which is above average
and highly profitable. At a 25% discount rate the NPV/barrel is $5. The NPV is positive across a large range of
discount rates, and with an after tax IRR of 50%, the project is robust, presenting relatively low financial risk.
The CAPEX is distributed over 5 years from facilities installation to drilling completion, and with revenue generated
as wells come on stream from 2017; the maximum financial exposure is US $ 3 billion in 2016. The breakeven point is
late 2019, a payback time of 3 years from the start of production, 5 years from the start of development.
Figure 11
18
$ 12.9 Bln
Field
IRR = 50%
Frigg
785
34.1
Piper
618
62.9
Ninian
1,200
53.0
Fulmar
525
65.1
Nystad. A 1981
19
Field production is to commence at 2017 after the hook up phase is completed, providing a 1 st year net income of
$580 mln. The 50% IRR is within realistic bounds of similar sized North Sea developments, in terms of similar
recoverable reserves, development periods and production durations (Nystad. A, 1981, SPE Economic Analysis of
the North Sea Oil and Gas Region). At the current oil price of $108.8 the IRR is 63%. The 20 year average OPEX,
calculated based on the rates from the production profile is expected to be approximately $ 370 mln/year, which
falls within ranges of DECC OPEX figures for similar fields (see Appendix). At the current discount rate, the gross
revenue is estimated to be $ 40 bln with an after tax profit estimated to be $ 11.2 bln. The net cashflow determines
the economic lifetime of a project, with the point of negative cashflow marking the project end date. Reservoir
simulation indicates economic production rates (50,000 bopd, $ 200 mln/year) and cash surplus beyond the current
20 year life plan at the current discount rate.
Investment
Period
First Oil
Figure 16
Components of Cashflow
20
Development Cost
Resources /Well
(Based on dynamic
simulation results)
Total Recovery
Feasible
In total there are 9 producers (individual production cumulatives shown in Figure 8), and 12
water injectors giving 21 wells, therefore approximately 80 MMbbl is produced per
production well and 34 MMbbl per total wells over a twenty year field life. The highest
producer delivers 148 MMbbl and the lowest gives 42 MMbbl.
The total feasible recovery of the field takes into account possible future development as well
as the original simulated data. In this case the future developments are segment 2 and the
implementation of two separate EOR projects. By the end of 2057 an estimate of over 1 bln
bbl will be produced.
21
Price Decrease
0
25%
50%
Oil Price
$70
$53
$35
Figure 18
NPV
$12.9 bln
$ 8 bln
$ 3 bln
IRR
50%
34%
21%
22
Tax
Tax increase effects on NPV have been calculated.
Corporation Tax Rate
70%
85%
NPV
$10.7 bln
$ 8.1 bln
IRR
43%
33%
With UK North Sea reserves declining, and generally decreasing investment and field development into the province,
the political climate has changed in recent years. The government has reduced corporation tax to the current 62%
from a once higher figure to encourage investment and secure future energy supply. Given the wide variation in
profitability of oil fields, it is inevitable that significant increases in tax rate will result in field developments being
rendered economically nonviable and detract investors. Hence tax rate increase can be considered to be low risk for
the near to mid-term future (House of Commons, Energy & Climate Change Committee Implications for the North
Sea oil and gas industry of the Budget 2011). Nonetheless, sensitivity study shows the project to have positive NPV
and good IRR at higher tax rates.
Spider Diagram -
Oil Production
OPEX
2
0
-2
Oil Price
-4
CAPEX
-6
-50
-40
-30
-20
-10
+10
+20
+30
+40
+50
23
Economic Sensitivity
The tornado plot shows that the project is most sensitive to variation in reserves, followed by oil price.
Reserves
-40%
Oil Price
-40%
40%
40%
CAPEX
20%
Tax
10%
-20%
-10%
Gas Production
Discount Rate
-20%
20%
-15%
15%
Figure 21
12
18
24
1 E +8
1.1 E +8
NPV ($ bln)
Geological Sensitivity
Porosity
Channel Permeability
NTG
Corey Coefficients
GOR
API
5E +7
6E +7
7 E+7
8 E+7
Figure 22
9 E +7
1.2 E +8
All fields have a significant uncertainty and heterogeneity range, only a part of which is relevant to the actual operations, and
depends on the production goals and technology used (Soto,2010). A sensitivity analysis was conducted through running
multiple realizations of the reservoir model to assess alternative scenarios. Static and dynamic uncertainties were computed
through a Monte Carlo sampling method, randomly sampling input parameters within the ranges of defined uncertainty limits.
The effect of uncertainties associated with each property on cumulative oil production has been plotted on a tornado chart. It
can be seen that uncertainties in NTG, porosity and permeability have the most effect on cumulative recovery, largely due to
lack of core and well data from across the field.
24
Category
Matrix
ID
A
Description
Impact
Probability
Effect of Impact
Ability to
Influence
L
Lack of skilled
workforce
Costs miscalculation
Incompetent platform
operations and maintenance
Potential over-investment,
insufficient funds to complete
Project abandonment
Personnel training
Unjustified facilities/OPEX
expenditure
Company reputation at risk,
fail shareholders
Affects production profile
Lower recovery
Commercial
B
C
Facilities
D
E
F
Uneconomically high
CAPEX
Insufficient
capacity/use
Failure to deliver rates
Wells
G
H
Reservoir
Engineering
I
J
Potential Mitigations
Discuss fiscal matters with department of
energy
25
High
I
J
D
A
Potential Impact
Low
Low
Ability to Control
High
In good business practice a strict HSSE assessment will be followed. This assessment is designed to keep people, the
environment and the investment safe throughout the whole of field life. The basic HSSE is outlined in the appendix.
26
There are a number of scenarios for which a contingency plan must be devised. These include instances such as
lower than expected production, high early water cut, or higher than expected gas drawdown, amongst many
others. In each instance it is important to understand which types of data should be collected to assess the extent of
the damage to the development plan and the best course of action. If the damage to the development plan is
potentially high, then the development plan should be scaled back until the problem has been fully investigated.
Problem
Type
Problem
Productivity
Low production
rates
Economic
Problem
Type
Environmental
Problem
Type
Contingency
Adjust water flood method if reservoir pressure is
too low.
High gas
productivity
Fluid sampling, 4D
seismic
Problem
Impact
High CAPEX
Reduces profitability
of project
High OPEX
Reduces profitability
of project
Problem
Not meeting
Government
regulations for
north sea
production
Impact
Impact can range
from being fined to
being made to shut
down production
Contingency
Reconduct economic evaluation with new CAPEX
values, potentially reduce OPEX by altering the
well numbers, or work to increase early
production.
Shut down wells with highest water cut 90% +
Contingency
Implement monitoring systems to ensure
standards maintenance. Contingency plan is to
set finance aside to deal with any environmental
problems.
27
EOR
Infill Drilling
Update Model
4D Seismic
SEGMENT 2
Reservoir Management
Multilaterals
Drilling
Recovery Methods
Artificial Lift
Consideration
Criteria/Time
The reservoir produces significant volumes of solution gas which could Low-pressure/rate
potentially be used to implement gas lift to increase recovery. Gas lift is not production wells
uncommon in the North Sea, and if implemented artificial lift systems would
have to be installed.
Dynamic simulation indicates the field production rate after 20 years to be
approximately 50,000 bopd which is a profitable rate based on current Secondary recovery
economics. However reality may be a different case and EOR could be (water injection) no
considered in late field life. Zone A3 containing higher density oil can be longer effective.
subjected to the recovery method, such as water alternating gas (WAG), which
involves water injection, followed by gas injection. Miscible gas injection is
another possibility, utilising the fields own natural gas.
(Decline phase)
Zones of high hydrocarbon saturation remain proximal to the flank fault where Late life, sharply
infill drilling can be considered to increase recovery. This practice is well declining
production/nearing
established in the North Sea.
economic threshold.
Drilling branching multilateral wells from existing wells to access pocket Decline phase
hydrocarbon zones and residual oil in upper Zone A3.
Production and well test data to be used to update and history match the To be conducted
regularly
model for reliable forecasting and evidence based decision making.
Decline phase Segment 2 despite being smaller holds considerable hydrocarbon volumes (420 Facilities are largely
not being fully utilised.
MMbbl) and is to be considered as a future second development phase.
Debottlenecking could potentially increase the capacity of the facilities to produce hydrocarbons later in field life as
new technology will allow for higher processing capacity. This option can be considered once real data has been
considered. The most likely use for debottlenecking would be in the water processing stream as this is the stream
which increases in volume throughout field life.
28
Decommissioning
At the end of field life the platform and subsurface facilities must be decommissioned following the rules set out in
the Petroleum Act 1998. This will require finance to safely seal all the wells and remove the platform whether it is
sunk to make an artificial reef or removed totally and recycled. The finance for this is accrued during field life and is
already accounted for by using an oil price of $70 during the economics as the oil price is currently $108.8 (17/4/14)
so part of the surplus will is put aside to prepare for decommissioning.
29
APPENDIX
CAPEX:
Integrated Platform and Facilities Integrated Platform Costs
Topside Weight
Tonnes
22,000
Cost
$1,540,000,000
Jacket Weight
26,400
48,400
$2,596,000,000
Max Capacity
400,000
200,000,000
200,000
200,000,000
400,000
Tonnes Required
4,000
2,000
2,000
2,000
4,000
Standard Rig
ERD Rig
1
0
4,000
0
Accomodation
75
3,000
Flare
1,000
$70 k / tonne
Processing
Liquids bbl/day
Gas scf/day
Water Injection bbl/day
Gas Compression (Reinjection) scf/day
Utilities
Drilling
22,000
Subsea Infrastructure
$250mln/manifold
Manifolds
M North
M South
Flowlines for Cluster Tieback
Number
2
Dist. To Plat. Km
2.7
3.4
Cost
$500,000,000
Oil Pipeline
Oil Pipeline
CapacityCapacity
Cost $/km
Cost $/km
Flowline Cost
$27,000,000
$34,000,000 DistanceDistance
Build Time
$3,000,000 Build Time
Total OilTotal
Pipeline
Oil Pipeline
Cost
Cost
$50mln/system
Control Systems
Total Subsea Cost
$100,000,000
$664,000,000
100-200100-200
Mb/d Mb/d
$4,000,000
$4,000,000
30
90
30
90
km
days
$120,000,000
$120,000,000
Gas Pipeline
Gas Pipeline
CapacityCapacity
Cost $/km
Cost $/km
DistanceDistance
Build Time
Build Time
100-200100-200
mmscf/day
mmscf/day
$4,000,000
$4,000,000
40 km 40 km
120 days120 days
Total GasTotal
Pipeline
Gas Pipeline
Cost
Cost
$160,000,000
$160,000,000
Total Pipelines
Total Pipelines
Cost
Cost
$280,000,000
$280,000,000
30
km
days
Wells drilled
Subsea Activities
Pipleine Construction
Subsea and drilling costs
Platform Costs
Total Costs
2014
2015
$794,533,333
$794,533,333
$767,665,056
$767,665,056
2016
P9 P2 I2
M north
Yes
$726,738,080
$741,705,368
$1,468,443,449
2017
I8 P3 I4 I1 I3 I7 P1
2018
P4, I11 P8 I10 P6 I5 P5
M south
2019
I9 I6 P7 I12
$385,129,535
$638,331,432
$186,076,070
$385,129,535
$638,331,432
$186,076,070
31
HSSE
Hazard
Environme
ntal risks
Fire
explosions
Oil Spills
GOR
H2S
Facility
problems
Risk
Natural disasters can damage production
and drilling facilities and are harmful to
personnel.
Leakage of the hydrocarbons can occur due
to improper facility installations and can
cause blowouts leading to significant
damages and fatalities.
Oil spills to the sea are major environmental
hazard and can cause significant ecological
and economical damage. They can occur by
leakage of the infrastructure or during
transportation of oil
Inability of gas compressors to handle gas
production rate, can cause blowout
Safety of personnel can be in doubt due to
harmful gas emissions
Facility breakdowns can cause significant
damage and sudden production shutdowns
Probability
Low
Impact
High
Potential Mitigations
Environmental manager should deal with accurate weather
forecasting. Personnel safety precautions should be considered.
Low
High
Low
High
Medium
High
Low
High
Medium
Medium
32
REFERENCES
Books and Papers
Mahmood, I, 2014 The Taminga A Field Depletion Planning Proposal, The University of Manchester, CHEN30232
Petroleum Engineering Design Project.
Jahn. F et al, 2008, Hydrocarbon Exploration and Production, Elsevier
Megill. R, 1988, Exploration Economics, Penwell
Kemp. A, The Official History of North Sea Oil and Gas, Vol. II: Moderating the States Role, 2012, Routledge
Nystad. A, 1981, Economic Analysis of the North Sea Oil and Gas Region, SPE Special Publication
House of Commons, Energy & Climate Change Committee Implications for the North Sea oil and gas industry of the
Budget, Written Evidence, 2011
DSouza et al, 2012, Selecting the Right Field Development Plan, Deep Offshore Technology, Paper 2317
Cromb et al, 1999, Subsea Solutions, Schlumberger Oilfield Review
Bai, Y. and Bai, Q. (2005). Subsea pipelines and risers. 1st ed. Amsterdam: Elsevier.
Bai, Y. and Bai, Q. (2010). Subsea engineering handbook. 1st ed. Burlington, MA: Gulf Professional Pub.
Kawaguchi et al (2011). Subsea engineering ROV and seafloor observatory construction. pp.1--6.
Kirkbride, et al (1994). Lightweight Subsea Manifold Design.
KW Ltd (2014). - Oil and Gas Engineering Company UK, Norway.
Williams, M., Hale, J. and others, (1998). Mensa Project: Subsea Manifold and Electrical Distribution Structure.
Guidance notes on the offshore petroleum production and pipelines (Assessment of Environmental effects) Regulations
1999, Version No: 2011
Websites
Cabinet Office Centre for Social Impact Bounds - http://data.gov.uk/sib_knowledge_box/discount-rates-and-net-presentvalue
http://www.legislation.gov.uk/ukpga/1998/17/contents
BP North Sea Region Environmental Statement 2011 www.oilandgas.co.uk/environment.cfm
Energy Matters euanmearns.com
DECC - https://www.gov.uk/government/organisations/department-of-energy-climate-change
https://www.gov.uk/oil-and-gas
33