Estimate Durations
The next step in the process is to assign durations to each activity. Estimating activity durations is the
process of approximating the number of work periods needed to complete individual activities with
estimated resources. [2]. The duration of planned activities is estimated to calculate the estimated
start and finish dates based on the defined scope of work, estimates of required resources and their
availability, and the expected performance (or consumption) rate of those resources [1].
Workday definition
After calendars are assigned to their respective activities, durations for each activity will reflect not only
the workweek per activity but any nonwork time associated to the activitys calendar. The user must be
aware of the work day definition (i.e. 8 hour workday or 10 hour workday, etc.). In P6 (prior to version
7) the work day was defined at the admin or user level with only one selection available therefore
causing issues when multiple calendars were used. In P6 version 7 (Admin menu, Admin Preferences,
Time Periods), the workday can be defined at the calendar level. The System Administrator can define
either global hours per time period (day, month, etc.) or set the hours per time period at the calendar
level.
The user can modify how durations (i.e. hours, days, etc.) are displayed across the users projects under
the Edit menu, User preferences option, Time Units tab.
It is important for the scheduler to understand the different duration types in P6 and the relationship
between the duration of the activity and the cost and/or resources assigned to the activity. The
scheduler must choose the correct duration type for each activity in the schedule for the schedule
model to accurately reflect the project plan.
NOTE: Part 5 Establish Schedule Requirements to be posted next week. Subscribe to our blog if you dont want
to miss it or follow us on Twitter @HillPCIGroup. If you have questions regarding this series or the products and
the services we offer, please feel free to email us at info@hillpci.com or call us at (800) 511-1888.
REFERENCES:
1.
AACE International Chapter 7.2. Schedule Planning and Development. Total Cost Management
Framework A Process for Applying the Skills and Knowledge of Cost Engineering, First Edition.
Pages(s) 129-138. AACE International, Morgantown, WV 2006
3.
4.
5.
Winter, Ronald M., PSP and F. Burak Evrenosoglu, CCE PSP. PS.15, Much Ado
About Dates Understanding P6 Date Information. 2009 AACE International
Transactions. AACE International, Morgantown, WV. 2009.
(800)-511-1888
INFO@HILLPCI.COM
TWITTER: @HILLPCIGROUP
REPRINTED WITH THE PERMISSION OF THE AUTHORS AND AACE INTERNATIONAL, ENTITY OF FIRST PUBLICATION, 1265 SUNCREST TOWNE
CENTRE DR., MORGANTOWN, WV 25605-1876 USA. PHONE 800-858-COST/304-296-8444. FAX: 304-291-5728. INTERNET:
HTTP://WWW.AACEI.ORG E-MAIL: INFO@AACEI.ORG COPYRIGHT 2010; ALL RIGHTS RESERVED.