Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Schedule Risk Analysis Simplified: by David T. Hulett, Ph. D

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10
At a glance
Powered by AI
The key takeaways are that the critical path method (CPM) provides an initial schedule but does not account for risk, and schedule risk analysis can identify risks and their likely impacts to better inform project management.

Some important reservations about CPM are that the completion date it produces is often optimistic and may not be the most likely, and the identified critical path may not be the one most likely to delay the project.

The three steps to conducting a schedule risk analysis are: 1) create the CPM schedule, 2) gather risk information such as optimistic and pessimistic durations and probability distributions, and 3) simulate the network using a Monte Carlo approach.

WHITE PAPER

Schedule Risk Analysis Simplified1


by David T. Hulett, Ph. D.

Table of Contents
Critical Path Method Scheduling - Some Important Reservations.....1 Three Steps to a Successful Schedule Risk Analysis, Illustrated by Case 1...........2 Summary of Schedule Risk Assessment............... 10

Critical Path Method Scheduling Some Important Reservations


The critical path method (CPM) of scheduling a project is a key tool for project management. A schedule network represents the project strategy. Activities, where the work is accomplished, are linked by relationships (e.g. finish-start, start-start, finish-tofinish) showing how the work is planned. Strings of linked predecessor and successor activities constitute paths through the network. When two or more paths are to be done simultaneously, they are described as parallel paths. Some of the most important points in the project are where several parallel paths converge. At these merge or join points, the paths must all be completed before a milestone is recorded for payment, an inspection can be done, sub-assemblies can be integrated for testing or the project can be recorded as complete. CPM computes the shortest project completion duration and or completion date from the longest path through the network. The longest pole in the tent is called the critical path. Any delay on the critical path will delay the project. Conversely, CPM shows that paths that are not critical can be delayed or lengthened, if they

have enough float or scheduling flexibility, without necessarily delaying the project. On the one hand, the critical path method (CPM) of scheduling is traditional and wellaccepted. It is essential for developing the logic of the project work and for managing the day-to-day project activities. On the other hand, the CPM schedule is only accurate if every activity is started as soon as possible and takes just as long as its duration estimate indicates. Project managers understand that projects do not ever go entirely according to plan, which is one reason for frequent status reviews. Since real projects do not work this way, CPM is just the beginning of project schedule management. Project managers need to understand some key reservations about the standard CPM, and how to use a schedule risk analysis to provide information crucial to a projects success, before they embark on their project: The project duration calculated by CPM is accurate only if everything goes according to plan. This is rare in real projects. In many cases the completion dates CPM produces are unrealistically optimistic and

Note 1 David Hulett is Principal of Hulett & Associates of Los Angeles, CA. He can be reached at (310) 476-7699, at info@ projectrisk.com and on the web at www.projectrisk.com. This article is reprinted from the PM Network, July 1996, pp. 23-30 with permission of the Project Management Institute, 130 South State Road, Upper Darby, PA. PMI is a worldwide organization of advancing the state-of-theart in project management. (610) 734-3330 FAX (610) 734-3266.

www.deltek.com

info@deltek.com

800.456.2009

highly likely to be overrun, even if the schedule logic and duration estimates are accurately implemented. The CPM completion date is not even the most likely project completion date, in almost all cases. The path identified as the critical path using traditional CPM techniques may not be the one that will be most likely to delay the project and which may need management attention. In a recent article2, Harvey Levine challenged the mathematically disinclined to determine the degree of schedule overrun risk without getting confounded by mathematical or statistical terminology. To help achieve this goal, three case studies are presented in this paper. Using simple schedules of two activities or four activities on two parallel paths, these case studies show both the pitfalls of relying on CPM and the benefits of a schedule risk analysis. These case studies show that it may not be feasible to complete even simple projects by their CPM-determined date, given risk characteristics that are similar to those often found in real, everyday projects. CPM does not identify these overrun problems very well, or at all. In fact, CPM shows that the project will finish on a certain date. If CPM does not work well in such simple projects, and those the problems are multiplied many times for the complex projects facing project managers every day, the benefits of conducting a risk analysis on every project become obvious.3 Popular, accessible commercial software is used for these case studies to show that schedule risk analysis methods are available to anyone. Graphical presentations of the results illustrate the steps required to conduct a quantified risk assessment and the results without using mathematics or statistics.

Three Steps to a Successful Schedule Risk Analysis, Illustrated by Case1


The three steps to a successful risk analysis are described. They are: (1) create the CPM schedule for the project, (2) estimate the uncertainty in the activity durations, and (3) perform a risk analysis of the schedule, usually with a Monte Carlo simulation method available in several software packages.

Step 1: CPM Schedule the Foundation of a Risk Analysis


CPM analysis of the project schedule is the key building block of a quantified risk assessment. Case 1 presents a very simple project and a typical schedule risk analysis. It illustrates how the CPM completion date can easily be overrun. It shows how a risk analysis can illuminate the issues in CPM and point to their resolution. For the first step, a project with two activities and a finish milestone is shown in Figure 1.

Figure 1 Figure 1
Case ProjectNetwork Network with Single Path Case 1: 1: Project with Single Path

A101

A102

Note 2 Harvey A. Levine, Risk Management for Dummies: Managing Schedule, Cost and Technical Risk and Contingency, PMNetwork, Software Forum, October 1995, p.p. 30- 32. Note 3 An analytical treatment of this subject, with more implications than are included here, can be found in David T. Hulett, Project Schedule Risk Assessment, Project Management Journal, March 1995, pp. 21-31.

Suppose the durations are set at 50 working days for A101 and 80 working days for A102. Suppose, further, that this project is scheduled to start on June 10, 1996. CPM shows that this simple project will take 130 working days (50 + 80 = 130) and complete on December 11, 1996. There are several considerations in developing a successful risk analysis network. For a risk analysis to be successful, the CPM network should be developed at a level of detail that shows the important project structure, i.e. the parallel paths and key merge points where the risk is often increased. There are three features to watch for in determining the correct level of a schedule:

WHITE PAPER: Schedule Risk Analysis Simplified

First, the network should not be developed at too high a level of detail, for instance at a level where most of the activities summarize important underlying detail. Summary activities are often characterized by start-to-start or finish-to-finish relationships. Second, the schedule should show clearly the parallel paths that could cause the project to be late if not coordinated. Case 2 below shows the merge bias that occurs when parallel paths converge. Third, the network should not be developed in such great detail that it requires too much information, since that would be unworkable and overly burdensome. When building the risk analysis network, the temptation is to schedule only those paths assessed as the longest poles in the tent. This is a dangerous practice that should be avoided. It is best to show more paths rather than fewer, since the shorter poles might actually have more risk than the long poles identified by CPM. Case 3, below, shows that a shorter path with more risk can actually be the highest risk path, i.e. the path most likely to actually delay the project. If shorter paths are not included in the network to begin with, their risk might not be explored at all. If there are scarce resources that make scheduling some activities in parallel infeasible, they ought to be identified and included in the schedule risk analysis. If constraints are included in the CPM network, however, these must be deleted in the risk analysis. These points are discussed in more detail below.

resources. Experienced project managers know that the work might take more or less time than the estimate they have assumed for the CPM calculation. These times make up the low and high ranges for a risk analysis. Duration ranges for each activity are the low (optimistic) and high (pessimistic) durations that the work on the activity might take under different possible extreme scenarios. High ranges, for instance, can be determined by examining the various things that could go wrong such as technical problems, site conditions, supplier delays, and permitting issues - - factors which are often called risk drivers. Risk drivers are identified and explored in interviews with the managers or team leaders of the projects activities who are the most knowledgeable people on risk in the work under their management and control. They are most familiar with the risk issues in each activity and can best assess their impact on the possible duration of each activity. Experienced guidance is often needed to develop the duration ranges. The risk interview starts with a description of what could go wrong with the work in an activity. It then turns to the likelihood of that scenario and how long the activity might take if everything goes wrong. This duration is the high-range duration for that activity. A serious and honest airing of the issues involved in doing an activity will soon uncover possible, though perhaps unlikely, pessimistic scenarios.4 Conversely, exploring with the managers what could go right should yield an optimistic scenario and the low estimate of duration for each activity. Sometimes, with aggressive or success-oriented schedule estimation, the CPM duration for many activities are already the shortest possible durations conceivable. Often the CPM duration is viewed as the most likely duration for most of the activities in the

Note 4 A 1960s government manual on PERT recommended that the highrange pessimistic estimate should include failure and making a fresh start if the likelihood of such an event was at least 1%. See; US Department of Defense, PERT Fundamentals: POTC Textbook, Bolling AFB, PERT Orientation and Training Center (date unknown), p. 3.28.

Step 2: Determine the Activity Duration Ranges


The activity durations that are used to calculate the critical path are often thought of as the best guess or most likely amount of time needed to complete the work given the planned

WHITE PAPER: Schedule Risk Analysis Simplified

project. This may not be true, however. The risk analyst should, with the project manager, seek to describe the most likely scenario and determine if the CPM duration, or some other duration, will accommodate it. The ranges of longer (Max Dur) and shorter (Min Dur) activities for the two Case 1 activities are shown in Figure 2, below. The table in that figure shows that there is a greater risk of overrun than opportunity for underrun in these two activities.5 The barchart shows the CPM completion date of December 11, 1996. There may be problems in collecting data about project schedule risk. For instance, project managers may be reluctant to commit their activity managers time to develop the information needed for a risk analysis, since they are the very people who are most busy managing the project itself. Alternatively, some project managers avoid examining risk at all because it poses difficult issues, highlights bad news, exposes embarrassing problems or raises issues that would have to be disclosed to the owner or customer. Even if a project manager wants to explore risk honestly, it is often challenging to develop realistic ranges, particularly for unlikely but possible extreme events. But, gathering duration range data has the major benefit of making everyone aware of the problems facing the project. A risk analysis usually reveals

important problems that had not been appreciated or communicated fully before the gathering of the duration range data. Sometimes projects have many activities, perhaps thousands. How should the ranges be developed for such a large project? In this case, risk banding is often used. The project manager organizes the activities into groups with common risk characteristics. For each of these risk types the low and high duration ranges would be expressed in percentages, e.g. minus 15%, plus 25%, from the CPM duration. With large networks there is little alternative but to use CPM durations as the most likely in the activity distributions. Once the ranges, often called 3-point estimates, are determined, the project manager must adopt a probability distribution shape for each risky activity. A probability distribution takes the three possible durations (low, most likely and high) and expresses the relative likelihood of alternative outcomes within that overall range. That is, there are some possible durations which are more likely than others. Triangular distributions are often used in risk analysis because they are easy to specify (just needing three points and a straightedge) and to use in analysis. Also, the project managers may not know enough to specify any other distribution type, although other distribution shapes are often available in the software.

Note 5 Asymmetrical distributions are quite common. The CPM durations are often optimistic scenarios that do not work out in practice. Sometimes the CPM duration is the low or most optimistic duration as well. Note 6 Figure 2 shows a view of the Case 2 network and risk ranges that were developed in Microsoft Project v. 4.1 from Microsoft Corporation and Risk+ v. 1.5, a MS Project addin, from Program Management Solutions, Inc.

Figure 26
Case 1: Simple 2-Activity Project Case 1: Simple 2-Activity Project
Qtr 2, 1996 ID 1 2 3 4 Task Name Total Project A101 A102 Finish Qtr 3, 1996 Qtr 4, 1996 Qtr 1, 1997 Qtr 2, 1997 Qtr 3, 1997 Min Dur Duration Max Dur Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep 0d 40c 70c 0d 130c 50c 80c 0d 0d 100c 100c 0d 12/11

Figure 26

WHITE PAPER: Schedule Risk Analysis Simplified

Suppose that the analyst in Case 1 chooses a simple triangular distribution for each activity, using the data in Figure 2. The distributions are shown in Figure 3. They make it clear that both CPM durations are optimistic, and that the A101 duration of 50 working days is quite optimistic.7
Case 1: Probability Distributions

Is December 11 even the most likely duration of this simple project? How many days are needed for a contingency to reduce the overrun risk exposure to an acceptable level? The method, usually used is called Monte Carlo simulation, has several steps: Each iteration begins by selecting a duration for each risky activity at random from its range and distribution like those in Figure 3. The total project and key milestone completion dates for that iteration are calculated using CPM for that particular configuration of durations. Those are only possible dates for completion of the project and its milestones, and they may not be representative of all possible solutions. To determine the entire pattern of possible completion dates for the project and its important milestones, the risk analyst iterates the project many times. At the end of each iteration, the completion dates for the total project and for any important milestone are collected and stored. The program also records which activities were on the critical path for that iteration. At the end of the entire simulation, project completion and important milestone dates computed from all iterations are collected and arrayed in graphs and tables showing the probability distribution, or relative frequency, of all possible dates. Suppose that the risk analyst examining Case 1 determines that 2,500 iterations will be sufficient for the accuracy needed.8 The result of that simulation is a cumulative likelihood distribution that represents the likelihood of the project completing on or before each possible date. This distribution is shown in Figure 4 above:

Figure 3 Figure 3

Case 1: Probability Distributions


A ctivity A 101 probability probability A ctivity A 102

40 50 Working days

100

70 80 100 Working days

Note 7 One measure of how optimistic these durations are is a comparison of the CPM duration to the average that would occur if the activities were to be done many times. The average durations that correspond to the given ranges and triangular distributions are computed by (low + most likely + high) / 3. For A101, an average overrun is calculated as (40 + 50 + 100) / 3 = 190 / 3 = 63.3 working days. An overrun from the CPM duration of 50 days is 13.3 working days, almost 3 weeks.

Step 3: Simulate the Project Schedule


Once the activities duration ranges and distributions have been determined, the schedule risk analysis can determine how risky the entire project schedule is. The most common method of determining schedule overrun risk is to simulate the project by solving (or iterating) it hundreds or thousands of times on the computer.
Q3 05 Q4 05results Q1 06 for Q2 06 Q3 06 06 Q1 07 Q2 07 Q3 07 Q4 07 The simulation Case 1, forQ4 instance, will answer such important project management questions as:

Is the completion date estimate of December 11 reasonable?

WHITE PAPER: Schedule Risk Analysis Simplified

9 Figure 4 9

Probability Distribution of Total Total Project Completion Proability Distribution of Project Completion Case 1: Simple Two-Activity Project
Case 1: Simple Two-Activity Project
Date: 01/26/96 06:54:15 PM Number of Samples: 2500 Unique ID: 6 Name: Total Project
300 270 240 1.0

Figure 4

Completion Std Deviation: 14.7d 95% Confidence Interval: 0.6d Each bar represents 4d.

Completion Probability Table Prob 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50 Date 12/05/96 12/10/96 12/12/96 12/17/96 12/19/96 12/23/96 12/24/96 12/27/96 12/31/96 01/03/97 Prob 0.55 0.60 0.65 0.70 0.75 0.80 0.85 0.90 0.95 1.00 Date 01/07/97 01/09/97 01/14/97 01/16/97 01/21/97 01/24/97 01/30/97 02/06/97 02/13/97 03/14/97

0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1


11/19/96 01/07/97 03/14/97

Sample Count

210 180 150 120 90 60 30 0

Completion Date
1-path Project Illustrating Path Risk

Note 8 More iterations will provide more accuracy and smoother output graphs. More complex models will require more iterations to produce accuracy. If different scenarios are embedded in the model (e.g. 20% chance of failing a test and starting over), more iterations will be needed. Often iterations will take computer time, especially with complex projects and resource leveling, so there is a practical side to how many iterations to use. Try a number of iterations on the specific schedule, using different seed values to start the Monte Carlo, until the results do not change materially as the number is increased. Note 9 Figure 4 shows the simulation results in a table that summarizes the cumulative distribution shown in the chart. The printout is from Risk+ software.

Figure 4 includes a likelihood distribution (bellcurve) and a cumulative distribution (Scurve) shown in both pictures and a table for the total project completion date. From the chart we can see: The CPM completion date of December 11 is only 10% - 15% likely to be adequate for this simple project. Placing confidence in completion by December 11 is very likely to get the contractor and customer in trouble. A look at the bell-shaped distribution reveals that the most likely completion date is close to December 24, not December 11. The common sense notion that adding most likely durations along a critical path will result in the most likely project completion date that is simply wrong, in most cases. The average completion date is January 7. If this simple project were done 100 times, its average completion would be a about a 3week overrun of the CPM duration, providing for the holidays. Suppose a conservative schedule is required, one that has an 80% likelihood of success. The results show that January 24 has such a success likelihood. Hence, a 6- week contingency is needed to reduce the risk of

Cumulative Probability

0.9

overrun to an acceptable level for this conservative company. CPM clearly establishes December 11 as the project end-date. Just as clearly, the risk analysis establishes that December 11 is highly optimistic. Any owner/customer or contractor that agrees to that date is in trouble now on this project. Without a risk analysis, the existence or degree of trouble is unknown. Monte Carlo is a well-established method to represent risk. Several commercial scheduling programs have a schedule risk analysis module. For some others, third-party software companies may have provided such capability. Not all network programs have risk analysis packages, however. The risk analyst using a network program that lacks the risk package will have to load the schedule into a network program that does. Two issues common to scheduling should be resolved before the simulation is begun. These are the handling of constraint dates and limited resource requirements. The first issue is the treatment of constraint dates such as not later than or must finish on dates. Constraints are often implemented in the CPM schedule to represent key dates contained in

WHITE PAPER: Schedule Risk Analysis Simplified

a contract or some other requirement. Constraints are used to highlight key contract dates because these dates must be met or the project is in trouble. Constraint dates have no place in a risk analysis, however. One main goal of a risk analysis to determine whether the important contract dates, those established in the network with constraint dates, are in jeopardy. If constraint dates were implemented in the simulation, each iteration would be forced to meet those dates. Simulation with constraints operating during each iteration cannot possibly investigate the feasibility of meeting the dates because success is enforced. Constraints must be taken off the schedule before doing a risk analysis because they invalidate a risk analysis. The second issue is the treatment of limited resources. If several activities using the same resource are potentially scheduled at the same time, they may require more of that resource than is available. Resource leveling in CPM pushes one or another resourceusing activity out in time so that a resources usage does not exceed its availability in any time period. Because each solution in a risk analysis must at least be feasible, it should not violate any resource limitations that exist. Each iteration must be resource-leveled if some resource(s) is (are) limited. The risk analysis software package should be able to level resources as it is iterating. This increases run time substantially.

Case 2: Project Schedule Risk with Parallel Paths -the Merge Bias
The three steps of a schedule risk analysis can be used in more complicated cases than Case 1. For instance, most projects have activities planned simultaneously along parallel paths. At the end of the project, and often at important internal milestones, these paths converge. At path convergence (or merge) points, projects can be delayed if the probability distributions of the converging paths durations overlap because a delay on any one of the paths will delay the work. Examples include; (a) several types of construction work that must be completed before an inspection can be conducted, or (b) several components that must be finished before integration and testing can be done. Of course, some merge points have several paths converging, and the opportunity for delay at such points is thus magnified. Clearly, path merge points can never be good news for a risk analysis. The increase in project risk at merge points, called the merge bias, is the subject of Case 2. In Case 2, a simple parallel path project is assumed. Suppose B101 is exactly like A101 and B102 is exactly like A102 in all respects; CPM durations and low and high ranges, as illustrated in Figure 5. The CPM result for this schedule is exactly the same as Case 1; 130 working days to a completion date scheduled at December 11. Both Path A and Path B are identified as critical paths by CPM.

Figure 5
Figure 5
Qtr 2, 1996 ID 1 2 3 4 5 6 Task Name Total Project A101 A102 B101 B102 Finish Qtr 3, 1996

Case 2: Project Network with Parallel Paths


Case 2: Project Network with Parallel Paths
Qtr 4, 1996 Qtr 1, 1997 Qtr 2, 1997 Qtr 3, 1997

Min Dur Duration Max Dur Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep 0d 40d 70d 40d 70d 0d 130d 50d 80d 50d 80d 0d 0d 100d 100d 100d 100d 0d 12/11

WHITE PAPER: Schedule Risk Analysis Simplified

Figure 6Project Completion Proability Distribution of Total


CaseDistribution 2: Four Activities in TwoProject Parallel Paths Probability of Total Completion Case 2: Four Activities in Two Parallel Paths
Date: 01/26/96 06:02:47 PM Number of Samples: 2500 Unique ID: 6 Name: Total Project
220 198 176 1.0

Figure 6

Completion Std Deviation: 12.8d 95% Confidence Interval: 0.5d Each bar represents 3d.

Completion Probability Table Prob 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50 Date 12/18/96 12/24/96 12/30/96 01/02/97 01/06/97 01/08/97 01/10/97 01/13/97 01/15/97 01/17/97 Prob 0.55 0.60 0.65 0.70 0.75 0.80 0.85 0.90 0.95 1.00 Date 01/21/97 01/23/97 01/24/97 01/28/97 01/31/97 02/04/97 02/07/97 02/12/97 02/19/97 03/12/97

0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1


11/29/96 01/17/97 03/12/97

Sample Count

154 132 110 88 66 44 22 0

Completion Date
2-path Project Illustrating Merge Bias

Note 10 MacCrimmon, K. R. and Ryavec, C. A. An Analytical Study of the PERT Assumptions, in R. Archibald and R. Villoria, NetworkBased Management Systems (PERT/CPM), New York, Wiley, 1967, Appendix C. Also described in Hulett, op. cit., pp. 24-26.

A project with parallel paths like Case 2 is almost always more likely to be overrun than the simple single-path schedule such as that in Case 1. The cause of this pessimistic result is the merge bias which has been known for some 25 years.10 The distribution of possible completion dates from a Monte Carlo simulation of Case 2, shown in Figure 6 below, reflects the impact of the merge bias: The CPM date, which is still December 11, is now not even 5% likely to occur. The most likely completion date is about January 7, not December 24, 1996 as in Case 1. The average completion date is January 17, not January 7 as in Case 1. This project has an average or expected overrun of 5 calendar weeks from the CPM estimate.

Cumulative Probability

0.9

The conservative company requiring an 80% likelihood of success now requires a completion date of February 4, not January 24 as in Case 1. The CPM schedule did not reveal these problems at all. Even with parallel critical paths, the CPM analysis forecasted the same completion date of December 11 in both cases. The risk analysis showed that the risk of overrun and necessary schedule contingency were materially higher in Case 2 over those in Case 1. This paper has shown that two simple projects, one with 2-activities and another with 4activities on 2 parallel paths, can be in trouble. It follows that real projects, which are infinitely more complex, are even more likely to be infeasible because they have more parallel paths and merge points. A risk analysis identifies and quantifies the difficulties faced by the project manager.

WHITE PAPER: Schedule Risk Analysis Simplified

Case 3: Risk Management and the Highest Risk Path


Suppose the project manager who received these risk analysis results took steps to mitigate the risk forecasted in Case 2, above. Several steps might be taken. First, the project manager might reduce the risk in activities A101 and A102, perhaps through different strategies, e.g. buy rather than make a tricky component or utilize a different supplier thought to be more reliable. Second, the project manager could shorten the duration of activity B101 by 5 days, to 45 working days, perhaps by adding a second shift to part of the work. For Case 3, it is assumed that the risk ranges around both activities durations in Path B are the same as in Case 2, perhaps reflecting geological conditions or the technological challenges which remain. Suppose that the new risk ranges resulting from these steps are shown in Figure 7. Experienced schedulers will recognize that shortening activity B101 makes Path B a near-critical path which has a CPM duration of 125 days and a float of 5 working days. Path A is now the only critical path with a total CPM duration of 130 working days. The completion date is still scheduled for December 11.

But, is Path A the most likely to delay the project? Is it the highest risk path? A risk analysis is now required not only to estimate the possible durations of this project after risk management but also to identify the highest risk path. As mentioned above, the simulation software identifies which activities are on the critical path for each iteration. At the end of the simulation, the percentage of the iterations in which the activities were critical indicates the relative likelihood that delays in their completion will delay the project, their relative criticality. In Case 3, path A may be the critical path using CPM durations, but that is not the end of the story. In the software display shown in Figure 7, relative criticality for each activity is indicated by the numbers to the left of the bars in the bar chart. These results indicate that Path B is the highest risk path, the one with the greatest likelihood to delay the project, with a 69% likelihood, even though its CPM duration is 5 days shorter than Path A. The risk management steps taken on the CPM critical Path A succeeded; Path A is forecasted to delay the project only 31% of the time. In this way a risk analysis helps identify the highest risk path for risk management.

Figure 7 Figure 7
3: AssessingRisk Risk Management Case 3:Case Assessing Management
Qtr 2, 1996 ID 1 2 3 4 5 6 Task Name Total Project A101 A102 B101 B102 Finish Min Dur Duration Max Dur 0d 45d 75d 35d 70d 0d 130d 50d 80d 45d 80d 0d 0d 60d 90d 95d 100d 0d 69 69 12/11 31 31 May Jun Jul Qtr 3, 1996 Aug Sep Oct Qtr 4, 1996 Nov Dec Jan

WHITE PAPER: Schedule Risk Analysis Simplified

Figure 8 Figure 8
Probability Distribution of Total Project Completion Case Effect ofRisk Risk Management Case 3: 3: Effect of Management
Date: 01/26/96 06:15:48 PM Number of Samples: 2500 Unique ID: 6 Name: Total Project Completion Std Deviation: 12.0d 95% Confidence Interval: 0.5d Each bar represents 3d.

Proability Distribution of Total Project Completion

288

0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1


12/03/96 01/03/97 03/03/97

Sample Count

252 216 180 144 108 72 36 0

www.deltek.com info@deltek.com 800.456.2009


Deltek is a global leader dedicated to delivering enterprise management software that meets the unique needs of projectfocused organizations. With over two decades of experience, Deltek enables companies to maximize profitability and productivity, integrating all aspects of their businesses. More than 11,000 customers worldwide rely on Deltek to streamline operations, improve performance and win more business.

Completion Date
Risk Management and the Highest Risk Path

Case 3 simulation results are presented in Figure 8, above: Figure 8 shows that the risk management actions have reduced the risk of the total project. The average completion date is now January 3, not January 17 as in Case 2 before risk management. Will the project complete on time after these risk management actions? The CPM date of December 11 is still less than 5% likely and further risk management steps are needed to reduce the risk to an acceptable level. Those steps might most profitably be applied to Path B, the highest risk path, at this time. Certainly, the project manager should look closely at the progress in B101 and B102 for those are highrisk activities.

Cumulative Probability

Contact Deltek

360 324

1.0 0.9

Completion Probability Table Prob 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50 Date 12/11/96 12/13/96 12/16/96 12/18/96 12/19/96 12/20/96 12/23/96 12/24/96 12/26/96 12/30/96 Prob 0.55 0.60 0.65 0.70 0.75 0.80 0.85 0.90 0.95 1.00 Date 12/31/96 01/03/97 01/08/97 01/10/97 01/14/97 01/20/97 01/23/97 01/29/97 02/05/97 03/03/97

amount of effort and judgment goes into developing the three-point activity duration estimates to use in a schedule risk analysis. The simple examples shown above highlight the benefits of risk assessment and the pitfalls of relying on a CPM analysis alone. Some of these benefits are: (1) finding out how likely the CPM completion date is, (2) determining the contingency needed to reduce the overrun risk to an acceptable level, (3) identifying the highest risk path for project risk management, and (4) evaluating the effect of risk management actions. The risk analysis has the potential of providing key information for project managers in advance so that risk mitigation plans can be developed and implemented now. The experience with risk analysis shows also that developing the data and reviewing the results enables the participants to understand and to manage their project better. There is risk in every project. Ignoring risk doesnt make it go away. A three-step risk analysis should be conducted for every important project.

Summary of Schedule Risk Assessment


Risk assessment of a project requires three steps; (1) create the CPM schedule, (2) gather risk information such as optimistic and pessimistic durations and probability distributions, and (3) simulate the network using a Monte Carlo approach. The greatest

Deltek 13880 Dulles Corner Lane, Herndon, VA 20171 US & Canada: 800.456.2009 or 703.734.8606 UK +44 (0) 20 7518-5010
2007 Deltek, Inc. All rights reserved. All referenced trademarks are the property of their respective owners.

You might also like