ADR Cases
ADR Cases
ADR Cases
PURISIMA, J.:
Before the Court is a Petition for Certiorari with Prayer for
Preliminary Injunction & Temporary Restraining Order under Rule 65
of the Revised Rules of Court assailing the decision of the Regional
Trial Court of Lanao del Norte, Branch 2, Iligan City, on the following
consolidated cases :
(a) Special Proceeding Case No. 2206 entitled National
Steel Corporation vs E. Willkom Enterprise Inc to Vacate Arbitrators
Award; and;
(b) Civil Case No. 2198 entitled to E. Willkom Enterprises
Inc. vs National Steel Corporation for Sum of Money with
application for Confirmation of Arbitrators Award.
The facts as found below are, as follows:
"xxx On Nov. 18, 1992, petitioner-defendant Edward Wilkom
Enterprises Inc. (EWEI for brevity) together with one Ramiro
Construction and respondent-petitioner National Steel Corporation
(NSC for short) executed a contract whereby the former jointly
undertook the Contract for Site Development (Exhs. "3" & "D") for
the latter's Integrated Iron and Steel Mills Complex to be
established at Iligan City.
Sometime in the year 1983, the services of Ramiro Construction
was terminated and on March 7, 1983, petitioner-defendant EWEI
took over Ramiro's contractual obligation. Due to this and to other
causes deemed sufficient by EWEI, extensions of time for the
(a)
P458,381.00 representing EWEI's last billing No. 16
with interest thereon at the rate of 1-1/4% per month from
January 1, 1985 to actual date of payment;
(b)
P1,335,514.20
representing
price
escalation
adjustment under PD No. 1594, with interest thereon at
the rate of 1-1/4 % per month from January 1, 1985 to
actual date of payment;
(c)
(d)
(e)
The Regional Trial Court of Lanao del Norte Branch 2, Iligan City
through Judge Maximo B. Ratunil, rendered judgment as follows:
(1) In Civil Case No. 11-2198, declaring the award of the
Board of Arbitrators, dated April 21, 1992 to be duly
AFFIRMED and CONFIRMED "en toto" ; that an entry of
judgment be entered therewith pursuant to Republic Act
No. 876 (the Arbitration Law); and costs against
respondent National Steel Corporation.
(2) In Special Proceeding No. 11-2206, ordering the petition
to vacate the aforesaid award be DISMISSED.
SO ORDERED.[2] "
With the denial on October 18, 1996 of its Motion for
Reconsideration, the National Steel Corporation (NSC) has come to
this court via the present petition.
After deliberating on the petition as well as the comment and
reply thereon, the court gave due course to the petition and
considered the case ripe for decision.
(d)
That the arbitrators exceeded their powers, or so imperfectly
executed them, that a mutual, final and definite award upon the
subject matter submitted to them was not made. xxx"
P458,381.00 representing EWEI's last billing No. 16 with interest thereon at the rate of 1 1/4%
xxx
xxx
xxx
xxx
(II)
Price escalation with the interest rate of 1-1/4% per month from 1 January 1985 to actual date
of payment.
The petition for review on certiorari before us seeks us to reverse and set aside
the decision of the Court of Appeals which denied due course to the petition
for certiorari filed by the Asset Privatization Trust (APT) assailing the order of the
Regional Trial Court (RTC) Branch 62, Makati City. The Makati RTCs order
upheld and confirmed the award made by the Arbitration Committee in favor of
Marinduque Mining and Industrial Corporation (MMIC) and against the
Government, represented by herein petitioner APT for damages in the amount
of P2.5 BILLION (or approximately P4.5 BILLION, including interest).
Ironically, the staggering amount of damages was imposed on the Government
for exercising its legitimate right of foreclosure as creditor against the debtor MMIC
as a consequence of the latters failure to pay its overdue and unpaid obligation
of P22 billion to the Philippine National Bank (PNB) and the Development Bank of
the Philippines (DBP).
In the course of the trial, private respondents and petitioner APT, as successor
of the DBP and PNBs interest in MMIC, mutually agreed to submit the case to
arbitration by entering into a Compromise and Arbitration Agreement,
stipulating, inter alia:
NOW, THEREFORE, for and in consideration of the foregoing premises and the
mutual covenants contain herein, the parties agreed as follows:
1. Withdrawal and Compromise. The parties have agreed to withdraw their
respective claims from the Trial Court and to resolve their dispute through arbitration
by praying to the Trial Court to issue a Compromise Judgment based on this
Compromise and Arbitration Agreement.
In withdrawing their dispute form the court and in choosing to resolve it through
arbitration, the parties have agreed that:
(a) their respective money claims shall be reduced to purely money claims; and
(b) as successor and assignee of the PNB and DBP interest in MMIC and the
MMIC accounts, APT shall likewise succeed to the rights and obligations of PNB
and DBP in respect of the controversy subject of Civil Case No. 9900 to be
transferred to arbitration and any arbitral award/order against either PNB and/or DBP
shall be the responsibility of, be discharged by and be enforceable against APT, the
partied having agreed to drop PNB and DBP from the arbitration.
2. Submission. The parties hereby agree that (a) the controversy in Civil Case No.
9900 shall be submitted instead to arbitration under RA 876 and (b) the reliefs
prayed for in Civil Case No. 9900 shall, with the approval of the Trial Court of this
Compromise and Arbitration Agreement, be transferred and reduced to pure
pecuniary/money claims with the parties waiving and foregoing all other forms of
reliefs which they prayed for or should have payed for in Civil Case No. 9900.[13]
The Compromise and Arbitration Agreement limited the issues to the
following:
5. Issues. The issues to be submitted for the Committees resolution shall be: (a)
Whether PLAINTIFFS have the capacity or the personality to institute this derivative
suit in behalf of the MMIC or its directors; (b) Whether or not the actions leading to,
and including, the PNB-DBP foreclosure of the MMIC assets were proper, valid and
in good faith.[14]
This agreement was presented for approval to the trial court. On October 14,
1992, the Makati RTC, Branch 62, issued an order, to wit:
2.
3.
4.
[15]
As this Committee holds that the FRP is valid, DBPs equity in MMIC is raised to
87%. So pursuant to the above provision of the Compromise and Arbitration
Agreement, the 87% equity of DBP is hereby deducted from the actual damages
of P19,486,118,654.00 resulting in the net actual damages of P2,531,635,425.02 plus
interest.
DISPOSITION
WHEREFORE, premises considered, judgment is hereby rendered:
1. Ordering the defendant to pay to the Marinduque Mining and Industrial
Corporation, except the DBP, the sum of P2,531,635,425.02 with interest thereon at
the legal rate of six per cent (6%) per annumreckoned from August 3, 9, and 24,
1984, pari passu, as and for actual damages. Payment of these actual damages shall
be offset by APT from the outstanding and unpaid loans of the MMIC with DBP and
PNB, which have not been converted into equity. Should there be any balance due to
the MMIC after the offsetting, the same shall be satisfied from the funds representing
the purchase price of the sale of the shares of Island Cement Corporation in the
amount of P503,000,000.00 held under escrow pursuant to the Escrow Agreement
dated April 22, 1988 or to such subsequent escrow agreement that would supercede
[sic] it pursuant to paragraph (9) of the Compromise and Arbitration Agreement;
2. Ordering the defendant to pay to the Marinduque Mining and Industrial
Corporation, except the DBP, the sum of P13,000,000.00 as and for moral and
exemplary damages. Payment of these moral and exemplary damages shall be offset
by APT from the outstanding and unpaid loans of MMIC with DBP and PNB, which
have not been converted into equity. Should there be any balance due to MMIC after
the offsetting, the same shall be satisfied from the funds representing the purchase
price of the sale of the shares of Island Cement Corporation in the
of P503,000,000.00 held under escrow pursuant to the Escrow Agreement dated
April 22, 1988 or to such subsequent escrow agreement that would supercede [sic] it
pursuant to paragraph (9) of the Compromise and Arbitration Agreement;
3. Ordering the defendant to pay to the plaintiff, Jesus Cabarrus, Sr., the sum
of P10,000,000.00, to be satisfied likewise from the funds held under escrow
pursuant to the Escrow Agreement dated April 22, 1988 or to such subsequent
escrow agreement that would supercede it, pursuant to paragraph (9) of the
Compromise and Arbitration Agreement, as and for moral damages; and
4. Ordering the defendant to pay arbitration costs.
This Decision is FINAL and EXECUTORY.
IT IS SO ORDERED.[16]
x x x.
Motions for reconsiderations were filed by both parties, but the same were
denied.
On October 17, 1994, private respondents filed in the same Civil Case No.
9900 an Application/Motion for Confirmation of Arbitration Award. Petitioner
countered with an Opposition and Motion to Vacate Judgment raising the
following grounds:
1. The plaintiffs Application/Motion is improperly filed with this branch of the
Court, considering that the said motion is neither a part nor the continuation of the
proceedings in Civil Case No. 9900 which was dismissed upon motion of the
parties. In fact, the defendants in the said Civil Case No. 9900 were the
Development Bank of the Philippines and the Philippine National Bank (PNB);
2. Under Section 22 of Rep. Act 876, an arbitration under a contract or submission
shall be deemed a special proceedings and a party to the controversy which was
arbitrated may apply to the court having jurisdiction, (not necessarily with this
Honorable Court) for an order confirming the award;
3. The issues submitted for arbitration have been limited to two: (1) propriety of the
plaintiffs filing the derivative suit and (2) the regularity of the foreclosure
proceedings. The arbitration award sought to be confirmed herein far exceeded the
issues submitted and even granted moral damages to one of the herein plaintiffs;
4. Under Section 24 of Rep. Act 876, the Court must make an order vacating the
award where the arbitrators exceeded their powers, or so imperfectly executed them,
that a mutual final and definite award upon the subject matter submitted to them was
not made.[17]
Private respondents filed a REPLY AND OPPOSITION dated November 10,
1984, arguing that a dismissal of Civil case No. 9900 was merely a qualified
dismissal to pave the way for the submission of the controversy to arbitration, and
operated simply as a mere suspension of the proceedings. They denied that the
Arbitration Committee had exceeded its powers.
In an Order dated November 28, 1994, the trial court confirmed the award of
the Arbitration Committee. The dispositive portion of said order reads:
WHEREFORE, premises considered, and in the light of the parties [sic] Compromise
and Arbitration Agreement dated October 6, 1992, the Decision of the Arbitration
Committee promulgated on November 24, 1993, as affirmed in a Resolution dated
July 26, 1994, and finally settled and clarified in the Separate Opinion dated
September 2, 1994 of Committee Member Elma, and the pertinent provisions of RA
876,also known as the Arbitration Law, this Court GRANTS PLAINTIFFS
APPLICATION AND THUS CONFIRMS THE ARBITRATION AWARD, AND
JUDGMENT IS HEREBY RENDERED:
(a) Ordering the defendant APT to the Marinduque Mining and Industrial
Corporation (MMIC, except the DBP, the sum of P3,811,757,425.00, as and for
actual damages, which shall be partially satisfied from the funds held under escrow
in the amount of P503,000,000.00 pursuant to the Escrow Agreement dated April 22,
1988. The Balance of the award, after the escrow funds are fully applied, shall be
executed against the APT;
(b) Ordering the defendant to pay to the MMIC, except the DBP, the sum
of P13,000,000.00 as and moral and exemplary damages;
(c) Ordering the defendant to pay to Jesus S. Cabarrus, Sr., the sum
of P10,000,000.00 as and for moral damages; and
(d) Ordering the defendant to pay the herein plaintiffs/applicants/movants the sum
of P1,705,410.22 as arbitration costs.
In reiteration of the mandates of Stipulation No. 10 and Stipulation No. 8 paragraph
2 of the Compromise and Arbitration Agreement, and the final edict of the
Arbitration Committees decision, and with this Courts Confirmation, the issuance
of the Arbitration Committees Award shall henceforth be final and executory.
SO ORDERED.[18]
On December 27, 1994, petitioner filed its motion for reconsideration of the
Order dated November 28, 1994. Private respondents, in turn, submitted their reply
and opposition thereto.
On January 18, 1995, the trial court handed down its order denying APTs
motion for reconsideration for lack of merit and for having been filed out of
time. The trial court declared that considering that the defendant APT through
counsel, officially and actually received a copy of the Order of this Court dated
November 28, 1994 on December 6, 1994, the Motion for Reconsideration thereof
filed by the defendant APT on December 27, 1994, or after the lapse of 21 days, was
clearly filed beyond the 15-day reglementary period prescribed or provided for by
law for the filing of an appeal from final orders, resolutions, awards, judgments or
decisions of any court in all cases, and by necessary implication for the filling of a
motion for reconsideration thereof.
On February 7, 1995, petitioner received private respondents motion for
Execution and Appointment of Custodian of Proceeds of Execution dated February
6, 1995.
Petitioner thereafter filed with the Court of Appeals a special civil action
for certiorari with temporary restraining order and/or preliminary injunction dated
February 13, 1996 to annul and declare as void the Orders of the RTC-Makati dated
November 28, 1994 and January 18, 1995 for having been issued without or in
excess of jurisdiction and/or with grave abuse of discretion. [19] As ground therefor,
petitioner alleged that:
I
THE RESPONDENT JUDGE HAS NOT VALIDLY ACQUIRED JURISDICTION
MUCH LESS, HAS THE COURT AUTHORITY, TO CONFIRM THE ARBITRAL
AWARD CONSIDERING THAT THE ORIGINAL CASE, CIVIL CASE NO. 9900,
HAD PREVIOUSLY BEEN DISMISSED.
II
THE RESPONDENT JUDGE COMMITTED GRAVE ABUSE OF DISCRETION
AND ACTED WITHOUT OR IN EXCESS OF JURISDICTION, IN ISSUING THE
QUESTIONED ORDERS CONFIRMING THE ARBITRAL AWARD AND
DENYING THE MOTION FOR RECONSIDERATION OF ORDER OF AWARD.
II
THE COURT OF APPEALS LIKEWISE ERRED IN HOLDING THAT
PETITIONER WAS ESTOPPED FROM QUESTIONING THE
ARBITRATION AWARD, WHEN PETITIONER QUESTIONED THE
JURISDICTION OF THE RTC-MAKATI, BRANCH 62 AND AT THE SAME
TIME MOVED TO VACATE THE ARBITRAL AWARD.
III
THE COURT OF APPEALS ERRED IN NOT HOLDING THAT THE
RESPONDENT TRIAL COURT SHOULD HAVE EITHER
DISMISSED/DENIED PRIVATE RESPONDENTS MOTION/PETITION
FOR CONFIRMATION OF ARBITRATION AWARD AND/OR SHOULD
HAVE CONSIDERED THE MERITS OF THE MOTION TO VACATE
ARBITRAL AWARD.
III
IV
On July 12, 1995, the Court of Appeals, through its fifth Division denied due
course and dismissed the petition for certiorari.
Hence, the instant petition for review on certiorari imputing to the Court of
Appeals the following errors.
V
THE COURT OF APPEALS ERRED IN NOT RULING ON THE LEGAL
ISSUE OF WHEN TO RECKON THE COUNTING OF THE PERIOD TO
FILE A MOTION FOR RECONSIDERATION.[21]
The petition is impressed with merit.
I
ASSIGNMENT OF ERRORS
I
THE COURT OF APPEALS ERRED IN NOT HOLDING THAT THE
MAKATI REGIONAL TRIAL COURT, BRANCH 62 WHICH HAS
PREVIOULSY DISMISSED CIVIL CASE NO. 9900 HAD LOST
JURISDICTION TO CONFIRM THE ARBITRAL AWARD UNDER THE
SAME CIVIL CASE AND IN NOT RULING THAT THE APPLICATION
FOR CONFIRMATION SHOULD HAVE BEEN FILED AS A NEW CASE
TO BE RAFFLED OFF AMONG THE DIFFERENT BRANCHES OF THE
RTC.
The RTC of Makati, Branch 62, did not have jurisdiction to confirm the arbitral award
The use of the term dismissed is not a mere semantic imperfection. The
dispositive portion of the Order of the trial court dated October 14, 1992 stated in no
uncertain terms:
4. The Complaint is hereby DISMISSED.[22]
The term dismiss has a precise definition in law. To dispose of an action suit, or
motion without trial on the issues involved. Conclude, discontinue, terminate,
quash.[23]
Admittedly the correct procedure was for the parties to go back to the court
where the case was pending to have the award confirmed by said court. However,
Branch 62 made the fatal mistake of issuing a final order dismissing the case. While
Branch 62 should have merely suspended the case and not dismissed it, [24] neither of
the parties questioned said dismissal. Thus, both parties as well as said court are
bound by such error.
It is erroneous then to argue, as private respondents do, that petitioner APT was
charged with the knowledge that the case was merely stayed until arbitration
finished, as again, the order of Branch 62 in very clear terms stated that the
complaint was dismissed. By its own action, Branch 62 had lost jurisdiction over
the vase. It could not have validly reacquired jurisdiction over the said case on mere
motion of one of the parties. The Rules of Court is specific on how a new case may
be initiated and such is not done by mere motion in a particular branch of the
RTC. Consequently, as there was no pending action to speak of, the petition to
confirm the arbitral award should have been filed as a new case and raffled
accordingly to one of the branches of the Regional Trial Court.
II
Petitioner was not estopped from questioning the jurisdiction of Branch 62 of the RTC of Makati.
The Court of Appeals ruled that APT was already estopped to question the
jurisdiction of the RTC to confirm the arbitral award because it sought affirmative
relief in said court by asking that the arbitral award be vacated.
The rule is that Where the court itself clearly has no jurisdiction over the
subject matter or the nature of the action, the invocation of this defense may de done
at any time. It is neither for the courts nor for the parties to violate or disregard that
rule, let alone to confer that jurisdiction, this matter being legislative in
character.[25] As a rule the, neither waiver nor estoppel shall apply to confer
jurisdiction upon a court barring highly meritorious and exceptional circumstances.
[26]
One such exception was enunciated in Tijam vs. Sibonghanoy,[27] where it was
held that after voluntarily submitting a cause and encountering an adverse decision
on the merits, it is too late for the loser to question the jurisdiction or power of the
court."
Petitioners situation is different because from the outset, it has consistently
held the position that the RTC, Branch 62 had no jurisdiction to confirm the arbitral
award; consequently, it cannot be said that it was estopped from questioning the
RTCs jurisdiction. Petitioners prayer for the setting aside of the arbitral award was
not inconsistent with its disavowal of the courts jurisdiction.
III
Appeal of petitioner to the Court of Appeals thru certiorari under Rule 65 was proper.
The Court of Appeals in dismissing APTs petition for certiorari upheld the
trial courts denial of APTs motion for reconsideration of the trial courts order
confirming the arbitral award, on the ground that said motion was filed beyond the
15-day reglementary period; consequently, the petition for certiorari could not be
resorted to as substitute to the lost right of appeal.
We do not agree.
Section 29 of Republic Act No. 876,[28] provides that:
x x x An appeal may be taken from an order made in a proceeding under this
Act, or from a judgment entered upon an award through certiorari proceedings,
but such appeals shall be limited to question of law. x x x.
The aforequoted provision, however, does not preclude a party aggrieved by the
arbitral award from resorting to the extraordinary remedy of certiorari under Rule 65
of the Rules of Court where, as in this case, the Regional Trial Court to which the
award was submitted for confirmation has acted without jurisdiction, or with grave
abuse of discretion and there is no appeal, nor any plain, speedy remedy in the course
of law.
Thus, Section 1 of Rule 65 provides:
SEC 1. Petition for Certiorari: - When any tribunal, board or officer exercising
judicial functions, has acted without or in excess of its or his jurisdiction, or with
grave abuse of discretion and there is no appeal, nor any plain, speedy, and adequate
remedy in the ordinary course of law, a person aggrieved thereby may file a verified
petition in the proper court alleging the facts with certainty and praying that
judgment be rendered annulling or modifying the proceedings, as the law requires, of
such tribunal, board or officer.
In the instant case, the respondent court erred in dismissing the special civil
action for certiorari, it being from the pleadings and the evidence that the trial court
lacked jurisdiction and/or committed grave abuse of discretion in taking cognizance
of private respondent motion to confirm the arbitral award and, worse, in confirming
said award which is grossly and patently not in accord with the arbitration
agreement, as will be hereinafter demonstrated.
IV
As a rule, the award of an arbitrator cannot be set aside for mere errors of
judgment either as to the law or as to the facts. [29] Courts are without power to amend
or overrule merely because of disagreement with matters of law or facts determined
by the arbitrators.[30] They will not review the findings of law and fact contained in
an award, and will not undertake to substitute their judgment for that of the
arbitrators, since any other rule would make an award the commencement, not the
end, of litigation.[31] Errors of law and fact, or an erroneous decision of matters
submitted to the judgment of the arbitrators, are insufficient to invalidate an award
fairly and honestly made.[32] Judicial review of an arbitration is, thus, more limited
than judicial review of a trial.[33]
Nonetheless, the arbitrators awards is not absolute and without
exceptions. The arbitrators cannot resolve issues beyond the scope of the submission
agreement.[34] The parties to such an agreement are bound by the arbitrators award
only to the extent and in the manner prescribed by the contract and only if the award
is rendered in conformity thereto.[35] Thus, Sections 24 and 25 of the Arbitration Law
provide grounds for vacating, rescinding or modifying an arbitration award. Where
the conditions described in Articles 2038, [36] 2039[37] and 2040[38] of the Civil Code
applicable to compromises and arbitration are attendant, the arbitration award may
also be annulled.
In Chung Fu Industries (Phils.) vs. Court of Appeals,[39] we held:
x x x. It is stated explicitly under Art. 2044 of the Civil Code that the finality of the
arbitrators awards is not absolute and without exceptions. Where the conditions
described in Articles 2038, 2039, and 2040 applicable to both compromises and
arbitration are obtaining, the arbitrators' award may be annulled or
rescinded. Additionally, under Sections 24 and 25, of the Arbitration Law, there are
grounds for vacating, modifying or rescinding an arbitrators award. Thus, if and
when the factual circumstances referred to in the above-cited provisions are present,
judicial review of the award is properly warranted.
Accordingly, Section 20 of R.A. 876 provides:
SEC. 20. Form and contents of award. The award must be made in writing and
signed and acknowledged by a majority of the arbitrators, if more than one; and by
the sole arbitrator, if there is only one. Each party shall be furnished with a copy of
the award. The arbitrators in their award may grant any remedy or relief which they
deem just and equitable and within the scope of the agreement of the parties, which
shall include, but not be limited to, the specific performance of a contract.
xxx
The arbitrators shall have the power to decide only those matters which have been
submitted to them. The terms of the award shall be confined to such
disputes. (Underscoring ours).
xxx.
Section 24 of the same law enumerating the grounds for vacating an award
states:
SEC. 24. Grounds for vacating award. In any one of the following cases, the court
must make an order vacating the award upon the petition of any party to the
controversy when such party proves affirmatively that in the arbitration proceedings:
(a) The award was procured by corruption, fraud, or other undue means; or
(b) That there was evident partiality or corruption in arbitrators or any of them; or
(c) That the arbitrators were guilty of misconduct in refusing to postpone the hearing
upon sufficient cause shown, or in refusing to hear evidence pertinent and material to
the controversy; that one or more of the arbitrators was disqualified to act as such
under section nine hereof, and willfully refrained from disclosing such
disqualifications or any other misbehavior by which the rights of any party have been
materially prejudiced; or
(d) That the arbitrators exceeded their powers, or so imperfectly executed them, that
a mutual, final and definite award upon the subject matter submitted to them was not
made. (Underscoring ours).
xxx.
Section 25 which enumerates the grounds for modifying the award provides:
SEC. 25. Grounds for modifying or correcting award In anyone of the following
cases, the court must make an order modifying or correcting the award, upon the
application of any party to the controversy which was arbitrated:
(a) Where there was an evident miscalculation of figures, or an evident mistake in
the description of any person, thing or property referred to in the award; or
(b) Where the arbitrators have awarded upon a matter not submitted to them, not
affecting the merits of the decision upon the matter submitted; or
(c) Where the award is imperfect in a matter of form not affecting the merits of the
controversy, and if it had been a commissioners report, the defect could have been
amended or disregarded by the court.
x x x.
Finally, it should be stressed that while a court is precluded from overturning an
award for errors in determination of factual issues, nevertheless, if an examination of
the record reveals no support whatever for the arbitrators determinations, their
award must be vacated.[40] In the same manner, an award must be vacated if it was
made in manifest disregard of the law.[41]
Q : Now in this portion of Exh. L which was marked as Exh. L-1, and we
adopted as Exh. 37-A for the respondent, may I know from you, Dr. Mapa
what you meant by that the decision to foreclose was neither precipitate
nor arbitrary?
A
: And this statement that it was premised upon the known fact that
means, it was referring to the decision to foreclose, was premised upon the
known fact that the rehabilitation plan earlier approved by the stockholders
was no longer feasible, just what is meant by no longer feasible?
The point need not be belabored that PNB and DBP had the legitimate right to
foreclose of the mortgages of MMIC whose obligations were past due. The
foreclosure was not a wrongful act of the banks and, therefore, could not be the basis
of any award of damages. There was no financial restructuring agreement to speak
of that could have constituted an impediment to the exercise of the banks right to
foreclose.
: Because the revenue that they were counting on to make the rehabilitation
plan possible, was not anymore expected to be forthcoming because it will
result in a short fall compared to the prices that were actually taking place
in the market.
: And I supposed that was you were referring to when you stated that the
production targets and assumed prices of MMICs products, among other
projections, used in the financial reorganization program that will make it
viable were not met nor expected to be met?
: Yes.
Against the backdrop of the foregoing provisions and principles, we find that
the arbitrators came out with an award in excess of their powers and palpably devoid
of factual and legal basis.
V
There was no financial structuring program; foreclosure of mortgage was fully justified.
1. The various loans and advances made by DBP and PNB to MMIC have become
overdue and remain unpaid. The fact that a FRP was drawn up is enough to establish
that MMIC has not been complying with the terms of the loan
agreement. Restructuring simply connotes that the obligations are past due that is
why it is restructurable;
2. When MMIC thru its board and the stockholders agreed and adopted the FRP, it
only means that MMIC had been informed or notified that its obligations were past
due and that foreclosure is forthcoming;
3. At that stage, MMIC also knew that PNB-DBP had the option of either approving
the FRP or proceeding with the foreclosure. Cabarrus, who filed this case
supposedly in behalf of MMIC should have insisted on the FRP. Yet Cabarrus
himself opposed the FRP;
4. So when PNB-DBP proceeded with the foreclosure, it was done without bad faith
but with honest and sincere belief that foreclosure was the only alternative; a
decision further explained by Dr. Placido Mapa who testified that foreclosure was, in
the judgment of PNB, the best move to save MMIC itself.
xxx
Which brings me to my last point in this separate opinion. Was PNB and DBP
absolutely unjustified in foreclosing the mortgages?
In this connection, it can readily be seen and it cannot quite be denied that MMIC
accounts in PNB-DBP were past due. The drawing up of the FRP is the best proof of
this. When MMIC adopted a restructuring program for its loan, it only meant that
these loans were already due and unpaid. If these loans were restructurable because
they were already due and unpaid, they are likewise forecloseable. The option is
with the PNB-DBP on what steps to take.
The mere fact that MMIC adopted the FRP does not mean that DBP-PNB lost the
option to foreclose. Neither does it mean that the FRP is legally binding and
implementable. It must be pointed that said FRP will, in effect, supersede the
existing and past due loans of MMIC with PNB-DBP. It will become the new loan
agreement between the lenders and the borrowers. As in all other contracts, there
must therefore be a meeting of minds of the parties; the PNB and DBP must have to
validly adopt and ratify such FRP before they can be bound by it; before it can be
implemented. In this case, not an iota of proof has been presented by
the PLAINTIFFS showing that PNB and DBP ratified and adopted the FRP.
PLAINTIFFS simply relied on a legal doctrine of promissory estoppel to support its
allegation in this regard.[42]
Moreover, PNB and DBP had to initiate foreclosure proceedings as mandated
by P.D. No. 385, which took effect on January 31, 1974. The decree requires
government financial institutions to foreclose collaterals for loans where the
arrearages amount to 20% of the total outstanding obligations. The pertinent
provisions of said decree read as follows:
SEC. 1. It shall be mandatory for government financial institutions, after the lapse of
sixty (60) days from the issuance of this Decree to foreclose the collaterals and/or
securities for any loan, credit, accommodations, and/or guarantees granted by them
whenever the arrearages on such account, including accrued interest and other
charges, amount to at least twenty percent (20%) of the total outstanding obligations,
including interest and other charges, as appearing in the books of account and/or
related records of the financial institutions concerned. This shall be without
prejudice to the exercise by the government financial institutions of such rights
and/or remedies available to them under their respective contracts with their debtor,
including the right to foreclosure on loans, credits, accommodations and/or
guarantees on which the arrearages are less than twenty percent (20%).
SEC. 2. No restraining order, temporary or permanent injunction shall be issued by
the court against any government financial institution in any action taken by such
institution in compliance with themandatory foreclosure provided in Section
1 hereof, whether such restraining order, temporary or permanent injunction is
sought by the borrower(s) or any third party or parties, except after due hearing in
which it is established by the borrower and admitted by the government financial
institution concerned that twenty percent (20%) of the outstanding arrearages has
been paid after the filing of foreclosure proceedings. (Underscoring supplied.)
1. Declaring the foreclosure effected by the defendants DBP and PNB on the assets
of MMIC null and void and directing said defendants to restore the foreclosed assets
to the possession of MMIC, to render an accounting of their use and/or operation of
said assets and to indemnify MMIC for the loss occasioned by its dispossession or
the deterioration thereof;
2. Directing the defendants DBP and PNB to honor and perform their commitments
under the financial reorganization plan which was approved at the annual
stockholders meeting of MMIC on 30 April 1984;
3. Condemning the defendants DBP and PNB, jointly and severally to pay the
plaintiffs actual damages consisting of the loss of value of their investment
amounting to not less than P80,000,000.00, the damnum emerges and lucrum cessans
in such amount as may be establish during the trial, moral damages in such amount
as this Honorable Court may deem just and equitable in the premises, exemplary
damages in such amount as this Honorable Court may consider appropriate for the
purpose of setting an example for the public good, attorneys fees and litigation
expenses in such amounts as may be proven during the trial, and the costs legally
taxable in this litigation.
Further, Plaintiffs pray for such other reliefs as may be just and equitable in the
premises.[44]
Upon submission for arbitration, the Compromise and Arbitration Agreement of
the parties clearly and explicitly defined and limited the issues to the following:
(a) whether PLAINTIFFS have the capacity or the personality to institute
this derivative suit in behalf of the MMIC or its directors;
(b) whether or not the actions leading to, and including, the PNB-DBP
foreclosure of the MMIC assets were proper, valid and in good faith.[45]
Private respondents thesis that the foreclosure proceedings were null and void
because of lack of publication in the newspaper is nothing more than a mere
unsubstantiated allegation not borne out by the evidence. In any case, a disputable
presumption exists in favor of petitioner that official duty has been regularly
performed and ordinary course of business has been followed.[43]
Item No. 8 of the Agreement provides for the period by which the Committee
was to render its decision, as well as the nature thereof:
VI
In the event the committee finds that PLAINTIFFS have the personality to file this
suit and extra-judicial foreclosure of the MMIC assets wrongful, it shall make an
award in favor of the PLAINTIFFS (excluding DBP), in an amount as may be
established or warranted by the evidence which shall be payable in Philippine Pesos
at the time of the award. Such award shall be paid by the APT or its successor-ininterest within sixty (60) days from the date of the award in accordance with the
provisions of par. 9 hereunder. x x x. The PLAINTIFFS remedies under this
Section shall be in addition to other remedies that may be available to the
PLAINTIFFS, all such remedies being cumulative and not exclusive of each other.
Not only was the foreclosure rightfully exercised by the PNB and DBP, but
also, from the facts of the case, the arbitrators in making the award went beyond the
arbitration agreement.
In their complaint filed before the trial court, private respondent Cabarrus, et
al. prayed for judgment in their favor:
On the other hand, in case the arbitration committee finds that PLAINTIFFS have no
capacity to sue and/or that the extra-judicial foreclosure is valid and legal, it shall
also make an award in favor of APT based on the counterclaims of DBP and PNB in
an amount as may be established or warranted by the evidence. This decision of the
arbitration committee in favor of APT shall likewise finally settle all issues regarding
the foreclosure of the MMIC assets so that the funds held in escrow mentioned in
par. 9 hereunder will thus be released in full in favor of APT.[46]
The clear and explicit terms of the submission notwithstanding, the Arbitration
Committee clearly exceeded its powers or so imperfectly executed them: (a) in ruling
on and declaring valid the FRP; (b) in awarding damages to MMIC which was not a
party to the derivative suit; and (c) in awarding moral damages to Jesus S. Cabarrus,
Sr.
Although the DBP sat in the board in a dual capacity-as holder of 36% of MMICs
equity (at that time) and as MMICs creditor-the DBP can not validly renege on its
commitments simply because at the same time, it held interest against the MMIC.
The fact, of course, is that as APT itself asserted, the FRP was being carried out
although apparently, it would supposedly fall short of its targets. Assuming that the
FRP would fail to meet its targets, the DBP-and so this Committee holds-can not, in
any event, brook any denial that it was bound to begin with, and the fact is that
adequate or not (the FRP), the government is still bound by virtue of its acts.
The FRP, of course, did not itself promise a resounding success, although it raised
DBPs equity in MMIC to 87%. It is not excuse, however, for the government to
deny its commitments.[52]
Atty. Sison, however, did not agree and correctly observed that:
The arbiters overstepped their powers by declaring as valid proposed Financial Restructuring Program.
The Arbitration Committee went beyond its mandate and thus acted in excess
of its powers when it ruled on the validity of, and gave effect to, the proposed FRP.
In submitting the case to arbitration, the parties had mutually agreed to limit the
issue to the validity of the foreclosure and to transform the reliefs prayed for
therein into pure money claims.
There is absolutely no evidence that the DBP and PNB agreed, expressly or
impliedly, to the proposed FRP. It cannot be overemphasized that a FRP, as a
contract, requires the consent of the parties thereto. [47] The contract must bind both
contracting parties.[48] Private respondents even by their own admission recognized
that the FRP had yet not been carried out and that the loans of MMIC had not yet
been converted into equity.[49]
However, the arbitration Committee not only declared the FRP valid and
effective, but also converted the loans of MMIC into equity raising the equity of
DBP to 87%.[50]
The Arbitration Committee ruled that there was a commitment to carry out the
FRP[51] on the ground of promissory estoppel.
Similarly, the principle of promissory estoppel applies in the present case
considering as we observed, the fact that the government (that is Alfredo Velayo) was
the FRPs proponent. Although the plaintiffs are agreed that the government
executed no formal agreement, the fact remains that the DBP itself which made
representations that the FRP constituted a way out for MMIC. The Committee
believes that although the DBP did not formally agree (assuming that the board and
stockholders approvals were not formal enough), it is bound nonetheless if only for
its conspicuous representations.
But the doctrine of promissory estoppel can hardly find application here. The
nearest that there can be said of any estoppel being present in this case is the fact that
the board of MMIC was, at the time the FRP was adopted, mostly composed of PNB
and DBP representatives. But those representatives, singly or collectively, are not
themselves PNB or DBP. They are individuals with personalities separate and
distinct from the banks they represent. PNB and DBP have different boards with
different members who may have different decisions. It is unfair to impose upon
them the decision of the board of another company and thus pin them down on the
equitable principle of estoppel. Estoppel is a principle based on equity and it is
certainly not equitable to apply it in this particular situation. Otherwise the rights of
entirely separate, distinct and autonomous legal entities like PNB and DBP with
thousands of stockholders will be suppressed and rendered nugatory.[53]
As a rule, a corporation exercises its powers, including the power to enter into
contracts, through its board of directors. While a corporation may appoint agents to
enter into a contract in its behalf, the agent, should not exceed his authority.[54] In the
case at bar, there was no showing that the representatives of PNB and DBP in MMIC
even had the requisite authority to enter into a debt-for-equity swap. And if they had
such authority, there was no showing that the banks, through their board of directors,
had ratified the FRP.
Further, how could the MMIC be entitled to a big amount of moral damages
when its credit reputation was not exactly something to be considered sound and
wholesome. Under Article 2217 of the Civil Code, moral damages include
besmirched reputation which a corporation may possibly suffer. A corporation
whose overdue and unpaid debts to the Government alone reached a tremendous
amount of P22 Billion Pesos cannot certainly have a solid business reputation to brag
about. As Atty. Sison in his separate opinion persuasively put it:
Besides, it is not yet a well settled jurisprudence that corporations are entitled to
moral damages. While the Supreme Court may have awarded moral damages to a
corporation for besmirched reputation in Mambulao vs. PNB 22 SCRA 359, such
ruling cannot find application in this case. It must be pointed out that when the
supposed wrongful act of foreclosure was done, MMICs credit reputation was no
longer a desirable one. The company then was already suffering from serious
financial crisis which definitely projects an image not compatible with good and
wholesome reputation. So it could not be said that there was a reputation
besmirches by the act of foreclosure.[55]
corporation itself for the benefit of the stockholders. In other words, to allow
shareholders to sue separately would conflict with the separate corporate entity
principle;
(2) x x x that the prior rights of the creditors may be prejudiced. Thus, our Supreme
Court held in the case of Evangelista v. Santos, that the stockholders may not
directly claim those damages for themselves for that would result in the
appropriation by, and the distribution among them of part of the corporate assets
before the dissolution of the corporation and the liquidation of its debts and
liabilities, something which cannot be legally done in view of section 16 of the
Corporation Law xxx;
The arbiters exceeded their authority in awarding damages to MMIC, which is not impleaded as a party to the derivative suit.
Civil Code No. 9900 filed before the RTC being a derivative suit, MMIC
should have been impleaded as a party. It was not joined as a party plaintiff or party
defendant at any stage of the proceedings. As it is, the award of damages to MMIC,
which was not a party before the Arbitration Committee, is a complete nullity.
Settled is the doctrine that in a derivative suit, the corporation is the real party
in interest while the stockholder filing suit for the corporations behalf is only
nominal party. The corporation should be included as a party in the suit.
An individual stockholder is permitted to institute a derivative suit on behalf of the
corporation wherein he holds stock in order to protect or vindicate corporate rights,
whenever the officials of the corporation refuse to sue, or are the ones to be sued or
hold the control of the corporation. In such actions, the suing stockholder is
regarded as a nominal party, with the corporation as the real party in interest. x x x.
[56]
(3) the filing of such suits would conflict with the duty of the management to sue for
the protection of all concerned;
(4) it would produce wasteful multiplicity of suits; and
(5) it would involve confusion in a ascertaining the effect of partial recovery by an
individual on the damages recoverable by the corporation for the same act. [58]
If at all an award was due MMIC, which it was not, the same should have been
given sans deduction, regardless of whether or not the party liable had equity in the
corporation, in view of the doctrine that a corporation has a personality separate and
distinct from its individual stockholders or members. DBPs alleged equity, even if it
were indeed 87%, did not give it ownership over any corporate property, including
the monetary award, its right over said corporate property being a mere expectancy
or inchoate right.[59]Notably, the stipulation even had the effect of prejudicing the
other creditors of MMIC.
The arbiters, likewise, exceeded their authority in awarding moral damages to Jesus Cabarrus, Sr.
It is perplexing how the Arbitration Committee can in one breath rule that the
case before it is a derivative suit, in which the aggrieved party or the real party in
interest is supposedly the MMIC, and at the same time award moral damages to an
individual stockholder, to wit:
WHEREFORE, premises considered, judgment is hereby rendered:
xxx.
3. Ordering the defendant to pay to the plaintiff, Jesus S. Cabarrus, Sr., the sum
of P10,000,000.00, to be satisfied likewise from the funds held under escrow
pursuant to the Escrow Agreement dated April 22, 1988 or to such subsequent
escrow agreement that would supersede it, pursuant to paragraph (9), Compromise
and Arbitration Agreement, as and for moral damages; x x x[60]
The majority decision of the Arbitration Committee sought to justify its award
of moral damages to Jesus S. Cabarrus, Sr. by pointing to the fact that among the
assets seized by the government were assets belonging to Industrial Enterprise Inc.
(IEI), of which Cabarrus is the majority stockholder. It then acknowledge that
Cabarrus had already recovered said assets in the RTC, but that he won no more
than actual damages. While the Committee cannot possibly speak for the RTC, there
is no doubt that Jesus S. Cabarrus, Sr., suffered moral damages on account of that
specific foreclosure, damages the Committee believes and so holds, he Jesus S.
Cabarrus, Sr., may be awarded in this proceeding.[61]
Cabarrus cause of action for the seizure of the assets belonging to IEI, of
which he is the majority stockholder, having been ventilated in a complaint he
previously filed with the RTC, from which he obtained actual damages, he was
barred res judicata from filing a similar case in another court, this time asking for
moral damages which he failed to get from the earlier case. [62] Worse, private
respondents violated the rule against non-forum shopping.
It is a basic postulate that s corporation has a personality separate and distinct
from its stockholders.[63] The properties foreclosed belonged to MMIC, not to its
stockholders. Hence, if wrong was committed in the foreclosure, it was done against
the corporation. Another reason is that Jesus S. Cabarrus, Sr. cannot directly claim
those damages for himself that would result in the appropriation by, and the
distribution to, him part of the corporations assets before the dissolution of the
corporation and the liquidation of its debts and liabilities. The Arbitration
Committee, therefore, passed upon matters not submitted to it. Moreover, said cause
of action had already been decided in a separate case. It is thus quite patent that the
arbitration committee exceeded the authority granted to it by the parties
Compromise and Arbitration Agreement by awarding moral damages to Jesus S.
Cabarrus, Sr.
Atty. Sison, in his separate opinion, likewise expressed befuddlement to the
award of moral damages to Jesus S. Cabarrus, Sr.:
It is clear and it cannot be disputed therefore that based on these stipulated issues,
the parties themselves have agreed that the basic ingredient of the causes of action in
this case is the wrong committed on the corporation (MMIC) for the alleged illegal
foreclosure of its assets. By agreeing to this stipulation, PLAINTIFFS themselves
(Cabarrus, et al.) admit that the cause of action pertains only to the
corporation(MMIC) and that they are filing this for and in behalf of MMIC.
Perforce this has to be so because it is the basic rule in Corporation Law that the
shareholders have no title, legal or equitable to the property which is owned by the
corporation (13 Am. Jur. 165; Pascual vs. Oresco, 14 Phil. 83). In Ganzon & Sons
vs. Register of Deeds, 6 SCRA 373, the rule has been reiterated that a stockholder is
not the co-owner of corporate property. Since the property or assets foreclosed
belongs [sic] to MMIC, the wrong committed, if any, is done against the
corporation. There is therefore no direct injury or direct violation of the rights of
Cabarrus et al. There is no way, legal or equitable, by which Cabarrus et al. could
recover damages in their personal capacities even assuming or just because the
foreclosure is improper or invalid. The Compromise and Arbitration Agreement
itself and the elementary principles of Corporation Law say so. Therefore, I am
constrained to dissent from the award of moral damages to Cabarrus.[64]
From the foregoing discussions, it is evident that, not only did the arbitration
committee exceed its powers or so imperfectly execute them, but also, its findings
and conclusions are palpably devoid of any factual basis and in manifest disregard of
the law.
We do not find it necessary to remand this case to the RTC for appropriate
action. The pleadings and memoranda filed with this Court, as well as in the Court
of Appeals, raised and extensively discussed the issues on the merits. Such being the
case, there is sufficient basis for us to resolve the controversy between the parties
anchored on the records and the pleadings before us.[65]
WHEREFORE, the Decision of the Court of Appeals dated July 17, 1995, as
well as the Orders of the Regional Trial Court of Makati, Branch 62, dated
November 28, 1994 and January 19, 1995, is hereby REVERSED and SET ASIDE,
and the decision of the Arbitration Committee is hereby VACATED.
SO ORDERED
[G.R. No. 129169. November 17, 1999]
NATIONAL
IRRIGATION
ADMINISTRATION
(NIA), petitioner,
vs. HONORABLE
COURT OF APPEALS
(4th
Division),
CONSTRUCTION INDUSTRY ARBITRATION COMMISSION, and
HYDRO
RESOURCES
CONTRACTORS
CORPORATION, respondents.
DECISION
DAVIDE, JR., C.J.:
In this special civil action for certiorari under Rule 65 of the Rules of Court,
the National Irrigation Administration (hereafter NIA), seeks to annul and set aside
the Resolutions[1]of the Court of Appeals in CA-GR. SP No. 37180 dated 28 June
1996 and 24 February 1997, which dismissed respectively NIAs petition
We take judicial notice that on 10 June 1997, CIAC rendered a decision in the
main case in favor of HYDRO.[13] NIA assailed the said decision with the Court of
Appeals. In view of the pendency of the present petitions before us the appellate
court issued a resolution dated 26 March 1998 holding in abeyance the resolution of
the same until after the instant petitions have been finally decided.[14]
At the outset, we note that the petition suffers from a procedural defect that
warrants its outright dismissal. The questioned resolutions of the Court of Appeals
have already become final and executory by reason of the failure of NIA to appeal
therefrom. Instead of filing this petition for certiorari under Rule 65 of the Rules of
Court, NIA should have filed a timely petition for review under Rule 45.
There is no doubt that the Court of Appeals has jurisdiction over the special
civil action for certiorari under Rule 65 filed before it by NIA. The original
jurisdiction of the Court of Appeals over special civil actions for certiorari is vested
upon it under Section 9(1) of B.P. 129. This jurisdiction is concurrent with the
Supreme Court[15] and with the Regional Trial Court.[16]
Thus, since the Court of Appeals had jurisdiction over the petition under Rule
65, any alleged errors committed by it in the exercise of its jurisdiction would be
errors of judgment which are reviewable by timely appeal and not by a special civil
action of certiorari.[17] If the aggrieved party fails to do so within the reglementary
period, and the decision accordingly becomes final and executory, he cannot avail
himself of the writ of certiorari, his predicament being the effect of his deliberate
inaction.[18]
The appeal from a final disposition of the Court of Appeals is a petition for
review under Rule 45 and not a special civil action under Rule 65 of the Rules of
Court, now Rule 45 and Rule 65, respectively, of the 1997 Rules of Civil Procedure.
[19]
Rule 45 is clear that decisions, final orders or resolutions of the Court of Appeals
in any case, i.e., regardless of the nature of the action or proceedings involved, may
be appealed to this Court by filing a petition for review, which would be but a
continuation of the appellate process over the original case. [20] Under Rule 45 the
reglementary period to appeal is fifteen (15) days from notice of judgment or denial
of motion for reconsideration.[21]
In the instant case the Resolution of the Court of Appeals dated 24 February
1997 denying the motion for reconsideration of its Resolution dated 28 June 1997
was received by NIA on 4 March1997. Thus, it had until 19 March 1997 within
which to perfect its appeal. NIA did not appeal. What it did was to file an original
action for certiorari before this Court, reiterating the issues and arguments it raised
before the Court of Appeals.
For the writ of certiorari under Rule 65 of the Rules of Court to issue, a
petitioner must show that he has no plain, speedy and adequate remedy in the
ordinary course of law against its perceived grievance. [22] A remedy is considered
plain, speedy and adequate if it will promptly relieve the petitioner from the
injurious effects of the judgment and the acts of the lower court or agency. [23] In this
case, appeal was not only available but also a speedy and adequate remedy.
Obviously, NIA interposed the present special civil action of certiorari not
because it is the speedy and adequate remedy but to make up for the loss, through
omission or oversight, of the right of ordinary appeal. It is elementary that the
special civil action of certiorari is not and cannot be a substitute for an appeal, where
the latter remedy is available, as it was in this case. A special civil action under Rule
65 of the Rules of Court will not be a cure for failure to timely file a petition for
review on certiorari under Rule 45 of the Rules of Court. [24] Rule 65 is an
independent action that cannot be availed of as a substitute for the lost remedy of an
ordinary appeal, including that under Rule 45,[25] especially if such loss or lapse was
occasioned by ones own neglect or error in the choice of remedies.[26]
For obvious reasons the rules forbid recourse to a special civil action
for certiorari if appeal is available, as the remedies of appeal and certiorari are
mutually exclusive and not alternative or successive. [27] Although there are
exceptions to the rules, none is present in the case at bar. NIA failed to show
circumstances that will justify a deviation from the general rule as to make available
a petition forcertiorari in lieu of taking an appropriate appeal.
whether the dispute arises before or after the completion of the contract, or after the
abandonment or breach thereof. The disputes may involve government or private
contracts. For the Board to acquire jurisdiction, the parties to a dispute must agree to
submit the same to voluntary arbitration.[28]
The complaint of HYDRO against NIA on the basis of the contract executed
between them was filed on 7 December 1994, during the effectivity of E.O. No.
1008. Hence, it is well within the jurisdiction of CIAC. The jurisdiction of a court is
determined by the law in force at the time of the commencement of the action.[29]
NIAs argument that CIAC had no jurisdiction to arbitrate on contract which
preceded its existence is untenable. E.O. 1008 is clear that the CIAC has jurisdiction
over all disputes arising from or connected with construction contract whether the
dispute arises before or after the completion of the contract. Thus, the date the
parties entered into a contract and the date of completion of the same, even if these
occurred before the constitution of the CIAC, did not automatically divest the CIAC
of jurisdiction as long as the dispute submitted for arbitration arose after the
constitution of the CIAC. Stated differently, the jurisdiction of CIAC is over the
dispute, not the contract; and the instant dispute having arisen when CIAC was
already constituted, the arbitral board was actually exercising current, not retroactive,
jurisdiction. As such, there is no need to pass upon the issue of whether E.O. No.
1008 is a substantive or procedural statute.
NIA also contended that the CIAC did not acquire jurisdiction over the dispute
since it was only HYDRO that requested for arbitration. It asserts that to acquire
jurisdiction over a case, as provided under E.O. 1008, the request for arbitration filed
with CIAC should be made by both parties, and hence the request by one party is not
enough.
permitted. The court may either grant the motion to dismiss, deny it, or order the
amendment of the pleading.
WHEREFORE, the instant petition is DISMISSED for lack of merit. The
Court of Appeals is hereby DIRECTED to proceed with reasonable dispatch in the
disposition of C.A. G.R. No. 44527 and include in the resolution thereof the issue of
laches and prescription.
SO ORDERED.
ASSOCIATION,
ASSOCIATION,
ASSOCIATION,
RESOLUTION
Puno, J.:
Before this Court are the separate Motions for Reconsideration filed by
respondent Philippine International Air Terminals Co., Inc. (PIATCO),
respondents-intervenors Jacinto V. Paras, Rafael P. Nantes, Eduardo C.
Zialcita, Willie Buyson Villarama, Prospero C. Nograles, Prospero A. Pichay,
Jr., Harlin Cast Abayon and Benasing O. Macaranbon, all members of the
House of Representatives (Respondent Congressmen), [1] respondentsintervenors who are employees of PIATCO and other workers of the Ninoy
Aquino International Airport International Passenger Terminal III (NAIA IPT III)
(PIATCO Employees)[2] and respondents-intervenors Nagkaisang Maralita ng
Taong Association, Inc., (NMTAI)[3] of the Decision of this Court dated May
5, 2003 declaring the contracts for the NAIA IPT III project null and void.
Briefly, the proceedings. On October 5, 1994, Asias Emerging Dragon
Corp. (AEDC) submitted an unsolicited proposal to the Philippine
Government through the Department of Transportation and Communication
(DOTC) and Manila International Airport Authority (MIAA) for the construction
and development of the NAIA IPT III under a build-operate-and-transfer
arrangement pursuant to R.A. No. 6957, as amended by R.A. No. 7718 (BOT
Law).[4] In accordance with the BOT Law and its Implementing Rules and
Regulations (Implementing Rules), the DOTC/MIAA invited the public for
submission of competitive and comparative proposals to the unsolicited
proposal of AEDC. On September 20, 1996 a consortium composed of the
Peoples Air Cargo and Warehousing Co., Inc. (Paircargo), Phil. Air and
Grounds Services, Inc. (PAGS) and Security Bank Corp. (Security Bank)
II
Pre-qualification of PIATCO
The Implementing Rules provide for the unyielding standards the PBAC
should apply to determine the financial capability of a bidder for prequalification purposes: (i) proof of the ability of the project proponent and/or
the consortium to provide a minimum amount of equity to the project and
(ii) a letter testimonial from reputable banks attesting that the project
proponent and/or members of the consortium are banking with them,
that they are in good financial standing, and that they have adequate
resources.[22] The evident intent of these standards is to protect the integrity
and insure the viability of the project by seeing to it that the proponent has
the financial capability to carry it out. As a further measure to achieve this
intent, it maintains a certain debt-to-equity ratio for the project.
At the pre-qualification stage, it is most important for a bidder to show
that it has the financial capacity to undertake the project by proving that it can
fulfill the requirement on minimum amount of equity. For this purpose, the
Bid Documents require in no uncertain terms:
The minimum amount of equity to which the proponents financial capability will be
based shall be thirty percent (30%) of the project cost instead of the twenty
percent (20%) specified in Section 3.6.4 of the Bid Documents. This is to correlate
with the required debt-to-equity ratio of 70:30 in Section 2.01a of the draft
concession agreement. The debt portion of the project financing should not exceed
70% of the actual project cost.[23]
In relation thereto, section 2.01 (a) of the ARCA provides:
Section 2.01 Project Scope.
The scope of the project shall include:
(a) Financing the project at an actual Project cost of not less than Three
Hundred Fifty Million United States Dollars (US$350,000,000.00) while
maintaining a debt-to-equity ratio of 70:30, provided that if the actual
Project costs should exceed the aforesaid amount, Concessionaire shall
ensure that the debt-to-equity ratio is maintained;[24]
Each member of the proponent entity is to provide evidence of networth in cash and
assets representing the proportionate share in the proponent entity. Audited financial
statements for the past five (5) years as a company for each member are to be
provided.
Testimonial letters from reputable banks attesting that each of the members of the
ownership entity are banking with them, in good financial standing and having
adequate resources are to be provided.[26]
It is beyond refutation that Paircargo Consortium failed to prove
its ability to provide the amount of at least P2,755,095,000.00, or 30% of
the estimated project cost. Its submission of testimonial letters attesting to
its good financial standing will not cure this failure. At best, the said letters
merely establish its credit worthiness or its ability to obtain loans to finance
the project. They do not, however, prove compliance with the aforesaid
requirement of minimum amount of equity in relation to the prescribed debtto-equity ratio. This equity cannot be satisfied through possible loans.
In sum, we again hold that given the glaring gap between the net worth
of Paircargo and PAGS combined with the amount of maximum funds that
Security Bank may invest by equity in a non-allied undertaking, Paircargo
Consortium, at the time of pre-qualification, failed to show that it had the
ability to provide 30% of the project cost and necessarily, its financial
capability for the project cannot pass muster.
III
1997 Concession Agreement
Again, we brightline the principle that in public bidding, bids are
submitted in accord with the prescribed terms, conditions and parameters
laid down by government and pursuant to the requirements of the project
bidded upon. In light of these parameters, bidders formulate competing
proposals which are evaluated to determine the bid most favorable to the
government. Once the contract based on the bid most favorable to the
government is awarded, all that is left to be done by the parties is to execute
specifies these fees as part of Public Utility Revenues and can be adjusted
only once every two years and in accordance with the Parametric
Formula and the adjustments shall be made effective only after the
written express approval of the MIAA.[29] The Bid Documents themselves
clearly provide:
4.2.3 Mechanism for Adjustment of Fees and Charges
4.2.3.1
c) groundhandling fees;
d) rentals on airline offices;
....
(f) porterage fees;
. . . .[30]
The plain purpose in re-classifying groundhandling fees, airline office
rentals and porterage fees as non-public utility fees is to remove them from
regulation by the MIAA. In excluding these fees from government
regulation, the danger to public interest cannot be downplayed.
but to dilute the extent of MIAAs regulation in the collection of these fees.
Again, the amendment diminished the authority of MIAA to protect the public
interest in case of abuse by PIATCO.
b.
Assumption by the
Assignment.
....
(b)
In the event Concessionaire should default in the payment of an
Attendant Liability, and the default has resulted in the acceleration of the payment
due date of the Attendant Liability prior to its stated date of maturity, the Unpaid
Creditors and Concessionaire shall immediately inform GRP in writing of such
default. GRP shall, within one hundred eighty (180) Days from receipt of the joint
written notice of the Unpaid Creditors and Concessionaire, either (i) take over the
Development Facility and assume the Attendant Liabilities, or (ii) allow the
Unpaid Creditors, if qualified, to be substituted as concessionaire and operator of the
Development Facility in accordance with the terms and conditions hereof, or
designate a qualified operator acceptable to GRP to operate the Development
Facility, likewise under the terms and conditions of this Agreement; Provided that if
at the end of the 180-day period GRP shall not have served the Unpaid Creditors and
Concessionaire written notice of its choice, GRP shall be deemed to have elected to
take over the Development Facility with the concomitant assumption of Attendant
Liabilities.
IV.
Direct Government Guarantee
(c)
If GRP should, by written notice, allow the Unpaid Creditors to be
substituted as concessionaire, the latter shall form and organize a concession
company qualified to take over the operation of the Development Facility. If the
concession company should elect to designate an operator for the Development
Facility, the concession company shall in good faith identify and designate a
qualified operator acceptable to GRP within one hundred eighty (180) days from
receipt of GRPs written notice. If the concession company, acting in good faith and
with due diligence, is unable to designate a qualified operator within the aforesaid
period, then GRP shall at the end of the 180-day period take over the Development
Facility and assume Attendant Liabilities.
A plain reading of the above provision shows that it spells out in limpid
language the obligation of government in case of default by PIATCO on its
loans. There can be no blinking from the fact that in case of PIATCOs
default, the government will assume PIATCOs Attendant Liabilities as
defined in the 1997 Concession Agreement. [38] This obligation is not found in
the draft Concession Agreement and the change runs roughshod to the spirit
and policy of the BOT Law which was crafted precisely to prevent
government from incurring financial risk.
In any event, PIATCO pleads that the entire agreement should not be
struck down as the 1997 Concession Agreement contains a separability
clause.
The plea is bereft of merit. The contracts at bar which made a mockery
of the bidding process cannot be upheld and must be annulled in their
entirety for violating law and public policy. As demonstrated, the contracts
were substantially amended after their award to the successful bidder on
terms more beneficial to PIATCO and prejudicial to public interest. If this
flawed process would be allowed, public bidding will cease to be competitive
and worse, government would not be favored with the best bid. Bidders will
no longer bid on the basis of the prescribed terms and conditions in the bid
documents but will formulate their bid in anticipation of the execution of a
future contract containing new and better terms and conditions that were not
previously available at the time of the bidding. Such a public bidding will not
inure to the public good. The resulting contracts cannot be given half a life
but must be struck down as totally lawless.
the 1997 Concession Agreement specifying the attendant liabilities that the
Government would be obligated to pay should PIATCO default in its loan
obligations is equally onerous to the Government as those contained in the
ARCA. According to the 1997 Concession Agreement, in the event the
Government is forced to prematurely take over NAIA IPT III as a result of
respondent PIATCOs default in the payment of its loan obligations to its
Senior Lenders, it would be liable to pay the following amounts as attendant
liabilities:
Section 1.06.
Attendant Liabilities
Attendant Liabilities refer to all amounts recorded and from time to time
outstanding in the books of the Concessionaire as owing to Unpaid
Creditors who have provided, loaned or advanced funds actually used for the
Project, including all interests, penalties, associated fees, charges, surcharges,
indemnities, reimbursements and other related expenses, and further including
amounts owed by Concessionaire to its suppliers, contractors and sub-contractors. [47]
These provisions reject respondents contention that what the
Government is obligated to pay, in the event that respondent PIATCO
defaults in the payment of its loans, is merely termination payment or just
compensation for its takeover of NAIA IPT III. It is clear from said section
1.06 that what the Government would pay is the sum total of all the
debts, including all interest, fees and charges, that respondent PIATCO
incurred in pursuance of the NAIA IPT III Project. This reading is consistent
with section 4.04 of the ARCA itself which states that the Government shall
make a termination payment to Concessionaire [PIATCO] equal to the
Appraised Value (as hereinafter defined) of the Development Facility [NAIA
Terminal III] or the sum of the Attendant Liabilities, if greater. For sure,
respondent PIATCO will not receive any amount less than sufficient to
cover its debts, regardless of whether or not the value of NAIA IPT III, at
the time of its turn over to the Government, may actually be less than
the amount of PIATCOs debts. The scheme is a form of direct government
guarantee for it is undeniable that it leaves the government no option but to
pay the attendant liabilities in the event that the Senior Lenders are unable
or unwilling to appoint a qualified nominee or transferee as a result of
PIATCOs default in the payment of its Senior Loans. As we stressed in our
Decision, this Court cannot depart from the legal maxim that those that
cannot be done directly cannot be done indirectly.
Section 17, Article XII of the 1987 Constitution grants the State in times
of national emergency the right to temporarily take over the operation of any
business affected with public interest. This right is an exercise of police
power which is one of the inherent powers of the State.
Police power has been defined as the "state authority to enact
legislation that may interfere with personal liberty or property in order to
promote the general welfare."[54] It consists of two essential elements. First, it
is an imposition of restraint upon liberty or property. Second, the power is
exercised for the benefit of the common good. Its definition in elastic terms
underscores its all-encompassing and comprehensive embrace. [55] It is and
still is the most essential, insistent, and illimitable [56] of the States
powers. It is familiar knowledge that unlike the power of eminent domain,
police power is exercised without provision for just compensation for its
paramount consideration is public welfare.[57]
It is also settled that public interest on the occasion of a national
emergency is the primary consideration when the government decides to
temporarily take over or direct the operation of a public utility or a business
affected with public interest. The nature and extent of the emergency is the
measure of the duration of the takeover as well as the terms thereof. It is the
State that prescribes such reasonable terms which will guide the
implementation of the temporary takeover as dictated by the exigencies of
the time. As we ruled in our Decision, this power of the State can not be
negated by any party nor should its exercise be a source of obligation for the
State.
Section 5.10(c), Article V of the ARCA provides that respondent PIATCO
shall be entitled to reasonable compensation for the duration of the
temporary takeover by GRP, which compensation shall take into account the
reasonable cost for the use of the Terminal and/or Terminal Complex. [58] It
clearly obligates the government in the exercise of its police power to
compensate respondent PIATCO and this obligation is offensive to the
Constitution. Police power can not be diminished, let alone defeated by any
contract for its paramount consideration is public welfare and interest. [59]
Panganiban, C.J.
(Chairperson),
- versus Ynares-Santiago,
Austria-Martinez,
Callejo, Sr., and
Chico-Nazario, JJ.
ANTONIO YULO BALDE II, PAULINO
M. NOTO and ERNESTO J. BATTAD,
SR., in their capacities as Arbitrators of
the CONSTRUCTION INDUSTRY
ARBITRATION COMMISSION,
Promulgated:
SPOUSES CESAR and CARMELITA
ESQUIG and ROSEMARIE PAPAS,
Respondents.
x ---------------------------------------------------------------------------------------- x
RESOLUTION
rulings made by the Court. Like the three other Division members, he merely
concurred with the actions/rulings proposed by the ponente. While some orders and
actions, especially temporary restraining orders, are issued in the name of the
Division chairman (who in this case is the Chief Justice), they are really collective
YNARES-SANTIAGO, J.:
actions of the entire Division, not merely those of the Chair. This is the normal
procedure in all Divisions, not just in the First.
Before the Court is a Motion to Inhibit the Honorable Chief Justice and
Motion to Refer Case to the Court En Banc, dated August 4, 2006, filed by Atty.
Francisco I. Chavez.
(2)
Chavez and Atty. Sedfrey Ordoez with whom Chief Justice worked either as
I.
associate or partner sometime ago has nothing to do at all with the concurrences
made by the Chief Justice on this case. These concurrences were given on the basis
According to the movant, the Motion to Inhibit the Chief Justice is not an
(3)
True, the Chief Justice was an associate (not a partner) in 1961 to 1963
in the Salonga, Ordoez and Associates, which incidentally had been dissolved in
1987. True also, he has had a close personal and professional relationship with the
principal partner in that law firm, Sen. Jovito R. Salonga. That is the reason the
The movant adds that the dizzying pace by which private respondents
motions have been received and favorably acted upon in record time supports Atty.
Chief Justice has inhibited himself from cases in which Sen. Salonga was/is a party
or a counsel.[1]
However, he had no similar closeness with Atty. Ordoez. That is why he has
not inhibited himself from cases involving Atty. Ordoez. In fact, he has not
hesitated, on several occasions, to vote against parties/causes represented by the
Atty. Chavezs perception about the alleged closeness and the good
relationship between Atty. Ordoez and the Chief Justice to impair the latters
objectivity and impartiality has no basis, for the following reasons:
(4)
indirectly, with the Chief Justice on any matter pending in the Supreme Court and in
(1)
the movant were made by the entire membership of the First Division. Not being
the ponente, the Chief Justice did not initiate or propose any of the actions and
any other court. He has never attempted, directly or indirectly, personally or through
others, to influence the Chief Justice in any manner whatsoever. In fact, the Chief
Justice understands that Atty. Ordoez has been seriously ill, going in and out of the
hospital, over the past several months. And yet the Chief Justice has not even visited
or spoken with him during such period.
(5)
On the other hand, the Chief Justice, when so warranted by the facts and
law, has voted in favor of causes and parties represented by Atty. Chavez. One
(1)
outstanding example is Chavez v. PCGG (360 Phil. 133, December 9, 1998; 366 Phil.
Judge, Regional Trial Court of Muntinlupa City, Branch 203, as public respondent
863, May 19, 1999), which was written by then Associate Justice Artemio V.
was denied because Section 4, Rule 45 of the Rules of Court provides that in a
Panganiban. Atty. Chavez knows that he has won the vote of the Chief Justice
petition for review on certiorari to the Supreme Court, there is no need to implead
(6)
Chief Justice was on official leave. The remaining Members of the Division can
upholding the CIAC jurisdiction must have somehow been relayed to the Honorable
proceed with official business despite the absence of the Chief Justice as long as the
required majority is present. This is in accordance with Section 4(3), Article VIII of
the Constitution which provides that cases or matters heard by a division shall be
between the Chief Justice and Atty. Ordoez (or anyone representing him) about any
decided or resolved with the concurrence of a majority of the Members who actually
matter related to any case in this, or any other, court. Neither is the Chief Justice
took part in the deliberations on the issues in the case and voted thereon, and in no
aware of any alleged personal interest of Atty. Ordoez to uphold the CIAC.
(7)
(2)
from the judiciary. It is totally inconceivable that he will smear his eleven year
City, Branch 203 from continuing with any of the proceedings in Civil Case No. 03-
record of integrity, independence and ethical conduct in the Supreme Court with any
110 and from enforcing the Order of the trial court dated June 29, 2006 ordering the
action that is less than objective, impartial and neutral. On the other hand, he
assures movant (and all concerned) that he will continue with his vow to lead a
order. Respondents satisfactorily established that they are entitled to the injunction.
as Civil Case No. 03-110 praying that an accounting be rendered to determine the
cost of the materials purchased by respondent Papas; that respondents be ordered to
pay the cost of the additional works done on the property; that the Design-Build
Construction Agreement be ordered rescinded because respondents breach the same;
and that respondents be ordered to pay moral and exemplary damages. Based on the
same Design-Build Construction Agreement, respondents filed with the Construction
It is important to mention that in both cases, the parties insist that the other
ordered to finish the project or, in the alternative, to pay the cost to finish the same;
however argues that the Regional Trial Court properly took cognizance of the case
while respondents claim that CIAC has the exclusive and original jurisdiction on the
subject matter. Otherwise stated, if we rule in the instant case that CIAC has
jurisdiction over the controversy, then it would necessarily follow that the Regional
On June 8, 2005,[2] the CIAC rendered a decision on the merits of the case
Trial Court does not have jurisdiction. Since it did not acquire jurisdiction over the
controversy, then the writ of execution that it issued was void. If we allow the RTC
Judge and the Sheriff to continue with the proceedings in Civil Case No. 03-110,
then, whatever judgment that would be rendered in the instant case would be
Meanwhile, on July 29, 2005, the trial court rendered judgment in Civil
Case No. 03-110 in favor of petitioner ordering the respondents to pay P840,300.00
representing the cost of the additional works; P296,658.95 representing the balance
of the contract price; P500,000.00 by way of moral damages; P500,000.00 as
Thus on July 12, 2006, the Court issued a Resolution that reads:
Order dated May 17, 2006, Judge Sabundayo, Jr. directed Sheriff Melvin T.
Bagabaldo to implement the writ of execution by causing the respondents to render
an accounting of all the construction materials they bought for the construction of the
project x x x; to levy the goods and chattels of the [respondents] x x x and to make
the sale thereof x x x.[5]
In their Second Manifestation with Prayer for Issuance of a Temporary
Restraining Order/Injunction[6] filed with this Court on July 10, 2006, respondents
averred that from July 7, 2006 until 4 oclock in the morning of July 8, 2006, Sheriff
Bagabaldo went to the residence of respondent Papas and levied several of her
personal properties.[7] Respondents bewailed that despite the pronouncement of the
Court of Appeals that the CIAC, not the Regional Trial Court, which has jurisdiction
over the case, and despite the pendency of the instant case before us, the Regional
Trial Court still proceeded with the implementation of the writ.
(3)
(6)
There is no truth or basis to the allegation that the case has been given
the above resolution. Accordingly, on July 19, 2006, we issued a resolution which is
special attention. All actions on the motions and incidents have been performed
a clarification of the TRO issued on July 12, 2006. Both the July 12, 2006 and July
regularly.
19, 2006 Resolutions are covered by the same bond in the amount of P300,000.00.
WHEREFORE, the Motion to Inhibit the Honorable Chief Justice
(4)
[8]
petition should be dismissed or denied, or where the petition is given due course, the
Supreme Court may require or allow the filing of such pleadings, briefs, memoranda
SO ORDERED.
SECOND DIVISION
or documents asit may deem necessary within such periods and under such
conditions as it may consider appropriate, and impose the corresponding sanctions in
case of non-filing or unauthorized filing of such pleadings and documents or noncompliance with the conditions therefor.[9] This Court exercised its discretion when
it did not require petitioner to file comment on respondents Manifestation with
Present:
Urgent Motion to Resolve with Prayer for Injunction, Second Manifestation with
Prayer for Issuance of a Temporary Restraining Order/Injunction, Urgent Motion
YNARES-SANTIAGO,
(5)
The Court did not exceed its jurisdiction; neither did it encroach on
the jurisdiction of the Court of Appeals or of the lower court when it issued the
- versus -
VELASCO, JR.,
LEONARDO-DE CASTRO,
BRION, JJ.
demanded. It may further be said that the issuance of a TRO on July 12, 2006 is not
a final determination of the matter. It was a remedy intended to avoid any
irreparable injury that might be caused to the parties. It may be recalled that the
CIAC and the trial court each asserted its jurisdiction over the controversy to the
exclusion of the other.
Promulgated:
Respondents.
June 5, 2009
x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -x
DECISION
QUISUMBING, J.:
the
that failure to comply with its demand will result in its exercise of
This
petition
for
review
on
31,
certiorari
assails
2005 and
In
view
of
these,
respondents
filed
with
Development
Corporation
residential
lot
located
some
time,
house,
which
was
approved
in February
10,
2002. Thus,
Housing and Land Use Regulatory Board (HLURB) that has original
the
structure;
otherwise,
it
will
be
constrained
to
forfeit
Aggrieved, the respondents questioned the dismissal of their
29,
2003,
respondents,
as
of Appeals.
SO ORDERED.[8]
Respondents, on the other hand, counter that the case they
MLPAI filed a motion for reconsideration but it was denied by
the Court of Appeals in its Resolution dated February 13, 2006.
Hence, this petition raising the following issues:
I.
WHETHER THE HONORABLE COURT OF APPEALS HAS
DISREGARDED
LAWS
AND
WELL-SETTLED
JURISPRUDENCE IN HOLDING THAT JURISDICTION
OVER [THE] DISPUTE BETWEEN HOMEOWNERS AND
HOMEOWNERS ASSOCIATION LIES WITH THE
REGULAR COURTS AND NOT WITH HLURB.
II.
WHETHER THERE IS NO OTHER RELIEF AND REMEDY
AVAILABLE TO PETITIONER TO AVERT THE CONDUCT
OF A VOID [PROCEEDING] THAN THE PRESENT
RECOURSE.[9]
xxxx
(b) Controversies arising out of intra-corporate relations
between and among members of the association, between any or
all of them and the association of which they are members, and
between such association and the state/general public or other
entity in so far as it concerns its right to exist as a corporate entity.
[16]
(Emphasis supplied.)
xxxx
Moreover, by virtue of this amendatory law, the HIGC also assumed the SECs
original and exclusive jurisdiction under Section 5 of Presidential Decree No. 902-A
to hear and decide cases involving:
Later on, the above-mentioned powers and responsibilities, which had been
vested in the HIGC with respect to homeowners associations, were transferred to the
xxxx
Consequently,
HLURB.
in Sta.
Clara
Homeowners
Association
v.
Gaston[14] and Metro Properties, Inc. v. Magallanes Village Association, Inc.,[15] the
Court recognized HIGCs Revised Rules of Procedure in the Hearing of Home
Owners Disputes, pertinent portions of which are reproduced below:
RULE II
Disputes Triable by HIGC/Nature of Proceedings
Section 1. Types of Disputes The HIGC or any person,
officer, body, board or committee duly designated or created by it
shall have jurisdiction to hear and decide cases involving the
following:
The extent to which the HLURB has been vested with quasi-
[20]
which provides:
questions
regarding
subdivisions
and
condominiums. The
the
HLURB,
to
which
all
parties
aggrieved
in
the
cannot
be
made
to
depend
on
the
exclusive
[26]
While
articles of incorporation and its by-laws, they did not, however, raise
being imbued with public interest and welfare, any question arising
any legal ground to support its nullification. The legality of the by-
laws in its entirety was never an issue in the instant controversy but
annulment of contracts.
has jurisdiction over a case are the allegations in the complaint and
discretion
and
services
requiring
of
the
the
special
administrative
knowledge,
tribunal
to
will
not
suffice
much
less
satisfy
the
requirement
of
to close the doors of the courts against the parties, the courts
all disputes between them before a party can file the appropriate
backward.[35]
WHEREFORE,
the
instant
petition
is GRANTED.
The
Decision dated August 31, 2005 and Resolution dated February 13,
[33]
ASIDE.
The
Order
dated July
Branch
31,
2003 of
7,
is
SO ORDERED.
DECISION
THIRD DIVISION
CHICO-NAZARIO, J.:
FORT BONIFACIO DEVELOPMENT
CORPORATION,
Petitioner,
Present:
QUISUMBING, J.,
CARPIO,**
- versus -
CHICO-NAZARIO,
Acting Chairperson,
NACHURA, and
MANUEL N. DOMINGO,
PERALTA, JJ.
Respondent.
petitioner.
the said Contract, petitioner had the right to withhold the retention
portion of the contract price, set aside by the project owner, from
defect-liability period.[4]
money was not yet due and demandable and may be ascertained
new
contractor
on
the
condominium
Construction
Industry
Arbitration
Commission
(CIAC)
in
the petitioner.
164.
Before
respondents
claim
could
be
fully
addressed,
amount
of P5,990,227.77
belonging
to
LMM
Construction. In
Petitioner now comes to this Court via this instant Petition for
respondent.
Decision of the Court of Appeals and 6 June 2006 Order of the RTC
and, ultimately, for the dismissal of Civil Case No. 06-0200-CFM
pending before the RTC.
Appeals dismissed the Petition for Certiorari and affirmed the 6 June
2006 Order
of
the
RTC
denying
the
Motion
to
Dismiss
of
the rights of the other.[10] The right of the respondent that was
CFM.
separate
and
distinct
from
the
right
to
payment
of
LMM
amount,
LMM Construction
assigned to
respondent
its
from petitioner under the Trade Contract, merely stepped into the
under the Trade Contract is not even in dispute in Civil Case No. 06-
claim;
and
that,
uncertain
over
which
one
between
LMM
scrupulous
examination
of
the
aforementioned
violation
knowledge of construction.
of
the
terms
of
agreement;
interpretation
and/or
[12]
construction.
installation
of
components
and
equipment.
[13]
Petitioners
arbitration those cases, such as the one at bar, the extant facts of
SO ORDERED.
x-------------------------------------------------x
THIRD DIVISION
DECISION
HUTAMA-RSEA
INC.,
JOINT
OPERATIONS,
Petitioner,
Present:
Before Us is a Petition[1] for Review on Certiorari under Rule
45
YNARES-SANTIAGO,
Chairperson,
of
the
Rules
of
Court
seeking
to
set
aside
the
AUSTRIA-MARTINEZ,
- versus -
CHICO-NAZARIO,
NACHURA, and
PERALTA, JJ.
Petitioner HUTAMA-RSEA Joint Operations Incorporation and
respondent
Promulgated:
CITRA METRO
CORPORATION,
MANILA
TOLLWAYS
Metro
organized
Manila
and
Tollways
existing
Corporation
under
are
Philippine
corporations
Citra
respondent
petitioners final billing; (3) early completion bonus; and (4) interest
under
the
EPCC
to
pay
the
former
total
amount
of
US$369,510,304.00.[4]
the
demanding
dispute. Despite
payment
several
of
the
following:
meetings
and
(1)
the
continuous
Petitioner
finally
filed
with
the
Construction
Industry
prompting
enforce
petitioner
to
demand
that
respondent
pay
the
its
money
claims
against
In
its
Answer ad
cautelam with
Motion
to
Dismiss,
public use, and toll fees were accordingly collected. After informing
of
[6]
said
case
was
premature
because
condition
No. 17-2005 and to direct the parties to comply first with Clause
20.4 of the EPCC.[9]
dated 6
December
2005.[14] The
CIAC
issued,
on 12
dated
December
12,
2005
is
herebyANNULED and SET
ASIDE and,
instead,
[CIAC, members of the Arbitral Tribunal, [17] and herein
petitioner], their agents or anybody acting in their
behalf, are enjoined from further proceeding with
CIAC Case No. 17-2005, promulgating a decision
therein, executing the same if one has already been
promulgated or otherwise enforcing said order of
December 12, 2005 until the dispute has been
referred to and decided by the Dispute Adjudication
Board to be constituted by the parties in accordance
with Sub-Clause 20.4 of the Engineering Procurement
Construction Contract dated September 25, 1996.
EPCC. The appellate court, thus, found that the CIAC exceeded its
WHEREFORE,
the
instant
petition
is GRANTED and the order of the Arbitration Tribunal
of the Construction Industry Arbitration Commission
to arbitration.
(a)
incorporate
the
model
terms
published
by
the
Fdration
Internationale des Ingnieurs-Conseils
(FIDIC),
(b)
(c)
(d)
xxxx
20.3
include
reimbursement
for
reasonable
expenses, a daily fee in accordance with the
daily fee established from time to time for
arbitrators under the administrative and
financial regulations of the International
Centre for Settlement of Investment Disputes,
and a retainer fee per calendar month
equivalent to three times such daily fee.
The
Dispute
Adjudication
Boards
appointment may be terminated only by
mutual agreement of the Employer and the
Contractor. The Dispute Adjudication Boards
appointment shall expire when the discharge
referred to in Sub-Clause 13.12 shall have
become effective, or at such other time as the
parties may mutually agree.
(a)
(b)
(c)
(d)
20.4
binding upon
Contractor.
20.5
20.6
the
Employer
and
the
(a)
(b)
20.7
20.8
reference
to
different
arbitration
[21]
the
CIAC
with
rule
applies,
xxxx
should
the
construction
contract
contain
an
arbitration
clause.
or
condition
precedent. To
affirm
condition
WHEREFORE,
the
Petition
is
Respondent.
ASIDE. The
instant
case
is
x------------------------------------------------------------------------------------x
the
Decision
Rules
[1]
of
Court,
of
the
Court
of
Appeals
[2]
(CA)
dated May
Petitioner,
Present:
YNARES-SANTIAGO,
- versus -
Chairperson,
AUSTRIA-MARTINEZ,
CHICO-NAZARIO,
*
Promulgated:
e)
METAL WORKS trench grating, Ibeam separator, manhole cover, ladder rungs of
tanks, stair railings and stair nosing
f)
2.1.
The CONTRACTOR shall complete the
civil/structural and masonry works of the building
based on the works (sic) items covered by the
CONTRACTORs Proposal of Complete Supply and
Installation of Building Shell Wet Construction Works
as indicated in the plans and specifications at the
Contract Price and within the Contract time herein
stipulated and in accordance with the plans and
specifications. The CONTRACTOR shall furnish and
supply all necessary labor, equipment and tools,
supervision and other facilities needed and shall
perform everything necessary for the complete and
successful masonry works of the building described
hereof, provided that it pertains to or is part of the
above mentioned work or items covered by the
Contract documents.
2.2.
The scope of works as
hereunder but not limited to the following:
stated
a)
CONCRETE WORKS foundation and
footings, tie beams, walls, columns, beams, girders,
slabs, stairs, stair slabs, cement floor topping, ramps,
rubbed concrete.
b)
MASONRY WORKS interior and
exterior walls including stiffeners, CHB laying, interior
and exterior plastering, non-skid tile installation and
scratch coating for tile installation.
c)
FORMWORKS
d)
OTHER CONCRETE WORKS trenches,
platform for transformers, ger sets and aircons
MISCELLANEOUS WORK
installation of Doors and Jambs (metal
and wood)
Lintel Beams/Stiffener Columns
Installation
accessories
of
Hardwares
and
g)
MISCELLANEOUS ITEMS column
guard, wheel guard, waterstop, vapor barrier,
incidental embeds, floor hardener, dustproofer,
sealant, soil treatment, elevator block-outs for call
button, block-outs for electro-mechanical works and
concrete landing sills.
h)
ROOFING
WORKS
Steel
Trusses/Purlins, Rib Type pre-painted roofing sheets,
Insulation
i)
Garbage Chutes
2.3.
The work of the CONTRACTOR shall
include but not be limited to, preparing the bill of
materials, canvassing of prices, requisition of
materials for purchase by OWNER, following up of
orders, checking the quality and quantity of the
materials within the premises of the construction site
and returning defective materials.[6]
Respondent further agreed that the construction work would be
completed within 330 calendar days from Day 1, upon the
Construction
Managers
confirmation.[7] Petitioner
initially
when respondent entered the project site, it could not start work
due
to
the
on-going
bulk
excavation
by
another
25,
1997 was
proposed
as
Day
respectively. Instead
of
and P1,805,225.90,
occasions,
respondents
accommodations.[19]
requests
for
payroll
and
material
Request
for
Adjudication
[21]
with
the
1.
CIAC. Respondent
Retention Money
Unpaid Billings
Retention Money
WHEREFORE,
premises
considered,
the
Claimant-Contractor prays that this Honorable
Commission render judgment against RespondentOwner EMPIRE EAST LAND HOLDINGS, INC., ordering
said Respondents to pay the Claimant the amount of
PhP22,770,976.66 plus costs of suit, broken down as
follows
a.
PhP4,442,430.90 as unpaid
amount from the contract price;
b.
PhP3,153,733.60
as
the
amount remaining unpaid for
additional works;
c.
PhP13,976,427.00
overhead expenses; and
d.
PhP1,198,385.16
as
additional costs due to wage
escalation;
P4,502,886
(P1,607,627.65)
(6,110,514.29)
2
.
1,805,225
3.
Overhead Expenses
1,397,642
4.
308,226
P8,013,981
as
1.
P248,350
P248,350
claims
and
counterclaims
are
On the other hand, as the punch list was drawn after the joint
inspection by the parties, CIAC found for the petitioner and thus
awarded a total amount of P248,350.00[27]
I.
WHETHER OR NOT THE COURT OF APPEALS
COMMITTED REVERSIBLE ERROR WHEN IT ORDERED
THE RELEASE OF RETENTION MONEY IN FAVOR OF
CICG.
II.
WHETHER OR NOT THE COURT OF APPEALS
COMMITTED REVERSIBLE ERROR WHEN IT AWARDED
THE CLAIM OF CICG FOR THE EXCAVATION OF
FOUNDATION.
III
WHETHER OR NOT THE COURT OF APPEALS
COMMITTED REVERSIBLE ERROR WHEN IT AFFIRMED
CIACS AWARD FOR THE PAYMENT OF ALLEGED
OVERHEAD EXPENSES
works.[33] Undoubtedly,
as
will
be
discussed
hereunder,
of
work. However,
apart
from
the
completion
and
acceptance of all works, the following requisites were set as preconditions for the release of the retention money:
a)
b)
c)
IV.
WHETHER OR NOT THE COURT OF APPEALS
COMMITTED REVERSIBLE ERROR WHEN IT DENIED
EMPIRE EASTS CLAIM FOR MASONRY AND OTHER
WORKS, LIQUIDATED DAMAGES, AND COST OF
MONEY FOR PAYROLL ASSISTANCE AND MATERIALS
ACCOMMODATION.[31]
The petition is partly meritorious.
On the Release of Retention Money
failure to comply with the conditions for its release as set forth in
merely
the contract.
focused
on
the
non-issuance
of
the
certificate
of
thereof
was
just
ministerial
duty
of
petitioner
which the injured party is entitled to recover for the wrong done
we cannot apply the rule to conditions (a) and (c), which remain as
degree of certainty.[35]
release the retention money had not, as yet, arisen. We would like
to emphasize, though, that this is without prejudice to respondents
compliance with the unfulfilled conditions, after which, release of
the retention money must, perforce, follow.
the propriety of the award, both the CIAC and the CA were in a
its
factual
claim,
is
not
entitled
even
to
the
reduced
amount
in
nature. Significantly,
jurisprudence
teaches
that
Petitioners
Counterclaim
for
the
Cost
of
Unfinished Works
During the construction period, the parties mutually agreed
that some items of work be deleted from respondents scope of
work. Specifically, as claimed by respondent, the following were
deleted: a) masonry works and all related items from the 6 th floor
to the roof deck; b) all exterior masonry works from the 4 th floor to
the roof deck; and c) the garbage chute. This deletion was,
however, denied by petitioner. It, instead, claimed that the only
modification it approved was the reduction by three floors of the
total number of floors to be constructed by respondent.[40]
both parties, both the CIAC and the CA concluded that the
of excavation of foundation.
price
was
reduced
from P84
million
to P62,828,826.53. The
deletion
was,
likewise,
confirmed
by
thus,
petitioner
cannot
now
be
permitted
to
raise
anew
liquidated damages.
On
Petitioners
Counterclaim
for
the
Cost
of
due
the
respondent
for
the
cost
of
WHEREFORE,
premises
considered,
the
WORLD INTERACTIVE
NETWORK SYSTEMS (WINS)
JAPAN CO., LTD.,
Respondent.
petition
x--------------------------------------------------x
DECISION
Promulgated:
CORONA, J.:
to set aside the February 16, 2005 decision [1] and August 16, 2005 resolution [2] of the
Court of Appeals (CA) in CA-G.R. SP No. 81940.
On September 27, 1999, petitioner ABS-CBN Broadcasting Corporation
when
Systems (WINS) Japan Co., Ltd., a foreign corporation licensed under the laws of
respondent
shall
have
complied
with
the
conditions
aforesaid.
Japan. Under the agreement, respondent was granted the exclusive license to
distribute and sublicense the distribution of the television service known as The
Filipino Channel (TFC) in Japan. By virtue thereof, petitioner undertook to transmit
SO ORDERED.
ABS-CBN BROADCASTING
CORPORATION,
Petitioner,
-versus-
the TFC programming signals to respondent which the latter received through its
decoders and distributed to its subscribers.
Present:
PUNO, C.J., Chairperson,
SANDOVAL-GUTIERREZ,
CORONA,
AZCUNA and
LEONARDO-DE
CASTRO, JJ.
[3]
The arbitrator found in favor of respondent.[7] He held that petitioner gave its
respondent of its intention to terminate the agreement effective June 10, 2002.
written exchanges between the parties. He also ruled that, had there really been a
material breach of the agreement, petitioner should have terminated the same instead
3.
4.
xxx
xxx
with application for temporary restraining order and writ of preliminary injunction. It
was docketed as CA-G.R. SP No. 81940. It alleged serious errors of fact and law
and/or grave abuse of discretion amounting to lack or excess of jurisdiction on the
part of the arbitrator.
Respondent, on the other hand, filed a petition for confirmation of arbitral
award before the Regional Trial Court (RTC) of Quezon City, Branch 93, docketed
as Civil Case No. Q-04-51822.
Consequently, petitioner filed a supplemental petition in the CA seeking to
enjoin the RTC of Quezon City from further proceeding with the hearing of
respondent's petition for confirmation of arbitral award. After the petition was
Petitioner moved for reconsideration. The same was denied. Hence, this
admitted by the appellate court, the RTC of Quezon City issued an order holding in
petition.
abeyance any further action on respondent's petition as the assailed decision of the
arbitrator had already become the subject of an appeal in the CA. Respondent filed a
Petitioner contends that the CA, in effect, ruled that: (a) it should have first
motion for reconsideration but no resolution has been issued by the lower court to
filed a petition to vacate the award in the RTC and only in case of denial could it
date.[8]
elevate the matter to the CA via a petition for review under Rule 43 and (b) the
assailed decision implied that an aggrieved party to an arbitral award does not have
On February 16, 2005, the CA rendered the assailed decision dismissing ABSthe option of directly filing a petition for review under Rule 43 or a petition for
CBNs petition for lack of jurisdiction. It stated that as the TOR itself provided that
certiorari under Rule 65 with the CA even if the issues raised pertain to errors of fact
the arbitrator's decision shall be final and unappealable and that no motion for
and law or grave abuse of discretion, as the case may be, and not dependent upon
reconsideration shall be filed, then the petition for review must fail. It ruled that it is
such grounds as enumerated under Section 24 (petition to vacate an arbitral award)
the RTC which has jurisdiction over questions relating to arbitration. It held that the
of RA 876 (the Arbitration Law). Petitioner alleged serious error on the part of the
only instance it can exercise jurisdiction over an arbitral award is an appeal from the
CA.
trial court's decision confirming, vacating or modifying the arbitral award. It further
stated that a petition for certiorari under Rule 65 of the Rules of Court is proper in
arbitration cases only if the courts refuse or neglect to inquire into the facts of an
arbitration dispute may avail of, directly in the CA, a petition for review under Rule
43 or a petition for certiorari under Rule 65 of the Rules of Court, instead of filing a
petition to vacate the award in the RTC when the grounds invoked to overturn the
WHEREFORE,
the
instant
petition
is
hereby DISMISSED for lack of jurisdiction. The application for a
writ of injunction and temporary restraining order is
likewise DENIED. The Regional Trial Court of Quezon City
Branch 93 is directed to proceed with the trial for the Petition for
Confirmation of Arbitral Award.
SO ORDERED.
arbitrators decision are other than those for a petition to vacate an arbitral award
enumerated under RA 876.
RA 876 itself mandates that it is the Court of First Instance, now the RTC,
a statute means the elimination of others not specifically mentioned. As RA 876 did
which has jurisdiction over questions relating to arbitration, [9] such as a petition to
not expressly provide for errors of fact and/or law and grave abuse of discretion
(proper grounds for a petition for review under Rule 43 and a petition for certiorari
under Rule 65, respectively) as grounds for maintaining a petition to vacate an
Section 24 of RA 876 provides for the specific grounds for a petition to vacate
arbitral award in the RTC, it necessarily follows that a party may not avail of the
an award made by an arbitrator:
latter remedy on the grounds of errors of fact and/or law or grave abuse of discretion
filed in the RTC which is not based on the grounds enumerated in Section 24 of RA
876 should be dismissed. In that case, the trial court vacated the arbitral award
seemingly based on grounds included in Section 24 of RA 876 but a closer reading
thereof revealed otherwise. On appeal, the CA reversed the decision of the trial court
and affirmed the arbitral award. In affirming the CA, we held:
Based on the foregoing provisions, the law itself clearly provides that the
RTC must issue an order vacating an arbitral award only in any one of the . . .
cases
enumerated
therein.
Under
the
legal
maxim
in
statutory
construction expressio unius est exclusio alterius, the explicit mention of one thing in
xxx
xxx
xxx
xxx
quasi-judicial instrumentality and is, thus, within the ambit of Section 9 (3) of the
Judiciary Reorganization Act, as amended. Under this section, the Court of Appeals
This rule was cited in Sevilla Trading Company v. Semana,[13] Manila Midtown
shall exercise:
xxx
xxx
xxx
also be resorted to, we hold the same to be in accordance with the Constitution and
jurisprudence.
(2)
(3)
Time and again, we have ruled that the remedies of appeal and certiorari are
mutually exclusive and not alternative or successive.[20]
judicial recourse if either party disagrees with the whole or any part of the
Proper issues that may be raised in a petition for review under Rule 43 pertain
arbitrator's award may be availed of cannot be held to preclude in proper cases the
to errors of fact, law or mixed questions of fact and law. [21] While a petition for
power of judicial review which is inherent in courts.
[16]
[17]
and there is no
cannot be availed of where appeal is the proper remedy or as a substitute for a lapsed
presented by the parties. Therefore, the issues clearly fall under the classification of
In the case at bar, the questions raised by petitioner in its alternative
errors of fact and law questions which may be passed upon by the CA via a
petition before the CA were the following:
A. THE SOLE ARBITRATOR COMMITTED SERIOUS
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION IN
RULING THAT THE BROADCAST OF WINS WEEKLY WAS
DULY AUTHORIZED BY ABS-CBN.
B. THE SOLE ARBITRATOR COMMITTED SERIOUS
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION IN
RULING THAT THE UNAUTHORIZED BROADCAST DID
NOT CONSTITUTE MATERIAL BREACH OF THE
AGREEMENT.
C. THE SOLE ARBITRATOR COMMITTED SERIOUS
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION IN
RULING THAT WINS SEASONABLY CURED THE BREACH.
D. THE SOLE ARBITRATOR COMMITTED SERIOUS
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION IN
RULING THAT TEMPERATE DAMAGES IN THE AMOUNT
OF P1,166,955.00 MAY BE AWARDED TO WINS.
E. THE SOLE ARBITRATOR COMMITTED SERIOUS
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION IN
AWARDING ATTORNEY'S FEES IN THE UNREASONABLE
AMOUNT
AND
UNCONSCIONABLE
AMOUNT
OF P850,000.00.
F. THE ERROR COMMITTED BY THE SOLE
ARBITRATOR IS NOT A SIMPLE ERROR OF JUDGMENT OR
ABUSE OF DISCRETION. IT IS GRAVE ABUSE OF
DISCRETION TANTAMOUNT TO LACK OR EXCESS OF
JURISDICTION.
petition for review under Rule 43. Petitioner cleverly crafted its assignment of errors
in such a way as to straddle both judicial remedies, that is, by alleging serious errors
of fact and law (in which case a petition for review under Rule 43 would be proper)
and grave abuse of discretion (because of which a petition for certiorari under Rule
65 would be permissible).
It must be emphasized that every lawyer should be familiar with the
distinctions between the two remedies for it is not the duty of the courts to determine
under which rule the petition should fall.[24] Petitioner's ploy was fatal to its
cause. An appeal taken either to this Court or the CA by the
wrong
inappropriate mode shall be dismissed. [25] Thus, the alternative petition filed in the
CA, being an inappropriate mode of appeal, should have been dismissed outright by
the CA.
WHEREFORE, the petition is hereby DENIED. The February 16, 2005
decision and August 16, 2005 resolution of the Court of Appeals in CA-G.R. SP No.
81940 directing the Regional Trial Court of Quezon City, Branch 93 to proceed with
the trial of the petition for confirmation of arbitral award is AFFIRMED.
A careful reading of the assigned errors reveals that the real issues calling for
the CA's resolution were less the alleged grave abuse of discretion exercised by the
arbitrator and more about the arbitrators appreciation of the issues and evidence
or
the Decision dated December 14, 2001 of the Arbitral Tribunal of the Construction
Industry Arbitration Commission (CIAC) in CIAC Case No. 18-2001, while the CA
Resolution granted in part the motion of Diesel for reconsideration and denied a
similar motion of UPSI.
- versus -
The Facts
The facts, as found in the CA Decision under review, are as follows:
On August 26, 1995, Diesel, as Contractor, and UPSI, as Owner, entered into a
Construction Agreement[3] (Agreement) for the interior architectural construction
works for the 14th to 16th floors of the UPSI Building 3 Meditel/Condotel Project
(Project) located on Gen. Luna St., Ermita, Manila. Under the Agreement, as
amended, Diesel, for PhP 12,739,099, agreed to undertake the Project, payable by
progress billing.[4] As stipulated, Diesel posted, through FGU Insurance Corp.
(FGU), a performance bond in favor of UPSI.[5]
Inter alia, the Agreement contained provisions on contract works and Project
completion, extensions of contract period, change/extra works orders, delays, and
damages for negative slippage.
Tasked to oversee Diesels work progress were: Grace S. Reyes Designs, Inc.
The Case
for interior design and architecture, D.L. Varias and Associates as Construction
Manager, and Ryder Hunt Loacor, Inc. as Quantity Surveyor.[6]
Before the Court are these petitions for review under Rule 45 separately
interposed by Diesel Construction Co., Inc. (Diesel) and UPSI Property Holdings,
Under the Agreement, the Project prosecution proper was to start on August 2,
Inc. (UPSI) to set aside the Decision [1] dated April 16, 2002 as partly modified in a
1999, to run for a period of 90 days or until November 8, 1999. The parties later
Resolution[2] of August 21, 2002, both rendered by the Court of Appeals (CA) in
Construction Co., Inc., and FGU Insurance Corporation. The CA Decision modified
1999.
and for a declaration that the deductions it made for liquidated damages were
proper. UPSI also sought payment of attorneys fees.[11]
equivalent to one-fifth (1/5) of one (1) percent of the total Project cost for each
calendar day of delay.[7]
In the course of the Project implementation, change orders were effected and
judgment for Diesel, albeit for an amount lesser than its original demand. To be
extensions sought. At one time or another, Diesel requested for extension owing to
precise, the CIAC ordered UPSI to pay Diesel the total amount of PhP 4,027,861.60,
the following causes or delaying factors: (1) manual hauling of materials from the
broken down as follows: PhP 3,661,692.60, representing the unpaid balance of the
14th to 16th floors; (2) delayed supply of marble; (3) various change orders; and (4)
contract price; and PhP 366,169 as attorneys fees. In the same decision, the CIAC
work. And for every default situation, UPSI assessed Diesel for liquidated damages
SP No. 68340. Eventually, the appellate court rendered its assailed Decision
Agreement.[9]
Apparently irked by and excepting from the actions taken by UPSI, Diesel,
thru its Project manager, sent, on March 16, 2000, a letter notice to UPSI stating that
the Project has been completed as of that date. UPSI, however, disregarded the
notice, and refused to accept delivery of the contracted premises, claiming that
Diesel had abandoned the Project unfinished. Apart therefrom, UPSI withheld
Diesels 10% retention money and refused to pay the unpaid balance of the
contract price.[10]
It is upon the foregoing factual backdrop that Diesel filed a complaint
before the CIAC, praying that UPSI be compelled to pay the unpaid balance of the
contract price, plus damages and attorneys fees. In an answer with counterclaim,
UPSI denied liability, accused Diesel of abandoning a project yet to be finished, and
prayed for repayment of expenses it allegedly incurred for completing the Project
1.
2.
3.
[15]
[16]
On the other hand, in G.R. No. 154937, UPSI presents the following issues:
I
Whether or not portion of the Decision dated April 16, 2002 of the
Honorable [CA] denying additional expenses to complete the
unfinished and abandoned work of [Diesel], is null and void for
being contrary to clean and convincing evidence on record.
II
Whether or not portion of the Decision x x x of the [CA]
finding delay of only forty five (45) days is null and void for
being not in accord with contractual stipulations upon which the
controversy arise.
III
Whether or not the resolution of the Honorable Court of Appeals
denying the herein petitioners motion for reconsideration and
partially granting the respondents motion for reconsideration is
likewise null and void as it does not serve its purpose for being
more on expounding than rectifying errors.[17]
The issues shall be discussed in seriatim.
In its petition in G.R. No. 154885, Diesel raises the following issues:
The Courts Ruling
The question of whether or not the findings of fact of the CIAC are
supported by substantial evidence has no causal connection to the personal
position that the factual findings of the CIAC are binding on and concludes the
undergraduate or postgraduate degrees, as the case may be, can hardly be invoked as
appellate court. The CA went to clarify, however, that the general rule is that factual
the sole, fool proof basis to determine that persons qualification to hold a certain
conclusions of highly specialized bodies are given great weight and even finality
position. Ones work experiences and attendance in relevant seminars and trainings
when supported by substantial evidence. Given this perspective, the CA was correct
in holding that it may validly review and even overturn such conclusion of facts
certain undertaking.
when the matter of its being adequately supported by substantial evidence duly
adduced on record comes to the fore and is raised as an issue.
the necessary technical expertise in their line of authority. In other words, the
underlying our Administrative Law is that courts of justice should respect the
members of the Arbitral Tribunal of the CIAC have in their favor the presumption of
whose favor the legal presumption exists may rely on and invoke such legal
insubstantial.
[18]
There can be no serious dispute about the correctness of the CAs above
posture. However, what the appellate court stated later to belabor its point strikes the
Court as specious and uncalled for. Wrote the CA:
presumption to establish a fact in issue. One need not introduce evidence to prove
that the fact for a presumption is prima facie proof of the fact presumed.[20]
To set the records straight, however, the CA did not cast aspersion on the
competence let alone the bona fides of the members of the Arbitral Tribunal to
arbitrate. In context, what the appellate court saidin reaction to Diesels negative
commentary about the CAs expertise on construction mattersis that the said
The CIAC found Diesel not to have incurred delay, thus negating UPSIs
members do not really enjoy a special advantage over the members of the CA in
entitlement to liquidated damages. The CA, on the other hand, found Diesel to have
In any event, the fact remains that the CA stands justified in reviewing the
CIAC decision.
In determining whether or not Diesel was in delay, the CIAC and CA first
turned on the question of Diesels claimed entitlement to have the Project period
extended, an excusable delay being chargeable against the threshold 90-day
completion period. Both were one in saying that occurrence of certain events gave
Diesel the right to an extension, but differed on the matter of length of the extension,
and on the nature of the delay, that is, whether the delay is excusable or not. The CA
deemed the delay, and the resulting extension of 14 days, arising from the manual
Diesel submits that the CA, in reaching its decision, substituted its own
conjectural opinion to that of the CIACs well-grounded findings and award.
hauling of materials, as undeserved. But the CIAC saw it otherwise for the reason
that Frederick W. Crespillo, the witness UPSI presented to refute the allegation of
Diesels entitlement to time extension for the manual hauling of materials, was
UPSI, instead of on Diesel, to prove that the delay in the execution of the Project was
from PhP 3,661,692.60, as earlier fixed by the CIAC, to PhP 2,441,482.64, although
excusable. Diesel explained that there was no place for its own hoisting machine at
it would consider the reduction and revert to the original CIAC figure. Unlike the
the Project site as the assigned location was being used by the General Contractor,
CIAC which found the award of liquidated damages to be without basis, the CA was
while the alternative location was not feasible due to power constraint. Moreover,
of a different disposition and awarded UPSI PhP 1,309,500, only to reduce the same
Diesel could not use the site elevator of the General Contractor as its personnel were
to PhP 1,146,519 in its assailed resolution. Also, the CA struck out the CIAC award
only permitted to use the same for one hour every day at PhP 600 per hour.
of PhP 366,169 to Diesel for attorneys fees. Additionally, the CIACs ruling making
UPSI alone liable for the costs of arbitration was modified by the CA, which directed
UPSI and Diesel to equally share the burden.
The provisions in the Agreement on excusable delays read:
2.3
Excusable delays: The Contractor shall inform the
owner in a timely manner, of any delay caused by the following:
extension. Thus, the CA excluded the delay caused thereby and only allowed Diesel
a total extension period of 85 days. Such extension, according to that court,
effectively translated to a delay of 45 days in the completion of the project. The CA,
in its assailed decision, explained why:
7. All told, We find, and so hold, that [Diesel] has
incurred in delay. x x x However, under the circumstances wherein
UPSI was responsible for some of the delay, it would be most
unfair to charge Diesel with two hundred and forty (240) days of
delay, so much so that it would still owe UPSI, even after
liquidated damages have eaten up the retention and unpaid balance,
the amount of [P4,340,000.00]. Thus, based on Our own
calculations, We deem it more in accord with the spirit of the
contract, as amended, x x x to assess Diesel with an unjustifiable
delay of forty-five (45) days only; hence, at the rate of 1/5 of one
percent as stated in the contract, [or at P1,309,500.00], which
should be deducted from the total unpaid balance of
[P2,441,482.64], which amount already includes the retention on
the additional works or Change Orders.[23]
The CA, in its questioned resolution, expounded on how it arrived at the
figure of 45-day delay in this wise:
7. x x x We likewise cannot give Our assent to the
asseveration of [Diesel] that Our calculations as to the number of
days of delay have no basis. For indeed, the same was arrived at
after taking a holistic view of the entire circumstances attendant to
the instant case. x x x
But prescinding from the above, the basis for Our ruling
should not be hard to discern. To disabuse the mind of [Diesel] that
the forty-five day delay was plucked from out of the blue, allow Us
to let the records speak. The records will show that while the
original target date for the completion x x x was 19 November
1999 x x x, there is a total of eighty-five (85) days of extension
which are justifiable and sanctioned by [UPSI], to wit: thirty (30)
days as authorized on 27 January 2000 by UPSIs Construction
Manager x x x; thirty (30) days as again consented to by the same
Construction Manager on 24 February 2000 x x x; and twenty-five
(25) days on 16 March 2000 by Rider Hunt and Liacom x x x. The
rest of the days claimed by Diesel were, of course, found by Us to
be unjustified in the main opinion. Hence, the project should have
The CIAC found that the COs were actually implemented on the following
dates:
CO No. 1 February 9 to March 3, 2000
CO No. 3 February 24 to March 10, 2000
CO No. 4 March 16 to April 7, 2000[27]
Dieselthe directives effectively extending the Project completion time at the behest
of UPSI.
Hence, as correctly held by the CIAC, UPSI, no less, effectively moved the
Section V of the Agreement on the subject Change Orders reads:
V. CHANGES IN SCOPE OF WORK AND EXTRA
WORK
ending March 22, 2000, Diesels scope of work, as of that date, was already 97.56%
considered as substantial to warrant full payment of the contract amount, less actual
damages suffered by UPSI. Article 1234 of the Civil Code says as much, If the
obligation had been substantially performed in good faith, the obligor may recover as
though there had been a strict and complete fulfillment, less damages suffered by the
obligee.
The fact that the laborers of Diesel were still at the work site as of March
22, 2000 is a reflection of its honest intention to keep its part of the bargain and
complete the Project. Thus, when Diesel attempted to turn over the premises to
UPSI, claiming it had completed the Project on March 15, 2000, Diesel could no
longer be considered to be in delay. Likewise, the CIAC cited the Uniform General
Conditions of Contract for Private Construction (CIAP Document 102), wherein it is
And for the same reason justifying the award of attorneys fees, arbitration
costs ought to be charged against UPSI, too.
stated that no liquidated damages for delay beyond the completion time shall accrue
after the date of substantial completion of the work.[29]
In all, Diesel cannot be considered as in delay and, hence, is not amenable
under the Agreement for liquidated damages.
As to the issue of attorneys fees, Diesel insists that bad faith tainted UPSIs
act of imposing liquidated damages on account of its (Diesels) alleged delay. And,
this prompted Diesel to file its petition for arbitration. Thus, the CIAC granted
Diesel an award of PhP 366,169 as attorneys fees. However, the CA reversed the
Fourth Issue
UPSI urges a review of the factual basis for the parallel denial by the CIAC
and CA of its claim for additional expenses to complete the Project. UPSI states that
the reality of Diesel having abandoned the Project before its agreed completion is
supported by clear and convincing evidence.
CIAC on the award, it being its finding that Diesel was in delay.
The Court cannot accord the desired review. It is settled rule that the Court,
The Court resolves to reinstate the CIACs award of attorneys fees, there
being sufficient justification for this kind of disposition. As earlier discussed, Diesel
was not strictly in delay in the completion of the Project. No valid reason, therefore,
obtains for UPSI to withhold the retention money or to refuse to pay the unpaid
balance of the contract price. Indeed, the retention and nonpayment were, to us, as
was to the CIAC, resorted to by UPSI out of whim, thus forcing the hand of Diesel to
sue to recover what is rightfully due. Thus, the grant of attorneys fees would be
justifiable under Art. 2208 of the Civil Code, thus:
Article 2208. In the absence of stipulation, attorneys fees
and expenses of litigation x x x cannot be recovered, except:
xxxx
(5) Where the defendant acted in gross and evident bad
faith in refusing to satisfy the plaintiffs plainly valid, just and
demandable claim.
not being a trier of facts, is under no obligation to examine, winnow, and weigh anew
evidence adduced below. This general rule is, of course, not absolute. In Superlines
Transportation Company, Inc. v. Philippine National Construction Company, the
Court enumerated the recognized exceptions to be:
x x x (1) when the findings are grounded entirely on
speculation, surmises or conjectures; (2) when the inference made
is manifestly mistaken, absurd or impossible; (3) when there is
grave abuse of discretion; (4) when the judgment is based on a
misapprehension of facts; (5) when the findings of facts are
conflicting; (6) when in making its findings the [CA] went beyond
the issues of the case, or its findings are contrary to the admissions
of both the appellant and the appellee; (7) when the findings are
contrary to the trial court; (8) when the findings are conclusions
without citation of specific evidence on which they are based; (9)
when the facts set forth in the petition as well as in the petitioners
main and reply briefs are not disputed by the respondent; (10)
when the findings of fact are premised on the supposed absence of
evidence and contradicted by the evidence on record; and
6.
Neither are We prepared to sustain UPSIs
argument that Diesel left the work unfinished and pulled-out all of
its workmen from the project. This claim is belied by the
assessment of its own Construction Manager in Progress Report
No. 19 for the period ending 22 March 2000, wherein it was
plaintly stated that as of that period, with respect to Diesel, there
were still twenty-three laborers on site with the project 97.56%
complete x x x. This indicates that the contracted works of Diesel
were substantially completed with only minor corrections x x
x, thus contradicting the avowal of UPSI that the work was
abandoned in such a state that necessitated the engagement of
another contractor for the project to be finished. It was therefore
not right for UPSI to have declined the turn-over and refused the
full payment of the contract price, x x x.[32]
WHEREFORE,
Diesels
petition
UPSIs Petition is DENIED with qualification. The assailed Decision dated April 16,
2002 and Resolution dated August 21, 2002 of the CA are MODIFIED, as follows:
(1)
(2)
The award to Diesel for the unpaid balance of the contract price of
UPSI shall pay the costs of arbitration before the CIAC in the amount
of PhP 298,406.03;
Given the 97.56% work accomplishment tendered by Diesel, UPSIs theory
of abandonment and of its having spent a sum to complete the work must fall on its
(4) Diesel is awarded attorneys fees in the amount of PhP 366,169; and
DECISION
(5) UPSI is awarded damages in the amount of PhP 310,834.01, the same to
be deducted from the retention money, if there still be any, and, if necessary, from the
VELASCO, JR., J.:
3,717,027.64. From this amount shall be deducted the award of actual damages of
PhP 310,834.01 to UPSI which shall pay the costs of arbitration in the amount of PhP
mediation, conciliation, and negotiation, being inexpensive, speedy and less hostile
298,406.03.
methods have long been favored by this Court. The petition before us puts at issue
In
summary,
the
aggregate
award
to
Diesel
shall
be
an arbitration clause in a contract mutually agreed upon by the parties stipulating that
they would submit themselves to arbitration in a foreign country. Regrettably,
instead of hastening the resolution of their dispute, the parties wittingly or
unwittingly prolonged the controversy.
FGU is released from liability for the performance bond that it issued in
Petitioner Korea Technologies Co., Ltd. (KOGIES) is a Korean corporation
favor of Diesel.
which is engaged in the supply and installation of Liquefied Petroleum Gas (LPG)
Cylinder manufacturing plants, while private respondent Pacific General Steel
No costs.
KOGIES
Present:
- versus -
would
set
up
an
LPG
Cylinder
Manufacturing
Plant
in
Carmona, Cavite. The contract was executed in the Philippines. On April 7, 1997,
the parties executed, in Korea, an Amendment for Contract No. KLP-970301
dated March 5, 1997[2] amending the terms of payment. The contract and its
amendment stipulated that KOGIES will ship the machinery and facilities necessary
for manufacturing LPG cylinders for which PGSMC would pay USD
1,224,000. KOGIES would install and initiate the operation of the plant for which
PGSMC bound itself to pay USD 306,000 upon the plants production of the 11-kg.
LPG cylinder samples. Thus, the total contract price amounted to USD 1,530,000.
On October 14, 1997, PGSMC entered into a Contract of Lease [3] with
On May 14, 1998, PGSMC replied that the two checks it issued KOGIES
Worth Properties, Inc. (Worth) for use of Worths 5,079-square meter property with a
were fully funded but the payments were stopped for reasons previously made
4,032-square meter warehouse building to house the LPG manufacturing plant. The
known to KOGIES.[7]
monthly rental was PhP 322,560 commencing on January 1, 1998 with a 10% annual
increment clause. Subsequently, the machineries, equipment, and facilities for the
manufacture of LPG cylinders were shipped, delivered, and installed in the Carmona
their Contract dated March 5, 1997 on the ground that KOGIES had altered the
quantity and lowered the quality of the machineries and equipment it delivered to
PGSMC, and that PGSMC would dismantle and transfer the machineries, equipment,
[4]
and facilities installed in the Carmona plant. Five days later, PGSMC filed before
22, 1998, after the installation of the plant, the initial operation could not be
I.S. No. 98-03813 against Mr. Dae Hyun Kang, President of KOGIES.
materials, thus forcing the parties to agree that KOGIES would be deemed to have
completely complied with the terms and conditions of the March 5, 1997 contract.
On June 15, 1998, KOGIES wrote PGSMC informing the latter that
PGSMC could not unilaterally rescind their contract nor dismantle and transfer the
For the remaining balance of USD306,000 for the installation and initial
operation of the plant, PGSMC issued two postdated checks: (1) BPI Check No.
insisted that their disputes should be settled by arbitration as agreed upon in Article
0316412 dated January 30, 1998 for PhP 4,500,000; and (2) BPI Check No.
its June 1, 1998 letter threatening that the machineries, equipment, and facilities
installed in the plant would be dismantled and transferred on July 4, 1998. Thus,
PGSMC threatening criminal action for violation of Batas Pambansa Blg. 22 in case
on July 1, 1998, KOGIES instituted an Application for Arbitration before the Korean
of nonpayment. On the same date, the wife of PGSMCs President faxed a letter
dated May
Contract as amended.
7,
1998to
KOGIES
President
who
was
then
staying
at
a Makati City hotel. She complained that not only did KOGIES deliver a different
brand of hydraulic press from that agreed upon but it had not delivered several
equipment parts already paid for.
were stopped were not funded but later on claimed that it stopped payment of the
reasoning that PGSMC had paid KOGIES USD 1,224,000, the value of the
checks for the reason that their value was not received as the former allegedly
machineries and equipment as shown in the contract such that KOGIES no longer
breached their contract by altering the quantity and lowering the quality of the
had proprietary rights over them. And finally, the RTC held that Art. 15 of the
machinery and equipment installed in the plant and failed to make the plant
Contract as amended was invalid as it tended to oust the trial court or any other court
jurisdiction over any dispute that may arise between the parties. KOGIES prayer for
1998 Certificate. Likewise, KOGIES averred that PGSMC violated Art. 15 of their
an injunctive writ was denied.[10] The dispositive portion of the Order stated:
transferring the machinery and equipment installed in the plant which the latter
threatened to do on July 4, 1998.
On July 9, 1998, PGSMC filed an opposition to the TRO arguing that
KOGIES was not entitled to the TRO since Art. 15, the arbitration clause, was null
and void for being against public policy as it ousts the local courts of jurisdiction
over the instant controversy.
On July 29, 1998, KOGIES filed its Reply to Answer and Answer to
Counterclaim.[11] KOGIES denied it had altered the quantity and lowered the quality
of the machinery, equipment, and facilities it delivered to the plant. It claimed that it
Counterclaim asserting that it had the full right to dismantle and transfer the
had performed all the undertakings under the contract and had already produced
machineries and equipment because it had paid for them in full as stipulated in the
certified samples of LPG cylinders. It averred that whatever was unfinished was
contract; that KOGIES was not entitled to the PhP 9,000,000 covered by the checks
for failing to completely install and make the plant operational; and that KOGIES
was liable for damages amounting to PhP 4,500,000 for altering the quantity and
[12]
lowering the quality of the machineries and equipment. Moreover, PGSMC averred
that it has already paid PhP 2,257,920 in rent (covering January to July 1998) to
Worth and it was not willing to further shoulder the cost of renting the premises of
the plant considering that the LPG cylinder manufacturing plant never became
operational.
for Reconsideration[14] of the July 23, 1998 Order denying its application for
an injunctive writ claiming that the contract was not merely for machinery and
After the parties submitted their Memoranda, on July 23, 1998, the RTC
issued an Order denying the application for a writ of preliminary injunction,
facilities worth USD 1,224,000 but was for the sale of an LPG manufacturing plant
technology for a total contract price of USD 1,530,000 such that the dismantling
injunction to enjoin the RTC and PGSMC from inspecting, dismantling, and
and transfer of the machinery and facilities would result in the dismantling and
transferring the machineries and equipment in the Carmona plant, and to direct the
transfer of the very plant itself to the great prejudice of KOGIES as the still unpaid
owner/seller of the plant. Moreover, KOGIES points out that the arbitration clause
under Art. 15 of the Contract as amended was a valid arbitration stipulation under
In the meantime, on October 19, 1998, the RTC denied KOGIES urgent
Art. 2044 of the Civil Code and as held by this Court in Chung Fu Industries
motion for reconsideration and directed the Branch Sheriff to proceed with the
(Phils.), Inc.[15]
inspection of the machineries and equipment in the plant on October 28, 1998.[19]
determine whether there was indeed alteration of the quantity and lowering of quality
No. 49249 informing the CA about the October 19, 1998 RTC Order. It also
of
properly
reiterated its prayer for the issuance of the writs of prohibition, mandamus and
installed. KOGIES opposed the motion positing that the queries and issues raised in
preliminary injunction which was not acted upon by the CA. KOGIES asserted that
the motion for inspection fell under the coverage of the arbitration clause in their
the Branch Sheriff did not have the technical expertise to ascertain whether or not the
contract.
machineries and equipment conformed to the specifications in the contract and were
the
machineries
and
equipment,
and
whether
these
were
properly installed.
On September 21, 1998, the trial court issued an Order (1) granting
PGSMCs motion for inspection; (2) denying KOGIES motion for reconsideration
On November
[21]
of the July 23, 1998 RTC Order; and (3) denying KOGIES motion to dismiss
Report
properly installed.
11,
1998,
the
Branch
Sheriff filed
his
Sheriffs
finding that the enumerated machineries and equipment were not fully and
of compulsory counterclaims.
The Court of Appeals affirmed the trial court and declared
the arbitration clause against public policy
On
October
2,
1998,
KOGIES
filed
an
Urgent
Motion
for
Reconsideration[17] of the September 21, 1998 RTC Order granting inspection of the
plant and denying dismissal of PGSMCs compulsory counterclaims.
Ten days after, on October 12, 1998, without waiting for the resolution of its
October 2, 1998 urgent motion for reconsideration, KOGIES filed before the Court
of Appeals (CA) a petition for certiorari [18] docketed as CA-G.R. SP No. 49249,
seeking annulment of the July 23, 1998 and September 21, 1998 RTC Orders and
On May 30, 2000, the CA rendered the assailed Decision[22] affirming the
RTC Orders and dismissing the petition for certiorari filed by KOGIES. The CA
found that the RTC did not gravely abuse its discretion in issuing the assailed July
23, 1998 and September 21, 1998 Orders. Moreover, the CA reasoned that KOGIES
contention that the total contract price for USD 1,530,000 was for the whole plant
and had not been fully paid was contrary to the finding of the RTC that PGSMC fully
paid the price of USD 1,224,000, which was for all the machineries and
equipment. According to the CA, this determination by the RTC was a factual
finding beyond the ambit of a petition for certiorari.
On the issue of the validity of the arbitration clause, the CA agreed with the
lower court that an arbitration clause which provided for a final determination of the
legal rights of the parties to the contract by arbitration was against public policy.
On the issue of nonpayment of docket fees and non-attachment of a
certificate of non-forum shopping by PGSMC, the CA held that the counterclaims of
PGSMC were compulsory ones and payment of docket fees was not required since
the Answer with counterclaim was not an initiatory pleading. For the same reason,
the CA said a certificate of non-forum shopping was also not required.
Furthermore, the CA held that the petition for certiorari had been filed
prematurely since KOGIES did not wait for the resolution of its urgent motion for
reconsideration of the September 21, 1998 RTC Order which was the plain, speedy,
and adequate remedy available. According to the CA, the RTC must be given the
opportunity to correct any alleged error it has committed, and that since the assailed
orders were interlocutory, these cannot be the subject of a petition for certiorari.
Hence, we have this Petition for Review on Certiorari under Rule 45.
The Issues
Petitioner posits that the appellate court committed the following errors:
a.
PRONOUNCING THE QUESTION OF OWNERSHIP
OVER THE MACHINERY AND FACILITIES AS A
QUESTION OF FACT BEYOND THE AMBIT OF A
PETITION FOR CERTIORARI INTENDED ONLY FOR
CORRECTION OF ERRORS OF JURISDICTION OR GRAVE
ABUSE OF DISCRETION AMOUNTING TO LACK OF (SIC)
order
of
the
trial
court.[26] The
CA
erred
on
its
reliance
should have paid docket fees and filed a certificate of non-forum shopping, and that
which was not assailable in an action for certiorari since the denial of a motion to
quash required the accused to plead and to continue with the trial, and whatever
objections the accused had in his motion to quash can then be used as part of his
defense and subsequently can be raised as errors on his appeal if the judgment of the
trial court is adverse to him. The general rule is that interlocutory orders cannot be
in its Answer with Compulsory Counterclaim dated July 17, 1998 in accordance with
Section 8 of Rule 11, 1997 Revised Rules of Civil Procedure, the rule that was
Corporation, we held:
effective at the time the Answer with Counterclaim was filed. Sec. 8 on existing
The proper remedy in such cases is an ordinary appeal
from an adverse judgment on the merits, incorporating in said
appeal the grounds for assailing the interlocutory orders. Allowing
appeals from interlocutory orders would result in the sorry
spectacle of a case being subject of a counterproductive pingpong to and from the appellate court as often as a trial court is
perceived to have made an error in any of its interlocutory
rulings. However, where the assailed interlocutory order was
issued with grave abuse of discretion or patently erroneous and the
remedy of appeal would not afford adequate and expeditious relief,
the Court allows certiorari as a mode of redress.[28]
On July 17, 1998, at the time PGSMC filed its Answer incorporating its
counterclaims against KOGIES, it was not liable to pay filing fees for said
counterclaims being compulsory in nature. We stress, however, that effective August
16, 2004 under Sec. 7, Rule 141, as amended by A.M. No. 04-2-04-SC, docket fees
are now required to be paid in compulsory counterclaim or cross-claims.
endless occasions for dilatory motions. Thus, where the interlocutory order was
[24]
remedy is certiorari.[29]
responsive pleading, hence, the courts a quo did not commit reversible error in
denying KOGIES motion to dismiss PGSMCs compulsory counterclaims.
that there is no plain, speedy, and adequate remedy in the ordinary course of law
amply provides the basis for allowing the resort to a petition for certiorari under Rule
[25]
65.
We now go to the core issue of the validity of Art. 15 of the Contract, the
arbitration clause. It provides:
the petition for certiorari. Note that KOGIES motion for reconsideration of the July
23, 1998 RTC Order which denied the issuance of the injunctive writ had already
been denied. Thus, KOGIES only remedy was to assail the RTCs interlocutory
order via a petition for certiorari under Rule 65.
While the October 2, 1998 motion for reconsideration of KOGIES of the
September 21, 1998 RTC Order relating to the inspection of things, and the
allowance of the compulsory counterclaims has not yet been resolved, the
circumstances in this case would allow an exception to the rule that before certiorari
Petitioner claims the RTC and the CA erred in ruling that the arbitration
clause is null and void.
may be availed of, the petitioner must have filed a motion for reconsideration and
Petitioner is correct.
said motion should have been first resolved by the court a quo. The reason behind
the rule is to enable the lower court, in the first instance, to pass upon and correct its
mistakes without the intervention of the higher court.[30]
The September 21, 1998 RTC Order directing the branch sheriff to inspect
the plant, equipment, and facilities when he is not competent and knowledgeable on
said matters is evidently flawed and devoid of any legal support. Moreover, there is
an urgent necessity to resolve the issue on the dismantling of the facilities and any
further delay would prejudice the interests of KOGIES. Indeed, there is real and
Established in this jurisdiction is the rule that the law of the place where the
contract is made governs. Lex loci contractus. The contract in this case was
perfected here in the Philippines. Therefore, our laws ought to govern. Nonetheless,
Art. 2044 of the Civil Code sanctions the validity of mutually agreed arbitral clause
or the finality and binding effect of an arbitral award. Art. 2044 provides, Any
stipulation that the arbitrators award or decision shall be final, is valid, without
prejudice to Articles 2038, 2039 and 2040. (Emphasis supplied.)
may be voided, rescinded, or annulled, but these would not denigrate the finality
customs, public order, or public policy. There has been no showing that the parties
have not dealt with each other on equal footing. We find no reason why the
arbitration clause should not be respected and complied with by both
[35]
is a contract and that a clause in a contract providing that all matters in dispute
between the parties shall be referred to arbitration is a contract. [36] Again in Del
Monte Corporation-USA v. Court of Appeals, we likewise ruled that [t]he provision
to submit to arbitration any dispute arising therefrom and the relationship of the
parties is part of that contract and is itself a contract.[37]
Having said that the instant arbitration clause is not against public policy,
we come to the question on what governs an arbitration clause specifying that in case
of any dispute arising from the contract, an arbitral panel will be constituted in a
foreign country and the arbitration rules of the foreign country would govern and its
The arbitration clause which stipulates that the arbitration must be done
in Seoul, Korea in accordance with the Commercial Arbitration Rules of the KCAB,
and that the arbitral award is final and binding, is not contrary to public policy. This
Court has sanctioned the validity of arbitration clauses in a catena of cases. In the
1957 case ofEastboard Navigation Ltd. v. Juan Ysmael and Co., Inc.,[38] this Court
had occasion to rule that an arbitration clause to resolve differences and breaches of
arbitrate disputes arising from contractual relations. In case a foreign arbitral body is
chosen by the parties, the arbitration rules of our domestic arbitration bodies would
we held that [i]n this jurisdiction, arbitration has been held valid and
not be applied. As signatory to the Arbitration Rules of the UNCITRAL Model Law
constitutional. Even before the approval on June 19, 1953 of Republic Act No. 876,
this Court has countenanced the settlement of disputes through arbitration. Republic
International Trade Law (UNCITRAL) in the New York Convention on June 21,
Act No. 876 was adopted to supplement the New Civil Codes provisions on
1985, the Philippinescommitted itself to be bound by the Model Law. We have even
arbitration.
[39]
incorporated the Model Law in Republic Act No. (RA) 9285, otherwise known as
the Alternative Dispute Resolution Act of 2004 entitled An Act to Institutionalize the
Use of an Alternative Dispute Resolution System in the Philippines and to Establish
the Office for Alternative Dispute Resolution, and for Other Purposes, promulgated
on April 2, 2004. Secs. 19 and 20 of Chapter 4 of the Model Law are the pertinent
provisions:
(1)
Under Sec. 24, the RTC does not have jurisdiction over disputes that are
properly the subject of arbitration pursuant to an arbitration clause, and mandates the
referral to arbitration in such cases, thus:
SEC. 24. Referral to Arbitration.A court before which
an action is brought in a matter which is the subject matter of an
arbitration agreement shall, if at least one party so requests not
later than the pre-trial conference, or upon the request of both
parties thereafter, refer the parties to arbitration unless it finds that
the arbitration agreement is null and void, inoperative or incapable
of being performed.
(2)
arbitration clause to be final and binding are not immediately enforceable or cannot
be implemented immediately. Sec. 35[43] of the UNCITRAL Model Law stipulates
the requirement for the arbitral award to be recognized by a competent court for
enforcement, which court under Sec. 36 of the UNCITRAL Model Law may refuse
recognition or enforcement on the grounds provided for. RA 9285 incorporated these
provisos to Secs. 42, 43, and 44 relative to Secs. 47 and 48, thus:
SEC. 42. Application of the New York Convention.The
New York Convention shall govern the recognition and
enforcement of arbitral awards covered by said Convention.
The recognition and enforcement of such arbitral awards
shall be filed with the Regional Trial Court in accordance with
the rules of procedure to be promulgated by the Supreme Court.
Said procedural rules shall provide that the party relying on the
award or applying for its enforcement shall file with the court the
original or authenticated copy of the award and the arbitration
agreement. If the award or agreement is not made in any of the
sent al least fifteen (15) days before the date set for the initial
hearing of the application.
It is now clear that foreign arbitral awards when confirmed by the RTC are
deemed not as a judgment of a foreign court but as a foreign arbitral award, and
when confirmed, are enforced as final and executory decisions of our courts of law.
Thus, it can be gleaned that the concept of a final and binding arbitral award
is similar to judgments or awards given by some of our quasi-judicial bodies, like the
National Labor Relations Commission and Mines Adjudication Board, whose final
judgments are stipulated to be final and binding, but not immediately executory in
the sense that they may still be judicially reviewed, upon the instance of any
party. Therefore, the final foreign arbitral awards are similarly situated in that they
need first to be confirmed by the RTC.
(3)
with specific authority and jurisdiction to set aside, reject, or vacate a foreign arbitral
award on grounds provided under Art. 34(2) of the UNCITRAL Model Law. Secs.
42 and 45 provide:
SEC. 42. Application of the New York Convention.The
New York Convention shall govern the recognition and
enforcement of arbitral awards covered by said Convention.
The recognition and enforcement of such arbitral awards
shall be filed with the Regional Trial Court in accordance with
the rules of procedure to be promulgated by the Supreme Court.
Said procedural rules shall provide that the party relying on the
award or applying for its enforcement shall file with the court the
original or authenticated copy of the award and the arbitration
agreement. If the award or agreement is not made in any of the
official languages, the party shall supply a duly certified translation
thereof into any of such languages.
an aggrieved party in cases where the RTC sets aside, rejects, vacates, modifies, or
corrects an arbitral award, thus:
Thus, while the RTC does not have jurisdiction over disputes governed by
arbitration mutually agreed upon by the parties, still the foreign arbitral award is
subject to judicial review by the RTC which can set aside, reject, or vacate it. In this
sense, what this Court held in Chung Fu Industries (Phils.), Inc. relied upon by
KOGIES is applicable insofar as the foreign arbitral awards, while final and binding,
do not oust courts of jurisdiction since these arbitral awards are not absolute and
without exceptions as they are still judicially reviewable. Chapter 7 of RA 9285 has
made it clear that all arbitral awards, whether domestic or foreign, are subject to
judicial review on specific grounds provided for.
(4) Grounds for judicial review different in domestic and foreign arbitral
awards
The differences between a final arbitral award from an international or
foreign arbitral tribunal and an award given by a local arbitral tribunal are the
specific grounds or conditions that vest jurisdiction over our courts to review the
awards.
available remedies under RA 9285. Its interests are duly protected by the law which
The issues arising from the contract between PGSMC and KOGIES on
requires that the arbitral award that may be rendered by KCAB must be confirmed
whether the equipment and machineries delivered and installed were properly
compliance by KOGIES in the production of the samples, given the alleged fact that
arbitration clause, stipulating that the arbitral award is final and binding, does not
PGSMC could not supply the raw materials required to produce the sample LPG
oust our courts of jurisdiction as the international arbitral award, the award of which
cylinders, are matters proper for arbitration. Indeed, we note that on July 1, 1998,
is not absolute and without exceptions, is still judicially reviewable under certain
KOGIES
conditions provided for by the UNCITRAL Model Law on ICA as applied and
incorporated in RA 9285.
Finally, it must be noted that there is nothing in the subject Contract which
provides that the parties may dispense with the arbitration clause.
instituted
an
Application
for
Arbitration
before
the
KCAB
Having ruled that the arbitration clause of the subject contract is valid and
Sheriff from the inspection made on October 28, 1998, as ordered by the trial court
binding on the parties, and not contrary to public policy; consequently, being bound
to the contract of arbitration, a party may not unilaterally rescind or terminate the
ascertain the actual status of the equipment and machineries as installed in the plant.
For these reasons, the September 21, 1998 and October 19, 1998 RTC
Angeles[47] and reiterated in succeeding cases, [48] that the act of treating a contract as
Orders pertaining to the grant of the inspection of the equipment and machineries
contract is availing, neither of the parties can unilaterally treat the contract as
rescinded since whatever infractions or breaches by a party or differences arising
Petitioner assails the CA ruling that the issue petitioner raised on whether the
from the contract must be brought first and resolved by arbitration, and not through
total contract price of USD 1,530,000 was for the whole plant and its installation is
xxx
xxx
It is thus beyond cavil that the RTC has authority and jurisdiction to grant
interim measures of protection.
Secondly, considering that the equipment and machineries are in the
possession of PGSMC, it has the right to protect and preserve the equipment and
Art. 17 J of UNCITRAL Model Law on ICA also grants courts power and
jurisdiction to issue interim measures:
machineries in the best way it can. Considering that the LPG plant was nonoperational, PGSMC has the right to dismantle and transfer the equipment and
machineries either for their protection and preservation or for the better way to make
good use of them which is ineluctably within the management discretion of PGSMC.
Thirdly, and of greater import is the reason that maintaining the equipment
and machineries in Worths property is not to the best interest of PGSMC due to the
prohibitive rent while the LPG plant as set-up is not operational. PGSMC was losing
PhP322,560 as monthly rentals or PhP3.87M for 1998 alone without considering the
10% annual rent increment in maintaining the plant.
Fourthly, and corollarily, while the KCAB can rule on motions or petitions
relating to the preservation or transfer of the equipment and machineries as an
(2)
The September 21, 1998 and October 19, 1998 RTC Orders in Civil
interim measure, yet on hindsight, the July 23, 1998 Order of the RTC allowing the
transfer of the equipment and machineries given the non-recognition by the lower
(3)
arbitration of their dispute and differences arising from the subject Contract before
(4)
equipment and machineries, if it had not done so, and ORDERED to preserve and
protected by the arbitral action it has instituted before the KCAB, the award of which
maintain them until the finality of whatever arbitral award is given in the arbitration
can be enforced in our jurisdiction through the RTC. Besides, by our decision,
proceedings.
No pronouncement as to costs.
SO ORDERED.
ESTATE OF NELSON R. DULAY, represented by his
wife MERRIDY JANE P. DULAY,
Petitioner,
or dispose of the same considering the pending arbitral proceedings to settle the
equipment and machineries with the diligence of a good father of a family [51] until
final resolution of the arbitral proceedings and enforcement of the award, if any.
Present:
- versus
differences of the parties. PGSMC therefore must preserve and maintain the subject
Promulgated:
DECISION
PERALTA, J.:
Before the Court is a petition for review on certiorari under Rule 45 of the
Rules of Court seeking to reverse and set aside the Decision [1] and Resolution[2] dated
July 11, 2005 and April 18, 2006 of the Court of Appeals (CA) in CA-G.R. SP No.
76489.
The factual and procedural antecedents of the case, as summarized by the CA,
are as follows:
Nelson R. Dulay (Nelson, for brevity) was employed by
[herein respondent] General Charterers Inc. (GCI), a subsidiary
of co-petitioner [herein co-respondent] Aboitiz Jebsen Maritime
Inc. since 1986. He initially worked as an ordinary seaman and
later as bosun on a contractual basis. From September 3, 1999
up to July 19, 2000, Nelson was detailed in petitioners vessel,
the MV Kickapoo Belle.
On August 13, 2000, or 25 days after the completion of his
employment contract, Nelson died due to acute renal failure
secondary to septicemia. At the time of his death, Nelson was a
bona fide member of the Associated Marine Officers and
Seamans Union of the Philippines (AMOSUP), GCIs collective
bargaining agent. Nelsons widow, Merridy Jane, thereafter
claimed for death benefits through the grievance procedure of
the Collective Bargaining Agreement (CBA) between AMOSUP
and GCI. However, on January 29, 2001, the grievance
procedure was declared deadlocked as petitioners refused to
grant the benefits sought by the widow.
On March 5, 2001, Merridy Jane filed a complaint with the
NLRC Sub-Regional Arbitration Board in General Santos City
against GCI for death and medical benefits and damages.
On March 8, 2001, Joven Mar, Nelsons brother,
received P20,000.00 from [respondents] pursuant to article
20(A)2 of the CBA and signed a Certification acknowledging
receipt of the amount and releasing AMOSUP from further
liability. Merridy Jane contended that she is entitled to the
aggregate sum of Ninety Thousand Dollars ($90,000.00)
pursuant to [A]rticle 20 (A)1 of the CBA x x x
xxxx
Herein respondents then filed a special civil action for certiorari with the
CA contending that the NLRC committed grave abuse of discretion in affirming the
jurisdiction of the NLRC over the case; in ruling that a different provision of the
CBA covers the death claim; in reversing the findings of the Labor Arbiter that the
Filipino workers. Petitioner argues that the abovementioned Section amended Article
cause of death is not work-related; and, in setting aside the release and quitclaim
217 (c) of the Labor Code which, in turn, confers jurisdiction upon voluntary
executed by the attorney-in-fact and not considering the P20,000.00 already received
On July 11, 2005, the CA promulgated its assailed Decision, the dispositive
portion of which reads as follows:
WHEREFORE, in view of the foregoing, the petition is
hereby GRANTED and the case is REFERRED to the National
Conciliation and Mediation Board for the designation of the
Voluntary Arbitrator or the constitution of a panel of Voluntary
Arbitrators for the appropriate resolution of the issue on the matter
of the applicable CBA provision.
SO ORDERED.[4]
Article 217(c) of the Labor Code, on the other hand, states that:
The CA ruled that while the suit filed by Merridy Jane is a money claim, the
same basically involves the interpretation and application of the provisions in the
subject CBA. As such, jurisdiction belongs to the voluntary arbitrator and not the
labor arbiter.
xxxx
(c) Cases arising from the interpretation or implementation
of collective bargaining agreements and those arising from the
interpretation or enforcement of company personnel policies shall
be disposed by the Labor Arbiter by referring the same to the
grievance machinery and voluntary arbitration as may be provided
in said agreements.
On their part, respondents insist that in the present case, Article 217, paragraph
(c) as well as Article 261 of the Labor Code remain to be the governing provisions of
Hence, the instant petition raising the sole issue of whether or not the CA
committed error in ruling that the Labor Arbiter has no jurisdiction over the case.
law with respect to unresolved grievances arising from the interpretation and
implementation of collective bargaining agreements. Under these provisions of law,
jurisdiction remains with voluntary arbitrators.
ARTICLE
261. Jurisdiction
of
Voluntary
Arbitrators or panel of Voluntary Arbitrators. The Voluntary
Arbitrator or panel of Voluntary Arbitrators shall have original and
exclusive jurisdiction to hear and decide all unresolved grievances
arising from the interpretation or implementation of the Collective
Bargaining Agreement and those arising from the interpretation or
enforcement of company personnel policies referred to in the
immediately preceding article. Accordingly, violations of a
Collective Bargaining Agreement, except those which are gross in
character, shall no longer be treated as unfair labor practice and
shall be resolved as grievances under the Collective Bargaining
Agreement. For purposes of this article, gross violations of
Collective Bargaining Agreement shall mean flagrant and/or
malicious refusal to comply with the economic provisions of such
agreement.
The Commission, its Regional Offices and the
Regional Directors of the Department of Labor and Employment
shall not entertain disputes, grievances or matters under the
exclusive and original jurisdiction of the Voluntary Arbitrator or
panel of Voluntary Arbitrators and shall immediately dispose and
refer the same to the Grievance Machinery or Voluntary Arbitration
provided in the Collective Bargaining Agreement.
general, which the general statute (Labor Code) treats in particular. [5] In the present
case, the basic issue raised by Merridy Jane in her complaint filed with the NLRC is:
which provision of the subject CBA applies insofar as death benefits due to the heirs
of Nelson are concerned. The Court agrees with the CA in holding that this issue
clearly involves the interpretation or implementation of the said CBA. Thus, the
specific or special provisions of the Labor Code govern.
In any case, the Court agrees with petitioner's contention that the CBA is the
law or contract between the parties. Article 13.1 of the CBA entered into by and
between respondent GCI and AMOSUP, the union to which petitioner belongs,
provides as follows:
The Company and the Union agree that in case of
dispute or conflict in the interpretation or application of any of
the provisions of this Agreement, or enforcement of Company
policies, the same shall be settled through negotiation,
conciliation or voluntary arbitration. The Company and the
Union further agree that they will use their best endeavor to ensure
that any dispute will be discussed, resolved and settled amicably by
the parties hereof within ninety (90) days from the date of filing of
the dispute or conflict and in case of failure to settle thereof any of
the parties retain their freedom to take appropriate action.
[6]
(Emphasis supplied)
From the foregoing, it is clear that the parties, in the first place, really intended
to bring to conciliation or voluntary arbitration any dispute or conflict in the
interpretation or application of the provisions of their CBA. It is settled that when
the parties have validly agreed on a procedure for resolving grievances and to submit
a dispute to voluntary arbitration then that procedure should be strictly observed.[7]
Articles 217(c) and 261 of the Labor Code are very specific in stating that voluntary
arbitrators have jurisdiction over cases arising from the interpretation or
implementation of collective bargaining agreements. Stated differently, the instant
case involves a situation where the special statute (R.A. 8042) refers to a subject in
It may not be amiss to point out that the abovequoted provisions of the CBA
are in consonance with Rule VII, Section 7 of the present Omnibus Rules and
Regulations Implementing the Migrant Workers and Overseas Filipinos Act of 1995,
as amended by Republic Act No. 10022, which states that [f]or OFWs with
It is clear from the above that the interpretation of the DOLE, in consultation
with their counterparts in the respective committees of the Senate and the House of
Representatives, as well as the DFA and the POEA is that with respect to disputes
involving claims of Filipino seafarers wherein the parties are covered by a collective
bargaining agreement, the dispute or claim should be submitted to the jurisdiction of
a voluntary arbitrator or panel of arbitrators. It is only in the absence of a collective
bargaining agreement that parties may opt to submit the dispute to either the NLRC
or to voluntary arbitration. It is elementary that rules and regulations issued by
administrative bodies to interpret the law which they are entrusted to enforce, have
the force of law, and are entitled to great respect. [8] Such rules and regulations
partake of the nature of a statute and are just as binding as if they have been written
in the statute itself.[9] In the instant case, the Court finds no cogent reason to depart
from this rule.
The above interpretation of the DOLE, DFA and POEA is also in consonance
with the policy of the state to promote voluntary arbitration as a mode of settling
labor disputes.[10]
No less than the Philippine Constitution provides, under the third paragraph,
Section 3, Article XIII, thereof that [t]he State shall promote the principle of shared
responsibility between workers and employers and the preferential use of voluntary
modes in settling disputes, including conciliation, and shall enforce their mutual
compliance therewith to foster industrial peace.
The
Philippine
Overseas
Employment
Administration (POEA) shall exercise original and exclusive
jurisdiction to hear and decide disciplinary action on cases, which
are administrative in character, involving or arising out of
violations of recruitment laws, rules and regulations involving
Consistent with this constitutional provision, Article 211 of the Labor Code
provides the declared policy of the State [t]o promote and emphasize the primacy of
union for illegal dismissal and unfair labor practice. The filing of a
request for reconsideration by the respondent union, which is the
condition sine qua non to categorize the termination dispute and the
ULP complaint as a grievable dispute as per CBA, was decidedly absent
in the case at bench. Hence, the respondent union acted well within
their rights in filing their complaint directly with the Labor Arbiter.
1.
Article 217. Jurisdiction of Labor Arbiters and the Commission - (a) Except as
otherwise provided under this Code, the Labor Arbiters shall have original and
exclusive jurisdiction to hear and decide x x x the following cases involving all
workers, whether agricultural or non-agricultural:
(1) Unfair labor practice cases:
(2) Termination disputes;
x x x
xxx
x x x.
The sole exception to the above rule can be found under Article 262 of the
same Code, which provides:
Aricle 262. Jurisdiction over other labor disputes - The voluntary arbitrator or panel
of voluntary arbitrators, upon agreement of the parties, shall also hear and decide
all other labor disputes including unfair labor practices and bargaining deadlocks.
(As added by R.A. 6715)
We subjected the records of this case, particularly the CBA, to meticulous
scrutiny and we find no agreement between SMC and the respondent union
that would state in unequivocal language that petitioners and the respondent
union conform to the submission of termination disputes and unfair labor
practices to voluntary arbitration. Section 1, Article V of the CBA, cited by the
herein petitioners, certainly does not provide so. Hence, consistent with the
general rule under Article 217 (a) of the Labor Code, the Labor Arbiter
properly has jurisdiction over the complaint filed by the respondent union on
February 25, 1991 for illegal dismissal and unfair labor practice.
Petitioners point however to Section 2, Article III of the CBA, under the
heading Job Security, to show that the dispute is a proper subject of the
grievance procedure, viz:
x x x The UNION, however, shall have the right to seek reconsideration of any
discharge, lay-off or disciplinary action, and such requests for reconsideration shall
be considered a dispute or grievance to be dealt with in accordance with the
procedure outlined in Article IV hereof [on Grievance Machinery] x x x[3]
(Emphasis ours)
ultimate facts showing how the discharges affected the rights to selforganization of individual respondents. [6] In short, petitioners maintain that
respondents complaint does not allege a genuine case for ULP.
The Court is not convinced.
The complaint alleges that:
5. Individual complainants are bona fide officers and members of complainant Ilaw
at Buklod ng Manggagawa (IBM). They are active and militant in the affairs and
activities of the union.
xxx
xxx
xxx
23. The dismissal or lock-out from work of the individual complainants clearly
constitutes an act of unfair labor practices in the light of the fact that the work being
performed by the individual complainants are being contracted out by the respondent
company, and, therefore, deprives individual complainants of their right to work and
it constitutes a criminal violation of existing laws.
xxx
xxx
xxx
x x x The explanation, however, does not by any means account for the permanent
dismissal of five of the unionists, where it does not appear that non-unionists were
similarly dismissed.
xxx
xxx
xxx
And the discrimination shown by the Company strongly is confirmed by the fact that
during the period from October 1958 to August 17, 1959 it hired from fifteen to
twenty new employees and ten apprentices. It says these employees were for its new
lead factory, but is (sic) not shown that the five who had been permanently dismissed
were not suitable for work in that new factory.
A similar ruling was made by this Court in Peoples Bank and Trust
Co. v. Peoples Bank and Trust Co. Employees Union [9] involving the lay-off
by a bank of sixty-five (65) employees who were active union members
allegedly by reason of retrechment. The Court likewise found the employer
in that case to have committed ULP in effecting the discharges.
This Court was more emphatic however in Bataan Shipyard and
Engineering Co., Inc. v. NLRC, et al.:[10]
Under the circumstances obtaining in this case, We are inclined to believe that the
company had indeed been discriminatory in selecting the employees who were to be
retrenched. All of the retrenched employees are officers and members of the
NAFLU. The record of the case is bereft of any satisfactory explanation from the
Company regarding this situation. As such, the action taken by the firm becomes
highly suspect. It leads Us to conclude that the firm had been discriminating
against membership in the NAFLU, an act which amounts to interference in the
employees exercise of their right of self-organization. Under Art. 249 (now Art.
248) of the Labor Code of the Philippines, such interference is considered an act of
unfair labor practice on the part of the Company x x x. (Emphasis ours)
It matters not that the cause of termination in the above cited cases was
retrenchment while that in the instant case was redundancy. The important
fact is that in all of these cases, including the one at bar, all of the dismissed
employees were officers and members of their respective unions, and their
employers failed to give a satisfactory explanation as to why this group of
employees was singled out.
It may be the case that employees other than union members may have
been terminated also by petitioner SMC on account of its redundancy
program. If that is true, the discharges may really be for a bona fide
authorized cause under Article 283 [11] of the Labor Code. On the other hand,
it is also possible that such may only be a clever scheme of the petitioner
company to camouflage its real intention of discriminating against union
members particularly the private respondents. In any case, these matters will
be best ventilated in a hearing before the Labor Arbiter.
It is for the above reason that we cannot hold the petitioners guilty of the
ULP charge. This will be the task of the Labor Arbiter. We however find that
based on the cicumstances surrounding this case and settled jurisprudence
on the subject, the complaint filed by the private respondents on
February 25, 1991 alleges facts sufficient to costitute a bona fide case of
ULP, and therefore properly cognizable by the Labor Arbiter under Article 2
17(a) of the Labor Code. This is consistent with the rule that jurisdictioin over
the subject matter is determined by the allegations of the complaint. [12]
Finally, petitioners try to impress on this Court the strong State policy on
the promotion of voluntary modes of settlement of labor disputes crafted in
the Constitution and the Labor Code which dictate the submission of the CBA
dispute to grievance and arbitration.[13]
In this regard, the response of the Solicitor General is apt:
Petitioners deserve commendation for divulging and bringing to public respondents
attention the noble legislative intent behind the law mandating the inclusion of
grievance and voluntary arbitration provisions in the CBA. However, in the absence
of an express legal conferment thereof, jurisdiction cannot be appropriated by an
official or tribunal (sic) no matter how well-intentioned it is, even in the pursuit of
the clearest substantial right (Concurring Opinion of Justice Barredo,
Estanislao v. Honrado, 114 SCRA 748, 29 June 1982).[14]
In the same manner, petitioners cannot arrogate into the powers of voluntary
arbitrators the original and exclusive jurisdiction of Labor Arbiters over unfair labor
practices, termination disputes, and claims for damages, in the absence of an express
agreement between the parties in order for Article 262[15] of the Labor Law to apply
in the case at bar.[16]
MALCOLM, J.:
The preliminary and basic question presented by the petition of the Manila
Electric Company, requesting the members of the Supreme Court, sitting as
a board of arbitrators, to fix the terms upon which certain transportation
companies shall be permitted to use the Pasig bridge of the Manila Electric
Company and the compensation to be paid to the Manila Electric Company
by such transportation companies, relates to the validity of section 11 of Act
No. 1446 and to the legal right of the members of the Supreme Court, sitting
as a board of arbitrators, to act on the petition. Act No. 1446 above referred
to is entitled. "An Act granting a franchise to Charles M. Swift to construct,
maintain, and operate an electric railway, and to construct, maintain, and
operate an electric light, heat, and power system from a point in the City of
Manila in an easterly direction to the town of Pasig, in the Province of Rizal."
Section 11 of the Act provides: "Whenever any franchise or right of way is
granted to any other person or corporation, now or hereafter in existence,
over portions of the lines and tracks of the grantee herein, the terms on
which said other person or corporation shall use such right of way, and the
compensation to be paid to the grantee herein by such other person or
corporation for said use, shall be fixed by the members of the Supreme
such purpose and affecting others than the parties to a particular franchise.
Here, however, whatever else may be said in extenuation, it remains true that
the decision of the board of arbitrators is made final, which if literally enforced
would leave a public utility, not a party to the contract authorized by Act No.
1446, without recourse to the courts for a judicial determination of the
question in dispute.
Counsel for the petitioner rely principally on the case of Tallassee Falls Mfg.
Co. vs. Commissioner's Court [1908], 158 Ala., 263. It was there held that an
Act of a state legislature authorizing the commissioners' court of a certain
county to regulate and fix the rate of toll to be charged by the owners of a
bridge is not unconstitutional as delegating legislative power to the courts.
But that is not the question before us. Here the question is not one of
whether or not there has been a delegation of legislative authority to a court.
More precisely, the issue concerns the legal right of the members of the
Supreme Court, sitting as a board of arbitrators the decision of a majority of
whom shall be final, to act in that capacity.
We run counter to this dilemma. Either the members of the Supreme Court,
sitting as a board of arbitrators, exercise judicial functions, or the members of
the Supreme Court, sitting as board of arbitrators, exercise administrative
or quasi judicial functions. The first case would appear not to fall within the
jurisdiction granted the Supreme Court. Even conceding that it does, it would
presuppose the right to bring the matter in dispute before the courts, for any
other construction would tend to oust the courts of jurisdiction and render the
award a nullity. But if this be the proper construction, we would then have the
anomaly of a decision by the members of the Supreme Court, sitting as a
board of arbitrators, taken therefrom to the courts and eventually coming
before the Supreme Court, where the Supreme Court would review the
decision of its members acting as arbitrators. Or in the second case, if the
functions performed by the members of the Supreme Court, sitting as a
board of arbitrators, be considered as administrative or quasi judicial in
nature, that would result in the performance of duties which the members of
the Supreme Court could not lawfully take it upon themselves to perform.
The present petition also furnishes an apt illustration of another anomaly, for
we find the Supreme Court as a court asked to determine if the members of
the court may be constituted a board of arbitrators, which is not a court at
all.lawphil.net
The Supreme Court of the Philippine Islands represents one of the three
divisions of power in our government. It is judicial power and judicial power
only which is exercised by the Supreme Court. Just as the Supreme Court,
as the guardian of constitutional rights, should not sanction usurpations by
any other department of the government, so should it as strictly confine its
own sphere of influence to the powers expressly or by implication conferred
on it by the Organic Act. The Supreme Court and its members should not and
cannot be required to exercise any power or to perform any trust or to
assume any duty not pertaining to or connected with the administering of
judicial functions.
The Organic Act provides that the Supreme Court of the Philippine Islands
shall possess and exercise jurisdiction as heretofore provided and such
additional jurisdiction as shall hereafter be prescribed by law (sec. 26). When
the Organic Act speaks of the exercise of "jurisdiction" by the Supreme
Court, it could not only mean the exercise of "jurisdiction" by the Supreme
Court acting as a court, and could hardly mean the exercise of "jurisdiction"
by the members of the Supreme Court, sitting as a board of arbitrators.
There is an important distinction between the Supreme Court as an entity
and the members of the Supreme Court. A board of arbitrators is not a "court"
in any proper sense of the term, and possesses none of the jurisdiction which
the Organic Act contemplates shall be exercised by the Supreme
Court.lawph!l.net
In the last judicial paper from the pen of Chief Justice Taney, it was said:
The power conferred on this court is exclusively judicial, and it
cannot be required or authorized to exercise any other. . . . Its
jurisdiction and powers and duties being defined in the organic law of
the government, and being all strictly judicial, Congress cannot
require or authorize the court to exercise any other jurisdiction or
power, or perform any other duty. . . . The award of execution is a
part, and an essential part of every judgment passed by a court
exercising judicial power. It is no judgment, in the legal sense of the
term, without it. Without such an award the judgment would be
inoperative and nugatory, leaving the aggrieved party without a
remedy. It would be merely an opinion, which would remain a dead
letter, and without any operation upon the rights of the parties, unless
Congress should at some future time sanction it, and pass a law
authorizing the court to carry its opinion into effect. Such is not the
NARVASA, J.:
A series of contracts was entered into between Western Minolco Corporation
and Gregorian Mining Company, basically for the operation by the former of
the latter's mining claims. 1 One of the stipulations in the contracts (a)
declared certain particular disputes to be subject to arbitration and (b)
specified the manner of enforcement by court action of the resulting
arbitration awards. 2 The stipulation reads as follows:
Article XII
It is made quite clear that these two (2) classes of disputes are to be
"referred to a board of arbitration." It is made equally clear that no action
concerning them may be instituted in any court by either party (1) unless the
controversy be "first submitted to and received by said board of arbitrators,"
and (2) only if the action "be based upon the award as obtained. " In the
event of such an action, the venue thereof "shall be in the City of Manila."
Now, it appears that Western Minolco Corporation subsequently executed
another agreement with another firm, the Dreamers Mining Association, for
the validation of 36 mineral lode claims in the latter's favor. As it happened,
It is Western Minolco's thesis that it was reversible error for the Court of
Appeals to find and declare that
a) the venue of the action instituted against it by Gregorian
Mining Co. was improperly laid;
b) the action could not be instituted until and unless the
dispute subject thereof had first been resolved by arbitration,
as covenanted by the parties;
c) public policy encourages arbitration and arbitration
agreements are to be liberally construed;
d) the Trial Court had no business interpreting the provisions
of the agreement the terms of which were otherwise clear,
unambiguous and unequivocal.
The terms of the applicable provision of the parties' agreements are indeed
"clear, unambiguous, and unequivocal." As pointed out in the opening
paragraphs of this opinion, only two (2) kinds of "disputes, differences or
disagreements" have been made subject of arbitration:
1) those "regarding the meaning, application or effect of the agreement(s) or
any clause thereof;" and
2) those "in regard to the amount and computation of the royalties, deduction,
or other item of expense" provided in the agreement.
The controversy involved in the action brought by Gregorian against Western
Minolco was the alleged violation by the latter of its agreements with the
former, consisting of its entering into a contract with a third party for the
validation of mining claims which it knew had already been located by
Gregorian. What was involved, in other words, was the breach of faith, or the
double dealing of Western Minolco in undertaking to validate in favor of a
third party the selfsame claims which it had earlier undertaken to operate
for Gregorian. Clearly, such a controversy does not fall within either of the
two categories of disputes which must first be submitted for arbitration. The
stipulation in question (for arbitration to be first had) did not therefore
constitute an impediment or a bar to the institution of the action commenced
by Gregorian against Western Minolco, for rescission and damages.
Even if, for the sake of argument, some measure of tenability be conceded to
the opposite view: that the controversy subject of Civil Case No. 2272 (220)
might be considered as dealing with the "meaning, application or effect" of
the agreementspecifically, whether the claims therein described are the
very same mining claims subject of Western Minolco's subsequent
agreement with a third partyand therefore should first be submitted to and
resolved by a board of arbitrators, the worst that could then be said of the
orders of the Trial Court, affirmed by the Court of Appeals, is that they are
attended by an error in the analysis and interpretation of the language and
import of the stipulation in question, but certainly not by that whimsical,
capricious, or totally groundless or tangential exercise of adjudgment or
discretion as would justify the issuance of the extraordinary writ of certiorari
or prohibition. 17 In no sense may it be said that power has been exercised
by either the Appellate Court or the Trial Court in so arbitrary or despotic a
manner, as by reason of passion, prejudice or personal hostility, or in so
patently and grossly mistaken a manner as to amount to an evasion of
positive duty or a virtual refusal to perform a duty enjoined or to act at all in
contemplation of law, so as to make needful the extension of this Court's
correcting hand by the peremptory writ of certiorari or prohibition. 18
Since the stipulation as to venue becomes relevant only when an action has
to be instituted "based upon the award as obtained" (from the board of
arbitrators) (i.e., as the mode of enforcement of the award); and since there
is here no such award because no controversy subject to arbitration existed
and was ever submitted to arbitration, no error can possibly be imputed to
the Trial Court in not applying the stipulation to the action a quo. In any
event, it is not entirely amiss to restate the doctrine that stipulations in a
contract, which specify a definite place for the institution of an action arising
in connection therewith, do not, as a rule, supersede the general rules on the
matter set out in Rule 4 of the Rules of Court, but should be construed
merely as an agreement on an additional forum, not as limiting venue to the
specified place. 19
WHEREFORE, the petition is DENIED, and the decision of the Court of
Appeals subject of the appeal is AFFIRMED. Costs against petitioner.
SO ORDERED.
G.R. No. 55159 December 22, 1989
CORTES, J.:
Petitioner impugns in this petition for certiorari that part of the public
respondent National Labor Relations Commission's (NLRC) decision in
NLRC Case No. RB-IV-9319-77 which ordered petitioner to restore private
respondent Dolina to its payroll, and to pay his salaries from 1 April 1979
"until this case is finally resolved" [Rollo, p. 33]. Petitioner contends that
public respondent NLRC gravely abused its discretion considering that in the
same decision public respondent affirmed the decision of the Labor Arbiter in
toto granting respondent's application for clearance to dismiss the private
respondent.
The pertinent facts are as follows:
Private respondent Dolina was admitted to the Philippine Airlines (PAL)
Aviation School for training as a pilot beginning 16 January 1973. The
training agreement bound PAL to provide regular and permanent
employment to Dolina upon completion of the training course. On 25 January
1974, Dolina completed the course, and undertook an equipment
qualification course up to 4 October 1974. On 9 October 1974, the Civil
Aeronautics Administration issued him a license as Commercial Pilot and
PAL then extended him a temporary appointment for six (6) months as
Limited First Officer. When his appointment was due to expire on 30 April
1975, Dolina had only logged eighty four (84) hours and fifty five (55) minutes
flying time, short of the minimum 500 flying hours required for regularization
as First Officer. To enable him to complete the requirement, his employment
was extended for another six months which appointment was described as
"permanent." On 31 October 1975, when his appointment was again due to
expire, he was still short of the minimum flying time requirement such that his
decision was not yet final because of his timely appeal. PAL opposed the
motion claiming that it was no longer obliged to return Dolina to its payroll
since the decision of the Labor Arbiter dated 23 March 1979 in its favor was a
final resolution of the case by arbitration [Annex "N" to the Petition, p. 1;
Rollo, p. 137].
On 8 February 1980, public respondent NLRC rendered its decision
containing the assailed portion to wit:
xxx xxx xxx
In fine it is our considered view that the respondent's
application for clearance to dismiss the complainant has
sufficiently surmounted the test of validity.
Be that as it may, we are not in accord with the
discontinuation of the payment of complainant's salaries.
The agreement of the parties stipulated in no uncertain
terms that the complainant [Dolina] is to be carried in
respondent's payroll until this case is finally resolved. As
things stand, the main issue is still being litigated. The
complainant, therefore, must be restored to the payroll and
paid for his salaries from 1 April 1979, the date he was
dropped from the respondent's payroll.
WHEREFORE, the Decision appealed from should be as it is
hereby affirmed in toto. However the respondent is ordered
to restore the complainant to its payroll and to pay his
salaries from 1 April 1979 until this case is finally resolved.
SO ORDERED. [NLRC Decision, pp. 10-11; Rollo, pp. 32-33;
Italics supplied]
Hence, this petition, with a prayer for a temporary restraining order. The
Court issued a temporary restraining order on 10 October 1980. Private
respondent Dolina failed to file his comment and the Solicitor General
submitted his own Comment supporting the stand of petitioner. Due to the
adverse stand of the Solicitor General, public respondent NLRC submitted its
own Comment.
The issue before the Court is whether or not the NLRC committed grave
abuse of discretion in holding that private respondent Dolina was entitled to
his salaries from 1 April 1979 "until this case is finally resolved."
PAL contends that inasmuch as the respondent Commission acting en banc
had affirmed in toto the decision of the Labor Arbiter granting petitioner the
clearance for the dismissal of private respondent Dolina, it is an act of grave
abuse of discretion amounting to lack of jurisdiction on its part to order
petitioner to pay private respondent's salaries from 1 April 1979 until the case
is finally terminated. PAL contends that said stipulation refers only to the
resolution of the case by arbitration and said arbitration of the case was
terminated when the Labor Arbiter rendered its decision dated 23 March
1979. PAL argues that the arbitration of the case is limited to and comprises
merely the proceedings before the Labor Arbiter such that when the latter
renders a decision, arbitration of the dispute is terminated .
Public respondent NLRC on the other hand contends that arbitration is a
continuing process from the time the case is referred by the Secretary of
Labor to the Arbitration Branch until the final judgment is had on appeal.
Since the Labor Arbiter's decision in favor of petitioner did not finally resolve
the case in view of the timely appeal by private respondent from said
decision, the case was not yet finally terminated by arbitration and Dolina is
entitled to be placed in petitioner's payroll until the complaint is finally
resolved.
The above contentions call for the proper interpretation of the agreement
between the parties, specifically the third stipulation containing the clause
"pending final resolution of the case by arbitration."
It is a basic rule in interpretation of contracts that the circumstances under
which an instrument was made, including the situation of the subject thereof
and the parties to it, may be considered so that the intention of the
contracting parties may be judged correctly [Art. 1371, Civil Code of the
Philippines; Section 11, Rule 130, Rules of Court; Lim v. Court of Appeals,
G.R. No. L-40258, September 11, 1980, 99 SCRA 668.] In the instant case,
the stipulation in the 2 March 1977 agreement that Dolina shag be included
in the payroll of PAL until final resolution of the case by arbitration was
intended to supersede the order of the Regional Director which, by stipulation
of the parties, was rendered moot and academic. In lieu of reinstatement and
the payment of his backwages, private respondent was included in
More important, however, is the fact that the NLRC's order for the continued
payment of Dolina's salaries is inconsistent with its affirmance of the Labor
Arbiter's decision upholding the validity of Dolina's dismissal. In affirming the
Labor Arbiter's decision granting the termination clearance, the NLRC held
that:
for a just cause, it would neither be fair nor just to allow the employee to
recover something he has not earned and could not have earned [Santos v.
National Labor Relations Commission, G.R. No. 76721, September 21, 1987,
154 SCRA 166].
Moreover, in ordering the continued payment of Dolina's salaries from 1 April
1979 until the case is finally resolved, the NLRC in effect ordered the
payment of backwages to Dolina notwithstanding its finding of a valid
dismissal.
This is clearly untenable.
In the first place, backwages in general are granted on grounds of equity for
earnings which a worker or employee has lost due to his illegal dismissal
[New Manila Candy Workers Union (NACONWA-PAFLU) v. Court of
Industrial Relations, G.R. No. L-29728, October 30, 1978, 86 SCRA 37;
Durabilt Recapping Plant & Co. v. National Labor Relations Commission,
supra; Chong Guan Trading v. National Labor Relations Commission, G. R.
No. 81471, April 26, 1989; Santos v. National Labor Relations Commission,
supra]. Where, as in this case, the dismissal was for a just cause, there is no
factual or legal basis for ordering the payment of backwages. The order of
the NLRC for the continued payment of Dolina's salaries would allow the
latter to unjustly enrich himself at the expense of the petitioner. This Court
has reiterated time and again that the law, in protecting the rights of the
laborer, authorizes neither oppression nor self-destruction of the employer
[Colgate Palmolive Philippines, Inc. v. Ople, G.R. No. 73681, June
30,1988,163 SCRA 323]. In this case, the NLRC chose not to adhere with
fidelity to this doctrine.
Secondly, NLRC's order for continued payment of Dolina's salary from 1 April
1979 up to the final resolution of the case would place Dolina in a better
position than those workers who were found to have been illegally dismissed
by their employer. For in the latter case, the backwages that can be
recovered by the worker is limited to three years [Mercury Drug Co., Inc. v.
Court of Industrial Relations, G.R. No. L-23357, April 30, 1974, 56 SCRA
694; Philippine Airlines, Inc. v. National Labor Relations Commission, G.R.
No. 64809, November 29, 1983, 126 SCRA 223; Madrigal & Co., Inc. v.
Zamora, G.R. No. L-48237, Madrigal & Co., Inc. v. Minister of Labor, G.R.
No. L-49023, June 30,1987] while Dolina, whose dismissal was found to be
valid, can recover approximately ten years backwages, which corresponds to
the period from 1 April 1979 until "final resolution" of the instant case.
Considering the foregoing, the Court holds that respondent NLRC's order for
the continued payment of Dolina's salaries from "l April 1979 until the case is
finally resolved" is contrary to law and established jurisprudence and the
NLRC acted in excess of its jurisdiction in issuing the assailed order. In the
recent case of Llora Motors, Inc. v. Drilon, G.R. No. 82895, November 7,
1989 the Court held as an act without or in excess of jurisdiction the portion
of the Labor Arbiter's award, which required the employer to pay to its
employee an amount equivalent to a half month's pay for every year of
service as retirement benefits, for being without basis either in law or
contract. Similarly, there is in this case an excess of jurisdiction on the part of
the NLRC in ordering the continued payment of Dolina's salaries "from 1 April
1979 until the case is finally resolved."
WHEREFORE, that part of the dispositive portion of the decision of the
National Labor Relations Commission in NLRC CASE NO. RB-IV-9319-77
requiring petitioner to restore private respondent to its payroll and ordering
the payment of his salaries from 1 April 1979 until the case is finally resolved
is hereby declared NULL and VOID and SET ASIDE. The temporary
Restraining Order issued by the Court on 10 October 1980 is made
PERMANENT.
SO ORDERED.
G.R. No. 102881 December 7, 1992
TOYOTA MOTOR PHILIPPINES CORPORATION, petitioner,
vs.
On October 10, 1991, Judge Tensuan denied Sun Valley's motion to dismiss.
Both Toyota and Sun Valley filed their respective motions for reconsideration.
Toyota moved to reconsider the denial of its injunctive application while Sun
Valley moved to reconsider the denial of its motion to dismiss.
On October 30, 1991, APT filed its answer with affirmative defenses alleging
that the complaint must be dismissed on the ground that Toyota and APT
should first have resorted to arbitration as provided in Toyota's deed of sale
with APT. On December 4, 1991, Toyota filed a motion alleging that Sun
Valley's long threatened destruction and removal of Toyota's walls and
structures were actually being implemented to which Judge Tensuan issued
another TRO enjoining acts of destruction and removal of the perimeter walls
and structures on the contested area.
Consequently, on December 17, 1991, Judge Tensuan reconsidered his
earlier denial of Toyota's application for injunction and granted a writ of
preliminary injunction enjoining Sun Valley from proceeding with its
threatened destruction and removal of Toyota's walls and directed Sun Valley
to restore the premises to the status quo ante.
On December 11, 1991, Judge Tensuan denied Sun Valley's motion for
reconsideration of its motion to dismiss. Sun Valley elevated this denial to the
Court of Appeals. The case was docketed as CA-G.R. Sp. No. 26942 and
raffled to the Eleventh (11th) Division.
On the same day, Judge Gorospe issued a TRO enjoining Toyota from
committing further acts of dispossession against Sun Valley.
On September 19, 1991, Toyota moved to lift the TRO and opposed Sun
Valley's application for injunction.
On September 23, 1991, Toyota filed a motion to dismiss on the ground that
the RTC has no jurisdiction over the case since the complaint was a simple
ejectment case cognizable by the Metropolitan Trial Court (MTC). The motion
to dismiss was set for hearing on September 27, 1991.
On September 27, 1991, Sun Valley filed an amended complaint to
incorporate an allegation that Toyota's possession of the alleged disputed
area began in September, 1988 when Toyota purchased the property.
Ruling that the amendment was a matter of right, Judge Gorospe admitted
the amended complaint. Toyota adopted its motion to dismiss the original
complaint as its motion to dismiss the amended complaint. After the
arguments to Toyota's motion to dismiss, the same was submitted for
resolution. Sun Valley's application for prohibitory and mandatory injunction
contained in its complaint was set for hearing on October 1, 1991.
Protesting the admission of the amended complaint, Toyota went to the Court
of Appeals, on certiorari on October 1, 1991. This petition was docketed as
CA-G.R. No. 26152 raffled to the Tenth (10th) Division.
Toyota was later prompted to file two supplemental petitions, before the
Court of Appeals as a result of Judge Gorospe's alleged hasty issuance of
four (4) Orders, all dated October 1, 1992. These are:
cease and desist from further proceeding with Civil Case No. 91-2504 and
from enforcing the Order dated December 17, 1991 and the writ of
preliminary mandatory injunction dated December 19, 1991.
(1) First supplemental petition dated October 4, 1991 which sought to nullify
the Order denying Toyota's motion to dismiss the amended complaint.
This prompted Toyota to file a motion to quash the TRO and file a
supplemental petition with this Court impleading the Court of Appeals'
Second Division.
(2) Second supplemental petition dated October 23, 1991 which sought the
nullification of the orders granting Sun Valley's application for preliminary
prohibitory and mandatory injunction and denying Toyota's motion to crossexamine Sun Valley's witnesses on the latter's injunction application.
On November 27, 1991, respondent Court of Appeals' Tenth Division
promulgated its questioned decision which is primarily the subject matter of
the present petition before us.
The respondent court denied due course to the Toyota petition on the finding
that the amendment of Sun Valley's complaint was a valid one as Sun
Valley's action was not for unlawful detainer but an accion publiciana.
Furthermore, the supplemental petitions filed by Toyota assailing the
prohibitory and mandatory injunctive writ were not ruled upon as they were
expunged from the records because of Toyota's failure to attach a motion to
admit these supplemental petitions.
Thus, Toyota filed its Second Supplemental Petition with this Court
challenging the validity of the injunction writ issued by the Court of Appeals'
Second Division.
Earlier, upon an ex-parte motion to clarify filed by Sun Valley on October 25,
1991, Judge Gorospe issued another order dated December 2, 1991 which
followed Sun Valley to break open and demolish a portion of the Toyota
perimeter walls, and eventually to secure possession of the disputed area.
Toyota was constrained to come to this Court for relief.
On December 11, 1991, we issued a TRO enjoining the implementation of
Judge Gorospe's injunction and break-open orders dated October 1, 1991
and December 2, 1991 respectively as well as further proceedings in Civil
Case No. 91-2550.
Meanwhile, the Court of Appeals' Second Division issued a TRO ordering
respondent Judge Tensuan and all other persons acting in his behalf to
Amid the clutter of extraneous materials which have certainly bloated the
records of this case, we find only two (2) issues vital to the disposition of the
petition: first, is the matter of jurisdiction, who as between Judge Tensuan or
Judge Gorospe has jurisdiction over the dispute; and second, who as
between the parties has the rightful possession of the land.
Anent the issue on jurisdiction, we examine the two actions filed by the
parties.
Toyota filed an action for reformation on September 11, 1991, before Judge
Tensuan alleging that the true intentions of the parties were not expressed in
the instrument (Art. 1359 Civil Code). The instrument sought to be reformed
is the deed of sale executed by APT in favor of Toyota. Toyota alleges that
there was a mistake in the designation of the real properties subject matter of
the contract. Sun Valley was impleaded in order to obtain complete relief
since it was the owner of the adjacent lot.
Sun Valley, however, argues that the complaint for reformation states no
cause of action against it since an action for reformation is basically one
strictly between the parties to the contract itself. Third persons who are not
parties to the contract cannot and should not be involved. Thus, Sun Valley
contends that it should not have been impleaded as a defendant.
The Court of Appeals' 11th Division, in its decision promulgated on April 15,
1992 where the denial of Sun Valley's motion to dismiss was sustained,
correctly ruled that misjoinder of parties is not a ground for dismissal.
American jurisprudence from where provisions on reformation of instruments
were taken discloses that suits to reform written instruments are subject to
the general rule in equity that all persons interested in the subject matter of
the litigation, whether it is a legal or an equitable interest should be made
parties, so that the court may settle all their rights at once and thus prevent
From the foregoing jurisprudence, it would appear that Toyota was correct in
impleading Sun Valley as party defendant. However, these principles are not
applicable under the particular circumstances of this case. Under the facts of
the present case, Toyota's action for reformation is dismissible as against
Sun Valley.
The contention that the arbitration clause has become disfunctional because
of the presence of third parties is untenable.
Attention must first be brought to the fact that the contract of sale executed
between APT and Toyota provides an arbitration clause which states that:
Toyota filed an action for reformation of its contract with APT, the purpose of
which is to look into the real intentions/agreement of the parties to the
contract and to determine if there was really a mistake in the designation of
the boundaries of the property as alleged by Toyota. Such questions can only
be answered by the parties to the contract themselves. This is a controversy
which clearly arose from the contract entered into by APT and Toyota.
Inasmuch as this concerns more importantly the parties APT and Toyota
themselves, the arbitration committee is therefore the proper and convenient
forum to settle the matter as clearly provided in the deed of sale.
Having been apprised of the presence of the arbitration clause in the motion
to dismiss filed by APT, Judge Tensuan should have at least suspended the
proceedings and directed the parties to settle their dispute by arbitration
(Bengson v. Chan, 78 SCRA 113 [1977], Sec. 7, RA 876). Judge Tensuan
should have not taken cognizance of the case.
But the more apparent reason which warrants the dismissal of the action as
against Sun Valley is the fact that the complaint for reformation amounts to a
collateral attack on Sun Valley's title, contrary to the finding of the Court of
Appeals' 11th Division.
It is disputed that Sun Valley has a Torrens title registered in its name by
virtue of its purchase of the land from APT.
Toyota contends that the 723 square meters strip of land which it understood
to be included in its purchase from APT was erroneously included in Sun
Valley's title. This is the reason why reformation was sought to correct the
mistake.
Well-settled is the rule that a certificate of title can not be altered, modified, or
cancelled except in a direct proceeding in accordance with law (Section 48,
P.D. No. 1529).
In the case of Domingo v. Santos Ongsiako, Lim y Sia (55 Phil. 361 [1930]),
the Court held that:
. . . The fact should not be overlooked that we are here
confronted with what is really a collateral attack upon a
Torrens title. The circumstance that the action was directly
brought to recover a parcel of land does not alter the truth
that the proceeding involves a collateral attack upon a
Torrens title, because as we have found, the land in
controversy lies within the boundaries determined by that
title. The Land Registration Law defines the methods under
which a wrongful adjudication of title to land under the
Torrens system may be corrected . . .
While reformation may often be had to correct mistakes in defining the
boundary of lands conveyed so as to identify the lands, it may not be used to
pass other lands from those intended to be bought and sold, notwithstanding
a mistake in pointing out the lines, since reformation under these
circumstances would be inequitable and unjust. (McCay v. Jenkins, 244 Ala
650, 15 So 2d 409, 149 ALR 746)
Assuming that Toyota is afforded the relief prayed for in the Tensuan court,
the latter can not validly order the contested portion to be taken out from the
Sun Valley's TCT and award it in favor of Toyota.
An action for reformation is in personam, not in rem (Cohen v. Hellman
Commercial Trust & Savings Bank, 133 Cal App 758, 24 P2d 960; Edwards
v. New York Life Ins. Co. 173 Tenn 102, 114 SW 2d 808) even when real
In the instant case the existence of a "clear positive right" especially calling
for judicial protection has been shown by Sun Valley.
GENTLEMEN:
Toyota's claim over the disputed property is anchored on the fact of its
purchase of the property from APT, that from the circumstances of the
purchase and the intention of the parties, the property including the disputed
area was sold to it.
Sun Valley, on the other hand has TCT No. 49019 of the Registry of Deeds of
Paraaque embracing the aforesaid property in its name, having been validly
acquired also from APT by virtue of a Deed of Sale executed in its favor on
December 5, 1990 (Rollo, pp. 823-825; 826-827).
There are other circumstances in the case which militate against Toyota's
claim for legal possession over the disputed area.
The fact that Toyota has filed a suit for reformation seeking the inclusion of
the 723 square meters strip of land is sufficient to deduce that it is not
entitled to take over the piece of property it now attempts to appropriate for
itself.
As early as September, 1988 prior to the construction of the perimeter fence,
Toyota was already aware of the discrepancies in the property's description
in the title and the actual survey.
CESAR D. ELE
Project Manager (Emphasis supplied, Rollo, p. 811)
Despite such notification, Toyota continued to build the perimeter fence. It is
highly doubtful whether Toyota may be considered a builder in good faith to
be entitled to protection under Article 448 of the Civil Code.
The records also reveal that Toyota's own surveyor, the Certeza Surveying &
Acrophoto Systems, Inc. confirmed in its reports dated April 1 and April 5,
1991 that Toyota's perimeter fence overlaps the boundaries of Sun Valley's
lot (Rollo, pp. 833-383).
Even communication exchanges between and among APT, Toyota & Sun
Valley show that the parties are certainly aware that the ownership of the
disputed property more properly pertains to Sun Valley. Among these are the
following:
May 28,
1991
MR. JOSE CH. ALVAREZ
President
Sun Valley Manufacturing &
Development Corp. (SVMDC)
Cor. Aurora Blvd. and Andrews Ave.
Pasay City, Metro Manila
Dear Mr. Alvarez:
Thank you for honoring our invitation to a luncheon meeting
held at noon time today at Sugi Restaurant.
As per our understanding, we would like to propose as a
package the settlement of differences between your property
and ours as follows:
1. Boundary Issue between TMP Main Office
& Factory and the recently acquired property
of SVMDC.
The boundary lines to our property lines
bidded early 1988 were determined after
making full payment in August 1988 jointly
by representatives of TMP/Metrobank
Messrs. Mitake, Pedrosa, Alonzo and
Jurado, APT Mr. Bince together with
representatives of Geo-Resources who
installed the monuments and prepared the
technical description of the property. The
construction of the fence utilized existing
fence marked yellow on Exhibit 1 and made
sure that the new fence to set boundaries
were on top of the monuments set by GeoResources. The replacement of existing wire
fence were affected by setting concrete
walls on exactly the same position.
This is the reason why we are surprised top
be informed that our fence goes beyond the
boundary lines set forth in the Technical
Description on the Transfer Certificate of
Title (TCT) to our property. This occurs even
on fence already existing and should have
been maintained in the TCT.
Since we have manifested our intention
when we set boundaries to our property, we
propose the following in relation to the
excess area occupied by TMP.
1. We offer to give way to an access road 5
m. wide more or less from point 15 to 16 of
Lot 2 (14.65 m. in length) at the back of our
Paint Storage Building (Exhibit 2).
2. We propose to pay for the balance of
excess land inside TMP fence (contested
areas) at a price mutually agreed upon.
II. Question of ownership of certain
permanent improvements (underground
water reservoir and perimeter walls/fences)
located at Lot 6 which we won by bidding
from APT on October 5, 1990.
We have made our position to APT that
these permanent improvements are part of
Lot 6 on "as is where is" bid basis (See
explanatory map Exhibit 3). However,
since you have relayed to us that the
underground water reservoir is of no use to
you, as part of the total package we are
March 2, 2000
Undaunted, petitioner filed a petition for certiorari with the Court of Appeals
on November 23, 1994. Meanwhile, petitioner also filed its Answer to the
Third Party Complaint in the trial court.
On September 29, 1995, respondent Court of Appeals rendered the assailed
Decision dismissing the petition forcertiorari. With the denial of its Motion for
Reconsideration, petitioner filed the instant petition for review, raising the
following issues
I.
THE COURT OF APPEALS DISREGARDED AN AGREEMENT TO
ARBITRATE IN VIOLATION OF STATUTE AND SUPREME COURT
DECISIONS HOLDING THAT ARBITRATION IS A CONDITION
PRECEDENT TO SUIT WHERE SUCH AN AGREEMENT TO
ARBITRATE EXISTS.
II.
THE COURT OF APPEALS HAS RULED IN A MANNER NOT IN
ACCORD WITH JURISPRUDENCE WHEN IT REFUSED TO HAVE
THE THIRD-PARTY COMPLAINT DISMISSED FOR FAILURE TO
STATE A CAUSE OF ACTION AND FOR RULING THAT THE
FAILURE TO STATE A CAUSE OF ACTION MAY BE REMEDIED BY
REFERENCE TO ITS ATTACHMENTS.8
Resolving first the issue of failure to state a cause of action, respondent
Court of Appeals did not err in reading the Complaint of Florex and
respondent AMML's Answer together with the Third Party Complaint to
determine whether a cause of action is properly alleged. In Fil-Estate Golf
and Development, Inc. vs. Court of Appeals,9 this Court ruled that in the
determination of whether or not the complaint states a cause of action, the
annexes attached to the complaint may be considered, they being parts of
the complaint.
Coming now to the main issue of arbitration, the pertinent clauses of the "Cooperation in the Pacific" contract entered into by the parties provide:
16.2 For the purposes of this agreement the Containership Operator
shall be deemed to have issued to the Principal Carrier for good
consideration and for both loaded and empty containers its nonnegotiable memo bills of lading in the form attached hereto as
Appendix 6, consigned only to the Principal Carrier or its agents,
provisions of which shall govern the liability between the Principal
Carrier and the Containership Operator and that for the purpose of
determining the liability in accordance with either Lines' memo bill of
lading, the number of packages or customary freight units shown on
the bill of lading issued by the Principal Carrier to its shippers shall
be controlling.
16.3 The Principal Carrier shall use all reasonable endeavours to
defend all in personam and in rem suits for loss of or damage to
cargo carried pursuant to bills of lading issued by it, or to settle such
suits for as low a figure as reasonably possible. The Principal Carrier
shall have the right to seek damages and/or an indemnity from the
Containership Operator by arbitration pursuant to Clause 32
hereof. Notwithstanding the provisions of the Lines' memo bills of
lading or any statutory rules incorporated therein or applicable
thereto, the Principal Carrier shall be entitled to commence such
arbitration at any time until one year after its liability has been finally
determined by agreement, arbitration award or judgment, such
award or judgment not being the subject of appeal, provided that the
Containership Operator has been given notice of the said claim in
writing by the Principal Carrier within three months of the Principal
Carrier receiving notice in writing of the claim. Further the Principal
Carrier shall have the right to grant extensions of time for the
commencement of suit to any third party interested in the cargo
without prior reference to the Containership Operator provided that
notice of any extension so granted is given to the Containership
Operator within 30 days of any such extension being granted.
xxx
32. ARBITRATION
xxx
xxx
between the parties expressly provided for by their Agreement, the Third
Party Complaint should have been dismissed.
This Court has previously held that arbitration is one of the alternative
methods of dispute resolution that is now rightfully vaunted as "the wave of
the future" in international relations, and is recognized worldwide. To brush
aside a contractual agreement calling for arbitration in case of disagreement
between the parties would therefore be a step backward. 12
WHEREFORE, premises considered, the instant Petition for Review
on Certiorari is GRANTED. The decision of the Court of Appeals in CA-G.R.
SP No. 35777 is REVERSED and SET ASIDE. The Regional Trial Court of
Quezon City, Branch 77, is ordered to DISMISS Respondent AMML's Third
Party Complaint in Civil Case No. Q-92-12593. No pronouncement as to
costs.
SO ORDERED.1wphi1.nt
All told, when the text of a contract is explicit and leaves no doubt as to its
intention, the court may not read into it any other intention that would
contradict its plain import. 11 Arbitration being the mode of settlement