Cop V2 Isbn 923 9291 06 8 PDF
Cop V2 Isbn 923 9291 06 8 PDF
Cop V2 Isbn 923 9291 06 8 PDF
[Perlindungan]
Unit Kejuruteraan-Peralatan Sekunder
Jabatan Pembangunan Aset
Bahagian Penghantaran
Hakcipta Terpelihara, 2003
Second Edition
Printed September 2003
Transmission Division
Tenaga Nasional Berhad
2003, Copyright Reserve
Subject
Page Range
10
11
12
13
14
15
Appendix
Subject
Page Range
INDEX
BACKGROUND
Index-1
Buku TNB Transmission Protection and Control Code of Practice Edisi Pertama yang diterbitkan
enam tahun dahulu pada Mac 1995 memberi garis panduan amalan system perlindungan dan
kawalan tempatan sistem penghantaran TNB. Seperti yang diharapkan, buku ini perlu dikemaskini
dari masa ke masa mengikut perkembangan sistem dan perkembangan teknologi. Edisi kedua ini
merupakan dokumen amalan bukan sahaja untuk sistem penghantaran TNB, malah merangkumi
sistem penjanaan, penghantaran dan pembahagian TNB. Struktur dokumen ini juga berbeza dari
Edisi Pertama. Polisi atau dasar di mana amalan asas dinyatakan supaya amalan dan keperluan
dapat difahami dan dihayati.
Berbeza dengan dokumen yang asal yang memberi maklumat dalam bentuk menyerupai spesifikasi
sistem dan peralatan, dokumen ini menyatakan amalan dalam bentuk yang ringkas. Kehendakkehendak teknikal yang lebih terperinci di buat dalam bentuk Garispanduan Teknikal dan Spesifikasi
Teknikal yang telah dan akan disediakan kelak.
Saya berharap, Edisi Kedua yang dinamakan TNB Protection and Control Code of Practice akan
digunakan sebagai bahan rujukan dalam merekabentuk sistem perlindungan dan kawalan tempatan
bagi sistem Penjanaan, Penghantaran dan Pembahagian TNB. Ianya juga di harap dapat
menyeragamkan amalan-amalan di dalam sistem tenaga TNB.
Akhir kata, saya ingin mengucapkan syabas dan tahniah serta terima kasih kepada kesemua jurutera
dan anggota kerja yang terlibat dalam penerbitan buku ini. Usaha gigih yang dilaksanakan oleh
Kumpulan-Kumpulan Kerja yang berkenaan dalam membuat kajian, penyusunan dan pengumpulan
maklumat dan data adalah disanjungi. Diharap usaha-usaha diteruskan untuk mengulangkaji
dokumen ini dari masa ke semasa.
____________________
Mohd Zainal Azirun
Naib Presiden
(Penghantaran)
Tenaga Nasional Berhad
Tarikh: May 2003
Index-2
ACKNOWLEDGEMENT
The committee would like to thank the following people, from various departments of TNB, namely
the Protection(HQ) Unit and Operation and Maintenance (Protection) of the previous PTT 1
Division, the new Engineering-Secondary Equipment Unit of the Transmission Division, TNBE
and TNBD for their full effort and support in drafting and finalising this valuable document;
Main Committee Members
Abdul Halim Abu Bakar
[Chairman]
Abdul Razak Muda
[Head]
Umar Ridzuan Hawari
[Technical Writer]
Dev Anandan
Zainoren Shukri
Ilham Sulaiman
Abdul Jalal Bakir
Hj. Jamil Samsuri
Nik Sofizan Nik Yusuf
Adnan Hashim
Aminuddin Musa
Contributing Members 2
Abdul Rahman Khalid
Abdul Wahab Zakaria
Ahmad Sharizan Mohd Aminallah
Anthonysamy Rajamanikam
Azzizuddin Zakaria
Chung Yoke Wai
Fadhilah Ahmad
Hasmarizal Hassan
Juliah Tan Sri Mohd Hassan
Khamarudin Mohd Isa
Low Eng Beng
M. Retnasamy
Mohd Asri Arshad
Mohd Faris Abdullah
Mohd Firdaus Yon
Mohd Fuzi Shukor
Mohd Halmi Mad Diah
Mohd Mohyiddin Mohd Nor
Mohd Nizam Mohd Komari
Mohd Thushan Abdul Majid
Nik Nasharuddin Nik Mohamad
Prem Raj
Rofidah Mohamed
Shyful Bahrin Ismail
Siti Jamilah Alias
Subramaniam S.
Sugunan Pillai
Syed Humaiyun Kebir
Zamri Abdul Rahman
Zarina Mohd Said
Zulkarnain Ishak
The committee also significantly value the contributions and comments from different IED
manufacturers and Malaysian local contractors, namely;
IED Manufacturers2
ABB, local and international
Alstom, local and international
Gabungan Sumber Tenaga
SEL
Siemens, local and international
Tamco
Toshiba, local and international
VA Tech, local and international
1
2
Local Contractors2
AMBC Controls
BQE Engineering
EPE
JBE Engineering
Mahkota Technologies
SimPro Engineering
SPM Trading
TopRank Corporation
Trans-System Technology
Xcell Advanced Technology System
Index-3
Index-4
CHAPTER 1
INTRODUCTION
Page 1-1
1.0 INTRODUCTION
1. Background
The first TNB Transmission Protection and Control Code of Practice (COP) describes the
requirements of protection and control for TNB transmission only. It is primarily used as
reference and guidelines for the preparation of tender specification for construction of
TNB substation.
This reviewed document segregates the basic practices from the detail requirements for
easy understanding, and also as a reference to detailed designs of TNB protection system.
Unlike the previous document, which does not cover the generation and distribution
sections, this reviewed document also includes the protection and control policies for all
TNB core businesses i.e. the generation, transmission and distribution sections.
2. Objective
The primary objective is to standardise the policies, schemes and practices on the
protection, control and their supporting equipment for TNB generation, transmission and
distribution systems.
3. Assumption
Basic electrical engineering, protection and control knowledge is required for the
understanding of this document.
4. References
The following standards and engineering practice documents have been the references for
formulating this COP;
1. COP 1st Edition - March 1995,
2. TEPCO Study Group No. 2: Technical Recommendations,
3. Confrence Internationale des Grands Reseaux Electriques (CIGRE),
4. International Electrotechnical Commission (IEC),
5. Institute of Electronics and Electrical Engineering (IEEE),
6. British Standards,
7. Factory and Machinery Act (Safety, Health and Welfare Regulations 1970).
Page 1-2
1. Background
1.
2.
3.
2. Definitions
1.
Substations form vital nodes in high voltage systems. They are used in transmission
network for transporting high power using high voltage levels often over larger
distances, while the distribution networks cover shorter distances with much lower
voltage levels.
In TNB power system, the transmission voltage levels are at 500kV, 275kV and
132kV, while the distribution voltage levels are at 33kV, 22kV and 11kV.
A substation typically consists of the following equipment;
a. Primary equipment,
b. Secondary equipment,
c. Auxiliary equipment.
1.
2.
3.
Substation
Secondary
Substation
Auxiliary
1.
2.
1.
2.
Descriptions
The primary system comprises all equipment, which, in whole or
in part, is in service at the nominal voltage of the electrical power
system.
Two types of primary equipment based on insulating media;
a. Air insulated switchgear (AIS),
b. Gas insulated switchgear (GIS).
For example, circuit breakers, disconnectors (isolators), current
transformers, voltage transformers, surge arresters, power
transformers, etc.
The secondary system comprises all equipment, which is used for
the control, protection, monitoring and measurement of the
primary system. The system collects and processes information
from substation primary equipment.
For example, protection systems, control systems, etc.
Auxiliary systems are those which are required to enable the
primary and/or secondary equipment to operate.
For example, A.C. auxiliary supplies, D.C. auxiliary supplies,
generator set, etc.
Page 1-3
CHAPTER 2
1. General............................................................................................................................10
2. Storage and Interrogation....................................................................................................10
3. Requirement .....................................................................................................................10
4. Quality Assurance ..............................................................................................................10
2.3.2 Numerical Relays ................................................................................................................................................. 11
1. General............................................................................................................................11
2. Storage and Interrogation....................................................................................................11
3. Requirements....................................................................................................................11
4. Pre -processing ..................................................................................................................11
5. Settings...........................................................................................................................12
6. Internal Logics ..................................................................................................................12
7. Input and Output Contacts ..................................................................................................12
8. Data Transmission .............................................................................................................12
9. Quality Assurance ..............................................................................................................12
2.4 Descriptions and Requirements of Protection/Control Schemes and Functions ..................................13
1. Policy ..............................................................................................................................13
2. Distance Relay Schemes......................................................................................................13
3. Directional Earth Fault Comparison Protection..........................................................................13
4. Switch On To Fault.............................................................................................................14
5. Power Swing Blocking.........................................................................................................14
6. Voltage Transformer Supervision...........................................................................................14
7. Evolving Fault Logic............................................................................................................14
8. Inrush Restrain..................................................................................................................14
9. Transformer Restristed Earth Fault ........................................................................................14
Page 2-1
1. Philosophy
1.
2. Maximum
Fault Clearing
Time
1.
For the Main protection relaying scheme, the maximum fault clearing time is defined
as the maximum time interval between the fault inception and the fault clearance of
the faulty element from the power system, and shall not exceed the following;
Type of Fault
132kV
275kV
500kV
150ms
100ms
100ms
600ms
150ms
130ms
130ms
For the Backup protection relaying scheme, the maximum fault clearing time shall not
exceed the short-circuit rating of the primary equipment.
Page 2-2
1. Philosophy
1.
2.
2. Zone of
Protection
1.
The typical type of protection zone and their zones of protection are shown in Figure
2.1A.
b
Substation C
c
c
Substation B
b
Substation A
c
Substation D
Figure 2.1A
Legend
a
b
c
d
3. Concept of
Overlapping
1.
2.
Zone of Protection
Generator
Transformer
Busbar
Overhead Line/Cable
Where the other type of protection zone is not shown in Figure 2.1A, the boundaries
of the zone of protection shall be determined by the locations of the current
transformers, which is conceptually shown in Figure 2.1B and Figure 2.1C.
The location for the current transformers shall form overlapping zone of protections.
CT for Zone A
Zone B
CB
Zone A
CT for Zone B
Figure 2.1B : Typical Bus Tie CT Location
CT for Zone A
Zone B
CB
Zone A
CT for Zone B
Figure 2.1C : Typical Feeder CT Location
Page 2-3
1. Philosophy
1.
2.
CT
Circuit Breaker
VT
Protection
Equipment
TE
Trip
Coil
CB
Mechanism
TE
D.C System 2
D.C System 1
2. Basic Criteria
1.
Criteria
Dependable
Reliable
Secure
Selective
Sensitive
Fast
Simple
Economical
Components
Current Transformer
Voltage Transformer
Telecommunication/Teleprotection Equipment
Direct Current
Circuit Breaker
In order to achieve the basic task of FCS, the following criteria as in Table 2.2A shall
be considered when designing the FCS;
Definition
The degree of certainty that a FCS will operate correctly.
The degree of certainty that a FCS will not fail to operate in the event of faults.
The degree of certainty that a FCS will not mal-operate.
The ability of protection to identify the faulty section and/or phase(s) of a power
system.
The minimum operating quantities that must be available for the FCS to detect an
abnormal condition.
FCS should operate as quickly as possible in order to minimise the duration of
system disturbance.
FCS should utilise minimal hardware components and software logics to perform
intended function.
The cost of the FCS should commensurate with the intended function.
Table 2.2A
Page 2-4
3. General
Protection
Classification
1.
2.
3.
The protection equipment of FCS is generally divided into two relaying classes, which
are described below in Table 2.2B.
For transmission network, the Backup function relays shall be separated from the
Main function relays. Multifunction Backup relays are acceptable.
For distribution network, integrated multifunction relay for Main and Backup
protection functions is allowed.
Relaying Class
Main
Backup
4. Component
Features
1.
TNB practices that the components of FCS shall have the following minimal features
as in Table 2.2C;
FCS Component
Current Transformer
Voltage Transformer
Telecommunication
Equipment
Protection Equipment
DC System 1
DC System 2
(Telecommunication)
Circuit Breaker Trip Coil
Circuit Breaker Mechanism
Minimum Features
Single primary core with multi-core secondary.
Single primary winding with multi-winding secondary.
Telecommunication channels path redundancy.
Single or Dual Main protection with Backup protection.
The supply system is with dual charger and dual battery bank system.
Dual or single Modular switch-mode rectifier with n+1 redundancy
system.
For 500kV and 275kV, dual trip coils per pole of circuit breaker. For
132kV, dual trip coils per circuit breaker. For distribution voltage levels,
one trip coil per circuit breaker.
Hydraulic, pneumatic or spring mechanism.
Table 2.2C
Page 2-5
1. Policy
1.
2.
2. General
Requirement
1.
2.
3.
4.
5.
6.
7.
3. Facilities
1.
2.
4. Relay
Contacts
1.
2.
3.
Relays shall be suitable for operation on D.C system in the range of 80% to 120% of
the nominal 110 volts D.C or 30 Volts D.C, without the use of voltage dropping
devices. This condition also applies for D.C/D.C converter.
All protective relays shall be stable and not be affected by a slow decay, surges, dips,
ripples, spikes and chattering of the D.C supply.
The protective relays shall not give a trip output signal when D.C supply is lost and
during restoration.
Relays shall be housed in dust and moisture proof cases as to IP51 according to IEC
60529.
The relay shall be suitable for duty under tropical climate.
Relays shall be insensitive to capacitive effect of control cable.
All relays shall be correctly rated to the current transformer secondary rating and
voltage transformer secondary rating.
Relay contacts shall be suitably rated for tripping, control and indication purposes.
Separate and sufficient number of contacts shall be provided for tripping, control and
alarm functions.
The effect of electrolysis shall be minimal.
5. Labels
1.
Relays, whether mounted in panels or not, shall be provided with clearly inscribed
labels describing their application and rating, including at least the following;
a. Function, e.g., Distance, Overcurrent,
b. Model and Version, e.g., REL561 V1.2, 7VK512 V1.0,
c. Serial number,
d. Nominal input ratings of D.C voltage, A.C voltage, A.C current and A.C
frequency.
6. Operating and
Reset Time
1.
The following table, Table 2.3A, shows the maximum pickup time, maximum
operating time and maximum reset time for the protection relays;
Voltage
Level
275kV and
above
132kV
33kV and
below
1
2
Protection
Maximum
Pickup Time
Maximum
Operating
Time
30 ms
40 ms
40 ms
50 ms
50 ms
50 ms
Maximum
Reset Time
30 ms
70 ms2
40 ms
100 ms2
100 ms
100 ms
Only applies if the element is IDMT Overcurrent or IDMT Earth Fault or Thermal Overload protection.
Except for Breaker Failure protection relays, which shall have maximum permitted reset time of 20ms.
Page 2-6
7. Operating
Characteristics
1.
Relaying Method
Current Differential
Current Comparison
Distance
Directional Earth Fault Comparison
Breaker Failure
Overcurrent
Earth Fault
Directional Overcurrent
Standby Earth Fault
Biased Differential
High Impedance Differential
Restricted Earth Fault
High Impedance Busbar Differential
Low Impedance Busbar Different ial
Overexcitation
Frequency
Synchronism
New operating principles may be considered subject to its proven performance, with
historical records, of the intended functions and through Transient Network Analysis
(TNA) tests.
3.
The control/protection relays to be used in the TNB system shall have the following
functionality, but not limited to, as in Table 2.3C;
Autoreclose
Synchronism
Operating Principle
Vector Differential
Phase Comparison3
Quadrilateral with Directional Impedance
Current Operated together with Permissive signalling
Definite Time Current Operated together with Start
Initiation, with phase segregated measurement
IDMT in accordance to IEC 60255-3
Definite Time
Instantaneous
IDMT in accordance to IEC 60255-3
Definite Time
Instantaneous
IDMT in accordance to IEC 60255-3
Definite Time
Instantaneous
Definite Time Current Operated
Circulating Current with restraint element
Circulating Current with stabilising element
Circulating Current with stabilising element
Circulating Current with stabilising element
Vector Differential/Circulating Current with restraint
element
Inverse time base on Volt/Hz measurement
Definite Time base on Volt/Hz measurement
Current dependant in accordance to IEC 60255-8
Light Detection w ith Definite Time
Definite Time Voltage Operated
Instantaneous Voltage Operated
Rate of change Voltage Operated
Definite Time Voltage Operated
Instantaneous Voltage Operated
Rate of change Voltage Operated
See section 5.2.1.2
Table 2.3B
2.
Control Relay
1.
2.
3.
1.
2.
3.
1.
2.
3.
1.
1.
1.
1.
1.
1.
1.
2.
3.
1.
1.
2.
3.
1.
2.
3.
1.
Overload
Arc Protection
Voltage
8. Control/
Protection Relay
Functionality
1.
1.
1.
1.
1.
1.
2.
3.
4.
1.
2.
Main
Functionality
Single-pole autoreclose
Three-pole autoreclose
Single and Three-pole autoreclose
Evolving fault logic
Voltage check
Synchronism check
Table 2.3C
1.
1.
Additional
Functionality
2-breakers controller4
Page 2-7
9. Relay
Functionality
1.
The Main protection relays to be used in the TNB system shall have the following
functionality, but not limited to, as in Table 2.3D;
Main Protection
Relay
Current Differential
1.
2.
3.
Main
Functionality
Current Differential
Intertrip
CT ratio correction factor
Current
Comparison
1.
2.
3.
Current Comparison
Intertrip
CT ratio correction factor
Distance
1.
2.
3.
3 forward zones
1 reverse zone
DEFC protection scheme with Current
Reversal and Echo functions (Separate
communication channel from Distance)
PSB
SOTF
VTS
PUTT
POTT
Differential element
Overcurrent Check
Intertrip
Biased Differential
CT ratio correction factor
Vector group correction factor
Inrush Restrain
Differential element
Through Fault Stability Restraint
Differential element
Through Fault Stability Restraint
Differential element
Through Fault Stability Restraint
Two-out -of-two operating zones
Two-out -of-two operating criteria
CT ratio correction factor
Self monitoring
Undervoltage
Overvoltage
Individual two-stage Volt/Hz elements
Dual Timers
Underfrequency
Overfrequency
Pilot Wire
Differential
Biased Differential
(Transformer)
High Impedance
Differential
Restricted Earth
Fault
High Impedance
Busbar Differential
Low Impedance
Busbar Differential
Voltage
Overexcitation
Frequency
Overcurrent
Earth Fault
5
6
4.
5.
6.
7.
8.
1.
2.
3.
1.
2.
3.
4.
1.
2.
1.
2.
1.
2.
3.
1.
2.
3.
1.
2.
1.
2.
1.
2.
1.
2.
3.
4.
5.
1.
2.
3.
4.
Three-elements
IDMT in accordance to IEC 60255-3
Definite Time
Instantaneous
Reverse Blocking Scheme
IDMT in accordance to IEC 60255-3
Definite Time
Instantaneous
Reverse Blocking Scheme
Table 2.3D
Additional Functionality
1.
2.
3.
4.
1.
2.
3.
4.
1.
2.
Transfer Trip
Overcurrent
Autoreclose5
Synchronism5
Transfer Trip
Overcurrent
Autoreclose 5
Synchronism5
Autoreclose 5
Synchronism5
1.
1.
2.
Overexcitation
Overvoltage
1.
CT Supervision
1.
Individual four-stage of
under/over voltage
1.
2.
1.
Individual four-stage of
under/over voltage
Rate of change of frequency
TCS6
1.
TCS 6
For 275kV and above systems, the autoreclose and synchronism functions shall be separated from the Main relays.
Trip Circuit Supervision for distribution voltage level
Page 2-8
10. Backup
Relay
Functionality
1.
The Backup protection relays to be used in the TNB system shall have the following
functionality, but not limited to, as in Table 2.3E;
Backup Protection
Relay
Distance
Breaker Failure
Overcurrent and
Undervoltage7
Overcurrent
Earth Fault
Directional Overcurrent
Standby Earth Fault
Thermal Overload
7
8
1.
2.
3.
4.
5.
1.
2.
3.
1.
2.
1.
2.
3.
4.
2.
3.
4.
1.
2.
3.
1.
1.
Main
Functionality
2 forward zones
1 reverse zone
PSB
VTS
SOTF
Dual Current Elements
Dual Timers
Intertrip
Overcurrent Definite Time
Undervoltage Definite Time
Three-elements
IDMT in accordance to IEC 60255-3
Definite Time
Instantaneous
IDMT in accordance to IEC 60255-3
Definite Time
Instantaneous
IDMT in accordance to IEC 60255-3
Instantaneous
VTS
Individual two-stage Definite Time
Individual two-stage current
dependant in accordance to IEC
60255-8
Table 2.3E
1.
Additional
Functionality
Thermal Overload
1.
TCS 6
1.
TCS 6
1.
1.
Instantaneous
Page 2-9
1. General
1.
All the requirements for protection relays as mentioned in section 2.3 also applies.
2. Storage and
Interrogation
1.
The static relay shall be able to conserve all its latest settings, registered values and
operation indications in the event of D.C power failure.
3. Requirement
1.
All static relays shall satisfy the following Standards, as tabulated in Table 2.3.1A;
Requirement
Electromagnetic
Compatibility
Electrical
Insulation
Mechanical
Standard
IEC 60255-22-1,
Class III
IEC 60255-22-2,
Class III
IEC 60255-22-4,
Class IV
IEC 60255-11
IEC 60255-5
IEC 60068-2-6
IEC 60255-21-1,
Class I
IEC 60255-21-1,
Class II
IEC 60255-21-2,
Class I
Test Descriptions
1.
High frequency
1.
Electrostatic discharge
1.
1.
2.
3.
1.
1.
1.
4. Quality
Assurance
1.
2.
The static relays shall have proven MTBF value of more than 70 years.
The static relays shall carry at least 10 years availability of support and parts from
the purchase date.
Page 2-10
1. General
1.
All the requirements for protection relays as mentioned in section 2.3 also applies.
2. Storage and
Interrogation
1.
The numerical relay shall be able to conserve all its latest logics, equations, settings,
registered values, events, oscillography and operation indications in the event of D.C
power failure for at least 168 hours.
The numerical relay shall be able to continuously keep track of its internal clock (time
and date) in the event of D.C power failure.
The numerical relays shall be able to be interrogated via human machine interface
(HMI) built onto the relays.
The numerical relays shall be able to be interfaced to the substation control system
(SCS) and conventional control system via IEC 60870-5-103 protocol or/and via
hardwire connection. The IEC 60870-5-103 interface shall be dedicated and
independent.
The numerical relays shall be able to be interrogated through relay password security
from local and remote computers via TCP/IP protocol. The interface shall be
dedicated and independent.
2.
3.
4.
5.
3. Requirements
1.
2.
3.
All numerical relays shall be equipped with continuous automatic internal selfsupervision functions that give indications and identifications for any internal relay
errors and failures. The self-supervision functions shall not affect the performance of
any protection functions during normal operation.
All numerical relays that are ranked as Main Protection shall be equipped with eve nt
recording and oscillosgraph recording functions, while relays that are ranked as
Backup Protection shall be equipped with at least event recording function. Where
the relays have combination of both the Main and Backup Protection, it shall be
equipped with event and oscillography recording functions.
All numerical relays shall satisfy the following Standards, as tabulated in Table
2.3.2A;
Requirement
Electromagnetic
Compatibility
Electrical
Insulation
Mechanical
Standard
IEC 60255-22-1,
Class III
IEC 60255-22-2,
Class III
IEC 60255-22-3,
Class III
IEC 60255-22-4,
Class IV
IEC 60255-6
IEC 60255-11
IEC 60255-5
IEC 60068-2-6
IEC 60255-21-1,
Class I
IEC 60255-21-1,
Class II
IEC 60255-21-2,
Class I
Test Descriptions
1.
High frequency
1.
Electrostatic discharge
1.
1.
1.
1.
2.
3.
1.
1.
1.
4. Preprocessing
1.
2.
3.
The isolation transformers inside the numerical relay shall be able to perform to the
accuracy in the range of 1% of its input values.
The effective sampling frequency shall be in the range of 800 Hz to 4000 Hz.
The analog-t o-digital converters shall not have conversion errors of more than 2%.
Page 2-11
5. Settings
1.
2.
6. Internal
Logics
1.
In any case, where the internal logics of the numerical relay are configurable, it shall
be made standard according to TNB practice, and approved by the relevant Technical
Committee of Transmission Division.
7. Input and
Output Contacts
1.
Adequate numbers of input and output contacts shall be provided and shall be
configurable.
The input and output contacts configurations shall be made standard according to
TNB practice, and approved by the relevant Technical Committee of Transmission
Division.
2.
8. Data
Transmission
1.
2.
3.
9. Quality
Assurance
1.
2.
For numerical relays that use teleprotection signalling, e.g. Distance relays, Breaker
Failure relays, etc., the permissive and direct intertrip schemes shall be of a 110 volts
DC interface to the teleprotection equipment. No external D.C/D.C converter
between the relay and the teleprotection equipment shall be allowed.
For numerical relays that use teleprotection data channels, e.g. Current Differential
relays, Current Comparison relays, etc., shall be able to handle a transmission delay
of not more than 15ms.
The numerical relays that use teleprotection data channels shall use 64kbit/sec codirectional complying with ITUT G.703 recommendations. An optical-t o-electrical
interface converter may be allowed to cater for interferences between the relay and
the communication equipment.
The numerical relays shall have proven MTBF value of more than 70 years.
The numerical relays shall carry at least 10 years availability of support and parts
from the purchase date.
Page 2-12
1. Policy
1.
All protection/control relays shall follow the protection/control schemes and functions
described in section 2.4.
2. Distance
Relay Schemes
1.
The Distance relay permissive schemes, namely Underreach and Overreach schemes,
shall be incorporated in the Distance relay.
The following table, Table 2.4A, describes the definition of the Distance relay
permissive schemes;
2.
Permissive
Scheme
Underreach
Overreach
Variation
Descriptions
Permissive
Underreach
Transfer Trip
(PUTT)
1.
2.
3.
Permissive
Overreach
Transfer Trip 1
(POTT1)
1.
2.
3.
4.
4.
5.
Permissive
Overreach
Transfer Trip 2
(POTT2)
1.
2.
3.
4.
5.
6.
Legend
ZM
T
CR
CS
Table 2.4A
3. Directional
Earth Fault
Comparison
Protection
1.
2.
3.
4.
5.
The Directional Earth Fault Comparison (DEFC) protection shall be incorporated in the
Main protection Distance relay, using Permissive Overreach Transfer Trip scheme
with current reversal logic to avoid unwanted tripping for parallel feeders.
The DEFC scheme shall be incorporated with a built -in, independent and selectable
timer to introduce delay in tripping, after detecting the fault and receiving the carrier.
The DEFC scheme shall be equipped with necessary Echo logic to cater for remote CB
open-condition of a protected line.
The DEFC scheme is preferably to be equipped with necessary Weak Infeed logic to
cater for no infeed or weak infeed conditions of a protected line.
The carrier contacts and channels for the Distance protection and the DEFC
protection shall be separated.
Page 2-13
4. Switch On To
Fault
1.
2.
3.
4.
5.
5. Power Swing
Blocking
1.
2.
3.
6. Voltage
Transformer
Supervision
1.
2.
3.
4.
7. Evolving Fault
Logic
1.
2.
3.
8. Inrush
Restrain
1.
2.
9. Transformer
Restristed Earth
Fault
1.
2.
The Switch On To Fault (SOTF) function shall be incorporated in the all Distance relay
using impedance based measurement.
The coverage of the SOTF shall be from the relaying point to a selectable Distance
relay zones, preferably Zone 2 Forward and Zone 3 Reverse, with instantaneous
tripping.
The SOTF function shall be initiated only after the opening of CB, with a short time
delay.
The SOTF function shall be deactivated after the CB has closed, after a sensible
period of time.
For each feeder, only one SOTF function shall be activated, preferably inside the
Backup Distance protection relay.
Power Swing Blocking (PSB) function shall be incorporated in the Distance relay using
impedance based measurement.
The Distance relay shall be blocked through PSB function from any operation when
the power swing condition is detected.
The PSB function shall be blocked during the dead time of 1-pole autoreclose cycle.
Evolving Fault Logic (EVFL) function shall be incorporated in the autoreclose relay.
Evolving fault is classified as fault that occurs after the clearance of the first-detected
fault and during the dead time of the first-detected fault.
The EVFL shall initiate changes from 1-pole autoreclose cycle to 3-pole autoreclose
cycle if evolving fault is detected by the Main protection relays, and reclose after the
3-pole autoreclose dead time elapses. [Refer to section 5.1.4].
The Inrush Restrain, or Inrush Current Restrain Logic, shall be incorporated in the
transformer Biased Differential relay, and preferably in Current Differential relay and
Current Comparison relay as well.
The Inrush Restrain shall have an option to block the relay from issuing trip
command during inrush current conditions, such as during switch on of
transformer/line/cable and paralleling of transformers/lines/cables.
Transformer Restricted Earth Fault (REF) protection scheme shall protect at least
90% of the intended transformers winding.
The transformer REF protection relay shall be rank as Main protection, and be
independent from other relays.
Page 2-14
CHAPTER 3
3.1
3.2
3.3
3.4
1. Background ....................................................................................................................... 3
2. Philosophy......................................................................................................................... 3
3. Equipment Selection............................................................................................................ 3
4. Symbols and Terms............................................................................................................. 3
Overhead Line Feeder Protection .......................................................................................................................... 4
1. Policy ............................................................................................................................... 4
2. Additional Policy Requirements.............................................................................................. 4
3. Teleprotection.................................................................................................................... 4
4. Autoreclose........................................................................................................................ 5
5. Specific Requirements.......................................................................................................... 5
6. Functional Scheme.............................................................................................................. 5
Underground Cable Feeder Protection ................................................................................................................ 6
1. Policy ............................................................................................................................... 6
2. Additional Policy Requirement................................................................................................ 6
3. Teleprotection.................................................................................................................... 6
4. Autoreclose........................................................................................................................ 6
5. Specific Requirements.......................................................................................................... 6
6. Functional Scheme.............................................................................................................. 7
Transformer Protection ............................................................................................................................................ 8
1. Policy ............................................................................................................................... 8
2. Requirements..................................................................................................................... 8
3. Functional Scheme.............................................................................................................. 9
Bus Tie Protection....................................................................................................................................................10
1. Background ......................................................................................................................10
2. Philosophy........................................................................................................................10
3. Specific Requirement ..........................................................................................................10
3.4.1 Bus Coupler Protection....................................................................................................................................... 10
1. Policy ..............................................................................................................................10
2. Additional Policy Requirements.............................................................................................10
3. Functional Scheme.............................................................................................................10
3.4.2 Bus Section Protection........................................................................................................................................ 11
3.5
3.6
3.7
3.8
3.9
1. Policy ..............................................................................................................................11
2. Additional Policy Requirements.............................................................................................11
3. Functional Scheme.............................................................................................................11
Capacitor Protection................................................................................................................................................12
1. Policy ..............................................................................................................................12
2. Protection Requirements.....................................................................................................12
3. Control Requirements.........................................................................................................12
4. Functional Scheme.............................................................................................................12
Reactor Protection ...................................................................................................................................................13
1. Policy ..............................................................................................................................13
2. Protection Requirements.....................................................................................................13
3. Control Requirement...........................................................................................................13
4. Functional Scheme.............................................................................................................13
Breaker Failure Protection .....................................................................................................................................14
1. Policy ..............................................................................................................................14
2. Requirements....................................................................................................................14
3. Specific Requirements.........................................................................................................14
4. Tripping Circuit Requirements...............................................................................................14
Busbar Protection ....................................................................................................................................................15
1. Policy ..............................................................................................................................15
2. Additional Policy Requirements.............................................................................................15
3. Functional Scheme.............................................................................................................15
4. Specific Low Impedance Scheme Requirements.......................................................................15
5. Specific High Impedance Scheme Requirements.......................................................................15
6. Specific Arc Protection Scheme Requirement ...........................................................................16
7. Specific Reverse Blocking Signal Scheme Requirements.............................................................16
8. Tripping Circuit Requirements...............................................................................................16
1 Breaker Busbar Protection .............................................................................................................................17
Page 3-1
1. Policy ..............................................................................................................................17
2. Additional Policy Requirements.............................................................................................17
3. Functional Scheme.............................................................................................................17
4. Additional Scheme Requirements..........................................................................................17
5. Tripping Circuit Requirements...............................................................................................17
3.10 Generator Protection.............................................................................................................................................18
1. Policy ..............................................................................................................................18
2. Functional Scheme.............................................................................................................18
3. Tripping Matrix ..................................................................................................................20
3.11 Load Shedding Schemes.....................................................................................................................................21
1. Policy ..............................................................................................................................21
2. Functional Scheme.............................................................................................................21
3. General Requirements for Underfrequency/Undervoltage Scheme ................................................21
4. General Requirements for Autotransformer Intertripping............................................................21
5. Special Requirement ...........................................................................................................21
6. Alarm and Indication ..........................................................................................................21
3.12 Special Protection Scheme .................................................................................................................................22
1. Policy ..............................................................................................................................22
2. Schemes..........................................................................................................................22
Page 3-2
1. Background
1.
This section describes the current practice on protection schemes and zone of
protection for TNB system.
2. Philosophy
1.
All TNB primary equipment shall be protected against damages from any type of
faults.
All external parties (e.g. independent power producers, co-generators, bulk
customers, etc.) primary equipment, that are connected and interfaced with TNB
primary equipment shall be protected against damage from any type of faults, and
shall follow the setup and schemes specified in this document .
2.
3. Equipment
Selection
1.
2.
3.
4. Symbols and
Terms
1.
2.
3.
All Main, Backup, Control and auxiliary relays shall be limited to the TNB Accepted
Relay List.
The acceptance of the relays shall follow the all the guidelines as in section 2.0 and
TNB Guidance Notes of Acceptance on relays.
Other protection related equipment shall be subjected to the consent and acceptance
from the Transmission Technical Working Committee (TTWC).
In this section only, the symbols as in Table 3.0A, are used inside functional table for
describing the relaying schemes.
In this section, the abbreviations as in Table 3.0B, are used for describing special
terms for TNB system.
In this section, all the relaying codes shall follow the protective device code in
Appendix B.
Symbols in
Functional Tables
+
or
( )
[ ]
Terms
PMU
PPU
SSU
Definition
With, and shall not be integrated in one relay except given the
symbol ( ).
Or
Backup functions and other functions shall be integrated inside
one relay. However for new projects, all Backup functions shall be
integrated in one relay.
Specific mode for the relaying scheme
Table 3.0A
Definition
Pencawang Masuk Utama, normally comprises of 500kV, 275kV
and 132kV substations.
Pencawang Pembahagian Utama, normally comprises of 33/11kV
substations
Stesen Suis Utama, normally comprises of 33kV and below
switching stations.
Table 3.0B
Page 3-3
1. Policy
1.
The overhead line shall be protected against faults and equipped with appropriate
autoreclosing facilities to reduce the outage period. In general, the overhead lines
shall be protected as tabulated in Table 3.1A.
Voltage
275kV and above
132kV
132kV
(GIS)
33kV and below
(Outgoing
Feeder)
>2
downstream
substation
=2
downstream
substation
1.
2.
3.
1.
2.
1.
2.
3.
1.
2.
1.
2.
Scheme
Main Distance protection and Unit protection, or duplicated
Unit protection
Backup Distance protection and Thermal Overload protection
Further Backup by Breaker Failure protection
Main Distance protection or Unit protection
Backup Distance protection
Main Distance protection or Unit protection
Backup Distance protection
Further Backup by Breaker Failure protection
Main Unit protection1
Backup Overcurrent and Earth Fault protection (Instantaneous
& IDMT)1
Main Overcurrent and Earth Fault protection (Instantaneous)1
Backup Overcurrent and Earth Fault protection (IDMT)1
Table 3.1A
2. Additional
Policy
Requirements
2.
For new installation, all protection relays shall be of the numerical type. For Breaker
Failure protection, refer to section 3.7.
1.
For 275kV systems and above, Main Distance protection and Unit protection may be
used for upgrading purposes, while duplicated Unit protection shall be used for all
new installations.
Duplicated Unit protection relays shall either have different principles, or same
principle but different manufacturer.
Main Distance protection relays at local end and all remote ends shall have similar
Distance characteristic, and compatible DEFC scheme.
All Unit protection shall use digital communications.
Unit protection and Distance protection relays shall have sufficient contacts to initiate
the Breaker Failure protection and other protection, control and signalling functions.
All Main protection relays shall be able to initiate autoreclose cycle. For distribution
networks, autoreclose shall also be initiated by Backup protections.
For distribution networks, a scheme for live line maintenance purposes shall be
incorporated.
2.
3.
4.
5.
6.
7.
3.
Teleprotection
1.
2.
3.
4.
5.
6.
For Current Differential (CD) relays and Current Comparison (CC) relays, the data
interface shall be 64kbit/sec complying with ITUT G.703 recommendation.
For 275kV and above system, the teleprotection data and signals shall be provided
through a duplicated multiplexed optical fibre communication only.
For 132kV, the teleprotection data shall be provided through multiplexed optical fibre
communication only.
For 132kV, the teleprotection signals shall be provided through preferably multiplexed
optical fibre, or PLC communication.
For 132kV and above, direct optical fibre connections shall be used for special
applications only.
For 33kV system and below, direct optical fibre connections shall be applied.
Page 3-4
4. Autoreclose
1.
5. Specific
Requirements
1.
The above -stipulated policy requirements shall be applied to all new installations.
However new installations may match the existing equipment, or both ends of the
substations shall be upgraded.
For 1 breaker system, all protection trip commands shall be issued to both CBs in a
diameter that controls the connected feeders.
2.
6. Functional
Scheme
1.
Voltage
Level
500kV
275kV
132kV
The functional scheme for all transmission and distribution systems are as tabulated
in Table 3.1B below;
Route
Length
>25km
Comm.
Medium
OF
=25km
OF
>10km
OF
=10km
OF
>10km
OF
PLC
=10km
OF
PLC
132kV
(GIS)
<10km,
with t-off
>10km
PLC/OF
OF
PLC
=10km
OF
PLC
33kV, 22kV
and 11kV
<10km,
with t -off
>2
subtations
=2
substations
PLC/OF
OF
N/A
Functional Scheme
Rank
Scheme
M1
87CD
M2
87CC or 87CD or (21Z[PUTT] + 67DEFCS[POTT])
BK1
(21Z + 49OL)
BK2
50BF
M1
87CD
M2
87CC or 87CD
BK1
(21Z + 49OL)
BK2
50BF
M1
87CD
M2
87CC or 87CD or (21Z[PUTT] + 67DEFCS[POTT])
BK1
(21Z + 49OL)
BK2
50BF
M1
87CD
M2
87CC or 87CD
BK1
(21Z + 49OL)
BK2
50BF
M1
87CC or 87CD
BK
21Z
M1
(21Z[PUTT] + 67DEFCS[POTT])
BK
21Z
M1
87CC or 87CD
BK
21Z
M1
(21Z[POTT2] + 67DEFCS[POTT])
BK
21Z
M1
(21Z[POTT2] + 67DEFCS[POTT])
BK
21Z
M1
87CC or 87CD
BK
21Z + 50BF
M1
(21Z[PUTT] + 67DEFCS[POTT])
BK
21Z + 50BF
M1
87CC or 87CD
BK
21Z + 50BF
M1
(21Z[POTT2] + 67DEFCS[POTT])
BK
21Z + 50BF
M1
(21Z[POTT2] + 67DEFCS[POTT])
BK
21Z + 50BF
M1
87CC1 or 87CD1
BK
(50OC + 50EF + 51OC + 51EF) 1
M1
(50OC + 50EF) 1
BK
(51OC + 51EF) 1
Table 3.1B
Page 3-5
1. Policy
1.
2.
The underground cable and gas-insulated line shall be protected against severe
damage caused by faults and insulation breakdown. In general, the underground
cable feeders shall be protected as tabulated in Table 3.2A.
For new installation, all protection relays shall be of the numerical type.
Voltage
275kV and above
1.
2.
3.
132kV
1.
2.
132kV
1.
(GIS)
2.
3.
33kV and below (Out going 1.
Feeder)
2.
2. Additional
Policy
Requirement
1.
2.
3.
4.
5.
6.
7.
3.
Teleprotection
1.
2.
Scheme
Duplicated Main Unit protection
Backup Distance protection and Thermal Overload protection
Further Backup by Breaker Failure protection
Main Unit protection
Backup Distance protection and Thermal Overload protection
Main Unit protection
Backup Distance protection and Thermal Overload protection
Further Backup by Breaker Failure protection
Main Unit protection1
Backup Overcurrent and Earth Fault protection1
Table 3.2A
Duplicated Main Unit protection shall either have different principles, or same
principle but different manufacturer.
Optical fibre shall be used for Unit protection systems for all new cable installations.
For loop-in/loop-out (LILO) and extension projects that involve Pilot Wire protection,
the existing systems may be matched, or both ends of the substations shall be
upgraded.
Unit protection relays shall have sufficient contacts to initiate the Breaker Failure
protection and other protection, control and signalling function.
For feeders with combination of both overhead line and cables, all protection
schemes shall follow the underground cable scheme policy.
Aerial Bundle Cable (ABC) installation shall be treated as underground cable feeder.
For transmission feeder installations with combination of overhead line and cable, the
cable section shall be equipped with Unit protection, as Backup protection, to
determine the faulted section of the feeder. The Unit protection shall only be used to
block the autoreclose operation at all ends.
Direct optical fibre communication shall be used. Teleprotection data and signals
shall be provided through multiplexed optical fibre communication only for special
arrangements.
For Current Differential relays and Current Comparison relay, the data interface shall
be 64kbit/sec complying with ITUT G.703 recommendation.
4. Autoreclose
1.
2.
5. Specific
Requirements
1.
The above -stipulated policy requirements shall be applied to all new installations.
However new installations may match the existing equipment where necessary, or
both ends of the substations shall be upgraded.
For 1 breaker system, all protection trip commands shall be issued to both CBs in a
diameter that controls the underground cable feeders.
2.
Page 3-6
6. Functional
Scheme
1.
The following table (Table 3.2B) described the functional detail of the required
underground feeder protection scheme:
Voltage Level
275kV and above
Comm.
Medium
OF
132kV
OF
132kV
(GIS)
33kV, 22kV and
11kV
OF
OF
Rank
M1
M2
BK1
BK2
M1
BK
M1
BK
M1
BK
Functional Scheme
Scheme
87CD
87CC or 87CD
(21Z + 49OL)
50BF
87CD
(21Z + 49OL)
87CD
(21Z + 49OL) + 50BF
87CD1 or 87CC1
(51OC + 51EF) 1
Table 3.2B
Page 3-7
1. Policy
1.
2.
3.
4.
Type
Autotransformer
500/275/132kV
Earthing
Transformer
1.
2.
3.
4.
5.
1.
2.
3.
4.
5.
1.
2.
3.
4.
5.
1.
2.
Protection Scheme
Duplicated Main Unit protection
Main Transformer Guards protection
Main Over-excitation protection (volts per hertz)
Backup Distance protection
Further Backup by Breaker Failure protection
Main Unit protection
Main Transformer Guards protection
Main Restricted Earth Fault protection
Backup Overcurrent and Earth Fault protection
Backup Standby Earth Fault protection
Main Unit protection
Main Transformer Guards protection
Main Restricted Earth Fault protection
Backup Overcurrent and Earth Fault protection
Backup Standby Earth Fault protection
Main Transformer Guards protection
Backup Standby Earth Fault protection
Local Transformer
1.
Power
Transformer
132/(33-22-11)kV
Power
Transformer
(33-22)/11kV
1.
Control Scheme
Automatic Voltage
Controller
1.
Automatic Voltage
Controller
1.
Automatic Voltage
Controller
1.
Automatic Voltage
Controller, where
required.
Automatic Voltage
Controller, where
required.
1.
Table 3.3A
2. Requirements
1.
2.
3.
4.
5.
6.
7.
Duplicated Main protection shall have a different operating principle. Normally Biased
Differential and High Impedance Differential principles are used.
For High Impedance Differential protection, current transformers shall be provided for
each phase at the neutral end of the autotransformer.
If the voltage levels are 500kV and/or 275kV, each CB for the transformers shall be
equipped with Breaker Failure protection.
Tertiary winding of autotransformer shall be equipped with Backup Overcurrent and
Earth Fault protection.
Where the tertiary winding of autotransformer is connected to reactor/capacitor and
grounded through earthing transformer, the earthing transformer and the connecting
power cable shall be protected using Restricted Earth Fault protection and Standby
Earth Fault, which shall be ranked as Backup Protection. An optional circuit
breaker/fuse for the tertiary winding is greatly encouraged.
The LV side of earthing and local transformers shall be protected by suitable rated
fuses.
Alarm and tripping indications for all types of transformers shall always be separated.
Page 3-8
3. Functional
Scheme
1.
The following table, Table 3.3B, describes the functional details of the required
transformer protection scheme;
Transformer
Type
Autotransformer
500/275/132kV
Power
Transformer
132/(33-22-11)kV
M
TXGT
TXGA
BK
Power
Transformer
(33-22)/11kV
M
TXGT
TXGA
BK
Earthing
Transformer
TXGT
TXGA
BK
M
Local Transformer
Rank
M1
M2
TXGT
TXGA
BK
Required if tertiary winding is connected to other equipment and grounded through earthing transformer.
Page 3-9
1. Background
1.
The Bus Tie consists of two different but similar types, which are tabulated in Table
3.4A below;
Function Descriptions
As a tie to couple two distinctive electrical buses
As a tie to segregate one distinctive electrical bus to two or more sections
Table 3.4A
2. Philosophy
1.
For protection purposes, the Bus Tie is used to segregate the faulty section of power
system, and also to help in the fault clearing process. Hence, the bus tie shall be
adequately equipped with relevant protection scheme to serve the above objectives.
3. Specific
Requirement
1.
Special care shall be taken when live-transfer procedure is being carried out to
prevent any unwanted operation of the bus tie protection schemes.
1. Policy
1.
The Bus Coupler for 500kV, 275kV and 132kV shall be able to perform bus
separation function under Backup protection operation. Therefore, it shall be
equipped with protection sc hemes as in Table 3.4.1A below;
Voltage
500kV & 275KV
132KV
33kV
(PMU only)
2. Additional
Policy
Requirements
1.
3. Functional
Scheme
1.
2.
3.
1.
1.
1.
Functional Scheme
Distance Protection
Distance Protection, or Overcurrent Protection and Earth Fault
Protection with Undervoltage Check
Overcurrent Protection, Earth Fault protection and Standby Earth
Fault Protection
Table 3.4.1A
For transmission systems, the Distance Protection shall be used for all new
installations, while the Overcurrent and Earth Fault Protection with Undervoltage
Check may be used for scheme upgrading purposes.
The relays shall be installed on each side of bus coupler.
For Distribution substations, namely PPU and SSU, the bus coupler protection scheme
is not required, unless stated otherwise.
The following table, Table 3.4.1B, describes the functional details of the required bus
coupler protection scheme;
Voltage
Level
500kV & 275kV
132kV
33kV (PMU only)
Rank
M1
M1
BK
M
BK
M
Functional Scheme
Scheme
Part of Busbar protection
Part of Busbar protection
21Z
Part of Busbar protection
21Z or ((51OC + 27UV) + (51EF + 27UV))
(51OC + 51EF) + 51SBEF1
Table 3.4.1B
Page 3-10
1. Policy
1.
The Bus Section shall be equipped with protection units as in Table 3.4.2A below;
Voltage
500kV, 275kV
and 132kV
33kV, 22kV & 11kV
2. Additional
Policy
Requirements
1.
3. Functional
Scheme
1.
2.
Functional Scheme
1.
1.
For Distribution substation, namely PPU, the bus section protection scheme is only
required on the 11kV system.
For SSU, the bus section protection scheme is not required, unless stated otherwise.
The following table, Table 3.4.2B, describes the functional details of the required bus
section protection scheme;
Voltage
Level
500kV & 275kV
132kV
33kV, 22kV & 11kV
Rank
M1
M2
BK
M1
BK
M
Functional Scheme
Scheme
Part of Busbar protection
Part of Busbar protection
(51OC + 27UV)
Part of Busbar protection
(51OC + 27UV)
51SBEF1
Table 3.4.2B
Page 3-11
1. Policy
1.
2.
Capacitor protection is required to prevent any damage on capacitor bank and all
associated equipment for all internal faults. This is to minimise loss of life due to
overload and overvoltage.
The type of the capacitor and its associated protection and control can be categorised
as in Table 3.5A below;
1.
2.
3.
4.
5.
Shunt,
33kV and below
6.
1.
2.
3.
4.
2. Protection
Requirements
1.
2.
3.
4.
5.
6.
3. Control
Requirements
1.
2.
3.
4. Functional
Scheme
1.
Protection
Scheme
Main Unbalance protection
Main Overload protection
Internal fuse protection
Backup Overcurrent protection
and Earth Fault protection
Backup Overvoltage protection
and Undervoltage protection
Backup Undercurrent protection
Main Unbalance protection and
Overload protection
Internal fuse protection
Backup Overcurrent protection
and Earth Fault protection
Backup Undercurrent protection
Table 3.5A
1.
2.
1.
Control
Scheme
Automatic Reactive Controller
(see Section 6.4.2)
Synchronous Switching relay
The Main protection relays shall be independent of the Backup protection relays.
The current relays and the voltage relays for the Backup protection shall be
independent of each other.
The capacitor protection shall be able to isolate the capacitor bank from any overload
and overvoltage condition.
The capacitor protection shall be able to detect and isolate the capacitor bank from
faulty individual capacitor unit.
The capacitor protection shall be able to isolate the capacitor bank from any voltage
loss in the system.
Voltage transformer supervision shall be provided for indication purposes.
The control scheme must provide for an automatic Opening and Closing of the
capacitor bank and CB into the system.
The control scheme shall prevent the associated switchgear from reclosing for an
allowable amount of time after opening to allow discharge of capacitor.
The capacitor banks CB operation shall be closed using point-on-wave switching.
The following table, Table 3.5B, describes the functional details of the required
capacitor protection scheme;
Rank
M1
M2
BK
M1
BK
Page 3-12
1. Policy
1.
2.
3.
Reactor
Type
Shunt
Reactor protection is required to prevent any damage on reactor bank and all
associated equipment for all internal faults and to minimise loss of life due to
overexcitation.
Reactor zone of protection shall include switchgear and reactor.
All other
interconnecting equipment, e.g. transformer cable tail, transformer tertiary winding
and earthing transformer, shall be protected by their relevant protection.
Types of reactor and its associated protection can be categorise as below, in Table
3.6A;
Connection
to..
Transformer
Tertiary
1.
2.
3.
4.
Shunt
Shunt
2. Protection
Requirements
Bus
Line/Cable
1.
2.
3.
4.
5.
3. Control
Requirement
1.
2.
4. Functional
Scheme
Reactor
Type
Shunt
1.
As
1.
2.
Protection
Scheme
Main Differential protection and
Overexcitation protection (V/Hz)
Main Reactor guard protections
Backup Overcurrent protection
Backup Negative Phase Sequence
protection
above
Main Differential protect ion
Main Reactor guard protections
Table 3.6A
1.
2.
Control
Scheme
Automatic Reactive
Controller (see Section
6.4.2)
Synchronous Switching
relay, where required.
As above
The main protection relays shall be independent of the Backup protection relays.
The reactor protection shall be able to isolate the reactor bank from overexcitation
conditions.
The reactor protection shall be able to isolate the reactor bank for all low magnitude
and high magnitude winding faults.
Reactor guard protection shall provide protection for all internal faults and inter-turn
fault.
For shunt reactor connected to the overhead line/underground cable, the zone of
protection for overhead line/underground cable shall also cover that of shunt reactor.
Adequate intertrip facilities shall also be provided to trip the relevant circuit breakers.
The control scheme must provide for an automatic opening and closing of the reactor
bank CB into the system.
Where Synchronising Switching relay is used, the reactor bank CB operation shall be
opened using point -on-wave switching.
The following table, Table 3.6B, describes the functional details of the required
reactor protection scheme;
Connection to..
Shunt
Transformer
Tertiary
Bus
Shunt
Line/Cable
Rank
M1
BK
M1
BK
M1
Page 3-13
1. Policy
1.
2.
3.
2. Requirements
1.
2.
3.
4.
5.
6.
3. Specific
Requirements
1.
2.
3.
4.
4. Tripping
Circuit
Requirements
1.
2.
The purpose of Breaker Failure protection is to clear the faults that have been
correctly detected by the appropriate protection, but for which the associated circuit
breakers (CBs) have failed to operate.
In the event of the CBs failing to open within pre -selected time, the Breaker Failure
protection shall initiate tripping of all adjacent circuit breakers connected to the same
section of the busbar. This shall include the provision for initiating direct intertrip of
any remote infeeds CBs via teleprotection channels.
All 500kV, 275kV, 132kV(GIS) and 132kV side of autotransformer CB shall be
equipped with phase-segregated circuit Breaker Failure protection (BFP).
The maximum permitted reset time of current measuring elements of BFP relays shall
not be more than 20ms.
The tripping contact of the BFR shall not be of latching type.
The circuit Breaker Failure relay shall consist of two Current elements for each pole
and two Timer elements for each circuit breaker. Each combination of Current and
Timer elements shall be connected in parallel to form stage 1 and stage 2 elements.
See section 2.3.10.1, Table 2.3E.
For 132kV AIS type substation where the adjacent substation is GIS type substation,
the necessary intertrip receive facility and tripping facility shall also be provided.
For 275kV and above, the tripping circuit of Breaker Failure protection shall be shared
with the High Impedance Busbar protection tripping circuit.
For 132kV GIS, the tripping circuit of Breaker Failure protection shall be shared with
the Main Busbar protection.
Page 3-14
1. Policy
1.
2.
The busbar shall be adequately protected and the Busbar protection shall be sensitive,
stable, selective, secure and highly reliable. The Busbar protection zone of protection
shall be provided for each busbar section in any substation busbar configuration system.
In general, busbars shall be protected as in the following table, Table 3.8A;
Voltage Level
500kV and 275kV
132kV
33kV, 22kV and 11kV
2. Additional
Policy
Requirements
1.
3. Functional
Scheme
1.
2.
2.
1.
2.
1.
1.
Functional Scheme
High Impedance Busbar Protection, with
Low Impedance Busbar Protection
High Impedance or Low Impedance Busbar Protection
Reverse Blocking Signal schemes or Arc Protection Scheme or High
Impedance Busbar Protection
Table 3.8A
Where it is required, intertripping scheme to the remote end shall be provided for
complete clearing of faults.
The D.C supply for the Busbar protection scheme at the busbar protection panels
shall be separated from other protection schemes.
The following table (Table 3.8B) describes the functional details of the required
busbar protection scheme:
For retrofitting purposes at 132kV AIS installation, the Low Impedance Busbar
protection may be considered.
Voltage
Level
500kV & 275kV
Busbar
132kV
GIS
AIS
GIS
AIS
4. Specific Low
Impedance
Scheme
Requirements
1.
2.
3.
4.
5. Specific High
Impedance
Scheme
Requirements
1.
2.
3.
4.
5.
6.
7.
Type
All
Functional Scheme
Rank
Scheme
M1
87BBHI
M2
87BBLO
M1
87BBLO or 87BBHI
M1
87BBHI
M1
Reverse Blocking Schemes or 87BBHI
M1
Reverse Blocking Scheme or Arc Protection Relay
Table 3.8B
The Low Impedance Busbar protection shall employ two different methods of
measurement, with 2-out -of-2 operations, where one of the methods shall use biased
differential.
For 132kV system, the current transformers for low Impedance Busbar protection
shall be dedicated for each bay.
If the relays are to be installed for retrofitting works, the current transformers may
be shared with Backup protection relays.
For 500kV and 275kV system, the current transformers for the Low Impedance
Busbar protection relays may be shared with the Breaker Failure protection.
The High Impedance relaying scheme shall employ several segregated zones
(discriminating zones), and one overall zone for the whole busbar (check zone).
Each discriminating zone and check zone shall operate to form two-out -of-two
tripping arrangement.
For 33kV, 22kV and 11kV only one zone shall be employed.
The current transformers shall be dedicated for each discriminating and check zone.
A fault in one discriminating zone shall cause tripping of that zone without resulting
operation of the other healthy discriminating zones.
Busbar Protection CT supervision relay shall be provided for each discriminating zone
to block from operation when CT circuits for Busbar Protection is open-circuited.
CT requirements for Busbar protection shall be referred to section 14.1.
Page 3-15
6. Specific Arc
Protection
Scheme
Requirement
1.
2.
The following table, Table 3.8C, describes the scheme requirement for the Busbar Arc
Protection.
The selection of which scheme to be used is largely dependent upon case-by-case
basis.
Arc Protection
Schemes
Scheme 1
(Master & Slave)
Scheme 2
(Selective)
Requirement
1.
2.
3.
4.
1.
2.
3.
7. Specific
Reverse
Blocking Signal
Scheme
Requirements
1.
2.
3.
4.
8. Tripping
Circuit
Requirements
1.
2.
3.
4.
5.
The relays used for the Reverse Blocking Signal Scheme shall employ two protection
functions, which are IDMT protection and Definite Time protection functions.
For the incomer feeder relays, the IDMT protection function shall be coordinated with
upstream and downstream relays, and the Definite Time protection function shall be
blocked by the Definite Time protection function of the outgoing feeders relays. If
the incomer feeder relays do not receive the blocking signal, the relays shall trip
(with time delay) the related busbar CBs.
For the outgoing feeder relays, the IDMT protection function shall be coordinated
with upstream and downstream relays, and the Definite Time protection function
shall be configured to send blocking signal to the incomer feeder relays Definite Time
function.
For all the Reverse Blocking Signal Scheme relays, all the related blocking and
tripping input/output contacts shall be dedicated to their functions.
The tripping circuit for Busbar protection shall be separated from other protection trip
circuits except for Breaker Failure protection.
For 500kV and 275kV, separate tripping circuits shall be provided for the Main 1 and
Main 2 Busbar protection relays.
Dedicated High Impedance Busbar protection tripping relays shall be provided for
each circuit breaker.
The tripping circuits for High Impedance Check Zone shall use the negative check
method with cathodic protection scheme.
Adequate and suitable isolating links shall be provided for each tripping circuit.
Page 3-16
1. Policy
1.
Voltage Level
500kV and 275kV
2.
1.
2.
132kV
2. Additional
Policy
Requirements
1.
2.
3.
4.
5.
3. Functional
Scheme
1.
132kV
1.
2.
3.
4.
5. Tripping
Circuit
Requirements
1.
2.
The duplicate Low Impedance busbar relays shall be from differe nt manufacturers.
The busbar tripping relay shall be duplicated, except for the 132kV voltage level.
The Stub protection shall be in the form of Differential protection.
The DC supply for the Busbar protection at the busbar protection panels shall be
separated from other protection schemes.
Only the bus-side circuit breakers shall trip when the busbar protection for the 1
breaker operates.
The following table, Table 3.9B, describes the functional details of the required
busbar protection scheme:
Voltage
Level
500kV and 275kV
4. Additional
Scheme
Requirements
1.
Rank
M1
M2
M3
M1
M2
Functional Scheme
Scheme
87BBHI or 87BBLO
87BBLO
87S
87BBHI or 87BBLO
87S
Table 3.9B
The tripping circuit for 1 Breaker Busbar protection shall be separated from other
protection trip circuits, but shared with the Breaker Failure protection.
For 500kV and 275kV, separate tripping circuits shall be provided for the Main 1 and
Main 2 busbar protection relays.
Page 3-17
1. Policy
1.
2.
2. Functional
Scheme
1.
2.
The generator protection shall consider its functional design, protected zones and
fast discriminative tripping, in the following manner;
a. Functions to protect against various types of faults due to electrical and
mechanical stresses and temperature rise,
b. Overlapping main protection zones and the shortest tripping time,
c. Backup protection with short operating time,
d. Degree of protection system depends on the unit rated power, significance
to the power system and its type.
For large generator/transformer units, protection schemes shall be grouped into
completely independent electrically isolated system, with its own auxiliary supply.
Such scheme shall consider group redundancy and also permits on-load testing of
each group by standard testing devices belonging to the generator protection
Type of Protection
l
l
Distance
l
l
100% Stator Earth Fault
l
l
l
l
95% Stator Earth Fault
l
l
l
l
Overvoltage
l
l
l
Negative Phase Sequence
l
l
l
Underfrequency
l
l
l
Reverse Power
Stage 1
Stage 2
l
l
Pole Slip
l
l
l
l
Stator Overload
l
l
Rotor Overload
l
l
l
Rotor Earth Fault
l
l
Overcurrent
l
l
l
Underexcitation
l
l
Generator Inter-Turn
l
l
l
l
Undervoltage
l
l
Power Plant Isolation
Table 3.10A: Typical General Protection Functions for Generator
Legend:
l - Required
- Optional
3.
Page 3-18
Type of Protection
Protection Grouping
1
2
l
Generator Differential
l
Overall Differential
l
Distance (HV-Side Step-Up Transformer)
l
Distance (Generator Stator Common)
l
100% Stator Earth Fault
l
90% Stator Earth Fault
Overvoltage
Stage 1
Stage 2
Overexcitation (LV -Side Step-Up Transformer)
Stage 1
Stage 2
Negative Phase Sequence
Stage 1
Stage 2
Underfrequency
Stage 1
Stage 2
Reverse Power
Stage 1
Stage 2
l
Pole Slip
l
Stator Overload
l
Rotor Overload
l
Rotor Earth Fault
l
Unit Transformer Overcurrent
l
Unit Transformer Buchholz
l
Step-Up Transformer Buccholz
l
Step-Up Transformer Differential
l
Step-Up Transformer Restricted Earth Fault
l
Step-Up Transformer Earth Fault
l
HV Interconnector Differential
l
Underexcitation
l
Excitation Transformer Overcurrent
l
Generator Inter-Turn
l
Undervoltage
l
Power Plant Isolation
Table 3.10B: Typical Protection Functions for Generator/Transformer Unit
Page 3-19
Generator Differential
Overall Unit Differential
Distance (HV-Side Step-Up
Transformer)
Distance (Generator Stator
Common)
100% Stator Earth Fault
90% Stator Earth Fault
Overvoltage
l
l
Stage 1
Underfrequency
Stage 1
Stage 2
Stage 2
Stage 1
Stage 1
Stage 2
Stage 2
l
Pole Slip
l
Stator Overload
l
Rotor Overload
l
Earth Fault
l
Interconnector Differential
l
Underexcitation
l
Generator Inter-Turn
l
Stage 1
Stage 2
Signaling
De-excitation
Type of Protection
Turbine Emergency
Stop Valve
Protection
Grouping
Unit Auxiliary CB
The general and typical tripping matrix is as shown below in Table 3.10C. The actual
implementation shall depend on the functions available to the generator system.
Generator CB
1.
Power System CB
3. Tripping
Matrix
Page 3-20
1. Policy
1.
2.
3.
2. Functional
Scheme
1.
Where the load shedding scheme is required, the following Table 3.11A, describes its
functional protection scheme;
Voltage Level
275kV and 132kV
33kV, 22kV and 11kV
Autotransformer 275/132kV
3. General
Requirements
for
Underfrequency
/Undervoltage
Scheme
1.
2.
3.
4.
5.
Functional Scheme
27UV + 81UF
27UV + 81UF
Autotransformer Intertripping
Table 3.11A
For transformer in PMU, the load shedding scheme relay shall be connected to the
high voltage side.
The relaying schemes voltage inputs shall be tapped directly from busbar voltage
transformer. Where busbar voltage transformer is not available, the voltage inputs
shall be tapped from voltage selection scheme.
Each busbar section shall have its own load shedding relay.
The load shedding scheme shall be able to trip single circuit breaker or/and multiple
circuit breakers at one time.
The distribution transformer in PPU and SSU, the load shedding relays shall be
mounted on the LV bus coupler or bus section relay panel.
4. General
Requirements
for
Autotransformer
Intertripping
1.
5. Special
Requirement
1.
For SCS equipped substation, the load shedding scheme information shall be made
available.
6. Alarm and
Indication
1.
Alarm and indication facilities, which are meaning and adequate, shall be provided at
each individual bay, where the scheme is designated to trip.
Adequate and meaningful labels shall be provided for the D.C circuits and the tripping
circuits.
2.
2.
Page 3-21
1. Policy
1.
2.
3.
Special Protection Scheme shall be dedicated for a particular protect ion function.
Typically, the Special Protection Scheme is designed on case-by-case basis.
The approval of any Special Protection Scheme shall be from the Transmission
Technical Working Committee.
2. Schemes
1.
Currently, the Special Protection Scheme includes, but not limited to the following;
a. Force Generator Tripping Scheme,
b. Islanding Scheme,
c. Interface feeder protection scheme to Large Power Consumer.
Page 3-22
CHAPTER 4
TRIPPING
Page 4-1
4.0 TRIPPING
1. Philosophy
1.
2.
All tripping elements shall be correctly designed and configured to the designated
relay tripping output contacts.
All tripping logics and schemes shall be correctly designed to trip the relevant circuit
breakers.
Page 4-2
1. Policy
1.
All tripping logic and command shall be designed to open the correct faulty phase or
all the phases of the relevant circuit breakers.
2. Tripping Logic
1.
The tripping logic for the Main and Backup relays are divided into primary equipment
applications and voltage levels, and shown in the tables, Table 4.1A, 4.1B and 4.1C,
below;
Phase-to-phase
Phase-to-phase-to
ground
3. Three-phase
4. Three-phase-toground
All type of faults
3-Pole
1.
2.
3.
4.
1.
2.
3.
4.
All
3-Pole
3-Pole
3-Pole
1.
2.
132kV
33kV, 22kV &
11kV
Main Relay
Elements
21Z (Zone 1)
21Z (Permissive)
87CD (Within LZOP)
87CC (Within LZOP)
21Z (Zone 2)
21Z (Zone 3)
21Z (Zone 3R)
DEFC
Main Relay Elements
Backup Relay
Elements
N/A
Table 4.1A
Backup Relay
Elements
All Backup Relay
Elements
All Backup Relay
Elements
Backup Relay
Elements
All Backup Relay
Elements1
All Backup Relay
Elements1
Pole discordance and load shedding scheme do not initiate Circuit Breaker Failure protection.
Page 4-3
1. Policy
1.
2.
3.
4.
2. Requirements
1.
3. 500kV and
275kV Systems
1.
All circuit breakers shall be provided with adequate and suitable tripping scheme.
Tripping scheme shall be designed to trip the CB upon receiving the tripping
command from the protection relays and control command, without any additional
delay.
For all the 132kV and above circuit breakers, redundant trip circuits shall be provided.
Lockout trip facility shall be provided to prevent inadvertent closing of circuit breaker,
except for 33kV, 22kV and 11kV underground cable circuit breakers.
All the tripping schemes shall follow the conceptual drawings of as shown in
Appendix A.
2. The trip contact shall be of heavy-duty type suitable for direct energising of trip coil.
2. The trip contact shall be of high-speed type to meet the minimum system critical fault
clearance time.
3. All Main protection relays shall initiate direct tripping to the CBs trip coil, and also
initiate all master trip relays (MTR).
4. All Backup protection relays shall initiate all master trip relays.
5. The tripping circuit shall not employ external auxiliary relay for direct tripping of
circuit breakers.
6. Each lockout relay shall trip all the trip coils.
7. An energised trip coil shall be de-energised only by circuit breaker auxiliary contact.
8. Suitable and adequate tripping isolating links shall be provided for each trip coil.
9. Separate and dedicated D.C supply shall be used for each trip coil.
10. Tripping circuit shall be independent of Substation Control System circuitry and
scheme.
11. For High Impedance protective relays where tripping contacts are limited,
multiplication of contacts for initiating Breaker Failure relays and MTR using highspeed and heavy-duty auxiliary relays may be considered.
The requirement for tripping scheme for the 500kV and 275kV systems are tabulated
in the Table 4.2A below;
Equipment
Overhead Line
2.
Basic Requirement
Two MTRs shall be provided for
each circuit breaker.
Main 1 and Main 2 protection
relays shall directly energise trip
coil 1 and trip coil 2 of the
circuit breaker respectively.
Underground Cable
1.
As Overhead Line
1.
Auto-transformer
1.
As Overhead Line
1.
Bus Tie
1.
Circuit Breaker
Failure
1.
1.
2.
1.
1.
2.
Special Requirement
In case of fault during reclaim time,
both MTR shall be initiated by
Autoreclose relay.
Main 1 and Main 2 protection relays
shall in itiate MTR1 and MTR2
respectively, for faults that do not
allow autoreclose. MTRs shall not
intiate AR blocking.
Main 1 and Main 2 protection relays
shall initiate both MTR1 and MTR2
respectively.
Table 4.2A
Page 4-4
4. 132kV System
1.
The requirement for tripping scheme for the 132kV system is tabulated in the Table
4.2B below;
Equipment
Overhead Line
1.
2.
Basic Requirement
One MTR relay shall be provided
for each circuit breaker.
Main protection relay shall
directly energise both trip coils
of the circuit breaker.
1.
2.
Underground Cable
1.
As Overhead Line
1.
Power Transformer
1.
As Overhead Line
1.
2.
3.
Bus Coupler
1.
Bus Section
Circuit Breaker
Failure
1.
1.
As bus coupler
For required circuit breakers.
1.
1.
2.
Special Requirement
In case of fault during reclaim time,
MTR shall be initiated by Autoreclose
relay.
Main protection relay shall initiate
MTR, for faults that do not allow
autoreclose. MTR shall not intiate AR
blocking.
Main protection re lay shall directly
energise both trip coils of the circuit
breaker and simultaneously initiate
MTR.
As Underground cable.
Intertrip scheme shall be made for
tripping the HV side CB and LV side
CB simultaneously. The HV to LV
Intertrip shall trip the LV side CB
directly, while the LV to HV Intertrip
shall initiate the HV side MTR before
tripping the HV side CB.
The LV Backup relays shall trip only
the LV circuit breaker.
Backup Protection shall initiate the
MTR.
Stage 1 retrip local CB.
Stage 2 trip all adjacent CBs.
Table 4.2B
5. 33kV, 22kV
and 11kV
Systems
1.
The requirement for tripping scheme for the 33kV and 11kV systems are tabulated in
the Table 4.2C below;
Equipment
Overhead Line
1.
Underground Cable
1.
Power Transformer
1.
Bus Coupler
1.
Bus Section
1.
6. Intertrip
1.
Basic Requirement
Main and Backup protection relay shall
directly energise the trip coil of the circuit
breaker.
Main and Backup protection relays shall
directly energise the trip coil of the circuit
breaker.
As 132kV Power Transformer
Backup protection relay shall
energise the trip coil.
As bus coupler
Table 4.2C
Special Requirement
1.
As 132kV Power
Transformer
directly
Intertrip tripping schemes and facilities shall be provided when the need for total
clearance of faults is essential and required for the system and the following
situations;
a. T-off condition,
b. Transformer feeder condition,
c. GIS type busbar.
Page 4-5
CHAPTER 5
1. General Requirements.......................................................................................................... 5
2. Specific Requirements.......................................................................................................... 5
5.2.2 Synchronising for Manual Close .......................................................................................................................... 5
1. General Requirements.......................................................................................................... 5
2. Specific Requirements.......................................................................................................... 6
Page 5-1
1. Philosophy
1.
For overhead lines, after the clearance of transient faults, the circuit breakers shall be
automatically reclosed so as to enhance system stability and increase overall system
availability.
2. Policy
1.
2.
All the overhead line feeders shall be equipped with autoreclose facilities.
All 132kV and above feeders shall be equipped with synchronising facilities to enable
safe interconnection of two sources of supply.
Separate synchronising facilities shall be made available for autoreclose and manual
closing.
3.
3. General
Requirements
1.
2.
3.
The autoreclose and synchronism functions shall be in the same relay, except for
manual closing purposes.
For 275kV and above, the autoreclose and synchronism functions shall be separated
from the Main protection relays.
For 132kV and below, the autoreclose and synchronism functions may be integrated
in the Main protection relay.
Page 5-2
1. Policy
1.
2.
3.
2. General
Requirements
1.
3. Selection
1.
All Backup protection relays/elements shall not initiate autoreclose. All Main
protection relays shall be able to initiate autoreclose cycle. For distribution system
networks, autoreclose may be initiated by both protections.
2. The master trip relays (MTR) shall not initiate autoreclose blocking.
3. Autoreclose scheme shall be able to determine the CB status (position and condition)
prior to initiating an autoreclose sequence.
4. Manual closing of CB shall inhibit autoreclose for a short period of time.
5. For single shot application, autoreclose shall not take place when fault occurs during
reclaim time.
6. During single-pole autoreclose, pole discordance, PSB and DEFC shall be inhibited for
the duration of the circuit breaker reclosing signal.
7. The dead time shall be separately adjustable for single-pole and three-pole
autoreclose.
8. The reclaim time, which shall start after the dead time has elapsed, shall be
separately adjustable, preferably for single-pole and three-pole autoreclose.
9. Separate counters for monitoring the single-pole and three-pole autoreclose attempts
shall be provided.
10. Autoreclose shall be initiated as shown by Table 5.1A, while other than specified in
Table 5.1A shall initiate lockout condition.
2.
3.
4. Specific
Requirements
1.
2.
3.
5. Evolving Fault
Logic
1.
2.
1
2
Single-pole and/or three pole, single-shot, autoreclose facilities shall be provided for
275kV and above overhead line circuit breakers.
Three-pole, single-shot, autoreclose facilities shall be provided for 132kV overhead
line circuit breakers.
For 33kV and below overhead line, three-pole multiple-shot autoreclose facilities shall
be made available. Sectionalising scheme shall be provided where necessary.
A 4-way autoreclose scheme selector switch (OFF / 1-pole / 1+3-pole / 3-pole) shall
be made available at the control panel for 275kV and above system.
A 2-way autoreclose scheme selector switch (ON/OFF) shall be made available at the
control panel for 132kV system.
A 2-way autoreclose scheme selector switch (ON/OFF) shall be made available at the
control panel for 33kV system and below.
For 1 Breaker system, separate autoreclose facilities shall be provided for each
breaker in a diameter that controls overhead line feeders.
For 1 Breaker system, all autoreclose facilities in a diameter shall be able to engage
priority scheme to determine the closing sequence priority between the circuit
breakers.
For all multi-terminal and transformer-fed feeders, specific autoreclose requirements
shall be considered on a case-by-case basis.
If the autoreclose selector switch is in the 1+3 pole selection mode, and if a second
single-phase-t o-earth fault occurs during the FSPAR1 dead time, three-pole tripping
shall take place with the DTPAR2 autoreclose cycle starting subsequently.
If the autoreclose selector switch is in the 1 pole selection mode, and if a second
single-phase-t o-earth fault occurs during the FSPAR dead time, three-pole tripping
shall take place without autoreclose.
Page 5-3
3-Pole
1+3-Pole
1.
2.
Phase-to-phase
Phase-to-phase-to
ground
OFF
1-Pole
3-Pole
1+3-Pole
132kV
1.
2.
3.
1.
Single-phase-toground
Phase-to-phase
Phase-to-phase-to
ground
OFF
ON
OFF
ON
OFF
Table 5.1A
Autoreclose
1.
1.
2.
3.
4.
Main Relay
Elements
All
21Z (Zone 1)
21Z (Permissive)
87CD (Within LZOP)
87CC (Within LZOP)
1.
2.
3.
4.
5.
6.
1.
2.
3.
4.
1.
2.
3.
4.
5.
6.
1.
1.
1.
2.
3.
4.
5.
6.
1.
2.
3.
4.
5.
6.
1.
1.
2.
3.
4.
5.
6.
1.
1.
2.
3.
4.
1.
21Z (Zone 1)
21Z (Permissive)
87CD (Within LZOP)
87CC (Within LZOP)
DEFC (POTT)
DEFC (Echo)
21Z (Zone 1)
21Z (Permissive)
87CD (Within LZOP)
87CC (Within LZOP)
21Z (Zone 1)
21Z (Permissive)
87CD (Within LZOP)
87CC (Within LZOP)
DEFC (POTT)
DEFC (Echo)
All
All
21Z (Zone 1)
21Z (Permissive)
87CD (Within LZOP)
87CC (Within LZOP)
DEFC (POTT)
DEFC (Echo)
21Z (Zone 1)
21Z (Permissive)
87CD (Within LZOP)
87CC (Within LZOP)
DEFC (POTT)
DEFC (Echo)
All
21Z (Zone 1)
21Z (Permissive)
87CD (Within LZOP)
87CC (Within LZOP)
DEFC (POTT)
DEFC (Echo)
All
87CD (Within LZOP)
87CC (Within LZOP)
50
51
All
DTPAR
Lockout
FSPAR
FSPAR
DTPAR
Lockout
Lockout
DTPAR
DTPAR
Lockout
DTPAR
Lockout
DTPAR
Lockout
Page 5-4
1. Policy
1.
1. General
Requirements
1.
2.
2. Specific
Requirements
1.
2.
3.
The synchronising relay shall be independent of any Main protection relays, except
for 132kV and below. The synchronising relay shall be located in the Main protection
relay panel.
The voltages to the synchronising relay shall be wired through MCBs with indication
facilities.
The synchronising relay shall be able to directly measure the following parameters of
the incoming and running voltages;
a. Phase angle difference,
b. Frequency difference,
c. Voltage difference,
d. Voltage check.
The synchronising relay shall be able to monitor the following conditions;
a. Dead line-live bus (DLLB),
b. Live line-dead bus (LLDB),
c. Dead line-dead bus (DLDB),
d. Synchronism check (SYNC).
Synchronising-fail timer and alarming functions shall be made available.
1. General
Requirements
1.
2.
3.
4.
5.
6.
7.
8.
Page 5-5
2. Specific
Requirements
1.
2.
3.
4.
All the three Specific Requirements of Synchronising for Autoreclose (section 5.2.1.2)
shall be followed.
A key operated synchronising selector switch for each circuit breaker shall be
interlocked such that synchronising can only take place on one circuit at a time.
For SCS equipped substation, the switch shall have two positions, as tabulated below
in Table 5.2.2A.
For conventional substation, the switch shall have three positions, as tabulated below
in Table 5.2.2B.
Position
MANUAL SYNCHRONISE
1.
1.
2.
6.
Page 5-6
CHAPTER 6
CONTROL: OPERATIONS
1. Policy ............................................................................................................................... 4
2. Requirements..................................................................................................................... 4
6.2.2 Sequential Switching Operation ............................................................................................................................ 4
1. Policy ............................................................................................................................... 4
2. Requirements..................................................................................................................... 4
6.2.3 Setting Of Reference Value .................................................................................................................................... 5
1. Policy ............................................................................................................................... 5
6.2.4 Manual Tap Changer Control................................................................................................................................. 5
1. Policy ............................................................................................................................... 5
2. Requirements..................................................................................................................... 5
6.2.5 Selection Of Auto/Manual Mode Of Automatic Regulating Devices ................................................................... 5
1. Policy ............................................................................................................................... 5
2. Requirements..................................................................................................................... 5
6.2.6 Control Of Parallel Operation Of Transformer...................................................................................................... 6
1. Policy ............................................................................................................................... 6
2. Requirements..................................................................................................................... 6
6.2.7 Resetting Of Master Trip Relays ............................................................................................................................ 6
1. Policy ............................................................................................................................... 6
2. Requirements..................................................................................................................... 6
6.2.8 Selection Of Relay Group Settings........................................................................................................................ 6
1. Policy ............................................................................................................................... 6
2. Requirements..................................................................................................................... 6
6.3 INTERLOCKING SCHEMES ...................................................................................................................................... 7
1. Policy ............................................................................................................................... 7
2. Definitions......................................................................................................................... 7
3. General Requirements.......................................................................................................... 7
4. Level of Interlocking............................................................................................................ 7
6.3.1 Station Level Interlock............................................................................................................................................ 8
1. Policy ............................................................................................................................... 8
2. Requirements..................................................................................................................... 8
6.3.2 Bay Level Interlock ................................................................................................................................................. 8
1. Policy ............................................................................................................................... 8
2. Requirements..................................................................................................................... 8
6.3.3 Apparatus Level Interlock ...................................................................................................................................... 8
1. Policy ............................................................................................................................... 8
6.3.4 Interlocking Schemes............................................................................................................................................. 9
1. Policy ............................................................................................................................... 9
2. Requirement ...................................................................................................................... 9
6.4 AUTOMATIC CONTROL FUNCTIONS ..................................................................................................................10
1. Policy ..............................................................................................................................10
2. Definition .........................................................................................................................10
3. Overview..........................................................................................................................10
6.4.1 Automatic Voltage Control (AVC)....................................................................................................................... 10
1.
2.
3.
4.
1. Policy ..............................................................................................................................11
2. Requirements....................................................................................................................11
Page 6-1
1. Background
1.
This chapter;
a. Describes the philosophy adopted for operating and controlling the power
system equipment within TNB substations.
b. Defines the policies and requirements established to support the control
operating philosophy.
2. Philosophy
1.
3. Definition
1.
The table below, Table 6.0A below describes several terms that are commonly used
for control operation purposes;
Terms
Network Level
Station Level
Bay Level
Apparatus Level
Definition
National Load Dispatch Center (NLDC) and Distribution Regional Control
Centers (RCC).
Station Human Machine Interface (HMI) and Station Level Controller (SLC)
for substations equipped with SCS.
Control panel for conventional control system or back-up panel for SCS and
RTCC for transformers.
Control facility at individual switching devices and transformer OLTC.
Table 6.0A
4. Overview
1.
The control operation, as a process, can be summarized into three major control
stages;
a. Cont rol initiation,
b. Interlocking,
c. Control execution.
Page 6-2
1. Policy
1.
Manual
a.
b.
c.
d.
2. Requirements
1.
2.
Only one level shall be permitted to initiate control of the equipment at any instance.
At the location of control levels, with exception of the network level, it shall be
possible to transfer control authority to the next lower priority level.
All control operations are permitted only when the authority for the device is selected
to the respective control level.
The control priority level for substation equipped with SCS shall be as in Table 6.1A.
The control priority for substation with conventional control system shall be as in
Table 6.1B.
3.
4.
5.
Priority
Lowest
|
|
Highest
Control priority level for substat ion equipped with conventional control system
Level
Source of Control
Priority
Level 1
Network Level
Lowest
|
Level 2
Bay Level
Highest
Level 3
Apparatus Level
Table 6.1B
For switching devices, switching operation at this level shall only be for maintenance and emergency opening.
Page 6-3
1. Policy
1.
The following control operation shall be made available at control level specified in
each sub items;
a. Switching operation,
b. Sequence switching operation,
c. Settings of reference value,
d. Manual tap changer control,
e. Selection of Auto/Manual mode,
f. Control of Parallel Operation of Transformer,
g. Resetting of Master Trip Relays,
h. Selection of Relay Group Settings.
1. Policy
1.
2. Requirements
1.
Switching operation from network, station and bay level shall be of three steps
control SELECT COMMANDEXECUTE.
A switching operation shall be completed before the next operation is initiated within
a substation.
Earthing switch shall only be operable at apparatus level.
Earthing switch for AIS installation shall be mechanically operated with electrical
release facility.
2.
3.
4.
1. Policy
1.
The following sequential switching operations for operational purposes shall be made
available at network and station level;
a. Live transfer of individual bay,
b. Live transfer of multiple selected bays,
c. Isolation and normalization of power transformers,
d. Isolation and normalization of overhead line or underground feeders,
e. Isolation of bus section and bus coupler,
f. Isolation of center breaker in a one and a half breaker system.
2. Requirements
1.
The sequence operation shall stop at the unsuccessful command stage and shall not
rollback.
Each individual switching command within the sequence operation shall check with
interlocking scheme.
Each switching operation in the sequence shall wait for successful status confirmation
before commencing subsequent operation.
For substations equipped with SCS, the sequence operation shall be configured in the
SCS.
For substations with conventional control system, the option for the sequence
operation shall be configured in the SCADA system.
2.
3.
4.
5.
Page 6-4
1. Policy
1.
Setting of reference value for the following automatic regulating devices shall be
made available at network, station and bay levels;
a. Automatic Voltage Controller (AVC),
b. Automatic Reactive Controller (ARC),
c. Generator Controller MW set-point,
d. Static VAR Compensator (SVC),
e. Capacitor and reactor controller.
1. Policy
1.
Manual tap changer control shall be made available at network, station and bay
levels, which include raising and lowering the tap changer position.
2. Requirements
1.
When the AVC is in automatic mode, facility to be able to override to manual control
of tap changer shall be made available.
Cancellation of the above override command shall revert the AVC to automatic mode.
In the case that transformers are in parallel operation, the manual tap changer
control shall only be done on master selected transformer.
When the transformer is in local mode, network and station level operation of tap
changer shall be inhibited.
2.
3.
4.
1. Policy
1.
Selection of automatic and manual mode of automatic regulating devices, e.g. AVC,
ARC and equivalent, shall be made available at network, station and bay levels.
2. Requirements
1.
At network and station levels, selection of modes from automatic to manual shall
require an override command, while selection of mode from manual to aut omatic
shall require an override cancel command.
At bay level, the selection of modes shall be by automatic/manual selection only.
2.
Page 6-5
1. Policy
1.
Facility for parallel operation of transformer shall be made available at station and
bay levels.
2. Requirements
1.
The control facilities for parallel control of transformers shall cater for the following
operation;
a. Changing of Master/Follower or independent in Master/Follower mode,
b. Changing of transformer grouping, if available,
c. Accepted mode of operation of transformer paralleling shall be either that of
Master/Follower method or other approved paralleling method.
If Master/Follower method is used, it may only be applied to transformers with
identical characteristic.
2.
1. Policy
1.
Resetting of any master trip relays, where applicable, shall be made available at
network, station and bay levels.
2. Requirements
1.
1. Policy
1.
Changing of relay pre -tested group settings, where applicable, shall be made
available at station level.
2. Requirements
1.
2.
Page 6-6
1. Policy
1.
2.
2. Definitions
1.
All switching devices within a substation shall be interlocked in a manner that ensures
they always operate safely.
The interlocking scheme shall be provided to ensure correct sequence of operation of
the switching devices.
Terms
Station Level
Interlock
Bay Level Interlock
3. General
Requirements
1.
2.
3.
Category
Operational
Maintenance
4. Level of
Interlocking
1.
Definition
Interlocking scheme incorporating information of more than one bay in the
substation.
Interlocking scheme for a specific bay.
Table 6.3A
For substation equipped with SCS, status information for all switchgear used in
interlocking shall be defined by both normally open and normally close auxiliary
contacts.
Status information for all switchgear use for interlocking shall not be derived from
multiplied contacts.
The interlocking scheme shall satisfy two distinct categories as follows, in Table 6.3B;
Description
Interlocking associated with normal system operation and switching, and
intended to ensure that a pre-determined switching sequence is satisfied.
Interlocking associated with a series of switching operations to render the
equipment or sections of the station safe for access and maintenance by
personnel.
Table 6.3B
Page 6-7
1. Policy
1.
Any failure to comply with the station level interlocking scheme shall block the
command from being executed.
2. Requirements
1.
For substation equipped with SCS, the station level interlocking scheme shall be
implemented. The implementation of station level interlocking shall be in either
station level or bay level unit by means of software. Electrical hardwired interlock
shall be implemented for primary equipment local control and remote CB emergency
control.
For substation with conventional control system, the station level interlocking scheme
shall be implemented by means of hardwired electrical interlock.
For GIS substation, software interlock scheme shall be implemented. Additional
electrical hardwired interlock scheme is preferable.
Facility for live transfer shall be provided, and the bus tie protection schemes shall be
trip-block during the live transfer. An alarm shall be provided.
For distribution voltage level, the implementation of hardwired electrical interlock
and/or software may be permitted.
2.
3.
4.
5.
1. Policy
1.
Any failure to comply with the bay level interlocking scheme shall block the command
from being executed.
2. Requirements
1.
For substation equipped with SCS, the bay level interlocking scheme shall be
implemented in the bay unit by means of software. Electrical hardwired interlock
shall be implemented for primary equipment local control and remote CB emergency
control.
For substation with conventional control system, the interlocking scheme shall be
implemented by mean of hardwired electrical interlock.
For GIS substation, software interlock scheme shall be implemented. Additional
electrical hardwired interlock scheme shall be allowed.
For distribution voltage level, the implementation of hardwired electrical interlock
and/or software may be permitted.
2.
3.
4.
1. Policy
1.
2.
3.
Page 6-8
1. Policy
1.
2.
3.
2. Requirement
1.
Interlocking scheme shall cater for both operational interlock as well as maintenance
interlock.
All switchgears except circuit breakers shall be prevented to operate on load.
Closing or opening of any earthing switch shall be prevented unless the point of
application is disconnected from all possible sources of supply.
Interlocking scheme design for each switchgear shall consider status of relevant
devices that can be generalized as stated in Table 6.3.4A below;
Apparatus
Circuit Breaker
Isolators
Earthing switch
Operation
Open
Close
Open
Close
Open
Close
*where applicable
Interlock Check
None.
Necessary isolators, necessary earthing switches, Master Trip
Relay*, synchronism check*, LV circuit breaker*, and NER
isolators*.
Circuit Breaker.
Necessary earthing switch.
Necessary circuit breakers and isolators.
Necessary circuit breakers and isolators and undervoltage
relay*.
Table 6.3.4A
Page 6-9
1. Policy
1.
2. Definition
1.
The following Table 6.4A describes the definition of the AVC and ARC;
Function
Automatic Voltage Control
(AVC)
Automatic Reactive Control
(ARC)
3. Overview
1.
2.
Definition
AVC maintains a busbar voltage within a specific range, using a tap
changer of a transformer or the tap changer of other transformer
connected to the same bus.
ARC controls reactive power flow into a substation by connecting
and/or disconnecting capacitors and/or reactors onto the busbar
depending on monitored voltage and reactive power values.
Table 6.4A
The Automatic Voltage Control (AVC) consists of dual levels i.e. station level and bay
level.
The Automatic Reactive Control (ARC) only consist of one level i.e. bay level
1. Policy
(Station Level)
1.
Station level Automatic Voltage Control (AVC) function shall coordinates several
transformers in parallel operation.
2. Requirements
(Station Level)
1.
2.
3.
4.
5.
6.
7.
8.
3. Policy (Bay
Level)
1.
Page 6-10
4. Requirement
(Bay Level)
1.
2.
3.
4.
5.
6.
7.
8.
9.
There shall be independent Automatic Voltage Controller (AVC) functional unit for
each transformer.
The control shall follow step-by-step operation i.e. only single control pulse is
permitted until a desired service position is reached.
AVC shall ensure safe operation by incorporating undervoltage blocking and
overcurrent blocking as well as over voltage monitoring.
During manual control of tap changer, the automatic regulation mode shall be
deactivated.
Facility to decrease the setting voltage by certain preset percentage shall be
permissible from local and remote control levels.
Facility for compensation function due to outgoing feeder impedance shall be
embedded either by means of Line Drop Compensator or Z-Compensation.
Control facilities from various control levels related to bay level AVC as mentioned in
section 6.2 shall be available.
Monitoring facilities for various control levels related to bay level AVC as mentioned in
chapter 7.0 shall be provided.
All AVC relays shall undergo and pass acceptance testing, and made listed in the TNB
Accepted Relay List before being accepted to be used in TNB substations.
1. Policy
1.
The Automatic Reactive Control (ARC) function shall be applied for all reactors and
capacitors in TNB substations.
2. Requirements
1.
2.
The ARC shall operate based on both continuously monitored busbar voltages.
The automatic function of ARC shall incorporate the status of the relevant circuit
breakers.
Facilities for adjusting the voltage settings (switch in and switch out) and time delay
settings, within acceptable values, shall be provided.
Facility for overriding the automatic function of ARC shall be provided.
All ARC relays shall undergo and pass acceptance testing, and made listed in the TNB
Accepted Relay List before being accepted to be used in TNB substations.
3.
4.
5.
Page 6-11
CHAPTER 7
CONTROL: MONITORING
1. Policy ............................................................................................................................... 4
2. Requirements..................................................................................................................... 4
7.2.2 Status Of Operation Modes.................................................................................................................................... 4
1. Policy ............................................................................................................................... 4
2. Requirements..................................................................................................................... 4
7.3 ALARMS ......................................................................................................................................................................... 5
1. Policy ............................................................................................................................... 5
2. Requirements..................................................................................................................... 5
7.3.1 Alarm Handling....................................................................................................................................................... 5
1. Policy ............................................................................................................................... 5
2. Requirements..................................................................................................................... 5
7.4 EVENTS .......................................................................................................................................................................... 6
1. Policy ............................................................................................................................... 6
2. Requirements..................................................................................................................... 6
7.4.1 Sequence of Events ................................................................................................................................................ 6
1. Policy ............................................................................................................................... 6
2. Requirements..................................................................................................................... 6
7.5 MEASUREMENT........................................................................................................................................................... 7
1. Policy ............................................................................................................................... 7
2. Requirements..................................................................................................................... 7
Page 7-1
1. Background
1.
This chapter;
a. Describes the philosophy adopted for monitoring the power system
equipment within TNB substations,
b. Defines the policies and requirements established to support the control
monitoring philosophy.
2. Philosophy
1.
Control monitoring provides comprehensive and accurate information for the benefits
of substation operation and operational analysis.
3. Overview
1.
Group
Status
Alarm
Event
Measurement
Definition
Position of switching devices and operation modes.
An information about a change of state from normal to alert/emergency
situation to be noticed by the operator or system supervisor; must be
acknowledged.
Status change of an external value (e.g. input contact) or of an
internal/calculated value (e.g. trip decision, limit violation), which is recording
with the related instant of time (time tag).
Quantization of electrical, mechanical and thermal quantities.
Table 7.0A
Page 7-2
7.1 GENERAL
1. Policy
1.
The control monitoring process groups shall be available at the following control
levels;
a. Network Level,
b. Substation Level,
c. Bay Level.
2. Requirements
1.
2.
Page 7-3
7.2 STATUS
7.2.1 Switchgear Status
1. Policy
1.
2. Requirements
1.
For voltage level 275kV and above, all poles of circuit breakers, isolators and earthing
switchers shall be utilised to determine the open and close status.
For voltage level 275kV and above, individual circuit breakers, isolators and earthing
switchers pole status shall be monitored.
Status indication for all switching devices at network, station and bay level shall
incorporate both normally open and close auxiliary contacts.
2.
3.
1. Policy
1.
The following operation modes for applicable devices shall be monitored at network,
station and bay levels;
a. Automatic devices,
b. Transformer paralleling modes,
c. Control level authority.
2. Requirements
1.
Operational modes having more than two states shall employ double bit indication for
network and station level monitoring.
Page 7-4
7.3 ALARMS
1. Policy
1.
2.
2. Requirements
1.
2.
3.
4.
5.
6.
7.
1. Policy
1.
Alarms shall be handled in a manner that they can be distinguished between active,
momentary or acknowledged alarms.
2. Requirements
1.
Active alarms shall blink and trigger the audible device and the acknowledgement of
active alarms shall stop the blinking and audible sound.
Acknowledgement of alarms shall be made from station level or bay level.
For conventional control system, upon clearance and acknowledgement of the
alarms, resetting the alarm will clear the annunciator.
2.
3.
Page 7-5
7.4 EVENTS
1. Policy
1.
2. Requirements
1.
For conventional control system, the sequence of events recording shall be done at
network level.
For substation equipped with SCS, the SOE shall also be archived at station and bay
levels.
2.
1. Policy
1.
Any change of state within the substation shall be recorded as sequence of event and
shall be made available for display and archive at station level and network level
interface.
2. Requirements
1.
2.
3.
4.
5.
Page 7-6
7.5 MEASUREMENT
1. Policy
1.
Measurement for the following items shall be made available at network, station and
bay levels;
a. All electrical measurands such as active power, reactive power, voltage,
current, frequency, power factor,
b. D.C battery charger voltage,
c. Transformer tap position,
d. Transformer temperature.
2. Requirements
1.
For substations equipped with SCS, all electrical measurands to the bay controller
shall be derived from direct CT and VT inputs.
For measurements such as D.C Voltage and 415 A.C Voltage and non-electrical
measurands shall be derived from 4-20mA sources.
Measurement for transformer tap position shall be derived from BCD devices.
2.
3.
Page 7-7
CHAPTER 8
CONTROL SYSTEMS
1. Policy ............................................................................................................................... 3
8.1.2 SCS Retrofitting ...................................................................................................................................................... 3
1. Policy ............................................................................................................................... 3
8.1.3 Substation Extension............................................................................................................................................. 3
1. Policy ............................................................................................................................... 3
8.2. CONVENTIONAL CONTROL SYSTEM .................................................................................................................. 4
1. Policy ............................................................................................................................... 4
8.2.1 Control Mimic Panel................................................................................................................................................ 4
1. Policy ............................................................................................................................... 4
2. Requirements..................................................................................................................... 4
8.2.2 Network Level Interface.......................................................................................................................................... 4
1. Policy ............................................................................................................................... 4
2. Requirements..................................................................................................................... 4
8.2.3 Display of measured parameters........................................................................................................................... 5
1. Policy ............................................................................................................................... 5
8.2.4 Control Command Interface ................................................................................................................................... 5
1. Policy ............................................................................................................................... 5
2. Requirement ...................................................................................................................... 5
8.3 SUBSTATION CONTROL SYSTEM .......................................................................................................................... 6
8.3.1 SCS General Requirements.................................................................................................................................... 6
1. Policy ............................................................................................................................... 6
2. Requirement ...................................................................................................................... 6
8.3.2 General System Architecture................................................................................................................................ 6
1. Policy ............................................................................................................................... 6
8.3.3 SCS Basic Functions ............................................................................................................................................. 7
1. Policy ............................................................................................................................... 7
2. Requirements..................................................................................................................... 7
3. Definition .......................................................................................................................... 7
8.3.4 Function Allocation................................................................................................................................................ 8
1. Policy ............................................................................................................................... 8
2. Requirements..................................................................................................................... 8
8.3.5 Integration of Protection Functions ..................................................................................................................... 8
1. Policy ............................................................................................................................... 8
2. Requirement ...................................................................................................................... 8
8.3.6 Integration of Automatic Functions...................................................................................................................... 8
1. Policy ............................................................................................................................... 8
2. Requirements..................................................................................................................... 8
8.3.7 Station Level Control and Monitoring Facilities (Station HMI) ........................................................................... 9
1. Policy ............................................................................................................................... 9
2. Requirements..................................................................................................................... 9
8.3.8 Remote Control Center Interface .......................................................................................................................... 9
1. Policy ............................................................................................................................... 9
2. Requirements..................................................................................................................... 9
8.3.9 Equipment Qualifications ...................................................................................................................................... 9
1. Policy ............................................................................................................................... 9
2. Requirements..................................................................................................................... 9
8.4 SUBSTATION INTERROGATION AND MONITORING SYSTEM ....................................................................10
1. Policy ..............................................................................................................................10
2. Requirements....................................................................................................................10
3. Substation Local Area Network .............................................................................................10
Page 8-1
1. Background
1.
This chapter;
a. Describes the philosophy adopted for control system method and equipment
within TNB substations,
b. Defines the policies and requirements established to support the control
system philosophy.
2. Philosophy
1.
3. Definition
1.
The following table, Table 8.0A, describes the types of control system;
Control System
Conventional Control
System
Substation Control
System
Description
The Conventional Control System is a hard-wired based control system
comprising control panels, switches and annunciators.
Substation Control System is a microprocessor based control system that
provides facilities for the monitoring and control of substations devices
and parameters.
Table 8.0A
Page 8-2
1. Policy
1.
2.
3.
Where required, all 500kV, 275kV and 132kV transmission substations shall be
equipped with SCS.
For substation with multiple voltage levels where equipped with SCS, a single type of
SCS system shall be used.
All new distribution substations shall be equipped with conventional control systems.
1. Policy
1.
2.
Where required, the existing 275kV and critical 132kV subst ation employing
conventional control system shall be retrofitted with SCS. The retrofitting of SCS will
only encompass transmission levels only.
For distribution level in the transmission substation, the decision to retrofit the
distribution control system shall be made on a case-by-case basis.
1. Policy
1.
Page 8-3
1. Policy
1.
Conventional control system shall provide control operation and monitoring facilities
for;
a. Control mimic panel,
b. Network level interface,
c. Control Operation,
d. Control Monitoring,
e. Alarm Display,
f. Status Display,
g. Display of measurement.
1. Policy
1.
The control mimic panel shall provide bay level control in a form of control panel
placed in a centrally designated location within the substation switch house.
2. Requirements
1.
The control mimic panel shall adhere to control panel policies and requirement as
described in chapter 12.0.
In double busbar and single busbar substations, the panel designated for control shall
be configured to allow control for one bay only.
In 1 breaker substation, control mimic panel shall be configured to allow control for
one diameter only.
2.
3.
1. Policy
1.
The substation with conventional control system shall be equipped with Remote
Terminal Unit (RTU) for Network Level interfacing. The RTU shall be connected to
supervisory interface panels that shall contain all necessary monitoring and control
signals from the plant.
2. Requirements
1.
The supervisory interface panel shall have facilities to isolate the plant circuits from
the RTU. The detail requirement for the interface panel is as described in chapter 12.
In the case of distributed RTU, the interface panel is not applicable.
The following table, Table 8.2.2A, shows the signal types that shall be used to
interface the control system;
2.
3.
Items
Status and alarms
Analogue input
Control output
Analogue output
Transformer Tap Indicator
Signal Type
Voltage free contacts and/or via protocol interface
4 to 20 mA
Interposing relays
4 to 20 mA output
BCD format
Table 8.2.2A
Page 8-4
1. Policy
At the bay level, analogue meters shall be used to provide reading information on the
measurement.
1. Policy
1.
There shall be a control command circuit interface from control system to the
respective apparatus.
2. Requirement
1.
Heavy-duty interposing relays (HDIR) shall be used for interfacing control command
from network level. The HDIR shall be located in each control panel for the respective
bay/diameter.
Page 8-5
1. Policy
1.
The Substation Control System (SCS) shall be designed in a manner that ensures
high reliability and availability of the entire system and individual subsystem within
SCS to avoid interruption of its service.
2. Requirement
1.
1. Policy
1.
2.
3.
The configuration of SCS shall employ two or three tier hierarchical general system
architecture.
The two-tier system shall be as follows;
a. Level 2 Station Level,
b. Level 1 Bay Level.
In the case of remote I/O being used, the three-tier system architecture shall be as
follows;
a. Level 3 Station Level,
b. Level 2 Bay Level,
c. Level 1 Apparatus Level.
Page 8-6
1. Policy
1.
The SCS shall perform all conventional control system functions and incorporate
additional added value features.
2. Requirements
1.
2.
3. Definition
1.
The table below, Table 8.3.3A, describes the terminology related to several SCS
functions;
Function
Automatic Sequence
Control
Time synchronization
System Supervision
Communication
Supervision
Description
Series of pre-programmed switching operation.
Ensures the setting and regulation of all real-time clocks in all subsystems
in the SCS and protection system.
Feature in SCS and protection system whereby the function in each unit is
cyclically running to check a failure in the unit continuously.
Supervises the communication system to ensure complete functionality at
all times.
Table 8.3.3A
Page 8-7
1. Policy
1.
Suitable function allocation to ensure failure effects are confined to a smaller degree
shall be considered.
2. Requirements
1.
Function that encompasses more than one bay shall either be allocated in station
level or bay level equipment.
Function that encompasses only one bay shall be allocated in bay level equipment.
2.
1. Policy
1.
2.
2. Requirement
1.
For transmission voltage levels, the main protection functions and control functions
shall not be integrated in the same functional unit.
For distribution voltage levels, the protection and control functions may be
integrated.
Control functions shall be able to use information from protection relays, if necessary,
to achieve certain special functions.
1. Policy
1.
Automatic function for control purposes shall be able to be integrated into the SCS.
2. Requirements
1.
2.
Page 8-8
1. Policy
1.
Station level control and monitoring facilities shall provide all control and monitoring
facilities, such that the entire substation operation can be supervised from t he station
level without leaving the control desk.
2. Requirements
1.
2.
3.
1. Policy
1.
Information from SCS shall be able to be communicated to the remote control center.
2. Requirements
1.
The communication protocols shall emulate and be compatible with the remote
control centers protocol.
1. Policy
1.
All hardware used in SCS shall be of high reliability design and shall withstand harsh
operational environment.
2. Requirements
1.
All SCS subsystem equipment shall be certified and type tested as protection grade
equipment except for station HMI.
Station HMI PC shall be certified and type tested as industrial grade equipment.
All SCS systems shall undergo acceptance testing before the systems are accepted to
be used in TNB substation.
2.
3.
Page 8-9
1. Policy
1.
2.
2. Requirements
1.
2.
3.
4.
5.
6.
3. Substation
Local Area
Network
1.
2.
The failure of SIMS shall not cause any interruption to the normal services of the
primary equipment and secondary equipment inside the substation.
All intelligent subsystems may be connected to the stations local area network (LAN).
All intelligent electronic devices (IED) shall be connected to the stations local area
network (LAN).
All subsystems and IEDs shall be able to be interrogated and monitored from any
remote engineering centers, e.g. Protection Interrogation and Monitoring Center
(PIMC), via the TCP /IP protocol of TNBs corporate networks through SIMS. (See
section 10.1.8)
The examples of subsystems and intelligent electronic devices (IED) are listed below;
a. Protection relays IED,
b. Recorders IED,
c. Fault locators IED,
d. Databank,
e. Condition Monitoring system,
f. Close-circuit television (CCTV),
g. Substation Control System (SCS),
h. Weather station.
The SIMS and remote monitoring centers shall support the following basic functions;
a. Network level interrogation and monitoring facilities,
b. Wide area network functions,
c. Parameter flow,
d. Information flow.
The substation local area network (LAN) for SIMS shall be classified as information
LAN.
The substation LAN shall at least consist of the following;
a. Switch-type hub,
b. Router.
Page 8-10
CHAPTER 9
RECORDERS
Page 9-1
9.0 RECORDERS
1. Philosophy
1.
All major power system disturbances shall be adequately recorded for post-fault and
disturbance analysis.
2. Types of
Recorders
1.
3. Policy
1.
Fault recorders shall be installed in the selected and important 132kV lines or cable
feeders, and power transformers.
Disturbance recorders shall be installed in all the 500kV and 275kV lines or cable
feeders, and all autotransformers.
All recorders shall undergo and pass acceptance testing, and made listed in the TNB
Accepted Relay List before being accepted to be used in TNB substations
2.
3.
4. Definition
1.
2.
Page 9-2
9.1 General
1. General
Requirements
1.
2.
3.
4.
5.
6.
7.
8.
2. Data Format
1.
All recorders shall be provided with at least, but not limited to, 8 analogue channels
and 16 digital channels per feeder.
All recorders shall be capable of storing information in a non-volatile memory and real
time clock operation to safeguard loss of information on system parameters during
periods of D.C. supply interruption.
All recorders shall be provided with an internal clock to time tag each fault record.
The internal clock shall continue to keep time and date during loss of auxiliary power
supplies and have a facility for external time synchronization using Global Positioning
System (GPS) receiver via IRIG-B port.
All recorders shall be able to record analogue inputs ranging from 1% to 100% of
full-scale without clipping, and with a maximum error of less than 2% of the input
value.
Interface facilities shall be provided for the connection of computers to allow the
recorders to be configured from computers keyboard, via direct connection and via
remote communication link.
Interface facilities shall be provided for the connection of remote computers to allow
the fault records data to be accessible and transferred, via direct connection and via
remote communication link via TCP/IP protocol.
Minimum recording time for fast sampling rate shall be 4 seconds and slow sampling
rate shall be 40 seconds.
All faults and disturbances shall be continuously recorded irrespective of the specified
record length.
The fault records data shall be in an open type form, which shall be converted into
COMTRADE format (according to IEEE C37.111-1992). TNB reserves the right to test
and accept the COMTRADE format for compatibility and other purposes.
Page 9-3
1. Fault
Recorder
Requirement
1.
All fault recorders shall provide, in analogue form, at least three phase voltages, zero
sequence voltage, frequency, three phase current, neutral current information, an
digital form event information, such as protection equipment outputs, associated
inter-tripping and signalling equipment outputs and breaker operation at a selectable
pre and post time frame of the primary system faults.
2. Sampling
Rate
1.
The sampling rate for both the analogue and event channels shall be user settable, in
the range of 1000 - 10000 Hz.
1. Disturbance
Recorder
Requirement
1.
All disturbance recorders shall provide, in analogue form, at least three phase
voltages, zero sequence voltage, three phase current, neutral current information,
frequency, active power, reactive power, and digital form event information, such as
protection equipment outputs, associated inter-tripping and signalling equipment
outputs and breaker operation at a selectable pre and post time frame of the primary
system faults.
2. Sampling
Rates
1.
Where two sampling rates are available, the sampling rates for both the analogue
and event channels shall be user settable, where they fall in the following ranges;
a. Fast sampling rate
i. 1000 - 10000 Hz
b. Slow sampling rate
i. 10 - 100 Hz.
Where more than two sampling rates are available, the sampling rates for both the
analogue and event channels shall be user settable, and will be defined as in the
guidelines.
2.
Page 9-4
CHAPTER 10
COMMUNICATION SYSTEMS
1. Policy ............................................................................................................................... 4
2. Requirements..................................................................................................................... 4
10.1.2 Inter-Bay Communication [IF2]........................................................................................................................... 5
1. Policy ............................................................................................................................... 5
2. Requirements..................................................................................................................... 5
10.1.3 Bay-Station Communication [IF3]....................................................................................................................... 5
1. Policy ............................................................................................................................... 5
2. Requirements..................................................................................................................... 5
10.1.4 Apparatus Communication [IF4]......................................................................................................................... 6
1. Policy ............................................................................................................................... 6
2. Requirements..................................................................................................................... 6
10.1.5 Inter-Station Communication [IF5]..................................................................................................................... 6
1. Policy ............................................................................................................................... 6
2. Requirements..................................................................................................................... 6
10.1.6 Station-Remote Control Communication [IF6]................................................................................................... 7
1. Policy ............................................................................................................................... 7
2. Requirements..................................................................................................................... 7
10.1.7 Intra-Station Level Communication [IF7]........................................................................................................... 7
1. Policy ............................................................................................................................... 7
2. Requirements..................................................................................................................... 7
10.1.8 Station-Remote Monitoring Communication [IF8]............................................................................................. 8
1. Policy ............................................................................................................................... 8
2. Requirements..................................................................................................................... 8
Page 10-1
1. Background
1.
2.
3.
2. Philosophy
1.
The power system communication system shall take into account the following
considerations [IEEE WG9];
a. Delay,
b. Dependability,
c. Security,
d. Electromagnetic Compatibility.
Page 10-2
1. Policy
1.
2. Requirements
1.
2.
3.
Flow
Operational Flow
Definition
Information for operation of the system with immediate access.
E.g. trip command.
Data communication for parameter change.
E.g. protection relays settings.
Data communicated for post -mortem display, monitoring, archiving and
statistics.
E.g. disturbance record.
Real time data from the process that may be used for operational or
informative functions.
E.g. Voltage indication.
A combination of slow operational, parameter and informative flow.
E.g. Manual open/close command.
Table 10.1A
Parameter Flow
Informative Flow
Primary flow
Supervisory flow
Remote Control
(Control Center)
TIME (Clock)
Remote Monitoring
(Monitoring Center)
IF6
STATION
LEVEL
IF8
DEVICE
e.g RTF
IF3
BAY
LEVEL
DEVICE
Protection
IF1
IF7
DEVICE
e.g MMI
IF2
DEVICE
Control
IF3
DEVICE
Protection
IF4
IF5
IF1
DEVICE
Control
IF4
IF5
APPRATUS
LEVEL
Remote
Protection
(Next station)
Remote
Protection
(Next station)
Page 10-3
Code
IF1
Communication Flow
Intra-Bay Communication
IF2
IF3
IF4
Inter-Bay Communication
Bay-Station Communication
Apparatus Communication
IF5
Inter-Station
Communication
IF6
Station-Remote Control
Communication
Intra-Station
Communication
Station-Remote Monitoring
Communication
IF7
IF8
Definition
Operational flow between related bay devices e.g.
between protection to control or between protection
devices.
Operational flow between different bays.
Supervisory flow between the bay and station level.
The primary flow between the bay and HV primary
equipment.
Operational flow between a local and remote (next
station) protection unit (analogue or digital signals for
teleprotection) or for control interlocking purposes.
Supervisory flow between the station level and remote
control center.
Flow between different devices at the station level.
Parameter and informative flow between the station level
and remote monitoring center.
Table 10.1B
1. Policy
1.
2. Requirements
1.
2.
Items
Protection-Protection
Protection-Bay Controllers
Practice
Current practice coordinates operat ional transfer/flow of information
using hardwired logical binary signals or optical fibre.
Current practice uses the IEC 60870-5-103 profile or/and the hardwire
logical binary signals to facilitate supervisory flow. A TNB specific
profile shall be defined inside a protocol implementation document
(PID).
An emerging standard for the application of substation Ethernet for
Intra-Bay and Inter-Bay level communication to be considered for later
practice.
Table 10.1.1A
Page 10-4
1. Policy
1.
2. Requirements
1.
2.
Items
Protection-Protection
Bay controllers-Bay
controllers
IEC 61850-8 SCSM for
Process Bus standardization
Practice
Current practice coordinates operational transfer/flow of information
using hardwired logical binary signals or optical fibre.
Current practice uses vendor-specific solutions.
An emerging standard for the application of substation Ethernet for
Intra-Bay and Inter-Bay level communication to be considered for later
practice.
Table 10.1.2A
1. Policy
1.
2. Requirements
1.
2.
3.
Items
Distributed Low
Impedance Busbar
Protection
Station level-Bay
controllers
Station level-Protection
Practice
Use proprietary protocols on a dedicated protection path.
The
performance speed requirement shall not affect the performance of the
protection relay to clear the fault(s) within the specified maximum fault
clearing time.
Current practice supports vendor-specific solutions
Current practice uses the IEC 60870-5-103 profile or/and the hardwire
logical binary signals to facilitate primary information flow. A TNB
specific IEC 60870-5-103 profile shall be defined inside a protocol
implementation document (PID).
An emerging standard for the application of substation Ethernet for
Substation-Bay level communication to be considered for later practice.
Table 10.1.3A
Page 10-5
1. Policy
1.
2. Requirements
1.
The performance speed requirement for IF4 is less than 1 ms (128 samples/cycle)
[CIGRE WG 34.03]
The following items in Table 10.1.4A fall under apparatus communication;
2.
Items
Relays-HV Equipment
BCU-HV Equipment
IEC 61850-9 Process Bus
Practice
Current practice supports hardwired electrical and/or optical fibre
interfaces.
Current practice supports hardwired electrical and/or optical fibre
interfaces.
An emerging standard for the application of substation Ethernet between
relays and merging units to be considered for later practice.
Table 10.1.4A
1. Policy
1.
2. Requirements
1.
The performance speed requirement for IF5 shall not affect the performance of the
protection relay to clear the fault(s) within the specified maximum fault clearing time.
The requirements are as tabulated in the following table, Table 10.1.5A, shown
below;
2.
Applications
Teleprotection Signal,
e.g. Distance relays,
Breaker Failure, etc.
Schemes
Teleprotection Data, e.g.
Current Differential and
Current Comparison relays
1.
2.
1.
2.
3.
4.
Requirements
Transmission of discrete contact logic signals from point to point
with high degree of security and dependability.
The communication interface shall allow communication between the
relays teleprotection interface to the telecommunication equipment.
(See section 2.3)
The main requirement is to eliminate time propagation delay to the
remote signal in order to prevent phase error in the comparison
process and false differential current. On a 50Hz system, 1 ms
creates a phase error of 18 degrees. (See section 2.3.2)
The use of microprocessor-based current differential and current
comparison relays with automatic delay compensation is highly
recommended. (See section 2.3.2)
Microprocessor based current differential and current comparison
relays shall utilize 64 kbps digital interface. The 64 kbps shall
support G.703 frame standards. (See section 2.3.2, 3.1 and 3.2)
In special cases, point-t o-point optical fibre communication shall be
supported. Current practice supports vendor specific solutions. (See
section 3.1 and 3.2)
Table 10.1.5A
Page 10-6
1. Policy
1.
2. Requirements
1.
The performance speed requirement for IF6 is in the range of 100 ms to 1000 ms
[CIGRE WG 34.03].
The requirements include;
2.
Items
EMS/DMS/SCADA
1.
2.
Feeder
Automation
(Distribution System)
1.
2.
3.
4.
5.
1. Policy
1.
2. Requirements
1.
The performance speed requirement for IF7 is in the range of 100 ms to 1000 ms
[CIGRE WG 34.03].
The current practice uses vendor specific solutions.
2.
Page 10-7
1. Policy
1.
2. Requirements
1.
2.
The performance speed requirement for IF8 is in the range of 100 ms to 1000 ms.
The requirements include;
Items
Engineering Analysis
(EA)
1.
2.
3.
4.
5.
6.
Corporate Application
7.
1.
2.
Page 10-8
CHAPTER 11
SUBSTATION AUXILIARIES
1. Policy ............................................................................................................................... 4
2. Requirements..................................................................................................................... 4
3. Battery Type...................................................................................................................... 4
4. Battery Sizing..................................................................................................................... 4
5. Isolatio n............................................................................................................................ 4
6. Battery Rack...................................................................................................................... 4
11.1.2 Battery Charger.................................................................................................................................................... 5
1. Policy ............................................................................................................................... 5
2. Requirements..................................................................................................................... 5
3. Operational Requirements .................................................................................................... 5
4. Indication and Alarms .......................................................................................................... 5
11.1.3 D.C Distribution Switchboard............................................................................................................................. 6
1.
2.
3.
4.
Policy ............................................................................................................................... 6
Requirement ...................................................................................................................... 6
Special Requirement ............................................................................................................ 6
Indication.......................................................................................................................... 6
1. Policy ............................................................................................................................... 7
2. Facilities............................................................................................................................ 7
11.2 30V D.C System ........................................................................................................................................................ 8
1. Philosophy......................................................................................................................... 8
2. Policy ............................................................................................................................... 8
11.2.1 30V Battery Charger............................................................................................................................................. 8
1. Requirements..................................................................................................................... 8
2. Indications ........................................................................................................................ 8
11.2.2 30V Battery........................................................................................................................................................... 9
1. Policy ............................................................................................................................... 9
2. Requirement ...................................................................................................................... 9
11.2.3 30V Battery Charger Cubicle............................................................................................................................... 9
1. Policy ............................................................................................................................... 9
2. Requirement...................................................................................................................... 9
11.3 A.C Supply System................................................................................................................................................10
1. Philosophy........................................................................................................................10
2. Policy ..............................................................................................................................10
3. LVAC System Requirement...................................................................................................10
4. LVAC Switchboard Requirement ............................................................................................10
11.3.1 LVAC Incoming Supply..................................................................................................................................... 11
1. Policy ..............................................................................................................................11
2. LVAC Incoming Supply Requirement ......................................................................................11
11.3.2 LVAC Distribution Busbar ................................................................................................................................. 11
1. Policy ..............................................................................................................................11
2. LVAC Distribution Busbar.....................................................................................................11
11.3.3 LVAC Outgoing Distribution Circuits ............................................................................................................... 12
1. Policy ..............................................................................................................................12
2. LVAC Outgoing Distribution Circuits Requirement .....................................................................12
Page 11-1
1. Philosophy
1.
All substations that require Direct Current (D.C) supply and Alternating Current (A.C)
supply for protection and control shall be provided with D.C and A.C auxiliary
systems.
2. Policy
1.
The D.C auxiliary supply shall be regulated and maintained at the suitable voltage
range to power the protections, control equipments and other essential services.
The A.C auxiliary supply shall be regulated and maintained at the suitable voltage
range for the use of other essential load and services.
Both the A.C and D.C supplies shall be taken from regulated sources, e.g. local
transformer equipped with tap changer or equivalent.
2.
3.
Page 11-2
1. Philosophy
1.
2. Policy
1.
2.
There shall be only one dedicated D.C system for each 500kV voltage level.
There shall be one shared D.C system for 275kV voltage level and below, provided all
the secondary equipment is housed in one building.
In the event of extension and where the D.C system needs to be upgraded, the new
D.C source shall be able to cater the existing load and new load.
The nominal system voltage shall be 110 volts D.C for transmission substation, 110 or
220 volts D.C for power station requirements, and 30 volts D.C for 11/0.415kV
distribution substation equipped with circuit breakers.
The D.C system shall have dual parallel redundant chargers and battery banks,
except for the 30 volts D.C system.
The supply for the D.C system shall be from LVAC auxilliary system.
3.
4.
5.
6.
3. D.C Auxiliary
Subsystems
1.
2.
MCB
MCB
Indicators
& Relays
Indicators
& Relays
Interlock
Charger No. 1
Charger No. 2
Anti-power
reversal device
Indicators
Anti-power
reversal device
Indicators
Battery Bank
No. 1
Battery Bank
No. 2
Indicators
& Relays
Indicators
& Relays
MCB
MCB
DC Busbar
MCB
MCB
DC Distribution Board
DC Distribution
Feeder No. 1
DC Distribution
Feeder No. n
4. Special
Requirements
1.
2.
The D.C supply circuits for the Busbar protection scheme and Breaker Failure
protection scheme shall be dedicated and independent of other protection and
control schemes.
For GIS system, the D.C supply circuits for the SF6 low pressure tripping shall be
dedicated and independent from all others.
Page 11-3
11.1.1 Battery
1. Policy
1.
2.
3.
4.
The batteries shall be suitable for substation applications where the batteries are
continuously charged and subject to infrequent discharges.
The batteries shall be easily replaced if there is reduction in capacity or abnormal
voltage.
The batteries shall consist of two identical, equally rated banks.
The minimum standby period, where the period for which a battery is required to
perform without recharge, shall be 8 hours.
2. Requirements
1.
2.
3.
4.
5.
The supply for the battery shall be from LVAC auxiliary system.
The battery shall be located in a separate and ventilated room from the charger.
The battery container shall be of translucent plastic type for visible electrolyte level.
The battery terminal polarity shall be colour coded for easy identification.
The battery terminal and inter cell connectors shall be covered with suitable
insulation material to prevent accidental contact or short circuit.
3. Battery Type
1.
2.
3.
4.
5.
4. Battery Sizing
1.
2.
3.
4.
5. Isolation
1.
2.
6. Battery Rack
1.
2.
3.
Each positive pole shall be isolated with suitable rated fuse, for battery isolation
purposes in the event of battery faults. The isolation switch-fuse shall be wall
mounted.
The isolated switch-fuse shall be installed outside the battery room, and shall be
clearly labelled.
Each battery bank shall have its own battery rack with insulated tier stand.
The rack shall be either hard wood or non-corrosive metal.
The battery shall be accessible for maintenance, testing and inspection.
Page 11-4
1. Policy
1.
2.
3.
4.
2. Requirements
1.
3. Operational
Requirements
1.
The battery charger panel shall be floor mounted, front opening for easy access to
facilitate fault locating and testing of individual electronic control units.
2. Each battery charger shall be adequately rated to supply any continuous standing
load with sufficient excess to recharge its own battery bank after emergency
discharged.
3. The battery charger shall supply the normal loads, with the batteries supplying any
peak transient loads above the charger capacity.
4. Three charging rate facilities shall be provided, which are float charge, manual boost
charge and automatic boost charge.
5. The battery charger shall be continuously supervised and alarmed for failures.
6. The facility to detect battery earth fault shall be incorporated in the battery charger.
7. The battery charger shall be short -circuit proof in the event of output short -circuited.
8. The battery charger shall be located inside an air-conditioned room.
9. Facilities for remote monitoring of the battery charger status shall be provided.
10. The battery charger shall be protected from abnormal A.C supply transient and
surges.
11. All transducers and relays used for remote monitoring shall be provided.
2.
3.
4.
4. Indication
and Alarms
Each battery charger shall be designed for operation from either a single-phase 240
volts 50Hz, or a three-phase 415 volts 50Hz depending on substation load
requirement and battery capacity.
The battery charger system shall be of a dual charger with A.C/D.C rectifier control
operating in parallel with battery bank.
The battery charger shall be of constant voltage, current limiting type that shall be
suitable for unattended charging of the batteries.
During normal service, the two battery chargers shall be able to be operated in
parallel for sharing the substation load.
1.
2.
During normal parallel operation, if any of the two battery chargers is required to
boost charge, then the load shall be automatically disconnected from the battery
charger that is undergoing the boost charge.
In boost charge mode, the charger shall be able to restore its battery bank to its full
capacity, and revert to float charge upon completing the boost charge cycle.
During normal operation, the float charge facility shall be able to compensate for its
battery bank self-discharging and to maintain its battery bank in fully charged
condition.
The boost charge shall be blocked when one charger fails. Only one charger is
allowed to boost charge at any one time.
Each battery charger shall be provided with the following separate minimum
indication and alarm facilities, as shown in Table 11.1.2A and Table 11.1.2B
respectively.
All the alarm facility as in Table 11.1.2B shall be made available for remote
monitoring.
INDICATION FACILITIES
Indication
Indicator
Voltmeter
Charger Output, D.C Voltage
Charger Input, A.C Voltage
Battery Output, D.C Voltage
Ammeter
Load Output, D.C current
Battery Output, D.C current
Selector Switch
Float/Boost/Auto Selection
MCB
A.C Mains ON/OFF Input
D.C Mains ON/OFF Output
Table 11.1.2A
Continue on next page
Protection and Control Code of Practice, 2nd Edition
Page 11-5
ALARM FACILITIES
Indication
Indicator
Neon
A.C Mains ON
LED
Charger Fail
Charger on Float
Charger on Manual Boost
Charger on Automatic Boost
Earth Fault
Battery Low Electrolyte Level1
Battery Voltage Low
Battery Voltage High
Table 11.1.2B
Colour
GREEN
RED
WHITE
WHITE
YELLOW
RED
YELLOW
RED
RED
1. Policy
1.
2.
3.
D.C distribution board (DCDB) shall be separated from and adjacent to the D.C
battery chargers.
Individual miniature circuit breaker (MCB) shall be provided for each outgoing
circuits.
The MCB size and rating shall be calculated to satisfy the coordination between the
short-circuit requirement and thermal rating requirement.
2. Requirement
1.
3. Special
Requirement
1.
For each 33kV, 22kV or 11kV system, 4 dedicated D.C circuits shall be provided, 2 for
switchgear and 2 for relay panel.
4. Indication
1.
2.
For 500kV and 275kV, dual D.C circuits shall be provided to each bay for protection
and control purposes, where one circuit is for Main 1 protection and control schemes
and one circuit is for Main 2 protection, BCU, Backup protection and outdoor
switchgear auxiliary supplies.
2. For 132kV, single D.C circuit shall be provided to each bay for protection, BCU,
control purposes and outdoor swit chgear auxiliary supplies.
3. One separate D.C circuit shall be provided for signalling, and alarms purposes.
4. One separate D.C circuit shall be provided for busbar protection and breaker failure
tripping relays at the busbar protection panels.
5. One separate D.C circuit shall be provided for SF6 low pressure tripping, for GIS
system.
6. One separate D.C circuit shall be provided for microprocessor based SCS and RTU
power supply.
7. One separate D.C circuit shall be provided for transformer remote tap changer
controller and its local and master control panels.
8. For G.I.S system, separate D.C circuits shall be provided for each local control panel.
9. All outgoing circuit MCBs shall be monitored.
10. Adequate number of spare outgoing circuits of different ratings, shall be provided.
If applicable
Page 11-6
1. Policy
1.
2.
A separate and dedicated room for all the D.C batteries shall be provided.
The floor shall be acid and alkaline proof.
2. Facilities
1.
Page 11-7
1. Philosophy
1.
2.
2. Policy
1.
2.
3.
The 30 volts D.C systems shall be applicable only for 11/0.415kV distribution
substation equipped with circuit breakers.
The D.C system shall be of a single charger and one battery bank.
The charger shall be designed for operation from a single-phase 240V, 50Hz A.C
supply.
The charger shall be of a constant potential, current limiting, suitable for an
unattended operation.
The nominal system voltage shall be 30 volts D.C.
1. Requirements
1.
2.
3.
4.
5.
6.
7.
8.
2. Indications
1.
The battery charger shall be SCR regulated with current output based on substation
load requirement and battery capacity.
The battery charger shall be fitted with an automatic boost facility, which detect and
trigger boost charging. The charger will automatically revert to float charge after a
preset time.
The battery charger must allow for boost charging of batteries with load still
connected, but the output voltage to the load shall be regulated.
The battery charger cubicle shall be free standing, ventilated and vermin proof.
The battery charger shall be supervised and alarmed for failures.
Facility to detect battery earth fault shall be incorporated.
The battery charger shall be protected from abnormal A.C supply transient and
surges.
The battery charger shall be adequately protected against short-circuit and overload.
Each battery charger shall be provided with the following minimum indication and
alarm facilities, as in Table 11.1.5A;
ALARM FACILITIES
Indication
Output Voltage
Output Current
LED
Indicators
Voltmeter, D.C Output
Ammeter, D.C Output
A.C Mains ON
Charger Fail
Charger on Float
Charger on Boost
Earth Fault
Battery Voltage Low
Battery Voltage High
Table 11.1.5A
Colour
GREEN
RED
WHITE
YELLOW
RED
RED
RED
Page 11-8
1. Policy
2. Requirement
1.
2.
3.
1.
The battery shall be of 40AH rating with minimum end cell voltage of 1.14V.
1. Policy
1.
2. Requirement
1.
2.
The cubicle shall be of a free standing, ventilated and vermin proof type.
The physical size should be designed to enable the charger and batteries to be house
in it.
Page 11-9
1. Philosophy
1.
2.
3.
4.
5.
2. Policy
1.
2.
3. LVAC System
Requirement
1.
2.
Low voltage alternating current (LVAC) auxiliary supply shall be provided to supply
the substations essential loads and non-essential loads.
LVAC supply shall have duplicated power sources (incomers).
Changeover facilities shall be provided to prevent the occurrence of parallel incomers.
The nominal system voltage shall be 415/240 volt s alternating current (A.C), and the
variation shall comply with the Electricity Supply Act regulations.
The system shall be three phase, four-wire, 50Hz, having the neutral solidly earthed.
The LVAC switchboard shall be in accordance with IEC 60439-1, Low Voltage
Switchgear and Controlgear Assemblies, Part 1: Requirements for Type-Tested (TTA)
and Partially Type-Tested (PTTA) Assemblies.
The LVAC switchboard shall be designed in the form of cubicles (floor-standing)
containing modularised incoming and outgoing units.
Incoming No. 2
Indicators
Indicators
Interlock
CB/Switch Fuse
Switch Fuse/CB
Indicators
Indicators
LVAC Busbar (with
bus-section)
Bus-section
MCB / MCCB
MCB / MCCB
Outgoing Distribution
Feeder No. 1
Outgoing Distribution
Feeder No. n
4. LVAC
Switchboard
Requirement
1.
2.
3.
4.
Page 11-10
1. Policy
1.
There shall be at least two sources of 415V A.C incoming supplies for the LVAC
system. The 415V A.C supply shall be taken from either auxiliary transformers or
local transformer or substat ion earthing transformers.
2. LVAC
Incoming
Supply
Requirement
1.
Each LVAC supply should be equipped with a switch-fuse or circuit breaker to isolate
the incoming supply (when necessary) from the A.C distribution busbars. The rating
of the switch-fuse or circuit breaker shall be able to cater all the loads.
Each LVAC incomer shall have a current transformer and voltage measuring
equipment for current and voltage measurements respectively. A selector switch
shall be provided for the ammeter in order to measure individual phase current.
Individual phase indicating lights shall be provided for the incomers and the busbars.
Each incomer shall have three-element undervoltage relays to monitor the availability
of the incoming A.C supply and the A.C status of the A.C distribution busbars.
The LVAC incoming supply system may be provided with automatic switch-over
facility.
2.
3.
4.
5.
1. Policy
1.
The LVAC main distribution busbar shall be connected to the LVAC incoming supplies
for the use of distributing the LVAC power via LVAC outgoing distribution circuits.
2. LVAC
Distribution
Busbar
1.
2.
3.
The loading for the each section of the busbar shall be balanced.
Single busbar with bus-section isolator switch of adequate rating shall be provided.
The vertical busbars shall be adequately insulated.
Page 11-11
1. Policy
1.
2.
2. LVAC
Outgoing
Distribution
Circuits
Requirement
1.
2.
The LVAC outgoing distribution circuits shall be able to cater all the substations
essential loads and non-essential loads requirements.
Spare LVAC outgoing distribution circuits shall be provided.
The LVAC outgoing distribution circuits shall be protected with Miniature Circuit
Breakers (MCB) for single-phase connection, and Moulded-Cased Circuit Breakers
(MCCB) or MCB for three-phase connection, depending on the load requirement.
The following list specifies the Substation Services to be supplied with 415V supply by
the LVAC system;
a. Building Services for building lighting & Air-conditioning and power points,
b. Outdoor perimeter lighting and switchyard lighting for AIS substation,
c. Dedicated circuit for control panels, relay panels for testing, panel lighting
and heating purposes for each 500kV, 275kV and 132kV systems,
d. Dedicated circuit for relay control panels (RCP) for each 33kV, 22kV and
11kV systems,
e. Dedicated circuit for indoor switchgear panels for each 33kV, 22kV and
11kV systems,
f. Transformer Oil Treatment Plant,
g. Transformer Local Control Panel,
h. Transformer Master Control Panel,
i.
Transformer RTCC,
j. Battery Chargers,
k. Outdoor Marshalling Kiosk,
l.
Telecommunication equipment D.C Charger,
m. GIS Local Control Panels for GIS substation,
n. Adequate number of spares.
Page 11-12
CHAPTER 12
PANELS
1.
2.
3.
4.
5.
6.
7.
Policy .............................................................................................................................................. 5
Construction .................................................................................................................................... 5
Orientation ...................................................................................................................................... 5
Arrangement ................................................................................................................................... 5
Test Block ....................................................................................................................................... 6
Isolation Link................................................................................................................................... 6
Annunciator Windows And Alarm Scheme.......................................................................................... 6
1. Policy .............................................................................................................................................. 6
2. Specific Requirements ...................................................................................................................... 6
12.1.3 Outdoor Marshalling Kiosk....................................................................................................................................6
1. Policy .............................................................................................................................................. 6
2. Construction .................................................................................................................................... 6
12.1.4 Isolator Box .............................................................................................................................................................7
1. Policy .............................................................................................................................................. 7
2. Construction .................................................................................................................................... 7
12.1.5 Transformer Local Control Panel (LCP) and OLTC .............................................................................................7
1. Policy .............................................................................................................................................. 7
2. Construction .................................................................................................................................... 7
12.1.6 Transformer Remote Tap Changer Control (RTCC) ............................................................................................8
1. Policy .............................................................................................................................................. 8
2. General Requirement ....................................................................................................................... 8
12.1.7 GIS Local Control Panel.........................................................................................................................................8
1. Policy .............................................................................................................................................. 8
2. Construction .................................................................................................................................... 8
12.1.8 Battery Charger Panel ............................................................................................................................................8
1. Policy .............................................................................................................................................. 8
2. Construction .................................................................................................................................... 8
Page 12-1
12.0 PANELS
1. Philosophy
1.
2.
All protection, control and any interface to the primary equipment shall be housed
inside cubicles or panels.
All panels shall be installed indoor, inside the substation, except mentioned
otherwise.
Page 12-2
1. Policy
1.
2.
3.
4.
3.
2. Types of
Panels
1.
The types of panels that will be discussed in this document are as follows, but not
limited to;
a. Relay Panel and Control Panel,
b. Supervisory Interface Panel,
c. Outdoor Marshalling Kiosk,
d. Isolator Box,
e. Transformer Local Control Panel and On Load Tap Changer Panel,
f. Transformer Remote Tap Changer Control Panel,
g. Local Control Cubicle,
h. Battery Charger Panel.
3. Colour
1.
2.
The interior of each panel shall be finished with a matte white surface.
The exterior finish and colour of all cubicles shall be light aircraft grey in accordance
to BS381C, Code 627.
4. Construction
1.
All indoor located panels shall comply with enclosure of at least IP31 in accordance to
IEC 60529.
2. All outdoor located panels shall comply with enclosure of at least IP44 in accordance
to IEC 60529.
3. All equipment and devices that are installed outdoor shall comply with enclosure of at
least IP54 in accordance to IEC 60529.
4. Panels shall be suitable for floor mounting and shall provide for bottom entry of
power and multi-core cables via vermin proof plates.
5. Each cubicle shall be well-ventilated through vermin proof louvres fitted with brass
gauze screens.
6. Panel shall be constructed of sheet steel not less than 2mm thickness and shall
preferably be folded construction.
7. All switches for electrically operated apparatus shall be of approved type.
8. Suitable types of switches shall be provided for the various dedicated applications.
9. Current position of switches (push-buttons, discrepancy and discrete types) shall be
clearly displayed and indicated.
10. Lamp test facilities shall be provided for panels with illuminated indicators.
11. Each panel shall be provided with single-phase 13A-240V AC supply complete with
socket and protection, mounted at the front of the panel.
12. The 415/240 volts terminals shall be segregated from other terminals and shall be
fitted with non-flammable transparent plastic covers to prevent contact with any live
parts. Adequate labels shall be provided.
Page 12-3
5. Mounting
1.
2.
3.
4.
5.
6. Identification
Labels
1.
2.
3.
Relays and their auxiliary equipment shall not be fitted on the rear doors.
Transparent panel doors may not be applicable for distribution level panels.
All panels shall be accessible from front and rear for transmission level substations.
The cubicle door and relay mounted hinged panels shall have the facility to be
opened and latched to a minimum of 150 degrees position.
All protection relays and control equipment shall be flush mounted on a removable
plate.
For transmission level installations, local control panel of equipment (especially GIS)
shall be made to stand alone and not attached to the primary equipment concerned.
All panels shall be provided with adequate identification labels designating the circuit
name of the particular panels on the front and rear.
The panel identification label shall be placed on the lower side of the front and rear
panel.
All items (relays, fuses, etc) fitted on control and relay panels shall be provided with
identification labels. The labels shall be on or as close as possible to each item.
7. Test Facilities
1.
2.
3.
8. Meters
1.
All indicating instruments and meters shall be of the flush mounted type with dust
and moisture proof covers.
Instruments shall be provided with a readily accessible zero point adjustment.
All meters shall be of analogue type and not transducer driven except for MW and
MVAr in SCS applications.
2.
3.
9. Heaters
1.
Anti-condensation heaters with thermostat control shall be fitted in each cubicle and
placed at a suitable and safe location.
10. Lighting
1.
Page 12-4
1.
2.
3.
4.
5.
6.
2. Construction
1.
2.
3.
4.
3. Orientation
1.
2.
All protection relays including automated scheme relays shall be located on its own
bay protection panels.
All control equipment for controlling the primary equipment shall be located on the
control panels.
Dedicated miniature circuit breakers (MCBs) shall be provided on the control and
relay panels for the individual protection, control and signalling functions.
Control boards and panels shall be provided with mimic diagrams according to the
standard TNB colour code showing the main primary connections in single line AC
schematic form at a convenient height, so as to permit ready operation of the circuit
breaker control switches and discrepancy type switches and indicators which shall be
incorporated on such diagrams.
Earthed anti-static strap or other possible means of anti-static device shall be
provided on each relay panel.
Panels shall be designed such that future extension work on the panel can be carried
out.
Each panel shall form a complete 800mm (Width) x 800mm (Depth) x 2275mm
(Height) enclosure and shall be associated with only one circuit of Main protection
scheme. For any other size of panel, approval shall be sought from the relevant
Technical Committee.
The stiffness of cubicle shall be such as to prevent mal-operation of protection
scheme.
Panels shall be suitable for floor mounting and shall provide for bottom entry of
power cables and multi-core cables via vermin proof plates.
The front door panels shall be of transparent type so that indications and relay
operations are clearly visible without having to open the panel door.
The arrangement of protection relay panels and control equipment panels shall follow
the actual switchgear orientation in the switchyard.
For SCS-equipped substation, relay panels and control panels for their respective bay
or diameter shall be located side by side, adjacent to each other, as typically shown
in Figure 12.1.1A.
Figure 12.1.1A: Typical Relay Panel and Control Panel Location for SCS-equipped
Substation
4. Arrangement
3.
For conventional substation, separate rows of relay panels and control panels shall be
provided.
1.
All relays that give any kind of visual indication shall be located not higher than 1800
mm from the bottom of the panel.
Equipment, relays and terminals shall be readily accessible and shall require a
minimum disturbance of any associated and adjacent equipment for access.
2.
Page 12-5
5. Test Block
1.
Test facilities shall be provided at the front face of the relay panels. These facilities
shall be dedicated for their specific relays and shall not be shared.
6. Isolation Link
1.
2.
7. Annunciator
Windows And
Alarm Scheme
1.
Adequate number of annunciator windows shall be provided for trip and alarm
functions.
For SCS-equipped stations, a limited number of grouped non-latched facia
annunciator windows shall be provided.
2.
1.
2. Specific
Requirements
1.
2.
3.
4.
5.
1.
For A.I.S, all bays shall be provided with outdoor marshalling kiosk to provide
interface between the primary equipment and secondary equipment.
2. Construction
1.
The outdoor marshalling kiosk shall be mounted at the respective bays in the
switchyard.
The marshalling kiosk shall be of vertical construction either free standing or
supported by support steel work on a concrete foundation.
The marshalling kiosk shall be provided with a close fitting lockable rigid steel door
and hinged and latched in such a manner that it can be opened through 190 degrees
from front and rear.
The terminal blocks shall be mounted horizontally in the middle of the marshalling
kiosk on both sides for easy accessibility and unrestricted by interference from other
cubicle devices.
All wiring in the marshalling kiosk shall be supported by cable raceway.
2.
3.
4.
5.
Page 12-6
1.
For A.I.S, all isolators shall be provided with outdoor isolator box to provide interface
between the primary equipment and secondary equipment.
2. Construction
1.
The terminal block shall be sized and rated in accordance to the size and current
carrying capacity of the wires. It shall be of the insertion type where the conductor is
tightened by non-removable screws. Terminal entries shall be shrouded such that no
current-carrying metal is exposed.
The terminal block shall be of the removable link type. The link will facilitate in the
testing and isolation purposes of all circuits during maintenance.
Switches, push-buttons and lamps provided shall be of reliable and standard types,
and also easily replaceable when necessary.
Anti-condensation heaters with thermostat control shall be fitted and placed at the
suitable and safe location inside the box.
2.
3.
4.
1.
All transformers shall be provided with local control panel (LCP) and On Load Tap
Changer (OLTC) to provide interface between the primary equipment and secondary
equipment.
Page 12-7
CHAPTER 13
ANCILLARY EQUIPMENTS
1. General Requirements.......................................................................................................... 3
2. Specific Requirement ........................................................................................................... 3
13.1.2 Transducers ......................................................................................................................................................... 4
1. General Requirements.......................................................................................................... 4
2. Specific Requirements.......................................................................................................... 4
13.1.3 Terminal Blocks ................................................................................................................................................... 5
1. General Requirements.......................................................................................................... 5
2. Specific Requirements.......................................................................................................... 5
13.1.4 Auxiliary Relays / Contactors.............................................................................................................................. 6
1. General Requirements.......................................................................................................... 6
2. Specific Requirements.......................................................................................................... 6
13.1.5 Interposing CT/VT ................................................................................................................................................ 6
1. General Requirements.......................................................................................................... 6
2. Specific Requirements.......................................................................................................... 6
13.1.6 Trip Circuit Supervision (TCS)............................................................................................................................ 6
1. Policy ............................................................................................................................... 6
2. General Requirements.......................................................................................................... 6
3. Specific Requirement ........................................................................................................... 6
13.1.7 Multi-Core Cables................................................................................................................................................. 7
1. Policy ............................................................................................................................... 7
2. General Requirements.......................................................................................................... 7
3. Cable Numbering................................................................................................................ 7
13.1.8 Test Facility.......................................................................................................................................................... 7
1. Policy ............................................................................................................................... 7
2. General Requirements.......................................................................................................... 7
Page 13-1
1. Philosophy
1.
2.
Ancillary equipment shall be provided to support and facilitate all protection, control
and measurement functions.
All ancillary equipment shall be sized and rated for their functions.
Page 13-2
1. Policy
1.
2.
All ancillary equipment shall follow the general ancillary equipment requirements.
All ancillary equipment provided shall be of the approved type with suitable rating for
its intended functions.
2. Type of
Ancillary
Equipment
1.
The type of ancillary equipment that will be discussed in this document are as
follows, but not limited to;
a. Master Trip Relay (MTR),
b. Transducer (TDC),
c. Terminal Blocks,
d. Auxiliary Relay/Contactor,
e. Interposing CT/VT,
f. Trip Circuit Supervision (TCS),
g. Multi-core Cable,
h. Test Facility.
1. General
Requirements
1.
7.
All master trip relay (MTR) shall undergo and pass acceptance testing, and made
listed in the TNB Accepted Relay List before being accepted to be used in TNB
substations.
MTR shall be provided with suitably rated heavy-duty contacts to trip and lockout the
circuit breaker. The number of contacts shall be sufficient for the tripping
requirements.
All MTRs shall have sufficient normally open (NO) and normally close (NC) contacts to
cater for all interlocking requirements.
All MTRs shall provide electrical reset facility.
All MTRs shall be provided with latched flag relay or LED that can only be reset
electrically from a single command.
Two MTRs shall be provided for 275kV and above systems, and located at each Main
protection panel.
One MTR shall be provided for 132kV system, and located at Main protection panel.
1.
For distribution feeders, MTR will not be provided unless specified otherwise.
2.
3.
4.
5.
6.
2. Specific
Requirement
Page 13-3
13.1.2 Transducers
1. General
Requirements
1.
2. Specific
Requirements
1.
2.
3.
4.
5.
2.
3.
All transducers shall be of static type and shall be used to convert A.C or D.C
quantities into a load independent D.C output.
All A.C transducer shall be rated for 50 Hz operations.
Transducers shall be powered up from the substation D.C auxiliary supply.
Transducers shall be of accuracy class of 0.2 or better, unless otherwise specified.
The output range of the transducers shall be of 4 to 20 mA.
All transducers located in the control panel shall only be used for telecontrol and
telemetering purposes.
The types of transducers;
a. True r.m.s A.C voltage,
b. True r.m.s A.C current,
c. Active power,
d. Reactive power,
e. D.C voltage,
f. Frequency.
All transducers shall fulfil and pass the Type Tests requirements.
Page 13-4
1. General
Requirements
1.
All terminal blocks shall comply in accordance to IEC 60947-7-1, and shall undergo
and pass acceptance testing, and made listed in the TNB Accepted Relay List before
being accepted to be used in TNB substations.
2. All terminal blocks rails shall be mounted in accessible position.
3. The spare cores for multicore are not required to be terminated. However, the spare
cores are required to be grouped to each cable and bundled together separately from
the raceway. Each core shall be numbered with core number preceded by cable
number.
4. There shall be not more than two cores of multi-core cables and internal cubicle wires
connected to any one terminal. Where bridging connections are necessary, these
shall be incorporated in the terminal blocks or via insulated comb-type links.
5. Insulated barrier shall be fitted between adjacent terminals.
6. Terminal assemblies are preferably to be of the unit form suitable for mounting
collectively on a standard assembly rail, secured from the front and giving the
required number for ways.
7. Adequate number of spare terminal blocks (typically 10% for each group) shall be
provided. In addition, a spare terminal block group with 10 number of terminal
blocks shall be added.
8. Each terminal shall be numbered in a consecutive order within the group, and each
group of the same rail shall be identified separately. Labels shall be used to
designate different group of assembly rails.
9. The terminal block shall be sized and rated in accordance to the size and current
carrying capacity of the wires. It shall be of the insertion type where the conductor is
tightened by non-removable screws or any approved method. Terminal entries shall
be shrouded such that no current carrying metal is exposed.
10. In all cases, the terminal blocks shall be of the removable, isolatable sliding link type.
The link will facilitate in the testing and isolation purposes of all circuits during
maintenance.
11. For Telecontrol purposes, isolatable link type terminal blocks shall be provided.
12. All terminal blocks shall be provided with standard banana sockets test points.
2. Specific
Requirements
1.
2.
3.
The 415/240 volts terminals shall be segregated from other terminals and shall be
fitted w ith non-flammable transparent plastic covers to prevent contact with any live
parts. Adequate labels shall be provided.
All connections shall be made at the front of the terminal boards and no live metal
shall be exposed at the back.
Clear demarcations and grouping of functions for the DC terminal blocks are to be
exercised.
Page 13-5
1. General
Requirements
1.
2.
3.
4.
5.
6.
7.
8.
2. Specific
Requirements
1.
All auxiliary relays shall be housed, labelled and arranged according to functions in a
dedicated enclosure within the kiosk/panel.
1. General
Requirements
2. Specific
Requirements
1.
4.
5.
Interposing Current Transformer (ICT) may be used for vector correction and
magnitude correction for transformer protection scheme.
The use of ICT solely for magnitude correction purposes is not allowed.
ICT and Interposing Voltage Transformer (IVT) used shall have sufficient accuracy
and characteristic for its intended functions.
The ICT and IVT shall be connected as close as possible to the burden.
Saturation ICT may be used if measuring purposes are sharing protection CT circuits.
1.
2.
2.
3.
1. Policy
1.
All tripping circuits including circuit breaker trip coils shall be continuously supervised
irrespective of its position.
2. General
Requirements
1.
2.
3.
4.
5.
Trip Circuit Supervision (TCS) scheme shall not cause any CB to trip.
A set of TCS relay shall be used to monitor one trip circuit only.
Monitoring shall be done continuously, immaterial of the CB status.
Indication on TCS shall only be triggered for discontinuity in the trip circuit.
All TCS relays/schemes shall undergo and pass acceptance testing, and made listed
in the TNB Accepted Relay List before being ac cepted to be used in TNB substations.
3. Specific
Requirement
1.
For 132kV systems and above, two sets of TCS relays shall be provided and located
at each Main protection panel.
Page 13-6
1. Policy
1.
All multi-core cables used for their intended applications shall be adequately rated
and insulated, with clear and purposeful demarcation.
2. General
Requirements
1.
7.
All secondary cable insulation for the protection, switchgear, control and etc. shall be
rated at 600/1000 volts.
All secondary CT, VT and A.C circuits shall be of copper conductor with minimum
cross sectional area not less than 4mm2 from the instrument transformers to the
terminal blocks in the relay/control panels. The cables shall be colour coded for
phase identification.
All secondary cabling used for control purposes shall be of stranded copper conductor
with minimum cross sectional area not less than 2.5mm2.
For internal panel wiring, the cross sectional area conductor of the copper conductor
may be less than the specified above, provided that it is not less than the minimum
of 2.5mm2 for CT, VT and A.C circuits, while for control circuits it is not less than
1.5mm2.
Cables used for inter-panel wiring shall be adequately armoured. The screen/armour
shall be effectively earthed.
The outdoor-laid cable for used for measurement purposes shall be of screened type
to reduce the effect of EMC interference. The screen/armour shall be effectively
earthed.
A.C inter-panel cables shall be segregated from D.C and control cables.
1.
2.
3.
4.
5.
6.
3. Cable
Numbering
1. Policy
1.
2. General
Requirements
1.
The test facility shall be designed such that maintenance of all protective relays and
instrument/meters can be carried out on live primary equipment without affecting
any other relays or control schemes that are in service.
Testing facilities shall be provided at a suitable position on the relevant panel.
All test facilities shall undergo and pass acceptance testing, and made listed in the
TNB Accepted Relay List before being accepted to be used in TNB substations.
2.
3.
Page 13-7
CHAPTER 14
INSTRUMENT TRANSFORMERS
Page 14-1
1. Background
1.
2. Type
1.
3. Labels
1.
All IT shall be clearly labelled with rating plates and diagram plates, and the plate
shall be on the IT itself and its structure.
Page 14-2
1. Policy
1.
2.
3.
4.
2. Requirements
1.
2.
3.
4.
5.
6.
3. Accuracy
Class
1.
Current transformer (CT) shall be used where current related relays and instruments
are used.
The CT should follow the guidelines as in IEC 60044-1 and IEC 60044-6.
The secondary rated current shall be 1 Amp for 132kV system and above, and 1 or 5
Amps for 33kV system and below.
The preferred position of the protection CT shall follow the concept of overlapping
zone as indicated in the Appendix A.
For bus coupler and bus section, t he CT shall be on each side of the circuit breaker.
CT for Unit protection scheme, including neutral CT, shall have identical turns ratio at
all ends. However for retrofitting purposes, CT mismatch may be acceptable if the
protection relay is capable of ratio and vector group corrections.
All the secondary windings of the CT shall be wired to the marshalling kiosk. The
selection of the ratio used shall be from the marshalling kiosk, and not from the CT
secondary terminals.
CT for High Impedance protection schemes1 including neutral CTs shall have identical
characteristics at all ends. Ratio correction via interposing CT shall not be allowed.
The CT burden shall be sufficient and able to cater for all its loads, and shall be more
than 15VA with minimum ALF = 20.
The detailed design and the burden calculation of each CT for correct application
shall be documented and furnished for approval.
The general applications of the CT shall follow the following accuracy class, as in
Table 14.1A;
Application
All non-unit protection and 87L
All unit protection except 87L
SCS, INSTRUMENTS
Energy Metering
Table 14.1A
Class
5P
TPS
0.5
0.2
4. Ratio
Selection
1.
The ratio selection shall follow the guidelines in the IEC 60044-1 and relevant TNB
guidance notes associated with this Code of Practice.
5. Earthing
1.
2.
3.
4.
6. Neutral
Current
Transformer
1.
For 33kV and below NCT, it shall be of outdoor (weatherproof) ring type construction
with adequate mounting steelworks, and complete cable box for secondary
connections.
Including High Impedance Busbar Protection, Restricted Earth Fault Protection, High Impedance Transformer Protection and
equivalent.
Protection and Control Code of Practice, 2nd Edition
Page 14-3
7. Multiple
Turns Ratio
1.
2.
3.
Where multiple turn ratios of the secondary windings are used, it shall be possible to
select any secondary ratio without any alteration to the primary turns.
Specific label shall be provided at the secondary terminals of the CT indicating clearly
the connection required for either ratio.
The connections and the turn ratios used for the protection scheme shall be shown
on the appropriated schematic and connection diagrams. The used ratio shall be
underlined.
Page 14-4
1. Policy
1.
2.
3.
4.
2. Type
Selection
1.
2.
3. General
Requirements
1.
2.
3.
4.
4. Accuracy
Class and
Burden
1.
2.
3.
Voltage transformer (VT) shall be used where voltage related relays and instruments
are used.
Voltage Transformer (VT) shall be designed suitable for protection and control
systems with minimum transient over-reach during fault conditions.
The VT should follow the guidelines as in IEC 60044-2, IEC 186 and IEC 358.
The secondary nominal voltage of the VT shall be 110/v 3 volts alternating current
(AC) per phase.
The detailed design and the burden calculation of each VT for correct application shall
be documented and furnished for approval.
The general application of the VT shall follow the following accuracy class, as in Table
14.2A.
The burden per winding for VT shall be sufficient and able to cater for all its loads,
and shall not be less than, as in Table 14.2B;
Application
Protection
Instruments
Energy Metering (where applicable)
Class
3P
0.5
0.2
Table 14.2A
Application
132kV and above
33kV and below
5. Earthing
1.
2.
3.
No. of Winding
2 or 3
1
Page 14-5
CHAPTER 15
TECHNICAL DOCUMENTATIONS
Page 15-1
1. Policy
1.
2.
3.
4.
5.
Technical documentations that are complete and adequate shall be provided for each
plant or station as part of the product, system or installation.
The documentations shall be fit for purpose for various tasks and functions
throughout the product life cycle, i.e. for;
a. Engineering design work,
b. Manufacturing,
c. Erection and installation,
d. Testing and commissioning,
e. Fault investigation,
f. Operation and maintenance,
g. Training.
All technical information shall be documented in a proper manner for easy reference.
All as-built documentations shall be kept updated with the latest revision.
Circuit drawings of equipment shall be laminated and placed inside the relevant
panels/cubicles/kiosks.
2. Purpose
1.
3. Document
Structure
Requirements
1.
2.
3.
Page 15-2
4. Document
Preparation
Requirements
1.
2.
3.
5. Computeraided-design
and Document
Requirements
1.
2.
3.
Page 15-3
1. Policy
1.
2.
3.
2. Function
Oriented
Documents
No.
1.
1.
Document
Overview Diagram
2.
Block Diagram
3.
Logic-function diagram
4.
Circuit diagram
5.
Terminal-function
Diagram
Descriptions
Relatively simple diagram, often using single line representation,
showing the main interrelations or connections among the items
within a system, subsystem, installation, part equipment, software,
etc.
For example, single line diagram.
Overview diagram using blocks symbols predominantly. Simplified
representation of a circuit. It shows only the most essential parts, the
basic operation principle, and the system structure.
For example, protection block diagram, protection zone of
overlapping diagram.
Diagram showing details of the theoretical or ideal operation of a
system, subsystem, installation, part, equipment, software, etc. by
means of theoretical or ideal circuits without necessarily taking into
account the means used for implementation.
For example, protection logic diagram, control logic diagram.
Diagram showing the implementation of the circuits of a system,
subsystem, installation, part, equipment, software, etc., depicting
parts and connections by means of graphical symbols arranged to
show the functions but without necessarily taking into account the
physical sizes, shapes, or locations of the items.
It is a detailed representation of the circuit with its individual
components. It illustrates the principle of electrical equipment
operations.
For example, circuit or schematic diagram.
Diagram for a functional unit showing the terminals for the interface
connections and a description of the internal functions. These may be
describe by means of a circuit diagram, simplified if applicable, a
function diagram, a function or sequence chart, or text.
For example, device terminal diagram, apparatus/device drawing list.
Table 15.1A
Page 15-4
3. Location
Documents
No.
1.
1.
Document
Installation
Drawing
[Plan]
2.
Installation Diagram
3.
Assembly Drawings
4.
Arrangement drawings
4. Connection
Documents
No.
1.
1.
Descriptions
Drawing [plan] showing the location of the components of an
installation.
For example, layout drawings.
Installation drawings showing the connections between items.
Drawing representing the spatial position and shape of a group of
assembled parts, normally to scale.
For example, panel assembly drawings.
Assembly drawings simplified or supplemented to give information
needed for some particular purpose.
For example, panel arrangement drawings.
Table 15.1B
Document
Connection Diagram
[table]
Descriptions
Diagram [table] showing or listing the connections of an installation
or equipment.
2.
Unit Connection
Diagram [table]
3.
Interconnection
Diagram [table]
4.
5. Items List
No.
1.
2.
1.
Document
Parts List
Descriptions
List specifying the items (parts, components, software, equipment,
etc.) that constitute an assembly (or sub-assembly) and, if
necessary, the reference documents.
For example, material lists.
List specifying the items (part, components, software, bulk material,
etc.) for preventive and corrective maintenance.
Table 15.1D
Page 15-5
1. Policy
1.
2. Basic Rules
1.
2.
Page 15-6
1. Policy
1.
2. Drawing
Papers
1.
The documentation paper especially paper used for the drawings shall have the
following characteristics;
Paper
Characteristics
Quality
Size Standard
Lettering Standard
3. Drawing
Format
Requirements
Minimum of 80 gsm
A3 (297mm x 420mm) or A4 (210mm x 297mm)
ISO 3098, with font name of ISOCPEUR (Regular style)
2.
3.
1.
2.
The drawings for one bay or system may be spread over several sheets.
The technical drawings and diagrams shall be formatted with the following
requirements;
a. Title block,
b. Borders and frame,
c. Reference grid systems,
d. Diagram component layout with graphical symbols, electrical connections
and linkage lines,
e. Reference designations,
f. Signal and location references,
g. Circuit function references,
h. Technical data (if applicable),
i.
Explanatory marking or notes (if applicable),
j. Terminal function.
Page 15-7
4. Title Block
1.
2.
The position of the title block shall be within the drawing space. The portion of the
title block containing the drawing identification shall be situated in the bottom right hand corner of the drawing space.
The following figure, Figure 15.3A, illustrates the typical drawing identification zone
of the title block, based on IEC 61082-1;
Other information, e.g. TNB logo, contractor/
supplier name and logo, issuing date,
approval by and date
Title field
Title field to include:
Document/Drawing type
Bay Name/Type
Drawing function type
Drawing no.
Drawing no.
Revision index
Revision index
Sheet no.
Substation name
TNB Identification
no.
Supplier
Identification no.
Page 15-8
5. Reference
Grid Systems
1.
DATE
OWNER:
DRAWN
CHECKED
REV
DATE
1
NAME
APP'D BY
2
CONTRACTOR:
TENAGA NASIONAL
BERHAD
TITLE:
SUPPLIER:
CONTRACT NO.:
TENDER NO.:
DWG. NO.:
SUBSTATION:
/
R E V . THIS SH.:
NEXT SH.:
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
The typical grid starting position is at the upper-left corner. Even number of grid
divisions is chosen in relation to the complexity of the drawings (Preferably 6 by 8
divisions).
The rectangles of the grid should be refe renced by means of capital letters along
vertical edges and numerals along the horizontal edges. The numbering direction
may start at the sheet corner opposite the title block drawing identification zone.
Page 15-9
6. Diagram
Layout
1.
2.
The diagram layout signal flow direction for overview, function, and circuit diagrams
shall be from top to bottom or, alternatively from left to right. The former is
preferred. The controlling system shall be placed to the top or left of the functionoriented group. The preferred circuit diagram layout is illustrated in Figure 15.3C.
The diagram signal flow direction for logic-function diagram shall be from left to
right. The preferred logic-function diagram layout is illustrated in Figure 15.3D.
&
0
0
0
>=1
0
7. Signal and
Location
References
3.
4.
If the flow is not obvious, connecting lines shall be provided with arrowheads.
Where applicable, the logic function diagram shall differentiate between software and
hardwire logic implementations.
1.
The signal designations for connecting lines or item designation shall be placed above
the horizontal connecting lines or to the left of the vertical lines.
If the connecting lines are interrupted on one sheet or continues on another sheet,
the end of the interrupted line shall be mutually referenced. Grid system reference
and/or sheet number shall be utilized for this function. The location reference is
indicated by the combination of the letter of the row and the number of the column.
These indications may be preceded by the sheet number.
The relay coils and terminals, other equipment secondary contacts, other
manufacturer devices, shall be cross-referred to the terminal function drawings.
2.
3.
8. Terminal
Function
Drawings
1.
2.
3.
4.
9. Circuit
Function
Reference
1.
Terminal function drawings shall be prepared for all circuit devices. The drawings
shall indicate the device designation, reference sheet and location references.
The drawings shall indicate the number of relay contact used in the drawings and
shall be labelled clearly. The relay type, model, version and rating shall also be
specified. When the contacts and coils/terminals used elsewhere (e.g. on other
circuit diagram sheet), the contact and coils/terminals shall be clearly indicated.
The terminal function drawings shall also include the primary equipment control
circuits, busbar isolator auxiliary contacts timing diagram and other equipment
secondary circuits.
The terminal function drawings may include relay configuration and table of relay
contacts.
For diagram layout signal flow direction from top to bottom, each circuitry function or
group of circuitry functions of the circuit diagrams may be designated at the top of
the drawing space.
Page 15-10
1. Policy
1.
2. Principles
1.
The alphanumeric codes of the reference designation for the purpose of clear and
unique identification of devices are made of the following designations, as in Table
15.4A.
The reference system below does not apply for internal supply system or equipment
within a power station. For power station, the Identification System for Power Plants
or KKS (Karftwerk Kennzeichen System) reference system shall be used.
2.
Qualifying
Symbols
=
+
.
:
3. Designation
block
1.
The reference designation block structure and formation consist of the qualifying
symbols assigned to it and series of alphanumeric characters as the following order,
as shown in Figure 15.4A below;
=
AA
NN
AA
NN
NN
AA
NN
Figure 15.4A
Page 15-11
4. Plant/Higher
Level
Designation
1.
The letter code A of the higher level designation block =AANN is defined as in
Table 15.4B.
Code
Letter A
B
D
E
F
H
J
K
N
NE, NF, NG, NH
NK, NL, NM, NN
2.
HV
Level/Plant
500kV
275kV
132kV
66kV
33kV
22kV
11kV
< 1kV
415/240V A.C
110V D.C
Table 15.4B
=D03
=D05
=D07
=D02
=D04
=D06
=D08
Figure 15.4B
3.
=E01
=E02
=E03
=E04
=E05
=E06
=E07
=E08
Figure 15.4C
Page 15-12
5. Location
Designation
1.
Code
Letter AA
J
N
P
Q
R
S
T
U
V
W
X
Y
AC
DC
DR
RW
RT or RTC
RTU
SC
SP
ST
2.
The letter code A of the location designation block +AANN is defined as in Table
15.4C.
Location
Junction Box
Auxiliary supply services
Operator desk
Metering panel
Relay panel or protection panel
Switchgear local control panel
Transformer
Supervisory marshalling cubicle (e.g. RTU marshalling)
Outdoor marshalling kiosk
Control panel
Centralised/Interface panel
Communication panel
415/240V LVAC switchboard
D.C charger
Recorder
Relay control panel
Remote tap-changer control panel
Remote Terminal Unit
Station level computer panel
Synchronising panel
Transformer local control panel
Table 15.4C
A typical panel arrangement for 275kV relay and control panel (for AIS station with
SCS facilities) is as shown in Figure 15.4D below. The arrangement shall corresponds
to the actual switchyard layout arrangement.
=D01+W1, =D01+R1, =D01+R2 as follows;
=D01+W1
=D01+R1
=D01+R2
=D03+W1
=D03+R1
=D03+R2
=D04+R1
=D04+W1
PANEL FRONT
PANEL FRONT
=D02+R2
=D02+R1
=D02+W1
=D04+R2
Figure 15.4D
Page 15-13
6. Device
Designation
1.
2.
Code Letter
A
B
C
E
F
G
H
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
7. Switching
Device
Designation
1.
Device
Designation
Q0
Q1
Q11
Q12
Q21
Q22
Q15Q19
Q25Q29
Q2
Q5
Q51
Q52
Q8
Q9
Q6, Q61, Q62
The letter code A of the device designation block -ANN is defined as in Table
15.4D.
For protective equipment, the designation includes the Protective device code instead
of numerical code. Refer to Section 15.9 for the protective device code.
For example, Main 1 Distance Protection is represented by -F21Z/1.
Apparatus/device
Device combination, assemblies, subassemblies, BCU
Converter
Condenser, capacitor
Heater, illuminations, lighting
Protection, relays, MCBs, transformer guards
Supply equipment, generator, power supplies
Signalling devices
Auxiliary relays, time delay relays, contactors
Inductor, reactor
Motor
Regulator, amplifier, controller
Metering device, test equipment, measuring equipment
HV circuit breaker, disconnector, isolator, switching devices
Resistor
Switches, control switch, limit switch, push button, selector
Current transformer, voltage transformer, transformer
Transducer
Diode, transistor, semiconductor
Transmission path, cable, busbar, hollow conductor, antennae
Terminal block, plug, socket, outlet, relay test plug
Electrically operated mechanical device, trip coil, closing coil
Filter, limiter
Table 15.4D
Apparatus/device
Circuit breaker
Main busbar isolator/disconnector
Main bus section isolator/disconnector
Main bus section isolator/disconnector
Reserve bus section isolator/disconnector
Reserve bus section isolator/disconnector
Main busbar earthing switch
Reserve busbar earthing switch
Reserve busbar isolator/disconnector
Maintenance earthing switch
First maintenance earthing switch
Second maintenance earthing switch
Line earthing switch
Line isolator/disconnector
1 CB tie isolator/disconnector
Table 15.4F
Page 15-14
8. Terminal
Designation
1.
2.
Page 15-15
1. Policy
1.
2. Document
Type
1.
Code
A
B
Type of Document
General
Overview Diagrams
Block Diagrams
E
F
Installation
Diagrams/Drawings
Logic Function Diagrams
Structural Drawings
Design Drawings
Technical/Design
Dalculations
Equipment Assembly
Drawings
Hydraulic/Gas(SF6)
Diagrams
Function Chart
M
P
R
S
Schematic Diagrams
(Circuit Diagrams)
Terminal Function Diagrams
V
X
Z
Panel Arrangement
Drawings
Unit Connection Diagram or
Tables
Interconnection Diagrams or
Tables
Other Documents
Example
Guides, drawing list, document list, master list, indices.
Function-orientated simple diagram, e.g. single-linediagram and network interconnection, etc.
Function-orientated overview diagram, e.g. bay/station
level block diagram, etc.
Ground system layouts and details, lightning system layout
and details, foundation grounding, etc.
Function-orientated diagram showing operation of a
syste/sub-system/installation/etc.
Structural specifications, formwork plans and reinforcement
diagrams.
Portal and lightning rod, cable rack, capacitor rack, etc.
and design drawings for fabrication.
Design calculations such as load calculation, short circuit
calculations, battery sizing, CT sizing, etc.
Equipment drawings such as for isolators, CBs, etc. and
normally to scale.
Gas, pneumatic and hydraulic diagrams.
Power and control system descriptions using steps and
transitions.
Function-orientated overview diagram showing the
implementation of the circuits of a system.
Diagrams for functional unit showing the terminals for the
interface connections and description of the internal
functions.
Function chart (table) describing the function and
behaviour of a control system.
Drawing showing special position and shape of a group of
assembled parts.
Drawings simplified or supplemented to give information
needed for particular purposes.
Connection diagram showing or listing the connections
within a constructional unit, e.g. wiring diagram or wiring
schedule.
Connection diagram showing the connections among
different constructional units such as core schedules.
Time schedule and other supplementary drawings.
Table 15.5A
Page 15-16
1. Policy
1.
The drawing function may be indicated in the documents and drawings. Generally,
the document type is indicated at the top right corner of the title block. The intended
drawing function is separated by an oblique stroke ( / ).
2. Drawing
function
1.
Code
/A
/B
/D
/G
/L
/M
/N
/P
/Q
/R
/S
/T
/U
/X
/Y
/Z
2.
Page 15-17
1. Policy
1.
All interconnection conductors, i.e. cable and wiring, shall be clearly marked based on
a standard designation marking.
2. Wiring
Marking
1.
Cable Number
Core Number
Terminal Number
Termination direction from left to right
Conductor
Trip **
Terminal Number
Termination direction from right to left
Trip **
Core Number
Conductor
Cable Number
** Red colour ferrule marker shall be provided for trip circuit only.
Figure 15.7A
2.
The ferrule marker for each block may be differentiated by the use of alternate white
and yellow ferrule marker. The above terminal number ferrules can be divided into
two groups with different colour, i.e. terminal group and dedicated terminal number,
as in Figure 15.7B;
Terminal
Block
E0110
XA
Trip
Conductor
White
Yellow
White
Yellow
Red
Conductor to
be crimped
with lug.
XA:2
3. Cable
Marking
3.
1.
NN
NN or NNN
Figure 15.7C
2.
The letter code A is defined as voltage level. The first numeric NN group
represents the bay number. The second numeric group NN or NNN is to be
classified based on a designated cable group running number.
Page 15-18
1. Policy
1.
All unit connection conductors, i.e. internal panel multi-core wiring, shall be clearly
marked based on a standard designation marking.
2. Wiring
Functional
Identification
1.
Each internal panel multi-core wiring shall be identified and marked according to its
function. The identification mark shall also be placed above the horizontal connecting
lines or to the left of the vertical lines of the circuit/schematic drawings.
For terminal block connection, terminal block number may be included with the
wiring functional identification number.
The wiring functions are as follows, as in Table 15.8A;
2.
3.
Code
A
Function
Current transformers for;
Busbar protection.
Current transformers for;
Backup protection,
Overcurrent protection,
instruments,
BCU,
metering,
voltage control.
Reference voltage for;
instruments,
BCU,
metering,
protection.
Reference voltage for;
synchronizing.
A.C supplies.
D.C supplies.
control,
B
C
L
M
Example
10-29 : Red phase.
30-49 : Yellow phase.
50-69 : Blue phase.
70-89 : Residual circuits and neutral
current transformers.
90 : Earth wires directly connected to
earth bar.
If more numbers are required, the wire
number may consist of three digits in
the multiplication of one hundred.
Page 15-19
Code
N
R
S
T
W
Y
Z
Function
Tap change control including;
transformers paralleling,
tap position,
protection,
tripping,
Example
Any running number from 1 upwards.
- J1, J2
- K1
Page 15-20
1. Policy
1.
2.
3.
2. Purpose
1.
3. Concept
1.
4. Relay Flag
and Lighting
Device
Indications
1.
The device flags and lighting indications on the relay shall be clearly labelled with
common understanding description according to its function.
5. Protective
Device Code
1.
Page 15-21
APPENDIX A
MAIN 1 PROTECTION
Current Transformer
A
MAIN 2 PROTECTION
MAIN PROTECTION
BACKUP
PROTECTION
B
AUTO
RECLOSE
Isolator or Disconnector
Earthing point
Autoreclose function
MTR 1
MTR 2
MTR
Circuit Breaker
EXTERNAL
AR BLOCK
START
BLOCK
BREAKER
FAILURE
S1
S2
BACKUP
PROTECTION
Xp
Xp
OR
REV
DATE
NAME
DATE
DRAWN
CHECKED
APP'D BY
25/10/2003
OWNER:
UMAR / RIZAL
RAZAK
ILHAM
CONTRACTOR:
TENAGA NASIONAL
BERHAD
Legends
SUPPLIER:
CONTRACT NO.:
TENDER NO.:
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
=
DWG. NO.:
SUBSTATION:
1
2
500kV or 275kV
BUS
132kV
BUS
132kV
BUS
CT1, Core 1
Main 1 Protection
CT1, Core 1
Main Protection
CT1, Core 1
Main Protection
CT1, Core 2
Main 2 Protection
CT1, Core 2
Backup Protection
CT1, Core 2
Backup Protection
CT1, Core 3
Backup Protection
(see Note)
CT1, Core 3
CT1, Core 3
CT1, Core 4
CT1, Core 4
Busbar Protection
(Discriminating Zone)
CT1, Core 4
Busbar Protection
(Low Impedance)
CT1, Core 5
Busbar Protection
(Discriminating Zone)
CT1, Core 5
Busbar Protection
(Check Zone)
CT1, Core 6
Busbar Protection
(Check Zone)
Note:
This CT core may also be used for Low Impedance
Busbar protection, Backup Diatance Protection,
Recorders and Breaker Failure protection.
F
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
CT_132kV_above_OHL/UGC
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
2
3
33kV
BUS
22kV
BUS
11kV
BUS
CT1, Core 1
Main Protection
CT1, Core 1
Main Protection
CT1, Core 1
Main Protection
CT1, Core 2
CT1, Core 2
CT1, Core 2
CT1, Core 3
Energy Meter
(Where required)
CT1, Core 3
Energy Meter
(Where required)
CT1, Core 3
Energy Meter
(Where required)
CT1, Core 4
Busbar Protection
(Where required)
CT1, Core 4
Busbar Protection
(Where required)
CT1, Core 4
Busbar Protection
(Where required)
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
CT_33kV_below_OHL/UGC
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
3
4
500kV or 275kV
BUS
Main 1 Protection
CT1, Core 1
B
Backup Protection
Backup Protection
(see Note 1)
CT1, Core 3
CT6, Core 1
33kV or 22kV
or 11kV
Main 1 Protection
Main 2 Protection
CT1, Core 2
CT1, Core 4
Busbar Protection
(Disriminating Zone)
CT1, Core 5
Main 2 Protection
Busbar Protection
(Check Zone)
CT1, Core 6
C
C
Earthing
XFMR
Red phase
*
Y Z
Blue phase
CT2, Core 5
CT2, Core 4
Busbar Protection
(Check Zone, see Note 2)
CT2, Core 6
CT5, Core 1
REF Protection
CT3, Core 2
CT5, Core 2
CT3, Core 1
Tertiary
grounding
SBEF Protection
Common grounding,
solid
Yellow phase
Busbar Protection
(Discrimination Zone, see Note 2)
Main 2 Protection
Backup Protection
CT2, Core 3
CT2, Core 2
CT2, Core 1
E
Main 1 Protection
Legend:
Single line diagram (SLD), bus
SLD, line/cable
Three-phase diagram, line/cable
Note:
1. This CT core may also be used for Low Impedance Busbar protection, Backup Distance Protection,
Recorders and Breaker Failure protection
2. Where 132kV busbar is protected by Low Impedance relay, the relay shall be connected to CT2
Core 5, and CT2 Core 6 is not required.
275kV or 132kV
*. Additional CT cores shall be provided for 500/275kV autoXFMR for Unrestricted Earth Fault
Protection.
BUS
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
CT_AUTOXFMR_TV
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
4
5
500kV or 275kV
BUS
Main 1 Protection
CT1, Core 1
B
Backup Protection
Backup Protection
(see Note 1)
CT1, Core 3
Main 1 Protection
Main 2 Protection
CT1, Core 2
CT1, Core 4
Busbar Protection
(Disriminating Zone)
CT1, Core 5
Main 2 Protection
Busbar Protection
(Check Zone)
CT1, Core 6
C
C
Red phase
Common grounding,
solid
Yellow phase
Blue phase
CT2, Core 5
CT2, Core 4
Busbar Protection
(Check Zone, see Note 2)
CT2, Core 6
CT3, Core 2
CT3, Core 1
Tertriary grounding,
see Note 3
Busbar Protection
(Discrimination Zone, see Note 2)
Main 2 Protection
Backup Protection
CT2, Core 3
CT2, Core 2
CT2, Core 1
E
Main 1 Protection
Legend:
Single line diagram (SLD), bus
SLD, line/cable
Three-phase diagram, line/cable
Note:
1. This CT core may also be used for Low Impedance Busbar protection, Backup Distance
Protection, Recorders and Breaker Failure protection.
2. Where 132kV busbar is protected by Low Impedance relay, the relay shall be connected to
CT2 Core 5, and CT2 Core 6 is not required.
275kV or 132kV
BUS
3. Tertiary winding is only grounded at one phase only, usually at Yellow phase.
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
CT_AUTOXFMR_TV_NONE
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
5
6
132kV
BUS
CT1, Core 1
Backup Protection
CT1, Core 2
CT1, Core 3
CT1, Core 4
Busbar Protection
(Check Zone, see
Note)
CT1, Core 5
REF Protection
Busbar Protection
(Discrimination Zone,
see Note)
Y
HV grounding, solid
CT3, Core 1
Earthing
XFMR
Z Y
D
CT2, Core 4
Busbar Protection
(Where required)
CT2, Core 3
Energy Meter
CT2, Core 2
Backup Protection,
SCS & Instrument
CT2, Core 1
CT4, Core 2
SBEF Protection
CT4, Core 1
REF Protection
Note:
Where 132kV busbar is protected by Low Impedance relay, the relay shall be
connected to CT1 Core 4, and CT1 Core 5 is not required.
BUS
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
4
=
+
CT LOCATION, NO. OF CORES AND
FUNCTIONS FOR 132/33kV,132/22kV & 132/
11kV Yd VECTOR GROUP XFMRs
CT_132kV_XFMR(Yd)
SUBSTATION:
6
7
/
REV. THIS SH.:
1
NEXT SH.:
8
6
7
132kV
Backup Protection
SCS & Instrument
CT1, Core 3
CT1, Core 4
Busbar Protection
(Check Zone, see
Note)
CT1, Core 5
REF Protection
CT1, Core 2
BUS
CT1, Core 1
Busbar Protection
(Discrimination Zone,
see Note)
SBEF Protection
REF Protection
Y
HV grounding, solid
CT3, Core 1
Busbar Protection
(Where required)
CT2, Core 3
Energy Meter
CT2, Core 2
Backup Protection,
SCS & Instrument
CT2, Core 1
CT4, Core 1
CT2, Core 4
CT4, Core 2
Note:
Where 132kV busbar is protected by Low Impedance relay, the relay shall be
connected to CT1 Core 4, and CT1 Core 5 is not required.
BUS
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
4
=
+
CT LOCATION, NO. OF CORES AND
FUNCTIONS FOR 132/33kV, 132/22kV & 132/
11kV Yy VECTOR GROUP XFMRs
CT_132kV_XFMR(Yy)
SUBSTATION:
6
7
/
REV. THIS SH.:
1
NEXT SH.:
8
7
8
CT2N, Core 4
CT2N, Core 3
Backup Protection
CT2N, Core 2
Main Protection
CT2N, Core 1
North Bus
132kV
OHL/UGC Feeder
Stub Protection
(North side)
CT1N, Core 1
Stub Protection
(North side)
CT1N, Core 2
Busbar Protection
CT1N, Core 3
Busbar Protection
(Where required)
CT3N, Core 1
Stub Protection
(South side)
CT3S, Core 1
Stub Protection
(North side)
Main 1 Protection
CT2S, Core 1
Main 2 Protection
(see Note)
CT2S, Core 2
Backup Protection
CT2S, Core 3
CT2S, Core 4
Stub Protection
(South side)
CT2S, Core 5
CT1S, Core 3
Busbar Protection
(Where required)
CT1S, Core 2
Busbar Protection
CT1S, Core 1
Stub Protection
(South side)
E
South Bus
Note:
Where required, such as for 275kV/132kV
AutoXFMR connection
132kV
XFMR Feeder
F
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
CT_132kV_1-half-breaker
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
8
9
CT2N, Core 5
North Bus
500kV or 275kV
OHL/UGC Feeder
Stub Protection
(North side)
Main 2 Protection
Main 1 Protection
CT2N, Core 4
CT1N, Core 1
CT2N, Core 3
CT1N, Core 2
CT2N, Core 2
CT1N, Core 3
CT2N, Core 1
CT1N, Core 4
CT3N, Core 1
C
Stub Protection
(North side)
Local Backup,
Main 2 BB Protection
Main 1 BB Protection
(Check Zone)
Stub Protection
(South side)
C
Local Backup
CT3N, Core 2
CT3S, Core 1
Main 1 BB Protection
(Disc. Zone)
Stub Protection
(North side)
Main 1 Protection
Main 2 Protection
Backup Protection
SCS & Instrument
Stub Protection
(South side)
CT2S, Core 1
CT1S, Core 4
CT2S, Core 2
CT1S, Core 3
CT2S, Core 3
CT1S, Core 2
CT2S, Core 4
CT1S, Core 1
Main 1 BB Protection
(Check Zone)
Main 1 BB Protection
(Discriminating Zone)
Local Backup,
Main 2 BB Protection
Stub Protection
(South side)
E
CT2S, Core 5
500kV or 275kV
Auto XFMR Feeder
South Bus
Abbreviation:
BB = Busbar
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
4
+
CT location, cores and functions for 500kV & =
275kV and above OHL and UGC feeders with 1half breaker busbar scheme
CT_275kV_1-half-breaker
SUBSTATION:
6
7
/
REV. THIS SH.:
1
NEXT SH.:
8
9
10
CT1M, Core 1
CT1M, Core 2
CT1M, Core 3
CT2M, Core 2
A
CT2M, Core 1
Main Bus 1
Main Bus 2
CT3M, Core 1
CT3M, Core 2
Backup Protection,
Low Impedance BB Protection
(see Note 1 & 2)
Main Bus 2, BB Protection*
CT1R, Core 3
Backup Protection
CT1R, Core 2
CT1R, Core 1
Note:
1. The Low Impedance BB protection is only for 275kV and 500kV systems only.
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
CT_132kV_above_BT
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
10
11
CT1M Core 1
CT2M, Core 1
Main Bus 1
Main Bus 2
CT3M, Core 2
CT3M, Core 1
D
CT1R, Core 1
E
Reserve Bus
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
CT_33kV_below_BT
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
11
12
DISCRIMINATION
ZONE
&
CT SUPERVISION
(HEALTHY)
B
FEEDER
TRIP
RELAYS
ISOLATORS
SELECTION
&
CHECK ZONE
TRIP
COIL
1
MTR 1
&
TRIP/
OPEN
CB
CT SUPERVISION
(HEALTHY)
TRIP
COIL
2
MTR 2
(see Note)
BREAKER
FAILURE
(Where
required)
S1
S2
INTERTRIP SEND
Note:
For 132kV system, only one MTR is required.
Abbreviation:
BB = Busbar
BBP = Busbar Protection
F
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
SUBSTATION:
4
12
13
MEASURING METHOD
1
(see Note 2)
&
BBP
[BAY ACQ
UNIT]
TRIP
COIL
1
MTR 1
TRIP/OPEN
CB
MEASURING METHOD
2
(see Note 2)
TRIP
COIL
2
MTR 2
(see Note 1)
D
E
Note:
1. For 132kV system, only one MTR is required.
2. One of the methods shall be Biased Differential
principle as mentioned in section 3.8.4.
Abbreviation:
BB = Busbar;
BBP = Busbar Protection;
ACQ = Acquisition.
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
SUBSTATION:
4
13
14
ISOLATORS
SELECTION
MEASURING METHOD
1
(see Note 2)
BBP
[BAY ACQ
UNIT]
&
TRIP
COIL
1
MTR 1
TRIP/OPEN
CB
MEASURING METHOD
2
(see Note 2)
TRIP
COIL
2
MTR 2
(see Note 1)
D
E
Note:
1. For 132kV system, only one MTR is required.
2. One of the methods shall be Biased Differential
principle as mentioned in section 3.8.4.
Abbreviation:
BB = Busbar;
BBP = Busbar Protection;
ACQ = Acquisition.
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
SUBSTATION:
4
TRIP_SCHEME_132kV_up_BB_
NLI_D
7
/
REV. THIS SH.:
1
NEXT SH.:
8
14
15
OPEN COMMAND
MAIN 1 PROTECTION
NON AR FAULTS
MTR 1
TRIP COIL 1
TRIP/OPEN
CB
MAIN 2 PROTECTION
NON AR FAULTS
TRIP COIL 2
BACKUP PROTECTION
MTR 2
BREAKER FAILURE
INTERTRIP RECEIVE
OR
CLOSING
SIGNAL
START
OR
BLOCK
AUTO
RECLOSE
EXTERNAL
AR BLOCK
AR LOCKOUT
AR LOCKOUT
BREAKER
FAILURE
S1
S2
87BBHI
TRIP
INTERTRIP SEND
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
SUBSTATION:
4
15
16
OPEN COMMAND
DIRECT TRIP
MAIN 1 PROTECTION
B
MTR 1
TRIP COIL 1
TRIP/OPEN
CB
DIRECT TRIP
MAIN 2 PROTECTION
C
TRIP COIL 2
MTR 2
BACKUP PROTECTION
BREAKER FAILURE
INTERTRIP RECEIVE
BREAKER
FAILURE
S1
S2
87BBHI
TRIP
INTERTRIP SEND
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
SUBSTATION:
4
16
17
OPEN COMMAND
MAIN PROTECTION
B
NON AR FAULTS
TRIP COIL 1
MTR 1
TRIP/OPEN
CB
BACKUP PROTECTION
C
TRIP COIL 2
BREAKER FAILURE
INTERTRIP RECEIVE
(See Note 1 & 2)
START
OR
EXTERNAL
AR BLOCK
BLOCK
CLOSING
SIGNAL
AUTO
RECLOSE
AR LOCKOUT
BREAKER
FAILURE
(see Note 1)
S1
S2
87BBHI
TRIP
INTERTRIP SEND
(see Note)
Note:
1. Breaker Failure Scheme is only required when the bus
system is GIS type.
2. Intertrip Receive tripping facility must also be provided for
AIS type substation to complement the Breaker Failure
Scheme for the adjacent GIS type substation.
F
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
TITLE:
Trip Scheme for 132kV OHL feeder, with
optional GIS type bus
SUPPLIER:
5
TRIP_SCHEME_132kV_OHL
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
17
18
OPEN COMMAND
DIRECT TRIP
MAIN PROTECTION
B
TRIP COIL 1
MTR 1
TRIP/OPEN
CB
BACKUP PROTECTION
C
TRIP COIL 2
BREAKER FAILURE
INTERTRIP RECEIVE
(see Note 1 & 2)
D
BREAKER
FAILURE
(see Note 2)
S1
S2
BBP
TRIP
INTERTRIP SEND
(see Note)
Note:
1. Breaker Failure Scheme is only required when the bus system
is GIS type.
2. Intertrip Receive tripping facility must also be provided for AIS
type substation to complement the Breaker Failure Scheme for the
adjacent GIS type substation.
F
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
TRIP_SCHEME_132kV_UGC
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
18
19
OPEN COMMAND
AR SOR MODE
D.C CIRCUIT FAIL
(TRIP RELATED)
MAIN PROTECTION
&
OR
TRIP/OPEN
CB
TRIP COIL
&
&
CLOSING
SIGNAL
AUTORECLOSE
NOR MODE
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
SUBSTATION:
4
19
20
OPEN COMMAND
MAIN PROTECTION
TRIP COIL
TRIP/OPEN
CB
BACKUP PROTECTION
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
SUBSTATION:
4
20
21
OPEN COMMAND
A
MAIN 1 PROTECTION
(HV SIDE)
MTR 1
(HV SIDE)
TRIP COIL 1
(HV SIDE)
MTR 2
(HV SIDE)
TRIP COIL 2
TRIP/OPEN
CB (HV)
MAIN 2 PROTECTION
B
S1
S2
87BBHI
TRIP
BREAKER
FAILURE
HV side
BACKUP PROTECTION
OPEN COMMAND
BACKUP PROTECTION
(LV SIDE)
MTR 1
(LV SIDE)
TRIP COIL 1
TRIP/OPEN
CB (LV)
BREAKER
FAILURE
(LV SIDE)
MTR 2
(see Note 2)
S1
S2
Notes:
(LV SIDE)
TRIP COIL 2
87BBHI
TRIP
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
TRIP_SCHEME_AutoXFMR
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
21
22
OPEN COMMAND
A
MAIN PROTECTION
(HV SIDE)
TRIP COIL 1
(HV SIDE)
MTR
TRIP/OPEN
CB (HV)
BACKUP PROTECTION
S1
BREAKER
FAILURE
S2
HI-BBP
TRIP
From LV to HV Intertrip >>
INTERTRIP SEND
(see Note 1)
HV side
OPEN COMMAND
MAIN
PROTECTION
(HV SIDE)
TRIP COIL 2
(LV SIDE)
MTR
REF
(LV SIDE)
TRIP COIL 1
TRIP/OPEN
CB (LV)
BACKUP
PROTECTION
SBEF
S2
Notes:
1. Breaker Failure Scheme is required when
the bus system is GIS type.
OCEF
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
SUPPLIER:
5
TRIP_SCHEME_132kV_XFMR
SUBSTATION:
4
/
REV. THIS SH.:
1
NEXT SH.:
8
22
23
OPEN COMMAND
B
MAIN PROTECTION
(HV SIDE)
TRIP COIL
BACKUP PROTECTION
From LV to HV Intertrip >>
HV side
TRIP/OPEN
CB (HV)
(HV SIDE)
MTR
OPEN COMMAND
D
BACKUP
PROTECTION
(LV SIDE)
TRIP COIL
(LV SIDE)
MTR
SBEF
S2
TRIP/OPEN
CB (LV)
OCEF
Note:
Repeat the LV side, if the other sides of the
transformer have CB.
F
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
TRIP_SCHEME_33kV_XFMR
SUBSTATION:
4
23
24
OPEN COMMAND
B
BACKUP PROTECTION
MTR 1
TRIP COIL 1
TRIP/OPEN
CB
TRIP COIL 2
MTR 2
BREAKER
FAILURE
S1
S2
BBP
TRIP
Note:
During Live Bus Transfer, all tripping shall be blocked.
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
24
25
OPEN COMMAND
B
BACKUP PROTECTION
MTR
TRIP COIL 1
TRIP/OPEN
CB
TRIP COIL 2
BREAKER
FAILURE
S1
S2
BBP
TRIP
Notes:
During Live Bus Transfer, all tripping shall be
blocked.
F
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
25
26
OPEN COMMAND
TRIP/OPEN
CB
TRIP COIL
BACKUP PROTECTION
25/10/2003
UMAR / RIZAL
OWNER:
RAZAK
CONTRACT NO.:
ILHAM
TENDER NO.:
DATE
NAME
1
2
3
Package = Visio; Page Size = A4,L; Unit = Inches; Scale = 1in.=1in.; 1 box = 1.25" x 1.25";
REV
CONTRACTOR:
TENAGA NASIONAL
BERHAD
26
-
APPENDIX B
Appendix B
RELAYING DESCRIPTION
Master Element Control Switch
Time Delay Starting or Closing Relay
Distance (Impedance) Protection
Phase Distance Protection
Earth Distance Protection
Distance Protection Relay
Distance Protection Relay First Main
Distance Protection Relay Second Main
Distance Protection Relay Bus Separation
Distance Protection Relay Bus Separation for Main Busbar
Distance Protection Relay Bus Separation for Reserve Busbar
Temperature Control Device, e.g. Thermostat
Overexcitation Protection Relay
Overexcitation with Overvoltage Protection Relay
Synchronising Relay or Synchronism Check Relay
Synchronising Relay for Busbar Voltage
Synchronising Relay for Feeder Voltage
Point-on-wave Synchronous Switching Relay
Synchronising Relay
Apparatus Thermal Device
Oil Temperature
Oil Temperature Alarm
Oil Temperature Trip
Winding Temperature
Winding Temperature Alarm
Winding Temperature Trip
Voltage Operated Relay
D.C Voltage Supply Failure
D.C Voltage Supply Supervision
Pilot Wire Supervision
Trip Circuit Supervision
Undervoltage Relay
V.T Reference Failure
Voltage Selection Relay
V.T Supply Failure
V.T Supply Supervision
Interlocking Relay
Annunciator Relay
Directional Power Relay
Minimum Power Relay
Low Forward Power Relay
Reverse Power Relay
Position Switch
Transformer Out-of-Step
Master Sequence Device, Computer Device
Undercurrent Relay or Underpower Relay
Minimum Power Relay
Master Contactor
Field Relay
Page 1 of 5
Appendix B
CODE
40FF
40LOE
43
46
46S
46D
47
47S
48
48TIC
49
49R
49S
49OL
50
50BF
50BFT
50BFT1
50BFT2
50EF or 50N
50OC
50OCR
50OCY
50OCBL
50OCA
50OCB
50OCC
50+51
51
51AUX
51COB
51EF or 51N
51OC
51OCR
51OCY
51OCBL
51OCA
51OCB
51OCC
51OC/TV
51TD
51V
52
52PD
55
59
59N
59OV
60
61
62
63
63B
RELAYING DESCRIPTION
Field Failure Relay
Loss of Excitation
Selector Switch, e.g. AR Selector Switch
Negative Phase Sequence Overcurrent Relay
Instantaneous Negative Phase Sequence Overcurrent Relay
IDMT Negative Phase Sequence Overcurrent Relay
Negative Phase Sequence Voltage Relay
Instantaneous Negative Phase Sequence Voltage Relay
Incomplete Sequence Relay
Transformer Tap Change Incomplete
Machine or Transformer Thermal Relay
Rotor Overload Relay
Stator Overload Relay
Thermal Overload Relay
Instantaneous Overcurrent or Rate of Rise
C.B. Failure Protection
C.B. Failure Protection, which may consist of Stage 1 and Stage 2
C.B. Failure Protection Timer 1
C.B. Failure Protection Timer 2
Instantaneous Earth Fault
Instantaneous Overcurrent
Instantaneous Overcurrent Red Phase
Instantaneous Overcurrent Yellow Phase
Instantaneous Overcurrent Blue Phase
Instantaneous Overcurrent A Phase
Instantaneous Overcurrent B Phase
Instantaneous Overcurrent C Phase
Instantaneous and Time Delayed Overcurrent Relay
Time Overcurrent Relay
Auxiliary Relay for 51 Relay
Capacitor Out-of-Balance
IDMT Earth Fault
IDMT Overcurrent
IDMT Overcurrent Red Phase
IDMT Overcurrent Yellow Phase
IDMT Overcurrent Blue Phase
IDMT Overcurrent A Phase
IDMT Overcurrent B Phase
IDMT Overcurrent C Phase
IDMT Overcurrent for Tertiary Winding
Definite Time Delay Overcurrent Relay
Voltage Dependent Overcurrent Relay
A.C Circuit Breaker
Circuit Breaker Pole Discrepancy Relay
Power Factor Relay
Voltage Relay
Neutral Displacement Relay
Overvoltage Relay
Voltage Balance Relay or Current Balance Relay
Density Device
Opening Relay or Time Stopping Relay
Liquid Pressure Relay or Gas Pressure Relay or Vacuum Relay
Buccholz Device
Page 2 of 5
Appendix B
CODE
63BA
63BT
63GPL1
63GPL2
63OPL
63PRD
63TCBT
64
64BAT
64REF/HV
64REF/LV
64ROT
64SBEF
64SBEF1
64SBEF2
64STA
67
67DEFC
67EF
67OC
67OCR
67OCY
67OCBL
67OCA
67OCB
67OCC
68
68PSB
70
71
71OLL
72
74
74AUX
77
78
78OOS
79
79AR
79E
80
81
81UF
81OF
83
84
85
85DEFCR
85DEFCS
85INTR
85INTS
85ZCR
85ZCS
RELAYING DESCRIPTION
Buccholz Alarm
Buccholz Trip
Gas (SF6) Pressure Low Stage 1
Gas (SF6) Pressure Low Stage 2
Oil Pressure Low
Pressure Relief Device
Tap Changer Buccholz Trip
Earth Fault Protective Relay
Battery Earth Fault
Restricted Earth Fault HV side
Restricted Earth Fault LV side
Rotor Earth Fault
Standby Earth Fault
Standby Earth Fault Stage 1
Standby Earth Fault Stage 2
Stator Earth Fault
A.C Directional Current Relay
Directional Earth Fault Comparison Protection
IDMT Directional Earth Fault
IDMT Directional Overcurrent
IDMT Directional Overcurrent Red Phase
IDMT Directional Overcurrent Yellow Phase
IDMT Directional Overcurrent Blue Phase
IDMT Directional Overcurrent A Phase
IDMT Directional Overcurrent B Phase
IDMT Directional Overcurrent C Phase
Blocking Relay
Power Swing Blocking Relay
Rheostat
Liquid or Gas Level Relay
Low Oil Level
D.C Circuit Breaker
Alarm Relay
Auxiliary Alarm Relay
Telemetering Device
Phase Angle Measuring or Out-of-Step Relay
Out-of Step Protection Relay
A.C. Reclosing Relay
Automatic Reclosing Relay or Autoreclose Relay
Autoreclose Lock-out Relay
Liquid Flow Relay or Gas Flow Relay
Frequency Relay
Underfrequency Relay
Overfrequency Relay
Automatic Selective Control or Transfer Relay
Operating Mechanism
Carrier Transceiver Relay or Pilot Wire Transceiver Relay
DEF Comparison Protection - Carrier Receive
DEF Comparison Protection - Carrier Send
Direct Intertrip Receive
Direct Intertrip Send
Distance Protection - Carrier Receive
Distance Protection - Carrier Send
Page 3 of 5
Appendix B
CODE
86
86AUX
86A
86B
86C
86R
86Y
86BL
86BB
86T
86E
86E1
86E2
86EBB
87
87BBLO
87BBHI
87CBB
87CBB/1
87CBB/2
87CC
87CD
87CD/1
87CD/2
87G
87G/1
87G/2
87L
87MBB
87M1BB
87M2BB
87M3BB
87MBB/1
87MBB/2
87OD
87PWR
87RBB
87R1BB
87R2BB
87RBB/1
87RBB/2
87R
87S
87T
87T/1
87T/2
87TBD
87THI
87UT
88
90
90AVR
94
94BB
RELAYING DESCRIPTION
Tripping Relay
Auxiliary Tripping Relay
Tripping Relay A Phase
Tripping Relay B Phase
Tripping Relay C Phase
Tripping Relay Red Phase
Tripping Relay Yellow Phase
Tripping Relay Blue Phase
Busbar Tripping Relay
Three Phase Tripping Relay
Lock-out Tripping Relay or Master Tripping Relay
Lock-out Tripping Relay 1
Lock-out Tripping Relay 2
Busbar Lock-out Tripping Relay
Differential Protection Relay
Busbar Protection Low Impedance
Busbar Protection High Impedance
Busbar Check Zone
Busbar Check Zone Relay First Main
Busbar Check Zone Relay Second Main
Current Comparison Protection Relay
Current Differential Protection Relay
Current Differential Protection Relay First Main
Current Differential Protection Relay Second Main
Generator Differential Protection Relay
Generator Differential Protection Relay First Main
Generator Differential Protection Relay Second Main
Line or Cable Differential Protection
Busbar Protection Main Busbar
Busbar Protection Main Busbar 1
Busbar Protection Main Busbar 2
Busbar Protection Main Busbar 3
Busbar Protection First Main Main Busbar
Busbar Protection Second Main Main Busbar
Overall Differential Protection Relay
Pilot Wire Differential Relay
Busbar Protection Reserve Busbar
Busbar Protection Reserve Busbar 1
Busbar Protection Reserve Busbar 2
Busbar Protection First Main Reserve Busbar
Busbar Protection Second Main Reserve Busbar
Reactor Differential Protection
Stub Protection Differential Relay
Transformer Differential Protection
Transformer Differential Protection First Main
Transformer Differential Protection Second Main
Transformer Biased Differential Protection
Transformer High Impedance Differential Protection
Unit Transformer Differential Protection
Auxiliary Motor
Regulating Device
Automatic Voltage Regulator Relay
Tripping or Trip-free Relay
Busbar Tripping Relay
Page 4 of 5
Appendix B
CODE
96
96BBF
96BBS
96TCS
96DCF
96DCS
96VRF
96VTF
96VTS
RELAYING DESCRIPTION
Supervision Relay
Busbar Protection Failure (Defective) Device
Busbar Protection Supervision Relay
Trip Circuit Supervision
D.C Voltage Supply Failure Device
D.C Voltage Supply Supervision Device
V.T Reference Failure Device
V.T Supply Failure Device
V.T Supply Supervision Device
References:
1. TNB Relay Code
2. ANSI
3. IEEE C37.2
Page 5 of 5
APPENDIX C
Appendix C
Closing Coil
D.C
Discriminating Zone
DR
DTPAR
Evolving Fault
FR
FSPAR
GIS
Inrush Current
Lockout
MTBF
Multi-shot Reclosing
NiCd
NLDC
Permanent Fault
PUTT
POTT
RCC
SBEF
Self-supervision
SIMS
Single-phase Fault
Definition
Alternating current
Air Insulated Switchgear
Some refers as autoreclose, is the automatic reclosing of CB associated with faulted
section of network after an interval of time which permits that section to recover
from transient fault [IEC 50(604)-1987]
The time during autoreclose when the power line(s) or phase(s) is(are) not
connected to any network voltage. Note: For radial fed power lines, the dead time
is equal to the autoreclose open time. [IEC 50(448)-1995]
The time after an autoreclosure, before the autoreclose equipment will initiate
another reclosures in the event of another power system fault. [IEC 50(448)-1995]
Circuit Breaker
Current Comparison
Current Differential
The non-selective part of a multi-zone High Impedance Busbar protection, generally
supervising current flow at the terminals of the complete substation. Note: Tripping
from the Busbar protection is conditional on operation of both the check zone and
discriminating zone. [IEC 50(448)-1995]
Coil used in the electromagnet that supplies power for the closing the device, usually
CB. Note: In an air or other stored-energy-operated device, the closing coil may be
the coil used to release the air or stored energy which in turn closes the device.
[IEEE C37.100-1981]
Direct current
The selective part of a multi-zone High Impedance Busbar protection, generally
supervising current flow into and out of a single section of busbar, see also Check
Zone. [IEC 50(448)-1995]
Disturbance Recorder
Delay Three Pole Autoreclose, is defined as delayed reclosing shall only be initiated
in the event of a single-phase fault or two-phase fault. Three-phase fault shall
initiate lockout condition.
Evolving fault terminology must include the operation of autoreclose cycle, where it
is classified as fault that occurs after the clearance of the first-detected fault and
during the dead time of the first-detected fault.
Fault Recorder
Fast Single Pole Autoreclose, is defined as single-pole, high speed reclosing shall be
initiated only in the event of a single-phase fault, and delay reclosing in the event of
two-phase fault. Three-phase fault shall initiate lockout condition.
Gas Insulated Switchgear
The current which results when a switching device is closed to energise an inductive
or capacitance circuit .
The disconnection of faulty equipment or part of the network after a pre-determined
number of reclosures and conditions. Sometimes the number of reclosures can also
be zero. Sometimes refer as final tripping [IEC 60(604)-1987]
Mean Time Between Failure, which is calculated using CIGRE WG34.10 method.
An autoreclosing repeated more than two times if it is unsuccessful.
Nickel Cadmium
National Load Despatch Center for TNB
A fault which affects a device and prevents its restoration into service until action
has been taken at the point of the fault. [IEC 50(604)-1987]
Permissive Underreach Transfer Trip
Permissive Overreach Transfer Trip
Regional Control Center for TNB
Standby Earth Fault. For TNB system, it is usually an Earth Fault relay using Definite
Time characteristic.
Some refers as self-checking, where self-testing by microprocessor-based relays that
checks operation of the processor software. [IEEE C37.113-1999]
Substation Interrogation and Monitoring System
Sometimes refer as single-phase-to-ground fault.
Page 1 of 2
Appendix C
Term/Abbreviation
SOTF
Three-phase fault
TTWC
Two-phase fault
Definition
Switch On To Fault, usually occurs during closing of CB for when fault happens at
the same period of time.
Three-phase fault includes phase-to-phase-t o-phase fault and phase-to-phase-t ophase-to-ground fault. In TNB system, if autoreclose is employed, it shall initiate
lockout condition.
The resistance between the tower grounding system and true ground.
TTC is chaired by the Vice President of Transmission Division of TNB. TTC is the
highest divisional committee to accept or to approve any changes to the philosophy,
policy and requirement. TTC is the body that acknowledge the acceptance of relay
model, SCS equipment and protection/control anciliary equipment to be used in TNB
secondary systems.
Transmission Technical Working Committee.
Two-phase fault includes phase-t o-phase fault and phase-to-phase-t o-ground fault
Page 2 of 2