RP 50-1
May 1993
Document Title
APPLICABILITY
Regional Applicability:
International
AMENDMENTS
Amd
Date
Page(s)
Description
___________________________________________________________________
CONTENTS
Section
Page
FOREWORD ................................................................................................................ ii
1. INTRODUCTION................................................................................................... 1
2. OBJECTIVES ......................................................................................................... 2
3. METHOD AND PROCEDURES ........................................................................... 3
3.1 Criticality Definitions ........................................................................................... 4
3.2 Criticality - General Principles.............................................................................. 4
3.3 Criticality Rating Procedure................................................................................. 5
3.3.1 Use of the Procedure..................................................................... 5
3.3.2 Evaluation of Failure Consequence................................................ 6
3.3.3 Assessing the Costs....................................................................... 7
4. ANALYSIS .............................................................................................................. 7
4.1 Categorisation ..................................................................................................... 7
4.2 Individual Rating Methods................................................................................... 8
5. CRITICALITY........................................................................................................ 8
5.1 Equipment ........................................................................................................... 8
5.2 Process Systems .................................................................................................. 9
5.3 Operations........................................................................................................... 9
FIGURE 1 ................................................................................................................... 10
OVERVIEW OF CRITICALITY ANALYSIS SYSTEM ........................................ 10
FIGURE 2 ................................................................................................................... 11
GENERAL CRITICALITY ASSESSMENT WORKSHEET .................................. 11
FIGURE 3 ................................................................................................................... 12
SUB-SYSTEM CRITICALITY RATING METHOD ............................................. 12
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE i
FOREWORD
Introduction to BP Group Recommended Practices and Specifications for Engineering
The Introductory Volume contains a series of documents that provide an introduction to the
BP Group Recommended Practices and Specifications for Engineering (RPSEs). In
particular, the General Foreword sets out the philosophy of the RPSEs. Other documents in
the Introductory volume provide general guidance on using the RPSEs and background
information to Engineering Standards in BP. There are also recommendations for specific
definitions and requirements.
Value of this Recommended Practice
This Recommended Practice has been prepared to offer a basic philosophy for the consistent
application of Criticality Rating, throughout the life of an asset. Its intent is to ensure that a
methodical approach to establishing priorities is adopted for all Engineering activity. This will
assist the appropriate allocation of scarce resources, whilst ensuring that equipment integrity,
Company revenue and operational safety are not compromised.
Application
Text in italics is commentary. Commentary provides background information which supports
the approach proposed in the Recommended Practice, and may offer alternative sources of
information.
The responsibility to ensure compliance with legislation and other statutory requirements, lies
with the user. The user should adapt or supplement this document to ensure compliance in
specific applications.
Changes from Previous Edition
BP CP 53 was developed as a guide to the application of the ISO 9000 series of International
Quality System standards. The Yellow Page Supplement included a guide to application of
criticality ratings. The use of the ISO 9000 series of standards is now mature, therefore the
BP guide to ISO 9000 is withdrawn, and this new document is an update of the former
Yellow Page Supplement.
Feedback and Further Information
Users are encouraged to feed back any comments or experiences in the application of RPSEs,
to assist in the process of continuous improvement.
For feedback and further information, please contact Standards Group, BP International or
the Custodian. See Quarterly Status Lists for contacts.
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE ii
1.
INTRODUCTION
"The Core of Management is the Art of Mobilising and putting together the
Intellectual Resources of All Employees, in the Service of the Firm."
K. Matsushita - 1979
The quotation above encapsulates the intention of this document; not to define any
prescribed methodology, but to encourage the adoption of a consistent methodical
approach to setting engineering priorities, by increased networking across disciplines
throughout asset life. Engineering, in this context, is the design, procurement,
fabrication, installation, commissioning, operation and maintenance of an asset and the
management of these functions.
There are individual Criticality Rating models listed in Section 5 of this Recommended Practice.
Its scope encompasses project and operations management, process systems and
equipment.
In order that the document is appropriate for all phases of BP Group engineering activities, the
principles contained within it must be part of a general philosophy relevant to an asset's life cycle.
The philosophy assists the identification, management and control of risk. This applies
to Health, Safety and the Environment, to the Group's investment and production
returns, and in all engineering areas of the Group's activities.
It is particularly valid in the context of the strategic shift which now allocates increased
accountability to external suppliers undertaking traditional BP roles.
A considerable amount of valuable work has been undertaken within the BP Group to
provide Criticality Rating guidelines for specific disciplines and phases in an asset's
operational life cycle.
The generic principles described in this document are drawn from these guidelines.
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 1
Criticality Rating will not provide a direct solution to any engineering problems in any
phase of project or operational life. It is intended to supply quantitative input to the
engineering decision making process.
The rating process is dynamic. The results obtained at each stage of the asset life cycle may feed
into the next stage. Changes in operational requirements may alter the inputs to the rating process,
as may the results of inspection activity. Criticality Rating should be an iterative exercise, and may
be revisited regularly throughout asset life. Modifications and refinements can be undertaken at
each stage of the asset life cycle, as a result of feedback from other stages.
This document does not attempt to replace or simplify available existing techniques
which are considered appropriate by specific businesses.
The primary purpose of the document is to consolidate the work in existing guidelines
and build them into a readily understood and uniform conceptual approach to the
assessment and analysis of Criticality.
For some years criticality rating models have been available which enable procurement Quality
Assurance activities to reflect the importance of equipment in terms of the risks associated with
failure. In recent years models have also been developed which enable similar focusing of
engineering activities, in particular for pressure systems, inspection planning, piping system
engineering and latterly for maintenance planning.
It has recently been recognised that the concept of criticality rating has a wide range of application
throughout the life cycle of an asset and for specific items of equipment. An important tool in
planning and management of engineering activity and expenditure, criticality rating enables
assessment of relative risk.
With this in mind it was concluded that a generic document describing the principles of criticality
rating was needed, to which existing detailed procedures could be linked, and which would provide
the basis for development of any other required procedures.
It is important that users should develop their own procedures for specific applications, so as to
achieve full understanding of the concepts involved.
The power of criticality rating models lies not so much in the ability to generate a comforting set of
numbers, rather in the focus that is brought to key areas of management, design and items of process
systems and equipment with the possibilities for teams to achieve consistent, ongoing understanding
of what is important, and what is not.
2.
OBJECTIVES
The essential requirements of a Criticality Rating procedure are that it must be:(i)
(ii)
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 2
(iii)
(iv)
Adaptable to computerisation.
(v)
Able to incorporate the experience available from the BP Group and allow
transfer of information within it.
(vi)
The focus for the approach to engineering practice for the whole life of an
operation.
The principles in this document are structured to apply to the following definition of
an operational life cycle:
(1)
CONCEPT
Every engineering proposal can be assessed in terms of the criticality of the
processes involved and the equipment required for them.
(2)
DEVELOPMENT
Sub systems within the proposal can be assessed in terms of their process and
management applications. This will encompass the long term health, safety and
environmental effects and the investment considerations for the proposal.
(3)
PROCUREMENT
Equipment included within a project or modification can be assessed for its
specific criticality and the optimum quality standards determined.
(4)
CONSTRUCTION
Areas and systems can be assessed for their risk impact on completion,
investment and future operation.
(5)
OPERATION
The assessment of all systems, sub-systems, equipment and spares may be
required. This should encompass modification, inspection and integrity,
maintenance and operating activities. It should also consider the optimisation
and/or minimisation of these activities, and the economic impact of equipment
replacement.
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 3
3.
3.1
Criticality Definitions
Criticality Rating as described in Section 1 relates to systems, subsystems, or the components within those systems.
The evaluation process may be used to select the appropriate design,
procurement, construction, commissioning and operational strategy for
all engineering systems and related items of equipment.
This process may have a different objective for different stages of the
asset life cycle.
For example, the inputs to (and hence outputs of) criticality rating during the
procurement stage will differ from those during the operating stage.
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 4
3.3.1
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 5
(c)
3.3.2
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 6
E - Economic
Failure of the sub-system or equipment item will have an impact on
revenue or investment return.
The rate at which this impact may become significant should also be
considered.
It may help to consider where the failure will result in immediate economic loss,
where a loss will occur after a delay, as may be expected with a storage vessel, and
where the economic loss is hidden, or dependent on a knock-on effect. The last
case would be relevant where stand-by units are available The economic impact
will not become apparent until failure of the stand-by occurs.
N - None
Failure results in none of the consequences defined above.
3.3.3
4.
ANALYSIS
The systematic approach to criticality analysis may be assisted by the use of an
appropriate computer package, adapted for the specific application. This could take
the form of a proprietary spreadsheet or database program.
4.1
Categorisation
The sub-systems or equipment items should now be sorted according to
Consequence of Failure classification.
The Safety categories may be sorted by engineering activity cost.
Sorting by the cost of the engineering activity allows a further analysis to be made
of systems and equipment which consume the greatest amount of resources. A
diesel fire water pump whose failure consequence is unequivocally safety related
appears as a critical item on the second sort because of its typical maintenance
costs.
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 7
5.
CRITICALITY
It is strongly recommended that although these models are useful as examples, maximum benefit will
be gained from use of the criticality concept if users think through their own requirements, bearing in
mind the principles outlined in this account, in order to develop a model and systems which cater for
their own needs.
The following models available from the BP businesses have been developed for use in
specific applications.
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 8
5.1
5.2
5.3
Equipment
1.
2.
BP Exploration Ltd., Kinneil Terminal Expansion Project "Criticality Ratings and Quality Programmes".
3.
BP
Exploration
Ltd.,
Pipelines
402/CPOM/Q/71615 "Criticality Ratings".
4.
5.
6.
Project
Group -
Process Systems
1.
2.
3.
Operations
1.
2.
3.
4.
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 9
Define Systems,
Sub-systems,
Equipment Item
Sub-system
Criticality Analysis
Component or Further
Sub-system Analysis
FIGURE 1
OVERVIEW OF CRITICALITY ANALYSIS SYSTEM
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE10
SYSTEM EQUIPMENT
DESCRIPTION
COMMENTS
MODE/EFFECT OF
FAILURE
CONSEQUENCE OF
FAILURE
ECONOMIC
IMPACT
ENGINEERING
COST
FIGURE 2
GENERAL CRITICALITY ASSESSMENT WORKSHEET
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 11
ANALYSE CONSEQUENCE OF
SUB-SYSTEM OR EQUIPMENT
FAILURE
CONSEQUENCE
CLASSIFICATION
SAFETY
ECONOMIC
NONE
HIDDEN
Evaluate Consequence of
Hidden Failure
FIGURE 3
SUB-SYSTEM CRITICALITY RATING METHOD
RP 50-1
GUIDE TO THE APPLICATION OF
CRITICALITY RATINGS
PAGE 12