Gbes Leedbdc Study Sheet
Gbes Leedbdc Study Sheet
Gbes Leedbdc Study Sheet
Sustainable Sites - SS
ID
SSp1
SSp2
SSc1
SSc2
SSc3
Credit
Site Selection
Pts
NC
Req
Schools
Req
CS
Req
NC
NA
Schools
Req
CS
NA
NC
Schools
CS
NC
Schools
CS
NC
Schools
CS
Brownfield Redevelopment
NC
SSc4.1
SSc4.2
Civil engineer or
landscape architect
Key Numbers
There are no
calculations for this
credit
Developers,
There are no
Environmental
calculations for this
Professionals and
credit
General Contractors
Landscape
architects,
ecologists,
environmental
engineers, and civil
engineers as well as
local professionals
Density - 60,000
SF/AC
Community
Connectivity - 1/2
mile radius
Developers should
contact
environmental
consultants, state
and local regulators
NA
NA
NA
NA
NA
Prevent sedimentation of
storm sewers or receiving
streams
If site is contaminated, it
must be remediated to
meet the most stringent
local, state, or federal EPA
standards
Previously undeveloped
land whose elevation is <5
feet above the elevation of
the 100-year flood as
defined by FEMA
Option 1 - Construct or
renovate building on a
PREVIOUSLY developed site
AND in a community with a
minimum density of 60,000
SF/AC
Option 2 - Construct or
renovate a building that is
located on a PREVIOUSLY
developed site
Same as NC
OPTION 3 Rideshare Proximity: Projects outside the U.S. may locate the project within 1/4-mile (400-meter) walking distance
of 1 or more stops for 2 or more existing rideshare options.
CS
NC
Schools
CS
Responsible
Party
Architect, design
team and client
Architect, Plumbing
Various standards,
Engineer, Civil
reference specific
Engineer and/or
credit information
Landscape Architect
Option 1 Comprehensive
Transportation MGT
Plan
Option 2 - Double
Transit Ridership
Implement a
Comprehensive
Transportation
Management Plan that
demonstrates a
reduction in personal
automobile use,
projects awarded an
exemplary performance
for SSc4.1 Option 2 are
not eligible
NA
NA
alternative compliance: Shuttle buses should provide direct access to transit facilities within 2 miles of the project site,
approximately a 5-10 minute drive, and must be available to all project occupants.
Provide secure racks and or storage within 200 yds of entrance for
55 or more of building staff and students above grade 3 (at peak
periods)
provide shower and changing facilities in building or within provide dedicated bike lanes that extend at least to the end of
the school property in 2 or more directions without any barriers
200 yds of entrance for 0.5% of FTE staff
NC
SSc4.3
CS
NC
SSc4.4
SSc5.1
SSc5.2
SSc6.1
Schools
CS
NC
Schools
CS
NC
Schools
NC
Schools
CS
Implement a
low-emitting vehicles are
Comprehensive
defined as vehicles that are
Transportation
classified as Zero Emission
Vehicles (ZEV) by the
Management Plan that
California Air Resources Board.
demonstrates a
Fuel-efficient vehicles are
reduction in personal
defined as vehicles that have
automobile use,
achieved a minimum green
projects awarded an
exemplary performance score of 40 on the American
for SSc4.1 Option 2 are Council for an Energy Efficient
Economy (ACEEE)
not eligible
Implement a
Comprehensive
Transportation
Management Plan that
demonstrates a
reduction in personal
automobile use,
projects awarded an
exemplary performance
for SSc4.1 Option 2 are
not eligible
Option 2 - Install
alternative fuel fueling
stations for 3% of total
vehicle parking capacity
Same as NC AND at least 1 designated carpool drop-off area for low- Develop and implement a plan for buses and maintenance
e and fuel-e vehicles
vehicles 20% alternative fuel
Same as NC
Case 1 (Non-Residential
Projects) Option 1: Size
Parking Capacity must meet
but not exceed min. local
zoning requirements
Option 1 - Size parking capacity must not exceed min. local zoning, Option 2 - Provide no new Option 3 - for projects that have no min. local zoning, provide
preferred parking for carpools etc. 5% of parking
25% fewer spaces
parking
Same as NC
Same as NC
Landscape Architect,
ecologist,
Various standards,
environmental
reference specific
engineer, civil
credit information
engineer, and local
professionals
Restoring or protecting
75% (excluding
building footprint) of
Land Trust Standards and
the site or 30%
Practices 2004
(including building
footprint) of the total
site
Case 2 - Previously Developed Areas or Graded Sites restore or protect a minimum of 50% of the site (excluding
Case 1 Greenfield Sites - limit all site disturbance to the following:
the building footprint) or 20% of the total site area
40 ft. beyond building perimeter and parking garages.
(including building footprint), whichever is greater with
10 ft. beyond surface walkways, patios, surface parking and utilities
native or adapted vegetation. projects earning SSc2 may
less than 12 inches in diameter, 15 ft. beyond primary roadway
include vegetated roof surface in this calculation IF the
curbs and main utility branch trenches
plants are native or adaptive, provide habitat and promote
biodiversity
Landscape
architects,
ecologists,
Various standards,
environmental
reference specific
engineers, and civil credit information
engineers as well as
local professionals
NA
Various standards,
Civil Engineer or
reference specific
Landscape Architect
credit information
No standard exemplary
point has been
established. However,
documenting a
comprehensive
approach to capture
and treat stormwater
may help achieve this
ID point
NA
Same as NC
All Cases - for projects earning SSc2, vegetated roof areas can
contribute to credit compliance, and pedestrian-oriented
hardscape areas can contribute as well, a minimum of 25%
open space must be vegetated for these projects. Wetlands or
naturally designed ponds may count as open space and the side
slope gradients average 1:4 (vertical: horizontal) or less and are
vegetated.
NC
SSc6.2
SSc7.1
SSc7.2
Schools
CS
NC
Schools
CS
NC
Schools
CS
NC
Schools
SSc8
No standard exemplary
point has been
treats the stormwater established. However,
Owner, landscape
runoff from 90% of documenting a
architect, and
the average annual comprehensive
engineers - civil and
approach to capture
rainfall, BMPs must
mechanical
remove 80% of TSS and treat stormwater
may help achieve this
ID point
Architect, landscape
architect, civil and
Various standards,
reference specific
mechanical
credit information
engineers, and an
ecologist
Landscape Architect,
Civil Engineer,
Lighting Designer,
Architect, Electrical
Engineer
NA
NA
NA
NA
OR Option 2 - place a
minimum of 50% of
parking spaces under
cover, any roof used to
shade or cover parking
must have an SRI of at
least 29, be a vegetated
roof or be covered by solar
panels
NA
Illuminating Engineering
Society of North America.
ANSI/ASHRAE/IESNA
Standard 90.1 2007.
NA
CS
NA
NC
NA
Schools
Project owner,
architect and design
team
CS
Architect, design
team and building
owner
NC
NA
NA
NA
Schools
CS
NA
NA
NA
NA
Project must achieve at least 4 out of the following 7 credits using the associate calculation methods, the 7 include: SSc1, SSc5.1, SSc5.2, SSc6.1, SSc6.2, SSc7.1, and SSc8
A site master plan for the school must be developed in collaboration with the school boarder other decision-making body. Projects where no future development is planned are not eligible for this
credit
NA
Publish an illustrated document that provides tenants with the following design and construction information: description of the sustainable design and construction features and project's
sustainability goals and objectives for tenant spaces
Information on LEED for Commercial Interiors and how core and shell building contributes to achieving these credits
Information that enables a tenant to coordinate space design and construction addressing the extensive list on page 143
Recommendations, including examples, for sustainable strategies, products, materials and services
SSc9
SSc10
Water Efficiency - WE
ID
Credit
Pts
NC
WEp1
WEc1
WEc2
WEc3
WEc4
Innovative Wastewater
Technologies
Key Numbers
Req
Schools
Req
CS
Req
NC
2-4
Schools
2-4
CS
2-4
NC
Schools
CS
NC
2-4
Responsible
Party
2-4
CS
2-4
NC
NA
Schools
CS
NA
Predesign - Owner,
Architect and
20% Reduction from
Engineers
baseline
Design Development
- Engineering Team
Landscape designer,
building owner,
Option 1 Reduce
architect, civil
Potable Water Use by
engineer and
50%
mechanical engineer
Owner, architect,
and engineering
team
Predesign - Owner,
Architect and
Engineers
Design Development
- Engineering Team
Reduce sewage
conveyance by 50%
or Treat 50% of
wastewater on-site
etc.
NA
NA
NA
Demonstrate a 100%
reduction in potable
water use for sewage
conveyance OR on-site
treatment of 100% of
generated wastewater
aggregate 30% (2
pts), 35% (3 pts), or Demonstrate a 45%
40% (4 pts) less
reduction in projected
water than the
potable water use
baseline
Calculating Occupancy account for Full-time staff, parttime staff, transients, and
residents
NA
NA
No refrigerant equipment
using once-through cooling
with potable water, no
garbage disposals, at least 4
process items were water use
is at or below levels on p.207
Credit
Pts
NC
EAp1
Fundamental Commissioning of
Building Energy Systems
Req
Schools
Req
CS
Req
Responsible
Party
Key Numbers
Owner,
Commissioning
Authority, and
Design Team
NA
NA
Owner
NC
EAp2
EAp3
Various standards,
reference specific
credit information
Fundamental Refrigerant
Management
Schools
Req
CS
Req
NC
Req
Schools
Req
CS
Req
NC
EAc1
EAc2
Req
1-19
Energy Modeler,
Architect, Mechanical
Engineer, LEED
Consultant, and
Commissioning
Authority
NA
NA
NA
Appendix G of
ANSI/ASHRAE/IESNA
Standard 90.1-2007
ASHRAE Advanced Energy
Design Guide
Advanced Buildings Core
Performance Guide by the
New Buildings Institute
Appendix G of
ANSI/ASHRAE/IESNA
Standard 90.1 2007
Advanced Buildings Core
ONLY Option 1 - Whole
Performance Guide
Building Simulation ASHRAE Advanced Energy
New Buildings 50%,
Design Guide for Small Retail
Existing Building Reno
Buildings 2006
46%
ASHRAE Advanced Energy
Option 2 & Option 3 Design Guide
There is no exemplary
Advanced Energy Design
performance
Guide for K-12 School
Buildings
ASHRAE Advanced Energy
Design Guide
Establish an energy
performance rating goal for
the facility using EPA's Target
Finder rating tool
1-19
CS
3-21
Same as NC
NC
1-7
Schools
1-7
CS
Project team,
Various standards,
Owner, Architecture, reference specific
and Engineer
credit information
NA
Commissioned Systems at a
minimum, include: HVAC&R and
associated controls, lighting and
daylighting controls, domestic
hot water systems, renewable
energy systems (wind and solar)
Option 3 - Prescriptive
Compliance Path - Advanced
Buildings Core Performance
Calculate baseline with
Guide - comply with the
Appendix G of
prescriptive measures in the
ANSI/ASHRAE/IESNA
guide developed by the New
Standard 90.1-2007 Buildings Institute
comply with mandatory
Building must meet the
provisions (5.4, 6.4, 7.4,
requirements: less than
8.4, 9.4 and 10.4, inclusion Option 2 - Comply with the
100,000 SF, comply with
Advanced Energy Design Guide
of all energy costs,
Section 1: Design Process
for k-12 school buildings, must
compare against a
Strategies, and Section 2: Core
be less than 200,000SF
baseline building that
Performance Requirements.
complies with Appendix G
Health care, warehouse and lab
projects are disqualified from
Same as NC
this path
Option 2 Prescriptive
Compliance Path - ASHRAE
Advanced Energy Design Guide
- comply with the prescriptive
measures in the guide
appropriate to the project
scope
Schools
Option 3 - Prescriptive
Compliance Path: Advanced
Buildings Core Performance
Guide (1-3 pts) - comply with
measures identified in the
Advanced Buildings Core
Performance Guide - for less
than 100,000 Sf, comply with
Section 1: Design Process
Strategies, Section 2: Core
Performance Requirements
Points Achieved: 1 pt for all
projects less than 100,000 SF
Up to 2 pts for performance
strategies in Section 3:
Enhanced Performance
Same as NC
1% = 4 pts
NC
EAc3
EAc4
EAc5
EAc5.1
EAc5.2
EAc6
Enhanced Commissioning
Enhanced Refrigerant
Management
Schools
NC
Schools
CS
NC
NA
Mechanical engineer
or HVAC&R
Specialist
Schools
CS
NC
Schools
NA
NA
NA
CS
NC
NA
Schools
NA
CS
NC
Schools
Green Power
CS
NA
Building Operators
Owner,
Commissioning
Authority, and
Design Team
NA
Building Operators
NA
NA
In addition to the
requirements outline in EAp1,
the CxA must conduct, at least
1 commissioning design
review of the basis of design
and design documents prior to
mid-construction documents,
and back check to confirm
NA
NA
NA
Option D: Calibrated
Simulation (Savings Estimation
Method 2) or Option B: Energy
Conservation Measure
Isolation IPMVP Volume III
NA
Option D: Calibrated
Simulation (Savings Estimation
Method 2) or Option B: Energy
Conservation Measure
Isolation IPMVP Volume III
Option D: Calibrated
Simulation (Savings Estimation
Method 2) or Option B: Energy
Conservation Measure
Isolation IPMVP Volume III
Building Operators
NA
NA
Project Team
2 year renewable
Purchase 100% of their
energy contract for at
electricity from
least 35% of the
renewable sources
building's electricity
Credit
MRp1
MRc1.1
MRc1.2
MRc2
MRc3
MRc4
MRc5
MRc6
MRc7
Pts
NC
Req
Schools
Req
CS
Req
NC
1-3
1-5
NC
Materials Reuse
Recycled Content
Regional Materials
Certified Wood
1-2
Responsible
Party
Local hauler, owner,
project team and
occupants
Key Numbers
NA
NA
NA
Various standards,
reference specific
credit information
CS if maintaining 95%
or more of the existing
walls, floors and roof
NA
NC
1-2
Schools
1-2
CS
1-2
NC
1-2
Schools
1-2
CS
NC
1-2
Schools
1-2
CS
1-2
NC
1-2
Schools
1-2
CS
1-2
NC
Schools
CS
NA
NC
Schools
CS - MRc6
NA
NA
NA
NA
Architect and
General Contractor
The minimum
Meet the 30%
percentage threshold
threshold for regional
10% = 1 pt, 20% =
materials
2 pts
NA
Architect and
General Contractor
2.5% rapidly
renewable
NA
Percent of Rapidly
Renewable = [Total Cost
of RRM ($) / Total
Materials Cost ($)] * 100
Architect or design
team, contractor
NA
1
NA
CS
Project team,
General Contractor
Owner, Architect or
Design Team, and
Contractor
NC and Schools 5%
= 1 pt, 10% = 2pts
CS 5% = 1 pt
General Contractor,
subcontractor and
suppliers
10% = 1 pt
20% = 2 pts
Calculations - by weight or
Minimum thresholds - 50% = 1
volume (must be
pt, 75% = 2 pts
consistent)
Credit
Pts
NC
Schools
EQp1
EQp2
EQp3
EQc1
NC
Req
Req
Architect, Mechanical
Engineer and project
team - owner,
tenants, facility
manager and
maintenance
personnel as
applicable
Key Numbers
NA
Facility Manager,
Prohibit smoking
Property Manager or
within 25 ft. of entry
Owner
NA
NA
Req
Same as NC
CS
NC
Req
NA
Same as NC
Schools
Req
CS
NA
NC
Schools
CS
Schools
NA
Various standards,
Mechanical Engineer
reference specific
and design team
credit information
increase ventilation
rates 30% above the
min.
Building Owners and
Intake accuracy +/Designers
15% OR
monitors 3-6 feet off
the ground
Case 2 - Naturally
Ventilated Spaces - must
comply with ASHRAE
Standard 62.1 2007,
Paragraph 5.1
Same as NC
NA
Design classrooms and other core learning spaces to include soundANSI Standard S12.60-2002,
absorptive finishes complying with ANSI Standard S12.60-2002,
Acoustical Performance
Acoustical Performance Criteria, Design Requirements and
Criteria, Design Requirements
Guidelines for Schools
and Guidelines for Schools
Achieve a maximum background noise level of 45 dBA
NA
Increased Ventilation
CS
Mechanical
Engineers, Electrical
Engineers and
Contractors
Schools
NC
EQc2
Req
Req
Responsible
Party
NA
ASHRAE 62.1-2007
NC
EQc3.1
Schools
CS
Subcontractors and
field personnel
EQc3.2
EQc4.1
EQc4.2
EQc4.4
Schools
CS
NA
NC
Schools
CS
NC
Schools
CS
LEED AP
NA
All adhesives and sealants must meet the California Department of Health Services Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small Scale
Environmental Chambers, including 2004 Addenda
Same as NC
Paints and coatings must comply with the following: architectural paints must not exceed VOC Green Seal Standard GS-11, Paints, 1st Edition limits
Anti-corrosive and anti-rust paints applied to interior ferrous metal substrates must not exceed the VOC limit of 250g/L in Green Seal Standard GC-03, Anti-Corrosive Pains, 2nd Edition
Green Seal GS-11, Green Seal Clear wood finishes, etc must not exceed the VOC limit in SCAQMD Rule 1113, Architectural Coatings
Standard GC-03, SCAQMD
All paints and coatings must meet the California Department of Health Services Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small Scale
Rule 1113, CA Standard
Environmental Chambers, including 2004 Addenda
Practice for Testing Volatile
Require/enforce tenants Organic Emissions
Same as NC
to meet IEQc4 (c4.1c4.4) throughout space
NA
LEED AP
NA
NA
LEED AP
NA
Schools
CS
Require/enforce tenants
to meet IEQc4 (c4.1c4.4) throughout space
NC
NA
Schools
CS
All adhesives and sealants must comply with the Scam Rule 1168 for VOC limits outline in the table on p.471 and aerosol adhesives must comply with Green Seal Standard for Commercial
Adhesives GS-36, table on p. 472
NA
NA
NC
EQc4.3
NA
Various standards,
reference specific
credit information
1
Contractor and
Subcontractors
NC
NA
LEED AP
NA
Option 1 - All carpet must comply with one of the following: 1) Carpet and Rug Institute Green Label Plus, 2) Max VOC
concentrations < CA Dept of Health Services Standard Practice for the Testing of Volatile Organic Emissions from Various
Sources Using Small-Scale Environmental Chambers AND meet VOC limits in Section 9.1a, 3) Maximum VOC meet CA CDPH
Standard Method V1.1-2010 or for non-US projects German AgBB/DIBt method. Carpet cushion to meet Carpet and Rug
Institute Green Label, carpet adhesive to meet IEQc4.1, hard surface flooring certified as FloorScore, (alternative path to
FloorScore - 100% of non-carpet must be FloorScore-certified and constitute > 25% of the finished floor area). Concrete, wood,
bamboo and cork must meet SCAQMD Rule 1113, Architectural Coatings, effective January 1, 2004. Tile adhesives and grout
must meet the SCAQMD Rule 1168. For carpet adhesive, concrete, wood, bamboo, and cork floor, and tile setting adhesives,
compliance can be demonstrated with test results.
Same as NC
Laminating adhesives used to fabricate on-site and shopComposite wood and agrifiber products used on the interior of the
Fixtures, furniture and
applied composite wood and agrifiber assemblies must not
Schools - California
building must contain no added urea-formaldehyde resins
equipment are not included
contain
added
urea-formaldehyde
resins
Department of Health Services
Standard Practice for the
Testing of Volatile Organic
All composite wood and agrifiber products must meet the California Department of Health Services Standard Practice for the Testing of Volatile Organic Emissions
Emissions from Various
from Various Sources Using Small Scale Environmental Chambers, including 2004 Addenda
Sources Using Small Scale
Environmental Chambers,
Require/enforce tenants including 2004 Addenda
Same as NC
Same as NC
to meet IEQc4 (c4.1c4.4) throughout space
NC
EQc4.5
EQc4.6
EQc5
Schools
CS
NA
NC
NA
Schools
CS
NA
NC
Schools
CS
NC
EQc6.1
EQc6.2
EQc7.1
EQc7.2
NA
NA
Various standards,
Design Team,
Architect, Mechanical reference specific
Engineer
credit information
CS
NA
NC
Schools
CS
NC
Schools
Building designers,
owner, property
management and
engineers
LEED AP
NA
NA
GREENGUARD
ANSI/BIFMA M7.1-2007 and
ANSI/BIFMA X7.1-2007
NA
California Department of
Health Services Standard
Practice for the Testing of
Volatile Organic Emissions
from Various Sources Using
Small-Scale Environmental
Chambers, including the 2004
Addenda
All gypsum board, insulation, acoustical ceiling systems and wall coverings installed in the
building interior must meet the requirements of the California Department of Health Services
Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using
Small-Scale Environmental Chambers, including the 2004 Addenda
NA
Employ permanent entryway systems at least 10 feet long in the primary direction of travel, grates, grills and slotted systems are acceptable, roll-out mats are
acceptable if maintained on a weekly basis (CS projects without entryway systems are not eligible for this credit)
Design to minimize and
Sufficiently exhaust each space where hazardous gases or chemicals may be present or used to create negative pressure when doors are closed. also provide selfcontrol the entry of pollutants closing doors and deck-to-deck partitions or hard lid ceilings
into the building with the
the exhaust rate must be at least 0.50 cfm per/sf with no recirculation, differential at least 5 PA on aver. and 1 Pa when doors are closed
following strategies:
For mechanically ventilated buildings, new filtration to meet: MERV13 or higher per ASHRAE 52.2, Class F7 or higher perCEN Standard EN 779: 202, or minimum
dust spot efficiency of 80% or higher and greater than 98% arrestance on particle size 3-10 micrograms.
Provide containment for appropriate disposal of hazardous liquid wastes in places where water and chemical concentrate are mixed
NA
Provide individual lighting controls for 90% min. of the building occupants to enable
adjustments to suit individual task needs and preference
Provide lighting system controls for all shared multi-occupant spaces to enable adjustments that
meet group needs and preferences
LEED AP
CS
NC
Schools
CS
NA
NA
NA
NA
NA
Provide individual comfort controls for 50% min. of the building occupants to enable adjustments to meet individual needs and
ASHRAE 62.1-2007 Paragraph preferences
5.1
Operable windows may be used in lieu for occupants within 20 ft. inside and 10 ft. to either side of the operable window - Meet Additional Requirements - projects that do not purchase and/or
Standards in IEQc7.1
the requirements of ASHRAE Standard 62.1-2007 Paragraph 5.1 Natural ventilation. thermal Comfort are described in IEQc7.1: install the mechanical system or operable windows or a
Thermal Comfort and include the primary factors of air temperature, radiant temperature, air speed and humidity
combination of both have not met the intent of this credit
NA
Standards in IEQc7.1
Achieve IEQc7.1 - conduct a thermal comfort survey of building occupants within 6 to 18 months after occupancy
Collect anonymous responses about thermal comfort, conduct an assessment identifying problem and agree to corrective action if more than 20% of occupants are dissatisfied, include
measurements in accordance with standard used for design in IEQc7.1
Building Operations
6 to 18 mo. And 20%
Team, Owner Agent
NA
dissatisfaction rate
or CxA
10
NC
EQ 8.1
EQ 8.2
EQC9
EQC10
Schools
1-3
CS
NC
Schools
1
1-3
CS
NC
NA
Mold Preservation
CS
NA
NC
NA
Schools
CS
NA
Various standards,
Owner, Architect and
reference specific
Engineers
credit information
NC & CS 95%
daylighting
Schools achieve 90% NA
classrooms and 95% other regularly
occupied spaces
Same as NC
NA
Achieve a direct line of sight to the outdoor environment via vision glazing 30-90 in. above the
finish floor, meeting the following criteria: in plan view, the area is within sight lines drawn from
perimeter vision glazing and in section view, a direct sight line can be drawn from the area to
perimeter vision glazing.
Sound Transmission - Design classrooms and other core learning spaces to meet the Sound
Transmission Class (STC) requirements of ANSI Standard S12.60-2002, Acoustical Performance AND Background Noise - Reduce background noise level to 40 dBA or less from HVAC systems in
Criteria, Design Requirements and Guidelines for Schools, the STC rating must be at least 35.
classrooms and other core learning areas
Non-US projects may use ANSI Standard S12/60-2002 local equivalent
cont. the line of sight may be drawn through interior glazing, for
private offices the SF may be counted if 75% or more of the
Core and Shell must incorporate
area has a direct line of sight to perimeter vision glazing, for
a tenant layout per occupancy
classrooms, the actual SF is counted
counts
IDc1.1
IDc1.2
IDc1.3
IDc1.4
IDc1.5
IDc2
IDc3
Credit
Pts
NC
1-5
Schools
1-4
CS
1-5
NC
Schools
CS
NC
1
NA
Schools
CS
NA
Responsible
Party
Key Numbers
NA
NA
NA
NA
NA
NA
NA
NA
Teachers
NA
NA
NA
Responsible
Party
Key Numbers
NA
NA
NA
Credit
Pts
NC
1-4
Schools
1-4
CS
1-4
NA
Certified 40-49 points Silver 50-59 points Gold 60-79 points Platinum 80-110 points
11