ALARP
ALARP
ALARP
ALARP
Core concepts
One of the main objectives of the Commonwealth Offshore Petroleum and Greenhouse Gas Storage
(Safety) Regulations 2009 [OPGGS(S)] is to ensure that the risks to health and safety of people at
offshore facilities are reduced to a level that is as low as reasonably practicable (ALARP).
A safety case has to show how an operator meets, or will meet, the requirements of the regulatory
provisions relevant to the control of major accident event risks and the risks to health and safety of
people at the operators facility. Many of the requirements are qualified by the phrase reduce the
risks to a level that is as low as reasonably practicable. This means that the operator has to show,
through reasoned and supported arguments, that there are no other practical measures that could
reasonably be taken to reduce risks further.
The adopted control measures for any particular identified major accident event must be shown to
collectively eliminate, or reduce to a level that is ALARP, the risk to health and safety.
The approach employed in providing the required evidence of ALARP within a safety case is at the
discretion of the operator. In practice a combination of approaches is likely to be necessary.
Only by inclusion of a sufficient level of detail of information will NOPSEMA be able to make a
judgement on the appropriateness of the safety case in accordance with OPGGS(S) Regulation 2.26 (for
new safety cases) or Regulation 2.34 (for revised safety cases).
This guidance note addresses how the ALARP concept can be addressed in the context of a safety case.
A138249
June 2014
1 of 22
Guidance note
ALARP
Table of Contents
1
2
3
4
5
6
7
8
9
10
Introduction
4
5
6
11
13
14
14
14
16
17
20
21
22
Abbreviations/Acronyms
ALARP
CBA
EERA
FERA
FSA
FPSO
HSC
HSE
ICAF
IMO
IPRA
LSA
MAE
MODU
NOPSEMA
OPGGSA
OPGGS(S)
QRA
SMS
A138249
June 2014
2 of 22
Guidance note
ALARP
The legal definition on this was set out in England by Lord Justice Asquith in Edwards vs. National Coal
Board [1949] who said:
Reasonably practicable is a narrower term than physically possible and seems to me to imply that a
computation must be made by the owner, in which the quantum of risk is placed on one scale and the
sacrifice involved in the measures necessary for averting the risk (whether in money, time or trouble) is
placed in the other; and that if it be shown that there is a gross disproportion between them the risk being
insignificant in relation to the sacrifice the defendants discharge the onus on them. Moreover, this
computation falls to be made by the owner at a point of time anterior to the accident.
This English decision has since been confirmed by the Australian High Court 1.
1
Slivak v Lurgi (Australia) Pty Ltd (2001) 205 CLR 304 cited in Bluff & Johnstone (2004) The relationship between Reasonably
Practicable and Risk Management (WP 27 ANU National Research Centre for OHS Regulation)
Introduction
A138249
June 2014
3 of 22
Guidance note
ALARP
The purpose of the guidance is to explain the objectives of the OPGGS(S) Regulations, to identify the
general issues that should be considered, and to provide practical examples to illustrate the concepts and
potential approaches that can be taken in the preparation of safety cases. It is not the intention of the
guidance to provide detailed approaches or detailed regulatory assessment criteria.
Guidance notes indicate what is explicitly required by the regulations, discuss good practice and suggest
possible approaches. An explicit regulatory requirement is indicated by the word must, while other cases
are indicated by the words should, may, etc. NOPSEMA acknowledges that what is good practice, and
what approaches are valid and viable, will vary according to the nature of different offshore petroleum
facilities and their hazards. This guidance note is not a substitute for detailed advice on the OPGGS(S)
Regulations or the Act under which the OPGGS(S) Regulations have been made.
(3) An object of these regulations is to ensure that the risks to the health and safety of
persons at offshore petroleum facilities are reduced to a level that is as low as
reasonably practicable.
A safety case has to show how an operator meets, or will meet, the requirements of the regulatory
provisions relevant to the control of major accident event risks and the risks to health and safety of people
at the operators facility. Many of the requirements are qualified by the phrase reduce the risks to a level
that is as low as reasonably practicable. This means that the operator has to show, through reasoned and
supported arguments, that there are no other practical measures that could reasonably be taken to reduce
risks further.
The concept of reasonably practicable is central to the safety case regime. It allows operators to set goals
for their own safety performance rather than following prescriptive requirements. It also allows NOPSEMA
to accept or reject the operators arrangements under the safety case. This flexibility is a great advantage
but it can be challenging because it requires people to exercise judgement with respect to how they are
going to manage their risks. In the great majority of cases, a decision can be made by referring to existing
good practice that has been established. However, for complex situations it may be difficult to reach a
decision on the basis of good practice alone. There may be some situations, for example in the case of
new technology, where there is no relevant good practice that can be followed. In these situations other
decision-making techniques need to be applied to inform our judgment.
Other regulators such as the United Kingdoms Health and Safety Executive (HSE) and the Norwegian
Petroleum Directorate have been successfully administering safety case regimes for many years. The HSE,
in particular, has developed constructive guidance on the topic of the application of ALARP (available on
the HSE website www.hse.gov.uk) and readers are encouraged to make reference to it. However, it is
essential to bear in mind that while there are parallels in the regulatory approach, there are also important
variations in the safety case legislation between the UK and Australia, and as such the HSE guidance should
only be referenced to for concepts and principles.
Key aspects of the HSE guidance are distilled in this guidance note with respect to how to go about
constructing an ALARP argument.
Further information is available in the NOPSEMA Policy:
Safety Case Assessment
A138249
June 2014
4 of 22
Guidance note
ALARP
Key Principles
It is important to understand the key principles underpinning the ALARP principle. The following
descriptions have been adapted from HSE information sheet no. 2/2006.
Reasonable practicability Determining whether risks have been reduced as low as is reasonably
practicable involves an assessment of the risk to be avoided, and an assessment of the sacrifice (in money,
time and effort) involved in taking measures to avoid that risk, and a comparison of the two. A risk may sit
on a spectrum from very low (where it is very unlikely that it would be possible to reduce the risk further)
through to levels of risk that are very high. The greater the initial level of risk under consideration, the
greater the effort likely to be required to demonstrate that risks have been reduced to a level that is as low
as reasonably practicable, however, just because the initial level of risk may be low doesnt mean it may
not be reasonably practicable to reduce it further. The basis on which the comparison is made involves the
test of gross disproportion.
Gross disproportion if a measure is practicable and it cannot be shown that the cost of the measure is
grossly disproportionate to the benefit gained; then the measure is considered reasonably practicable and
should be implemented. The criterion is reasonably practicable not reasonably affordable: justifiable cost
and effort is not determined by the budget constraints/viability of a project.
Inherently safer design It is good practice to apply the principles of prevention as a hierarchy.
A138249
June 2014
5 of 22
Guidance note
ALARP
Reverse ALARP operators have from time to time tried to show through quantitative risk assessment
(QRA) and cost benefit analysis (CBA) that moving to a less protected situation will meet the legal
requirement to reduce risks to a level that is ALARP, sometimes arguing that the increase in risk is more
than balanced by gains in reduced operational costs or increased operating profit a reverse ALARP
argument. The legal requirement to reduce risks as low as reasonably practicable would rule out
NOPSEMA accepting a less protected but significantly cheaper approach to the control of risks.
Changed circumstances operators may wish to introduce new processes, new technology or alter the
conditions in which equipment is operated in response to changed circumstances. Such changes may
result in a change to the risk profile - some risks may increase. This may be permissible provided control
measures are taken to ensure that the risks are reduced as low as reasonably practicable for the new
situation.
The safety case for the facility must also contain a detailed description of the
formal safety assessment for the facility, being an assessment, or series of
assessments, conducted by the operator that:
(a) identifies all hazards having the potential to cause a major accident event;
and
(b) is a detailed and systematic assessment of the risk associated with each of
those hazards, including the likelihood and consequences of each potential
major accident event; and
(c) identifies the technical and other control measures that are necessary to
reduce that risk to a level that is as low as reasonably practicable.
The formalised descriptions within the safety case must provide evidence a formal safety assessment (FSA)
has been carried out for the facility, and that the FSA has identified the technical (i.e. hardware and
software) and other (i.e. procedural) control measures that are necessary to reduce risk to a level that is
ALARP. In respect of this requirement, the OPGGS(S) Regulations also explicitly require two studies in
particular to be carried out as part of the FSA:
an evacuation, escape and rescue analysis (EERA) that identifies control measures necessary to
reduce the risks associated with emergencies to a level that is ALARP [OPGGS(S) subregulation
2.16(2)(h)];and
a fire and explosion risk analysis (FERA) that identifies control measures necessary to reduce the risks
associated with fires and explosions to a level that is ALARP [OPGGS(S) subregulation 2.17(2)(g)].
Operators should note that the regulations require the consideration of a range of control measures in each
instance, including different procedures, a range of amenities and/or equipment, alternative measures, etc.
[OPGGS(S) subregulation 2.16(2) and subregulation 2.17(2)]. Consequently, information presented in the
safety case should not simply focus on promoting or selling the chosen design option but rather a
discussion on the merits of different options and a justification that the chosen option is indeed the one
that reduces risk to a level that is ALARP.
A138249
June 2014
6 of 22
Guidance note
ALARP
For existing facilities, operators should not merely concentrate on providing information on design
features of control measures, but should also put effort into providing knowledge acquired from
operating the facility, such as adequacy assurance gained from control measure performance data over
time. Design ALARP should be taken as a starting point only.
The safety case for the facility must contain a detailed description of the safety
management system that:
(e) provides for the reduction to a level that is as low as reasonably practicable of risks
to health and safety of persons at or near the facility including, but not limited to:
(i) risks arising during evacuation, escape and rescue in case of emergency; and
(ii) risks arising from equipment and hardware.
While the FSA must identify the technical and other control measures that are necessary to reduce risk to
ALARP, the SMS must be comprehensive and integrated to cover all control measures. The so called
other control measures are found within the safety management system (SMS), and include elements
such as policies and procedures. The regulatory requirement is that SMS itself must provide for reduction of
risks to ALARP; and that the detailed description within the safety case provides information to support that
the SMS achieves this requirement. This aspect is particularly relevant for safety cases which cover ongoing
activities and operations over time. The safety case should show how effectiveness is maintained and how
deviations are managed to ensure they achieve a risk profile that is ALARP.
OPGGS(S) Regulations SMS Description
Reg 2.5(3)
The safety case for the facility must contain a detailed description of the safety
management system that:
(i) specifies the performance standards that apply.
In order to maintain risks at a level that is ALARP it is essential that control measures remain effective. The
information provided in the safety case in support of the ALARP argument should cover the following
aspects as a minimum:
Performance is measured against set performance standards within inspection, maintenance and
safety management systems.
There is periodic review of the process by which performance standards are established and
maintained, including checks that the right things are being measured.
Further guidance is available in the NOPSEMA guidance note:
Control Measures and Performance Standards
A138249
June 2014
7 of 22
Guidance note
ALARP
In setting out to provide evidence that the risks are reduced to a level that is ALARP, it is a fundamental
requirement to demonstrate, in the first instance, that the hazard identification and risk assessment carried
out have been systematic and detailed, as they provide the foundation on which to base the control
measure selection. The following approaches may be considered:
Hazard / Risk Criteria Approach
Define criteria that is considered to correspond to reducing risk to a level that is as low as is
reasonably practicable, assess performance quantitatively or qualitatively (using matrices for
example) and compare against the criteria.
Comparative Assessment of Risks, Costs and Benefits
Evaluate risk and associated costs for a range of control measure options for the facility and
compare the relative merits of the different options, selecting the options which are practicable.
Cost Benefit Analysis [CBA]
The numerical assessment of the costs of implementing a design change or modification and the
likely reduction in fatalities that this would be expected to achieve. The quality of the modelling
and the data will affect the robustness of the numerical estimate and the uncertainties in it must
always be borne in mind when using the estimate in risk management decisions. In making this
assessment there is a need to set criteria on the value of a life or implied cost of averting a
statistical fatality (ICAF). In reality of course there is no simple cut-off and a whole range of factors,
including uncertainty need to be taken into account in the decision-making process.
Comparison with Codes and Standards
Compare design, the management system framework and operational procedures against
recognised national, international or industry standards, codes of practice, guides etc.
Audit against good practice
Audit the basis and implementation of the management system, including operations and
maintenance systems, against good practice for offshore facilities, vessels, or relevant similar
industries onshore.
Technical Analysis
Evaluate control measures in technical terms; assess strengths and weaknesses, e.g. effectiveness,
functionality, availability, reliability, technical feasibility, compatibility, survivability, correspondence
of control measures to hazards and risks, appropriateness of performance standards, etc.
Performance Data
Evaluate MAE safety-related performance data as evidence of adequacy or satisfactory levels of
performance, e.g. data on the operational effectiveness or reliability of a control measure may
support the demonstration of its appropriateness for that service.
Improvement Approach
Demonstrate the extent of relative improvements in performance for the facility based on past,
present and planned modifications and enhancements.
Judgement Approach
Present considered judgements as to the suitability of control measures and the management
systems, or the perceptions of a cross-section of various stakeholders, e.g. key members of the
workforce, senior management, plus independent observers.
Practical Tests
Demonstrate that the management system and/or control measures function effectively, using
major accident event simulations, management system tests, equipment breakdown and recovery
tests, etc. For example, it may be possible to conduct fire impingement tests to show that fire
rating of the material being used is appropriate.
For safety case acceptance purposes, NOPSEMA will evaluate the operators approach in terms of its
robustness, transparency and appropriateness to the facility. The operator should therefore define the
underlying rationale, criteria and decision-making basis for the case.
National Offshore Petroleum Safety and Environmental Management Authority
A138249
June 2014
8 of 22
Guidance note
ALARP
The description must be convincing; this means that the rationale for deciding the completeness of the
hazard identification and the adequacy of the measures employed should be supported and accompanied
by all assumptions made and conclusions drawn. Where appropriate, it should present/summarise the
results of supporting studies that have been performed.
The description should demonstrate that the process was systematic which means that it followed a fixed
and pre-established scope. Finally, the degree of analysis in support of the demonstration should be
proportionate to the risk and to the complexity of the facility, hazards and the control measures.
The UK offshore oil and gas industry has developed a framework to assist risk-related decision making (Oil
& Gas UK, formerly UKOOA, 1999), which helps decision-makers choose an appropriate basis for their
decisions. A summary of the framework is shown in Figure 2.
The framework takes the form of a spectrum of decision bases, ranging from those decisions dominated
purely by engineering concerns to those where company and societal values are the most relevant factors.
Down the right-hand edge of the framework are typical characteristics which indicate the decision context;
these can be used to help the user determine the context of the specific decision. Once this level has been
identified, reading horizontally across the framework shows the suggested balance of decision bases to be
taken into account in the decision. Some means of calibrating or checking the decision basis are shown on
the left-hand side of the framework.
Figure 2 Risk Related Decision Support Framework (UKOOA 1999)
A138249
June 2014
9 of 22
Guidance note
ALARP
This approach shows that risk assessment may have a major input to Type B decisions involving some
uncertainty, deviation from standard practice, risk trade-offs etc., whilst codes and standards are likely to
have a major input to Type A decisions, with less influence on Type B and C. What is evident from the
model is that a combination of decision bases is most likely to be applicable in any case.
The model is intended to be dynamic with the diagonal lines shifting either towards the X-axis or the Y-axis
depending on circumstances of the application being considered. It is advisable to make reference to the
Oil & Gas UK guidelines themselves for detail on the use of the framework as the diagram is complex and its
interpretation can be very subjective.
As an additional caution, operators who are making Type A decisions that rely predominantly on codes and
standards as a decision basis should ensure they truly understand how the codes and standards act to
minimise risks. Without this knowledge it is difficult to identify when change (planned or otherwise) will
undermine the effectiveness of that standard or code as a control measure.
The following example gives an application of the framework for illustration purposes: three facilities, three
different outcomes.
Table 1 - Example of applying the risk related decision support framework
Facility 1
Facility 2
Facility 3
Scenario
Standard temperature /
pressure pipeline in a
mature oil and gas
development area with no
known unique
environmental concerns
and much existing similar
infrastructure.
Decision
Type
Hydrocarbon processing
facilities are not novel but
they are new to the
operator and thus deviate
from established company
practice. Qualified
engineering judgement and
some risk based assessment
will be required to
determine that the design is
ALARP. The decision type is
B.
Risk
reduction
measures
Standard measures
specified in design codes
and adopted on the existing
infrastructure are put in
place.
A138249
June 2014
10 of 22
Guidance note
ALARP
The basic requirement for control measures for MAEs is that they must collectively reduce the risk to the
health and safety of people to a level as low as is reasonably practicable (ALARP). Risk assessment provides
information necessary to test this requirement, and it is this information that must be included in the safety
case. Reduction of risk to ALARP is dependent on identification of hazards having the potential to cause
MAEs and proper selection of the necessary control measures for each of them. This has several aspects, all
of which will in general apply to each facility:
The knock-on effects of hazards must be considered, i.e. any chain of events, causes and contributing
factors leading to MAEs.
For any MAE there may be several independent hazards or combinations of hazards, each of which
could lead to that event, and several control measures which may be particularly important because
they may impact on one or more of those hazards.
The potential for escalation of major accident events needs to be considered, i.e. the cumulative
consequences of apparently separate events that may be triggered by each other.
In cases where a large number of different hazards and potential incidents exist, the cumulative risk
may be significant even if the risk arising from each is low. For example, the cumulative effects of
many sources of risk in an offshore accommodation area may identify an unacceptable risk even if
each source is low risk.
Consequently the demonstration that risks from MAEs are eliminated or reduced to ALARP may need to be
made for hazards individually, in groups, and as a whole.
As stated earlier, there is no single correct way to demonstrate ALARP. However, it is expected that for
each MAE identified for the facility, the demonstration would contain elements of the following process:
Identification and consideration of a range of potential measures for risk reduction (both those
adopted and those rejected);
Systematic analysis of each of the identified measures and a view formed on the safety benefit
associated with each of them;
Evaluation of the reasonable practicability of the identified measures and the adoption or rejection of
each; and
Recording of the process and results, to be summarised in the safety case.
Clearly, the balance between benefits in terms of reduced risk and the costs of control measures will play a
part in achieving and justifying ALARP. For example, if a control measure has a benefit that greatly
outweighs the cost, this control measure would almost always have to be implemented, or very good
reasons provided for not doing so. In contrast, if the cost greatly outweighs the benefit, demonstrating that
the control measure is not appropriate is straightforward, as other options will almost certainly exist that
are able to achieve a similar level of risk reduction at lower cost. If benefits and costs are both high, or are
both low, more careful consideration may be required before selecting or rejecting control measures.
The operator may be able to rank available control measure options according to their benefits and costs in
qualitative or quantitative terms. This will enable the operator to show that the appropriate balance has
been achieved, where further steps to reduce risk would incur unreasonably high cost with little gain.
For existing facilities, in undertaking risk assessment and providing justification, operators shouldalso
consider if newly adopted control measures could pose additional hazards or contribute to incident
scenarios, e.g. during installation or commissioning of new control equipment, or arising from spurious
operation of control measures.
Implementation arrangements should be included for any risk control measures that are planned but not
yet in place, i.e. scheduled implementation. Specific and explicit commitments should be included that
demonstrate the operators intention not to operate their facilities at an increased level of risk, in that
activities will not be carried out until such time as the corresponding control measures have been fully
implemented.
A138249
June 2014
11 of 22
Guidance note
ALARP
While there is no explicit requirement within the OPGGS(S) Regulations to record in the safety case the
range of control measures that has been considered, the content and level of detail needs to be sufficient
to gain an appreciation of the scope and process for undertaking the consideration including sources of
data and rationale for excluding or discounting items from consideration. It is difficult to see how an
operator could show that risks are as low as reasonably practicable without making reference to other,
discarded risk control measures.
Given all of the issues that may need consideration in demonstrating that the necessary control measures
have been identified, it is appropriate to develop an approach that is logical, structured and efficient. For
example, it would be inefficient to assess the effect of a control measure in detail if itwas not practicable
from a cost perspective. Equally, if there are control measures that can eliminate hazards, there may be
little purpose in devoting significant effort to the assessment of measures for reduction or mitigation of the
identified associated MAE.
Performance standards should be set for MAE control measures, and the safety case will need to include a
convincing argument that these standards are appropriate. This is required to provide evidence to enable
NOPSEMA to make a decision on whether the safety case is appropriate to the facility in accordance with
OPGGS(S) subregulation 2.5(2)(c). These factors are discussed in greater detail in NOPSEMA Guidance Note
Control Measures and Performance Standards.
Further guidance is available in the NOPSEMA guidance note:
Control Measures and Performance Standards
A138249
June 2014
12 of 22
Guidance note
ALARP
Points to Consider
Elimination
Prevention
Reduction
Mitigation
Technical (Hardware/software)
Other (SMS/Procedural)
Layers of Protection
Design Standards
Control Systems
Operating Procedures
Safety Devices
Emergency Systems
Operating Circumstances
Environment
Operating conditions
Have the controls been assessed for effectiveness over the range
of different operating circumstances they may have to operate
in?
Effective
Functionality
Availability
Reliability
Survivability
ALARP
A138249
June 2014
13 of 22
Guidance note
ALARP
Operators of offshore facilities must adopt a comprehensive and systematic method for assessing the risks
of major accident events at their facilities. Some operators may choose to adopt quantitative methods,
particularly if this is common practice in their company, whereas others may choose to adopt qualitative
methods. The results of such assessments should be used to support the evidence that necessary control
measures have been identified, and to show that risks are eliminated or reduced to a level that is ALARP.
NOPSEMA expects the operator to justify the adopted risk assessment methodology and associated risk
acceptance criteria as being suitable and appropriate to the specific facility.
Unacceptable /
Intolerable Region
IRPA 1x10 -3
ALARP
Region
IRPA 1x10 -6
Broadly
Acceptable
Region
A138249
June 2014
14 of 22
Guidance note
ALARP
Risk is most commonly represented on an inverted triangle (such as Figure 3 above) as increasing from a
broadly acceptable risk region, through a tolerable region only if shown to be ALARP, to an intolerable
region, in which the risk cannot be justified on any grounds. Such diagrams also typically introduce
numerical thresholds between the risk bands, often in terms of the Individual Risk Per Annum (IRPA) of a
fatality. Operators may find it helpful to think of risk in terms of the inverted ALARP risk triangle; however it
is important to be aware that the overall provisions the operator has to make through the safety case need
to consider hazards and risks in all regions of the triangle.
As shown in Figure 4, a more accurate representation of an ALARP triangle in the context of the OPGGS(S)
Regulations is simpler, but more challenging, with the sole requirement being the reduction in risk to
ALARP. It is notable that in order to keep risk at a level that is ALARP requires ongoing action to ensure the
integrity of the control measures is maintained.
Figure 4 OPGGS(S) ALARP triangle diagram
Untreated
Risk
Application of
cost effective
control measures
to reduce risk
Ongoing action to
maintain integrity of
control measures
Risk reduced to a
level that is
ALARP
Cost of further risk
treatment grossly
disproportionate to
the reduction in risk
Although the Australian safety case regime may appear broadly compatible with that applied
internationally, it is important to stress that the requirements contained within the OPGGS(S) Regulations
incorporate continuous improvement aspects. This means that at the lowest risk band, it may be
reasonably practicable to further reduce the risk, and the regulations also require that this is considered.
The safety case will have to show that:
all hazards with the potential to lead to a major accident event have had all reasonably practicable
risk reduction measures applied;
any hazards or risks that may arise in the future will be effectively dealt with; and
there are suitable and reliable processes for continuing to manage hazards and risks at all levels,
and for achieving continuous improvement
It is appropriate to apply concepts of proportionality to treating risks, and to concentrate effort on high
risk areas. Numerical categorisation of risk may provide a yardstick to assist understanding and
prioritizing risk reduction measures, however it should not be used as a single acceptance criterion.
A138249
June 2014
15 of 22
Guidance note
ALARP
Level of RIsk
Continuous Improvement
Identify
Hazards
Assess
Risks
Implement
Controls
Identify
Controls
Identify
Hazards
Manage
Safety
Implement
Controls
Identify
Controls
Assess
Risks
Safety Case
Submission
ALARP
It is expected that over the life of a facility an operators risk managementprocesses will identify
opportunities to enhance the effectiveness of existing control measures or implement additional control
measures and that a proportion of these will be reasonably practical to implement. This expectation is
based on both ongoing developments in the state of knowledge concerning hazards and risks and the
associated control measures and the over-arching duty of an operator to take all reasonably practicable
steps to ensure that the facility and activities carried out at the facility are safe and without risk to the
health and safety of any person at or near the facility.
A138249
June 2014
16 of 22
Guidance note
ALARP
For most facilities, compliance with industry standards, codes or practices may play an important role in
providing evidence that necessary and appropriate control measures have been identified and adopted. In
principle, such standards may be Australian Standards, equivalents from overseas organisations such as ISO
standards, international industry practices such as those from the American Petroleum Institute, or
company-specific standards. However, the existence of a published standard does not imply that it is
always useful or correct. Whichever standards are being used, these standards, and the control measures
that they apply, should all be shown to be suitable and appropriate to the specific facility, taking account of
its type, scale, activities, location, etc. Operators have the responsibility to consider the available
standards, specify the correct one, enforce compliance, and use the system or equipment correctly.
Validation of suitability of standards for safety-critical equipment is also necessary.
Further guidance is available in the NOPSEMA guidance note:
Control Measures and Performance Standards
Technical standards issued by classification societies, IMO, national authorities and industry bodies
underpin the design of many aspects of most offshore installations. For example, ISO 13702 (Control and
mitigation of fires and explosions on offshore production installations), ISO 15544 (Requirements and
guidelines for emergency response) and ISO 10418 (Basic surface process safety systems) provide guidance
in relation to offshore production facilities. These standards have been developed using the expertise of
the industry, responding to previous accident and incident experience and, in general, prescribe specific
design solutions. The aim of technical standards is to ensure that, provided the installation is used for a
standard application under good safety management, the risks will be reduced. However, it is an
established part of good safety management to make use of risk assessment to identify hazards and
minimise risks. Compliance with technical standards provides a sound design basis for standard offshore
installations, but does not replace risk assessment altogether.
The standards may not address the types of incident that are of prime concern to the facility;
There may be gaps in the standards, such that the particular standard does not govern all aspects of
hazards and risks at a facility; and
A138249
June 2014
17 of 22
Guidance note
ALARP
The standard has fallen behind current good practice, or the facility has fallen behind the standard
as that has been further developed.
A138249
June 2014
18 of 22
Guidance note
ALARP
An object of these regulations is to ensure that safety cases for offshore petroleum
facilities make provision for the following matters in relation to the health and safety of
persons at or near the facilities:
(a) the identification of hazards
(b) the implementation of measures to eliminate the hazards or otherwise control the
risks;
(c)
a comprehensive and integrated system for management of the hazards and risks;
(d) monitoring, audit, review and continuous improvement.
With respect to OPGGS(S) subregulation 1.4(2)(d) the review of facility hazards and risks should be a
periodic process whereby the applied standards on a facility are reviewed against new and updated
standards. If new standards or requirements are introduced they cannot be dismissed because the plant or
facility was built prior to them; neither should they be automatically adopted: the risk assessment process
must be undertaken. The task would be to understand the intent of the new standard and the change that
it evokes from the current/existing operating situation. Once the assessment has taken place then
decisions can be made about implications for a new understanding of risk on the facility and the steps that
need to be taken.
Example: MODU Code
A number of MODUs operating in Australian waters are only classed to the 1979 MODU Code (rather
than the 1989 Code or 2001 amendment). One area of significant difference with later versions of
this code is considerations for ballast control following the Ocean Ranger incident in which a MODU
and all on board were lost. Any ALARP argument for the management of ballasting related MAEs
should explicitly consider the limitations of the older code and implementation of the current code or
equivalent control measures unless it can be demonstrated not to be reasonably practicable to do so.
It is also an option for an operator to use earlier versions of a code or standard if it can be shown that by
doing so the risks are reduced to a level that is ALARP. In taking such an approach an operator wouldalso
need to be mindful of the basis for the change to the code or standard noting that such changes are
generally improvements in response to an identified failure or weakness of the code or standard.
Example: Electrical colour coding
An operator may in the past have complied with Electrical Installation Standard AS 3000 which was
revised in 2007 with respect to selection of cables for size and colour. The operator may assess that
there is a risk arising from the use of two different cable colour schemes in the same system.
NOPSEMA would expect under such circumstances that older conductors would be thoroughly tested
to ensure that their physical condition is acceptable and that existing cables do actually meet the
standard the operator has quoted in terms of adequate cross-sectional area, voltage drop levels,
cable grouping etc.
A138249
June 2014
19 of 22
Guidance note
ALARP
In determining what is reasonably practicable (or not), the courts usually do so in the context of an incident
and therefore take an event focus - they consider in hindsight an alleged breach associated with a
particular incident, and each incident is judged on a case by case basis. Due to the event focus of
prosecutions, courts traditionally have not been concerned with what proactive steps might need to be
taken by an operator to address risk across a facility. In contrast, risk management provisions in the
OPGGS(S) Regulations are framed as a proactive and holistic process, to prevent or control risks before
incidents occur rather than simply reacting to them when they do.
In the decision by Lord Asquith, the computation associated with reasonably practicable falls to be made
by the owner at a point of time anterior to the accident. Furthermore, in regard to what is practicable,
the test of gross disproportion applies: if a measure is practicable and it cannot be shown that the cost of
the measure is grossly disproportionate to the benefit gained, then the measure is considered reasonably
practicable and must be implemented. This reinforces a precautionary approach by requiring the requisite
control measures to be implemented unless there is an obvious imbalance between the sacrifice (cost) and
the risk and further that as risk levels rise so too does the sacrifice (cost) that could reasonably be
considered as being grossly disproportionate. .
When reviewing health or safety control measures for an existing facility, plant, installation or for a
particular situation (such as when considering retrofitting, safety reviews or upgrades), operators should
compare existing measures against current good practice. The good practice measuresshould be adopted
so far as is reasonably practicable. It might not be reasonably practicable to apply retrospectively to
existing plant, for example, all the good practice expected for new plant. However, there may still be ways
to reduce the risk e.g. by partial solutions, alternative measures, etc.
In determining what is reasonably practicable, the starting point for the risk/sacrifice computation should
be the current situation. Operators should also consider the adequacy of the relevant good practice. An
operators SMS should incorporate processes to monitor changes to applicable codes and standards. When
a code or standard is updated to a higher standard, the facility, plant, installation or situation should be
examined to see if it can be brought up to the new standard. Any such upgrades must be undertaken if it is
reasonably practicable to do so.
New plant, installations or situations should conform to current good practice, as a starting point. Other
potential options should be considered to determine whether further risk reduction measures are
reasonably practicable. As a guide, designers can aim and compare against levels of safety that are known
to have been achieved in other good practice designs.
The use of good practice at the design stage is essential to demonstrating achievement of ALARP.
Therefore, it is important that the operator capture all of the relevant information about risk-reduction
decisions made during the early design stages. This should include use of sound design principles (e.g.
inherent safety) as well as codes, standards and guidance. The earlier an operator undertakes an ALARP
evaluation, the greater the ability to reduce risks to a level that is ALARP. Practicability is reduced as the
project progresses and inherent safety opportunities are often lost beyond the concept selection stage. As
previously mentioned, the criterion is reasonably practicable, not reasonably affordable: justifiable cost and
effort is not determined by the budget constraints/viability of the project.
A138249
June 2014
20 of 22
Guidance note
ALARP
Timeliness. The earlier an operator undertakes an ALARP evaluation, the greater the ability to reduce
risks to a level that is ALARP.
Safety case content that is consistent with the requirements specified in the OPGGS(S) Regulations;
Access to a wide range of reference material such as standards, safety alerts, etc.;
Description with an sufficient level of detail that explains the means by which the operator ensures
suitability of the design, construction, installation, operation, maintenance or modification that is
appropriate to the facility;
A transparent and robust presentation of evidence showing that the adopted control measures
reduce risk to ALARP; and
A transparent and robust presentation of evidence that the SMS provides for and will continue to
provide for reduction of risk to ALARP, and that the SMS is comprehensive and integrated.
A138249
June 2014
21 of 22
Guidance note
ALARP
A138249
June 2014
22 of 22