Paper On Fuzzy Logic in Selecting Piles For Testing PDF
Paper On Fuzzy Logic in Selecting Piles For Testing PDF
Paper On Fuzzy Logic in Selecting Piles For Testing PDF
Abstract
The construction industry in Sri Lanka has seen a boom in the past two decades. The
promising construction industry does not fail to endow a number of high rise buildings in
and around the commercial capital, Colombo. Due to the soil conditions, building loads,
resource availability etc; Geotechnical experts quite often recommend bored and cast-in-situ
pile as the deep foundation of choice in such high rise buildings. However, the quality
assurance systems for piling have not developed in par with the increasing piling
construction works. The cost and time are the major factors that set constraints against
maintaining high quality assurance standards in any projects. The selection of piles for
testing has been the critical aspect in determining the cost and time of the quality assurance
system. In this technique, scores were assigned to various aspects such as boring method,
boring equipment, de-sanding method, flushing method, duration of borehole kept open
before concreting, quality of the concrete, concreting method, cube strength of concrete,
concrete wastage, pile integrity, etc. These scores have different weightings based on their
individual importance. The piles scoring above a preset score would be selected for dynamic
testing. The devised method to select piles for dynamic testing has proven extremely effective
and efficient. The outcomes from the adopted quality assessment system had accentuated the
importance of keeping track of the quality of each and every pile from their preconstruction
stage itself.
Key words: Piling, Quality assurance, PDA, PIT, SLT, Fuzzy logic
1 Introduction
The booming construction industry in Sri Lanka has endowed many high rise buildings in
and around the commercial capital, Colombo. There are a number of proposed high rise
projects in progress presently and also in the pipeline to be commenced; awaiting a positive
gesture from the economic indicators of the country. High rise buildings, over 20 stories, are
most likely to be supported by deep foundations like piles. Due to the sub soil conditions,
building loads, availability of resources etc; Geotechnical experts quite often recommend
bored and cast-in-situ piles as the deep foundation of choice for such high rise buildings.
Increasing construction activities have caused the stakeholders of construction to resort for
new methodologies and techniques of construction as opposed to conventional tested- andtrue procedures. The construction of piles is a very important exercise as the failure of a pile
would cost the owner in millions to reinstate the building.
Therefore, the construction processes ought to be monitored and controlled in every step of
the way to avoid such failures. Even though there are a number of methods available to
construct bored and cast-in-situ piles, such as (a) Uncased Drilling Method- Hole Stabilized
by Slurry ( bored and cast in-situ ), (b) Fully cased Drilling with Rotary Drive, (c) Drilling
with Continuous Flight Augur, (d) Fully Cased Drilling Oscillator, (e) Drilling with
Displacement System, (f) Drilling with Fixed Double Rotary Drives, (g) Mixed-in-Place
System with Triple Auger, (h) Drilling with Movable Double Rotary Drives, etc; yet the
method (a) is the common method being adopted in Sri Lanka. Thus, Uncased Drilling
Method is the method of concern in this paper.
Major steps involved in the construction of bored and cast-in-situ piles using Uncased
Drilling Method are: (a) Installation of top casing with rotary drive of the drill rig, (b)
Excavation of soil with the drill bucket and stabilization of the bore hole with slurry
(bentonite or polymer), (c) Cleaning the slurry with the de-sander or flushing, (d) Installation
of reinforcement cage, (e) Pouring of concrete with the tremie pipe while pumping back the
slurry to the tank, and finally (f) extraction of the top casing with the rotary drive of the rig
(Fig.1) [1]. In order to produce a flawless pile, the quality assurance and quality control
(QA/QC) system shall be in place to monitor and control the factors involved with above
method during the process of the construction. In the absence of a proper QA/QC system it is
reckoned that an unacceptable number of piles could fail to achieve the design pile load
capacities. The piles found to have failed to mobilize the required design load are most
probably replaced with compensatory piles as per the present practice in Sri Lanka. Since the
piles, which have failed, remain unused in the ground they could be termed as dead piles.
This paper primarily discusses a novel technique of evaluating and assuring the quality of
piling works with limited time and cost that set constraints against maintaining high quality
assurance standards in any projects, the method of construction of piles and the available
methods of testing of the same.
The selection of piles for testing has been the critical aspect in determining the cost and time
involved in a quality assurance system. The method discussed in this paper has been tested
and proven to be successful in one of the largest building projects in Sri Lanka. The method
essentially used a scoring technique using the fuzzy logic techniques.
In this technique, scores were assigned for various aspects given under the generalized titles
such as Quality of Drilling Machines and Drilling Tools, Quality of Rock Socketing,
Quality of Maintaining Borehole, Quality of Cleaning the Borehole, Quality of Concreting,
Integrity of the Pile, etc. These scores have different weighting limits, which can be
adjusted at the discretion of the Engineer, set by the authors based on their individual
importance. The aggregate of assigned scores is used to check against a preset value and if
the aggregate is found to be greater than the preset value then the pile is subjected to testing.
60
50
40
30
20
10
0
10
20
30
40
50
60
70
80
90
100
110
120
(7a)
(7b)
Fig. 7a & 7b Pile Integrity Testing
Fig.8 Typical velocity wave propagation diagram from PIT of a cast-in-situ pile
The pattern of wave speed generated in PIT can be studied thoroughly to investigate the
presence of necking, poor quality concrete, bulging, cavities etc. and the location of such
defects in the pile shaft. Also, one important observation made in our study using PIT was
the identification of soft toe condition, which is the primary cause for reduced end baring
capacities of piles and large settlements under service load conditions. Soft toe condition
occurs mainly due to improper cleaning and flushing of the pile toe.
The velocity curves obtained from PIT were compared against the wave pattern generated for
different toe conditions using the software Pilewave, version 3.0.0 [5]. The wave pattern
generated by this software clearly shows that a negative wave reflection at the toe when the
toe is well socketed into the basement rock; whereas a positive wave reflection is observed
when the toe is unsocketed (Fig. 9 and Fig 10). The latter is analogous to a soft toe condition.
Thus, PIT results with such a wave pattern could be doubted for soft toe condition. This
reasoning is convincingly supported by Jayasinghe [6] in his book on Pile Integrity Testing
and Dynamic Pile Testing.
A further investigation showed that when a positive reflection or the reflection of the same
sign as the input wave is encountered, a necking or defect (not necessarily) could be expected
at that location of the pile (Fig 11, Fig 12 and Fig.13).
Quality of Concreting
Linguistic Variable
Score
Satisfactory
Moderately Satisfactory
Not Satisfactory
10
Satisfactory
Moderately Satisfactory
Not Satisfactory
10
Satisfactory
Moderately Satisfactory
Not Satisfactory
10
Satisfactory
Moderately Satisfactory
Not Satisfactory
10
Satisfactory
Moderately Satisfactory
Not Satisfactory
10
Satisfactory
Moderately Satisfactory
Not Satisfactory
10
Weighting (%)
10
10
15
20
40
An example of evaluating the final score of a pile for selection for testing is given in Table 2.
Linguistic Variable
Score
Weighting (%)
Final Score
Satisfactory
0.0
Satisfactory
10
0.0
Moderately
Satisfactory
10
0.5
Not Satisfactory
10
15
1.5
Quality of Concreting
Moderately
Satisfactory
20
1.0
Moderately
Satisfactory
40
2.0
Total Score
Since the preset score for this project was 4, the pile is required to be subjected to dynamic
testing. Some of the results obtained in our study using the above method of assessment are
given in Table 3 and Table 4. This is a testimony for the usefulness of this technique to
assess the quality of constructed piles.
S
S
S
S
P49
P114
P123
P142
S
S
S
S
MS
S
MS
S
S
NS
S
S
Note:
S- Satisfactory
MS- Moderately satisfactory
NS- Not Satisfactory
MS
S
NS
S
NS
NS
NS
NS
Total Score
Quality of Concreting
Pile No.
5.5
5.5
6.5
4.0
PIT Results
PDA Results
Test
Mobilized
Load
Capacity
(Tons)
(Tons)
P49
2569.5
1311
P114
2569.5
1537
P123
P142
2569.5
1124
2569.5
1137
5. Conclusions
The consequences of a pile failing could prove atrocious to the owner of the building.
Therefore, a proper QA/QC plan needs to be in place to ensure, preferably, all the piles
checked against the expected design parameters. Testing of each pile for its load bearing
capacity is not pragmatic, since the testing of each pile by static load test (SLT) or by
dynamic load testing (PDA) is very costly and a time consuming process. Presently the
selection process of piles for load testing is arbitrarily carried out on approximately 5-10% of
piles without considering all the factors that are likely to cause failure of piles during
installation. The arbitrary selection of piles possibly contributes to the high cost and time
involvement in quality assurance and control systems.
The degree of confidence with a constructed pile is essentially unquantifiable as there are
various unknowns involved in the factors discussed in sections 3.1 through 3.6. Our study
focused on developing a technique to quantify the degree of confidence of a pile by
considering the critical factors that are involved in the construction of a pile. The method
devised in this study to select piles for dynamic testing had proven extremely effective and
efficient
References
1. http://www.bauer.de
2. Singapore Standard, CP 4 :2003 (ICS 91.040; 93.020),Code of Practice for
Foundations, SPRING Singapore.
3. British Standard, BS 8004: 1986, Code of Practice for Foundations, British Standards
Institution.
4. Specification for Piling, Table 5.1, Institute of Civil Engineers London.
5. http://www.piletest.com
6. L.P.Jayasinghe, Pile Integrity Testing (PIT) and Dynamic Pile Testing (PDA),
Geotech Testing Services (PVT) Ltd.
7. Bart Kosko, Fuzzy Engineering, Prentice Hall. Inc, 1997, USA.
Acknowledgement
We are thankful to a number of individuals, who have had in many ways contributed to this
study. Firstly, we appreciate Mr.O.C.Jayawardane for his unfettered support endowed to us
in developing a state-of-the-art quality monitoring system in pile construction. His
knowledge and experience in this field had facilitated us in developing a framework for the
quality monitoring system using fuzzy logic technique. We are, also, grateful to Eng.
T.P.G.U.Alwis for his support in gathering information from various sources and making us
available with the necessary technical software for the assessments. We are obliged to thank
Eng.Dr.A.C.Visvaling and Eng. Mahesh Gamage for their valuable encouragement and
advice in piling works.
Bibliography
Eng.W.J.B.Shiromal Fernando, BSc. Eng (Hons), Mphil, CEng, MIE (SL), Eng. Shiromal
is presently working at Design Consortium Limited as Director cum Senior Structural
Engineer. He has vast experience in designing of high rise buildings in Sri Lanka. He was the
former honorary Secretary of the Society of Structural Engineers, Sri Lanka.. He is also a
member of Institution of Engineers Sri Lanka. He has conducted a number of short courses at
ICTAD and University of Moratuwa, Preadeniya and Ruhuna on his field of specialization.
He is the Vice president if Green Building Council of Sri Lanka.
Eng. R.Thivakar, BSc. Eng (Hons), MSc. (Struct. Eng.), MBA (Business Management),
ACS, was born on 11th May, 1977. Eng. R.Thivakar is working at Design Consortium
Limited as a Structural Engineer since 2006. He has had worked as Research Assistant at
Uniuversity of Moratuwa under the guidance of Prof.W.P.S.Dias and Dr.S.M.S.Nanayakkara
after his graduation. He has successfully completed Masters program in Structural
Engineering at the University of Moratuwa in 2006 and in Business Administration at ICBS,
affiliated to Warnborough University, UK, in 2005. He is an Associate member of Society of
Structural Engineers, Sri Lanka.