Republic of Moldova

Ministry of Transport and Road Infrastructure


State Road Administration
and
European Investment Bank

ROAD SECTOR PROGRAM


Rehabilitation of R6 M1-Ialoveni Road
km 0+000 to km 6+550

TENDER DOCUMENTS:
PART 2 REQUIREMENTS
PREAMBLE TO THE BILLS OF QUANTITIES

Tendering No. RSP/2013/OT/W6


Invitation for Tenders No. RSP/2013/OT/W6/05

Chisinau, 2014

PREAMBLE TO THE BILLS OF QUANTITIES


1

GENERAL

1.1

The Bill of Quantities shall be read in conjunction with the Instructions to Tenderers,
General Conditions, Conditions of Particular Application, Tender Data, Technical
Specifications, and Drawings.

1.2

General directions and descriptions of work and materials are not necessarily
repeated or summarized in the Bill of Quantities. Where summaries of the work
covered by the items are given in the item descriptions they are indicative only and
the rates entered by tenderers shall include for all ancillary work or materials not
specifically stated but implicit in the item of work. Tenderers should refer to the
relevant sections of the contract documentation before entering rates or prices
against each item in the Bill of Quantities.

1.3

The Technical Specification Clause/Item references given in the Bills of Quantities


are for the convenience of tenderers and generally refer to the principal relevant
specification clause but do not necessarily represent the whole of the specification
requirements for the work required within the item. The presence of a Technical
Specification clause reference shall not in any way reduce the Contractors obligation
to complete work in accordance with all the requirements of the Specification.

1.4

All rates and prices shall be in Euros and stated to two places of decimals. The
tenderer shall be responsible for entering a rate or price against all of the applicable
and quantified items in the Bills of Quantities. The cost of execution of items against
which the tenderer has failed to enter a rate or price shall be deemed to be covered
by other rates and prices entered in the Bills of Quantities.

1.5

The Bills of Quantities, submitted with tenders that are determined by the Employer to
be substantially responsive, will be checked by the Employer for any arithmetic
errors. Errors will be corrected by the Employer in accordance with the provisions of
the Tender Documents, Part I, Section I, F Tender Evaluation and Comparison, 29
Evaluation of Tenders and Correction of Mathematical Errors.

1.4

The rates and prices tendered for the execution of the works items and listed in the
Bills of Quantities are all inclusive and the Contractor shall be deemed to have
ensured the sufficiency of his rates and prices to take account of all things necessary
for the proper execution and completion of the works items and activities, the
execution and completion of the Works and the remedying of any defects.

1.5

The whole cost of complying with the provisions of the Contract shall be included in
the Items provided in the priced Bills of Quantities, and where no items are provided
the cost shall be deemed to be distributed among the rates and prices entered for the
related items of work. The rates and prices tendered in the priced Bill of Quantities
shall include for all Costs including but not limited to:
all costs and expenses required on and for the construction of the Works
costs of temporary works and installations which may be necessary
costs of all general risks, liabilities and obligations set out or implied in the
documents on which the tender is based
taxes, duties and other charges for which the Contractor is liable.

1.6

It will be assumed that establishment charges, profit and allowances for the
Contractors obligations (except those covered by specific Bill of Quantities items) are
spread evenly over all the unit rates. Without affecting the generality of the foregoing
provisions, the rates and prices entered by the Contractor in the Bills of Quantities
shall include the cost and expense of the following:
The provision, storage, transport, use and maintenance of all materials,
equipment, machinery and tools;
The provision, maintenance and welfare of all staff and labour and their
accommodation, transport etc, and the supply of all immigration permits and other
requirements;
Condition

surveys,

measurements,

inspections,

supervision

and

any

topographical survey and drawing necessary for the execution or measurement of


the work;
The preparation of Construction Drawings as required by the Specifications Subsections 006.02, 101.03 and 101.04
The preparation of Record Drawings as required by the Specifications Subsection 006.05 and 101.04
The preparation and compliance with the Environmental Management Plan as
required by the Specifications Chapter 016
The provision, transport, use and maintenance of all consumable stores, fuel,
water, drainage, electricity and telephones, including those required under the
Contract by the Engineer and his staff;
Initial condition surveys of roads to be used by the Contractor for transport and
access to the site, the installation of additional safety provisions on such roads, as
necessary, and the rectification of any damage to such roads;
Care of the properties, the safety and the rights of others;

Sampling, testing and trials, including trail lengths of pavement and checking
information given by the Engineer;
Commissioning and testing of Plant, pipelines, structures and other major
components provided under the Contract;
Damage caused to the works under construction, equipment, materials and
consumable stores by weather conditions within the 95% range of normal
statistical occurrence probability;
The provision, erection and removal of all Contractors offices, equipment yards,
stores and temporary works, including fencing and all site restrictions;
Repair of the Works during the Defects Notification Period;
The additional costs of the Engineers supervision of the Works when extended
working hours and/or weekend working is permitted;
The rates shall not include for items for which provisional items are inserted.
1.7

Incidental activities may be required in order to execute and complete the works
activities, to execute and complete the Works and to remedy any defects, in
accordance with the Contract and with the intentions of the designs. Where any such
incidental activities are not expressly included within the specifications applicable to
the rates and prices tendered, the cost of all such incidental activities shall be
deemed to be included for within the rates and prices listed in the Bills of Quantities.

1.8

Certain items in the Bills of Quantities shall be known as fixed rate items and for the
purposes of evaluation in accordance with Sub-Clause 12.3(a) of the Conditions of
Contract such items shall not be eligible for consideration of a new rate or price in the
event of a change in the quantity of work payable against the item. Fixed rate items in
this Contract are:
Items which apply to machine laid asphaltic material in regulating, binder and
wearing course layers;
Items which apply to the cleaning and sealing of cracks in the asphaltic surfacing;
Items which apply to the provision and placing of stress absorbing membrane
interface (SAMI) layers.

2.

QUANTITIES AND MEASUREMENT OF WORKS ITEMS

2.1

The quantities given in the Bills of Quantities are estimated and provisional, and are
given to provide a common basis for tendering. The basis of payment will be the
actual net quantities of work executed in accordance with the Contract and the
Instructions of the Engineer (subject to the Employers approval), with any defects
remedied.

2.2

There is no guarantee to the Contractor that he will be required to carry out the
quantity of work indicated under any particular item in the Bill of Quantities or that the
quantities will not differ in magnitude from those stated in the Bills. The Contractor
shall promptly notify the Engineer, with a copy to the Employer requesting
authorisation to proceed, of differences between the listed quantities in the Bills of
Quantities and the prospective actual quantities which would increase the Contract
Price.

2.3

The procedure for determining the works quantities for execution shall be as follows:
A comprehensive initial condition survey of all of the existing elements of the
highway shall be jointly carried out by the Engineer, the Designers
Representative and the Contractor.
The Contractor shall carry out an initial topographical survey of the highway,
verified by the Engineer, carry out a comprehensive photographic survey and
prepare strip plans to clearly differentiate between defects included for by the
designs and any requirement for additional works.
The Contractor shall prepare Draft Construction Drawings, which correct the
defects and minimise the estimated Cost of the works to be executed. The
Contractor shall submit his Proposal for construction (in accordance with the Draft
Construction Drawings), with a detailed Cost analysis and a Programme for
execution within the Time for Completion.
The Designers Representative shall Review and agree, or provide comments
upon, the conformity of the Draft Construction Drawings with the intentions of the
Design and verify the Contractors Cost analysis.
The Engineer shall review the conformity of the Contractors Programme together
with the review of the Designers Representative, require corrections as
necessary and, when he determines the Proposal to be technically and financially
acceptable, forward the submission to the Employer for approval as a Variation
and (subject to the approval of the Employer), issue the Variation to the
Contractor as Approved for Construction.

2.4

The method of measurement and computations to be used in determination of


quantities of materials furnished and of work performed under the contract will be
those internationally recognised as conforming to good engineering practice. The
quantities will be computed net with no allowance for bulking, shrinkage or waste in
accordance with the provisions of sub-para (a) of Sub-Clause 12.2 (Method of
Measurement), of the General Conditions of Contract : measurement shall be made
of the net actual quantity of each item of the Permanent Works.

2.5

Lump sum items shall include but not be limited to the full inclusive cost of all the
temporary and permanent work and all attendant activities necessary to complete the
item of work to the satisfaction of the Engineer.

2.6

Provisional Sum items shall include agreed direct costs charged by suppliers plus
overheads established from the breakdown of the bill prices submitted by the
Contractor and as agreed with the Engineer.

2.7

Except where expressly stated otherwise in the Contract, only the permanent works
shall be measured.

2.8

The Engineer shall measure the net authorised Works quantities from the approved
Construction Drawings having verified the Contractors certification of conformity of
the quantities and quality of the measured works with the Contract. The Engineers
measurement of quantities on site shall be with the attendance and assistance of the
Contractor in accordance with the Contract.

2.9

For any item for which measurement is based upon records made before or during
construction, the records shall be prepared and agreed between the Engineer and the
Contractor. Should the Contractor carry out such work without the prior agreement of
the Engineer, the Engineer may request the Contractor to carry out investigations to
confirm the extent of the work. The quantity of work certified for payment shall be
solely at the Engineers discretion. The cost of any such investigation shall be borne
by the Contractor.

2.10

Where excavation works are to be measured, the depth of excavation shall be


measured from the commencing surface level to the required level of excavated
surface and no allowance shall be made for over-excavation or working space.

2.11

For measurement purposes, rock is defined as cement concrete or natural material


encountered in the course of excavation works which, in response to notification of
any such encounter by the Contractor, the Engineer accepts to be too hard to be
excavated with the bucket of a 115KW (150HP) tracked excavator. Road pavement
layers are excluded from the definition of rock.

2.12

The Engineers authority to authorise Varied works and instruct additional quantities
without the approval of the Employer, shall be limited to the percentage of the
Accepted Tender Amount as stated in the Tender Data. Excepting as otherwise
provided for in the Contract, any executed quantities of unauthorised Varied works
shall be to the account of the Contractor and shall not be certified by the Engineer for
payment.

DAYWORKS

3.1

DAYWORKS GENERAL

3.1.1 The Bill of Quantities includes Provisional Sums for use when work is to be executed
on a daywork basis, only after approval of the Engineer.
3.1.2 Rates shall be entered into the Euro/hr column of the Schedules to cover the types of
labour and Contractors Equipment which the Tenderer anticipates using on the
Works.
3.1.3 The rates entered by the Contractor as part of his Tender will be used to value any
work ordered by the Engineer to be executed on a daywork basis. For the purpose of
this Schedule the rates shall be deemed to cover:
Head Office charges;
Site Supervision and Site Staff costs and expenses;
Transport of labour and travelling allowances;
Use of protective clothing;
Any statutory or incidental charges levied on the employment of labour;
Overtime, unless specifically ordered or subsequently sanctioned in writing by the
Engineer;
Time lost due to inclement weather;
Insurances of whatsoever nature;
Holiday and sickness pay or benefits;
Use, repair and sharpening of small tools;
All non-mechanically operated equipment, erected scaffolding, staging and
trestles, protective clothing, artificial lighting, storage facilities and the like that
may be in general use on the site;
All other liabilities and obligations whatsoever.

3.1

DAYWORKS LABOUR

3.2.1 The Labour Schedule rates shall include for the amount of wages to be paid to the
work people inclusive of all overheads and profit and such extra payments or
differentials as are paid in respect of subsistence payments, condition payments, tool
allowances, bonus payments, responsibility, discomfort, inconvenience and risk.
3.2.2 The Labour Schedule rates shall include the costs in respect of portable tools such as
picks, shovels, barrows, trowels, ladders, hand-saws, buckets, trestles, hammers,
chisels and all items of a like nature, which for the purpose of work executed on a
Daywork basis shall not be considered as Contractors Equipment.

3.2.3 In the case of equipment, operators and banksmen, the payment shall be calculated
using the hours actually worked by the associated equipment.
3.2.4 No payment shall be made in respect of the net amount of wages of the Contractors
Site Supervisory or Administrative Staff, the costs in respect of which shall be
included within the rates for labour contained in the Labour Schedule rates. Gangers
or charge-hands working with their gangs shall not be counted as Site Supervisory or
Administrative Staff.
3.2

DAYWORK MATERIALS

3.3.1 Where materials supplied by the Contractor are used for Daywork, the Contractor
shall be reimbursed the actual net cost of the materials, including delivery to the site,
plus a percentage of this cost. This percentage shall be deemed to cover the costs of
taking delivery and putting into the store or stockpile, storage and all other charges
and costs in respect of or incidental to the procurement and handling of such
materials and Contractors overheads and profit.
3.3.2 The actual net costs of materials referred to above is the cost less all trade discount
but including all discounts for cash not exceeding five percent.
3.3

DAYWORK CONTRACTORS EQUIPMENT

3.4.1 Payment in respect of Contractors Equipment employed in the execution of the work
on a daywork basis, exclusive of drivers and attendants but inclusive of fuel and
consumable stores, shall be at the rates entered in the Daywork Equipment
Schedule.
3.4.2 Such rates shall apply to Contractors Equipment already on the Site at the time of
the relevant Engineers order to execute work on a daywork basis.
3.4.3 Payment for mechanical equipment shall be for the actual hours worked only and the
time for which Contractors Equipment is broken down or during which it is being
serviced shall not be paid for. Any labour or other Contractors Equipment engaged
on daywork operations which is unable to work by reason of such breakdown or
servicing shall not be paid for. The costs of servicing and breakdown time will be
deemed to be included in the rates.
3.4.4 If the Contractor should use types of Contractors Equipment for dayworks that are
not included in the Schedule, the Engineer shall fix an appropriate dayworks unit rate
analogous to the Contractors Equipment Schedules rates.
3.4.5 The rates shall include for all costs incurred in owning and operating Contractors
Equipment and shall include Contractors overheads and profit.