Hydraulics Manual - Drainage Design
Hydraulics Manual - Drainage Design
Hydraulics Manual - Drainage Design
Cover Page
Hydraulics
Hydraulics
Acknowledgments
This manual was originally prepared by NBS Lowry Engineers and Planners, and McLaughlin
Water Engineers, Ltd. under the direction of the Flood Control District of Maricopa County
(FCDMC). Work groups composed of representatives from the FCDMC and various communities in Maricopa County were formed to advise the consultants about the applicability of technical
criteria, special problem areas, and resolve conflicts over potential differences in drainage standards between communities.
The first edition of this manual was released in a draft format (November 1991) for review and
comment by public and private sector engineers, and other interested parties. The FCDMC staff
revised the manual using comments received from the public and reissued the manual with a
date of September 1992.
The second edition of the manual was revised in January 1996 by FCDMC staff based on comments received from users. Letters were sent to all the Cities and Towns in Maricopa County
informing them of the revisions to the manual, and inviting them to review the manual before the
FCDMC released it.
The third edition of the manual was updated in a collaborative effort between the FCDMC and the
City of Phoenix. Stantec Consulting Inc. performed the updating of the manual. Coincident with
the updating of this manual, the Hydrology manual underwent revisions. This effort saw the creation of a third document to contain policies and standards that can be tailored to each communitys needs. This manual along with the Hydrology Manual was completed in January 2004, but
not released because of further pending revisions.
During 2005 and 2006, the policies and standards manual was reviewed and revised by a working committee composed of representatives from the Flood Control District, Maricopa County
Planning and Development, Maricopa County Department of Transportation, and Maricopa
County Environmental Services. Following completion of the policies and standards manual, the
draft third edition of the Hydraulics manual was revised. A new chapter 7 was inserted and the
following chapters renumbered.
released in March 2007 as a draft. Between March 2007 and April 2013, the manual was further
refined, including a complete rewrite of Chapter 11 Sedimentation and fairly extensive technology
updates to Chapter 6 Open Channels and Chapter 8 Hydraulic Structures.
The Flood Control District of Maricopa County wished to thank the many individuals who contributed to the preparation of this document. (1989, 1995).
Chapter 11 required extensive research to provide the additional depth and detail included in this
new edition. It would not have been possible without the help of many individuals who contrib-
uted their time and experience to review and edit the chapter. The Flood Control District of Maricopa County wishes to express its appreciation for the efforts of everyone who contributed, and
the following individuals in particular:
Gary Freeman, PhD, PE
Comments
Users of this manual are welcomed to submit comments, suggestions, or findings of errors. This
information should be addressed to:
Engineering Division Manager
Flood Control District of Maricopa County
2801 West Durango
Phoenix, AZ 85009
Revisions
Because of ongoing technical and administrative changes in the field of stormwater management, revisions to this manual will be required from time to time. Such revisions will take place
on an ongoing, as needed, basis and will be posted on the FCDMCs Web page (www.fcd.maricopa.gov). The dates of revision and an overview of changes made are listed below.
1st Edition
September 1, 1992
2nd Edition
3rd Edition
ii
used in this list refer to the September 1, 1992 manual, unless otherwise stated.
Comments - Added this page requesting comments on the manual.
Acknowledgments - Added this page that identifies and thanks those individuals who have contributed to the manual in some official format.
Revisions - Added this section to summarize some of the significant changes to the
September 1, 1992 edition.
Chapter 1 - Changed the use of the phrase "regulation" to "recommended uniform policy requirement." Revised the descriptions of the chapters to reflect the revisions made to the chapters.
Revised the wording of the recommended uniform policy requirements to match with what is in
the chapters.
Chapter 2 - In Table 2.1 changed the Vmin from 2.5 to 3.0 fps for the 50 year peak frequency on
cross road culvert collector and arterial streets. Revised the wording for the finish floor elevation
for buildings within a FEMA floodplain area. In the footnote changed the minimum discharge for
delineating a floodplain for submittal to FEMA from 1,000 cfs to 500 cfs. Also, added Section 2.4
(References).
Chapter 3 - In Section 3.1 made minor corrections to some of the definitions. In Table 3.1
revised the second footnote. Renumbered the equations to account for identifying a new equation 3.2. For equation 3.2 added a sentence on what terms were inserted into equation 3.1 in
order to derive equation 3.2. Revised the wording in the recommended uniform policy box on
page 3-6.
Chapter 4 - This chapter was divided into two chapters. The new Chapter 4 is titled Storm
Drains, and the new Chapter 5 is titled Culverts and Bridges. In Section 4.1 deleted and added
definitions as needed for the revisions to the new chapter. Replaced the whole method for analyzing storm drains (Section 4.2). This required the addition of several new sections and the
complete revision to several old sections. Revised the wording slightly in the recommended uniform policy requirement on page 4-5. Added a section on minimum slope as Section 4.2.2.3.
Had to revise the numbering for some of the sections because of the new Section 4.2.2.3. In
Section 4.2.2.5 added a paragraph on minimum pipe size. Changed the title of Section 4.2.2.6
and revised some of the wording slightly. The methods to calculate the various losses are now
all located in Section 4.3.3.
The new Chapter 5 on Culverts and Bridges begins with Section 4.3 from September 1, 1992 edition. Because of being broken out into a new chapter all the numbering for the sections changed.
The wording in the recommended uniform policy requirement boxes on pages 4-73, 4-74, 4-81,
4-82, 4-83, and 4-85. In Section 4.3.2.2 revised the minimum velocity to 3 ft/s. In Section 4.3.2.7
the italic subsections were made into numbered sections. Sections 4.3.3.6 and 4.3.3.3 were
relocated under Section 5.2.2. This was done in order to locate all the various losses together in
one section.
iii
Chapter 5 - The chapter had to be renumbered to 6. Section 5.2 was made into the first section
of the chapter, which is consistent with the other chapters. Revised the recommended uniform
policy requirement boxes on pages 5-12, 5-16, 5-30, 5-33, and 5-41. In Figure 5.1 changed the
side slope of the riprap channel to 3:1. In Section 5.5.1.2 deleted the paragraph on the slope
paving method and Figure 5.7. In Section 5.5.2.2 thickness of the lining is now determined using
an ADOT reference. Table 5.4 was revised. On page 5-38 revised the thickness required for the
riprap layer. In Section 5.5.3.3 revised the method for sizing riprap. Deleted Table 5.7. Revised
Figure 5.10 to agree with the text. Changed the title of Table 5.10. In Section 5.6.3.1 changed
the Q100 in the example problem to 565 cfs.
Chapter 6 - The chapter was renumbered to. Section 6.2 was made into the first section of the
chapter, which is consistent with the other chapters. Revised the definitions of some of the symbols. Made the fourth paragraph on page 6-14 into a recommended uniform policy requirement.
Moved the hydraulic jump analysis (Section 6.8.1) to just after Section 6.3.2.).
Chapter 7 - Made this part of the new Chapter 5 on Culverts and Bridges. Deleted Sections
7.3.1.1 to 7.3.1.4 because there wasn't enough information presented here to do a complete
analysis of a bridge, and most designers will use a computer program for the analysis. From
these sections only the recommended uniform policy requirement on page 7-7 needed to be
kept. Revised the wording of the recommended uniform policy requirements on page 7-11. The
minimum freeboard for a bridge was revised to two feet for the 100-year event. Section 7.3.2.1
was revised.
Chapter 8 - Created a new Section 8.1, which defines the symbols used in this chapter and modified the numbering of the other sections because of it. In Section 8.2.1.2 added an equation for
determining the volume of retention required. Also, added a new recommended uniform policy
requirement dealing with off -site flows. Revised the wording for the recommended uniform policy requirements on pages 8-4, 8-6, 8-7, and 8-18. Added a new section dealing with sedimentation right before Section 8.2.1.3. In Section 8.2.1.8 added a recommended uniform policy
requirement about dry wells. The recommended uniform policy requirements on pages 8-18, 824, 8-25, and 8-30 were dropped although the text remains.
Chapter 9 - Revisions to this chapter were only to correct typographical errors.
Glossary - Revisions to this chapter were only to correct typographical errors
Index - A subject index was added to make it easier to find information in the manual.
iv
The sedimentation chapter summary was added. The summary of policies and standards was
eliminated with a section on safety added. The Purpose section was revised to identify this document as a Substantive Policy Document as defined in A.R.S. 48-3641.6.
Chapter 2 Hydrology - Changes to this chapter were minimal, most of which were corrections
for word selection. The table identifying hydrology design criteria was eliminated as this information is listed in a separate volume.
Chapter 3 Street Drainage - Chapter structure/format was revised to follow the following major
sections:
1. Introduction: Intent of Chapter and source of information
2. Procedures: Technical guidelines for engineering analyses.
3. Instructions: Example problems.
Figures 3.9 through 3.19 (Curb Opening Inlet Capacity Curves for MAG Details) were removed.
Chapter figures are revised/updated.
Chapter 4 Storm Drains - The following major sections were added/revised:
1. Introduction: Intent of Chapter and source of information
2. Procedures: Technical guidelines for engineering analyses.
3. Criteria: General criteria for hydraulic design and evaluation of storm drains.
4. Design Standards.
5. Design Examples.
The procedure for estimating losses that occur at a storm drain junction was replaced with the
Thompson Equation (Los Angeles County Flood Control District, Design Manual Hydraulic,
March 1982). The method for estimating the bend loss coefficient for curved and deflected sewers was changed. Procedures for estimating the hydraulic grade line for connector pipes (catch
basin to trunk line) were added from the City of Phoenix, Storm Drain Design Manual, Storm
Drains With Paving of Major Streets, July 1987. An appendix was added that provides a pressure plus momentum approach to estimate the hydraulic grade line through a storm drain junction.
Chapter 5 Culverts & Bridges - The introduction was revised to better identify the intent of the
chapter. Discussions pertaining to trashracks was moved to Chapter 7, Hydraulic Structures.
The discussion on scour hole geometry was eliminated. The procedure for Protection of Culvert
Outlets was deleted and reference made to the procedure in Chapter 7. An equation that allows
the estimation of scour depth was added to aid in the design of cutoff walls. The discussion on
scour was eliminated with reference made to Chapter 10, Sedimentation.
Chapter 6 Open Channels - This chapter was re-organized in its entirety with several sections
re-written, reorganized, or amended. Of particular note, the fundamentals of open channel
hydraulics was expanded and relocated to the beginning of the chapter. The design procedures
section and design checklist was removed while design guidelines remain.
Chapter 7 Hydraulic Structures - Discussions pertaining to the hydraulic analysis of trashracks
and access barriers, spillways, side channel spillways (forthcoming), channel bifurcations, channel access ramps, grade control structures, groins, and guide dikes were added along with other
design guidance related to these structures. The discussion on Low Flow Check Structures was
eliminated.
Chapter 8 Stormwater Storage - The Detention/Retention chapter was renamed Stormwater
Storage in order to eliminate confusion between the terms retention and detention. The lengthy
discussion on safety was moved to Chapter 1. The discussion on trashracks was moved to
Chapter 7. The section on flood routing was eliminated since it overlapped with other chapters of
the Hydraulics Manual and Hydrology Manual. Design considerations for stormwater storage
basins was expanded to elaborate multi-use concepts. The benefit of stormwater storage on
water quality was described in more detail. The discussion on sedimentation was condensed
with reference made to Chapter 10, Sedimentation.
Chapter 9 Pump Stations - The design criteria and checklist were revised and incorporated into
the chapter. The remainder of the chapter was completely rewritten to add a basic discussion on
pump station design and hydraulic analysis.
Chapter 10 Sedimentation - This chapter in its entirety was added.
vi
September 2003
1. The entire manual was reformatted for 2-sided printing.
2. Equation 6-14, which was missing, was added back in. Equation 6-15 was blank and
was deleted. Subsequent equations were re-numbered.
December 2006
1. A new Chapter 7 Friction Losses in Open Channels was inserted and the following
chapters renumbered. References throughout the document were revised to reflect the
new chapter. Text revisions to accommodate the new Chapter 7 were added, particularly
in Chapter 6.
2. Chapter 11 Sedimentation was revised to include comments received from the public
and significant edits by Dr. Bing Zhao.
March 2009
1. Chapter 11 Sedimentation is currently under revision after a peer review by sediment
mechanics experts from around the southwestern United States.
2. Chapter 5 Culverts and Bridges. Tables 5.2 and 5.3 revised to match the reference
document intent.
3. Chapter 6. Revised Table 6.1 to remove duplicate items.
4. Chapter 6. Revised text under Section 6.6.3 to correctly address computing a combined correction factor, C, for adjusting the riprap size to arrive at a stable riprap size.
The statement now matches HEC-11.
5. Chapter 6. Revised reference to Table 6.2 on page 6-62 to refer to Table 6.3 and Table
6.4.
6. Added Section 8.4.2 Riprap Aprons at Conduit Outlets.
April 2010
1. Entire Document. Miscellaneous revisions correcting references and typographical
errors.
2. Chapter 6, Section 6.6.3. Revised riprap channel bank lining procedure.
vii
viii
Approvals
ix
Table of Contents
Acknowledgments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i
Comments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .ii
Revisions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .ii
Table of Contents. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
List of Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
INTRODUCTION
TABLE OF CONTENTS . . . . . . . . . . . . . . .
1-1
1.1
PURPOSE . . . . . . . . . . . . . . . . . . . 1-1
1.2
BACKGROUND. . . . . . . . . . . . . . . . . . 1-2
1.3
SCOPE . . . . . . . . . . . . . . . . . . . . 1-2
1.3.1
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.3.2
Hydrology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.3.3
Street Drainage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.3.4
Storm Drains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.3.5
Culverts and Bridges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
1.3.6
Open Channels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
1.3.7
Hydraulic Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
1.3.8
Stormwater Storage Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
1.3.9
Pump Stations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
1.3.10 Sedimentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
1.4
SAFETY
. . . . . . . . . . . . . . . . . . . 1-5
1.4.1
Street Drainage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-7
1.4.2
Storm Drains & Culverts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-7
1.4.3
Open Channels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-8
1.4.4
Hydraulic Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-8
1.4.5
Stormwater Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-9
1.5
SUPPLEMENTAL DISCIPLINES . . . . . . . . . . . . . 1-10
1.5.1
Geotechnical Engineering . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-10
1.5.2
Structural Engineering. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-10
1.5.3
Environmental Expertise . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11
1.6
REFERENCES . . . . . . . . . . . . . . . . . . 1-11
HYDROLOGY
TABLE OF CONTENTS . .
2.1
METHODOLOGY . .
2.2
CRITERIA . . . .
2.3
DRAINAGE PLANNING
2.4
REFERENCES . . .
.
.
.
.
STREET DRAINAGE
TABLE OF CONTENTS .
3.1
SYMBOLS . . .
3.2
INTRODUCTION .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
2-1
.
.
.
.
2-1
2-2
2-2
2-3
3-1
. 3-1
. 3-3
3.3
3.2.1
General Discussion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3
3.2.2
Source of Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3
PROCEDURES . . . . . . . . . . . . . . . . . . 3-3
3.3.1
General Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3
Catch Basin Selection..............................................................................................3-3
Site Specific Design Considerations ........................................................................3-6
Storage Facilities .....................................................................................................3-6
3.3.2
3.4
APPLICATION . . . . . . . . . . . . . . . . . . 3-32
3.4.1
Design Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-32
3.4.2
Design Examples . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-33
Example 1 ..............................................................................................................3-33
Example 2 ..............................................................................................................3-35
Example 3 ..............................................................................................................3-37
Example 4 ..............................................................................................................3-40
Example 5 ..............................................................................................................3-44
Example 6 ..............................................................................................................3-45
3.5
REFERENCES .
STORM DRAINS
TABLE OF CONTENTS . . . .
4.1
SYMBOLS . . . . . .
4.2
INTRODUCTION . . . .
4.3
PROCEDURES . . . . .
4.3.1
General Considerations
. 3-47
4-1
. . . . . . . . . . . . . 4-1
. . . . . . . . . . . . . 4-3
. . . . . . . . . . . . . 4-3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-3
4.3.2
4.4
4.5
4.6
4.7
4.8
CRITERIA . . . . . . . . . . . . . . . . . . . 4-25
4.4.1
Main Line Hydraulic Grade Line . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-25
4.4.2
Determination of Controlling Water Surface Elevation . . . . . . . . . . . . . . . 4-26
4.4.3
Connector Pipe Hydraulic Grade Line. . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-27
DESIGN STANDARDS . . . . . . . . . . . . . . . . 4-27
DESIGN EXAMPLE. . . . . . . . . . . . . . . . . 4-28
REFERENCES . . . . . . . . . . . . . . . . . . 4-61
APPENDIX 4-A PRESSURE MOMENTUM ANALYSIS . . . . . . . 4-62
5.3.3
5.3.4
5.3.5
5.4
5.5
5.6
5.4.3
Protection at Culvert Outlets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-64
INVERTED SIPHONS . . . . . . . . . . . . . . . . 5-64
5.5.1
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-64
5.5.2
Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-64
5.5.3
Design Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-65
BRIDGES . . . . . . . . . . . . . . . . . . . 5-65
5.6.1
Hydraulic Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-66
5.6.2
5.7
REFERENCES . . . . . . . . . . . . . . . . . . 5-68
5.7.1
Cited in Text . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-68
5.7.2
References Relevant to Chapter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-68
OPEN CHANNELS
TABLE OF CONTENTS . . . . . . . . . . . . . . .
6-1
6.1
SYMBOLS . . . . . . . . . . . . . . . . . . . 6-3
6.2
INTRODUCTION . . . . . . . . . . . . . . . . . 6-6
6.2.1
Open Channel Defined . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-6
6.2.2
Scope of Chapter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-6
6.2.3
Application. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-6
6.2.4
Limitations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-6
6.3
BASIC OPEN CHANNEL HYDRAULICS . . . . . . . . . . . 6-7
6.3.1
Flow Classification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-7
6.3.2
Flow Regimes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-8
Froude Number........................................................................................................6-8
Specific Energy ........................................................................................................6-8
Critical Flow ...........................................................................................................6-10
Subcritical Flow......................................................................................................6-10
Supercritical Flow...................................................................................................6-11
6.3.3
6.3.4
6.3.5
6.3.6
6.4
6.3.7
Control Sections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-26
GENERAL CONSIDERATIONS FOR OPEN CHANNEL DESIGN . . . . . 6-26
6.4.1
Route Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-26
6.4.2
Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-26
6.4.3
Grade Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-27
6.4.4
Channel Linings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-27
Earth Lined Channels ............................................................................................6-29
Grass Lined Channels ...........................................................................................6-29
Compound Channels With Multi-Use Opportunities ..............................................6-29
Rock Lined Channels.............................................................................................6-30
Soil Cement ...........................................................................................................6-31
Concrete Lined Channels ......................................................................................6-31
6.4.5
6.4.6
6.4.7
6.5
6.6
6.4.8
Confluence Junction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-32
DESIGN FACTORS FOR OPEN CHANNELS . . . . . . . . . . 6-32
6.5.1
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-32
6.5.2
Minimum Velocity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-33
6.5.3
Maximum Velocity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-33
6.5.4
Freeboard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-35
6.5.5
Channel Curvature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-36
6.5.6
Superelevation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-36
DESIGN GUIDELINES FOR OPEN CHANNELS . . . . . . . . . 6-37
6.6.1
Concrete Lined Channels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-37
6.6.2
Soil Cement Lined Channels. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-42
Design of Soil Cement Linings...............................................................................6-42
6.6.3
6.6.4
6.6.5
6.6.6
6.6.7
6.6.8
6.7
REFERENCES . . . . . . . . . . . . . . . . . . 6-74
6.7.1
Cited in Text . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-74
6.7.2
References Relevant to Chapter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-77
7.6
7.7
7.6.6
Values of Mannings n For Agriculture or Overbank Areas . . . . . . . . . . . . 7-27
7.6.7
Composite Values of n For Constructed Channels . . . . . . . . . . . . . . . . . . 7-29
7.6.8
Procedure For Subdivision of Cross Sections. . . . . . . . . . . . . . . . . . . . . . 7-29
7.6.9
Procedure for Selection of n For Changing Vegetation Conditions. . . . . . 7-35
7.6.10 Selection Procedure of n for Natural and Constructed Channels . . . . . . . 7-41
VEGETATION MAINTENANCE PLAN GUIDELINES . . . . . . . . 7-53
7.7.1
Freeboard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-54
Examples of Guideline Use....................................................................................7-55
Example Case 1.....................................................................................................7-55
Example Case 2.....................................................................................................7-59
Example Case 3.....................................................................................................7-65
Example Case 4.....................................................................................................7-71
7.8
7.9
7.7.2
Vegetation Assessment and Maintenance Plan Outline . . . . . . . . . . . . . . 7-74
SUMMARY AND CONCLUSIONS . . . . . . . . . . . . . 7-75
REFERENCES . . . . . . . . . . . . . . . . . . 7-76
7.9.1
Cited in Text . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-76
HYDRAULIC STRUCTURES
TABLE OF CONTENTS . . . . . . . . . . . . . . .
8-1
8.1
SYMBOLS . . . . . . . . . . . . . . . . . . . 8-3
8.2
USE OF STRUCTURES IN DRAINAGE . . . . . . . . . . . 8-9
8.2.1
Channel Drop Structures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-9
8.2.2
Conduit Outlet Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-9
Spillways ................................................................................................................8-10
8.2.3
8.3
8.2.4
Access Ramps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-11
8.2.5
Trashracks and Access Barriers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-11
8.2.6
Factors of Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-11
CHANNEL DROP STRUCTURES . . . . . . . . . . . . . 8-12
8.3.1
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-12
Design Considerations...........................................................................................8-13
8.3.2
8.3.3
8.3.4
8.4
8.4.3
8.4.4
8.4.5
8.4.6
8.5
8.4.7
Baffle Chute Energy Dissipator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-77
8.4.8
Use of the HY-8 Software for Energy Dissipator Design. . . . . . . . . . . . . . 8-79
SPILLWAYS
. . . . . . . . . . . . . . . . . . 8-80
Hydraulic Analysis of Spillways..............................................................................8-80
Weir-Type Spillways ..............................................................................................8-80
Conduit Type Spillways..........................................................................................8-82
Stepped Spillway ...................................................................................................8-82
Compound Rating Curves......................................................................................8-85
8.6
8.6.2
8.6.3
8.6.4
8.6.5
8.7
8.8
SAFETY
. . . . . . . . . . . . . . . . . . . 8-98
OPERATION, MAINTENANCE & AESTHETIC CONSIDERATIONS . . . . 8-99
8.8.1
Operation and Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-99
8.8.2
Structure Aesthetics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-99
General ..................................................................................................................8-99
Open Spaces and Parks ......................................................................................8-100
Materials ..............................................................................................................8-100
8.9
REFERENCES . . . . . . . . . . . . . . . . . 8-101
8.9.1
Cited in Text . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-101
8.9.2
References Relevant to Chapter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-103
STORMWATER STORAGE
TABLE OF CONTENTS . . . . . . . . . . . . . . .
9-1
9.1
SYMBOLS . . . . . . . . . . . . . . . . . . . 9-2
9.2
INTRODUCTION . . . . . . . . . . . . . . . . . 9-2
9.2.1
Interaction with Other Components of a Drainage System . . . . . . . . . . . . . 9-3
9.2.2
Limitations on Use of Stormwater Storage Facilities. . . . . . . . . . . . . . . . . . 9-3
9.3
DESIGN GUIDELINES . . . . . . . . . . . . . . . . 9-4
9.3.1
Guidelines for Stormwater Storage Facilities . . . . . . . . . . . . . . . . . . . . . . . 9-5
Design Frequency....................................................................................................9-5
Hydrology.................................................................................................................9-5
Sedimentation in Stormwater Storage Basins .........................................................9-8
Siting and Geometry ................................................................................................9-8
Drain Time ...............................................................................................................9-9
Lining/Surface Treatment.........................................................................................9-9
Low Flow Channels..................................................................................................9-9
Stormwater Storage Facility Inlet and Outlet Structures ........................................9-10
Subsurface Disposal ..............................................................................................9-13
Permanent Pools ...................................................................................................9-20
9.3.2
9.3.3
9.4
9.5
SAFETY
. . . . . . . . . . . . . . . . . . . 9-26
OPERATION AND MAINTENANCE . . . . . . . . . . . . 9-26
9.5.1
Access. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-27
Design Recommendations.....................................................................................9-27
9.5.2
9.5.3
9.5.4
9.5.5
9.5.6
9.5.7
Design Recommendations.....................................................................................9-27
Design Recommendations.....................................................................................9-28
Design Recommendations.....................................................................................9-28
Design Recommendations.....................................................................................9-28
Design Recommendations.....................................................................................9-29
Design Recommendations.....................................................................................9-29
9.5.8
9.6
9.7
9.8
9.6.2
Stormwater Storage Facilities as Water Amenities . . . . . . . . . . . . . . . . . . 9-33
9.6.3
Urban Green Space . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-33
9.6.4
Water Harvesting for Reuse or Recharge . . . . . . . . . . . . . . . . . . . . . . . . . 9-33
WATER QUALITY . . . . . . . . . . . . . . . . . 9-34
9.7.1
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-34
9.7.2
Major Pollutants and Their Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-34
9.7.3
Role of Stormwater Storage Facilities in Water Quality Control . . . . . . . . 9-35
9.7.4
Method for Control of Sedimentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-36
REFERENCES . . . . . . . . . . . . . . . . . . 9-38
9.8.1
Cited in Text . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-38
9.8.2
Relevant to Chapter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-38
10 PUMP STATIONS
TABLE OF CONTENTS . . . . . . . . . . . . . . . 10-1
10.1 SYMBOLS . . . . . . . . . . . . . . . . . . . 10-1
10.2 INTRODUCTION . . . . . . . . . . . . . . . . . 10-2
10.3 DESIGN CRITERIA. . . . . . . . . . . . . . . . . 10-2
10.3.1 Design Frequency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-2
10.3.2 Drainage of Basins and Ponding Areas . . . . . . . . . . . . . . . . . . . . . . . . . . 10-2
10.3.3 Bleedoff Lines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-2
10.3.4 Pump Station Design Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-3
10.3.5 Pump Station Facility Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-4
10.4 DISCUSSION . . . . . . . . . . . . . . . . . . 10-4
10.4.1 Pump Selection Study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-4
10.4.2 System Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-5
10.4.3 Pump Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-7
10.4.4 Pump Selection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-7
10.4.5 Piping and Valves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-8
10.4.6 Location. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-8
10.4.7 Wet Well Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-9
10.4.8 Pump Room or Drywell . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-9
10.4.9 Pump Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-10
10.4.10 Pump Controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-10
10.4.11 Electrical Power Supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-10
10.4.12 Emergency Power Supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-10
10.5 AIDS
. . . . . . . . . . . . . . . . . . . 10-11
10.6 REFERENCES . . . . . . . . . . . . . . . . . 10-12
11 SEDIMENTATION
TABLE OF CONTENTS .
11.1 DEFINITIONS . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
11-1
. 11-3
11.2
11.3
11.4
11.5
11.6
11.7
11.8
11.9
10
INTRODUCTION . . . . . . . . . . . . . . . . . 11-5
SEDIMENTATION PROBLEMS . . . . . . . . . . . . . 11-7
SOLUTIONS TO SEDIMENTATION PROBLEMS . . . . . . . . . 11-9
FUNDAMENTALS FOR ALLUVIAL CHANNELS . . . . . . . . 11-11
11.5.1 Channel Patterns and Sinuosity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-11
11.5.2 Bed Forms. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-12
11.5.3 Regime Theory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-15
11.5.4 Equilibrium Concept and Channel Design. . . . . . . . . . . . . . . . . . . . . . . . 11-16
11.5.5 Equilibrium Concept Challenges in Arid and Semiarid Regions . . . . . . . 11-18
11.5.6 Channel Bed Scour and Deposition . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-20
11.5.7 Channel Lateral Migration, Meandering, and Bank Erosion . . . . . . . . . . 11-21
11.5.8 Headcut Migration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-25
11.5.9 Sand and Gravel Mining . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-28
FUNDAMENTALS FOR SEDIMENT TRANSPORT . . . . . . . 11-35
11.6.1 Sediment Properties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-35
11.6.1.1 Properties for Individual Sediment Particles . . . . 11-36
11.6.1.2 Bulk Properties for Sediment Mixture or Deposit . . . 11-41
11.6.1.3 Properties for Water-Sediment Mixtures . . . . . 11-49
11.6.2 Incipient Motion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-59
11.6.3 Armoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-60
11.6.4 Sediment Bulking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-61
11.6.5 Sediment Transport Functions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-62
WATERSHED SEDIMENT YIELD . . . . . . . . . . . . 11-63
11.7.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-63
11.7.2 Sediment Yield Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-65
11.7.3 Analytic Methods to Estimate Sediment Yield. . . . . . . . . . . . . . . . . . . . . 11-69
11.7.3.1 Introduction . . . . . . . . . . . . . 11-69
11.7.3.2 Sediment Yield Estimation by Empirical Equations
. . 11-70
11.7.3.3 Total Bed Material Load . . . . . . . . . 11-71
11.7.3.4 Volume Estimation for Total Bed Material Load . . . 11-72
11.7.3.5 Volume Estimation for Wash Load . . . . . . . 11-73
11.7.3.6 Sediment Delivery Ratio (SDR) for Wash Load . . . 11-75
11.7.3.7 Wash Load by Modified Universal Soil Loss Equation . . 11-77
11.7.3.8 Soil Erodibility Factor and Cover Management Factor . . 11-83
ESTIMATION OF SCOUR . . . . . . . . . . . . . . 11-83
11.8.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-83
11.8.2 Total Scour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-84
11.8.2.1 Long-Term Scour (Degradation) . . . . . . . 11-90
11.8.2.2 General Scour . . . . . . . . . . . . 11-96
11.8.2.3 Bend Scour . . . . . . . . . . . . . 11-104
11.8.2.4 Bedform Scour . . . . . . . . . . . . 11-106
11.8.2.5 Low-Flow Incisement Scour . . . . . . . . 11-107
11.8.2.6 Local Scour. . . . . . . . . . . . . 11-108
ESTIMATING LATERAL-EROSION HAZARD ZONES
. . . . . . 11-122
11.9.1 Straight Channel Reach (historical aerial photos available) . . . . . . . . . 11-125
11.9.2 Straight Channel Reach (historical aerial photos not available) . . . . . . 11-126
11.9.3 Channel Located Between Upstream and Downstream Bends . . . . . . 11-127
11.9.4 Straight Channel Reach Upstream and Downstream of a Bend . . . . . . 11-127
11.9.5 Application Limitations and Design Implications . . . . . . . . . . . . . . . . . . 11-129
11.9.6 Sand and Gravel Mining Operation Exception . . . . . . . . . . . . . . . . . . . 11-130
11
12
List of Tables
1
INTRODUCTION
HYDROLOGY
STREET DRAINAGE
4 STORM DRAINS
Table 4.1
Values of Roughness and Friction Formula Coefficients for Closed Conduits
Table 4.2
Storm Sewer Energy Loss Coefficients Under Open Channel Conditions .
Table 4.3a Coefficient ke for Gradual Enlargement Under Pressure Flow Conditions .
Table 4.3b Coefficient ke for Sudden Enlargement Under Pressure Flow Conditions .
Table 4.4
Coefficient kc for Sudden Contraction Under Pressure Flow Conditions .
Table E.1
Subbasin Parameters . . . . . . . . . . . . . .
Table E.2
Street and Inlet Parameters and Dimensions . . . . . . . .
Table E.3
Mainline Design Discharge and Pipe Parameters . . . . . . .
Table E.4
Hydraulic Grade Line Calculation Sheet. . . . . . . . . .
Table E.5
Connector Pipe Summary . . . . . . . . . . . . .
Table 4.A1 Pressure Plus Momentum Factors for Partially Full Circular Conduits . .
. 4-13
. 4-15
. 4-16
. 4-17
. 4-17
. 4-30
. 4-31
. 4-39
. 4-58
. 4-60
. 4-65
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. 5-29
. 5-62
. 5-62
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. 6-19
. 6-34
. 6-35
. 6-47
. 6-48
. 6-48
. 6-59
. 6-59
. 7-2
. 7-11
. 7-11
. 7-17
. 7-27
. 7-31
. 7-32
. 7-36
. 7-38
. 7-38
. 7-40
6 OPEN CHANNELS
Table 6.1
Elements of Channel Sections . . . . . . . . . .
Table 6.2
Maximum Permissible Velocities for Roadside Drainage Channels .
Table 6.3
Maximum Permissible Velocities for Grass-Lined Roadside Channels
Table 6.4
Riprap Gradation Limits . . . . . . . . . . . .
Table 6.5
Gradation for Gravel Bedding . . . . . . . . . .
Table 6.6
Thickness Requirements for Gravel Bedding . . . . . .
Table 6.7
Volume Increase Coefficient in Percent for Sand-bed Channels .
Table 6.8
Volume Increase Coefficient in % for Gravel-bed Channels. . .
13
Table 7.12
Table 7.13
Table 7.14
Table 7.15
Table 7.16
Table 7.17
Table 7.18
Table 7.19
Table 7.20
Table 7.21
Table 7.22
Table 7.23
Table 7.24
8 HYDRAULIC STRUCTURES
Table 8.1
Types of Hydraulic Jumps . . . . . . . . . . . .
Table 8.2
Uniform Flow in Circular Sections Flowing Partly Full . . . . .
Table 8.3
Lane's Weighted-Creep: Recommended Ratios
. . . . . .
Table 8.4
General Seepage Cutoff Technique Suitability . . . . . . .
Table 8.5
Quality Control Measures and Concerns of Drop Structure Components
Table 8.6
Apron Length and Thickness
. . . . . . . . . . .
Table 8.7
Loss Factors for Approach Angle Skewed to Trashrack. . . . .
.
.
.
.
.
.
.
. 8-21
. 8-28
. 8-30
. 8-31
. 8-33
. 8-59
. 8-96
9 STORMWATER STORAGE
Table 9.1
Minimum Quantity of Soil Log Hole/Percolation Tests Required
. .
Table 9.2
Recommended Minimum Percolation De-Rating Factors . . . .
Table 9.3
Non-Regulatory Emergency Spillway Design Capacity Requirements .
.
.
.
. 9-16
. 9-18
. 9-25
10 PUMP STATIONS
Table 10.1 Design Checklist for Pump Stations .
10-11
.
.
.
.
.
.
.
.
11-36
11-42
11-46
11-48
11-50
11-56
11-65
11-76
11 SEDIMENTATION
Table 11.1 Sediment Grade Scale . . . . . . . . . . . . .
Table 11.2 U.S. Standard Sieve Sizes . . . . . . . . . . . .
Table 11.3 Initial Bulk Specific Weights of Sediments of Various Grain Size . .
Table 11.4 Consolidation Coefficients for Specific Weight of Reservoir Sediments.
Table 11.5 Sediment Flow Classification Based on Concentration . . . . .
Table 11.6 Suspended Sediment Load for 10 Major Rivers in US in 1980 . . .
Table 11.7 Measured Sediment Yield From Representative Watersheds . . .
Table 11.8 Relationship between Drainage Area and Sediment Delivery Ratio. .
Table 11.9 Values of k1 . . . . . . . . . . . . . . . . . . .
Table 11.10 Correction Factor, K1, for Pier Nose Shape . . . . . . . .
Table 11.11 Correction Factor, K2, for Flow Angle of Attack . . . . . . .
Table 11.12 Correction Factor, K3, for Bed Form Condition . . . . . . .
Table 11.13 Abutment Shape Coefficients . . . . . . . . . . .
Table 11.14 Coefficients for Culvert Outlet Scour in Cohesionless Soils . . . .
Table 11.15 Coefficient, CS, for Culvert Slope . . . . . . . . . .
Table 11.16 Coefficient, CH, for Outlets above the Bed . . . . . . . .
14
.
.
.
.
.
.
.
. 11-99
11-111
11-112
11-112
11-116
11-119
11-120
11-120
List of Figures
1
INTRODUCTION
HYDROLOGY
3 STREET DRAINAGE
Figure 3.1 Catch Basin Inlets. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-5
Figure 3.2 Typical Street Intersection Drainage to Storm Drain System . . . . . . . . . . . . . . . . 3-7
Figure 3.3 Crown Ditch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-8
Figure 3.4 Nomograph for Triangular Gutters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-10
Figure 3.5 Composite Cross-Slope Gutter Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-11
Figure 3.6 Ratio of Frontal Flow to Total Gutter Flow . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-12
Figure 3.7 Curb Opening and Slotted Drain Inlet Length for Total Interception. . . . . . . . . . 3-14
Figure 3.8 Curb Opening and Slotted Drain Inlet Interception Efficiency. . . . . . . . . . . . . . . 3-15
Figure 3.9 Flow in Composite Gutter Sections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-16
Figure 3.10 Curb Opening Catch Basin Inlets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-19
Figure 3.11 Depressed Curb Opening Inlet Capacity in Sump Locations . . . . . . . . . . . . . . . 3-20
Figure 3.12 Curb Opening Inlet Capacity in Sump Locations . . . . . . . . . . . . . . . . . . . . . . . . 3-21
Figure 3.13 Curb Opening Inlet Capacity for Inclined and Vertical Orifice Throats . . . . . . . . 3-22
Figure 3.14 Grate Inlet Frontal Flow Interception Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . 3-24
Figure 3.15 Grate Inlet Side Flow Interception Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-26
Figure 3.16 Grate Inlet Capacity in Sump Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-28
Figure 3.17 Slotted Drain Inlet Capacity in Sump Condition . . . . . . . . . . . . . . . . . . . . . . . . . 3-31
4 STORM DRAINS
Figure 4.1 Efficient Manhole Shaping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-5
Figure 4.2 Inefficient Manhole Shaping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-6
Figure 4.3 Storm Drain Profile Pressure Flow Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-9
Figure 4.4 Storm Drain Profile Open Flow Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-10
Figure 4.5 Hydraulic Grade Line Calculation Sheet. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-11
Figure 4.6 Transition Loss . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-15
Figure 4.7 Formed or PreFab Storm Drain Junction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-19
Figure 4.8 Storm Drain Junction At Manhole With Aligned Crowns Under Pressure Flow . 4-19
Figure 4.9 Formed Storm Drain Junction with Aligned Crowns Under Pressure Flow . . . . 4-20
Figure 4.10 Bend Loss Coefficient. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-23
Figure 4.11 Initial Storm Drain Layout For Example Problem . . . . . . . . . . . . . . . . . . . . . . . . 4-28
Figure 4.A1 Circular Conduit Flowing Partially Full, Pipe Inlet . . . . . . . . . . . . . . . . . . . . . . . . 4-64
5 CULVERTS & BRIDGES
Figure 5.1 Barrel Skew Angle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-6
Figure 5.2 Inlet Skew Angle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-7
Figure 5.3 Typical Headwall/Wingwall Configurations for Skewed Channels . . . . . . . . . . . . 5-8
Figure 5.4 "Broken Back" Culvert . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-9
Figure 5.5 Culvert Junction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-10
Figure 5.6 Inlet Bevel Detail. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-13
Figure 5.7 Side-Tapered Inlet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-13
Figure 5.8 Slope-Tapered Inlet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-14
15
Figure 5.9
Figure 5.10
Figure 5.11
Figure 5.12
Figure 5.13
Figure 5.14
Figure 5.15
Figure 5.16
Figure 5.17
Figure 5.18
Figure 5.19
Figure 5.20
Figure 5.21
Figure 5.22
Figure 5.23
Figure 5.24
Figure 5.25
Figure 5.26
Figure 5.27
Figure 5.28
Figure 5.29
Figure 5.30
Figure 5.31
Figure 5.32
Figure 5.33
Figure 5.34
Figure 5.35
Figure 5.36
Figure 5.37
Figure 5.38
Figure 5.39
Figure 5.40
Figure 5.41
Figure 5.42
Figure 5.43
Figure 5.44
6 OPEN CHANNELS
Figure 6.1 Specific Energy Curve . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-9
Figure 6.2 Energy In Gradually Varied Open Channel Flow . . . . . . . . . . . . . . . . . . . . . . . . 6-12
Figure 6.3 Specific-Force Curves Supplemented with Specific-Energy Curves . . . . . . . . . 6-16
Figure 6.4 Diagram of Idealized Urban Floodplain . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-21
Figure 6.5 Classification of Flow Portion of Gradually Varied Flow . . . . . . . . . . . . . . . . . . . 6-24
Figure 6.6 Typical Channel Sections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-28
Figure 6.7 Compound Channel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-30
Figure 6.8 Typical Bank-Protection Key-Ins. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-38
Figure 6.9 Flap Valve Installation for a Channel Underdrain . . . . . . . . . . . . . . . . . . . . . . . . 6-41
Figure 6.10 Soil Cement Placement Detail . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-43
Figure 6.11 Relationships for Soil Cement Lining . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-44
16
Figure 6.11
Figure 6.12
Figure 6.13
Figure 6.14
Figure 6.15
Figure 6.16
Figure 6.17
Figure 6.18
Figure 6.19
Figure 6.20
Slope, Facing Thickness, Layer Thickness, and Horizontal Layer Width . . . . . . 6-44
Definition for Bank Angle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-51
Definition for Channel Bend Angle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-52
Toe Protection Channel Lining . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-60
Toe Protection Channel Lining Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-60
Required Blanket Thickness of Grouted Rock . . . . . . . . . . . . . . . . . . . . . . . . . . 6-62
Grouted Riprap Sections: (a) section A-A; (b) section B-B; and (c) section C-C 6-64
Grouted Riprap Schematic . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-65
Slope Mattress Lining . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-67
Design Example Channel Typical Cross Section . . . . . . . . . . . . . . . . . . . . . . . . 6-69
17
Figure 7.38
Figure 7.39
Figure 7.40
Figure 7.41
Figure 7.42
Figure 7.43
Figure 7.44
Figure 7.45
Figure 7.46
Figure 7.47
Figure 7.48
Figure 7.49
Figure 7.50
Figure 7.51
Figure 7.52
Figure 7.53
Figure 7.54
Figure 7.55
Figure 7.56
Figure 7.57
8 HYDRAULIC STRUCTURES
Figure 8.1 Typical Drop Structure Components. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-12
Figure 8.2 Drop Structure Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-14
Figure 8.3 Typical Vertical Drop Crest Configuration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-17
Figure 8.4 Typical Sloping Drop Crest Configuration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-18
Figure 8.5 Typical Section and Profile for Sloping Drop . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-20
Figure 8.6 Height of a Hydraulic Jump for a Horizontal Rectangular Channel . . . . . . . . . . 8-23
Figure 8.7 Length of Hydraulic Jump for Rectangular Channels . . . . . . . . . . . . . . . . . . . . . 8-24
Figure 8.8 Height of a Hydraulic Jump for a Horizontal Trapezoidal Channel . . . . . . . . . . . 8-25
Figure 8.9 Length of a Hydraulic Jump for Non-Rectangular Channels . . . . . . . . . . . . . . . 8-26
Figure 8.10 Surface Profile of a Hydraulic Jump in a Horizontal Channel . . . . . . . . . . . . . . . 8-27
Figure 8.11 Baffle Chute Drop . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-36
Figure 8.12 Baffle Chute Design Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-38
Figure 8.13 Baffle Chute Crest Modifications and Forces . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-39
Figure 8.14 Vertical Hard Basin Drop . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-44
Figure 8.15 Vertical Drop Hydraulic System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-45
Figure 8.16 Vertical Riprap Basin Drop . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-49
Figure 8.17 Curves for Scour Depth at Vertical Drop . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-50
Figure 8.18 Stilling Basins for Sloping Concrete Drops . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-52
Figure 8.19 Grouted Boulder Placement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-54
Figure 8.20 Box Inlet Drop Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-56
Figure 8.21 Riprap Apron Plan View . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-58
Figure 8.22 Profile of Riprap Basin . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-60
Figure 8.23 Half Plan of Riprap Basin . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-60
Figure 8.24 Dimensionless Rating Curves for the Outlets of Rectangular Culverts . . . . . . . 8-62
Figure 8.25 Dimensionless Rating Curves for the Outlets of Circular Culverts . . . . . . . . . . . 8-63
Figure 8.26 Distribution of Centerline Velocity for Flow from Submerged Outlets. . . . . . . . . 8-66
Figure 8.27 Typical Stilling Basin. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-68
18
Figure 8.28
Figure 8.29
Figure 8.30
Figure 8.31
Figure 8.32
Figure 8.33
Figure 8.34
Figure 8.35
Figure 8.36
Figure 8.37
Figure 8.38
Figure 8.39
Figure 8.40
Figure 8.41
Figure 8.42
Figure 8.43
Figure 8.44
Figure 8.45
Figure 8.46
Figure 8.47
9 STORMWATER STORAGE
Figure 9.1 Isopluvial 100-Year, 2-Hour Precipitation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-6
Figure 9.2 Flood Routing (Inflow and Outflow Hydrograph). . . . . . . . . . . . . . . . . . . . . . . . . . 9-7
Figure 9.3 Rectangular Concrete Channel Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-10
Figure 9.4 Examples of Primary Outlet Structures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-11
Figure 9.5 Orifice Plate Detail . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-12
Figure 9.6 Typical Drywell Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-14
Figure 9.7 Typical Drywell Surface Treatments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-15
Figure 9.8 Typical Section of a Stormwater Storage Facility Embankment Dam . . . . . . . . 9-24
Figure 9.9 Stormwater Storage Facility Recreation Elements . . . . . . . . . . . . . . . . . . . . . . . 9-32
Figure 9.10 Typical Cross Section of Stormwater Storage Facility w/Recreation Elements . 9-32
Figure 9.11 Storage Components of a Dual Purpose Stormwater Storage Facility. . . . . . . . 9-36
Figure 9.12 Sediment Trap Concept . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-37
10 PUMP STATIONS
Figure 10.1 System-Head Curves for a Fluctuating Static Pumping Head . . . . . . . . . . . . . . 10-5
Figure 10.2 Total Static Head . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-6
Figure 10.3 Pump Operating Point in a Given Piping System . . . . . . . . . . . . . . . . . . . . . . . . 10-7
11 SEDIMENTATION
Figure 11.1 Bed Forms and Flow Regimes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-13
Figure 11.2 Lanes Relationship . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-17
Figure 11.3 Profiles Showing Headcut Migration, San Juan Creek, California . . . . . . . . . . 11-30
Figure 11.4 Non-Adverse Impact When Base Condition is Subject to Natural Erosion. . . . 11-34
Figure 11.5 Non-Adverse Impact When Base Condition is Subject to Natural Deposition . 11-35
Figure 11.6 Relationship of Sieve Diameter and Fall Velocity . . . . . . . . . . . . . . . . . . . . . . . 11-41
Figure 11.7 Cumulative Semilogarithmic Size-Gradation Curve . . . . . . . . . . . . . . . . . . . . . 11-42
Figure 11.8 Initial Bulk Specific Weight for Sediment Deposits . . . . . . . . . . . . . . . . . . . . . . 11-47
19
20
Hydraulics: Introduction
1 INTRODUCTION
TABLE OF CONTENTS
1
INTRODUCTION
1.1
PURPOSE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1
1.2
BACKGROUND. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
1.3
SCOPE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
1.3.1
Introduction ................................................................................................. 1-3
1.3.2
Hydrology .................................................................................................... 1-3
1.3.3
Street Drainage ........................................................................................... 1-3
1.3.4
Storm Drains ............................................................................................... 1-3
1.3.5
Culverts and Bridges ................................................................................... 1-3
1.3.6
Open Channels ........................................................................................... 1-4
1.3.7
Hydraulic Structures .................................................................................... 1-4
1.3.8
Stormwater Storage Facilities ..................................................................... 1-5
1.3.9
Pump Stations ............................................................................................. 1-5
1.3.10 Sedimentation ............................................................................................. 1-5
1.4
SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
1.4.1
Street Drainage ........................................................................................... 1-7
1.4.2
Storm Drains & Culverts.............................................................................. 1-7
1.4.3
Open Channels ........................................................................................... 1-8
1.4.4
Hydraulic Structures .................................................................................... 1-8
1.4.5
Stormwater Storage .................................................................................... 1-9
1.5
SUPPLEMENTAL DISCIPLINES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-10
1.5.1
Geotechnical Engineering ......................................................................... 1-10
1.5.2
Structural Engineering............................................................................... 1-10
1.5.3
Environmental Expertise ........................................................................... 1-11
1.6
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11
1.1
PURPOSE
The objective of the Drainage Design Manual for Maricopa County, Hydraulics (Hydraulics Manual) is to provide criteria and design guidance for storm drainage facilities in Maricopa County.
There are two reasons to develop such a manual: 1) it provides a convenient source of technical
information that is specifically tailored to the unique hydrologic, environmental, and social character of Maricopa County; and 2) it provides a consistent set of criteria that, when used by the
local governing agencies and the land development community, will result in uniform drainage
practices throughout the county. Use of the Hydraulics Manual will result in improved hydraulic
performance of drainage facilities, uniformity in design practices across jurisdictional boundaries,
1-1
Hydraulics: Introduction
and reduction of conflict between the regulatory agencies and the land development community.
Recommended policy and standard requirements are provided in a separate volume and are
jurisdictional specific. That is, each jurisdictional entity (municipal or county) will have its own
policies and standards. In many cases, these may be the same or only slightly modified for each
jurisdiction. For this reason, the user is encouraged to review the policies and standards for the
jurisdiction in which the project is located.
1.2
BACKGROUND
The first edition of this manual was produced by a team of consultants and the Flood Control District of Maricopa County. Beginning in 1987, the manual was developed through a highly interactive process involving work groups for each major topic. The work groups were composed of the
engineering consultant, the Flood Control District, representatives of the various communities in
Maricopa County, and representatives of home builders and land developers. The work groups
were charged with advising the consultant about applicability of technical criteria, special problem areas to be addressed, and resolving conflict over potential differences in drainage standards between communities.
The first edition was made available to the public in 1991. By that time, several communities had
policies, standards, criteria, and/or guidelines already in place. As a result, many communities
elected to utilize this manual in conjunction with their own policies, criteria, etc.
In 1998, the City of Phoenix, which was in the process of updating its drainage manual, started a
collaborative effort with the Flood Control District of Maricopa County to meld their drainage manuals. The purpose was threefold. First, various technical aspects of both the City and Countys
manuals required updating due to advances in the engineering science and further experience
with applications unique to Maricopa County. Second, advances in computer technology provided the opportunity to develop a living document that would be posted on the internet that
encompassed unique engineering software for the design/evaluation of drainage facilities.
Thirdly, Volumes I (Hydrology) and II (Hydraulics) of the Drainage Design Manual for Maricopa
County, included recommended uniform policy requirements. As identified above, several communities had policies that varied, however slightly, from the recommended uniform policies. This
third edition has afforded the opportunity for individual jurisdictional entities to have their own policies and standards to suit their particular needs within the confines of federal and state laws/regulatory requirements. Thus, the Hydrology and Hydraulics Manuals serve as technical manuals,
thereby affording each community flexibility in setting policies.
1.3
SCOPE
The Drainage Design Manual for Maricopa County, Hydraulics, is divided into ten chapters that
address the major subject areas of hydraulic design. The intent of this manual is to provide general design guidance for designs that are common to the Maricopa County environment. Com-
1-2
Hydraulics: Introduction
plex designs requiring specific expertise are not included in this manual; however, where design
exceeds the scope of this manual, the user is referred to documentation appropriate for that
design. The following sections briefly summarize each of the chapters in the manual.
1.3.1 Introduction
Chapter 1 defines the purpose, background, and scope of the manual along with a brief summary
of each chapter. It also includes a discussion of public safety associated with drainage structures.
1.3.2 Hydrology
Chapter 2 provides an overview of the hydrology criteria for drainage structures; the flood hydrology that is recommended for use in Maricopa County is contained in the Hydrology Manual. That
manual provides for the use of the Rational Method for small, uniform watersheds, and for use of
the Unit Hydrograph Method for larger watersheds with diverse surface conditions. The Hydrology Manual provides design rainfall criteria that have been developed specifically for Maricopa
County, rainfall loss methods that are based on the best practical technology that is available for
estimating surface retention losses and infiltration rates, and unit hydrograph procedures that
have been selected and developed for the various land-uses in Maricopa County.
1-3
Hydraulics: Introduction
(HDS-5), Hydraulic Design of Highway Culverts (FHWA, 1985). Some brief guidelines are presented to follow when designing inverted siphons. The design of bridges requires special expertise and experience in regard to hydraulic analyses, design of flow training works, and estimates
of pier and abutment scour. Therefore, only an overview of the hydraulic analyses for bridge
openings is presented.
1-4
Hydraulics: Introduction
1.3.10 Sedimentation
Chapter 11 provides an overview of sediment transport theory. There is a general discussion of
scour and sedimentation. It provides basic concepts of sedimentation engineering and analytical
methods and design procedures for sediment yield and scour estimation in support of the goal of
minimizing maintenance. It identifies considerations to be taken in the design of culverts,
bridges, channel, and stormwater storage facilities to minimize maintenance from scour and sedimentation. It is not intended to be all-inclusive, but instead, its purpose is to identify the issues
and provide references for further consideration by the design engineer.
1.4
SAFETY
During storm events, people are known to intentionally or inadvertently enter water that is dangerous during flood conditions. Or, worse, purposely boat or float in drainage facilities during high
runoff levels. It is not possible to develop drainage facilities that are without hazard, that will preclude people from doing unintelligent acts, and that will also be hydraulically efficient. These
objectives are, for the most part, mutually exclusive. However, reasonable levels of protection
can be provided to people exercising reasonable judgement even when the structure is performing its primary function, i.e., efficiently passing storm water.
1-5
Hydraulics: Introduction
An overriding goal of any public improvement project is to protect, maintain, and enhance the
public health, safety and general welfare by establishing requirements and procedures to control
the adverse affects of stormwater runoff and pollution.
The issue of safety includes the following principles:
Stormwater naturally accumulates, frequently in amounts that present hazards to property, traffic, and life and health.
Traffic
Property
Public access and safety are inherent elements in the design of all drainage facilities. These elements are of primary importance, particularly in the case of multiple-use facilities where public
use is encouraged in areas subject to potential flooding. The primary factors associated with
safety at stormwater storage or conveyance facilities are user education, advance warning,
potential water depth/velocity, slopes, escape routes from flooded areas, and time to drain.
These factors can be addressed in two ways. The first relates to the need to identify and communicate potential hazards to the public. For example, with proper signage, users can be made
aware of the existence of potential hazards, such as flooding, high velocity flows, etc. User education is a fundamental element in safety design for a stormwater facility. Clear, concise signage
with illustrative graphics can inform the public of the primary flood control purpose of the facility
and describe the various features and their potential danger during a flood.
The second relates to the design of the facility to include safety devices that can be readily maintained. Appropriate steps should be taken to mitigate potentially dangerous conditions. Where
the dangerous condition cannot be prevented, appropriate measures should be implemented to
keep users away from hazardous locations. Advance warning (alarms or lights triggered by
upstream water levels) should be considered for multiple-use facilities, particularly where flash
flooding and rapid basin inflow is possible.
Safety devices can be divided into two types:
Devices that Limit or Deter Access
1-6
Fencing
Guard rails
Warning signs
Safety barriers
Hydraulics: Introduction
Safety racks (to prevent persons already in a flood hazard from passing to an area of
more severe hazard)
An important distinction between these two categories is that devices that permit escape, may
also impede the flow of stormwater into or through drainage facilities.
Safety devices for drainage facilities should be considered for both dry weather and runoff conditions. Dry weather hazards include traffic and personal safety. Examples of traffic hazards
include improper placement of guardrails on structures, unprotected drops at structures located
near roads, and grading, all of which promote vehicle rollovers. Dry weather hazards include
vertical drops or walls that may present hazards to the public that would be attractive to them for
unsafe recreation.
The basic concept of this proposed approach to safety is to apply more restrictive measures as
hazards increase. The primary purpose for constructing drainage facilities is the efficient conveyance of stormwater to minimize property damage and to permit traffic flow across and parallel to
drainageways; therefore, safety in this context refers to protection from life and health hazards.
Safety considerations by hydraulic topic are enumerated below:
1-7
Hydraulics: Introduction
Access barriers serve a similar safety function as trashracks. It is rare that cost-effective access
barriers and trash collectors can be retroactively added without a reduction of intended system
design capacity.
When any of the following conditions are met, trashracks should be required on the entrances
and access barriers on outlets to all conduits or other hydraulic structures:
When a conduit or hydraulic structure outfalls into a channel with side slopes steeper than
4(H): 1(V) for hydraulically smooth (concrete and soil cement) banks, 3(H): 1(V) for riprap
linings, 2(H): 1(V) gabion embankments, and 1(H): 1(V) stepped side slopes.
Conduits and hydraulic structures with a cross sectional area of 20 square feet or less.
Conduits and hydraulic structures with a cross sectional area greater than 20 square feet
and longer than 200 feet in length.
Conduits and hydraulic structures being used as outlets from multiple-use detention facilities.
Conduits and hydraulic structures with sufficient bend that the opposite ends cannot be
clearly seen.
Flap gates can be considered for substitution for access barriers on conduit outlets when it can
be shown that sedimentation will not prevent the flap gate from opening or that the design of the
outlet structure will reduce downstream sedimentation that would prevent the flap gate from
opening.
1-8
Hydraulics: Introduction
vided to identify the potential hazard of flooding or dangerous flow measures to the public. Second, appropriate measures should be designed to keep the public away from hazardous
locations. For example, vertical drop structures should not exceed 2.5 feet in height, and adequate fencing or railings should be provided along all other walls, such as wing walls or training
walls.
1-9
Hydraulics: Introduction
A properly designed trashrack can prevent clogging by debris as well as prevent a person from
being swept into the outlet structure and pipe. In addition, where hydraulic conditions at the outlet
structure can lead to the formation of a vortex, the design should include anti-vortex protection. It
is important to note, however, that an outlet structure is not a safe structure during flood conditions, whether it is a horizontal pipe outlet or a riser type structure mounted to a horizontal pipeline. Powerful inlet velocities can draw a person underwater at the outlet structure regardless of
the existence of a trashrack or grate. Signage is important to alert the public of this danger. In
addition, trashracks should be designed to prohibit, to the extent practical, a small child being
forced through the openings.
All site furnishings, such as benches, trash receptacles, and picnic tables should be secured to
prevent them from becoming waterborne-debris that could clog the outlet structure.
Safety should also be considered downstream of outlet structures. Release flows, even though
they may be controlled, can present a hazard. Specific conditions downstream of an outlet should
be evaluated in terms of safety. To protect the public, structural walls should have fencing or railing along the top of an outlet structure.
1.5
SUPPLEMENTAL DISCIPLINES
1-10
Hydraulics: Introduction
1.6
REFERENCES
Phillips, J.V., and Tadayon, S., 2006, Selection of Mannings roughness coefficient for natural
and constructed vegetated and non-vegetated channels, and vegetation maintenance plan
guidelines for vegetated channels in Central Arizona: U.S. Geological Survey Scientific
Investigations Report 2006-5108, 41 p.
United States Department of Transportation, Federal Highway Administration, 1984, Drainage
of Highway Pavements, Hydraulic Engineering Circular No. 12.
, 1985, Hydraulic Design of Highway Culverts, Hydraulic Design Series No.5.
1-11
Hydraulics: Introduction
1-12
Hydraulics: Hydrology
2 HYDROLOGY
TABLE OF CONTENTS
2
HYDROLOGY
2.1
METHODOLOGY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1
2.2
CRITERIA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-2
2.3
DRAINAGE PLANNING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-2
2.4
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3
2.1
METHODOLOGY
The determination of flood hydrology for designing stormwater facilities in Maricopa County is to
be made using one of the following:
Existing studies of record that have been approved by the jurisdiction. Such studies
include flood insurance studies, Area Drainage Master Studies and Plans, and design
reports for adjacent facilities.
If appropriate existing information is not available, then the procedures set forth in the
Drainage Design Manual for Maricopa County, Hydrology Manual (FCDMC, 2008), hereinafter referred to as the Hydrology Manual are to be used.
Peak flow rates and volumes from studies or reports of record should be checked for reasonableness using the procedures set forth in Chapter 8 Indirect Methods of the Hydrology Manual. Use
of historical data of record and deviations from the procedures in the Hydrology Manual require
prior approval from the jurisdictional agency and/or the Flood Control District of Maricopa County
(FCDMC) before proceeding with the determination of design hydrology.
It is not the intent of the Hydrology Manual to inhibit sound, innovative analysis, utilization of
superior technology, or the development of improved techniques. Therefore, the investigation,
development, and use of the best practical technology for flood hydrology is strongly encouraged
in all situations.
The selection of the procedure used to determine the design flood hydrology is dependent upon
the intended application. For small urban watersheds (defined as less than 160 acres and having
fairly uniform land use), the use of the Rational Method is acceptable. Use of this method will only
produce peak discharges and it should not be used if a complete runoff hydrograph is needed,
such as for the routing of flow through a detention facility. For larger, more complex watersheds
or drainage networks, a rainfall-runoff model should be developed. The Hydrology Manual pro-
2-1
Hydraulics: Hydrology
vides guidance in the development of such a model and the estimation of the necessary input
parameters to the model.
Although not necessarily required, the use of the U.S. Army Corps of Engineers' HEC-1 Flood
Hydrology Program (USACE, 1998) facilitates the use of the procedures that are contained in the
Hydrology Manual, which was written to supplement the HEC-1 User's Manual.
All of the hydrology that is required for the design of stormwater storage facilities that are normally encountered can be performed by using the HEC-1 program. The design and performance
of pump stations cannot normally be satisfactorily performed using the simplified procedures that
are incorporated in the HEC-1 program. Although the inflow hydrograph to a pump station can be
adequately developed with HEC-1, the performance and design of pump stations will often
require the use of specialized programs. Furthermore, HEC-1 does not efficiently model street
drainage/storm drain systems.
2.2
CRITERIA
The Hydrology Manual is to be used to develop the design discharge for storms of frequencies
up to and including the 100-year event. Section 2.1.2 of the Hydrology Manual lists the different
durations to be analyzed depending upon the size of the drainage area.
All development should make provisions to retain the peak flow and volume of runoff from rainfall
events up to and including the 100-year, 2-hour duration storm falling within the boundaries of the
proposed development. The criteria to be applied is provided in the Policies and Standards Manual for the local jurisdiction. Refer to the Uniform Drainage Policies and Standards for Maricopa
County, Arizona (FCDMC, 2007) for criteria for unincorporated Maricopa County.
2.3
DRAINAGE PLANNING
Drainage planning shall be done in the earliest stages of the planning process. A drainage plan
shall incorporate the hydrologic analysis for on-site and off-site runoff and outline the recommended plan for handling stormwater runoff.
Drainage planning can be encountered on both basin-wide and local scales. When undertaking a
basin-wide plan, the designer must comprehensively evaluate practical alternatives to find the
most cost-effective solution for the general public. When preparing drainage plans for local development, the designer shall illustrate conformance with basin-wide drainage plans where they
exist, or shall demonstrate that the plan will not increase extraordinarily the cost of providing
basin-wide drainage for the local agency or the FCDMC.
The planning process begins with the conceptual layout of the drainage system, which includes
both large and small drainage facilities. All drainageway entrance and exit points in the proposed
development must remain in the original location and, as near as possible, in the original condition.
2-2
Hydraulics: Hydrology
In many areas about to be urbanized, the runoff has been so minimal that natural channels do
not exist. However, surface depressions normally exist and will provide an excellent basis for the
initial siting of open channels. This condition is also true for open channels that are to be used
primarily for road or highway drainage.
Drainage plans illustrate selected alternatives, including the footprint of facilities or land uses,
approximate sizes, and physical impact on the land. General requirements for structures and
their overall size and impacts are also determined during the master planning phase; however,
detailed selection of structure types, sizing of riprap, structural design, and selection and detailing of peripheral elements (inlets, trashracks, fencing, etc.) are completed in later phases using
the criteria outlined in this manual.
2.4
REFERENCES
Flood Control District of Maricopa County (FCDMC), 2007, Uniform Drainage Policies and
Standards for Maricopa County, Arizona.
, 2008, Drainage Design Manual for Maricopa County - Hydrology, 4th Edition.
U.S. Army Corps of Engineers (USACE), 1998, HEC-1 Flood Hydrograph Package, User's
Manual.
2-3
Hydraulics: Hydrology
2-4
3 STREET DRAINAGE
3
3
TABLE OF CONTENTS
3
STREET DRAINAGE
3.1
SYMBOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
3.2
INTRODUCTION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3
3.2.1
General Discussion ..................................................................................... 3-3
3.2.2
Source of Data ............................................................................................ 3-3
3.3
PROCEDURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3
3.3.1
General Considerations .............................................................................. 3-3
3.3.2
Applications and Limitations........................................................................ 3-9
3.4
APPLICATION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-32
3.4.1
Design Procedures.................................................................................... 3-32
3.4.2
Design Examples ...................................................................................... 3-33
3.5
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-47
3.1
SYMBOLS
a
a
A
Ag
Co
Cw
d
di
do
E
Orifice coefficient
Weir coefficient
Depth of flow at curb measured from the normal cross slope, ft (i.e., d = TSx)
Hydraulic efficiency of an inlet shorter than the length required for total
interception (Qi /Q)
Eo
g
H
L
LT
n
Height of curb opening catch basin, curb-opening orifice, or orifice throat width, ft
3-1
P
Q
Qcap
Qi
Perimeter of the grate, disregarding bars and side against the curb, ft
Qs
Qt
Qw
rH
Rf
Rs
S
Hydraulic radius, ft
Se
Sx
Sw
Sw
Cross slope of a depressed gutter section measured from the normal cross slope
of the pavement (a/W), ft/ft
T
Ts
V
Vo
W
Y
Z
Depth of flow, ft
3-2
3.2
INTRODUCTION
3.3
PROCEDURES
3-3
Grated or gutter catch basins refers to an opening in the gutter covered by one or more grates
through which water falls. As with other catch basins, grated catch basins may be depressed or
undepressed and are more efficient than curb-opening catch basins when located on a continuous grade. When grated catch basins are used, the engineer should design them to optimize
hydraulic efficiency, bicycle and pedestrian safety, and structural adequacy. Grated catch basins
shall not extend into traffic lanes.
The interception capacity of a combination catch basin on a continuous grade consisting of a
curb-opening and grate placed side by side is not appreciably greater than that of the grate
alone. The interception capacity is computed using only the grate for this situation. A combination catch basin with the curb-opening longer than the grate has additional capacity. The curbopening in such an installation intercepts debris which might otherwise clog the grate and has
been termed a sweeper by some. A combination inlet with a curb-opening upstream of the
grate has an interception capacity equal to the sum of the two inlets, except that the frontal flow
and thus the interception capacity of the grate is reduced by interception of the curb.
In a sump, combination inlets are very desirable. The curb-opening provides a relief if the grate
should become clogged.
A slotted drain is a slot opening in the pavement which intercepts sheet flow and conveys it
through a pipe (normally corrugated steel). Slotted drains are most effective when street slopes
are shallow. Slotted drains can be used on curbed or uncurbed sections and offer little interference to traffic operations.
3-4
FIGURE 3.1
CATCH BASIN INLETS
3-5
Storage Facilities
In some areas it may be favorable to retain street drainage within retention facilities. This is
acceptable with approval from the appropriate governmental agency. Please refer to Chapter 8
for storage facility design.
3-6
Roadside ditches are commonly used in rural areas to convey runoff from the highway pavement,
and from areas which drain toward the highway. Where practicable, the flow from major areas
draining toward curbed highway pavements should be intercepted by ditches.
These examples show the minimum required
inlets. Additional inlets may be necessary based
upon allowable carrying capacity of gutters.
FIGURE 3.2
TYPICAL STREET INTERSECTION DRAINAGE TO STORM DRAIN SYSTEM
The following criteria pertain to the design of open channels along roadsides. For additional criteria for open channels, see Chapter 6.
3-7
Roadside ditches adjacent to public streets are discouraged in urban areas and require approval
from the governing agency. When they are allowed, adhere to the criteria outlined in this section.
Depth of flow in roadside ditches for the design storm shall be limited to preclude saturation of
the adjacent roadway subgrade. Where curbs exist and roadside ditches are used in lieu of
storm drains, catch basins or scuppers should be provided as needed to drain the pavement into
the drainage ditch.
Geometric considerations in the design of channel cross sections should incorporate hydraulic
requirements for the design discharge, safety, minimization of right-of-way acquisition, economy
in construction and maintenance, and good appearance.
Channel side slopes should be as mild as practical and should be no steeper than 4:1 where terrain and right-of-way permit. The advantages of mild slopes are that the potential for erosion and
slides is lessened, the cost of maintenance is reduced, and the safety of errant vehicles is
enhanced. Safety considerations are subject to the requirements of the local jurisdiction.
Trapezoidal channel bottoms should be a minimum of 4 feet wide for maintenance purposes. Vshaped channels may also be used when approved by the governing agency.
Local soil conditions, flow depths, and velocities within the channel are usually the primary
hydraulic considerations in channel geometric design; however, terrain and safety considerations
have considerable influence. Steeper side slopes of rigid, lined channels may be more economical and will improve the hydraulic flow characteristics. The use of steeper slopes is normally limited to areas with limited right-of-way where the hazard to traffic can be minimized through the
use of guardrails or parapets.
Rural Crown Ditch: In mountainous terrain where large cuts are required, crown ditches constructed on top of the cut embankment will intercept runoff preventing it from eroding the face of
the cut slope. A typical crown ditch is shown in Figure 3.3.
FIGURE 3.3
CROWN DITCH
3-8
(3.1)
Flow area, sq ft
rH
Hydraulic radius, ft
When the allowable pavement spread has been determined, the theoretical gutter carrying
capacity shall be computed using the modified Mannings formula as expressed in Equation (3.2)
or shown on Figure 3.4.
0.56
Q t = ---------- S x1.67 S 0.5 T 2.67
n
where:
(3.2)
Qt
Sx
3-9
FIGURE 3.4
NOMOGRAPH FOR TRIANGULAR GUTTERS
(USDOT, FHWA, 1984, HEC-12, CHART 3)
3-10
For gutters with composite cross-slopes, pavement spread is determined using the relationships
presented in Figure 3.5.
FIGURE 3.5
COMPOSITE CROSS-SLOPE GUTTER SECTION
(3.3)
Qs
Ts
S
Sx
=
=
Sw Sx
E o = 1 1 + ------------------------------------------------
2.67
Sw Sx
1 + -------------- 1
T- 1
---
W
where:
(3.4)
Eo
Sx
W
T
Sw
=
=
=
Width of gutter, ft
Width of flow, spread, ft
depression
---------------------------------------------Cross-slope of a depressed gutter ( S x + gutter
), ft/ft
W
3-11
FIGURE 3.6
RATIO OF FRONTAL FLOW TO TOTAL GUTTER FLOW
(USDOT, FHWA, 1984, HEC-12, CHART 4)
Qs
Q = ------------------( 1 Eo )
(3.5)
(3.6)
Qw = Q Qs
where:
3-12
Qw
Qs
where:
1 0.6
--------
nS
x
0.42 0.3
(3.7)
Sx
3-13
FIGURE 3.7
CURB OPENING AND SLOTTED DRAIN INLET LENGTH FOR TOTAL INTERCEPTION
(USDOT, FHWA, 1984, HEC-12, CHART 9)
3-14
The efficiency (E) of curb-opening catch basins shorter than the length required for total interception is:
L 1.8
E = 1 1 -----
Lt
where:
(3.8)
L =
Lt =
Figure 3.8 provides a solution of Equation (3.8) and the equation is applicable with either straight
cross slopes or compound cross slopes.
FIGURE 3.8
CURB OPENING AND SLOTTED DRAIN INLET INTERCEPTION EFFICIENCY
(USDOT, FHWA, 1984, HEC-12, CHART 10)
3-15
The length of catch basin required for total interception by depressed curb-opening catch basins
or curb openings in depressed gutter sections can be found by using an equivalent cross slope,
Se. Se can be calculated using Equation (3.9).
S e = S x + S w E o
where:
(3.9)
Sw
Eo
Cross slope of the gutter (at the inlet) measured from the
cross slope of the pavement, ft/ft ( S w = a 12W see Figure
3.7)
Ratio of flow in the depressed section to total gutter flow
Sx
Eo is the ratio of flow in the depressed section to the total gutter flow, and Sw is the cross slope of
the gutter measured from the cross slope of the pavement, Sx. Figure 3.9 can be used to determine the spread, and then Figure 3.6 can be used to determine Eo.
FIGURE 3.9
FLOW IN COMPOSITE GUTTER SECTIONS
(USDOT, FHWA, 1984, HEC-12, CHART 5)
3-16
The length of curb-opening required for total interception can be significantly reduced by increasing the cross slope or the equivalent cross slope. The equivalent cross slope can be increased
by use of a continuously depressed gutter section or a locally depressed gutter section.
Using the equivalent cross slope, Se Equation (3.7) becomes:
L t = 0.6Q
1 0.6
--------
nS
e
0.42 0.3
(3.10)
Figure 3.7 and Figure 3.8 are applicable to depressed curb-opening catch basins using Se rather
than Sx.
Sumps - The capacity of a curb-opening catch basin in a sump depends on water depth at the
curb, the curb opening length, and the height of the curb opening. The catch basin operates as a
weir for depths of water up to the curb-opening height and as an orifice at depths greater than 1.4
times the opening height. At water depths between 1.0 and 1.4 times the opening height, flow is
in a transition stage.
The weir location for a depressed curb-opening catch basin is at the edge of the gutter, and the
effective weir length is dependent on the width of the depressed gutter and the length of the curbopening. The weir location for a curb opening catch basin that is not depressed is at the lip of the
curb-opening, and its length is equal to that of the curb-opening catch basin.
The equation for the interception capacity of a depressed curb opening-catch basin operating as
a weir is:
Q i = C w ( L + 1.8W )d
where:
1.5
(3.11)
Qi
Cw
The weir equation is applicable to depths at the curb approximately equal to the height of the
opening plus the depth of the depression. Thus, the limitation on the use of Equation (3.11) for a
depressed curb opening catch basin is:
3-17
a
d < h + -----12
(3.12)
where:
Experiments have not been conducted for curb opening catch basins with a continuously
depressed gutter, but it is reasonable to expect that the effective weir length would be as great as
that for a catch basin in a local depression. Use of Equation (3.11) will yield conservative estimates of the interception capacity.
The weir equation for curb opening catch basins without depression (W = 0) becomes:
Q i = C w Ld
15
where:
(3.13)
Cw
3.0
Depth of flow, ft
where:
0.5
(3.14)
Co
do
Equation (3.14) is applicable to depressed and undepressed curb opening catch basins and the
depth at the catch basin includes any gutter depression.
3-18
Height of the orifice in Equation (3.14) assumes a vertical orifice opening. As illustrated in Figure
3.10, other orifice throat locations can change the effective depth on the orifice and the dimension ( d i h 2 ) . A limited throat width could reduce the capacity of the curb-opening catch basin
by causing the catch basin to go into orifice flow at depths less than the height of the opening.
FIGURE 3.10
CURB OPENING CATCH BASIN INLETS
(Modified from: USDOT, FHWA, 1984, HEC-12, Figure 21)
Figure 3.11 provides solutions for Equations 3.11 and 3.14 for depressed curb-opening catch
basins, and Figure 3.12 provides solutions for Equations 3.13 and 3.14 for curb-opening catch
3-19
basins without depression. Figure 3.13 is provided for use for curb openings with inclined or vertical orifice throats.
FIGURE 3.11
DEPRESSED CURB OPENING INLET CAPACITY IN SUMP LOCATIONS
(USDOT, FHWA, 1984, HEC-12, Chart 12)
3-20
FIGURE 3.12
CURB OPENING INLET CAPACITY IN SUMP LOCATIONS
(USDOT, FHWA, 1984, HEC-12, Chart 13)
3-21
FIGURE 3.13
CURB OPENING INLET CAPACITY FOR INCLINED AND VERTICAL ORIFICE THROATS
(USDOT, FHWA, 1984, HEC-12, Chart 14)
3-22
The ratio of frontal flow to total gutter flow, E o for a straight cross slope is:
Qw
W 2.67
E o = ------= 1 1 -----
Q
T
where:
(3.15)
Qw
Figure 3.6 provides a graphical solution of Eo for either straight cross slopes or depressed gutter
sections.
The ratio of side flow, (Qs) to total gutter flow (Q) is:
Qw
Q
------s = 1 ------= 1 Eo
Q
Q
where:
(3.16)
Qs
Qw
The ratio of frontal flow intercepted to total frontal flow, Rf, is expressed:
R f = 1 0.09 ( V V o )
where:
(3.17)
Rf
Vo
This ratio is equivalent to frontal flow interception efficiency. Figure 3.14 provides a solution of
Equation (3.17) which takes into account grate length, bar configuration and gutter velocity at
which splash-over occurs. The gutter velocity needed to use Figure 3.14 is total gutter flow
divided by the area of flow.
3-23
FIGURE 3.14
GRATE INLET FRONTAL FLOW INTERCEPTION EFFICIENCY
(USDOT, FHWA, 1984, HEC-12, Chart 7)
3-24
The ratio of side flow intercepted to total side flow, Rs, or side flow interception efficiency, is
expressed:
1
R s = ----------------------------1.8
0.15V
1 + -------------------2.3
Sx L
where:
(3.18)
Sx
Length of grate, ft
3-25
FIGURE 3.15
GRATE INLET SIDE FLOW INTERCEPTION EFFICIENCY
(USDOT, FHWA, 1984, HEC-12, Chart 8)
3-26
(3.19)
The first term on the right side of Equation (3.19) is the ratio of intercepted frontal flow to total
gutter flow, and the second term is the ratio of intercepted side flow to total side flow. The second
term is insignificant with high velocities and short grates.
The interception capacity (Qi) of a grate catch basin on grade is equal to the efficiency of the
grate multiplied by the total gutter flow:
Q i = EQ = Q [ R f E 0 + R s ( 1 E 0 ) ]
(3.20)
Sump - The efficiency of catch basins in passing debris is critical in sump locations because all
runoff which enters the sump must be passed through the catch basin. Total or partial clogging of
catch basins in these locations can result in hazardous ponding conditions. Grate catch basins
alone are not recommended for use in sump locations because of the tendencies of grates to
become clogged. Combination catch basins or curb-opening catch basins are recommended for
use in these locations.
A grate catch basin in a sump location operates as a weir to depths dependent on the bar configuration and size of the grate and as an orifice at greater depths. Grates of larger dimension and
grates with more open area, that is, with less space occupied by lateral and longitudinal bars, will
operate as weirs to greater depths than smaller grates or grates with less open area.
The capacity of grate catch basins operating as weirs is:
Q i = C w Pd
1.5
where:
(3.21)
Cw
0.5
(3.22)
Co
Ag
3-27
Use of Equation (3.22) requires the clear opening area of the grate. Tests of three grates for the
Federal Highway Administration showed that for flat bar grates, such as P-1-7/8-4 and P-1-1/8
grates, the clear opening is equal to the total area of the grate less the area occupied by longitudinal and lateral bars.
Figure 3.16 is a plot of Equation (3.21) and Equation (3.22) for various grate sizes. The effects of
grate size on the depth at which a grate operates as an orifice is apparent from the chart. Transition from weir to orifice flow results in interception capacity less than that computed by either the
weir or the orifice equation. This capacity can be approximated by drawing in a curve between
the lines representing the perimeter and net area of the grate to be used.
FIGURE 3.16
GRATE INLET CAPACITY IN SUMP CONDITIONS
(USDOT, FHWA, 1984, HEC-12, Chart 11)
3-28
0.5
+ 0.67hL ( 2gd o )
0.5
(3.23)
Qi
Ag
do
Trial and error solutions are necessary for depth at the curb for a given flow rate using Figure
3.11, Figure 3.12, Figure 3.13, or Figure 3.16 for orifice flow.
3-29
0.5
(3.24)
Qi
Width of slot, ft
3-30
0.5
(3.25)
The interception capacity of slotted drain catch basins at depths between 0.2 and 0.4 feet can be
computed by using the orifice equation. The orifice coefficient varies with depth, slot width, and
the length of the slotted drain catch basin.
Figure 3.17 provides the solutions for weir flow, transition flow and orifice flow.
FIGURE 3.17
SLOTTED DRAIN INLET CAPACITY IN SUMP CONDITION
(USDOT, FHWA, 1984, HEC-12, CHART 15)
Guidelines
Inlets in sumps are generally much more efficient and economically justifiable than inlets on a
continuous grade, so the street designer should strive to adjust grades, when practical, to provide sumps for inlets. A sump is created at each intersection of a side street with a major street
where the crown of the side street is extended at least to the quarter point of the major street.
This provides an efficient pick up point. However, on the downstream side of the side street,
3-31
incoming storm drainage will tend to flow on down the major street and bypass a catch basin.
Therefore, where conditions permit, the side street may be depressed for a short distance
upstream from the curb return to provide a second efficient pick up point, if the side street is
bringing a large volume of runoff. Another alternative is multiple catch basins to intercept the
excessive runoff. The most economical alternative shall be used.
To account for a potential reduction of inflow capacity due to clogging, the design of the inlet
should include a factor of safety. Here the area or length required is adjusted by clogging or
reduction factors as set forth by the standards used by the jurisdictional entity. For Maricopa
County, clogging or reduction factors are set forth in the Policies and Standards Manual.
3.4
APPLICATION
This section offers design procedures for street drainage and presents design examples. Equations presented in this chapter shall be used for design purposes. Nomographs presented in this
chapter can be used for design concept evaluations or initial evaluations.
3-32
Determine the total discharge (Q) for the composite gutter section.
Given:
Allowable spread
12 ft
Sx
0.02 ft/ft
Gutter depression
1 inch or 0.0833 ft
Longitudinal Slope
0.008 ft/ft
Gutter Width
1.42 ft
0.015
Cross-slope
(3.3)
1.67
0.5
2.67
0.56
Q s = ------------- 0.02
0.008 10.58
= 2.64 cfs
0.015
Use Figure 3.4 to determine the discharge (Qs). To do this, connect the values for S and Sx with a
straight line that intersects the turning line. Now draw a straight line from the turning line through
the value Ts to the discharge line. Read the value Qsn.
3-33
Q s n = 0.04
0.04
0.04
Q s = ---------- = ------------- = 2.67 cfs
n
0.015
Step 3:
Determine the total discharge (Q) using Equations 3.4 and 3.5.
Sw Sx
E o = 1 1 + ------------------------------------------------
2.67
Sw Sx
1 + -------------- 1
T- 1
---
(3.4)
Sw
0.0787
------ = ---------------- = 3.93
Sx
0.02
12 - = 8.45
T- = -----------1.42
W
By substitution:
3.93
E o = 1 1 + ---------------------------------------------------- = 0.348
3.93 2.67
1
+
----------------- 1
8.45 1
Determine the total discharge using Figure 3.5 and Equation (3.5). To determine the value Eo
using Figure 3.6, begin with the W/T value and go vertically up until you intersect the Sw/Sx value.
Project horizontally to the Eo axis and read value.
E o = 0.33
Use Equation (3.5) to solve for the total discharge using Qs and Eo from Figure 3.4 and Figure
3.6.
Qs
2.67 - = 3.99 cfs say 4 cfs
- = ----------------------Q = ------------------1.0 0.33
( 1 Eo )
3-34
(3.5)
Example 2
Determine the length of a curb-opening inlet on grade for the interception of the gutter flow determined in Example 1.
Given:
4 cfs
Cross-slope
Sx
0.02 ft/ft
Gutter depression
1 inch or 0.0833 ft
Longitudinal Slope
0.008 ft/ft
Gutter Width
1.42 ft
0.015
2 inches or 0.167 ft
S e = S x + S w E o
ft
a- = 0.167ft
----------------- = 0.12 --S w = ---ft
1.42ft
W
E o = 0.35 from Example 1
ft
ft
ft
S e = 0.02 --- + 0.12 --- 0.35 = 0.062 --ft
ft
ft
Step 2:
Using Equation (3.10) solve for length.
L t = 0.6Q
1 - 0.6
------ nS
e
0.42 0.3
(3.10)
3-35
L t = 0.6 4
0.42
0.008
0.3
1
---------------------------------
0.015 0.062
= 16.6 ft
To use Figure 3.7 to determine the length of curb opening, first draw a straight line through the n
and S values to intersect the turning lane. Then draw a straight line from the turning line through
the Se value intersecting the second turning line. From the second turning line draw a straight
line to the Q value. Read the value Lt.
L t = 17 feet
Step 3:
Determine length with a clogging factor of 1.25.
Lt (with clogging factor) = L t 1.25
= 16.6 1.25 = 20.75
Try a curb opening inlet catch basin with a 10-foot wing. Total Length, L = 13 ft .
Step 4:
The curb opening provided is 13 feet; therefore, determine the catch basin efficiency (E), the flow
intercepted (Qi) and the bypass flow.
Use Equation (3.8) to determine the efficiency of the catch basin provided.
L 1.8
E = 1 1 ----
Lt
13 1.8
E = 1 1 ------------= 0.83
20.75
(3.8)
Qi = Q E
Q i = 4 cfs 0.83 = 3.3 cfs
Q bypass = Q Q i
= 4 cfs 3.3 cfs
= 0.7 cfs
To use Figure 3.8 to determine the efficiency, begin with the L/Lt value and go vertically up to the
efficiency curve (E) and then project horizontally to the efficiency value.
E = 0.83
3-36
Example 3
Determine the interception capacity of a single grated inlet on grade for the flow rate determined
in Example 1.
Given:
4 cfs
Qs
Cross slope
Sx
0.02 ft/ft
1 in or 0.0833 ft
Sw
Longitudinal slope
0.008 ft/ft
Gutter width
1.42 ft
0.015
Eo
12 ft
Gutter depression
Cross slope of a depressed gutter ft/ft
Allowable spread
3-37
2
( 0.32 ft 0.21 ft ) 1.42 ft
= ( 0.21 ft 1.42 ft ) + ----------------------------------------------------------------
2
= 0.376 sq ft
Use Q w = VA w to determine velocity
Qw
1.36 cfs = 3.6 fps
------- = V = ------------------------0.376 sq ft
Aw
Step 3:
Determine splash over velocity (Vo) from Figure 3.14.
Length of grate = 3 feet, extend vertically from the length of grate value a line to the
P-1-7/8-4 curve, then extend a line horizontally to the splash-over velocity axis, read value.
V o = 6.1 fps
Step 4:
Using Equation (3.17) or Figure 3.14 determine the ratio of frontal flow intercepted to total frontal
flow.
R f = 1 0.09 ( V V o ) = 1 0.09 ( 3.6 fps 6.1 fps )
(3.17)
With a clogging factor the width of opening perpendicular to flow is 0.5 times the actual width of
the grate. Therefore Rf actual is equal to Rf with clogging R f 0.5 = 0.5 .
To use Figure 3.14 to determine Rf, extend a line vertically from the length of grate value to the P1-7/8-4 curve, then extend a line horizontally to the diagonal V line to the value determined in Step
2 and then vertically down to the Rf axis, read value. Maximum Rf value is equal to 1.
3-38
Step 5:
Using Equation (3.18) or Figure 3.15 determine the ratio of side flow intercepted to total side flow,
applying a 1.25 clogging factor to length of grate, L.
1
1
R s = -------------------------------------- = ------------------------------------------------ = 0.09
1.8
1.8
0.15V
0.15 ( 3.6 )
1 + ---------------------------1 + -------------------------------------L 2.3
3.0 2.3
S x ----------
( 0.02 ) ----------
1.25
1.25
(3.18)
To use Figure 3.15 to determine Rs, extend a line horizontally from the Sx value to the diagonal L
line with the L value adjusted for clogging, extend the line vertically to the diagonal V line with the
V value determined in Step 2, then horizontally extend a line to the Rs axis and read the value.
R s = 0.09
Step 6:
Using Equation (3.19) determine the efficiency of the grate.
E = R f Eo + R s ( 1 E o )
(3.19)
3-39
Example 4
Determine the capacity of a combination curb opening inlet for the flow rate determined in Example 1.
Given:
4 cfs
Cross slope
Sx
0.02 ft/ft
Gutter depression
1 in or 0.0833 ft
Longitudinal slope
0.008 ft/ft
Gutter width
1.42 ft
0.015
14 ft
11 ft
Grate length
3 ft
2 inches or 0.167 ft
Step 1:
Compute the interception capacity (Qic) of the curb opening upstream of the grate.
From Example 2: L t = 16.6 with clogging factor L t = 16.6 1.25 = 20.75
Use Equation (3.8) to determine efficiency of curb opening.
L 1.8
E = 1 1 ----Lt
(3.8)
11 1.8
E = 1 1 ------------= 0.74
20.75
3-40
Q ic = Q E
Q ic = 4 cfs 0.74 = 2.97 cfs say 3 cfs
Step 2:
Determine interception capacity (Qig) of the grate.
Flow to grate Q g = Q Q ic = 4 cfs 3.0 cfs 1.0 cfs
Step 2.1:
By assuming the flow spread Ts calculate the discharge Qs in the paved section adjacent to grate
using the procedure listed in Example 1 Step 2. This is an iterative process.
Assume:
Ts = 4.2 ft
Q s = 0.22 cfs
Step 2.2:
Determine the total discharge following procedures listed in Example 1 Step 3.
Note: Use gutter depression-value at inlet.
ft
0.167
S w = ------------- + 0.02 = 0.138 --ft
1.42
Sw
0.138
------ = ------------- = 6.88
Sx
0.02
T
4.2 + 1.42
----- = ------------------------ = 3.96
W
1.42
6.88
E o = 1 1 + ---------------------------------------------------- = 0.78
2.67
6.88
1 + ----------------- 1
3.96 1
Qs
0.22
- = ------------------------ = 1 cfs
Q t = ------------------( 1 Eo )
( 1 0.78 )
Qt from Step 2.2 equals Qg from Step 2 therefore the assumption of Ts = 4.2 feet in Step 2.1 is
correct. Should Qt not equal Qg, a different value for Ts would need to be assumed.
3-41
Step 3:
Determine flow rate (Qw) in gutter width.
Qw = Q Qs
= 1.0 cfs 0.22 cfs = 0.78 cfs
Step 4:
Determine velocity of flow in gutter width using procedures listed in Example 3, Step 2.
Note: T = T s + W = 4.2 ft + 1.42 ft = 5.62 ft
d 1 = 0.084 ft
d 2 = 0.28 ft
Flow area = 0.26 sq ft
V = 3 fps
Step 5:
Determine splash over velocity (Vo) from Figure 3.14.
V o = 6.1 fps
Step 6:
Determine the ratio (Rf) of frontal flow intercepted to total frontal flow for the grate. Use procedures listed in Example 3, Step 4.
R f = 1.28 if greater than 1, say 1
With a combination curb opening and grate no clogging factor is applied to the grate.
Step 7:
Determine the ratio (Rs) of side flow intercepted to total side flow for the grate. Use procedures
listed in Example 3, Step 5. No clogging factor applied.
R s = 0.19
3-42
Step 8:
Using procedures listed in Example 3, Step 6 determine efficiency of the grate.
E = R f Eo + R s ( 1 E o )
E = ( 1 ) ( 0.78 ) + ( 0.19 ) ( 1 0.78 ) = 0.82
Step 9:
Determine the flow rate (Qig) intercepted by the grate.
Q ig = Q E = 1 cfs 0.82 = 0.82 cfs
Step 10:
Determine the total flow (Qi) intercepted by the combination catch basin.
Q i = Q ic + Q ig = 3.0 cfs + 0.82 cfs = 3.82 cfs
Q bypass = Q Q i = 4 cfs 3.82 cfs = 0.18 cfs
3-43
Example 5
Determine length of curb opening inlet in a sump location.
Given:
4 cfs
Allowable spread
12 ft
Sx
0.02 ft/ft
2 inches or 0.167 ft
Width of gutter
1.42 ft
5 inches or 0.417 ft
Cw
2.3
Cross-slope
Gutter depression at inlet
Weir coefficient
Clogging factor
Step 1:
Determine depth at inlet (di)
di = ( Sx ) ( T )
d i = ( S x ) ( T ) = 0.02 ft/ft 12 feet = 0.24f eet
Step 2:
Check that
ad i < h + ----12
20.24 ft < 0.417 + ----12
0.24 ft < 0.58 ft
Step 3:
Using Equation (3.11) determine length
Q i = C w ( L + 1.8W )d i
3-44
1.5
(3.11)
or
Qi
4 cfs
L = ----------------- 1.8W = ---------------------------------- ( 1.8 ) ( 1.42 feet ) = 12.24 feet
1.5
1.5
Cw di
( 2.3 ) ( 0.24 )
Using Figure 3.11 extend a vertical line up from the discharge rate value to the water depth value
determined in Step 1, read P value.
P = 15
P = L + 1.8W
P 1.8W = L
15 ( 1.8 ) ( 1.42 ) = 12.44 feet
Step 4:
Apply clogging factor to inlet length
L c log ging factor = 12.44 1.25 = 15.55 feet
Example 6
Determine size of a grate inlet in a sump condition.
Given:
2 cfs
Allowable spread
12 ft
Sx
0.02 ft/ft
Cross-slope
Gutter depression
Width of gutter
3-45
Weir coefficient
Cw
3.0
Grate dimensions
3 ft by 2 ft
Clogging factor
Step 1:
Determine depth at inlet (d)
d = ( S x ) ( T ) = 0.02ft/ft 12.0 feet = 0.24
Step 2:
Use Equation (3.21) to solve for P where P is equal to the perimeter of the grate in feet disregarding bars and the length of the side against the curb.
Q i = C w Pd
1.5
(3.21)
Qi
2 cfs - = 5.67 ft
---------------- = P = ----------------------------1.5
1.5
3.0 0.24
Cw d
Using Figure 3.16 extend a vertical line up from the discharge rate value to the water depth value
determined in Step 1, read P value.
P = 5.5 feet
Step 3:
Apply clogging factor to perimeter of grate.
P c log ging factor = 5.67 feet 2 = 11.34 feet
for 2 grates end to end P = 10 ft
for 3 grates end to end P = 13 ft
Use 3 grate inlets or try a different type of catch basin.
3-46
3.5
REFERENCES
Maricopa Association of Governments (MAG), 1979, Uniform Standard Details for Public Works
Construction.
U.S. Department of Transportation (USDOT), Federal Highway Administration, 1984, Hydraulic
Engineering Circular No. 12, Drainage of Highway Pavements. [USDOT Hydraulics WEB
Site]
, 1996, Hydraulic Engineering Circular No. 22, Urban Drainage Design Manual.
3-47
3-48
4 STORM DRAINS
TABLE OF CONTENTS
4
STORM DRAINS
4.1
SYMBOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
4.2
INTRODUCTION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-3
4.3
PROCEDURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-3
4.3.1
General Considerations .............................................................................. 4-3
4.3.2
Applications and Limitations........................................................................ 4-8
4.4
CRITERIA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-25
4.4.1
Main Line Hydraulic Grade Line ................................................................ 4-25
4.4.2
Determination of Controlling Water Surface Elevation .............................. 4-26
4.4.3
Connector Pipe Hydraulic Grade Line....................................................... 4-27
4.5
DESIGN STANDARDS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-27
4.6
DESIGN EXAMPLE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-28
4.7
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-61
4.8
APPENDIX 4-A PRESSURE MOMENTUM ANALYSIS . . . . . . . . . . . . . . . . . . . . . 4-62
4.1
SYMBOLS
Specific energy, ft
EGL
HGL
hb
hf
hi
Headloss at inlet, ft
4-1
hj
hmn
hminor
Minor headlosses, ft
ho
Headloss at outlet, ft
hi
kb
kc
ke
kj
ken
Radius of curvature, ft
Hydraulic radius, ft
Sf
So
Tc
Velocity, ft/sec
4-2
4.2
INTRODUCTION
This chapter describes methodology that should be used for the hydraulic design of a storm drain
system. In this manual, a storm drain system refers to a coordinated group of inlets, underground
conduits, manholes, and various other appurtenances which are designed to collect stormwater
runoff from the design storm and convey to a point of discharge into a major or regional drain outfall. The size of a storm drain system is based on a designated design storm. The design storm is
a storm with a specific storm duration and return period. The design storm will vary from community to community. The designer shall determine the appropriate design storm from the governing
agency.
Storm drains should generally only be considered for minor watercourses. Storm drains typically
are not economical for the flows conveyed within larger watercourses. Therefore, the storm drain
system will collect runoff to a point where storm drains become too large to be economical and
will then discharge into a major or regional watercourse outfall consisting of a man-made channel, or natural watercourse.
The designer of the storm drain system will have to use professional judgement when dealing
with the conflicts that can occur with existing utilities. When the designer has to deviate from the
requirements of this chapter, he or she should contact the governing agency as soon as possible
to explain the situation and agree upon an acceptable solution. This will expedite the design process.
There are many computer programs available to help in the design of storm drain systems.
These programs, however, may determine the various headlosses by methods different than
those presented in this chapter. It is therefore recommended that the designer of any storm drain
system check with the governing agency before using a particular program.
4.3
PROCEDURES
4-3
result when storm runoff exceeds that used for design purposes or simply because junction
losses or manhole/junction losses were underestimated or neglected in the design. In storm
drain systems, junctions in closed conduits can cause major headlosses across the junction. If
these losses are not included in the hydraulic design, the capacity of the conduit may not be adequate for the desired design flow.
For a straight flow through condition at a manhole, pipes should be positioned vertically so that
the crowns are aligned. An offset in the plan is allowable provided the projected area of the
smaller pipe falls within that of the larger. Aligning the crowns of the pipes is the most hydraulically efficient.
When two inflowing laterals intersect in a manhole, the horizontal alignments of those laterals is
important. For example, if two lateral pipes are aligned opposite each other such that the outflows impinge directly upon each other, the magnitude of the losses can be extremely high.
If the installation of directly opposed inflow laterals is necessary, the installation of a deflector, as
shown in Figure 4.1 will result in significantly reduced losses. The research conducted on this
type deflector is limited to the ratios of Do/Di = 1.25. The tests indicate that it would be conservative to assume the coefficient of pressure change at 1.6 for all flow ratios and pipe diameter ratios
when no catch basin is considered, and 1.8 when the catch basin flow is more than 10 percent of
Qo.
Lateral connector pipes should not be located directly opposite; rather, their centerlines should
be separated laterally by at least the sum of the two lateral pipe diameters. Some jurisdictions
require greater separation, and therefore, the design engineer should check jurisdiction specific
standards. Studies have shown that this reduces headlosses as compared to directly opposed
laterals, even with deflectors. Sufficient data has not been collected to determine the effect of offsetting laterals vertically.
Jets issuing from the upstream and lateral pipes must be considered when attempting to shape
the inside of manholes. Tests for full flow revealed that very little, if anything, is gained by shaping
the bottom of a manhole to conform to the pipe invert. Shaping of the invert may even be detrimental when lateral flows are involved, as the shaping tends to deflect the jet upwards, causing
unnecessary headloss. From a practical point of view, limited shaping of the invert is necessary
in order to handle low flows and to reduce sedimentation.
Figure 4.1 details several types of deflector devices that have been found efficient in reducing
losses at junctions and bends. In all cases, the bottoms are flat, or only slightly rounded, to handle low flows. Numerous other types of deflectors or shaping of the manhole interiors were tested
by the University of Missouri. Some of these devices which were found inefficient are shown in
Figure 4.2. The fact that several of these inefficient devices would appear to be improvements
indicates that special shapings deviating from those in Figure 4.1 should be used with caution,
possibly only after model tests.
Tests indicate that rounding entrances or the use of pipe socket entrances do not have the effect
4-4
on reducing losses that might be expected. Once again, the effect of the jet from the upstream
pipe must be considered. Specific reductions to the pressure change factors are indicated with
each design figure.
FIGURE 4.1
EFFICIENT MANHOLE SHAPING
(University of Missouri, 1958)
4-5
FIGURE 4.2
INEFFICIENT MANHOLE SHAPING
Although these modifications look like improvements, studies have proven these
designs to be less efficient than the designs in Figure 4.1.
Use caution when deviating from recommended designs.
4-6
Lateral pipe 24 inches or less in diameter should be no more than 5 feet above the invert.
b.
Lateral pipe 27 inches or larger in diameter should be no more than 18 inches above the
invert, with the exception that catch basin connector pipe less than 50 feet in length may be no
more than 5 feet above the invert.
Exceptions to the above requirements may be permitted where it can be shown that the cost of
bringing laterals into a main line box conduit in conformance with the above requirements would
be excessive.
Outlet Considerations
When a storm drain outlets into a natural channel, an outlet structure must be provided which
prevents erosion and property damage. Velocity of flow at the outlet should agree as closely as
possible with the existing channel velocity.
a.
When the discharge velocity is low or subcritical, the outlet structure should consist of a
concrete headwall, wingwalls, and an apron. See Chapter 6 for velocity tolerances for unlined
and grass lined channels.
b.
When the discharge velocity is high or supercritical, the designer should also consider
adding bank protection in the vicinity of the outlet and an energy dissipator structure.
See Chapter 5 and Chapter 8 for additional information concerning conduit outlet structures.
The orientation of the outfall is another important design consideration. Where practical the outlet
of the storm drain should be positioned in the outfall channel so that it is pointed in a downstream
direction. This will reduce excessive flow disturbance and the potential for excessive erosion. If
the outfall structures can not be oriented in a downstream direction, the potential for outlet scour
must be considered. For example, where a storm drain outfall discharges perpendicular to the
direction of flow of the receiving channel consideration should be given to the possibility of erosion on the opposite channel bank. If erosion potential exists, a channel bank lining of riprap or
other suitable material should be installed in the bank. Alternatively an energy dissipator structure could be used at the storm drain outlet.
4-7
Energy Equation
Most procedures for calculating hydraulic grade line profiles are based on the energy equation
and can be expressed as:
2
V1
V2
-------- + Y 1 + S o L = ------- + Y 2 + S f L + headlosses
2g
2g
4-8
(4.1)
The various terms used in Equation (4.1) are identified in Figure 4.3 and Figure 4.4. Minor losses
have been included in the energy equation because of their importance in calculating hydraulic
grade line profiles.
FIGURE 4.3
STORM DRAIN PROFILE PRESSURE FLOW CONDITIONS
(MODIFIED FROM Los Angeles County Flood Control District, 1982)
As depicted, Y1 and Y2 include the pressure components since they are above the soffit of the
pipe.
4-9
FIGURE 4.4
STORM DRAIN PROFILE OPEN FLOW CONDITIONS
In this presentation of design methods, provision is made to identify pipes by use of numbered
subscripts. The number one (1) is used to identify the upstream main pipe, the number two (2) is
used to identify the downstream main pipe, and the number three (3) is used for incoming or
branching flow.
The general procedure for the hydraulic calculations is to establish the downstream control elevation. From there the hydraulic calculations proceed upstream from point of interest to point of
interest. For example, from one junction to another junction or from a junction to the beginning of
a bend. At the lower end of each point of interest the pipe friction losses from the downstream
section are added to the downstream hydraulic grade line. The losses through the point of interest are added at the upstream end of the point of interest. The procedures for calculating the various headlosses encountered in a storm drain system are presented in the following Head
Losses Section. Figure 4.5 may be used to assist in the accounting and computing of the losses.
4-10
2gn /2.21
Q = Rate of flow
V = Velocity
Sf
= Friction slope
Comments
Total Losses, ft
Other Losses, ft
ht, ft
hj, ft
hb, ft
= Velocity head
h1, ft
Length, ft
V /2g
Sf, ft/ft
V2/2g, ft
V, ft/sec
Q, cfs
Area, sq ft
Size/Type
Invert Elev.
Station
FIGURE 4.5
HYDRAULIC GRADE LINE CALCULATION SHEET
hf
= Headloss due to
friction
hb
= Headloss due to a
bend
hj
= Headloss due to a
junction
4-11
Equation (4.2) is a simplification of a more complex equation and is a convenient method for
locating the approximate point where pressure flow may cease (may become open channel
2
flow). It is derived by substituting specific energy ( E ) for the quantity V /2g + Y in Equation (4.1)
and rearranging the results. For S f use the average friction slope between the two points of
interest.
E2 E1
L = ----------------So Sf
(4.2)
Head Losses
The headlosses that need to be determined are: friction, transition, junction, manhole, bend, inlet
and exit. These losses need to be determined individually and then added together to determine
the overall headloss for each segment of the storm drain. The methods for determining the various headlosses presented in this section were selected for their wide acceptance and ease of
use.
Friction Losses
Friction losses for closed conduits carrying stormwater, including pump station discharge lines,
will be calculated from Manning's equation or a derivation thereof. The Manning's equation is
commonly expressed as follows:
(4.3)
Flow area, sq ft
Hydraulic radius, ft
Sf
The equation for determining pipe friction slope can be expressed as,
2
V
S f = K ---------------4/3
2gR
where:
(4.4)
V
Velocity, ft/sec
The value of K is dependent only upon the roughness coefficient (n) for the pipe. The Mannings
n-values for various pipe materials are given in Table 4.1. The value of K can be estimated using
Equation (4.5).
4-12
2gn
K = -----------2.21
where:
(4.5)
g
TABLE 4.1
VALUES OF ROUGHNESS AND FRICTION FORMULA COEFFICIENTS FOR CLOSED CONDUITS
Conduit Material
Manning's n
0.013
Brick
0.015
0.013
Concrete (monolithic)
Smooth forms
0.013
Rough forms
0.017
Concrete Pipe
0.013
0.024
Paved invert
0.020
0.013
0.018
18 to 36 Diameter
0.020
0.013
Vitrified Clay
Pipes
0.013
Liner plates
0.013
The loss of head due to friction throughout the length of reach (L) is calculated by:
hf = Sf L
where:
(4.6)
hf
Friction headloss, ft
Reach length, ft
4-13
Transition Losses
There are two types of pipe transitions that can occur in a storm drain system that would add
headloss to the energy grade line. The transition types are expansion and contraction. Figure
4.6 shows the two types of transitions that can be encountered. The headloss due to the expansion of flow for a storm sewer flowing under open channel conditions is expressed as:
V 12 V 22
h t = k e ------ ----- 2g 2g
where:
(4.7)
ht =
Transition headloss, ft
ke =
V1 =
V2 =
g =
Note:
The values for the transition coefficient, ke, for enlargements are given in Table 4.2.
The headloss due to the contraction of flow under open channel flow conditions is expressed as:
V2 V2
h t = k c -----2- -----1-
2g 2g
where:
Note:
(4.8)
kc =
V1 =
V2 =
Values for the transition loss coefficient, kc, for contractions can also be found in Table 4.2.
4-14
FIGURE 4.6
TRANSITION LOSS
TABLE 4.2
STORM SEWER ENERGY LOSS COEFFICIENTS UNDER OPEN CHANNEL CONDITIONS
(ASCE, 1992)
D2
-----D1
Kc
D2
------ = 3
D1
D2
------ = 1.5
D1
0.5
10
0.17
0.17
0.4
0.4
20
0.40
0.40
0.6
0.3
45
0.86
1.06
0.8
0.1
60
1.02
1.21
1.0
90
1.06
1.14
120
1.04
1.07
180
1.00
1.00
4-15
Under pressure flow conditions, the headloss due to contraction and expansion of flow can be
expressed as:
2
V
h = k -----2g
(4.9)
where:
h
k
V
The values for the transition coefficient, ke, for gradual enlargements are given in Table 4.3a. For
sudden enlargements, values for the transition coefficients are listed in Table 4.3b. Values for the
transition loss coefficient, kc, for sudden contractions can be found in Table 4.4.
Table 4.3a
COEFFICIENT ke FOR GRADUAL ENLARGEMENT UNDER PRESSURE FLOW CONDITIONS
(AISI, 1990)
Angle of Cone, degrees
D2 /D1
10
15
20
25
30
35
40
45
50
60
1.1
.01
.01
.01
.02
.03
.05
.10
.13
.16
.18
.19
.20
.21
.23
1.2
.02
.02
.02
.03
.04
.09
.16
.21
.25
.29
.31
.33
.35
.37
1.4
.02
.03
.03
.04
.06
.12
.23
.30
.36
.41
.44
.47
.50
.53
1.6
.03
.03
.04
.05
.07
.14
.26
.35
.42
.47
.51
.54
.57
.61
1.8
.03
.04
.04
.05
.07
.15
.28
.37
.44
.50
.54
.58
.61
.65
2.0
.03
.04
.04
.05
.07
.16
.29
.38
.46
.52
.56
.60
.63
.68
2.5
.03
.04
.04
.05
.08
.16
.30
.39
.48
.54
.58
.62
.65
.70
3.0
.03
.04
.04
.05
.08
.16
.31
.40
.48
.55
.59
.63
.66
.71
.03
.04
.05
.06
.08
.16
.31
.40
.49
.56
.60
.64
.67
.72
4-16
Table 4.3b
COEFFICIENT ke FOR SUDDEN ENLARGEMENT UNDER PRESSURE FLOW CONDITIONS
(AISI, 1990)
D2/D1
1.2
1.4
1.6
1.8
2.0
2.5
3.0
4.0
5.0
10.0
2
.11
.26
.40
.51
.60
.74
.83
.92
.96
1.00
1.00
3
.10
.26
.39
.49
.58
.72
.80
.89
.93
.99
1.00
4
.10
.25
.38
.48
.56
.70
.78
.87
.91
.96
.98
5
.10
.24
.37
.47
.55
.69
.77
.85
.89
.95
.96
6
.10
.24
.37
.47
.55
.68
.76
.84
.88
.93
.95
Velocity, V1 (ft/sec)
7
8
10
.10 .10 .09
.24 .24 .23
.36 .36 .35
.46 .46 .45
.54 .53 .52
.67 .66 .65
.75 .74 .73
.83 .82 .80
.87 .86 .84
.92 .91 .89
.94 .93 .91
12
.09
.23
.35
.44
.52
.64
.72
.79
.83
.88
.90
15
.09
.22
.34
.43
.51
.63
.70
.78
.82
.86
.88
20
.09
.22
.33
.42
.50
.62
.69
.76
.80
.84
.86
30
.09
.21
.32
.41
.48
.60
.67
.74
.77
.82
.83
40
.08
.20
.32
.40
.47
.58
.65
.72
.75
.80
.81
Table 4.4
COEFFICIENT kc FOR SUDDEN CONTRACTION UNDER PRESSURE FLOW CONDITIONS
(AISI, 1990)
D1 /D2
1.1
1.2
1.4
1.6
1.8
2.0
2.2
2.5
3.0
4.0
5.0
10.0
2
.03
.07
.17
.26
.34
.38
.40
.42
.44
.47
.48
.49
.49
3
.04
.07
.17
.26
.34
.38
.40
.42
.44
.46
.48
.48
.49
4
.04
.07
.17
.26
.34
.37
.40
.42
.44
.46
.47
.48
.48
5
.04
.07
.17
.26
.34
.37
.39
.41
.43
.46
.47
.48
.48
6
.04
.07
.17
.26
.34
.37
.39
.41
.43
.45
.47
.48
.48
Velocity, V2 (ft/sec)
7
8
10
.04 .04 .04
.07 .07 .08
.17 .17 .18
.26 .26 .26
.34 .33 .33
.37 .36 .36
.39 .39 .38
.41 .40 .40
.43 .42 .42
.45 .45 .44
.46 .46 .45
.47 .47 .46
.47 .47 .47
12
.04
.08
.18
.26
.32
.35
.37
.39
.41
.43
.45
.46
.46
15
.04
.08
.18
.25
.32
.34
.37
.38
.40
.42
.44
.45
.45
20
.05
.09
.18
.25
.31
.33
.35
.37
.39
.41
.42
.43
.44
30
.05
.10
.19
.25
.29
.31
.33
.34
.36
.37
.38
.40
.41
40
.06
.11
.20
.24
.27
.29
.30
.31
.33
.34
.35
.36
.38
4-17
Junction Losses
A junction occurs where one or more lateral pipes enter the main storm drain, at a formed junction, prefabricated fitting or at a manhole. Multiple pipes coming together at a junction should flow
together smoothly to avoid high headlosses. Figure 4.7 through Figure 4.9 show typical junctions
in plan and profile.
Junction headloss for a single lateral can be determined by applying the Energy Equation and
the Thompson Equation (California Department of Transportation, 1985).
The Energy Equation (Equation (4.1)) at a junction (as displayed in Figure 4.7 through Figure
4.9) is expressed as:
V 12 2g + Y 1 + Z 1 = V 22 2g + Y 2 + Z 2 + headlosses
where:
4-18
(4.1)
headlosses
V 12 2g
V 22 2g
Y1
Y2
Z1
Z2
FIGURE 4.7
FORMED OR PREFAB STORM DRAIN JUNCTION
FIGURE 4.8
STORM DRAIN JUNCTION AT MANHOLE WITH ALIGNED CROWNS UNDER PRESSURE FLOW
4-19
FIGURE 4.9
FORMED STORM DRAIN JUNCTION WITH ALIGNED CROWNS UNDER PRESSURE FLOW
V 12 2g V 22 2g + Y 1 Y 2 + Z 1 Z 2 = headlosses
Substitute HG1 for Y1 + Z1 and HG2 for Y2 + Z2
V 12 2g V 22 2g + HG 1 HG 2 = headlosses
V 12 2g V 22 2g + HG = headlosses
The Thompson Equation (Equation (4.10a)), a form of the momentum equation, is used to determine the change in flow depth across a junction.
A1 + A2
Q 2 V 2 Q 1 V 1 Q 3 V 3 Cos
HG ------------------ = ----------------------------------------------------------------2
g
(4.10a)
or
Q 2 V 2 Q 1 V 1 Q 3 V 3 Cos
----------------------------------------------------------------
g
HG = -----------------------------------------------------------------------A1 + A2
-----------------2
4-20
where:
HG
A1
A2
Q1
Q2
Q3
V1
V2
V3
Angle between lateral and main line storm drain (See Figure
4.9), degrees
To determine junction headloss hj, substitute the Thompson Equation into the rewritten Equation
(4.1), assuming transition and friction losses at the junction are negligible.
2 ( Q 2 V 2 Q 1 V 1 Q 3 V 3 Cos )
-------------------------------------------------------------------------- + V 12 2g V 22 2g = h j
( A 1 + A 2 )g
(4.10b)
Should friction losses be determined not to be negligible Equation (4.10c) should be used.
Sf 1 + Sf 2
2 ( Q 2 V 2 Q 1 V 1 Q 3 V 3 Cos )
-------------------------------------------------------------------------- + V 12 2g V 22 2g + --------------------- L = h j
2
( A 1 + A 2 )g
where:
Sf1
Sf2
Length of transition, ft
(4.10c)
Should transition losses be determined not to be negligible but friction losses are negligible, then
Equation (4.10d) should be used for computing junction loss hj.
2 ( Q 2 V 2 Q 1 V 1 Q 3 V 3 Cos )
V2 V2
h j = ------------------------------------------------------------------------- + V 12 2g V 22 2g + k je -----1- -----2-
( A 1 + A 2 )g
2g 2g
(4.10d)
where:
kje
4-21
kje = 3.50 x (Tan /2) 1.22(California Department of Transportation, 1985). See Figure 4.7 through Figure 4.9 for location
of angle.
V1
V2
no change in pipe size or rate of flow, the loss can be estimated by: h mh
where:
hmh
Velocity, ft/sec
V
= 0.05 -----2g
(4.11)
Bend Losses at Manholes (no laterals) - The bend loss at a manhole is determined using
Equation (4.12). The bend loss coefficient, kb, can be determined using Figure 4.11.
2
h mh
V
= k b -----2g
where:
4-22
(4.12)
hmh
kb
Velocity, ft/sec
FIGURE 4.10
BEND LOSS COEFFICIENT
(MODIFIED FROM AISI, 1990)
4-23
Bend Losses at Curved Sewer - For bend loss at a curved sewer, the loss is calculated using
Equation (4.13).
2
V
h b = k b -----2g
where:
(4.13)
hb
kb
The value of the bend loss coefficient, kb, depends upon the angle of the bend. It can be estimated from Equation (4.14) (USDOT, 2001).
k b = 0.0033
where:
(4.14)
kb
Bend losses should be included for all closed conduits, those flowing partially full as well as those
flowing full.
Inlet Losses - At open inlets to a storm drain system, an inlet will function the same as a culvert
inlet. Under inlet control, the hydraulic grade line at the entrance can be estimated by using the
appropriate procedures and figures presented in the Culvert Chapter. Under outlet control,
entrance losses can be calculated using Equation (4.15).
2
V
h i = k en -----2g
where:
(4.15)
hi
Headloss at inlet, ft
ken
4-24
Vo
h o = 1.0 -------2g
where:
4.4
(4.16)
ho
Headloss at outlet, ft
Vo
CRITERIA
4-25
runoff passing directly over the catch basin to flow down the street (or overland) until it enters the
system elsewhere. Another indication is water standing in sumps (storage facility ponding) until
there is sufficient capacity in the storm drain to admit the ponded water. The designer should size
the pipes so that the hydraulic grade line is below the inlet elevation for the design storm frequency. The separation distance between the inlet elevation and the hydraulic grade line is set by
the reviewing agency as a standard for storm sewer design.
Often a closed conduit designed for open channel flow operates as a pressure conduit. This may
result when storm runoff exceeds that used for design purposes or simply because junction
losses were underestimated or neglected in the design. In storm drain systems, junctions in
closed conduits can cause major losses in the energy grade line across the junction. If these
losses are not included in the hydraulic design, the capacity of the conduit may not be adequate
for the design flow.
Although not always feasible, the recommended procedure is to design storm drains to flow
under pressure because this maximizes conveyance while minimizing capital expenditure.
Whether or not the final design assumes the pipe is flowing partially or completely full, a hydraulic
grade line must be computed and displayed on a profile drawing of the conduit. The design shall
establish the hydraulic grade line to be below an inlet, ground or manhole rim elevation. When
the hydraulic grade line rises above ground level, stormwater can be found shooting out of catch
basins or popping manhole covers, which can lead to damage and inconvenience to pedestrian
and vehicular traffic.
2.
3.
The controlling water surface elevation at the point of discharge is commonly referred to as the
tailwater elevation. The tailwater elevation at the storm drain outfall must be considered carefully.
Evaluation of the hydraulic grade line for a storm drain system begins at the system outfall with
the tailwater elevation.
Generally, it shall be assumed that the tailwater elevation at the storm drain outlet is equivalent to
the water surface elevation within the receiving channel or facility which has the same return
period as the storm drain design discharge, unless otherwise approved by the governing agency.
In general the two types of tailwater conditions are:
1.
Tailwater elevation above the crown elevation. In such situations the control shall conform
to the following criteria:
a.
4-26
In the case of a conduit discharging into a storage basin, the control shall be the stor-
age basin water surface elevation coinciding with the design peak flow to the storage
basin.
b.
In the case of a conduit discharging into an open channel, the tailwater elevation shall
be the water surface elevation of the channel coinciding with same return period as
the storm drain design peak discharge.
c.
In the case of a conduit discharging into another conduit, the control shall be the highest hydraulic grade line elevation of the outlet conduit immediately upstream or downstream of the confluence.
2.
Tailwater elevation at or below the crown elevation. The tailwater shall be the crown elevation at the point of discharge.
V
h i = ( 1 + k en ) -----2g
where:
(4.17)
hi
Headloss at inlet, ft
ken
4.5
DESIGN STANDARDS
Design standards may vary from community to community. The designer shall adhere to policies
and standards of the governing agency. For a detailed description of design standards the
designer is referred to the Policy/Standards Manual of the governing agency. When the designer
has to deviate from the standards for storm drain design, they should contact the governing
agency as soon as possible to explain the situation and come to an agreement on a solution.
4-27
4.6
DESIGN EXAMPLE
OBJECTIVE:
Design and evaluation of an existing and proposed storm drain system.
PROBLEM STATEMENT:
FIGURE 4.11
INITIAL STORM DRAIN LAYOUT FOR EXAMPLE PROBLEM
4-28
Determine the initial and final system design of the initial storm drain layout presented in Figure
4.11 by calculating peak design discharge, size of storm drain pipes required and the associated
hydraulic and energy grade lines (HGL and EGL respectively). Storm drain segments 010005
through 010030 represent the proposed storm drain system whereas storm drain segments
010035 and 010040 represent the existing storm drain.
GIVEN:
1. Minimum connector pipe size is equal to 15 inch diameter.
2. Minimum storm drain pipe size is equal to 18 inch diameter.
3. Design event is the 2-year storm.
4. Drainage areas, runoff coefficients, and rainfall intensity to be used for estimating peak
discharges for Catch Basins 0105, 0106, 0107, 0108, and flow in storm drain segment
010035 are listed in Table E.1.
5. Regional retention basin bottom elevation = 1265.0 ft
6. Pipe 010040s inlet invert elevation and Junction J010040s outlet elevation = 1266.8 ft
7. 18 inch minimum cover required over pipe (18 inch + pipe wall thickness).
8. The design requirement for the catch basin HGL elevation is at least 1 ft below the catch
basin inlet elevation (freeboard is 1 ft).
9. At M010025 and M010020, no special shaping for bends are proposed.
10. There is an existing buried utility between M010025 to S010030. The client has
requested that the storm drain be sized to travel over the existing utility. The maximum
pipe diameter available to use in these sections is a 18 inch pipe, which will safely lay
over the utility without having to go under the utility line. There is a formed abrupt transition at S010030.
11. Use City of Phoenix Standard Drawings (2005) for Catch Basin Type.
12. Initial storm drain size and estimated travel time between concentration points assumed
full conditions.
13. Storm drain outlet pipe invert elevation at retention basin is set 0.5 ft above basin bottom.
4-29
SOLUTION:
Step 1.
Sub Basin
Sub Basin
ID
Area
Runoff
Coefficient
(acres)
4-30
Length
Slope
(ft)
(ft/ft)
Rainfall
Time of
Sub Basin
Intensity
Concentration
Runoff
(2YR)
(min)
(in/hr)
(cfs)
0105
0.47
0.91
390
0.0077
10.00
2.80
1.20
0106
0.86
0.91
1000
0.0170
10.00
2.80
2.20
0108
0.67
0.91
510
0.0059
10.00
2.80
1.70
0107
0.47
0.91
450
0.0111
10.00
2.80
1.20
0111
50.00
0.85
1350
0.0074
15.00
2.40
102.00
TABLE E.2
STREET AND INLET PARAMETERS AND DIMENSIONS
Street and Inlet
Average
Upstream
Gutter Slope
Cross
Slope at
Inlet
(Sx)
Flow by
to Inlet
(Column
25)
(ft/ft)
(ft/ft)
(cfs)
(cfs)
(ft)
38+00 RT
0.0120
0.0200
0.00
1.20
0106
34+10 LT
0.0091
0.0270
0.00
0108
33+50 RT
0.0095
0.0200
0107
28+50 RT
0.0095
0.0270
Inlet ID
Station
0105
Depth of
Total
Spread Of
Flow
Flow to
Flow In
Upstream Of
Inlet
Street
Inlet
Gutter
Velocity
Depth Of
Sump
(ft)
(fps)
(ft)
10
0.20
6.79
2.20
0.27
0.00
1.70
0.40
2.00
Inlet Type
Catchbasin
Depth
Intercepted
Flow
Flow By
(ft)
(cfs)
(cfs)
11
12
13
14
15
16
17
2.38
P1569M1-3
3.50
0.80
0.40
0107
1274.73
1271.23
7.66
2.63
P1569M2-3,6
3.50
2.20
1274.74
1271.24
0.22
8.27
2.34
P1569M2-6,6
3.60
1.70
1274.23
1270.63
0.26
7.31
2.62
P1569M1-3
3.58
2.00
1274.23
1270.65
0.39
(ft)
V, Sump
Elev.
(ft)
1. Inlet type identifications are from the City of Phoenix Standard Drawings (2005).
Step 2.
2.1
Considering proposed catch basin, manholes and existing storm drain, a preliminary
schematic of the storm drain system was drawn. Figure 4.11 displays the layout of the
initial storm drain system.
2.2
Considering design constraints such as storm drain and connector pipe soffit elevations,
and the invert elevation of catch basins (catch basin v depths) initial storm drain slopes
are estimated.
For this example an assumed hydraulic grade line (HGL) was estimated by taking into
consideration, dimensions of the existing storm drain system, design criteria (listed under
given) and ground elevations. Assuming that the system will be in full flow conditions, the
hydraulic grade line of the proposed system at the junction with the existing system was
set above the 48-inch pipe and approximately 2 feet below the surface. At the upstream
end of the proposed system the assumed hydraulic grade line was set approximately 2
feet below the surface (setting a target elevation of 2 feet below the surface will help
insure that there is at a minimum of 1 foot of freeboard below the catch basin inlet). A
slope was then determined between the two points (slope = 0.0025 ft/ft). The assumed
hydraulic grade line slope was then used as the initial pipe slope for the main line and for
the connector pipes (an assumption was made that the connector pipe HGL slope will be
the same as for the main line). Figure 4.13 displays a HGL profile for the initial storm
drain layout.
The initial profile (soffit profile) of the storm drain was laid out by matching the storm drain
soffit of the proposed system to the soffit of the existing storm drain and utilizing the storm
4-31
drain slope determined above and proceeded up stream to the beginning of the proposed
system.
The next step was to determine the initial soffit profile for the collector pipes and v depths
of catch basins. To determine catch basin v depth and collector pipe soffit profiles, initial
collector pipe size were estimated. Initial collector pipe size was estimated utilizing the
following steps and assumptions:
Connector pipe slope = 0.0025 ft/ft (slope is the same for all connector pipes).
For pipes flowing full, pipe diameter can be estimated utilizing the following equation:
nQ 3/8
D = 1.33 -------
S
( 0.013 ) ( 2.20 ) 3/8
D = 1.33 ----------------------------------
= 1.07 feet
0.0025
D = 12.80 inches - use minimum pipe diameter of 15 inches for all connector pipes.
Catch basin v depth is a catch basin dimension cited in the Uniform Standard Details for
Public Works Construction (Maricopa Association of Governments, 1998) measured from
the top of curb to the catch basin invert. Minimum v depth is typically 3.5 feet. In this
example the v depth for catch basins were set so that the initial collector slope of 0.0025
ft/ft between the catch basin and the main line storm drain could be obtained (soffit elevations of main line and collector pipe are matched).
4-32
FIGURE 4.12
HGL PROFILE FOR INITIAL STORM DRAIN LAYOUT
4-33
2.3
The peak discharge at J010005 was calculated utilizing the following steps (refer to Table
E.3):
2.3.1
A T = 1.33 acres
2.3.2
A1 C1 + A2 C2 + + An + 1 Cn + 1
C w = ----------------------------------------------------------------------------A 1 + A 2 + A n + 1
0.47 ) ( 0.91 ) + ( 0.86 ) ( 0.91 -) = 0.91
C w = (------------------------------------------------------------------0.47 + 0.86
2.3.3
Using the longest time of concentration (Tc = 10 minutes), for the contributing
areas, and the 2-year design storm, determine rainfall intensity from rainfall intensity-duration-frequency relation graphs provided in the Hydrology Manual.
i = 2.8 in/hr
2.3.4
Determine the design peak discharge, Qd, using the Rational Method:
Q d = C w iA T
Q d = ( 0.91 ) ( 2.80 ) ( 1.33 ) = 3.4 cfs.
2.4
The initial storm drain size for storm drain segment 010005 was estimated utilizing the following steps:
2.4.1
Calculate the initial size of storm drain segment 010005 using the peak discharges determined in Step 2.3.4, pipe slope estimated in Step 2.2, the assumption that the pipe is flowing full and the following equation:
nQ 3/8
D = 1.33 -------
S
( 0.013 ) ( 3.4 ) 3/8
D = 1.33 -------------------------------
= 1.27 feet
0.0025
D = 15.2 inches - use minimum pipe diameter of 18 inches.
Q
3.4
Assuming full flow, velocity = ---- = ---------- = 1.92 ft/sec
A 1.77
Velocity is less than desired 5 ft/sec cleansing velocity. Check that the velocity of
flow from one half the design peak discharge is greater than the minimum velocity
4-34
of 2 ft/sec (criteria may vary from community to community). To check for minimum velocity a computer program was utilized to facilitate a solution using Mannings equation. Estimated pipe size, slope, and one half the design peak
discharge was used to estimate velocity.
Velocity at half design peak discharge = 2.65 ft/sec.
2.5
The estimated travel time in storm drain segment 010005 was determined utilizing the following steps:
2.5.1
Using the velocity, V, calculated in Step 2.4, determine the travel time (Tcd)
between J010010 and J010005 using the following equation:
L
T cd = ---------60
V -----m
where:
T cd = time in drain, ft
V = velocity, ft/sec
60/m = 60 sec per 1 min
190 ft
Travel time = ------------------------------------------------------------- = 1.65 min.
( 1.92 ft/sec ) ( 60 sec/min )
2.6
Sum contributing drainage areas to catch basins 0105, 0106 and 0108.
A T = acres
2.6.2
Calculate the weighted runoff coefficient, Cw using procedures listed in Step 2.3.2.
C w = 0.91
2.6.3
Using the longest time of concentration, Tc = 11.65 minutes, (Tc from Step 2.3.3
plus the travel time from Step 2.5.1 as compared to the Tc estimated for the contributing drainage area to Catch Basin 108), and the 2-year design storm, determine rainfall intensity from rainfall intensity-duration-frequency relation graphs
provided in the Hydrology Manual.
i = 2.6 in/hr
4-35
2.6.4
Determine the design peak discharge, Qd, using the Rational Method:
Q d = C w iA T
Q d = ( 0.91 ) ( 2.60 ) ( 2.00 ) = 4.7 cfs.
2.7
The initial storm drain size for storm drain segment 010010 was estimated utilizing the following steps:
2.7.1
Calculate the preliminary size of storm drain segment 010010 using the peak discharges determined in Step 2.6.4, pipe slope estimated in Step 2.2 and procedures presented in Step 2.4. The selected pipe size shall be sufficient to convey
the design peak discharge.
D = 18 inches
V = 2.65 ft/sec
Velocity at half design peak discharge = 2.9 ft/sec
2.8
Using procedures in Step 2.5 estimate travel time for storm drain segment 010010.
2.8.1
2.9
Sum contributing drainage areas to catch basins 0105, 0106, 0107 and 0108.
A T = 2.47 acres.
2.9.2
Calculate the weighted runoff coefficient, Cw using procedures listed in Step 2.3.2.
C w = 0.91
2.9.3
Using the longest time of concentration, Tc = 11.71 minutes (Tc from Step 2.3.3
plus the travel time from Step 2.5.1 and 2.8.1 as compared to the Tc estimated for
the contributing drainage area to Catch Basin 0107), and the 2-year design storm,
determine rainfall intensity from rainfall intensity-duration-frequency relation
graphs provided in the Hydrology Manual.
i = 2.6 in/hr
2.9.4
Determine the design peak discharge, Qd, using the Rational Method:
Q d = C w iA T
4-36
The initial storm drain size for storm drain segments 010015, 010020, 010025 and
010030 was estimated using the following steps:
2.10.1 There are no inlets draining to the storm drain segment 010015, 010020, 010025
and 010030 therefore use the peak discharge determined in Step 2.9, pipe slope
estimated in Step 2.2 and procedures presented in Step 2.4.
Results of the evaluation are presented below.
Pipe Segment
Pipe Size,
inches
Capacity
Velocity, ft/sec
Velocity at 1/2
Design Peak,
ft/sec
010015
181
Full Flow
3.3
3.0
010020
181
Full Flow
3.3
3.0
010025
181
Full Flow
3.3
3.0
010030
24
Full Flow
(Assume)
1.9
3.0
1.
Step 3.
3.1
18 inch diameter pipe is used to avoid conflicts with existing utilities. Appropriateness of the 18 inch diameter
pipe will be checked while determining the hydraulic grade line for the system.
Estimate design peak discharge for storm drain segments 010035 and 010040
(existing storm drain).
Estimate design peak discharge for storm drain segment 010035.
3.1.1
Sub-basin 0111 drains to pipe segment 010035. Design discharge for segment
010035 was estimated in Step 1.
Q d = 102.0 cfs
3.2
To determine the longest time of concentration for the overall drainage area draining to
storm drain segment 010040 (existing storm drain drainage area versus proposed storm
drain drainage area) the flow travel time for storm drain segments 010015, 010020,
010025, 010030 and 010035 needs to be determined. Using procedures in Step 2.5.1
estimate travel time for storm drain segments and then the respective time of concentration for each storm drain segment.
4-37
3.2.1
3.2.1.2
3.2.2
3.2.2.2
3.3
Sum contributing drainage areas to catch basins 0105, 0106, 0107, 0108 and
Sub-basin 0111.
A T = 52.47 acres
3.3.2
Calculate the weighted runoff coefficient, Cw using procedures listed in Step 2.3.2.
C w = 0.853
3.3.3
i = 2.35 in/hr
3.3.4
Determine the design peak discharge, Qd, using the Rational Method:
Q d = C w iA T
Q d = ( 0.853 ) ( 2.35 ) ( 52.47 ) = 105.2 cfs.
4-38
TABLE E.3
MAINLINE DESIGN DISCHARGE AND PIPE PARAMETERS
Main Storm Drain
Runoff/Mainline Discharge
Invert
Elevation
(Inlet)
Invert
Elevation
(Outlet)
Size
Slope
Velocity Length
Time in Manning's
Drain
n
(min)
(in/hr)
(cfs)
(ft)
(ft)
(in)
(ft/ft)
(fps)
(ft)
(min)
10
11
12
13
010005
1.33
0.91
1.21
10.00
2.80
3.40
1270.79
1270.31
1 - 18 Pipe
0.0025
1.92
190
1.65
0.013
010010
2.00
0.91
1.82
11.65
2.60
4.70
1270.31
1270.29
1 - 18 Pipe
0.0025
2.66
10
0.06
0.013
010015
2.47
0.91
2.25
11.71
2.60
5.80
1270.29
1270.24
1 - 18 Pipe
0.0025
3.28
20
0.10
0.013
010020
2.47
0.91
2.25
11.71
2.60
5.80
1270.24
1270.05
1 - 18 Pipe
0.0025
3.28
75
0.38
0.013
010025
2.47
0.91
2.25
11.71
2.60
5.80
1270.05
1269.80
1 - 18 Pipe
0.0025
3.28
100
0.51
0.013
010030
2.47
0.91
2.25
11.71
2.60
5.80
1269.30
1268.80
1 - 24 Pipe
0.0025
1.85
200
1.81
0.013
010035
50.00
0.85
42.50
15.00
2.40
102.00
1268.30
1266.80
1 - 48 Pipe
0.0050
8.12
300
0.62
010040
52.47
0.85
44.76
15.62
2.35
105.20
1266.80
1265.50
1 - 48 Pipe
0.0163
8.37
80
Step 4.
0.013
0.013
Design peak discharges and initial pipe sizes to be used in calculating the hydraulic grade line for
the proposed and existing storm drain system have been determined in Steps 2 and 3. The next
step is to set up a calculation sheet to aid in the hydraulic grade line calculations.
The general procedure for hydraulic grade line calculations is to establish the downstream control elevation and proceed upstream from one point of interest to another point of interest (i.e.
from one junction to another, from one junction to a structure or from one junction to the beginning of a bend).
Table E.3 is an example of a hydraulic grade line calculation sheet. The calculation sheet aids the
designer in keeping data organized. In this example the first row of data, is for storm drain segment 010005. In descending order, each following row lists data in a downstream direction for
each storm drain segment. Since the proposed storm drain (storm drain segment 010035) connects into an existing storm drain, a row should be left blank to separate the data for the two
storm drain systems. The row following the blank row is for storm drain segment 010035, the
next row for storm drain segment 010040 and the last row for the analysis is for the outlet.
4-39
4.2
4.1.1
4.1.2
Estimated starting water surface elevation (refer to Section 4.4.1 of the drainage
design manual) = 1265.0 + 4.90 = 1269.90 ft
Soffit elevation at outlet pipe is = 1265.5+ 4.0 = 1269.50 ft. The starting water surface elevation is greater then the soffit elevation at the outlet, therefore use full
flow conditions.
4.2.2
Vo
h o = ------2g
Q
V o = ---A
(4.16)
D
A = -----4
2
4
A = ----- = 12.57 sq ft
4
105.2
V o = ------------- = 8.37 ft/sec
12.57
2
8.37
h o = ----------------------- = 1.09 ft
( 2 ) ( 32.2 )
4.2.3
Enter the headloss of 1.09 ft in the appropriate column of the calculation sheet.
4.2.4
Sum the headlosses for the storm drain segment, and calculate the hydraulic and
energy grade lines and list in the appropriate column.
HGL = 1269.90 ft + 1.09 ft (exit loss) = 1270.99
EGL = 1269.90 ft + 1.09 ft (exit loss) + 1.09 ft (velocity head) = 1272.08 ft
4-40
4.3
V
S f = K ---------------4/3
2gR
(4.4)
2gn K = ----------2.21
(4.5)
2
12- = 1.0 ft
R = 48
--------------4
Calculate the velocity:
Q
V = ---A
------------- =
V o = 105.2
12.57
8.37 ft/sec
4-41
8.37
- = 0.0053 ft/ft
S f = 0.0049 ------------------------------------4/3
( 2 ) ( 32.2 ) ( 1 )
4.3.2
hf = Sf L
(4.6)
h f = ( 0.0053 ) ( 80 ) ft = 0.42 ft
4.3.3
The HGL at the upstream end of pipe 010040 (downstream end of J010040) is
equal to (Tailwater Elevation) + (headloss due to friction for pipe segment
010040).
The first step is to determine if the HGL is above or below the soffit at
the junction. If the HGL is above the soffit proceed assuming full flow
conditions. Verify by checking that the HGL at the upstream end of
pipe segment 010040 is high enough to inundate the junction soffit.
Storm drain segment 010040s soffit elevation at junction J010040
1266.80 ft (invert elevation) + 4 ft (pipe diameter) = 1270.80 ft
From Step 4.3.3 HGL at downstream end of J010040 = 1271.41 ft
Assume full flow conditions.
4.3.4.2
2 ( Q 2 V 2 Q 1 V 1 Q 3 V 3 Cos ) V 12 V 22
+ ------ -----h j = ---------------------------------------------------------------------------( A 1 + A 2 )g
2g 2g
(4.10b)
where:
Q 2 = Q 010040 = design peak discharge for storm drain segment 010040 = 105.2 cfs
Q 1 = Q 010035 =difference in design peak discharge between storm drain segments
010040 and 010030 = 99.4 cfs
Q 3 = Q 010030 = design peak discharge for storm drain segment 010030 = 5.8 cfs
4-42
A 2 = A 010040 = full flow area for storm drain segment 010040 = 12.57 sq ft
A 1 = A 010035 = full flow area for storm drain segment 010035 = 12.57 sq ft
A 3 = A 010030 = full flow area for storm drain segment 010030 = 3.14 sq ft
V 2 = V 010040 = full flow velocity for Q 010040 = 8.37 ft/sec
V 1 = V 010035 = full flow velocity for Q 010035 = 7.91 ft/sec
V 3 = V 010030 = full flow velocity for Q 010030 = 1.85 ft/sec
2
4.3.5
Record friction and junction headlosses and summation of headlosses for storm
drain segment 010040 in appropriate calculation sheet columns. Calculate HGL
and EGL and record.
Total Head Loss = 0.42 ft + 0.11 ft = 0.53 ft
Downstream HGL Elevation = 1270.99 ft
Upstream HGL Elevation = 1271.52 ft
Downstream EGL Elevation = 1272.08 ft
Upstream EGL Elevation = 1272.61 ft
Upstream Soffit Elevation = 1266.80 ft + 4.0 ft = 1270.80 ft
4.4
Using procedures from Step 4.3.1 and 4.32 calculate friction slope and headloss
for storm drain segment 010035. Based on HGL elevation at J010040 storm drain
segment 010035 starts in full flow.
2
8.12
- = 0.0050 ft/ft
S f = 0.0049 ------------------------------------4/3
( 2 ) ( 32.2 ) ( 1 )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
4-43
h mh
V
= 0.05 -----2g
(4.11)
2
8.12
h mh = 0.05 ----------------------- = 0.05 ft
( 2 ) ( 32.2 )
4.4.3
Record friction and manhole headlosses and summation of headlosses for storm
drain segment 010035 in appropriate calculation sheet columns. Calculate HGL
and EGL elevations and record.
Total Head Loss = 1.50 ft + 0.05 ft = 1.55 ft
Downstream HGL Elevation = 1271.52 ft
Upstream HGL Elevation = 1273.07 ft
Downstream EGL Elevation = 1272.61 ft
Upstream EGL Elevation = 1274.09 ft
Upstream Soffit Elevation = 1268.30 ft+ 4.0 ft = 1272.30 ft
4.5
Start HGL calculations for storm segment 010030 (proposed storm drain segment). HGL
for proposed storm drain segment commences at J010040 with an HGL elevation of
1271.52 ft determined in step 4.3.5. Full flow conditions exist.
4.5.1
Using procedures from Step 4.3.1 and 4.32 calculate friction slope and headloss
for storm drain segment 010030. Based on HGL elevation at J010040 and the
upstream soffit elevation, storm drain segment 010030 starts in full flow.
2
1.85
S f = 0.0049 -----------------------------------------= 0.0007 ft/ft
4/3
( 2 ) ( 32.2 ) ( 0.5 )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
Calculate transition headlosses at S010030. Structure S010030 is an abrupt transition (expansion) from a 18 inch pipe (010025) to a 24 inch pipe (010030).
Determine if the HGL elevation at the inlet of storm drain segment 010030 indicates that the storm drain is flowing full. In the example, pipes, 010030 and
010025 are flowing full (pressure flow conditions).
4.5.2.1
Calculate the transition headloss using Equation (4.9) and Table 4.3b:
2
V
h t = k e -----2g
4-44
(4.9)
4.5.2.2
D
D1
24
18
To use Table 4.3b, first calculate ------2 = ------ = 1.33 (say 1.4)
where:
Q 010025
V 010025 = ----------------A 010025
5.8 cfs- = 3.28 ft/sec
V 010025 = ----------------2
1.77 ft
Use Table 4.3b to determination of the sudden expansion coefficient:
V 010025
h t = k e ----------------------( 2 ) ( 32.2 )
2
3.28
h t = 0.20 ----------------------- = 0.03 ft
( 2 ) ( 32.2 )
4.5.3
Record friction and transition headlosses and summation of headlosses for storm
drain segment 010030, in appropriate calculation sheet columns. Calculate HGL
and EGL elevations and record.
Total Head Loss = 0.14 ft + 0.03 ft = 0.17 ft
Downstream HGL Elevation = 1271.52 ft (refer to Step 4.5)
Upstream HGL Elevation = 1271.69 ft
Downstream EGL Elevation = 1272.61 ft
Upstream EGL Elevation = 1271.74 ft
Upstream Soffit Elevation = 1269.30 ft + 2.0 ft = 1271.30 ft
4.6
Using procedures from Step 4.3.1 and 4.3.2 calculate friction slope and headloss
for storm drain segment 010025. Based on HGL elevation at S010030 storm drain
segment 010025 starts in full flow.
4-45
3.28
S f = 0.0049 -----------------------------------------------= 0.0030 ft/ft
4/3
( 2 ) ( 32.2 ) ( 0.375 )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
4.6.2.2
Using bend angle identified in the schematic (62 degrees) and Figure
4.10, determine the bend loss coefficient (kb):
V
h mh = k b -----2g
Q 010020
V 010020 = ----------------A 010020
(4.12)
h mh
V 010020
= k b ----------------------( 2 ) ( 32.2 )
2
3.28
h mh = 0.68 ----------------------- = 0.11 ft
( 2 ) ( 32.2 )
4.6.3
Record friction and manhole bend headlosses and summation of headlosses for
storm drain segment 010025, in appropriate calculation sheet columns. Calculate
HGL and EGL elevations and record.
Total Head Loss = 0.30 ft + 0.11 ft = 0.41 ft
Downstream HGL Elevation = 1271.69 ft
Upstream HGL Elevation = 1272.10 ft
4-46
Using procedures from Step 4.3.1 and 4.3.2 calculate friction slope and headloss
for storm drain segment 010020. Based on HGL elevation at M010025, storm
drain segment 010020 starts in full flow.
2
3.28
= 0.0030 ft/ft
S f = 0.0049 -----------------------------------------------4/3
( 2 ) ( 32.2 ) ( 0.375 )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
h f = ( 0.0030 ) ( 75 ft ) = 0.23 ft
4.7.2
4.7.2.2
Using bend angle identified in the schematic (28 degrees) and Figure
4.10, determine the bend loss coefficient ( k b ) :
( k b ) = 0.19
4.7.2.3
V
h mh = k b -----2g
Q 010015
V 010015 = ----------------A 010015
(4.12)
h mh
V 010015
= k b ----------------------( 2 ) ( 32.2 )
4-47
h mh
4.7.3
3.28
= 0.19 ----------------------- = 0.03 ft
( 2 ) ( 32.2 )
Record friction and manhole bend headlosses and summation of headlosses for
storm drain segment 010020, in appropriate calculation sheet columns. Calculate
HGL and EGL elevations and record.
Total Head Loss = 0.23 ft + 0.03 ft = 0.26 ft
Downstream HGL Elevation = 1272.10 ft
Upstream HGL Elevation = 1272.36 ft
Downstream EGL Elevation = 1272.27 ft
Upstream EGL Elevation = 1272.53 ft
Upstream Soffit Elevation = 1270.24 ft + 1.50 ft = 1271.74 ft
4.8
Using procedures from Step 4.3.1 and 4.3.2 calculate friction slope and headloss
for storm drain segment 010015. Based on HGL elevation at M010020 storm
drain segment 010015 starts in full flow.
2
3.28
= 0.0030 ft/ft
S f = 0.0049 -----------------------------------------------4/3
( 2 ) ( 32.2 ) ( 0.375 )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
h f = ( 0.0030 ) ( 20 ft ) = 0.06 ft
4.8.2
The first step, is to determine if the HGL is above or below the soffit at
the junction. If the HGL is above the soffit, proceed assuming full flow
conditions. Verify by checking that the HGL at the upstream end of
pipe segment 010015 is high enough to inundate the junction soffit.
Storm drain segment, 010010s soffit elevation at junction J010015 =
1270.29 ft + 1.5 ft (pipe diameter) = 1271.79 ft.
From Step 4.7.3 and 4.8.1, the HGL at downstream end of J010015 =
1272.36 ft + 0.06 ft = 1272.42 ft. Junction is submerged. Assume full
flow conditions.
4.8.2.2
2 ( Q 2 V 2 Q 1 V 1 Q 3 V 3 Cos ) V 12 V 22
h j = ---------------------------------------------------------------------------+ ------ -----( A 1 + A 2 )g
2g 2g
4-48
(4.10b)
where:
h j = 0.05 ft
4.8.3
Record friction and junction headlosses and summation of headlosses for storm
drain segment 010015 in appropriate calculation sheet columns. Calculate HGL
and EGL and record.
Total Head Loss = 0.06 ft + 0.05 ft = 0.11 ft
Downstream HGL Elevation = 1272.36 ft
Upstream HGL Elevation = 1272.47 ft
Downstream EGL Elevation = 1272.53 ft
Upstream EGL Elevation = 1272.64 ft
Upstream Soffit Elevation = 1270.29 ft + 1.50 ft = 1271.79 ft
4.9
Using procedures from Step 4.3.1 and 4.3.2 calculate friction slope and headloss
for storm drain segment 010010. Based on HGL elevation at J010015 storm drain
segment 010010 starts in full flow.
2
2.66
= 0.0020 ft/ft
S f = 0.0049 -----------------------------------------------4/3
( 2 ) ( 32.2 ) ( 0.375 )
4-49
hf = Sf L
(4.6)
h f = ( 0.0020 ) ( 10 ft ) = 0.02 ft
4.9.2
The first step, is to determine if the HGL is above or below the soffit at
the junction. If the HGL is above the soffit proceed assuming full flow
conditions. Verify by checking that the HGL at the upstream end of
pipe segment 010005 is high enough to inundate the junction soffit.
Storm drain segment 010005s soffit elevation at junction J010010 =
1270.31 ft + 1.5 ft (pipe diameter) = 1271.81 ft
From Step 4.8.3 and 4.9.1 HGL at downstream end of J010010 =
1272.47 ft + 0.02 ft = 1272.49 ft. The junction is submerged. Assume
full flow conditions.
4.9.2.2
2 ( Q 2 V 2 Q 1 V 1 Q 3 V 3 Cos ) V 12 V 22
h j = ---------------------------------------------------------------------------+ ------ -----( A 1 + A 2 )g
2g 2g
(4.10b)
where:
4-50
h j = 0.06 ft
4.9.3
Record friction and junction headlosses and summation of headlosses for storm
drain segment 010010 in appropriate calculation sheet columns. Calculate HGL
and EGL and record.
Total Head Loss = 0.02 ft + 0.06 ft = 0.08 ft
Downstream HGL Elevation = 1272.47 ft
Upstream HGL Elevation = 1272.55 ft
Downstream EGL Elevation = 1272.64 ft
Upstream EGL Elevation = 1272.66 ft
Upstream Soffit Elevation = 1270.31 ft + 1.5 ft = 1271.81 ft
4.10
1.92
= 0.0010 ft/ft
S f = 0.0049 -----------------------------------------------4/3
( 2 ) ( 32.2 ) ( 0.375 )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
Design peak discharges and initial pipe sizes to be used in calculating the hydraulic grade line for
proposed connector pipes draining catch basins have been determined in steps 1 and 2. Two
types of headlosses are primarily associated with connector pipes segments, losses due to fric-
4-51
tion and inlet headlosses. The hydraulic grade line and energy grade line in the main storm drain
at the junction is used as the starting HGL for the connector pipe. THe HGL and EGL at the
upstream end of the connector pipe is computed using the velocity in the connector pipe.
5.1
Determine starting water surface elevation. From Step 4.8.3 starting HGL at
J010015 is equal to 1272.47 ft.
5.1.2
Using procedures from Step 4.3.1 and 4.3.2 calculate friction slope and headloss
for connector pipe P0107. Based on HGL elevation at J010015 connector pipe
P0107 starts in full flow. Note catch basin at 0107 also intercepts 0.4 cfs overflow
from 0105 for a total interception of 1.6 cfs.
2
1.30
= 0.0006 ft/ft
S f = 0.0049 --------------------------------------------4/3
( 2 ) ( 32.2 ) ( 0.31 )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
h f = ( 0.0006 ) ( 36 ft ) = 0.02 ft
5.1.3
To calculate the inlet headloss for 0107, Table 5.1 from Chapter 5 must
be used to determine the entrance loss coefficient. For the example
the type of structure used to determine the coefficient was Pipe, Concrete: headwall, square edge, (ken):
k en = 0.5
5.1.3.2
V
h i = ( 1 + k en ) -----2g
(4.17)
2
1.30
h i = ( 1 + 0.5 ) ----------------------- = 0.04 ft
( 2 ) ( 32.2 )
5.1.4
Record friction and inlet headlosses and summation of headlosses for connector
pipe P0107 in appropriate calculation sheet (see Table E.5) columns. Calculate
HGL and EGL and record. Check to verify that there is 1 ft of freeboard between
the EGL and the inlet elevation.
Total Head Loss = 0.02 ft + 0.04 ft = 0.06 ft
Downstream HGL Elevation = 1272.47 ft
Upstream HGL Elevation = 1272.53 ft
Downstream EGL Elevation = 1272.64 ft
4-52
Determine starting water surface elevation. From Step 4.9.2 starting HGL at
J010010 is equal to 1272.55 ft.
5.2.2
Using procedures from Step 4.3.1 and 4.3.2 calculate friction slope and headloss
for connector pipe P0108. Based on HGL elevation at J010010 connector pipe
P0108 starts in full flow.
2
1.38
- = 0.0007 ft/ft
S f = 0.0049 ------------------------------------------------4/3
( 2 ) ( ( 32.2 ) ( 0.31 ) )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
h f = ( 0.0007 ) ( 35 ft ) = 0.02 ft
5.2.3
To calculate the inlet headloss for 0108, Table 5.1 from Chapter 5 must
be used to determine the entrance loss coefficient. For the example
the type of structure used to determine the coefficient was Pipe, Concrete: headwall, square edge, (ken):
k en = 0.5
5.2.3.2
V
h i = ( 1 + k en ) -----2g
(4.17)
2
1.38
h i = ( 1 + 0.5 ) ----------------------- = 0.04 ft
( 2 ) ( 32.2 )
5.2.4
Record friction and inlet headlosses and summation of headlosses for connector
pipe P0108 in appropriate calculation sheet (see Table E.5) columns. Calculate
HGL and EGL and record.
Total Head Loss = 0.02 ft + 0.04 ft = 0.06 ft
Downstream HGL Elevation = 1272.55 ft
Upstream HGL Elevation = 1272.61 ft
Downstream EGL Elevation = 1272.66 ft
4-53
Determine starting water surface elevation. From Step 4.10.2 starting HGL at
J010005 is equal to 1272.74 ft.
5.3.2
Using procedures from Step 4.3.1 and 4.3.2 calculate friction slope and headloss
for connector pipe P0106. Based on HGL elevation at J010005 connector pipe
P0106 starts in full flow.
2
1.79
= 0.0012 ft/ft
S f = 0.0049 --------------------------------------------4/3
( 2 ) ( 32.2 ) ( 0.31 )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
h f = ( 0.0012 ) ( 38 ft ) = 0.05 ft
5.3.3
To calculate the inlet headloss for 0106, Table 5.1 from Chapter 5 must
be used to determine the entrance loss coefficient. For the example,
the type of structure used to determine the coefficient was Pipe, Concrete: headwall, square edge, (ken):
k en = 0.5
5.3.3.2
V
h i = ( 1 + k en ) -----2g
(4.17)
2
1.79
h i = ( 1 + 0.5 ) ----------------------- = 0.07 ft
( 2 ) ( 32.2 )
5.3.4
Record friction and inlet headlosses and summation of headlosses for connector
pipe P0106 in appropriate calculation sheet (see Table E.5) columns. Calculate
HGL and EGL and record.
Total Head Loss = 0.05 ft + 0.07 ft = 0.12 ft
Downstream HGL Elevation = 1272.74 ft
Upstream HGL Elevation = 1272.86 ft
Downstream EGL Elevation = 1272.80 ft
Upstream EGL Elevation = 1272.91 ft
Curb opening inlet/gutter Elevation = 1274.24 ft
4-54
5.4
Determine starting water surface elevation. From Step 4.10.2 starting HGL at
J010005 is equal to 1272.74 ft.
5.4.2
Using procedures from Step 4.3.1 and 4.3.2 calculate friction slope and headloss
connector pipe P0105. Based on HGL elevation at J010005 connector pipe
P0105 starts in full flow. Note catch basin at 0105 only intercepts 0.8 cfs.
2
0.65
= 0.0002 ft/ft
S f = 0.0049 --------------------------------------------4/3
( 2 ) ( 32.2 ) ( 0.31 )
The headloss due to friction is calculated using Equation (4.6):
hf = Sf L
(4.6)
h f = ( 0.0002 ) ( 36 ft ) = 0.01 ft
5.5
To calculate the inlet headloss for 0105, Table 5.1 from Chapter 5 must be used to
determine the entrance loss coefficient. For the example the type of structure
used to determine the coefficient was Pipe, Concrete: headwall, square edge,
(ken):
k en = 0.5
5.5.2
V
h i = ( 1 + k en ) -----2g
(4.17)
2
0.65
h i = ( 1 + 0.5 ) ----------------------- = 0.01 ft
( 2 ) ( 32.2 )
5.5.3
Record friction and inlet headlosses and summation of headlosses for connector
pipe P0105 in appropriate calculation sheet (see Table E.5) columns. Calculate
HGL and EGL and record.
Total Head Loss = 0.00 ft + 0.01 ft = 0.01 ft
Downstream HGL Elevation = 1272.74 ft
Upstream HGL Elevation = 1272.76 ft
Downstream EGL Elevation = 1272.80 ft
Upstream EGL Elevation = 1272.77 ft
Curb opening inlet/gutter Elevation = 1274.23 ft
4-55
Step 6.
Confirm adequate cover over all pipes and check freeboard at all catch basins,
manholes and junctions.
Step 7.
SUMMARIZED RESULTS:
Hydraulic grade line calculation summary sheets are provided as Table E.4 and Table E.5. Figure 4.13 displays the final HGL profile calculated for the proposed storm drain.
4-56
FIGURE 4.13
FINAL HGL PROFILE FOR PROPOSED STORM DRAIN
4-57
4-58
1270.31
1270.29
1270.24
1270.05
1269.30
1268.30
1266.80
010010
010015
010020
010025
010030
010035
010040
OUTLET
1270.79
010005
1265.50
1266.80
1268.80
1269.80
1270.05
1270.24
1270.29
1270.31
(ft)
(ft)
Invert
Elevation
(Outlet)
Invert
Elevation
(Inlet)
Conveyance
ID
Outlet
1 - 48 Pipe
1 - 48 Pipe
1 - 24 Pipe
1 - 18 Pipe
1 - 18 Pipe
1 - 18 Pipe
1 - 18 Pipe
1 - 18 Pipe
(in)
Size
0.013
0.013
0.013
0.013
0.013
0.013
0.013
0.013
Manning's
n
12.57
12.57
3.14
1.77
1.77
1.77
1.77
1.77
(ft )
Flow
Area
105.20
102.00
5.80
5.80
5.80
5.80
4.70
3.40
(cfs)
Design
Discharge
Hydraulic Data
8.37
8.11
1.85
3.28
3.28
3.28
2.66
1.92
(fps)
Velocity
1.09
1.02
0.05
0.17
0.17
0.17
0.11
0.06
(ft)
v /2g
0.0049
0.0049
0.0049
0.0049
0.0049
0.0049
0.0049
0.0049
10
1.00
1.00
0.50
0.38
0.38
0.38
0.38
0.38
11
(ft)
0.0163
0.0050
0.0025
0.0025
0.0025
0.0025
0.0025
0.0025
12
(ft/ft)
Slope
0.0053
0.0050
0.0007
0.0030
0.0030
0.0030
0.0020
0.0010
13
(ft/ft)
Sf
TABLE E.4
HYDRAULIC GRADE LINE CALCULATION SHEET
10
20
75
100
200
300
80
010010
010015
010020
010025
010030
010035
010040
OUTLET
190
010005
15
(ft/ft)
(ft)
14
Average
Sf
Length
Conveyance
ID
Hydraulic
Data Cont.
1.09
16
(ft)
ho
0.42
1.50
0.14
0.30
0.23
0.06
0.02
0.19
17
(ft)
hf
0.11
0.05
0.06
18
(ft)
hj
0.05
19
(ft)
hmh
0.11
0.03
20
(ft)
hb
Head Losses
0.03
21
(ft)
ht
1.09
0.53
1.55
0.00
0.17
0.41
0.26
0.11
0.08
0.00
0.19
22
(ft)
Total
Head
Loss
1270.99
1271.52
1273.07
1271.69
1272.10
1272.36
1272.47
1272.55
1272.74
23
(ft)
Inlet
1269.90
1270.99
1271.52
1271.52
1271.69
1272.10
1272.36
1272.47
1272.55
24
(ft)
Outlet
HGL
1272.08
1272.61
1274.09
1271.74
1272.27
1272.53
1272.64
1272.66
1272.80
25
(ft)
Inlet
1269.90
1272.08
1272.61
1272.61
1271.74
1272.27
1272.53
1272.64
1272.66
26
(ft)
Outlet
EGL
1271.22
1272.72
1271.55
1271.76
1271.95
1272.00
1272.02
1272.50
27
(ft)
Inlet
1269.92
1271.22
1271.05
1271.51
1271.76
1271.95
1272.00
1272.02
28
(ft)
Outlet
Crown
Elevation
Table E.4
Hydraulic Grade Line Calculation Sheet (Continued)
4-59
4-60
38
35
36
P0106
P0108
P0107
15
15
15
15
3.58
3.60
3.50
3.50
(ft)
Catch
Basin
Depth
36
P0105
(ft)
(ft)
2
Lateral
Size
Length
Of
Lateral
Connector
ID
0107
0108
0106
0105
Inlet
ID
0.50
0.50
0.50
0.50
Entrance
Loss, Ke
0.04
0.04
0.07
0.01
(ft)
hi
Connector Pipe
0.02
0.02
0.05
0.01
(ft)
hf
0.06
0.06
0.12
0.02
(ft)
htotal
1272.53
1272.61
1272.86
1272.76
10
(ft)
HGL
at
Inlet
1273.73
1273.73
1274.24
1274.23
11
(ft)
Catch
Basin
Inlet
Elevation
0.20
0.12
0.38
0.47
12
(ft)
Head
Between 1'
Below Lip
of Gutter
to Inlet
H.G.L 1
TABLE E.5
CONNECTOR PIPE SUMMARY
4.7
REFERENCES
4-61
4.8
The following pressure plus momentum method for evaluating junctions are offered to aid the
designer in situations in which crowns of pipes at a storm drain junction are not matching. The
method is taken from Orange County Flood Control District Design Manual, July 1972.
Junctions should be analyzed by the specific force (pressure plus momentum, P+M) method if
the incremental increase in flow is more than 10 percent of the flow in the main channel or if the
incremental increase, regardless of magnitude, could adversely affect the system. Structures
flowing at slightly supercritical velocities are especially susceptible to adverse affects from side
inflows.
The P+M method (based on Newtons second law of motion) has been expanded from the Corps
of Engineers open channel analysis to include all junctions.
The general equilibrium equation is:
P 2 + M 2 = P 1 + M 1 + M 3 cos + P i + P w P f
where:
P1
P2
Pi
Ps =
Pw
Pf
M1
M2
M3 cos =
P = wAy (lbs)
where:
4-62
w =
A =
M = wQV g (lbs/s)
However, since the unit weight of water (w) appears in all terms of the general equilibrium equation it may be omitted and the dimension for P+M becomes feet to the third power.
Since most applications of junction analysis involve relatively small elevation changes simplifying
assumption have been made that cosines of the invert slope equal unity and tangents and sines
of the friction slope are equal.
The designer should recognize that components of wall and invert pressures may be either positive or negative and should be used accordingly.
Often when a confluence is within a transition from trapezoidal to rectangular shape (or reverse),
a portion of the invert and wall pressures are of negative sign. These can be measured by superimposing the end areas of the sections over each other and developing a graphical representation of the negative areas. By adding algebraically the component Ays, a reasonable
approximation of the wall and invert pressures is obtained.
4-63
FIGURE 4.A1
CIRCULAR CONDUIT FLOWING PARTIALLY FULL, PIPE INLET
(Orange County Flood Control District, 1972)
4-64
TABLE 4.A1
PRESSURE PLUS MOMENTUM FACTORS FOR PARTIALLY FULL CIRCULAR CONDUITS
(Orange County Flood Control District, 1972)
4-65
4-66
5
5
TABLE OF CONTENTS
5
5.1
SYMBOLS
=
=
A
B
Ch
Cr
Cs
5-1
dc
ds
d50
D
D.I.
ELo
ELho
FALL
g
H
Hb
Hj
Ht
Hv
HW
HWr
ho
ht
Kb
Ke
Kt
L
L1
La
Lr
Lx
n
n1
PI
Q
Qo
Rc
S
Sv
TW
5-2
= Inlet bevel, in
=
Critical depth, ft
Diameter of a rock particle for which 50% of the gradation is finer by weight (other per-
=
=
=
Velocity head, ft
=
=
Submergence factor
=
=
Length of apron, ft
=
=
Manning's n-value
Desired Manning's n-value
=
=
=
= Slope, ft/ft
= Saturated shear strength, lb/ft2
=
t
c
Time, minutes
V
Va
Wa
y
ye
ys
=
=
Velocity, ft/sec
Approach channel velocity, ft/sec
Width of apron, ft
=
=
Depth of scour, ft
5.2
INTRODUCTION
Culverts and bridges are structures that convey stormwater under roads. Their purpose is to prevent water from the more frequent storm events from overtopping and crossing the road as such
conditions inhibit safe passage of vehicles. The intent of this chapter is to provide guidance for
the design of culverts. This includes the necessary design aids/examples and guidance for treatment of culvert inlets and outlets. Some brief guidelines are presented to follow when using
inverted siphons. The design of bridges requires special training and experience in regard to
hydraulic analyses, design of flow training works, and estimates of pier and abutment scour.
Therefore, only an overview of the hydraulic analyses for bridge openings is presented.
5.3
CULVERTS
The charts and procedures for culvert design used in this manual are taken from the Federal
Highway Administration, Hydraulic Design Series Number 5, Hydraulic Design of Highway
Culverts (USDOT, FHWA, HDS-5, 1985). Culvert designers use this reference liberally as it is the
result of years of research and experience in culvert design and at this time represents the state
of the art.
5-3
Minimum Velocity
Culverts should be designed to provide adequate velocity to self-clean during partial depth flow
events. Debo and Reese (1995) suggest a minimum velocity of 2.5 feet per second for partial
flow depths. Greater velocities are recommended for installations where sediment loads are
heavy. Alternatively, a sediment trap can be utilized where culvert velocities are lower or excessive sediment deposition is expected.
Maximum Velocity
As a practical limit, outlet velocities should be kept below 15 feet per second unless special conditions exist. The maximum velocity should be consistent with channel stability requirements at
the culvert outlet. As outlet velocities increase, the need for channel stabilization at the culvert
outlet increases. If culvert outlet velocities exceed permissible velocities for the outlet channel lining material, suitable outlet protection must be provided. Outlet velocities may exceed permissible downstream channel velocities by up to 10 percent without providing outlet protection if the
culvert tailwater depth is greater than the culvert critical depth of flow under design flow conditions. Table 6.2 and Table 6.3 outline the permissible velocities for several channel lining materials.
Materials
The selection of a culvert material may depend upon structural strength, hydraulic roughness,
durability, and corrosion and abrasion resistance. The culvert materials that should be considered are concrete (reinforced and non-reinforced), corrugated aluminum, corrugated steel, and
PVC. Culverts may also be lined with other materials to inhibit corrosion and abrasion. Linings
are not recommended to reduce hydraulic resistance because culvert linings have a short life
span and are seldom reapplied as part of normal culvert maintenance. When linings are applied,
the culvert sizing should neglect the reduced roughness from the lining material.
Minimum Cover
Minimum cover of fill over culverts must be provided to maintain the structural integrity of the
structure under anticipated loading conditions. Culvert manufacturers provide minimum cover
requirements for prefabricated pipe. A general rule of thumb for estimating minimum cover
requirements is to provide one-eighth of the barrel diameter or span, with a minimum of 1 foot.
The top of culverts should not extend into the roadway subgrade. Minimum cover should be measured from the top of subgrade, which is the bottom of the pavement structural section.
5-4
Skewed Channels
A good culvert design is one that limits the hydraulic and environmental stress placed on an
existing natural watercourse. This stress can be minimized by designing a culvert that closely
conforms to the natural stream in alignment and grade. Often the culvert barrel must be skewed
with respect to the roadway centerline to accomplish this goal. Alterations to the normal inlet
alignment are often necessary as well.
The alignment of a culvert barrel with respect to a line perpendicular to the roadway centerline at
5-5
the point of crossing is referred to as the barrel skew angle. A culvert aligned normal to the roadway centerline has a zero skew angle. Directions (right or left) must accompany the barrel skew
angle (Figure 5.1). Some advantages of following a natural stream alignment include: reduction
of entrance losses, equal depths of scour at the footings, less sedimentation, and less excavation
for installation.
The angle from the culvert face to a line normal to the culvert barrel is referred to as the inlet
skew angle (Figure 5.2). The structural integrity of circular sections is compromised when the
inlet is skewed due to the loss of a portion of the full circular section where the culvert barrel
extends beyond the full section. Although concrete headwalls help stabilize the pipe section,
structural considerations should not be overlooked in the design of skewed inlets. Culverts which
have a barrel skew angle often have an inlet skew angle as well. This is because headwalls are
generally constructed parallel to a roadway centerline to avoid warping of the embankment fill.
In cases where the culvert barrel cannot be aligned with the channel flowline, such as when
runoff is directed along a roadway embankment to a suitable crossing location, the flow enters
the culvert barrel at an angle. The approach angle should be limited to a maximum of 90
degrees. When high velocities exist, inlet losses resulting from turning the flow into the culvert
should be considered. If backwater computations are not employed and the approach channel
velocity is 6 feet per second or greater, the following equation should be used to estimate the
loss. The loss should be added to the other inlet losses in the culvert design computation, if they
aren't included in the appropriate nomographs.
2
Va
H t = ------ sin a
2g
(5.1)
FIGURE 5.1
BARREL SKEW ANGLE
(USDOT, FHWA, HDS-5, 1985)
5-6
FIGURE 5.2
INLET SKEW ANGLE
(USDOT, FHWA, HDS-5, 1985)
5-7
FIGURE 5.3
TYPICAL HEADWALL/WINGWALL CONFIGURATIONS FOR SKEWED CHANNELS
(USDOT, FHWA, HDS-5, 1985)
Bends
A straight culvert alignment is desirable to avoid clogging, increased construction costs, and
reduced hydraulic efficiency. However, site conditions may require a change of alignment, either
horizontally or vertically. When considering a nonlinear culvert alignment, particular attention
should be given to erosion, sedimentation, and debris control. Vertical bends are permitted when
they transition from a flatter to a steeper slope, but should not transition from steeper to flatter
slopes because of the potential for sediment deposition in the flatter reach.
5-8
FIGURE 5.4
"BROKEN BACK" CULVERT
(USDOT, FHWA, HDS-5, 1985)
In designing a nonlinear culvert, the energy losses due to the bends must be considered. If the
culvert operates in inlet control, no increase in headwater occurs unless the bend losses cause
the culvert to flow under outlet control. If the culvert operates in outlet control, an increase in
energy losses and headwater will result due to the bend losses. To minimize these losses, the
culvert should be curved or have bends not exceeding 15 degrees at intervals of not less than 50
feet. Under these conditions, bend losses can be ignored.
If these conditions cannot be met, analysis of bend losses is required. Bend losses are a function
of the velocity head in the culvert barrel. To calculate bend losses, use the following equation:
2
V
H b = K b -----2g
(5.2)
Hb is added to the other outlet losses. See Chapter 4, Storm Drains, to determine loss coefficients (Kb) for bend losses in conduits flowing full.
The broken back culvert, shown in Figure 5.4, has four possible control sections: the inlet, the
outlet, and the two bends. The upstream bend may act as a control section, with the flow passing through critical depth just upstream of the bend. In this case, the upstream section of the culvert operates in outlet control and the downstream section operates in inlet control. Outlet control
calculation procedures can be applied to the upstream barrel, assuming critical depth at the
bend, to obtain a headwater elevation. This elevation is then compared with the inlet and outlet
control headwater elevations for the overall culvert. The controlling flow condition produces the
highest headwater elevation. Control at the lower bend is very unlikely. That possible control
section can be ignored except for the bend losses in outlet control.
5-9
Junctions
Flow from two or more separate culverts or storm drains may be combined at a junction into a
single culvert barrel. For example, a tributary and a main stream intersecting at a roadway crossing can be accommodated by a culvert junction (Figure 5.5).
FIGURE 5.5
CULVERT JUNCTION
(USDOT, FHWA, HDS-5, 1985)
Loss of head may be important in the hydraulic design of a culvert containing a junction. Attention
should be given to streamlining the junction to minimize turbulence and head loss. Also, timing of
peak flows from the two branches should be considered in analyzing flow conditions and control.
When possible, the tributary flow should be released downstream of the culvert barrel. When this
is not practical, the following procedure should be used to estimate the losses.
For a culvert barrel operating in outlet control and flowing full, the junction loss is calculated using
the equations given below. The loss is then added to the other outlet control losses.
H j = y + H V1 H V 2
(5.3)
Q 2 V 2 Q 1 V 1 Q 3 V 3 cos j
y = ----------------------------------------------------------------0.5 ( A 1 + A 2 )g
(5.4)
The subscripts 1, 2, and 3 refer to the outlet pipe, the upstream pipe, and the lateral pipe respectively.
5-10
Safety
Culverts shall be designed to conform to the safety protocols identified in the introduction to this
manual.
Inlets
Culvert inlets are used to transition the flow from a headwater condition upstream of the culvert
into the culvert barrel. Losses caused by the inlets have been studied extensively for several
types of inlets. The inlet control nomographs in Section 5.3.4 give the required headwater depth
to pass the design discharge through several types of culvert entrances. The hydraulic capacity
of a culvert may be improved by appropriate inlet selection. Since the channel is usually wider
than the culvert barrel, the culvert inlet edge represents a flow contraction and may be the primary flow control. The provision of a more gradual flow transition will lessen the energy loss and
thus create a more hydraulically efficient inlet condition. Design charts for improved inlets are
contained in Hydraulic Design of Highway Culverts (USDOT, FHWA, HDS No. 5, September
1985). It should be noted that improving culvert inlets will cause the greatest increase in culvert
capacity when the culvert is operating in inlet control.
5-11
The hydraulic performance of culverts operating in inlet control can be improved by changing the
inlet geometry of the headwall. Improvements include bevel-edged, side-tapered, and
slope-tapered inlets. The advantage of these improvements is to convert an inlet control culvert
closer to outlet control by using more of the barrel capacity.
A beveled-edge provides a decrease in flow contraction losses at the inlet and the entrance loss
coefficient, Ke is normally reduced to 0.2, which can increase the culvert capacity by as much as
20 percent. Bevels are required on all culverts with headwalls and should be constructed as
shown in Figure 5.6.
Side-tapered inlets have an enlarged face area accomplished by tapering sidewalls as shown in
Figure 5.7. It provides an increase in flow capacity of 25 to 40 percent over square-edged inlets.
There are two types of control sections for side-tapered inlets; face and throat control. The
advantages of side-tapered inlets under throat control are; reduced flow contraction at the throat
and increased head at the throat control section.
Slope-tapered inlets provide additional head at the throat section as shown in Figure 5.8. This
type of inlet can have over 100 percent greater capacity than a conventional culvert with square
edges. The degree of increased capacity depends upon the drop between the face and the throat
section. Both the face and the throat are possible control sections. The inlet face should be
designed with a greater capacity than the throat to promote flow control at the throat and therefore greater potential capacity of the culvert. This type of inlet may not be appropriate for flows
containing high sediment loads; caution should be excised for this design condition.
Prefabricated steel inlet end sections (Figure 5.9) are available for corrugated steel pipe that perform about as well as a square-edged headwall inlet with an entrance loss coefficient of 0.5.
When there is a potential for inlet uplift failure or inlet damage from other sources, concrete headwalls are recommended. In some cases, such as when concrete encasement of the pipe is
utilized, metal end sections such as the one shown in Figure 5.9 may be acceptable.
5-12
FIGURE 5.6
INLET BEVEL DETAIL
(USDOT, FHWA, HDS-5, 1985)
FIGURE 5.7
SIDE-TAPERED INLET
(USDOT, FHWA, HDS-5, 1985)
5-13
FIGURE 5.8
SLOPE-TAPERED INLET
(USDOT, FHWA, HDS-5, 1985)
FIGURE 5.9
PREFABRICATED CULVERT END SECTION
5-14
Outlets
The receiving channel at culvert outlets must be protected from high culvert outlet velocities
caused by the flow constriction that is inherent in culvert operation. If the culvert outlet velocity is
greater than the allowable velocity for the receiving channel, protective measures must be provided.
Projecting culvert outlets are not permitted unless approved by the appropriate governing
agency.
The minimum requirement is to provide a preformed metal or concrete end section, or a headwall
(with or without a wingwall configuration) with a cutoff wall provided at the end of the apron. Culvert outlet designs are presented in Section 5.4. Energy dissipation structures, if needed are presented in Chapter 8, Hydraulic Structures, Section 8.4.
5-15
FIGURE 5.10
CULVERT DESIGN FORM
(USDOT, FHWA, HDS-5, 1985)
5-16
Inlet Control
The inlet control calculations determine the headwater elevation required to pass the design flow
through the selected culvert configuration if the culvert is operating in inlet control. The inlet control nomographs in Section 5.3.4 are used in the design process. For the following discussion,
refer to the schematic inlet control nomograph shown in Figure 5.11.
1. Locate the selected culvert size (point 1) and flow rate (point 2) on the appropriate scales of
the inlet control nomograph. (Note that for box culverts, the flow rate per foot of barrel width is
used.)
2. Using a straightedge, extend a straight line from the culvert size (point 1) through the flow
rate (point 2) and mark a point on the first headwater/culvert height (HW/D) scale (point 3).
The first HW/D scale is also a turning line.
3. If another HW/D scale is required, extend a horizontal line from the first HW/D scale (the
turning line) to the desired scale and read the result.
4. Multiply HW/D by the culvert height, D, to obtain the required headwater (HW) from the invert
of the control section to the energy grade line. HW equals the required headwater depth. If
trashracks are used, add trashrack losses to HW.
5. Calculate the inlet control headwater elevation.
EL hi = EL i + HW
where EL i is the invert elevation at the inlet.
6. If the inlet control headwater elevation exceeds the design headwater elevation determined
in the first step and tabulated on Figure 5.10, a new culvert configuration must be selected
and the process repeated. Improvements to the inlet may suffice, or an enlarged barrel may
be necessary, particularly if the outlet control headwater elevation calculated in the following
section also exceeds the design headwater elevation.
Outlet Control
The outlet control calculations result in the headwater elevation required to convey the design
discharge through the selected culvert if the culvert is operating in outlet control. The critical
depth charts and outlet control nomographs of Section 5.3.4 are used in the design process. For
illustration, refer to the schematic critical depth chart and outlet control nomograph shown in Figure 5.12 and Figure 5.13, respectively.
5-17
FIGURE 5.11
INLET CONTROL NOMOGRAPH (SCHEMATIC)
(USDOT, FHWA, HDS-5, 1985)
1. Determine the tailwater depth above the outlet invert (TW) at the design flow rate. This is
obtained from backwater or normal depth calculations of the downstream channel, or from
field observations. Field observations are important in determining tailwater depths. The area
downstream of the culvert should be examined for features that may create backwater
effects, i.e., channel control, another culvert, etc. If such features are found, appropriate
backwater analysis techniques should be employed to determine the tailwater depth. When
5-18
culverts are in series, the headwater elevation from the downstream culvert should be
checked to make sure that it doesn't back up water affecting the outlet conditions of the
upstream culvert.
2. Enter the appropriate critical depth chart (Figure 5.12) with the flow rate and read the critical
depth (dc). If the computed dc is greater than D, use D for critical depth. dc cannot exceed the
top of the culvert.
(Note: The dc curves are truncated for convenience when they converge. If an accurate dc is
required for dc much greater than 0.9D, consult the Handbook of Hydraulics by Brater and
King, 1976, or other hydraulic references.)
3. Calculate ( d c + D ) 2
4. Determine the depth from the culvert outlet invert to the hydraulic grade line (ho).
h o = TW or ( d c + D ) 2 , whichever is larger
5. From Table 5.1 obtain the appropriate entrance loss coefficient, Ke, for the culvert inlet configuration.
FIGURE 5.12
CRITICAL DEPTH CHART (SCHEMATIC)
(USDOT, FHWA, HDS-5, 1985)
5-19
6.
Determine the losses through the culvert barrel, H, using the outlet control nomograph
(Figure 5.13) or appropriate equations if outside the range of the nomograph.
a) If the Manning's n-value given in the outlet control nomograph is different than the
Manning's n for the culvert, adjust the culvert length using the equation:
n1 2
L 1 = L -----
n
(5.5)
Then use L1 rather than the actual culvert length when using the outlet control
nomograph.
b) Using a straightedge, connect the culvert size (point 1) with the culvert length on the
appropriate Ke scale (point 2). This defines a point on the turning line (point 3).
c) Again using the straightedge, extend a line from the discharge (point 4) through the
point on the turning line (point 3) to the Barrel Losses (H) scale. Read H, which is
the energy loss through the culvert, including entrance, friction, and outlet losses.
d) All other applicable losses should be added to H.
7.
EL ho = EL o + H + h o
(5.6)
If the outlet control headwater elevation exceeds the design headwater elevation determined in the first step, and tabulated on Figure 5.10, a new culvert configuration must be
selected and the process repeated. Generally, an enlarged barrel will be necessary since
inlet improvements are of limited benefit in outlet control.
Evaluation of Results
Compare the headwater elevations calculated for inlet and outlet control. The higher of the two is
designated the controlling headwater elevation. The culvert can be expected to operate with that
higher headwater for at least part of the time.
The outlet velocity is calculated as follows:
1.
5-20
If the controlling headwater is based on inlet control, determine the normal depth and
velocity in the culvert barrel. The velocity at normal depth is assumed to be the outlet
velocity (Figure 5.14). Normal depth for circular and rectangular culverts can be found
using Figure 5.19.
FIGURE 5.13
OUTLET CONTROL NOMOGRAPH (SCHEMATIC)
(USDOT, FHWA, HDS-5, 1985)
2.
If the controlling headwater is in outlet control, determine the area of flow and velocity at
the outlet based on the barrel geometry (see Figure 5.15) and the following:
a)Critical depth, if the tailwater is below critical depth.
b)The tailwater depth if the tailwater is between critical depth and the top of the barrel.
c) The height of the barrel if the tailwater is above the top of the barrel.
5-21
FIGURE 5.14
OUTLET VELOCITY - INLET CONTROL
(USDOT, FHWA, HDS-5, 1985)
Repeat the design process until an acceptable culvert configuration is determined. Once the
barrel is selected it must be fitted into the roadway cross section. The culvert barrel must have
adequate cover, the length should be close to the approximate length, and the headwalls and
wingwalls must be dimensioned.
If outlet control governs and the headwater depth (referenced to the inlet invert) is less than 1.2D,
it is possible that the barrel flows partly full through its entire length. In this case, caution should
be used in applying the approximate method of setting the downstream elevation based on the
greater of tailwater or ( d c + D ) 2 . If an accurate headwater is necessary, backwater calculations
should be used to check the result from the approximate method. If the headwater depth falls
below 0.75D, the approximate method should not be used.
If the selected culvert will not fit the site, return to the culvert design process and select another
culvert. After a selected culvert is found to meet the design conditions, document the design to
this point. Culvert design documentation shall include a performance curve which displays culvert behavior over a range of discharges. Development of performance curves is presented later
in this section, and Example 4 in Section 5.3.5 contains a performance curve calculation.
Additional design considerations including stage discharge ratings, roadway overtopping, and
performance curves, are discussed in the following sections.
5-22
Performance Curves
Performance curves are representations of flow rate versus headwater depth or stage for a culvert. Because a culvert has several possible control sections (inlet, outlet, throat), a given installation will have a performance curve for each control section and one for roadway overtopping.
The overall culvert performance curve is made up of the controlling portions of the individual performance curves for each control section.
Inlet Control - The inlet control performance curves are developed using the inlet control nomographs of Section 5.3.4. The headwaters corresponding to the series of flow rates are determined and then plotted. The transition zone is inherent in the nomographs.
Outlet Control - The outlet control performance curves are developed using the outlet control
nomographs of Section 5.3.4. Flows bracketing the design flow are selected. For these flows, the
total losses through the barrel are calculated or read from the outlet control nomographs. The
losses are added to the elevation of the hydraulic grade line at the culvert outlet to obtain the
headwater.
If backwater calculations are performed beginning at the downstream end of the culvert, friction
losses are accounted for in the calculations. Adding the inlet loss to the energy grade line in the
barrel at the inlet results in the headwater elevation for each flow rate. An example of
development of a performance curve is contained in Example 4 in Section 5.3.5.
5-23
FIGURE 5.15
OUTLET VELOCITY OUTLET CONTROL
(USDOT, FHWA, HDS-5, 1985)
Roadway Overtopping - A performance curve showing the culvert flow as well as the flow
across the roadway is a useful analysis tool. Rather than using a trial and error procedure to
determine the flow division between the overtopping flow and the culvert flow, an overall performance curve can be developed. The performance curve depicts the sum of the flow through the
culvert and the flow across the roadway.
5-24
FIGURE 5.16
CULVERT PERFORMANCE CURVE WITH ROADWAY OVERTOPPING
(USDOT, FHWA, HDS-5, 1985)
The overall performance curve can be determined by performing the following steps:
1.
Select a range of flow rates and determine the corresponding headwater elevations for
the culvert flow alone. These flow rates should fall above and below the design discharge and cover the entire flow range of interest. Both inlet and outlet control headwaters should be calculated. It is recommended that the 2-, 10-, 50- and 100-year flow
rates be included in the range of flow rates considered.
2.
Combine the inlet and outlet control performance curves to define a single performance
curve for the culvert based on the controlling stage for each discharge.
3.
When the culvert headwater stages exceed the roadway crest elevation, overtopping
will begin. Calculate the equivalent upstream water surface depth above the roadway
(crest of weir) for each selected flow rate. Use these water surface depths and Equation
(5.7a) or Equation to calculate flow rates across the roadway.
4.
Add the culvert flow and the roadway overtopping flow at the corresponding headwater
elevations to obtain the overall culvert performance curve.
Using the combined culvert performance curve, it is an easy matter to determine the headwater
stage for any flow rate, or to visualize the performance of the culvert installation over a range of
5-25
flow rates. When roadway overtopping begins, the rate of headwater increase will diminish. The
headwater will rise very slowly from that point on. Figure 5.16 depicts an overall culvert
performance curve with roadway overtopping. Example 4 in Section 5.3.5 illustrates the
development of an overall culvert performance curve. The 100-year discharge should be identified on the performance curve and the corresponding depth of flow over the roadway.
The Federal Highway Administration's computer program, HY8 (USDOT, 1999), can be used in
the development of performance curves. HY8 automates the design methods described in
HDS-5 (USDOT, 1985), and HEC-14 (USDOT, 2006). The U.S. Army Corps of Engineers HEC-2
(USACE, 1990) and HEC-RAS computer programs (USACE, 2001a and 2001b) are also capable
of analyzing culverts. The use of HY8 is preferred for design of culverts that are not subject to
backwater conditions. HEC-RAS is preferred for modeling and design of culverts in river systems where backwater effects are of concern
Roadway overtopping will begin as the headwater rises to the elevation of the lowest point of the
roadway. This type of flow is similar to flow over a broad crested weir. The length of the weir can
be taken as the horizontal length along the roadway. The flow across the roadway is calculated
from the broad crested weir equation:
Q o = K t C r L x ( HW r )
1.5
(5.7a)
where:
(5.7b)
HWra =
flow depth above the roadway at the high end of the weir segment, ft.
HWrb =
flow depth above the roadway at the low end of the weir segment, ft.
5-26
headwater depth for a specific discharge, such as the 100-year discharge can then be read from
the curve. Design Example 4 in Section 5.3.5 illustrates this procedure.
FIGURE 5.17
DISCHARGE COEFFICIENT AND SUBMERGENCE FACTOR FOR ROADWAY OVERTOPPING
(USDOT, FWHA, HDS-5, 1985)
5-27
FIGURE 5.18
WEIR CREST LENGTH DETERMINATIONS FOR ROADWAY OVERTOPPING
(USDOT, FHWA, HDS-5, 1985)
5-28
TABLE 5.1
ENTRANCE LOSS COEFFICIENTS
OUTLET CONTROL, FULL OR PARTLY FULL ENTRANCE HEAD LOSS
(USDOT, FHWA, HDS-5, 1985)
Type of Structure and Design of Entrance
Coefficient, Ke
Pipe, Concrete
Projecting from fill, socket end (grove-end)
0.2
0.5
0.2
Square-edge
0.5
0.2
0.7
0.5
0.2
0.2
0.9
0.5
0.7
0.5
0.2
0.2
0.5
0.2
0.4
0.2
0.5
0.7
0.2
5-29
FIGURE 5.19
CURVES FOR DETERMINING THE NORMAL DEPTH
(Chow, 1959)
5-30
FIGURE 5.20
INLET CONTROL HEADWATER DEPTH FOR CONCRETE PIPE CULVERTS
(USDOT, FHWA, HDS-5, 1985)
5-31
FIGURE 5.21
INLET CONTROL HEADWATER DEPTH FOR C.M. PIPE
(USDOT, FHWA, HDS-5, 1985)
5-32
FIGURE 5.22
INLET CONTROL HEADWATER DEPTH FOR CIRCULAR PIPE CULVERTS WITH BEVELED RING
(USDOT, FHWA, HDS-5, 1985)
5-33
FIGURE 5.23
CRITICAL DEPTH FOR CIRCULAR PIPE
(USDOT, FHWA, HDS-5, 1985)
5-34
FIGURE 5.24
HEAD FOR CONCRETE PIPE CULVERTS FLOWING FULL
n = 0.012
(USDOT, FHWA, HDS-5, 1985)
5-35
FIGURE 5.25
HEAD FOR C.M. PIPE CULVERTS FLOWING FULL
n = 0.024
(USDOT, FHWA, HDS-5, 1985)
5-36
FIGURE 5.26
INLET CONTROL HEADWATER DEPTH FOR BOX CULVERTS
(USDOT, FHWA, HDS-5, 1985)
5-37
FIGURE 5.27
INLET CONTROL HEADWATER DEPTH FOR RECTANGULAR BOX CULVERT (FLARED WINGWALLS)
Flare Wingwalls (18o to 33.7o, and 45o) and Beveled Edge at the Top of the Inlet
(USDOT, FHWA, HDS-5, 1985)
5-38
FIGURE 5.28
INLET CONTROL HEADWATER DEPTH FOR RECTANGULAR BOX CULVERT (90o HEADWALL)
90o Headwall - Chamfered or Beveled Inlet Edges
(USDOT, FHWA, HDS-5, 1985)
5-39
FIGURE 5.29
CRITICAL DEPTH RECTANGULAR SECTION
(USDOT, FHWA, HDS-5, 1985)
5-40
FIGURE 5.30
HEAD FOR CONCRETE BOX CULVERTS FLOWING FULL
n = 0.012
(USDOT, FHWA, HDS-5, 1985)
5-41
FIGURE 5.31
INLET CONTROL HEADWATER DEPTH FOR OVAL CONCRETE PIPE - LONG AXIS HORIZONTAL
(USDOT, FHWA, HDS-5, 1985)
5-42
FIGURE 5.32
INLET CONTROL HEADWATER DEPTH FOR OVAL CONCRETE PIPE - LONG AXIS VERTICAL
(USDOT, FHWA, HDS-5, 1985)
5-43
FIGURE 5.33
CRITICAL DEPTH FOR AN OVAL CONCRETE PIPE - LONG AXIS HORIZONTAL
(USDOT, FHWA, HDS-5, 1985)
5-44
FIGURE 5.34
CRITICAL DEPTH FOR AN OVAL CONCRETE PIPE - LONG AXIS VERTICAL
(USDOT, FHWA, HDS-5, 1985)
5-45
FIGURE 5.35
HEAD FOR CONCRETE PIPE FLOWING FULL - LONG AXIS HORIZONTAL OR VERTICAL
n = 0.012
(USDOT, FHWA, HDS-5, 1985)
5-46
FIGURE 5.36
HEADWATER DEPTH FOR C.M. PIPE - ARCH CULVERT WITH INLET CONTROL
(USDOT, FHWA, HDS-5, 1985)
5-47
FIGURE 5.37
CRITICAL DEPTH FOR STANDARD C.M. PIPE - ARCH
(USDOT, FHWA, HDS-5, 1985)
5-48
FIGURE 5.38
HEAD FOR STANDARD C.M. PIPE - ARCH CULVERTS FLOWING FULL
n = 0.024
(USDOT, FHWA, HDS-5, 1985)
5-49
Circular pipe culvert, CMP (standard 2-2/3 by 1/2 inch corrugations) with
beveled edge or reinforced concrete pipe with groove end. No FALL.
Example 2:
Reinforced cast-in-place concrete box culvert with square edges and with
bevels. No FALL.
Example 3:
Example 4:
Example 1
A culvert at a new roadway crossing must be designed to pass the 25-year flood. Hydrologic
analysis indicates a peak flow rate of 200 cfs. Use the following site information:
Design a circular pipe culvert for this site. Consider the use of a corrugated metal pipe with
standard 2-2/3 by 1/2 inch corrugations and a headwall with beveled edges, and concrete pipe
with a groove end, projecting. Base the design headwater on the shoulder elevation with a 2-foot
freeboard (elevation 108.0 ft). Set the inlet invert at the natural streambed elevation (no FALL).
Figure 5.39 represents a completed Culvert Design Form for this example. Notice the headwater
depth of 8 feet at the inlet. The designer should verify that backwater from the culvert will not
present a hazard to upstream facilities and that flow will not be diverted into another watercourse.
An easement may be necessary for ponding on private property. Notice the high estimated outlet
velocity of 13.5 fps. The designer should provide outlet erosion control in conformance with Section 5.4.3 or Section 8.4, or investigate other culvert options such as a larger pipe size or multiple
smaller pipes. When making this decision, the designer should consider the geometry and allowable velocity of the receiving channel to be sure that the selected pipe or pipes are appropriate
given the width and depth of the receiving channel. The design should not result in erosion of the
bed, banks or overbanks of the downstream system.
Note: Figure 5.20, Figure 5.21, Figure 5.23, Figure 5.24, Figure 5.25 and Table 5.1 were used in
this example.
5-50
FIGURE 5.39
EXAMPLE 1 CULVERT DESIGN FORM
(USDOT, FHWA, HDS-5, 1985)
5-51
Example 2
A new culvert at a roadway crossing is required to pass a 50-year flow rate of 300 cfs. Use the
following site conditions:
Design a reinforced concrete box culvert for this installation. Try both square edges and 45
degree beveled edges in a 90o headwall. Do not depress the inlet (no FALL).
Figure 5.40 represents a completed Culvert Design form for Problem No. 2. Notice the headwater depth of 10 feet at the inlet. The designer should verify that backwater from the culvert will not
present a hazard to upstream facilities and that flow will not be diverted into another watercourse.
An easement may be necessary for ponding on private property. Notice the high estimated outlet
velocity of 12.2 fps. The designer should provide outlet erosion control in conformance with Section 5.4.3 or Section 8.4, or investigate other culvert options such as a larger pipe size or multiple
smaller pipes. When making this decision, the designer should consider the geometry and allowable velocity of the receiving channel to be sure that the selected pipe or pipes are appropriate
given the width and depth of the receiving channel. The design should not result in erosion of the
bed, banks or overbanks of the downstream system.
Note: Figure 5.26, Figure 5.28, Figure 5.29, Figure 5.30, and Table 5.1 are used in this solution.
5-52
FIGURE 5.40
EXAMPLE 2 CULVERT DESIGN FORM
(USDOT, FHWA, HDS-5, 1985)
5-53
Example 3
Design a culvert to pass a 25-year flow of 180 cfs. Minimum depth of cover for this culvert is 2
feet.
Tailwater Depth: 4 ft
Due to the low available cover over the conduit, use a horizontal elliptical concrete pipe. This
example allows a small depression (FALL) of about 1 ft at the inlet to demonstrate how FALL is
applied. Use of FALL in streams carrying a heavy sediment load, which is the case for most of
Maricopa County, is not recommended.
Refer to Figure 5.41 for a completed Culvert Design Form for this problem.
Note: Figure 5.31, Figure 5.33, Figure 5.35, and Table 5.1 are used in this solution.
5-54
FIGURE 5.41
EXAMPLE 3 CULVERT DESIGN FORM
(USDOT, FHWA, HDS-5, 1985)
5-55
Example 4
Develop a performance curve for the installation in Figure 5.42 below, including roadway overtopping up to 0.5 feet above the roadway. Use the following dimensions:
Tailwater Channel:
Flow, cfs
TW, ft
50
101.8
100
102.6
150
103.1
200
103.5
250
103.8
300
104.2
350
104.4
Figure 5.21, Figure 5.23 and Figure 5.25 were used in completion of the Culvert Design Form.
Figure 5.43 represents a completed Culvert Design Form for this problem. Figure 5.44 provides
the performance curve and roadway overtopping computations.
FIGURE 5.42
EXAMPLE 4 ROADWAY OVERTOPPING AND PERFORMANCE CURVE DEVELOPMENT
5-56
FIGURE 5.43
EXAMPLE 4 CULVERT DESIGN FORM
5-57
FIGURE 5.44
EXAMPLE 4 PERFORMANCE CURVE AND ROADWAY OVERTOPPING COMPUTATIONS
5.4
This section provides guidelines for design of culvert type inlets and outlets to closed conduit systems. Runoff entering and exiting closed conduits may require transitions into and out of the conduit to minimize entrance losses and protect adjacent property and drainage facilities from
possible erosion. Pavement drainage inlets that allow runoff to drop into catch basins are
discussed in Chapter 3, Section 3.3 and are not addressed here.
5-58
5-59
Outlet Structures
Standard measures for scour protection at conduit outlets include cutoff walls, wingwalls with
aprons, and grouted or ungrouted riprap. These measures should be used as appropriate such
that the velocity entering the receiving channel is within the allowable range of velocities for the
channel outlet condition. Outlet conditions are classified as follows:
1.
Natural channel outlets where the existing natural channel is modified only to transition
to and from the culvert.
2.
Artificial channel outlets where the culvert is part of an overall drainage plan and discharges into an improved, artificial channel.
3.
Side channel outlets where a conduit drains into a larger receiving channel from the
side at some angle of confluence.
It is not always desirable to totally restrict the movement of natural channels at the culvert outlet.
Limited downstream scour and channel movement may be allowed in some cases. However, for
artificial channel and side channel outlets, scour and bed movement should not be permitted.
The following criteria shall be used in determining the type of outlet protection required based on
the outlet condition.
Culverts with outlet velocities less than or equal to 1.3 times the average natural stream
velocity for the design discharge should have a cutoff wall as a minimum for protection.
Design criteria for cutoff walls are presented below.
2.
Where the outlet velocity is greater than 1.3 times the natural stream velocity, but less
than 2.5 times, a riprap apron should be provided. Design procedures for riprap aprons
are in Section 8.4.2.
3.
When outlet velocities exceed 2.5 times the natural stream velocity, an energy dissipator
should be provided. Several energy dissipators are described in Chapter 8, Hydraulic
Structures.
5-60
1.
Conduits with outlet velocity less than or equal to the allowable require no outlet protection.
2.
Conduits with outlet velocity greater than one and less than 2.5 times the allowable
velocity should be provided with a riprap, concrete, or other suitable apron to transition
the flow to the allowable channel velocity.
3.
When outlet velocities exceed 2.5 times the allowable channel velocity, an energy dissipator should be provided. Several energy dissipators are described in Chapter 8,
Hydraulic Structures.
Cutoff Walls
A cutoff wall placed at the culvert outlet in a natural wash provides adequate protection of the
downstream end of the culvert when the outlet velocity does not exceed 1.3 times the average
natural stream velocity for the design discharge. Cut-off walls are appropriate where the development of a scour hole will not undermine nearby structures or result in other harmful effects.
Depth of scour for cohesionless materials (0.2mm<=D50<=2.0mm) downstream of culvert structures may be estimated using Equation (5.8) from Hydraulic Design of Energy Dissipators for
Culverts and Channels (USDOT, FHWA, HEC-14, 2006).
0.39
2.27- ----------------------Q -
t - 0.06
-------d s = R c C h C s --------
2.5
1/3
316
g ( R c )
(5.8)
where:
ds =
Rc =
Q =
discharge, cfs
( D 84 D 16 )
0.5
5-61
TABLE 5.2
COEFFICIENT Ch FOR OUTLETS ABOVE THE BED
Hd
Ch
1.00
1.22
1.26
1.34
Cs
1.00
1.03
1.08
>7
1.12
V 2
d s = y e C h C s e ----------
c
0.18
t - 0.10
------- 316
(5.9)
where:
ds = depth of scour hole, ft
ye =equivalent depth ( A 2 )
5-62
12
A =
V =
(5.10)
where:
PI =
The following guidelines, applicable to cutoff walls, are based on the computed depth of scour
hole analysis identified above.
1. The depth of the cutoff wall should be equal to or greater than the maximum depth
of scour hole.
2. The depth of the cutoff wall should not normally exceed 6 feet. Where a deeper
wall is necessary to meet the above guidelines, either another form of protection
should be employed or an analysis will be required to substantiate the walls structural
stability. Typically, some combination of cutoff wall and erosion protection such as riprap is used at culvert outlets.
Topics on scour are presented in Chapter 11, Sedimentation.
Safety
Inlets and outlets to closed conduits may present dangers to the public when access is not controlled. Refer to Chapter 1, Section 1.4 for the safety requirements related to conduit inlets and
outlets.
5-63
5.5
INVERTED SIPHONS
5.5.1 General
Because of the resulting physical conditions, inverted siphons are rarely used in urban drainage
and should be avoided where possible. Due to the flat topography and a large number of canals
in Maricopa County, however, the designer may have to consider using an inverted siphon.
Inverted siphons are used to convey water by gravity under canals, roads, railroads, other structures, and depressions. An inverted siphon is a closed conduit designed to run full and under
pressure. When flowing at design capacity, the structure should operate without excess head.
For canal structures, inverted siphons are economical, easily designed and built, and have
proven to be a reliable means of water conveyance. However, because of sediment and debris
present in stormwater, maintenance can be a significant negative factor. In addition, canals run
more or less continually and can be drained between periods of use, but inverted siphons for
stormwater do not operate on a regular cycle. If water is left to stand, significant health hazards
could result. Inverted siphons shall be considered only when absolutely necessary, and permitted
by the jurisdictional agency.
5.5.2 Design
All pipes should be designed for watertight joints. Velocity in the conduit should be a minimum of
5.0 ft/sec to prevent sedimentation. The cover over the conduit should exceed the minimum
cover necessary to meet its loading classification. Inlet and outlet structures are required, and
the facility shall meet the requirements for safety described in Chapter 1, Section 1.4. Pipe collars and blow-off structures may be required as determined by the jurisdictional agency. Air
vents, after the entrance, should be used unless the agency agrees with eliminating the vents.
5-64
At a minimum, the designer should compute losses for the entrance and outlet (including
trashracks), pipe friction, and losses at bends and transitions.
5.6
BRIDGES
This section presents a brief overview of the hydraulic analyses for bridge crossings over open
channels. A general discussion of scour is also presented. Comprehensive guidelines and
criteria for hydraulic analyses of bridge crossings are beyond the scope of this manual. The
reader should refer to appropriate texts and technical handbooks for further information on this
subject.
Roadways must often cross open channels in urban areas; therefore, sizing the bridge openings
is of paramount importance. In general, bridges should be designed to have as little effect as
possible upon the flow passing beneath them. If possible, bridges over natural or man-made
channels should be designed so that there is no disturbance to the flow whatsoever. Whenever
piers are used, they need to be oriented parallel to flow. Impacts upon channels and floodplains
created by bridges usually take the form of increased flow velocities through and downstream of
the bridges, increased scour and upstream ponding due to backwater effects. These impacts can
cause flood damage to the channel, to adjacent property and to the bridge structure itself.
A new or replacement bridge should not be permitted to create a rise in the existing water surface elevation, to cause an increase in lateral extent of the floodplain, or to otherwise worsen
existing conditions for discharges up to and including the 100-year discharge, unless appropriate
measures are taken to mitigate the effects of such increases.
5-65
Freeboard
Freeboard at a bridge is the vertical distance between the design water surface elevation and the
low-chord of the bridge. The bridge low-chord is the lowest portion of the bridge deck superstructure. The purpose of freeboard is to provide room for the passage of floating debris, to provide
extra area for conveyance in the event that debris build-up on the piers reduces hydraulic capacity of the bridge, and to provide a factor of safety against the occurrence of waves or floods larger
than the design flood. Freeboard should be provided as required by jurisdictional standards.
A minimum freeboard of 2 feet for the 100-year event is recommended. The structural design of
the bridge should take into account the possibility of debris and/or flows impacting the bridge.
In certain cases, site conditions or other circumstances may limit the amount of freeboard at a
particular bridge crossing. An example would be the replacement of a perched bridge across a
natural watercourse where major flows overtop the roadway approaches. In general, variances to
the minimum freeboard requirement will be evaluated on a case by case basis by the
jurisdictional agency.
5-66
Supercritical Flow
For the special condition of supercritical flow within a lined channel, the bridge structure should
not affect the flow at all. That is, there should be no projections, piers, etc. in the channel area.
The bridge opening should be clear and permit the flow to pass unimpeded and unchanged in
cross section.
Scour
The issue of scour analysis at a bridge is beyond the scope of this chapter. The following discussion touches upon the subject matter to provide the interested designer an indication of the
issues. Local pier and abutment scour, contraction scour, and long-term scour must be investigated when designing a bridge. Refer to Chapter 11, Sedimentation for guidance and insight into
sedimentation and scour.
General scour from a contraction usually occurs when the normal flow area of a stream is
decreased by a bridge. The contraction of the flow by the bridge can be caused by a decrease in
flow area of the stream channel by the abutments projecting into the channel and/or the piers
taking up a large portion of the flow area. Also, the contraction can be caused by approaches to
the bridge that cut off the overland flow that normally goes across the floodplain during high flow.
This latter case also can cause clear-water scour at the bridge section because overland flow
normally does not transport any significant bed material sediments. This clear-water picks up
additional sediment from the bed when it returns to the bridge crossing. In addition, if floodwater
returns to the stream channel at an abutment it increases the local scour there. A guide bank at
an abutment decreases the risk from scour of that abutment from returning overbank flow. Also,
relief bridges in the approaches reduce general scour by decreasing the amount of flow returning
to the natural channel, which then decreases the scour problem. See Chapter 11, Sedimentation
for scour analysis protocol.
5-67
5.7
REFERENCES
5-68
5-69
5-70
6
6
6 OPEN CHANNELS
TABLE OF CONTENTS
6
OPEN CHANNELS
6.1
SYMBOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-3
6.2
INTRODUCTION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-6
6.2.1
Open Channel Defined................................................................................ 6-6
6.2.2
Scope of Chapter ........................................................................................ 6-6
6.2.3
Application................................................................................................... 6-6
6.2.4
Limitations ................................................................................................... 6-6
6.3
BASIC OPEN CHANNEL HYDRAULICS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-7
6.3.1
Flow Classification ...................................................................................... 6-7
6.3.2
Flow Regimes ............................................................................................. 6-8
6.3.3
Equations of Flow...................................................................................... 6-11
6.3.4
Resistance to Flow .................................................................................... 6-17
6.3.5
Uniform Flow ............................................................................................. 6-18
6.3.6
Gradually Varied Flow ............................................................................... 6-23
6.3.7
Control Sections ........................................................................................ 6-26
6.4
GENERAL CONSIDERATIONS FOR OPEN CHANNEL DESIGN . . . . . . . . . . . . . 6-26
6.4.1
Route Considerations................................................................................ 6-26
6.4.2
Layout ....................................................................................................... 6-26
6.4.3
Grade Control............................................................................................ 6-27
6.4.4
Channel Linings ........................................................................................ 6-27
6.4.5
Low Flow Channels ................................................................................... 6-31
6.4.6
Safety ........................................................................................................ 6-32
6.4.7
Maintenance.............................................................................................. 6-32
6.4.8
Confluence Junction.................................................................................. 6-32
6.5
DESIGN FACTORS FOR OPEN CHANNELS . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-32
6.5.1
General ..................................................................................................... 6-32
6.5.2
Minimum Velocity ...................................................................................... 6-33
6.5.3
Maximum Velocity ..................................................................................... 6-33
6.5.4
Freeboard.................................................................................................. 6-35
6.5.5
Channel Curvature .................................................................................... 6-36
6.5.6
Superelevation .......................................................................................... 6-36
6.6
DESIGN GUIDELINES FOR OPEN CHANNELS . . . . . . . . . . . . . . . . . . . . . . . . . . 6-37
6.6.1
Concrete Lined Channels.......................................................................... 6-37
6.6.2
Soil Cement Lined Channels..................................................................... 6-42
6.6.3
Riprap Lined Channels.............................................................................. 6-45
6.6.4
Bank Toe Protection.................................................................................. 6-56
6.6.5
Grouted Riprap Lined Channels................................................................ 6-61
6.6.6
Gabion Lined Channels............................................................................. 6-65
6.6.7
Design Documentation Requirements for Major Watercourses ................ 6-67
6.6.8
Design Example ........................................................................................ 6-69
6.7
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-74
6-1
6.7.1
6.7.2
6-2
6.1
SYMBOLS
=
=
=
=
=
Lo/Lt
the total length of the reach along a profile parallel to flow, LT, ft/ft
A
AT
=
=
=
Alf
Amc
b
C
=
=
Csf
Csg
CVI
d
dave
=
=
D
DAR
Di
=
=
=
E
EL
=
=
Diameter, ft
Durability absorption ratio
The average diameter of a rock particle for which "i" percent of gradation is
finer by weight, mm
Specific energy, ft
Elevation, ft
ET
Total energy, ft
FB
Fr
=
=
G
hf
=
=
6-3
hf
Toe thickness, ft
HV
K1
KE
l
L
=
=
=
Kinetic energy, ft
Length along channel, ft
Characteristic length, ft, or required toe length, ft
Lo
LT
m
M
n
no
=
=
=
=
Mass, lb
Momentum, ft-lb
Manning's roughness coefficient
Roughness coefficient for the area between the buildings in the floodplain
nu
P
PT
=
=
Wetted perimeter, ft
Perimeter of composite section, ft
Plf
Pmc
Ph
Hydrostatic pressure, ft
q
Q
R
Re
rc
=
=
=
=
=
SF
So
=
=
Stability factor
Channel bottom slope, ft/ft
Sf
Ss
V or v
v
=
=
Channel width along the top of the water surface, ft, or riprap layer thickness, ft
Average velocity of a section, ft/sec
Vectoral velocity, ft/sec
Va
W
w
=
=
Wi
Wo
6-4
WT
W
y
yc
=
=
=
yn
ZT
Elevation of channel invert (elevation head), ft, or distance from water surface to the centroid of the section, ft
Total scour depth, ft
6-5
6.2
INTRODUCTION
Section 6.3 - Open channel hydraulics fundamentals which are applicable to both engineered and natural channels, augmented with illustrative computational examples;
Section 6.4 General considerations for open channel drainage planning, such as route
and layout factors; hydraulic analysis considerations and limitations which are generally
applicable to both engineered and natural channels, but some, such as grade control, will
be specific to engineered channels;
Section 6.5 Design factors for open channels, such as determination of freeboard and
toe down requirements;
Section 6.6 - Design guidelines are recommended for various types of open channels and
for several alternate channel materials, including concrete lined channels, shotcrete, soil
cement, cement stabilized alluvium, riprap, and gabions.
6.2.3 Application
The theories and concepts presented in this chapter are applicable to both natural and engineered channels.
6.2.4 Limitations
This chapter assumes that all channel boundaries are rigid, i.e., the channel cross section
remains unaffected by erosion and the channel gradient remains constant for all flows. In this
6-6
respect, this chapter is limited to channels where erosion, transportation, and deposition of sediment are not critical design considerations. For channels requiring consideration of non-rigid
boundaries and/or sedimentation, see Chapter 11.
Recommendations in this chapter address only channels designed to sustain subcritical or mildly
supercritical flow regimes. Supercritical flows with Froude numbers greater than 1.13 require
design procedures outside the scope of this chapter. If a designer determines that flows in the
supercritical regime are unavoidable because of unique physical conditions, they should consult
the technical staff of the jurisdiction involved for appropriate guidance. Section 6.3.2 contains
discussion of the calculation of the Froude number and the determination of flow regime.
The design guidelines in Section 6.5 of this chapter for channel side slopes, lining materials, and
allowable velocities have been put forth to protect the health and welfare of the public while minimizing societal costs. Designers are strongly encouraged to stay within these guidelines, unless
alternative analytic procedures, guidelines, etc. can be substantiated.
6.3
6-7
abruptly over a relatively short distance. Examples of rapidly varied flow include local phenomena, such as hydraulic jumps and hydraulic drops. Under steady flow conditions, if the depth of
flow along the length of the channel gradually increases or decreases it is gradually varied. This
is the usual condition in open channel flow. Gradually varied flow occurs under either subcritical
or supercritical flow regimes. Water surface profile computations are required to estimate the
depth of flow for varied flow conditions at any given location as described in Section 6.3.6.
(6.1)
where V is the mean velocity (ft/sec), g is the acceleration of gravity (ft/sec2), and d is the hydraulic depth (ft) which is the cross sectional area of the water, A (sq ft), divided by the width of the
free surface, T (ft).
When Fr is equal to 1, the flow is in the critical state. This flow condition is unstable and flow
depths at or near critical depth should be avoided. If Fr is less than 1, the flow is subcritical and
gravity forces dominate. When Fr is greater than 1, the flow is supercritical and inertial forces
predominate.
Specific Energy
Specific energy in a channel section is defined as the energy per pound of water at any section of
a channel measured with respect to the channel bottom and may be expressed as:
2
2
V
Q
E = y + ------- = y + ------------2g
2
2gA
(6.2)
When the depth of flow is plotted against the specific energy for a given channel section and discharge, a specific energy curve is obtained (Figure 6.1). The specific energy curve has two
limbs, AC and BC. The limb AC approaches the horizontal axis asymptotically toward the right.
The limb BC approaches the line OD as it extends upwards and to the right. The line OD has an
angle of inclination equal to 45o. At any point P on this curve, the ordinate represents the depth
of flow, and the abscissa represents the specific energy that is equal to the sum of the pressure
2
head, y, and the velocity head, V 2g . The curve shows that, for a given specific energy, there
6-8
are two possible depths, the low stage, y1, and the high stage, y2. The low stage is called the
alternate depth of the high stage and vice versa.
At point C, the specific energy is a minimum and the stage is at critical depth. When the depth of
flow is greater than the critical depth, the velocity of flow is less than the critical velocity and the
flow is subcritical. When the depth of flow is less than the critical depth, the flow is supercritical.
Inspection of the energy curve in the vicinity of critical depth reveals that a small change in the
energy will result in a relatively large change in the depth of flow. For this reason, it is strongly
recommended that flow depths producing Froude numbers between 0.87 and 1.13 be avoided.
The Froude Number limit for all types of channel linings is Fr 0.86. For concrete and shotcrete
lined channels, the additional range of 1.13 Fr 2.0 is allowed. Fr should not fall between 0.86
and 1.13 in order to maintain stable flow conditions. Due to safety concerns resulting from
excessively high velocities and intractable hydraulic forces, the recommended upper limit of Fr is
2.0 except at certain structures such as drop structures.
FIGURE 6.1
SPECIFIC ENERGY CURVE
(MODIFIED FROM: Chow, 1959)
6-9
Critical Flow
Critical depth in an open channel has the following characteristics:
Q
A------ = ----g
T
(6.3)
EXAMPLE 6.1: What is the critical depth of flow for 400 cfs flowing
in a rectangular channel 10.0 feet wide?
3
2
( 10y c )
400
----------- = ----------------32.2
10
y c = 3.68 ft
Subcritical Flow
Flows producing Froude numbers less than 1.0 are subcritical and have the following general
characteristics relative to critical depth:
Slower velocities.
Greater depths.
6-10
Supercritical Flow
Flows with Froude numbers greater than 1.0 are supercritical and have the following general
characteristics relative to critical depth:
Higher velocities.
Shallower depths.
Q = AV
(6.4)
Where V is the mean velocity (ft/sec) and A is the cross sectional area of the flow measured normal to the direction of flow (sq ft). Under steady flow conditions, the discharge is constant and:
Q = A1 V 1 = A2 V 2
(6.5)
The subscripts denote different channel sections. Equation (6.5) is known as the Continuity
Equation and is applicable to the flow conditions addressed in this chapter.
Obviously, Equation (6.5) is invalid for unsteady flow conditions in which discharge increases nor
decreases along the course of flow. Examples of unsteady flow are flood waves, bores, roadside
gutters, side-channel spillways, wash water troughs in filters and, effluent channels around sewage treatment tanks. Precise treatment of unsteady flow is mathematically complicated and
beyond the scope of this chapter.
Energy
The First Law of Thermodynamics states that energy can neither be created nor destroyed; it can
only be transformed. Thus, in the case of an open channel carrying a steady flow, the total
energy at any two points must be equal. At a given cross section, the total energy at any point is
the sum of kinetic and potential energy at that point as illustrated in Figure 6.2.
6-11
FIGURE 6.2
ENERGY IN GRADUALLY VARIED OPEN CHANNEL FLOW
(Chow, 1959)
(6.6)
where:
y 1 = d 1 cos
The velocity head coefficient, , is a correction to account for the non uniformity of the velocity in
the channel. Experimental data indicates this value varies between 1.03 and 1.36 for fairly
straight, prismatic channels. The value is generally higher for small channels, and lower for
larger streams of considerable depth. For channels of regular cross section and fairly straight
alignment, the effect of non-uniform velocity distribution on the computed velocity head is small,
especially when compared to other uncertainties involved in the computation. Therefore, is
often assumed to be 1.0. Additionally, experience indicates that using the average velocity often
gives satisfactory accuracy for usual open channel flow conditions. However, in some cases it
6-12
may be desirable to use the computed value of the energy coefficient . Kinetic energy (KE) is
estimated by Equation (6.7).
2
v
KE = -----2g
1.0
(6.7)
where:
v dA
-------------3
(6.8)
v A
Computational form:
3
v A
--------------------
(6.9)
v A
Example 6.2: The flow in a river downstream of a bridge constriction is
as shown. Calculate the energy coefficient.
6-13
(6.10)
Equation (6.10) is the basis for calculating water surface profiles, which will be discussed in more
detail in Section 6.3.6.
Momentum
The momentum of a flow passing a channel section per unit time is expressed by wQV/g.
where:
According to Newton's Second Law Of Motion, the change of momentum per unit time in a body
of water in a flowing channel is equal to the resultant of all the external forces that are acting on
the body. Assuming a channel of small slope, the momentum of a volume of water between section 1 and 2 can be expressed as follows (Chow, 1959):
2
V1
V2
z 1 + y 1 + 1 -------- = z 2 + y 2 + 2 -------- + h f
2g
2g
(6.11)
Where 1 and 2 are momentum correction coefficients at the two sections. In the energy equation, hf measures the internal energy dissipated in the whole mass of water in the reach, whereas
hf in the momentum equation measures the losses due to external forces exerted on the water
by the boundaries of the channel. Assuming the small differences between a and in uniform
flow, the rate with which surface forces are doing work is equal to the rate of energy dissipation.
In that case, a distinction does not exist between hf and hf except in definition.
6-14
The momentum (M) is estimated by mv where m is mass and v is vectoral velocity. For nonuniform velocity distributions, this should be corrected.
M = mv
1.0
(6.12)
v dA
-------------2
where:
(6.13)
v A
Computational form:
2
A = v
---------------2
v A
(6.14)
The similarity between the energy and momentum principles may be confusing. A clear understanding of the basic differences is important, despite the fact that in many instances the two
principles produce practically identical results. The inherent distinction between the two lies in
the fact that energy is a scalar quantity whereas, momentum is a vector quantity. Also, the
energy equation contains a term for internal losses (energy), whereas, the momentum equation
contains a term for external resistance (force).
Chow (1959) presents the development of the specific energy and specific force curves for a
given channel and discharge (Figure 6.3). For a short horizontal reach of prismatic channel, the
external force of the friction and the weight effect of water can be ignored. Thus, the momentum
equation can be written as:
w
Q ---- ( V 2 V 1 ) = P h1 P h 2
g
(6.15)
P h1 = wz 1 A 1
(6.16)
P h2 = wz 2 A 2
(6.17)
with z as the distance to the centroids of the respective water areas below the surface of flow.
With constant steady flow and V = Q/A,
6-15
Q - + z A = -------Q-+z A
-------1 1
2 2
gA 1
gA 2
(6.18)
FIGURE 6.3
SPECIFIC-FORCE CURVES SUPPLEMENTED WITH SPECIFIC-ENERGY CURVES
(a) Specific-Energy Curve; (b) Channel Section; (c) Specific-Force Curve.
(Chow, 1959)
Equation (6.18) is the most basic form of the momentum equation. For a channel forming angle
with the horizontal, a weight of water W between the points 1 and 2 of the equation, and inserting to account for non-parallel flow, the equation becomes:
2
1 Q
2 Q
------------ + z 1 A 1 = -----------+ z 2 A 2 + W sin + F
gA 1
gA 2
(6.19)
where W = weight (W) in pounds divided by w (62.4 lb/ft3), and where F is the force in ft3 resulting from friction, bends, and all other factors. The sum of external forces (F) is Fw.
Specific Force
The two sides of Equation (6.18) are analogous and may be expressed by the general function:
2
F = Q gA + zA
(6.20)
Both terms in the function are essentially force per unit weight of water, and their sum may be
called the specific force. Since F1 = F2, the specific forces of Sections 1 and 2 are equal, provided that the external forces and the weight effect of water in the reach between the two sec-
6-16
tions can be ignored. On a plot of depth against specific force for a given channel section and
discharge, two possible depths are evident for a given-value of the specific force. These depths
constitute the initial and sequent depths of a hydraulic jump. At the point where the two depths
become one, specific force is at a minimum and the depth is equal to critical depth. The two
basic equations for hydraulic analysis are energy and momentum. The simplest forms of the
equations are developed for restricted cases which establish boundary conditions so that complex differential equations are avoided. These equations, when correctly applied, can provide
good solutions to many problems; however, the hydrologist or engineer must know the limits of
the basic foundation of the equations. The assumptions for the equations as presented are as
follows:
1. The flow is steady.
2. Water is incompressible.
3. The continuity equation is valid.
4. The flow is essentially parallel.
Generally, the energy principle offers a simpler and clearer explanation than does the momentum
principle. However, the momentum principle has many advantages in problems involving
hydraulic jumps, hydraulic structures, and channel junctions.
6-17
Table 7.6, is representative of this design-life condition. Channel design based on the maximum
n-value results in a conservative estimation of flow depth. Likewise, use of the minimum n-value
results in estimation of the maximum velocity of flow in the channel. The minimum n-values as
listed in Table 7.6 represent newly constructed conditions. Maximum expected channel velocity
should be a consideration in the analysis of supercritical flow, hydraulic jumps, and forces on
structures, among others.
It is recommended that both maximum and minimum n-values be applied in the design of channels to check for sufficient hydraulic capacity and stability of channel linings, respectively. The
scour estimation should be based on the minimum n-values.
1.486 2 3 1 2
V = ------------- R S f
n
(6.21)
Substituting Equation (6.4) and rearranging yields the familiar form of Mannings equation:
1.486 2 3 1 2
Q = ------------- AR S f
n
(6.22)
The Mannings roughness coefficient (n-value) is a measure of the frictional resistance exerted
by a channel on the flow. The n-value can also reflect other energy losses such as those resulting from unsteady flow, extreme turbulence, and transport of suspended material and debris that
are difficult or impossible to isolate and quantify. The reader is referred to Chapter 7 and to
Barnes (1967) and Thomsen and Hjalmarson (1991) for discussion of the estimation of n-values
for constructed, natural and composite channels.
The most common error in the application of Mannings equation is to substitute the bed slope of
the channel, So, for the slope of the energy gradient, Sf. This substitution is correct only when the
two gradients are parallel, as in the case of uniform flow. For a given condition of n, Q, and So,
uniform flow is maintained only at normal depth. Normal depth rarely occurs in nature, and it is
primarily a theoretical concept that simplifies the computation and analysis of uniform flow. Table
6.1 lists the algebraic expressions for computing the hydraulic geometry for typical channel sections.
6-18
TABLE 6.1
ELEMENTS OF CHANNEL SECTIONS
(1)
Channel
Section
Area
Rectangle
bd
Trapezoid
zd
Circular
bd -------------b + 2d
2
b + 2d z + 1
2d z + 1
D
- sin
------ -------
8 180
Hydraulic
Radius
b + 2d
bd + zd
Triangle
Wetted
Perimeter
Top
Width
b
2
bd + zd --------------------------------2
b + 2d z + 1
b + 2zd
zd
--------------------2
2 z +1
2zd
D
----------360
D sin
or
2 d(D d)
Circular
D
------ 2 -------+ sin
8
180
D
( 360 )-----------------------------360
45D
------------------------ ( 360 ) *
D sin
or
- + sin 2 d ( D d )
2 -------
180
(1) After USDA Soil Conservation Service ES-33 (NRCS), 1956.
(2) = 4sin
d D Insert in degrees
d D Insert in degrees
(3) = 4cos
Rectangle
Trapezoid
Triangle
Circular
6-19
Composite Channels
The cross section of a natural or artificial watercourse or a street right-of-way may be composed
of several distinct subsections, with each subsection having different hydraulic characteristics,
such as hydraulic roughness and average flow depth. For example, a natural alluvial channel
may have a primary, sand-bed channel which is bounded on both sides by densely-vegetated,
overbank floodplains, or an urban flooded street section may be bounded on both sides by landscaped front yards having shallower flow depths and slower flow velocities.
In composite channels like these, the discharge is computed for each subsection having distinct
and different hydraulic characteristics, and the total computed discharge is set equal to the sum
of the individual discharges. Similarly, the mean velocity for the entire flow cross section is
assumed to be equal to the total discharge divided by the total water area. Open Channel
Hydraulics (Chow, 1959), provides an example of computing flow in channels having composite
roughness.
In the urban setting, it is not unusual for buildings and other structures to occupy a significant
portion of any given hydraulic cross section. Under these circumstances, it is often difficult to
estimate both the effective width of the cross section and the Mannings roughness coefficient for
the overbank areas. Given this situation, the engineer should eliminate the portion of the cross
section occupied by the building.
Where only an estimate of the computed water surface elevation is needed, a second option may
be selected. An adjusted urban roughness coefficient, nu, may be computed and applied to the
total cross sectional area (Hejl, 1977). See Figure 6.4.
WT
W T L o
n u = n o 1.5 ----------- + 1 ---------- --------- 0.5
W o
W L T
(6.23)
6-20
FIGURE 6.4
DIAGRAM OF IDEALIZED URBAN FLOODPLAIN
(Hejl, 1977, JOURNAL OF RESEARCH, U.S. GEOLOGICAL SURVEY)
6-21
Examples:
The following examples illustrate the concept of normal depth and the selection of the roughness
coefficient.
EXAMPLE 6.4: What is the hydraulic capacity of a shotcrete lined
channel with a 20 foot bottom width, 2:1 side slopes, an invert gradient of 0.0016 ft./ft., and a uniform flow depth of 4.0 feet? Selecting the appropriate expressions from Table 6.1 for the cross
section area and the hydraulic radius:
2
A = bd + zd = ( 20 ) ( 4 ) + ( 2 ) ( 16 ) = 112ft
( 20 ) ( 4 ) + ( 2 ) ( 4 ) - = -----------112 - = 2.96ft
bd + zd
- = --------------------------------------------------R = -------------------------------------37.89
2
2
b + 2d ( z + 1 )
20 + ( 2 ) ( 4 ) ( 2 + 1 )
Select the appropriate Mannings roughness coefficient from Table
7.6. Substituting these values in Equation (6.22):
1.49 2 3 1 2
Q = ---------- AR S f
n
23
12
AR
23
Qn
( 625 ) ( 0.022 )
= --------------------- = -------------------------------------------- = 230.70
12
12
1.49S
( 1.49 ) ( 0.0016 )
2
( 20d + 2d )
= ( 20d + 2d ) ----------------------------------------------2
20 + ( 2d ) ( 2 + 1 )
2
23
6-22
The letter is descriptive of the slope, i.e., H for horizontal, M for mild, C for critical, S for
steep (supercritical), and A for adverse slope; and
These types are designated as H1, H2, H3; M1, M2, M3; C1, C2, C3; S1, S2, S3; and A1, A2, A3
as shown in Figure 6.5.
Flow profile analysis enables the designer to predict the general shape of the flow profile for a
given channel layout. This step is a significant part of the open channel design process and it
should not be omitted. Flow profile analysis will serve to identify control sections and to provide
a work plan for more detailed design calculations.
6-23
FIGURE 6.5
CLASSIFICATION OF FLOW PORTION OF GRADUALLY VARIED FLOW
(Chow, 1959)
6-24
6-25
6.4
6.4.2 Layout
Unless special exception is made by the governing agency, all artificial channels must begin and
end where, historically, runoff has flowed.
The alignment of new drainage channels should follow existing washes, swales, and depressions
whenever possible. The water must be collected and discharged at the same point and in the
same manner as prior to the construction of the new channel. This means that the design of the
new drainage features must account for runoff entering the property in the same location and
manner as it historically flowed, and collect the water and transition it into the new channel for
conveyance through the project site. At the downstream end of the channel, the drainage design
must provide a transition from the on-site channel to return the runoff to its historic location prior
6-26
to leaving the property. This requirement applies to the hydraulic geometry and velocity of the
water, and the elevation of the water surface.
6-27
FIGURE 6.6
TYPICAL CHANNEL SECTIONS
6-28
The type of stabilization that may be best suited for a particular purpose will depend upon a variety of factors, including hydraulic conditions, economic factors, soil conditions, material availability, aesthetics, maintenance and compatibility with existing improvements. The order of
preference for subcritical flow conditions is natural channels with periodic grade-control structures, channels with vegetal linings, compound channels, channels lined with riprap, or its variations, channels lined with soil cement, and concrete-lined channels. Where supercritical flow
conditions occur, only acceptable structurally sound channel linings such as concrete and shotcrete are recommended.
6-29
FIGURE 6.7
COMPOUND CHANNEL
(Simons, Li, and Associates, 1989)
6-30
Soil Cement
Soil cement linings are composed of a thick layer (4-foot minimum) of unreinforced soil cement
and are used successfully in many locations in Maricopa County. Soil cement is subject to
weathering and abrasion. Soil cement can withstand relatively high velocities for short periods of
time and, therefore, is most appropriate for channels with limited right-of-way or as a bank lining
near bridges and culverts where local velocities tend to be high. Refer to Section 6.6.2.
6-31
b
------ 1.40
Vy
(6.24)
where:
6.4.6 Safety
Deep channels with steep side-slopes and high flow velocities can be a hazard to the health,
safety, and welfare of the general public. Therefore, the design engineer must always consider
the safety aspects of any design. The reader is referred to Chapter 1, Section 1.4 of this manual.
6.4.7 Maintenance
The design engineer must also consider maintenance issues associated with any design. At a
minimum, a 16-ft maintenance access lane with access ramps is recommended to be provided
on one side of a channel for publicly maintained channels. Refer to each jurisdictions Policies
and Standards Manual for specific criteria. To minimize maintenance; paths, walkways, play
areas, and irrigation systems should be located in less frequently inundated levels of channels.
Bottom widths of channels should be designed in consideration of maintenance requirements for
the channel lining, and will be no narrower than 8 feet unless otherwise approved by the jurisdictional entity.
6.5
6.5.1 General
Good design practice requires that several issues be addressed. Unless exempted by the
governing agency, water surface profiles must be computed for all channels during final design
and clearly shown on a copy of the final drawings. Computation of the water surface profile
should use standard step backwater methods (see Section 6.3.6). These computations must
account for all losses due to changes in velocity, drops, bridge openings, and other factors.
6-32
Computations should begin at a known point and extend in an upstream direction for subcritical
flow regimes, and in a downstream direction for supercritical regimes. Concrete lined channels
with supercritical flow regimes should be analyzed as described in Section 6.3.6. The energy
gradient must be shown on all preliminary drawings to help check for errors; however, it is
optional for final drawings. Open channel flow in urban drainage is usually non-uniform due to
bridge openings, channel curves, and hydraulic structures, therefore backwater computations
must be used for all final channel design work.
6-33
TABLE 6.2
MAXIMUM PERMISSIBLE VELOCITIES FOR ROADSIDE DRAINAGE CHANNELS
WITH ERODIBLE LININGS
(USDOT, FHWA, 1961 AND 1988)
Soils Type of Lining (Earth, No Vegetation)
(1)
2.5
2.5
3.0
3.5
Fine Gravel
5.0
5.0
5.0
5.5
3.5
5.0
6.0
5.5
6.0
(2)
6-34
Higher velocities may be allowed for design of unlined channels, for the 100-year design event in particular,
based on sediment balance considerations defined using the guidelines in Chapter 11. However, sufficient
setback allowance should be provided for expected bank erosion during the 100-year event, or a series of
annualized events over a 60-year period. Higher velocities may also be acceptable for 100-year peak flow
design with approved engineering justification based on a tractive force analysis (USDOT, FHWA HEC-11,
1989).
TABLE 6.3
MAXIMUM PERMISSIBLE VELOCITIES FOR GRASS-LINED ROADSIDE CHANNELS
UNIFORM STAND OF GRASS COVER AND WELL MAINTAINED
(ADAPTED FROM USDOT, FHWA 1961 AND 1988)(1)(2)(3)
Cover
Bermuda Grass
6.5.4 Freeboard
Freeboard is the distance between the calculated water surface and the top of the channel lining
or bank. The minimum freeboard is calculated as follows:
2
V-
FB = 0.25 y + ----2g
(6.25)
In subcritical channels, the minimum required freeboard is the larger of 1 foot or that calculated
using Equation (6.25). In supercritical channels, the required freeboard is the larger of 2 feet or
the results of Equation (6.25). In all instances, the freeboard required is additive to any increases
in water surface due to superelevation or channel curvature. Freeboard for levees must meet
FEMA freeboard requirements (3, 3.5 or 4 feet minimum depending on location relative to end of
levee, and to other structures). Refer to 44 CFR Section 65.10: Mapping of Areas Protected by
Levee Systems (USGPO, 2000).
For sand-bed channels, when the Froude Number is equal to or larger than 0.7, the freeboard
shall be the larger value of 0.027V2 or 0.25(y+V2/(2g)) where V is the channel velocity and y is the
flow depth. The reason is as follows. When the Froude Number reaches 0.7 in sand-bed channels, an antidune bed form may develop. Under the antidune bed form condition, the water surface wave is in phase with the sand wave on the channel bed, i.e., the peaks and troughs of the
sand wave and water wave on the surface will occur simultaneously. The amplitude of the water
surface wave may exceed that of the sand wave by a factor of 1.5 to 2 (Chien and Wan, 1998).
6-35
The amplitude for the antidune sand wave can be estimated by 0.027V2 where V is the channel
velocity. Therefore, the water wave amplitude can be estimated by 0.054V2 if a factor of 2 is
used. Water wave amplitude is the vertical distance between the wave peak and wave trough.
Assuming the average water surface elevation is at the middle of the amplitude, the wave height
above the water surface elevation is then 0.027V2.
Roll waves also known as slug flow are intermittent surges on steep slopes that will occur when
the Froude Number is greater than 2.0 and the channel invert slope is greater than 12/Re where
Re is the Reynolds Number (Chow, 1959). The Reynolds Number (Re) is defined as VL
where V is velocity fps, L is characteristic length ft, and is the kinematic viscosity. L can be
assumed as flow depth for a wide open channel. When this occurs, it is important to estimate the
wave height as part of freeboard design. Detailed discussions and design procedures and examples on roll wave height can be found in LACFCD (1982) and Brock (1967).
r c 3T
(6.26)
If the channel is carrying supercritical flows, the recommended minimum radius is:
2
r c = 4V
------------Tgy
(6.27)
6.5.6 Superelevation
Curves in a channel cause the maximum flow velocity to shift toward the outside of the bend.
Along the outside of the curve, the depth of flow is at a maximum. The consequent rise in the
water surface is referred to as superelevation. Under subcritical conditions, the following
equation is recommended to estimate the magnitude of the superelevation:
2
y = 0.5V
----------------Tgr c
(6.28)
Readers are cautioned to avoid curves in channels with supercritical flows. The shift in the
velocity distribution may cause cross-waves to form, which will persist downstream and could
severely limit the hydraulic capacity of the channel. Advanced design criteria or physical model
studies beyond the scope of this chapter may be required.
6-36
6.6
6-37
anticipated construction techniques. The concrete lining must be keyed into the adjacent overbanks as shown in Figure 6.8.
FIGURE 6.8
TYPICAL BANK-PROTECTION KEY-INS
(NOT TO SCALE; Simons, Li and Associates, 1989A)
The roughness coefficient for a concrete lining can vary from 0.011 for a troweled finish to 0.020
for a very rough or unfinished surface. Refer to Table 7.6. For shotcrete, roughness coefficients
can vary from 0.016 to 0.025. The accumulation of sediment and debris must be taken into
account when determining the roughness coefficient.
Long-term stability of concrete lined channels depends in part on proper bedding. Undisturbed
soils often are satisfactory for a foundation for lining without further treatment. Expansive clays
are usually an extreme hazard to concrete lining and should be avoided. A filter underneath the
6-38
lining is recommended to protect fine material from creeping along the lining. A well-graded
gravel filter should be placed over the channel bed prior to lining the channel with concrete.
Since concrete-lined channels are often used at locations where excessive seepage exists or
smaller channel cross sections are required, transitions will be required both upstream and
downstream of the concrete lined channel. Such transitions are intended to prevent undermining
of the lining and to reduce turbulence. Transitions should be lined with concrete or other scour
resistant material to reduce scour potential.
Cutoff walls should be incorporated with transitions at both the upstream and downstream end of
the concrete lined channel to reduce seepage forces and prevent lining failure due to scour,
undermining, and piping. The depth of cutoff walls should extend below the expected scour
depth. Determination of expected total scour depth requires analyses as discussed in Chapter
11.
The probability of damaging the concrete lining due to hydrostatic back pressure and subgrade
erosion can be greatly reduced by providing underdrains. There are two types of artificial drainage installations. One type consists of 4- or 6-inch diameter perforated pipelines placed in
gravel-filled trenches along one or both toes of the inside slopes. These longitudinal drains are
either connected to transverse cross drains which discharge the water below the channel or to
pump pits, or extend through the lining and connect to outlet boxes on the floor of the channel.
The outlet boxes are equipped with one-way flap valves that prevent backflow and relieve any
external pressure that is greater than the water pressure on the upper surface of the channel bottom. The second type consists of a permeable gravel blanket of selected material or sand and
gravel pockets, drained into the channel at frequent intervals (10 to 20 feet) by flap valves in the
channel invert. Figure 6.9 shows a drawing of a flap valve for use without tile pipe and in a fine
gravel and sand subgrade. Both the tile and pipe system and the unconnected flap valve type
must be encased in a filter that will prevent piping of subgrade material into the pipe or through
the valve. For detailed information on underdrains refer to Lining for Irrigation Canals (USBR,
undated).
Where a lesser degree of seepage control is warranted, weep holes spaced at appropriate
intervals may be used. When embankment stability may be compromised or when groundwater
levels may be raised by back drainage from the lined channel, weep holes may be equipped with
flap valves or other measures that allow seepage relief but prevent backflow or introduction of
surface water behind the lining.
The shotcrete process has become an important and widely used technique. Shotcrete is mortar
or concrete pneumatically projected at high velocities onto a surface. In the past, the term
gunite was commonly used to designate dry-mix mortar shotcrete. The term is currently out-
6-39
dated and shotcrete has become the trade name for all pneumatically applied dry-mix or
wet-mix concrete or mortar.
ACI 506R (2005) discusses the properties, applications, materials, reinforcement, equipment,
shotcrete crews, proportioning, batching, placement, and quality control of the shotcrete process.
As a channel lining, shotcrete is an acceptable method of applying concrete with a general
improvement in density, bonding, and decreased permeability. The same design considerations
discussed for concrete channels apply in the design of shotcrete channels. Shotcrete linings are
to be designed to the same thickness and reinforcement as required for concrete linings. Given
the limitations of construction, the minimum slope for concrete and shotcrete channels is 0.0015
ft/ft.
6-40
.
FIGURE 6.9
FLAP VALVE INSTALLATION FOR A CHANNEL UNDERDRAIN
(Simons, Li and Associates, 1981)
6-41
Materials
A wide variety of soils can be used to make durable soil cement. For maximum economy and
most efficient construction, it is recommended that:
1. The soil contains no material retained on a 3-inch (75 mm) sieve;
2. Between 40 percent and 80 percent pass the No. 4 (4.75 mm) sieve; and
3. Between 2 percent and 10 percent pass the No. 200 (0.074 mm) sieve.
4. The Plasticity Index (PI) of the fines should not exceed 10.
If the onsite material does not meet these guidelines, the addition of import material may be necessary. Standard laboratory tests are available to determine the required proportions of cement
and moisture to produce durable soil cement. The design of most soil cement for water control
projects is based on the cement content indicated by ASTM testing procedures and increased by
a suitable factor to account for direct exposure, erosion or abrasion forces.
The Portland cement should comply with one of the following specifications: ASTM C150, CSA
A5, or AASHTO M85 for Portland cement of the type specified; or ASTM C595 or AASHTO M240
for Portland blast-furnace slag or Portland pozzolan cement, excluding slag cements Types S
and SA.
It is important that testing to establish required cement content be done with the specific cement
type, soil, and water that will be used in the project.
Typically, soil cement linings are constructed by the central-plant method, where selected onsite
soil materials, or soils borrowed from nearby areas, are mixed with Portland cement and water
and transported to the site for placement and compaction.
6-42
sons. Figure 6.11 shows the relationship between slope of facing, thickness of compacted horizontal layer, horizontal layer width and minimum facing thickness measured normal to slope. For
a horizontal working width of 9 feet, a side slope of 2:1 and 6-inch thick layers, the resulting minimum thickness of facing would be about 4 feet, measured normal to the slope. The sideslope
can vary from 1:1 to 3:1 depending on the soil type and natural angle of repose. Side slopes
steeper than 2:1 are not recommended, due to safety issues, but may be allowed when right-ofway is a problem. Soil cement may be placed on slopes 3:1 or flatter at a minimum thickness of
eight to twelve inches, depending upon the mixing technique. This would be done without the
stair-step layer approach, where a lesser level of protection is permissible.
An important consideration in the design of the soil cement facing is to provide that all extremities
of the facing are tied into non-erodible sections or abutments. The upstream and downstream
ends of the facing should terminate smoothly into the natural channel banks. A buried cutoff wall
normal to the slope or other measures may be necessary to prevent undermining of the soil
cement facing by flood flows.
The top of the lining should be keyed into the ground to protect against erosion of the backside of
the soil cement layer by lateral inflows, as shown in Figure 6.8. As with any impervious channel
lining system, seepage and related uplift forces should be considered and, if required, appropriate counter-measures provided, such as weep holes or subdrains. Tributary storm drain pipelines can normally be accommodated by placing and compacting the soil cement by hand, using
small power tools, or by using a lean mix concrete. For earthen channels with soil cement side
slope protection, the lining should be designed to extend to the anticipated depth of total scour
below thalweg. Further design information may be found in ACI 230.1(1990), State Of The Art
Report On Soil Cement. Additional information on design and construction is available from the
Portland Cement Association, Skokie, IL (http://www.cement.org/).
FIGURE 6.10
SOIL CEMENT PLACEMENT DETAIL
(NOT TO SCALE)
6-43
FIGURE 6.11
RELATIONSHIPS FOR SOIL CEMENT LINING
SLOPE, FACING THICKNESS, LAYER THICKNESS, AND HORIZONTAL LAYER WIDTH
(Portland Cement Association, 1987)
6-44
riprap quality;
hydraulic requirements;
river conditions.
In Arizona, site requirements and river conditions are important factors in the protection of bridge
structures and flood control channels.
Riprap Quality
Riprap quality determination refers to the physical characteristics of the rock particles that make
up the bank protection. Qualities determined to be most important include density, durability, and
shape. Requirements for each of these properties are summarized in this section.
Specific Gravity - The design stone size for a channel depends on the particle weight, which is a
function of the specific gravity of the rock material. All stones composing the riprap should have
a specific gravity equal to or exceeding 2.5, following the standard test ASTM C127 (2007). It
may be noted that the minimum specific gravity required by MAG (2012) is 2.5.
Durability - Durability addresses the in-place performance of the individual rock particles, and
also the transportation of riprap to the construction site. In-place deterioration of rock particles
can occur due to cycles of freezing and thawing, or can occur during transportation to the site.
The rock particles must have sufficient strength to withstand abrasive action without reducing the
gradation below specified limits. Qualitatively, a stone that is hard, dense, and resistant to weathering and water action should be used. Rocks derived from igneous and metamorphic sources
provide the most durable riprap.
Laboratory tests should be conducted to document the quality of the rock. Specified tests that
should be used to determine durability include: the durability index test and absorption test (see
ASTM C127). Based on these tests, the durability absorption ratio (DAR) is computed as follows:
6-45
(6.29)
6-46
G = 0.5 ( d 84 d 50 + d 50 d 16 )
(6.30)
Table 6.4 provides design gradations for riprap. As a practical matter, the designer should check
with local quarries and suppliers regarding the classes and quality of riprap available near the
site.
TABLE 6.4
RIPRAP GRADATION LIMITS
(USDOT, 1989)
Stone Size Range
(ft.)
Percent of Gradation
Smaller Than
100
85
50
15
Thickness - The riprap-layer thickness shall be the greater of 1.0 times the d100 value, or 1.5
times the d50 value. But the thickness need not exceed twice the d100 value. The thickness is
measured perpendicular to the slope upon which the riprap is placed.
Filter Blanket Requirements - The purpose of granular filter blankets underlying riprap is
two-fold. First, they protect the underlying soil from washing out; and, second, they provide a
base on which the riprap will rest. The need for a filter blanket is a function of particle-size ratios
between the riprap and the underlying soil which comprise the channel bank. The inequalities
that must be satisfied are as follows:
( d 15 )
( d 15 )
filter
filter---------------------- < 5 < --------------------< 40
( d 85 )
( d 15 )
base
base
(6.31)
( d 50 )
filter--------------------< 40
( d 50 )
base
(6.32)
In these relationships, filter refers to the overlying material and base refers to the underlying
material. The relationships must hold between the filter blanket and base material and between
the riprap and filter blanket (USDOT, 1988 and 1989).
If the inequalities are satisfied by the riprap itself, then no filter blanket is required. If the difference between the base material and the riprap gradations are very large, then multiple filter lay-
6-47
ers may be necessary. To simplify the use of a gravel filter layer, Table 6.5 outlines
recommended standard gradations.
The Type-I and Type-II bedding specifications shown in Table 6.5 were developed using the criteria given in Equation (6.31) and Equation (6.32), considering that very fine grained, silty,
non-cohesive soils can be protected with the same bedding gradation developed for a mean
grain size of 0.045 mm. The Type-I bedding in Table 6.5 is designed to be the lower layer in a
two-layer filter for protecting fine grained soils. When the channel is excavated in coarse sand
and gravel (i.e., 50 percent or more by weight retained on the No. 40 sieve), only the Type-II filter
is required. Otherwise, two bedding layers (Type-I topped by Type-II) are required. For the
required bedding thickness, see Table 6.6.
TABLE 6.5
GRADATION FOR GRAVEL BEDDING
(Simons, Li and Associates, 1989)
Type I (1)
100
95 to 100
45 to 80
10 to 30
2 to 10
0 to 2
Type II (1)
90 to 100
20 to 90
0 to 20
0 to 3
TABLE 6.6
THICKNESS REQUIREMENTS FOR GRAVEL BEDDING
(Simons, Li and Associates, 1989)
Riprap Size
Classification (in)
6-48
6, 8
12
18
24
30
10
36
10
Filter Fabric Requirements - The design criteria for filter fabric are a function of the permeability
of the fabric and the effective opening size. The permeability of the fabric must exceed the permeability of the underlying soil, and the apparent opening size (AOS) must be small enough to
retain the soil.
The criteria for apparent opening size are as follows:
1. For soil with less than 50 percent of the particles, by weight, passing a No. 200 sieve, the
AOS should be less than 0.6 mm (a No. 30 sieve).
2. For soil with more than 50 percent of the particles, by weight, passing a No. 200 sieve,
the AOS should be less than 0.3 mm (a No. 50 sieve).
The detailed specifications can be found in Section 796 of MAG (2012). Filter fabric is not a
complete substitute for granular bedding. Filter fabric provides filtering action only perpendicular
to the fabric and has only a single equivalent pore opening between the channel bed and the riprap. Filter fabric has a relatively smooth surface which provides less resistance to stone movement. Tears in the fabric greatly reduce its effectiveness so that direct dumping of riprap on the
filter fabric is not allowed and due care must be exercised during construction. The site conditions and specific application and installation procedures must be carefully considered in evaluating filter fabric as a replacement for granular bedding material. Filter fabric can provide an
adequate bedding for channel linings along uniform mild sloping channels where leaching forces
are primarily perpendicular to the fabric.
Numerous failures have occurred because of the improper installation of filter fabric. Therefore,
when using filter fabric it is critical that the manufacture's guidelines for installing it be followed.
6-49
2gC cos s w
(6.33)
where:
Va
coefficient (use 1.2 for low turbulence areas or 0.86 for high turbulence areas),
d50
median rock size, also defined as the diameter where 50% is finer by
weight (ft).
This general equation can be simplified under various conditions: (1) channel banks on straight
reaches, (2) channel banks on curve reaches, (3) channel bed on straight reaches, (4) channel
bed on curve reaches, (5) downstream of grade control/drop structures, downstream of stilling
basins, spur disk/guide bank/abutments, sloped drop structures and rock chutes. Simplified
equations are presented on the following pages.
6-50
FIGURE 6.12
DEFINITION FOR BANK ANGLE
d 50
0.0191V a2 w
= ----------------------- ----------------
cos s w
(6.34)
where:
d50
Va
6-51
0.0372V a2 w
d 50 = ----------------------- ----------------
cos s w
(6.35)
where:
d50
Va
The inner bend riprap sizing can be based on the straight reach equation.
FIGURE 6.13
DEFINITION FOR CHANNEL BEND ANGLE
(FIGURE ADAPTED FROM Simons, Li and Associates, 1989B)
6-52
w
d 50 = 0.0191V a2 ----------------
s w
(6.36)
where:
d50
Va
This equation is also a simplified Isbash equation with C = 1.2 and 0.0 degrees of bank angle.
w
d 50 = 0.0372V a2 ----------------
s w
(6.37)
where:
d50
Va
This equation is also a simplified Isbash equation with C = 0.86 and 0.0 degrees of bank angle.
6-53
w
d 50 = 0.0372V a2 ----------------
s w
(6.38)
where:
d50
Va
This equation is also a simplified Isbash equation with C = 0.86 and 0.0 degrees of bank angle.
d 50 = 0.0126V a2
(6.39)
where:
d50
Va
d 50 = 0.01V a2.44
(6.40)
where:
d50
Va
6-54
safety factor of 1.5, the loose angular riprap median size equations are simplified from Robinson,
et al. (1998) as:
0.794
d 50 = 2.12q 0.529 S 0
d 50 = 0.69q
0.529 0.307
S0
0.02<S0<0.10
(6.41)
0.1<S0<0.4
(6.42)
where:
d50
S0
It should be noted that these two equations are for loose riprap on the slope of the structure. For
downstream of the sloped drop structure, the equation above for Downstream of Grade Control/
Drop Structure should be used. The thickness for the riprap layer on the slope should be at least
2d50. A granular filter should be used beneath the riprap layer. The design for rock chutes and
downstream energy dissipators can be found in Lorenz et al. (2000).
Concrete Rubble
Concrete rubble or broken concrete is a very economical riprap material. However, the successful use of such material requires good quality control on shape, specific weight, gradation, and
durability (USDOT, 1989). Due to the difficulties of achieving good quality of these aspects, extra
caution must be exercised. Careful inspection of the material must be performed to ensure the
quality of the material meets the specified requirements. In addition, aesthetics should be considered. Agency approval is required before the use of concrete rubble material. The following
specifications should be followed for concrete rubble design. The specifications have been
developed by FCDMC based on Florida Department of Transportation (2010), Missouri Department of Natural Resources (2009), and Montana Department of Environmental Quality (2011).
The specific gravity shall be at least 2.3 or the specific weight shall be at least 143.5 lb per
cubic foot. The specific gravity shall be shown on the construction plan.
Materials shall be free of grease, oils, paint, chemicals, and other pollutants.
6-55
The longest dimension shall not be more than three times the shortest dimension. The
length shall not be greater than twice its width.
Materials, when trucked or imported to the site, must be sorted at the site.
Materials shall be stockpiled before placement to allow for inspection. Visual inspection
shall ensure that materials are free of cracks, soft seams or other structural defects.
Materials shall be hard, durable, rough and angular in shape. Additional tests may be
required subject to the inspector's judgment. Examples of such tests include the Los
Angeles Abrasion Test (AASHTO T96), Durability and Soundness Test (AASHTO T104),
Absorption Test (AASHTO T85), Drop Test (USACE, 1990, EM 1110-2-2302). The
requirements for these tests are a maximum loss of 45% for the Los Angeles Abrasion
Test, a maximum loss of 12% for the Durability and Soundness Test, and a maximum of
5% for the Absorption Test. The Drop Test requirements are: no new cracks developed, or
no existing crack widened more than an additional 0.1 inch, or final largest dimension
greater than or equal to 90% of the original largest dimension of a dropped piece.
The maximum weight of any piece shall not exceed 500 lbs.
Materials shall be reasonably well graded. The gradation shall be based on general riprap gradation documented in Table 6.4. All large slabs shall be broken up to conform to
the gradation requirement.
Either a granular or fabric filter blanket is required for loose rubble concrete riprap. The
specification for filter blankets can be found in the Riprap Layer Characteristics Section,
Filter Blanket Requirements.
The thickness of rubble concrete riprap for river bank protection shall be based on the
Riprap Layer Characteristics Section, Thickness.
All material shall be placed in a manner such that the large and small sizes are evenly distributed and placed so as to fill the voids between the larger pieces without sharp
exposed edges.
All material shall be placed in a manner such that each piece is touching the adjacent
piece in a configuration creating the highest possible density while producing a reasonably solid mass within the limits shown in the plans.
The largest material must be keyed into the toe and also used in the base of the riprap.
6-56
design of protection from toe scour involves two parameters. First, an estimate of the total scour
depth must be made. Second, a means of protection must be provided for the total scour. The
first parameter, total scour depth estimation, requires specialized analysis techniques by a qualified engineer. The procedure for estimating the total scour depth can be found in Chapter 11.
Mitigation measures for providing protection for the total scour are presented in this section.
The two methods of providing toe protection in erodible channels are:
1. To extend protection to the total scour depth; and
2. To provide protection that adjusts to the scour as it occurs.
The first method is the preferred technique because the protection is initially placed to a known
depth and the designer does not have to depend on uncertainties associated with the method
that adjusts to the scour. This method requires extension of the bank protection into the excavated channel bed and is primarily used for placement in dry conditions because of the expense
and uncertainties of deep excavation that can frequently encounter groundwater.
The second method is also called the launchable riprap toe protection method. The main advantage of the second method is the elimination of relatively deep excavation and related water control. The most frequently used material for providing adjustable toe protection is riprap placed at
the toe of the bank in a weighted riprap configuration. The riprap moves downslope, as scour
occurs, to form a protective cover. Figure 6.14 shows the desirable configuration for a weighted
riprap toe. Studies by Linder (1976) and the U.S. Army Corps of Engineers (1981 and 1994) on
riprap toe protection arrived at the following conclusions:
1. Volume of rock in the weighted riprap toe is probably the most significant factor in
determining the success of the weighted riprap toe.
2. Toe shape has a definite influence on performance. Thin toes do not release rock fast
enough, which results in poor slope coverage. Thick toes release rock at a greater rate
than is needed. The thickness of the recommended toe ranges from two to three times
the thickness of the riprap bank protection. The recommended toe shape is shown in Figure 6.14.
3. Complex toe designs that are difficult to construct are not necessary.
4. Downslope rock movement occurred without significant movement in the downstream
direction.
5. Results from modeling and the subsequent prototypes show that the recommended
6-57
L can be computed by
Hv
C VI
L = 1.5H + 1 + -------- T 5 -----H
100
(6.43)
where H is the toe thickness 2T <H < 3T, CVI is the volume increase in percent from
Table 6.8, T is the riprap layer thickness T = 1.5d50, and HV is the vertical launch distance = ELTOP - H - ELTG + ZT where ELTOP is the top elevation for toe protection, ELTG
is the thalweg elevation, and ZT is the total scour depth. The total scour depth estimation
procedure can be found in Chapter 11.
The launchable toe protection method has been widely used on sand bed streams for
applications such as windrow revetments (riprap placed at top of bank), trench-fill revetments (riprap placed at low water level), and weighted riprap toes (riprap placed at intersection of channel bottom and side slope). However, this method for gravel bed streams
is not as widely accepted as in sand bed streams (USACE, 1994). For gravel-bed or cobble-bed streams, extra caution should be exercised because more rocks may be lost during the launching process due to the impinging force caused by the moving cobbles as
part of stream bed load. For gravel-bed streams with large cobbles, the rock size (d50) or
rock volume at the toe protection section may be increased by 25%. A filter must be
installed beneath the rock at the bank slope and the toe protection section as shown in
Figure 6.14. A granular filter must be installed beneath the toe protection section because
a fabric filter may affect the launching process.
6-58
TABLE 6.7
VOLUME INCREASE COEFFICIENT IN PERCENT FOR SAND-BED CHANNELS
(ADAPTED FROM USACE, 1994)
Vertical Launch
Distance (HV)
Underwater Placement
<15 ft
25
50
>15 ft
50
75
TABLE 6.8
VOLUME INCREASE COEFFICIENT IN % FOR GRAVEL-BED CHANNELS
WITH LARGE COBBLES (ADAPTED FROM USACE (1994))
Vertical Launch
Distance (HV)
Underwater Placement
<15 ft
50
75
>15 ft
75
100
Weighted riprap toes have been used successfully for many years. However, success has not
been universal. A common factor among the failures appears to be the presence of impinged
flow on the bank. Therefore, the guidelines herein apply chiefly to flow conditions parallel to the
bank. Where impinged flow is likely, then analyses must be made to determine an appropriate
additional level of protection for this type of hydraulic condition.
6-59
FIGURE 6.14
TOE PROTECTION CHANNEL LINING
(Wright-McLaughlin, 1969)
FIGURE 6.15
TOE PROTECTION CHANNEL LINING DETAILS
6-60
Applying grout to salvage a failing conventional riprap treatment without proper design to
address the cause of the failure should not be undertaken. This practice most often does
not provide a successful repair and results in a waste of resources. Examples are slope
failures resulting from upslope surface runoff, piping-related internal erosion, down-slope
6-61
riprap failure resulting from toe scour, and failures of frequently overtopped drainways
and drainage ditches.
Materials - Riprap quality should conform to the property requirements described in Section
6.6.3. Figure 6.16 gives the required blanket thickness of grouted rock for a given design channel velocity. The median rock size d50 shall not exceed 0.67 times the blanket thickness and the
largest rock used should not exceed the blanket thickness. d50 and d100 can be 0.67 and 1.0
times the blanket thickness, respectively. It is required that rocks smaller than the d50 size be
removed. The other gradation limits should conform to those described in Section 6.6.3.
The grout mix should be specified to provide the strength and durability required to meet the specific application. The minimum 28-day compressive strength shall be 2,000 psi and the slump
shall be within a range of 4 to 7 inches. The stone aggregate should conform to the gradation
requirements of Size Number 8 coarse aggregate (3/8 inch to No. 8) as specified in ASTM C-33.
A maximum of 30 percent of the cementitious material may be fly ash (ASTM C-618, Type C or
F). Fiber reinforcement is recommended to be added to the grout to provide additional control of
shrinkage and cracking.
FIGURE 6.16
REQUIRED BLANKET THICKNESS OF GROUTED ROCK
(USDOT, 1989)
6-62
The grout shall extend the full thickness of the rock blanket.
Finished grout should leave face stones exposed for one-fourth to one-third their depth.
Bank slopes for grouted riprap shall not exceed 1.5:1 (H:V)
The grouted riprap protection for open channels must extend below the channel thalweg
to the depth of total scour. The total scour depth estimation method can be found in
Chapter 11.
Bank should be prepared by first clearing all trees and debris from the bank, and grading
the bank surface to the desired slope. The bank surface should be tamped or lightly compacted. Care must be taken during bank compaction to maintain a soil permeability similar to that of the natural, undisturbed bank material. The foundation for the grouted riprap
revetment should have a bearing capacity sufficient to support either the dry weight of the
revetment alone or the submerged weight of the revetment plus the weight of the water in
the wedge above the revetment for design conditions, whichever is greater.
Filters are required under all grouted riprap revetments to provide a zone of high permeability to carry off seepage water and prevent damage to the overlying structure from uplift
pressures. A 6-in (15.4-cm) granular filter is required beneath the grouted riprap to provide an adequate drainage zone. The filter can consist of well-graded granular material,
or uniformly-graded granular material with an underlying filter fabric. The filter should be
designed to provide a high degree of permeability while preventing base material particles
from penetrating the filter.
Weep holes should be provided in the revetment to relieve hydrostatic pressure build-up
behind the grout surface. Weeps should extend through the grout surface to the interface
with the gravel underdrain layer. Weeps should consist of 3-in (7.6-cm) diameter pipes
having a maximum horizontal spacing of 6-ft (1.8 m) and a maximum vertical spacing of
10 feet (3.0 m). The buried end of the weep should be covered with wire screening of an
appropriate gage or a fabric filter that will prevent passage of the gravel underlayer.
The edges of grouted rock revetments (the head, toe, and flanks) require special treatment to prevent undermining. The revetment toe should extend to a depth below anticipated channel bed total scour depths or to bedrock. Grouted riprap should extend from
below the anticipated channel bed total scour depth to the design high water level plus
additional height for freeboard. The total scour depth procedures can be found in Chapter
11. The toe should be designed as illustrated in Figure 6.17(a). After excavating to the
desired depth, the riprap slope protection should be extended to the bottom of the trench
and grouted. The remainder of the excavated area in the toe trench should be filled with
ungrouted riprap. The ungrouted riprap provides extra protection against undermining at
6-63
the bank toe. The riprap sizing for the ungrouted riprap should be based on the loose
angular riprap sizing equation, Equation (6.33).
To prevent outflanking of the revetment, the upstream and downstream edge of the
grouted riprap should be designed in accordance with Figure 6.17(b) and Figure 6.17(c).
Figure 6.18 shows three typical design sections for bank and channel revetments. Section A-A is a mid-section. Sections B-B and C-C are flank sections documenting the
upstream and downstream edge details respectively.
FIGURE 6.17
GROUTED RIPRAP SECTIONS: (a) SECTION A-A; (b) SECTION B-B; AND (c) SECTION C-C
(REFER TO Figure 6.18 FOR SECTION LOCATIONS).
6-64
FIGURE 6.18
GROUTED RIPRAP SCHEMATIC
6-65
designer should verify site specific conditions and coordinate with a qualified manufacturer to
properly specify gabion wire. See ASTM A-974 and ASTM A-975.
Gabions are not maintenance free and must be periodically inspected to determine whether the
wire is sound. If breaks are found while they are still relatively small, they may be patched by
weaving new strands of wire into the wire cage. Wire enclosed rock installations have been
found to attract vandalism. Flat mattress surfaces seem to be particularly susceptible to having
wires cut and stones removed. It is recommended that, where possible, mattress surfaces be
buried, where they are less prone to vandalism. Wire enclosed rock installations should be
inspected at least once a year under the best circumstances and may require inspection every
three months in vandalism prone areas in conjunction with a regular maintenance program.
They should also be inspected after high flow events. Under high flow velocity conditions, mattresses on sloping surfaces must be securely anchored to the surface of the soil as discussed
previously.
Materials
Rock and Wire Enclosure Requirements - Rock filler for the wire baskets should meet the rock
property requirements for common riprap. Rock sizes and basket characteristics should meet
ASTM A-974 and ASTM A-975. The minimum rock size d0 should be equal to the size of the
gabion mesh opening. The maximum rock size d100 should be less than the gabion thickness.
Bedding Requirements - Long term stability of gabion (and common riprap) erosion protection
is strongly influenced by proper bedding conditions. A large percentage of all riprap failures are
directly attributable to bedding failures, which is particularly disturbing in light of the fact that over
half of all riprap installations experience some degree of failure within 10 years of construction.
Refer to Section 6.6.3 for gravel bedding or filter design. Nonwoven, 8 ounce filter fabric has
been found acceptable in many applications. The design engineer should check with the manufacturer for its given application.
6-66
gabion counterforts (thickened gabion sections that extend into the channel bank) at the
upstream edge of the lining. Counterfort spacing shall be per manufacturers recommendations.
Mattresses and flat gabions on channel side slopes need to be tied to the banks. The ties should
be metal stakes no less than 4 feet in length (sandy soils warrant longer lengths). These should
be located at the inside corners of basket diaphragms along an upslope (highest) basket wall, so
that the metal stakes are an integral part of the basket. The exact spacing of the stakes depends
upon the configuration of the baskets, however the following is the suggested minimum spacing:
stake every 6 feet along and down the slope for 2:1 slopes or steeper. Channel linings should be
tied to the channel banks with gabion counterforts (thickened gabion sections that extend into the
channel bank) at the upstream edge of the lining. For most applications, mattresses should be a
minimum of 9 inches thick.
FIGURE 6.19
SLOPE MATTRESS LINING
(Wright-McLaughlin Engineers, 1969)
6-67
suitable for submittal to FEMA, using Requirements For Flood Study Technical Documentation,
ADWR 1997.
The starting water surface elevations for profile computations for mainstreams and tributaries
should be based on FEMA requirements (FEMA, 2003). In general, the starting water surface
elevations chosen for profile computations should be based on normal depth (or slope-area),
unless known water surface elevations are available from other sources. When using normal
depth on the main stream, the model should be started several cross sections downstream of the
beginning of the study reach. For starting conditions on tributaries, normal depth should be used
unless a coincident peak situation is assumed, or the tributary flow depths are higher than the
corresponding main stream events. The assumption of coincident peaks may be appropriate if a)
the ratio of the drainage areas lies between 0.6 and 1.4, b) the times of peak flows are similar for
the two combining watersheds, and c) the likelihood of both watersheds being covered by the
storm being modeled are high. If gage records are available for the basin, guidance for coincidence of peak flows should be taken from them.
The Consultant shall estimate blockage due to debris at bridge piers based on field conditions.
As a minimum, use the greater of 2 times the diameter of the pier or 1 foot on each side of the
pier.
Freeboard for levees shall, as a minimum, comply with FEMA freeboard criteria: 3 feet of freeboard at the 100-year peak stage plus 1 foot additional at bridges (FEMA, 2003). Refer to the
local jurisdiction Policies and Standards Manual for possible more stringent conditions.
Locations of cross sections used in the water surface profile calculations shall be provided on a
scaled map and also in a tabular format. The cross section labels on the maps shall reflect cross
sections in the models (ADWR, 1997).
Refer to the
Consideration shall be given to how the upstream and downstream floodplain conditions will
impact the proposed channel. The effects of existing and potential mining and fill operations
shall be addressed. Overbank flooding upstream of the channelization shall be analyzed to demonstrate that design flows enter and are contained within the improved channelization. The
6-68
design and analysis shall address the potential impacts of future modifications proposed by others. Gradual transition of the existing floodplain/floodway upstream and downstream of the
channelization is required.
The minimum factor of safety applied to hydraulic forces on structural components shall be 1.5,
based on the 100-year frequency peak flow.
The analysis shall address sediment transport, scour, lateral migration, and river mechanics as
discussed in Chapter 11.
Plans submitted for review shall include profiles showing the top of levee protection, toe ground
elevation, toe-down, hydraulic grade line, water surface elevation, existing and design invert elevations at the thalweg, and the low chord elevations for bridges. Also, road and railway crossing
locations must be shown on plans and profiles.
Requirements
Use available right-of-way width of 50 feet, with approximately 3 feet of depth above the
low flow channel.
6-69
Solution
A. Use Equation (6.22) to determine channel capacity.
1. Find cross sectional area of flow, [Total area ( A T ) = area of low flow channel ( A lf ) + area
of main channel ( A mc ) ].
A T = A lf + A mc
= ( 1.5 ) ( 5 ) + 3 ( ( 18 + 42 ) 2 )
= 7.5 + 90
A T = 97.5 sq ft
2. Find wetted perimeter and indicate a 4 inch thickness for low flow wall.
P T = P lf + P mc
2
2 0.5
P T = 45.7ft
3. Find hydraulic radius.
R = AT PT
= 97.5 45.7
R = 2.13 ft
4. Determine Manning's n from Table 7.6.
Find composite n-value:
Concrete lined low flow: n = 0.015
Grass-lined main channel: n = 0.025
6-70
P i n i1.5
n = i -------------PT
0.67
1.5 )
( P lf ) ( n lf1.5 ) + ( P mc ) ( n mc
n = -----------------------------------------------------------PT
0.67
1.5
1.5 0.67
0.67
n = 0.023
5. Substitute values to solve for slope and multiply Equation (6.22) by A T and rearrange:
Q = ( 1.49 n )A T R
0.67
So
S o = [ ( Qn ) ( 1.49A T R
0.5
0.67
)]
0.67
)]
S o = 0.0029 ft/ft
Since a channel bottom slope of 0.0029 ft/ft is sufficient to convey the design flow of
565 cfs , the steeper existing S o of 0.006 ft/ft will convey the flow with a smaller cross
0.67
sectional area. Equation (6.22) can be solved for A T R , which can then be used to
determine the actual cross section of flow by trial and error:
AT R
0.67
= Qn 1.49S o
0.5
0.5
6-71
y n = 2.45 ft
A T = 7.5 + 2.45 ( ( 18 + 37.6 ) 2 ) = 75.6 ft
2 0.5
) = 41.2 ft
0.67
= ( 75.6 ) ( 1.83 )
0.67
Flow along the channel at S o = 0.006 ft/ft has reduced the water depth by 0.55 ft .
Note that the composite n-value was not revised using the new values of P lf , P mc and
PT .
B. Check velocity and Froude Number.
1. Check velocity.
V = QA
= 565 75.6
V = 7.5 fps > 6 fps
6 ft/sec allowable for Bermuda grass lined channels with erosion resistant soil only.
2. Check the Froude number.
F r = V ( gd )
0.5
0.5
6-72
0.5
0.5
= 0.67
which is within the acceptable range of subcritical flow. See Chapter 8 for grade control
structures.
3. Check channel transitions (see Chapter 8).
C. Check freeboard requirement using Equation (6.25).
Using the revised slope of S o = 0.0029 ft/ft , and velocity of V = 5.8 ft/sec .
2
FB = 0.25 ( y + V 2g )
2
Summary
Use grass lined channel with 4:1 side slopes.
Velocity = 5.8 ft/sec ; F r = 0.67 , subcritical flow. See Table 6.2 and Table 6.3 for allowable soil and grass types.
Channel slope = 0.0029 0.006 ft/ft (existing).
Provide grade control.
Provide 1 foot minimum freeboard allowance.
Check flow velocities and hydraulic properties for other flows anticipated. In particular,
check for sedimentation problems that may result from smaller more frequent storms with
resultant lower velocities.
It should be noted that erosion may occur along the edges of the concrete-lined low flow
6-73
channel, especially at a bend. Grouted riprap and/or loose riprap should be installed
along the edges to prevent scour.
6.7
REFERENCES
6-74
6-75
Robinson, K.M., Rice, C.E., and Kadavy, K.C., 1998. Design Rock Chutes, Transactions of the
American Society of Agricultural Engineers, 41(3): 621-626.
Simons, D. B., and Senturk, F., 1992. Sediment Transport Technology: Water and Sediment
Dynamics, Water Resources Publications, Littleton, CO.
Simons, Li and Associates, Inc., 1981, Design Guidelines and Criteria for Channels and
Hydraulic Structures on Sandy Soil, Urban Drainage and Flood Control District and City of
Aurora, Colorado.
, 1989, Sizing Riprap for the Protection of Approach Embankments and Spur Dikes and
Limiting the Depth of Scour at Bridge Piers and Abutments, prepared for Arizona Department of Transportation, Report No. FHWA-AZ89-260.
, 1989a, Sizing Riprap for the Protection of Approach Embankments and Spur Dikes and
Limiting the Depth of Scour at Bridge Piers and Abutments. Arizona Department of Transportation.
, 1989b, (revised July, 1998). Standards Manual for Drainage Design and Floodplain Management in Tucson, Arizona. Prepared for City of Tucson, Department of Transportation,
Engineering Division.
Subramanya, K., 1997. Flow in Open Channels. McGraw-Hill, 2nd edition.
Thomsen, B.W., and Hjalmarson, H.W., 1991, Estimated Manning's Roughness Coefficients for
Stream Channels and Floodplains in Maricopa County, Arizona, U.S. Geological Survey,
Water Resources Division, Tucson, Arizona, Prepared for the Flood Control District of Maricopa County.
U.S. Army Corps of Engineers (USACE), 1981, Final Report to Congress, The Streambank
Erosion Control Evaluation and Demonstration Act of 1974, Section 32, Public Law 93-251,
Washington, D.C.
, 1990, HEC-2 Water Surface Profiles, User's Manual.
, 1990, Engineering and Design - Construction with Large Stone, Engineer Manual EM
1110-2-2302.
, 1992, "Engineering and Design: Design and Construction of Grouted Riprap," Technical
Letter ETL No. 1110-2-334, US Army Corps of Engineers, Washington, DC 20314-1000.
, 1994, Hydraulic Design of Flood Control Channels. Engineer Manual 1110-2-1601.
, 2001a, HEC-RAS River Analysis System, Hydraulic Reference Manual. [HEC WEB Site]
, 2001b, HEC-RAS River Analysis System, User's Manual. [HEC WEB Site]
U.S. Department of the Interior, Bureau of Reclamation, undated, Lining for Irrigation Canals.
6-76
U.S. Department of Transportation (USDOT), Federal Highway Administration, 1961, Hydraulic Design Series No. 3, Design Charts for Open-Channel Flow. [USDOT Hydraulics WEB
Site]
, 1988, Design of Roadside Drainage Channels with Flexible Linings, Hydraulic Engineering Circular No. 15, Publication No. FHWA-IP-87-7.
,1989, Design of Riprap Revetment, Hydraulic Engineering Circular No. 11, Publication No.
FHWA-IP-89-016.
U.S. Government Printing Office (USGPO), Code of Federal Regulations, 2000. 44CFR Section 65.10: Mapping of Areas Protected by Levee Suystems. http://www.gpo.gov/fdsys/
pkg/CFR-2000-title44-vol1
Wright-McLaughlin Engineers, 1969, Urban Storm Drainage Criteria Manual, Urban Drainage
and Flood Control District, Denver, Colorado.
6-77
Simons, Li and Associates, Inc., 1985, Design Manual for Engineering Analysis of Fluvial Systems, Arizona Department of Water Resources.
U.S. Department of Transportation (USDOT), Federal Highway Administration, 1965, Hydraulic Design Series No. 4, Design of Roadside Channels.
6-78
7 FRICTION LOSSES IN
OPEN CHANNELS
TABLE OF CONTENTS
7 FRICTION LOSSES IN OPEN CHANNELS
7.1
7.2
7.3
SYMBOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-1
CONVERSION FACTORS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-2
INTRODUCTION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-3
7.3.1
Purpose and Scope..................................................................................... 7-4
DESCRIPTION OF STUDY AREA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-5
MANNINGS EQUATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-6
VALUES OF MANNINGS N FOR MAIN CHANNELS AND OVERBANK AREAS . . 7-7
7.6.1
Base Values of n for Unstable Channels .................................................... 7-7
7.6.2
Base Values of n for Stable Channels ...................................................... 7-11
7.6.3
Equations for Selection of Base n-values for Stable Channels ................. 7-12
7.6.4
Flow Depth and Channel Gradient ............................................................ 7-14
7.6.5
Values and Descriptions For Components of Mannings n ....................... 7-15
7.6.6
Values of Mannings n For Agriculture or Overbank Areas ....................... 7-27
7.6.7
Composite Values of n For Constructed Channels ................................... 7-29
7.6.8
Procedure For Subdivision of Cross Sections........................................... 7-29
7.6.9
Procedure for Selection of n For Changing Vegetation Conditions........... 7-35
7.6.10 Selection Procedure of n for Natural and Constructed Channels.............. 7-41
VEGETATION MAINTENANCE PLAN GUIDELINES . . . . . . . . . . . . . . . . . . . . . . . 7-53
7.7.1
Freeboard.................................................................................................. 7-54
7.7.2
Vegetation Assessment and Maintenance Plan Outline ........................... 7-74
SUMMARY AND CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-75
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-76
7.9.1
Cited in Text .............................................................................................. 7-76
7.4
7.5
7.6
7.7
7.8
7.9
7.1
SYMBOLS
A
B
BM
Cblocking
Cdist
Cdepth
d50
=
=
=
=
=
=
=
7-1
d84
Dmax
K
Kt
Kv
m
n
nveg
P
Q
R
Se
Sw
SP
V
Vflex
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
7.2
CONVERSION FACTORS
TABLE 7.1
CONVERSION FACTORS
Multiply
By
To Obtain
Length
inches (in)
25.4
millimeters (mm)
feet (ft)
0.3048
meters (m)
miles (mi)
1.609
kilometers (km)
Area
square miles (mi2)
2.590
Flow rate
cubic feet per second
7-2
0.02832
7.3
INTRODUCTION
Forward: This chapter is derived from the U.S. Geological Survey Scientific Investigations
Report 2006-5108 (Phillips and Tadayon, 2006). It is reproduced here in its entirety, with some
slight changes in organization, formatting, and table and figure titles. It is intended to be a guide
for estimation of friction losses in both natural and constructed open channels through selection
of Mannings n. In addition, guidance and design considerations for friction loss estimation are
provided for planning for ongoing management of vegetation so that public safety can be maintained in conjunction with other design goals including preservation and enhancement of riparian
habitat, and landscape character.
The U.S. Geological Survey, in cooperation with the Flood Control District of Maricopa County,
has been studying the hydraulic effects associated with channel-roughness elements in streams
in Arizona. Computation of flow in an open channel requires evaluation of the channels resistance to flow, which is typically represented by a roughness parameter, such as Mannings n. The
characteristics of natural channels and of some constructed channels and the factors that affect
channel roughness can vary greatly; however, the combinations of these factors are numerous.
In many cases, components of Mannings n cannot be determined with sufficient accuracy by
direct measurement of roughness characteristics, such as vegetation and variations in channel
shape. Therefore, selection of roughness for natural and constructed channels typically is based
on field judgment and skill, which are acquired mainly through experience. The expertise necessary for proper selection of roughness coefficients can be obtained, in part, by examining characteristics of channels that have known or verified coefficients (Barnes, 1967; Aldridge and Garrett,
1973; Phillips and Ingersoll, 1998), or have been selected by experienced personnel (Thomsen
and Hjalmarson, 1991). The roughness coefficient can be verified by computations made by
using data from streamflow measurements and from measurements of the physical features of
the channel. Photographs of channel segments for which n-values have been verified can be
used as a comparison standard to aid in assigning n-values to similar channels. Semi-empirical
equations that relate hydraulic and channel properties have been derived from verified values of
Mannings n. The equations also can be used as a tool for selection of n-values.
In the arid to semi-arid southwestern United States, one factor that retards flow and that can have
the greatest single impact on energy losses and resulting computed water surface elevations is
the vegetation occupying the channel bed, banks, and overflow areas. Vegetation characteristics
for particular channel reaches may have a larger effect than all other flow resistance elements by
a factor of three to four (Phillips and Ingersoll, 1998). Vegetation is a constantly changing factor
as well; it can be laid over or removed during floodflows, or grow to substantial spatial densities
and heights in just a few years time. Different species of vegetation also have different flexural
strengths for a given size or height, which further complicates assessing flow impacts on vegetation, and the subsequent impact of vegetation on flow-energy losses. When vegetation for a particular channel either grows to significant heights and densities or is laid over and possibly
removed during floodflows, the roughness coefficients selected for that channel for earlier
7-3
hydraulic studies, years, or decades may have changed significantly, possibly significantly
impacting the earlier computed conveyance and water surface elevations for the design discharge. A semi-empirical relation has been developed that relates hydraulic properties of flow to
vegetation characteristics and conditions within the channel (Phillips, et al., 1998). The relation
will allow the user to determine impact of flow on the vegetation so estimates of n-values for the
vegetation component can be more accurately selected. The relation is restricted primarily to
vegetation growing in the main channel of natural and constructed stream channels.
In past decades, these heavy growths of vegetation may have been modified or removed completely to allow for adequate conveyance of floodflows. With a shift in emphasis in recent years
toward preserving riparian vegetation to provide habitat for many species of wildlife and aesthetically pleasing multi-use areas for homeowners and businesses, however, engineering-based
vegetation maintenance guidelines are now deemed to be necessary. Vegetation maintenance
guidelines presented in this document are intended to optimize the preservation of riparian habitat and the aesthetics of multi-use areas, while mitigating damage from floodflows along natural
and constructed channels.
7-4
7.4
The basin and range topography typical in most parts of Arizona is characterized by steep blockfaulted mountains separated by gently sloping valleys. Ephemeral and intermittent streams in the
study area (Figure 7.1) cover a wide variety of conditions ranging from unstable alluvial channels,
generally stable channels of cobble to boulder-sized bed material, and extremely stable bedrock
channels. Sand-dominated streambeds commonly are characterized by unstable boundary conditions, high sediment loads, and long periods of low or no flow punctuated by brief periods of
flooding that increase discharge several orders of magnitude within minutes. Although generally
more stable than sand channels, some gravel-dominated channels in Arizona are ephemeral or
intermittent and subject to flooding for brief periods. Flash flooding and the general instability of
the beds of natural channels in Arizona complicate the task of accurately selecting roughness
characteristics that may represent conditions during peak flow. Many stream channels in urban
areas are manmade and fairly stable. They may be composed of either soil, cement, concrete,
riprap, grouted and wire-enclosed rock, firm earth, grass, or a combination of these materials.
The type, distribution, and density of riparian vegetation can vary in the study area. Vegetation
types found in and along many streams in central Arizona include saltcedar, willow, cottonwood,
mesquite, palo verde, and many shrub and grass species. Effluent-dominated streams in the
study area may contain elevated nutrient levels resulting in increased vegetation growth. Vegetation in ephemeral and intermittent streams and constructed channels in central Arizona can be
the primary factor in estimating total resistance to flow.
Mean annual precipitation in the study area ranges from about 7 in. near Phoenix to more than
30 in. in adjacent mountain ranges. Precipitation in Arizona mainly occurs during June through
October and December through March; rainfall is about equal in each period. Summer precipitation normally is produced by convective thunderstorms. These storms are characterized by rainfall of high intensity and short duration. They usually cover small areas and may result in flash
floods. Winter precipitation normally is produced by regional frontal systems that are characterized by low-intensity rainfall of long duration that covers a large areal extent. Dissipating tropical
cyclones cause storms in Arizona that occur primarily in September and October (Webb and
Betancourt, 1992). These storms can cause record floods of regional extent.
7-5
FIGURE 7.1
MAP SHOWING STUDY AREA IN MARICOPA COUNTY, ARIZONA
112
11130'
iv
er
113
17
Cr
3330'
te
ca
m
nn
60 89
ia l
360
10
20 MILES
20 KILOMETERS
10
Ri
er
a sh
l W
ko
Ve
R i v er
10
85
Gil a
R ive
lt
Wa sh
33
87
R ive r
Sa
en
Sy
Ver de
un
India
n
Wa
nd
Be
sh
10
Phoenix
A g ua
New
Sk
ree
k
eek
r
Ri
ve
Hassa
ya
m pa
89
Fri a
R i ve r
60
or e
11230'
60
C av
e C
ree
k
34
ARIZO NA
M A R I C O P A
C O U N T Y
3230'
7.5
MARICOPA
COUNTY
MANNINGS EQUATION
Owing to its simplicity of form and to the satisfactory results it lends to practical applications,
Mannings equation has become the most widely used of all uniform-flow equations for openchannel flow computations (Chow, 1959). Mannings equation in the following form is commonly
used to compute discharge in natural channels:
7-6
1.486
23 12
Q = ------------- AR S e
n
where:
Se
(7.1)
Equation (7.1) was developed for conditions of uniform flow in which the area, depth, and velocity
are constant throughout the reach (Thomsen and Hjalmarson, 1991). The equation is also valid
for non-uniform reaches if the energy gradient is modified to reflect only the losses due to boundary friction. In applying Mannings equation, the greatest difficulty lies in the determination of the
roughness coefficient, n (Chow, 1959).
7-7
FIGURE 7.2
RELATION OF STREAM POWER AND MEDIAN GRAIN SIZE TO FLOW REGIME
4.0
2.0
Upper-regime flow
Transition-regime flow
1.0
0.8
0.6
Lower-regime flow
0.4
NOTE: 62=specific weight of water, in pounds
per cubic foot;
R=hydraulic radius, in feet;
Sw =water-surface slope, in feet per foot;
V=mean velocity, in feet per second
0.2
0.1
0.2
0.4
0.6
0.8
1.0
1.2
The flow regime is governed by the size of the bed material and the stream power, which is a
measure of energy transfer. Simons and Richardson (1966) defined stream power (SP) as
SP = 62.4RS w V
where:
62.4
Sw
(7.2)
In lower-regime flow, the bed may have a plane surface with little or no movement of sand or
small, uniform waves (ripples), or it may have large, irregular waves (dunes) that are formed by
sediment moving downstream. Water surface undulations manifested in lower-regime flow generally are out of phase with the bed surface (Figure 7.3). The fact that the water surface is out of
phase with the bed surface is a positive indication that the flow is tranquil or subcritical (Simons
and Richardson, 1966, p. J9).
The bed configuration in the transition-zone regime can be erratic and may manifest bedforms
typical to those in upper-regime flow depending mainly on antecedent conditions (Simons and
Richardson, 1966, p. J11). Resistance to flow and sediment transport also has the same variability as the bed configuration in the transition zone.
7-8
FIGURE 7.3
IDEALIZED DIAGRAM OF BED AND SURFACE CONFIGURATIONS
for Alluvial Streams for Various Regimes of Flow
A. Lower-regime flows
Plane-bed
regime prior
to movement
Ripple regime
Dune regime
B. Transition-regime flows
Plane-bed
transition
regime
C. Upper-regime flows
Standingwave
regime
Antidune
regime
In upper-regime flow, the bed may have a plane surface or it may have long, smooth sand formations in phase with the surface waves (Leopold, et al., 1964; Karim, 1995). These surface waves
are known as standing waves or antidunes (Figure 7.3; Simons and Richardson, 1966). As the
size of the antidunes grow, the water surface slope on the upstream side of the waves becomes
steeper, and the antidune may eventually collapse. Following collapse of the antidunes, the flow
generally will shift back to plane-bed conditions. When antidune formations occur in upperregime flow and the water and bed surface are in phase, the flow is rapid or supercritical (Simons
and Richardson, 1966, p. J9).
7-9
The n-value for a sand channel is generally assigned for upper-regime flow, and the flow regime
is checked by computing the velocity and subsequently the stream power that corresponds to the
assigned n-value. The computed stream power is compared with the n-value necessary to cause
upper regime flow.
Aldridge and Garrett (1973, p. 5) suggest that n-values for lower- and transitional-regime flows
can vary greatly and depend on the bed forms present at a particular time; these values generally
will be much larger than the values for upper-regime flow. Unfortunately, there is a lack of definition of roughness coefficients available for the lower regime (Benson and Dalrymple, 1967). Most
flood peaks on sand channels, however, occur when the bed configuration is in the upper regime
(Figure 7.4A and B). According to Benson and Dalrymple (1967), the n-values for upper-regime
flow are dependent on the median grain size of bed material (Table 7.2).
FIGURE 7.4
TYPICAL UNSTABLE SAND CHANNEL IN CENTRAL ARIZONA
A, View Upstream of Midchannel During No-Flow Period.
B, View from Cableway Looking Upstream During Flow of February 9, 1993.
A. No-flow view
NO
N
NOT
NOTE:
O E:
OT
E: Ro
Rod
R
od
d ind
indicates
nd
d ca
cates
ess wa
w
water-surface
terr surfac
f e eelevation
fac
ev tio
on
on
for the peak flow of January 8, 1993
B. Flow view
7-10
TABLE 7.2
BASE VALUES OF n FOR UPPER-REGIME FLOWS IN SAND CHANNELS
[Modified from Benson and Dalrymple (1967)]
Median Size of Bed Material (mm)
Base n-value
0.2
0.012
0.3
0.017
0.4
0.020
0.5
0.022
0.6
0.023
0.8
0.025
1.0
0.026
Firm earth
Coarse sand
Fine gravel
Gravel
Coarse gravel
Base n-value
Millimeters
Inches
Benson and
Dalrymple (1967)
Chow
(1959)
---
---
0.0250.032
0.020
12
---
0.0260.035
---
---
---
---
0.024
264
0.082.5
0.0280.035
---
---
---
---
0.028
7-11
TABLE 7.3
BASE VALUES OF MANNINGS n FOR CHANNELS CONSIDERED STABLE
Channel Type
Base n-value
Millimeters
Inches
Benson and
Dalrymple (1967)
Chow
(1959)
Cobble
64256
2.510.5
0.0300.050
---
Boulder
> 256
> 10
0.0400.070
---
0.0926R
n = ----------------------------------------------R
7-12
(7.3)
d 84
FIGURE 7.5
TYPICAL COBBLE-BED CHANNEL IN CENTRAL ARIZONA
for Which Mannings n was Verified
(Used for Development of Equation (7.4))
A similar equation was developed for generally lower-gradient stable channels in central Arizona
for which the base n-value was the only perceivable factor that contributed to total roughness
(Figure 7.5; Phillips and Ingersoll, 1998). That equation is in the form of:
16
0.0926R
n = -------------------------------------------------R
where:
d 50
(7.4)
The equation was developed by utilizing channels with a median diameter of bed material that
ranged from 0.28 to 0.36 foot. These equations have their limitations, but can be utilized as a
check or reference for assigning base values of n.
7-13
FIGURE 7.6
TYPICAL HIGH-GRADIENT COBBLE-BED CHANNEL IN CALIFORNIA
for Which Manning's n was Verified and Utilized for Development of Equation (7.3)
7-14
n = ( n 0 + n 1 + n 2 + ... + n n )m
where:
n0
(7.5)
FIGURE 7.7
THE MANNINGS n COMPONENT FOR CHANNEL BANK IS CONSIDERED SMOOTH
with a Corresponding Component of 0.000 (Table 7.4)
7-15
FIGURE 7.8
THE MANNINGS n COMPONENT FOR THE ERODED AND SCOURED BANKS
is Considered Moderate with a Range of 0.006 to 0.010 (Table 7.4)
FIGURE 7.9
THE MANNINGS n COMPONENT FOR THE ERODED AND SLIGHTLY SCOURED BANKS
is Considered Minor with a Range of 0.001 to 0.005 (Table 7.4)
7-16
TABLE 7.4
ADJUSTMENT FACTORS OR COMPONENT RANGES FOR VARIOUS CHANNEL CONDITIONS
Used to Determine Mannings n-values
(Adjustment to degree of meandering values apply to flow confined in the channel and does not
apply where flow crosses meanders; Modified from Cowen, 1956; and Chow, 1959.)
Channel
Conditions
Mannings n
Adjustment
Example
Degree of irregularity
Smooth
0.000
Minor
0.0010.005
Moderate
0.0060.010
Severe
0.0110.020
0.000
Alternating
occasionally
0.0010.005
Alternating
frequently
0.0100.015
Effects of obstructions
Negligible
0.0000.004
Minor
0.0050.015
Appreciable
0.0200.030
7-17
TABLE 7.4
ADJUSTMENT FACTORS OR COMPONENT RANGES FOR VARIOUS CHANNEL CONDITIONS
Used to Determine Mannings n-values
(Adjustment to degree of meandering values apply to flow confined in the channel and does not
apply where flow crosses meanders; Modified from Cowen, 1956; and Chow, 1959.)
Channel
Conditions
Mannings n
Adjustment
Severe
0.0400.060
Example
Obstructions occupy more than 50 percent of the cross section
area, or the space between obstructions is small enough to
cause turbulence across most of the cross section.
Amount of vegetation
Negligible
0.0000.002
Small
0.0020.010
Medium
0.0100.025
Large
0.0250.050
Very large
0.0500.100
7-18
TABLE 7.4
ADJUSTMENT FACTORS OR COMPONENT RANGES FOR VARIOUS CHANNEL CONDITIONS
Used to Determine Mannings n-values
(Adjustment to degree of meandering values apply to flow confined in the channel and does not
apply where flow crosses meanders; Modified from Cowen, 1956; and Chow, 1959.)
Channel
Conditions
Mannings n
Adjustment
Extremely
large
0.1000.200
Example
Mature (greater than 10 years old) willow trees and tamarisk
intergrown with brush and blocking flow by more than 70 percent of the flow area, causing turbulence across most of the
section. Depth of flow is less than average height of the vegetation. Dense stands of palo verde or mesquite that block flow
by 70 percent or more and hydraulic radius is about equal to or
greater than average height of vegetation.
Degree of meandering
Minor
1.00
Appreciable
1.15
Severe
1.30
FIGURE 7.10
THE MANNINGS n COMPONENT FOR THE SLOUGHED BANKS
(Jagged and irregular surfaces are considered severe with a range of 0.011 to 0.020 (Table 7.4))
7-19
FIGURE 7.11
CHANNEL REACH WHERE THE SIZE AND SHAPE OF SECTIONS CHANGES GRADUALLY
(The Mannings n component for this example is considered negligible or 0.000 (Table 7.4))
Effect of Obstructions
Isolated boulders, debris deposits, logs, power poles and towers, and bridge piers that disturb
the flow pattern in the channel increase energy losses, or n-values (Figure 7.12 - Figure 7.16).
The amount of increase depends on the shape of the obstruction, its size in relation to other
roughness elements in the cross section, the number, arrangement, and spacing of the obstructions, and the magnitude of flow velocity (Aldridge and Garrett, 1973). When the flow velocity is
high, an obstruction exerts a sphere of influence that can be much larger than the obstruction
because the obstruction can affect the flow pattern for considerable distances on each side. At
velocities that generally occur in channels that have gentle to moderately steep slopes, the
sphere of influence is about 3 to 5 times the width of the obstruction (Figure 7.12; Aldridge and
Garrett, 1973). Several obstructions create overlapping spheres of influence and can cause considerable disturbance and loss of energy even though the obstructions may occupy only a small
part of the cross section. Aldridge and Garrett (1973) assigned values to four degrees of obstructions (Table 7.4).
7-20
FIGURE 7.12
GENERAL FLOW DISTURBANCE CAUSED BY BRIDGE PIERS
at Colorado River near Moab, Utah
FIGURE 7.13
LARGE ANGULAR BOULDER IN MIDCHANNEL
7-21
FIGURE 7.14
POWER POLE OBSTRUCTING LESS THAN 5 PERCENT OF THE CHANNEL AREA
(The Mannings n component for the obstruction is considered negligible, with a corresponding
range of 0.000 to 0.004 (Table 7.4))
FIGURE 7.15
REMOVED BRUSH CAUGHT ON MORE FLOW RESISTANT VEGETATION
(Resulting in a localized angular obstruction with a larger sphere of influence than the resistant
vegetation alone)
7-22
FIGURE 7.16
BRIDGE PIER DEBRIS
(The Mannings n component is considered to range from 0.005 to 0.015 (Table 7.4))
Amount of Vegetation
The degree to which vegetation affects flow depends on the depth of flow relative to vegetation
height, the percentage of flow obstructed by the vegetation, the degree to which vegetation is
affected or flattened by high water, and the alignment of vegetation relative to the flow (Figure
7.17 - ; Phillips, et al., 1998). In wide channels having small depth to width ratios and no vegetation on the channel bed, the effect of bank vegetation is generally small, and the maximum
adjustment is about 0.005. If the channel is relatively narrow and has steep banks covered by
dense vegetation that hangs over the channel, the maximum adjustment would be about 0.030.
The larger adjustment values given in Table 7.4 apply primarily in places where vegetation covers most of the main channel. If vegetation is the primary factor that affects n, as in flood plains,
in parts of a channel that are seldom flooded, or in the main channel of ephemeral or intermittent
streams, the n-value is assigned for the vegetation rather than for the material in which it is growing (Thomsen and Hjalmarson, 1991). Similar to the impact of obstructions on energy losses, at
flow velocities that generally occur in channels that have gentle to moderately steep slopes, the
sphere of influence can be about 3 to 5 times the width of the vegetation. Closely clumped trees
or reaches where flow-resistant vegetation blocks flow by more than 50 percent of the cross sectional area can create overlapping spheres of influence and can cause considerable disturbance
and loss of energy with n-value adjustments that range from 0.050 to 0.200 (Table 7.4).
7-23
FIGURE 7.17
TALL GRASS LAID OVER AS A RESULT OF A FLOW OF 6,480 CUBIC FEET PER SECOND
FIGURE 7.18
LONE TREE THAT IS APPROXIMATELY 20 FEET IN HEIGHT
FIGURE 7.19
RANDOMLY SCATTERED SHRUBS
(Flow elevation approximated at the level of the survey rod for a discharge of 403 cubic feet per
second)
7-24
FIGURE 7.20
LARGE MESQUITE WITH BRANCHES THAT HANG OVER THE MAIN-CHANNEL AREA
FIGURE 7.21
RANDOMLY DISTRIBUTED MESQUITE AND PALO VERDE
Approximately 15 to 20 feet in Height (Table 7.4)
FIGURE 7.22
IMAGE SHOWING FLOW ALTERED BY VEGETATION
(Table 7.4)
7-25
FIGURE 7.23
MANNINGS n COMPONENT FOR THE VEGETATION IS CONSIDERED EXTREMELY LARGE
(with a corresponding range in of 0.100 to 0.200 (Table 7.4))
FIGURE 7.24
EXTREMELY DENSE VEGETATION IN THE CHANNEL THAT DRAINS THIS URBAN AREA
(A, Downstream from midchannel before the flow of December 10, 1991; B, Upstream from left
bank during the flow of December 10, 1991)
A. View before flood event
B. View of flooding
7-26
Utilizing verified roughness coefficients for a site in central Arizona (Skunk Creek above Interstate 17), Phillips and Ingersoll (1998) developed a semi-empirical relation for non-submerged
and randomly-distributed shrubs. The relation or equation is in the form of
(7.6)
Use of the equation is somewhat limited to channel and vegetation conditions similar to those in
Skunk Creek above Interstate 17, Arizona (Figure 7.19; Phillips and Ingersoll, 1998). Extrapolations to other channels with similar types of flow, channel, and vegetation conditions can be
made, but should be done so with caution.
Mannings n
Minimum
Normal
Maximum
Short grass
0.025
0.030
0.035
High grass
0.030
0.035
0.050
No crop
0.020
0.030
0.040
0.025
0.035
0.045
0.030
0.040
0.050
0.035
0.050
0.070
0.035
0.050
0.060
0.040
0.060
0.080
0.045
0.070
0.110
0.070
0.100
0.160
Pasture, no brush
Cultivated areas
Shrubs
7-27
TABLE 7.5
VALUES OF MANNINGS n FOR AGRICULTURE OR OVERBANK AREAS
[Modified from Chow (1959) and Thomsen and Hjalmarson (1991)]
Trees
Dense willows, mesquite, saltcedar
0.110
0.150
0.200
0.030
0.040
0.050
0.050
0.060
0.080
0.080
0.100
0.120
0.100
0.120
0.160
FIGURE 7.25
EXAMPLES OF COTTON IN SUMMER AND FALL
Fields of Mature Cotton in the Summer (A) and Defoliated Cotton in the Fall (B)
A. Mature cotton
B. Defoliated cotton
7-28
7-29
best results (Cruff, 1999). One of the largest shortcomings of the equation when working with
natural channels, and even some constructed channels, is the change in energy loss, or n,
across or perpendicular to the channel. Because of these changes there is a tendency to subdivide the channel section at changes in roughness. This subdivision method can greatly affect the
computation for hydraulic radius, R, and significantly and erroneously impact the final computations.
7-30
TABLE 7.6
COMPOSITE VALUES OF n FOR STABLE CONSTRUCTED CHANNELS
Type of Channel and Description
n-value1
Minimum
Normal
Maximum
1. Trowel finish
0.011
0.013
0.015
2. Float finish
0.013
0.015
0.016
3. Unfinished
0.014
0.017
0.020
0.016
0.019
0.023
0.018
0.022
0.025
b. Soil cement
0.018
0.020
0.025
0.031
0.033
0.040
0.038
0.042
0.056
0.028
0.030
0.040
0.017
0.020
0.025
0.020
0.023
0.026
0.023
0.033
0.036
0.018
0.022
0.025
0.022
0.025
0.033
0.028
0.030
0.035
2. Stony bottom
0.025
0.035
0.040
0.030
0.040
0.050
7-31
TABLE 7.6
COMPOSITE VALUES OF n FOR STABLE CONSTRUCTED CHANNELS
Type of Channel and Description
n-value1
Minimum
Normal
Maximum
0.025
0.035
0.040
0.035
0.040
0.050
c. Rock cuts
1.Excerpt from: Simons, Li and Associates (1981). Adapted from Chow (1959), Aldridge
and Garret (1973), and USDOT (2005).
TABLE 7.7
COMPOSITE MANNINGS n-VALUES FOR ROCK RIPRAP LINED CHANNELS
Source: USDOT (2005), page 6-1, equation 6.1
d50 (in)
Average
Flow Depth
(A/T) (ft)
2.5
3.0
5.0
6.0
9.0
12.0
15.0
18.0
21.0
24.0
1.0
0.045
0.049
0.062
0.069
n/a
n/a
n/a
n/a
n/a
n/a
1.5
0.042
0.044
0.054
0.059
0.073
0.088
n/a
n/a
n/a
n/a
2.0
0.040
0.042
0.051
0.054
0.066
0.077
0.089
n/a
n/a
n/a
2.5
0.039
0.041
0.048
0.052
0.061
0.070
0.080
0.090
n/a
n/a
3.0
0.038
0.040
0.047
0.050
0.058
0.066
0.074
0.082
0.091
0.099
3.5
0.037
0.039
0.046
0.048
0.056
0.063
0.070
0.077
0.084
0.092
4.0
0.037
0.039
0.045
0.047
0.055
0.061
0.067
0.074
0.080
0.086
4.5
0.036
0.038
0.044
0.046
0.053
0.059
0.065
0.071
0.077
0.082
5.0
0.036
0.038
0.043
0.046
0.052
0.058
0.063
0.069
0.074
0.079
5.5
0.036
0.038
0.043
0.045
0.051
0.057
0.062
0.067
0.072
0.077
6.0
0.036
0.037
0.043
0.045
0.051
0.056
0.061
0.065
0.070
0.074
Cobble
Riprap
where:
A = cross sectional area of channel at flow depth,
T
7-32
In most cases the main channel should not be subdivided, and an average n should be selected
(Cruff, 1999). Cross sections with distinct changes in shape, however, should be subdivided into
subsections and the n-values determined separately for each subsection. In this manner the
Mannings equation will solve a series of near rectangular or trapezoidal channels, which can
produce much more accurate results (Davidian, 1984). Cross sections should be subdivided if
the flow-depth in the main-channel is greater than or equal to twice the flow depth at the stream
edge of the overflow area (Thomsen and Hjalmarson, 1991; Figure 7.27). Subdivision also
should be considered where the width of the overflow area is at least five times the flow depth in
the overflow area (Figure 7.27).
FIGURE 7.27
SUBDIVISION CRITERIA COMMONLY USED FOR STREAMS IN MARICOPA COUNTY, ARIZONA
L
db
Dmax
L = width of floodplain
db = depth of flow on floodplain
Dmax = maximum depth of flow
in cross section
Davidian (1984) presents several examples illustrating the effects of improper subdivision. Figure
7.28 illustrates a cross section of a trapezoidal shaped channel having dense shrubs and trees
on the banks; the section was subdivided near the bottom of each bank because of the abrupt
change in roughness. A large percentage of the wetted perimeters ( P ) of the triangular subareas
( A 1 and A 3 ) and possibly of the main channel ( A 2 ) are eliminated. A smaller wetted perimeter
abnormally increases the hydraulic radius ( R = A P ), and this in turn results in a computed
conveyance different from the conveyance determined for a section with a complete wetted
perimeter. Conveyance ( K 1 ) computed for the cross section in Figure 7.28 would require a composite value of 0.034. This is smaller than the n-values 0.035 and 0.100 that describe the roughness for the various parts of a basic trapezoidal shaped channel. The trapezoidal-shaped cross
section in Figure 7.28, therefore, should be left unsubdivided.
7-33
FIGURE 7.28
EFFECTS OF SUBDIVISION ON A TRAPEZOIDAL SECTION
Subarea 1
Subarea 2
Subarea 3
10 feet
n = 0.100
50 feet
n = 0.035
10 feet
n = 0.100
10 feet
Subdivided solution:
A 1 =A 3 = 50
A 2 = 500
P 1 =P 3 =14.14
P 2 =50
R 1 =R 3 =3.54
R 2 =10
K 1 =K 3 =1,730
K 2 =98,500
Composite solution:
A total =A 1 +A 2 +A 3 =600
P total =P 1 +P 2 +P 3 =78.3
R total =R 1 +R 2 +R 3 =7.66
K total =K 1 +K 2 +K 3 =102,000
n total =(1.486A total R total 2/3)/K total = 0.034
At the other extreme, the panhandle of the cross section in Figure 7.29, which has a main channel and an overbank area, should be subdivided into two parts at the abrupt change in geometry.
The value of n is 0.040 throughout the section. If the section is not subdivided, the increase in
wetted perimeter of the overbank area is relatively large with respect to the increase in area. The
hydraulic radius is abnormally reduced, and an erroneous, lower n-value of 0.028 is needed to
obtain the conveyance equivalent to that of the combined conveyances ( K 1 and K 2 , Figure
7.29). Irregular cross sections with major breaks in channel geometry (Figure 7.27), therefore,
should be subdivided to create individual basic shapes.
FIGURE 7.29
EFFECTS OF NOT SUBDIVIDING A PANHANDLE SECTION
Subarea 1
Subarea 2
1 foot
10 feet
n = 0.040
n = 0.040
1 foot
Subdivided solution:
A 1 = 100
A 2 = 670.5
P 1 = 101
P 2 =79.7
R 1 = 0.990
R 2 =8.41
K 1 = 3,700
K 2 =103,000
50 feet
10
feet
71 feet
Composite solution:
A total = A 1 + A 2 = 770.5
P total = P 1 + P 2 = 108.7
R total = R 1 + R 2 = 4.26
K total = K 1 + K 2 = 107,000
n total =(1.486A total R total 2/3)/K total = 0.028
7-34
Kv
(7.7)
7-35
V flex
C depth
= flow-depth coefficient.
The vegetation flexibility factor, V flex , is considered the most significant factor in determining
whether vegetation will bend or remain in a generally upright position when subjected to the
power of flow. The unique physical properties of many types of vegetation enable them to bend to
extreme angles when force is applied. The degree of bending generally varies for a given applied
force. The force required to bend and lay over vegetation was quantified to obtain the flexural
strength of different vegetation types (Phillips, et al, 1998).
Dynamometers, which are mechanical instruments that measure the magnitude of tension in
cables, were used to determine the force required to lay over four types of vegetation of varying
size. The vegetation (saltcedar, willow, mesquite, and palo verde) ranged in height from 3 to 18
feet. Bending moments were determined by computing the product of the moment arm (distance
from the base or pivot point to the location where the force was applied) and the force required to
bend the vegetation to 45 degrees from vertical. Equations were developed from regression techniques of the bending moment with height for each of the four vegetation types (Table 7.8).
TABLE 7.8
REGRESSION EQUATIONS RELATING BENDING MOMENT TO VEGETATION HEIGHT
(For mesquite, palo verde, saltcedar, and willow. [BM, bending moment, in foot-pounds; H, height
of vegetation, in feet])
Coefficient of
Equation
Determination, r2
Mesquite
BM = 100.124H + 0.935
0.88
Palo verde
BM = 100.171H + 0.848
0.86
Saltceder
BM = 100.102H + 0.880
0.87
Willow
BM = 100.122H + 0.581
0.98
Vegetation Type
The bending moment (also referred to as flexural strength or stiffness) of the vegetation at varying heights can be estimated from the equations in Table 7.8. For example, a flexural strength of
63.2 ft-lb is estimated for a 10-foot-tall willow, whereas a flexural strength of 361 ft-lb is estimated
for a 10-foot-tall palo verde. It is assumed that a lone palo verde in midchannel is substantially
more likely to resist bending than a lone willow in midchannel when they are subjected to a similar magnitude of stream power and degree of submergence. Data acquired and analyzed during
method development seem to support this conclusion (Phillips, et al, 1998). For example, Figure
7.30A shows a lone willow about 15 feet tall that was laid over during a flow calculated at 6,590 ft/
s; Figure 7.30B shows a lone 16-foot-tall palo verde that remained erect throughout a flow of
7-36
9,760 ft/s. Depth of flow was about equal. The magnitude of the stream power that affected the
palo verde was 20.2 (ft-lb/s)/ft (Table 7.8). The magnitude of stream power to which the willow
was subjected was equal to 12.9 (ft-lb/s)/ft (Table 7.8). These data indicate that the large flexural
strength of palo verde enabled it to resist a computed stream power that was substantially larger
than the computed stream power that altered or laid over the willow with similar dimensions.
FIGURE 7.30
IMPACT OF SIMILAR FLOWS, OR STREAM POWER, ON DIFFERENT VEGETATION SPECIES
(of Similar Heights)
A. Willow
B. Palo Verde
A separate analysis of the flexural strength of arrowweed and other types of shrubs was not
done. The flexural strength of shrubs studied during the investigation (Phillips, et al, 1998) was
assumed to be similar to that of willow. Other prevalent types of vegetation common in central
Arizona, such as cottonwood and ironwood, were assumed to behave in a similar manner as willow and mesquite, respectively.
During the course of the study, the percent of the flow area blocked by vegetation was assumed
to account for the combined resistant force associated with the vegetation (Phillips, et al, 1998).
The vegetation-blocking coefficient value, C blocking , was determined for each site by assigning a
7-37
weighted value to the estimated percentage of the cross section area of flow blocked by vegetation (Table 7.9).
The spatial distribution of riparian vegetation in natural and constructed channels can substantially influence the effect of flow on the vegetation (Phillips, et al, 1998). Vegetation aligned parallel to the direction of flow generally results from consistent base flow in a channel. Due to the
combined resistant effect of the vegetation during high flow conditions, vegetation aligned parallel to flow can result in the redistribution of velocities across a channel section (Figure 7.31). The
combined resistance causes a decrease in the velocities at the immediate location of the vegetation and may lessen the effect of flow on vegetation conditions. When vegetation is randomly distributed throughout a channel, velocity distribution is assumed to be fairly constant across a
channel section. Vegetation-distribution coefficients ( C dist ) were, therefore, determined for vegetation aligned parallel to flow and for vegetation situated in a generally random manner throughout the main channel (Table 7.10).
TABLE 7.9
VEGETATION-BLOCKING COEFFICIENTS
for Selected Areas of Flow Blocked by Vegetation
[<, less than; >, greater than]
Area of Flow Blocked by
Vegetation (percent)
Vegetation-Blocking Coefficient
< 30
30 to 70
> 70
TABLE 7.10
VEGETATION-DISTRIBUTION COEFFICIENTS FOR VEGETATION ORIENTATION TO FLOW
7-38
Orientation to Flow
Vegetation-Distribution
Coefficient
Parallel
Random
FIGURE 7.31
VEGETATION ALIGNED PARALLEL TO FLOW
as a Result of Consistent Base Flow in a Low-Flow Channel
Flows in vegetated channels do not always result in total submergence of the vegetation.
Because strength of vegetation generally increases as the ratio of the moment arm and vegetation height decreases, the depth of flow in relation to vegetation height requires consideration
(Figure 7.32).
Flow-depth coefficients ( C depth ) were determined for five categories that relate hydraulic radius
to average vegetation height (Table 7.11). Computed hydraulic radius is assumed to approximate
depth of flow at the immediate location of the vegetation.
Vegetation-susceptibility indices were derived from vegetation conditions at selected sites in central Arizona. Stream power was computed for flow events that occurred at these sites. Impact of
flow on vegetation conditions was documented shortly following flow. Vegetation-susceptibility
indices were compared to stream power, which indicates a trend (Phillips, et al, 1998; Figure
7.33).
7-39
FIGURE 7.32
VEGETATION THAT WAS AFFECTED LITTLE BY FLOW
NOTE: Elevation of flow is indicated by level of survey rod;
the flow elevation was less than half the height of
the vegetation, which reduced the ability of flow to
lay over the vegetation
The trend indicates a relation exists between the vegetation-susceptibility index value and the
magnitude of stream power (Figure 7.33). According to the relation, as computed vegetation-susceptibility indices increase, the stream power required to significantly impact and lay over the
vegetation also increases. The trend line was defined as the vegetation-susceptibility threshold.
In general, for stream power values that plot above this threshold, the vegetation can be
expected to layover. For method use, the vegetation conditions and flow characteristics studied
should be similar to the values used to develop the relationship (Phillips, et al, 1998; Figure
7.33).
TABLE 7.11
FLOW-DEPTH COEFFICIENTS
for Ratios of Hydraulic Radius to Average Vegetation Height
[<, less than; >, greater than]
7-40
Flow-depth Coefficient
< 0.4
60
0.4-0.6
20
0.7-0.9
1.0-1.5
> 1.5
FIGURE 7.33
RELATIONSHIP BETWEEN STREAM POWER AND A VEGETATION-SUSCEPTIBILITY INDEX
for Estimating the Effect of Flow on Vegetation Conditions
100
Laidover
10
ti
Vegeta
scep
on-su
tibilit
sh
y thre
old
Erect
10
100
1,000
10,000
100,000
1,000,000
7-41
order to estimate the possible range in n-values (Aldridge and Garrett, 1973; Thomsen and Hjalmarson, 1991; Phillips and Ingersoll, 1998).
FIGURE 7.34
FLOW CHART FOR ASSIGNING n-VALUES
(modified from Aldridge and Garrett, 1973).
1. Determine channel type, and estimate conditions at time of flow event; compare the channel to other
channels (both before and after flows) by using photographs and descriptions. If main-channel vegetation is
present, utilize the stream power relationship to determine impact of peak flow on vegetation conditions (see Figure 7.35).
2. Determine extent of reach to which the roughness factor will apply.
3. Determine how a base value(s) of n will be assigned.
11. Adjust for factors not considered in steps 7 and 8 of individual segment options,
including channel alignment, change in channel shape, vegetation, obstructions,
and meander. Round off as desired for use in Mannings equation.
12. Compare the value determined with that of other channels and to assess validity
of the selected value.
13. For sand channels: check flow regime by computing stream power using velocity
(by using Mannings equation with the above selected n), hydraulic radius, and
water surface slope. Determine flow regime from Figure 7.2. The n-value is valid
only for upper regime flow.
7-42
FIGURE 7.35
FLOW CHART FOR ESTIMATING FLOW-INDUCED CHANGES TO VEGETATION CONDITIONS
1b. Run standard-step computations using the surveyed channel parameters and
selected roughness coefficients. From the computations, obtain average velocity,
hydraulic radius, and water surface slope for the selected cross section.
1c. By using the type and average height of vegetation in the selected cross section,
estimate the vegetation-flexibility factor, Vflex for each vegetation type using
equations found in Table 7.8.
1d. Determine the orientation of the vegetation (either oriented randomly or parallel to
the flow), the percent cross section area of flow blocked by vegetation, and the
ratio of hydraulic radius to average vegetation height for the selected discharge.
From this information, determine the values for the vegetation-blocking coefficient,
Cblocking, the vegetation-distribution coefficient Cdist, and the flow-depth coefficient,
Cdepth (see Tables 7.9, 7.10 and 7.11).
1g. Plot the values for the vegetation-susceptibility index and stream power for each
type of vegetation present in the channel. If the values plot below the vegetationsusceptibility threshold, the vegetation probably will not be significantly altered by
flow, and estimated values of n should be weighted accordingly. If the values plot
above the vegetation-susceptibility threshold, the vegetation will be altered and
possibly laid over. Use engineering judgment to estimate Mannings n-values for
the laid over vegetation.
In addition to visualizing conditions at peak flow, especially vegetation conditions, utilize the
stream power and vegetation-susceptibility index relation described in the previous section to
assist in determining flow impact on vegetation (Figure 7.35). Example case 2 at the end of this
section illustrates the use of this method for estimating peak-flow vegetation conditions (Figure
7.38, Figure 7.39, Table 7.14 and Table 7.15).
Step 2. Determine the extent of the reach to which the roughness factor will apply. Although n
may be applied to an individual cross section that is typical of a reach, it must account for the
roughness in the reach of channel that encompasses the section (Thomsen and Hjalmarson,
1991). When two or more cross sections are being considered, the reach that encompasses any
one section is considered to extend halfway to the next. For example, see Figure 7.37. In exam-
7-43
ple 1, the n-value for section 2 represents the roughness in reach B. If the roughness is not uniform throughout the reach being considered, n should be assigned for the average condition
(Aldridge and Garrett, 1973).
Step 3. If the roughness is not uniform across the width of the channel, determine whether a
base n should be assigned to the entire cross section, or whether a composite n should be developed by weighting values for individual segments of the channel having different amounts of
roughness (Aldridge and Garrett, 1973; Jarrett, 1985; Thomsen and Hjalmarson, 1991). When
the base value of n is assigned to the entire cross section, the channel constitutes one segment
being considered, and steps 5, 8, 9, and 10 do not apply in such a case.
Step 4. Determine the factors or individual components that contribute to roughness and how
each is to be taken into account. Particular factors may be dominant in a particular segment of
the channel, or they may impact the flow for the entire cross section equally. The manner in
which each factor is determined depends on how it combines with the other factors (Aldridge and
Garrett, 1973). For example, a gently sloping bank may constitute a separate segment of the
cross section; whereas, a vertical bank may add roughness either to the adjacent segment or the
entire channel. Isolated boulders generally should be considered as obstructions (Aldridge and
Garrett, 1973), but if boulders are scattered across the entire reach, it may be necessary to
determine the median size of the bed material. Flow resistant vegetation growing in a distinct
segment of channel may be assigned an n-value of its own (Aldridge and Garrett, 1973; Thomsen and Hjalmarson, 1991); whereas energy loss caused by vegetation growing on or along
steep banks or scattered along the channel bottom will be accounted for by using an adjustment
factor that can be applied either to a segment of the channel or to the entire cross section
(Aldridge and Garrett, 1973; Phillips and Ingersoll, 1998). Parts of the channel that have dense
vegetation and vegetation downstream from projections of banks may be areas of dead water or
backwater areas. The backwater areas can be eliminated from the cross section, however, the
Mannings n-value for the adjacent segment should be sufficiently high to account for roughness
along the streamward side of the brush. If a composite n is derived from segments, the user
should continue to step 5. For all other instances, step 5 is omitted from the procedure.
7-44
FIGURE 7.36
PROCESS FOR COMPUTATION OF MANNINGS n, EXAMPLE 1
Stream and location: See Figure 7.37
Reach or section: Sections 1-3; example for section 2, reach B
Event or design for which n is assigned: Flood Insurance Study for the 100-year design
discharge
1. Describe channel (if needed draw sketch on back of sheet): Reach B has a low-water
sand channel bounded by bedrock on one side and a sloping bar of gravel, cobbles, and boulders on the other. Section should be divided into segments - (1) bedrock, (2) sand, (3) gravel
and cobble 1 to 6 inches in diameter, and (4) boulders 1 to 3 feet in diameter.
Does the use of the stream power relation indicate the vegetation (shrubs) will be laid
over or remain in a relatively upright position (use flow chart in Figure 7.35 and information in the previous section)? The stream-power relation is not utilized as no vegetation is
present in the channel.
2. Are present conditions representative of those during flood? Mannings n-value
assigned for present conditions as no past flood information is available for this site.
3. Is roughness uniformly distributed across the channel? No If no, on what basis
should n for individual segments be weighted? By wetter perimeter.
4. How will the roughness producing effects of the following roughness components be
accounted for?
Bank roughness: Bedrock bank will be used as a separate segment
Bedrock outcrops: Not applicable
Isolated boulders: Add adjustment for 2 large boulders at start of reach
Bank roughness: Bedrock bank will be used as a separate segment
Vegetation: Not applicable
Obstructions: Not applicable
Meander: Not applicable
5. Refer to Table 7.12 and Table 7.13 for example n-value computations.
7-45
Re
ac
be
dro
ck
FIGURE 7.37
DIAGRAM OF HYPOTHETICAL CHANNEL SHOWING REACHES AND SEGMENTS
Used in Assigning n-values for Example 1
Ste
ep
l
n
pi
slo
10 feet
Sloping
B
bedrock
bedrock
25 feet
20 feet
25 feet
20 feet
10
DEPTH, IN FEET
Re ac h B
el
Low-flow chann
Large
boulders
8
6
4
2
0
Reach C
Slop
ing
SEGMENT
Isolated
blocks
of rock
EXPLANATION
BEDROCK
SAND
BOULDERS
HIGH-FLOW WATER
SURFACE
DIRECTION OF FLOW
7-46
10
25
20
25
20
(1) Bedrock
(2) Sand
(3) Gravel
(4) Boulders
(5) Bedrock
Sum = 170
30
40
37
43
20
Wetted
perimeter
(feet)
Banks
Channel alignment (curves and bends)
Changes in shape
Obstructions
Vegetation
Meander
Other
7-0
8-7
9-8
7-9
0-7
Depth
Factor
Width
Segment
number and
material
Approximate
dimensions
(feet)
0.045
0.050
---
---
---
---
---
Adjustments
TABLE 7.13
ADJUSTMENTS, EXAMPLE 1
24
0.035
0.025
0.8mm (1/32)
6
0.045
Base n
for
segment
Median
grain size
(inches)
0.045
0.050
0.035
0.025
0.045
Adjusted
n
Included above
Bend in reach A causes some turbulence
Channel has fairly uniform shape within reach B
2 large boulders at upstream end of reach - add roughness
Not used
Not used
Multiply by: -
Area
(square
-feet)
TABLE 7.12
COMPUTATION OF WEIGHTED MANNINGS n, Example 1
Sum =
0.0389
0.0081
0.0115
0.0077
0.0062
0.0054
Adjusted n
X weight
factor
Weighted n + added
adjustments = 0.043
Use n = 0.043
+0.002
0
+0.002
0
Add: ---
---
Adjustment
Weighted n = 0.039
Sum = 1.00
0.18
0.23
0.22
0.25
0.12
Weight
factor
7-47
FIGURE 7.38
PROCESS FOR COMPUTATION OF MANNINGS n, EXAMPLE 2
Stream and location: See Figure 7.39
Reach or section: Sections 1-3; example for section 2, reach B
Event or design for which n is assigned: Flood Insurance Study for the 100-year design
discharge
5. Describe channel (if needed draw sketch on back of sheet): Reach B has a low-water
sand channel bounded by bedrock on one side and a sloping bar of cobbles on the other.
Shrubs grow randomly throughout the channel. Flow depth is almost 2 times the height of the
shrubs.
Does the use of the stream power relation indicate the vegetation (brush) will be laid
over or remain in a relatively upright position (use flow chart in Figure 7.35 and information in the previous section)? Use of stream power relation indicates all the shrubs will be
laid over as a result of the power of flow (see Table 7.14, Table 7.15 and ).
6. Are present conditions representative of those during flood? The shrubs were probably laid over during flow.
7. Is roughness uniformly distributed across the channel? Yes If no, on what basis
should n for individual segments be weighted? N/A
8. How will the roughness producing effects of the following roughness components be
accounted for?
Bank roughness: Bedrock bank will be added under adjustments
Bedrock outcrops: Not applicable
Isolated boulders: Add adjustment for 2 large boulders at start of reach
Vegetation: Shrubs are randomly distributed in the channel
Obstructions: Not applicable unless mats of shrubs catch on the boulders
Meander: Not applicable
7-48
ng
pi
slo
Ste
ep
ly
Re
ac
be
dro
ck
FIGURE 7.39
DIAGRAM OF HYPOTHETICAL CHANNEL SHOWING REACHES
Used in Assigning n-values for Example 2
Re ac h B
Slo in
el
Low-flow chann
Large
boulders
Reach C
Slo
ing
bedrock
bedrock
Isolated
blocks
of rock
EXPLANATION
BEDROCK
GRAVEL AND COBBLES
HIGH-FLOW WATER
SURFACE
DIRECTION OF FLOW
7-49
7-50
2 large boulders at upstream end of reach - add roughness
Stream power relation indicated vegetation impact on energy losses will be negligible
Not used
Obstructions
Vegetation
Meander
Other
Changes in shape
TABLE 7.15
ADJUSTMENTS, EXAMPLE 2
Sum =
Channel alignment
(curves and bends)
Depth
Right bank is fairly smooth bedrock, similar in roughness to cobbles. d50 cobbles = 6
Width
Sum =
Adjusted n X
weight factor
Multiply by: -
Used n = 0.039
Weighted n +
added adjustments = 0.039
Add: ---
+0.002
+0.002
+0.035
Adjustment
Weighted n =
Sum =
Median
grain
Area
Wetted
size
Base n for
Weight
perimeter (square
-feet) (inches) segment Adjustments Adjusted n factor
(feet)
Factor
Segment number
and material
Approximate
dimensions (feet)
TABLE 7.14
COMPUTATION OF WEIGHTED MANNINGS n, Example 2
FIGURE 7.40
COMPUTED STREAM POWER IMPACT ON THE VEGETATION-SUSCEPTIBILITY INDEX
FOR SHRUBS
STREAM POWER, IN FOOT-POUNDS
PER SECOND PER SQUARE FOOT
100
ti
Vegeta
scep
on-su
tibilit
sh
y thre
old
Erect
10
100
1,000
10,000
100,000
1,000,000
TABLE 7.16
VEGETATION CHARACTERISTICS, COEFFICIENTS, AND SUSCEPTIBILITY INDEX FOR SHRUBS
Vegetation Type
Shrubs
15.5
3070
4
Randomly
1
1.6
Hydraulic
Radius (R) (ft)
Water Surface
Slope (Sw) (ft/ft)
62.4
0.006
9.5
7-51
Step 5. Divide the channel width into segments according to general roughness (Jarrett, 1985;
Thomsen and Hjalmarson, 1991). If distinct parallel bands of bed material of different particle
sizes or of different roughness are present, use of segments can facilitate defining the contact
between the different types of material (Figure 7.37). The dividing line between any two segments should parallel the general flow lines in the stream and should be located to represent the
average contact between the differing types of material (Thomsen and Hjalmarson, 1991). The
dividing line must extend through the entire reach, as defined in step 2, even if one of the different types of bed material may not be present throughout the entire reach. If a segment contains
more than one type of roughness, it may be necessary to use an average size of bed material,
which would apply in Figure 7.37 if the sand in segment 3 extended further downstream and the
gravel and cobbles started closer to section 1. Figure 7.37 shows two distinct segments in reach
B having material in the gravel- to boulder-size range. In the field, however, material of this size
usually grades from fine-grained material at the edge of the sand channel to boulders near the
shrub or vegetation line. In both instances, segments 3 and 4 should be combined as one segment. Where sand is mixed with gravel, cobbles, and boulders throughout a channel, it may be
impractical to divide the main channel (Aldridge and Garrett, 1973).
Step 6. Determine the type of material that occupies each segment of channel, and determine
the median particle size in each segment.
If the particles can be separated by size by screening, small samples of the bed material should
be collected at 8 to 12 sites in the segment of the reach (Aldridge and Garrett, 1973). The samples are combined and the composite sample for the particular segment is passed through
screens that divide the sample into a minimum of five size ranges. The volume or weight of material in each size range is measured and converted to a percentage of the total. The size or weight
that corresponds to the 50th percentile is obtained from a distribution curve developed by plotting
particle size versus the percentage of the size smaller than that indicated (Phillips and Ingersoll,
1998).
If the material is too large to be screened, the median size of a random sample of the bed material in the segment is measured (Thomsen and Hjalmarson, 1991; Phillips and Ingersoll, 1998).
Approximately 100 cobbles or boulders are sampled. For determination of d50, particle diameter
equals that of 50 percent of the particles.
Experienced personnel generally can make a fairly accurate estimate of the median particle size
by inspection of the channel bed material if the range in particle size is small (Aldridge and Garrett, 1973).
Step 7. Determine the base value of n for each segment of channel using Table 7.2 or Table 7.3,
equations (7.3) or (7.4), the comparisons made in step 1, or a combination of these. If a composite n-value is derived from segments, the user should proceed to step 8. If n is assigned for the
channel as a whole, the user should go to step 11.
Step 8. Add adjustment factors from Table 7.4 that contribute to energy loss; these factors apply
7-52
7.7
Vegetation has the ability to grow to significant heights and densities in a matter of a few years,
and stream power may not be sufficient to alter vegetation in some stream channels. Homes and
businesses have been built directly adjacent to some of these vegetated channels. If substantial
amounts of mature vegetation are not included in n-value estimates in the initial design of the
channel, then the vegetation may result in decreased channel conveyance and flood waters
overtopping channel banks when design flows do occur.
In the past, vegetation may have been removed completely to ensure adequate conveyance of
floodflows. In recent years, however, emphasis has shifted toward preservation of riparian vegetation that can provide habitat for wildlife, as well as aesthetically pleasing, multiuse areas for
homeowners and businesses.
7-53
7.7.1 Freeboard
Freeboard can be defined as an additional amount of conveyance area measured by using
height above a flood level. The purpose of freeboard is to mitigate risk by providing a factor of
safety. The flood level considered is normally the design water surface elevation computed for
the design discharge, or the Base Flood Elevation (BFE) used for Flood Insurance Studies (FIS).
The design water surface elevation is used to describe both situations. For the purposes of
example cases 2, 3, and 4 at the end of this section, the minimum amount of freeboard required
above the design water surface elevation is 1 foot. An alternate vegetation-maintenance process
is illustrated in example case 1, in which freeboard is not considered. Channel banks are not levied in any of the example cases.
The importance of maintaining the minimum factor of safety is significant; therefore, vegetation
management and maintenance plans should adhere to maintaining the minimum required freeboard. Vegetation can grow quickly, which can cause channel conveyance to decrease and freeboard, or the factor of safety, to diminish or be consumed completely. This is the primary purpose
for making periodic inspections of vegetation conditions.
Ideally, for stream channels with newly computed BFEs and void of all vegetation, Mannings nvalues are adjusted according to the amount of vegetation anticipated for future conditions
(TABLE 7.4). For example, a newly constructed channel that has a firm earth base and concrete
banks requires assessment of current roughness factors, including those for future vegetation
conditions. If a Mannings n-value of 0.030 is selected for a channel void of vegetation, and it
would be desirable to allow mesquite to grow to a density of approximately 1 tree per 100 feet of
channel; the adjusted vegetation component may be in the range of 0.025 to 0.050. The vegetation conditions and corresponding n-value should not increase above the design value, or freeboard, may be partially or completely lost.
For channels that were originally designed under no-vegetation conditions and for which futurevegetation conditions were not taken into account, only flexible grasses and other types of vege-
7-54
tation determined to layover during design flows should be allowed to grow within the channel.
Any vegetation that may decrease velocity, and consequently increase design flow area, should
be considered for removal from the channel.
Example Case 1
The use of, and the rationale for, the new guidelines can be illustrated by examining alternative
vegetation-maintenance activities in a constructed channel (Figure 7.41 A and B). The constructed flood-control channel originally was designed for no or very sparse vegetation conditions. Subsequently, however, growths of mesquite, palo verde, and shrubs such as desert
broom have grown to large spatial densities and to heights that surpass the flood-channel banks
(Figure 7.41 A). Owing to a growing concern that channel conveyance has been reduced and
flood banks could be overtopped by the design discharge, local representatives determined that
vegetation in the wash needed to be maintained or thinned (Figure 7.41 B). By using thinning criteria that was primarily based on tree height and trunk diameter, shrubs and smaller palo verde
and mesquite were removed and lower branches on the remaining palo verde and mesquite
trees were trimmed to allow for greater channel conveyance. USGS staff, by using information
acquired before and after maintenance, determined the roughness coefficients for five surveyed
cross sections of the channel (Table 7.18). Mannings n-values were selected for initial, pre- and
post-vegetation conditions on the basis of information contained in Table 7.4. The U.S. Army
Corps of Engineers Hydrologic Engineering Centers River Analysis System (HEC-RAS) was
used to simulate water surface elevations for the channel under the various vegetation conditions. The step-backwater computer simulations were run by using the design discharge, the
channel geometry from the surveyed sections, and the selected roughness coefficients ( A, B,
and C). When the channel was originally designed, it appears there would have been adequate
freeboard ( A). Simulation results using HEC-RAS, however, indicate that the design discharge
for the channel for full-grown vegetation conditions would overtop channel banks and flood adjacent areas ( B). Velocities would be slowed significantly compared to initial channel conditions
and cross section area would compensate with a rise in water-surface elevations by an average
of 3.92 feet (Table 7.18). Simulations conducted for post-vegetation maintenance conditions indi-
7-55
cate that the design discharge would remain within most of the channel. Because of the thinning
criteria, many large trees were left within the reach from sections 3 to 5. The remaining cluster or
clump of trees resulted in selection of larger roughness coefficients for this area of the study
reach. Consequently, the design discharge overtopped the right channel bank at sections 4 and 5
( C). Additionally, the simulated water surface removed all conveyance that should have been
available for freeboard. Use of the guidelines in this report would have resulted in more vegetation being removed, lower roughness coefficients, and larger conveyance, allowing design flow to
remain below required freeboard levels.
FIGURE 7.41
CONSTRUCTED CHANNEL THAT REQUIRED VEGETATION MODIFICATION
(A, Before maintenance of vegetation, July 28, 2005. B, after maintenance of vegetation,
August 3, 2005.)
A. Before maintenance
B. After maintenance
7-56
TABLE 7.18
HYDRAULIC PROPERTIES OF FLOW FOR THE CONSTRUCTED CHANNEL IN EXAMPLE CASE 1
(Velocity, area, and water surface elevations were computed by using estimated Mannings n-values and a design discharge. [See for sections and simulated water surface elevations. ft, feet; ft/
s, feet per second; ft2, square feet])
Mannings
Value
Velocity
(ft/s)
Area (ft)
0.028
11.86
320
13.00
0.028
9.56
325
14.20
0.028
10.80
367
14.29
0.028
12.17
325
14.62
0.028
12.37
320
15.88
0.080
7.12
557
16.00
0.080
6.41
617
16.90
0.100
6.35
623
17.80
0.150
5.81
681
19.46
0.150
5.53
716
21.41
0.035
9.76
406
14.00
0.035
8.81
450
14.67
0.040
9.30
426
15.04
0.050
9.21
430
15.87
0.060
9.61
412
17.07
7-57
FIGURE 7.42
SIMULATED WATER SURFACE ELEVATIONS FOR CONSTRUCTED CHANNEL
in Example Case 1: A, Initial channel conditions. B, Fully-grown vegetation conditions. C, Postvegetation maintenance conditions
A. Simulated water-surface elevations for initial channel conditions.
Right b
ank
Water su
rf
ace
Left b
Right
Section 5
ank
bank
Section 4
Section 3
Section 2
Section 1
Water
su
rface
Left bank
Right bank
Section 5
Section 4
Section 3
Section 2
NOTE: As indicated, computed water-surface elevations
would have overtopped channel banks at all cross
sections under fully-grown vegetation conditions.
Section 1
Wate
rs
urface
Left b
Right ba
ank
nk
Section 5
Section 4
Section 3
NOTE: Under post-maintenance conditions,
computed water-surface elevations for
the design discharge still overtopped the
right bank at sections 4 and 5. Several
ditches were excavated during the
maintenance procedure to aid in
conveying water during flows
7-58
Section 2
Section 1
Example Case 2
For example case 2, consider a constructed trapezoidal-shaped channel that originally was void
of any vegetation. The initial Mannings n-value selected was 0.030 and an additional 0.015 was
estimated for future conditions when vegetation is anticipated to grow in the bed of the channel.
An n-value of 0.045 was used for the final design computations, allowing 1 foot of additional conveyance or freeboard. A vegetation maintenance plan was established on completion of the
channel. Over the next 10 years, however, the vegetation assessment and maintenance plan
was neglected and forgotten. After 10 years, mesquite rooted in the channel substrate and grew
to a height that averaged 16 feet, surpassing the height of the channel banks. Furthermore,
shrubs took root that averaged about 5 feet in height. The average amount of mesquite that
blocks flow is approximately 60 percent, and the approximate amount of shrubs that blocks flow
is 20 percent. According to information in Table 7.4, Mannings n for the design flow increased
from the initial composite value of 0.045 to a range of 0.100 to 0.200 (average 0.150). According
to standard-step simulations, the channel no longer has adequate conveyance to carry the
design flow, thus freeboard will be lost and banks will be overtopped when a design flow occurs
(Figure 7.43 A and B).
It would seem that significant thinning of the vegetation is now warranted. Before any maintenance activities are engaged, however, the stream power relation should be utilized to determine
if the design flow has the power to lay over the shrubs and possibly the mesquite.
Values acquired in the field needed to compute the vegetation-susceptibility index for the shrubs
and mesquite are given in Table 7.19. Hydraulic values acquired from the HEC-RAS simulations
for peak design flow were used for the stream-power computations (Table 7.20). The resultant
values for each vegetation type are then plotted with corresponding stream power (Figure 7.44).
As indicated, although shrubs plot close to the threshold, both shrub and mesquite need to be
considered for thinning to decrease the Mannings n-value for the vegetation component back to
its original value of 0.015 (or a composite n-value of 0.045).
For this example case, the Mannings n-value for the vegetation component should be no more
than 0.015, which allows for a select amount of shrubs and trees to remain in the channel (Table
7.4). There are many vegetation maintenance schemes or scenarios that could be developed to
meet the criteria for freeboard. For example case 2, however, only two vegetation-maintenance
scenarios are presented. For scenario 1, native vegetation was left randomly distributed to diminish the potential additive effect of the sphere of influence for turbulence on flow caused by the
vegetation (Figure 7.45; Table 7.4). Scenario 1 may be more aesthetically pleasing to local residents (Figure 7.46). For scenario 2, native mesquite trees and some shrubs would be clumped
where possible (Figure 7.47). Clumping the vegetation may present a better habitat environment
for wildlife (Figure 7.52). The additive strength of clumped vegetation will make it much more
resistant to flow and, therefore, could be a good method for protecting vegetation from the power
of flow. The trees for scenario 2 should be arranged or maintained so that there is one clump per
three cross section lengths of channel to ensure spheres of influence do not overlap (Figure
7-59
7.47). These procedures should allow the vegetation component of Mannings n to be approximately 0.015 for this constructed channel (Table 7.4).
A new maintenance plan should be enacted that includes periodic inspection or assessment of
vegetation conditions. Maintenance of vegetation should be conducted if deemed necessary.
FIGURE 7.43
HEC-RAS COMPUTER SIMULATIONS FOR CONSTRUCTED CHANNEL IN EXAMPLE CASE 2
(A, Original design computed water surface elevation for n = 0.045 (base n-value = 0.030 and
future vegetation n-value component of 0.015). B, Water surface elevation for a fully vegetated
channel at an average n = 0.150.)
A. Original design computed water-surface elevation
Water surface
Se
cti
on
Se
Se
cti
cti
Se
on
on
Se
Se
cti
on
cti
on
cti
on
Sec
7-60
tion
Sec
1
Sec
tion
Sec
tion
tion
Sec
4
Sec
tion
tion
TABLE 7.19
VEGETATION COEFFICIENTS AND SUSCEPTIBILITY INDEX FOR SHRUBS AND MESQUITE
Example Case 2, [ ft-lb , foot-pound]
Vegetation Type
Shrubs
Mesquite
16
15.5
830
< 30
3070
Randomly
Randomly
1.2
0.4
20
TABLE 7.20
HYDRAULIC PARAMETERS USED TO COMPUTE STREAM POWER
2
Example Case 2,[ ( ft-lb s ) ft , foot-pounds per second per square foot]
Specific Weight of
Water (lb/ft3)
Hydraulic Radius
(R) (ft)
Water Surface
Slope (Sw) (ft/ft)
62.4
0.003
7-61
FIGURE 7.44
IMPACT OF COMPUTED STREAM POWER FOR SHRUBS AND MESQUITE
Example Case 2
STREAM POWER, IN FOOT-POUNDS
PER SECOND PER SQUARE FOOT
100
Laidover
usce
tion-s
Vegeta
10
ptibil
esh
ity thr
old
Erect
Shrubs
10
Mesquite
100
1,000
10,000
100,000
1,000,000
FIGURE 7.45
PLAN VIEW ILLUSTRATION OF CONSTRUCTED CHANNEL FOR EXAMPLE CASE 2, SCENARIO 1
A. Originally designed channel
Left
bank
7-62
Main
channel
Right
bank
FIGURE 7.46
A CONSTRUCTED CHANNEL FOR EXAMPLE CASE 2, SCENARIO 1
(A, Mannings composite roughness coefficient is estimated to be 0.150 prior to vegetation maintenance. B, Energy loss components subsequent to vegetation maintenance. C, Vegetation conditions approximately six months following maintenance.)
A. Before maintenance
B. After maintenance
7-63
FIGURE 7.47
PLAN VIEW ILLUSTRATION OF CONSTRUCTED CHANNEL FOR EXAMPLE CASE 2, SCENARIO 2
(Following vegetation maintenance, trees are clumped together primarily to provide better habitat
for wildlife.)
7-64
FIGURE 7.48
A CONSTRUCTED CHANNEL FOR EXAMPLE CASE 2, SCENARIO 2
(A, Mannings composite roughness coefficient is estimated to be 0.150 prior to vegetation maintenance. B, Mannings composite roughness coefficient is estimated to be 0.045 subsequent to
vegetation maintenance.)
A. Before maintenance
B. After maintenance
Example Case 3
The vegetation-maintenance plan considered in example case 3 is for a gravel- and cobble-bed,
straight uniform channel that recently had experienced a high-flow event. Following the event, a
few palo verde trees in the channel remained in an upright position, and had fairly significant
amounts of debris on the upstream side. Shrubs were evident in the reach prior to the flow (Figure 7.49), but laidover and/or removed during the event (Figure 7.50). The area adjacent to this
channel (right and left banks) was designated for a new housing and business development. A
FIS was conducted prior to development. A base Mannings n-value of 0.033 was selected for the
cobble substrate (Figure 7.50). The vegetation component of Mannings n selected for the few
standing palo verde trees was selected to be 0.020 (Figure 7.51). No vegetation-component
addition was made to account for future growth of shrubs or other vegetation, and no other components of n were believed to contribute to energy losses within the channel. Total composite n,
7-65
therefore, for the hydraulic computations was 0.053. The FIS indicated that the previous flow
event approximated a statistical 25-year flow. A 100-year design flow was determined, and the
BFE was computed with 1 foot of freeboard (Figure 7.52). Within 1 year of completion of the FIS,
homes and business were constructed adjacent to the channel.
After a 5-year period, no additional trees grew in the channel; however, shrubs grew throughout
the channel to a density greater than about 70 percent and heights averaging 5 feet (Figure
7.53). Because the originally selected n-value of 0.053 did not account for future growth of vegetation in the channel, and homes and business were constructed immediately adjacent the channel, there was concern the channel may no longer be capable of conveying the design discharge
(Figure 7.54). Vegetation maintenance was considered; however, first the stream-power relation
was used to determine if the shrubs would be fully laidover on the rising limb of the 100-year
design flood hydrograph.
From standard-step computations made after the 5-year period, and a Mannings n-value for
present conditions (selected to be 0.083), values were acquired for computation of stream power.
For shrubs and palo verde averaging 5 and 16 feet in height, respectively, the vegetation flexibility factor is 15.5 and 3,848 ft-lbs, respectively. The percent of flow blocked by the shrubs is estimated to be greater than 70 percent, while the palo verde is estimated at less than 30 percent.
The vegetation blocking coefficients, therefore, are 9.0 for shrubs and 1.0 for palo verde. The
palo verde and shrubs are randomly distributed in the main channel. The vegetation distribution
coefficient, therefore, is 1.0 for palo verde and shrubs. From the standard-step computations,
hydraulic radius is equal to 3.6 feet. The flow-depth ratio, therefore, is 0.7 and 0.2 for shrubs and
palo verde, respectively. Hence, the flow-depth coefficient is 5.0 and 60, respectively. The vegetation-susceptibility index is 698 for the shrubs, and 231,000 ft-lbs for the palo verde (Table 7.21
and Table 7.22).
Subsequently, stream power was computed and plotted with the vegetation-susceptibility indices
for the shrub and palo verde (Figure 7.55). According to their plotting positions, the shrubs would
be laidover on the rising limb of the 100-year flow hydrograph. Thus, the roughness component
that represents the shrub can be considered negligible and not be added to the composite nvalue. The palo verde, however, probably would remain in an upright position. The impact of the
palo verde on total roughness was included in the original FIS when the BFE was determined. It
was determined that it should not be maintained. For this example case, the guidelines indicate
that shrubs also should not be maintained, and a vegetation assessment and maintenance plan
should be enacted to periodically document any noticeable future changes in vegetation conditions.
7-66
FIGURE 7.49
EXAMPLE OF A CHANNEL WITH RANDOMLY DISTRIBUTED SHRUBS
Prior to the Statistical 25-year Event
FIGURE 7.50
EXAMPLE OF A CHANNEL WITH REMOVED SHRUBS
Following the Statistical 25-year Event
7-67
FIGURE 7.51
LOCATIONS AND DENSITY OF PALO VERDE TREES IN THE CHANNEL
for Example Case 3 Following the 25-year Flow Event
FIGURE 7.52
BASE FLOW ELEVATION (BFE) WITH 1 FOOT OF FREEBOARD
for the Channel Used in Example Case 3 for a 100-year Design Flood
7-68
1 foot freeboard
FIGURE 7.53
EXAMPLE OF A CHANNEL WITH A VEGETATION DENSITY GREATER THAN 70 PERCENT
Five Years After a Flood Insurance Study
FIGURE 7.54
EXAMPLE CHANNEL WITH DEVELOPMENT AND FIVE YEARS VEGETATION GROWTH
(A, Distribution of shrubs and trees in main channel and approximate location of homes.
B, Shrubs (smaller circles) and palo verde (larger circles) and homes along channel.)
A. Cross-section view
B. Plan view
7-69
TABLE 7.21
VEGETATION COEFFICIENTS AND SUSCEPTIBILITY INDEX FOR SHRUBS AND PALO VERDE
Example Case 3, [ ft-lb , foot-pound]
Vegetation Type
Shrubs
Palo Verde
16
15.5
3,848
> 70
< 30
Randomly
Randomly
0.7
0.2
Hydraulic Radius
(R) (ft)
Water Surface
Slope (Sw) (ft/ft)
62.4
3.6
0.009
10
FIGURE 7.55
IMPACT OF COMPUTED STREAM POWER FOR SHRUBS AND PALO VERDE
100
Laidover
shold
Shrubs
y thre
ptibilit
e
c
s
u
tion-s
Vegeta
10
Erect
10
100
1,000
10,000
Palo Verde
100,000
7-70
Example Case 4
The vegetation-maintenance plan considered in case 4 is for a planned residential community
that is built adjacent to a gravel- and grass-lined channel. A low-flow channel was constructed,
which winds through the bottom of the main channel in this multiuse area. Small mesquite trees
were planted along the side of the low-flow channel to a density of about 2 to 3 trees per cross
section length of reach (Figure 7.56 A and B). Current and future conditions for the planted mesquite trees were considered in the selection of the vegetation component of Mannings n for the
FIS. A base n-value of 0.027 was selected for the gravel- and grass-lined channel; the vegetation
component selected for the mesquite for present conditions was 0.015. An estimated 0.025 was
added to the component for the mesquite to account for future growth (Table 7.4). The total composite n-value for the design discharge for the FIS, therefore, was 0.067. A freeboard of 1 foot
was added to the BFE, and the homes were subsequently constructed. The original engineers
and developers initiated a vegetation assessment and maintenance plan to ensure that roughness coefficients would not exceed the design n-value of 0.067. The assessment plan, however,
was neglected, and after 5 years many additional mesquite trees had taken root.
After 10 years the mesquite trees were mature, and the area maintained a density of approximately 6 to 7 mesquite trees per cross section length of reach (Figure 7.56 C). The mesquite
trees averaged 16 feet in height. Homeowners generally were pleased with the aesthetic value of
the dense and mature mesquite in the multiuse area, however, others, including the local floodplain manager, were concerned that the design discharge would result in the loss of available
freeboard and overtop channel banks. The new estimated composite roughness coefficient was
in the range of 0.100 to 0.200 (Table 7.4).
The stream-power relation was used to determine impact of the design discharge on the mesquite. For mesquite trees averaging 16 feet in height, the vegetation flexibility factor is 830 ft-lbs.
The amount of flow blocked by these trees is about 60 percent. Standard-step HEC-RAS computations were run for the channel with an n-value that averaged 0.150. Velocity and hydraulic
radius were acquired from these computations to determine the remaining vegetation-susceptibility index components (Table 7.23). Values used for computation of stream power also were
acquired from the standard-step computations (Table 7.24). Stream power and the vegetationsusceptibility index were plotted for mesquite to determine if flow would have any impact on the
vegetation (Figure 7.57).
The mesquite trees probably would not be altered by a 100-year design flow for this multiuse
area (Figure 7.57). The design flow would, therefore, overtop the channel banks considerably
(Figure 7.56 C and D). A substantially larger flow would be required to alter the mesquite trees. In
order to maintain the original BFE and 1-foot freeboard, all mesquite trees should be removed
except those originally planted for which future growth was considered when n-values were
selected for the original FIS (Figure 7.56 E and F). The vegetation assessment and maintenance
plan should be followed closely to ensure that estimates of Mannings n do not again exceed
0.067.
7-71
FIGURE 7.56
PLAN VIEW AND CROSS SECTION VIEWS SHOWING DISTRIBUTION OF MESQUITE
(in the main channel as simulated water surface elevation, and location of homes. A, Plan view after mesquite trees were initially planted. B, cross section view of simulated water surface for the design discharge
for initial condition. C, Plan view showing mesquite trees after 10 years of growth. D, cross section view of
simulated water-surface for the design discharge for vegetation conditions after 10 years of growth. E, Plan
view showing remaining mesquite trees following vegetation maintenance. F, cross section view of simulated water surface for the design discharge for post-maintenance conditions.)
A. Plan view of initial planting
Simulated water-surface
for the design discharge
for initial conditions
ow-flo
Low-flow
channe
channel
Main
i n cchannel
ha
Simulated water-surface
for the design discharge
for vegetation conditions
after 10 years of growth
Low-flow
ow-flo
channel
channe
Main
i n cchannel
ha
Simulated water-surface
for the design discharge for
post-maintenance conditions
Low-flow
ow-flo
channel
channe
Main
i n cchannel
ha
7-72
TABLE 7.23
VEGETATION COEFFICIENTS AND SUSCEPTIBILITY INDEX FOR MESQUITE
Example Case 4, [ ft-lb , foot-pound]
Vegetation Type
Mesquite
16
830
60
Randomly
0.6
20
TABLE 7.24
HYDRAULIC PARAMETERS USED TO COMPUTE STREAM POWER
2
Hydraulic Radius
(R) (ft)
Water Surface
Slope (Sw) (ft/ft)
62.4
0.003
7-73
FIGURE 7.57
IMPACT OF COMPUTED STREAM POWER FOR MESQUITE TREES
100
Laidover
tion
Vegeta
10
eptib
-susc
resh
ility th
old
Mesquite
Erect
10
100
1,000
10,000
100,000
1,000,000
Site.
______________
2.
Date.
3a.
4.
5.
6.
7.
8.
9.
10.
After assessment with stream power relations, are current Mannings n-values
______________
_____
_____
7-74
7.8
11.
12.
13.
Hydraulic computations of open channel flow require evaluation of the channels resistance to
flow, which typically is represented by a roughness parameter. The Mannings roughness coefficient, n, commonly is used to represent flow resistance. Verified and estimated Mannings roughness coefficients for natural and constructed stream channels in Arizona have been presented in
several previously published documents. Most of the information from which is available in the
form of guidelines, tables, figures, and examples.
Proper estimation of n-values for open channels in arid to semi-arid environments can present
difficulties in estimating channel resistance. In particular, vegetation in ephemeral and intermittent streams can be a constantly changing factor making estimation of n for this energy-loss component difficult. Vegetation can grow to large proportions in just a few seasons, and floods may
dramatically alter the roughness characteristics of the channel by flattening or even removing
vegetation, which acts to decrease Mannings n. Roughness coefficients selected in hydraulic
studies years or decades earlier may change significantly. Consequently, earlier computed water
surface elevations may no longer be valid for the design discharge. Semi-empirical relations and
guidelines developed to estimate the impact of flow on channel vegetation conditions and the
resultant impact on Mannings n are presented in this document.
In the past, heavy growths of vegetation, which were believed to substantially increase Mannings n-value and decrease channel conveyance, commonly were removed completely to
enable adequate conveyance of floodflows. In recent decades, however, emphasis has shifted
toward preservation of riparian vegetation to provide habitat for many species of wildlife, as well
as aesthetically pleasing multiuse areas for homeowners and businesses. Developed and presented herein are engineering-based guidelines for optimizing the preservation of riparian habitat
and the aesthetics of multiuse areas, while mitigating damage from floodflows along stream
channels. The guidelines primarily are based on the vegetation component of Mannings n that
should be maintained in a waterway to allow adequate freeboard, which is an additional amount
of conveyance area intended to mitigate risk by providing a factor of safety.
The information, methods, and guidelines available in this report are presented to provide a tool
for engineers, hydrologists, developers, and conservationists to gain experience and make better
and informed decisions when selecting values of Mannings n based on channel and vegetation
7-75
conditions.
7.9
REFERENCES
7-76
Phillips, J.V., and Hjalmarson, H.W., 1994, Floodflow effects on riparian vegetation in Arizona:
New York, American Society of Civil Engineers Proceedings of the 1994 National Conference on Hydraulic Engineering, v. 1, p. 707711.
Phillips, J.V., and Ingersoll, T.L., 1998, Verification of roughness coefficients for selected and
natural channels in Arizona: U.S. Geological Survey Professional Paper 1584, 77 p.
Phillips, J.V., and Tadayon, S., 2006, Selection of Mannings roughness coefficient for natural
and constructed vegetated and non-vegetated channels, and vegetation maintenance plan
guidelines for vegetated channels in Central Arizona: U.S. Geological Survey Scientific
Investigations Report 2006-5108, 41 p.
Riggs, H.C., 1976, A simplified slope-area method for estimating flood discharges in natural
channels: U.S. Geological Survey Journal of Research, v. 4, no. 3, MayJune 1976, p. 285291.
Simons, Li and Associates, Inc., 1981, Design Guidelines and Criteria for Channels and
Hydraulic Structures on Sandy Soil, Urban Drainage and Flood Control District and City of
Aurora, Colorado.
Simons, D.B., and Richardson, E.V., 1966, Resistance to flow in alluvial channels: U.S. Geological Survey Professional Paper 422-J, 61 p.
Thomsen, B.W., and Hjalmarson, H.W., 1991, Estimated Mannings roughness coefficients for
stream channels and flood plains in Maricopa County, Arizona: Phoenix, Arizona, Flood
Control District of Maricopa County, 126 p.
U.S. Department of Transportation (USDOT), Federal Highway Administration, 2005, Design of
Roadside Drainage Channels with Flexible Linings, Hydraulic Engineering Circular No. 15,
Publication No. FHWA-IP-87-7.
Webb, R.H., and Betancourt, J.L., 1992, Climatic variability and flood frequency of the Santa
Cruz River, Pima County, Arizona: U.S. Geological Survey Water-Supply Paper 2379, 40 p
7-77
7-78
8 HYDRAULIC STRUCTURES
TABLE OF CONTENTS
8
HYDRAULIC STRUCTURES
8.1
SYMBOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-3
8.2
USE OF STRUCTURES IN DRAINAGE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-9
8.2.1
Channel Drop Structures............................................................................. 8-9
8.2.2
Conduit Outlet Structures ............................................................................ 8-9
8.2.3
Special Channel Structures....................................................................... 8-10
8.2.4
Access Ramps .......................................................................................... 8-11
8.2.5
Trashracks and Access Barriers ............................................................... 8-11
8.2.6
Factors of Safety ....................................................................................... 8-11
8.3
CHANNEL DROP STRUCTURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-12
8.3.1
General ..................................................................................................... 8-12
8.3.2
Hydraulic Analysis Considerations ............................................................ 8-15
8.3.3
Selection of Drop Structures ..................................................................... 8-30
8.3.4
Design Guidelines for Drop Structures...................................................... 8-35
8.4
ENERGY DISSIPATION STRUCTURES AT CULVERT OUTLETS . . . . . . . . . . . . 8-57
8.4.1
General ..................................................................................................... 8-57
8.4.2
Riprap at Culvert Outlets ........................................................................... 8-57
8.4.3
Riprap Downstream of Energy Dissipators ............................................... 8-67
8.4.4
Stilling Basins ............................................................................................ 8-67
8.4.5
Streambed Level Dissipator Basins .......................................................... 8-70
8.4.6
Modifications to USBR TYPE VI Basin...................................................... 8-75
8.4.7
Baffle Chute Energy Dissipator ................................................................. 8-77
8.4.8
Use of the HY-8 Software for Energy Dissipator Design........................... 8-79
8.5
SPILLWAYS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-80
8.6
SPECIAL CHANNEL STRUCTURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-86
8.6.1
Channel Transitions .................................................................................. 8-86
8.6.2
Supercritical Flow Structures..................................................................... 8-92
8.6.3
Access Ramps .......................................................................................... 8-94
8.6.4
Trashracks and Access Barriers ............................................................... 8-95
8.6.5
Groins and Guide Dikes ............................................................................ 8-97
8.7
SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-98
8.8
OPERATION, MAINTENANCE & AESTHETIC CONSIDERATIONS . . . . . . . . . . . 8-99
8.8.1
Operation and Maintenance ...................................................................... 8-99
8.8.2
Structure Aesthetics .................................................................................. 8-99
8.9
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-101
8.9.1
Cited in Text ............................................................................................ 8-101
8.9.2
References Relevant to Chapter ............................................................. 8-103
8-1
8-2
8.1
SYMBOLS
= Main channel contraction angle used in Hagers side weir discharge equation,
radians. Also used as the flow expansion angle downstream from culvert outlets,
the V-notch weir spillway configuration, and for Nappe Flow on a stepped spillway.
Constant pi
an
ag
Area, sq ft
A1
A2
Ac
Cross sectional area of flow at critical depth. Also used as weir width.
Bottom width, ft
bt
Weir Coefficient
C0
Tailwater parameter
Cd
Ch
Co
Orifice Coefficient
Cp
Cp-max
Cw
8-3
Depth of flow, ft
d2
d15
d50
d85
d100
dmax, dm
dmin
ds
Depth of scour, ft
Jet plunge height, ft. Also used as diameter of circular pipe or equivalent diameter
for non-circular culvert, ft, and as depth of flow over a weir.
Db
De
Dg
Grout depth, ft
Dj
Djm
Djt
Dn
Drop number
Dr
Rock depth, ft
EGLm
EGLt
Elc
Elm
Elt
Fb
Force at bend, lb
Fj
Fr
Froude number
Fr1
8-4
Fs
Height of the wingwalls above the main crest, ft. Also used as the difference
between weir measured head and flow depth over a weir (h=H-D).
hj
hL
Head loss, ft
hs
hv
Velocity head, ft
hw
Head on the weir or orifice, or the height of a rectangular culvert for subcritical
flow, ft. Also used as height of a baffle, ft.
Hb
Height of a baffle, ft
Hcw
Hd
Hdf
Hg
Hm
Hs
Differential head, ft
Ht
= Total head for Hagers side weir discharge equation measured from the top of the
weir crest, ft. Also used as measured head for a sharp-crested weir.
Hwt
Ratio of Y2 to Y1
Kt
Apron length for a riprap apron, ft. Also used as horizontal-crested weir width, ft
and side weir length, ft.
L 1, L 2
La
LA
Lbm
8-5
Lbt
LB , Lb
Ld
Drop length, ft
Ldm
Ldt
Lf
LH
Lj
Ls
Ltd
Ltu
LV
Vertical creep distance along any contact surfaces greater than 45 degrees, ft.
Also used as transition length, ft.
Lwt
Height of the weir crest above the approach channel, ft. Also used as the force
due to pressure on the bend.
qc
qm
qt
Discharge, cfs
Qw
rw
Hydraulic radius, ft
8-6
so
Tc
TW
Tailwater depth, ft
vc
Velocity, ft/sec
Va
Vallow
Vave
VB
Vc
Vg
(VL)ave
Vn
Vo
Chute width, ft
WB
Wh
Wo
W1
W2
W3
W4
Depth of flow, ft
yB
yc
8-7
ycm
yct
ye
Equivalent depth, ft
yf
yh
ym
Hydraulic depth, ft
yn
Normal depth, ft
yo
yp
At a vertical drop, the pool depth under the nappe just below the crest, ft
Y1
Y2
(Y2)m
(Y2)t
Yf
Yp
Ytw
For a vertical drop structure, the difference in the bed elevations of the approach
channel at the weir and the downstream channel at the end of the structure, ft.
Also used as the side slope, ft/ft.
Zf
8-8
8.2
Hydraulic structures are used in storm drainage works to control water flow characteristics such
as velocity, direction and depth. Structures may also be used to control the elevation and slope of
a channel bed, as well as the general configuration, stability and maintainability of the waterway.
The use of hydraulic structures can increase the capital cost of drainage facilities while lowering
O&M costs. The use of hydraulic structures should be limited by careful and thorough hydraulic
engineering practices to locations and functions justified by prudent planning and design. On the
other hand, use of hydraulic structures can reduce initial and future maintenance costs by changing the characteristics of the flow to fit the project needs, and by reducing the size and cost of
related facilities.
Hydraulic structures include channel drop structures, spillways, grade control structures, energy
dissipators, bridges, transitions, chutes, bends and many other specific drainage works. Depending on the function to be served, the shape, size and other features of hydraulic structures can
vary widely from project to project. Hydraulic design procedures (including model testing in some
cases) that examine the structure and related drainage facilities are a key part of the final design
for all structures.
This chapter is oriented toward control structures for drainage channels, outlets for storm drains
and culverts, and spillways for non-jurisdictional dams. Design guidelines for spillways for jurisdictional dams or other specialized conveyance measures are beyond the scope of this manual.
The design professional is referred to the references cited at the end of this chapter.
8-9
Spillways
Spillways are conveyance features that permit outflow from stormwater basins. Engineering
nomenclature divides these into principal spillways and emergency spillways. The principal spillway for a dam is that hydraulic structure that has been designed to pass the more frequent flow
events while the hydraulic capacity of the emergency spillway is held in reserve for the rare flow
events. Principal spillways are associated with water storage impoundments (i.e. those with a
permanent pool) and stormwater detention basins (wet or dry). Emergency spillways, in one form
or another, are provided at these facilities as well as stormwater retention basins. An emergency
spillway is a flow conveyance feature designed to safely pass flows in excess of the facility
design discharge in a manner that does not threaten the integrity of the principal spillway, facility
embankment, or surrounding infrastructure. It also serves to pass flows normally conveyed by
the principal spillway under circumstances when the principal spillway becomes plugged. This
chapter presents the hydraulic equations used to determine hydraulic capacity for simple spillways. See Chapter 9 for a more detailed discussion pertaining to how these facilities are incorporated into stormwater basins.
Channel Transitions
Channel transitions are typically used to moderately vary the cross sectional geometry to allow
the waterway to fit within a more confined right-of-way, or to purposely accelerate the flow to be
carried by a specialized high velocity conveyance structure. Constrictions are designed to restrict
and reduce the conveyance along a short reach. Examples are a bridge with roadway approach
embankments that significantly encroach into a floodplain, or a structure designed to raise the
upstream water surface to force spills into an off-channel storage facility. An expansion structure
is usually required at the downstream end of a constricted channel reach or structure to provide a
safe, non-eroding transition to the unconstricted channel. Potential conditions for creation of a
hydraulic jump must be examined and provisions made for control of a jump and associated tur-
8-10
bulent flow conditions. Bifurcations are structures that permit flow to be diverted within a channel.
Similarly, side channel spillways also permit the diversion of flow. Finally, channel junctions pose
interesting design considerations, especially under supercritical flow conditions.
8-11
8.3
8.3.1 General
The term drop structure is broadly defined. Included are structures built to restore previously
damaged channels, those constructed during new urban development to prevent accelerated
erosion caused by increased runoff, and applications in which other specialized hydraulic conditions are created in the flow channel.
The focus of this design guideline is on drop structures with design flows up to 10,000 cfs. Flows
less than 500 cfs are in the usual range for grade control structures.
8-12
Design Considerations
In addition to hydraulic performance (discussed in Section 8.3.2), a number of other considerations affect the selection of an appropriate drop structure for a particular application.
Soil and Foundation Condition - Geotechnical investigations should be completed to identify the
characteristics of the on-site soils. Silty and sandy soils require detailed analyses for seepage
control. Expansive soils require special design techniques to minimize differential movement.
Structure design for foundation, walls and slabs must consider soil and hydrostatic pressures,
seepage and potential scour.
Construction Concerns - The selection of a drop and its foundation may also be tempered by
construction difficulty, access, material availability, etc. Quality control through conscientious
inspection is an important consideration.
Maintenance Concerns - Issues to be considered in the design include, ease of access to the
crest and stilling basin areas, vandal resistance, eliminate trapped (ponded) water, sediment
accumulation, and landscaped or grassed slopes that are easily maintained.
Sociological Considerations - These include public acceptability issues such as safety (Section
8.7), visual appearance (Section 8.8), mosquito breeding in ponded water, etc.
Drop Structure Types - Design guidance is presented in this section for the following drop structures:
8-13
FIGURE 8.2
DROP STRUCTURE TYPES
(McLaughlin Water Engineers, Ltd. 1986)
Due to a high failure rate and excessive maintenance costs, drop structures having loose riprap
on a sloping face are discouraged. Refer to Sloped Drop Structure/Rock Chute for design guidelines.
All drop structures should be inspected on a regular basis during construction in regard to construction quality and integrity. In addition, drop structures must be monitored on a periodic basis
after construction.
8-14
Additional bank and bottom protection may be needed if secondary erosional tendencies are
revealed. Thus, it is advisable to establish construction contracts and budgets with this in mind.
Use of standardized design methods for the types of drops described herein can reduce the need
for secondary design refinements. Section 8.3.3 presents considerations for the selection of the
appropriate type of drop structure for particular application or site conditions.
Define the maximum design discharge (usually the 100-year) and other discharges
appropriate for analysis (selected discharge(s) expected to occur on a more frequent
basis, which may behave differently at the drop).
2.
3.
Determine the required longitudinal channel slope and the total drop height required to
produce the desired hydraulic conditions.
4.
Establish the channel hydraulic parameters, reviewing drop structure and channel combinations that may be most effective.
5.
Conduct hydraulic analyses for the structure. Where appropriate, apply separate hydraulic analyses to the main channel and the low flow zones of the drop to determine the
extent of protection required, as well as the potential problems/solutions for each. (See
discussion later in this section.)
6.
Perform soils and seepage analyses to obtain foundation and structural design information. Combine seepage and hydraulic analysis data to determine forces on the structure.
Evaluate uplifting, overturning, and sliding.
7.
Evaluate alternative structures in terms of their estimated capital and maintenance costs,
and identify comparable risks and problems for each alternative. Review alternatives with
client and jurisdictional agency to select final plan. (This task is not specifically a part of
the hydraulic analysis criteria, but is mentioned to illustrate other factors which are
involved in the analysis of alternatives.)
8-15
8.
Use specific design criteria to determine the drop structure dimensions, material requirements and construction methods necessary to complete the design for the selected structures.
2.
To optimize crest and basin dimensions to achieve the most cost-effective structure, and
3.
To prevent erosion in the transition zone, where flow accelerates approaching the crest.
8-16
FIGURE 8.3
TYPICAL VERTICAL DROP CREST CONFIGURATION
(McLaughlin Water Engineers, Ltd. 1986)
8-17
A crest expansion may be necessary to maintain adequate freeboard in the upstream channel
and reduce drawdown velocities just upstream of the crest. A crest constriction may be appropriate for wide channels to reduce the cost of the crest wall.
Sloping Abutments at Drop Crest - Figure 8.4 shows a schematic layout for the drop crest and
upstream channel at a sloping drop structure. The design objectives discussed previously also
apply here. Constricting the trapezoidal crest serves to economize the structure while maintaining upstream freeboard. The seepage cutoff wall is typically placed at or near the upstream end
of the transition zone and the zone protected with concrete or grouted rock. This arrangement
also provides better seepage control, as discussed later in this section.
FIGURE 8.4
TYPICAL SLOPING DROP CREST CONFIGURATION
(McLaughlin Water Engineers, Ltd. 1986)
8-18
q
F s = ----- + y----gy 2
(8.1)
The depth y, for downstream specific force determination, is the tailwater surface elevation minus
the ground elevation at the point of interest, which is typically the main basin elevation or the
trickle channel invert (if the jump is to occur in the basin). The depth for the upstream specific
force (supercritical flow) is the supercritical flow depth at the point in question.
For jumps in vertical riprap basins, the user has to rely on the criteria derived from laboratory
studies. The shaping or reshaping of riprap influences the jump stability and location. Nevertheless, the basic specific force equation provides some guidance.
Ideally, for economic considerations, the jump should begin no further downstream than the drop
toe. This is generally accomplished in the main drop zone by depressing the basin to a depth
nearly as low as the downstream trickle channel elevation.
Analysis should be conducted for a range of flows, since flow characteristics at the drop can vary
with discharge. For example, the 10-year flow may cascade down the face of a sloping drop and
form a jump downstream of the toe, whereas the 100-year flow may totally submerge the drop.
Where a major channel incorporates a low flow channel, separate analyses should be completed
for the low flow zone and the major channel overbank zone. This is because the deeper flow profile in the low flow channel zone has a higher energy grade line profile (Figure 8.5). Specific force
analysis in this zone shows that the hydraulic jump will not occur in the same location as the rest
8-19
of the flow over the drop, and in most cases the jump will occur further downstream. Separate
analysis for this condition will determine if the stilling basin length is sufficient to contain the jump.
FIGURE 8.5
TYPICAL SECTION AND PROFILE FOR SLOPING DROP
(McLaughlin Water Engineers, Ltd. 1986)
Hydraulic Jump
With the exception of the baffle chute drop, all of the drop structures described herein use the formation of a hydraulic jump to dissipate energy. A discussion of this hydraulic phenomenon is presented as follows.
A hydraulic jump occurs when flow changes rapidly from low stage supercritical flow to high
stage subcritical flow. Hydraulic jumps can occur: 1) when the slope of a channel abruptly
changes from steep to mild; 2) at sudden expansions or contractions in the channel section; 3) at
locations where a barrier, such as a culvert or bridge, occurs in a channel of steep slope; 4) at the
8-20
downstream side of dip crossings or culverts; and 5) where a channel of steep slope discharges
into other channels.
Hydraulic jumps are useful in dissipating energy, and consequently they are often used at drainage way outlet structures and drop structures as an efficient way to minimize the erosive potential of floodwaters. However, because of the high turbulence associated with hydraulic jumps,
they must be contained within a well-protected area. Complete computations must be made to
determine the height, length and other characteristics of the jump (including consideration of a
range of flows) in order to adequately size the containment area.
The type of hydraulic jump that forms, and the amount of energy that it dissipates, is dependent
upon the upstream Froude number (Fr1). The various types of hydraulic jumps that can occur are
listed in Table 8.1.
TABLE 8.1
TYPES OF HYDRAULIC JUMPS
(USDOT, FHWA, HEC-14, 2006)
Upstream Froude
Number
Type of Jump
Energy Loss, %
Undular Jump
Minimal
Weak Jump
20%
Oscillating Jump
20 to 45
Steady Jump
45 to 70
Strong Jump
70 to 85
Jump Height - The depth of flow immediately downstream of a hydraulic jump is referred to as
the sequent depth (Y2). The sequent depth in rectangular channels whose upstream Froude
number is > 1.7, can be computed by use of the following equation:
1
2 1]
Y 2 = --- Y 1 [ 1 + 8F r1
2
(8.2)
The solution for sequent depth in trapezoidal channels can be obtained from a trial-and-error
solution of Equation (8.3), which is derived from momentum equations. It is also acceptable for
design purposes to determine the sequent depth in trapezoidal channels from Equation (8.2).
Equation (8.2) is much simpler to solve and produces only slightly greater values for sequent
depth than does Equation (8.3).
8-21
3 bY 2
ZY 13 ZY 12
Q - = ZY
Q--------- + --------- + ----------------2 + --------2- + -------3
2
gA 1
3
3
gA 2
(8.3)
Figure 8.6 and Figure 8.8 provide graphs of hydraulic jumps for a horizontal rectangular channel
and a horizontal trapezoidal channel, respectively.
Undular Jump - An undular hydraulic jump is the type of jump which occurs where the upstream
Froude number is between 1.0 and 1.7. This type of jump is characterized by a series of undular
waves which form on the downstream side of the jump. Experiments have shown that the first
wave of an undular jump is higher than the height given by Equation (8.3). Therefore, the height
of this wave should be determined as follows:
Y2 Y1
2 1
----------------- = F r1
Y1
(8.4)
Jump Length - The length of a hydraulic jump is defined as the distance from the front face of the
jump to a point immediately downstream of the roller. Jump length can be determined from Figure 8.7 and Figure 8.9.
Surface Profile - The surface profile of a hydraulic jump may be needed to design the extra bank
protection, or training walls for containment of the jump. The surface profile can be determined
from Figure 8.10.
Jump Location - In most cases a hydraulic jump will occur at the location in a channel where the
initial and sequent depths and initial Froude number satisfy Equation (8.3). This location can be
found by performing direct-step calculations in either direction toward the suspected jump location until the terms of the equation are satisfied. Specific force analysis can then be used by
employing Equation (8.1) to establish where a jump will occur. The hydraulic jump will begin to
form where the unit specific force of the downstream tailwater is greater than the unit force of the
supercritical approach flow.
8-22
FIGURE 8.6
HEIGHT OF A HYDRAULIC JUMP FOR A HORIZONTAL RECTANGULAR CHANNEL
(USDOT, FHWA, HEC-14, 2006)
8-23
FIGURE 8.7
LENGTH OF HYDRAULIC JUMP FOR RECTANGULAR CHANNELS
(USDOT, FHWA, HEC-14, 2006)
8-24
FIGURE 8.8
HEIGHT OF A HYDRAULIC JUMP FOR A HORIZONTAL TRAPEZOIDAL CHANNEL
(USING HYDRAULIC DEPTH) (USDOT, FHWA, HEC-14, 1983)
8-25
FIGURE 8.9
LENGTH OF A HYDRAULIC JUMP FOR NON-RECTANGULAR CHANNELS
(USDOT, FHWA, HEC-14, 1983)
8-26
FIGURE 8.10
SURFACE PROFILE OF A HYDRAULIC JUMP IN A HORIZONTAL CHANNEL
(Chow, 1959)
8-27
TABLE 8.2
UNIFORM FLOW IN CIRCULAR SECTIONS FLOWING PARTLY FULL
(USDOT, FHWA, HEC-14, 2006)
8-28
The weighted-creep distance of a cross section of a drop structure is the sum of the vertical creep distances (along contact surfaces steeper than 45 degrees), LV, plus one-third
of the horizontal creep distances (along contact surfaces less than 45 degrees), LH.
2.
( L H + 3L v )
C w = -------------------------3H df
3.
Lane's recommended weighted-creep ratios are given for various foundation materials in
Table 8.3.
4.
Reverse filter drains, weep holes, and pipe drains are aids to provide security from seepage, and recommended safe weighted-creep head ratios may be reduced as much as 10
percent, if used.
5.
Care must be exercised that cutoff walls extend laterally into each bank so that flow will
not outflank them.
6.
The upward pressure to be used in design may be estimated by assuming that the drop in
pressure from headwater to tailwater along the contact line of the drop structure and cutoff wall is proportional to the weighted-creep distance.
Seepage is controlled by increasing the seepage length such that Cw is raised to a conservative
value. Soils tests must be taken during design and confirmed during construction. These tests
are especially critical for reinforced concrete structures.
An example of this technique can be found in Design of Small Dams (USBR, 1977). An alternative approach is to use a flow net or computerized seepage analysis to estimate subsurface flows
and uplift pressures under a structure. Seepage considerations should be included in the design
of cutoff walls, wall footings, drains, filters, structural slabs, and grouted masses.
Locating a seepage cutoff wall upstream of the crest of a drop structure and using horizontal
impervious blankets can be effective. It is also very important to control lateral seepage around
the structure.
8-29
TABLE 8.3
LANE'S WEIGHTED-CREEP: RECOMMENDED RATIOS
(Lane, 1935)
Material
CW Ratio
Very fine sand or silt
8.5
Fine sand
7.0
Medium sand
6.0
Coarse sand
5.0
Fine gravel
4.0
Medium gravel
3.5
3.0
2.5
Soft clay
3.0
Medium clay
2.0
Hard clay
1.8
1.6
8-30
TABLE 8.4
GENERAL SEEPAGE CUTOFF TECHNIQUE SUITABILITY
(UDFCD, 2008)
Soil Conditions
Drop Height (ft)
2
4
8
12
Sand and gravel over bedrock with
S*
S*
S/SwB*
S/SwB*
sufficient depth of material to provide
support - groundwater prevalent.
CTc
CTc/ST
ST
ST
CTf
CTf/CTI
Sand and gravel with shallow depth
CTc
CTc/ST
ST
ST
to bedrock - groundwater prevalent.
CW
CW
CW
CW
S**
S**
S**
SwB**
Sand and Gravel, great depths to
S
S
S
S/SwB
bedrock - groundwater prevalent.
CTc
CTc/ST
ST
ST
Sand and gravel, no groundwater, or
S
S
S
S/SwB
water table normally below requirement (for variation caused by depth
to bedrock, see first case).
CTf/CTI
CTI
CTI
CTI
CW
CW
Clay (and silt) - medium to hard.
CTc
CTc
CTc
CTc
CW
Reduce length for difficult backfill
conditions
CTf/CTI
Only for local seepage zones/silts
ST
Expensive - for special problems
Clay (and silt) - soft to medium with
S
S
S
S/SwB
lenses of permeable material groundwater present.
CTc
CTc
CTc/ST
ST
S
S
S
S/SwB
Clay (and silt) - soft to medium with
lenses of permeable material-may be
moist but not significant groundwater
source.
CTc
CTf
CW
CTc
CTI
CW
CTc/ST
CTI
CW
ST
CTI
CW
8-31
Legend
S
Sheet pile
SwB
CTc
ST
Slurry Trench; similar to CTc; but trench walls are supported with slurry
and then later replaced with concrete or additives that effect cutoff
CW
Cutoff Wall; conventional wall, possibly with footer, backfilled; note that
the effective seepage length should generally be decreased because of
backfill
CTI
CTf
Economic Considerations
Evaluation of alternative drop structure costs should include consideration of construction costs
and maintenance costs. Construction costs include site work specific to the structure, seepage
control, excavation, reinforced concrete, riprap, boulders, grout and backfill. Maintenance costs
include rock replacement, debris removal, erosion repair, structural repairs, graffiti and silt
removal. A standard method of cost comparison is present-worth analysis by which estimated
maintenance costs are converted to present worth amounts by applying an appropriate discount
rate factor. The present worth maintenance cost is then added to the construction cost of each
structure under consideration for comparison.
Other factors also affect the economics of alternative types of drop structures. In many cases,
specific site requirements may dictate the direction of drop structure design. Depending on location, some construction materials, such as riprap or boulders, may not be readily available at reasonable cost. Analysis may include consideration of the cost of a single drop structure of height
(Hd) versus the cost of two structures, each 1/2 Hd high.
Construction Considerations
The selection of a drop and its foundation may also be tempered by construction difficulty, location, access, and material availability/delivery. Table 8.5 lists construction considerations for key
drop structure materials. Additional discussion of construction concerns is included with the
design guidelines for each drop type in the following section.
8-32
TABLE 8.5
QUALITY CONTROL MEASURES AND CONCERNS OF DROP STRUCTURE COMPONENTS
Type
Quality Concerns
Reinforcing
Steel
During construction there are numerous items which require checking, including: rebar placement, formwork, tie placement, weep holes
and drains, form release coatings and form cleaning before concrete
placement, form removal, concrete placement and testing, weather
protection, sealants, tie hole treatment, concrete finish work, and
earthwork, especially that related to seepage control.
Riprap
Rock
A significant effort is needed in the area of rock quality control. Submittals should be required from suppliers to document quality. Rock
should be durable, sound, and free of seams or fractures. The specific gravity should be a minimum of 2.40.
Concrete
and
Good placement techniques should result in a riprap layer with surface materials d50 size or greater, closely spaced with voids thoroughly chinked and locked between larger rock, top surfaces
generally parallel to the plane of the overall riprap bank or surface,
and no great departures in surface elevation from rock to rock.
Graded riprap should not be used for grouting, as the smaller rock
can prevent full penetration of the grout to the subgrade and can
cause incomplete filling of the voids. Large rock or boulders should
be placed with a gradall or multi-prong grapple device for ease of
handling and to minimize disturbance of the subgrade. A minimum
dimension should be specified for the rock to aid field inspection. On
slopes, uphill boulders should be keyed in below the tops of downhill
boulders for stability. A "stairstep" arrangement where the top surface of the rock is flat and horizontal is preferable for both aesthetic
and hydraulic reasons.
8-33
Quality Concerns
Grout
Sheetpile
Roller
Compacted
Concrete
Soil Cement
Synthetic
Liners
The subgrade should be inspected and sloped to achieve compaction of the cutoff soils and the adjacent subgrade. In order to use this
type of drop structure, the subgrade soil needs to be a clay (CL), as
classified by a qualified soils engineer.
Drains
8-34
Quality Concerns
Cutoffs using
Slurry Trench
Architectural
and
Landscape
Items
8-35
chute extends below grade and is backfilled with loose rock to prevent undermining the structure
by eddy currents or minor degradation of the downstream channel. This rock will rearrange to
establish a stable bed condition and produce additional stilling action. The structure is effective
without tailwater; however, higher tailwater reduces scour at the toe. Grouted and concrete
basins have also been used to prevent a standing pool from forming at the transitions to the
downstream trickle and main channels. The structure also lends itself to a variety of soils and
foundation conditions.
FIGURE 8.11
BAFFLE CHUTE DROP
(McLaughlin Water Engineers, Ltd., 1986)
8-36
There are fixed costs associated with the upstream wing walls, crest approach section, downstream transition walls and a minimum length of sloping apron (for four baffle rows). Consequently, the baffle chute becomes more economical with increasing drop height.
This design is quite flexible in adaption, once the hydraulic principles are understood. For example, the design has been modified for low drops by locating two rows of baffles on the slope and
two rows on a horizontal extension of the chute. Another approach has been to use a flatter chute
slope than the usual 2 horizontal to 1 vertical. There are examples where sloping abutments
have been used. Other examples include the use of sloping abutments at the crest and chute
sides. These drops can be extended at a later date if downstream bed degradation occurs
beyond that initially anticipated.
The potential for debris flow must also be considered. Use caution when conditions include
streams with heavy debris flow, because the baffles can become clogged between the interstices, resulting in overflow, low energy dissipation, and direct impingement of the erosive stream
jet on the downstream channel.
The design performance has been documented for numerous baffled apron drops (USBR, 1974).
The resulting design precautions generally relate to relatively minor problems, such as erosion
protection in adjacent channels, spray above the chute walls, and debris problems. The basic
design criteria and modification details are given in Figure 8.12 and Figure 8.13. Remaining
structural design parameters must be determined for specific site conditions. The recommended
design procedures are discussed on the following pages.
8-37
FIGURE 8.12
BAFFLE CHUTE DESIGN CRITERIA
(ADAPTED FROM: Peterka 1984)
8-38
FIGURE 8.13
BAFFLE CHUTE CREST MODIFICATIONS AND FORCES
(ADAPTED FROM: Peterka 1984)
Determine the maximum inflow rate and the design discharge per unit width:
q = QW
(8.5)
The chute width, W, may depend on the upstream or downstream channel width, the
upstream hydraulic control, economy, or local site topography. Generally, a unit discharge
between 35 to 60 cfs/ft is most economical.
8-39
2.
An upstream channel transition section with vertical wing walls, constructed 45 degrees
to the flow direction, causes flow approaching the rectangular chute section to constrict. It
is also feasible to use walls constructed at 90 degrees to the flow direction. In either configuration, it is important to analyze the approach hydraulics and water surface profile.
Often, the effective flow width at the critical cross section is narrower than the width of the
chute opening due to flow separation at the corners of the abutment. To compensate for
flow separation, it is recommended that the actual width constructed be 1 foot wider than
the design analysis width if the constricted crest width is less than 90 percent of the
upstream channel flow width. In any case, the design should carefully consider the
approach hydraulics and contraction/separation effects. Depth and approach velocities
should be evaluated through the transition to determine freeboard, scour, and sedimentation zones.
3.
The entrance transition is followed by a rectangular flow alignment apron, typically 5 feet
in length. The upstream approach channel velocity, V, should be as low as practical and
less than critical velocity at the control section of the crest. Figure 8.12(b) gives the USBR
recommended entrance (channel) velocity. In a typical grass-lined channel, the entrance
transition to the rectangular chute section will produce the desired upstream channel
velocity reduction. The elevated chute crest above the channel elevation, as shown in
Figure 8.12(a), should only be used when approach velocities cannot be controlled by the
transition. Special measures to prevent aggradation upstream would be necessary with
the raised crest configuration.
Entrance Modification:
1.
The trickle flow (or low flow) channel should be maintained through the apron, approach,
and crest sections. It may be routed between the first row of baffle piers. The trickle channel should start again at the basin rock zone which should be slightly depressed and then
graded up to transition to the downstream channel. Figure 8.13(c) illustrates one method
of designing the low flow channel through the crest.
2.
The conventional design shown in Figure 8.12(a) results in the top elevation of the baffles
being higher than the crest, which causes a higher backwater surface effect upstream.
Figure 8.12(b) may be used to estimate the extent of the effect and to determine corrective measures, such as increasing the upstream freeboard or widening the chute. Note
that baffles projecting above the crest will tend to produce upstream sediment aggradation. Channel aggradation can be minimized by the low flow treatment suggested in the
previous paragraph.
8-40
Another means of alleviating these problems is the Fujimoto entrance, developed by the
USBR and illustrated in Figure 8.13(b). The upper rows of baffles are moved one row
increment downstream. The important advantage of this entrance is that there is no backwater effect of the baffles. The serrated treatment of the modified crest begins disrupting
the flow entering the chute without increasing the headwater. More importantly, this configuration provides a level crest control. The designer may either bring the invert of the
upstream low flow channel into this crest elevation, widening the low flow channel as it
approaches the crest, or the designer may have a lower trickle channel and bring it
through the serrated crest similar to 1, above. These treatments will have to be observed
until more application experience shows what may work best.
Structural Design Dimensions: (see Figure 8.11)
1.
Assume critical flow at the crest and determine critical depth for both peak flow and for 2/
3 of peak flow. For unit discharge exceeding 60 cfs/ft, Figure 8.12(b) may be extrapolated:
2
yc = ( q g )
2.
0.33
(8.6)
The chute section (baffled apron) is concrete with baffles of height, Hb, equal to 0.8 times
critical depth. The chute face slope is 2:1 for most cases, but may be reduced for low
drops or where a flatter slope is desirable. For unit discharge applications greater than
60 cfs/ft, the baffle height may be based on 2/3 of the peak flow; however, the chute side
walls should be designed for peak flow (see number 4).
Baffle pier widths and spaces should equal, preferably, about 1.5 Hb but not less than Hb.
Other baffle block dimensions are not critical hydraulically. The spacing between the rows
of baffle blocks should be Hb times the slope. For example, a 2:1 slope makes the row
spacing equal to 2Hb parallel to the chute floor. The baffle piers are usually constructed
with the upstream face normal to the chute floor surface.
3.
Four rows of baffle piers are required to establish full control of the flow, although fewer
rows have operated successfully. At least one row of baffles are buried in riprap where
the chute extends below the downstream channel grade. Riprap protection continues
from the chute outlet to a distance of approximately 4Hb, or as necessary to prevent eddy
currents from undermining the walls. Additional rows of baffles may be buried below
grade to allow for downstream channel degradation.
4.
The baffle chute side wall height (measured normal to the floor slope) should be 2.4 times
the critical depth based on peak discharge (or 3Hb). The wall height will contain the main
flow and most of the splash. The design of the area behind the wall should consider that
8-41
some splash may occur, but extensive protection measures are not required.
5.
Determine upstream transition and apron side wall height as required by backwater analysis. Lower basin wing walls are generally constructed normal to the chute side walls at
the chute outlet to prevent eddy current erosion at the drop toe. These transition walls are
of a height equal to the channel normal depth plus 1 foot, and length sufficient to inhibit
eddy current erosion.
6.
All concrete walls and footer dimensions are determined by conventional structural methods. Cutoff walls and underdrain requirements are determined by seepage analysis (see
Section 8.3.2).
7.
The most troublesome aspect of the design is the determination of the hydraulic impact
forces on the baffles to allow the structural engineer to size adequate reinforcing steel.
Figure 8.13(d) may be used as a guideline. The structural engineer should apply a conservative safety factor, as this curve is based on relatively sparse information.
Construction Considerations:
There are numerous steps necessary in the construction of a baffle chute, but they are usually
easily controlled by a contractor. For quality control and inspection, there are consistent, measurable, and repeatable standards to apply.
Potential areas of concern include foundation problems, riprap quality control and placement,
and finish work with regard to architectural and landscape treatments. Formwork, form ties, and
seal coatings can leave a poor appearance, if not handled properly. Poor concrete vibration can
result in surface defects (honeycombing) or more serious conditions, such as exposed rebar.
In summary, baffle chute drop structures are the most successful as far as hydraulic performance
is concerned and are straightforward to construct. Steel, formwork, concrete placement and finish, and backfill require periodic inspection.
8-42
The hydraulic phenomenon provided by this type of drop is a jet of water which overflows the
crest wall into the basin below. The jet hits the hard basin and is redirected horizontally. With sufficient tailwater, a hydraulic jump is initiated. Otherwise, the flow continues horizontally in a
supercritical mode until the specific force of the tailwater is sufficient to force the jump. Energy is
dissipated in the turbulence through the hydraulic jump; therefore, the basin is sized to contain
the supercritical flow and the erosive turbulent zone.
Generally, a rough basin is advantageous since increased roughness will result in a shorter, more
economical basin. Figure 8.14 shows a vertical drop with a grouted boulder basin (concrete may
also be used), and illustrates several important design considerations.
General Hydraulic Design Procedure:
1.
The design approach uses the unit discharge in the main channel and the trickle channel
to determine the separate water surface profiles and jump locations in these zones. The
basin is sized to adequately contain the hydraulic jump and associated turbulent flows.
2.
The rock lined approach length ends abruptly at a structural retaining crestwall which has
a nearly rectangular cross section and trickle channel section. (Refer to Section 8.3.2)
3.
Crest wall and footer dimensions are determined by conventional structural methods.
Underdrain requirements are determined from seepage analysis.
4.
Open Channel Hydraulics (Chow, 1959), makes a brief presentation for the "Straight Drop
Spillway," which applies here. Separate analysis would need to be undertaken for the
trickle channel area and the main channel area as discussed in Section 8.3.2. In the following equations add the subscript t for the trickle channel area, and the subscript m for
the main channel area.
Refer to Figure 8.15 to identify the following parameters. Lb is the design basin length
which includes Ld and the distance to the jump, Dj, which is measured from the downstream end of Ld. The jump length, Lj, is approximated as six times the sequent depth, Y2.
As a safety factor, to assure a sufficient length for Lb, 0.6 Lj is added in the design of Lb,
such that:
L b L d + D j + 9.6Y 2
(8.7)
8-43
FIGURE 8.14
VERTICAL HARD BASIN DROP
(McLaughlin Water Engineers, Ltd., 1986)
8-44
FIGURE 8.15
VERTICAL DROP HYDRAULIC SYSTEM
(McLaughlin Water Engineers, Ltd., 1986)
When a hydraulic jump occurs immediately where the nappe hits the basin floor, the following variables are defined:
L d Y f = 4.3D n
0.27
(8.8)
where:
2
D n = q c ( gY f )
Y p Y f = 1.0D n
5.
0.22
Y 1 Y f = 0.54D n
0.425
Y 2 Y f = 1.66D n
0.27
(8.9)
(8.10)
(8.11)
(8.12)
In the case where the tailwater does not provide a depth equivalent to or greater than Y2,
the jet will wash downstream as supercritical flow until its specific force is sufficiently
reduced to allow the jump to occur. Determination of the distance to the hydraulic jump,
Dj, requires a separate water surface profile analysis for the main and low flow zones.
Any change in tailwater affects the stability of the jump in both locations.
6.
Caution is advised regarding the higher unit flow condition in the low flow zone. Large
boulders and meanders in the trickle zone of the basin are shown to help dissipate the jet,
8-45
and rock is extended downstream along the low flow channel. This results in three possible basin length design conditions:
a. At the main channel zone:
L bm = L dm + D jm + 0.60 ( 6 ) ( Y 2 ) m
(8.13)
L bt = L dt + D jt + 0.60 ( 6 ) ( Y 2 ) t
(8.14)
c. When large boulders or baffles are used to confine the jump to the impingement area
of the low flow zone, the low flow basin length may be reduced:
L bt = L dt + 0.60 ( 6 ) ( Y 2 ) t
(8.15)
7.
The basin floor elevation is depressed at depth B, variable with drop height and practical
for trickle flow drainage. Note that the basin depth adds to the effective tailwater depth.
The basin is constructed of concrete or grouted rock. Either material must be evaluated
for the hydraulic forces and seepage uplift.
8.
There is a sill at the basin end to bring the invert elevation to that of the downstream
channel and side walls extending from the crestwall to the sill. The sill is important in
causing the hydraulic jump to form in the basin. Buried riprap should be used downstream
of the sill to minimize any local scour caused by the lift over the sill.
9.
Water surface profile analyses have proven that base widths of the rectangular crest
which are less than that of the channel will result in high unit discharges and velocities,
thereby requiring unreasonable extensions of both the basin length and upstream rock
protection. Roughness in the basin area can reduce the basin length required to contain
the hydraulic jump. This is the primary advantage of the use of grouted rock in the drop
basin.
Construction Considerations:
Foundation and seepage concerns are very critical with regard to the vertical wall, as poor control
can result in sudden failure. The use of caissons or pile can mitigate this effect. Put in comparative terms with the baffle chute, seepage problems can result in displacement of the vertical wall
with no warning, where the box-like structure of the baffle chute may evidence some movement
or cracking, but not total failure, and thus allow time for repairs.
The quality control concerns and measures for reinforced concrete are described under baffle
chutes. The foundation concerns for the wall are critical as described above. The subsoil condi-
8-46
tions for the basin are also important so that the basin concrete or grouted riprap is stable against
uplift pressures.
A grouted boulder stilling basin provides roughness, which is useful in shortening the basin
length. As the name implies, the basin should be constructed of individual boulders placed on a
prepared subgrade. Boulders should be a minimum dimension that exceeds the grout layer thickness, so that the contractor and the inspector can see and have grout placed directly to the subgrade and completely filling the voids. Graded riprap should not be used for grouting, as the
smaller rock prevents the voids from being completely filled with grout. The result is a direct piping route for water beneath the grout, and a structural slab with insufficient mass. The completed
combination of boulders and grout should have an overall weight sufficient to offset uplift forces.
A minimum dimension of 18 inches is recommended for boulders, and 12 inches for the grout
layer. By maintaining the finished surface of the grout below the top of the boulder, both appearance and roughness characteristics are enhanced. Seepage relief for the basin slab should be
provided.
This type of structure has a moderate level of construction difficulty. The wall, once foundation
conditions are addressed, is conventional construction. It is very possible for the construction of
the seepage control and earthwork to go awry and problems to go undetected until the time of
failure. The flat concrete or grouted rock placement is easier for the contractor than graded rock
placement/quality control, but again poor placement and undetected subsoil, bedding or rock
problems can result in failure. Thus, it is easier than many other types to construct, but susceptible to some hidden risks and problems.
8-47
Structural design for the vertical crest wall is complicated by the lack of downstream support,
seepage, soil saturation and hydraulic loading on the upstream side. In sandy or erosive soils, it
is common to use sheet pile for the crest wall construction, while caissons may be an acceptable
foundation for certain other applications. A concrete retaining wall is frequently selected for ease
of construction, seepage control and low maintenance.
General Hydraulic Design Procedure:
The hydraulic analysis of this type of drop is generally similar to that presented previously in this
section for crest hydraulics. The design of the flexible plunge pool basin is described below.
The desired drop across the structure is the difference in the bed elevations of the approach
channel at the weir and the downstream channel at the end of the structure. Let this difference be
Hd. It follows from Figure 8.16 that:
H d = D 0.67d s
(8.16)
The designer must find the combination of rock size and jet plunge height D that gives a depth of
scour which balances Equation (8.16). The relation between rock size d50, jet plunge height D,
head on the weir, H, ( H = 1.5y c ) and depth of scour ds is given in Figure 8.17. As these values
will be different in the main drop and the trickle, the design d50 and/or ds will vary.
To obtain an adequate cutoff, the depth of the vertical wall that forms the weir crest must extend
below the bottom of the excavation for the riprap. Thus, it usually becomes uneconomical to
design a scour depth ds, any greater than 0.3 D. To meet this limitation in the field it is necessary
to: increase the rock size d50; decrease the jet plunge height D (by using more drops); decrease
H (by using a wider structure); or, to use another type of drop structure.
The side slopes in the basin must be riprapped also as there are strong back currents in the
basin. Granular filter material is required under this riprap. The side slopes in the basin should be
the same slope as for the downstream channel.
8-48
FIGURE 8.16
VERTICAL RIPRAP BASIN DROP
(Stevens, 1981)
8-49
FIGURE 8.17
CURVES FOR SCOUR DEPTH AT VERTICAL DROP
(Stevens, 1981)
8-50
Construction Considerations:
Foundation and seepage concerns are critical with regard to the vertical wall in this type of drop.
They are also generally more critical than with an equivalent vertical drop into a hard basin
because the riprap basin may scour and reshape, leaving less supporting material on the downstream side. Thus, if seepage is worse than anticipated, backfill is poor, or if seepage control
measures are not functioning, an immediate and severe structure stability problem can occur.
The use of caissons or piles can mitigate this effect. Seepage problems can result in displacement of the vertical wall with no cracking as an advance warning. Seepage can also cause piping
failure where the water will actually flow under the vertical wall. Problems can result from rock
that does not meet specifications for durability, specific gravity or gradation. Quality control of
rock installation can be difficult in regard to measuring performance and maintaining consistency.
Undersized rock in the plunge pool basin can cause the basin to reshape differently than
designed and result in stability problems for the wall, the basin, and the downstream channel.
This type of structure has a moderate level of construction difficulty. The wall, once foundation
conditions are addressed, is straightforward. It is very possible for the construction of the seepage control and earthwork to go awry and for problems to go undetected until the time of failure.
The flat riprap placement is easier than sloping, but again poor placement and undetected subsoil, bedding, or rock problems can all contribute to failure.
8-51
FIGURE 8.18
STILLING BASINS FOR SLOPING CONCRETE DROPS
(ADAPTED FROM: USDOT, FHWA, HEC-14, 1983)
8-52
tion and supercritical water surfaces down the sloping face, seepage uplift forces must be evaluated. Net uplift forces vary as a function of location along the drop, cutoff measures, drain gallery
locations and water surface profiles through the basin.
For a stable structure, net uplift force from seepage must be countered by net forces in the downward direction. For a smooth concrete chute, downward forces are the buoyant weight of the
concrete structure and the weight of water (a function of the depth of flow). Significant pressure
differentials can occur with a combination of high seepage forces and shallow supercritical flow.
Seepage analyses should be conducted using Lane's weighted creep methodology (Section
8.3.2), and suitable countermeasures designed. Such measures include cutoff walls, weep drain
galleries and concrete slab thickness design. A range of flood discharges should be evaluated,
since differential pressure relationships can vary with flow depth and location of hydraulic jump.
Construction Considerations:
There may be applications where sloping concrete drops are advantageous, but generally other
drops such as baffle chutes or vertical drops are more appropriate for a wider range of applications. The design guidance provided by the literature is clear and relatively easy to use, but the
implementation is often difficult or impractical. This basically has to do with providing basin depth
without creating a maintenance problem and less flexibility in adapting to varying bed conditions.
The integrity of the cutoff is important as seepage and resultant uplift forces are key concerns.
Uncontrolled underflow could easily lift a major concrete slab.
The stilling basin should be designed to drain completely, to eliminate nuisances related to ponded water, such as mosquito breeding and sediment/debris accumulation.
Considerations relating to general concrete construction are the same as discussed previously
for baffle chute drops. Public acceptability is likely to be low in urban areas, as the sloping concrete face is inviting for bicyclists, roller skaters, and skateboard enthusiasts.
8-53
Addition of roughness elements on the face of a sloping concrete drop can provide increased
energy dissipation. "Stepped" concrete has been successfully applied at spillways and drop
structures. Roller compacted concrete is a methodology that can achieve the stairstep geometry
on the face of a sloping drop. Reinforced concrete steps can be constructed by standard construction methods on small structures. Stepped drop structures have been found to be effective
in dissipating the energy associated with low flows but fail to effectively dissipate energy of higher
flows. Thus, stilling basin length for a stepped drop structure will be based upon the conventional
length calculations for a sloping drop presented herein. Stepped drop structures will be no
steeper than 2H:1V with a step height no greater than 2.5 feet and a step apron length of 6 feet.
Construction of a drop with grouted boulders is another means of creating desirable roughness
on the sloping face and in the stilling basin (see Figure 8.19).
FIGURE 8.19
GROUTED BOULDER PLACEMENT
(McLaughlin Water Engineers, Ltd., 1986)
However, because the structure is comprised of a structural slab with two components (boulders
and grout), great care must be taken to design the structure to withstand uplift and to specify
boulder and grout material to assure full quality control in the field. Seepage analysis is required
to determine a compatible combination of cutoff depth, location of the toe drain and/or other
drains, and the thickness of rock and grout. Problems with rock specific gravity, durability and
8-54
hardness are of concern. Gradation problems are largely eliminated because the boulders are
specified to meet minimum physical dimensions and/or weights, which is much easier to observe
and enforce in the field than with graded riprap.
The handling of the large boulders requires skilled work force and specialized equipment. Equipment similar to logging tongs, and specially modified buckets with hydraulically powered
"thumbs" have been used in recent years and have greatly improved quality and placement
rates. The careful placement of stacked boulders, so that the upstream rock is keyed in behind
the downstream rock, and placed with a large flat surface horizontally, has been shown to be successful.
The greatest danger lies with a "sugar coated" grout job, where the grout does not penetrate the
voids between the rock and the subgrade, leaving a direct piping route for water under the grout.
This can easily occur when attempting to grout graded riprap, thus the need to use individual
boulders that are larger in diameter than the grout layer so that the contractor and the inspector
can see and have grout placed directly to the subgrade. The best balance appears to be boulders 33 to 50 percent greater in size than the grout thickness, but of an overall weight sufficient to
offset uplift. Also, when holding grout to this level, the appearance will be much better.
The grout should have a minimum 4,000 psi compressive strength at 28 days, stone aggregate
with a maximum dimension of one-half inch and a slump within a range of 4 to 7 inches. The
water/cement ratio should not exceed 0.48.
Other USBR Basins - Some other stilling basins developed by the USBR (Peterka, 1984) have
limited application. For example, Basin I is basically a horizontal concrete apron downstream of a
sloping or vertical drop. This type of basin is applicable only to a concrete lined channel, and, as
the USBR states, has wave problems that are difficult to overcome. Maintenance of sufficient tailwater depth is important to cause a hydraulic jump within a practical zone close to the toe of the
drop. Generally, other types of USBR basins are better alternatives to Basin I.
USBR Basin V is a stilling basin with sloping apron, and provides dissipation as effective as that
which occurs in the basin with a horizontal apron. Again, adequate tailwater is a must. This type
of structure would have an application as a spillway into a pond with a permanent pool, so that
minimum tailwater is essentially guaranteed.
Box Inlet Drop Structure - The box inlet drop structure may be described as a rectangular box
open at the top and downstream end (Figure 8.20). Water is directed to the crest of the box inlet
by earth dikes and headwalls. Flow enters over the upstream end and two sides and leaves the
structure through the open downstream end. The long crest of the box inlet permits large flows to
pass at relatively low heads. The width of the structure does not need to be greater than the
downstream channel. It is applicable for drops from 2 feet to 12 feet. Designers of box inlet drop
8-55
structures should review permissible drop heights allowed by governing jurisdictions as safety
issues need to be considered.
FIGURE 8.20
BOX INLET DROP STRUCTURE
(ADAPTED FROM: USDOT, FHWA, HEC-14, 1983)
The outlet structure can be adjusted to fit a wide variety of field conditions. It is possible to
lengthen the straight section and cover it to form a highway culvert. The sidewalls of the stilling
basin section can be flared if desired, thus permitting use with narrow channels or wide floodplains. Flaring the sidewalls also makes it possible to adjust the outlet depth to match the natural
channel.
Design guidelines are presented in Hydraulic Design of Energy Dissipators for Culvert and Channels (USDOT, 1983).
8-56
headcutting. Here, headcutting is defined as the scouring of the channel bed proceeding from a
downstream to upstream direction. Local soils, bed materials, and sediment gradation must be
considered along with channel hydrology and hydraulics for the effective design of a grade control structure (See Chapter 5 and Chapter 11 for further discussion on sediment transport and
estimating scour depth). The longevity of the structure is dependent upon the depth of toe down
(among other things), which must exceed the depth of scour in order to stabilize the channel
slope upstream of the structure. The potential for seepage cutoff must be assessed for hydrostatic pressure and the potential failure of the structure foundation due to piping of the underlying soils. If an issue, the appropriate engineered solutions should be employed in the design.
These solutions include the use of geotextile filter fabrics to prevent soil loss and small diameter
PVC pipes to relieve hydrostatic pressure. In any case, appropriate access to grade control
structures is necessary to permit intermittent maintenance.
8.4
8.4.1 General
This section is applicable to both culvert and storm drain outlets. Outlet structures can provide a
high degree of energy dissipation and are generally effective even with relatively low tail water
control. Rock protection at culvert outlets is appropriate where moderate outlet conditions exist;
however, there are many situations where rock aprons or basins are impractical even at low to
moderate flow conditions. Concrete energy dissipation or stilling basin structures are then
required to prevent scour damages caused by high exit velocities and flow expansion turbulence
at culvert outlets. Concrete outlet structures can be designed easily and are suitable for a wide
variety of site conditions. In some cases, they are more economical than large rock basins, particularly where long term costs are considered. Covered in this section are both riprap and concrete energy dissipators.
8-57
detention basin or a channel where the velocity is so small that it will not move the riprap. If culverts outfall to a channel as a side drainage system, the riprap must be large enough to withstand
the flow in the channel. The riprap sizing equation for channel flow can be found in Channel Bed
on Straight Reach or Channel Bed on Curved Reach in Section 6.6.3. The larger riprap size
between the riprap apron/basin approach and the channel flow riprap sizing method should be
used. When the riprap for channel flow is larger than that for the riprap basin approach, the riprap basin parameters should be adjusted based on the larger median riprap
Riprap Apron
The material for a typical riprap apron is loose angular riprap. The apron should be level wherever possible, or set at the streambed slope. The median diameter for riprap (d50) can be estimated by the loose riprap sizing equation for Channel Bed on Straight Reach in Section 6.6.3.
When a highly turbulent flow is expected at the culvert outlet, the loose riprap sizing equation for
Downstream of Grade Control/Drop Structure in Section 6.6.3 should be used to compute d50.
When riprap size becomes too large to be practical, the culvert should be re-designed to reduce
the culvert exit velocity. The other riprap gradation limits (d100, d85, and d15) can be found in
Table 6.4. The apron has a fan-shape as shown in Figure 8.21 with a 3:1 expansion ratio. "D" in
Figure 8.21 represents the diameter for a circular pipe or equivalent diameter for a non-circular
culvert.
FIGURE 8.21
RIPRAP APRON PLAN VIEW
The apron length and thickness can be estimated based on Table 8.6 (USDOT, 2006). For a d50
size not listed in Table 8.6, a linear interpolation can be performed to determine the apron length
and apron thickness.
8-58
TABLE 8.6
APRON LENGTH AND THICKNESS
(USDOT, 2006)
d50 (in)
4D
3.5 d50
4D
3.3 d50
10
5D
2.4 d50
14
6D
2.2 d50
20
7D
2.0 d50
22
8D
2.0 d50
The apron width at the outlet should be 3 times the diameter for a circular culvert or equivalent
diameter for a non-circular culvert. The apron width at the apron downstream end can be estimated by 3D + 2L 3 where D is the diameter or equivalent diameter and L is the apron length.
The apron shall have a filter beneath the riprap. The filter can be a fabric filter or granular filter.
Refer to Riprap Layer Characteristics in Section 6.6.3 for the filter design procedure.
Grouted riprap may also be used for the riprap apron for side inlet outfall erosion protection. The
grouted riprap apron bed should have a zero slope. The apron should also be fan-shaped as
shown in Figure 8.21 using the same expansion ratio. The apron length should be at least 8D
where D is the diameter for a circular culvert or equivalent diameter for a non-circular culvert.
The width at the beginning of the apron is at least 3D. The width at the downstream end of the
apron is at least 3D + 2L 3 where L is the apron length. Riprap sizing and gradation limits can
be found in Section 6.6.5 Grouted Riprap Lined Channels. Concrete turndowns to total scour
depth and 1 foot wide shall be constructed around the entire perimeter of the grouted riprap
apron. If the total scour depth is large, a 2.5-ft deep concrete turndown may be used with loose
angular riprap around the perimeter of the concrete turndown. The volume of riprap should be
sufficient to launch to the total scour depth. Concrete grout mix shall be an 8 sack mix per MAG
Specification 220.6 (MAG, 1998). A filter blanket underneath the grouted riprap apron is not necessary. Additional loose angular riprap 3 feet wide may be needed around the turndown to
ensure that the turndown will be protected from channel flow if the total scour depth is more than
2.5 feet. The depth of the additional loose angular riprap should be based on the channel total
scour depth computed using the procedures in Section 11.8.2. The loose angular riprap design
can be based on toe protection requirements in Section 6.6.4.
8-59
Riprap Basin
The following design procedures for a riprap basin are adapted from Chapter 10, USDOT, 2006.
The procedures are applicable for both circular and box culverts. The typical riprap basin is
shown on Figure 8.22 and Figure 8.23. Either angular or rounded riprap may be used. A fabric
or granular filter blanket shall be installed beneath the riprap. The filter design procedure is
defined in Riprap Layer Characteristics in Section 6.6.3.
FIGURE 8.22
PROFILE OF RIPRAP BASIN
(USDOT, 2006)
FIGURE 8.23
HALF PLAN OF RIPRAP BASIN
(USDOT, 2006)
8-60
Step 1. Compute the culvert outlet flow depth (yo) and velocity (Vo).
For subcritical flow (culvert on a mild or horizontal slope), use Figure 8.24 for rectangular culverts
or Figure 8.25 for circular culverts to obtain yo/D and then compute yo. TW stands for tailwater
depth and can be estimated by using Manning's equation for the channel section downstream of
the culvert. Vo is then computed by dividing Q by the wetted area associated with yo. D is the
height of a box culvert or diameter of a circular culvert.
For supercritical flow (culvert on a steep slope), yo and Vo can be found by solving the Manning's
equation inside the culvert. Compute the Froude number to verify it is a supercritical flow condi12
tion by Fr = V o ( gy e )
, for brink conditions using brink depth for box culverts (ye = yo) and
12
equivalent depth ( y e = ( A 2 )
) for non-rectangular sections where A is the wetted cross section area inside the culvert at ye.
Step 2. Estimate the median riprap size (d50) and Dissipator Pool Depth (hs).
d50 and hs can be estimated by the trial and success method on d50 based on the following equation until the h s d 50 2 and d 50 y e 0.1 conditions are both met.
d 50 0.55 V o
hs
---- = 0.86 -------
------------- C 0
ye
ye
gy e
(8.17)
where:
hs
ye
d50
C0
When the consequences of riprap basin failure are severe, the following tailwater parameter C0
for the envelope design relationship should be used, which is defined as:
C 0 = 1.4
for
TW y e < 0.75
C 0 = 4 ( TW y e ) 1.6
for
C 0 = 2.4
for
1.0 < TW y e
where TW is the tailwater depth (ft), which can be estimated by using Manning's equation for the
channel section and ye is the equivalent outlet depth (ft).
8-61
FIGURE 8.24
DIMENSIONLESS RATING CURVES FOR THE OUTLETS OF RECTANGULAR CULVERTS
ON HORIZONTAL AND MILD SLOPES
(Simons, et al., 1970)
8-62
FIGURE 8.25
DIMENSIONLESS RATING CURVES FOR THE OUTLETS OF CIRCULAR CULVERTS
ON HORIZONTAL AND MILD SLOPES
(Simons, et al., 1970)
8-63
When a riprap basin failure can be easily addressed as part of routine maintenance, the tailwater
parameter for the best fit design relationship should be used, which is defined as:
C 0 = 2.0
for
TW y e < 0.75
C 0 = 4 ( TW y e ) 1.0
for
C 0 = 3.0
for
1.0 < TW y e
Basins sized where h s d 50 2 is greater than, but close to, 2 are often the most economical
choice (USDOT, 2006). Either angular or rounded riprap can be used (USDOT, 2006). The recommended riprap gradation limits (d100, d85, and d15) can be found in Table 6.4. The riprap
basin shall have a filter beneath the riprap. The filter can be a fabric filter or granular filter. The
riprap gradation limits and the filter design information are presented in Riprap Layer Characteristics in Section 6.6.3.
Step 3. Determine riprap basin dimensions.
Dissipator pool length Ls is equal to the larger value of 10hs or 3Wo where Wo is the culvert width
at the culvert outlet. The length of apron LA is the larger value of 5hs or Wo. The overall length of
the basin LB is the larger value of 15hs or 4Wo. The riprap layer thickness at the pool shall be at
least 2d50 or 1.5d100 thick. The riprap layer immediately downstream of the culvert outlet shall
have a minimum thickness of 3d50. The basin width at the basin exit (WB) can be computed
using the 1:3 expansion ratio from the culvert outlet to the basin exit, which is W o + 2 ( L B 3 ) .
When there are multiple culverts, the estimation of Ls, LA, and LB may be based on a single culvert because the equations were developed based on single culvert experiments. However, WB
should be based on the multiple culvert total width. The other basin parameters such as slopes
can be found in Figure 8.22 and Figure 8.23. The walls and apron of the basin should be warped
or transitioned so that the cross section of the basin at the exit conforms to the cross section of
the natural channel. Abrupt transition of surfaces should be avoided to minimize separation
zones and resultant eddies.
Step 4. Determine the basin exit depth (yB) and exit velocity (VB).
It is assumed that the flow at the basin exit is critical flow. Therefore, basin exit depth (yB) is critical depth (yB = yc) and exit velocity (VB = Vc). The critical depth at the basin exit can be determined by solving the critical flow condition equation:
2
Q g = ( Ac ) Tc
(8.18)
where
8-64
Ac
y c ( W B + zy c ) ,
Tc
W B + 2zy c ,
Vc
Q Ac .
where:
After Vc is computed, it is compared with Vallow where Vallow is the allowable exit velocity which
can be taken as the estimated normal velocity in the tailwater channel or a velocity specified
based on stability criteria, whichever is larger. If Vc is less than Vallow, then the basin design at
above Step 3 is acceptable. If not, the above steps are repeated to evaluate alternative dissipator designs. The normal velocity is computed by Manning's equation. HEC-RAS may be used to
estimate channel normal velocity. The stability criteria may be the permissible velocity for the
soils downstream of the basin. Permissible velocity standards are set forth in Section 6.5.3.
Step 5. Assess need for additional riprap downstream of the dissipator exit.
If the outlet hydraulics constitute a low tailwater condition defined by TW y o 0.75 , no additional riprap is needed. If the outlet hydraulics constitute a high tailwater condition defined by
TW y o > 0.75 , the high velocity core of water passes through the basin and diffuses downstream. As a result, the scour hole is longer and narrower. Therefore, if is the outlet protection
hydraulics constitute a high tailwater condition, additional riprap is required downstream of the
dissipator exit.
The required total distance measured from the dissipator outlet exit can be estimated using Figure 8.26. Figure 8.26 shows a decreasing relationship for L/De and (VL)ave/Vave where L is the
0.5
distance downstream from the culvert outlet, De is the equivalent circular diameter ( 4A ) for
a non-circular culvert, Vave (or Vo) is the average velocity at the culvert outlet and (VL)ave is the
average velocity for the distance L. Various values for L can be tried until (VL)ave is less than Vallow. Once the value of L is found, the additional length of riprap can be found by subtracting LB
from L. The riprap median size for the additional riprap downstream of the riprap basin can be
computed by the riprap sizing equation for Downstream of Stilling Basin in Section 6.6.3. The
other gradation limits for the riprap can be found in Table 6.4.
8-65
FIGURE 8.26
DISTRIBUTION OF CENTERLINE VELOCITY FOR FLOW FROM SUBMERGED OUTLETS
(USDOT, 2006)
8-66
Step 6. Determine the toe-down depth for sloping apron or cutoff wall.
The total scour depth should be estimated based on scour estimation procedures in Chapter 11.
The toe-down depth for a sloping apron should, as a minimum, be set equal to the total scour
depth. The toe-down depth for vertical cutoff walls can be estimated based on the toe protection
procedure in Section 6.6.4. This procedure is also sometimes referred to as the launching of riprap procedure.
8-67
FIGURE 8.27
TYPICAL STILLING BASIN
(USDOT, 2006)
FIGURE 8.28
USBR TYPE III STILLING BASIN
(USDOT, 2006)
8-68
FIGURE 8.29
USBR TYPE IV STILLING BASIN
(USDOT, 2006)
8-69
FIGURE 8.30
ST. ANTHONY FALLS (SAF) STILLING BASIN
(USDOT, 2006)
8-70
USBR Type VI impact basin (USDOT, 2006). The CSU rigid boundary basin uses staggered
rows of roughness elements to initiate a hydraulic jump. The Contra Costa energy dissipator
basin is intended for use primarily in urban areas with defined tailwater channels. There are two
types of Hook basins. One uses warped wingwalls, another a uniform trapezoidal channel. The
Hook basin roughness elements consist of upstream facing hook-shaped dissipators. The USBR
Type VI impact basin is contained in a relatively small box-like structure that requires no tailwater
for successful performance. This structure can also be used in open channels. The design procedures and examples for these basins can be found in USDOT, (2006). Figure 8.31, Figure
8.32, Figure 8.33, Figure 8.34, and Figure 8.35 illustrate these streambed level energy dissipator
basins.
FIGURE 8.31
CSU RIGID BOUNDARY BASIN
(USDOT, 2006)
8-71
FIGURE 8.32
CONTRA COSTA BASIN
(USDOT, 2006)
8-72
FIGURE 8.33
HOOK BASIN WITH WARPED WINGWALLS
(USDOT, 2006)
8-73
FIGURE 8.34
HOOK BASIN WITH UNIFORM TRAPEZOIDAL CHANNEL
(USDOT, 2006)
8-74
FIGURE 8.35
USBR TYPE VI IMPACT BASIN
(USDOT, 2006)
8-75
FIGURE 8.36
MODIFICATIONS TO IMPACT STILLING BASIN
(TO ALLOW BASIN DRAINAGE FOR URBAN APPLICATIONS)
(McLaughlin Water Engineers, Ltd., 1986)
A low flow gap is extended through the basin end sill wall. The gap in the sill should be as narrow
as possible to minimize effects on the sill hydraulics. This implies that a narrow and deeper (1.5
to 2-foot) low flow channel will work better than a wider gap section. The low flow width should
not exceed 60 percent of the pipe diameter to prevent the jet from short-circuiting through the
cleanout notches.
Low flow modifications have not been fully tested to date. Caution is advised to avoid compromising the overall hydraulic performance of the structure. Other ideas are possible including
8-76
locating the low flow gap at one side (off center) to prevent a high velocity jet from flowing from
the pipe straight down the low flow channel.
The optimal configuration results in continuous drainage of the basin area and helps to reduce
the amount of sediment entrapment.
1.
For large basins where the sill height is greater than 2.0 feet, the depth dimension, d, (in
Figure 8.36) may be reduced to avoid a secondary drop from the sill to the main channel.
The low flow invert thereby matches the floor invert at the basin end and the main channel elevation is equal to the sill. Dimension d should not be reduced by more than
one-third and not less than 2 feet. This implies that a deeper low flow channel (1.5 to 2.0
feet) will be advantageous for these installations.
Note that dimension d is also reduced at the minimum pipe invert height and at the bottom
of the baffle wall.
2.
A sill section should be constructed directly in front of the low flow notch to break up bottom flow velocities. The length of this sill section should overlap the width of the low flow
by about 1 foot. The general layout for the low flow modifications is shown in Figure 8.36.
8-77
channels in which some future degradation is anticipated. As mentioned previously, the apron
can be extended at a later time to account for channel subsidence. Generally, this type of structure is only cost effective if a grade drop is necessary below the outfall elevation and a hydraulic
backwater can be tolerated in the culvert design.
Figure 8.37 illustrates a general configuration for baffled outlet for a double box culvert outlet. In
this case, an expansion zone occurs just upstream of the approach depression. The depression
depth is designed as required to achieve the flow velocity at the chute entrance as described in
Section 8.3.4. The remaining hydraulic design is the same as for a standard baffle chute. The
same crest modifications are applicable to allow drainage of the approach depression, to reduce
the upstream backwater effects of the baffles, and to reduce the problems of debris accumulation
at the upstream row of baffles.
FIGURE 8.37
BAFFLE CHUTE AT CONDUIT OUTLET
(ADAPTED FROM: Peterka, 1984)
8-78
An effective means of controlling velocities within the culvert is the use of reinforced concrete
pipe (RCP) velocity control rings. The culvert velocity reduction by internal energy dissipators
(velocity control rings or roughness elements) force the hydraulic jump to occur within the culvert,
thus eliminating costly outlet structures. The design procedures can be found in Concrete Pipe
Handbook (ACPA, 1988) and HEC-14 (USDOT, 2006).
8-79
8.5
SPILLWAYS
Q = CLH
32
Q = C o A ( 2gH )
(8.19)
12
(8.20)
Weir-Type Spillways
Weir-type spillways can be generally classified as sharp crested, broad crested or compound
curve (ogee) shaped (Figure 8.38). The primary difference between sharp crested and broad
crested weirs is the thickness of the weir (in profile) relative to the depth of water passing the
crest. Where the crest thickness is greater than 6/10 the depth of flow over the weir, the weir can
be considered to be broad crested (Simon, 1981). In all cases, the weir equation is generally
used to assess spillway performance and to establish a spillway capacity rating curve. However,
the selection of the weir coefficient, C, is a function of numerous factors including the total head
on the weir, the vertical height of the weir, inclined faces of the weir (both upstream and/or downstream), submergence conditions, and breadth of broad crested weirs. Care must be taken in
selecting the value of C and in applying appropriate correction factors to C depending upon the
structure configuration and flow conditions.
8-80
FIGURE 8.38
WEIR SPILLWAY CONFIGURATIONS
(ADAPTED FROM: Brater and King, 1976)
For sharp crested weirs, the weir coefficient can range from about 3.2 to an excess of 5.0. The
Rehbock equation (Equation (8.21)) (Chow, 1959, page 362) is often used to estimate C:
C = 3.27 + 0.40H h w
(8.21)
where H is the measured head and hw is the height of the weir. That equation is valid for H/hw up
to 5 but can be extended to H/hw = 10 with fair approximation. Values of C in excess of 5.0 should
not be used without careful deliberation of all factors including consequence of overestimated
capacity. Typical C values are in the lower end of the aforementioned range. It is important to
note that this discussion assumes that the nappe of water over the sharp crested weir is fully aerated. Insufficient aeration will result in undesirable performance, including pressure differential on
the structure, unsteady and pulsing discharge over the weir, and increase in spillway discharge.
Brater and King (1976) provides useful tables in selecting appropriate values for C.
Broad crested weirs have widely varying physical conditions which significantly affects the value
of the weir coefficient. The normal range of C is from about 2.4 to about 3.5, however, use of values in excess of 3.1 must be carefully analyzed and are generally not recommended. A discharge coefficient of 3.0 is typical for flow over roadway embankments without backwater
8-81
(Bureau of Public Roads, 1978). See Section 5.3.3 for adjustment to C for roadway embankments subjected to submergence. The head, H, is measured at least 2.5H upstream of the weir
for broadcrested weirs.
Ogee shaped spillways can offer the best hydraulic performance, however, the cost of such spillways is usually greater than other comparable weir types. Ogee spillways must be designed and
analyzed by appropriate methods, such as those enumerated in the Design of Small Dams
(USBR, 1987, p353 and 366-367).
It is important to note that downstream water surface elevation (tailwater) must be analyzed by
appropriate methods (see Chapter 6) to assess potential for submergence of any weir.
Stepped Spillway
Stepped spillways consist of a series of steps on a slope. Because energy is dissipated by flow
over each step, stepped spillways produce cost savings in the size of the energy dissipator (US
Bureau of Reclamation, 2006). There are two flow regimes for stepped spillways, which are
nappe flow and skimming flow as shown in Figure 8.39 and Figure 8.40. For nappe flow, the
water plunges from one step to another. Nappe flow is associated with low discharges. As the
discharge increases, the nappe flow will transition to skimming flow. For skimming flow, the
water flows down the steps as a coherent stream skimming over the steps. A comprehensive
review of stepped spillways can be found in US Bureau of Reclamation (2006). Other references
on stepped spillways are Chanson (1994a, 1994b, and 2001), Gonzales and Chanson (2007),
and Boes and Hager (2003a, 2003b, and 2005).
8-82
FIGURE 8.39
NAPPE FLOW ON STEPPED SPILLWAY
(US Bureau of Reclamation, 2006)
8-83
FIGURE 8.40
SKIMMING FLOW ON STEPPED SPILLWAY
(US Bureau of Reclamation, 2006)
8-84
8-85
8.6
8-86
Contractions
Specially designed open channel flow transitions (contractions) are normally not required for
highway culverts. A culvert is normally designed to operate with an upstream headwater pool
which dissipates the channel approach velocity and, therefore, negates the need for an approach
flow transition. The side and slope tapered inlets for culverts are also designed primarily as submerged transitions and are discussed in Chapter 5.
Special inlet transitions are useful when the conservation of flow energy is essential because of
allowable headwater consideration, such as an irrigation structure in subcritical flow, or where it
is desirable to maintain a small cross section with supercritical flow in a steep channel. Furthermore, special transitions should be considered at locations where channel geometry changes,
bridges, chutes, and other structures.
Expansions
Outlet transitions (expansions), changes in Q, right-of-way, channel geometry, bridges, chutes
and other structures must be considered in the design of all culverts, channel, protection, and
energy dissipators. Design considerations for subcritical channel transitions are presented in
Hydraulic Design of Energy Dissipators for Culverts and Channels (USDOT, 1983)
Bifurcation Structures
It may occasionally be necessary to divert part of the flow in a channel. For example, the
designer may need to divert a portion of the flow to a stormwater basin or, the downstream rightof-way may be too narrow to accommodate the full flow and a portion of the flow may have to be
diverted to another outfall point. In these instances the designer will have to provide a splitter or
bifurcation structure to apportion the flow in the appropriate direction.
In order for the structure to work as designed, the water surface elevation must be the same in all
three channels at the proposed structure. This is accomplished by determining the water surface
elevation in the upstream channel at the proposed structure. Then, the exact location of the splitterwall to divert the desired amount of water is calculated. Last, the geometry of both downstream channels must be adjusted to produce water surface elevations at the structure that
match the water surface elevation in the upstream channel.
If the flow in the channel at the structure site is supercritical, the process is reversed and the
water surface profiles are calculated in the downstream direction. However, considerable caution
should be exercised in attempting to split supercritical flows. Readers are strongly encouraged to
consult appropriate references listed at the end of this chapter or seek the advise of an experienced professional.
Once the water surface at the structure site has been established, the amount of flow in each
area of the upstream channel can be calculated and the precise horizontal location of the splitter
wall established. The initial angle of departure of the diverted channel should not exceed 12
8-87
degrees. This will minimize the formation of standing waves and turbulence that could encroach
on the channel freeboard or otherwise reduce the capacity of the channel.
Hagers Weir Discharge Coefficient Equation. Hager's equation deals with three types of side
weirs: sharp-crested weir, broad-crested weir, and round-crested weir (Hager, 1987). Figure
8.43, Figure 8.44 and Figure 8.45 show the side view of these three types of weirs. In Figure
8.43, Figure 8.44 and Figure 8.45 water in the main channel flows perpendicular to the figure
view.
8-88
FIGURE 8.43
SHARP-CRESTED WEIR
(Hager, 1987)
FIGURE 8.44
BROAD-CRESTED WEIR
(Hager, 1987)
FIGURE 8.45
ROUND-CRESTED WEIR
(Hager, 1987)
8-89
The flow equation for the side weir can be expressed in the conventional weir equation as follows:
Q w = CLH
1.5
(8.22)
where:
3 ( 1 yh )
1 ( + S 0 ) --------------------yh Wh
0.5
0.5
(8.23)
where:
m =
hw
W h = ----------------Ht + hw
(8.24)
H + hw
y h = ----------------Ht + hw
(8.25)
where:
H t = Total head measured from the top of the weir crest, ft;
h w = Weir height, ft;
g = Acceleration due to gravity, 32.2 ft/sec2;
S 0 = Main channel bed slope, ft/ft;
= Main channel contraction angle in radians (see Figure 8.46).
8-90
FIGURE 8.46
MAIN CHANNEL CONTRACTION
2
C h = 1 ------------------------------4
H
t
9 1 + -----
b
(8.26)
H 2
22
------ -----t
81 r w
3
C h = ------- 1 + -------------------------2
1 Ht 2
1 + --- -----
2 rw
(8.27)
Channel Junctions
Special design considerations are needed for channel junctions as follows:
The design water surface elevations immediately upstream of the confluence should be
equal.
8-91
The angle of junction intersection should be less than 12 degrees (zero is preferred). The
centerline radius of any channel can not be less than 3 times the top-width at the water
surface.
The design depth of the main channel below the junction should be the same (or virtually
so) as the main channel upstream of the confluence.
For supercritical flow regime a momentum analysis as outlined in the Corps of Engineers
document EM 1110-2-1601 (USACE, 1994) must be undertaken. On a case by case
basis, model testing will be required.
Channels designed with Froude numbers between 0.9 and 1.13 will not be allowed.
Straight Inlet
Box Inlet
Side-Channel Inlet
8-92
Culvert Inlet
Drop Inlet
Normally, the flow must remain at supercritical through the length of the chute and into the channel or conduit downstream. Care must be exercised in the design to insure against an unwanted
hydraulic jump in the downstream channel or conduit. The analysis must include computation of
the energy gradient through the chute and in the downstream channel or conduit.
Bends
Structures are generally unnecessary in subcritical flow channels unless the bend is of small
radius. Structures for supercritical flows are complex and require careful hydraulic design to control the flow.
Bends are normally not used in supercritical flow channels because of the costs involved and the
hazards introduced. It is possible to utilize banking, easement curves, and diagonal sills (Knapp,
1951). Sometimes outside bank rollover structures might even be considered. All of these, however, are generally out of place in urban drainage works. Additional design guidelines for open
channel bends may be found in Hydraulic Design of Flood Control Channels (USACE, 1991).
When a bend is necessary, and it is not practical to first take the flow into subcritical flow, the
designer will generally conclude that the channel should be placed in the closed conduit for the
entire reach of the bend, and downstream far enough to eliminate the main oscillations. A model
test is usually required on such structures. Furthermore, the forces exerted on the structure are
large and must be analyzed.
The forces involved with hydraulic structures are large, and their analyses are often complex.
The forces created can cause substantial damage if provisions are not made for their control. In
bends, forces are usually larger than what is intuitively assumed. The momentum equation permits solution for the force acting upon the flow boundary at a bend.
F b = MV
(8.28)
where V represents the change in direction and/or magnitude of the velocity through the section
bend. The force due to pressure on the bend should also be calculated when conduits flow under
pressure.
P
2
P = --- ( V )
2
(8.29)
where P represents the pressure change caused by the difference in the squares of the velocities through the bend. The total exerted force on the bend by the water, the total of momentum
and pressure forces, must be counteracted by external forces. Allowable soil bearing should be
8-93
determined using soil tests if necessary. Forces which cannot be handled by conduit bearing on
the soil must be compensated for by additional thrust blocks or other structures.
The City of Albuquerque, New Mexico investigated the hydraulic effects of vehicle ramps and
flared side slopes in channels (Heggen, 1991).
Although the study is too long to be included in this manual, the final recommendations are consistent with other recommendations in this manual and can be summarized as follows:
1.
For subcritical flow, the hydraulic consequences of occasional access structures are
minor. For supercritical flow, the hydraulic consequences of channel cross sectional
changes can be major. Hydraulic jumps or oblique waves can jeopardize the entire channel.
2.
3.
The Froude number approaching downstream ramps should not exceed 2.2 for a onesided configuration.
4.
5.
The Froude number approaching 3:1 flared sideslopes should not exceed 3.5 for a onesided configuration.
8-94
6.
The Froude number approaching a 6:1 flared sideslopes should not exceed 2.2 for a onesided configuration.
7.
8.
Upstream and downstream channel slopes are not a significant factor in performance.
9.
Ramps perform somewhat better than 6:1 flared sideslopes, but not as well as 3:1 flared
sideslopes.
As a general rule, access structures should be provided at the upstream and downstream side of
every culvert and street crossing. Access over or around drop structures also needs to be considered.
8-95
[ V g2 V a2]
H g = 1.5 ----------------------2g
(8.30)
TABLE 8.7
LOSS FACTORS FOR APPROACH ANGLE SKEWED TO TRASHRACK
DERIVED FROM Metcalf and Eddy (1972)
Approach Angle (degrees)
Loss Factor
1.0
20
1.7
40
3.0
60
6.0
For trashracks in detention basins, reservoirs, dams or areas where the flow into the outlet conduit is ponded, the headloss shall be computed by Equation (8.31) (Metcalf and Eddy, 1972):
V
H g = K t -----n2g
(8.31)
an an 2
K t = 1.45 0.45 ----- -----
a g a g
(8.32)
A plugging factor of 50 percent shall be used for all trashrack analysis. For maximum headloss,
1/2 of the net area between the bars shall be considered blocked. This will result in twice the
velocity through the trashrack. For detention basin and dam outlet works analysis, trashrack
headloss shall be calculated for the plugged condition as well as the unplugged condition.
The trashrack/access barrier assembly shall be hinged or removable to allow access to the outlet
construction. The screen shall be fabricated of a minimum of 1/2 inch x 2 inch flat steel bars or
larger designed to withstand the hydrostatic load resulting from the 100-year design ponding with
screen openings blocked. Attachment points shall be cast in the headwall concrete and anchored
by substantial anchor bolts. Shear pins shall be in 1/8 inch, 3/16 inch or 1/4 inch rods depending
on the size of the barrier involved. The largest size possible shall be utilized The rack assembly
shall be galvanized steel or steel with a protective coating suitable for exposure to sunlight, as
well as submerged conditions. An anti-vortex device should be included with the trashrack
design if vortices are anticipated which could affect hydraulic efficiency and cause erosion of
adjacent earth slopes.
8-96
Groins
Structures located along and protruding from the banks of a channel for purposes of training flow
away from the bank, reducing velocities, or reducing erosion are termed groins herein. Other
terms used for structures meeting this definition are spurs, hardpoints, and dikes. In a natural setting, these structures are often deployed at the outside of bends in a channel to reduce bank erosion and redirect higher velocities towards the center of the channel where higher velocities are
better tolerated due to armoring. In the absence of armoring, these structures merely relocate the
area subject to continued erosion (see Chapter 11 for further discussions on sedimentation).
Hydraulically, groins create greater depths of flow upstream of the structure in subcritical flow
conditions and flatten the energy grade line. Acting like a constriction, the energy grade line is
steeper at the structure while backwater eddies are created immediately downstream of the
structure unless they are drowned out by overtopping flow. These structures tend to be designed
to train low to moderate flows without overtopping. Higher flood flows usually overtop the structure. Under certain circumstances, groins deployed on both sides of an engineered channel can
be used to flatten the energy grade line, thereby allowing a steeper channel slope. Under all
applications, the appropriate hydraulic analysis should be employed to evaluate velocities under
the range of conditions expected or required to meet regulatory requirements. Erosion protection is often required at the groin and downstream of the groin.
Groins may be made of many different materials including riprap, gabions, piling (wood and
steel), rock and earth filled cribs. Depending upon the entity responsible for maintenance, the
designer should verify acceptable materials for the application at hand.
Guide Dikes
These structures are deployed upstream of bridge abutments and serve to transition flow into the
bridge from the floodplain. Also called guide banks, these structures have been found to minimize scour of the abutments and piers. Here, the scour is relocated to the head of the guide dike,
thereby offering hydraulic efficiency and scour protection to the bridge structure. Design procedures for guide banks are enumerated in Bridge Scour and Stream Instability Countermeasures
(USDOT, 2001).
8-97
8.7
SAFETY
Hydraulic structures constructed in Maricopa County will usually be subject to public access.
Designs for hydraulic structures must address the issue of safety. First, signage must be provided to identify the potential hazard of flooding or dangerous flow measures to the public. Second, appropriate measures must be designed to keep the public away from hazardous locations.
For example, vertical drop structures should not exceed 2.5 feet in height with 6-foot horizontal
aprons, and adequate fencing or railings must be provided along all other walls, such as wing
walls or training walls.
Additional considerations for safety are discussed in the introduction to this manual (Chapter 1).
8-98
8.8
8-99
Material selection and landscape design can provide visual character and create interesting
spaces in and around hydraulic structures.
Materials
A variety of materials and finishes are available for use in hydraulic structures. Concrete color
additions, exposed aggregates and form liners can be used to create visual interest to otherwise
stark walls. The location of expansion and control joints in combination with reveals can be used
to create effective design detailing of headwalls and abutments. Rock and vegetation can be
used for bank stability and erosion protection around structures to provide visual contrast and
diversity, and spatial character.
8-100
8.9
REFERENCES
8-101
McLaughlin Water Engineers, Ltd., 1986, Evaluation of and Design Recommendations for Drop
Structures in the Denver Metropolitan Area, prepared for the Urban Drainage and Flood
Control District, Denver, Colorado.
Metcalf and Eddy, 1972, Wastewater Engineering, McGraw-Hill, New York.
Peterka, A.J., 1984, Hydraulic Design of Stilling Basins and Energy Dissipators, Engineering
Monograph No. 25, United States Department of the Interior, Bureau of Reclamation.
Rhone, T.J., 1977, Baffled Apron as Spillway Energy Dissipator, American Society of Civil Engineers Journal of Hydraulics, No. HY12.
Searcy, James K., 1967. "Use of Riprap for Bank Protection," Federal Highway Administration,
Washington, D.C., pp. 43.
Simon, A.L., 1981, Practical Hydraulics, Jon Wiley & Sons, New York, N.Y.
Simons, D.B., Stevens, M.A., and Watts, F.J., 1970, Flood Protection at Culvert Outlets, Colorado State University, Fort Collins, Colorado, CER 69-70, DBS-MAS-FJW4.
Smith, C.D., 1975, Cobble Lined Structures, Canadian Journal of Civil Engineering, Volume 2.
Smith, C.D., and Strang, D. K., 1967, Scour in Stone Beds, Proceedings of 12th Congress of
the International Association for Hydraulic Research.
Stevens, Michael A., 1981, Hydraulic Design Criteria for Riprapped Chutes and Vertical Drop
Structures, prepared for Urban Drainage and Flood Control District, Denver, Colorado.
Stevens, M.A., Simons, D.B. and Lewis, G.L., 1976, Safety Factors for Riprap Protection,
American Society of Civil Engineers Journal of Hydraulic Engineering, Paper No. 12115,
HY5 pp. 637-655.
U.S. Army Corps of Engineers (USACE), 1991, Hydraulic Design of Flood Control Channels.
, 1994, Hydraulic Design of Flood Control Channels Change 1 ENG 4794-R, Engineering
Manual 1110-2-1601.
, 2008, HEC-RAS River Analysis System, Hydraulic Reference Manual.
U.S. Department of Agriculture, Soil Conservation Service (SCS), 1976, Chute Spillways, Section 14, SCS Engineering Handbook.
U.S. Department of the Interior, Bureau of Reclamation (USBR), 1974, Design of Small Canal
Structures.
, 1976, Design of Gravity Dams.
, 1977, Design of Small Dams, p 341-342.
, 1987, Design of Small Dams, p353, p366-367, p453-470.
8-102
, 2006, Research state-of-the-art and needs for hydraulic design of stepped spillways. U.S.
Department of the Interior. Hydraulic Laboratory Report HL-2005-06.
U.S. Department of Transportation (USDOT) Federal Highway Administration, 1983, Hydraulic
Design of Energy Dissipators for Culverts and Channels, Hydraulic Engineering Circular
No. 14. [USDOT Hydraulics WEB Site]
, 1988, Design of Roadside Drainage Channels with Flexible Linings, Hydraulic Engineering Circular No. 15, Publication No. FHWA-IP-87-7.
, 1989, "Design of Riprap Revetment," Hydraulic Engineering Circular No. 11 (HEC 11),
FHWA-IP-89-016, Washington, D.C.
, 2001, Bridge Scour and Stream Instability Countermeasures, Hydraulic Engineering Circular No. 23, FHWA NHI-01-003.
, 2006, Hydraulic Design of Energy Dissipators for Culverts and Channels, Hydraulic Engineering Circular No. 14, 3rd Edition. [USDOT Hydraulics WEB Site]
U.S. Navy, 1982, Design Manual, Foundations and Earth Structures, Naval Facilities Engineering Command, NAVFAC DM-7.2.
Urban Drainage and Flood Control District (UDFCD), Revised 2008, Drainage Criteria Manual,
Project Consultant Wright Water Engineers.
8-103
Posey, Chesley J., 1955, Flood-Erosion Protection for Highway Fills, with discussion by Gerald
H. Matthes, Emory W. Lane, Carl F. Izzard, Joseph N. Bradley, Carl E. Kindsvater, and Parley R. Nutey, ASCE.
Reese, Anderson J., 1986, Nomographic Riprap Design, Hydraulics Laboratory, U.S. Department of the Army.
Reeves, Gary N., 1985, Planned Overtopping of Embankments Using Roller Compacted Concrete, Hydraulics and Hydrology in the Small Computer Age, Volume 2, William R. Waldrop,
editor.
Richardson, E.V., Simons, D.B., and Lagasse, P.F., 2001, River Engineering for Highway
Encroachments, Highways in the River Environment, Hydraulic Design Series No. 6, U.S.
Department of Transportation, Federal Highway Administration. [USDOT Hydraulics WEB
Site
Sabol, George V., and Martinez, R.J., 1982, Energy Dissipator/Grade Control Structures for
Steep Channels, Phase II, Albuquerque Metropolitan Arroyo Flood Control Authority and
City of Albuquerque, Civil Engineering Department, New Mexico State University.
Shen, Hsieh Wen, Editor, 1971, River Mechanics, Vol. I and II, Colorado State University.
Shields, F. Douglas Jr., 1982, Environmental Features for Flood Control Channels, Water
Resources Bulletin, Vol. 18, No. 5.
Simons, D.B., 1983, Symposium on Erosion and Sedimentation, Ruh-Ming Li and Peter F.
Lagasse, Simons Li and Associates Inc., co-editors.
Urban Drainage and Flood Control District (UDFCD), 2001, Drainage Criteria Manual, Project
Consultant Wright Water Engineers.
U.S. Department of Agriculture, Soil Conservation Service, 1977, Design of Open Channels,
Technical Release No. 25.
, 1976, Hydraulic Design of Riprap Gradient Control Structures, Technical Release No. 59.
8-104
9 STORMWATER STORAGE
TABLE OF CONTENTS
9
STORMWATER STORAGE
9.1
SYMBOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-2
9.2
INTRODUCTION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-2
9.2.1
Interaction with Other Components of a Drainage System ......................... 9-3
9.2.2
Limitations on Use of Stormwater Storage Facilities................................... 9-3
9.3
DESIGN GUIDELINES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-4
9.3.1
Guidelines for Stormwater Storage Facilities .............................................. 9-5
9.3.2
Criteria for Special Stormwater Storage Methods ..................................... 9-21
9.3.3
Embankment Design Criteria .................................................................... 9-23
9.4
SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-26
9.5
OPERATION AND MAINTENANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-26
9.5.1
Access....................................................................................................... 9-27
9.5.2
Sediment Removal .................................................................................... 9-27
9.5.3
Repair of Eroded Slopes ........................................................................... 9-28
9.5.4
Weed Control ............................................................................................ 9-28
9.5.5
Maintenance of Low Flow Channels and Drainage Structures ................. 9-28
9.5.6
Landscape Maintenance ........................................................................... 9-29
9.5.7
Irrigation System Maintenance.................................................................. 9-29
9.5.8
Sign, Wall, and Fence Maintenance ......................................................... 9-29
9.6
MULTIPLE-USE CONCEPTS & AESTHETIC DESIGN GUIDELINES . . . . . . . . . . 9-30
9.6.1
Recreation Elements ................................................................................. 9-30
9.6.2
Stormwater Storage Facilities as Water Amenities ................................... 9-33
9.6.3
Urban Green Space .................................................................................. 9-33
9.6.4
Water Harvesting for Reuse or Recharge ................................................. 9-33
9.7
WATER QUALITY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-34
9.7.1
Introduction ............................................................................................... 9-34
9.7.2
Major Pollutants and Their Sources .......................................................... 9-34
9.7.3
Role of Stormwater Storage Facilities in Water Quality Control................ 9-35
9.7.4
Method for Control of Sedimentation ........................................................ 9-36
9.8
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-38
9.8.1
Cited in Text .............................................................................................. 9-38
9.8.2
Relevant to Chapter .................................................................................. 9-38
9-1
9.1
SYMBOLS
9.2
INTRODUCTION
Stormwater storage facilities are man-made storage structures intended to mitigate the negative
impacts of urbanization on storm drainage, which include
Reduction of natural vegetation, which, in a natural state, reduces storm runoff through
the process of increased infiltration and interception.
9-2
intended to drain the basin within 36 hours. The design intent for retention basins is to capture
the runoff volume for the design storm frequency and duration.
This chapter presents the engineering methodologies and details associated with the planning,
analysis and design of detention and retention facilities. The guidelines herein are intended to
achieve the following goals:
1.
Design of stormwater storage facilities that satisfy ordinance provisions with regard to
hydraulic function and maintainability;
2.
Design of stormwater storage facilities that are amenities, and, where possible, incorporate multiple-use concepts; and
3.
Design of facilities that will not jeopardize the quality of surface water or groundwater
resources.
9-3
Residential developments (recorded subdivisions) shall not provide for nor rely on single-lot, onsite stormwater storage, and the design of common facilities shall not assume any individual lot
on-site storage, unless approved by the jurisdictional agency. Developments with Homeowner's
Associations will locate its facilities in private drainage tracts or in public sites dedicated by the
developer, in accordance with the jurisdictional agencys requirements. The Homeowners Association will maintain the private facilities, and the jurisdictional agency will usually maintain the
public tracts. Common storage facilities for single family developments without a Homeowner's
Association and with public streets will have maintenance provisions determined by the jurisdictional agency. The number and location of storage facilities within a development are to be
approved by the jurisdictional agency. Dedication to the public may require the inclusion of recreational facilities or other features deemed necessary by the jurisdictional agency.
Single lot, non-residential developments that are not served by a public stormwater storage facility will provide the required storage on the lot itself and outside the right-of-way area, regardless
of lot size. Maintenance shall be provided for by the property owner.
Single lot, residential parcels that are not a part of a recorded subdivision, such as lots created by
parcel splits and minor land divisions, will also provide the required storage on the lot itself and
outside the right-of-way area, if it is demonstrated that a common basin with adjacent parcels is
not practical. Each jurisdictional agency may establish lot size requirements governing the application of this requirement, but in all cases the residential lots smaller than 1 acre in size shall provide the required storage.
Regional Stormwater Storage Facilities - Regional detention/retention facilities are large storage facilities located at strategic sites within a watershed to provide control of runoff. The
regional approach is best suited to watersheds that were primarily developed prior to retention
requirements instituted in Maricopa County in the late 1980s. The advantage of this type of facility is that the siting and design of regional storage facilities is normally incorporated as part of an
overall drainage master plan. Thus, alternative siting combinations and their respective hydraulic
routing effects can be investigated. Storage alternatives can be evaluated with other factors (that
is, conveyance system, land and maintenance costs), to arrive at an optimal solution to alleviate
flooding problems within the drainage basin.
9.3
DESIGN GUIDELINES
This section presents certain guidelines, procedures and criteria to be used in the analysis and
design of detention and retention facilities. Because specific policies and criteria vary, the
designer must contact the jurisdictional agency for the area in which the basin will be located
before beginning design.
9-4
Design Frequency
All stormwater storage facilities incorporated within new developments will be designed to retain
the peak flow and volume of runoff from the design storm event. The duration and intensity of the
design storm event is designated by the jurisdictional agency for the given area under study. In
the special case of when a detention only facility is allowed, the requirement to retain the design
storm runoff volume may be waived. However, the peak discharge requirement must still be met,
and the effects of using a detention only facility on more frequent events must be determined.
In jurisdictions where multi-frequency control is required, the design will be prepared to regulate
the peak discharge rates for one or more storm events in addition to the design storm. Specific
multi-frequency events shall be verified with the appropriate jurisdiction, but it is recommended
that the 2-, 10- and 100-year events be verified, as a minimum.
Hydrology
Procedures and criteria for development of inflow hydrographs for stormwater storage facilities
are described in the Drainage Design Manual for Maricopa County, Hydrology.
Volume Calculations For Retention Facilities - Some jurisdictional agencies have developed
simplified equations for determining the volume required for retention. The engineer should verify
the methodology for calculation of the required storage volume with the appropriate jurisdiction.
Where the rational method is approved for use, volume calculation should be done by applying
the following equation:
P
V = C ------ A
12
(9.1)
In the case of volume calculations for retention design, P equals the design storm depth in
inches. The 100-year, 2-hour depth for Maricopa County is shown in Figure 9.1. The amount of
rainfall for other frequencies and durations can be determined by using Section 2.2 of the Hydrology Manual.
9-5
FIGURE 9.1
ISOPLUVIAL 100-YEAR, 2-HOUR PRECIPITATION
9-6
Flood Routing - Routing methods are also acceptable to determine volume, particularly for
larger, regional basins. For a typical stormwater detention facility, there are three variables to be
considered in flood routing through the structure:
1.
2.
Outflow from the facility, which varies as a function of inflow and storage volume; and
3.
Storage, which is the result of the difference between the inflow and outflow for a period
of time or time interval.
FIGURE 9.2
FLOOD ROUTING (INFLOW AND OUTFLOW HYDROGRAPH)
Figure 9.2 illustrates the general relationship among the three variables that must be considered
for flood routing through a structure.
The outflow hydrograph from a proposed stormwater detention facility shall be determined using
the Storage Indication or Modified Puls method of flood routing. Other similar hydrologic routing methods may also be used, provided that the chosen method is first approved by the appropriate review agency. Numerous computer software programs such as HEC-1 (USACE, 1990)
have been developed for flood routing through detention facilities. Use of a particular computer
program should be approved by the appropriate jurisdictional agency prior to its application on a
particular project. If a computer program for flood/reservoir routing is intended to be used, documentation of the program shall be submitted to the appropriate review agency prior to commencing design. Non-tributary flows may not be routed through a detention facility unless specifically
approved by the jurisdictional agency. Off-site flows should not be routed through a stormwater
storage facility unless specifically approved by the appropriate jurisdictional agency.
Detention ponds in series (that is, when the discharge of one facility becomes the inflow of
another) are complex and require special consideration and design by a hydraulic engineer. If
such a system is unavoidable, the engineer must submit a hydrologic and hydraulic analysis
which demonstrates the system's adequacy. This analysis must incorporate the construction of
hydrographs for all inflow and outflow components, and rating curves for hydraulic structures.
9-7
9-8
Drain Time
The design of all stormwater storage facilities shall be such that the stored runoff is completely
discharged from the facility within 36 hours after the runoff event has ended. The draining of
stormwater storage facilities may be accomplished via in-situ percolation, bleeding off (low flow)
outlets, drywells, pump station, or a combination thereof.
Lining/Surface Treatment
In keeping with the goal of stormwater storage facilities as amenities that incorporate multiple
use concepts where possible, grass and/or landscape plantings are preferred surface treatments. As a general rule, grass and plant species used for landscape development and revegetation should be native to Maricopa County. A registered landscape architect should prepare the
landscape design with consideration toward use of plant species appropriate for the level and frequency of inundation of the facility. Permanent irrigation systems are required for grass areas
and most types of basin revegetation and landscaping. However, use of native and drought tolerant species (including seeding) may only require a temporary system to obtain effective germination and establishment. Whether permanent or temporary, that portion of the irrigation system
within the flood zone must be designed to tolerate inundation and silt accumulations.
The use of inert materials is appropriate for stabilization and erosion control where steep slopes
are unavoidable, including along channels, at inflow points, at the outlet control structure and any
other location where flowing water may threaten stability. Use of these materials should be properly engineered (refer to Chapter 6) and should respond to aesthetic considerations. Inert materials for erosion control include:
River stone
Gabions
Designs that combine landscape planting with the use of inert materials are recommended. Voids
can be designed within the inert material to allow installation of plants. The result is a durable and
attractive method of protection.
9-9
of loose rock or other movable materials can only be made after careful consideration.
FIGURE 9.3
RECTANGULAR CONCRETE CHANNEL SECTION
(Adapted from: WRC Engineering, Inc. 1985)
9-10
If the flow capacity of an outlet pipe must be further reduced, an orifice plate may be attached, as
shown on Figure 9.5(a). The orifice plate must be constructed of heavy, galvanized steel and
9-11
attached by tamper-proof bolts. Other outlet configurations may be allowed provided they meet
the requirements of the permitted release rates at the required volume and include proper provisions for maintenance and reliability.
Primary outlet structures, particularly those controlling multiple storm events, are often special
design structures unique to specific site applications. Furthermore, consideration must be given
to structural adequacy and flotation under hydrostatic loads.
FIGURE 9.5
ORIFICE PLATE DETAIL
(Adapted from WRC Engineering, 1987)
Trashracks - Trashracks shall be provided to inlets of pipe and orifice outlet structures. See
Chapter 8 for hydraulic analysis guidelines and Chapter 1 for safety considerations.
Energy Dissipation at Outlet - Adequate energy dissipation measures shall be provided at the
downstream end of primary outlet structures. Such measures shall be designed to control local
scour at the pipe outlet and to reduce velocities to pre-development conditions prior to exiting
onto the downstream property.
Emergency Spillways - Emergency spillways are normally surface overflow weirs, channels, or
combinations thereof, provided for the safe overflow and routing of floodwaters under unusual
circumstances. Such situations include the blockage or malfunction of the primary outlet structure or the occurrence of a storm event larger than that for which the facility was designed. Consideration must be given to the layout and configuration of the emergency spillway so that excess
9-12
flow is safely released and conveyed without increasing flood hazards to adjacent properties and
in the same manner and direction as would have occurred under pre-development or historic
conditions. Emergency spillways must be designed to convey the unattenuated 100-year peak
discharge at non-erosive velocities. For criteria regarding design of emergency spillways for
embankments, refer to Section 9.3.3.
Low Flow/Low Level Outlets - For health and safety reasons, stormwater storage facilities must
drain within 36 hours for the design storm runoff volume. For stormwater facilities in a series, the
cumulative post storm drain time is 36 hours. In addition, the peak discharge from a low flow outlet shall be significantly less than the existing watershed peak discharge for retention facilities.
These guidelines form the basis for design. Compliance with NPDES requirements often dictate
a third criteria for low flow/low level outlets. Here, the outlet is often designed to retain the first
flush and/or the floating hydrocarbon pollutants. In this situation, undershot weirs or inverted
siphons may be used. See Section 9.7 for an additional discussion on water quality.
Subsurface Disposal
The primary methods of underground disposal of stormwater runoff at retention facilities are engineered basin floors and drywells. Infiltration rates of basin floors or drywells shall not be used in
determining outflow rates in flood-routing procedures.
Engineered Basin Floors - Analysis and design of the bottom of a retention facility intended for
subsurface disposal is detailed in Underground Disposal of Stormwater Runoff Design Guidelines Manual (USDOT, 1980); refer to that publication for specific design criteria.
Drywells - Drywells may be used for subsurface disposal of stormwater, if approved by the jurisdictional agency, and if criteria such as subsurface strata permeability, groundwater levels and
maintenance can be satisfactorily addressed. The main cause of drywell failure is clogging of the
transmission media (gravel) by silt and debris. Failure can be avoided by utilizing proper design
and installation guidelines, and by following recommended maintenance procedures. Figure 9.6
shows a typical drywell installation, while Figure 9.7 shows examples of surface treatments.
All drywells must be registered with the Arizona Department of Environmental Quality (ADEQ).
9-13
FIGURE 9.6
TYPICAL DRYWELL INSTALLATION
(McGuckin Drilling Inc., 1987)
9-14
FIGURE 9.7
TYPICAL DRYWELL SURFACE TREATMENTS
(McGuckin Drilling Inc., 1987)
9-15
The following list of general requirements and criteria shall be used in the design and construction of engineered basins and drywells (or other methods of subsurface disposal of stormwater).
In addition, the engineer is referred to specific policies and standards of the applicable jurisdictional agency.
Field investigations shall be performed and shall include soil borings and percolation tests
taken at the bottom of the proposed basin to obtain percolation rates for use in the design
of the stormwater storage facility. Procedures used should be one of the following two
methods, listed by order of preference:
1.
ASTM D 3385-03, Double Ring Infiltrometer. If the soils present are outside the
accepted range for application of ASTM D 3385-03, then method 2 shall be applied. Soils
outside the acceptable range for ASTM D3385-03 are typically very pervious or very
impervious with a saturated hydraulic conductivity greater than about 14 inches/hour or
less than about 0.0014 inches/hour. Very impervious soils that are outside the range of
applicability for ASTM D3385-03 are not suitable for stormwater percolation disposal system applications. Dry wells may be a better choice for these conditions. If there is a question regarding the applicability of this method for the soils at a particular site, ASTM D
3385-03 should be applied and the results checked against the acceptable range of values of hydrologic conductivity. ASTM D 3385-03 may also not be applicable for dry or stiff
soils that will fracture when the rings are installed, or gravels that do not allow penetration
by the rings.
2.
EPA Falling Head Percolation Test Procedure from Design Manual - Onsite
Wastewater Treatment and Disposal Systems (EPA, 1980).
A minimum of two (2) tests are required per retention basin. Refer to the Policies and
Standards manual of the jurisdictional entity for the type and total number of tests
required. The recommended testing frequency, based on the basin bottom area proposed for percolation, is listed in Table 9.1. Each test should include one soil log hole
and one percolation test. Each soil log boring hole should extend at least 10-feet below
the bottom of the proposed basin. A soil horizon log should be prepared for each boring
to obtain the approximate soil texture of each soil layer (horizon) observed and to identify
soil horizons that may impede percolation.
TABLE 9.1
MINIMUM QUANTITY OF SOIL LOG HOLE/PERCOLATION TESTS REQUIRED
9-16
TABLE 9.1
MINIMUM QUANTITY OF SOIL LOG HOLE/PERCOLATION TESTS REQUIRED
Retention Basin Bottom Area (Ap) (sf)
The tests should be distributed evenly throughout the retention basin using engineering judgment. For example, when 5 tests are required, the typical distribution assuming a square basin would be a test in each corner and one in the middle.
Field percolation test values should be reduced by a safety factor when designing any
percolation facility (Stahre and Urbonas, 1990). This is necessary because soils will tend
to clog with time, which has proven to be a significant cause for basin failure to drain
within 36-hours in Maricopa County. The de-rating factors for Method 2 (EPA, 1980)
should include negation of sidewall percolation and a higher degree of uncertainty in the
results when using this approach. Recommended de-rating factors are shown in Table
9.2. The selected percolation rate should then be de-rated using Equation (9.2). The
tests shall be performed by a testing laboratory, and the results sealed by a civil engineer,
licensed to practice in the State of Arizona. Stormwater disposal by percolation is not recommended if the percolation rate, after application of the de-rating factor, is less than 0.5
inches per hour. Stormwater disposal by percolation is also not recommended if groundwater or an impermeable layer is encountered within 4-feet below the bottom of the
basin.
P
P d = -----rDr
(9.2)
Where Pd is the design percolation rate in inches/hour, Pr is the lowest measured percolation rate in inches/hour, and Dr is the de-rating factor.
Basin drain time is estimated by using Equation (9.3).
V
T d = -----------Pd
A p -----12
(9.3)
Where Td is the retention basin drain time in hours, Ap is the percolation area of the basin
bottom in acres, Pd is the design percolation rate in inches/hour, and V is the retention
basin design storage volume (100-year, 2-hour) in acre-feet.
9-17
Only the bottom area of the retention basin may be used for computing the basin drain
time by infiltration/percolation. The side slope areas shall not be used in the drain time
computation unless the basin configuration is "V" shape without a flat bottom. For a "V"
shaped basin without a flat bottom, the bottom area assumed available for percolation is
recommended to be computed using Equation (9.4).
( D 3 ) ( SS L + SS R )L
A p = ------------------------------------------------43, 560
(9.4)
Where D is the design ponding depth in feet, L is the length of the basin in feet, and SSL
and SSR are the left and right basin side slopes in feet horizontal per foot vertical.
TABLE 9.2
RECOMMENDED MINIMUM PERCOLATION DE-RATING FACTORS
(FOR RETENTION BASIN DESIGN)
De-Rating Factor
Method 2 (by test hole diameter)
Condition
Method 1
6-inch
8-inch
10-inch
12-inch
10
20
16
14
12
Drywells shall be designed, operated, and maintained in conformance with the most current ADEQ guidelines. EPA (1980) procedures may be used for estimating initial design
percolation rates. The final design rate is recommended to be based on a constant-head
percolation test performed on each completed well at the site. Refer to the Policies and
Standards of the jurisdictional agency for design standards for drywells. The test results
for each well should be de-rated based on the in-situ soil conditions. A de-rating factor of
2 is recommended for coarse-grained soils (cobbles, gravels and sands). A de-rating factor of 3 is recommended for fine grained soils (silts and loams). A de-rating factor of 5 is
recommended for clay soils. These de-rating factors are required to compensate for deterioration of the percolation capacity over time in addition to providing a factor of safety for
silting and grate obstruction. The accepted design disposal rate for a dry well, after application of the de-rating factor, should not be less than 0.1 cfs per well. The maximum
allowable rate, after application of the de-rating factor, is not recommended to exceed 0.5
9-18
cfs per drywell for design purposes. It is the owner's, or owner's representatives', responsibility to clean and maintain each dry well to ensure that each remains in proper working
order. The regular maintenance schedule is not recommended to exceed 3-years. Drywells that cease to drain a retention basin with 36-hours should be replaced or refurbished by the owner or his representative. Maintenance requirements are to be written in
the CC&R's for subdivisions where dry wells are used to drain retention basins. In accordance with ADEQ requirements, the installation of any subsurface drainage structure
must be located into a permeable porous strata at least 10-feet above saturated soils and
100-feet away from any water supply well.
A test well shall be installed for any retention facility utilizing drywells for stormwater disposal. Upon approval of performance, adjusted as presented above, this test well may
then be used as one of the functioning drywells within the retention facility.
The design of a drywell must include provisions for trapping sediment within a settling
chamber. The system shall use a floating absorbent blanket or pillow to enhance the
removal of petroleum-based organics floating on the water. A hydrophobic petrochemical
absorbent with a minimum capacity of 100 ounces per chamber is recommended. This
measure will significantly increase both the efficiency and useful life of the well. Once a
year, at a minimum, the settling chamber should be inspected, and it should also be
inspected after any major inflow to the drywell. Sediment shall be removed from the
chamber at such time that approximately 15 to 20% of the original volume of the chamber
is filled. All sediment removed from a settling chamber shall be disposed of either at an
authorized sanitary landfill or at any other suitable location approved by the governing
jurisdiction.
Infiltration rates of drywells shall not be used in determining outflow rates in flood-routing
procedures. Any retention facility which relies solely upon infiltration as its method of
drainage shall be sized to contain the maximum storage volume that would be required
without considering an outflow rate.
Disposal methods using infiltration shall not be permitted for stormwater runoff which carries significant concentrations of sediment. This includes stormwater runoff flowing
through sand bed channels, as well as stormwater runoff emanating from a predominantly
natural watershed.
During site development, all drywells shall be securely covered with filter cloth or other
material to prevent the introduction of excessive sediment into the settling chamber.
Retention of runoff emanating from industrial developments and infiltration of runoff to the
subsurface will be handled on a case-by-case basis by the appropriate reviewing agency
subject to water quality concerns.
Runoff stored in a retention facility shall be completely drained from the facility within a
maximum time period of 36 hours after the runoff event has ended. Drywells that cease to
drain a facility within the 36-hour period shall be replaced by the owner with new ones,
unless an alternate method of drainage is available.
9-19
Permanent Pools
Certain jurisdictions permit the design of a stormwater storage facility that incorporates a
permanent pool for aesthetic purposes. The engineer should contact the appropriate
jurisdiction for specific criteria and regulations regarding such facilities. General considerations for facilities incorporating permanent pools are listed below:
Flood storage volume shall be maintained above the level of the permanent pool. Provision for draining the full depth of the pond shall be included at the outlet structure.
Maintenance of a minimum water level should be provided either by the inflow from the
watershed, and/or by augmentation from other sources during prolonged dry periods and
by the capability of the bottom of the facility to retain water. Seepage and evaporation
losses shall be considered.
Maintain water quality and minimize algae growth by designing for sufficient minimum
depth and incorporating use of recirculation and aeration measures.
Consider public safety as primary in the design of all features related to the permanent
pool.
Resolve permanent pool water depth issues versus safety needs; a 3-foot depth at
shoreline required to limit pond edge vegetation growth exceeds the recommended
pond edge depth (1.5 to 2.0 feet). Therefore, other safety measures must be considered (see Section 9.4).
The design should consider measures to minimize sediment inflow to the pond. Once
sediment has entered the permanent pond, then removal can be expensive and may
require draining the pond. Erosion should ideally be controlled at the source or by mitigation measures along the incoming channel. However, if such measures are not feasible, a
9-20
sediment trap should be designed at the pond inflow location to intercept the majority of
the incoming sediment and to facilitate removal (see Section 9.7.4).
If the stormwater storage facility and permanent pool are created by a retaining structure,
such as an earth embankment, then the design guidelines for embankments shall be followed, with particular emphasis on seepage control and embankment stability (see Section 9.3.3).
Potential impacts downstream shall be considered. The designer should be aware that an
impoundment may improve, worsen or maintain existing downstream flow characteristics,
and that any changes, even apparent improvements, may be viewed as infringements of
downstream riparian rights.
Since a permanent pool is most often desired for creation of a focal amenity for a development, it is appropriate that a registered landscape architect work in conjunction with the
engineer to achieve an aesthetic design with consideration of costs of construction and
maintenance.
Underground Storage
This type of storage involves the construction of underground tanks, pipes, or vaults, which
accept stormwater runoff by means of inlets and storm drain pipes. Due to the high cost of this
type of installation, it is generally limited to high-density developments, where surface storage is
not feasible due either to the scarcity or high cost of land, or both.
Underground storage facilities must be provided with some method of outfall (that is, gravity
drains, pumps, or infiltration). In all cases, manholes (or some other means of access to the
underground storage facilities) must be provided for maintenance purposes.
9-21
Conveyance Storage
During the period that channels and floodplains are filling with runoff, the stormwater is being
stored in transient form. This type of storage is known as conveyance storage. Construction of
slow velocity channels with large cross sectional areas assist in the accomplishment of such storage. Conveyance storage systems are usually feasible only on large projects, and require
detailed hydrologic modeling for analysis.
9-22
9-23
FIGURE 9.8
TYPICAL SECTION OF A STORMWATER STORAGE FACILITY EMBANKMENT DAM
Emergency Spillway
All embankments for stormwater storage facilities shall incorporate an emergency overflow spill-
1. Hydraulic height is defined herein as the vertical distance from the lowest natural ground at the
toe of the slope to the water surface of the unattenuated 100 year inflow flowing over the spillway or emergency overflow area.
9-24
way for the safe overflow and routing of floodwaters under unusual circumstances1. Such conditions include the blockage or malfunction of the primary outlet structure or the occurrence of a
storm event larger than that for which the facility was designed. Floodwaters that might otherwise
overtop the embankment shall exit the facility via the emergency spillway and flow downstream
out of the project property in the same manner and direction as would have occurred under
pre-development or historic conditions.
The design of emergency spillways shall incorporate adequate erosion control and energy dissipation measures. Due to the high hazard potential of embankments, the minimum design standard for emergency spillways for embankments not regulated by ADWR shall be as indicated in
Table 9.3. Spillway design standards for jurisdictional dams and total freeboard and residual freeboard dimensions shall conform to the applicable ADWR design requirements.
TABLE 9.3
NON-REGULATORY EMERGENCY SPILLWAY DESIGN CAPACITY REQUIREMENTS
(for an Embankment that is Not Regulated by ADWR)
Dam Height
H < 6 ft.
Seepage
There are basically two categories of seepage considerations in embankment dam design. The
primary concern is that seepage does not adversely affect the integrity or stability of the dam.
The other category, water storage loss, is something the owner is usually most concerned about.
This category relates to design of additional seepage control measures as required to maintain a
permanent pool for reuse (water harvesting), or aesthetic or recreational purposes. Analyses
shall be conducted in the following areas at a minimum, to address seepage.
Foundation - The flow of water through a pervious foundation produces seepage forces as a
result of the friction between the percolating water and the soil medium. As the water percolates
upward at the toe of the embankment, the seepage forces lift the soil by reducing its effective
weight. In certain cases, this piping of the foundation soil can result in the failure of an embankment. A very common approach used is to excavate a cutoff trench into the foundation strata,
1.
Generally, these are designed as a broad crested weir (see Chapter 8, Hydraulic Structures).
9-25
typically into an impervious layer. The trench is then carefully backfilled with relatively impervious
material.
Embankment - Seepage through an embankment will occur, even with the tightest materials. On
the upstream side of the dam, the embankment soils will reflect a water level equal to the
impounded water level. As the water seeps through the dam, its pressure reduces and the water
level drops. Design of the embankment should be such that seepage at the downstream toe
occurs with no residual pressure. If the seepage were excessive, or were to emerge at an
unplanned higher location, then erosion could begin at the discharge point and rapidly remove
materials from within the embankment. Toe drains are typically designed to intercept the planned
seepage flow, preventing nuisance conditions and enhancing slope stability.
Slope Stability - Combined with seepage analysis, slope stability analysis is critical. The forces
pushing a mass of soil are analyzed with respect to the force resisting that movement. A related
problem is slope stability during conditions of rapid change. A common concern is during a rapid
drawdown, such as when operational problems with outlet works or seepage occur. With such
operational problems, pressures in the soil may cause the slopes to fail during drawdown.
Piping along Boundary Conditions - Wherever there are boundary conditions, such as along
an outlet conduit, spillway wall, cutoff trench or more subtle situations (such as layers of fill that
have been rolled to a smooth hard surface), there is the potential of creating a more direct route
for piping. The water flows at a higher erosive rate because it has a shorter, more efficient route.
The technique that is often used along conduits and walls is to construct cutoff collars which
extend laterally at intervals into the trench or embankment. When a much longer flow path is created, piping is minimized.
9.4
SAFETY
Public access and safety are inherent elements in the design of a detention or retention facility.
These elements are of primary importance, particularly in the case of multiple-use facilities where
public use is encouraged in areas subject to potential flooding. See Chapter 1 for a more thorough discussion on safety issues at stormwater facilities.
9.5
There are two major components to the maintenance of a stormwater storage facility. The first is
to design a facility that is maintainable, and the second is the physical work required to keep the
facility operating as designed and constructed. Maintenance of a stormwater storage facility falls
into two categories; scheduled and unscheduled. Scheduled maintenance includes those activities such as mowing, pruning, and trash removal. These activities can be predicted and can be
performed on a regular basis.
9-26
Unscheduled maintenance will involve the repair of facilities after storms and flooding. The frequency and scope of this type of maintenance cannot be predicted. Some examples of unscheduled maintenance are:
1. Embankment repair to keep erosion or rock riprap or earth fill sloughing from weakening
the dam structure.
2. Debris removal during and following storms.
3. Inlet and outlet channel repairs to halt erosion and maintain hydraulic capacity.
4. Inlet and outlet structure repair so that the facility will function as intended.
It is important that adequate funding be provided for unscheduled maintenance such that repairs
can be made immediately after flood or inundation damage occurs.
The following sections outline design considerations and recommendations which facilitate maintenance of stormwater storage facilities.
9.5.1 Access
Access roads for service and maintenance vehicles should be maintained to allow for equipment
access to the facility, whenever needed. Access control gates should be provided if restricted
access is required.
Design Recommendations
Access ramps into the facility shall be graded at 10 percent or less. Turning radii shall
be 50 feet or greater. Access ramps shall be designed for vehicle wheel capacities not
less than 12,000 lbs.
Service drives and gates shall be located in readily accessible, but inconspicuous,
locations so as to not encourage unauthorized use.
Design access control gates and adjacent areas shall be as secure as economically
feasible. Initial expenditures for access control can save significant costs in future
repairs.
Design Recommendations
Provide stilling basins or fore-basin collection points where most sediment will be
deposited (see Section 9.7.4).
Provide controlled vehicular access into the facility for trucks and front-end loaders.
9-27
Design Recommendations
Adequately protect slopes subject to moving water or foot traffic. Make detailed evaluation
of anticipated conditions and design protection accordingly. Use collector ditches for
on-site drainage at the top of slopes.
Design Recommendations
Plant or seed all non-paved areas in and around the basin to establish a vegetation cover.
Weed infestation is much less likely in areas which have a cover of desirable plants than
on disturbed or untreated areas.
Design basins to allow all areas, including slopes, to be accessible by equipment such as
flail mowers which can cut or remove weed growth.
Design Recommendations
Provide access to channels for front-end loaders and hauling equipment. Provide accessible areas, free of trees, to accommodate equipment movement.
Provide energy dissipators to prevent damage to the channel or drainage structures during high inflow conditions.
Design structures so that they will not collect debris, which could impact proper operation.
9-28
Design Recommendations
Select species with growth habits that minimize pruning and trimming or other maintenance requirements.
Specify and use the largest plants within budgetary constraints. This can minimize potential damage during initial growth seasons.
Design Recommendations
Specify and use equipment that will continue to operate when contaminated with sand or
other soil deposition. For example, large sprinkler head orifices, verses drip emitters, are
less likely to clog when lake or well water is used for irrigation.
Zone and layout system to avoid crossing channels where scour and erosion are likely to
occur.
Install control equipment (other than remote control valves) in areas not subject to stormwater inundation or vandalism.
Design Recommendations
Use signs that are made of aluminum or other durable material that does not corrode or
cannot be burned.
Secure signs to posts or standards with tamper-proof fasteners. Use posts or standards
that will not be damaged by anticipated flooding or vandalism.
9-29
Locate fences away from areas likely to collect debris and act as dams to incoming water
or water moving within the basin.
Design fences, gates, walls, etc., to minimize damage or accidental opening during normal area use or by flooding.
In non-critical areas, design fences with an open or clear-space at grade to allow shallow water and debris to flow or blow under them.
Design fences, such as backstops, with break-away or swing-away panels so flow is not
impeded through the basin.
9.6
The goal is to design stormwater storage facilities as amenities and, where possible, to incorporate multiple-use concepts. Flood control functions and other uses in stormwater storage facilities
are generally compatible. Rationale for multiple-use facilities includes decreased facility costs
and an increased community acceptance. Combining flood storage with recreation uses or other
community facilities on a single site decreases total costs for land acquisition and site development. The development of stormwater storage facilities as parks or urban green space increases
the acceptance by area residents and minimizes maintenance requirements and costs. If appropriately designed, use conflict is a minor concern. Stormwater storage facilities should be
designed as a focal point to encourage proper usage and maintenance.
The planning and development of facilities for multiple-use requires cooperation between the
engineer, a qualified landscape architect, intergovernmental agencies, community organizations,
park and recreation departments, and risk management agencies.
Appropriate uses for stormwater storage facilities include active and passive recreation, urban
green space, water amenities, water harvesting, and groundwater recharge. Use(s) in addition to
flood control should address specific community needs and be clearly identified before the facility
is designed.
9-30
Passive Recreation
Passive recreation generally involves individuals or small groups and a minimal amount of physical activity. Typically, passive recreation does not require large open spaces, and is, therefore,
appropriate for both large and small (< 10 acres) stormwater storage facilities. Passive recreational elements should be incorporated in portions of stormwater storage facilities having the
greatest potential flood risk and frequency.
Design Considerations
Several design considerations are fundamental to incorporating recreation elements within
stormwater storage facilities. Frequent inundation from low flows must be confined to areas that
will characteristically require only limited maintenance. Contouring within facilities is recommended to create internal elevation variations (or tiers) that have differing frequencies and
depths of inundation and differing flood risk. Suggested tiers may include: Lowest lying areas
semi-natural riparian zones, wetlands, habitat areas.
Lower elevated tiers passive recreation zones, picnic areas, open fields.
Upper elevated tiers court games, play areas, tot lots, pit games, parking facilities.
Areas elevated above 100-year flood level restrooms, habitable structures, and swimming pools.
In addition, internal drainage within stormwater detention facilities should provide for positive flow
across elevated tiers and to the basin floor to prevent nuisance-standing water within recreation
areas. Internal slopes should be flat enough to allow for mowing of turf areas and to allow for
other routine recreation related maintenance activities. Hydraulic design components (inflow
structures, outflow structures, spillways, sediment basins, etc.) should be included as needed.
Figure 9.9 provides a generic site plan for recreation elements that might be incorporated into a
stormwater storage facility. Figure 9.10 depicts a typical cross section of the site plan.
9-31
FIGURE 9.9
STORMWATER STORAGE FACILITY RECREATION ELEMENTS
FIGURE 9.10
TYPICAL CROSS SECTION OF STORMWATER STORAGE FACILITY W/RECREATION ELEMENTS
9-32
9-33
appropriate for a surface storage system. Distribution of water is typically achieved by pumping
from the pond for irrigation.
A facility may be designed specifically to augment the groundwater aquifer. The facility should be
designed to maximize the surface contact area between the stored water and the soil, thus maximizing the potential for water to percolate through the subsurface to the groundwater table.
Potential siltation problems must be addressed by providing a settling basin at the inlet or by
other suitable measures.
Runoff water stored for recharge or reuse purposes should not occupy volume needed for
stormwater storage within the storage facility. Adequate volume for stormwater storage must be
provided at all times, in addition to the volume provided for harvesting water.
9.7
WATER QUALITY
9.7.1 Introduction
Urban runoff is distinguished from undeveloped area runoff in two principal ways: it typically
occurs at greater discharge rates and volumes, and it contains varying but commonly higher concentrations of toxic substances, bacteria, and dissolved organic matter. Stormwater storage facilities can play a significant role in mitigating the pollution problems associated with urban runoff.
9-34
complexes. Runoff from vehicular right-of-way (which accounts for over 20 percent of some
urban lands), will contain hydrocarbons, other organics, and a diminishingbut still significant
amount of lead. Fertilizers and pesticides are transported by runoff from residential and agricultural areas.
Using long, narrow basin configurations that is length to width ratios of 2:1 to 3:1, with
the length measured along a line between the inlet and outlet.
Constructing ponds with active wet storage and inactive flood storage. An example
of a dual-purpose detention facility is illustrated in Figure 9.11.
Using riser outflow structures instead of ground level pipes to maintain a slow-draining
pool encouraging infiltration. Here, undershot weirs or inverted siphons should be considered to keep floating pollutants from conveyance downstream.
Using underground tile drains for outlet discharge to provide soil filtration of the runoff.
Using wet rather than dry ponds will generally improve quiescent conditions, maximize infiltration, and provide a degree of biological treatment.
The function of water quality storage elements within a stormwater detention facility is to provide
for settlement of pollutants, thereby improving downstream water quality. Periodic removal and
proper disposal of accumulated sediments will be needed to prevent their accumulation from
reaching toxic levels. A program for occasional reworking and/or removal of accumulated sediments within stormwater detention facilities is essential.
9-35
FIGURE 9.11
STORAGE COMPONENTS OF A DUAL PURPOSE STORMWATER STORAGE FACILITY
2.
The length/width ratio of the sediment trap should be a minimum of 2:1, with the length
measured along a line between the inlet and outlet.
3.
The basin shape should be wedge-shaped, with the narrow end located at the inlet to the
basin (see Figure 9.12).
4.
Provisions for total drainage and accumulated sediment removal of the sediment trap
must be provided. Maintenance access should also be provided and designed to accommodate heavy trucks and other equipment necessary for removal of accumulated sediment.
9-36
FIGURE 9.12
SEDIMENT TRAP CONCEPT
(Pima County Department of Transportation and Flood Control District, 1986)
9-37
9.8
REFERENCES
9-38
Transportation Research Board, 1980, Synthesis No. 70, Design of Sedimentation Basins.
Urban Land Institute, 1975, Residential Stormwater Management: Objectives, Principles, and
Design Considerations, Washington, D.C.
Urbonas, B.R., 1985, Stormwater Detention Outlet Control Structures, American Society of Civil
Engineers.
U.S. Department of Interior, Bureau of Reclamation, 1987, Design of Small Dams, Third Edition.
U.S. Department of Agriculture, 1978, Soil Conservation Service, Stormwater Management
Pond Design Manual, Maryland Association of Soil Conservation Districts.
, 1972, SCS National Engineers Handbook, Section 4, Hydrology.
9-39
9-40
10 PUMP STATIONS
TABLE OF CONTENTS
10 PUMP STATIONS
10.1 SYMBOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-1
10.2 INTRODUCTION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-2
10.3 DESIGN CRITERIA. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-2
10.3.1 Design Frequency ..................................................................................... 10-2
10.3.2 Drainage of Basins and Ponding Areas .................................................... 10-2
10.3.3 Bleedoff Lines ........................................................................................... 10-2
10.3.4 Pump Station Design Requirements ......................................................... 10-3
10.3.5 Pump Station Facility Requirements ......................................................... 10-4
10.4 DISCUSSION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-4
10.4.1 Pump Selection Study ............................................................................... 10-4
10.4.2 System Analysis ........................................................................................ 10-5
10.4.3 Pump Types .............................................................................................. 10-7
10.4.4 Pump Selection ......................................................................................... 10-7
10.4.5 Piping and Valves ..................................................................................... 10-8
10.4.6 Location..................................................................................................... 10-8
10.4.7 Wet Well Design........................................................................................ 10-9
10.4.8 Pump Room or Drywell ............................................................................. 10-9
10.4.9 Pump Settings ......................................................................................... 10-10
10.4.10 Pump Controls ........................................................................................ 10-10
10.4.11 Electrical Power Supply .......................................................................... 10-10
10.4.12 Emergency Power Supply ....................................................................... 10-10
10.5 AIDS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-11
10.6 REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-12
10.1 SYMBOLS
The following symbols are used in equations in this chapter:
h
pipe length, ft
pipe diameter, ft
HL
minor loss, ft
10-1
Vw
tm
10.2 INTRODUCTION
The consideration of a pumping station as an alternative will occur when an area to be drained is
so low that construction of a gravity drain is not feasible. Pumping stations are used to drain
depressed sections of urban roadways and paved areas and for discharge of water from retention basins when other means of gravity drainage are not available.
The design of pumping stations involves many different disciplines and the design approach is
dependent on the size and purpose of the facility, and the consequences of system failure. This
chapter provides general requirements and guidelines for planning and analysis of pumping facilities. For a more rigorous discussion of the design of stormwater pump stations, refer to the Highway Stormwater Pump Station Design, HEC-24 (USDOT, 2001).
10-2
Discharge directly to a nearby storm drain system with a maximum discharge limited to
the available capacity of the system as approved by the City/County.
Discharge to the surface of a storm drain system if pumped water can be discharged
directly into a catch basin or other inlet.
Headloss calculations for the entire system, including maximum and minimum Total
Dynamic Head (TDH) and flow rate.
Net positive suction head (NPSH) and pump level settings for on, off and alarm positions.
10-3
Inflow and outflow hydrographs and accumulated inflow and outflow curves (mass flow
curves). The use of HEC-1 is not appropriate for the design of pumping stations. A realtime procedure which routes the design inflow hydrograph using pump on and off elevations and actual pump performance curves must be used.
Specifications for the model and type of pump(s) proposed including pump curves (single
pump and parallel operation). Overloading the pump anywhere on the pump curve is not
permitted.
10.4 DISCUSSION
10.4.1 Pump Selection Study
Information required for the pump selection study includes proposed station capacity and pertinent water surface elevations for maximum, average, and minimum flow conditions, points of discharge, proposed station locations and their soil conditions, proposed piping system and
pertinent information on terrain, location of utilities, and the proposed method of operation.
Possible requirements for future expansion must be considered in the planning. Expansion may
be accomplished by modification of the existing units (such as increasing the pump impeller
diameter), by adding pumps or by replacement of the original pumps. The last alternative is the
least desirable one as it would entail considerable alteration in the facility. Allowances for any of
the alternatives should be made in the original design, as should the provision of a large enough
motor if the pump impeller diameter is to be increased at a later time or the provision of space
and foundation size for an additional pump along with proper sizing of piping.
10-4
Pipe friction losses are calculated by the Mannings equation. For this calculation the equation
may be expressed as follows:
h = 2.87 n 2
LV 2
D4 3
(10.1)
where h is the head loss (ft), L is the pipe length (ft), D is the pipe diameter (ft), V is the flow
velocity (ft/sec) and n is the Mannings roughness coefficient. Commonly used values of n range
from 0.010 to 0.041. Wherever possible, local experience with different pipe materials should be
used in choosing a value of n.
Minor losses are most often expressed as:
10-5
HL =
(10.2)
KV 2
2g
where HL is the head loss (ft), K is a coefficient for the particular fitting and V2/2g is the velocity
head (ft) in the pipe. Alternatively, minor losses may be expressed as equivalent length of pipe.
Static head is the difference in elevation between the water surface in the wet well and that at the
discharge point. Storm water pumping systems are usually designed to discharge into a channel,
conduit or receiving body at atmospheric pressure; in this case, the appropriate elevation to use
is the centerline elevation of the effluent pipe (see Figure 10.2). Since the level in the wet well
may vary, system head curves for maximum and minimum static heads are usually plotted.
FIGURE 10.2
TOTAL STATIC HEAD
(a) Intake below pump centerline; (b) intake above pump centerline
(Clark et al., 1977)
The analysis proceeds with the plotting of the head-discharge curve for the selected pump(s).
Intersection of the pump curve with a system head curve represents an operating point of the
pump under the assumed conditions of static head and head loss. Efficiency and input power
curve should be also plotted. The operating point (see Figure 10.3) should be at or near to the
best efficiency point for the selected pump(s). It is not only desirable that the pump operate efficiently from the standpoint of power consumption, but also it has been found that pumps operating at the best efficiency point do so more quietly and with less wear than otherwise, resulting in
lower maintenance costs.
10-6
FIGURE 10.3
PUMP OPERATING POINT IN A GIVEN PIPING SYSTEM
(ASCE, 1975)
10-7
Pump speeds used in stormwater pumping are usually limited to 1,750 rpm to minimize maintenance problems and provide greater reliability. Generally, constant speed control is used.
10.4.6 Location
The following points related to the location of a pumping station should be taken into account:
Soil conditions at proposed site and information on groundwater levels, particularly maximum heights.
10-8
t=
Vw
V
+ w
PQ Q
(10.3)
where t is the cycling time in minutes, P is the pumping rate in gallons per minute, Q is the inflow
in gallons per minute and V is the wet well volume in gallons, between the levels of the on and off
controls. Then, the required wet well volume for minimum cycling time, tm is:
Vw =
tm P
4
(10.4)
(10.5)
If two pumps are used alternately, the cycling time is increased by a factor of two.
Other details of wet well design which should be considered are the following:
Access to the wet well should be from the outside and means of ventilation should be provided.
Divided wet wells should be provided for larger pumping stations so that one part may be
used while the other is shut down.
10-9
between each pump discharge casing. The pump room should be adequately and safely lighted
and ventilated. Floor drainage should be provided. Openings for removing equipment should provide ample space for so doing.
Sufficient submergence of the suction inlet so that air is not drawn into the pump by vortexes
Priming or the need for a centrifugal pump to be filled with water when started
For dry pit pumps it is recommended that the high point of the casing be set below the minimum
water level in the wet well to ensure proper priming.
10-10
applies to fuel storage as well. Proper exhaust ventilation must be planned. The need for emergency power supply will be considered on a case by case basis and will be dependent upon the
threat to public health and welfare.
10.5 AIDS
TABLE 10.1
DESIGN CHECKLIST FOR PUMP STATIONS
General
Initial Data
Contributing Drainage Basin
Location of Outfall
Capacity of Outfall
Probable Growth in the Contributing Basin
Inflow Hydrographs
Possible Components
Source of Power (primary and emergency)
Pumps
Intakes and Catch Basins
Controls
Storage
Debris Handling
Potable Water Supply
Testing
Hoisting Equipment
Ventilation
Control of Hazardous Materials
Hydrology
Economic and Alternative Analysis
Designation of Significantly Different Concepts
Hydrologic and Hydraulic Detailing of Alternatives
Cost Evaluation
Extreme Event Evaluation of Components and Alternatives
Environmental Considerations
Documentation and Comprehensive Evaluation
10-11
TABLE 10.1
DESIGN CHECKLIST FOR PUMP STATIONS (CONTINUED)
Hydraulic Analysis
Mass Curve Routing
Outflow Hydrograph
Pump Characteristics
Pipe Losses
Miscellaneous Losses
Sediment Transport
Additional Considerations
10.6 REFERENCES
American Society of Civil Engineers (ASCE), 1975, Pipeline Design For Water and Wastewater.
Clark, John W., Viessman, Warren, and Hammer, Mark J., 1977, Water Supply and Pollution
Control, Third Edition, Harper & Row.
U.S. Department of Transportation (USDOT), Federal Highway Administration, 2001, Highway
Stormwater Pump Station Design, Hydraulic Engineering Circular No. 24, Publication No.
FHWA-NHI-01-007, Washington, DC. [USDOT Hydraulics WEB Site]
10-12
10
Hydraulics: Sedimentation
11 SEDIMENTATION
TABLE OF CONTENTS
11 SEDIMENTATION
11.1 DEFINITIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-3
11.2 INTRODUCTION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-5
11.3 SEDIMENTATION PROBLEMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-7
11.4 SOLUTIONS TO SEDIMENTATION PROBLEMS . . . . . . . . . . . . . . . . . . . . . . . . . 11-9
11.5 FUNDAMENTALS FOR ALLUVIAL CHANNELS . . . . . . . . . . . . . . . . . . . . . . . . . 11-11
11.5.1 Channel Patterns and Sinuosity .............................................................. 11-11
11.5.2 Bed Forms............................................................................................... 11-12
11.5.3 Regime Theory........................................................................................ 11-15
11.5.4 Equilibrium Concept and Channel Design............................................... 11-16
11.5.5 Equilibrium Concept Challenges in Arid and Semiarid Regions.............. 11-18
11.5.6 Channel Bed Scour and Deposition ........................................................ 11-20
11.5.7 Channel Lateral Migration, Meandering, and Bank Erosion.................... 11-21
11.5.8 Headcut Migration ................................................................................... 11-25
11.5.9 Sand and Gravel Mining.......................................................................... 11-28
11.6 FUNDAMENTALS FOR SEDIMENT TRANSPORT . . . . . . . . . . . . . . . . . . . . . . . 11-35
11.6.1 Sediment Properties................................................................................ 11-35
11.6.2 Incipient Motion ....................................................................................... 11-59
11.6.3 Armoring.................................................................................................. 11-60
11.6.4 Sediment Bulking .................................................................................... 11-61
11.6.5 Sediment Transport Functions ................................................................ 11-62
11.7 WATERSHED SEDIMENT YIELD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-63
11.7.1 Introduction ............................................................................................ 11-63
11.7.2 Sediment Yield Data ............................................................................... 11-65
11.7.3 Analytic Methods to Estimate Sediment Yield......................................... 11-69
11.8 ESTIMATION OF SCOUR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-83
11.8.1 Introduction ............................................................................................. 11-83
11.8.2 Total Scour .............................................................................................. 11-84
11.9 ESTIMATING LATERAL-EROSION HAZARD ZONES . . . . . . . . . . . . . . . . . . . 11-122
11.9.1 Straight Channel Reach (historical aerial photos available).................. 11-125
11.9.2 Straight Channel Reach (historical aerial photos not available)............ 11-126
11.9.3 Channel Located Between Upstream and Downstream Bends ............ 11-127
11.9.4 Straight Channel Reach Upstream and Downstream of a Bend ........... 11-127
11.9.5 Application Limitations and Design Implications ................................... 11-129
11.9.6 Sand and Gravel Mining Operation Exception ...................................... 11-130
11.10 SUMMARY AND CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-132
11.11 REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-133
11.11.1 Cited In Text .......................................................................................... 11-133
11.11.2 References Relevant to Chapter ........................................................... 11-145
11-1
11-2
Hydraulics: Sedimentation
Hydraulics: Sedimentation
11.1 DEFINITIONS
Aggradation
Antidune
Alluvial channel bed form in upper regime flow that are often in
trains. Antidunes are often called standing waves and exhibit
surface waves that are in phase with the antidunes. The Mannings
n for antidunes ranges from 0.01 to 0.02 and the sediment
concentration ranges from 2,000 to 5,000 mg/liter.
Avulsion
Bar
Bed load
Bed material
Bed or streambed
Channel Migration
Upper flow regime bed forms at very steep slopes with high
velocities and high sediment discharge. Large elongated mounds of
sediment create chutes where the flow is rapid and followed by a
hydraulic jump and a pool. This bed form consists of chutes
connected by pools.
Degradation (bed)
11-3
11-4
Hydraulics: Sedimentation
Deposition
Dune
Lower flow regime bed forms that are larger than ripples and smaller
than bars. Dunes are large triangular-shaped sand elements similar
to ripples with a length from 2 feet to hundreds of feet. The size of a
dune is related to the flow depth. It indicates higher sediment
transport rates than ripples.
Erosion
Fluvial sediment
Ripple
Lower flow regime bed forms that are smaller than dunes. Ripples
are small triangular-shaped sand elements similar to dunes. Ripples
have gentle long upstream slopes and steep short downstream
slopes. The ripples' length ranges from 0.4 feet to 2 feet, and the
height from 0.03 ft to 0.2 ft.
Scour
Sediment
Sediment
concentration
Ratio of the weight of the sediment to the weight of the watersediment mixture; or ratio of dry weight of sediment divided by the
weight of the water-sediment mixture and multiplied by 1 million for
the convenience in lab (in parts per million, ppm); or ratio of the
weight of dry sediment to the volume of water-sediment mixture; or
ratio of the volume of sediment to the volume of water-sediment
mixture.
Sediment
discharge (or
sediment load)
Sediment yield
Sedimentation
Suspended load
Sediment load for the sediment particles that are supported by the
turbulent motion in the stream flow.
Hydraulics: Sedimentation
Wash load
That part of the total sediment load that is composed of fine particles
(generally clays and colloids) in the suspended load that are
continuously maintained in suspension by flow turbulence. Wash
load originates primarily from erosion on the land slopes of the
drainage area and is present to a negligible degree in the bed itself.
D10 or D5 from the bed material size distribution can be used to
separate the wash load from the bed material load.
Watercourse
A general term for all open water conveyances typically called rivers,
streams, creeks, washes, arroyos, etc., in their natural state, but
also includes constructed conveyances such as channels, canals,
ditches, etc.
11.2 INTRODUCTION
Sedimentation embodies the processes of erosion (Photograph 11.1), entrainment, transportation, deposition (Photograph 11.2), and the compaction of sediment (ASCE, 1975, 2006). Sedimentation engineering deals with analyses, modeling, design, and mitigation measures to
analyze and solve problems associated with sedimentation. This chapter provides the basic concepts of sedimentation engineering and analytical methods and design procedures for sediment
yield and scour estimation. Specific references are provided throughout this chapter. Some useful general references in the topic of erosion and sedimentation include ASCE (1975, 2006,
2008), ADWR (1996), USDOT (2001d), Simons and Senturk (1992), Simons, Li and Associates
(1985), Guy (1989), Henderson (1966), Julien (2002), Schumm (1977), SCS (1977), and
USACE.
11-5
Hydraulics: Sedimentation
PHOTOGRAPH 11.1
ERODED ROAD SEGMENT
PHOTOGRAPH 11.2
CULVERT CONVEYANCE CAPACITY REDUCED BY SEDIMENT DEPOSITION
11-6
Hydraulics: Sedimentation
Braided channels.
2.
3.
4.
Channel bends.
5.
6.
7.
8.
Diversion points.
9.
10.
11.
12.
13.
11-7
1.
Volume of deposition.
2.
Location of deposits.
3.
4.
5.
Turbidity.
6.
Density current.
7.
8.
Shoreline erosion.
9.
10.
Downstream degradation.
11.
12.
Hydraulics: Sedimentation
Since Maricopa County is in a semi-arid region, the dryland landscapes and "flashy" storms produce a large amount of sediment entrainment and transportation in a way very different from a
humid environment. The major sedimentation problems in Maricopa County include:
11-8
1.
2.
3.
4.
5.
Scour for flood control structures such as bank protection and spur dikes.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Hydraulics: Sedimentation
11-9
Hydraulics: Sedimentation
1.
2.
3.
4.
Lowering or raising the base-level of the stream system water surface elevations.
5.
6.
Turbidity.
7.
8.
9.
10.
Headcutting up tributaries.
11.
12.
Once the natural sedimentation processes are quantified for the "future" base condition, different
alternatives can be analyzed to mitigate the sedimentation hazards as possible solutions to the
sedimentation problems. The general solutions to sedimentation problems may be classified as
structural measures and non-structural measures. The structural measures for channel bank
erosion protection can be direct protection, indirect protection, and grade control (USACE, 1989,
1995). Direct bank protection measures include riprap, gabions, other flexible mattresses, soil
cement, and concrete. The indirect protection includes impervious or pervious dikes that are
constructed away from the banks to deflect the erosive forces. Grade control structures can be
used to reduce the bed slope, and thus the velocity and erosion in the channels. The structural
solutions to aggradation can be debris basins, periodic removal of sediment, and upstream grade
control structures that reduce the bed slope, velocity, and the sediment supply. The structural
solutions to degradation are drop structures that reduce the bed slope and overall channel velocity. The structural solutions to sand and gravel mining headcut problems can be structural erosion barriers installed upstream of the pit and below the channel bed.
The non-structural measures to sedimentation problems are through scour anticipation, erosion
hazard setbacks, and erosion monitoring and maintenance. If the anticipated scour depth can be
estimated, the channel bank protection toe down should be extended beyond the anticipated
scour depth. The anticipated scour depth is critical to bridge pier, bridge abutment, guide banks,
spur dikes, culvert outlets, power line poles, and utility crossings. Erosion setback is another
useful non-structural measure to manage the scour or deposition hazard. For example, if the lateral erosion distance can be estimated, a new house shall not be allowed to be built inside the
lateral erosion zone without adequately designed structural measures. Another example is the
setback for tailcut erosion caused by a sand and gravel mining pit. The tailcut setback must be
11-10
Hydraulics: Sedimentation
reserved as a "no-mining" space so the erosion caused by the proposed pit is contained and mitigated within the pit owner's property line. The erosion downstream of the pit's property line
should not be more than the erosion for the "future" base condition without the pit or at least the
difference in erosion between the "future" base condition and the "future" project condition should
be within a reasonable engineering accuracy level. Finally, erosion/deposition monitoring tied to
maintenance program may be a very cost-effective non-structural measure to reduce some sedimentation problems.
One of the most important objectives for sediment engineering analyses is to develop a future
base condition for sediment transport/degradation/aggradation; then perform similar analyses for
proposed alternatives such that the proposed alternatives will not have adverse impacts on adjacent, downstream or upstream areas. All erosion/deposition hazards should be contained within
the project owner's property lines. Therefore, these hazards should be mitigated by the property
owner and no negative impact should occur on adjacent, downstream, or upstream property
owners.
11-11
Hydraulics: Sedimentation
of channel stability, meandering channels are more stable than braided channels. Braided channels are mainly bed load channels while meandering channels are suspended load channels.
Although a braided channel may have some meandering reaches, its overall pattern is much less
sinuous than a meandering channel. It is common to observe that the thalweg line (the line of the
maximum depth) meanders within a relatively straight channel or a braided channel. Leopold and
Wolman (1960) developed a relationship between the slope and bankfull discharge for a variety
of natural streams. Based on this relationship, when the bankfull discharge is 1,000 cfs, if the
channel slope is greater than 0.003 ft/ft, then the channel is braided; if the channel slope is less
than 0.003 ft/ft, then the channel is meandering. When the bankfull discharge is 10,000 cfs, if the
channel slope is greater than 0.001 ft/ft, then the channel is braided; if the channel slope is less
than 0.001ft/ft, then the channel is meandering.
11-12
Hydraulics: Sedimentation
FIGURE 11.1
BED FORMS AND FLOW REGIMES
(USDOT, 2001d)
11-13
Hydraulics: Sedimentation
The lower flow regime consists of a plane bed without sediment movement, ripples, dunes with
ripples superposed, or dunes. The above figure shows ripples and dunes bed forms. The upper
flow regime consists of plane bed, antidunes with standing waves, antidunes with breaking
waves, or chutes and pools.
In the lower flow regime, resistance to flow is large and sediment transport is small. For a plane
bed without sediment movement, the Manning's n is 0.014 and sediment concentration is 0 mg/
liter (Julien, 2002). When the average shear stress on the channel bed exceeds the critical shear
stress, the sediment particles start to move and the plane bed starts to change to ripple bed form.
Ripples are small triangular-shaped sand elements on the channel bed, with gentle long
upstream slopes and steep short downstream slopes. The upstream slope is generally between
2 and 4 times as long as the downstream slope (Chien and Wan, 1998). The ripples' length
ranges from 0.4 feet to 2 feet, and the height from 0.03 ft to 0.2 ft. The Manning's n ranges from
0.018 to 0.028 and the sediment concentration ranges from 10 to 200 mg/liter (Julien, 2002).
The occurrence of ripples has little correlation with the water depth and is the result of the unstable viscous layer near the boundary (Chien and Wan, 1998). When the velocity increases, ripples will eventually become dunes. Dunes are large triangular-shaped sand elements similar to
ripples with the length ranging from 2 feet to hundreds of feet. The size of a dune is closely
related to the water depth. In the Mississippi River, 700 ft long and 40 ft high dunes are observed
(USDOT, 2001d). The amplitude of dunes can increase with increasing flow depth. Like ripples,
the longitudinal cross section of the dune shape is not symmetrical (longer upstream slope and
shorter downstream slope). The water surface wave and dune wave are out of phase. When the
water surface wave reaches crest (trough), bed dune wave reaches trough (crest). The Manning's n for dune bed channels ranges from 0.02 to 0.04 and the sediment concentration ranges
from 200 to 3,000 mg/liter (Julien, 2002).
As the velocity increases further, the dunes elongate and reduce in amplitude, which results in
washed out dunes, also referred as transition regime (USDOT, 2001d). The Manning's n for
washed-out dunes ranges from 0.014 to 0.025 and the sediment concentration ranges from
1,000 to 4,000 mg/liter (Julien, 2002). As the velocity further increases, a plane bed form with
sediment movement will develop. A large sediment transport magnitude is characteristic of this
bed form. The Manning's n for a plane bed with sediment movement ranges from 0.01 to 0.013
and the sediment concentration ranges from 2,000 to 4,000 mg/liter (Julien, 2002). As the velocity further increases, antidunes will develop. Unlike ripples and dunes, the antidune sand wave is
symmetrical along the longitudinal cross section of the sand waves. The water surface wave and
antidune sand waves are in phase, i.e. both waves reach the crests and troughs at the same time
or the water surface streamlines parallel with the river bed. While ripples and dunes can only
travel in a downstream direction, antidunes can travel in both directions or remain stationary.
The antidunes often form in shallow flows but moving at high velocities (Chien and Wan, 1998).
It may be pointed out that although the antidunes wave profile can move in an upstream direction, the sediment particles still move in a downstream direction.
11-14
Hydraulics: Sedimentation
When there are antidunes, the water surface undulates. The amplitude of the water surface wave
may exceed that of the antidune sand wave by a factor of 1.5 to 2 (Chien and Wan, 1998). This
may have a significant impact on freeboard design for flood control channels. The antidunes with
standing waves are those sand waves that gradually subside. The antidunes with breaking
waves are those sand waves that grow in height until they become unstable and break like the
sea surf (USDOT, 2001d). If the antidunes do not break, the resistance is about the same as that
for a plane bed. If the antidunes break, resistance is larger than that for a plane bed with sediment movement. The Manning's n for antidunes ranges from 0.01 to 0.02 and the sediment concentration ranges from 2,000 to 5,000 mg/liter (Julien, 2002).
Chutes and pools form at very steep slopes with high velocities and high sediment discharge
rates (USDOT, 2001d; Simons and Senturk, 1992). Large elongated mounds of sediment creates chutes where the flow is rapid and followed by a hydraulic jump and a pool. This bed form
consists of chutes connected by pools. The Manning's n for chutes and pools ranges from 0.018
to 0.035 and the sediment concentration ranges from 5,000 to 50,000 mg/liter (Julien, 2002).
11-15
Hydraulics: Sedimentation
Regime equations were also discussed by Schumm (1971), and practical guidance for selected
regime equations are provided by Leopold and Maddock (1953) and Mahmood and Shen (1971).
Leopold and Miller (1956) developed three regime equations to relate channel width, depth, and
velocity with the flow rate by studying 20 river cross sections for rivers in the Great Plains and the
Southwest semi-arid conditions. Simons and Albertson (1963) developed more generalized
regime equations based on canals in both India and the United States. Their regime equations
have wide applicability because their data range was much wider than that of previous equations.
They also developed regime equations for different types of channel/bank material (sand and
cohesive material). Regime equations for gravel-bed channels were discussed in Bray (1982)
and Hey and Thorne (1986). Julien and Wargadalam (1995) refined a regime approach based
on fluid mechanics principles.
It should be mentioned that the application of regime equations must be made with care since
they are empirical. Regime equations should be applied to channels which have conditions similar to the channels for which the regime equations were developed.
Qw S Qs ds
(11.1)
where:
Qw
Qs
ds
Alteration of one variable, as illustrated by the "balance" of Figure 11.2, will indicate the effect
upon the others. In practice, it is often useful to consider two of the variables to remain constant
while considering the quantitative effect in one variable by a change in the fourth variable.
11-16
Hydraulics: Sedimentation
FIGURE 11.2
LANES RELATIONSHIP
(Lane, 1955)
11-17
Hydraulics: Sedimentation
a stable channel design for coarse noncohesive material carrying clear water or water with wash
load (Lane, 1955). This method requires that the shear force on the sediment particle by the fluid
must be less than the critical tractive force. Other methods involve using zero sediment transport
capacity to determine the stable slope with width and depth design parameters. Such equations
are the Schoklitsch zero bedload equation (Schoklitsch, 1932), Meyer-Peter and Muller beginning transport equation (Meyer-Peter and Muller, 1948), and the Shields diagram method (Pemberton and Lara, 1984).
Extremal hypothesis is another approach to describing alluvial channels equilibrium condition
(ASCE, 1998a). It is based on the maximization or minimization of stream power, energy dissipation rate, or sediment concentration (Chang, 1980, 1988a, 1988b; White et al., 1981; Yang et al.,
1981; Yang and Song, 1986; Bettess and White, 1987; Yang, 1992; Millar and Quick, 1997). As
indicated in ASCE (1998a), although the theoretical justification for this approach is not entirely
clear, the predictions provide global agreement with a wide range of observations.
11-18
Hydraulics: Sedimentation
individual reaches; (3) there are strong correlations between channel form and process variables; and (4) dryland rivers can be adjusted to maximum sediment transport efficiency under
conditions of low gradient, abundant within-channel vegetation, and declining downstream discharges.
It may be mentioned that whether or not a channel is at an equilibrium condition is relative and is
a function of time scale. A channel may be in equilibrium for a short time period, but may not be
in equilibrium for a long time period. An equilibrium channel is also a function of the magnitude of
rainfall and climate changes. A channel in Maricopa County may reach its equilibrium condition
in the past 10 years with a series of nominal discharges. The equilibrium condition can be easily
disrupted when a larger flood event occurs at the end of the 10-year period. To understand the
equilibrium condition, it is very important to consider the applicable time scales, which could be
1,000 years, 100 years, 10 years, 1 month, 1 minute, or any other time intervals.
Another challenge is related to the use of sediment transport equations. Most sediment transport
equations were developed under a steady state condition, i.e., the flow and sediment data are
collected when flow and sediment movement do not change with respect to time during the
observation. The steady state can be considered as a special case of an equilibrium condition for
a short time scale. Under the equilibrium condition or a steady state condition, there is no degradation or aggradation in the channel reach and the sediment inflow is equal to the sediment outflow for the reach. Under these conditions, the actual sediment transport rate is the same as the
sediment transport capacity rate. Therefore, most sediment transport rate equations are the sediment transport capacity rate equations. In fact, most sediment models are based on an assumption that the actual bed-load transport rate is equal to the transport capacity under the equilibrium
condition at every computational time step (Wu, 2007). However, sediment transport in natural
rivers is not usually in a state of equilibrium and sediment cannot reach a new equilibrium state
instantaneously due to the temporal and spatial lags between flow sediment transport (Wu,
2007). In addition, flumes in laboratories usually have solid walls and therefore the bank effects
are not included in the sediment transport equations, which limits the application of the equations
in natural rivers because natural rivers are usually subject to bank erosion. When natural rivers
are not in a steady state condition during a flood such as a flash flood, the sediment transport
equations may not give accurate results because most sediment transport equations were developed under the steady state condition.
Han (1980) derived a non-equilibrium sediment transport equation based on a convective-diffusion equation considering wash load. Bell and Sutherland (1983) performed experiments to study
the nonequilibrium bedload transport behavior. Nakagawa et al. (1989) used convolution-integral
modeling to describe non-equilibrium bed load sediment transport. Chien and Wan (1998) extensively studied the non-equilibrium condition where the sediment concentration distribution varies
in the streamwise direction. Recently, Wu and Vieira (2002) improved Bell and Sutherland's
approach and added non-equilibrium total sediment transport into the CCHE1D model (Wu and
11-19
Vieira, 2002).
(2007).
Hydraulics: Sedimentation
Non-equilibrium and unsteady state channel condition and sediment transport phenomenon pose
challenges for river mechanics engineers in arid and semiarid regions. Further research is
needed in this field. Application of equilibrium conditions to alluvial channels in arid and semiarid regions such as Maricopa County is subject to great uncertainty and results should be carefully reviewed. Engineering judgment must be applied, and a safety factor should be considered
to account for uncertainties and risks.
11-20
Hydraulics: Sedimentation
11-21
Hydraulics: Sedimentation
PHOTOGRAPH 11.4
VERTICAL BANKS DUE TO LATERAL EROSION
The excess energy theory assumes that a channel with excess energy tends to damp out the
excess energy by increasing its length, therefore meandering. Leopold et al. (1964) stated that,
The meandering pattern approaches more closely the equilibrium condition as defined by the
entropy concept than does the nonmeandering one. Under the equilibrium condition, the channel adjusts so that the rate of work expended in the system is a minimum. Leopold et al. (1964)
used some examples to explain that the energy slope in a meandering channel tends to be more
uniform, implying that the energy loss along the channel length is more uniform than the straight
channel. In addition to the above five theories, excessive sediment load can also cause a channel to increase the bed slope and channel width therefore causing meandering or lateral migration. Channel avulsion (a channel takes a different path when the flow capacity is reduced by
sediment deposition) on braided channels can be another factor to cause a channel to laterally
migrate. The Kosi River on an alluvial fan in India had an annual shift rate of 1.04 kilometers
from 1933 to 1950 (Garde and Raju, 1985) until levees were installed to arrest the lateral migration.
In most cases, banks must erode in order for a channel to migrate laterally or meander. Erosion
along the outer bank and deposition along the inner bank have always been observed in meandering channels. The bank erosion mechanism plays a key role in studying channel migration
and meandering. Bank erosion mechanisms include hydraulic forces, erosion from waves, and
11-22
Hydraulics: Sedimentation
geotechnical failures (USACE, 1989, 1995). The hydraulic forces include tangential shear stress
from the drag of the water against the channel bank and direct impingement of the water against
the channel bank. Erosion from waves is generally applicable only to lake and reservoir banks.
Geotechnical failures are due to bank slope instability. The channel bed erosion at the bank toe
will increase the bank instability. The tangential shear stress and direct impingement play a more
important role for noncohesive bank material erosion than for cohesive bank material erosion.
Cohesive material is more resistant to tangential shear stress, however, it is subject to bank collapse failure due to increased pore pressure when the water levels in the channel side drop.
Ikeda et al. (1981) was among the first researchers who studied the bank erosion rate by using
the linear perturbation analysis to derive an equation of bank erosion. The bank erosion rate as
proposed by Ikeda et al. (1981) is assumed to be a linear function of difference between the near
bank tangential velocity and the one-wavelength reach averaged velocity. Their research provided a description for the meander and migration growth. Parker et al. (1982) derived a generalized nonlinear equation for bend migration which reduced the lateral and downstream migration
rates and increased the meander wavelength as compared with the linear assumption in Ikeda et
al. (1981). Odgaard (1989) linked bank erosion rate to the near-bank water depth rather than the
difference between the near-bank velocity and the one-wavelength reach averaged velocity.
Osman and Thorne (1988a, 1988b) provided a methodology based on a combination of lateral
erosion, bed degradation, and geotechnical bank failure. Simon et al. (2000) proposed a method
to include hydrostatic and pore-water pressure in the bank stability analysis. Darby and Thorne
(1996) added rotational failure mechanism to the bank stability analysis of Osman and Thorne
(1988a, 1988b). Hasegawa (1989) derived an equation for bank erosion and channel migration
rate based on the assumption that bank erosion is proportional to the velocity difference between
the near-bank velocity and centerline depth-averaged streamwise flow velocity. A universal bank
erosion coefficient was proposed by Hasegawa (1989). Duan (2005) proposed a probabilistic
approach to estimate the bank erosion rate for cohesive bank material of planar bank failure.
An extensive discussion on channel width adjustment and bank erosion was provided by ASCE
(1998a, 1998b, 2008). It was stated in ASCE (1998a) that the width adjustment may be caused
by disruption of the long-term equilibrium condition due to an extreme event or maybe a morphological response to river engineering or management. It was concluded from ASCE (1998b) that
no one universal width adjustment model exists that is applicable to all circumstances and calls
for further research on comprehensive field and lab data for model verification. As summarized
in ASCE (1998b) and ASCE (2008), all numerical models belong to one of two general categories: those based on extremal hypotheses or those based on the geofluvial approach. The extremal hypotheses are based on minimization of stream power. The geofluvial approach is based
on flow hydraulics, sediment transport, bank erosion, and bank failure modeling. A list of potential
models for width adjustment is discussed in ASCE (1998b) and ASCE (2008). The examples for
models based on extremal hypotheses are quasi-2D GSTARS (Yang et al., 1988) and 1D FLU-
11-23
Hydraulics: Sedimentation
VIAL-12 (Chang, 1988a). Examples for models based on a geofluvial approach are 1D WIDTH
(Osman, 1985), 2D CCHEBank (Li and Wang, 1993), and 1D STREAM2 (Borah and Bordoloi,
1989).
Simon et al. (2000) provided a detailed discussion on the role of negative pore pressure in the
unsaturated zone; the role of hydraulic forces causing bank erosion and steepening of toe profiles; effects of variability of moisture content with time on other geotechnical properties; and
development of a bank-stability algorithm for layered cohesive streambanks. A bank stability
algorithm was proposed to model the timing and conditions leading to mass failure with the consideration of matric suction for the portion of the failure plane, confining pressure, positive porewater pressure, varying soil unit weight and layering within the banks (Simon, et al., 2000).
Olsen (2003) developed a three-dimensional model that was successfully used to simulate the
meandering streams in the laboratory, which does not require a separate bank erosion model as
most other models. Olsen's model is based on finite volume that directly solves the NavierStokes equations with the standard k turbulence model. The secondary flow is directly modeled. Duan and Julien (2005) incorporated the physically based bank erosion model into the twodimensional flow and mass conservation equations to predict bank erosion with consideration of
secondary flow effects. CCHE2D and CCHE3D developed by the National Center for Computational Hydroscience and Engineering (NCCHE) in the University of Mississippi are capable of
simulating channel migration and meandering (Jia and Wang, 1999; Jia and Wang, 2001). The
information on CCHE3D can be obtained from http://www.ncche.olemiss.edu/
index.php?page=freesoftware#cche3d.
A qualitative geomorphic analysis is also important. It should include a study of published soil
maps, topography, field identification and verification of bedrock outcrops, armored channel
beds, cutbanks and existing man-made bank protection structures. All available historical aerial
photographs should be analyzed as a part of the geomorphic analysis in support of other estimation procedures. Comparison of historical aerial photographs should be made in a GIS framework, if possible. A discussion on some quantitative methods for evaluating the channel lateral
stability can be found in USDOT (2001c). Hydraulic and geotechnical engineering principles
should be applied to estimate bank stability and erosion limits. The procedure recommended by
Osman and Thorne (1988a, 1988b) may be used to determine the bank erosion distance in conjunction with equilibrium slope or sediment transport modeling for channel bed scour. A simplified use of Osman and Thorne's methodology can be found in Mussetter et al. (1994). Another
useful methodology developed by the National Sedimentation Laboratory can be found in Simon
et al. (2000), which accounts for the effect of vegetation roots. A discussion on bank erosion
mechanisms can also be found in USDOT (2001c). CCHE2D (2007 version or later), a twodimensional hydraulic and sediment transport model, may be used to model the lateral erosion
(Jia and Wang, 2001). Recently, the NCCHE has added a procedure from Osman and Thorne
(1988a) to the CCHE2D model as requested by the FCDMC (Jia and Wu, 2007). The FCDMC
has developed a practical engineering methodology suitable to the Maricopa County environ-
11-24
Hydraulics: Sedimentation
ment to estimate the lateral erosion. Detailed discussion on the methodology can be found in
Section 11.9. The methodology will replace the lateral migration estimation procedures documented in Arizona State Standard 5-96 (ADWR, 1996) for Maricopa County.
In addition to quantifying the bank erosion and lateral erosion distance, mitigation through a
structural solution is extremely important. The mitigation structures for bank stabilization and
bend control include revetments, spurs, retardance structures, longitudinal dikes, vane dikes,
bulkheads, and channel relocations (USDOT, 2001a). Detailed discussion on bank protection
can be found in other chapters of this manual.
11-25
Hydraulics: Sedimentation
A significant amount of research has been done to quantify the headcut and its migration rate.
Leopold et al. (1964) indicated that when the ratio of headcut height to the flow depth is large, for
example 1.5 ft/ft, the vertical drop will be maintained as it moves upstream for cohesive soil material. When the ratio is less than or equal to 1.0 ft/ft, the knickpoint is obliterated by the flattening
slope. Experiments were performed by Bennett et al. (1997) for a movable bed channel. It was
found that the shape of the scour hole below the knickpoint does not change as the headcut
migrates upstream. Empirical equations for headcut migration rate and experimental studies can
be found in De Ploey (1989), Temple (1992), Temple and Moore (1994), Robinson and Hanson
(1994), Hanson et al. (1997), NRCS (1997), Temple and Moore (1997), Robinson et al. (2000),
and Hanson et al. (2001). A two-dimensional model was developed by Stein and LaTray (2002)
based on a cantilever mass failure model and a scour model to simulate the headcut migration
rate for a two-layer soil where the upper layer is erosion-resistant soil and the lower layer is erosive soil. In 2005, another two-dimensional model was developed by Frenette and Pestov (2005)
based on the vertex flow concept.
PHOTOGRAPH 11.5
SHALLOW FLOW OVER ROADWAY INITIALLY CAUSES HEADCUTTING INTO
ROAD SUBGRADE AND PAVEMENT
Channel incision takes place in degradational zones where there is fine bed material Julien
(2002). Rills (Photograph 11.6) are small-scale channels, and gullies (Photograph 11.7) are
large-scale channels often found in upland areas. Channel incision is often found in ephemeral
11-26
Hydraulics: Sedimentation
channels also called arroyos. Headcuts that migrate upstream are a characteristic feature of
incised channels. Headcuts can also be found when a tributary channel enters into a main channel which has a lower bed elevation than that for the tributary channel. Gullies and headcuts can
also be found in earthen dam spillways. A large-scale "man-made" headcut can be found in the
vicinity of sand and gravel mining pits where there are abrupt changes in bed elevation.
PHOTOGRAPH 11.6
RILL EROSION
PHOTOGRAPH 11.7
GULLY EROSION
11-27
Hydraulics: Sedimentation
11-28
Hydraulics: Sedimentation
PHOTOGRAPH 11.8
SAND AND GRAVEL MINE HEADCUT
11-29
Hydraulics: Sedimentation
FIGURE 11.3
PROFILES SHOWING HEADCUT MIGRATION, SAN JUAN CREEK, CALIFORNIA
(USACE, 1989, 1995)
BRIDGE PIER SCOUR IN VICINITY OF MINING PITS
11-30
Hydraulics: Sedimentation
PHOTOGRAPH 11.9
FAILURE OF INDIAN SCHOOL ROAD BRIDGE, AGUA FRIA RIVER, ARIZONA
(USACE, 1981)
11-31
Hydraulics: Sedimentation
Another adverse effect due to mining pits is scour downstream of the pits. This is because a
sand and gravel mining pit traps most of the sediment, therefore the flow leaving the pit does not
have much sediment, and the sediment-starved water removes bed material from the channel
(USACE, 1989, 1995). As indicated by Kondolf (1994), the "hungry water" has excess energy
and erodes its bed and banks to regain at least part of its sediment load. This erosion, often
called tailcut, can also damage structures in the vicinity of mining pits. As discussed in Lee et al.
(1993), Tan-Shui River, one of the major rivers in Taiwan, is subject to serious degradation problems downstream of sand and gravel mining pits. The bed elevation of the downstream reach
close to the river mouth is as low as 30-40 meters below sea level, which threatens the safety of
the dikes and bridges in that area. The physical modeling results by (Chen, 1980) indicate a tailcut distance of about 1,000 feet and a maximum tailcut depth of about 12 feet at the downstream
knickpoint.
Other effects due to mining pits, which can damage in-stream structures, are lateral erosion,
bank failure, channel widening, and low flow channel re-direction. The incision channels caused
by headcuts and tailcuts can cause bank undercutting and erosion, resulting in a significant fourfold increase in the sediment load. For example, incision channeling resulted in a four-fold
increase in the sediment load of Blackwood Creek, California (Kondolf, 1994). A gravel pit in San
Juan Creek, California caused channel widening resulting from undercutting of banks (Kondolf,
1994). The physical modeling results by (Chen, 1980) indicate a lateral erosion of 300 feet long
and 13 feet deep.
The mitigation measures for eliminating adverse impacts of sand and gravel operations consist of
two approaches: set-back and structural solutions. The first approach is to estimate the headcut,
tailcut, and lateral erosion distances, which are then used to establish set-back limits. The sand
and gravel mining pits must be designed such that the upstream, downstream, and lateral erosion limits are confined to the mining owner's property. The estimation of headcut and tailcut for
sand and gravel mining pits can be done by both empirical equations and sediment transport
modeling. Lee et al. (1993) developed some empirical equations based on a series of experiments for a sand-bed flume to estimate the headcut and tailcut profiles. ADOT (Li et al., 1989)
also developed empirical equations based on a computer simulation for both sand-bed and
gravel-bed channels. However, there are two issues with ADOT's methodology. The first one is
that ADOT's method may significantly under-estimate the headcut distance for both sand-bed
and gravel-bed conditions while it may significantly over-estimate the tailcut distance for a sandbed channel. The second issue is that ADOT's method yields a zero tailcut distance for gravelbed channels. The FCDMC recently developed a software called PitScour to compute headcut
and tailcut based on ADOT's method. The physical modeling results by Chen (1980) for the Salt
River indicate that the headcut distance should be in thousands of feet for a gravel bed channel
and the tailcut distance should be around a 1,000 feet for a 60-ft deep gravel pit. A field observation in the Lower Hassayampa River indicates a 0.5 mile headcut migration from a 10-foot deep
sand pit upstream of the Tonopah-Salome Highway, Maricopa County, Arizona (FCDMC, 2006).
11-32
Hydraulics: Sedimentation
The headcut distance/depth and tailcut distance/depth for pits in Maricopa County should be estimated by using a sediment transport software such as HEC-6 (USACE, 1991), HEC-6T (MBH,
2002), Fluvial-12 (Chang, 1988a; Chang Consultants, 2006), or other FCDMC-approved sediment transport software.
When sediment transport modeling is used, both the base condition model without the pit and
proposed condition model with the pit are needed. Both sediment transport models are run to
obtain the maximum scour depth and deposition depth at each cross section for the entire simulation time period. It may be noted that "maximum" is with respect to the maximum value over the
entire simulation time period. The scour and deposition are with respect to the channel thalweg.
The scour depth at adjacent properties' boundary lines for the proposed condition model with the
pit should be less than or equal to the scour depth for the base condition without the pit. If the
modeling results for the base condition indicate an aggradation at adjacent properties' boundary
lines, the minimum channel thalweg elevation corresponding to maximum scour depth for the
proposed condition should be between the channel initial thalweg elevation and the maximum
channel thalweg elevation for the base condition.
The headcut and tailcut setbacks must be reserved as "no-mining" spaces so that the scour
caused by the proposed pit is contained within the pit owner's property lines unless the adjacent
property owners agree with the scour depth on their properties. However, since the adjacent
property owners may also plan to excavate sand and gravel pits or sell the land in the future for
potential future sand and gravel activities, the sediment transport modeling for the "combined"
pits should be analyzed to estimate the cumulative impact on further upstream and downstream
properties. Figure 11.4 depicts the non-adverse impact scenario when the base condition is subject to natural erosion. Figure 11.5 depicts the non-adverse impact scenario when the base condition is subject to natural deposition.
It may be noted that since FLUVIAL-12 can simulate the formation of narrow headcut and tailcut
channels and HEC-6 or HEC-6T's prediction is the average value over the entire erodible cross
section, the scour distance and depth computed by FLUVIAL-12 may be larger than those computed by HEC-6 and HEC-6T.
The second approach to mitigation measures is through structural solutions such as grade control structures, drown-out structures, rock-filled trenches, levees, and lateral erosion control
structures. It should be mentioned that grade control structures can effectively control the headcut problems, but cannot control the tailcut problems, because tailcut problems are due to the
lack of sediment in the flow leaving the pits. Erosion and sediment control methods for surface
mining are available in U.S. EPA (1976). Technical guidelines and procedures for analyzing sand
11-33
Hydraulics: Sedimentation
and gravel mining and its potential impact on watercourses are provided by USACE ((1980 and
1987), Li et al. (1989) and Urban Drainage and Flood Control District (1987).
FIGURE 11.4
NON-ADVERSE IMPACT WHEN BASE CONDITION IS SUBJECT TO NATURAL EROSION
11-34
Hydraulics: Sedimentation
FIGURE 11.5
NON-ADVERSE IMPACT WHEN BASE CONDITION IS SUBJECT TO NATURAL DEPOSITION
11-35
Hydraulics: Sedimentation
Particle Size
The sediment particle size is one of the most important and commonly used properties (Garde
and Raju, 1985). There are four common definitions for particle size (USACE, 1995):
1.
The nominal diameter of a particle is the diameter of a sphere that has the same
volume as the particle.
2.
The sieve diameter of a particle is the length of the side of the smallest square
opening through which the given particle will pass.
3.
The sedimentation diameter of a particle is the diameter of a sphere that has the
same specific gravity and has the same terminal settling velocity as the given particle in the same fluid under the same conditions.
4.
The standard fall diameter (or simply fall diameter) of a particle is the diameter of
a sphere that has a specific gravity of 2.65 and has the same terminal settling
velocity as the given particle in quiescent distilled water at a temperature of 24C.
Particle Classification
Sediment particles are classified into six general categories: clay, silt, sand, gravel, cobbles, and
boulders based on the particle size (USACE, 1995). There are many grading systems in the
engineering and geologic literature to define the size range for each of the six categories. For
sediment work and modeling, the sediment grade system proposed by the subcommittee on
Sediment Terminology of the American Geophysical Union (Lane, 1947; ASCE 1975, 2006)
should be used. Table 11.1 shows the sediment grade scale system.
TABLE 11.1
SEDIMENT GRADE SCALE
(Lane, 1947; ASCE 1975, 2006)
Approximate Sieve Mesh
Openings per inch
Size Range
Class Name
Millimeters
Inches
Tyler
United
States
Standard
(1)
(2)
(3)
(4)
(5)
4,096-2,048
160-80
Large boulders
2,048-1,024
80-40
Medium boulders
1,024-512
40-20
11-36
Hydraulics: Sedimentation
TABLE 11.1
SEDIMENT GRADE SCALE
(Lane, 1947; ASCE 1975, 2006)
Approximate Sieve Mesh
Openings per inch
Size Range
Tyler
United
States
Standard
Class Name
Millimeters
Inches
Small boulders
512-256
20-10
Large cobbles
256-128
10-5
Small cobbles
128-64
5-2.5
64-32
2.5-1.3
Coarse gravel
32-16
1.3-0.6
Medium gravel
16-8
0.6-0.3
2-1/2
Fine gravel
8-4
0.3-0.16
4-2
0.16-0.08
10
2.0-1.00
16
18
Coarse sand
1.0-0.5
32
35
Medium sand
0.5-0.25
60
60
Fine sand
0.25-0.125
115
120
0.125-0.062
250
230
Coarse silt
0.062-0.031
Medium silt
0.031-0.016
Fine silt
0.016-0.008
0.008-0.004
Coarse clay
0.004-0.002
Medium clay
0.002-0.001
Fine clay
0.001-0.0005
0.0005-0.00024
Note: A 200 US Sieve Size (Tyler 200 Mesh) corresponds to 0.074 mm (0.0029 in) opening size.
11-37
Hydraulics: Sedimentation
Particle Shape
As discussed by Garde and Raju (1985), the sediment particle shape affects the bed load transport, fall velocity, and mean velocity of the flow at which the particle on the bed moves. Sediment
particle shape can be defined by the shape factor, SF, (USACE, 1995) as:
cS F = --------ab
(11.2)
where:
a
The shape factor for a sphere is 1.0. Natural sediment typically has a shape factor of about 0.7
(USACE, 1995). Other shape factors and parameters describing the sediment particle shape
can be found in Chien and Wan (1998).
11-38
Hydraulics: Sedimentation
4gd s
2
V s = ---------- ------------
3C D
(11.3)
where:
Vs
CD
24
0.5
C D = ------ ( 1 + 0.152Re + 0.0151Re )
Re
(11.4)
where:
Re
Vs
0.00000179
= --------------------------------------------------------------2
1 + 0.03368T + 0.00021T
(11.5)
where:
2
When the Reynolds number is less than 0.1, CD can be approximated by 24/Re. Then, the settling velocity becomes the Stokes Law equation as follows:
11-39
2
gd
s
V s = --------- ------------
18
Hydraulics: Sedimentation
(11.6)
For typical engineering sedimentation studies, the fall velocity can be estimated by Figure 11.6.
In general, the drag coefficient decreases as the Reynolds number increases. When the Reynolds number for spheres is between 1,000 and 10,000, the drag coefficient is around 0.5 (Rouse,
1938). When Reynolds number is less than 0.1 (Stokes' range), the drag coefficient is independent of the thickness of the sediment particle as long as the particle is not relatively long (Garde
and Raju, 1985). The shape affects the fall velocity significantly when Reynolds number is large.
For the same Reynolds number, a larger shape factor will give a smaller drag coefficient. A discussion on fall velocity for nonspherical particles can also be found in ASCE (2008). The suspended sediment concentration also affects the fall velocity. Experiments show that fine
sediments with a diameter less than 0.062 mm reduce the fall velocity (Simons, Richardson and
Haushild, 1963). Shen and Julien (1993) indicated that heavy sediment concentrations reduce
the fall velocity for a sediment particle. Open channel experiments indicate an increase in fall
velocity due to turbulence (Garde and Raju, 1985). Generally speaking, the particle roughness
will increase the drag coefficient. However, when the Reynolds number is below a certain-value,
the influence of the roughness on the drag coefficient disappears (Graf, 1984). The effects on
the fall velocity due to these and other factors are discussed in Graf (1984), Garde and Raju
(1985), Shen and Julien (1993), and ASCE (1975, 2006).
11-40
Hydraulics: Sedimentation
FIGURE 11.6
RELATIONSHIP OF SIEVE DIAMETER AND FALL VELOCITY
FOR NATURALLY WORN QUARTZ PARTICLES
FALLING ALONE IN QUIESCENT DISTILLED WATER OF INFINITE EXTENT
(Interagency Committee, 1957)
11-41
Hydraulics: Sedimentation
.
FIGURE 11.7
CUMULATIVE SEMILOGARITHMIC SIZE-GRADATION CURVE
The commonly used U.S. standard sieve sizes for gradation graph are 3 inches, 1.5 inches,
inches, 3/8 inches, No. 4, No. 10, No. 20, No. 40, No. 60, No. 100, and No. 200. The sizes in mm
for No. 4 through No. 200 are shown below in Table 11.2.
TABLE 11.2
U.S. STANDARD SIEVE SIZES
USACE (1970)
11-42
Size (mm)
No. 4
4.76
No. 10
2.00
No. 20
0.841
Hydraulics: Sedimentation
TABLE 11.2
U.S. STANDARD SIEVE SIZES
USACE (1970)
Commonly Used Sieve Size Number
(U.S. Standard Sieve Size, ASTM E-11-6)
Size (mm)
No. 40
0.420
No. 60
0.25
No. 100
0.149
No. 200
0.074
The sediment arithmetic mean size da is the average value of the size for each sediment particle.
Sediment samples from natural rivers often follow log-normal distribution (the log values of the
sediment size follows the normal distribution or Gaussian distribution). When the sediment sizes
follow a log-normal distribution, the sediment geometric mean, dg, and sediment median, d50,
are equal, and they can be estimated (Mays, 1999) by:
d g = d 50 = ( d 84 d 16 )
12
(11.7)
While the median and geometric mean are used to measure the average size of the sediment
mixture, the geometric standard deviation or gradation coefficient is used to measure the size
variation of the sediment mixture. When the sediment size follows a log-normal distribution, the
geometric standard deviation g is estimated as (Mays, 1999):
g = ( d 84 d 16 )
12
= d 84 d 50 = d 50 d 16 = 0.5 ( d 84 d 50 + d 50 d 16 )
(11.8)
The term 0.5 ( d 84 d 50 + d 50 d 16 ) is often called the gradation coefficient. For more discussion
on other statistical parameters for a sediment mixture, see Garde and Raju (1985), Shen and
Julien (1993), and ASCE (2008).
Porosity
The porosity of a sediment deposit is defined as the percentage of pore space in the total bulk
volume of the sediment (Shen and Julien, 1993):
P = Vv Vt
(11.9)
where:
the porosity,
Vv
11-43
Vt
Hydraulics: Sedimentation
Fine sediment particles usually have more voids than coarse particles because the surface area
of fine particles is relatively larger (Chien and Wan, 1998). The porosity ranges for fine sand,
medium sand, and coarse sand are 44%-49%, 41%-48%, and 39%-41%, respectively. The
porosity for sandy soils with a small amount of clay may be between 50% and 54%. The porosity
of a natural sediment mixture is between 25% and 50%.
b = Ws Vt
(11.10)
where:
Ws
Vt
The bulk volume is equal to the sediment volume plus the void volume. The bulk specific weight
can be derived and expressed as a function of porosity and particle specific weight by:
b = ( 1 P ) s
(11.11)
where:
the porosity,
SG
62.4 lb/ft3.
Since there are voids among the particles in a sediment deposit, the specific weight for sediment
deposits is always less than that for a single sediment particle. This can be observed from the
11-44
Hydraulics: Sedimentation
above equation since P is less than 1.0 and greater than or equal to 0.0. Table 11.3 lists the initial specific weights for sediments that have been in deposits for 1 year or less (ASCE, 2006).
Table 11.3 also contains the approximated D50 values when only the data range or D90 was
given in the original table from ASCE (2006). Figure 11.8 shows the initial specific weights as a
function of D50 based on-values from Table 11.3. A regression equation was developed by
FCDMC to fit the data points in Figure 11.8 as given below:
(11.12)
where:
initial
D50
The applicable range for D50 is between 0.0005 mm and 180 mm. The solid line in Figure 11.8 is
the fitted line that corresponds to the regression equation.
11-45
Hydraulics: Sedimentation
.
TABLE 11.3
INITIAL BULK SPECIFIC WEIGHTS OF SEDIMENTS OF VARIOUS GRAIN SIZE
(MODIFIED FROM ASCE, 2006)
Hembree, Colby,
California Division of
Water Resources
Trask (Laboratory)
Initial
D50
Weight
3
Happ (Middle
(Countrywide)
Rio Grande)
Initial
Specific
D90
Initial
Specific
Size Range
D50
Weight
3
Initial
Specific
D50
Weight
3
Specific
D50
Weight
(mm)
(mm)
(lb/ft )
(mm)
(mm)
(lb/ft )
(mm)
(lb/ft )
(mm)
(lb/ft3)
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
0.125
0.089
92
---
---
---
---
---
---
---
0.25
0.179
92
---
---
---
---
---
---
---
0.5
0.357
93
---
---
---
---
---
---
---
0.714
95
---
---
---
---
---
---
---
1.429
98
0.001-0
0.0005
0.001
42
0.0012
48
2.857
103
0.004-0.001
0.0025
23
0.005
52
0.005
68
5.714
109
0.016-0.004
0.01
55
0.01
57
0.01
73
16
11.429
116
0.064-0.016
0.04
79
0.05
70
0.05
78
32
22.857
124
0.125-0.064
0.0945
86
0.1
77
0.1
88
64
45.714
132
0.25-0.125
0.1875
89
0.25
89
---
---
128
91.429
138
0.5-0.25
0.375
89
0.5
104
---
---
256
182.857
140
---
---
---
1.0
120
---
---
Notes: Column (2) is obtained by dividing column (1) by 1.4. 1.4 is obtained by interpolating the middle values of stone size
ranges for 100 and 85 based on Table 6.4 from the FCDMC Hydraulics Manual (1996). Column (5) is the averaged values of the
lower and upper bounds from Column (4).
11-46
Hydraulics: Sedimentation
FIGURE 11.8
INITIAL BULK SPECIFIC WEIGHT FOR SEDIMENT DEPOSITS
(MODIFIED FROM ASCE, 2006)
As indicated in ASCE (1975, 2006), three factors influence the specific weight of a deposit. They
are mechanical composition, the environment in which deposits are formed, and time. Coarse
materials may not change with time, but fine materials such as clay and silt may have an initial
specific weight which is much smaller than the specific weight for the ultimately consolidated
deposit over time. The initial bulk specific weight for sediment deposits will increase as the sediment deposit is being consolidated over time. The bulk specific weight for reservoir sediment
deposits after T years can be expressed (ASCE, 2006) as:
(11.13)
where:
res, initial = the reservoir sediment bulk specific weight for the initial deposit
after 1 year of consolidation,
time in years.
11-47
Hydraulics: Sedimentation
Table 11.4 lists the consolidation coefficients for sand, silt, and clay. When the sediment deposit
contains sand, silt, and clay, the above equation can be used to find the individual consolidated
sediment specific weight after T years for each. Then, the composite specific weight can be estimated by Colby's equation (ASCE, 2006) as:
1
Comp,T = --------------------------------------------------------F clay
F silt
F sand
-------------- + ------------ + -------------- clay,T silt,T sand,T
(11.14)
where:
Comp,T
clay,T
silt,T
sand,T
F clay
F silt
F sand
TABLE 11.4
CONSOLIDATION COEFFICIENTS FOR SPECIFIC WEIGHT OF RESERVOIR SEDIMENTS
(MODIFIED FROM ASCE, 2006)
Sand
Silt
Clay
res, initial
res, initial
res, initial
93
65
5.7
30
16
93
74
2.7
46
10.7
93
79
60
93
82
78
Reservoir Operation
11-48
Hydraulics: Sedimentation
= 32.5 + 1.27d
(11.15)
where:
Sediment Concentration
There are several definitions for sediment concentration. The first definition, Cw/w, is the ratio of
the weight of the sediment to the weight of the water-sediment mixture. The second definition is
the first definition in parts per million, ppm, denoted by Cppm, i.e., the dry weight of sediment
divided by the weight of the water-sediment mixture multiplied by 1 million for convenience in the
laboratory (Porterfield, 1972). The third definition, Cw/v, is the weight of dry sediment in a watersediment mixture per volume of mixture. A fourth definition is the ratio of the sediment volume to
the water-sediment mixture, denoted by Cv/v. The following equations show the relationships
among these definitions:
SG s *C v v
C w w = ------------------------------------------1 + ( SG s 1 )C v v
6
(11.16)
C ppm = 10 C w w
(11.17)
Cw v = b Cw w
(11.18)
11-49
Hydraulics: Sedimentation
where:
SGs
A special case of Cw/v is milligrams per liter, Cmg/l. The relationship between Cmg/l and Cppm can
be expressed as:
SG s *C ppm
C mg l = --------------------------------------------------------------6
SG s + ( 1 SG s )C ppm 10
(11.19)
SG s *C mg l
C ppm = ----------------------------------------------------------------6
SG s + ( SG s 1 )C mg l 10
(11.20)
The numerical values of Cppm and Cmg/l are similar when the concentration is less than 16,000
mg/l because the water-sediment mixture has a density close to water density, 1 mg/ml.
The sediment concentration can be used to classify flows (O'Brien, 1986), as illustrated in Table
11.5.
TABLE 11.5
SEDIMENT FLOW CLASSIFICATION BASED ON CONCENTRATION
(OBrien, 1986)
Type of Flow
(1)
(2)
Water flood
0 - 410,000
Mud flood
410,000 - 650,000
Mudlflow
650,000 - 730,000
Landslide
730,000 - 880,000
Sediment Load
The term sediment load is used to denote sediment transport rate, and the dimension of sediment load can be expressed either as weight per unit time or as volume per unit time (Shen and
Julien, 1993). Herein, the terms sediment load and sediment discharge are used interchangeably. Sediment load is often expressed in tons/day. The relationship between Cmg/l and suspended sediment discharge can be expressed as:
11-50
Hydraulics: Sedimentation
Q s = 0.0027C mg l Q w
(11.21)
where:
Qs
Cmg/l
Qw
It may be noted that the above equation is based on an assumption that the weight of a cubic foot
of water-sediment mixture is 62.4 pounds (Porterfield, 1972).
The sediment discharge in tons per day can be converted to cubic feet per second by:
Q s, cfs = 0.02315Q s s
(11.22)
where:
Qs,cfs
Total sediment load can be defined as the sediment transport load for an entire cross section.
Based on the mechanism of movement, total sediment load can be divided into bed load and
suspended load (Shen and Julien, 1993). The bed load is the sediment load transported close to
the bed where particles move intermittently by rolling, sliding, or jumping (USACE, 1995). The
suspended load is the sediment load for the sediment particles that are supported by the turbulent motion in the stream flow.
Based on its availability in the streambed, total sediment load can be divided into bed-material
load and wash load. Bed material load is the sediment transport load for those sediment particles sizes that are readily apparent on the surface of the streambed (Shen and Julien, 1993).
Particles that move as suspended load or bed load and periodically exchange with the bed are
part of the bed material load (USACE, 1995). The bed material load can be computed from the
composition of the streambed. Wash load consists of the finest particles in the suspended load
that are continuously maintained in suspension by flow turbulence. The D10 or D5 sizes from the
bed material size distribution can be used to separate the wash load from the bed material load
(Shen and Julien, 1993). D10 is defined as the sediment size on the streambed surface for which
10 percent is finer. D5 is defined as the sediment size on the streambed surface for which 5 percent is finer. Wash load may be calculated based on upstream supply rate, watershed sediment
yield analysis, or actual sediment rate measurement (Shen and Julien, 1993). According to the
11-51
Hydraulics: Sedimentation
method of calculation, bed material load can be divided into suspended bed material load and
bed load. The suspended load can be divided into wash load and suspended bed material load.
Based on the measurement method, sediment can be divided into measured and unmeasured.
When depth-integrated suspended sediment samplers are used, the lower 0.5 ft of the water column is unmeasured. The unmeasured load includes some of the suspended sediment and usually all of the bed load (USACE, 1995). Figure 11.9 shows the total sediment load definitions by
the mechanisms of sediment movement, sediment availability in the streambed, and the method
of measurement. Procedures for measurement of fluvial sediment are provided by Guy and Norman (1970). Methods for laboratory analyses of sediment samples are provided by Guy (1969).
FIGURE 11.9
TOTAL SEDIMENT LOAD DEFINITION BY DIFFERENT CLASSIFICATIONS
Guy (1989)
At a particular cross section of a river, the peak of the sediment concentration may coincide with
the peak of the water-discharge, but it may also lag behind or advance in front of the flow peak.
Generally speaking, when the travel distance from the erosion source is short, the peak sediment
concentration usually coincides with the peak flow or somewhat precedes it (Guy, 1989). When
the travel distance from the erosion source is large, the peak of the sediment concentration may
lag behind the peak of the flow. Figure 11.10 from Guy (1989) shows these three types of relationships.
11-52
Hydraulics: Sedimentation
FIGURE 11.10
SEDIMENT CONCENTRATION AND WATER DISCHARGE HYDROGRAPH
(Guy, 1989)
11-53
Hydraulics: Sedimentation
In Maricopa County, there is a lack of adequate sediment discharge and corresponding storm
runoff data. Therefore, it is often necessary to estimate sediment yield from the watershed by
analytic or empirical methods. Techniques of sediment transport modeling, such as HEC-6
(USACE, 1991), are often used in such analyses. Sediment inflow relations are generally
required and those are often in the form of sediment load rating curves of sediment discharge
(tons per day) as a function of water discharge (cfs). Figure 11.11 gives an example of a sediment rating curve.
FIGURE 11.11
EXAMPLE OF A SEDIMENT DISCHARGE RATING CURVE
Sediment Data
Figure 11.12 shows suspended sediment concentration and sediment discharge in rivers of the
conterminous United States in 1980 (Meade and Parker, 1984). The darker brown color on the
map represents higher sediment concentration (mg/l). The size of the semicircles is proportional
11-54
Hydraulics: Sedimentation
to the sediment volume. The numerical values next to the semicircles are the sediment load (in
million tons per year) that is discharged into the coastal zone.
FIGURE 11.12
SEDIMENT CONCENTRATION AND LOAD IN US FOR 1980
(FROM Meade and Parker, 1984)
Table 11.6 lists the suspended sediment to the coastal zone by 10 major rivers of the United
States for the year 1980 (Meade and Parker, 1984). As can be seen, the Mississippi River generates the largest volume of sediment. Figure 11.13, Figure 11.14, and Figure 11.15 show the
historically measured suspended sediment concentration for the Mississippi River, the Colorado
River, and the Gila River, respectively. Figure 11.16 and Figure 11.17 show annual suspended
sediment amount in metric tons for the Colorado River and the Gila River. Figure 11.18 shows a
few measured suspended sediment transport rates in tons/day for several rivers near Maricopa
County, Arizona in 2005.
11-55
Hydraulics: Sedimentation
TABLE 11.6
SUSPENDED SEDIMENT LOAD FOR 10 MAJOR RIVERS IN US IN 1980
(Meade and Parker, 1984)
Rivers
(1)
(2)
Mississippi
2301
Copper
80
Yukon
65
Susitna
25
Eel
15
Brazos
11
10
40
St. Lawrence
1.5
Rio Grande
0.8
Colorado
0.1
11-56
Hydraulics: Sedimentation
FIGURE 11.14
MEASURED SUSPENDED-SEDIMENT CONCENTRATION (MG/L) FOR COLORADO RIVER
(http://co.water.usgs.gov/sediment/)
FIGURE 11.15
MEASURED SUSPENDED-SEDIMENT CONCENTRATION (MG/L) FOR GILA RIVER
(http://co.water.usgs.gov/sediment/)
11-57
Hydraulics: Sedimentation
FIGURE 11.16
ANNUAL SUSPENDED-SEDIMENT DISCHARGE IN METRIC TONS FOR COLORADO RIVER
(http://co.water.usgs.gov/sediment/images/az10.gif)
FIGURE 11.17
ANNUAL SUSPENDED-SEDIMENT DISCHARGE IN METRIC TONS FOR GILA RIVER
(http://co.water.usgs.gov/sediment/images/az20.gif)
11-58
Hydraulics: Sedimentation
FIGURE 11.18
SUSPENDED SEDIMENT DISCHARGE NEAR MARICOPA COUNTY IN 2005
GRAPH GENERATED BASED ON DATA FROM USGS WATER-DATA REPORT AZ-05-1 (Fisk et al, 2005)
o
d c = ----------------------F* ( s )
(11.23)
where:
dc
the sediment specific weight, typically 165 pounds per cubic foot,
11-59
Hydraulics: Sedimentation
F*
F* ranges from 0.03 to 0.06. A value of 0.047 is suggested by Meyer-Peter and Muller (1948).
The bed shear stress in pounds per square foot, is calculated by:
o = RS
(11.24)
where
Incipient analysis, as presented herein, does not cover all aspects of incipient motion. For a discussion of applications, limitations and modifications see (Mussetter et al. (1994), ASCE (1975,
2006), USDOT (2001d), Simons and Senturk (1992), Yang (1973), Simons, Li and Associates
(1985), Chang (1988b), and Shen (1971, 1972, 1973).
Application of incipient motion analysis may provide information on the magnitude of discharge
required to move the particles lining the watercourse bed and/or the banks. These analyses are
generally most reliable and useful for gravel or cobble-bed watercourses. When applied to sandbed systems, incipient motion results usually show that the sediment particles are in motion,
even at small discharges.
11.6.3 Armoring
Armoring occurs when material finer than the incipient motion size is eroded and transported
away leaving a layer of coarser, immobile (for a given discharge) material on the surface. Armoring will occur in time when the channel bed downstream from a dam contains more than 10 percent coarse material which can not be transported under dominant flow conditions (Pemberton
and Lara, 1984). If the watercourse is degrading, this process can continue over a range of discharge events. Each subsequent larger event removes increasingly larger particle sizes. Armoring is effective only to a given magnitude of flood event, flows exceeding that magnitude may
disrupt the armor layer causing bed scour and degradation.
Armoring analysis normally requires the application of incipient motion analysis to determine the
critical sediment particle size, dc. The Shields relation can be used to estimate the sediment critical particle size. Four other methods for estimating the sediment critical particle size, dc, are
11-60
Hydraulics: Sedimentation
given in Pemberton and Lara (1984). It should be cautioned that these methods may give different results. Engineering judgment must be used to select the most appropriate method(s) for
estimating the critical particle size. Once dc is estimated, the decimal percentage of original bed
material larger than dc is determined based on the bed material gradation curve. The scour
depth, Zs, necessary to establish an armor layer can be estimated by Pemberton and Lara (1984)
as follows:
Z s = Y a 1.0
------- 1.0
P
(11.25)
where:
Pc
the decimal percentage (fraction) of bed material coarser than the critical particle size,
Ya
the thickness of the armor layer which is either 3*dc or 0.5 ft, whichever is smaller (Pemberton and Lara, 1984).
Vm = Bf Vw
(11.26)
where:
Bf
Vw
The relationship between total sediment concentration and the bulking factor is given by Figure
11.19. For example, if the sediment load concentration is 200,000 mg/l, the total water-sediment
volume discharge is increased by a factor of about 1.10. For high sediment concentration discharges, design capacities should, based on engineering judgement, accommodate the bulked
volumetric discharge.
11-61
Hydraulics: Sedimentation
FIGURE 11.19
RELATIONSHIP BETWEEN TOTAL SEDIMENT CONCENTRATION AND BULKING FACTOR
(Mussetter et al., 1994)
11-62
Hydraulics: Sedimentation
respective results evaluated. The results by different functions often differ drastically. It is absolutely imperative that the application and limitation of the various transport functions be understood when using the equations to estimate sediment transport. The engineer must use
experience and judgment in both the selection of the sediment transport function and in the interpretation of the results. Yang (2003) gave a detailed discussion on different sediment transport
equations. Thomas et. al. (2002) gave the data range that was used to develop sediment transport equations, see (Mussetter et al. (1994), ASCE (1975, 2006), Yang (1973, 2003), Simons, Li
and Associates (1985), Chang (1988b), USDOT (2001d), Shen (1971, 1972, 1973), Sheppard
(1960), and Simons and Senturk (1992) for further discussions of sediment transport functions.
11-63
Hydraulics: Sedimentation
PHOTOGRAPH 11.10
DEPOSITION UPSTREAM OF ROADWAY EMBANKMENT/CULVERT
Sediment yield is highly dependent upon vegetation cover and precipitation. Langbein and
Schumm (1958) illustrate in Figure 11.20 a trend of increasing sediment yield with increasing
annual (effective) precipitation, until increased precipitation results in improved vegetation cover.
Beyond that point, sediment yield then decreases with increasing precipitation. Maximum sediment yield occurs in the 8 to 15 inches of annual precipitation range. Notice in Figure 11.20 that
the sediment yield is considerably higher when data for small watersheds is used. Smaller
watersheds typically have higher unit sediment yields because of the influence of high intensity
rainfalls that can impact the entire watershed.
11-64
Hydraulics: Sedimentation
FIGURE 11.20
SEDIMENT YIELD, AS AFFECTED BY CLIMATE
(Langbein and Schumm, 1958)
Sediment Yield
(ac-ft/sq. mi./year)
Reference
(see footnote)
No.
Location
Drainage Area
(sq. miles)
(1)
(2)
(3)
(4)
(5)
121.00
0.24
Spookhill FRS, AZ
16.40
0.15
Saddleback FRS, AZ
30.00
0.08
Davis Tank, AZ
0.21
0.96
11-65
Hydraulics: Sedimentation
TABLE 11.7
MEASURED SEDIMENT YIELD FROM REPRESENTATIVE WATERSHEDS
(REPRESENTATIVE OF CONDITIONS TO BE EXPECTED IN MARICOPA COUNTY, AZ)
Sediment Yield
(ac-ft/sq. mi./year)
Reference
(see footnote)
No.
Location
Drainage Area
(sq. miles)
(1)
(2)
(3)
(4)
(5)
Kennedy Tank, AZ
0.97
0.27
Juniper Tank, AZ
2.00
0.29
Alhambra Tank, AZ
6.61
0.03
1.14
0.68
1.56
0.58
10
Mesquite Tank, AZ
9.00
0.03
11
Tank 76, AZ
1.17
0.21
12
Camp Marston, CA
1.59
0.14
13
Embudo Arroyo, NM
20.68
0.07
14
La Cueva, NM
8.00
0.05
15
Baca Arroyo, NM
11.55
0.34
16
2.82
0.22
17
9.33
0.13
18
Bear Arroyo, NM
15.50
0.12
19
Vinyard Arroyo, NM
0.98
0.28
20
Hahn Arroyo, NM
5.80
0.01
21
N. Diversion Channel, NM
101.01
0.21
Average =
0.24
Median
0.21
AZ Average =
0.32
AZ Median =
0.24
11-66
Hydraulics: Sedimentation
TABLE 11.7
MEASURED SEDIMENT YIELD FROM REPRESENTATIVE WATERSHEDS
(REPRESENTATIVE OF CONDITIONS TO BE EXPECTED IN MARICOPA COUNTY, AZ)
No.
Location
Drainage Area
(sq. miles)
(1)
(2)
(3)
Sediment Yield
(ac-ft/sq. mi./year)
Reference
(see footnote)
(4)
(5)
Table footnotes:
A - USACE, 1974
B - USDA, Natural Resources Conservation Service file data
C - Peterson, 1962
D - Langbein et al., 1951
E - Mussetter et al., 1994
The sediment yield data from Table 11.7 are plotted in Figure 11.21 along with an envelope of
sediment yield for 51 watersheds in the United States (Glymph, 1951). It is noted that the U.S.
Army Corps of Engineers used a sediment yield of 0.30 acre-feet per square mile per year for the
design of Cave Buttes Dam in Maricopa County, Arizona (USACE, 1974). Although at the time
(1970), sediment yield for the area immediately upstream of Cave Creek Dam was only 0.24
acre-feet per square mile per year. The larger value (0.30 acre-feet per square mile per year)
was used for design purposes to account for large sediment inflow during the September 1970
flood that is not reflected in the 0.24 acre-feet per square mile per year measurement.
The USACE (1974) indicate a range of sediment yield of 0.009 to 1.33 acre-feet per square mile
per year for watersheds in Arizona and New Mexico. The U.S. Department of Agriculture
(Alonso, 1997), reports sediment yield of 0.12 to 0.4 acre-feet per square mile per year for the
Walnut Gulch Experimental Watershed near Tombstone, Arizona.
The wide range of sediment yield is caused by watershed size, soil conditions, precipitation,
watercourse conditions and other factors. For example, the relatively small yield of 0.08 acre-feet
per square mile per year from the 30 square mile basin above Saddleback Flood Retarding
Structure in Maricopa County, Arizona is possibly due to the land surface being covered with
well-developed desert pavement. The differences in sediment yield are also related to climate
variation. For example, certain watersheds in San Diego County, California reflect yields of only
0.07 and 0.13 acre-feet per square mile per year due to the low annual precipitation of 3 inches
per year. Some sites with a large sediment yield, such as Davis Tank, Arizona, are known to have
watercourse bed and bank erosion. Lastly, other sites with relatively high yield, such as Black
Hills Tank, Arizona, may have experienced a large flood during a short period of data collection.
11-67
Hydraulics: Sedimentation
FIGURE 11.21
REGIONAL SEDIMENT YIELD AS A FUNCTION OF DRAINAGE AREA
LINES INDICATE ENVELOPE FOR 51 U.S. WATERSHEDS BY Glymph (1951)
Runoff and sediment yield data were collected at the Black Hills Tank, near Cave Creek, Arizona,
from 1945 to 1948 (Langbein et al., 1951; Peterson, 1962). The precise location of the site is
uncertain, but it was near the northern end of the McDowell Mountains on a granite pediment at
an elevation of about 2,600 feet. It was possibly the Black Hills Tank located near Dixileta and N.
128th Street. Vegetation was mountain-brush type consisting mainly of snakeweed, yucca, creo-
11-68
Hydraulics: Sedimentation
sote bush, and cactus, with small palo verde and mesquite trees along the channels. According
to Langbein et al. (1951), the approximately 2.5 mile long drainage basin was 1.56 square miles
in area, headed at 3,200 feet elevation, and was drained by a network of 0.5 to 2 feet deep
watercourses at a slope of about 2 percent.
The granitic rock is capped with a thin veneer of coarse residual soil. The watershed sediment
yield was 0.9 acre-feet per year or 0.58 acre-feet per square mile per year based on capacity surveys at the beginning and end of the data collection. A field examination of the 1948 flood reportedly showed coarse sediment with uprooted mesquite trees deposited in a fan at the entrance to
the tank. There was no spill during the period. According to Peterson (1962), the drainage basin
is only 1.14 square miles and the watershed sediment yield is 0.78 acre-feet per year or 0.68
acre-feet per square mile per year. The difference in reported sediment yield for the same watershed is not significant. However, the reported large flood in 1948 is significant because unusually
large amounts of sediment were deposited in the tank. The reported average annual sediment
yield in Table 11.7 for Black Hills Tank for the 4-year period probably is too high because of the
1948 flood. However, those data indicate the magnitude of sediment that can be produced from a
single intense runoff event.
11-69
Hydraulics: Sedimentation
Stone (1981) report sediment yield increases of nearly four times that estimated by the universal
soil loss equation (USLE) as a result of channel and bank erosion at two small watersheds in the
San Pedro Basin.
Headcutting and gully erosion, and their influence on sediment yield, is discussed by Leopold et
al. (1966). Recent headcutting is apparent in the Cave Creek basin especially near the main
channel of Cave Creek. Channel incision also is apparent in the Indian Bend Wash basin such as
Lost Dog Wash at the southern end of the McDowell Mountains. For watersheds larger than a
few acres that have defined channels, mean annual soil loss may or may not be a large part of
the sediment yield. The proportion of sediment yielded from the soil and from watercourse beds
and banks is difficult to estimate.
The above examples indicate that large amounts of sediment can be derived from the watercourses of small desert watersheds. Large amounts of sediment can be derived from rill development, gully formation and watercourse bed and bank erosion where concentrated runoff from
urban development crosses unprotected soil.
Sediment yield/transport numerical simulation models may be used to estimate the sediment
yield. The models include, but are not limited to, KINEROS (Smith et al., 1995), HEM (Lane et
al., 1995), AGWA (Semmens et al, 2001), GSSHA (Downer and Ogden, 2002), and CCHE1D
(Vieira and Wu, 2002). The justification for the selection of a numerical simulation model shall be
discussed with FCDMC staff for approval before it is used.
For estimating the total sediment yield by empirical equations in Maricopa County, it is recommended to use Zeller-Fullerton's total bed material equation for bed material load and MUSLE for
wash load for single events and then to use the probability-based averaging method for annual
sediment yield. The following section will focus on this method.
11-70
Hydraulics: Sedimentation
the Zeller-Fullerton equation over floods of different return periods. The probability-weighted
value over different return period floods can be computed as follows (Mussetter et al., 1994):
(11.27)
(11.28)
where:
Wash_P
Wash_Pi
eroded sediment for i = 2-, 5-, 10-, 25-, 50-, and 100-year
return periods (from using MUSLE);
BedL_P
BedL_Pi
total bed material load for i = 2-, 5-, 10-, 25-, 50-, and 100-year
return periods (from using the Zeller-Fullerton equation).
The above equations require six return periods. Mussetter et al. (1994) also developed a simplified equation that is based on three return periods.
4.32
0.45
n Va G
-
q s = 0.0064 ------------------------------------0.3 0.61
Y h D50
(11.29)
where:
qs
Va
Yh
11-71
Hydraulics: Sedimentation
D50
gradation coefficient,
where:
1 D 84.1 D 50
G = --- ----------- + -----------2 D 50 D 15.9
D84.1, D50 & D15.9
(11.30)
Qs
Q
------ = -----Vw
Vs
(11.31)
where:
Qs
Vs
Vw
Therefore, the total bed material volume for a flood event is:
11-72
Hydraulics: Sedimentation
Qs
V s = V w ------
Q
(11.32)
The sediment volume, Vs, can be found by using the peak sediment discharge, Qs, and peak Q,
and Vw for the specified return periods (2-yr, 10-yr, etc.). Peak Qs is equal to qs multiplied by the
average channel flow width. The annual bed material volume (given in cubic feet) can be found
by using the probability-weighted equation (Equation (11.28)).
(11.33)
where:
median sediment size of the wash load, also defined as the diameter where 50% is finer weight, mm.
Note that D50 is the median sediment size of the wash load and not the median sediment size for
the soil sample. It is rather difficult to estimate D50 of the wash load. Based on Garde and Raju
(1985), the limiting size for the wash load may be D10 for the soil sample on a river bed. Therefore, D50 of the wash load may be approximated by D10 of the sediment sample where D10 is
defined as the diameter of which 10% is finer by weight.
A second method can be used when sediment sampling is not available. In this method, the
FCDMC developed a procedure for estimating specific weight for each Natural Resource Con-
11-73
Hydraulics: Sedimentation
servation Service (NRCS) soil map unit in Maricopa County. It is automated in the latest version
of the DDMSW software. More detailed information can be found in the River Mechanics Manual
for DDMSW (FCDMC, 2010).
This methodology is based on a relationship between the specific weight and sand percentage
(ASCE, 2006) as follows:
= 51 ( P + 2 )
0.13
(11.34)
where:
the percentage of material larger than 0.05 mm; For actual application
when the NRCS soil survey books can be used, P may be assumed to
be the percentage of material larger than 0.074 mm but smaller than
4.75 mm (percent).
Based on the Unified Soil Classification System (USCS) and the Bureau of Reclamation (USBR,
1977), sand is defined as that material which does not pass the No. 200 sieve size (0.074 mm)
but passes the No. 4 sieve size (4.75 mm).
If multiple layers (vertical direction) were present in a specific map unit, only the top layer was
considered. If a map unit was comprised of multiple soil types on the top layer, the map unit percentage of sand was an average of the soil types percentage of sand (e.g., if two soils are present, the total percentage would be the sand percentage of soil 1 plus the sand percentage of soil
2 divided by 2).
However, there were some map units (e.g., Lakes, ponds, reservoirs and rocks) for which a specific weight could not be developed with the above methodology. For lakes, ponds and reservoirs, the specific weight was assumed to be the conservative value of 50 lb/ft3 in the DDMSW
software. For rocks, the specific weight was assumed to be 165 lb/ft3 in DDMSW, which is the
specific weight of quartz.
An average specific weight for the watershed of interest needs to be developed from the
specific weights of each map unit. To find this watershed specific weight, an area-weighted, soil
erodibility-weighted average is automatically calculated with the following equation. The equation has the form:
11-74
tot
Hydraulics: Sedimentation
( K A )
i i i
i = 1
= ---------------------------------- n
(
K
A
)
i i
i = 1
(11.35)
where:
Ki
Ai
tot
The watershed specific weight can then be used to convert the wash load result (from the
MUSLE method) from tons to cubic feet. As a note, for lakes, ponds and reservoirs, the erodibility is zero, and these map units do not contribute to the bulk specific weight of the watershed.
11-75
Hydraulics: Sedimentation
(11.36)
where SDR is the sediment delivery ratio (percent), and AD is the drainage area (square miles).
The regression equation should only be used for drainage areas larger than 0.04 square miles
and smaller than 500 square miles.
FIGURE 11.22
RELATIONSHIP BETWEEN DRAINAGE AREA AND SEDIMENT DELIVERY RATIO
(MODIFIED FROM USDA, 1972)
TABLE 11.8
RELATIONSHIP BETWEEN DRAINAGE AREA AND SEDIMENT DELIVERY RATIO
(MODIFIED FROM USDA, 1972)
11-76
Drainage Area
(square miles)
FCDMC
Recommended
(percent)
0.04
87
0.1
77
0.2
72
Hydraulics: Sedimentation
TABLE 11.8
RELATIONSHIP BETWEEN DRAINAGE AREA AND SEDIMENT DELIVERY RATIO
(MODIFIED FROM USDA, 1972)
Drainage Area
(square miles)
FCDMC
Recommended
(percent)
0.4
67
61
57
15
47
30
44
57.53
41
200
35.5
500
32
Y s = ( Vq p ) KLSCP
(11.37)
where:
Ys
qp
= peak flow rate from a storm event of a particular return period, in cfs;
= 95;
= 0.56;
11-77
Hydraulics: Sedimentation
= the soil erodibility factor which can be obtained from Figure 11.23. An
Arcview shape file of NRCS soil map units containing default tabulated
values for K may be obtained from FCDMC; the FCDMC has developed
preliminary values for K values for all soil map units in Maricopa County
based on the NRCS Web Soil Survey data http://websoilsurvey.nrcs.usda.gov/app/HomePage.htm (this allows automation of estimating averaged K value for a watershed); more discussion on K
values is provided in Section 11.7.3.8.
LS
n
2
LS = ---------- ( 0.065 + 0.0454S + 0.0065S )
72.6
(11.38)
where:
the cover and management factor. Arcview shape files for land use
from Maricopa Association of Governments (MAG) may be used in
conjunction with a land use table to automatically compute the C factor;
the FCDMC has developed preliminary values of C for all land use
types in Maricopa County based on the MAG's land use GIS shape file;
these values serve as a good starting point and allow the automatic
estimation of C value for a watershed; more discussion can be found in
Section 11.7.3.8.
the erosion control practice factor (usually 1.0 for wild land areas). P
values for erosion control methods in an agricultural field can be
obtained from Wischmeier and Smith (1978).
Slope length, , is defined as the distance from the point of origin of overland flow to the point
where either the slope gradient decreases enough such that deposition begins, or the runoff
water enters a well-defined channel that may be part of a drainage network or a constructed
channel. Percent slope, S, is the slope for the slope length. It is in percent, for example, 30 for
30%. It may be approximated by the average watershed slope (Simons, Li and Associates,
1985). The MUSLE equation is best used for slope lengths of less than 400 ft and gradients of 3
to 8 percent.
11-78
Hydraulics: Sedimentation
The cover and management factor, C, can be divided into three distinct types of effects as follows:
C = C I C II CIII
(11.39)
where:
(11.40)
CI
CII
CIII
Type III, the tillage and residual effects of the land use as shown in
Figure 11.26 (Simons, Li and Associates, 1985),
11-79
Hydraulics: Sedimentation
FIGURE 11.23
SOIL ERODIBILITY FACTOR (K)
(Wischmeier and Smith, 1978)
11-80
Hydraulics: Sedimentation
FIGURE 11.24
INFLUENCE OF VEGETAL CANOPY ON EFFECTIVE RAINFALL (Ci)
(Wischmeier and Smith, 1978)
11-81
Hydraulics: Sedimentation
FIGURE 11.25
EFFECT OF PLANT RESIDUES OR CLOSE-GROWING STEMS AT SOIL SURFACE (Cii)
(Wischmeier, 1972)
FIGURE 11.26
TYPE III EFFECTS ON UNDISTURBED LAND AREAS (Ciii)
(Wischmeier, 1972)
11-82
Hydraulics: Sedimentation
2.
3.
4.
5.
6.
Estimation of scour depth for bridge piers, embankments, guide banks, and spur
dikes.
The estimation of scour is critical to the evaluation of the watercourse stability at and near highway structures. Procedures to investigate watercourse stability are provided in HEC-20 (USDOT
2001c). Procedures to provide bridge scour countermeasures are provided in HEC-23 (USDOT,
2001a). The estimation of scour is an engineering application that requires both specific exper-
11-83
Hydraulics: Sedimentation
tise and experience. Every application of scour technology is unique because of the wide variability of hydrologic, hydraulic and geologic/geomorphic factors. It is not possible to compile a
comprehensive methodology in a drainage design manual that would be adequate to address all
aspects of scour estimation. In addition, the knowledge of erosion and sedimentation is continually expanding because of the need to provide better technology in this field of engineering.
Often, newer methodologies are presented in the engineering literature that should be considered and used, if appropriate. The following are general guidelines for estimating scour along
with currently used methodologies that are considered applicable in Maricopa County.
2.
3.
4.
5.
6.
Local scour due to bridge pier, bridge abutment, guide bank, etc.
Total scour, Z t , is the sum of each of these individual components, Z i , of scour. Total scour can
be expressed as:
(11.41)
where:
FS
FSlocal
the factor of safety for local scour such as pier scour, downstream
scour for drop structure/grade control structures and other local
scour components.
The factor of safety is often used for hydraulic engineering design to account for uncertainties in
hydraulic engineering analyses. In general, a factor of safety of 1.3 for long-term, general, bend,
bedform and low flow incisement scour should be used for the design of toe-down for bank protection. However, a lower value of the safety factor may be used under special circumstances
with prior approval from the FCDMC and other jurisdictional agencies. The use of a higher safety
factor, such as 1.5, may be justified where underestimation of scour could cause catastrophic
failure that may result in loss of life or unacceptable economic consequences. The local scour
safety factor, FSlocal, may be less than 1.3 under special conditions, such as in the calculation of
11-84
Hydraulics: Sedimentation
pier local scour when the debris width is added to the pier diameter or in the calculation of drop
structure downstream scour when the result shows unreasonably large local scour. A safety factor of less than 1.3 may also be used for abutment scour because the abutment scour methodology often over-estimates the value.
In general, the recommended toe-down depth or utility burial depth is the total scour depth below
the channel thalweg for areas inside the FEMA floodway or main channel banks (Figure 11.27).
The thickened dash line in Figure 11.27 represents the toe-down or utility burial depth. The channel thalweg is the lowest point on a channel cross section. The velocity for computing the total
scour depth within the floodway or main channel should be the main channel velocity or floodway
velocity, whichever is larger. The toe-down depth or utility burial depth is the total scour depth
below the adjacent ground for areas on the lateral-erosion line (Figure 11.27). The procedure for
estimating the lateral-erosion line can be found in Section 11.9. For areas between the FEMA
floodway line and the lateral erosion line, the toe-down depth or utility burial depth can be linearly
interpolated as shown in Figure 11.27. For areas between the lateral erosion line and the FEMA
floodplain line, the toe-down depth or utility burial depth can be linearly interpolated between the
toe-down/burial depths at the lateral erosion line and the FEMA floodplain line. The toe-down/
burial depth at the FEMA floodplain line can be the total scour depth based on overbank velocity
and flow depth. The overbank velocity may be obtained from an existing HEC-RAS model.
Figure 11.28 illustrates the recommended toe-down depth or utility burial depth for a very erosive
condition where very erosive material is found in the channel bank and bed and large erosion
and channel migration were observed in the past. Figure 11.29 and Figure 11.30 illustrate the
recommended toe-down depth or utility burial depth for a situation where the lateral erosion line
is outside the FEMA floodway line. It may be noted that areas outside the FEMA floodplain may
be beyond the floodplain administrators jurisdiction. Engineering judgment is highly recommended about the toe-down or burial depth for areas outside the FEMA floodplain but within the
lateral erosion line.
The following is a discussion of each component of scour that should normally be considered
when estimating total scour. FCDMCs DDMSW software can be used to estimate the scour
components. The software can be downloaded from FCDMCs web site at (http://www.fcd.maricopa.gov).
.
11-85
Hydraulics: Sedimentation
FIGURE 11.27
TOE-DOWN AND UTILITY BURIAL DEPTH (EROSION, INSIDE FLOODPLAIN)
(LATERAL EROSION LINE IS INSIDE FLOODPLAIN LINE)
11-86
Hydraulics: Sedimentation
FIGURE 11.28
TOE-DOWN AND UTILITY BURIAL DEPTH (VERY EROSIVE, INSIDE FLOODPLAIN)
(A VERY EROSIVE CONDITION; LATERAL EROSION LINE IS INSIDE FLOODPLAIN LINE)
11-87
Hydraulics: Sedimentation
FIGURE 11.29
TOE-DOWN AND UTILITY BURIAL DEPTH (EROSION, OUTSIDE FLOODPLAIN)
(LATERAL EROSION LINE IS OUTSIDE FLOODPLAIN LINE)
11-88
Hydraulics: Sedimentation
FIGURE 11.30
TOE-DOWN AND UTILITY BURIAL DEPTH (VERY EROSIVE, OUTSIDE FLOODPLAIN)
(A VERY EROSIVE CONDITION; LATERAL EROSION LINE IS OUTSIDE FLOODPLAIN LINE)
11-89
Hydraulics: Sedimentation
2.
3.
4.
Trend Analysis
A trend analysis of historic bed elevation data is limited by the availability of adequate, long-term
data for the watercourse. Therefore, such an analysis may be possible only for some of the
major watercourses in Maricopa County. In addition, factors such as instream gravel mining and
channelization of the watercourse may complicate such historic analyses.
11-90
Hydraulics: Sedimentation
Site-specific bed material sediment data is needed for sediment transport modeling. The bed
material sediment sampling approval should be based on Pemberton and Lara (1984).
The inflowing sediment load for various discharges for the study reach may be estimated by (1)
field measurement at the study reach upstream end (very unlikely in Maricopa County), (2) use of
an appropriate sediment transport equation if the upstream supply reach is in an equilibrium condition, and (3) an iterative sediment transport modeling approach for the upstream supply reach if
the supply reach is in equilibrium (trial of different sediment inflow loads for supply reach until the
sediment outflow for the supply reach is equal to the sediment inflow). However, when HEC-6T
is used, the recirculation option may be used to automatically determine the inflowing sediment
load.
An equilibrium condition for a channel reach is where the inflowing sediment load (volume or
peak sediment discharge) for a channel reach is the same as the sediment outflow load (volume
or peak sediment discharge). It corresponds to the case where there is no overall channel degradation or aggradation. If no significant channel degradation or aggradation is observed from
aerial photos, topographic data comparison, and field visits, the channel may be considered in an
equilibrium condition. When using the sediment transport modeling approach, if the immediate
upstream supply reach is not in equilibrium, one should look further upstream until an equilibrium
condition reach is located.
11-91
Hydraulics: Sedimentation
Z long-term = L S
(11.42)
where:
Zlong-term
S0-Seq
where:
S0
Seq
When the equilibrium slope is larger than the existing bed slope upstream from the pivot point, it
would indicate aggradation rather than degradation. When it is an aggradation zone, the longterm scour depth may be considered zero as part of the total scour depth for structures design,
because the long-term equilibrium status is dynamic and simply deducting aggradation depth
from the total scour depth may under-estimate the total scour depth.
Application of long-term degradation is illustrated by the following:
A natural watercourse has a slope of 22 feet per mile (0.0042 ft/ft). Proposed channelization of the watercourse will increase the unit discharge and the equilibrium slope is estimated to decrease to 15 feet per mile (0.0028 ft/ft). A drop structure is proposed at a
distance of 2,000 feet upstream of a pivot point (armored channel cross section). The
long-term degradation at the toe of the drop structure is estimated by:
11-92
Hydraulics: Sedimentation
D*B 3 4
S eq = 0.00174 -----------
Q
(11.43)
where:
Seq
D50
For the sediment-laden condition where there is no upstream reservoir, sand or gravel pits, or
hydraulic structures that will significantly reduce the sediment load to the study reach, the iterative method should be used based on Section 5.3.7 in Design Manual for Engineering Analysis of
Fluvial Systems (Simons, Li and Associates, 1985). The requirement of this method is that the
immediate upstream supply reach must be in an equilibrium condition where the inflowing sediment load and outflowing sediment load for the upstream supply reach are the same. This can
be checked by historical and recent aerial photos, topographic maps, and field visits. If no significant aggradation or degradation is found in the supply reach, then the supply reach may be considered in equilibrium and an appropriate total bed material load equation such as the ZellerFullerton equation, Equation (11.44), (Zeller and Fullerton, 1983) can be used to estimate the
sediment load from the supply reach. When the immediate upstream supply reach is not in equilibrium, one should consider a longer supply reach where the channel may reach equilibrium or
look for an equilibrium segment further upstream. Once the supply reach has been verified that it
is in an equilibrium condition, the Zeller-Fullerton (Zeller and Fullerton, 1983) total bed material
load equation, Equation (11.44), can be used to estimate the sediment load for the supply reach,
which is the sediment inflow to the study reach. The total bed material sediment discharge
based on Zeller-Fullerton equation is:
1.77
0.45
n V a4.32 G
- W
Q s = q s W = 0.0064 ------------------------------------0.61
Y h0.3 D 50
(11.44)
where:
Qs
qs
11-93
Hydraulics: Sedimentation
Va
Yh
D50
1 D 84.1 D 50
G = --- ----------- + -----------2 D 50 D 15.9
(11.45)
and D84.1, D50 and D15.9 are sediment diameters based on a percent finer by dry weight, mm.
After the supply total bed material sediment discharge is computed, one uses the Zeller-Fullerton
equation to compute the total bed material sediment discharge for the study reach. If the sediment discharge for the study reach is equal to the supply sediment discharge, then the current
channel bed slope for the study reach is the equilibrium slope. If not equal, one should vary the
channel bed slope such that the sediment discharge for the study reach is equal to the supply
reach sediment discharge. Once the sediment discharges are equal, the computed bed slope is
the equilibrium slope. During this iteration process, Manning's equation or HEC-RAS may be
used to compute the hydraulic variables.
When the immediate upstream supply reach is not in equilibrium, one should consider a longer
upstream supply reach where the channel may reach equilibrium or look for an equilibrium segment further upstream.
11-94
Hydraulics: Sedimentation
w
d 50 = kV a2 ----------------
s w
(11.46)
where:
d50
the required median sediment particle diameter for which 50% of the
material (by weight) finer, ft;
Va
11-95
Hydraulics: Sedimentation
If the entire channel bed is not covered with large cobbles/rocks, but a large amount of rocks are
observed on the surface, it may be reasonable to assume that an armored layer may eventually
develop at a certain depth below the bed surface. When the channel bed surface and sub-surface contains more than 10% coarse material, which can not be transported under dominant flow
conditions, d90>dc, armoring will eventually develop at a certain depth below the surface (Pemberton and Lara, 1984). This depth may be assumed to be the long-term scour depth, Zs, which
can be estimated by Equation (11.25).
11-96
Hydraulics: Sedimentation
qf
Z general = Zd i ---qi
(11.47)
where:
Zgeneral
di
average depth at bankfull discharge in incised reach, ft (= hydraulic depth for bankfull discharge or dominant discharge);
qf
design flood discharge per unit width (width can be defined as wetted cross sectional area divided by flow depth where flow depth
can be the Mannings equation-based normal depth or maximum
flow depth from HEC-RAS), cfs/ft;
qi
bankfull discharge in incised reach per unit width (bankfull discharge can be from HEC-RAS main channel flow discharge
between appropriate bank stations or taken as the 10-year event
with the same definition as dominant discharge (Simons, Li and
Associates, 1985); width can be defined as wetted cross section
area divided by depth where flow depth can be the Mannings
equation-based normal depth maximum flow depth from HECRAS, cfs/ft;
exponent varying from 0.67 for sand to 0.85 for coarse gravel; and
11-97
Hydraulics: Sedimentation
The HEC-18 contraction scour equations (USDOT, 2001b) are used to predict the depth of the
contraction scour component in a contracted section. The equations for the clear-water condition
and the live-bed condition are different. The following equation for critical velocity can be used to
determine if the flow upstream of the bridge is clear-water or live-bed (USDOT, 2001b). The
equation has the form:
1 3
V c = 11.17y a1 6 D 50
(11.48)
where:
Vc
ya
D50
The D50 is taken as an average of the bed material size in the reach of the stream upstream of
the contraction.
When Vc < mean velocity, the live-bed equation should be used. Conversely, when Vc > mean
velocity, use the clear-water equation.
Live-bed Contraction Scour
The live-bed contraction scour equation is the modified Laursen equation (USDOT, 2001b) given
as:
Q 2 6 7 W 1 k1
y2
----- = ------ -------
Q1
W2
y1
(11.49)
ys = y2 y0
(11.50)
and
where:
11-98
ys
y0
y1
y2
Hydraulics: Sedimentation
Q1
Q2
W1
W2
bottom width of the main channel in the contracted section less pier
widths, ft;
k1
Please note that Q1 may be smaller than, larger than or equal to Q2, since there are varied flow
conditions, and Q1 is defined as the flow that is carrying sediment. This means that in some
cases wide shallow overbank areas will not be counted in Q1, but may be counted in Q2 if the
entire flow is pushed through the contracted section.
TABLE 11.9
VALUES OF K1
(USDOT, 2001b)
( V* )
k1
<0.5
0.59
0.5 to 2.0
0.64
>2.0
0.69
V*
S1
fall velocity in m/s of bed material from Figure 11.31 based on using D50 as
Ds in mm, or in ft/s from regression equations developed by FCDMC as follows:
= 3.28*10
11-99
Hydraulics: Sedimentation
where:
for 40o C:
(11.51)
+ 0.049991(log10D50)3
for 20o C:
a
(11.52)
+ 0.052387(log10D50)3
for 0o C:
a
(11.53)
+ 0.012187(log10D50)3
D50
11-100
Hydraulics: Sedimentation
FIGURE 11.31
FALL VELOCITY
(USDOT, 2001b)
11-101
Hydraulics: Sedimentation
ys = y2 y0
(11.54)
0.0077Q 2 3 7
-
y 2 = --------------------- D m2 3 W 2
(11.55)
where:
ys
y2
Dm
D50
bottom width of the contracted section less pier width, ft; and
y0
Lacey Equation
The Lacey equation is more applicable to a natural river system (Blench, 1969) where there are
no upstream structures that capture sediment:
Q
Z general = Z 0.47 ---
f
13
(11.56)
where:
11-102
Zgeneral
Dm
Hydraulics: Sedimentation
The bend scour should be computed for the areas both at the bend and downstream of the bend
because the secondary currents will still cause scour downstream of the bend. The distance from
the bend at which the secondary currents will have decayed to a negligible magnitude can be
found in Section 11.8.2.3.
Blench's Equation
The Blench equation, as presented in Pemberton and Lara (1984), is more applicable to clearwater flow conditions when there is a reservoir, sand and gravel pit, or hydraulic structure
upstream that will significantly reduce the sediment supply.
Blench's equation is as follows:
Z general
q f2 3
= Z ---------1 3
F b0
(11.57)
where:
Zgeneral
qf
multiplying factor (0.6 for a straight channel reach and 1.25 for a
vertical rock bank or wall. If there is a bend, the bend scour equation by Zeller should be used to compute the bend scour; see
Bend Scour Section 11.8.2.3); and
Fb0
Blenchs zero bed factor from Figure 11.32 or from the equation
developed by the FCDMC, which is:
(11.58)
where:
D50
11-103
Hydraulics: Sedimentation
FIGURE 11.32
CHART FOR ESTIMATING Fb0FOR THE BLENCH EQUATION
(Pemberton and Lara, 1984)
11-104
(11.59)
Hydraulics: Sedimentation
where:
=
computed value when 0.5 < r c T < 10.0 or 17.8 o < < 60 o ;
rc
Va
yh
Se
Zbend
FIGURE 11.33
SKETCH OF CHANNEL BEND
(Simons, Li and Associates, 1985)
11-105
Hydraulics: Sedimentation
The bend scour equation should be applied to the entire channel reach through the bend. It
should also be applied to a certain distance downstream from the end of the bend because secondary currents will still cause scour in the downstream reach. The distance from the end of a
bend at which the secondary currents will have decayed to a negligible magnitude can be estimated per Simons, Li and Associates, 1985, as:
C
X = 2.3 ------- Y
g
(11.60)
where:
X
1.486
n
depth of flow (to be conservative, use maximum depth of flow, including superelevation and exclusive of scour, within the bend), feet.
This equation may also be used to determine the distance when the Neill equation and the Lacey
equation include the bend scour.
Z bedform = 0.5d h
(11.61)
where:
11-106
Zbedform
dh
Hydraulics: Sedimentation
Dunes form during lower regime flow, typically at Froude Numbers, Fr, less than 0.7. The Froude
Number is defined as V a gy h where Va is the average channel velocity, g is gravitational
acceleration (32.2 feet/second2); and yh is the hydraulic depth. Antidunes form during the upper
regime flow where Fr is greater than or equal to 1.0 and may form during the transition from
lower to upper regime flows. In the transition region where Fr is between 0.7 and 1.0, the larger
of either dune or antidune height should be used.
The dune height equation for lower regime flow where F r < 0.7 is shown per Gyr and Hoyer,
2006 and Zanke, 1976, as:
dh
0.15 < ----- < 0.3
yh
(11.62)
where:
dh
yh
Since a range is given for dune height in the above equation, engineering judgment should be
exercised to judiciously select a dune height within the given range.
The anti-dune height equation (based on Kennedy, 1961) for upper regime flow where Fr > 1.0 is
shown per Simons, Li & Associates, 1985, as:
d h = 0.027V a2
(11.63)
where:
dh
Va
When 1.0 F r 0.7 , the higher value between the dune height equation and anti-dune height
equation should be used.
11-107
Hydraulics: Sedimentation
value should be used for regional watercourses. When there is channelization where the channel bed is graded, the low flow channel depth may be estimated by assuming a small peak discharge (2-year event) for a simple chart that relates the depth to the channel-forming discharge
(Figures 5-10 in USACE, 1994). If the low-flow channel is very stable and the toe-down or total
scour is measured from the channel thalweg (lowest elevation in the entire cross section), this
scour component may be ignored in the total scour computation. However, engineering judgment must be carefully exercised to avoid over-estimation or under-estimation of low-flow channel depths.
Generally, local scour depths are much larger than long-term degradation or general scour.
However, if there are major changes in watercourse conditions, such as a water storage facility
built upstream or downstream or severe straightening of the watercourse, long term bed elevation changes can be the larger element in the total scour estimate.
11-108
Hydraulics: Sedimentation
Bridge local scour and culvert outlet local scour are discussed in the following sections. The estimation of bridge guide bank scour is similar to the bridge abutment scour estimation procedure
(USDOT, 2001b). When estimating the bank protection scour or abutment scour and if the bank
protection or abutment is close to piers, scour hole influence zones should be computed. The
scour due to influence zones at the bank protection or abutment should be added to the total
scour. A certain minimum distance, based on engineering judgment, between the piers and
abutments should be preserved to minimize the scour impact to each other.
Local scour downstream of a hydraulic structure can be estimated by empirical equations from
Schoklitsch (1932), Veronese (1937), and Zimmerman and Maniak (1967). Pemberton and Lara
(1984) or the original references should be consulted and engineering judgment should be exercised when selecting or applying any of these equations.
PHOTOGRAPH 11.12
CULVERT CAUSES BACKWATER RESULTING IN UPSTREAM AGGRADATION.
For a submerged structure, the local scour depth can be estimated by the Simons, Li & Associates (1986) equations. These equations are a function of grade control structure face slope,
drop height and other hydraulic parameters, but are independent of bed material grain size.
These equations may overestimate scour depth for coarse bed material watercourses. Simons,
Li & Associates (1986) should be consulted when using these equations.
In this chapter, the scour caused by sand and gravel mining operations is classified as local
scour. There are two types of erosion caused by sand and gravel mining. One is erosion that
starts from the pit's upstream brink point and moves upstream, which is called headcut. Another
is erosion that starts from the pit's downstream brink point and moves downstream, which is
called tailcut. The estimation of headcut and tailcut may be done by both empirical equations
11-109
Hydraulics: Sedimentation
and sediment transport modeling. The available empirical equations are the methodology developed for the Arizona Department of Transportation (ADOT) by Li, et al. in 1989. However, it has
been found that the methodology provides a reasonable estimate for headcut scour depth at the
knickpoint but may under-estimate the headcut distance (FCDMC, 2006). Sediment transport
modeling can be performed to estimate the headcut and tailcut by using HEC-6, HEC-6T, FLUVIAL-12 or other FCDMC-approved models. However, since most models are one-dimensional,
when the pit width is much smaller than the river width, the model input file may need to be set up
in a way that flow can be confined in a corridor that is equivalent to the pit width.
y 0.35 0.43
Z local
------------- = 2.0K 1 K 2 K 3 K 4 ----1-
Fr
a
a
(11.64)
where:
11-110
Zlocal
y1
flow depth directly upstream of the pier, ft (= normal depth from Mannings equation; maximum channel depth from HEC-RAS);
K1
correction factor for pier nose shape from Table 11.10 and Figure
11.34;
K2
correction factor for angle of attack of flow from Table 11.11 and discussion below;
K3
correction factor for bed condition from Table 11.12 (note: if the bed
form scour is already computed based on bed form trough depth,
then K3 should be set to 1.0 to avoid double-counting of the bed
condition scour);
K4
Fr
V1
Hydraulics: Sedimentation
TABLE 11.10
CORRECTION FACTOR, K1, FOR PIER NOSE SHAPE
(USDOT, 2001b)
Shape of Pier Nose
K1
1.1
1.0
1.0
1.0
0.9
FIGURE 11.34
PIER NOSE SHAPE
(USDOT, 2001b)
11-111
Hydraulics: Sedimentation
TABLE 11.11
CORRECTION FACTOR, K2, FOR FLOW ANGLE OF ATTACK
(USDOT, 2001b)
Angle (degree)
L/a=4
L/a=8
L/a=12
1.0
1.0
1.0
15
1.5
2.0
2.5
30
2.0
2.75
3.5
45
2.3
3.3
4.3
90
2.5
3.9
5.0
(11.65)
where:
TABLE 11.12
CORRECTION FACTOR, K3, FOR BED FORM CONDITION
(USDOT, 2001b)
Bed Condition
K3
Clear-Water Scour
N/A
1.1
N/A
1.1
3 > H 0.6
1.1
9>H3
1.2 to 1.1
H9
1.3
Small Dunes
Medium Dunes
Large Dunes
11-112
Hydraulics: Sedimentation
K 4 = 0.4 ( V R )
0.15
(11.66)
where:
V 1 V icD50
->0
V R = ------------------------------V cD50 V icD95
(11.67)
where:
V1
50 or 95.
D x 0.053
V icDx = 0.645 ------
V cDx
a
(11.68)
where:
V cD x
V cD x
11.17y11 6 Dx1 3
where:
y1
Dx
11-113
Hydraulics: Sedimentation
While K4 provides a good fit with the field data, the velocity ratio terms are so formed that if D50
is held constant and D95 increases, the value of K4 increases rather than decreases. For field
data an increase in D95 was always accompanied with an increase in D50. The minimum value of
K4 is 0.4.
Z local
L
------------- = 2.27K 1 K 2 ----ya
ya
0.43
Fr
0.61
+1
(11.69)
where:
Zlocal
ya
K1
coefficient for abutment shape from Figure 11.35 and Table 11.13;
K2
K2
( 90 )
0.13
11-114
L'
Fr
Ve
Q e A e , ft/s;
Ae
flow area of the approach cross section obstructed by the embankment, ft2;
Qe
1 2
Hydraulics: Sedimentation
The HIRE equation is used when the ratio of the length of the abutment (normal to flow) to flow
depth L y a > 25 , (USDOT, 2001b). It has the form:
Z local
0.33 K 1
------------- = 4Fr ---------- K 2
0.55
y1
(11.70)
where:
Zlocal
y1
depth of flow at the abutment on the overbank or in the main channel, ft;
K1
coefficient for abutment shape from Figure 11.35 and Table 11.13;
K2
( 90 )
0.13
FIGURE 11.35
COMMON ABUTMENT SHAPES
(USDOT, 2001b)
11-115
Hydraulics: Sedimentation
TABLE 11.13
ABUTMENT SHAPE COEFFICIENTS
(USDOT), 2001b)
Description
K1
Vertical-wall abutment
1.00
0.82
Spill-through abutment
0.55
FIGURE 11.36
ABUTMENT SKEW; FOR ABUTMENTS ANGLES UPSTREAM
(USDOT, 2001b)
11-116
Hydraulics: Sedimentation
FIGURE 11.37
LENGTHS OF EMBANKMENT
(USDOT, 2001b)
Z local
L
------------- = 1.248 ----ya
ya
0.43
Fr
0.61
+1
(11.71)
where:
Zlocal
ya
L'
11-117
Hydraulics: Sedimentation
Fr
Ve
Q e A e ft/s;
Ae
flow area of the approach cross section obstructed by the embankment, ft2;
Qe
1 2
When the ratio, L/ya, between the embankment projected length, L, normal to the flow and floodplain average depth, ya, is greater than 25, the HIRE equation becomes:
Z local
0.33
------------- = 4.0Fr
y1
(11.72)
where:
Zlocal
y1
depth of flow at the abutment on the overbank or in the main channel, ft; and
Fr
- ---------------Q - ---t-
local W local L local V local
Z
------------, ---------------, -------------, ------------- = C s C h --------- Rc
1 3 gR 2.5 t o
Rc
Rc
R c3
(11.73)
where:
11-118
Zlocal
Wlocal
Llocal
Hydraulics: Sedimentation
Vlocal
Rc
hydraulic radius at the end of the culvert (assuming full flow), ft;
discharge, cfs;
to
( D 84 D 16 )
D16
D84
, ,
0.5
Cs
Ch
If the soil is cohesive in nature the above equation should not be used. The equation in Section
5.2 (pages 5-6) of USDOT (2006) should be used.
TABLE 11.14
COEFFICIENTS FOR CULVERT OUTLET SCOUR IN COHESIONLESS SOILS
(USDOT, 2006)
Depth, Zlocal
2.27
0.39
0.06
Width, Wlocal
6.94
0.53
0.08
Length, Llocal
17.1
0.47
0.1
Volume, Vlocal
127.08
1.24
0.18
11-119
Hydraulics: Sedimentation
TABLE 11.15
COEFFICIENT, CS, FOR CULVERT SLOPE
(USDOT, 2006)
Slope %
Depth
Width
Length
Volume
1.03
1.28
1.17
1.3
1.08
1.28
1.17
1.3
>7
1.12
1.28
1.17
1.3
TABLE 11.16
COEFFICIENT, CH, FOR OUTLETS ABOVE THE BED
(USDOT, 2006)
1H
Hd1
Depth, Zlocal
Width, Wlocal
Length, Llocal
Volume, Vlocal
1.22
1.51
0.73
1.28
1.26
1.54
0.73
1.47
1.34
1.66
0.73
1.55
d is
Schoklitsch Equation
The Schoklitsch equation was developed to calculate scour depth below a structure with a free
overfall of water on an unprotected river bed. It can also be used for evaluating local scour below
a sharp-crested spillway, drop structure or grade control structure. It has the form:
0.2 0.57
q -y
Z loc = 3.15H
------------------------------m
0.32
D 90
11-120
(11.74)
Hydraulics: Sedimentation
where:
Zlocal
design discharge per unit width (= design discharge divided by average flow width; the average flow width can be defined as wetted
cross section area divided by flow depth where flow depth can be
the Mannings equation-based normal depth or maximum flow depth
from HEC-RAS), cfs/ft;
D90
ym
Veronese Equation
The Veronese equation for computing the scour depth below a low head stilling basin design is in
the form:
0.225 0.54
Z local = 1.32H T
ym
(11.75)
where:
Zlocal
HT
design discharge per unit width (= design discharge divided by average flow width; the average flow width can be defined as wetted
cross section area divided by flow depth where flow depth can be
the Mannings equation-based normal depth or maximum flow depth
from HEC-RAS), cfs/ft; and
ym
Z local
0.93
q 0.82 y m
- ----------
= 1.95 --------------- ym
D 85 0.23 q 2 3
(11.76)
11-121
Hydraulics: Sedimentation
where:
yloc
design discharge per unit width (= design discharge divided by average flow width; the average flow width can be defined as wetted
cross section area divided by flow depth where flow depth can be the
Mannings equation-based normal depth or maximum flow depth
from HEC-RAS), cfs/ft; and
D85
ym
FIGURE 11.38
TYPICAL CROSS SECTION FOR A NATURAL CHANNEL
11-122
Hydraulics: Sedimentation
As illustrated in Figure 11.39, the lateral-erosion zone is determined by the lateral-erosion distances measured from the FEMA floodway lines, or the main-channel bank stations whichever
gives a larger value. If a FEMA floodway has not been delineated, a HEC-RAS model should be
developed to estimate the 100-year floodway line. The main-channel bank locations can be
determined by the standard approach for selecting main-channel bank stations in HEC-RAS
modeling. If a FCDMC-approved HEC-RAS model exists, the bank stations in the hydraulic
model should be used as the main-channel bank stations. Under some special conditions, the
main-channel bank stations may be used instead of the floodway lines with a prior approval by
FCDMC staff. One special condition may be a sand and gravel mining pit that is located near an
outdated FEMA floodway line and the pit owner owns the property adjacent to the lateral-erosion
zone.
When the FEMA floodway elevations and bank station elevations on both banks are not the
same, the highest elevation among floodway elevations and bank station elevations should be
used to determine the starting point for measuring the lateral-erosion distance. For example, Figure 11.39 shows that the FEMA floodway elevation on the right bank (looking into the paper) is
higher than the left FEMA floodway elevation and the two bank station elevations. It should be
used as the starting point for measuring the lateral-erosion distance for the right bank. For the left
bank, a horizontal line should be drawn to intersect the left bank. The intersection point should be
used as the starting point for measuring the left lateral-erosion distance.
11-123
Hydraulics: Sedimentation
.
FIGURE 11.39
LATERAL EROSION ZONES FOR TYPICAL STRAIGHT CHANNELS
The methodology presented herein is developed by adapting the City of Austins Guidance on
Establishing an Erosion Hazard Zone for Structure and Utility Locations near Streams (City of
Austin, September, 2007) and Erosion Setback and Stabilization Criteria for City of Austin
Streams (Ayres Associates, 2004). Essentially, the lateral-erosion distance is three times or six
times the main-channel potential incision depth measured from the FEMA floodway line or chan-
11-124
Hydraulics: Sedimentation
nel bank line whichever is greater. When historical aerial photos are available to estimate the
historical lateral-erosion distance due to a single flood event, the lateral-erosion distance is the
largest lateral-erosion distance due to the single flood event plus three times the main-channel
potential incision depth. When historical aerial photos are not available, the lateral-erosion distance is six times the main-channel potential incision depth. The slope of 6:1 (horizontal:vertical)
is Ayres (2004) recommendation for alluvial channels. The details for computing lateral-erosion
distance are discussed in the rest of this section.
The procedure is presented for several scenarios which are (1) a straight channel reach when
sufficient historical aerial photos are available to estimate the largest single-event lateral-erosion
distance; (2) a straight channel reach when there are not sufficient historical aerial photos to estimate the largest single-event lateral-erosion distance; (3) when the project site is located
between upstream and downstream bends; and (4) when the project site is located on a straight
reach, but upstream or downstream of a bend. Areas that are within the FEMA floodway are considered to be automatically within the lateral-erosion zone. Lateral-erosion is assumed to be limited by man-made or natural physical constraints such as bank protection, bedrock, or other
lateral-erosion-resistant features. However, detailed engineering and geologic analyses must be
performed in order to remove an area from the lateral-erosion zone because of man-made or
natural physical constraints. Since the methodology is related to the FEMA 100-year floodplain
and scour analysis for a 100-year flood, the results can be considered as the 100-year lateralerosion hazard zone.
11-125
Hydraulics: Sedimentation
L = L H + 3 ( 3D ) = L H + 9D
(11.77)
where:
LH
If the total scour depth for the 100-year flood event is estimated based on FCDMCs total scour
estimation method (Section 11.8.2), the main-channel potential incision depth is estimated as the
sum of the main-channel depth, D, and the total scour depth, Zt, in feet. Thus, the lateral-erosion
distance, L (feet) is estimated by:
L = LH + 3 ( D + Zt )
(11.78)
where:
LH
Zt
L = 6 ( 3D ) = 18D
(11.79)
where:
D
If total scour depth for a 100-year flood event is estimated based on FCDMCs total scour estimation method presented in this chapter, the main-channel potential incision depth is estimated as
the sum of the main-channel depth, D, and the total scour depth, Zt, in feet. Total scour depth is
11-126
Hydraulics: Sedimentation
measured from the thalweg of the channel. The lateral-erosion distance, L in feet, is estimated
by:
L = 6 ( D + Zt )
(11.80)
where:
Zt
11-127
Hydraulics: Sedimentation
FIGURE 11.40
LATERAL-EROSION ZONE FOR A CURVED CHANNEL
11-128
Hydraulics: Sedimentation
FIGURE 11.41
LATERAL EROSION ZONE FOR STRAIGHT AND CURVED CHANNELS
11-129
Hydraulics: Sedimentation
sion hazard zone because of the very complex mechanisms for lateral-erosion. Adjustment may
be necessary based on engineering judgment or additional engineering analyses.
The lateral-erosion can be controlled by man-made or natural physical constraints such as bank
protection, bedrocks, or other lateral-erosion-resistant features. However, detailed geologic,
hydraulic, river mechanic, and geotechnical engineering analyses must be performed in order to
remove an area from the lateral-erosion zone. Although the lateral-erosion hazard zone methodology is reproducible, estimation of largest single-event lateral erosion can still be subjective
especially when there are not sufficient photos or the time span is not more than fifty years. Aerial photos may be only available on a yearly basis or every five years. It is rare to have aerial photos right before and after a flood event. Engineering judgment plays a key role in this scenario.
Typically, for a large river, a few hundred feet is a reasonable estimate for the lateral-erosion distance from one single event. The estimation may be obtained by analyzing aerial photos for similar rivers or different reaches in the same river. An erosion monitoring plan may be added as part
of erosion protection measure when it is difficult to estimate the largest single event lateral-erosion distance based on available historical aerial photos.
L = L H + 18D
(11.81)
where:
LH
When the total scour depth is computed based on FCDMCs total scour estimation method presented in this chapter, the modified lateral-erosion distance equation for the case when the largest single-event lateral-erosion distance is available can be estimated by:
11-130
Hydraulics: Sedimentation
L = LH + 6 ( D + Zt )
(11.82)
where:
LH
Zt
If the historical aerial photos are not available to estimate the largest single-event lateral-erosion
distance, the modified lateral-erosion distance can be estimated by:
L = 36D
(11.83)
where D is the channel depth. If total scour depth for a 100-year flood event is estimated based
on FCDMCs total scour estimation method presented in this chapter, the main-channel potential
incision depth is estimated as the sum of the main-channel depth, D, and the total scour depth,
Zt, in feet. Total scour depth is measured from the thalweg of the channel. The modified lateralerosion distance for the case when the historical aerial photos are not available can be estimated
by:
L = 12 ( D + Z t )
(11.84)
The lateral-erosion zone can be identified by using these modified lateral-erosion distance equations. When the lateral-erosion distance computed by these modified equations is less than 500
feet, a minimum distance of 500 feet is recommended for large rivers. The lateral-erosion zone
can be used in toe-down design for engineering berms. For the engineering berms or levees that
separate the pits from the river flow, erosion protection shall be provided on the river-side with
toe-down protection depth which is the total scour depth. For areas at or within the lateral-erosion line for a sand and gravel mining site between upstream and downstream meandering
peaks, the toe-down depth should be the total channel scour depth below the channel thalweg.
For areas outside the lateral-erosion line, the toe-down depth should be the total channel scour
depth below the adjacent ground if a monitoring plan is developed to monitor the safety and erosion potential for the erosion protection structures. The main channel velocity or floodway velocity should be used for scour calculations.
For a sand and gravel mining pit located in a straight channel reach, the toe-down requirement
for erosion protection can be found in Section 11.8.2 Total Scour. The launchable riprap
11-131
Hydraulics: Sedimentation
approach can be used instead of fully extending the protection to the toe-down depth. The design
methodology for launchable riprap can be found in Section 6.6.4 Toe Protection.
FIGURE 11.42
LATERAL EROSION ZONE FOR SAND AND GRAVEL MINING EXCEPTION
11-132
Hydraulics: Sedimentation
adverse effects as compared with the pre-project conditions. In Maricopa County, one of the
most important sedimentation engineering issues is scour estimation, which is critical to the stability of bridges, channel bank protection, pipeline crossings, and other structures. Due to potential flash flood conditions and a lack of data in the desert environment, the estimation for scour
and other sedimentation engineering parameters is a challenging task. A higher safety factor
may be used to deal with the uncertainties in those sedimentation engineering parameters.
11.11 REFERENCES
11.11.1 Cited In Text
Alonso, M.A., 1997, Controls on Erosion, Subbasins of Walnut Gulch, Arizona: in Management
of Landscapes Disturbed by Channel Incision, Edited by Want and others, University of
Mississippi, Oxford, MS.
American Society of Civil Engineers (ASCE), 1975, Sedimentation Engineering, Manual 54,
Sedimentation Committee of the Hydraulics Division, Edited by Vito Vanoni, New York, NY.
--, 2006, Sedimentation Engineering, Manual 54, Sedimentation Committee of the Hydraulics
Division, Edited by Vito Vanoni, New York, NY.
--, 2008, Sedimentation Engineering, Processes, Measurements, Modeling, and Practice, Manual 110, Sedimentation Committee of the Hydraulics Division, Edited by Marcelo Garcia,
New York, NY.
ASCE Task Committee on Hydraulics, Bank Mechanics, and Modeling of River Width Adjustment, 1998a, River Width Adjustment. I: Processes and Mechanisms, Journal of Hydraulic
Engineering, 124(9), 881-902.
-- ASCE Task Committee on Hydraulics, Bank Mechanics, and Modeling of River Width Adjustment, 1998b, River Width Adjustment, II: Modeling, Journal of Hydraulic Engineering
124(9), 903-917.
Arizona Department of Water Resources (ADWR), 1996, State Standard for Watercourse System Sediment Balance, Flood Warning and Dam Safety Section.
Ayres Associates, 2004, Erosion Setback and Stabilization Criteria for City of Austin Streams,
Prepared for City of Austin, Watershed Protection and Development Review Department,
Watershed Engineering Division.
Bell, R.G. and Sutherland, A.J. 1983, Nonequilibrium Bedload Transport by Steady Flow, Journal of Hydraulic Engineering, ASCE, 109(3), 351-367.
Bennett, S.J., Alonso, C.V., Prasad, S.N. and Romkens, M.J. M. 1997. Dynamics of Headcut in
Upland Concentrated Flows, Proceedings of the Conference on Management of Landscapes Disturbed by Channel Incision, Oxford, Mississippi, pp. 510-515.
11-133
Hydraulics: Sedimentation
Bettess, R. and White, W.R., 1987, Extremal Hypotheses Applied to River Regime. Sediment
Transport in Gravel-bed Rivers, C.R. Thorne, J.C. Bathurst, and R.D. Hey. eds., John Wiley
& Sons, Inc., Chichester, U.K., 767-791.
Blench, T., 1951, Regime Theory for Self-Formed Sediment-Bearing Channels, Proceeding of
the American Society of Civil Engineers, Vol. 77.
--, 1957, Regime Behaviour of Canals and Rivers, Butterworth, London, England, pp. 138.
--, 1964, Practical Regime Analysis of River Slopes, Journal of Hydraulics Division, ASCE,
90(HY2): pp.81-98.
--, 1969, Mobile-Bed Fluviology, the University of Alberta Press, Edmonton, Canada.
--, 1986, Mechanics of Plains Rivers: A Regime Theory Treatment of Canals and Rivers for
Engineers and Environmentalists, Printing Services University of Alberta, Edmonton,
Alberta, Canada.
Borah, D.K. and Bordoloi, P.K., 1989, Stream Bank Erosion and Bed Evolution Model, Sediment Transport Modeling, S. Wang, ed., ASCE, New York, N.Y., 612-619.
Bray, D.I., 1982, Regime Equations for Gravel-bed Rivers, in Gravel-bed Rivers: Fluvial Processes, Engineering and Management, Hey, R.D., Bathurst, J.C., and Thorne, C.R., editors, John Wiley & Sons, Inc., Chichester, U.K., 517-552.
Chang Consultants, 2006, Generalized Computer Program FLUVIAL-12 Mathematical Model
for Erodible Channels, Users Manual.
Chang, H.H., 1980, Geometry of Gravel Streams, Journal of Hydraulic Engineering, ASCE,
106(9), 1443-1456.
--, 1988a, Introduction to FLUVIAL-12 Mathematical Model for Erodible Channels, Twelve
selected computer stream sedimentation models developed in the United States, S. Fan,
ed., Federal Energy Regulatory Commission, Washington, D.C.
--, 1988b, Fluvial Processes in River Engineering, Wiley, New York, NY.
--, 2006, Hydraulic and Sediment Study for Riprarian Restoration in El Monte Valley, prepared
for El Capitan Golf Club.
Chen, Y.H. 1980. Investigation of Gravel Mining Effects, Salt River Channelization Project at
Sky Harbor International Airport. Prepared for Anderson-Nichols, Palo Alto, California, by
Colorado State University, Ft. Collins, Colorado.
Chien, N. 1955, A Concept of Lacey's Regime Theory, Proceedings ASCE, Vol. 81.
Chien, N. and Wan, Z. 1998. Mechanics of Sediment Transport, ASCE.
11-134
Hydraulics: Sedimentation
City of Austin, September 10, 2007. Guidance on Establishing an Erosion Hazard Zone for
Structure and Utility Locations near Streams, Watershed Protection and Development
Review Department, Texas.
Cruff, R.W., 1999, Channel Subdivision and Bank Selection in Open Channels; Phoenix, Arizona. Flood Control District of Maricopa County Engineering Library, pp. 17.
Darby, S.E. and Thorne, C.R., 1996, Numerical Simulation of Widening and Bed Deformation of
Straight Sand-bed Rivers. I: Model Development, Journal of Hydraulic Engineering, ASCE,
122(4), 184-193.
De Ploey, J. 1989. A Model for Headcut Retreat in Rills and Gullies, CATENA Supplement
14:81-86, Cremlingen, West Germany.
Downer, C.W. and Ogden, F.L., 2002, GSSHA User's Manual, US Army Engineering Research
and Development Center and University of Connecticut. http://chl.erdc.usace.army.mil/
gssha.
Duan, J.G., 2005, Analytical Approach to Calculate Rate of Bank Erosion, Journal of Hydraulic
Engineering, ASCE, 131(11), 980-990.
Duan, J.G. and Julien, P.Y., 2005, Numerical simulation of the inception of channel meandering,
Earth Surface Processes and Landforms, 30, 1093-1110.
Fisk, G.G., Duet, N.R., McGuire, E.H., Roberts, W.P., Castillo, N.K., and Smith, C.F., 2005,
Water Resources Data Arizona Water Year 2005, Water-Data Report AZ-05-1, U.S. Geological Survey, U.S. Department of the Interior.
Flaxman, E. M., 1972, Predicting Sediment Yield in Western United States, Proceeds American
Society of Civil Engineers, Journal of the Hydraulics Division, HY 12, p. 2073-2085.
-- 1974, Progress Report on Development of Sediment Yield Predictive Equations, Soil Conservation Service, TSC Advisory ENG-PO-32, Portland, Oregon.
Flood Control District of Maricopa County (FCDMC), 1996, Hydraulics Manual.
--, 2006, Lower Hassayampa Watercourse Master Plan, River Behavior Report, prepared by JE
Fuller/Hydrology and Geomorphology, Inc for FCDMC.
--, 2010, Engineering Division, River Mechanics Manual for DDMSW.
Frenette, R. and I. Pestov. 2005. Flow and Erosive Stresses at the Base of a Headcut, Journal
of Hydraulic Engineering, ASCE, 131(2), American Society of Civil Engineers.
Garde, R.J. and Raju, K.R. 1985, Mechanics of Sediment Transportation and Alluvial Stream
Problems, 2nd edition, Halsted Press, a Division of John Wiley & Sons, New York, New
York.
Glymph, L. M., 1951, Relation of Sedimentation to Accelerated Erosion in the Missouri River
Basin, Technical Paper 102, Soil Conservation Service, USDA.
11-135
Hydraulics: Sedimentation
Graf, W.H., 1984, Hydraulics of Sediment Transport, Water Resources Publications, Littleton,
Colorado.
Guy, H. P., 1969, Laboratory Theory and Methods for Sediment Analyses, Techniques of
Water-Resources Investigations, U.S. Geological Survey, U.S. Department of the Interior,
Washington, D.C.
--, 1989, Fluvial Sediment Concepts, Techniques of Water-Resources Investigations of the U.S.
Geological Survey, U.S. Department of the Interior, Washington, D.C.
Guy, H. P. and Norman, V. W., 1970, Field Methods for Measurement of Fluvial Sediment,
Techniques of Water-Resources Investigations, U.S. Geological Survey, U.S. Department
of the Interior, Washington, D.C.
Gyr, A., and Hoyer, K., 2006. Sediment Transport a Geophysical Phenomenon, Springer, The
Netherlands.
Han, Q. 1980. A Study on the Non-Equilibrium Transport of Suspended Load, Proceedings of
the International Symposium on River Sedimentation, Beijing, China, pp. 793-802 (in Chinese).
Hanson, G.J., Robinson, K.M., and Cook, K.R. 1997. Headcut Migration Analysis of a Compacted Soil, Transactions of the American Society of Agricultural Engineers, 40(2): 355361.
--, 1999. Prediction of Headcut Migration Using a Deterministic Approach, An ASAE Meeting
Presentation at the 1999 ASAE/CSAE-SCGR Annual International Meeting, Toronto,
Ontario, Canada.
--, 2001. Prediction of Headcut Migration Using a Deterministic Approach, Transactions of the
American Society of Agricultural Engineers.
Hasegawa, K., 1989, Universal Bank Erosion Coefficient for Meandering Rivers, Journal of
Hydraulic Engineering, ASCE, 115(6), 744-765.
Henderson, F. M., 1966, Open Channel Flow, MacMillan, New York, NY.
Hey, R.D. and Thorne, C.R., 1986. Stable Channels with Mobile Gravel Beds, Journal of
Hydraulic Engineering, ASCE, 112(6), 671-689.
Hooke, R.L., 1994. On the efficacy of humans as geomorphic agents. GSA Today, 4(9), 217,
224-225.
Hooke, J. and Mant, J. 2002, Morpho-dynamics of Ephemeral Streams in Dryland Rivers:
Hydrology and Geomorphology of Semi-Arid Channels, Edited by Bull, L.J and Kirkby, M.J.,
John Wiley and Sons Ltd., England.
Ikeda, S., Parker, G., and Sawai, K., 1981, Bend Theory of River Meanders, Part 1: Linear
Development, Journal of Fluid Mechanics, 112, 363-377, Cambridge University Press,
Cambridge, United Kingdom.
11-136
Hydraulics: Sedimentation
Interagency Committee on Water Resources, Subcommittee on Sedimentation. 1957. Measurement and Analysis of Sediment Loads in Streams: Report No. 12, Some Fundamentals
of Particle Size Analysis, St. Anthony Falls Hydraulic Laboratory, Minneapolis, MN.
Jia, Y. and Wang, S.S.Y., 1999, Numerical Model for Channel Flow and Morphological Change
Studies, Journal of Hydraulic Engineering, ASCE, 125(9), 924-933.
Jia, Y.F. and Wang, S., 2001, CCHE2D: Two-dimensional Hydrodynamic and Sediment Transport Model For Unsteady Open Channel Flows Over Loose Bed, National Center for Computational Hydroscience and Engineering, the University of Mississippi. http://
www.ncche.olemiss.edu/index.php?page=freesoftware.
Jia, Y. and Wu, W., 2007, Numerical and Empirical Modeling Tools Development for Studying
Bank Erosion and Evolution of Headcut and Tailcut due to Sand and Gravel Mining Pits in
Alluvial Rivers, Technical Report No. NC CHE-TR-2007-2, National Center for Computational Hydroscience and Engineering, The University of Mississippi.
Julien, P.Y., 2002, River Mechanics, Cambridge University Press, Cambridge, United Kingdom.
Julien, P.Y. and Wargadalam, J., 1995, Alluvial Channel Geometry: Theory and Applications,
Journal of Hydraulic Engineering, ASCE, 121 (4), 312-325.
Kennedy, R.G., 1895, The Prevention of Silting in Irrigation Canals, Minutes of the Proceedings
Institute of Civil Engineers, London, England, 119, 281-290.
Kennedy, J.F., 1961, Stationary Waves and Antidunes in Alluvial Channels, Caltec Report, No.
KH-R-2.
Kondolf, G.M., 1994, Geomorphic and Environmental Effects of Instream Gravel Mining, Landscape and Urban Planning, Elsevier Science B.V., Amsterdam, 28, 225-243.
--, 1997, Hungry Water: Effects of Dams and Gravel Mining on River Channels, Environmental
Management, 21(4), 533-551.
Lacey, G., 1929, Stable Channels in Alluvium, Minutes of Proceedings Institute of Civil Engineers, London, England, 229, 259-292.
--, 1937, Stable Channels in Erodible Material: A Discussion, Transactions of the American
Society of Civil Engineers, Vol. 102.
Lane, E. W., 1947, Report on the Subcommittee on Sediment Terminology, Transactions of the
American Geophysical Union, Washington, D.C., Vol. 28 (6), 936-938,
--, 1955, Design of Stable Channels, Transactions of the American Society of Civil Engineers,
120, 1234-1260.
Lane, L.J., Nichols, M. H., and Paige, G.B., 1995, Modeling Erosion on Hillslopes: Concepts,
Theory, and Data, In: Proceedings of the International Congress on Modeling and Simulation (MODSIM'95) (ed. by P. Binning, H. Bridgman, and B. Williams), November 27-30,
11-137
Hydraulics: Sedimentation
1995, University of Newcastle, Newcastle, NSW, Australia, Uniprint, Perth, Australia, pp. 17. http://eisnr.tucson.ars.ag.gov/hillslopeerosionmodel/.
Lane, L.J., Kidwell, R., and Weltz, A., 2000, Watershed Sediment Yield and Rangeland Health,
International Journal of Sediment Research, 15(1), 51-59.
Langbein, W. B., Hains, C. H. and Culler, R. C., 1951, Hydrology of Stock-water Reservoirs in
Arizona, U.S. Geological Survey Circular 110, 18.
Langbein, W. B. and Schumm, S.A., 1958, Yield of Sediment in Relation to Mean Annual Precipitation, Transactions of the American Geophysical Union, 39, 1076-1084, Washington,
D.C.
Lee, H.Y., Fu, D.T. and Song, M.H., 1993, Migration of Rectangular Mining Pit Composed of
Uniform Sediment, Journal of Hydraulic Engineering, ASCE, 119(1), 64-80.
Leopold, L.B. and Maddock, T. M., 1953, The Hydraulic Geometry of Stream Channels and
Some Physiographic Implications, USGS Professional Paper 252, Washington, D.C.
Leopold, L.B. and Miller, J. 1956. Ephemeral Streams-Hydraulic Factors and Their Relation to
the Drainage Net, USGS Professional Paper 282-A, Washington, D.C.
Leopold, L.B. and Wolman, M.G., 1957, River Channel Patterns: Braided, Meandering and
Straight, USGS Professional Paper 282-B, Washington, D.C.
Leopold, L.B. and Wolman, M.G., 1960, River Meanders, Geologic Society of America Bulletin,
Vol. 71.
Leopold, L.B., Emmett, W. W. and Myrick, R. M., 1966, Channel and Hillslope Processes in a
Semiarid Area of New Mexico, USGS Professional Paper 352-G, Washington, D.C., 193253,
Leopold, L.B., Wolman, M.G., and Miller, J.P., 1964, Fluvial Processes in Geomorphology, W.H.
Freeman and Company, San Francisco, CA.
Li, L., and Wang, S.S.Y., 1993, Numerical Modeling of Alluvial Stream Bank Erosion, Advances
in Hydro-Science and Engineering, S.S.Y. Wang, ed., University of Mississippi, Oxford, Mississippi, Vol. 1, 2085-2090.
Li, R. M., Cotton, G. K., Zeller, M. E., Simons, D. B., and DesChamps, P. Q., 1989, Effects of Instream Mining on Channel Stability, prepared for Arizona Department of Transportation,
FHWA-AZ89-250, Phoenix, AZ.
Lindley, E.S., 1919, Regime Channels, Proceedings, Punjab Engineering Congress, Vol. VII.
Lopez S., J.L., 2004, Channel Response to Gravel Mining Activities in Mountain Rivers, Journal
of Mountain Science, 1(3), pp. 264-269.
MBH Software, Inc., 2002, Sedimentation in Stream Networks User's Manual (HEC-6T), Clinton, Mississippi.
11-138
Hydraulics: Sedimentation
Mahmood, K., and Shen, H. W., 1971, Regime Concept of Sediment-Transporting Canals and
Rivers, River Mechanics, Vol. 2, H. W. Shen, ed., Fort Collins, CO.
Meade, R.H. and Parker, R.S., 1984, Sediment in Rivers of the United States, U.S. Geological
Survey Water Supply Paper 2250, 49-60.
Mays, Larry W. 1999, Hydraulic and Design Handbook, McGraw-Hill.
Meyer-Peter, E. and Muller, R, 1948, Formulas for Bed-load Transport, International Association for Hydraulic Structures, Second Meeting, Stockholm, Sweden.
Millar, R.G. and Quick, M.C., 1997, Discussion of Development and Testing of a Riverbank-stability Analysis, by S.E. Darby and C.R. Thorne, Journal of Hydrologic Engineering, ASCE,
123(11), 1051.
Mussetter, R. A., Lagasse, P.F., and Harvey, M.D., 1994. Erosion and Sediment Design Guide,
prepared for Albuquerque Metropolitan Arroyo and Flood Control Authority.
Nakagawa, H. Tsujimoto, T. and Murakami, S. 1989. Convolution-integral Modeling of NonEquilibrium Sediment Transport, Proceedings of the International Symposium on Sediment
Transport Modeling, edited by Wang, S.Y., ASCE.
Nanson, G.C., Tooth, S., and Knighton, D. 2002, A Global Perspective on Dryland Rivers: Perceptions, Misconceptions and Distinctions, in Dryland Rivers: Hydrology and Geomorphology of Semi-Arid Channels, Edited by Bull, L.J and Kirkby, M.J., John Wiley and Sons Ltd.,
England.
Natural Resources Conservation Services (NRCS). 1997. Earth Spillway Erosion Model, Chapter 51 from National Engineering Handbook (part 628 Dams).
Neill, C. R., 1973, Guide to Bridge Hydraulics, Roads and Transportation Association of Canada.
O'Brien, J. S., 1986, Physical Processes, Rheology and Modeling of Mud Flows, Ph.D. Dissertation, Colorado State University.
Odgaard A., 1989, River Meander Model, I: Development. Journal of Hydraulic Engineering,
ASCE, 115(11): 1433-1450.
Olsen N.R.B. 2003. Three-dimensional CFD modelling of self-forming meandering channel.
Journal of Hydraulic Engineering, ASCE, 129(5): 366-372.
Osman, A.M., 1985, Channel Width Response to Changes in Flow Hydraulics and Sediment
Load, PhD thesis, Colorado State University, Fort Collins, Colorado
Osman, A. M. and Thorne, C. R., 1988a, Riverbank stability analysis, I: Theory, Journal of
Hydraulic Engineering, ASCE, 114(2).
--, 1988b, Riverbank stability analysis, II: Application, Journal of Hydraulic Engineering, ASCE,
114(2).
11-139
Hydraulics: Sedimentation
Pacific Southwest Inter-Agency Committee, 1974, Erosion and Sediment Yield Methods,
Pacific Southwest Inter-Agency Committee, Report of the Water Management Subcommittee, p. 45.
Parker, G., Sawai, K., and Ikeda, S., 1982, Bend Theory of River Meanders. Part 2. Nonlinear
Deformation of Finite-amplitude Bends, Journal of Fluid Mechanics, 115, 303-314, Great
Britain.
Pemberton, E. L. and Lara, J. M., 1984, Computing Degradation and Local Scour, Technical
Guideline, U.S. Bureau of Reclamation, Engineering and Research Center, Denver, CO.
January 1984.
Peterson, H. V., 1962, Hydrology of Small Watersheds in Western States, U.S. Geological Survey Water-Supply Paper 1475-I, pp. 217-356.
Porterfield, G., 1972, Computation of Fluvial-Sediment Discharge, Techniques of WaterResources Investigations, U.S. Geological Survey, U.S. Department of the Interior, Washington, D.C.
Renard, K. G. and Stone, J. J., 1981, Sediment Yield From Small Semiarid Rangeland Watersheds, Proceedings of the Workshop on Estimating Erosion and Sediment Yield on Rangelands, Tucson, Arizona, U.S. Department of Agriculture, pp. 129-144.
Richards, K. 1982, Rivers: Form and Process in Alluvial Channels, Methuen, London.
Robinson, K.M., and G.J. Hanson, 1994. A Deterministic Headcut Advance Model, Transactions of the American Society of Agricultural Engineers, 37(5): 1437-1443.
--, 1995. Large-Scale Headcut Erosion Testing, Transactions of the American Society of Agricultural Engineers, 38(2), 429-434.
Robinson, K.M., Bennett, S.J., Casali, J., and GJ. Hanson. 2000. Processes of Headcut
Growth and Migration In Rills and Gullies, International Journal of Sediment Research,
15(1), 69-82.
Rouse, H. 1938. Fluid Mechanics for Hydraulic Engineers, Chap. XI, Dover, New York.
Schoklitsch, 1932, Prevention of Scour and Energy Dissipation, translated from German by
E.F. Wilsey, U.S. Bureau of Reclamation.
Schumm, S. A., 1971, Fluvial Geomorphology: Historical Perspective, River Mechanics, Vol. 1,
H. W. Shen, ed., Fort Collins, CO., pp. 4-30.
--, 1977, The Fluvial System, Wiley, New York.
Scott, K.M., 1973, Scour and Fill in Tujunga Wash - A Fanhead Valley in Urban Southern California - 1969, USGS Professional Paper 732-B, Washington, D.C.
Semmens, D.J., S.N. Miller, M. Hernandez, P. Miller, D. Goodrich, and W. Kepner, 2001. Automated Geospatial Watershed Assessment (AGWA) - A GIS Based Hydrologic Modeling
11-140
Hydraulics: Sedimentation
11-141
Hydraulics: Sedimentation
Soil Conservation Service (SCS), 1977, Design of Open Channels, Technical Release No. 25,
U.S. Department of Agriculture, Washington, D.C.
Soil and Water Conservation Society, 1995, RUSLE User Guide, Revised Universal Soil Loss
Equation Version 1.04.
Stein, O.R., and P.Y. Julien. 1993. Criterion Delineating the Mode of Headcut Migration, Journal
of Hydraulic Engineering, ASCE, 119(3), 37-50.
Stein, O.R. and D.A. LaTray. 2002. Experiments and Modeling of Head Cut Migration in Stratified Soils, American Geophysical Union, Water Resources Research, 28(12).
Temple, D.M., 1992. Estimating Flood Damage to Vegetated Deep Soil Spillways, Applied Engineering in Agriculture, 8(2): 237-242.
Temple, D.M. and J.S. Moore, 1994. Headcut Advance Prediction for Earth Spillways, American Society of Agricultural Engineers, Paper No. 94-2540, St. Joseph, Michigan.
--, 1997. Headcut Advance Prediction for Earth Spillways, Transactions of the American Society of Agricultural Engineers, 40(3): 557-562.
Thomas, W.A., Copeland, R.R., and McComas, D.N., 2002, SAM Hydraulics Design Package
for Channels, Coastal and Hydraulics Laboratory, U.S. Army Engineer Research and
Development Center, 3909 Halls Ferry Road, Vicksburg, MS 39180-6199.
Tiffany, T.B. 1939, Studies of Meandering of Model Streams, Transactions of the American
Geophysical Union, Vol. 20.
Toy, T. J. and Osterkamp, W. R., 1995, The Applicability of RUSLE to Geomorphic Studies,
Journal of Soil and Water Conservation, V. 50, No. 5, pp. 498-503.
Urban Drainage and Flood Control District, 1987, Technical Review Guidelines for Gravel Mining Activities Within or Adjacent to 100-year Floodplains, Denver, Colorado.
U.S. Army Corps of Engineers (USACE), 1970, Engineering and Design Laboratory Soils Testing, Engineer Manual EM 1110-2-1906, pp. V-26.
--, 1974, New River and Phoenix City Streams, Arizona-Design Memo. No. 2, Hydrology, Part
1, Los Angeles, District, 51 p and plates.
--, 1980, Sand and Gravel Mining Guidelines, Los Angeles District.
--, 1981, Phoenix Flood Damage Survey, February 1980.
--, 1987, Skunk Creek, New and Agua Fria Rivers, Los Angeles, District
--, 1989, Sedimentation Investigations of Rivers and Reservoirs, Engineer Manual 1110-24000.
11-142
Hydraulics: Sedimentation
--, 1991, HEC-6, Scour and Deposition in Rivers and Reservoirs, User's Manual. [HEC WEB
Site]
--, 1994, Channel Stability Assessment for Flood Control Projects, Engineering Manual 1110-21418, published by ASCE Press, New York, NY, pp.108.
--, 1995, Sedimentation Investigations of Rivers and Reservoirs, Engineer Manual 1110-24000, Revised.
U.S. Department of Agriculture (USDA), 1972, National Engineering Handbook, Washington
D.C. Section 3, Chapter 6. Sedimentation.
--, 1997, Predicting Soil Erosion by Water: A Guide to Conservation Planning with the Revised
Universal Soil Loss Equation (RUSLE), Agricultural Handbook Number 703.
U. S. Department of the Interior, Bureau of Reclamation (USBR), 1977, Design of Small Dams,
U. S. Government Printing Office, Washington, D.C.
U.S. Department of Transportation (USDOT), 2001a, Bridge Scour and Stream Instability
Countermeasures, Hydraulic Engineering Circular No. 23, FHWA NHI-01-003 (USDOT
Hydraulics WEB Site).
--, 2001b, Evaluating Scour at Bridges: Fourth Edition, Hydraulic Engineering Circular No.18,
Publication No. FHWA NHI 01-001.
--, 2001c, Stream Stability at Highway Structures: Third Edition, Hydraulic Engineering Circular
No. 20, Publication No. FHWA NHI 01-002.
--, 2001d, River Engineering for Highway Encroachments: Highways in the River Environment,
Hydraulic Design Series Number 6, Publication No. FHWA NHI 01-004.
--, 2006, Hydraulic Design of Energy Dissipators for Culverts and Channels, Hydraulic Engineering Circular No. 14, Publication No. FHWA NHI 06-086.
U.S. Environmental Protection Agency (EPA), 1976, Erosion and Sediment Control, Surface
Mining in the Eastern U.S., EPA-625/3-76-006.
Veronese, A., 1937, Erosioni Di Fondo A Valle Di Uno Searico.
Vieira, D.A. and Wu, W., 2002, One-Dimensional Channel Network Model CCHE1D, User's
Manual, National Center for Computational Hydroscience and Engineering, the University
of Mississippi. http://www.ncche.olemiss.edu/index.php?page=cche1d_documents.
White, W.R., Paris, E., and Bettess, R., 1981, Tables for the Design of Stable Alluvial Channels,
Rep. No. IT 208, HR Wallingford, Wallingford, United Kingdom, 30.
Wischmeier, W.H. 1972, Estimating the Cover and Management Factor for Undisturbed Areas,
Presented at the Sediment Yield Workshop, USDS Sedimentation Laboratory, Oxford, Mississippi.
11-143
Hydraulics: Sedimentation
Wischmeier, W.H. and D.D. Smith, 1978, Predicting Rainfall Erosion Losses. A Guide to Conservation Planning. Agriculture Handbook No. 537, USDA-SEA, US. Government Printing
Office, Washington, D.C. pp. 58.
Wolman, M.G., 1954, A Method of Sampling Coarse River Bed Material, Transactions of the
American Geophysical Union, Vol. 35.
Wu, W., 2007. Computational River Dynamics, Taylor & Francis Group, New York, New York.
Wu, W., and Vieira, D.A., 2002, One-Dimensional Channel Network Model CCHE1D, Technical
Manual, National Center for Computational Hydroscience and Engineering, the University
of Mississippi. http://www.ncche.olemiss.edu/index.php?page=cche1d_documents.
Yang, C.T., 1973, Incipient Motion and Sediment Transport, Journal of the Hydraulics Division,
ASCE, Vol. 99, No. HY10.
--, 1992, Force, Energy, Entropy and Energy Dissipation Rate, Entropy and Energy Dissipation
in Water Resources, V.P. Singh and M. J. Fiorention, eds., Kluwer Academic Publishers,
The Netherlands, 63-89.
--, 2003, Sediment Transport: Theory and Practice, McGraw-Hill Companies, Inc.
Yang, C.T. and Song, C.C.S., 1986, Theory of Minimum Energy and Energy Dissipation Rate.
Encyclopedia of Fluid Mechanics, Gulf Publishing Co., Houston, Texas, 353-399.
Yang, C.T., Molinas, A., and Song, C.C.S., 1988, GSTARS - Generalized Stream tube Model
for Alluvial River Simulation, Twelve selected computer stream sedimentation models
developed in the United States, S. Fan, ed., Federal Energy Regulatory Commission,
Washington, D.C.
Yang, C.T., Song, C.C.S., and Woldenberh, M.J., 1981, Hydraulic Geometry and Minimum
Rate of Energy Dissipation, American Geophysical Union, Water Resources Research,
17(4), 1014-1018.
Zanke, U., 1976, Uber den Einfluss von Kornmaterial, Stromung un Wassestanden auf die Kenngrossen von Transportkorpern in offenen Gerinnen. Mitt. Franzius-Inst. TU Hannover 44.
Zeller, M. E., 1981, Scour depth formula for estimation of toe-protection against general scour,
Pima County Department of Transportation and Flood Control District, Tucson, Arizona.
Zeller, M. E. and W. T. Fullerton, 1983. A Theoretically Derived Sediment Transport Equation
for Sand-Bed Channels in Arid Regions, Proceedings of the D. B. Simons Symposium on
Erosion and Sedimentation, R. M. Li and P. F. Lagasse, eds., Colorado State University and
ASCE.
Zimmerman, F. and Maniak, U. 1967, Scour Studies, Zimmerman, F. and Maniak, U. 1967,
Scour Studies, Journal of Hydraulic Engineering Division, ASCE.
11-144
Hydraulics: Sedimentation
11-145
Hydraulics: Sedimentation
Leopold, L. B. and Wolman, M. G., 1957, River Channel Patterns-Braided, Meandering, and
Straight: USGS Professional Paper 282-B. Washington, D.C.
MacBroom, J. G., 1981, Applied Fluvial Geomorphology, University of Connecticut - Storrs,
Institute of Water Resources Report No. 31.
Mavis, F. T. and Laus, L. M., 1948, A Reappraisal of the Beginning of Bed-movement-competent velocity, International Association for Hydraulic Research, Second Meeting, Stockholm,
Sweden.
National Research Council, 1996, Alluvial Fan Flooding, National Academy Press, Washington,
D.C., p. 172.
Pemberton, E. L. and Lara, J. M., 1971, A Procedure to Determine Sediment Deposition in a
Settling Basin, U.S. Bureau of Reclamation, Sedimentation Section, Denver, CO.
Rosgen, D., 1996, Applied River Morphology, Wildland Hydrology, Pagosa Springs, CO.
Schumm, S. A., 1961, Effect of Sediment Characteristics on Erosion and Deposition in Ephemeral Stream Channels, USGS Professional Paper 352-C. Washington, D.C.
Shields, A., 1936, Anwendung der Aenlichkeitsmechanik und der Turbulenzforschung anf die
Geschiebebewegung, Mitteil, PVWES, Berlin, No. 36.
Stevens, M. A., Simons, D. B., and Richardson, E. V., 1975, Nonequilibrium River Form, Journal of the Hydraulics Division, ASCE, Vol. 101, No. HY5.
Thorne, C. R., 1998, Stream Reconnaissance Handbook - Geomorphological Investigation and
Analysis of River Channels, John Wiley & Sons, New York.
U.S. Army Corps of Engineers (USACE), 2001a, HEC-RAS River Analysis System, Hydraulic
Reference Manual. [HEC WEB Site].
--, 2001b, HEC-RAS River Analysis System, User's Manual. [HEC WEB Site].
U.S. Department of Transportation (USDOT), 1989, Design of Riprap Revetment, Hydraulic
Engineering Circular No. 11, FHWA-IP-89-016.
11-146