Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

BL PGP Case 2 14 Feb 2015

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

Business Law Case Assignment

Case Number 2
Submitted to Prof. Anil B Suraj

CASE 2

M/s. Bell Co. was nominated by the Government of India as the prime
contractor for realizing the modernization plan of Police forces across the
nation. In this regard, M/s. Bell floated a Request for Proposal (RFP) for
procurement of Digital Radio Trunking System, also popularly known as
Terrestrial Trunked Radio (in short `TETRA'). The RFP called upon the vendors
to make technical and commercial proposals, and in a pre-bid meeting it was
also specified that the commercial offers could be based on an estimate of a
minimum of 100 systems.
This deal attracted considerable public/media attention, and in a press
conference the CEO of M/s. Bell announced that this is indeed a significant
country-wide project of modernization that shall involve commission and
installation of more than 1000 units of TETRA systems. Eventually, nine
bidders submitted their bids in response to the RFP and upon the technical
bids being considered, there were two bids that were finally shortlisted
those of M/s. Me-Too and M/s. Y-Not, with the following pricing details:

NAME OF THE BIDDER

UNIT PRICE QUOTE

TOTAL QUANTITY

M/s. Y-Not

Euros 150.00

Per requirement

M/s. Me-Too

Euros 125.00

Minimum of 500 units

Based on the pricing information above, M/s. Bell finally chose M/s. MeToo as the L-1.
This decision was challenged by M/s. Y-Not on the ground that M/s. MeToos bid was invalid and should have been rejected by M/s. Bell. In the
absence of any constructive response from M/s. Bell, M/s. Y-Not has filed a
petition before the Supreme Court of India that this process needs to be
invalidated on various grounds, including, unreasonableness in evaluating its
bid and wrongful discrimination.

CASE SOLUTION
1 ASSUMPTIONS

Government is the guardian of the finances of the State. It is expected to protect the financial
interest of the state. The right to refuse the lowest or any other tender is always available to
the Government but the principles laid down in Article 14 of the Constitution have to be kept
in view while accepting or refusing a tender. There can be no question of infringement of
Article 14 if the Government tries to get best person or best quotation.

The Court does not sit as a court of appeal but merely reviews the manner in which the
decision was made. The duty of the court is to confine itself to the question of legality. Its
concern should be:
o Whether a decision making authority exceeded its powers?
o Committed an error of law
o Committed a breach on the rules of natural justice
o Reached a decision which no reasonable tribunal would have reached
o Abused its powers

2 JUDGEMENT

Evaluation Committee has not violated any norms while preparing the report and holding
M/s. Me-Too as the lowest bidders
Conditions of the tender were not violated and all the guidelines were followed scrupulously
while arriving at total price considering the complete requirement of RFP and there is no
genuine grievance of the writ petitioner giving rise to any cause of action in their favor.
In this case, it should be noted that at the time of floating the tender, no separate quantities
were furnished to the vendors. The bids were public, there was no question of
changing/adding/altering/modifying the same by any of the parties
M/s. Bell Co cannot be faulted for strictly adhering to the rates furnished by M/s. Y-Not in
its original bid documents.
On examining the facts and circumstances of the present case, we are of view that none of
the criteria has been satisfied justifying Courts interference in the grant of contract in favour
of the M/s. Y-Not

When the power of judicial review is invoked in


the matters relating to tenders or award of contracts, certain special features have to be
considered. A contract is a commercial transaction and evaluating tenders and awarding
contracts are essentially commercial functions.
In such cases principles of equity and natural justice stay at a distance. If the decision
relating to award of contracts is bona fide and is in public interest, Courts will not exercise
the power of judicial review and interfere even if it is accepted for the sake of argument that
there is a procedural lacuna.
In the instant case, it cannot be held that the process adopted or decision made is so arbitrary
or irrational that no responsible authority acting reasonably or in accordance with the
relevant law could not have taken such a decision. The inevitable conclusion is that the
appeal is devoid of any merit and deserves dismissal, which we order.

3 XYZ

If the contract has been entered into without ignoring the procedure which can be said to be
basic in nature and after an objective consideration of different options available taking into
account the interest of the State and the public, then Court cannot act as an appellate
authority by substituting its opinion in respect of selection made for entering into such
contract

It can choose its own method to arrive at a decision and it is free to grant any relaxation for
bona fide reasons, if the tender conditions permit such a relaxation. It was further held that
the State, its corporations, instrumentalities and agencies have the public duty to be fair to
all concerned. Even when some defect is found in the decision making process, the Court
must exercise its discretionary powers under Article 226 with great caution and should
exercise it only in furtherance of public interest and not merely on the making out of a legal
point.

The decision must not only be tested by the application of Wednesbury principle of
reasonableness but must be free from arbitrariness not affected by bias or actuated by mala
fides

You might also like