Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Boil Off Gas Qatar

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4
At a glance
Powered by AI
The key takeaways are that the JBOG Project aims to recover boil-off gas from LNG carriers at Ras Laffan Port in Qatar to reduce flaring and emissions. It will help Qatar meet environmental standards and regulations.

The JBOG Project aims to recover boil-off gas currently being flared during LNG ship loading. It will collect gas from ships, compress it, and send it back to LNG producers. This will reduce flaring by an estimated 0.6 million tonnes per year and 1 million tonnes of CO2 emissions annually.

The project will collect gas from ships via pipelines, compress it at a central facility, and send it to LNG trains. Challenges included designing valves that can efficiently operate across a wide range of temperatures and pressures.

Qatargas Jetty Boil-Off Gas Recovery Project A Major Environmental Initiative

Qatargas is leading an environmental project to recover gas currently being flared during Liquefied Natural
Gas (LNG) ship loading at Ras Laffan Port in Qatar. The $1 billion Jetty Boil-Off Gas (JBOG) Recovery Project,
which is part of the Common Facilities Projects at Ras Laffan Industrial city (RLC), will enable boiled-off gas
to be collected from LNG ships and compressed at a central facility. The compressed gas will then be sent to
the LNG producers to be consumed as fuel or converted back into LNG.
The JBOG Project is one of the cornerstones of Qatargas overall flare management strategy and will be
instrumental in the companys drive to reduce and maintain total flaring at regulatory target levels in the
long term to protect the environment. The project, when fully operational, will recover the equivalent of
some 0.6 million tonnes per year of LNG based on an expected 90% recovery efficiency during normal
operations. In flaring units, this works out to be approximately 29 billion standard cubic feet (BSCF) per year
that would otherwise have been flared during LNG ship loading, which is enough natural gas to power more
than 40,000 homes. In terms of Greenhouse Gas (GHG) emission reductions, the above flare recovery
amounts to approximately 1 million tonnes of CO2 per annum, which excludes indirect emissions resulting
from JBOG facility operation such as electrical power utilized by JBOG compressors.
With an anticipated reduction of 1 million tonnes of CO2 per annum, the JBOG Project definitely ranks highly
in terms of emissions reductions as well as overall environmental and air quality impact mitigation potential.
Qatargas Chief Executive Officer, Khalid Bin Khalifa Al Thani says: We are very pleased that Qatargas is able
to lead this project on behalf of all the LNG producers at Ras Laffan Industrial City. Qatargas, Qatar
Petroleum, and RasGas are all focused on reducing our emissions and energy use so that we can bring our
emissions to the lowest levels possible to meet or beat international standards. This project will contribute
greatly to reducing emissions from our facilities.
The Engineering, Procurement and Construction Management (EPCm) contract for the project was awarded
to Fluor in the USA in February 2010. Qatargas awarded the contract on behalf of the owners of the project:
the four Qatargas and three RasGas companies that own the 14 LNG trains at Ras Laffan.

Sheet 1 of 4

The detailed design and procurement services are being carried out at the Fluors offices in Sugar Land,
Texas, and New Delhi, India. Over 240 Fluor personnel are currently working on this project in Sugar Land
and New Delhi. Fluor has mobilised a team of over 100 people to work in Ras Laffan to support the
construction, commissioning and start-up phases of the project.
The project design is based on collection of the LNG boil-off gas from the LNG carriers and transfer of this
gas to a Central Compression Area via large diameter stainless steel pipelines. At the Central Compression
Area, the gas will be compressed and sent to the LNG trains for use as fuel gas. The project is expected to be
completed by early 2014.
The Project Manager, Bashir Mirza, who has been leading the JBOG Project since June 2007 says, We in the
JBOG team are very proud to be associated with the largest environmental project in Qatars history. We
have a great team which is determined to build this project safely and within our budget and schedule.
Initial Phase
The Front End Engineering Design (FEED) of the JBOG Project was awarded to Fluor in October 2007. The
FEED completed the initial design of the project, produced the compressor requisition, estimated the cost of
the project and completed a high level schedule. This work was overseen by a small Qatargas team in Sugar
Land. The FEED was completed by the end of 2008.
In 2009, significant work was done on defining and developing interfaces with RLC, Qatargas and RasGas.
Compressors purchase requisition was finalised to the point where the compressors could be ordered early
during the execution phase. Detailed design and procurement was carried out to prepare for installing tieins at the LNG Berths 2 and 3 during a planned shutdown in May 2010.
By the end of 2009, the JBOG Owners gave the JBOG Project an initial approval to proceed with the
execution phase. This step led to the award of the Engineering, Procurement and Construction
Management contract to Fluor in February 2010.
Project Design
The project design is simple. The gas is taken off the LNG ships during loading, sent via pipelines to a Central
Compression Area (CCA), compressed and sent to the LNG producers. The boil-off gas is discharged from
the ships at cold temperatures ranging between -80oC to -100oC. The pipelines material needs to be
stainless steel to withstand the low temperature gas. The result is a network of large diameter stainless
steel pipelines which carry the gas from the ships to the CCA. The diameter of these lines ranges from 34
to 60.
Tie-ins are needed at each of the six LNG berths at the connection between the ship loading arms and the
existing flares. Tie-ins for Berths 4, 5 and 6 have already been installed by the Qatargas Common Lean LNG
Project. Berths 2 and 3 Tie-ins were installed by JBOG in May 2010.
The CCA is located adjacent to the RasGas LNG Tank Farm, also known as the Lot H. JBOG needs two
compressor trains, each sized for 50% of the rated capacity of 163 tonnes of JBOG per hour. There are three
main buildings in the CCA. ITR 65 houses the control equipment for the project, as well as a small number of
office spaces for the operators. The 132kV Substation building will have the switchgear for the 132kV power
received from Kahramaa. The largest building will have the 33kV and 415V switchgear.
An interesting feature of JBOG construction is that the CCA is being built on reclaimed land. This means that
1500 piles had to be drilled to carry the load of the facilities. The piles are around 9m deep, and around half
of the pile length is within the water table. The seawater can cause severe and rapid corrosion of the steel in
the piles unless it is protected. JBOG has an extensive cathodic protection system, which uses sacrificial
Sheet 2 of 4

magnesium anodes to create a galvanic cell diverting the flow of current from the piles to these sacrificial
anodes, thus protecting the piles.
The power is supplied from the Kahramaa Substation 2 in RLC via two sets of cables, which take the power
from Kahramaa to the CCA. The compressed gas is carried by a set of carbon steel pipelines from the CCA to
Lot H, Qatargas Lean LNG Tank Farm at Lot N and Qatargas 1 LNG trains. The Lot N has tie-ins for both
Qatargas 2 and Qatargas 3&4 LNG trains. The tie-in for Qatargas 3&4 has already been installed by JBOG at
the end of 2010.
While the design of JBOG is fairly simple, there have been several innovations on the project. The first stage
compressor is the largest ever built for this application. The gas taken from the LNG ships warms up as it
travels to the compressors in the Central Compressors Area. This, coupled with the drop in pressure, causes
the gas to expand, thus needing a large volume compressor. Qatargas sought help from compressor
specialists from ConocoPhillips, Shell and Fluor to review the design by GE Nuovo Pignone for the
compressor. The inlet gas condition varies substantially with respect to the temperature and hence the
volume. The LP compressor has inlet guide vanes to ensure that the compressor operates efficiently at all
inlet volumes. The design of the inlet guide vanes at varying inlet temperatures ranging from -140C to
ambient temperature was a huge challenge.
Due to the very low pressure drop allowed between the ship and compressor, there was no existing check
valve design which could work with those limitations. Qatargas and Fluor engineers started working with
several valve manufacturers, reviewed computational flow dynamics (CFD) models and involved subject
matter experts from Shell and ConocoPhillips to come up with a new design of the valve flap. The
lightweight titanium flap uses aerodynamics to reduce the drag, and increase lift. The JBOG engineering
team did not just rely on modeling, and arranged for the first valve to be tested at a specialised valve testing
shop to ensure that the valve met the design conditions. This valve was tested late in 2011 successfully,
leading to the release for the building of the next five valves.

Sheet 3 of 4

Focus on Safety
The top priority of the JBOG Project is the safety of everyone who works on the project. JBOG has fully
implemented the Qatargas Incident and Injury Free (IIF) program. This behaviour based program increases
the awareness of everybody on the project about taking care of themselves and of their colleagues at all
times. In order to make sure that Everybody Goes Home Safely day in and day out, twelve mandatory JBOG
Golden Rules have been introduced. The JBOG Safety, Health, Environment and Security team carries out
regular review of safe working through safety walks, safety leadership teams and a safety steering
committee. JBOG Project recently celebrated its first Safety Day, which proved to be a great way to
motivate our workers to continue to work safely.
Progress
The engineering of the project is around 75% complete. Construction drawings are being issued for
concrete, steel and pipe. 90% of material by value has been purchased. Construction has started at site.
There are around 120 construction team members working at the site office in RLC for JBOG. The Qatargas
and Fluor site teams were recently integrated to form a single JBOG Site PMT. This move will reduce
unnecessary interaction between QG and Fluor, and improve focus on safety and productivity.
As discussed previously, since the CCA is reclaimed land, the site has around 1500 piles to allow the site to
take the load of the JBOG facilities. These piles have been installed by a specialist contractor, Ammico, who
mobilised to site in October 2010. JBOG needs to bridge the water body between the new and old
breakwaters. This is being done by STFA, who are using quarry material to create, what the project has
termed, the Wajba Causeway. Qcon has been awarded the contract for Civil, Structural, Piping and
Mechanical work, while Qatar Kentz has been awarded the Electrical, Instrumentation and Telecoms work.
Around 800 contractor staff are currently mobilised to JBOG site, and this number is planned to grow to over
2500 people during 2012.
The JBOG workers and other contractor staff live in the Global Village camp located on the western edge of
RLC. This camp was built in 2006 for RasGas, and has a capacity for 3500 people. JBOG has taken over this
camp, and is in the process of refurbishing it to bring to our required standards.
There are two site offices. The main office is located close to the QG plant fence. The port office is located
inside the port boundaries.
Summary
JBOG Project is set to become a landmark project for the State of Qatar, underlining the demonstrated
commitment of the Qatari people to balance industrial development with care for the environment. This
huge investment in JBOG by Qatar Petroleum and its partners will reduce the carbon footprint of the 77
million tonnes per annum (MTPA) of LNG production facilities to the minimum practically possible. Qatargas
is proud and privileged to have been asked to build and operate this flagship Qatari project.

Sheet 4 of 4

You might also like