PT Ground Anchors
PT Ground Anchors
PT Ground Anchors
Preface
1. Securing of slopes
1.1. General
1.2. Consolidation of the rock
projection of Baji-Krachen,
Switzerland
1.3. Securing of abutment at Libby
Dam, Montana, USA
1.4. Securing the slope at the south
portal of the Schallberg Tunnel,
Switzerland
1.5. Securing of portal of Engiberg
Tunnel, Arth-Goldau,
Switzerland
1.6. Anchorage of scour prevention
wall at Tarbela Dam, Pakistan
2. Anchoring of retaining walls
2.1. General
2.2. Upper retaining wall at Delli and
slope stabilisation at Hauetli,
Alpnachstad, Switzerland
2.3. Anchored wall at Flachau,
Austria
2.4. Retaining wall on the N2,
Eptingen, Switzerland
2.5. Retaining walls on the N5 on
Lake Biel, Switzerland
2.6. Pile wall at the south portal of
the Naxberg tunnel, Switzerland
3. Securing of excavations
3.1. General
3.2. Centre Beaubourg, Paris,
France
3.3. Underground railway station
Lok Fu, Hong Kong
3.4. Underground railway station,
Stockholm, Sweden
3.5. Building for Swedish Credit
Bank, Stockholm, Sweden
3.6. Children's Clinic of the , Insel
Hospital, Berne, Switzerland
Page
1
1
1
Printed in Switzerland
4.1. General
4.2. Rainwater overflow tank,
Ellwangen, Federal Republic of
Germany
4.3. Stilling basin No. 3 at Tarbela
Dam, Pakistan
Page
18
18
18
19
6
7
7
7
8
9
10
10
12
13
13
13
15
16
16
17
Copyright 1978 by
VSL INTERNATIONAL LTD, Berne / Switzerland
All rights reserved
5. Securing of caverns
5.1. General
5.2. Cavern Waldeck II, Federal
Republic of Germany
5.3. Ventilating station at Huttegg
for the Seelisberg tunnel,
Bauen, Switzerland
5.4. Review of various other
caverns
20
20
20
21
24
25
6.1. General
6.2. Rock fall gallery on the
Axenstrasse, Switzerland
6.3. Spherical valve anchoring,
underground power station
Waldeck II, Federal Republic of
Germany
6.4. Cable crane anchorage at Jiroft
Dam, Iran
25
25
26
27
28
28
28
29
29
30
32
Preface
In the recent past there has been a considerable
ofthewiderangeofpossibleapplications.
Various
1. Securing of slopes
1.1. General
Slopes, rock faces and embankments frequently
slips.
1.2.
Introduction
The consolidation of the rock projection of
Baji-Krachen near Gondo on the southern slope of
the Simplon Pass was carried out in conjunction
with the widening of this highway to three lanes.
The rock face rose almost vertically for 40 to 50 m
and then continued its ascent at about 45. This
meant that large cuts into the rock were
intact.
Rock investigations
In order to carry out a stability computation,
it was necessary to obtain sufficient
information about the angles of friction in
the main fractures. From a study of the
natural conditions and the fact that the rock
face in spite of everything was in
equilibrium, it was certainly possible to
conclude that the angle of friction in fracture
system I must be of the order of 40;
nevertheless, direct verification by tests was
imperative. The firm Terrexpert AG, of
Berne, was therefore entrusted with the task
of carrying out a number of shear tests on
specimens, which had been core drilled
transversely to the natural fractures, as they
then existed. Fig. 2 shows the results of one
such test. This was a multiple shear test,
which was carried out on the same
specimen in both directions, but with
different axial forces. The diagram indicates
the shear force and the corresponding
stress as a function of the axial force and
axial stress.
From the curves for the various movements,
it is possible to recognise a thresh-
Stability calculations
On this basis, simple calculations of the
stability against sliding were carried out. Fig.
3 shows the results of a series of
calculations. An optimisation study had
previously shown that the most favourable
angle for the rock anchors was 27 to the
horizontal. This inclination was therefore
adopted for all the main anchors. By
investigating the various fracture planes, it
was possible to determine the anchor
length. It was also possible to eliminate a
deep slip joint, which would have passed
beneath the existing road. The small table in
Fig. 3 gives the results of the calculations
for prestressing forces of 0, 1000, 2000 and
2800 kN per metre of rock face, forfracture
inclinations of 35 and 40and forangles of
friction of 32, 36, 40 and 44. It was first of
all confirmed that without prestressing
equilibrium was evidently only possible if
the angles of friction were at least as large
as the slopes of the fractures.
Fig. 6: Anchorage blocks of 1400 kN-anchors
1.3.
1.4.
Nature of rock
The Schallberg region is located in an area
of highly stratified, mica-rich calcareous
schistswitha strong tendancyto mobility.
Stability investigation
The stability investigation was carried out by
the method of Fellenius, using a computer
programme prepared by Terrexpert AG, of
Berne. In view of the length/ height ratio of
about 3 for the portion of the slope above
the road and the low shear transmission
capacity, no allowance was made for lateral
support of the individual segments. Since
the material when in the slip condition is
practically cohesionless and behaves more
like a kind of soil, soil mechanics slip
concepts were adopted for the computer
model.
The five computed cross-sections are
shown in fig. 9. From the pattern of the
contours the position of a number of furrows
can be seen, giving an indication of the
disturbed zones.
The result of the stability computation for
the part of the slope above the road is given
in fig. 10 for the cross-section 12/ 13. The
calculation was made for circular segments,
which passed through the corner of the
foundation on the uphill side.To determine
the least favourable profile, the radii of the
circles were varied in the usual way.
This gave a minimum safety factor of
F=1.42,for the case where full allowance
was made for cohesion. If, however, such
cohesion were to become ineffective for any
reason, for example due to disintegration
phenomena, then adequate stability would
no longer exist. Measures therefore were
necessary to ensure maintenance of
cohesion and to prevent disintegration
phenomena from occurring. In the present
case rock anchoring was chosen for this
purpose.
After the investigation of the slope stability
the question of the stability of the entire
slope was studied. It was pointless to
1.5.
Client
Construction Department of
Canton Schwyz
Engineer Th. Ulm, Schwyz
Contractor Joint Venture
Losinger AG, Lucerne
Locher & Co. AG, Zurich
Woest AG, Lucerne
Drilling
Injectobohr AG, Zurich
Anchors VSL INTERNATIONALAG
(formerly Spannbeton AG)
Year ofconstruction
1974
1.6.
Client
Engineer Tippetts-Abbett-McCarthy-Stratton,
New York
ContractorDrilling
Tarbela Joint Venture
contractor Johann Keller GmbH,
Frankfurt
Anchors
Years of construction
1973-1974
2 Anchoring of
retaining owalls
2.1. General
The cutting into a steep slope in soil or highly
fractured rock normally results in a
correspondingly large excavation of material
in order to prevent slips. This excess
removal can be considerably reduced with
advantage by building an anchored retaining
wall. A structure of this type can either be
formed as a continuous wall, a procedure
required particularly with soil, or it can be
broken up into slabs, a method which can be
used if local instabilities do not occur.
In general, retaining walls are constructed
more or less vertical. The procedure usually
adopted is to underpin in horizontal strips of
1.5 to 3 m height, depending on the stability
of the material. Since the stability of the wall
is assured by the stressed
2.2.
Upper-retaining wall at Delli
and
slope stabilisation at
Hauetli,
Alpnachstad, Switzerland
Client
Public Works Department,
Canton Obwalden
Engineer Werffeli & Winkler, Samen
Drilling DellI:SIF-GroutborSA,
Renens
Hauetli: Fehlmann Grundwasserbauten AG, Berne
Anchors VSL INTERNATIONALAG
(formerly Spannbeton AG)
Years of construction
Delli:1976-1977
Hauetli: 1974-1976
Introduction
The building of Swiss National High-way N8
along the central section of Lake Alpnach
(Lake Lucerne) raised the question of how
to provide sufficient area for the three traffic
routes, namely the N8, the railway and a
secondary highway. Of
the many possible variants, a combination
of placing fill in the lake and cutting into the
rock face was chosen. This required
extensive slope stabilisation work, including
the slope stabilisation at Hauetli and the
upper retaining wall at Delli.
The problem
A description of the upper retaining wall of
Delli should start with that of the
stabilisation of the slope at Hauetli (a few
hundred metres from Delli), since results of
extensive investigations exist about the
conditions at the latter and these also
applytothe Delli zone. The rockface in the
region of Hauetli was excavated in 1970/ 71
to slopes of 2:3 in the soil and of 1:1 in the
rock, without any movement being
observed. Shortly after completion of the
work, however, cracks began to appear in
the grass turf above the excavated slope.
Ayearand a half later, in November 1972,
the portion of the slope bounded by one of
these cracks slipped and further cracks
appeared, providing evidence of an
extensive movement of the ground and the
possibility of a deep slip surface. The slope
was then further monitored by
(1)
(2)
2.3.
Introduction
The Tauern Motorway runs generally north-south
from Salzburg to Villach in Carinthia, traversing the
alps. The main part of this connection which is kept
open during winter comprises the 75 km long top
section including the Tauern tunnel. In the region of
Flachau in the Ennsvalley, the motorway crosses a
pronounced geological faultzone. The outcropping
rock is a deeply weathered graywacke zone, in
which the cohesive shale decomposition products
in particular have a low shear
Bases of design
With steep slopes of such great height and the
presence of hill water, soil mechanics calculations
can, of course, give only broad guidelines; they
are useful predominantly for deciding upon
theoretical or hypothetical limiting values.
Socalled refined computation procedures usually
provide a deceptively high degree of accuracy,
which
does
not
exist
in
practice.
To examine the possibilities of slope failure, both
non-laminar and laminar methods (the Swedish
method according to Fellenius) were used and
comparative calculations were carried out by earth
pressure theory. All the investigations were based
upon highly idealised assumptions, due to the
wide scatter of the soil parameters.
The extraordinarily large influence of the soil
parameters upon the result of the stability
calculations can be seen from the following:
By changing the angle of internal friction by only
1, the anchor force necessary for obtaining a
calculated safety coefficient
9
2.4.
Client
Drilling
Anchors
2.5.
Lake
Biel, Switzerland
Highway Construction
Department, Canton Berne
Engineer Engineering joint venture
Suiselectra AG, Basle
Schaffner & Dr Mathys AG,
Biel
Steiner & Grimm AG, Berne
Contractor
Walo Bertschinger AG,
P Andrey & Cie / H. R.
Schmalz SA
Drilling Fehlmann Grundwasserbauten AG, Berne
Anchors VSL INTERNATIONALAG
(formerly Spannbeton AG)
Years of construction
1973-1974
Client
10
11
2.6.
Client
Canton Uri
Engineer Cantonal Construction
Department of Uri and
Ingenieurbro Th. Klin,
Goschenen and Schwyz
Contractor Joint venture Naxberg
Ed. Zblin & Cie AG
LVG Bauunternehmung AG
Bonetti AG
Drilling
Injectobohr AG, Zurich
Anchors VSL INTERNATIONA LAG
(formerly Spannbeton AG)
Years of construction
1972-1973
12
type 5-6
95 No. of
type 5-9
lengths of
13 te 21 m whereof 5 m
22 No. of
type 5-11
bond length
(Working force 1345 kN,
ultimate strength 1922 kN) with
lengths of
13 te 21 m, including
6 m bond length
3.
Securing of
excavations
the
Renard
authorities
are
therefore
increasingly
foundation
3.1. General
work
could
be
carried
out
in
reasons:
Client
Etablissement Public du
building.
E.T.F./Intrafor-Cofor, Paris
Paris
Intrafor-Cofor, Paris
Years of
construction
supports.
1972-1973
site.
A sheet pile wall is particularly suitable where
groundwater is present in sandy soil or gravel,
containing no rock fragments. If little or no water
Introduction
investigated:
excavation
architecte
the
soldier beams.
(Fig. 35).
anchors.
proceeds.
At
the
saure
time,
R.
Piano
&
Rogers
with
after
destressing,
they
can
form
14
Concluding comment
The use of the Berlin wall construction method
proved to be a rapid and economical solution. It
enabled the excavation to be kept clear of
obstructions so that the works could be carried out
without interference.
3.3.
Client
Railway Corporation
Engineer Freeman Fox & Partners
(Far East), Hong Kong
Contractor Metro Joint Venture
(MJV) consisting of:
Hochtief AG (FR Germany), Dragages (France),
Gammon Ltd. (Hong
Kong), Sentab (Sweden)
Drilling and Anchor contractor
VSL Engineers (HK) Ltd.,
Hong Kong
Years of construction
1975-1976
Introduction
I n view of the enormous increase in traffic
resulting from the high population density, the
government of the British Crown Colony of Hong
Kong decided in 1972 after extensive studies to
construct an underground railway network. When
completed, this will comprise four independent
lines with a total of 53 km of track, 48 stations and
two underwater tunnels (see fig. 42).
The first section to be constructed is the line
between the stations of Chater on Hong Kong
(fig. 43).
Construction was carried out partly in a 130 m
long open excavation and partly, for the remaining
100 m, by tunnelling. Since the ground water level
15
3.5.
Client
Drilling contractor
Stabilator AB, Stockholm
Anchors Internordisk Spannarmering AB,
Stockholm
Years of construction
1970-1972
Concluding comment
The successful use of soil anchors in the
Client
Stockholms Gatukontor
Engineer AB Skanska Cement-gjuteriet,
Stockholm
Anchors
Yea r of construction
1974
The rock formation underlying Stockholm is
16
drilling.
Since, as already mentioned, this was the first
3.6.
form of a
which was
Client
(Diaphragm wall)
(Prefabrication: lgeco
AG, Lyssach)
Drilling
Fehlmann Grundwasser-bauten AG,
Berne
Anchors VSL INTERNATIONALAG
(formerly Spannbeton AG)
diaphragm
Fig. 50: View of the wall
Years of construction
1972-1973
Fig. 49: Section
17
4. Anchoring against
hydrostatic uplift
4.1. General
In the vicinity of bodies of water such as
rivers, lakes, or the sea, where the
groundwater level is in general relatively
near to the surface, buildings must often be
secured against uplift. One solution to the
problem is to give the building sufficient
weight; this is, however, not always possible
and in many cases it is also not economical.
The anchoring of the structure into the
deeper, load-bearing ground by prestressed
anchors results however in considerable
savings, both in the quantity of the spoil to
be excavated and the materials to be used.
A provision for resisting uplift may be of a
temporary nature, for example for the
foundation slabs of buildings, in that it only
needs to remain effective up to the time at
which the structure possesses sufficient
weight, or it may fulfil a permanent
function,forexampleinthetanks of sewage
treatment plants, swimming pools, dry
docks etc., which are not sufficiently heavy
when empty to resist uplift. The anchors
used for uplift prevention may therefore be
formed as eithertemporary or permanent
anchors.
Another way of using prestressed anchors
is in conjunction with piles. If buoyancy or
horizontal forces act in addition to the
vertical loads, the piles must also be
capable of accepting a tensile load.
Generally such piles are therefore
prestressed. If, however, it is not possible to
drive them sufficiently into the ground, they
cannot transmit the tensile forces by surface
friction. They then are provided with
anchors which pass through them and
anchor them in the deeper strata.
4.2.
18
Introduction
The Tarbela Dam, which has already been
referred to in Section 1.6,comprisesapart from the
main dam and various auxiliary plant four bypass
tunnels, two of which are equipped with stilling
basins,
In August 1974, that is two years before the
planned commissioning of the installation, the lake
had to be drained as an emergency measure
through tunnels no. Sand 4, due to damage in
tunnels nos. 1 and 2. Due to the asymmetrical
outflow, stones and broken rock and concrete
were washed from downstream into the stilling
basins, and erosion and cavitation damage
occurred to the bottom slabs of these basins.
Since both tunnels had nevertheless to be kept in
use for irrigation purposes, the erosion increased,
especially in stilling basin no. 3, to a dangerous
extent. In the winter of 1975/ 76, the damage was
repaired with underwater concrete. In April 1976,
the basins were again brought into use
butafteronly a few hours stilling basin no. 3 again
had to be taken out of use, since large areas of the
concrete base had been carried away. This new
setback made comprehensive remedial work
essential. The main part of the new work consisted
in the anchoring of the bottom slab by rock
anchors, and making good the slab and
strengthening it. The main objective of anchoring
the bottom slab was to secure it against static and
dynamic uplift forces (vibrations) and also to make
the underlying rock participate in the actions in the
concrete.
Stilling basin No. 3is 186m long, 36.60m wide and
is sub-divided into 12 sections (see Fig. 54). The
rock conditions in the vicinity of the bottom slab
are very heterogeneous. Chlorite shales,
carbonate shales, limestone and gypsum outcrop.
The thickness and depth of the individual strata
vary considerably, and so does the quality of the
rock. Moreover, in the 80 trial bores which were
-VG=A
where
VG=calculated
working
force
of anchor (=60% of ultimate strength).
A=the uplift force associated with the
anchor, calculated from a=a1+a2
- G'=VGS1
where
Test Anchors
Ten anchors were constructed as test anchors, in
order to test the anchor itself, the installation
19
5. Securing of caverns
5.1. General
The excavation of underground chambers
in rock for tunnels, galleries and caverns
inevitably leads to a change in the state of
stress, which is reflected in strains and
deformations and in the worst case can lead
to a collapse. To prevent such an event, the
cavity must be secured. This can be done
by the installation of supports followed by
the concreting of a rigid lining. The principal
disadvantage of this method consists in the
considerable reduction of the space
available for carrying out the work by
mechanical means.
Present-day knowledge of rock mechanics
and modern rock anchor technology makes
the securing of large caverns by
prestressed anchors and gunned concrete
possible. With this method, which was
introduced in the sixties, the anchors have
the function of creating in the rock mass
around the cavity a loadbearing ring, which
is intended to prevent destressing and
appreciable displacement of the rock during
the excavation. The method has proved
very successful both as a permanent
support system itself and also in
relation to the execution of the rock removal
work.
20
5.3.
for
Bauen,
Client
Introduction
Apart from the Gotthard tunnel, the
Seelisberg tunnel is the most important
underground work on Swiss National
Highway N2, which forms the main
motorway connection in the North South
direction between Basle and Chiasso and
crosses the Alps. The tunnel is situated on
the left bank of Lake Lucerne, between
Beckenried and Seedorf. It consists of two
parallel tubes, each 9.25 km long (Fig. 60).
For the contract, the tunnel was divided into
three sections, the limits being defined by
the geological conditions. The north and
south section together with the two portals
lead partly through very hard limestone
formations. Its horseshoeshaped crosssection was driven using conventional
blasting procedures. The central section, on
the other hand, i. e. the Huttegg section, is
located throughout its entire length of about
2 km in the Valanginien marl, which
experience has shown to possess a
tendency to compression phenomena under
high overburden, its loadbearing strength
then lasting only a few hours to a few days.
It was therefore decided to adopt a circular
tunnel section and to use shield driving with
tubbings to line the tunnel.
21
22
features:
points as follows:
time;
severe
All
anchors
were
factory-assembled
deformations
were
observed.
The
and
remainder descending.
m at extensometer 2.
Surveillance instrumentation
During
the
entire
construction
time,
the
The
already
mentioned
periodic
force
23
Lausanne
Anchors
Years of construction
Dimensions of cavern
Height 29.3 m, Breadth 17.0 m, Length
330.0 m Excavation 150,000 m'
Type of rock
Client
Engineer
Contractor
Anchors
Years of construction
Dimensions of cavern
Client
Engineer
Contractor
Client
Engineer
Contractor
Anchors
Years of construction
Dimensions of cavern
Anchors
Years of construction
Dimensions of cavern
Type of rock
Securing of roof:
366 VSL rock anchors of 1350 kN working force; Length: 11.4-18.4 m. Plus 132 VSL
rock anchors of 1150 kN working force; Length: 11.4-18.4 m 1150 kN or 1350 kN rock
anchors were used depending upon the local conditions.
Spacing in longitudinal direction: 4.3 m Spacing in transverse direction: 3.0 to 4.0 m On
average, there was one rock anchor to 14 m2 of developed vault surface.
Securing of walls and face sides:
155 VSL rock anchors of 1150 kN working force; Length: 1 1.4-18.4 m
Additional securing between the large anchors:
1,729 VSL rock anchors type 6-1; length; 4.0 m. These rock anchors were anchored with
synthetic mortar. The synthetic mortar enabled the rock anchors to be stressed after 7 to
24 hours.
24
Securing of walls:
The high cavern required considerable securing of its walls.
This was done with:
270 VSL
rock anchors type 5-2
(working force 217 kN)
270 VSL
rock anchors type 5-3
(working force 325 kN)
185 VSL rock anchors type 5-4
(working force 433 kN)
11 VSL rock anchors type 5-5
(working force 542 kN)
260 VSL rock anchors type 5-7
(working force 758 kN)
45 VSL rock anchors type 5-9
(working force 975 kN)
Length: 16.0-17.0 m
The spacings between anchors both horizontally and vertically were 3 m.
In addition, 2,400 VSL mono rock anchors type 5-1 with a length of 5.0 m
were installed at regular spacings. The mono rock anchors were anchored in
synthetic mortar.
Client
Engineer
Consulting Engineer
Contractor
Anchors
Years of construction
Dimensions of cavern
Client
Engineer
Type of rock
6. Anchoring of
concentrated forces
6.1.
General
The use of prestressed anchors for the
anchoring
of
concentrated
forces
represents a very suitable method of solving
problems of this type. The function of the
anchors is to anchor parts of a structure or
entire structures to the ground.Theclassical
use of anchoring concentrated forces is
found in foundation blocks which are
subjected to large tensile forces. Examples
are the anchoring of cables for cable
railways, cable cranes, suspension bridges
and tension structures, of penstocks, crane
beam brackets, galleries etc.
6.2.
Contractor
Anchors
Years of construction
Dimensions of cavern
Type of rock
Granite
Anchors VSL
INTERNATIONAL AG
(formerly Spannbeton AG)
Years of
construction
1968-1970
Introduction
The Axenstrasse, which leads from
Brunnen along Lake Lucerne towards
Altdorf, is subjected to heavy rock falls. The
effects of erosion are particularly
unpleasant here and the mechanical
destruction of the rock due to snow, ice,
wind, rain and vegetable growth leads to a
risk of rock falls onto the main road. Rock
cleaning teams check the critical rock faces
every spring and if necessary at other times
of the year and use crowbars or explosives
to remove the looser parts of the material.
Rock falls still occur, promoted by warm
winds in the spring, and it is impossible to
prevent them completely on the 500,000 m2
rock face.The Axenstrasse is situated
throughout at about 435 m above sea level.
It is bounded on the lake side by almost
vertical rock faces. The highly fractured
The problem
Observations overa numberofyears have
shown that in general the falling stones are
not larger than a man's head, i. e., 2050 kg
in weight. Occasionally, blocks of larger
weight do occur. The most suitable way of
counteracting the rock falls effectively was
to construct a rock fall gallery. Apart from
the size and frequency of the falling stones,
the distance of drop was of great
importance for the design of this protective
gallery. The maximum difference in levels
between the Axenstrasse and the
uppermost band of rock is about 350 m.
However, since the steep parts of the face
alternate with larger and smaller steep
slopes, the actual heights of free fall are
considerably less. The probability of stones
dropping from heights exceeding 50 m
directly onto the road is extremely small.
The free fall is interrupted by impacts
25
6.3.
Client
Preussenelektra, Hanover
Engineer Siemens AG, Erlangen
girders is 5.00 m.
The rock foundations are the only parts of the
works which had to be constructed on site. The
Frankfurt
Baugesellschaft H. Rella &
Co., Vienna
Allg. Bauges. A. PorrAG,
Vienna
Dyckerhoff & Widmann KG,
Wiesbaden
Drilling
contractor Terrasond Grundbau GmbH,
Essen
Anchors
26
6.4.
76).
When fixing the position of the bores, account had
turbine discharge.
7.Stability against
overturning
7.1. General
The problem of preventing overturning
arises in a great variety of structures, the
common factor of all being that they are
subjected to horizontal forces such as wind,
water pressure, earth pressure, waves, ice
pressure, earthquake forces and the like of
sufficient intensity for their stability against
overturning to be jeopardised unless special
additional measures are taken. One
possible way of solving this problem is to
increase the weight and dimensions of the
structure. This procedure is, however,
frequently impossible or undesirable and
moreover is not often the most economical.
The stability can be provided at less cost by
means of anchors, enabling material and
construction time to be saved.
The structures where this type of problem
arises include in particular slender, light
structures such as towers, masts, pylons
and also quay walls, which in many cases
are vertically anchored, instead of being
provided with broad and heavy footings. On
the other hand, a large number of old dams
or spillway structures, which were built in
the first decades of this century, need to be
strengthened. Most of them are indeed still
in a generally satisfactory state, but they no
longer satisfy modern safety requirements
in regard to stability at exceptionally high
water levels and earthquake movements.
An ideal means of strengthening such
structures is the prestressed anchor. It
requires little space, is adaptable, can be
installed at short notice and rapidly, and no
complicated site equipment is required.
Moreover, the number of anchors required
can be kept small because of the large
forces which can be applied. In earthquake
regions, the anchors increase the
resistance to shearing, sliding and
overturning.
Swedish Navigation
Department
Engineer Vattenbyggnadbyran
(VBB), Stockholm
Drilling
contractor
Stabilator AB, Bromma
Anchors Internordisk Spannarmering
AB, Stockholm
Year of construction
1975
Introduction
At the end of the fifties the Swedish
Navigation Authorities drew up a
comprehensive programme for the
replacement of the majority of the lightships
and buoys situated alwig the east coast of
Sweden by stationary equipment. Since the
weather conditions in this region are often
bad, it was more economical to carry out the
building and installation workasfaras
possible on land and then to tow out the
completed structure to the appointed
position.
28
H=
3600
=0.48
F=0.94
N = 8300 - 800
Sliding stability with anchors:
Prestressing force after all losses > 4000 kN
m=
m=
3600
=0.48
8300-800+ 4000
F=0.94
Cost comparison
The construction costs for the lighthouse of
Kullagrund amounted to 2.0 million Swedish
crowns, of which 600,000.crowns were for the
electrical equipment (including the connecting
cable to the mainland). A cost comparison showed
that a gravity structure to give a factor of safety of
Years of construction
1978-1979
Conclusion
A structure, for which the stability is attained by
gravity alone, exerts a lower pressure on the soil
and the resulting settlements are smaller. In
addition, the stability when floating is better due to
the larger diameter of foundation, and therefore
higher towers could be built. The following points,
however, are against the foregoing and in favour
of anchoring:
the size of the forces acting upon the
structure depends to a great extent upon its
geometry, so that if the dimensions are
increased in orderto increase the weight, the
force due to the waves also increases. The
increase in weight then leads to larger
loadings and these in turn lead to an increase
-
in the dimensions.
the overall stability of a lighthouse is
determined predominantly by the friction of
the foundation slab on the ground. Even if it is
accepted that prestressing does not provide
as high a factor of safety against overturning
as gravity, nevertheless a structure secured
by anchors has a considerably increased
factor of safety against sliding.
Introduction
Milton Lake Dam is a 15.2 m high earth dam,
which dams the Mahning River, Ohio; it was built
in 1913 to 1917. Like many other small and
medium-sized dams, which were constructed at
the beginning of the twentieth century, it was
rapidly approaching the end of its
29
(Fig. 82).
anchors
were
assembled in the vicinity of the spillway. Each
anchor (ultimate strength 4783 kN) contains 26
strands of 13 mm dia, with lengths of 29.30 to
34.80 m and was fabricated to the exact borehole
length as ascertained by plumbing and was
the holes.
At the day of installing the anchors, the helicopter
hovered at 09.00 hours above the assembly area
in order to hook on the first rock anchor. A choker
was attached to the lead line of the suspension
cable on the underside of the helicopter and a
30
- Prestressing losses
Pull-out tests were carried out on two of these
anchors using bond lengths of 2.8 m and 3.3
metres. Based on these results it was decided to
use an 8 m bond length on all anchors in order to
be modified.
Design concept
Taking into account such factors as overturning
stability, resistance to sliding etc. for the revised
PMF the Engineers conducted feasibility studies
on various alternative proposals. Taking into
for
Anchor design
6000 kN
A multi-pull single jacking operation
Size of drill-hole limited
Reasonable amount of flexibility for
installation purposes
A large hollow central core to be left
tested
Initial work
The specification called for five test anchors to be
installed close to the dam wall in order to assess:
31
7.6.
32
NORTH AMERICA
Corporate Office
VSL Corporation
1671 Dell Avenue
Campbell, CA 95008
Tel 1-408-866 6777
Fax 1-408-374 4113
INDIA
Killick Prestressing Ltd.
Killick House/Killick Estate
Baji Pasalkar Marg, Chandivli
Bombay 400072
Tel 91-22-578 44 81
Fax 91-22-578 47 19
Brunei
VSL Systems (B) Sdn. Bhd.
P.O. Box 33
Bandar Seri Begawan 2600
Tel 673-2-229 153
Fax 673-2-221 954
Malaysia
VSL Engineers (M) Sdn.
Bhd., 39 B Jalan Alor
50200 Kuala Lumpur
Tel 60-3-242 4711
Singapore
VSL Singapore Pte. Ltd.
151 Chin Swee Road
# 11-01/10 Manhattan House
Singapore 0316
Tel 65-235-7077/9
Indonesia
PT VSL Indonesia
Jalan Bendungan Hilir Raya
Kav. 36A Blok B No. 3
Tromol Pos 3609/JKT
Jakarta 10210
Tel 62-21-571 1882
Fax 62-21-581 217
New Zealand
Precision Precasting
(Wgtn.) Ltd.
Main Road South
Private Bag, Otaki
Tel 64-694 8126
Thailand
VSL (Thailand) Co., Ltd.
7th Fl., Sarasin Building
14 Surasak Road
Silom, Bangrak Bangkok
10500
Tel 66-2-237 3288
Hong Kong
VSL Engineers (HK) Ltd.
20/F., East Town Building
41 Lockhart Road
Wanchai, Hong Kong
Tel 852-520 1600
Fax 852-865 6290
Korea
VSL Korea Co., Ltd.
5/F., Yang Jae Building
261, Yangjae-Dong,
Seocho-Gu
Seoul
Tel 82-2-574 8200
Fax 82-2-577 0098
Macau
VSL Redland Concrete
Products Ltd.
18 B Fragrant Court
Ocean Gardens
Taipa
Tel 853-81 00 77
Taiwan
VSL Systems (Taiwan) Ltd.
1 Fl., No 20-1, Lane 107
Hoping East Road, Sec. 2
Taipei, R.O.C.
Tel 886-2-707 7253
VSL Corporation
P.O. Box 1228
11925 12th Avenue South
Burnsville, MN 55337
Tel 1-612-894 6350
Fax 1-612-894 5708
VSL Corporation
370 Middletown Blvd. # 500
Langhorne, PA 19047
Tel 1-215-750 6609
VSL Corporation
4208 198th Street, SW
Lynnwood, WA 98036
Tel 1-206-771 3088
VSL Corporation
VSL Corporation
5555 Oakbrook Parkway, # 530 1414 Post&Paddock
Norcross, GA 30093
Grand Prairie, TX 75050
Tel 1-404-446 3000
Tel 1-214-647 0200
Fax 1-404-242 7493
Fax 1-214-641 1192
USA West
VSL Western
1077 Dell Avenue
Campbell, CA 95008
Tel 1-408-866 5000
VSL Corporation
91-313 Kauhi Street
Ewa Beach, HI 96707
Tel 1-808-682 2811
VSL Corporation
7223 N.W. 46th Street
Miami, FL 33166-6490
Tel 1-305-592 5075
Fax 1-305-592 5629
VSL Corporation
608 Garrison Street # V
Lakewood, CO 80215
Tel 1-303-239 6655
Fax 1-303-239 6623
VSL Corporation
10810 Talbert
Fountain Valley, CA 92708
Tel 1-714-964 6330
Canada
Canadian BBR (1980) Inc.
P.O. Box 37
Agincourt, ONT M1S 3134
Tel 1-416-291 1618
Austria
Sonderbau GesmbH
Sechshauser Str. 83
1150 Wien
Tel 43-222-892 02 80
Fax 43-222-892 02 80 33
Greece
VSL Systems S.A.
18, Valaoritou Str.
Athens 10671
Tel 30-1-36 38 453
Fax 30-1-36 09 543
Norway
VSL Norge A/S
P.O. Box 173
4001 Stavanger
Tel 47-4-56 37 01
Spain
VSL Iberica S.A.
Paseo de la Castellana,
11772 D
28046 Madrid
Tel 34-1-556 18 18
France
VSL France S.a.r.l.
154, rue du Vieux-Pont-duSevres
92100 Boulogne-Billancourt
Tel 33-1-462 149 42
Fax 33-1-476 105 58
Italy
Preco S.r.l.
Via Olona 12
20123 Milano
Tel 39-2-48 18 031
Fax 39-2-28 10 2111
Portugal
Sweden
VSL Prequipe SA
Internordisk Spannarmering
Av. da Republica, 47-2. Esq. AB (ISAB)
1000 Lisboa
Vendevagen 89
Tel 351-1-793 85 30
18225 Danderyd
Tel 46-8-753 0250
Germany
SUSPA Spannbeton GmbH
Max-Planck-Ring 1
4018 Langenfeld/Rhld.
Tel 49-2173 79020
Fax 49-2173 790 220
Netherlands
Civielco BY.
Rhijnhofweg 9
2300 At Leiden
Tel 31-71-768 900
Fax 31-71-720 886
South Africa
United Kingdom
Steeledale Systems (Pty.) Ltd. Balvac Whitley Moran Ltd.
8 Nansen Place
Ashcroft Road, P.O. Box 4
Tulisa Park 2197
Kirkby, Liverpool L33 7ZS
Johannesburg 2000
Tel 44-51-549 2121
Tel 27-11-613 7741
Japan
VSL Japan Corporation
Tachibana Shinjuku Bldg. 4F
2-26, 3-chome Nishi-Shinjuku
Shinjuku-ku, Tokyo 160
Tel 81-33-346 8913
Fax 81-33-345 9153
USA East
VSL Eastern
8006 Haute Court
Springfield, VA 22150
Tel 1-703-451 4300
Fax 1-703-451 0862
SOUTH AMERICA
Brazil
Bolivia
Rudloff-VSL Industrial Ltda.
Prestress VSL of Bolivia
Rua Dr. E. Th. Santana, 158
Jauregui Ltd.
Barra Funda
Calle Fernando Guachala
2do, Pasaje No 715-B, La Paz Sao Paulo/CEP 01140
Tel 55-11-826 0455
Tel 591-2-321 874
Fax 55-11-826 6266
Fax 591-2-371 493
Chile
Sistemas Especiales de
Construccion SA
Josue Smith Solar 434
Santiago 9
Tel 56-2-233 1057
Peru
Pretensado VSL del Peru SA
Avenida Principal 190
Santa Catalina
Lima 13
Tel 51-14-760 423