A Case Study:

Project: Cluster of EWS Houses 350Nos


Client: Karnataka Housing Board Govt of Karnataka
Project Implementing Agency: Rajiv Gandhi Housing
Corporation/Karnataka Habitat Centre
Technology Support: UltraTech Cement Limited, Unit -UltraTech Concrete
Specifications:
EWS House for Urban Poor
Area of Plinth - 285 sft. Single storey, I Hall, I Kitchen, I Bedroom& I Bath
cum toilet
Cost of a House - Rs 2 lacs
Technology RMD Technology adopted
Grade of Concrete M20 Dynamic grade for wall & M20 forRoof &
Foundation
Shuttering Aluminium shuttering (Mivan or equivalent)
The increase in carpet area in the above case is about 22.35 sftof the total
285 sft. Hence, increase in carpet area will be 7.8%
The above calculation does not includes the additional cost-benefits such early
occupational cost (4-5 months), and saving ininterest cost, resources holding
charges (4-5months) etc. as incase of conventional construction. The wastage of
materials at sitenot accounted (3-5%). Also not considered the scrap value of
Aluminum forms after 100 repetition (generally scrap value ishigher compared to
steel). Considering above all cost aspects, byadopting RMD Technology, about
15-20% of overall cost shall besaved.
RMD Technology as sustainable:
Mass Housing involves designing and building a homeon the insideand outto
maximize performance and conserve resources. AConcrete home consumes less
energy, water and naturalresources; creates less waste; and is healthier and
morecomfortable for the occupants all qualities that are easily achievedby using
concrete.
Case Study: 2
Execution Model House: Location Bankapura Shigao DharawdDist.

Day I: Marking of foundation, Earth work excavation by JCB at4.00 pm


Day 2: Sand Piling and Sand Bed filling, Steel fabrication forFoundation &
Plinth Beam, Concreting of Foundation & PlinthBeam, fabrication of
reinforcement of steel for wall & roof
Day 3: Erection of shuttering with reinforcement for wall &roof and
Concreting for wall & roof

Day 4: De -shuttering of wall & roof, curing compoundapplication, filling


the holes etc..
Day 5: Doors & Windows fitting, Sanitary & electrical fittings,
Whitewashing/coloring, flooring, finishing
Day 6: Ready for Opening at 10.30 am morning by ChiefMinister of
Karnataka & His Cabinet colleagues and opened at2.30 pm by CM & His
Cabinet.

Take away:
Perception Change (Reputation):
The perception onquality in mass housing among the public is very poor. With
adaptation of RMD Technology, it has been proven that theperception has been
totally changed. The RMD Technologybrings pride & appreciation to the designer,
owner, contractor,agencies who associated with the project by the end users.
On Speed: At site, 3 day/ 4 day cycle can be easily achievableand can complete
the entire house in a week time. TheFoundation, Wall & Roof components has to
be designed,based on the soil & structural considerations. All the details of
Electrical & Plumbing has to be precise and shall be placed inposition before
concreting. The RMD Technology is widelyacceptable, and the fastest technology
available at present, however, the precast technology is yet to mature enough to
replace RMD Technology in terms of cost, assembly ofelements at site, issues
associated with Joints & its sealants etc.
On Quality: The de-shuttering shall be done for wall & roofafter 24 hours of
concreting, by leaving adequate props tosupport roof concrete. Hence quality
houses are built at onego. The RMD Technology is the only technology which can
deliver the quality parameters as designed & targeted withoutmuch deviation.
The maintenance of these houses overperiod will be very less/minimum. In all
other methods,considerable change in design, manual errors, rectification,
repetitions of works etc.. is seen during the project period andsubsequently
demands high maintenance cost.
On Labour: The requirement of Labour and Skills are veryminimum and hence,
the less quality issues, speedierconstruction.
On Technology: The RMD Technology delivers the stronghouses which are
more durable & sustainable against tornado's,earthquakes etc,, compare to any
other methods of construction
On Cost: The RMD Technology for Mass Housing is com-parable and
economical for Mass Housing Projects or thesimilar projects are repeated across
many locations/sites.
Limitations:
Generally, used in mass housing project with same plan andthe multi-
storey structures having same plan area at all floors.
Huge initial investment for formwork procurement- Clientscan invest and
issue to contractor
Large number of repetitions makes this technology cost effective.

About 70-80% of form work elements shall be useful for newproject (new
plan) after first project, rest shall be suitablydesigned and procured for
next projects
Initial setting of formwork at site (as demo), as per drawingdimension, may
take more time
The training of labour to handle designed formworks at site-however, this
would overcome with support of formworksuppliers
All the utilities, has to lay & embedded in concrete walls/slabs,hence
relocation, repair of these will be very difficult
Since, structure is monolithic and wall thickness is less, thesehouses are
little warmer than the conventional duringsummer/ sunny days. However,
this problem can overcomeby using Light weight concrete (Foam
Concrete) or thermalinsulated paint for external wall or by adopting simple
thermalinsulation techniques or growing creepers & plants around the
external walls.