Chapter 1: Introduction ..1-8
Chapter 1: Introduction ..1-8
Chapter 1: Introduction ..1-8
1-8
1.1
1.2
1.3
1.4
1.5
GENERAL..1
ABOUT PLANNING OF ROAD ......7
OBJECTIVE OF THE STUDY..8
SCOPE8
BACKGROUND
CHAPTER 2: LITERATURE REVIEW..9-13
2.1 GENERAL..9
2.2 LITERATURE REVIEW9
CHAPTER 3: METHODOLOGY..14-55 (
3.1 PLANNING AND CONTOURING.14
3.2 ....16
CHAPTER 4: PLANNING OF ROAD NETWORK IN JNGEC
56-152
4.1 DESIGN RESULTS FOR AUDITORIUM...56
4.2 DESIGN RESULTS FOR DIRECTOR RESIDENCE.................................63
CHAPTER 1
1.1 GENERAL
Jawaharlal engineering college was established in the year 2006. This is the first state
government aided engineering college in Himachal Pradesh. The college campus is being
located 2 kilometers away from the NH21 at village Pungh which is 2 kilometers from
Sundernagar bus stand. At present the campus is spread over 2.6726 hectares of land, but
the total acquired land for the college campus is 14 hectares. The construction work of
administration block A, academic block B and C was completed in 2012. But
according to the norms of AICTE, the following buildings should also be present in a wellestablished engineering college. Therefore, the following buildings have been planned and
architecturally designed on Autocadd while the design & analyses is done on Staad pro in
this project report. In an engineering college campus, all the buildings are divided under
the following headings:
Administrative block
Academic block
Central library
Residential block
Office buildings
Recreational centers
1.1 INTRODUCTION
1.1. Preparation ofhighway projects involves a chain ofactivities, such as, field surveys and
investigations, selection ofalignment, carrying out various designs, preparation ofdrawings
and estimates,etc. To be compatible with technical requirements, consistent with economy,
it is essential that everyproject should be prepared after thorough investigations and
collecting all relevant information and evaluating all possible alternatives.
1.2. The extent and quality ofinvestigations have a strong influence on selection ofthe most
cost-effective design, estimation ofquantities cost and execution ofthejob itself As such,
accuracy andcompleteness of surveys deserves very special attention in project
preparation.
The objective can beachieved by carrying out the project preparation work either
departmentally or with the help ofconsultants.In any case, it should be ensured that experts
having the required knowledge are deployed on the work.Use of modern instruments and
survey techniques ensure high degree ofaccuracy and can speed up thework. Quality
Assurance Plan is required to be drawn before the start offield investigations.
1.3. Adequate funds should be earmarked for the work ofsurvey, investigation and project
preparation. Estimation ofrealistic fund and time requirement needed for project
preparation will go a longway in making the project preparation a success. It will be found
that in the long run, such investment paysmore than for itself in the form ofwell prepared
and cost effective projects, orderly schedule ofwork andtimely completion.
1 .4. Systematic presentation ofproject details is no less important. The project document is
the very basis oftechnical, administrative and financial sanction ofa project. It is also
crucial for accurateexecution of work in the field. The project should, therefore, be
comprehensive enough for properappreciation ofthe proposals as well as easy
understanding ofthe details. This Manual lays down guidelinesboth for survey and
investigations and presentations ofthe project details.
1.5. The Indian Roads Congress first published this manual in 1977. Since then,
considerableexperience has been gained by the Highways Departments and Consultants in
this field, making it necessaryto revise the manual.
1.2 STAGES IN PROJECT PLANNING
3.1. Broadly, the stages involved in the preparation and sanction of project are
1. Pre-feasibility study
2. Feasibility study/preliminary project report preparation
3. Detailed engineering and plan of construction
3.2. in some cases, specially for externally funded and BOT^ projects, it may be necessary
toprepare a pre-feasibility report to enable a funding agency or private financier to
appreciate the broadfeatures ofthe project, the levels offmancial involvement and probable
1.4 SURVEY
8. PRELIMINARY SURVEY
8.1. Purpose
8.1.1. The preliminary survey is a relatively large scale instrument survey conducted for
the purpose of collecting all the physical information which affects the proposed location
of a new highway or improvements to an existing highway. In the case of new roads, it
consists of running an accurate traverse line along the route previously selected on the
basis of the reconnaissance survey. In the case of existing roads where only improvements
are proposed, the survey line is run along the existing alignment. During this phase of the
survey, topographic features and other features, like, houses, monuments, places of
worship, cremation or burial grounds, utility lines, existing road and railway lines, stream,
river, canal crossings, cross-drainage structures, etc. are tied to the traverse line.
Longitudinal-sections and cross-sections, are taken and bench marks established. The data
collected at this stage will form the basis for the determination of the final centre line of
the road. For this reason, it is essential that every precaution should be taken to maintain a
high degree of accuracy.
Survey Procedure
8.2.1. The preliminary survey starts with running of a traverse along the selected route,
adhering as far as possible to the probable final centre line of the road. In difficult
situations, a secondary traverse connected to the primary one at either end may also be run.
In hilly areas, a trace cut 1 .0 to 1 .2 m wide, if required may be made during the
preliminary survey. For details in this regard, reference maybe made to IRC:52
'Recommendations About the Alignment Survey and Geometric Design of Hill Roads".
8.2.2. The traverse consists of a series of straight lines with their lengths and intermediate
angles measured very carefully. In difficult terrain, the alignment may have to be
negotiated through a series of short chords, preferably, the traverse should be done with a
theodolite with Electronic Distance Measurement (EDM) and all angles measured with
double reversal method. Global Positioning System (GPS) is also very useful and
appropriate for preliminary survey. The GPS will give locations in co-ordinates all the
necessary points on the traverse. GPS is very fast reasonably accurate for preliminary
system and computer friendly for data transfer. Control pillars in cement concrete should
be fixed at suitable interval (ranging from 500 m to 2 km) to have control on accuracy. It
also helps in repeating the survey, if required, within the control pillars.
8.2.3. Distances along the traverse line should be measured with EDM or total station and
accuracy of at least 1 in 10000 should be aimed at mall distance measurement.
8.2.4. No hard and fast rule can be laid down as regards distance between two consecutive
transit stations . In practice, the interval will be dictated by directional changes in the
alignment, terrain conditions and visibility. The transit stations should be marked by means
of stakes and numbered in sequence. These should be protected and preserved till the final
location survey.
8.2.5. Physical features, such as, buildings, monuments, burial grounds, cremation
grounds, places 24 IRCSP: 19-2001Of worship, posts, pipelines, existing roads and railway
lines, stream/'river/canal crossings, cross-drainage structures, etc. that are likely to affect
the project proposals should be located by means of offsets measured from the traverse
line. Where the survey is for improving or upgrading an existing road , measurements
should also be made for existing carriageway, roadway and location and radii of horizontal
curves. In case of highways in rolling and hilly terrain the nature and extent of grades,
ridges and valley sand vertical curves should necessarily be covered. The width of land to
be surveyed will depend on the category of road, purpose of the project, terrain and other
related factors. Generally, the survey should cover the entire right-of-way of the road, with
adequate allowance for possible shifting of the centre line from the traverse line.
8.2.6. Levelling work during a preliminary survey is usually kept to the minimum.
Generally, fly levels are taken along the traverse line at 50 metre intervals and at all
intermediate breaks in ground.
To draw contours of the strip of land surveyed, cross-sections should b<; taken at suitable
intervals, generally 100 to 250m in plain terrain, upto 50m in rolling terrain, and upto 20 m
in hilly terrain. To facilitate the leveling work, bench marks, either temporary or
permanent, should be established at intervals of 250 to 500 metres. The levels should be
connected to GTS datum.
8.2.7. Field notes of the survey should be clear and concise, yet comprehensive enough for
easy and accurate plotting.
8.2.8. Apart from traverse survey, general information about traffic, soil, drainage should
be
collected while the traverse is being run, as mentioned in para 8. 1 .2
(v) The vertical curves are designed and the profile determined.
1 1 .2. The alignment determined in the design office shall be cross checked in the field,
specially when the data base is not adequately updated.
11.3. Determination of the final centre line of the road forms the appropriate stage for
preparing plans and estimates for land acquisition. Land acquisition proceedings involve
time and these need not wait till the preparation of the detailed project report especially, if
administrative approval has already been obtained.
IRC:SP: 19-2001
Construction and Maintenance of Rural Roads". However, the provisions and guidelines in
this manual are expected to be applicable to a large extent to Urban Roads, Expressways
and BOT projects also. But for these roads, some additional specific requirements maybe
there, than those dealt in this document. The manual deals with new construction as well as
improvements to existing roads. Special aspects of each have been highlighted wherever
necessary. The selection of alignment of any road is generally not governed by the sitting
of cross-drainage structures except in case of major bridges of length more than 60 m.
IRC:SP:54 "Project Preparation
Manual for Bridges" lays down guidelines covering the various aspects which are to be
detailed in the preparation of a bridge project of length more than 6 m. The survey and
investigation for small cross-drainage works with length less than 6 m is covered in
IRC:SP: 1 3 . For hill roads and road tunnels, reference may also be made to IRC: 52
"Recommendations about the Alignment, Survey and Geometric
Design of Hill Roads" and IRC:SP:48 "Hill Road Manual".
2.2. In order to ensure that the surveys and investigations. Feasibility Report and Detailed
Project Report are complete and no essential detail is missed, a checklist for each of those
activities is presented in the Appendices - 4, 5&6.
2.3. It should be understood clearly that the extent of operations involved in surveys and
Investigations including the detailing of the individual aspects , would depend very much
on the size and scope of each project and the class of the highway. Depending on needs of
the situation, one or more phases of investigations might be curtailed, telescoped or made
more extensive than prescribed in the manual.
2. SCOPE
IRCSP: 19-2001
The order in which various surveys are discussed in the manual should not be taken to
mean that such work must strictly follow the same pattern or sequence. Some of the
surveys could easily be initiated in advance and carried out simultaneously overlapping
each other. For example some results of soil and materials survey and study of crossdrainage structure would be needed as an essential input to the Feasibility Report. But
more detailed investigations of these aspects may be continued in the detailed engineering
phase. It should be upto the Engineer-in-charge to exercise his discretion and adopt a
flexible approach. The requirements of the funding agencies or the authority according
administrative approval may also result in rescheduling the sequence of work and in
redefining the extent of coverage of
each work.
CHAPTER 4
Contouring
Plotting of existing buildings
Planning for other buildings about location and position
Selection of alternatives of road network
Selection of best alternatives
Preparation of master plan
Reporting final plan of road network
4.2 CONTOURING
Contouring is done using Google earth which involves selection of data points and then
interpretation of these data points with the help of other Software as explained below
Software used:
Google earth
TCX Converter
Quick grid.
Procedure for selection of area and data points from Google earth is explained below:
file
Now next further processing is done in TCX converter software.
Open TCX converter software and click on open file and select file data points for
contours.kml
Now click on update altitude and wait until altitudes are updated.
Now save the file as extension.csv
And then open this file in MS excel and delete all columns except altitude, longitude ,
Fig. 4.3 showing details of file updated with altitude in TCX converter
Open quick grid software and select add data points and input scattered data points and
select the file.
And then click on edit and set contour interval and other features as per requirements .
Now click on export DXF file and save file with extension.dxf
Now file is saved and open it in auto cad and further processing is done in auto cad as
follows
OPEN file in auto cad and contours are obtained and further processing is done as