Distribution System Handbook
Distribution System Handbook
Handbook
CONTENTS
TOPIC
PAGE
1.
Basic Electricity
1 - 10
2.
Transformer
11 - 25
3.
Testing of Transformer
26 - 73
4.
Switchgear
74 - 88
5.
Testing of Switchgear
6.
Cable
101 - 120
7.
121 - 124
8.
125 - 140
9.
141 - 173
10.
Metering Practices
174 - 196
11.
197 - 203
12.
System Loss
204 - 205
13.
206 217
14.
218 249
15.
System Operations
250 - 263
16.
264 - 289
17.
System Earthing
290 296
18.
297 - 315
19.
MASD System
316 - 334
89 - 100
BASIC ELECTRICITY
Ohms Law
Current flowing through a conductor is directly proportional to the potential difference between two
ends of the conductor provided the temperature remains constant. Therefore I V or I = V/R where
I is the current flowing through the conductor, V is the potential difference across it and 1/R is the
constant of proportionality. R is known as resistance of the conductor and is expressed in ohms ().
Kirchhoffs Current Law (KCL) states that the sum of the currents that are entering a given node
must equal the sum of the currents that are leaving the node. i.e. the algebraic sum of the currents
meeting at a node is zero. i = 0
Kirchhoffs Voltage Law (KVL) states that the algebraic sum of the voltages drops around any
closed path and the algebraic sum of the emf in that closed path at any instant of time is zero. ie E
+ iR = 0
Resistors
The resistance of a conductor is directly proportional to the resistivity of the material and the length
of the resistor and inversely proportional to the cross-sectional area of the conductor. The resistance
R of a resistor is given by R= l /
Where is the resistivity ( cm), l is the length (cm), and A is the cross-sectional area (cm2) of
the conductor. Resistivity is an inherent property of materials.
All resistors dissipate power when a voltage is applied. The power dissipated by the resistor is
represented by P = V2 / R Watt. Resistors may be joined to form networks. If resistors are joined in
series, the effective resistance (R) is the sum of the individual resistances. If resistors are joined in
parallel, the effective resistance (R) is the reciprocal of the sum of the reciprocal of individual
resistances.
Temperature Coefficient of Electrical Resistance
The resistance of a conductor changes with temperature. The temperature coefficient of a conductor
is the change in electrical resistance of the conductor per unit change in temperature. The
temperature coefficient of resistance is measured in / C and may be either positive or negative.
Capacitors
Capacitance is the concept of energy storage in an electric field and is restricted to the area, shape,
and spacing of the capacitor plates and the property of the material separating them. Capacitance of
a parallel plate is expressed as C = A/d and its unit is in Farad.
When electrical current flows into a capacitor, a force is established between two parallel plates
separated by the dielectric. This energy is stored and remains even after the input is removed. The
value of energy stored in a capacitor is C V2
Dielectric Constant is the ratio of the capacitance of a capacitor with a given dielectric to that of the
same capacitor having a vacuum dielectric. The dielectric constant of vacuum is
0 = 8.854 X 10-12 Farad/meter. The dielectric constant of most materials is affected by both
temperature and frequency, except for quartz, Styrofoam, and Teflon, whose dielectric constants
remain essentially constant.
If Capacitors are joined in parallel, the effective Capacitance (C) is the sum of the individual C. If
Capacitors are joined in series, the effective Capacitance (C) is the reciprocal of the sum of the
reciprocal of individual Capacitances.
In an ac circuit, the capacitive reactance, or the impedance, of the capacitor is Xc = 1/ 2fC
where XC = capacitive reactance, ; f = frequency, Hz; and C = capacitance, F. The current will
lead the voltage by 90 in a circuit with a pure capacitor.
When a dc voltage is connected across a capacitor, a time t is required to charge the capacitor to the
applied voltage. This is called a time constant and is calculated with the equation t = RC where t =
time(sec.); R = resistance(); and C = capacitance(F).
Quality factor is the ratio of the capacitors reactance to its resistance at a specified frequency and is
found by the equation Q = 1/ 2fCR.
Inductors
Inductance is the property which opposes any change in the existing current. Inductance is present
only when the current is changing. Inductance is used for the storage of magnetic energy. Magnetic
energy is stored as long as current keeps flowing through the inductor. In a perfect inductor, the
current of a sine wave lags the voltage by 90.
The impedance of an inductor to an ac signal, is given by XL = 2fL. where XL = inductive
reactance, ; f = frequency, Hz; and L = inductance in Henry.
If Inductors are joined in series, the effective Inductance (L) is the sum of the individual
Inductances. If Inductors are joined in parallel, the effective Inductance (L) is the reciprocal of the
sum of the reciprocal of individual Inductances. The energy stored in an inductor is equal to
L I2 where L is the Inductance of coil, I is the current flowing in it.
Mutual inductance is the property that exists between two current-carrying conductors when the
magnetic lines of force from one link with those from another.
Inductance of a coil is affected due to following:
Inductance is related to the turns in a coil as follows:
The inductance is proportional to the square of the turns.
The inductance increases as the length of the winding is increased.
A shorted turn decreases the inductance, affects the frequency response, and increases the
insertion loss.
The inductance increases as the permeability of the core material increases.
The inductance increases with an increase in the cross-sectional area of the core material.
Inductance is increased by inserting an iron core into the coil.
Introducing an air gap into a choke reduces the inductance.
When a dc voltage is applied to an RL circuit, a certain amount of time is required to change the
circuit. The time constant of the circuit is given by t = L/R where R = resistance ();
L = inductance (H); and T = time (sec).
Resonant Frequency
When an inductor and capacitor are connected in series or parallel, they form a resonant circuit. The
resonant frequency can be determined from the equation f = 1/2(LC)
Electrostatics
It is normally observed that crackling sound is produced when dry hair is combed with a comb or
while taking off terelene or nylon clothes. The above phenomena are due to the fact that synthetic
clothes and the comb are strongly electrified due to friction. When two bodies are rubbed together a
redistribution of electrons takes place. The body which loses electrons becomes positively charged,
while the body which receives electrons becomes negatively charged.
Coulombs Law of Electrostatics
The magnitude of force of attraction or repulsion between any two charged bodies:
Directly proportional to the products of their charges
Inversely proportional to the square of the distance between them, and
Depends upon the nature of medium between the charges.
Thus electrostatic force between the two charges Q1 and Q2 placed at a distance r from each other is
given by F = k Q1Q2 / r2, where k is a constant of proportionality and depends upon the nature of
medium between the two charges and is called the specific inductive capacity or the dielectric
constant of the medium. The value of k = 1 / 40r
Potential Gradient
Potential gradient is defined as the rate of change of potential with distance. It is generally denoted
by symbol g. the potential gradient g is given by g = dV / dx where dV is the change in potential
between the two points at distance dx apart. When dV is measured in volts and distance in meters,
the unit of g is volts/meter.
Electromagnetism
The bodies which exhibit the property of attracting iron are generally called magnets. Magnets are
of two types natural and artificial magnets. An iron ore called magnetite is natural magnet.
Artificial magnet can be prepared either by rubbing iron bar with a magnet or by passing an electric
current through a wire wound coil round the iron piece. This is called electromagnet. Magnet has
got two poles north & south and the line joining the two poles is called magnetic axis.
Magnetic Field
The area around a magnet or magnetic pole within which its influence is perceptible, is called its
magnetic field. Magnetic field normally termed as magnetic lines of force travel from one pole to
the other. These lines of forces form a closed loop.
Magnetic Flux
The total number of lines of force in magnetic field is called the magnetic flux. Its unit is Weber
(Wb). The lines of magnetic flux have no physical existence and it is purely imaginary. The
magnetic flux has following properties:
They form closed loops.
They always start from north pole and terminates to south pole and are continuous through
the body of magnet.
They never intersect each other.
Lines of force are like stretched elastic cords and tends to contract lengthwise.
Lines of magnetic flux are parallel and in the same direction thus repel one another.
Lines of force exert lateral pressure therefore tends to bulge outside.
Magnetic flux density is defined as magnetic flux per unit area of a surface at right angle to the
magnetic field. This is measured in Tesla or Wb/m2.
Permeability
A magnetic material when placed in a magnetic field acquires magnetism due to induction. The
measure of the degree to which the lines of force of the magnetizing field can penetrate or permeate
the medium is called the absolute permeability of the medium. The permeability of air is equal to
4 x 10-7 H/m. The absolute permeability of a magnetic medium is expressed as = 0 x r where
0 is the permeability of air and r is the relative permeability of medium.
Magnetic Field Strength
It is the force maintaining the magnetic flux and producing a particular flux density at any point in a
magnetic field. It is denoted by H and is equal to B/ where B is the flux density and is the
permeability of the medium.
Biot Savarts Law
The magnetic field at any point (x) due to an element of length dl carrying a current is directly
proportional to
Length of the element
Current carried by the element (i)
Sine of the angle between the line joining the point (x) with the length (dl)
Inversely proportional to the square of the distance of the point from the element.
Biot Savarts law is very helpful in calculating field strength of a conductor of any configuration
carrying a current.
Direction of Magnetic Field
The direction of the current flow and the direction of the magnetic field generated due to current
flowing are interrelated and can be determined through Cork Screw Rule or Right Hand Rule.
The shape of the hysteresis loop will depend upon the nature of magnetic material. Steel alloyed
with 4 % silicon has a very narrow hysteresis loop.
Hysteresis in magnetic materials results in dissipation of energy, which is proportional to the area
of the hysteresis loop. Hence the following conclusions can be drawn:
1. Flux density B always lags with respect to the magnetizing force H.
2. An expenditure of energy is essential to carry the specimen through a complete cycle of
magnetization.
3. Energy loss is proportional to the area of hysteresis loop and depends upon the quality of the
magnetic material.
Magnetomotive Force (MMF)
Magnetomotive force can be produced when current flows in a coil of one or more turns. The
Magnitude of mmf is directly proportional to the current i and the number of turns of the coil N.
mmf = N i A. If magnetic circuit of a magnetic material is homogeneous and of uniform crosssectional area, the magnetomotive force per unit length of magnetic circuit is called magnetic field
strength(H).
Reluctance
As emf / current is called resistance in electrical circuits, similarly mmf / flux can be termed as
reluctance for magnetic circuits. Thus the reluctance is the property of the magnetic material which
opposes the flow of magnetic flux though it. The magnitude of reluctance is given by
Reluctance = L/ orA for magnetic materials
Reluctance = L/ o A for non-magnetic materials
Hence the reluctance offered by the magnetic circuit or a part of magnetic circuit depends upon
nature of magnetic material, i.e. or,
length of magnetic flux path in the part of magnetic circuit (L)
cross-sectional area of the material through which flux is passing,(A)
The reluctance is expressed in ampere/weber and is denoted by S.
The reciprocal of reluctance is termed as permeance.
Laws of Magnetic Circuits
All the laws applicable to electric circuits such as Ohms law, Kirchhoffs laws etc. can be applied
to magnetic circuits simply by replacing the electrical terms with the corresponding magnetic terms.
Flux in a magnetic circuit is analogous to the current flowing in an electrical circuit.
Magnetomotive force for magnetic circuit is analogous to electromotive force for electrical circuit.
With a similar analogy, different electrical terms can be replaced by similar magnetic term.
Ohms law for magnetic circuit will be,
mmf = flux reluctance
For magnetic circuits,
Reluctance = (1 / permeability) (length / area)
=1 / or l / a
If magnetic circuit are in series than the total reluctance of the complete magnetic circuit will be
equal to the sum of the reluctances of various portions, i.e.
S = S1+S2+S3+
The total mmf for the complete magnetic circuit consisting of a number of homogeneous parts is
given by F = H1l1+ H2 l2+ H3 l3+.
Or, total mmf F = (B1/1 L1 ) + (B2 / 2 L2 ) + (B3 / 3 L3 ) +..
Where l1, l2, l3, etc, are the magnetic flux path lengths in the various parts of the magnetic circuits
and 1, 2, 3,etc, are the absolute permeability of the corresponding parts of the magnetic circuit.
Magnetic circuits
Flux is assumed to flow
Path of flux is called magnetic circuit
Flux flows due to mmf
Flow of flux is restricted by of the of
reluctance of the circuit
Flux = MMF/Reluctance
Reluctance S = L/A
Dissimilarities
1.
Self-induced EMF
The property of the coil that enables to induce an emf due to a change in current is called selfinduction of the coil. Consider a coil of N turns carrying a current of I amperes and let be the
resulting flux linking the coil. The magnetic flux forms complete loops. The product N is
normally termed as flux linkages. The term N/, i.e. flux linkages/ampere is generally called the
self-inductance of the coil or the coefficient of self-induction and is denoted by a symbol L.
e = -L di /dt
where
L = N/ I henry
Mutually Induced EMF
The phenomenon of generation of induced emf in a circuit by changing the current in a neighboring
circuit is called mutual induction. The unit of mutual inductance is also henry. It is denoted by M.
Let 1 be the flux in coil P due to current i flowing in it and 2 the flux induced in coil S due to flux
1 in coil P. Thus Mutual inductance can be expressed as the ratio of flux linkage of coil S due to
change of current in coil P.
10
TRANSFORMERS
Introduction:
Electrical Energy is considered very useful because it can be very easily transmitted & distributed
and also converted to other form of energy. The wide application of electricity has necessitated
development of robust & reliable transmission & distribution network. For transmitting bulk power
over a distance, it is desirable to have high voltage, in order to decrease I2R losses in the conductor.
On the other hand a comparatively much lower voltage is required for distribution & utilisation of
the same power for reasons of safety & convenience. A transformer makes this change of voltage
levels possible- techno-commercially. For all practical purposes, the electrical energy is
transformed thrice or may be four times before being utilised at domestic level.
There are two related principles forming the foundation upon which are based all electromagnetic
machines:
a) Law of Induction:The essentials for production of an electromotive force are electric and magnetic circuits, mutually
interlinked. In a changing / pulsating magnetic field, an emf is induced in the electric circuit. The
emf will persist only for the duration the pulsation takes place. The magnitude of the emf is
proportional to the rate of change of flux linkage.
For engineering purposes the induction law may be represented in a simplified form as
e= - Tc(d/dt) volts
where Tc is the number of turns in the electric circuit, all of which are linked completely with all the
Weber of induction. The gross flux may be resolved into two components i) mutual or working
component, ii) leakage component.
b) Law of interaction:When a conductor of length l mts. Carrying a current of i amps., lies in & perpendicular to the
direction of a magnetic field of density B webers per sq. m, a mechanical force is developed on it.
The magnitude of the force is represented as
f = Bli newtons
The direction of force is perpendicular to both current and magnetic field.
Principle of Operation:
An electric circuit / conductor carrying electricity, generates a magnetic field in its neighbourhood.
If the current is pulsating / alternating, then the magnetic field at any point in the surrounding will
pulsate / alternate in tandem with the change in current with time.
If another circuit is in the vicinity of the first, it will link some of the magnetic flux produced by the
first. If the current in the first circuit is alternating, it will produce alternating magnetic field, which
in turn will link with the second circuit and induce an emf, which may be represented as
N2 T21
In general N2 will differ from the simple product of T2 & 1 as it is not possible to ensure that all
flux generated by the first circuit will link the second one.
The mutually induced emf produced in the second circuit may be shorted through a load, in which
case a current will flow through the load and dissipate energy. The energy will flow from the first
circuit, to which the entire operation is due. Thus the energy is being transferred from the first to
the second circuit by means of mutual magnetic field. The more closely the first & second circuits
are mutually linked, the more intense becomes the transfer of energy. If the two circuits are linked
by a common iron core, the effect becomes more prominent in the following aspects:
11
a) Considerable increase in the total flux by virtue of improved permeance of the iron core
magnetic circuit.
b) A comparatively low current in the first circuit will be required, since the increased flux
per ampere induces more emf.
c) A much greater proportion of mutual to leakage flux
d) Introduction of losses in the iron core
A transformer is required to transfer electrical energy from one circuit to another, via the medium
of pulsating mutual magnetic field, as efficiently and economically as possible. Our knowledge of
magnetic materials advocates the use of iron or steel for conveyance of magnetic flux with much
greater ease than any other material. The circuits / coils are therefore made to embrace an iron core,
which serves as a good conducting path for the mutual magnetic flux, ensuring that the flux links
each coil completely.
An elementary transformer may be represented as follows:
With this elementary transformer circuit, the action of a transformer can be summarised as follows:
An alternating / pulsating voltage V1 is applied to a primary coil of T1 turns linking a suitable iron
core as shown in the figure. A magnetising current (reactive in nature) flows in the coil,
establishing a flux m in the iron part (called core). The magnitude of the flux will be such that it
induces in the coil an emf E1 due to self induction to counterbalance the applied voltage V1 and
establish an electrical equilibrium. If there is secondary coil of T2 turns, linking the same core, then
by mutual induction, an emf E2 is developed. Now if a load of finite value is connected across the
second coil, a current I2 will flow in the secondary circuit under the influence of E2. The secondary
current will, by Lenzs law, tend to reduce the pulsating flux m. This is however is prevented by
automatic adjustment of the primary current I1, thereby maintaining the flux m at the value
required to produce the emf E1. Any reduction of the flux would cause diminution of E1, leaving a
voltage difference between V1 & E1, which would be sufficient to increase the primary current and
thereby re-establish the flux. Thus any current which flows in the secondary, causes its counterpart
to flow in the primary. It is therefore evident that the electrical energy is conveyed from primary to
secondary via the magnetic flux.
The input to the transformer is V1I1 E1I1, neglecting the value of resistance.
Since the entire power input is transferred via the magnetic field, then neglecting the losses, we can
equate E1I1 = E2I2
Then E1/E2 = T1/T2 = I2/I1.
Transformer Construction:
The chief elements of a transformer are:
a) Magnetic Circuit: comprising of limbs, yoke and clamping structure
b) Electric circuit: comprising of the primary, secondary and tertiary windings, formers,
insulation and bracing devices
c) Terminals, tap switches, terminal insulators and leads
d) Tank, oil, cooling devices, conservators
e) Other ancillaries like temperature monitors, pressure relief device, Buchholz relay, oil level
indicator
Distribution Training Institute, CESC Limited
12
In older days core was generally built up with E & I section laminations. This method of core
building generally gave way to higher losses and exciting current due to abrupt transfer of magnetic
flux at joints.
Three phase mitred core with top yoke
removed.
The Core is assembled on a horizontal surface. The laminations are built up to form the magnetic
circuit. The laminations are interleaved at joints between the limbs and yokes to allow smooth &
efficient flux transfer along the natural grain lines between the core legs & yoke. This is commonly
referred to as mitred core joint. Recent trend for large power transformers is step lap joint where
flux fringing at the joint is further reduced, thereby minimising core losses, exciting current & most
importantly noise level.
13
CRGO is available in various grades generally termed as M3, M4, M5 & M6 depending on
thickness & specific loss & maximum flux density. For example 27 P 100 M4 grade steel
lamination will have specific loss 1.00 W/ Kg at max flux density of 1.85 T whereas 27G 120 M4
shall exhibit somewhat inferior properties like specific loss of 1.2 W / Kg at 1.78 T.
Conventional CRGO laminations are used in cores for general application transformers. With the
advent of star rating of energy efficiency of transformers it has become very important to reduce
core loss. In the last decade manufacturers have come out with a special silicon steel known as HiB grade core, which exhibit very low specific loss ~ 0.85 W / Kg. Popular Hi-B materials are 23
MOH & 27 MOH.
Important Physical properties of CRGO are:
Density in gm/cc: 7.65
Silicon Content: 3.10 %
Resistivity in micro ohm-cm: 48.0
Stacking factor: M4 96 %
M5 96.5 %
M6 97.0 %
Electric Circuit :
There are primarily four types of coils used and they may be classified as:
a) Crossover Coils
b) Disc Coils
c) Helical Coils and
d) Spiral Coils
Crossover Coils: These type of coils are fabricated essentially out round section of conductors and
are suitable for maximum current upto 30 amperes. Crossover coils are largely used for hv
windings of distribution transformers. The complete winding consists of a number of such coils in
series.
Disc Coils: These coils as their name implies, consist of a number of discs wound continuously
from a single wire or strips in parallel. Each coil consists of a number of turns wound radially over
one another, the conductor passing uninterruptedly from disc to disc. The conductor in this case has
to rectangular section, single or multiple in parallel. With multiple strip conductors, transpositions
are made at suitable intervals to ensure uniform current distribution. These windings are suitable for
current ranges from 40 to 60 amperes.
14
Helical Coils: These coils are suitable for windings carrying moderate current up to 70 to 100
amperes and invariably used for lv windings. The name suggests that the winding is wound in the
form of a helix and consists of a number of rectangular strips wound in parallel radially so that each
separate turn occupies the radial depth of the winding. Helical coils are used for current range ~100
amperes.
Spiral Coils: These coils are suitable for windings carrying large currents over 100 amperes. Spiral
coils consist of layers wound in continuous length from top to bottom and the composite conductor
consists of rectangular strips in parallel.
2-layer spiral winding with
2x3 rectangular section
conductor.
Transformer Oil:
Oil in a transformer serves the double purpose of cooling and insulation. For the oil to be used in
transformer, it has to satisfy certain criteria and carefully selected. The following parameters of oil
play important role:
a) Viscosity- affects cooling and varies with temperature
b) Flash Point- determines the maximum temperature the transformer can attain (1400C)
c) Pour point determines the minimum ambient temperature in which a transformer can be
run ( -60C)
d) Dielectric Strength determines the insulating property of the oil(30 / 50 KV)
e) Water Content expression of moisture present in the oil (50 during acceptance)
f) Acidity determines the maximum extent to which the deterioration of oil may be allowed
due to oxidation ( < 0.03 mg KOH / gm)
g) Resistivity (>35x1012 Ohm-cm at 900C)
h) Dielectric Dissipation Factor - 0.2 % ie 0.002 at 900C
i) Specific gravity has to be always less than 1. Value of around 0.89 acceptable.
All the above parameters play important roles in the functioning of the transformer. The oil in the
transformer undergoes deterioration during the service life of the transformer and it is essential to
carryout periodical inspection & testing of oil. The oil in service has to be purified whenever
necessary in order to maintain it in good condition.
The undesirable impurities, which cause deterioration of oil are:
Distribution Training Institute, CESC Limited
15
1. Moisture
2. Gas particularly oxygen
3. Suspended impurities
4. Acids
Guiding standards are IS 335, IEC 296
Transformer oil by nature is inflammable. There are some locations where flammable nature of oil
prevents installation of oil filled transformers. In earlier years, Askarels a synthetic liquid based
on polychlorobiphenyls (PCBs) have been used to meet such restrictions on the use of mineral oil.
However, due to environmental hazards of PCB productions, these liquid coolants have become
banned in many countries.
Transformer Tank and Cooling:
Tanks are fabricated from sheet steel, welded at joints. The top lid and radiators are of bolted
design with oil resistant sealing gaskets used at bolted joints. In older version transformers cooling
tubes were welded onto tank. In present day design, radiators are either tank mounted or header
mounted depending on transformer capacity.
The various methods of cooling are:
a) AN Air Natural
b) ON- Oil Natural
c) AF- Air Forced
d) OF- Oil Forced
All oil immersed transformers shall have cooling codification ONAN. A transformer having two or
more ratings shall have cooling code ONAN / ONAF / OFAF. By thumb rule these ratings change
in the ratio 1/ 1.5/ 2
The oil present in the transformer tank takes up heat from the coil & core through surface
conduction and rises upward. The cool oil from the bottom flows into space vacated by hot oil.
Thus a continuous circulation of oil is established. The flow of oil is completed by the hot oil
flowing to the tank sides, through the heat exchanger (or radiator), where cooling of oil takes place
and the cold oil flows downward to the bottom of the tank.
To dissipate the heat generated in a large transformer, a plain tank would have an excessively large
surface area and volume, for which a large quantity of oil will be required. Since both space & oil
are very expensive, artificial means for increasing the surface area without increasing the cubic
capacity of the tank have therefore been developed. Artificial cooling surfaces thus developed are in
the form of:
1. Plain Sheet Steel Tank
2. Fins welded to the tank wall
3. Corrugations on the tank surface
4. Round / elliptical section tubes
5. Radiators mounted on tanks or on header structure.
For large size transformers, radiators are employed for better cooling. To achieve even more
cooling with the same radiator format, it is desirable to blow air from the bottom of the radiator
banks by electric fans. For even higher capacity transformers, the best cooling solution is in the
form of an oil pump. The pump forces oil in the direction of natural flow of oil. If however the
cooling medium is water, care has to be taken to ensure that oil in the transformer has a higher
static head than the cooling water so that any leakage in water pipe line will not contaminate the oil
in the transformer.
Conservators are required to take up the expansion & contraction of the oil with changes of
temperature, without allowing the oil to come in contact with the air, from which it is liable to take
up moisture. The displacement of air due to change in oil volume takes place through a breather
containing silica gel crystals which extracts moisture from the air. Experience shows that it is not
Distribution Training Institute, CESC Limited
16
practically possible to trap the entire moisture present in air by slica gel crystals. The minimal
quantity of moisture that goes into the conservator with air due to breathing action is instantly
absorbed by hot oil due its hygroscopic nature. Absorption of moisture by oil results in its
deterioration along with dissolved gasses particularly oxygen. To obviate this mechanism of oil
contamination by air due to breathing action, design of conservators has been modified to
accommodate an air cell of suitable size, inside. The air cell has to be leak proof and non-reactive to
hot transformer oil. The air cell serves the purpose of separating oil from air since air flows in &
out from inside of the cell while oil occupies area outside the cell.
Conservators are fitted with oil gauges, which indicate oil level in the conservator. Oil gauges are
generally of two types:
a) Prismatic oil
b) Magnetic Oil Gauge
Temperature Monitors:
Distribution Training Institute, CESC Limited
17
18
19
20
21
Losses in a Transformer:
Distribution Training Institute, CESC Limited
22
a) No-load loss: It comprises of loss in the core, which in turn may be broken into hysteresis &
eddy current loss, also no-load loss includes I2R loss in the HV winding.
b) Load Loss: It comprises I2R losses in both HV & LV windings as well as stray loss that take
place in tank wall and other sheet metal structures.
Impedance Volt:
It is the voltage required on the primary side, to circulate full rated current in the secondary winding
with the secondary winding terminals fully shorted. It is expressed as percentage of the primary
rated voltage and is popularly known as percent impedance.
Parallel Operation of Transformers:
Satisfactory parallel operation of transformers is dependent on 5 principal characteristics:
a) The phase angle difference shall be identical ie of same vector group
b) Same voltage ratio
c) Same polarity
d) Identical or near identical % impedance
e) Same phase sequence
Voltage Variation & Tap Changer:
The voltage of a power system is varied by adjusting tappings on the transformers. The variation in
voltage may be in carried out in pre-determined steps or by stepless control. The tappings on a
transformer are taken out from the HV winding because of low current.
Transformer tap changing equipment generally classified into two categories:
a) OFF circuit Tap Changing in which case the tap changing operation is carried out after
switching off the load & isolating the transformer from both sides. The drawback of this
arrangement is that it necessitates opening the handhole cover & lowering of oil. It is
however extremely simple & cheap.
3-phase 11 KV, 50 A, off-circuit
rotary tap switch
b) ON-Load Tap Changing in which case the tap change operation is carried without
interrupting the load.
All forms of on-load tap changer circuits possess two fundamental features:
An impedance is introduced to prevent direct shorting of two taps
A duplicate circuit is provided so that one circuit may carry the load current while
tap change operation is carried out in other.
The impedance can take the form of either a resistance or a centre-tapped reactor based on which
OLTCs are in general termed as reactor or resistance type. It is well accepted that resistance type
OLTCs demonstrate advantages due to longer contact life, due to relatively short arcing times
(because of upf switching). However in older version OLTCs reactor type switching was more
popular inspite of low contact life, because the reactors were designed to carry full load current
continuously. Whereas the transition resistances have finite time rating due to high power
dissipation when in circuit.
Distribution Training Institute, CESC Limited
23
The switching or transition resistances are short time rated. With the introduction of nickel
chromium alloy in resistance material, the risk of resistance damage has been reduced to minimal as
the resistances are in the circuit for a few milli-second. The switching time is ~ 60 70 ms.
24
25
TESTING OF TRANSFORMER
1.0
Tests on Transformer:
Unlike many items of power system electrical plant (e.g. switchgear, motors) most
transformers are still virtually handmade, little or no mass production is employed in
manufacture and each is produced very much as a one-off. Since transformer is important
and vital equipment, it is therefore, necessary to ensure its proper performance throughout
its service life.
When all manufacturing process has been completed, necessary type testing and / or routine
testing and special & additional tests are performed on transformer at the manufacturer's
works prior to dispatch.
Tests are also carried out on a transformer before commissioning after installation at site
and to detect fault in the transformer after failure in service.
1.1
Standards to be Referred:
The general requirements and details of the various categories of tests are in accordance
with IEC Publication 60076 and Indian Standard IS: 2026.
1.2
Routine Tests:
To check that the quality requirements have been met and that performance is within the
tolerances guaranteed, the following tests are generally performed on every unit
manufactured at works which may also form a part of the customer acceptance requirements.
a) Measurement of winding resistance (Ref. 2.0)
b) Measurement of voltage ratio, polarity and check of voltage vector relationship (Ref.3.0).
c) Measurement of no-load loss and excitation current (Ref.4.0).
d) Measurement of short-circuit impedance and load loss (Ref.5.0).
e) Measurement of insulation resistance & PI (Ref.6.0).
f) Tests on load-tap chargers where appropriate (Ref.7.0).
g) Dielectric tests (Ref.8.0).
(i) Switching impulse withstand voltage test, transformer winding Um > 170Kv
(ii) Lightning impulse withstand voltage test, transformer winding Um > 72.5Kv
(iii) Separate Source withstand voltage test.
(iv) Induced AC over voltage withstand voltage test.
1.3
Type Tests:
The following tests are carried out on a transformer which is the representative of other
transformer to prove that the transformer meets the customer specifications and design
expectations.
a) Dielectric type tests (Ref.8.0).
b) Temperature rise test (Ref.9.0).
26
1.4
Special Test:
In addition to the above tests , any or more of the following special tests other than routine &
type tests may also be performed by mutual agreement between the purchaser and the
supplier to obtain information useful to the user during operation or maintenance of the
transformer.
a) Lightning impulse test on neutral terminal (Ref.10.0).
b) Long-duration induced AC Voltage test (ACLD) for transformer winding
72.5 < Um = 120kV (Ref.8.0)
c) Short circuit Test (Ref.11.0)
d) Measurement of zero sequence impedance on three phase transformer (Ref.12.0)
e) Measurement of acoustic noise level (Ref.13.0)
f) Measurement of harmonics of the no-load current (Ref.14.0)
g) Measurement of the power taken by the fan and oil pump motors (Ref.23.0).
h) Test with lightning impulse chopped on the tail (Ref.15.0).
i) Determination of capacitance and dissipation factor between winding to earth and between
windings (Ref.16.0).
j) Determination of transient voltage transfer characteristics (Ref.17.0).
k) Measurement of Partial Discharge of windings (Ref.27.0)
1.5
Additional Test:
The tests carried out for customer specific requirements are referred as additional Tests.
Any or more of the following tests shall be arranged as additional test.
a) Magnetic circuit (Isolation) test (Ref.18.0)
b) Determination of capacitances and dissipation factor condenser bushing (Ref.16.0).
c) Magnetic balance test on three phase transformers (Ref.19.0)
d) Dissolved gas analysis (DGA) of oil filled in the transformer before and after temperature
rise test above 72.5kV (Ref.20.0).
e) Frequency response analysis (FRA) test >170kV (recommended) (Ref.21.0).
f) Measurement of magnetization current at low voltage (Ref.22.0).
g) Functional test on auxiliary equipment (Ref.23.0)
h) Tests on oil filled in transformer (Ref.24.0)
i) Oil pressure test on completely assembled transformer (Ref.25.0)
j) Dew point measurement before dispatching (Ref.26.0)
l) Dielectric tests (Ref.8.0).
m) Measurement of Efficiency & Voltage Regulation (Ref.28.0).
27
1.6
The purpose interpretation, acceptance criteria and explanation for specific conditions of the tests
are briefly described here.
28
2.0
2.1
General:
Resistance measurement helps to determine the following:
a)
Calculation of the I2R losses.
b)
Calculation of winding temperature at the end of a temperature rise test.
c)
As a benchmark for assessing possible damage in the field
Determination of cold temperature:
The resistance is measured at ambient (cold) temperature and then converted to
resistance at 750C, for all practical purpose and comparison with specified design
values, previous results and diagnostics. Thus cold temperature of the winding shall
be determined as accurately as possible when measuring the cold resistance.
For the winding with tapping, the resistance shall be measured at all taps.
2.2
Resistance Measurement Methods:
2.2.1 Voltmeter Ammeter Method :
Method can be employed for the transformer winding with rated current of 1A or
more.
Measurement circuit connections are shown in Fig.1
29
The direct current should be switched off by a suitably insulated switch to protect
the personnel from inductive kick
The applied direct current shall be 15% of rated current of winding under text to
avoid heating of the winding.
The measuring instruments shall have such ranges as will give reasonably large
deflection.
Readings shall be taken after the current voltage has reached steady state values.
The voltage leads shall be independent of the current leads and shall be connected as
closely as possible to the terminals of the winding to be measured.
Readings shall be taken with at least four values of current when
deflecting type
instruments are used.
Test results of a typical transformer
30
3.0
Measurement of Voltage Ratio, Polarity & Check of Voltage Vector Relationship:
3.1
Ratio Test
3.1.1 General:
The turn ratio of a transformer is the ratio of the number of turns in the high voltage
winding to that in the low voltage winding.
When the transformer has taps the turn ratio shall be determined for all taps and for
the full winding.
The ratio test shall be made at rated or lower voltage.
The voltage shall be applied to the winding from source with higher voltage rating.
When each phase is accessible and independent single-phase supply can be used
although, when convenient, three-phase supply may be used.
3.1.2 Ratio Test Methods
3.1.2.1 Voltmeter Method :
Measuring circuit diagram shown in Fig. 2
The measuring instruments shall have such ranges as will give reasonably large
deflection.
3.1.2.2 Ratio Meter Method :
The diagram of connections for this test is shown in Fig. 3.
This method is most commonly adopted.
In this method the turn ratio on each tapping between pairs of winding shall be
measured by a direct reading ratio meter.
Distribution Training Institute, CESC Limited
31
This method gives more accurate results using a ratio bridge that provides phase
angle correction, as compared to other methods.
3.2
Polarity and Vector Group Verification :
3.2.1 General:
Polarity and phase relation tests are of interest primarily because of their bearing on
paralleling or banking two or more transformers.
Phase relation tests are made to determine angular displacements and relative phase
sequence.
Phase relation or vector group verification test is performed on a three-phase
transformer on a bank of three single-phase transformers.
3.2.2 Polarity Check
3.2.2.1 Polarity by Alternating Voltage Test :
32
winding.
3.2.2.2
The Modern Ratio Bridge are also used to Test Polarity Phase Relation and Phase
Sequence
3.2.3 Vector Group Verification:
A ratio meter method may be adopted to check polarity and vector group
verification.
When ratio meter is not available, this is usually the case on site so that polarity must
be checked by voltmeter.
In this method primary and secondary winding are connected together at one point as
indicated in Fig.5. Low voltage three phase supply is then applied to the HV
terminals. Voltage measurements are then taken between various pairs of terminals
as indicated in the diagram and the readings should be the phasor sum of the separate
voltage of each winding under consideration.
33
34
3.2.3.1
c
C
35
4.0
4.1
4.2
P=
Pm
P 1 + KP 2
K =
U r
U = Voltage measured by r.m.s. voltmeter
U r = Voltage measured by mean voltmeter
The above corrected is valid for the excitation voltage having 5% distortion. For
greater distortion the excitation voltage should be corrected.
If the test frequency is not equal to the rated frequency, the no-load losses measured
should be corrected to the rated frequency by multiplying correction factor (Kf) as
shown below:
Kf = 0.5 (Fr / Ft) + 0.5 (Fr / Ft) 2
Where Kf = No load loss correction factor to rated frequency
Fr = Rated frequency
Ft = Test frequency
The currents measured during test are excitation current. For three-phase transformer
the average value of three currents is considered for calculation.
36
4.3
Tolerance:
According to IEC 60075 tolerance on iron loss/no-load loss is +15%, but the
combined iron loss plus copper loss must not exceed + 10% of the declared value.
The tolerance of no-load current is + 30% of the declared value.
37
38
b)
For three phase transformer three phase power measurement utilising two wattmeter
results in very large errors at low power factors encountered in the test.
For accurate measurement wattmeter should be connected in each phase for three phase
transformer.
Measurement with Power Analysers:
Now a days, digital power analysers or power meters are available for determination of
load losses.
The new generation of analysers are equipped with software for automatic calculation of
corrected losses based on the input data of voltage, current, power, frequency and
temperature.
The connection circuit diagram is shown in Fig.8.
Fig.8
5.4 Corrections:
Load loss measurements vary with temperature and in general must be corrected to a
reference temperature.
The copper loss and impedance are normally guaranteed at 750C but in fact both are
normally measured at test room temperature and the results obtained corrected to 750C
on the assumption that the direct load loss (I2R) varies with temperature as the variation
in resistance and the stray load loss varies with the temperature inversely as the
variation in resistance.
The formula for calculating load loss at reference temperature is
R r =R
235 + r
235 + t
t
Pa t = Pt I 2 Rt
P ar = P
235 + t
235 + r
at
Pr = I 2 R r + Pa r
where, I = Rated current of test winding
Rr = Winding resistance at reference temperature in ohm
Distribution Training Institute, CESC Limited
39
40
41
10 min the leakage current becomes constant and effects of charging current and absorption current
die down.
6.6 Acceptance Criteria:
It is recommended that PI value for power transformer shall be better than 1.5
42
With the transformer de-energized, eight complete cycles of operations (a cycle of operation
goes from one end of the tapping range to the other, and back again)
With the transformer de-energized, and with the auxiliary voltage reduced to 85% of its rated
value, one complete cycle of operation.
With the transformer energized at rated voltage and frequency at no load, one complete cycle of
operation.
With one winding short circuited and, as far as practicable, rated current according to IEC
60076-1 in the two windings, 10 tap-change operations across the range of two steps on each
side from where a coarse of reversing change over selector operates, or otherwise from the
middle tapping.
7.2 Auxiliary Circuits Insulation Test:
After the tap-changer is assembled on the transformer, the wiring of auxiliary power & control
circuitry shall be subjected to a 1 min AC separate source test of 2 kV r.m.s. to earth according to
IEC 60076-3 unless otherwise specified.
7.3 Test Report of OLTC for a typical transformer is given below
43
Highest
voltage for
equipment
Um kV
Uniform
insulation
Um=<
72.5
72.5<Um=
Uniform
and non- <170
uniform
170<Um
insulation
=<300
Um>=300
Tests
Lightning
Impulse
(LI)
Switching
Impulse
test (SI)
Long
duration
AC
(ACLD)
Short
duration
AC
(ACSD)
Separate
source AC
Type
Not
applicable
Special
Routine
Routine
Routine
Not
applicable
Special
Routine
Routine
Routine
Routine*
Routine
Special*
Routine
Routine
Routine
Routine
Special
Routine
44
Table: Dielectric withstand test level according to IEC 60076-3 or IS 2026-3 for typical system
voltages.
System voltage (kV)
220
395
132
275
36
70
11
28
20
0.4
Te s t Tra ns fo rm e r
T r a n s f o r m e r u n d e r te s t
CV D
C h a r g in g
c urrent
A m m e te r
F IG -
A
*
**
T y p ic a l C o n n e c t io n D ia g r a m fo r S e p a r a t e S o u r c e
V o lt a g e W ith s t a n d T e s t
45
Tra ns f orm e r
T r a n s f o r m e r u n d e r te s t
CT1
CT2
G
CT3
CV D
P.T .
V m k V / 2
D ig it a l P o w e r M e t e r
F IG -
In d u c e d V o lt a g e T e s t
46
2 x 1 /3 V 1
V1
F ig - A
V 2= 2 x 1/3 V 1
Vs
A
C
Us
V a=2 x V s
F ig - B
Vs
F ig - C
8.3 Long duration induced AC withstand
voltage test (ACLD)
This test is not a design proving test, but a quality control test and is intended to cover temporary
over voltages and continuous service stress. I verifies PD free operation of the transformers under
operating condition.
47
ACLD test is always performed with the measurement of partial discharge during the whole
application of test.
Test arrangements and conditions are similar to that for ACSD test.
The time sequence for application of the test voltage, whether this is a test to earth or a test between
phases is as shown in fig.
The test voltages to earth shall be:
U1 = 1.7 Um / 3 kV
U2 = 1.5 Um / 3 kV
For networks where transformers are severely exposed over voltages, values for U1 & U2 can be
U1 = 1.8 Um / 3 kV & U2 = 1.6 Um / 3 kV
Time sequence for the application of test voltage with respect to earth
A = 5 min
B = 5 min
C = test time
D = 5 min
E = 5 min
48
220
950
132
650
36
170
11
75
60
The test is successful if no failure is detected after comparing wave shapes of different oscillograms
during the test.
49
Rectifier
Rod gap
Voltage Divider
CRO
Impulse
Generator
CRO
Test Object
Sphere gap
HV Transformer
FIG-
8.5 Switching Impulse Withstand Voltage Test (Transformer Winding Um > 170Kv) :
This test is intended to verify the switching impulse withstand strength of the line terminals and its
connected windings to earth and other windings, the withstand strength between phases and along
the winding under test for surges generated by system switching.
The impulses are applied either directly from the impulse voltage source to a line terminal of the
winding under test, or to a lower voltage winding so that the test voltage is inductively transferred
to the winding under test.
For switching impulse withstand test the voltage impulse shall have a virtual front time of at least
100s, a time above 90% of the specified amplitude of at least 200s, and a total duration from the
virtual origin to the first zero passage of at least 500s but preferably 1000s.
The impulses are applied either directly from the impulse voltage source to a line terminal of the
winding under test, or to a lower voltage winding so that the test voltage is inductively transferred
to the winding under test.
According to IEC 60076-3 the test voltage for transformer winding with highest system voltage
245kv is 750kv.
The test is successful if there is no sudden collapse of voltage or discontinuity of the neutral current
indicated on the oscillographic or digital record.
9.0 Temperature Rise Test
9.1 General:
Temperature rise test is performed to prove that temperature rise comply to limits specified in
standards and to derive thermal characteristic of the transformer.
9.2 Test Conditions:
The test is carried out by supplying calculated total losses (sum of maximum copper loss or load
loss at reference temperature and iron loss or no-load loss at rated voltage previously obtained by
two separate determination of losses) for sufficient time to ensure that the temperature rise of the
winding and oil reach steady state value.
The transformer shall be assembled completely with its cooling equipment and conservator.
The top oil temperature is measured by a temperature sensor in a pocket (filled with oil) at the top
of the transformer tank, and this is used to verify that steady conditions have been reached.
Final winding temperatures cannot be measured directly. The average winding temperature is
determined via measurement of winding resistance.
50
The transformer shall be tested in the combination of connections and taps that give the highest
winding temperature rises. This will generally involve those connections and taps resulting in the
highest losses.
All temperature rise test shall be made under normal (or equivalent to normal) conditions of the
means of cooling.
The temperature-rise test shall be made in a room that is free from drafts as practicable and
equipped with its protective device.
Precautions should be taken to minimize variations of cooling air temperature specially when the
steady state is approached. Rapid variation of reading should be prevented by providing at least
three sensors, and average of their readings shall be used for evaluation. The sensors shall be
distributed around the tank 1m to 2m away from the tank or cooling surface and protected from
direct radiation. The sensors shall be placed at a level about half way up the cooling surface.
9.2 Purpose of This Test:
To establish the top oil temperature rise in steady state condition with dissipation of total losses.
To establish the average winding temperature rise at rated current and with the top oil
temperature rise as determined above.
9.3 Short Circuit Method of Temperature-rise Test:
Simplified connection diagram is shown with sample test report.
This is achieved b in two steps
a) Total Loss Injection
First the top oil and average oil temperature rises are established when the transformer is
subjected to a test voltage such that the measured power is equal to total losses or at least 80%
of the total losses of the transformer. The test current will be above the rated current to the
extent necessary for producing an additional amount of loss equal to the no-load losses, and
winding temperature rise will be correspondingly elevated.
The oil temperature and cooling medium temperature are monitored, and the test is continued
until a steady state temperature rise is established.
The test may be terminated when the rate of change of top oil temperature rise has fallen below
1deg cent per hour and has remained there for a period of 3 hour.
b) Rated Current Injection
When the top oil temperature rise has been established, the test shall immediately be continued
with a test current reduced to 50% the rated current for the winding combination connected.
This condition is maintained for 1 hour, with continuous observation of oil cooling medium
temperatures.
At the end of 1 hour, the resistances of windings are measured with a suitable method.
During the hour with rated current the oil temperature falls. The measured values of winding
temperature shall therefore be raised by the same amount as the average oil temperature rise has
fallen from the correct value. The corrected winding temperature value minus the cooling
medium temperature at the end of the total losses injection period is the average temperature
rise.
9.4 Determination of Average Winding Temperature Rise
The average winding temperature is determined via measurement of winding resistance. A
reference measurement (R1, 1) of all winding resistance is made with the transformer at ambient
temperature, in a steady state condition. When the resistance R2 at different temperature (2) is
measured this yields the temperature value
Copper: 2 = R2/R1( 235 + 1) 235
The external cooling medium temperature at the time of shutdown is a
Distribution Training Institute, CESC Limited
51
Corrections
If the specified values of power and current have not been obtained during the test, the result shall
be corrected according to the following relation. They are valid within a range of +/-20% from
target value of power and +/-10% from target value of current.
The rise of oil temperature above ambient during the test is multiplied by
[Total losses/Test losses]
Where
X = 0.8 for distribution transformers
X = 0.9 for larger transformers with ON cooling
X = 0.8 for transformers with OF & OD cooling
The average winding temperature rise above average oil temperature during the test is multiplied
by:
[Rated current/Test current]
Where
X = 1.6 for ON & OF cooled transformer
X = 0.8 for OD cooled transformer
52
53
54
55
Components
Zs Test system impedance
S Synchronous switch for post-set short circuit or a rigid connection bar for pre-set short circuit.
56
57
Measurement of the audible sound and microphone location for a typical transformer is given
below.
58
59
60
The standard chopped lightning impulse shall have a time to chopping between 2s to 6s sec.
The recommended order of the different impulse application is
One reduced level full impulse.
One full level full impulse.
One or more reduced level chopped impulse.
Two full level chopped impulse.
Two full level full impulse.
The same types of measuring channels and oscillographic or digital records are specified as for the
full wave impulse test.
16.0 Determination of Capacitances and Dissipation Factor between winding to earth &
between windings and Bushings.
Capacitance and tan delta are usually determined for winding to earth & between windings by
bridge measuring technique such as Schering Bridge.
The test specimens have the following requirements:
All windings immersed in insulating material.
All windings short circuited.
All bushings are in place.
The applied voltage for measuring capacitance and tan delta shall not exceed half of the low
frequency test voltage, for any part of the winding or 10kV whichever is lower.
The above test shall be made from winding to ground and between winding as shown below.
61
Function
UST
GST
GSTg
Connection
Guard
Result
HV
LV
CHL
LV
HV
CLH
HV
LV
CHL+CH
LV
HV
CLH+CL
HV,LV
Tank
CH+CL
HV
LV
CH
LV
HV
CL
Accepta
nce
criteria:
At temp. 20oC
Winding
Bushing
62
1U
2U
1V
2V
1W
2W
The induced voltage is measured with 2 kV applied on HV winding on all the three limbs, one at a
time.
* Voltage applied
19.2 Evaluation criteria:
The voltage induced in the center phase is generally 15% to 90% o the applied voltage on the outer
phases. However when the center phase is exited then the voltage induced in the outer phases is
generally 30-70% o the applied voltage.
Distribution Training Institute, CESC Limited
63
64
The reference frequency responses obtained during laboratory testing serve as fingerprints to
monitor the condition of the transformer or reactor during service.
The frequency response of an electrical winding is obtained by application of sweep frequency
(sinusoidal).
The response is uniquely determined by the winding arrangement involved and any winding
movement or other fault will modify the frequency response due to changes in inductances and
capacitances.
The sweep frequency voltage is applied through network analyzers.
The frequency response of the winding is determined between the frequency ranges of 10Hz to 2
MHz.
The FRA test is performed in one winding of the electrical equipment at a time.
The two end terminals of each winding shall be made available for measuring the frequency
response across the winding.
For star connected winding, the response shall be measure across the line terminal &
neutral.
For delta connected winding, the response shall be measure across two line terminals and in
case of open delta, across individual winding.
For auto connected winding , the response of series and common windings shall be measure
separately.
The frequency response of the winding is determined by plotting the ratio of the output of the
winding to the input in a frequency range of 10Hz to 2MHz.
The FRA results are analysed for :
Changes in response of the winding.
Significant difference between the FRA records of different phases of the same transformer.
Significant difference between same phase of identical transformers.
FRA test is primarily a condition assessment test and can be used in conjunction with other
diagnostic tests for detail analysis and interpretation of the transformer.
22.0 Measurement of Magnetization Current at Low Voltage
For three phase transformers , the test shall be conducted either with 415 volts 3phase (neutral
grounded) or 230 V single phase.
For 1-phase transformer the test shall be conducted with 230V.
The test is performed to locate defect in magnetic core structure, shifting of winding, failure in turn
insulation or problem in tap changers.
The acceptance criteria for the results of exiting current measurement should be based on the
comparison with the previous site test results or factory test results.
The general pattern is two similar high readings on the outer phases and one lower reading on the
center phase, in case of 3- phase transformer. And agreement to within 25% of measured exciting
current with the previous test is usually considered satisfactory.
If the measured exciting current value is 50% higher than the value measured during pre
commissioning test, then the winding needs further analysis.
65
Test Results of a typical transformer when primary winding is supplied from 400V 3-phase source
and secondary winding kept open circuited and vice versa are given below.
66
Measurement of current & power consumption at rated voltage and frequency with pumps
and fans being operated as appropriate for the rating of the transformer under test.
23.6 High Voltage Test on Insulation of auxiliary winding
Unless otherwise specified the wiring or auxiliary power and control circuitry shall be subjected to
a 1 minute power frequency withstand test of 2 kV rms to earth.
Test report of auxiliary power consumption for a typical transformer is given below.
67
72.5
60
20
<0.05
72.5
245
65
15
<0.02
245
420
70
10
<0.01
420
800
75
10
<0.01
24.4 Resistivity:
This is numerically equal to the resistance between opposite faces of a centimeter cube of liquid.
Resistivity measurement are made at many different temperature but for acceptance test it is
generally done at a temperature of 90 oC, while for routine testing, it is usually made at room
temperature or at 90 oC.
The average electrical stress to which specimen is subjected to shall not be >200V/mm nor
<1200V/mm.
68
The upper limit is set with the purpose of avoiding possible ionization if higher stresses are
permitted.
25.0 Oil Pressure Test on Completely Assembled Transformer
25.1 General
This test is done after completion of all electrical and temperature rise test. Transformer with
cooling bank, bushing and other accessories shall be tested for any oil leakage at high pressure
(normal pressure plus 35kN per sq.m measure at the base of tank) and at room temperature as
specified by the customer.
25.2 Procedure
The procedure for conducting this test is as follows:
Conservator along with the Buchholtz relay shall be disconnected.
Calibrated pressure gauge shall be mounted at the bottom of the tank.
Bushings will remain mounted.
In welded cover type construction cooler bank, bushing shall be removed but all turrets &
cover pipe work shall remain.
Fill the oil, completely and release all trapped air.
The specified pressure shall be maintained for the specified test duration as specified in the
test schedule or quality plan.
The test duration should be at least one hour unless otherwise specified.]
25.3 Criteria for oil pressure test:
During the pressure test there shall not be any leakage.
If there is pressure drop during the test either because of some trapped air inside the transformer or
due to ambient temperature variation, the pressure shall be raised to the specified level.
The unit will be considered to pass the test only if there is no visual oil leakage.
Pressure drop shall be considered as failure of the unit of the test.
26.0 Dew-Point Measurement for Large Transformers Filled with Dry Air or Nitrogen
Large rating transformer are transported to site from manufacturing works, without oil and filled
with dry air or nitrogen due to weight limitations. Positive gas pressure is generally maintained at
0.175kg/sq.mm during transportation & storage.
After arrival of transformer at site it is necessary to check the gas pressure and if it is not positive
there is every possibility that moisture must have gone inside the transformer during transportation.
To ascertain this factor & to check the dryness of the insulation, dew point measurement is carried
out at site.
Dew point is the temperature at which the water vapors present in the gas filled in the transformer
begins to condense.
69
For transformer with a gas pressure of 0.3 PSI, the acceptable limits of dew point shall be as under:
70
27.0
PD Measurement of Winding :
71
72
2.0
References:
IS 2026 & IEC 60076
73
SWITCHGEAR
74
4. Voltage Transformers :
Steps down the primary voltage to a value, usually 110V, for relaying, metering & other
miscellaneous purposes.
VTs are housed on the CB truck (Siemens, ABB etc.) upto 33kV but in 132 kV system and
above VTs are separate entity.
5. Operating mechanism :
This is a mechanical device which enables closing & tripping of the switchgear. The mechanism
can be hand operated or electrically operated or pneumatic/ hydraulic operated.
Solenoid closing
Spring closing
Manual closing
Pneumatic closing/opening
For low rupturing capacities hand operated mechanisms are used, otherwise in all HV and EHV
Breakers spring or solenoid mechanism are used except in 132 kV GIS Breakers.
6. Bus Bars :
A busbar in electrical power distribution refers to thick strips of copper or aluminum that
conduct electricity within a switchboard, distribution board, substation, or other electrical
apparatus.
Size of the busbar is important in determining the maximum amount of current that can be
safely carried.
Busbars are typically either flat strips or hollow tubes as these shapes allow heat to dissipate
more efficiently due to their high surface area to cross-sectional area ratio.
Due to skin effect, hollow or flat shapes are prevalent in higher current applications. A
hollow section has higher stiffness than a solid rod, which allows a greater span between
busbar supports in outdoor switchyards.
Busbars may be connected to each other and to electrical apparatus by bolted or clamp
connections. Often joints between high-current bus sections have matching surfaces that are
silver-plated to reduce the contact resistance.
75
Busbar Arrangements
Single Bus Bar (SBB) :
6 & 11 kV SBB: ABB SF6 switchboard & Siemens Vacuum switchboard at different stations,
Reyrolle board at Hare Street D/S (vertical isolation) 33 kV SBB: Siemens board at SRS, East Cal
S/S, Majerhat S/S.
Double Bus Bar (DBB) :
6 & 11 kV DBB: Reyrolle board at Sukchar D/S, Park Lane D/S, BIECCO board at Elgin Road
D/S, AEI board at Sinthia D/S, Voltas board at BBD Bag D/S, Southern D/S, Amherst Street D/S
etc. 33 kV DBB: Reyrolle board at TRS, PRS, Siemens board (horizontal isolation) at SRS etc.
Double Breaker Double Bus Bar (DBDBB) :
76
7. Circuit Chamber :
In this chamber power cables are terminated. Different types of termination arrangements are used
in our system - Single Cable per phase
- Two Cables per phase
- Three Cables per phase
- Doubling Arrangement
Types of Switchgear:
1. Basis : Location of installation
a. Outdoor
b. Indoor
2. Basis: Isolation capability:
a. Fixed Execution type (Non-withdrawable, cannot be isolated)
b. Withdrawable type (can be isolated)
Withdrawable CBs can again be of two types a) Horizontal Isolation & draw out type
b) Vertical Isolation & Horizontal draw out type
3. Basis: No. of Busbars
a. Single Busbar
b. Double Busbar
4. Basis: Interrupter type
a. ACB (Air Circuit Breakers)
b. BOCB (Bulk Oil Circuit Breakers)
c. MOCB (Minimum Oil Circuit Breakers)
d. VCB (Vacuum Circuit Breakers)
e. SF6 Circuit Breakers
Circuit Breaker Theory & Practice
Function of a Circuit Breaker :1. Carry the load current (Normal rating) upto maximum rating continuously without overheating.
2. Make and break the circuit under normal load conditions.
3. Must interrupt the fault current rapidly during short circuit to isolate the faulty part from the
system (kA rating).
4. Close onto a circuit in which a fault exists and immediately reopen.
5. In the off state the gap must withstand any abnormal voltage rise between the circuit and
busbar.
6. Should be able to carry short circuit currents till the fault is cleared by another breaker in the
downstream.
7. Ensure safety to the operating personnel.
The process of fault clearing has the following sequence:
1 - As the fault occurs, the fault impedance being low, the currents increase and the relay gets
actuated. The moving parts of the relay move because of the increase in the operating torque.
The relay takes some time to close its contacts.
Distribution Training Institute, CESC Limited
77
2 - Relay contacts close the trip circuit of the Circuit Breaker closes and trip coil is energized.
3 - The operating mechanism starts operating for the opening operation. The Circuit Breaker
contacts separate.
4 - Arc is drawn between the breaker contacts. The arc is extinguished in the Circuit Breaker by
suitable techniques. The current reaches final zero as the arc is extinguished and does not
restrict again.
Function of an Interrupter:
In a Circuit breaker, on receipt of a trip command, the main contacts start separating and as a result
an arc is drawn across them. This arc is controlled and ultimately extinguished in the interrupter.
The interrupter therefore,
Elongates Arc length
Cools down Arc temperature
Safely & quickly interrupts Arc
Arc Quenching Process in Different CBs 1) BOCB In Bulk Oil Circuit Breaker oil serves a two-fold purpose, i.e., as means of extinguishing the arc
and also for providing insulation between the live parts and the metallic tank.
In its simplest form the process of separating the current carrying contacts was carried out under
oil with no special control over the resulting arc other than the increase in length caused by the
movement of contacts. As the power systems began to develop, resulting in higher voltages and
higher fault levels, plain break type breaker could no longer keep pace with the requirements.
Various methods of controlling the breaking process were investigated and developed.
This led to the development of controlled break oil Circuit Breaker. This employed pressure
chamber and is still widely used because it is relatively cheap to make and gives greatly
improved performance in terms of final extinction, gap length and arcing time, as against the
plain break oil Circuit Breaker. Various designs exist according to the preferences and
requirements of individual manufacturers and designations such as Cross Jet Type, Explosion
Pot and Baffle pot, etc.
Many oil Circuit Breakers feature special arc control devices most of which are based on the
simple pressure chamber principle but incorporate certain modifications aimed at improving the
breaking capacity.
Key Points
Interrupters of all 3 phases are enclosed in an oil filled tank (Dead tank)
Oil has two functions (1) to provide insulation, (2) to assist arc interruption.
Disadvantage - Fire Hazard & need for frequent maintenance.
2) MOCB As the system voltages and fault levels increased the Bulk Oil Breakers required huge quantities
of insulating oil and became unwieldy in size and weight. This added enormously to the cost of
a power system. Simultaneously improvements were made in the technique of ceramics. The
function of oil as insulating medium in the Bulk Oil Breakers was transferred to the porcelain
containers. Only a small quantity of oil was used to perform its functions as arc quenching
medium. This led to the development of minimum oil volume or low oil content breakers in the
continent of Europe.
78
Like the Bulk Oil Breakers these have also since then passed through many stages of
development with varying designs of the arcing chambers. Contrary to the operation of the
impulse type Circuit Breaker, such as air blast Circuit Breaker, in which arc extinction and
dielectric recovery are affected by means of an external quenching medium, the process of arc
extinction in the minimum oil volume Circuit Breaker is of internal thermodynamic origin.
During the tripping operation an arc strikes in oil between the moving contact and the fixed
contacts This arc is elongated vertically in the explosion pot until the distance travelled is
sufficient to withstand the voltage between contacts.
The increase in internal pressure due to splitting up and vaporization of oil by the arc creates a
rapid movement of the extinguishing medium round the arc. This self-quenching effect causes a
rapid cooling of the ionized column along its whole length due to partition of the explosion pot
and the dielectric recovery is sufficiently rapid to prevent the arc restricting after a natural
passage through zero. The electric arc itself has, therefore, supplied the necessary energy for its
own extinction.
One of the limitations put forward against this class of breakers is frequent maintenance, owing
to reduced quantity of oil and consequent liability to quick carbonization, on circuits susceptible
to frequent tripping because of too many faults.
Key Points
Each phase has separate Insulated tank (Live tank)
Oil has one function namely to assist arc interruption.
Disadvantage - Fire hazard exits but less than BOCB & frequent maintenance is required
3) VCB In case of a Vacuum Interrupter, when the contacts separate, the current to be interrupted
initiates a metal vapour arc discharge and flows through this plasma until the next current zero.
The arc is then extinguished and the conductive metal vapour condenses on the metal surfaces
within a matter of microseconds. As a result, the dielectric strength in the break builds up very
rapidly.
The self generated field causes the arc root to travel, thereby preventing local overheating when
large currents are being interrupted. Certain minimum current is necessary to maintain the metal
vapour arc discharge. Current of a lesser value is chopped prior to current zero, causing unduly
high voltages, as may happen during interruption of no load magnetizing currents of unloaded
transformers. The rapid build up of the dielectric strength in the break enables the arc to be
safely extinguished even if contact separation occurs immediately prior to current zero.
Further the arc voltage developed in vacuum interrupter is low (say between 20 to 200 V) due to
high conductivity of metal vapour plasma. For these reasons the arc energy developed in the
break is very small. High Switching life is claimed on this account.
Performance is claimed to be immune to pollution because of interrupters being hermetically
sealed.
Key Points
Each phase has separate vacuum interrupter (vacuum level 10-8 Torr, 1 Torr= 1 mm of Hg)
(Live tank)
No fire Hazard
Light mechanism & less wear & tear
However vacuum cannot be monitored on line.
Interrupters cannot be repaired
79
4) SF6 CB The first high-voltage SF6 circuit-breaker built in 1956 by Westinghouse, could interrupt 5 kA
under 115 kV, but it had 6 interrupting chambers in series per pole. In 1957, the puffer-type
technique was introduced for SF6 circuit breakers where the relative movement of a piston and a
cylinder linked to the moving part is used to generate the pressure rise necessary to blast the arc via
a nozzle made of insulating material. In this technique, the pressure rise is obtained mainly by gas
compression.
Several characteristics of SF6 circuit breakers can explain their success:
Simplicity of the interrupting chamber which does not need an auxiliary breaking chamber;
Autonomy provided by the puffer technique;
The possibility to obtain the highest performance, up to 63 kA, with a reduced number of
interrupting chambers;
Short break time of 2 to 2.5 cycles;
High electrical endurance, allowing at least 25 years of operation without reconditioning;
Possible compact solutions when used for GIS or hybrid switchgear;
Integrated closing resistors or synchronized operations to reduce switching over-voltages;
Reliability and availability;
Low noise levels.
The reduction in the number of interrupting chambers per pole has led to a considerable
simplification of circuit breakers as well as the number of parts and seals required.
Distribution Training Institute, CESC Limited
80
New types of SF6 breaking chambers, which implement innovative interrupting principles, have
been developed over the past 15 years, with the objective of reducing the operating energy of the
circuit-breaker. One aim of this evolution was to further increase the reliability by reducing the
dynamic forces in the pole.
Puffer Technique In this technique, the reduction of operating energy was mainly achieved by the lowering energy
used for gas compression and by making increased use of arc energy to produce the pressure
necessary to quench the arc and obtain current interruption. Low current interruption, up to about
30% of rated short-circuit current, is obtained by a puffer blast.
AutoPuffer Technique Further development in the Puffer technique was made by the introduction of a valve between the
expansion and compression volumes. When interrupting low currents the valve opens under the
effect of the overpressure generated in the compression volume. The blow-out of the arc is made as
in a puffer circuit breaker thanks to the compression of the gas obtained by the piston action. In the
case of high currents interruption, the arc energy produces a high overpressure in the expansion
volume, which leads to the closure of the valve and thus isolating the expansion volume from the
compression volume. The overpressure necessary for breaking is obtained by the optimal use of the
thermal effect and of the nozzle clogging effect produced whenever the cross-section of the arc
significantly reduces the exhaust of gas in the nozzle. In order to avoid excessive energy
consumption by gas compression, a valve is fitted on the piston in order to limit the overpressure in
the compression to a value necessary for the interruption of low short circuit currents. This Auto
Puffer technique has now been used extensively for the development of many types of interrupting
chambers.
Key Points
Each phase has separate SF6 gas filled interrupter (Live tank)
No fire Hazard
Mechanism heavier & higher wear & tear than vacuum
SF6 gas pressure/ density can be monitored on line.
Interrupters can be repaired.
Possibility of gas leakage.
Standard Ratings of Circuit Breakers 1) Rated Voltage It is the highest System Voltage for which the CB is designed.
In our network the highest system voltage is taken as 10% above the nominal
voltage. This voltage also depends upon the altitude of the installation site.
Nominal
Voltage
Highest
System Volt
Altitude in
Feet
Voltage Correction
Factor
6.6 kV
7.2 kV
11 kV
12 kV
3300
1.00
33 kV
36 kV
4000
0.98
132 kV
145 kV
5000
0.95
220 kV
245 kV
10000
0.80
2) Rated Insulation Level It is the basic dielectric withstand capacity of the CB, which it must
withstand under specified test conditions. For impulse tested apparatus it is expressed by a peak
81
impulse voltage value and for nonimpulse tested apparatus it is expressed by a power frequency
r.m.s. voltage value.
Rated
Voltage
7.2 kV
20 kV
60 kVp
12 kV
28 kV
75 kVp
36 kV
70 kV
170 kVp
145 kV
275 kV
650 kVp
245 kV
395 kV
950 kVp
82
Terms Associated with Circuit Breakers In a reactive circuit when current is interrupted at zero point, a transient voltage appears across the
opened contacts, which after successful interruption, dies down to system voltage. When a pure
resistive circuit is interrupted, the supply voltage is zero at the time of interruption; therefore the
recovery voltage has no transient component.
1) Restriking Voltage It is the transient peak value of voltage that appears across the circuit
breaker terminals at or near current zero after extinction of arc.
2) Rate of Rise of Restriking Voltage (R.R.R.V.) It is the rate of voltage rise across the CB
terminals after current interruption. For a restriking voltage having a single frequency transient
component, the RRRV is obtained by dividing the maximum amplitude of the voltage by
duration of the first half cycle.
83
3) Transient Recovery Voltage - It is the voltage that appears across the terminals after current
interruption. It is a critical parameter for fault interruption by a high-voltage circuit breaker, its
characteristics (amplitude, rate of rise) can lead either to a successful current interruption or to a
failure (called reignition or restrike).
The TRV is dependent on the characteristics of the system connected on both terminals of the
circuit-breaker, and on the type of fault that this circuit breaker has to interrupt (single, double
or three-phase faults, grounded or ungrounded fault ..).
Characteristics of the system include:
Type of neutral (effectively grounded, ungrounded, solidly grounded)
Type of load (capacitive, inductive, resistive)
Type of connection: cable connected, line connected..
According to IEEE standard, the most severe oscillatory or exponential recovery voltages tend
to occur across the first pole to open of a circuit breaker interrupting a three-phase ungrounded
symmetrical fault at its terminal when the system voltage is at a maximum.
4) Recovery Voltage - The Power Frequency rms voltage, which appears across the breaker
contacts after the arc is finally extinguished and transient oscillations die out, is called Recovery
Voltage.
5) First Pole to Clear Factor A three pole CB will not trip all three phases simultaneously. The
first pole to clear the fault will experience the highest Transient Recovery Voltage and the
associated Power Frequency Recovery Voltage for this first phase will begin to appear after the
second pole has interrupted the current flow. The Pole Factor is the ratio between the Power
Frequency Recovery Voltage and the corresponding phase voltage after the current interruption.
In solidly earthed system the highest First Pole to Clear Factor occurs with three phase fault.
For rating purposes, two values of the First-Pole to Clear Factor (kpp) are defined for the threephase short-circuit condition. The choice between these two values is dependent on the system
grounding arrangement:
a) Systems with ungrounded neutral: Value for kpp of 1.5 is used;
b) For effectively grounded systems: Value for kpp used is 1.3.
A third condition does exist, this is where the fault is single-phase in an effectively grounded
system and the last-pole-to-clear is considered. For this kpp is taken as1.0.
Formula for the first-pole-to-clear factor
where X0 is the zero sequence & X1 the positive sequence reactance of the system.
If X0 >> X1, as in ungrounded systems then: kpp = 1.5
If X0 = 3.0 X1, as in effectively grounded neutral systems then: kpp = 1.3
Pole-to-clear factors (kpp) for each pole when clearing three-phase to ground faults
84
85
86
Outdoor Switchyards
Components:
1. Outdoor Circuit Breakers
2. ACSR / Pipe Busbars
3. Outdoor Isolators
4. Outdoor CTs & PTs
5. Lightning Arrestors
6. Cable Termination / Overhead Jumpers
7. Transformers & Earthing Transformers
8. Yard Earthing
Secondary Components of Switchgear
The components are auxiliary switch, auxiliary plugging contacts, spring charge motor circuit,
closing, tripping, alarm, indication, metering, protection circuit, secondary wiring and accessories.
Isolators
Isolating Device to isolate
CBs from Busbars & Circuits
VTs from Circuits
Circuits / Cables from Busbars / CBs
Can interrupt negligible current & hence generally to be operated in off-load condition.
Interlocks are provided to ensure such operation.
Types:
On the basis of mounting
Horizontal (Upright)
Vertical
Underhung (Drop down)
On the basis of construction
Center Post Rotating (conventional and Turn Twist)
Center break
Pantograph
Vertical
On the basis of operation
Manual (hand operated)
Power operated (electrical usually, also pneumatic & stored spring operated)
Interlocks
Mainly two types ie. mechanical & electrical.
Isolators on both sides of a CB cannot he operated unless the CB is off (usually
mechanical with Castle Key).
Earthing Isolator cannot be closed unless the Main Isolator is open (usually mechanical &
built in with the mechanism, at times Castle Key)
Line Isolator can be closed when corresponding CB & Earth switches are open.
CB can be closed if Isolators on both sides are fully open or close.
In case of Line Isolators Incoming Circuits having CB at a remote station, the Isolator can
be opened when remote CB is OFF (usually Electrical Bolt Interlock).
Distribution Training Institute, CESC Limited
87
88
TESTING OF SWITCHGEAR
Broadly a Switchgear comprises of the following electrical parts which undergo various rigorous
tests before it is actually commissioned in an utilitys Network:
Circuit Breaker
Busbars and associated Insulators.
Isolators/ Disconnectors
Instrument Transformers
Protective Relays and auxiliary circuits
Switchgear Testing
Switchgear testing can be broadly classified as :
A. Developmental Test
B. Type Test
C. Routine Test
D. Factory Inspection Test
E. Pre-Commissioning Test
A. Developmental Test
These tests are carried out on components, sub-assemblies and complete switchgear during and
after the development of switchgear. The R&D sections verify the effect of various parameters on
the behaviour of Circuit Breaker by conducting Developmental Tests.
After several R&D tests a proto-type switchgear is manufactured. These types of tests are not
covered in the standards.
B. Type Test
These tests are carried out for the purpose of proving characteristics of switchgear and control gear,
their operating devices and auxiliary equipment. The type tests are carried our on a maximum of
four test specimen unless otherwise specified in the relevant IEC standards. The details of type tests
are as follows:
Lightning Impulse Test
Switching Impulse Test
A1 Power Frequency Over Voltage Withstand Test
A2 Partial Discharge Test
A3 Artificial Pollution Test
Temperature Rise Test
A4 Resistance Measurement of the Main Circuit.
A5 Short Time Withstand Current Test, Peak Withstand Current Test
A6 Making Current and Breaking Current Test
A7 Mechanical Endurance Test
A1. Lightning Impulse Test
Purpose: The insulation of switchgear should be so designed that it can withstand the
occasional Lightning surges of high peak value, sharp rate of rise and short duration. The
lightning impulse voltage withstand level of the switchgear is proved by conducting this test.
The test is performed with voltages of both positive and negative polarity with respect to earth
using the standard Lightning Impulse 1.2/50s waveform (Fig 1).
The withstand voltage levels for different ratings of breakers are as under:
Distribution Training Institute, CESC Limited
89
Rated Voltage
(KVrms)
3.6
40
7.2
60
12.0
75
36.0
170
145.0
650
245.0
1050
90
91
3.6
10
7.2
20
12.0
28
36.0
70
145.0
275
245.0
530
The test voltage is obtained from a single ph ac generator driven by an induction motor. The
terminal voltage can be varied by changing the field current. The generator voltage is stepped up by
high voltage transformers to the required value and fed to the switchgear under test.
On Auxiliary & Control Circuits
Auxiliary and control circuits of switchgear shall be subjected to power frequency voltage
withstand test in accordance with IEC 61180-1. The test shall be performed between the auxiliary
and control circuits connected together as a whole and the frame of the switching device.
The test voltage is 2 KV with duration of 1 min. The auxiliary and control circuits of switchgear
shall be considered to have passed the tests if no disruptive discharge occurs during test.
A4. Partial Discharge Test
Purpose: The primary reason of this test is to check the healthiness of insulation of switchgear.
The applied power frequency voltage is raised to a pre-stress value which is identical to the power
frequency withstand voltage test and maintained at that value for 1 min. Partial discharge occurring
during this period shall be disregarded. Then the voltage is decreased to a specific value defined in
the table below depending upon the configuration of equipment and system neutral for partial
discharge measurement.
System Earthing Condition
Solidly earthed
1.2 Ur
92
a = application factor
If = minimum nominal specific creepage distance (mm/kV)
Ur = Rated voltage of switchgear in KV
KD= Correction factor due to diameter
Application to Insulation
Application factor
1.0
Between phases
1.0
If the creepage distances do not comply with the above relationship, artificial pollution tests should
be performed, using the rated voltage and the application factor as given in the above table.
A6. Temperature Rise Test
This test is to be made indoors in an environment substantially free from air currents. The
switchgear should obviously be in closed position with clean contacts. The test is done with the
normal rated sinusoidal current with the three poles connected in series. Temperature rise test is
carried out over a period of time sufficient for the temperature rise to reach a constant value. When
the steady temperature is reached the maximum temperature rise of each part should be less than
the permissible limits as per IS.
When a circuit breaker in closed condition carries normal current the heat is generated in current
carrying parts due to I2R loss. This heat is dissipated by conduction, convection and radiation. To
maintain the temperature rise within specified limits, the I2R losses should be reduced by increasing
conductor cross-section using suitable low resistivity material, improving convection, conduction
and radiation of heat.
93
A8. Short Time Withstand Current Test, Peak Withstand Current Test
Purpose : Main circuits and where applicable, the earthing circuits of the switch gear are subjected
to a test to prove their ability to carry the rated short time withstand current and rated peak
withstand current due to short circuits in power system.
The ac component of test current is, in principle, equal to the ac component of the rated short-time
withstand current (Ik) of the switchgear. The peak current under test is not less than the rated peak
withstand current (Ip) and shall not exceed it by more than 5%. The test current It is in principle be
applied for a time tt equal to the rated duration tk of short circuit. The value of It2tt on test should not
be less than the value of Ik2tk calculated and should not be greater than 10% of this value.
The short circuits produce a severe stress on switch gear and it should be capable of withstanding
the stresses. When short circuit current is passed through current carrying parts of the switch gear,
the contacts and current carrying parts are subjected to thermal stresses. The insulation in the
vicinity of conductors is severely stressed. The poles and terminals experience electro-dynamic
forces.
A9. Rated Short Circuit Making Current and Breaking Current Test
The Making Current tests
Purpose: These tests verify the ability of the current carrying parts of switchgear to close on short
circuit.
As the CB closes on existing short circuit, the current reaches a high value during the peak of the
first current loop. The electro-dynamic forces between contacts and between poles reach a high
value. The circuit breaker should be capable to withstand the high mechanical forces during such
closures. This capability is proved by carrying out the making current test. The rated short circuit
making current of a CB is the peak value of first current loop of short circuit current which the
breaker is capable of making at its rated voltage.
The rated short circuit making current should be at least 2.5 times the r.m.s value of AC component
of rated breaking current.
The breaking Current tests
Purpose: These tests verify the ability of the circuit breaker to clear short circuits under specified
conditions of Transient Recovery Voltage and power frequency voltage.
The transient recovery voltage is that transient voltage which appears across the CB pole at the
instant of contact separation immediately after the arc interruption. The rated values of TRV are
specified for various rated voltages of CBs. For specified conditions of rated TRV and rated power
frequency recovery voltage, a circuit breaker has a certain limit of breaking current. This limit is
determined by conducting short circuit type tests on switch gear. During the breaking operation, the
operating mechanism is subjected to mechanical stresses. The contacts and the current carrying
parts are subjected to thermal stresses. These stresses depend on the magnitude of the fault current
and the design of the circuit breaker.
A10. Mechanical Endurance test
The mechanical operational test shall be made at ambient temperature. The mechanical operational
tests consist of 2000 operating cycles. No adjustments or replacement of parts is permitted during
the test. After the test, the contacts, linkages and all other parts should be in good condition and
should not show any permanent deformation or distortion. Successful performances in mechanical
operational tests prove the adequacy of design and also good quality of materials.
94
C. Routine Test
These tests confirm the proper functioning of the switchgear. These tests are for the purpose of
revealing faults in material or construction. These tests are carried out on each apparatus
manufactured.
Routine tests are conducted on each circuit breaker before dispatch.
Routine tests reveal the defects in the materials and construction of the circuit breakers. The results
of the tests confirm the quality of the circuit breaker:
Routine tests include the following:
Tightness test
The purpose of tightness tests is to demonstrate that the absolute leakage rate does not
exceed the specified value of the permissible leakage rate. The test shall be performed at
normal ambient air temperature with the assembly filled at the the pressure ( or density)
corresponding to manufacturers test practice.
Power frequency voltage withstand test on main circuit and auxiliary circuits
This test is already discussed in type test no. A3
95
IR measurement
Insulation resistance of the CT secondary is measured with the help of 1000V
Megger (Insulation Tester) with respect to Earth & in between different cores.
Ratio Checking
The usual method is to apply test current to the primary winding of CT close to rated
primary current and measure the magnitudes of primary and secondary currents with a low
value of secondary burden.
96
Polarity Test
If at any instant, current is entering the primary from P1 the current should leave secondary
from terminal marked S1. A set up shown in the figure, tests whether the polarity markings
with respect to the secondary are correct or not. (S1 should correspond to P1)
97
98
Polarity Test
The test details are identical to that carried out for Current Transformers.
Measurement of IR of VT
Measurement is done with a 1000V Megger to ascertain the insulation resistance of primary
winding w.r.t earth isolating the intentional earthing, insulation resistance of secondary
windings w.r.t earth and insulation resistance in between primary and secondary winding.
Ratio Test
The ratio of VT is checked by applying variable AC voltage to the secondary winding and
measuring its voltage reflection in the primary.
99
100
CABLES
Introduction
Cables form the artery system for the transmission and distribution of Electrical energy. The
residential and industrial loads today have a trend towards their growing density. This requires
rugged construction, greater service reliability, increased safety and better appearance. The
interferences from external disturbances like storms, lighting, ice, trees etc. should be reduced to
minimum. These difficulties are easily overcome by the use of underground cables and a troublefree service is achieved under a variety of environmental condition.
Earlier underground cables were mainly used in or near densely populated areas and were operated
at low or medium voltages only, but the present day requirements seek to use them even at extra
high voltages for longer distances. The underground system although more costly as compared with
the overhead system for the same voltage, is more acceptable to public from the point of view of its
merits mentioned above.
Comparison in costs of Underground cable and Overhead line
Voltage in KV
Ratio =
400
18
275
13
132
66
33
11
0.42
2 or less
Underground cables are to be laid in areas where it is almost impracticable to use overhead lines,
for example in case of transmission lines through sea, cross-over or terminal connections in
substation or air field crossings. The cross-channel link between France and England and the
submarine link from Swedish mainland to the island of Got land are the examples of High voltage
Power cables.
Increased working voltages of the overhead lines require the cables to be insulated for such voltages
in order to meet the requirements of the overhead lines. The design of Power cables is, therefore,
governed by the requirements of the overhead line.
The possibility of supply interruption due to lightning or other external influences is lesser with
underground cables, but if a fault occurs due to any reason it is not easily located. For long distance
transmission, cables cannot be used due to their large charging currents.
Components and Construction of Power Cables
Many types of modern electrical cables have been in use for underground distribution and
transmission of power. They vary greatly in their design and constructional techniques. However,
all power cables consist of three essential components.
1.
The metallic conductor which provides an electrical conducting path.
2.
The insulation of a cable, often called dielectric or insulant , which prevents direct
contact and dangerous proximity between energized conductor and other objects.
A conductor with its insulation but without mechanical protection is known as the core of the
cable.
101
3.
The external protection preventing the ingress of moisture, mechanical damage, chemical or
electrochemical attack, fire or any other harmful influences which are detrimental to the
cable itself.
All power cables can be divided into two distinct groups, namely:
a) Solid-type cables in which the pressure within their insulation is not boosted above
atmospheric, and may even fall below it locally, e.g. in voids of the insulation.
Solid-type cables, in turn, can be sub divided into two categories. One is Taped insulated
cable, sometimes known as lapped insulated cables. Other one is cables with extruded
synthetic dielectric which for simplicity are often just called extruded cables.
b) Pressurized cables in which pressure is always maintained above atmospheric, either by oil
in oil-filled cables or by gas in gas-pressurized cables, during all conditions of their
operation, thus inhibiting the formation of voids in the insulation.
Conductor
Copper was the traditional metal for cable conductors. But the escalated price of copper had
resulted in forcing a change in practice based on introduction of Aluminium.
Aluminium is the fourth metal in the scale of electrical conductivity, just behind silver, copper and
gold with two-third the conductivity of copper but density of only 30.4 % of that of copper. An
aluminium conductor made of metal with a high degree of purity will carry twice the power carried
by copper conductor of equal weight.
Stranded conductors of copper and aluminium are normally employed in order to increase the
flexibility of cables. Stranded conductors having more than one layer of wires are made such that
the directions of lay of wires in adjacent layers are opposite to each other. The strands follow a
helical path and, therefore, the individual strands are greater in length as compared to the length of
the cable. Stranding thus increases the resistance of the cable.
M = 1 + 3n (n+1)
M is the number of wires (strands) forming a Stranded conductor
n is the number of layers of wires (strands )
Insulation
All the materials for the insulation of modern power cables can be broadly divided as follows.
a) Impregnated paper
b) Synthetic dielectrics
c) Compressed gases
In general, the main characteristics which the cable insulating material should have are
1. High Dielectric strength
2. High Insulation resistance
3. Great durability and long life
4. Sufficiently low Thermal resistivity
5. Reasonably low Relative permittivity and Dielectric loss angle when used for a.c. cables.
6. Good mechanical properties.
7. Low power factor
8. Preferably non-hygroscopic, but if hygroscopic it is essential that they should be in a watertight sheathing or covering.
9. Immunity to chemical attacks over a fairly wide range of temperature.
10. Easy handling from the point of view of manufacture and installation.
11. Lowest possible cost consistent with the above requirements.
102
Impregnated Paper
Paper has been the most commonly used insulating material for cables since the early days of
power distribution and transmission.
Paper is essentially composed of cellulose fibres felted to form a strong sheet. Most insulating
paper is made from wood-pulp (pine or spruce) but originally was produced from manila fibres. A
special water-washing process helps to eliminate water-soluble salts in the paper, resulting in
significant improvements in the power factor at high temperature.
There are four most important physical characteristics of cable paper.
a) The thickness, which usually varies from 0.075 to 0.200 mm
b) The density, which varies from 1250 to 950 kg per meter cube
c) The air impermeability, which is reciprocal of its porosity. The higher the impermeability of
the paper the more difficult it will be to dry and subsequently impregnate it with insulating
oils and compounds.
d) The mechanical strength of the paper tapes to avoid breakage or tearing during lapping or
bending of cable. The tensile strength of the paper in the longitudinal direction with respect
to its fibres is 77 MN per sqmt and crosswise is 35 MN per sqmt.
Paper is a hygroscopic fibrous material and, as such, must be thoroughly dried under vacuum and
there upon impregnated with a suitable oil or compound. The power frequency breakdown stress of
dry paper is about 6-8 MV per mt but that of impregnated paper is approximately 50 MV per mt.
Common types of insulating oils are
1. Viscous mineral oils, which contain refined resin , the refined gum of pine trees
2. Microcrystalline petroleum waxes
3. Low-viscosity oil with some additives.
4. Refined Synthetic oils
The drainage of oil from the mass impregnated cables has been overcome by the introduction of
special microcrystalline wax impregnant which is nearly solid at the usual operating temperature
but is sufficiently fluid at impregnating temperatures. Cables of this type, which are manufactured
for all voltages up to and including 33 KV are known as mass-impregnated non-draining (MIND)
cables.
Synthetic Dielectrics
The introduction of synthetic dielectrics instead of impregnated paper gained popularity mainly due
to the following reasons.
1. The elimination of expensive and rather heavy metallic sheaths due to the non-hygroscopic
nature of the synthetic insulants.
2. The simplification of Cable jointing and termination as well as repair work coupled with a
saving in the cost of labour.
3. Complete freedom from compound drainage troubles, especially in cable terminations.
In the recent years, many synthetic or plastic insulants were employed in power cable manufacture,
of which the following four dielectrics are most common.
1. Polyvinyl Chloride ( PVC )
2. Polyethylene ( PE ) or Polythene
3. Cross linked Polyethylene ( XLPE )
4. Ethylene Propylene Rubber ( EPR )
103
(Max) ( 0 C )
Continuous Operation
(Max) ( 0 C )
Short circuit Operation
Impregnated paper
65-80
160-250
PVC
70
150-160
Low Density PE
70
120
High Density PE
80
160
XLPE
90
250
EPR
90
250
PVC
PE
XLPE
EPR
Impregnated
Paper
Density ( Kg / m 3 )
1400
900
900
1200
1250
Thermal resistivity
( 0Cm/W)
3.5
5.5
Relative permittivity
2.3
2.5
3.3
3.5
0.01
0.0004
0.0004
0.004
0.002
104
Polyethylene (PE)
Polyethylene or polythene was discovered in early 1930s in Britain by Imperial Chemical Industries
using ethylene gas obtained from coal.
H H H H H
I I
I
I
I
The chemical structure of PE is H C C C -- C C -- ..
I
I I
I I
H H H
H H
LDPE : Low density PE is manufactured by a high-pressure polymerization process has density of
916-930 kg / m3
HDPE : High density PE is manufactured by a high-pressure polymerization process has density of
945-960 kg / m3 . Because of the less branched molecular structure compared to LDPE, they are
stiffer, harder and more brittle than LDPE.
Advantages:
1. Readily available in sufficiently pure and uniform state
2. Its dielectric strength is in excess of 800 MV per mt at room temperature
3. Its dielectric loss factor is about 20 % of that of oil impregnated paper insulation
4. Its relative permittivity is low, being about two-thirds of that for impregnated paper
5. Its thermal resistivity is much lower than that of the impregnated paper insulation
6. Good resistance to wide variety of chemicals
Disadvantages:
1. PE is not fully impervious to moisture
2. Poor flame retarding property
3. Moderately resistant to oils
4. Operating temperature is limited to 70 0 C as it melts at 110 0 C
Cross-linked Polyethylene ( XLPE )
The main advantage of XLPE dielectric is that it has a thermal performance at least equivalent and
possibly superior to impregnated paper insulation, and also retains good electrical and some of the
thermal properties of the extruded PE.
This dielectric is manufactured by cross-linking the polymer. The most common method of crosslinking is by the incorporation of peroxides into the polymer followed, after extrusion, by heating
under pressure to activate the peroxides. The most popular peroxide used in this process is Dicumyl
peroxide.
If steam is used for heating, the pressure is correspondingly high (18-20 bar) so as to achieve a
temperature of the order of 210 0 C.
If an electrically heated tube with Nitrogen gas is used, the gas pressure needs to be around 5-10 bar
to prevent formation of voids due to peroxide decomposition products.
The entire cross-linking and extrusion process is usually carried out by two methods. They are CCV
(Continuous catenary vulcanization) and VCV (Vertical catenary vulcanization) process.
XLPE dielectric, being a thermosetting material (molecules held together by chemical bonds) does
not suffer from deformation at elevated temperature and therefore may be operated continuously at
temperatures up to 90 0 C. It will sustain much higher temperatures (250 0 C) for emergency period
or under short-circuit conditions.
105
106
107
108
Electric Stress
Metallised Paper
or Tape
Screened cables have greater breakdown strength; better heat dissipating properties and reduced
risk of core-to-core faults. The current rating of screened cable is more than that of belted cable.
Screening of High voltage insulated cables consists of conductor Screening and insulation
screening.
Conductor Screening
The stranding of conductor can increase the maximum electrical stress by about 20 %. To alleviate
this effect all paper insulated cables at higher voltages are manufactured with conductor screens in
the form of semi conducting carbon paper tape lapped over the stranding conductor.
For power cables with synthetic or polymeric insulation of same rating, conductor screens are
employed to preclude excessive electrical stress in voids between the conductor and the insulation.
This conductor screen is in the form of extruded semi-conducting compound. To be effective they
must adhere to and remain in intimate contact with the conductor and the insulation under all
conditions.
Insulation Screening
An insulation screen has a number of functions to perform, each of which is of equal importance for
either paper or synthetic-insulated cables of multi-core or single-core construction. These are
1. To confine the electric field within the cable.
2. To obtain strictly symmetrical radial distribution of electrical stress with the dielectric,
thereby minimizing the possibility of surface discharges by precluding tangential and
longitudinal stresses.
3. To reduce the hazard of shock, achieved by the screen being well earthed.
4. To protect the cable connected to overhead lines from being subjected to induced potential.
5. To limit Radio interference.
The insulation screen for paper-insulated cables consists of metallised paper.
The insulation screen for synthetic or polymeric insulated cables consists of extruded layer of semi
conducting material, which must be applied and vulcanized in a triple extrusion process including
the conductor screen and the insulation. To avoid discharge the screen should adhere well to the
insulation and move with it during expansion and contraction due to load cycles or bending.
However, at the same time it must be easily removable during Jointing.
109
110
Insulation
Screen / Sheath
Conductor
Single Core Cable
Let r = radius of conductor or inner radius of insulation
R = internal radius of sheath or outer radius of insulation
0 = the permittivity of free space
r = the relative permittivity of the dielectric
q = charge on the conductor per unit length in coulombs
V = operating phase to neutral voltage in volts
Flux passing through a cylinder of radius x and length one metre surrounding the core is q.
The electric flux density at a distance x from the centre is
Dx = q / (2x. 1) C/m2and the dielectric stress is given by
gx = Dx / ( 0 . r ) = q / (2 0. rx ) V/m ........(1)
The potential difference between the conductor and the sheath is equal to the work done to move a
unit charge from the conductor to the sheath.
Thus, V = rR gx dx
= rR q / (2 0. rx) dx
= {q / (2 0. r )}. ln (R/r) Volts ...............(2)
Combining equations (1) and (2), we get
gx = V/ {x. ln (R/r)}
Volts/metre
Distribution Training Institute, CESC Limited
111
Now, the maximum stress will occur at the smallest radius, i.e., for x = r. The maximum stress is
given by
gmax = V/ {r. ln (R/r)}
Volts/metre
When x = R, the stress will be a minimum which indicates that stress has a maximum value at the
sheath. The minimum value is given by
gmin = V/ {R. ln (R/r)}
Volts/metre
Also, gmax / gmin = R/r .
Current Rating of Cables
The current rating of power cables is very important. It decides the upper limit of the power transfer
by a cable.
The cable rating is classified under three headings.
1. Normal maximum continuous current rating
2. Over-current rating
3. Short circuit current rating
Normal or safe Current carrying capacity
The normal or safe current carrying capacity depends upon a number of factors.
1. Temperature: Primarily it is the temperature rise which is important but this is governed by
the base ambient temperature for the given cable location and the maximum temperature
applicable to the insulation and cable construction.
2. Cable design: Apart from the temperature limit, the other effect of cable design is the ability
to transfer heat from the conductors to the outer surface. This varies with the materials used
and the number of layers in the construction.
3. Condition of Installation: On the whole, a cable in air can dissipate heat better than a cable
in the ground but in this respect the cable diameter, or more particularly the surface area, is
important. Up to a certain size of cables in air have a lower rating than buried cables and
when cables are buried the rating decreases with depth of burial. The rating also depends on
the thermal resistivity of the soil.
4. Effect of neighbuoring cables: Any other heat input from hot pipes or other cables in the
vicinity has to be taken into account.
112
50 sqmm Al
105
100
150 sqmm Al
190
200
225 sqmm Al
240
260
300 sqmm Al
280
310
50 sqmm Al
126
137
150 sqmm Al
233
268
240 sqmm Al
307
364
300 sqmm Al
344
414
113
20
25
30
35
40
45
50
55
Rating factor
1.18
1.14
1.1
1.05
0.95
0.89
0.84
15
20
25
30
35
40
45
50
Rating factor
1.12
1.08
1.04
1.0
0.96
0.91
0.87
0.82
Voltage Grade
100
120
150
200
250
300
1.18
1.08
1.00
0.88
0.81
0.74
6.6, 11, 22 KV
1.16
1.08
1.00
0.90
0.83
0.76
33 KV
1.12
1.07
1.00
0.90
0.83
0.78
1.1 KV Cables
500 750
1.00
750 -- 900
0.98
1.00
900 -- 1050
0.96
0.99
1.00
1050 1200
0.94
0.98
0.99
1200 1500
0.92
0.96
0.98
1500 -- 1800
0.90
0.95
0.96
3.3,6.6,11 KV Cables
22, 33 KV Cables
Group Rating Factors for Multicore Cables or Groups of Single Core Cables in Horizontal
Formation Laid Direct in Ground
Number of Cables or
Groups of single core
cables in same trench
Touching
0.79
0.69
0.63
0.58
0.55
70 mm
0.85
0.75
0.67
0.64
0.6
250 mm
0.87
0.79
0.75
0.72
0.69
114
I2
K2 S2
A1 + B
= ------------ log e ---------------T
A0 + B
where,
I = Short circuit current ( r m s over duration ) in Amp
T = Duration of Short-circuit ( second )
K = Constant for the material of the conductor
S = Area of the conductor ( sq mm )
A1 = Final Temperature ( 0C )
A2 = Initial Temperature ( 0C )
B = Reciprocal of the temperature co-efficient of resistance of the conductor
(per degree Celcius at 0 0C )
Material
Copper
226
234.5
Aluminium
148
228
Lead
42
230
Steel
78
202
115
Alumunium
sqmm
Amp
Amp
16
2280
1510
25
3570
2360
35
5000
3300
50
7150
4720
70
10000
6600
95
13580
8960
120
17160
11320
150
21450
14160
185
26450
17460
240
34320
22650
300
42900
28320
400
57200
37760
500
71500
47200
630
90000
59400
800
75520
1000
94400
116
117
It is important that any rolling of the drum to this position should be in accordance with the arrow
on the drum wing as loose turns will develop, by unwinding, if the opposite direction is used. The
distance of rolling should be kept to a minimum.
Drums are normally mounted so that the cable is pulled from the top of the drum and for very heavy
cables it may be necessary to use a ramp to support the cable during passage into the trench.
Another factor, which may affect the drum position, is the presence of any services or obstructions
at the trench entry, which could cause abrasion damage to the cable entry.
For mounting a drum a pair of screw jacks is adequate for relatively light drums but fabricated Aframes containing hydraulic jacks are necessary for heavier drum.
Excavation
Depth of laying
The desired minimum depth of laying from ground surface to top of the cable as per IS: 1255
1983 are as follows:
LV, MV and Control cable
750 mm
3.3 KV to 11 KV
900 mm
22 KV to 33 KV
1050 mm
Timbering / Shuttering
As the excavation depth for most distribution cables is about 1 mts or less, there is seldom any
requirement of full close boarder timbering. However, skeleton timbering may frequently be
necessary to prevent deterioration of trench sides due to traffic vibration and to protect building
foundations, street lamps etc. At a depth of 1 mts the use of close timbering is dependent on ground
conditions and for safety it is essential at depths below 1.3 mts.
However, the key factor is overall safety for personnel and property. Safeguards may be necessary
for a shallow trench next to an old building to avoid danger from possible collapse of walls etc.
Preparation of the Trench
Preparation comprises the installation, as necessary, of skid plates, rollers etc and paying out the
winch if using power assistance. Cable rollers are necessary to prevent the cable from touching the
ground and should be spaced a maximum of 2 mts apart for normal size cable. With heavy cables
this spacing may need to be reduced to 1.2 mts. Correct positioning is important to keep the friction
load component to a minimum.
Cable Laying
Preparation for the cable
The cable should, wherever, be decoiled from the top of the drum. For this the drum must be
positioned such that the arrow on the drum points opposite to the direction of rotation for decoiling.
The drum is lifted on its axle by the aid of winches such that the plank used for braking cannot
become wedged beneath.
The cable must be inspected for external damage, which e.g. may have been incurred by incorrect
rolling of drum. Since the laying of cable sis often carried out by unskilled labour it is necessary to
emphasize that the cable is a high-value commodity and is very sensitive to damage and must be
handled with the necessary care.
In order to avoid damage to the corrosion protection and the insulation, the cables must not be
dragged over sharp objects and must not be bent too sharply.
The minimum permissible bending radii is 30 x D where D is the outer diameter of the cable.
Distribution Training Institute, CESC Limited
118
It must be possible to brake the drum at any time in order to avoid, in the event of sudden stoppage,
continuation of decoiling which would result in sharp bending of the cable. Avoidance of kinking is
especially critical under all circumstances.
To avoid ingress of moisture it must be observed that the end capping of the cable is not damaged.
Cut points of cables must be immediately capped.
Cable Laying Methods
The following methods may be employed for laying cables
1)
Paying out from a cable trailer
2)
Laying by hand
3)
Laying by motor driven rollers
4)
Pulling off by winches
5)
Ploughing in
Paying out from a Cable trailer
Providing there are no obstructions in the trench or its vicinity, cable may be paid out direct from
the cable trailer. However, it must be ensured that during the paying out the drum is manually
rotated and braked in accordance with the laying speed to avoid high-tensile force or sharp bending
of the cable.
Laying by Hand
Cable rollers placed at distances between 2-3 mts will make laying easier. Corner rollers or similar
devices should be provided at any bend in the route, always maintaining minimum bending radii of
the cable.
If the cable is not guided by the rollers it must be guided by hand. The men supporting the cable
should be spaced at between 4-6 mts along the cable.
Laying by Motor Driven rollers
Motorized rollers are used to pull the cable off the jacked up drum. It is advantageous to use rollers
driven by electric motors installed in the cable trench at distances of 20-30 mts. When sharp bends
occur it may be necessary to place such a roller at both the commencement and at the end of the
bend.
Pulling off by winches
Pulling off by winch is possible only if there are few bends or other obstructions in the route.
After releasing the cable end from the drum a pilling stocking is placed over the end and tied in
position. A rope is secured to the eye of the pulling stocking.
When laying unarmoured cables or steel-tape armoured cables with the aid of the winch, the rope
can be secured to the cable via a pulling head, which grips directly on to the conductors.
All cables, in particular single-core cables should not be straightened after laying, but left slightly
meandering, to allow for longitudinal expansion and contraction during thermal cycling (change in
current loading).
Plough laying of Cables
In open terrain the cables may be plough-laid directly into the ground where circumstances permit,
no obstructions e.g. pipe runs which cross the route and where protection of the cable with plastic
119
plates or similar is not acceptable. This type of cable laying is particularly cost effective. Cables
with PE sheath are particularly suitable for this form of laying.
Final Spacing
Prior to disconnecting the pulling rope, the cable is laid-off i.e. staring at one end it is carefully
lifted from the rollers and deposited on the bottom of the trench. About 10 mts of cable should be
lifted at one time, any slack being carried forward. This exercise is simple if only one cable is being
installed but needs careful control if the rollers are to be reused for further cables in the trench. The
cables cannot be positioned until the last one has been pulled.
The end position of the cable may require double handling because it is not possible to draw cable
straight into a sub-station or any building. In this case the cable is over pulled and then manhandled
around the duct entry and fed into the required position. At all times the loops should be kept as
large as possible so that the bending radius is always above the minimum permitted. Similarly, at
the drum position, the necessary length of cable may be unwound from the drum and laid out, if
necessary, in a figure eight if space is limited, prior to cutting to length and placing in position.
Immediately after cutting the cable must be suitably sealed to prevent ingress of moisture. In this
respect it is important to examine the pulling end seal to ensure that it has not been damaged during
laying.
Backfilling
Prior to backfilling, it is necessary to carry out a visual inspection and some items, which required
to be checked, are as follows.
a) The cables have proper bedding
b) The spacing is correct if there is more than one cable in the trench
c) Cables at duct mouths are suitably supported and ducts are sealed to prevent ingress of
moisture.
d) Pulling equipment is removed. In the case of skid plates etc this may need to be combined
with backfilling to prevent collapse of the trench wall.
e) The cable is free from the obvious damage caused by the installation. A very high
proportion (possibly 90 %) of cable failures in service are due to such damage.
The cables should be first surrounded and covered with appropriate bedding materials, using sand
or riddled soil as necessary, to give a compacted cover of 75 mm thickness over the cable. The
concrete covers / tiles may then be placed centrally over the cable.
120
121
around the aligned conductors and filled up by basting with molten solder. Grade M solder is used
for copper conductors and Alca P for stranded alumunium. The ferrule or lug is then wiped and
rubbed down to give a smooth outer surface.
For joints the weak-back ferrule is the most popular, so-called because its design allows it to be
opened to fit the stranded conductors and permit the introduction of solder. The same technique is
used for fitting lugs, where the hot metal is poured in at the end.
The fitting of lugs and ferrules is a highly skilled operation, which relies on the jointers expertise
to produce a solid ferrule and lug with no cavities or badly, tinned conductor strands. These defects
will result in high resistance connection, which could lead to premature failure of the Joints and
terminations.
Soldered ferrules are limited to a maximum temperature under short-circuit conditions of 1600 C.
They are therefore unsuitable for cable systems taking full advantage of the 2500 C short-circuit
rating offered by polymeric cables such as XLPE.
Compression connectors
This system utilizes an installation tool equipped with specially designed dies to deform a metallic
tube on to the conductor, producing a low resistance electrical contact with good mechanical grip.
The tools are either hydraulic or electro-hydraulic in operation and the dies impart an indent,
hexagonal or circumferential form on the connector depending on the conductor and customer
preference.
The connectors themselves are either made from copper or alumunium tube, which is machined to
produce ferrules or flattened to produce lugs.
The use of compression tooling provides a more reproducible connection that requires a lower level
of operator skill than for soldered connections, which is particularly beneficial for connection to
alumunium conductors.
Mechanical Connectors
Now a days the mechanical connectors are becoming exceedingly popular through out the world.
For stranded low voltage conductors and all medium voltage applications the torque applied is
controlled by the screws, which have a tapered portion which shears off at a predetermined torque.
Like compression connectors, mechanical connectors provide a consistent connection when
installed by unskilled operators. They also have the advantage that they do not require installation
tooling. Because the manufacturing processes for mechanical connectors are more difficult they are
therefore more expensive than compression connectors.
Stress Control at Dielectric Screen Termination
In the preparation of cable prior to jointing, the termination of the dielectric core screen produces an
increase in the potential gradient along the interface between the dielectric and the surrounding
space.
The stress in the dielectric will be much higher than the design stress of the cable, increasing the
probability that premature failure will occur. If the medium surrounding the termination is air, or if
there is an air gap between the dielectric and the filling compound, then the stress may cause the air
to discharge at working voltage. Polymeric materials are less resistant to discharges than paper
insulation; hence discharges in the termination region will erode polymeric dielectrics, leading to
premature failure.
A number of techniques are used for stress control. They are
1)
Capacitive Stress control
2)
High permittivity Stress control
Distribution Training Institute, CESC Limited
122
3)
123
Medium voltage terminations use track resistant weatherproof materials for both tubings and
breakout together with heat shrinkable rain sheds, also in the same material, for outdoor
terminations. Stress control is by means of either a high permittivity or non-linear resistive tube or
coating, whilst for 11 KV belted paper cables this breakout is made of semicondiucting materials,
effectively converting the cable into a screened design. Heat shrinkable terminations can be used in
boxes designed for compound clearances by the addition of a heat shrink shroud or boot.
Early version of Joints for medium voltage cables consisted of a number of tubes to provide stress
control, insulation, screening and overall protection. More modern designs combine these layers by
method of co-extrusion, thereby making the installation somewhat easier.
Premoulded Joints and Terminations
These products are made from either EPR or silicon rubber or are only suitable for polymeric
cables. Premoulded products, being factory made and tested, are of consistent quality and can be
installed very quickly. They are designed to form an interference fit on the cable. They will
accommodate small variations in diameters so it is very important to know the dimensions of the
cable to be jointed or terminated.
Indoor terminations designed for air clearances consist of stress cone and the conductor connector:
these are converted to outdoor terminations by adding interlocking rains sheds together with a cap
seal onto the conductor connector.
Joints are also available which use the Stress Cone in the form of a cable reducer. The inner bore of
the cable reducer is sized to suit the cable diameter and the outer diameter forms an interference fit
with a housing. This has an inner semi-conducting portion to control stresses at the connector
position, a middle insulating layer and an outer semi-conducting layer.
Cold Shrink
Over the last few years the use of elastomeric materials, which shrink onto the cable, are now
rivaling heat shrink as a method of terminating medium voltage cables. Like heat shrink they can
accommodate a wide range of cable diameters, but they offer a number of advantages. Equipment
such as Gas cylinder and torches is unnecessary and installation is less dependent upon the skill of
the operator. Cold shrink is capable of following any subsequent movement such as resetting cores
etc.
.
124
125
Spark Gap
Rf
Conductor/Sheath
Shunt Fault
Cf
Spark Gap
Conductor/Sheath
Series Fault
126
the cable and readings of the resistance value must be noted. Any imbalances indicate presence of a
series fault with some resistance.
r
Checking of
Continuity
y
b
Earth
Earth
Measurement of continuity and insulation resistance of all the cores (in three phase cables ) with
respect to ground and in between from both ends of the faulty cable give the equivalent circuit
picture of the faults nature. Although it may be apparent that checking of continuity and insulation
resistance from one end is sufficient to establish fault condition, some typical cases as the one
shown below suggest that it is better to check the cable condition from both ends in order to prevent
erroneous conclusion about the nature of the fault.
r
y
b
A Single end Continuity and Insulation resistance check would yield erroneous results
Some of the common and typical types of cable faults as represented through different equivalent
circuits are given below.
Different Types of Equivalent Ckt. Representation
127
a x
a
x
=
=
(a + b ) (x + y )
b y
and, taking into consideration the resistance per unit length of the cable conductor to be constant, x and y
can be considered as lengths. The location of the fault as a fraction of loop length (2L) is given by,
X =
a (x + y )
(a + b )
a
x=
* (2 L )
(a + b )
128
With potentiometer type bridge arms, the dial reading is given as percentage of the loop length 2L.
Although readings from a single end are sufficient for fault location, it is better to have readings
from both ends for cross-checking purposes. If a and b are the percentage readings of the
potentiometer as shown above and a and b are the percentage readings with the bridge connected
at the other end, then results obtained should be cross-checked as follows:
a + b = 100%
a+ b = 100%
a + a = 50%
b + b = 150%
As the location of a fault depends on the linearity of resistance per unit length along the cable cores,
this brings into focus that the cross-sections & materials of the cores, and the positions of any
points of change of cross-section must be known. For feeders having cables of different crosssection & materials (Cu/Al) , it is necessary to convert the total length to a common section (
equivalent length ) and reconvert the equivalent fault distance to actual distance. The main
advantage of Murray loop test is its accuracy. Accuracy of around 0.1 percent is achievable if there
are no other sources of error, e.g. poor cable length and cross-section data, parallax or human error
in null point detection during bridge balancing, formation of local resistance at joints of test leads
connecting the bridge with the cable or at the shorting loop at the other end. This emphasizes that
the connection and loop shorting must be very short, heavy and bolted connection of zero ohms.
Two factors influence sensitivity of the bridge:
The sensitivity of the galvanometer itself. Now a days highly sensitive amplifier assisted
galvanometer is used.
The current driven through the fault resistance. In practice a fine balance is easy to achieve with
about ten milli amperes flowing.
Another bridge configuration is sometimes also used viz. Murray Warren Loop for some specific shunt
fault conditions as shown in the following figure.
In this case, the cable condition is such that all the three phases are continuous but all have developed
low Insulation Resistance with respect to earth/sheath. However in order to perform this test, it is
necessary that the Insulation Resistance of at least two of the three cable cores, although may be
comparable are not equal. In this bridge method, taking readings from both ends are essential for the
determining the fault location.
END A
END B
129
a b
x L ,where L is the Route Length of the Cable
a b + a- b
c
V = , where is the Dielectric Constant of the insulating medium.
Since velocity of light is constant, velocity of propagation of pulse in the cable is proportional to
the reciprocal of the square root of the dielectric constant, and is called as Velocity Propagation
Factor or v.p.f which is being set by the operator in the instrument. However it is impractical to
have the knowledge of exact value of dielectric constant for every type in the network. Generally
for most of the paper or XLPE cables the v.p.f lie between 0.52 0.58
If the faulty cable has at least one sound conductor (phase) and the length of the cable is known,
exact v.p.f of the cable can be determined by connecting the healthy phase and calibrating by
varying v.pf setting against the available known length. Subsequently the fault distance can be
measured at same v.p.f by connecting to the faulty phase.
When sound phase is not available, the factor of velocity propagation is eliminated from the
calculation by measuring the apparent distance to fault from both ends of the faulty phase with
same v.p.f setting, say 0.56 or any and calculating through ratio as under:
130
d1
Fd1 =
(d1 + d2)
Where d1 & d2 are apparent fault distance from end 1&2
respectively,
L is the route length of the faulty cable and
Fd1 is the fault distance from end 1.
Normally v.p.f setting of 0.56 give close reading to exact length for most of the power cables.
Typical nature of display obtained for some common types of series and low resistance shunt faults
are given below.
PE/TDR Trace for Series Fault
131
r = Rf / (2Zo + Rf )
Following tables give Reflection factor (%) in a power cable of Zo = 40 ohms for different values
of Rf for shunt and series faults.
Fault resistance in ohms Reflection factor (%), shunt fault Reflection factor (%), series fault
1
- 95
1.2
10
-67
11
40
-33
33
100
-17
55
400
-4.8
83
1000
Negligible
93
100K
Negligible
Approx. 100
132
133
related to the fault break down. A wrong pre-location can often waste hours of valuable time, and,
can reduce operators faith in the equipment.
In late seventies Dr. P. F. Gale revolutionized the power cable fault location by developing
equipment that analyzes the current transient associated with the voltage transient on the basis of
above approach. This simplified the equipment and gave safer approach by deriving the current
transient from a simple linear coupler connected in the earth return lead of the HV surge generator.
The process is called impulse current method. When considering current transients as opposed to
voltage transients one has to take different view of the trace features produced. A positive voltage
transient produces a negative current transient and the co-efficient of reflection are of opposite
sense, as shown below.
Features of Voltage and Transients Current
Transient
Feature
Co Eff. Of Reflection
Voltage
Open circuit
Current
Open circuit
- 1, Inverts on reflection
Voltage
Short circuit
- 1, Inverts on reflection
Current
Short circuit
Practical Procedure:
When performing a pre location by impulse current method it is usually helpful to carry out few
diagnostic checks using the ICE (Impulse Current Equipment). With SG (Surge Generator)
connected on the healthy core or faulty core, a low voltage of 2 3 Kv is set, ICE is also set and a
single surge is applied to produce a trace as shown. At this low voltage no break down occurs.
Trace produced is of PE/TDR type.
The portion AB represents the total cable length and the corresponding time in microseconds
(proportional to the cable length) is measured. Thus we get velocity propagation constant for the
cable under test as say, X metres / microsecond. Sometime similar check is also done with other
end shorted to earth with a trace as shown and super imposing the traces under open and short
circuit
134
Superimposing one trace upon another to accurately measure the cable length.
Next the voltage at which the faulty core is flashing or breaking down is determined with the SG in
its continuous mode. Then the SG is selected in surge mode and set at least 1.5 times the flashing
voltage and with the ICE connected, surge is applied to monitor the trace. Surge voltage may be
increased in steps for a better quality of trace. A few samples of traces under different conditions of
break down is shown as under.
135
Long ionisation delay; fault features of the end off the screen.
Trace produced when fault breakdown occurs after the surge has passed
the fault position and has been reflected from the other end i.e end B.
The exact point to which the measurement to be made on the trace for fault is very critical. It is
taken to the start of a small positive bump occurring just before the negative going front of the
feature at point A on the trace which is the arrival of the first reflection of the break down pulse at
the test end. This bump is the result of the time delay introduced by of the inductive mismatch
offered at the surge generator and this can produce errors of measurement if not recognized. On a
long cable length this error will be several hundred metres.
To eliminate the error due to improper identification of this notch on the trace a method known as
LOOP IN / LOOP OUT is applied. A healthy & a faulty core is looped at SG end of the cable
and a trace is obtained for the break down. The trace is stored in the memory of ICE. Next the two
cores are also looped at far end that is cables healthy & faulty cores are looped at both near end of
the SG and far end. Trace is again obtained keeping the settings of ICE unaltered from the previous
trace. Two types of traces thus obtained are compared by superimposing one on the other aligning
at the break down point of the two traces. The point of separation of the two traces in two different
directions from the alignment point gives the distance to fault from other end of the cable as
illustrated below.
Distribution Training Institute, CESC Limited
136
ICE
The above two traces are superimposed and the breakdown features carefully coincided.
137
Trace Showing the Fault Point and Other End of the Cable with SIM
138
139
140
141
Ia1
Ia2
1200
Ic1
1200
1200
Ib2
1200
Ic2
Negative Sequence components
Ib1
Ia
Ia0
Ia2
Ia1
Ic1
Ic2
Ib
Ic
Ib0
Ib1
Ib2
Ic0
142
Thus :
Ia=Ia0 + Ia1 + Ia2
Ib = Ib0 + Ib1 + Ib2
Ic = Ic0 + Ic1 + Ic2
- Eqn.1
- Eqn.2
Operator a :
The letter a is an operator that causes a rotation of 1200 on a phasor in the counter clockwise
direction. It is a complex number of unit magnitude with an angle of 1200 and is defined as
a = 1<1200 = - 0.5 + j 0.866
If the operator a is applied to a vector twice in succession, the phase is rotated through 2400.
Thus,
a2 = 1 <2400 = -0.5 - j0.866.
From Balanced Vector to Symmetrical Components:
Referring to Fig.1 we obtain as follows:
Positive Sequence Components are:
Ia1
Ib1 = a2 Ia1
Ic1=a Ia1
Negative Sequence Components are:
Ia2
Ib2 = a Ia2
Ic2 = a2 Ia2
Ia0
Ib0 = Ia0
Ic0 = Ia0
From equation 1
Ia = Ia0 + Ia1 + Ia2
Ib = Ia0 + a2Ia1 + aIa2
Ic = Ia0 + aIa1 + a2Ia2
- Eqn.3
In matrix from
Ia
Ib
Ic
1
1
1
Lel
A=
Then
A-1
1
a2
a
1
a
a2
Ia0
Ia1
Ia2
1
1
1
1
a2
a
1
a
a2
1
1
1
1
a
a2
1
a2
a
Eqn.4
143
Ia0
Ia1
Ia2
=
=
=
(Ia + Ib + Ic)
(Ia + aIb + a2Ic)
(Ia + a2Ib + aIc)
Ia
Ib
Ic
- Eqn.5
In delta connected load, the line currents do not find return neutral path. Hence line currents do not
have zero sequence components.
In star connected system without neutral path or neutral grounding In is zero. Hence zero
sequence currents are zero.
Sequence Impedances
The impedance of any section of a balanced network to current of one sequence may be different
from impedance to current of another sequence.
The impedance offered by a circuit to the positive sequence component of current is called positive
Sequence Impedance of that circuit. Likewise the negative sequence impedance and zero
sequence impedance are defined.
Sequence Networks
The single phase equivalent circuit composed of the impedances to current of any one sequence
only is called the Sequence Network for that particular sequence.
The sequence network consists of any generated emf of like sequence. Sequence networks carrying
the currents Ia1, Ia2 and Ia0 are interconnected to represent various unbalanced fault conditions.
Sequence Networks of an Unloaded Generator:
Circuit diagram of an unloaded generator grounded through a reactance is shown :
144
Ia
a
+
Ea
-
Zn
- Eb
+
Ec
Ib
Sequence Network :
a
+
Z1
+
Ea -
Ia1
Va1
Z2
Ia2
Va2
Zg0
Ia0
Va0
3Zn
Positive Sequence
Negative Sequence
Zero Sequence
2)
3)
145
Ia
Fault
Ia=In
Ea
-
Zn
- Eb
+
Ec
Ib
Ia0
1
1
Ia1
= 1
a
Ia2
1
a2
Ia0 = Ia1 = Ia2 = Ia
1
a2
a
Ia
Ib
Ic
= Ia
146
The connection of sequence networks of unloaded generator for a single line-to-ground fault
on phase a at the terminal of the generator will be as follows:
_
Ea
Z1
Va=0
Va1
Ia1
+
Ia1 = Ia2 = Ia0
Z2
Ia2=Ia1
Va2
+
-
3Zn
Z0
Zg0
2.
Va0
Ia0=Ia1
In=0
Ea
-
Zn
- Eb
+
+
C
Ec
b
Ib
IC
147
1
= 1
1
1
a
a2
1
a2
a
0
-Ic
Ic
1
a
a2
1
a2
a
Va
0
0
Ia0 = 0
and Ia2 = - Ia1
1
= 1
1
Va0
Va1
Va2
Va1 = Va2
And since Ia0 = 0, Va0 = 0
Ea
+
Va1
Z2
Va2
Z1
+
Ia1
+
Ia2
Ia1 = - Ia2
We derive, Ea-Ia1Z1 Ia2 Z2 = O
Ea
Ia1 =
= I a 2, I a = O
Z 1+ Z 2
Va1 = Ea Ia1Z1 = Va2, Va = 0
From the sequence components we can derive currents and voltages
148
3.
Ia
+
In
Ea
-
- Eb
Zn
+
+
Ec
b
Ib+Ic=In
Ib
IC
Va0
Va1
Va2
1
= 1
1
1
a
a2
1
a2
a
Va
0
0
Ea
3Zn
+
Va1
Z2
Va2
Z0
Va0
Zg0
Z1
+
Ia1
Ia2
Ia0
149
Ea
I a1=
1
1
z
2 z0
Z +1
1
Ea
=
Z 1+
z2z0
z 2+z0
Va1 = Ea Ia1 Z1
Va1 = Va2 = Va0
Ia2 =
V a1
Z2
Ia0 =
V a1
Z0
From these symmetrical components the currents and voltages can be determined.
Sequence Impedances of Different Elements of Power System :
The positive and negative sequence impedances of linear, symmetrical, static circuits are identical
because impedance of such circuits is independent of phase sequence provided the applied voltages
are balanced.
The impedance of a transmission line to zero sequence currents differs from the
impedance to positive and negative sequence currents.
The impedance of rotating machines to currents of the three sequences will generally
be different for each sequence.
A transformer in a three-phase circuit may consist of three individual single-phase
units, or it may be a three-phase transformer. The zero sequence series impedances of
three-phase units may differ slightly from the positive and negative sequence values, but
for all practical purposes, series impedances of all sequences may be assumed equal.
The zero-sequence impedance of balanced Y and - connected loads equals the
positive and negative sequence impedance.
Zero Sequence Current in case of Star or Delta connection:
Zero sequence currents flow only if return path is available through which circuit is completed.
Zero sequence equivalent circuits of three phase transformers banks for different connection
diagrams are discussed below:
Case I :
Y-Y Bank, one neutral grounded
A
Symbol
Reference Bus
If either one of the neutrals of Y-Y bank is ungrounded, zero sequence current cannot flow in either
winding.
150
Case II :
Z0
Reference Bus
Symbol
Where both neutrals of Y-Y Bank are grounded, a path through the transformer exists for
zero sequence currents in both the windings.
Case III
Y- Bank, Grounded Y
A
Symbol
Z0
If the neutral of a Y- bank is grounded, zero Sequence currents have a path to the ground through
the Y because corresponding induced currents can circulate in the .
The zero sequence current circulating in the to balance the zero sequence current in the Y cannot
flow in the lines connected to the .
Case IV :
Y- Bank, Ungrounded Y
A
Z0
Reference Bus
Symbol
In this case also, zero sequence current cannot flow in the transformer winding.
Case V :
- Bank
A
Symbol
Z0
Reference bus
Circuit provides no return path for zero sequence current, no zero sequence current can flow in a
- Bank, although it can circulate in the winding.
151
Z 1+ Z 2+ Z 0
_______________ 1
_______________ 2
The above equations indicate that the three sequence networks should be connected in series
through the fault point in order to circulate a single line-to-ground fault.
2)
Line-to-line fault
a__________________________
Ia
b__________________________
Ib
c___________________________
Ic
3
I a1=
Z 1+ Z 2
The above equations indicate that the positive and negative sequence networks should be
connected in parallel at fault point in order to simulate a line-to-line fault.
3)
Double line to ground fault
The following relations exist at the fault :
Vb = Vc = 0
Ia = 0
Vf
Z Z
Z 1+ 2 0
Z 2+ Z 0
a___________________________
Ia
b__________________________
Ib
c__________________________
IC
5
6
In Earth Fault
The above equation indicate that three sequence networks should be connected in parallel
at the fault point in order to simulate a double line-to-ground fault.
Distribution Training Institute, CESC Limited
152
4)
a___________________________
Ia
b__________________________
Ib
c__________________________
IC
Earth Fault
and
Ia0 = 0
Ia2 = 0
V f = I a 1 Z1 or Ia1 = Vf / Z1
For three phase symmetrical fault only the positive sequence network exists.
Power System Protection:
Basic need of a power system:
1.
To provide uninterrupted quality power
2.
Prevention of failure power system elements
3.
Mitigation of the effects of failure in power system elements
Protection philosophy is based on mitigating the effects of failure in power system.
Protection is a diagnosis, not prevention or cure.
It is a watchdog, not a police
The purpose of protection is to provide
Reliable Service.
Stability of the System.
Protective Gear:
This is a collective term which covers all the elements used in detecting, locating and initiating the
removal of a faulty part of the power system network from rest of the healthy system.
Elements for promptly disconnecting the faulty element:
1.
Protective relaying.
2.
Circuit breakers with sufficient rupturing capacity.
3.
Fuses.
Characteristics of protective relaying:
Reliability.
Speed.
Selectivity.
Sensitivity.
Stability.
Reliability
Repeated performance of correct operation even after long period of inactivity. A Silent
sentinel.
It is essential that protective relaying equipment must be reliable. Incorrect operation can be
attributed to the following reasons:
Distribution Training Institute, CESC Limited
153
Speed
Incorrect design
Incorrect installation
Deterioration of protection system component elements
The purpose of protection is to isolate faults from the power system in a very short time to
minimize (i) extent of damage and (ii) risk of instability of the system than could be
achieved manually.
Selectivity
Selection of only unhealthy part of network.
When a fault occurs in a system the protection is required to select and trip only the
concerned circuit breakers to isolate the faulty part only. The property of selective tripping
is also called discrimination and is achieved by the following methods:
Unit System
Time Graded System and
Directional System.
Sensitivity
Detection of unhealthiness at its lowest level.
A protective system is said to be sensitive if the primary operating current is low.
Stability
Ability to operate only for those conditions that calls for its operation.
If refers to the ability of the system to remain inert to all load conditions and through faults.
It is a term applicable to Unit Systems; the term discrimination is the equivalent expression
applicable to non-unit systems.
The above requirements / features of protection are achieved through:
i)
Proper Selection of CTs &VT, Sensor
ii)
Proper Type of relay and relaying schemes/ logic
iii)
Proper Co-ordination of relay settings,
iv)
Proper selection of Trip Supply etc.
Primary and Back up Protection:
Primary or main protections are basically unit protections and are instantaneous, i.e. operate
and reset with no intentional delay.
Several factors may cause protection failure and there is also a possibility of circuit breaker failure
itself. For this reason, it is usual to supplement Primary Protection with Back up Protection
and to minimise the possibilities of failure to clear a fault from the system.
Back up protection is inherently slower than the main protection and depending on the power
system configuration, may be less discriminative.
The extent and type of back up protection will be related to failure risks and relative economic
importance of the system. For distribution systems where fault clearance time are less critical in
comparison, time delayed remote back up protection is adequate but for EHV systems, where
stability is at risk unless a fault is cleared quickly, two main or primary protection with local
breaker failure backup are normally chosen.
Different classes of protective relays:
Depending on the measurement of actuating quantities (voltage and current) which are present at
the relaying point, protective relays can be grouped as follows:
154
a) Magnitude Relays
Measures magnitude such as over-current, undercurrent, over voltage, under-voltage relays,
frequency relays etc.
These relays respond to their input quantities and operate to trip whenever the magnitude exceeds a
certain value which is settable.
IDMT Over-current Relay
The operating principle of an over-current relay can be defined as,
fault current magnitude, [If] > Relay Pick up current, [Ip] trip
[If] < [Ip]
block
The simplest form of over-current relay is not versatile. Another parameter needs to be incorporated
the time it takes to operate after [If] exceeds [Ip]. The above conditions can be supplemented by
if [If] > [Ip]
T= ([If]-[Ip])
Where T is the relay operating time and is a function which describes its dependence on the fault
current level.
The traditional method of representing the characteristics of a time over-current relay is as shown.
Op. Time
(in secs.)
2
1
TMS SETTING
For long transmission lines or transformer feeders, where the source impedance is small in
comparison with the protected circuit impedance, a high set instantaneous element is used in
conjunction with IDMT over-current element. This makes possible a reduction in tripping time at
high fault levels, and improves the overall system grading.
b) Product measuring Relays
These relays measure product VI Cos such as Directional Over-current & Earth fault relays,
Power relays etc. It depends for its operation upon the angle () of the current with respect to the
voltage. That way the relay can be set to operate for fault in a particular direction with reference to
the relay location.
The operating principle can be described by
Distribution Training Institute, CESC Limited
155
trip
block
c) Ratio relays
These relays measure the ratio of V / I. For example, distance relay which operates for faults within
a certain distance of its location. It measures the ratio of the voltage and current at the relay
location, which is proportional to the distance.
Z=V/I
The relay performance can be described by
[Z] < [Zr]
trip
[Z] > [Zr]
block
The relay is called an impedance relay.
In complex plane, the locus of constant [Zr] is a circle.
X
[Zr]
.
Z
Trip
R
Block
This type of impedance relay has characteristic non-directional, a fault either to left or right of
relay location having [Z] < [Zr] will lead to a trip decision.
By a simple modification in the relay, the circle which is centered at the origin can be offset by an
amount Z1 producing the characteristic of the offset impedance relay. The performance of this type
of relay can be described by
[Z-Z1] < [Zr] trip
[Z-Z1] > [Zr] block
Z1 Zr r
.Z
By selecting Z1=Zr, the relay characteristic can be made to pass through the origin. The
characteristic is called Mho relay characteristic. A Mho relay is inherently directional.
d) Differential Relays.
These relays compare between two quantities / two vectors. It employs the principle of Kirchoffs
current law. Two CTs having the same turns ratios are placed at the boundaries of the zone of
156
protection and they are connected in such a way that the vector difference of secondary currents (I1I2) passes through the relay coil.
The operating principle can be defined by
[I1-I2] > Ip trip
[I1-I2]< Ip block
Often the CT errors increase with increasing values of I1 and I2. For such cases, it is possible to
make the value Ip dependent upon the av. of I1 and I2. A relay can designed in the fashion that the
op. principle becomes.
[I1-I2] > k [I1+I2]/2 trip
[I1-I2] < k [I1+ I2]/2 block
The factor k decides the bias slope of the relay characteristic.
When the entire zone of protection of relay occupies a relatively small physical space near the
relay, like in case of a transformer, a generator or a bus, it is possible to apply this simple
relaying scheme.
When transmission lines are to be protected by a differential relay, their terminals may be long
distance apart and it becomes impractical to connect the signals from the ends of the transmission
line to the relay. Pilot relaying provides a technique of communicating information from a remote
zone boundary to the relay at each terminal.
The physical medium used for pilot channels could be conductors for a telephone circuit, powerline carrier, optical fire and microwave channels.
Transformer Protection
Type of faults in a Transformer Electrical.
Non- Electrical.
Electrical Faults I) Phase to phase.
II) Phase to earth fault at terminals.
III) Phase to phase at winding.
IV) Inter turn short circuit
Non Electrical Faults Core fault due to breakdown of insulation between core lamination.
Decomposition of oil due to ageing.
Failure of cooling system.
Protection in Transformer
Small Transformers I) HRC Fuse, CFS Unit
II) No detection of non-electrical faults.
Medium Size TransformersI) IDMTL O/C & E/F relays.
II) Instantaneous low transient over-reach type high-set O/C & E/F relays.
III) Buchholz device, OTI / WTI / Low oil level alarms.
Large & Very Large Transformers I) Differential Protection.
II) REF Protection.
Distribution Training Institute, CESC Limited
157
132kV - TURRET CT
POST MOUNTED CT
33kV- SWITCH CT
75 MVA
132/34.5KV
158
159
Diagram showing residual connection of three O/C & one E/F relay
160
161
162
163
The principle is that whatever current is fed from Station A is taken out from Station B, then the
system is healthy and the relay do not operate
If there is a fault in the feeder then the currents at Stns. A & B are reversed & the relays operate.
33 kV Transformer Feeders :
1. Unit protection is one type of protection.
2. There is another method for providing instantaneous main protection. Instantaneous Over current
& Earth fault relay is used as shown the diagram.
164
Distance Protection:
It is a non unit system of protection but by zone and time setting unit and discrimination is
achieved.
A single relay can provide primary as well as backup protection.
It can easily be modified into unit system by combining it with a signaling channel.
It measures impedance, which is proportional to the line length.
The relay takes input both from CT & VT in order to calculate impedance.
Zones of Protection
Zone 1 typically covers 80% of the line & is instantaneous in operation.
Zone 2 typically is set to cover 120% of the line or 50% of the shortest adjacent line, whichever is
greater. A time delay is given for Zone2 operation to allow discrimination.
Zone3 is further time delayed & covers the entire second line section or more.
Zone 4 is actually the Starter.
Distance Protection Relays used:
1. PYTC - English Electric make.
2. RAZOA - ABB make
3. 7SA - Siemens make.
Distribution Training Institute, CESC Limited
165
M2 Section
X
X
M1
M2
CH
166
Diagram showing Busbar Protection with CT Switching Scheme (with two feeders):
167
Device Name
21
Distance Relay
25
27
Under-voltage Relay
29
Isolating Contactor
30
Annunciator Relay
32
37
40
Field Relay
46
49
50
51
52
AC Circuit Breaker
55
59
Over-voltage Relay
60
64
168
67
74
Alarm Relay
78
79
AC-Reclosing Relay
81
Frequency Relay
85
86.
Lockout Relay
87
94
Note: A suffix letter may be used with the device number; for example, suffix N is used if the
device is connected to a Neutral wire (example: 59N in Siemens Relay is used for protection
against Neutral Displacement); and suffixes X, Y, Z are used for auxiliary devices. Similarly, the
G suffix denotes a ground, hence a 51G being a time over-current ground relay.
169
170
171
172
173
METERING PRACTICES
Voltage /
Current
Time
Frequency is the no of cycles per second and is expressed in Hz. Our system frequency is 50 Hz.
Power is the Electrical capacity of the equipment and is expressed in Watts. Electrical Power is
computed by multiplying Voltage, Current and Power factor in case of AC and only Voltage and
Current in case of DC. (1kW=1000Watts and 1MW=1000kWatts)
Energy is quantum of Power absorbed by a load during a time period. It is computed by
multiplying Power and time and is expressed in Watt-hour / kWatt-hour (1000Watt-hour).
Electrical Unit: Electrical energy consumption is also expressed in Unit.
1 Unit = 1kWh (1000Wh), 1MU = 10 lakh Units
Power Factor is the ratio of actual power consumed by a load to Volt-Amps supplied in it. It is a
ratio and can never be greater than unity. Power factor depends upon consumers load. Power
Utility looses in supplying low Power factor loads and hence imposes a surcharge for low Power
factor (<0.85) and allows rebate for Power factor >0.90 to encourage consumers for drawing energy
at high Power factor. The Power factor surcharge and rebate is applicable for HT consumers. In
case of DC supply Power factor is misnomer since it is always unity.
Connected Load indicates the summation of rated power of all each individual appliances /
equipment lying installed in a premises. It is expressed in kW.
Maximum Demand means the highest average loads in kW drawn over a period (30 minutes)
during a billing month by consumer.
Load Factor means the ratio of the average load to the maximum load during the month. It is
expressed in %.
Demand Factor means the ratio of the maximum demand to the connected load.
Diversity Factor: The ratio of sum of the individual maximum demands of all the consumers
supplied by it to the maximum demand of the power station is called the diversity factor
Average Demand = Maximum Demand X Load Factor
Maximum Demand = Connected Load X Demand Factor
174
175
3 ph 3 - Wire
176
177
Old EM Meter
Superior Quality Meter
178
Registration
Counter
Iron Frame
Gear
Mechanism
Voltage /
Pressure Coil
Aluminium
Disc
Current
Coil
Spindle
Brake
Magnet
Potential
Link
3 Phase AC Meter with Components
Registration
Counter
Voltage Coil
Adjustment
Screws
Brake Magnet
Magnetic
Suspension
Aluminium Disc
Current Coil
179
Cyclo Dial
Electronic
Display
Pointer Dial
Terminal Blocks
1.
2.
3.
4.
Ph In Neutral Neutral Ph Out
In
Out
1.
2.
R ph In R ph
Out
3.
B ph
In
4.
B ph
Out
5.
Y ph
In
6.
7. 8.
Y ph Neutral In
Out
& Out
180
Meter Constant
(revs/kWh)
Meter Accuracy Class
CESCs Serial No.
Meter Name Plate
Voltage and Current Electro-magnet
Voltage electro-magnet consists of a voltage coil and a laminated "E" core. Meter phase to neutral
voltage is applied across this coil and it generates magnetic field proportional to supply voltage for
developing torque after interaction with magnetic field of current coil.
Voltage coils are essentially made of very small cross sectional wires with high no. of turns.
Current electro-magnet consists of a current coil and a "C" shaped laminated core. The coil
continuously takes the load current and therefore made of thick wires with very small no. of turns.
Current Coil
Aluminium Disc
181
Disc Spindle and Supporting Arrangement: Spindle is an integral part of the disc, used for
supporting the disc vertically across the top pivot and bottom jewel. The modern energy meters
(Superior quality) are provided with magnetic suspension bearing which has eliminated stopping
the meter due to failure of jewel bearing. Starting current of the modern energy meters are also very
low (less than 0.5%) due to introduction of magnetic suspension bearing and hence they are
too sensitive to record very low amount of energy.
Magnetic Suspension
Brake Magnet: It is used for slow fast adjustment of the meter disc whenever necessary. Brake
magnet is essentially a permanent magnet and covers a portion of the disc. It generates reverse
torque on the meter disc due to eddy current principle when the disc is in motion.
Brake Magnet
Low Load Adjustment
Low load adjustment is made at 5% of the rated current with the help of the low load plate. Moving
the metal plate assembly across the poles of the potential electro-magnet by turning the micrometric
screw provided for this purpose, produces a small torque to compensate for friction of the moving
parts
Distribution Training Institute, CESC Limited
182
Over Voltage
Ageing
Anti-Creep Holes
183
Inductive Coupling
Unit with Battery
Backward Scrolling
PB
Short Transparent
Terminal Cover
SPRINT (WHOLE
CURRENT 10 60 A)
Ultra-sonically
Welded Cap on
meter body-cover
fixing screw
Ultra-sonic Welding
Manufacturers
Plastic Seal
SPRINT (WHOLE
CURRENT 10 60 A)
184
Universal MD Reset
PB
Scrolling PB
LT CT OPERATED STATIC
METER
RS232
Communication
Module
LCD Display
Universal MD Reset
PB
Scrolling PB
HT STATIC METER
Distribution Training Institute, CESC Limited
185
RS-232
Communication
Port
Sealing
arrangement of
communication
port
HT STATIC METER
186
187
Requirement of Metering CT
The metering CT should be accurate in the entire operating range upto the rated current and even
beyond, upto a certain limit.
A typical specification :
300/5 A
Cl : 1.0 , Burden : 15 VA
ISF 2
This CT must maintain its error within 1% of rated current upto 300 A , definitely & also upto
600A ( rated current X ISF I.e. 300 X 2 ) beyond which it must saturate. The whole idea is faithful
reproduction of current upto a certain level & saving the connected meters from over current
beyond that level.
Main types of CTs (Construction wise)
1. Ring type or window type or Bar primary type
In this case no. of turn in primary winding = 1
2. Wound primary type
3. Post type (Outdoor)
Current Transformer
188
189
190
Testing of VTs
1.
Error measurements ( In Lab)
2.
Insulation tests
3.
Induced voltage test
4.
Polarity test
5.
HV test.
List of instrument required for VT Test :
1.
Multimeter (2nos. 1 for current & 1 for Voltage)
2.
Low resistance measuring instrument (inductive)
3.
1-ph Variac
4.
Battery
5.
Ratio & Phase angle error measuring inst. (for Lab.use)
6.
HV AC Test set (for Ratio check)
7.
1 kV Megger
Indian Standard :
Current Transformers are covered by IS:2705, 1992 (Reaffirmed 2002).
Voltage Transformers are covered by IS:3156, 1992 (Reaffirmed 2002).
191
192
193
For the second feeder let the demand be as shown in the second graph with the maximum demand
corresponding to time = 90 min, value of the demand is 190 KVA.
If on each instance the demands are added we get the maximum demand at time period
corresponding to 75 minute. Demand value is 320 KV A
If the two maximum demands for the feeder 1 and 2 are simply added what we get is 190 + 190 =
380 kV A, which is considerably higher than the concurrent maximum demand in this particular
case the difference, is about 18.75 percent, which is not acceptable.
This situation arises because of the difference in occurrence of maximum demand on the two
feeders. The example clearly indicates that there has to be a method to determine concurrent
maximum demand for the combined feeder.
Net summation Metering Scheme
Summation on the feeder meters can be done in following two different metering schemes. The
simple summation metering scheme which adds the successive values of the active and reactive
energy and calculates the apparent energy. When replacing a summation current transformer on a
multiple feeder metering system it is essential to calculate the net values of active energy import or
export and the net value of the reactive energy import or export. The net apparent value should be
calculated after calculating the net active and net reactive values. This will give the net apparent
demand values. Using the net apparent import! export maximum demand for shall be calculated.
The Quadrant Definition
The following definition shall apply for all references to quadrants as applicable to metering for
tariff purpose.
The voltage vector is assumed in the vertically upward direction and the quadrants have been
defined based on position of the current vector in the tie line.
Tariff components in each quadrant:
The electricity meter is expected to register the energy components that contribute to tariff. While,
active energy transferred (import or export) is the fundamental tariff register; reactive and apparent
energy registers are also used for tariff purposes either directly or indirectly. The fundamental
purpose of this component is to account for the "Capacity" expenses of the transmissions and
distribution system. There is a lack of standardisation in this regard, and while some parts of the
world impose an active only tariff, others use reactive energy as well. Yet another set of utilities use
apparent energy (lag + lead or lag only) as a component for computing tariff. The objective of this
section is to identify the incorrectness of the apparent energy based tariff.
194
Quadrant I: In the QI, both active and reactive power is being imported (as seen from the load side
of the metering system). The active power is in import mode, as the VICos<l> is positive. The load
is inductive (lagging power factor), and reactive power is said to be imported.
The brown arrow indicates the direction of the CT and hence as seen from the meter, the grid is
importing active as well as reactive power from the generator. In other words, the inductive current
that the generator has to supply to the grid uses up its current carrying capacity.
Put in a different way, if capacitors were installed in the grid system, the reactive power would have
been supplied by the capacitors and the generator could have used its current carrying capacity to
provide for higher active power transfer. Thus, the generator is entitled to a compensation for this
loss of capacity. Tariff in this quadrant can therefore be based on both the active energy and
apparent energy (kVAh = (kWh2 + kVArh2 ) computations. However, any tariff structure based on
active and reactive energies would have been equally beneficial, if not more.
Quadrant II: In the QII, active power is being imported and reactive power is being exported. (As
seen from the load side of the metering system). The active power is in import mode, as the
VICos<l> is positive. The load is capacitive (leading power factor), and reactive power is said to be
exported.
In general the grid is always assumed to be hungry of lagging power factor. Hence a leading current
flowing from the generator to the grid may be conceived, as reactive export from the grid to the
generator (see blue arrow). This sort of situation is very common to find in wind power generators,
who may be at times supplying some active power, but drawing huge amount of reactive power
from the grid.
It is in this quadrant now that a kVA tariff becomes difficult to interpret. The system "capacity" is
now partially being used by the active power (for which the grid pays the generator), and partially
by the reactive power (for which the generator should pay the grid). However, any definition of kVA
for use of capacity tariff is illogical and incorrect, as in itself it does not carry the "sense" of
payment (who pays whom). Thus, while the grid is entitled to a compensation for its loss of
capacity, it should be computed upon the reactive energy export.
Quadrant III: In the QIII, both active and reactive power is being exported (as seen from the load
side of the metering system). The active power is in export mode, as the VICos is negative. The
load is inductive (lagging power factor), and reactive power is said to be imported.
195
The brown arrow indicates the direction of the CT and hence as seen from the meter, the grid is
exporting active as well as reactive power to the generator. In 'other words, the inductive current
that the grid has to supply to the generator uses up its current carrying capacity.
This situation is exactly opposite to the situation in quadrant I and the generator is entitled to a
compensation for this loss of capacity. Tariff in this quadrant may be based on both the active
energy and apparent energy (kVA = ...J(kW2 + kVAr ) computations.
Again, needless to mention that any tariff structure based on active and reactive energies would
have been equally beneficial, if not more.
Quadrant IV: In the QIV, active power is being exported and reactive power is being imported.
(As seen from the load side of the metering system). The active power is in export mode, as the
VICos is negative. The load is inductive and reactive power is said to be imported into the grid.
As in Q II, in this quadrant as well, a kVA tariff becomes difficult to interpret. The system
"capacity" is now partially being used by the active power (for which the generator pays the grid),
and partially by the reactive power (for which the grid should pay the generator). Once again, any
definition of kVA for use of capacity tariff is illogical and incorrect, as in itself it does not carry the
"sense" of payment (who pays whom). Thus, while the grid is entitled to a compensationfor its loss
of capacity, it should be computed upon the reactive energy export.
Conclusion
In the light of above the kVA metering is done as follows:
Q1 Active Import Reactive Import
kVA Register = kW
kVA Register = kW
196
197
198
Inspection
Central Server
Outstanding
checking &
recovery
Consumer, Meter
& SD Details
New Consumers to
Billing System
Meter Reading
A fleet of around 600 Meter Inspectors are engaged for noting / capturing the Meter Reading of ~24
lacs Meters every month, from the premises of our Consumers (where the Meters are installed) in
and around the city of Kolkata and Howrah. Besides the Electro-mechanical Meters, we also have
installed Electronic Static Meters for our High-Tension and high-end Low-Tension Consumers.
Every month, our Meter Inspectors note the Meter Reading from the Electro-mechanical Meters in
their Meter Books and subsequently data from these Books are captured through the Off-line Data
Entry System (with necessary validation check) at our six Regional Offices. However, from Static
Meters we down-load Meter Reading and related data directly (through Optical cable) into the
Palm-Top Microprocessor based instruments called MRI and in turn, download the same into the
Computers at our Regional Offices. CESC is presently in the process of installing Electronic Static
Meters attaching GSM Modems, for capturing Meter-Reading and other related data from remote
locations (CESC House and Testing Department). This process is called Automated Meter Reading
(AMR). Presently we are using AMR for HT and Street Lighting (LT) supplies. All the said Meter
Reading Data are subsequently sent to Computer House through our Network (BILL NET) for
processing through our Billing System.
199
Electronic
Meter
Down-load
In Computer
Reading thru
MRI
Electronic
Meter
Reading thru
GSM Modem
Down-load
In Computer
Electro
Mechanical
Meter
Manual
Reading
Off-line
Data Entry
Meter
Reading Data
to Billing
System
WAN
(Bill Net)
Payment Data
CESC has thirty eight fully automated payment receiving centers (Cash Offices), scattered all over
its licensed area. Since most of our Computer generated bills are Bar-Coded, we can capture
accurate information from the bills, paid at our Cash Offices, with the help of our intelligent cashregister machines (POS), capable of scanning Bar-Codes. Subsequently, after reconciliation at
Treasury Department end, these data are transferred to our Central Computer System through our
own Wide Area Network, called CASH-NET, for processing through our Billing System.
1. Block Diagram of Payment Data Capture at Cash Offices
38 Cash Offices
Capture of
Bar-Coded
Payment data
thru POS
Machines
38 Cash Office
Down-load in
Computer from
POS Machines
WAN
(Cash Net)
CESC House
Scrutiny of
data at
Treasury
Dept.
Park Lane
Scrutiny of
data at
Treasury
Dept.
Payment
information to
Billing System
WAN
(Cash Net)
CESC House
CESC House
Off-Line Data
Entry
Reconciliation of
Payment data
Payment
information to
Billing System
WAN
(Cash Net)
Distribution Training Institute, CESC Limited
200
A/c of
Disconnected
Supplies
Electricity
Bills & MIS
Reports
Payment of
Bills
Core Billing
System
Outstanding
Follow-up &
C/Off jobs
New Supply
Security
Deposit
Processed data
to Finance
(ERP) & other
Departments
The front-end Consumer Service Systems at our Regional Offices are basically the sub-Systems of
the Core Billing System. The said sub-Systems helps us for (1) Redressal of Consumer complaints,
(2) On-line enquiry related to Consumer and Meter, (3) Generation of duplicate Electricity Bills, (4)
Preparation of bills related to Security Deposit and Re-connection of Supply, (5) Follow-up and
recovery of outstanding dues, (6) Dynamic allocation of jobs for the Meter Inspectors and keeping
track of the same, (7) Several Statistical Reports for focused and efficient operation, (8) Correction
of bills and (9) Accounting of dishonored cheques.
The entire gamut of the Billing System successfully traverses the total life cycle of Consumer in a
seamless manner, without much human intervention and hindrance.
Outstanding Follow-up
The Core Billing System helps in close monitoring of the outstanding dues of defaulting consumers.
Disconnection Notices are generated by the Billing System for the Consumers, who have not paid
any of their previous electricity consumption bills. The System also generates advices for
Distribution Training Institute, CESC Limited
201
disconnection of Supplies for the defaulting Consumers, depending on the variable parameters,
matching with our business requirements and operational convenience. The System also produces
jobs for inspection and further follow-up of outstanding dues of the already disconnected
Consumers, where the outstanding dues have not been settled for a considerable time. Such
efficient automated monitoring System helps us to keep the outstanding dues under control, over
the years.
Security Deposit
The accounting of the Security Deposit of all individual Consumers is also a sub-system of our
Billing System. (1) Keeping the details of the Security Deposit made by the Consumers, (2)
Determining the maintainable Security Deposit for each of the Consumers, as per the SERC
guideline, (3) Calculation and keeping accounts of the yearly accrued interest, (4) Income Tax
deduction at source on the interest thereon, wherever required and (5) Refund of Security Deposit
for disconnected supplies etc. are the main Application areas of this sub-system.
MIS Reports
Different cluster of MIS Reports generated by the System, helps us in Job planning, Manpower
planning, Smooth Operation, Decision making, Setting business priority, Close monitoring of
Consumers, Budgeting and Accounting, Assessment of financial and sales position etc.
Tariff Structure
The schedule of Tariff for the LT and HT Consumers are reviewed every year and awarded to
CESC by the State Electricity Regulatory Commission (SERC). In addition to the Tariff, the
structure of Govt. Duty on electricity charges are also modified from time-to-time by the State
Power Department and CESC arrange for collection of the same through the electricity
consumption bills.
While determining the Tariff Structure, SERC takes the following parameters as the main guiding
factors;
a) Cost of Power Generation, which includes cost of fuel, operational cost, proportional cost
for construction of Power Plants, etc.
b) Distribution cost, which includes cost of materials including the cost of Transformers,
Cables, etc.
c) Establishment cost, which includes salary of employees, cost for running different
establishments, cost of capital items like Computers, Furniture, etc.
d) Operational cost like maintenance charges of different assets and equipment, transport cost
etc.
e) Recovery of debts and re-payment of loans.
f) Amount of cross-subsidy to be allowed, from high-end to low-end Consumers, as a policy
matter and guide-line provided by the Central / State Govt.
g) Amount of subsidised electricity to Govt. (State & Central) establishments, Public Bodies,
Municipalities, Charitable Organisations, public & private Educational Institutions and
Hospitals etc.
h) Tariff of electricity to be imposed on Govt. and Public Body Offices, separately for the
establishments located within Municipal and Non-Municipal areas, depending on the
financial ability for making payment of the electricity bills.
i) Demand side management, through introduction of TOD Tariff for different Categories of
LT Consumers.
j) Demand side management, through introduction of Seasonal Tariff for HT Consumers.
k) Introduction of Pre-payment Meters for reducing the outstanding dues / debts of the Power
Distribution Companies.
Distribution Training Institute, CESC Limited
202
Category of Consumers
In the Tariff Structure, Consumers are classified in the following Categories depending on the
usage of electricity.
Sl.
No.
Tariff Defined on
the Type of Supply
1
2
3
4
5
6
7
8
9
10
11
12
LT
LT & HT
LT & HT
LT
LT
LT
HT
LT & HT
LT & HT
LT & HT
LT & HT
LT
13
14
15
16
17
18
19
20
21
Street Lighting
Short term Supply [for religious festivals, fairs, social functions etc.]
Emergency Supply
Power supply for Construction purposes
Single point bulk Supply to Co-operative Housing Societies
Common Supply to Industrial Estates
Sports Complex / Auditorium under Local Bodies
Metro Rail & Kolkata Tramways
Cold Storage
LT
LT & HT
LT & HT
LT & HT
LT & HT
LT & HT
HT
HT
HT
Time Zone
Classification
Normal
Peak
Off-peak
Peak
Off-peak
Normal
203
Time Zone
Classification
Normal
Peak
Off-peak
Normal
Peak
Off-peak
204
SYSTEM LOSS
A.
Component :
To any power utility, keeping down the system loss and / or containment of the same is a major
challenge.
In normal parlance, we call it T&D Loss, but as per the present guidelines, the utility needs to
measure the AT&C Loss also. For the purpose of arriving at AT&C Loss figures, the revenue
collection efficiency is given a weightage over T&D Loss.
T&D Loss comprises of Technical and Non-Technical Losses. While Technical Loss is primarily
due to improper load management, long LT lines, haphazard growth, inadequate investment on
T&D network etc., the Non-Technical Loss is the outcome of metering errors, billing errors and
pilferage of electricity. The pilferage (theft) of electricity is done by way of tampering the metering
arrangement(s) and / or by means of hooking / tapping from O/H and U/G network respectively.
B.
Methods Employed for Reduction of T&D Loss :
In order to bring down technical loss, our Company has made huge investments to revamp the
network adequately. Similarly, state of the art intelligent electronic meters have been introduced in
a phased manner starting from high-end consumers. Our age old Billing Software is continuously
upgraded as per requirement of Commercial Department and other allied departments to minimize
billing errors. In order to curb theft and pilferage of electricity, our Company embarked upon site
inspections on a war footing starting from 2000-2001 when the T&D Loss rose to an alarming
figure of 23%. Selected Engineers / Officers from almost all the divisions across the company were
either transferred or seconded to Loss Control Cell in 2001 to revamp the same. An Executive
Director was exclusively given the charge of taking tough measures in order to constrict theft of
electricity. Simultaneously, supervisory and non-supervisory staff were also transferred to the Loss
Control Cell and the onerous journey to bring down the T&D Loss figure started. This entire group
was also backed by Executives from Legal Department and recruitment of retired yet efficient
Police Officers as Security Consultants.
Initially, all our energy was directed towards removal of illegal hookings and tappings and
inspection / disconnection of tampered meters. Since CESC was using proprietary sealing system
on each and every energy meter for long, the above assorted group of Engineers / Officers were
sent to our Testing Department to hone the skill of identifying the seals which are not genuine but
tampered. Area-wise survey was undertaken based on the nature of establishment, be it industrial
or commercial or domestic. Such areas were identified with the knowledge backed by our
Engineers in distribution system who had to visit such places for the purpose of maintaining
supplies. Our billing database was also a good pointer to identify such areas based on consumption
patterns. The data from our Testing Department as to how many times meters of a particular
consumer are getting exchanged and for what reason, was another indicator.
This all out effort of ours started giving result from 2001-2002 onwards, but we felt the need of
knowing the process involved in each type of industry, viz., rubber, plastic, wire drawing, rolling
mills, heat treatment plants, tanneries, jute etc. We also deputed our engineers to know the
geography and topography of an area, market analysis of products, detection of multiple services /
meters etc.
C.
Course Correction Of Initiatives:
Enactment of the Electricity Act, 2003 gave the necessary impetus in curbing theft of electricity.
From end 2003, certain initiatives were taken to bring about radical changes in operation of Loss
Control Cell. This included blocking of service cutout, installation of cutout less service, seizure of
meters / appliances / motors etc., upon detection of unauthorised use of electricity, arresting the
Distribution Training Institute, CESC Limited
205
pilferers of electricity and continuous follow up with Police Authority for instituting cases at
Special Court. Apart from increasing our surveillance in order to disconnecting the tampered
meters or removal of hookings, Power Loss Audit Cell (PLAC) took up the challenging job of
auditing the street lighting supplies in order to garner lost revenue.
IT based surveillance was made order of the day. And for this purpose, the SLIM Software
developed in 2001-02 for monitoring cases disconnected by LCC was enhanced to capture various
facets of loss control activities while parallely many customized data banks were developed for
different types of industries. Usage of data from billing database kept at IT Department, CIS
database, metering database and MASD System were increased manifold so as to exploit the huge
data available with us more judiciously and productively.
D.
Auditing of DTRs in Pilfer Prone Areas:
Armed with the geographical and topographical knowledge of our licensed area about 30 odd pilfer
prone areas were identified. Out of these, 17 areas were earmarked to be the most pilfer prone
zones. Loss Control Cell took the decision of auditing the energy fed through the Distribution
Transformers located in these areas. Initially, 564 such DTRs representing about 10% of total no.
of DTRs installed in our system were selected and the cluster of consumers fed through these DTRs
were identified in a phased manner. While such clustered data were sent to our IT Department to
keep us informed about the summated billed units every month for these consumers, we started
collecting the monthly energy input to these DTRs remotely by way of putting energy meters at
these DTRs and taking help of GSM Modems. Other technical details from these Intelligent
Energy Meters were also made available through modems at our base stations. The results obtained
monthly, guided us to embark upon different strategies to combat theft of electricity.
As a direct fall out of the above energy audit exercise, many technical data of these DTRs are now
available which can be used by Mains, Planning and Sub-Station Departments in order to take
action for a more reliable distribution system.
Analysis of DTR-wise monthly loss figures backed by our experience at site in combating abuse of
distribution system revealed that in some areas meters need to be taken out of consumers premises
to road side kiosks (Meter Pillar Boxes) so that our meters and the LT Network going through the
lanes and by-lanes of the area do not easily fall prey to the pilferers of electricity. Obviously, the
socio economic condition of an area also helps in strategizing our moves. However, in a typical
O/H area, we felt the need of extending HVDS as a means to curb theft of electricity. The idea is to
eliminate hooking from O/H lines and giving supplies through MPBs from small DTRs put in
HVDS network.
The results of such auditing exercise not only vindicated our identification of pilfer prone zones /
areas, but also gave us a pointer that in order to combat the subtle changes in distribution
management, our focus has to be group-audit of a cluster of DTRs so that we may zero-in to the
deliverables more technically and tactically.
E.
Micro Audit
In all our Loss Control Cell Units, we have started micro audit exercise on large meter boards
catering to the energy requirement of commercial & high-end domestic consumers in affluent areas.
This exercise is carried out for a limited period of 15 days, unlike energy audit in DTRs where such
auditing is done month after month. This way, we have been able to extend our surveillance on the
affluent strata of our society in order to detect theft, replacement of faulty meters, as also
renovation of meter boards.
While the war against pilferage of electricity is continuing unabated, active participation of our
colleagues from other departments has given us the necessary strength to take this menace head-on.
It is indeed a matter of great satisfaction that T&D loss in 2007-08 has been reported to be less than
14% and we have taken a vow to reduce it further.
Distribution Training Institute, CESC Limited
206
207
Remote Terminal Unit (RTU): This is the main hardware responsible for interfacing process
signals (input / output).
Communication Media: The media over which the SCADA data are transported between
RTUs and Master Control Centre.
Master Control Centre: Station MIMICs along with network interconnections are displayed at
Master Control Centre. From Master Control Centre, commands can be generated to operate
circuit breakers at different stations selectively. Many management information service (MIS)
related reports can be obtained from Master Control Centre Servers.
1.1. Remote Terminal Unit (RTU)
1.1.1. RTU Functions:
A. Data Acquisition: Power system signals at different stations are acquired from the field
and fed to the RTU hardware. These signals are broadly classified into two categories.
i) Digital Indication: Circuit breaker status, Isolator status, Protective Relay status,
Metered pulse from energy meters etc. are considered as Digital indications. Signals of
digital indication have two states (0 and 1). Suitable interposing relays are used. The
potential free contacts of the interposing relays are connected to RTU for processing.
The interposing relays are installed inside respective relay control panel. Different types
of digital indications are described below :
Single Indication : Only 1 input channel is utilized. e.g. : isolator status.
Double Indication: 2 input channels are utilized. Failure of any channel input will
indicate error in RTU. Faulty state can be suppressed during change of state. e.g. :
circuit breaker status.
Fleeting Indication: The contacts which are of fleeting nature can also be sensed by
RTU. Example: protective relay output contact.
Metered Value: Pulse inputs from energy meters can be counted by the RTU, which
facilitates energy / demand monitoring.
ii) Analogue Measurands: Power system parameters like Active power, Reactive power,
Current, Voltage, and Frequency are categorized as Analogue measurands. Suitable
Transducers operated of current transformer and potential transformers are used for
converting the power system parameter to milliAmps. Transducers with uni-polar /
bipolar and with several range of outputs (e.g. -2.5 - 0 - 2.5 mA, 0 5 mA, 4 - 20 mA)
are available. The Transducer output is fed to RTU for processing. These transducers are
installed inside respective relay control panel.
B. Supervisory Control: Remote operation of circuit breaker is possible through HMI
terminals located at Master Control Centre and also from local operator console at RTU site.
On receiving command from operator, RTU operate the selected circuit breaker via
interposing relay. This feature is available but not regularly used in CESC.
All the signals between relay control panel & RTU are fed via MDF ( Marshalling
Distribution Frame ) for operational convenience.
1.1.2. RTU Hardware:
Input / output interface modules
Central Processing Unit
Telecontrol Unit
208
DIGITAL
INPUT
MODULE
DIGITAL
OUTPUT
MODULE
SYSTEM BUS
PROCESS
ANALOG
INPUT
MODULE
Central
Processing
To
Master
Control
Centre
Tele Control
Unit
209
210
MMI 2
TCS 1
MMI 4
RTC 1
ADM 1
RTC 2
ADM SP
TCS 1
MMI 3
MMI 1
TCR 1
GPS
CLOCK
TCS 1
TCS 2
T
C
B
T
C
B
T
C
B
T
C
B
TCR 2
T
C
B
T
C
B
T
C
B
T
C
B
Communication Media
RTU 1
Legend
RTU 2
RTU 18
211
To Master
Control Station
RTU - 1
3 Serial Interfaces to
Master control
station
To Master
Control Station
RTU - 2
SAT 230
To Master
Control Station
RTU - 4
RTU - 3
To
Master
Control
Station
RTU - 5
To
Master
Control
Station
RTU - 6
LAN
RTU TEST CENTRE
(Auckland Sq. CCC)
212
UNMANNED STATION
RACK
MANNED STATION
PC XT
MODEM
MODEM
INTERFACE
RACK
MIMIC PANEL
FIELD
F1
F2
F3
F4
F1
F2
F3
F4
2. Intermediate Design : The Rack and the Mimic panel at the manned end were replaced by a
PC with appropriate software for Man-Machine-Interface.
UNMANNED STATION
RACK
MANNED STATION
MODEM
MODEM
MONITOR
INTERFACE
FIELD
F1
F2
F3
P
C
A
T
F F F F
1 2 3 4
F4
213
3. Existing Design : The Centralized Rack based Remote Terminal Unit (RTU) was replaced with
a distributed architecture using low cost Intelligent Electronic Devices (IED)
UNMANNED STATION
MANNED STATION
PC AT
MODEM
DISTRIBUTED
ADAM
MODULE
485 TO 232
CONVERTER
MODULE
RS 485 BUS
MODEM
MONITOR
P
C
A
T
F F F F
1 2 3 4
FIELD
F1
F2
F3
F4
OPERATORS KEYBOARD
C. Communication Infrastructure
Modern distribution system practice demands rapid and reliable information exchange among
Substations, Load Dispatch Centre, Engineering offices, Regional Commercial offices and Loss
Control Cells. A modern state of the art Communication network is therefore absolutely essential to
provide pipe lines for transfer of information (both voice and data) related to various automation
processes e.g. SCADA/EMS, LOSS CONTROL & CRM. Towards this end, CESC Limited has
developed a large Telecommunication and Networking infrastructure of its own which has been
commissioned and is being maintained round the clock by a group of well trained professionals.
With the induction of various latest technologies, the following different types of Communication
systems are available
There are two different types of Transmission Network to transport the traffic of this Voice
Network.
Point to Multipoint TDM/TDMA Microwave Communication system
With the growing demand for increasing & reliable telephone & data communication the process of
migration from old analog systems via copper media to modern digital state of the art
communication system started in the early nineties. In the first phase a point to multipoint Digital
Microwave Radio system based on TDM/TDMA technology in 2 GHz. band of radio frequency
spectrum was installed.
The system was procured from SR Telecom, CANADA and is in operation since 1996. The system
consists of
(i)
1 No. Central Station including Radio Equipment, Control Modules and Voice/Data Traffic
Channel modules.
(ii)
26 Nos. Outstation equipment with Radio equipment, Control Module and Voice/data
Traffic Channel module.
214
(iii)
(iv)
1 No. Omni directional Antenna at the Roof Top of Central Station, i.e. CESC House.
Grid Parabolic reflector Antenna of different sizes at different outstations located at
different offices, Generating Stations, Substations & Distribution Stations.
The entire network is managed, configured & monitored from a Network management System
(NMS).
The system contains the following traffic
(i)
200 nos. Telephone line
(ii)
16 Nos. EPABX Tie line
(iii) 10 Nos. Data Switching equipment
STATION : B
PATCH
CORD
30
CH
16
PCM
MUX
30
FDF
FDF
PIGTAIL
ATTN.
TJB
34
T Mbps
E
CH
H
L
TJB
30
PCM
MUX
16
SJC
O.F CABLE
16
16
30
Optical Line Terminal Equipment (OLTE) - It converts the 34 Mbps Electrical signal to Optical
signal.
215
Higher Order Multiplexer (HOM) - Digitally multiplex 16 nos. E1 (2.048 Mbps) PCM input
signals from E1 Multiplexer and the output is 34.368 Mbps (E3) electrical signal.
30 Channel PCM MUX - Primary level digital multiplexer which multiplexes a total 30 nos. of
Voice and/or Data channels and the output is E1 (2.048 Mbps) digital signal.
Straight Joint Closure - Underground Joint Closure for straight jointing of O.F. cable in the run.
Terminal Joint Box (TJB) - Joint Box for termination of O.F. cable at a terminal station.
Fiber Distribution Frame (FDF) - Distribution frame mounted with suitable adaptor for
interconnection between equipment and fiber. At one end of the adaptor, pigtails (with connector at
one end and bare fiber in the other end) from TJB are connected and at the other end Patch cords
(with connectors at both ends) from equipment are connected.
The Microwave & Optical fiber based transmission systems enable the transportation of the
following infrastructures.
1. Corporate Telephone Network:
The heart of the Corporate Voice network is a high capacity Switch (EPABX) from Avaya Global
Connect Limited located at CESC House which is the Corporate Head office as well as the Central
Load Dispatch Centre. Around 250 extension lines of this Switch are distributed all around starting
from Engineering and Commercial offices to Substations, Distribution Stations, and Regional
Depots. EPABX systems of other locations are integrated to these central EPABX over E1 and
E&M to form an integrated omnipresent Corporate Voice network which is schematically shown
below.
Station - A
Station - B
M
W
Station D
TRANSMISSI
ON
CENTRA
O.F.
L
EPABX
AT
MEDI
A
EPABX
EPABX
Direct Extension
line
Station C
EPABX
EPABX
2.
Data Network for SCADA
(a) For Point to Multipoint SCADA system, to improve reliability, three different media (1 active +
2 stand-by), namely Microwave, Optical Fibre and copper Cable are available to transport data
from a RTU to the Central Station. The Data is serial (RS 232C) and having a format of
1200(baud), Odd (Parity), 8 (bits) and 1 (stop bit) & 19200(baud), Even (Parity), 8(bits) and
1(stop bit).
216
(b) For Point to Point SCADA, two options namely copper Cable or Optical Fibre are used for
transportation of data. The format of the serial (RS 232C) Data is 9600(baud), none (Parity), 8
(bits) and 1 (stop bit).
3.
Corporate Data Network
With the induction of latest Information Technology applications in various business processes and
to keep pace with sustained growth & modernisation, flow of information between various units of
the organisation is absolutely essential. A Corporate data network has been developed in this
respect which has deployed the latest technological advances in networking in different phases.
Migration from low speed copper cable based data links to a Packet Switched Data network (X.25
protocol based) started from early nineties. The network is schematically shown below.
PAD
PAD
PSE
PAD
PAD
An X.25 Switch located at the corporate office has a no. of network ports which are connected to
remote station equipment. At the remote nodes i.e. at our different Regional Offices, Engineering
Offices and IT centre, Packet Assembler Dissembler (PAD) equipment are installed. Network
Ports of all these PADs are connected to the network ports of the Central Switch over Microwave
and Optical Fibre system. Computers at the nodal offices are connected to the serial ports of the
PADs. Few Serial ports of the Regional Office Servers are also connected to the PAD ports. There
may be two different types of connection
(a) Switched Virtual Circuit (SVC):
(i) For accessing the Regional Office Servers from Computers located at different offices.
(ii) IP based applications are also supported over this serial connection by using Point to Point
Protocol. The main application is File Transfer among different host machines in simultaneous
multiple sessions.
(b) Permanent Virtual Circuit (PVC): This is a permanent point to point connection between two
computers for dedicated, secured file transfer operation.
The interconnection of the X.25 Data Network with the carrier system (Microwave Network) is
shown below.
217
MW
O/S
DATA NMS
PAD
SR
SR TELECOM
TELECOM
9000 PC
9000 PC
HP OPENVIEW
HP OPENVIEW
18
X.25
S
W
I
T
C
H
ROUTER
MW
O/S
MW
C/S
16
2
1
PAD
SR
SR TELECOM
TELECOM
MW
O/S
PAD
DTU
SR
SR TELECOM
TELECOM
X.25 Port
PAD
INBRIDGE
3630
DTU
INBRIDGE
3630
PAD
218
District
Southern District
Overhead
Overhead
Central District
Underground
Underground
Northern District
Overhead
Howrah District
Overhead
Serampore District
Overhead
Underground
Overhead
10
Overhead
Sl
No.
Size mm2
x No. Of
Cores
Guiding
IS Code
Type Of
Insulation
25 x 3
1554 Pt I
PVC
75
70
Service
70 x 3
1554 Pt I
PVC
1357
130
Service /
Distributor
150 x 3
7098 Pt I
XLPE
255
294
Service /
Distributor
240 x 3
7098 Pt I
XLPE
333
402
Distributor /
Service
400 x 4
7098 Pt I
XLPE
426
542
Feeder
*Current Rating In
Amps
In Ground In Air
End Use
219
Cables are laid to enable load growth and also for obtaining flexibility of supply in case of
outages.
Cable laying job can be divided into two areas A) Fixing of Route and B) Process of
laying.
A) Fixing of Route
a) Route Fixation
Cable route should be as straight as possible.
Width of route should be adequate to allow jointing of higher size cables.
As far as possible crossing of major roads, tram tracks or rail tracks should be avoided.
Footpath must be used as much as possible.
b) Plan Sanction
After finalizing route, a detailed plan of route with all relevant details must be
prepared.
The plan has to meet the approval of the concerned Municipal Authority.
The plan must be sent well in advance to above authority to enable completion within
target period.
For PCP (Public Common Passage) written permission of co-owners of plots / buildings
along that passage is required.
c) Trial Pits
On receipt of sanction, an intimation is to be sent to appropriate authorities giving
tentative programme of work.
Trial pits are to be dug approx at 10 meters intervals or less as necessary.
This determines exact cable alignment to be followed during laying
Thus creating minimum interference with underground obstructions and installations
of other agencies.
220
B) Process of Laying
a) Pipes and Pipe Laying
Pipes used now for cable laying below ground are made from HDPE.
Pipes are laid for crossing roads, tram tracks, petrol pumps garage entry or entry to
multistoried buildings.
For wide roads pipe laying is done by excavating half the road width at one time.
For smaller roads and lanes while open cut is adopted traffic should be diverted.
Road crossing operation should preferably be done at night.
Pipes are also required to be laid inside consumers premise by consumer, if location of
service termination is away from kerb edge.
Pipes are also used as support and protection from external damage where a) cables
emerging from underground and to be terminated on to Overhead Conductor at a pole
and b) where cables run vertically. These pipes are made of G.I.
The table gives an idea of the selection criteria of pipes
Sl
No.
Cable Size
(mm2)
Road Width To
Be Crossed
Material
Diameter Of
Pipe (mm)
Pipes for
Pole Box
Cable
400
All Roads
HDPE
150
----
240
All Roads
HDPE
100
G.I / 75 mm
150
All Roads
HDPE
100
G.I / 75 mm
70
HDPE /
G.I
100
G.I / 50 mm
25
HDPE /
G.I
75
G.I / 50 mm
b) Trenching Work
The CESC notice board should be deployed at site and work area should be cordoned off.
Depth of trench should not be less than 75 cm and 60 cm wide.
The trench should not be continuous to enable pedestrian crossing.
Holes should be bored into the earth at uncut pedestrian crossings.
Excavated earth should be retained besides the trench on either side.
Exposed cables and pipes should be suitably supported.
In case of damage to installation of other agencies they should be immediately informed.
An attempt should also be made for temporary repairing of damaged installations.
Standby pumps and shuttering planks are required for exigencies.
c) Laying Procedure
Before placing drum at site the following needs checking - condition of drum, cable size,
cable length and integrity of cable end sealing.
The drum is then placed around spindle and lifted by Jacks, both of suitable capacity.
A few lashings of a manila rope of adequate strength are made around outer sheath of cable
end.
Cable payout is done by rolling drum in direction opposite to marked Roll This Way.
Overlapping with any existing cable should be maintained as per jointing instruction.
Upon completion, the cable is covered with 150 mm loose soil free of rubbles.
Distribution Training Institute, CESC Limited
221
Tiles are then placed, over this surface, butting each other.
Backfilling is done with excavated soil and rammed at different levels.
Upon completion, necessary restoration order has to be made for municipality and work
card for updating the 50ft plan.
LT Tiles
The tiles used in our system are made from Reinforced Cement Concrete.
The reinforcement is done by steel wire cage having wire thickness12 SWG.
The concrete is mixed in proportion 1:1.5:3.
The colour of tiles is RED.
This differentiates from tiles of other voltage grades and other agencies.
The dimensions of the tile used are: 345 mm long x 180 mm wide x 25 mm thick
The front protruding head has a radius R50
While the rear has a cavity of radius R52 for easy insertion of head.
New Service Installation
The procedure of service installation can be divided into five subgroups namely:
A) Inspection for service;
B) Laying of service cable;
C) Fixing of meter board;
D) Termination of cable at meter board; and
E) Tee Jointing of cable.
A) Inspection For Service
In Areas Served By Overhead Network:
Selection between Overhead or Underground mode of supply is done weighing both
economic and technical parameters.
In O.H area if consumer insists on U.G supply then whole cable is chargeable.
If width of road is less than 3.0 meters, then U.G service is given.
If load requisition is more than 15 kw, then U.G service is provided.
In Areas Served By Underground Network:
The size and location of Distributor cable from which service is to be tapped is noted.
If required, the Distributor has to be strengthened keeping in mind future load growth.
General Requirement:
If consumers load requirement is more than 40 kw, then dedicated service through CT
metering is done.
A clear space 80 cm wide should be available in front for installation up to 4 way meter
board and 1.2 meters for multiway meter boards.
Consumers Main Switch must be within 3 feet from our meter board and always in same
room.
Consumer has to be informed to make meter board wall 10 thick, if not done.
Length of cable required in MP, PCP, and PP should be clearly defined.
Cable route is kept as short as possible and free from obstructions.
Selection of the Correct Cable Size for Service
The size of cable is selected on basis of load requisitioned by consumer.
The selection of Cutout to be installed is also dependant on cable size and load.
222
Range Of Load
Cable Size
Cut-Out size
0 Less than 25 KW
25 mm2
25 KW Less than 40 KW
70 mm2
150 mm2
240 mm2
223
Loops Max
Current
Rating
32
Loops Safe
Current
Rating
27
1 ph, 5/20 A
3.1 to 4.0 kw
10 mm2 s/c Cu
72
60
1 ph, 10/40 A
4.1 to 12.0 kw
---
---
3 ph x 10/20 A
12.1 to 36.0 kw
10 mm2 s/c Cu
---
---
3 ph x 30/60 A
36.1 kw and
above
70 mm2 s/c Cu
235
205
Static CT
95 mm2 s/c Al
180
150
----
For Temporary
Lighting
16 mm2 s/c Al
50
40
----
Sl
No.
Range of Load
Suggested Loop /
Bus Bar cable
Up to 3.0 kw
Meter Size
224
225
o Al Bus Bars of size 50mm x 12mm, and length to suit 6 / 4 way box are fixed with top and
Neutral studs.
o Hylam sheet Phase separators are fitted over each bus bar with L shaped Clamps.
o Rewireable Cu fuse wires are fixed between the L Contacts at Top and Bottom studs.
Earthing Practice
All pillar boxes body are earthed.
Two nos. 4.5 mtr long x 50m dia G.I pipes are sunk into holes dug with the help of earth
Auger.
The holes are 600 mm apart and dug 450 mm away from pillar box.
Two nos. 95 mm2 S.C cables are bolted at the ends of the Angle Iron Frame within pillar
box.
The Neutral Conductor is earthed only at Feeder pillar box.
Here the two earthing cables are bolted to the Al Bus Bar where the Neutral conductors are
terminated.
Neutral earth and body earth must be on opposite sides of box and separated by one meter.
Nowhere in underground system are the Neutral and cable armour interconnected.
Fig 2 & 3 illustrates the installation of 6 way pillar along with earth arrangements.
Figure 2
Distribution Training Institute, CESC Limited
226
Figure 3
Earthing In Joints
The function of Continuous Earth Wire in overhead system is performed by armour wires of
cables in underground system.
Hence during jointing it is imperative that correct installation method is adopted for earth
clamp and collet and the clamps are connected by the requisite earth lead provided in kit.
In tee jointing, armour of both the main and branch cables are to be interconnected by
means of clamps and leads.
Earth Lead Sizes for Joints
Sl No.
1
2
3
4
5
25 mm
70 mm2
150 mm2
240 mm2
400 mm2
227
LT Jointing
There are three types of cable jointing done.
A) Straight Through Jointing.
Here crimping is done when jointing Aluminium conductors.
However at a few instances, solder basting is done when Cu & Al conductors are jointed.
Crimping of Conductors
o Aluminium crimping ferrules or In-Line connectors are made as per IS 8308
o Salient features of the process involved in crimping are:
The conductor surfaces(s) are to be thoroughly scrubbed using emery cloth.
The inner surface of the barrel of ferrule will have to be thoroughly scrubbed also
using emery paper.
Corrosion Inhibiting grease based on Lithium and having conducting properties,
popularly known by its trade name Pentex A is applied over these scrubbed
surfaces
The ferrule is inserted over the conductors placed in line and with a defined gap in between.
The correct Die, appropriate to conductor size, is selected for Ratchet type tools.
For Rotary tools, the Die heads are rotated till the correct size is set.
Crimping is started from the edge of conductor cut which is inserted inside barrel.
The second crimp is given on the other conductor edge.
After completion of crimping, the sharp edges are smoothened away and excess grease
should be wiped away.
Recommended Gap Between Conductors and Number of Crimps Required For Each
Conductor Size
Conductor Size In
mm2
Gap In mm
No. Of Crimps
Required On Each
Side
25
70
150
240
400
228
Item
Sl. No.
Item
Crimping Thimbles
Emery Paper
Plastinet Mesh
Cleansing Solvent
Earth Leads
Cleansing Cloth
10
Polyurethane Compound
PVC Tape
11
BOPP Tape
Insulating Pads
12
Sl No.
1
2
3
4
5
Cable Size In sq mm
25 x 3 C
70 x 3 C
150 x 3 C
240 x 3 C
400 x 4 C
Kit Nomenclature
SLA 4 / CESC
SLA 6 /CESC
SLA 8 / CESC
SLA 11 / CESC
SLA 13 / CESC
The above kits also contain the Instruction Manual showing steps to be adopted for making
a correct joint.
B) Tee Jointing
Here a married joint is made between conductors of tee cable and main cable.
This is adopted for service connections
Materials Required for Making A Tee Joint
Sl.
No.
1
2
3
4
5
6
7
Item
Sl. No.
Item
Eyre 7 Flux
Alca P solder metal
White Cotton Tape
Cleansing Solvent
Cleansing Cloth
Emery Cloth
PVC Tape
8
9
10
11
12
13
Insulating Pads
Earth Clamps with Collets
Plastinet Mesh
Earth Leads
Polyurethane Compound
BOPP Tape Rolls
o The above items except those in Sl. Nos. 1, 2 & 3 are available in Kit form.
o The kits have been specially designed for use with 25 mm2 service cable.
229
Branch Cable
25
70
150
240
25
25
25
25
Kit Nomenclature
T-3 / Mesh
T-7 / Mesh
T-14 / Mesh
T-23 / Mesh
The above kits also contain the Instruction Manual showing steps to be adopted for making a
correct joint.
Kit Design
o In a Kit the requisite quantity is pre-assembled.
o Kits are made of light weight material and as compact as possible.
o Kits are portable with easy availability of all items.
o This ensures minimum wastage, better quality control.
Married Jointing Of Conductors.
o The salient features of the process are:
The outer strands of conductors of service cable are flared.
The inner single strand is wound round the core where the insulation is cut to reinforce the
base.
Cotton tape is wrapped around the insulation cuts of both service and distributor cable cores,
to serve as protection during soldering.
The conductors of distributor cable are first Tinned using Alca P and Flux.
The flared strands of service cable cores are divided in two parts.
One part is wound in clockwise direction and another in anticlockwise direction around the
tinned conductors of distributor after matching of phases is ensured.
Pour Alca P over the married joint.
Flux is then applied once more over this joint.
Alca P, metal maintained at a liquefied temperature of 300 330 degC is poured so as to
ensure basting.
Basting continues till metal cools down to semi-liquid and then to viscous stage.
The excess metal is wiped off by cotton tape.
After soldering is complete the cotton tapes are removed.
Evostrip Compound should be applied over conductors at their insulation cuts.
Figs 5 & 6 illustrate the winding of strands to form a married joint.
Figure - 5
Distribution Training Institute, CESC Limited
230
Figure - 6
C) Cable Termination
o The conductors of different cables are terminated using Al Crimping Thimbles.
Aluminium crimping thimbles are made as per IS 8309.
The requirements for crimping have already been explained earlier.
Termination can be of two types.
At Meter Board
explained earlier
At Pillar Box - where
o A cable coil is retained at base of pillar box for future use.
o The cable portion kept in vertical position against the 500/300 Amps frame is terminated at
the studs of the frame.
Pillar Box termination consists of two parts
a) Armour termination and b) Conductor termination.
Heat Shrink Components are used at both locations.
o Al crimping thimbles are used for terminating the conductors on to the studs of fixing
frame.
o Cu braids and Cu mesh are used for maintaining earth continuity between cable armour and
ground through pillar box frame earthing.
o The heat shrink components, crimping thimbles along with earthing accessories are
available in Kit form for cable sizes 150, 240 and 400 mm2.
o The above kits also contain the Instruction Manual showing steps to be adopted for making
a correct termination.
231
Overhead
Type of Pole Used
Poles are manufactured vide IS 2713.
Poles are of two types i) Stepped Poles and ii) Swaged Poles.
We procure Swaged poles vide our drawings which is in line with IS- 2713.
Poles used for LT Mains has a specification equivalent to 410SP38.
Planting
Outside Diameter
Overall
Approx
Depth in
Length of Section
&
Length
Weight
Ground
Thickness of Section
Working
Load
Bottom Middle
Top
200 kgf
mm
mm
mm
assuming
160 kgs
9.5 mtrs 1.8 mtrs
5.0
2.25
2.25
165.1
139.7
114.3
Factor of
mtrs
mtrs
mtrs
X 4.85
X 4.5
X 3.65
Safety 2.0
In our procurement drawing some of the thickness have been rationalized for easy procurement and
better quality check.
Pole Erection
Bill of Materials Required For Pole Erection
Item
Quantity
MS Pole
01
Bricks
2 nos.
Khoa
0.2 cu.m
Soorky
0.1 cu.m
Lime
0.05 cu.m
Poles installed in our system have three nomenclatures namely:
Description
Illustrating
Sl
Nomenclature
Figs
No.
Bottom
1
2
3
Tangent Pole
Sectional Pole
Terminal Pole
Middle
Top
1
2
3
Figure - 2
Distribution Training Institute, CESC Limited
232
Figure -3
233
Figure - 4
Figure-5
234
Pole Earthing
All Poles must be Earthed
Bill of Materials for Pole Earthing
Sl
No.
1
2
3
4
Item
Quantity
50 mm C.I. Pipe
No.4 G.I. Wire
! x MS Bolt & Nut
1 x MS Bolt & Nut
1 no.
1.2 kgs
1 no.
1 no.
Method of Earthing
Insert a 5 mtr. long No. 4 SWG GI Wire through PVC pipe.
Connect one end of wire to a 50 mm dia C.I Pipe.
Sink pipe to a depth of 4.0 meters below ground at 1.0 meter away from Pole with the aid of
Pole Auger.
Connect other end of Wire to Earth Terminal Block fixed on pole.
Connect the Continuous Earth wire to Bolt of Shackle plate to maintain earth continuity with
pole.
Fig 6 illustrates the installation of Pole Earthing procedure.
Figure - 6
Distribution Training Institute, CESC Limited
235
Protection of Poles
A) Painting
All new manufactured poles are to be protected against corrosion.
The external surface is to be de-rusted.
Black Bituminous paint is applied throughout the outer surface up to depth of burial.
The remaining portion is painted by a coating of Red oxide paint.
Erected poles must be painted first by Red Oxide, then with Aluminium paint.
B) Muffing of Poles
Muffing is to be done on all steel poles after erection.
Muffing stops corrosion of pole base and subsequent breakdown.
The outer surface of pole base has to be thoroughly derusted.
A concrete mixture consisting of inch stone chips, coarse sand and cement mixed in ratio
4:2:1 is to be used.
Concrete should cure for 07 days, with water being sprayed twice daily.
The muffed surface should be lapped with a coating of cement slurry and polished.
The top should be sloped to prevent water accumulation.
This slope must have a flush finish against the pole surface.
The angle of the flushed slope should not exceed 45 deg with vertical.
Fig 7 illustrates the typical muffing.
Figure - 7
C) Reinforcing of Poles
236
Figure - 8
Different Types of Stay Arrangements and Their End Uses
A Stay is a device installed to maintain the mechanical stability of the overhead line.
It exerts a force opposing the resultant tension of a line upon completion of installation.
A Stay is installed on Angle (Tangent) pole, on Terminal pole, or on Sectionalizing pole.
However, in an Urban Suburbs like in our case, where the overhead network is increasing,
there exists little scope for installing a standard Stay.
A resolution of force tension on Stay will show that the best angle for a Stay is 45 deg.
So, various types of Stays have been devised and also adopted in our system.
Some of the Stays along with their end use and sketches are enumerated below:
Sl
No.
a
Types of
Stays
Line Stay
Strut Pole
Stay
c
d
e
f
End Use
This is the standard stay used where space is
available.
Sketch
Fig 9
Fig 10
Fig 11
Fig 12
Fig 13
Fig 14
237
Figure-9
Figure - 11
Figure-13
Figure-10
Figure-12
Figure-14
238
Trade
Name
Size of
Conductor
Recommended
Maximum Current
Loading in Amps
Sectional Area
of Aluminium
Weight in Kgs
Per 100 Meters
1
2
3
Raccoon
Ferret
Squirrel
6 / 1 / 4.09 mm
6 / 1 / 3.00 mm
6 / 1 / 2.11 mm
268 A
180 A
120 A
78.83 mm2
42.41 mm2
20.98 mm2
31.8
17.1
8.5
The End Use and the Recommended G.I Earth Continuity Wires are tabulated :
Types of Insulators and their use
Name of
Sl.
Size (SWG) Of G I Earth
Size Of
Type of End Use
Main Line
No.
Continuity Wire
Neutral
Conductor
Main Line
Raccoon
Ferret
Spur Line
Ferret
Squirrel
Squirrel
Squirrel
Sl.
1
2
3
Squirrel
Squirrel
There are nine types of Insulators used in our system and their end use are tabulated below:
Type of Insulator
Small Reel Insulator
Large Reel Insulator
Egg Insulator
End Use
Carrier for 10mm2 Service cable
Carrier for 16 mm2 Service Cable
Installed on Main Line Device between
Continuous Earth wire and Neutral Conductor
in Delta Configuration
4
Guy Insulator
Used after Large Straining Screw on 4/8 GI
Wire at Terminal Pole
5
Small Shackle
Used at Service Ends and on Sectional /
Insulator
Terminal Poles for Squirrel / Ferret
Conductors / continuous Earth Wire
6
Large Shackle
Used on Sectional / Terminal Poles for
Insulator
Raccoon Conductor.
7
EP -53
In Line / Tangent Pole with less than 5deg
Angle, for Squirrel & Ferret Conductor
8
Round Head Insulator
In Line Pole / Tangent Pole with less than
5deg Angle, for Ferret & Squirrel Conductors
9
Large Pin Insulator
In Line / Tangent Pole with less than 5deg
Angle, for Raccoon Conductor
Use of Different Joints, Device and Jumper
Use of Al Binding Wire
Material
HDPE
HDPE
HDPE
Brown Glazed
Porcelain
White Porcelain
White Porcelain
White Porcelain
White Porcelain
White Porcelain
239
Number of Turns
Raccoon
Ferret
Squirrel
7
7
5
Figure - 15
Distribution Training Institute, CESC Limited
240
Figure - 17
241
Figure - 18
12 pairs
9 nos.
Item
Span (s)
Ferret
3 span length
Squirrel
2 span length
Quantity
As per Span Length
2 kgs
1.2 kgs
242
Quantity
3
1
1
Lump Sum
One pack
If Required
Quantity
2
3
4
5
8
4
12
12
6
7
1 kg
kg
Figure - 19
Distribution Training Institute, CESC Limited
243
Installation of Insulators
Install the relevant Insulator as per the pole and conductor.
Use of Tools and Tackles for Stringing Conductors
Apply tension on the conductor being drawn by Sisal Rope;
Ferret Conductor is drawn with help of Single Pulley;
Raccoon Conductor is drawn with help of winch and two Pulleys;
Tie the conductors with the Insulators by 14 SWG Al Binding Wire;
Stringing In Delta configuration
R&Y Phases are drawn first simultaneously followed by B Phase Conductor.
Neutral and Earth Conductors are drawn after that followed by Street light
Conductor.
Device on Delta Configuration
Provide Main Line Device made from No.8 G.I wire to isolate Neutral And Earth.
Fix Device from 2 meters away from pole and at every 5 meters interval.
Earthing of Neutral Conductor
On Radial Distributor over a span length of10 spans, further Neutral Earthing is required.
This eliminates the chance of floating neutral in case of snapping.
A hole is bored into soil by means of earth Auger.
A 50 mm2 S.C Insulated cable is terminated on to a telephone Bracket.
This Bracket is then clamped around a 2 Dia x 4.5 mtr. long G.I pipe.
The pipe is sunk to a depth of 6.0 mtrs.
The top of pipe should be 1.5 mtr. from the soil surface.
The cable is then drawn through another 2 dia G.I Pipe
This pipe is clamped on to pole by Saddle.
The free end of cable is tied to Neutral by Binding with No. 4 Al wire.
The fig 20 illustrates the method of Earthing.
Figure - 20
Distribution Training Institute, CESC Limited
244
Material
2 HDPE Bend
1 no.
19
2 G.I Bend
1 no.
20
2 Telephone Bracket
1 no.
21
Star Plate
1 no.
22
5
6
2 Jam Nut
G.I Stay Hook
3/8 x 10 Straining
Screw
1 no.
2 nos.
23
24
1 no.
25
Small Shackle
2 nos.
26
Multiple Connector
2 nos.
27
10
Stay Hook
2 nos.
28
11
2 nos.
29
12
Al Binding wire
0.8 kgs
30
13
3.5 mtrs
31
14
15
16
17
18
Neutral Disc
Lead Seal
Sand
PhilPlug
No.8 G.I wire
1 no.
3 nos.
4 kgs
0.075 kgs
1 kg
32
33
34
35
36
Sl
No.
Quantity
Sl No.
Fixed Quantity Materials
Quantity
Material
10 mm2 Al
Crimping Socket
Wooden Plug
Toughset B
Compound
6 x 5/8 MS Bolt
& Nut
4 x 14 No. Screw
x 7 No. Screw
C Bracket and
Back
DMC Cut
4 x MS
Earthing Clamp
9 x 2 G.I Short
Piece
20 mm Reel
Insulator
G.I Cleat
1 x G.I bolt &
Nut
x No.8 screw
Cement
Notice Plate
Iron Tacks
2 way M/Board
There are two types of cables in use for providing service connection
The technical details are given in table:
Size
Insulation
Conductor
10 mm2 x 2 C
16 mm2 x 4 C
Aluminium,
stranded
Aluminium,
Stranded
Current
Rating
47
51
Quantity
4 nos.
6 nos.
1 unit
4 nos.
4 nos.
4 nos
1 set
2 nos.
1 no.
1 no.
15 nos.
4 nos.
4 nos.
8 nos.
2 kgs
1 no.
4 nos.
1 no.
Relevant IS
Code
1554
Pt. 1
1554
Pt. 1
245
Initial Activity
Collect meter and service material.
Inspect applicants details from paid bill against job slip.
Check meter-board wall for requisite thickness of 10.
Identify and check position of applicants Main Switch.
Check whether applicants installation is ready.
246
Figure - 21
Figure - 22
Figure - 23
Distribution Training Institute, CESC Limited
247
Figure - 24
Figure - 25
248
Figure - 26
Application of I.E. Rules
Some of the IE Rules which are applicable in our system while stringing LT / MV lines are in a
nutshell:
A) Rule 74:
Minimum Breaking Strength of any Overhead Conductor shall not be less than 350 kgs.
However if span is less than 15 meters or on consumers premise this Breaking Strength
should not be less than 150 kgs.
B) Rule 75:
There shall not be more than 02 nos. joints on any O/H Conductor in any One Span.
The ultimate strength of a joint shall not be less than 95% of the ultimate strength of the
conductor and electrical conductivity same as the conductor.
C) Rule 77:
Minimum Clearance Required Above Ground of the Lowest Conductor / Service Line
For lines erected across a street
For Low and Medium Voltage Lines 5.8 metres;
For High Voltage Lines 6.1 metres;
Distribution Training Institute, CESC Limited
249
250
SYSTEM OPERATIONS
Generation Details
Station
BBGS
SGS
TGS
NCGS
TOTAL
Terminal Voltage
(kV)
16.5
10.5
10.5
33
Installed Capacity
(MW)
250 x 2
67.5 x 2
60 x 4
100 (derated)
Total (MW)
500
135
240
100
975
IMPORT
132kV
132/33kV
NCGS
TGS
SGS
33kV
33/20kV
33/11kV
11kV
33kV
CONSUMER
11/0.42kV
20kV
CONSUMER
33/6kV
CONSUMER
6kV
6/0.42kV
CONSUMER
6/3.3kV
400/230 V
CONSUMER
3.3kV
CONSUMER
Nearly 9% of this total generation is consumed by station auxiliaries and the rest is released
as Sent Out.
Average Summer peak demand of CESC system is 1400 MW. We therefore need nearly 510
MW from outside agencies to meet this demand.
Bulk of this power is imported from WBSEDCL and the rest from other power utilities
through various trading agencies.
251
Import Points
Receiving
Station
Southern
Corresponding
WBSETCL Substation
Botanical
Garden
Kasba
Prinsep Street
Belur
Titagarh
Howrah
Kasba
Belur
Titagarh
170
75 MVA x 2 +
125 MVA +
50 MVA X 2
= 375 MVA
50 MVA x 3
65 MVA x 2
220
130
40
CESC OVERVIEW
252
Islanding of System
Normally CESC system runs synchronised with the grid at SRS/BGS points. But whenever any
abnormal condition arises in the grid, our system needs to be islanded from the grid.
Islanding is carried out on the following occasion :
Under frequency
: 47.8 Hz, 0.5 Hz
Over frequency
: 52.3 Hz, 0.5 Hz
Directional Over current : > 500 A for 2.5 sec.
towards WBSETCL
Emergency push button
Busbars in CESC System
Broadly two types of CBs are used viz. Outdoor type & Indoor typeOutdoor type
B.
1 BREAKER
A.
M1
M2
TRANSFER
Indoor type
A. Single Bus Bar System
M1
253
10:00
15:00
Drawal Schedule
S
L
D
C
17:00
22:00
CESC
Revision in Requisition
23:00
Final
Drawal Schedule
0 to 24
hours
Revisions during
Current day
Generation
Cost (Rs.)
BBGS
1.02
1.11
SGS
1.13
1.23
TGS
1.22
.34
NCGS
2.54
2.81
Combined
1.17
1.27
254
KRS
M3
M2
132 KV BUS
M1
EE BUS
75 MVA T3
75 MVA T2
75 MVA T1
We intend to take 33KV M3 Bus of KRS from Import to Generation ( 150 MVA Jadavpur Circuit)
Export and its Control:
CESC Commenced export at 0000 hrs on 12th March 2004 to WBSEB
Exported outside the region through Trader from 8th October 2004
Since then exported to the following states : West Bengal, Madhya Pradesh,
Maharashtra, Punjab, Jammu & Kashmir, Haryana, Meghalaya, Tripura, Andhra
Pradesh, Chhattisgarh, Meghalaya, Sikkim etc.
Traders are : PTC, NVVNL, RETL, LEUL, JSWPTCL, GEL, VISA POWER,
Karamchand Thapar, ADANI, TPTCL etc.
We also export power on day ahead basis through bidding in Indian Energy
Exchange (IEX).
Power Trading (Import):
CESC normally import power from WBSEDCL.
Distribution Training Institute, CESC Limited
255
We first imported power from outside the region through Trader from 26th
September 2004
Since then we have imported power from the following states and CPPs : Tripura,
Gujrat, Nagaland, Andhra Pradesh, GRIDCO, TISCO, NBFAL, and other CPPs of
SR and ER through traders.
We also import power through bidding in Indian Energy Exchange (IEX).
Energy Exported:
Energy Exported
500
458.32
450
418.5
441.4
400
350
(MU)
300
250
200
160.05
150
100
50
7.52
0
2003-04
2004-05
2005-06
2006-07
2007-08
140
121.37
120
90.6
100
80
(MU)
54.57
60
40
20
12.89
2007-08
2006-07
2005-06
2004-05
256
7660
7136
7056
7176
7091
7006
6674
6654
6172
6011
5583
5089
4975
4847
4624
4482
4284
4000
4086
5000
3885
(MU)
4234
6000
5345
7000
6433
8000
7520
9000
8238
3000
2000
2006-07
2004-05
2000-03
2000-01
1998-99
1996-97
1994-95
1992-93
1990-91
1988-89
1986-87
1984-85
1000
Load Curves
SYSTEM LOAD CURVES (TYPICAL SUMMER)
07/05/2008
1500
1300
1100
900
MW
700
500
300
100
0 -100
50
-200
0:
00
1:
00
2:
00
3:
00
4:
00
5:
00
6:
00
TIME
CESC Sent Out
7:
00
8:
00
9:
00
10 11
:0 :0
0
0
Import
12
:0
0
13
:0
0
14 15 16 17 18
:0 :0 :0 :0 :0
0
0
0
0
0
System Demand
19
:0
0
20
:0
0
21 22
:0 :0
0
0
export
23
:0
0
257
Load Curves:
Load Curves:
19/12/2007
1250
1200
1150
1100
1050
1000
950
900
850
800
750
700
650
600
MW 550
500
450
400
350
300
250
200
150
100
50
0
-50
-100
-150
-200
23:00
22:00
16:00
11:00
12:00
13:00
14:00
15:00
21:00
20:00
17:00
19:00
0:00 1:002:003:004:005:006:007:008:009:0010:00
18:00
TIME
Import
System Demand
export
50.50
Freq corresponding to
UI rate equal to
WBSEDCL Tariff
50.00
49.50
49.00
48.50
Curtailment
Actual Net Drawal
Grid Freq
(A-S)/S : -0.51%
UI Receivable
258
ABT Overview
It is a performance-based tariff for the supply of electricity by generators owned and
controlled by the central government.
It is also a new system of scheduling and despatch, which requires both generators and
beneficiaries to commit to day-ahead schedules.
It is a system of rewards and penalties seeking to enforce day ahead pre-committed
schedules, though variations are permitted if notified One and half hours in advance.
The order emphasises prompt payment of dues. Non-payment of prescribed charges will
be liable for appropriate action.
Grid Status Before Introduction of ABT
Low frequency during peak load hours, with frequency going down to 48.0-48.5 Hz for
many hours every day.
High frequency during off peak hours, with frequency going up to 50.5-51 Hz for many
hours every day.
Rapid and wide changes in frequency 1 Hz change in 5 to 10 minutes, for many hours
every day.
Very frequent grid disturbances, causing tripping of generating stations,
interruption of supply to large blocks of consumers, and disintegration of the regional grids.
Integrated grid operations require the normalisation of frequency across all five regions
requiring proactive load management by beneficiaries and dispatch discipline by generators.
Least cost power not dispatched in preference of more costly power
ABC of ABT
Three Part Tariff
Capacity Charge
A fixed charge (FC) payable every month by each beneficiary to the generator for making
capacity available for use. It will comprise interest on loan, depreciation, O&M expenses,
ROE, Income Tax and Interest on working capital.
Energy Charge
Energy charge per kWh of energy supplied as per a pre- committed schedule of supply
drawn a daily basis.
Unscheduled Interchange (UI)
A charge for Unscheduled Interchange (UI charge) for the supply and consumption of
energy variation from the pre-committed daily schedule. This charge varies inversely with
the system frequency prevailing at the time of supply /consumption. UI Charge is payable or
receivable depending upon the deviation from the schedule and also subjected to the grid
condition (frequency) at that point of time. Through this clause, disciplining regime is
introduced using commercial tools.
ABT and UI
UI mechanism is primarily a competitive real-time balancing Mechanism
The view that UI mechanism is a penal and disciplinary mechanism to deter utilities from
deviating from schedule needs reconsideration
UI mechanism is Real-time Pricing
UI mechanism is self-healing, self-dealing
UI rate is transparent
259
Decreasing marginal return with every additional unit of deviation from schedule acts as a
counterweight
Settlement is weekly
Significance of Unscheduled Interchange Mechanism in the Indian Electricity Supply
Industry:
Helping the grid gets rewarded, hurting the grid is penalized
Is hedgehog simple, elegant and flexible
Eliminates the need for elaborate contracts
Is inexpensive to implement
Price signal available at any outlet
Addresses the concerns of Grid operators & all other players in the power system
Economists Regulators, Policy makers
UI Rate: a function of frequency
For a frequency F <= 49, the UI rate will be = 10.00 Rs/kwh
For a frequency F >= 50.5, the UI rate will be = 0
For a frequency 49 < F <= 49.8, the UI rate will be = (1000 - (F-49)*18/.02) / 100 Rs/kwh
For a frequency 49.8 < F < 50.5, the UI rate will be = (0 + (50.5-F)*8/.02) / 100 Rs/kwh
UI
UI
Schedule Actual
Schedule Actual
If UI Rate > S.O. Cost, then Payment is penalty & Receipt is incentive
w.r.t. Receipt of Scheduled Cost @ S.O. Cost
If UI Rate < S.O. Cost, then the opposite is true
In case of Import If UI Rate > Import Cost, then Payment is penalty & Receipt is incentive
w.r.t. Payment of Scheduled Cost @ Import Cost
If UI Rate < Import Cost, then the opposite is true
260
UI Rate
1100
1000
18 paisa
ramp
900
1000 paisa at
below 49.00
hz
Paise/kwh
800
0 paisa at
50.50 hz or
above
700
600
500
BBGS
cost
400
300
TGS &
SGS
cost
8 paisa
ramp
NCGS
cost
280 paisa at
49.80 hz
200
100
48.96
49.14
49.32
49.50
49.68
49.86
50.04
50.22
50.40
50.58
Frequency
Deficit Condition
in the Grid
800
600
Surplus
condition
in the Grid
400
280
200
Frequency (HZ)--->
51
50.9
50.8
50.7
50.6
50.5
50.4
50.3
50.2
50
50.1
49.9
49.8
49.7
49.6
49.5
49.4
49.3
49.2
49.1
49
48.9
48.8
48.7
48.6
0
48.5
Rate(Paise/KWH)--->
1000
261
Power Trading
Bilateral Import and Import of power take place through short term, day ahead and same day
contracts.
Short term contracts: The quantum and price are fixed at least three months ahead.
Day ahead contracts: Although the price is fixed earlier, the quantum is fixed on one day in advance
Same day contracts: The price is fixed earlier but the quantum is fixed 4/6 hours in advance.
Connection of Five Regions :
NORTHERN
REGION
400 kV DC
Gorakhpur
Muzaffarpur
(AC)
NORTH
EASTERN
REGION
400 kV DC
Malda
Bongaigaon
1 X 500 MW Sasaram (HVDC)(AC)
\\ \\
WESTERN
REGION
//
EASTERN
REGION
///
SOUTHERN
REGION
Power flow through regions
Whenever any power flows through our region to another, the receiving end gets less power than
the sending end due to power loss in the network.
262
ER
WR
95 MW
91 MW
88 MW
5%
4% 3.9%
263
264
2.0
2.1
Grounding :
Grounding is the practice of providing a good electrical connection between metallic parts,
structures or electrical circuits with a metallic system usually buried in earth with the
objective of maintaining these metallic parts at the electrical potential of the earth (zero
potential) to prevent rise of dangerous potential. Due to failure of insulation in power
circuits of any electrical equipment, dangerous conditions may arise resulting in their
metallic parts getting alive and hence susceptible to electric shock to any personnel touching
the body of the equipment. Proper earthing will protect the installation from occurrence of
such conditions thereby increasing safety of personnel as well as improving quality of
service.
Hence, Earthing of non-current carrying metal work and conductor is essential to the safety
of human life, animals and property and is generally known as Equipment Earthing while
Earthing associated with current carrying conductor is normally essential to the security of
the system is known as System Earthing.
Adequate grounding is required to prevent at any installation causing the body of the
electrical equipments to become live. Hence, a low resistance between the grounding
connections and earth is necessary to keep the potential developed during an earth fault to
minimum. However, grounding forms an important aspect in the operation of power
systems. The basic functions of a proper grounding installation are:
1) To limit the touch and step potential in and around the installation such as power
house, switchyard, substations etc. within tolerable levels to ensure safety to
personnel.
2) To limit total potential rise above true earth within acceptable limits during fault
conditions.
3) To limit system over-voltages during fault conditions.
4) To provide a current path for operation of protective gears.
A grounding system will prove itself adequate to perform these functions if :
A. It has a low value of earth resistance
B. The surface potential gradients are within acceptable limits.
The acceptable value of earth resistance may be anywhere from 0.1 to around 1 ohm or
slightly more depending on the acceptable value of ground potential rise, which in turn is
dependent on the magnitude of the fault currents flowing through the ground. With power
systems growing, the magnitude of fault currents is increasing rapidly, hence there is need
to achieve as low an earth resistance as possible.
Requirements of a Good Grounding System
Current carrying capacity
Any conductor, electrode or connection used in grounding system should be large enough to
carry the following currents without excessive heating
a) Faults currents of magnitude and duration such as to produce maximum heating effect
(I2t) in the grounding system components.
b) The currents caused by a direct lightning stroke or induced by a lightning stroke.
These currents may be relatively high but are usually of short duration and therefore
generally present no problem for grounds that meet the other electrical and mechanical
requirements.
c) The current that may be expected to flow in the grounding system as a result of
sustained system neutral currents.
Distribution Training Institute, CESC Limited
265
2.2
2.3
3.0
3.1
3.2
Effect of Frequency
Humans are very vulnerable to the effects of electric current at frequencies of 50 to 0 Hz.
Currents of approximately 0.1 amps can be lethal. At higher frequencies, of 3000-10,000
Hz, higher currents can be tolerated
3.3
Effect of Magnitude
The physiological effects of electric current on human body in the order of increasing
magnitude are muscular contraction, unconsciousness and fibrillation of heart and burning.
Currents of 1mA is generally recognized as threshold perception.
Currents of 1 6mA are often termed as let-go currents, though unpleasant to sustain,
generally do not impair the ability of a person holding an energized object to control his
266
3.4
Accidental ground Circuit
3.4.1 Resistance of Human body
For DC & AC voltage at power frequency, the human body can be represented by a noninductive resistance. The value of this resistance is difficult to establish and varies between
500-3000 ohms. For the purpose of designing of grounding systems Hand and shoe resistances are assumed as zero.
Value of resistance of a human body is considered as 1000 ohms for calculation
purpose.
Step Potential
It is the difference in surface potential experienced by a person bridging a distance of 1
meter with his feet without contacting any other grounded object.
Touch potential
It is the potential difference between the ground and surface potential at the point where a
person is standing, while at the same time having his hand in contact with a grounded
structure.
Mesh Potential
It is the maximum touch potential to be found within a mesh of a grid.
4b
(2)
RMfoot
= 2dF
(3)
Where,
Distribution Training Institute, CESC Limited
267
RB
RMF
IA
RF
df
(1 mtr.)
Similarly, the equivalent circuit for a hand-to-two feet contact as shown in fig. 2, i.e., for a
touch potential circuit is given by :
(7)
RA = RB + [Rfoot + RMfoot ]
IA
U
RB
U
RF
IA
RMF
RF
Touch Voltage Circuit
In IEEE Std. 80, the radius of the disc representing one foot is considered as 0.08m (3
inches) and neglects mutual resistance. Hence, the eqn. for series & parallel resistances of
two feet can be obtained in numerical form and expressed by combining the above
equations as
(8)
R2FS = 6
R2FP = 1.5
. (9)
If the surface soil has a different soil resistivity [s] compared to that of an underlying soil
[] as in case of substations with a top layer of crushed rock or gravel, the eqns. (8) & (9)
will be,
(10)
R2FS = 6 Cs (hs*K)s
Distribution Training Institute, CESC Limited
268
269
their metallic content. Sands, loams and rocks are however, in themselves of such high
resistance that they can be treated as non-conductors. However, when soil contains traces of
moisture, the conductivity increases considerably although it is still very poor when
compared with metals. Conduction of electricity in soil is through water.
4.1
4.2
4.3
4.4
4.5
4.6
270
=
1+
2a
2
a
2
a + 4b
a2 + b2
However, in practice, four rods are usually driven into earth in a straight line at equal
intervals a, to a depth not exceeding 0.1a. So we assume b = 0 and the formula reduces
to
= 2 aR
This gives approximately the average resistivity of the soil to a depth b. Usually, a
variation in apparent resistivity upto 30% is neglected and such a soil is considered as
homogenous soil.
A
a
C1
a
P1
a
P2
C2
271
the Earth Tester shorted and connected to ground system E. Current I is injected into the
earth through C1 with return through electrode C2. The passage of the current produced at
a distance X from E results in a voltage drop VX in the soil. VX is measured by a
potential probe P2. The quotient VX/ I is the apparent resistance which under conditions give
the true resistance RE of the grounding system. VX/ I is plotted as a function of the potential
probe distance X.
The above exercise is repeated at various locations of the area where earth resistance is to be
measured and at various spacing in each location from which the average and maximum soil
resistivity in Ohm-meter of the area is determined. The table format in which the data
may be collected and the resistivity value that may be determined is furnished in Annexure
I attached.
6.0
6.1
6.2
272
6.3
6.4
all through the substation area. Besides, generally a substation always have a layer of
crushed granite which also forms a surface layer above the original soil layer.
Determination of Maximum ground fault current
Considering the correct value of ground fault current is important while designing of
grounding system of a substation. The three types of ground fault currents are :
i) Three phase- to-ground
ii) Two phase-to-ground
iii) Single phase-to-ground
The first two possible causes of fault currents are encountered to a lesser extent than single
phase-to-ground fault current. Moreover, the currents in these two cases are of lesser
magnitude since they have a return path. As single phase to ground current is more
commonly encountered and is more than the others, therefore, the maximum single phaseto-ground fault current is adopted for the grounding system design.
Evaluation of ground resistance
An ideal grounding system should provide a near zero resistance to earth. In practice, the
ground potential rise at the station site increases proportionately with the fault current. The
higher the fault current, the value of the calculated ground grid resistance should be lower.
Estimation of the total resistance to remote ground is one of the first steps in determining
the size and basic layout of grounding systems. The station resistance primarily depends on
the area to be occupied by the ground system.
As per IEEE-std.80:1986, SVERAKS approximation formula has been considered for
estimation total station ground resistance Rg.
For grid depths between 0.25 and 2.5 m, Sveraks approximation can be used which is -
Rg
6.5
6.6
1
+
L
1
1 +
20 A
20
1+ h
A
1
where,
Rg
=
station ground resistance, in ohm
=
earth resistivity in ohm-m
A
=
area occupied by the ground grid, in m2
L
=
total buried length of conductors of grid rod combination, m
h
=
depth of burial of grid, m
Calculation of Maximum Grid Potential rise
The maximum rise in potential above remote earth is Eg = Ig * Rg, where Ig is the maximum
ground current in the grid and Rg is the ground resistance. If need for decrease in grid
potential rise occurs in case of transferred potential, the resistance may be decreased by
modifying the design and using more conductor length and if possible by increasing the area
of the grid. The increasing in area of grid is more effective than the increase in conductor
length only for decreasing the ground resistance.
Transferred Potentials
Where it is possible for the grounding system voltage to be conveyed to places outside the
grounding grid area, transferred potentials should be checked for pipes, rails, metallic
fences, auxiliary buildings etc. Adequate protection against transferred potential should be
273
274
Vm
Va
Vo
K0
Is equal to 1/ 0
1
0104
(K0 + V0) TCAP
275
200 C
TCAP
Resistivity Factor
0.00393
234
1083
1.7241
3.685
97.0
0.00381
242
1084
1.7774
3.680
Copper
Clad
Steel Core wire
40.0
0.00378
245
1084/
1300
4.310
3.684
Copper
Clad
Steel Core wire
30.0
0.00378
245
1084/
1300
5.747
3.858
Commercial EC
Aluminium Wire
61.0
0.00403
228
657
2.8264
2.846
Aluminium Alloy
Wire 5005
53.5
0.00353
263
660
3.2226
2.689
Aluminium Alloy
Wire 6201
52.5
0.00347
268
660
3.2840
2.676
Aluminium Clad
Steel Core Wire
20.3
0.00360
258
660/
1300
8.49
2.860
Stainless
No. 304
2.4
0.00130
747
1400
72.0
4.037
Description of
Materials
Material
Conductivity
Standard
Annealed
Soft
Copper wire
100.0
Commercial
Hard
Drawn
Copper wire
Steel
0 Factor
at 20 0C
276
hasten the corrosion of the latter. Due to cost of copper and the reasons as mentioned above,
galvanized steel flat or round CI Rods are used for underground earthmat grid nowadays.
6.8.6 Conductor length required for gradient control
A minimum conductor length has to be calculated to keep the touch voltages inside the grid
perimeter within safe limits. Touch voltages rather than step voltages or transfer voltages
are used as the basis for this computation because :
a) Step voltages encountered in practical installations are usually smaller than touch
voltages. Ground resistance between two feet are in series rather than parallel and are
thus more effective in limiting body current. Also, body can tolerate higher current
through foot-to-foot path.
b)
Transfer voltages are more difficult to limit and usually require isolation or other
special treatment.
For calculation of the minimum conductor length, the method / equations mentioned as per
IEEE Std. 80: 1986 is widely followed as furnished below.
The preliminary design should be adjusted so that the total length of the buried conductors is
able to limit the touch and step voltages to safe values. While designing the buried
conductor length, an irregularity factor should also be used to allow non-uniformity in the
flow of ground current per unit length of buried conductor.
L=
Km.Ki..I G t
116 + 0.174 s c s
Where,
Km
=
Ki
=
IG
ts
t
=
=
=
Km =
( D + 2h) 2 h Kii 8
1 D 2
ln
+
ln
+
2 16hd
8 Dd
4d Kh ( 2n 1)
where,
Kh = 1 +
K ii
h
ho
1 for grids with ground rods along perimeter or with ground rods both in the
grid corners and inside the grid area
Or
Kii
( 2n)
2
n
277
Ki
h0
nI.nII.nIII.nIV
Where,
=
nII
nIII
nIV
and/otherwise,
nI
nII
2Lc
Lp
Lp
4 A
0. 7 A
nIII
nIV
Lx. Ly Lx .Ly
A
Dm
Lx 2 + Ly 2
where,
A
Lp
Lc
278
Lx
Ly
Dm
Cs
=
material
=
1
s
1
a
1
0 .9 6
(2 h s + a )
;
Ref:- Eq.10 & 10A of IEEE Transaction on Power
Delivery, Vol-13,No.-3, July-1998
a = 0.106
hs
reflection factor
( s )
( + s )
t
Distribution Training Institute, CESC Limited
279
=
(1000+1.5Cs. S )0.116
_________________
t
Ref:- Eq.11 of IEEE
Transaction on Power
Delivery, Vol-13,No.-3,
July-1998
Km.Ki. .I G
Lm
Lr
Lc + 155
. + 1.22
LR
2
2
+
Lx
Ly
LR
Lr
where, LC
Step voltage calculated on the basis of effective buried length Ls applicable to grids with or
without ground rods is
Es
K s .Ki. .I G
Ls
280
where,
Ls
0.75 Lc + 0.85 Lr
Ks
1 1
1
1
+
+
1 0.5n 2
2h D + h D
Rg
where,
Rg
=
=
6.11
1
+
L
1
1
1 +
20 A
20
1+ h
A
=
area occupied by the ground grid, in m2
L
=
total buried length of conductors of grid rod combination, m
h
=
depth of burial of grid, m
Ground mat is designed to control the surface gradients i.e. to see that the touch and step
voltages are well within the safe limits. Generally the average S.R. is considered for design
of the mat. However the step and touch voltages are again checked for the highest S.R. and
found to be less than the safe values.
Corrosion in Metals and buried grounding grids
Corrosion can be defined as the gradual destruction of a material because of reaction with its
environment. In case of metals, the destructive attack is usually by chemical or
electrochemical reaction.
281
Corrosion of metals buried in soil has been established as an electrochemical process and
the phenomenon is attributed to the flow of electrical currents in the innumerable micro
galvanic cells constituted by the existence of local anodic and cathodic sites on the metal
surfaces. Various constituents of the soil affect the ohmic resistance by the cathodic and
anodic processes.
The resistivity of soil is a measure of almost all the physiochemical properties of the soil.
The degree of corrosion of most of the soils increases with the decrease in the resistivity of
the soil as can be seen from the table furnished below :
Class
Less than 25
Severely corrosive
26 - 50
Moderately corrosive
51 - 100
Mildly corrosive
Above 100
Soils acts as an electrolyte in corrosion. The moisture, oxygen and hydrogen concentrate
affect the electrochemical corrosion of metals buried in soils. The rate of corrosion of
earthing conductors will primarily depend upon the metal used for earthing, characteristics
of soil and any dissimilar metals that come in direct contact with the earthing installation in
ground.
Metals dissolve in corrosion medium by forming ions. Reduction in conductor area of metal
due to corrosion may reduce its current carrying capacity and strength. Copper has been
extensively and universally used as the material of underground conductors due to its high
corrosion resistance property in most of the soils. Steel (galvanized and un-galvanized) is
also very commonly used for earthing in view of its low cost. The unit of measure of
corrosion rate or more precisely corrosion resistance is given by MPY (Mils per year).
Safeguard against Corrosion
1. Providing extra allowance in conductor size. Hence bigger section of steel can take care
of corrosion economically and adequately. steel corrodes almost six times that of
copper.
2. Zinc coatings are used extensively as a measure against corrosion of steel. Galvanised
steel in ground corrodes at a slow rate in the beginning but when the zinc coating is
destroyed, it starts corroding at its usual high rate. Therefore, galvanizing as means of
protection against underground corrosion for extended period of time can not be
depended upon.
Ground mat is designed to control the surface gradients and see that the touch and step
voltages are well within the safe limits. Generally, the average soil resistivity is considered
for design of earth mat. However, the step and touch voltages are checked for the highest
soil resistivity and should be less than the safe/permissible values.
7.0 CASE STUDY
The grounding system design our 220/132kV Eastern Metropolitan Substation was carried
following the procedure as detailed in the previous chapters. At first, the soil resistivity
measurement of the substation site was carried out using proper earth testers and accessories
as mentioned below adopting the method described in point no. 5 of this report. The results
obtained is furnished below.
282
Resistance
(ohm)
Soil
Resistivity
(ohm-m)
Resistance
(ohm)
(N - S)
Soil
Resistivity
(ohm-m)
Resistance
(ohm)
(E - W)
Soil
Resistivity
(ohm-m)
(NW - SE)
0.62
7.791168
1.7
21.36288
0.67
8.419488
0.15
4.7124
0.1
3.1416
0.09
2.82744
10
0.05
3.1416
0.06
3.76992
0.04
2.51328
15
0.04
3.76992
0.03
2.82744
0.04
3.76992
25
0.02
3.1416
0.03
4.7124
0.02
3.1416
Resistance
(ohm)
Soil
Resistivity
(ohm-m)
Resistance
(ohm)
(NE - SW)
Soil
Resistivity
(ohm-m)
Resistance
(ohm)
(NW - SE)
Soil
Resistivity
(ohm-m)
(E - W)
0.38
4.775232
0.285
3.581424
0.51
6.408864
0.12
3.76992
0.07
2.19912
0.08
2.51328
10
0.04
2.51328
0.04
2.51328
0.04
2.51328
15
0.01
0.94248
0.01
0.94248
25
0.01
1.5708
0.01
1.5708
283
The earth flat has been designed with equally spaced grids being buried at a depth of
900mm from finished grade level. 100mm of crushed rock / gravel spread over finished
formation level is suggested around the base of all the equipment to a distance of 2 to 2.5
mtrs. This can be used for the entire area of the grid mat which is desirable but not essential
and hence for the purpose of economy it is suggested only around the equipment base.
7.3
RESULTS
7.3.1 Determination of Allowable Touch and Step voltages under different Soil Resistivity
Values
The allowable Touch and Step voltages have been worked out using the equations furnished
in the previous chapters for determination of these voltages as furnished in the table below
considering 4 typical cases of Maximum, Minimum, Average and Two layer soils.
Accordingly, the grid resistances have also been derived under these cases.
Allowable Volts
Case-2
Case-3
Case-4
Parameter
With
Surface
Layer
Spreading
Touch
voltage
648 V
116.4 V
10.5
178.9
45.8
66.9
Step
voltage
2121 V
119.6 V
5.7
96.4
24.7
15.6
0.0027
0.62
0.011
0.023
Without
Surface
Minimum Max. of Average Two Layer with
Layer
of all
all
SR=4.1 Layer depth of
Spreading
readings readings
3.5mtrs
SR=21.36
SR1=12.52,
SR=0.98
SR2=3.45
Grid resistance
284
MS
Earth Mat
Earth Equipme Total
Round
Flat
flat-Fence nt Earth
Flat
Rods 1 length in Earthing
flat in
Length
Mtr LongMtrs
in Mtrs
Mtrs. in Mtrs.
Nos.
40
476
27159
870
2653
30682
2.5
12
36
384
21941
870
2829
25640
16
33
316
18474
870
3005
22349
22
30
236
14132
870
3357
18359
28
28
190
11539
870
3709
16118
33
26
160
9780
870
4061
14711
38
26
136
8350
870
4413
13633
42
25
116
7640
870
4765
13275
46
25
102
6816
870
5117
12803
10
49
24
94
6258
870
5469
12597
11
53
24
84
5868
870
5821
12559
12
56
24
78
5462
870
6173
12505
13
59
24
70
4997
870
6525
12392
14
62
24
68
4738
870
6877
12485
15
65
24
60
4474
870
7229
12573
16
69
24
56
4163
870
7581
12614
17
70
24
56
4203
870
7933
13006
18
73
24
52
3873
870
8285
13028
19
77
24
48
3545
870
8637
13052
20
78
24
48
3623
870
8989
13482
21
81
24
44
3346
870
9341
13557
22
82
24
40
3372
870
9693
13935
23
85
24
38
3192
870
10045
14107
24
88
24
36
3041
870
10397
14308
25
89
24
36
3067
870
10749
14686
Vertical electrodes of 100 mm dia, 10 to 13mm thick and 2.75 mtr long of machinable grade
Cast Iron pipes have been considered for all important equipments such as power
transformers, lightning arrestors etc., as close to the equipment as possible and inturn, they
are to be connected to the mat. Minor equipment and structures etc. have also been
considered to be connected to the mat. M.S. Round rods of 1 mtr long have been considered
to be connected to the grid at the periphery, driven into the soil at each junction on the
periphery.
285
Analysis of results
Emesh is less than Etouch (allowable as per the earlier table) for each case of analysis
and hence design is safe.
Es (calculated) is less than Estep (allowable as per the earlier table) for each case of
analysis and hence design is safe.
As seen from the above table, although design is safe for higher spacing, but there
is not much variation in total Earth Flat requirement for spacing of 9 mtrs. Hence
9 Mtrs spacing for Earthmat grid design has been considered here.
7.5
Bill of materials
G.I.Flat of size 75x8 mm for grid conductor, fence earthing, risers(connection to the
earth mat from the equipment) Total length 12803 mtrs(The length of the risers is calculated
with the assumption that all the equipments lie at the centre of each mesh which is the worst
case and hence the actual requirement may be less).
2) M.S. Rods of 1 inch dia each of 1mtr long nos 102.
3) Cast iron pipes of machinable grade 2.75 mtr long 10 to 13 mm thick having I.d. of
100mm nos Min 70 spread over the grid area such that they are as close to the
equipment as possible but a min dist of 5.5 mtrs is to be maintained between any two of
them as far as possible. All major equipments should be connected to individual
electrode and in turn they should all be connected to the earth mat without exception and
minor equipment and structure grounding can be directly connected to the earth mat
7.4
8.0
GUIDELINES FOR INSTALLATION OF EARTHMAT
8.1
EARTHING MATERIALS
8.1.1 The Conductor to be used for the underground earthmat is 75 x 8 mm Galvanised Iron Flat
for the entire yard. The fence earthing, risers for equipment, equipment body, transformer
neutral point, structures etc. shall also be done with 75 x 8 mm size G.I.Earth Flat.
8.1.2 The Earth electrodes i.e., the vertical electrodes shall be Cast Iron Pipes of machinable
grade 2.75 meter long, 10 to 13 mm thick having internal diameter of 100mm.
8.1.3 M.S. Round Rods of 1 meter long (as detailed in clause no. 2.12) are to be installed at the
periphery and to be driven into the soil at each junction of the periphery after connecting it
to the earthmat through proper welding.
8.1.4 All earth connections from equipment / cast iron pipe electrodes to the earthmat shall be
made using Galvanised Steel flats of cross section equal to the G.I. Flat size suggested for
the eartmat.
8.2
EQUIPMENT AND STRUCTURE EARTHING
8.2.1 All steel structures in the outdoor yard, steel / RCC columns, metallic stairs, hand rails etc.,
of the building housing electrical equipment shall be connected to the nearby earthing grid
conductor by earthing leads at two pints. Electrical continuity shall be ensured by bonding
the different sections of earth flats, metallics etc.
8.2.2 The connection between earthing pads / terminals and the earthing grids shall be made short
and direct earthing leads free from kinks and splices.
8.2.3 Electrical conduits, pipes and cable tray sections shall be bonded to ensure electrical
continuity and connected to earth conductors at regular intervals. Apart from intermediate
connections, end and beginning points shall also be connected to earthing system.
8.2.4 Metallic conduits and pipes shall not be used as earth continuity conductor.
8.2.5 Separate earthing conductors shall be provided for earthing of Street light poles, junction
boxes on the poles, flood light supporting structures, lighting fixtures, receptacles, switches,
286
8.2.6
8.2.7
8.2.8
8.2.9
8.3
8.3.1
8.3.2
8.3.3
8.3.4
8.3.5
8.3.6
8.3.7
8.3.8
8.4
8.4.1
8.4.2
junction boxes, lighting conduits etc. and shall be connected to the station earthing grid /
mat at minimum two points.
Railway tracks within plant area shall be bonded across fish plates and connected to
earthing grid at several locations. At the point where the track leaves the plant area, the rail
section shall be provided with insulated joint at both ends.
Earthing conductor shall be buried 1000mm outside the Substation fencing. Every alternate
post of the fence shall be connected to earthing grid by one lead and gates by flexible braid
to the earthed post.
Miscellaneous items like junction boxes, field switches, cable end boxes / glands, fittings
and fixtures shall be earthed whether specifically mentioned or not.
Flexible earthing connectors shall be used where flexible conduits are connected to rigid
conduits to ensure continuity.
JOINTING OF EARTHING CONDUCTORS
The overlap portion shall be welded on all four sides by continuous welding keeping an
overlap not less than 100 mm along the run. To facilitate welding on all four sides, welding
work shall be done at ground surface and then laid in trench.
Resistance of the joint shall not be more than the resistance of the equivalent length of the
conductor.
The welding surfaces shall be cleaned and made free of all oxide films, grease, oil or any
foreign materials. However, the jointing surfaces should not be made too smooth / highly
polished to prevent the jointing metal from flowing away.
All welding connections shall be made of electric arc welding. All welded joints shall be
allowed to cool down gradually to atmospheric temperature before putting any load on it.
Artificial cooling shall not be allowed.
Since the efficiency of the earthing system is entirely dependent on the electrical continuity
of the earthmat, which in turn is dependent on the welding work, hence utmost care shall be
taken while welding, duly avoiding butt joints and mere spot welds.
Thick 2 coats of Anti-corrosive bituminous paint shall be applied at the welded joints duly
removing weld, flux and any burrs.
Earthing connections to equipment earthing pads / terminals shall be bolted type with GI
bolts and nuts. Contact surfaces shall be free from scale, paint, enamel, grease, rust or dirt.
Two bolts shall be provided for making each connection. Equipment bolted connections
after being checked and tested shall be painted with anti-corrosive paint / compound.
Flexible earthing leads shall be provided for earthing of equipments wherever required.
REQUIREMENTS FOR EQUIPMENT / SYSTEM EARTHING
POWER TRANSFORMER NEUTRAL - Two earthing leads shall be provided for
transformer neutral from the transformer base. Each of the earthing leads shall be directly
connected to a separate rod / pipe electroded treated earth pits which in turn shall be
connected to Sub-station earthing grid. The earthing leads shall be continuous earth
conductors i.e., Galvanised Steel Flats without any joints as far as possible and both the flats
are to be individually taped using PVC insulating tape. They shall run in opposite directions
from the power transformer neutral point to the earth pits provided for their earthing.
LIGHTNING ARRESTERS - Earthing terminal of each lightning arrester and lightning
down conductors shall be directly connected to rod / pipe electrodes which in turn shall be
connected to Station Earthing Grid. Each phase of the lightning arrester base plate shall be
connected to the cast iron pipe electrode provided for that individual phase by running
Galvanised Steel Flat from the base plate. The Cast Iron pipe in turn shall be connected to
the earthmat by welding using Galvanised Steel Flat. A flexible braided earth bond
287
8.4.3
8.4.4
8.4.5
8.4.6
8.4.7
8.4.8
8.5
8.5.1
8.5.2
8.5.3
8.5.4
8.5.5
8.5.6
8.5.7
8.6
connection shall be made firmly between the base terminals and the Galvanised Steel Flat.
The length of the earth connection shall be as minimum as practicable.
LIGHTNING MAST - The earth conductor from the top of the Mast shall run up to the
earthmat and then to be welded.
OUTDOOR ISOLATORS AND CIRCUIT BREAKER - Earthing Mat comprising of
closely spaced (150mm approx.) conductors shall be provided below the operating handles
of HV Isolators and breaker operating kiosk. Operating handles shall be properly bonded
with flexible conductors.
INDOOR SWITCHBOARD - A minimum of two cast iron pipe electrodes are to be
provided at both ends of the switchboard / switchgear. A separate earth bus of Galvanised
Steel Flat shall be run along the switchgear on power cable entry side and cable sheath
earths shall be connected to this bus, which in turn shall be connected to the earthmat
through cast iron electrodes. Further, the earth bus provided in the switchgear by the
manufacturers shall also be connected to the earth bus run as above. The inter panel earth
connections shall be made firmly at the time of erection of panels.
EQUIPMENT BODY EARTHING - All non current carrying metal parts such as bodies
of Transformers, Circuit Breakers, Current Transformers, Voltage Transformers, Isolators,
Lightning Arresters, Outdoor Isolators and Isolator Structures are to be directly connected to
the earthmat using Galvanised Steel Flats with two distinct connections run in opposite
directions.
For Isolator Structures, a GS Flat shall run from the mounting pedestal channel duly
welding the three channels to the GS Flat running down to the earthmat. The Voltage
Transformer body shall be connected to the earthmat through an independent electrode for
each phase. The operating handles of isolators are to be connected to the earthmat
conductors (Galvanised Steel Flat) using braided earth bonds.
Flexible earthing leads shall be provided for earthing the equipments wherever required.
SUBSTATION FENCE EARTHING
Fence earthing shall be isolated from the main earthing of the substation.
The substation fence and fence earthing shall be provided at a distance of minimum 1.0 mtr
away from the edge of the substation earthmat along the periphery.
A separate earthing conductor of minimum size 75 x 8 mm GI Flat should be run along the
perimeter of the fence at a depth of 900 mm below ground surface.
The perimeter fence is to be connected to this GI Flat through independent vertical
electrodes (CI Pipe Electrodes) using Galvanised Steel Flat of minimum size 75 x 8 mm.
The connections are to be made by welding. When chain link / barbed wire fence is
provided, two flats shall be welded on either side of the fence vertically abutting the fence
and these flats are to be welded to the flat run below the ground through CI pipe electrode.
The metal gate and fence shall be firmly bonded.
The CI pipe electrodes shall be provided at corners and mid points of the fence if the
perimeter is more than 200 mtr. Otherwise, CI pipe electrodes may be provided only at the
corners or mid points.
The fence earth and Sub-station earthmat shall not have any electrical tie and should be
physically separate.
DISTANCE BETWEEN ELECTRODES
The location of the Cast Iron Pipe electrodes shall be installed keeping the following in
view:
a) The CI pipe electrode for lighting arrester and Power Transformer neutral shall be as
near as practicable to the respective equipment.
288
b)
The distance between any two CI pipe electrodes should not be less than twice the
length of the CI pipe electrode.
The lightning arrester earth connection should not be run over the ground surface. They
should be buried at the mat depth and connected to the earthmat at the nearest point.
9.0
9.1
DESIGN OF GIS EARTHING SYSTEM
9.1.1 Size of the Grid
As the area occupied by a GIS is typically only 10-25% of that of the equivalent air
insulated installation, then clearly achieving the required level of earth resistance is going to
be more difficult. It may therefore be necessary to resort to additional methods to achieve
the required value of earth resistance. Before designing, it is necessary to also necessary to
know the maximum earth fault current that the system will have to carry, the soil resistivity
and consequently, knowing the max. allowable earth potential rise, it is possible to calculate
the required overall earth electrode resistance.
Example :
If the max. allowable earth potential rise during a fault is 650 volts and the current is 10kA,
the ground resistance should be less than 0.065 Ohm.
9.1.2 Effect of different Mesh arrangements
Increase in length of the conductors laid within a single loop of perimeter conductor will
reduce the resistance of the grid but not in direct proportion to the additional length laid.
However, the desirability of proving frequent and short connections for the closely spaced
individual items of equipment does provide a better result.
9.1.3 Use of Deep driven Rods
289
DATE OF MEASUREMENT
TYPE OF SOIL
CALIBRATION
Electrode
Spacing
(meters)
Readings in Ohms
5m
10m
15m
20m
25m
Location - 1
Location - 2
Location - 3
Location - 4
Location - 5
Average Resistivity in Ohm-meters
Maximum Resistivity Obtained
Accessories Required :
4. Four terminal Earth Tester
5. Electrodes : 4 nos. 50 centimeters long, 18mm dia
6. Leads : 7/20 PVC insulated copper wire of 200meters length
7. Measuring Tape : 50 meters
8. Hammer : 2 to 4kg
9. Common tools
References:
1. Indian Standard code of practice for Earthing, IS-3043.
2. IEEE Guide for Safety in AC Substation Grounding - IEEE, STN.80 -2000.
3. CBIP Tutorial on Power System grounding practices.
4. Indian Electricity Rules, 1956 (Amended upto 2006) published in 2008.
5. Earthing system parameters for HV, EHV and UHV Substations - Technical report No. 49,
CBIP.
290
SYSTEM EARTHING
What is it?
System Earthing or Neutral Earthing refers to the mode in which the power system Neutral
(viz. neutral point of a star-connected generator, transformer, motor or neutral point of a earthing
transformer) is connected to the Earth.
It is different from Equipment Earthing, which is the connection between non-current carrying
metallic parts in electrical installation to the earth.
From Ungrounded System to Grounded Systems A Journey
Before 1950s, the power systems were used to operate with a free neutral (ungrounded neutral).
Such systems were called insulated systems, and the advocates of this method claim its superiority
on the grounds that the supply can be maintained for a time on two healthy lines while an earthfault exists on the third. This argument is particularly true for an overhead transmission when the
failure of one line to earth is first of all, transient in a nature generally and when permanent is not
likely to develop into fault between two for more lines. On a cable system, however, one line down
to earth leads to heating and burning with the likelihood that, within a short time, an earth fault will
develop into a phase fault and to avoid this possibility, quick acting earth fault protection is
required. Hence, the majority of three-phase systems today operate with an earthed neutral, earthing
being achieved directly or through impedance.
On systems with insulated neutral, a fault to earth does not constitute a short circuit. The only
current flowing is the capacitance current of the healthy phases, the condition being indicated in
Figure 1. In case of overhead lines, this current may be so small as to render automatic isolation by
protective means difficult if not impossible. Such a fault has the effect of raising the voltage of the
two healthy lines above the normal to earth and may result in insulation breakdown. Furthermore, it
is an unstable condition, which may lead to arcing grounds at supporting insulations, causing
transient surge voltages to travel in both directions along the line, which may bring about further
failure at the insulators for terminal apparatus.
F
3I
3I
3I
Fig. 1
The advantages of the earthed neutral are many and include the following:
1)
When an earth-fault occurs, the fault current can return via the neutral point and in doing so
it can be utilised to bring about discriminative operation of protective apparatus, thereby
disconnecting the faulty circuit without disturbing the healthy parts of the system.
2)
By reason of (1) the voltage on healthy parts of the system is always held down to normal
line to neutral voltage.
3)
It avoids the transient overvoltage caused by earth fault arcs (arcing grounds) on insulated
neutral systems and which can be damaging to the system insulation as a whole.
4)
Induced static charges are conducted to earth without disturbance.
291
X 100
Typical Cases
a) Resonant Earthing:
Earthing through reactance of such a value that power frequency current in neutral connection is
almost equal and opposite to power frequency capacitance current between unfaulted phases and
earth.
Such reactance coil is also known as Arc-Suppression Coil or Peterson Coil or Ground Fault
Neutraliser, since by the use of such a coil as means of earthing, the danger of arcing grounds is
eliminated and under certain conditions the system can be left in service with one line to ground
until it is convenient to disconnect and effect repair.
IF
IP
3I
F
0
3I
3I
Fig. 2
In the condition shown at Fig.2, the capacitance current will lead the voltage of the faulty phase by
nearly 900. It follows that if an inductance of appropriate value is connected in parallel with the
capacitances, the current in fault will be either very considerably reduced or cancelled out, bringing
about the extinction of fault-arc. When the fault is a flashover due to some transient cause, the
extinguishing of the arc restores the system to normal, if no permanent damage has been done.
292
b) Earthing Transformer :
The neutral point (star point) is usually available at every voltage level from generator or
transformer neutral. However, if no such point is available due to delta connections or if neutral
point is desired on busbars, the most common method is using a zig-zag earthing transformer. Stardelta transformer is also sometimes used in these cases for earthing.
Source of Supply
Earth
a) Interconnected Star (zig-zag)
b) Star/Delta
Earthing Transformers
In zig-zag transformer as shown above, each phase of primary has two equal parts. There are 3
limbs and each limb has two windings providing opposite flux during normal condition. Since the
fluxes oppose, the transformer takes very small magnetising currents during normal condition.
During earth faults in the system, the zero sequence voltages are generated which have same phases
for three components VRO, VYO, VBO and so can easily flow zero sequence currents through the zigzag winding. In other words, zig-zag transformer offers low impedance to an earth fault.
Annexure on rc-Suppression Coils
B
R
CB
Ip
ICB
CY
CR
ICY
293
Fig. A
Icap
ICB
ERB
EB
ICY
ICY
ER
300
0
ICB
30
ER
EY
ERY
Fig B
Ip
Fig. B. shows the line-to earth capacitance currents and their driving voltages, and also indicates
that the total capacitance current in the fault is,
Ip = ICAP
E
Or
= 3EwC
wL
where, w= 2f
f = frequency (Hz)
1
Or L =
Henries
3w 2 C
294
6kV level
At this voltage level, the system neutral is earthed through resistance, because the insulation
level of almost all the equipments of this level are of 11kV grade.
R
R
V
3V
3V
V
N
Before Fault
On Fault on R. Phase
As shown in the above figure, the earth point will shift from the neutral point towards the
faulty phase on development of earth fault. The amount of shifting will depend
predominantly on the value of resistance chosen for earthing. As shown, the maximum
voltage-rise to earth will be 3 times. Hence with 11kV grade insulation level, 6kV system
can be safely being earthed through resistance.
Now, the value of resistance is so chosen to limit the earth fault current to a small value.
i)
I E / F=
6000 / 3
= 1385 A
2.5
NGR=2.5
295
The earth fault current with this resistance is limited to less than 1400A at 6kV voltage (i.e.
less than 15MVA)
ii)
Generating Stations:
Various neutral grounding resistance values are chosen to limit the earth fault
current level of respective power system to their rated current withstand level.
Typical rating:
* TGS > 3.81, 1000A for 15 secs.
* SGS > 13.27 300A for 10 secs.
c)
11kV Level :
At this level of distribution network, we solidly earth the system neutral to avoid voltage
rise to earth during fault, since the insulation level of equipments are of 11kV grade only.
As the earthfault current is high, the fault clearing time by protection schemes are set to a
low value.
d)
33kV Level:
At our substations or receiving stations, where we have 132/33kV transformers (Yd1
connected), the 33kV delta side is earthed through zig-zag earthing transformer. As already
explained, zig-zag transformer behaves as a simple reactance to earth fault (But offers very
high impedance to normal positive sequence voltages).
Here also, voltage-rise during earth fault occurs but the equipments at this level are designed
with insulation level to withstand the short duration voltage-rise, which is fast cleared by
protection apparatus. Importantly, the reactance earthing is chosen to neutralize the high
magnitude capacitive fault currents, which is present in our 33kV network due to presence
of large high capacitance cable network at this level.
For an idea, the typical E/F current rating for 30 seconds of ET varies between 2000A,
1500A, 836A at our substations and receiving stations.
At generating stations, as no large cable network is present, the system neutral (Yconnected) is earthed through resistance. Typical rating:
*TGS > 15.88 , 1200A for 30 secs.
*SGS > 14.43 , 1400A for 30 secs.
e)
132kV Level:
At this level, neutral of the Y-connected 132kV side of 132kV/33kV transformers are
solidly earthed to prevent any voltage rise to earth. The cost of providing extra margin for
insulation at this high-voltage level is quite high. Moreover, the faults clearing time for
earth-faults (and all faults) are made very small by using high-speed protection schemes and
apparatus.
Another point is worth mentioning here, all the 132kV neutrals are solidly earthed, so our
132kV system is multipoint-earthed system. This is done to ensure reliably that the system
earthing is never lost due to outage of one 132kV/33kV transformer.
At all other levels, the system neutral is mostly single point earthed apart from few
unmanned distribution stations and few important receiving stations, etc where all system
neutrals are kept earthed.
f)
296
To Generator neutral
Trafo Rating
1 phase trafo
R
Here, the primary concern in selecting the system-earthing mode is to limit the earth-fault
current to few amperes (less than 5A) because even a small amount of fault current may be
devastating the machine (generator stator) core. The arcing at the fault point burns iron at
the core and welds laminations. Replacement of faulty conductor may not be a serious
matter but to re-building the core would require extensive dismantling of the winding. The
cost of repair and the cost of unavailability of large generator would be a mammoth.
The resistor in the secondary winding, allows the resistor value to be of low ohmic value
and be of rugged construction while still presenting high equivalent value in the generator
circuit and thus limiting the fault current to extremely low value.
While choosing the resistor value, it is checked that the equivalent resistance in the stator
circuit does not exceed the impedance at system frequency of the total summated
capacitance of the three phases. In other words, the resistive component of fault current
should not be less than the residual capacitance current. This is done to protect the
production of high transient over voltages in the event of an arcing earth-fault, which is
done by discharging the bound charge in the circuit capacitance through the resistor.
In NCGS, the 33kV generator neutral is earthed solidly through OCB before
synchronisation. After synchronisation, the OCB is made off.
References:
1. Fault Calculations: C H W Lackey
2. J & P Switchgear Handbook
297
Preface
Transmission & Distribution system forms the connecting link between Electricity Demand
and Supply and Substations and Distribution stations are major component in the T&D
system. With the growing demand in power, substations have the key role to play in the
power system.
In CESC system, to keep pace with the growing demand, there is on an average a yearly
capacity addition of around 75MVA at Substation level and 120MVA at Distribution
Station level including transformer capacity augmentation of around 30MVA. Presently,
there are around 13 Nos. of 132/33kV Substations, 1 no. 132kV Switching station and 92
nos. of 33/11-6.25kV Distribution stations in the system. As per the Rolling Capex (20072008 to 2011-2012), CESC have planned to install 24 nos. 33/11kV Distribution Stations &
3 nos. 132/33kV Substations.
2.0
Availability of land
3.0
4.0
PLANNING PROCESS
The initial process for installation of substations is done by the power system planners. The
following studies are done in the planning stage for finalization of a substation:
STEP 1 : Short, Medium & Long term Load Forecasts
Assessment of Area-wise Present daily, monthly & yearly loading patterns
Assessment of area-wise forecasts of forthcoming loads from the future infrastructural
development plans of Govt. and other non-Govt. agencies.
Determination of load growth from pending connections
Assessment of addition of new consumers from past trends
Assessment of Bulk load requisitions
Assessment of Immediate / temporary load requirements in different areas.
Distribution Training Institute, CESC Limited
298
Projection of load growth patterns from the above using standard statistical methods
299
n)
o)
6.0
Initial Studies
Normally, a few site locations are first inspected and from these locations, the best suited
location is finalized. The initial studies that are carried out after inspection of these locations
are as follows :
a)
Site comparison and suitability evaluation.
b)
Environmental Assessment (EA) study.
c)
Preparation of final SLD
d)
Preparation of General Arrangement and detailed layout drawings of different
facilities
7.0
TYPE OF SUBSTATIONS
Substations may be Indoor or Outdoor type and are designed and constructed considering
the system requirement, availability of space, location of site, various public concerns etc.
The different types of outdoor substations are :
A.
DISTRIBUTION SUBSTATION :
B.
T RANSMISSION SUBSTATION :
300
catering the load of a nos. of present and proposed distribution stations & bulk consumers, a
transmission or grid substation is installed.
C.
SWITCHING SUBSTATIONS :
8.0
DESIGN CONSIDERATIONS
The following are the basic design aspects required to be considerate while setting up a
Substation :
1. Sizing/Capacity of Substation (MVA)
2. Operational & System requirements
3. Reliability Considerations
5. Future extension provisions
6. Maintenance considerations
7. Safety considerations
8. Interfacing considerations
9. Cost considerations
9.0
LAYOUT CONSIDERATIONS
After the initial planning studies are complete, the next step that comes is finalization of
layout of the substation. For this purpose, the following aspects are to be considered and
each of these areas are to studied and finalized keeping in view the available land and
projected cost of the substation :
1.
Selection of Busbar / Switching Scheme
2.
Finalisation of major equipment Both Indoor & Outdoor equipment
3.
Probable layout of the outdoor yard
4.
Electrical Safety clearances
5.
Substation Control Room Building layout
6.
Auxiliary facilities
7.
Control & Protection
8.
SCADA & Communication
9.
Fire handling & Protection facilities
10.0
301
6.
7.
8.
9.
10.
11.0
12.0
13.0
302
1.
2.
14.0
BIL
(kV)
11
Phase to
Earth
Min.
Ground
Clearance
Sectional
Clearance
75
320
320
3700
2600
33
170
630
630
3700
2800
145
550
900
1100
4600
3000
650
900
1100
950
1100
1100
5500
3500
1050
1300
1300
245
303
14.2
14.3
15.0
Equipment
Elevation of Main Bus / Buses
Live Terminal
(Mtrs.)
elevation
Low
High
(Mtrs.)
Take-off
elevation
(mtrs.)
11 & 33
4.0
5.5 to 6.5
9.0
6.5 to 8.5
66
4.0
6.0 to 7.0
9.0 to 10.5
9.5
132
4.5 to 5.0
8.0 to 9.5
13.5 to 14.5
12.0 to 12.5
220
5.0 to 5.5
9.0 to 13.0
18.5
15.0 to 18.5
400
8.0
14.0
--
20.0
16.0
BUSBAR SCHEMES
Different busbar schemes / configurations are used in different types of substations to suit
the requirement of the stations. The physical size, type and arrangement of major equipment
such as power transformers, circuit breakers, isolators, current and voltage transformers etc.
Distribution Training Institute, CESC Limited
304
may cause variance in the layouts. It is important to design a flexible bus bar arrangement so
that power may be served through alternative arrangement during fault in any specific
substation equipment and the equipments can be attended and maintained without any
supply interruption during routine and breakdown maintenance.
The busbar schemes that are generally implemented are :
Single Busbar
Main and Transfer Busbar
Double Busbar
Double Main and Transfer Busbar
Ring Busbar & Mesh Busbar
One-&-half Breaker arrangement or Diameter arrangement
16.1
305
16.2
This arrangement is basically two or more single bus schemes and each tied together with
bus sectionalizing breakers. The sectionalizing breakers may be operated normally open or
closed depending on system requirements. In this arrangement, a bus fault or breaker failure
causes only the affected bus-section to be removed from service thus eliminating total
substation shutdown. Usually, the fault can be isolated and rest portion can be restored to
service easier and faster because of the increased flexibility of the arrangement.
Advantages:
1. Flexible operation
2. Higher reliability than single bus scheme
3. Isolation of bus sections for maintenance
4. Loss of only part of the substation for a breaker failure or a bus fault
Disadvantages:
1. A sectionalized bus arrangement has a higher cost than a single bus scheme.
2. Additional circuit breakers are required for sectionalizing.
16.3
306
Bus-tie
Advantages:
1. Accommodation of circuit breaker maintenance while maintaining service & line
protection
2. Reasonable in cost
3. Fairly small land area required compared to the flexibility achieved.
4. Easily expandable
Disadvantages:
1. An additional circuit breaker is required for bus tie.
2. Since the bus tie breaker have to be able to be substituted for any line breaker, its
associated relaying may be somewhat complicated.
3. Failure of a circuit breaker or a bus fault causes loss of the entire substation.
16.4
307
Advantages:
1. Flexible operation
2. High reliability
3. Can isolate either main bus for maintenance without disrupting service
4. Can isolate any circuit breaker for maintenance without disrupting service
5. Double feed to each circuit
6. Bus fault does not interrupt service to any circuits
7. All switching done with circuit breakers
Disadvantages:
1. One-and-a-half breakers are required per circuit.
2. Relaying is involved, since the center breaker has to respond to faults of either of its
associated circuits.
3. Land requirement is more.
16.5
308
Advantages:
1. Flexible operation
2. Very high reliability
3. Isolation of either main bus for maintenance without disrupting service
4. Isolation of any circuit breaker for maintenance without disrupting service
5. Double feed to each circuit
6. No interruption of service to any circuits from bus fault
7. All switching with circuit breakers
Disadvantages:
1. This configuration carries a high cost.
2. Two circuit breakers are required for each circuit.
COST COMPARISON OF TYPICAL SUBSTATIONS
The selection of bus bar scheme is very much dependent on the cost apart from other
aspects. In the table below, an approximate cost comparison of various schemes is
furnished.
SWITCHING
SCHEMES
Single Bus
Main & Transfer Bus
One-and-half Breaker
Double Bus
APPROX. RELATIVE
COST COMPARISON
100%
150%
200%
225%
309
17.0
INSULATORS
Outdoor insulators are primarily used to support rigid buswork and other electrical
equipment operated above ground potential. They are manufactured normally from single
piece electrical-grade wet-process porcelain. End caps are cemented at the two ends of the
porcelain. Presently, polymer insulators are also manufactured.
While designing requirement of insulators the criteria to be considered are:
1. Quantity of insulators required are to be optimized commensurate to the reliability of
supply and safety of personnel.
2. Creepage distance depending on atmospheric conditions (kV/mm).
3. Rated Power frequency & minimum impulse withstand voltage.
4. Usage : Bus Support i.e., Post type or Strain Insulators.
5. Failing Load (KN) i.e., Mechanical characteristics Horizontal breaking load at top,
ultimate tensile strength, ultimate torsional strength.
6. Type Cap & Pin / Solid core / Hollow / Disc / Long Rod / Stack / String
7. Material - Glazed Porcelain / Polymeric / Glass.
8. Nos. of stack in case of tension / suspension string or post type stack.
17.1
Creepage Distance
The contour of the insulators forms its creepage distance which allows the path for leakage
current to flow from the live part at the top to the earth member at the bottom.
In areas of high contamination, the contour of the insulators are such that the leakage
distance is more which prevents electrical breakdown from surface contamination. These
are called fog type insulators. The normal ones are called Anti-fog type.
Creepage Distances Recommended For Different Pollution Levels Are:
Pollution Level
Light
Medium
Heavy
Very Heavy
17.2
17.3
310
The nos. of suspension / tension insulators to be connected in series for a particular voltage
should be such that there are no occurances of any phase-to-phase or phase-to-earth
flashovers.
Suspension/Tension insulators are tested and categorized with simultaneous mechanicalelectrical strength ratings of a string. These are the rated strengths at which they were tested
at the factories and not the actual loads.
18.0
311
system in a substation should apart from the substation equipment and overhead lines shall
also include the terminating points of the overhead and incoming lines.
18.2.2 Shielding Masts
Shielding masts are used for all types of outdoor substations to provide protection against
direct lightning strokes. It consists of high mast installed on the poles or lattice structures
which forms the highest points in the substations and they are connected to earth through GI
wires running all along the structures and embedded in the ground in separate earth pits.
Normally in outdoor substations, a combination of Shielding masts and Overhead Shield
wires are used for Direct stroke lightning protection.
18.3 Calculation of Zone of Protection
There are two widely used methods for substation shielding / lightning protection.
1.
Fixed Angle method
2.
Rolling sphere method
The zone of protection of a shielding system is the volume of space inside which the
equipment and overhead conductors of a substation is considered adequately protected for
direct stroke lightning.
18.3.1 Fixed Angle method
The fixed angle design method uses vertical angles to determine the number, position and
height of shielding masts and wires. The figure above shows the zone of protection covered
by single and double mast and/or shield wires. For a single shield wire, the zone of
protection is a wedge. For a single mast, the zone of protection is a cone. When a
combination of two or more masts and shield wires are used, the zones of protections of
each overlap to provide complete coverage.
As per CBIP guideline, a single shield wire/mast covers a zone of protection of 45 deg
vertical solid angle A and two or more masts / wires covers a zone of protection of 60 deg.
solid angle B as shown in the drawing.
18.3.2 Rolling Sphere method
The rolling sphere method involves rolling a imaginary sphere of a specific radius over the
substation over the lightning masts, shield wires and other grounded structures provided for
shielding. An equipment is protected from a direct stroke if it remains below the curved
surface of the sphere as shown in the figure below, by virtue of the sphere being elevated by
shield wires and masts. The equipment / system that touches the sphere is not protected.
312
The radius of the sphere is determined by calculating the strike distance. The strike distance
is the length of the final jump of the stepped leader as its potential exceeds the breakdown
resistance of the last gap of air to ground. A stepped leader is the static discharge that
propagates from a cloud into the air.
Here, R=8KIg0.65
Where Ig= Allowable stroke Current
& K=1 for strokes to wires & 1.2 for strokes to a Mast
Land development
Substation Building
- Switch Room
- Control Room
- Cable Basement
- Cable Spreader Room
- Station / SCADA Battery Room
- Office & Utilities
- Standby DG room
- Material Unloading Bay
Roads
19.1
Design of Structures
Steel is commonly used for substation structures. They are normally hot-dip galvanized for
protection against corrosion. The type of structures essentially used are :
Lattice Structures
Tubular Structures
Tower
Gantry
Equipment Supports
313
The structures are designed as per the maximum loading that can on them due to any static
or dynamic loading. The maximum electrodynamic force that the structures may experience
during short circuit conditions are also taken into account during design. For ascertaining
the loading on structures, the following parameters are taken into account :
a)
Height of Main / strung bus
b)
Slope of conductor Span
c)
Static Load on Structures :
Weight of equipment
- Weight of Tension or Suspension Insulator String
- Weight of Conductors
- Weight of earth wires
d)
Max. Stringing Tension on Gantry
- Nos. of Strings per phase Single /double etc.
- Tension on one side or both sides of the gantry
- Turn angle of the strings at gantry / terminal points
e)
Max. Span length of overhead Conductor / bus
f)
Max. Span length & tension of overhead earth wires
g)
Wind Pressure on Structures 125 kg/sq.m
h)
Wind Pressure on Conductors
20.0
314
STEP -4
STEP -5
STEP -6
21.0
resultant of the weight of Insulator String and wind pressure on the total
Insulator String length is considered for measuring this loading.
Determination of Load Distribution in the Span due to W1, W2 & W3
Determination of maximum loading at two Anchoring points
Determination of Sag from (Sag = Total cross force / moment on the
conductor / Tension on the conductor) from shear force diagram.
BUSBAR MATERIALS
Flexible Conductors
Busbars installed in outdoor yards are either flexible / strain bus or rigid bus. The flexible
busbars are generally of ACSR conductors and are used for overhead busbars strung
between structures from strain / tension insulators as well as equipment tappings / jumpers /
droppers in an outdoor substation. The conductor type selected for a particular application
depends on :
Rated Current
Span length
Tension
Tolerable sag
Cost
Bundle conductors (two / three / four) are used where high ratings of busbars are required.
ACSR is manufactured from hard-drawn aluminium and galvanized steel wires having
desired mechanical and electrical properties. The various sizes of ACSR commonly used
and their design parameters are furnished in the table below.
Code
Name of
ACSR
Panther
30/3.0
7/3.0
976
0.1375
370
510
Deer
30/4.27
7/4.27
1977
0.06786
590
800
Zebra
54/3.18
7/3.18
1621
0.06915
610
812
Moose
54/3.53
7/3.53
2002
0.05517
665
880
Climatic conditions and surface emissivity i.e., surface conditions have effect on conductor
Ampacity. ACSR conductors are normally designed with ambient of 40 deg C and maxm.
Temperature rise of 75 deg C.
Rigid Conductors
Rigid conductors are generally used for connection between equipment to equipment in
outdoor substations. Aluminium pipes are commonly used for rigid busbars and there are
varieties of pipes of different sizes which are used for this purpose. The selection criteria of
these pipes are based on the following parameters :
Duty Type
Light / Heavy / Extra Heavy (Depending on current)
Material
Aluminium / Copper
Shapes
Flat / Tubular / Channel
Alloys
Variety of alloys with conductivities and strengths
The different sizes of Aluminium tubes (specified in IPS meaning International Pipe
Standard) normally used at different voltage levels are :
315
22.0
Voltage Grade
11 / 33kV
132kV
220kV
400kV
50 mm
65 / 80 mm
80 / 100mm
100 mm
Bus Connections
The bus connections can be done using the following methods :
Type of Connectors /
connections
Use
Bolting
Clamping
Compression
Welding
Properties of connectors :
There are various types and shapes of connectors manufactured as per requirement. The
connectors are mostly made of aluminium alloy.
The connectors should have equivalent electrical & Mechanical Properties to that of the
conductors where they are connected. The ratings specified for connectors apart from their
size are Rated current, Short time current, breaking strength etc.
Bi-metallic plates / washers are used in transition joints Between copper to aluminium.
Clamps are used where ACSR Conductors are to anchored with string insulators at tension
or compression points in Conductor strings
References:
1. Indian Electricity Rules, 1956 (Amended upto 2006) published in 2008.
2. Technical Handbook of APSEB Engineers, Hyderabad.
3. Power Engineers' Handbook, TNEB Engineers' Association.
3. Design Guide for Rural Substations, U.S. Dept. of Agriculture.
4. Relevant IS & IEC of different Substation equipments.
316
MASD SYSTEM
In CESC, the System for processing applications for new connection by the way of new service,
new load in existing service, additional load, shifting and/or strengthening of service etc. is known
as MASD System.
MASD stands for Mains Account Security Deposit. This is an age old system which operates from
the District Offices of Mains Department.
The primary objective of this System is to process an application at the quickest possible time,
addressing all en-route paraphernalia, towards giving new connection to the intending consumers
whose applications get matured.
All the applications that are submitted do not go to the maturity stage. Many applications get stuck
up due to non-compliance on the part of the applicants and finally attain their natural death. Some
are regretted by the licensee, i.e. us, and for some cases the Bills tendered by us are not paid by the
applicants.
Statistics show that on an average around 2 lac applications are submitted in a calendar year
across the 10 Mains Districts out of which little more than 1 lac get matured for execution.
The activities in the MASD System are broadly classified into seven stages.
Sl No
Application Stage
Inspection Stage
Letter Stage
Offer Stage
Bill Stage
6
7
Execution Stage
Pending stage
Deals with
Receiving of the application from, giving an
acknowledgement thereof and booking of an inspection
Carrying out of the inspection and scrutiny of inspection
report.
Sending of a standard letter to the applicant after carrying
out an inspection.
Sending of the offer letter to the applicant and receiving of
the compliances to be met by the applicant
Sending of the Bill to the applicant. Receiving payment of
the Bill.
Maturing a job after payment matching, sending the job to
site office and executing the work.
Keeping aside a matured job from execution due to noncompliance of any formalities on the part of the applicant.
The job is again re-matured once that compliance is met.
In MASD parlance item 1&2 are termed as Pre-MASD stage, item 2-5 are termed as MASD stage
and item 6&7 are termed as Post MASD stage.
Before 1976 the system for processing applications for supply of electricity was purely manual. The
office of the District Engineer, upon receipt of an application, used to arrange for a site inspection.
On the basis of the inspection report, if the District Engineer decides, an offer letter was sent to the
applicant requesting him to meet with certain compliances. On receipt of the compliances a manual
Bill for service charges was raised from the District Office and sent across to the applicant. After
the Bill is paid the supply is given and meter fixed by the Site Office and the Commercial
Department is advised to commence the monthly billing.
From 1976 the MASD system became partially computerized, the computerization was mainly
oriented at Computer House. It continued till 1986 when Mains Dept. started computerization of
MASD system at users level, i.e. at District Office end. This System is known as Pre-Fast Track
MASD System. The basic flow of the business process was as below:
317
1. The applicants used to submit an application in Provisional Requisition form (PRF), which are
available at District Offices free of cost.
2. On receipt of the PRF, the static data (name, address, load, rate category etc.) are entered in the
counter and a zone code is given. The system allocates a MR No. and an Inspection Date and a
slip is printed in two parts, showing the MR No. and inspection date, one part of which is handed
over to the applicant across the counter. The format of MR Number is xx/yyyyy/zz, where xx =
Two digit District Code, yyyyy = Running Serial Number and zz = Year Code.
3. On the appointed date the Inspector Concerned (IC) carries out the requisite inspection,
furnishes the report onto the RC and submits to the District Engineer (DE).
4. DE scrutinizes the report and gives his decision on the RC. The decisions predominantly varies
around three broad categories, viz. i) Offer (where DE intends to offer a new supply), ii) letter
(where any kind of correspondence with the applicant is felt necessary) or iii) Further Appointment
(F/A).
5. Where a letter is to be sent, the same is typed out on a Letterhead stationary and sent across
through post after DE has signed the same. Sometimes pre-printed standard formats are used and
the typist strikes off appropriate portions.
6. Where an Offer Letter is to be sent, the same is typed out on Letterhead stationary and sent to DE
for his signature. The forms pertaining to statutory and/or specific compliances are attached with
the offer letter before it is dispatched by post. Test Form (TF) is one such statutory compliance. By
filling up this form a Govt. licensed Electrical Contractor certifies that the wiring installation of the
applicant is drawn by him under supervision of a licensed supervisor and is tested ok. The applicant
is required to meet this compliance by submitting this TF duly filled in by the Govt. Licensed
Contractor and Supervisor having respective license valid up to date.
7. If the inspection carried out at site turns out to be ineffective, for any reason whatsoever, and
cannot help DE to take a firm decision until a re-inspection is made, then it necessitates for a F/A.
In such event another appointment is fixed and the applicant is intimated through post card, and the
process recycles.
8. The RC, which is the master document containing all information pertaining to an application,
also contains a formatted portion (see Appendix-4) where the technical information are entered in
terms of specific codes. These codes were designed by IT Department and they consider the RC as
a Data card and termed D-01. When the applicant meets all compliances then one clerk codifies
the D-01 portion in the RC. The codified RCs are then sent to IT Department at Computer House
where all static information like MR No, name, address etc. along with the codes for technical
details are entered in the computer. The RCs are then sent back to the respective District Office.
9. After the details are entered in IT Department, they print a D-03 form and send it to the
concerned Regional Office of Commercial Department. The D-03 form is meant for allocation of
consumer number, which is done by the DR Section of Commercial Department. Before
allocating the consumer number the Commercial Department checks for existence of any
Outstanding (OS) amount lying recoverable in the premises where the supply in question is
requisitioned for. If any such OS is detected, then the DR Section refers the application to OS
section and the applicant is advised by letter to settle the OS. Once the OS is cleared then the DR
section allocates a consumer number, enters in the D-03 form and sends back to Computer House
for data entry.
10. The IT Department at Computer House then prints the MASD Bill and sends it to the applicant
by post. The MASD Bill comprises both Service Charge (MA part) and Security Deposit (SD part)
and also contains the allocated consumer number. A Bill Register is printed at Computer House and
sent to the respective Mains District, who in turn dockets the Bill date, Bill Amount etc. in the
manual Master Register as well as on the RC.
318
11. The applicant pays the MASD Bill at the concerned Regional Office cash counter. The stub
portion goes for data entry. Once the payment data is entered and matched at IT Department,
another form called D-07 is printed and sent to respective District Office. D-07 is known as
Payment Advice cum Meter Installation Order.
12. The District Office, on receipt of the D-07 form, dockets the payment date on Master Register
and RC and matures the job. The matured RC, attached with D-07, is then sent to Site Office for
execution of job.
13. The job (new service / new load in existing service / shifting / strengthening / alteration of
service etc.) is executed from Site office and meter is fixed or exchanged, as the case may be. The
detail of meter installation / exchange is furnished both on the RC and on D-07. The D- 07 forms,
duly filled in, are then sent across to Computer House for entry of meter details.
14. Once the meter details are entered, IT Department generates the Meter Page and sends to
Commercial Department for inclusion in the Meter Book and monthly meter reading commences
from the next reading date.
In the later stage some of the standard letters and the offer letters were being printed through the
System. The Offer letter contained only service charge comprised of Material and Labour. There
was no mention of the Security Deposit in those offer letters. To begin with, the System used to
calculate the service charge for loop cases only. Later on it started calculating service charges for
the direct services as well. The service charges for all other cases were computed and entered into
the system manually. This system continued to 1995 till the FAST TRACK MASD System came
into being in Calcutta Central District.
The FAST TRACK MASD System, which was indigenously conceived and developed by the
Mains MIS Cell, not only alleviated all the shortcomings of its earlier system but also computerized
all the activities of Mains District Offices. It embarked in Calcutta Central District followed by
North Suburban District in 1995, and thereafter proliferated slowly and gradually in other Regional
/ District offices till it was implemented in NRO in year 2001.
The major advantages of FAST Track MASD System are enumerated below: 1. Not all the applications are sent for inspection. Applications submitted at the PRF counter in
District offices are rather passed through OS checking by Commercial staff first and only those
cases are sent for inspection where OS is not present.
2. Most of the Standard Letters and the Offer Letter are computerized. The estimated amount in
the offer letter comprises both Service Charge and Security Deposit. Before printing of the offer
letter the technical data including the D-01 codes is codified in the System in two parts viz. Job
Detail 1 & Job Detail 2 (i.e. JD-1 and JD-2).
3. The traditional practice of sending of original RC to Computer House for data entry is done away
with. A great operational inconvenience is thus avoided.
4. Instead of generating the MASD Bill at Computer House, it is generated at the concerned District
Office after all compliances are met. This MASD Bill, however, does not bear the allocated
consumer number; thereby the wastage of man hour as well as redundant consumer number could
be avoided.
5. IT Department is provided with all static, technical and commercial information pertaining to the
paid MASD Bills through one Master Input data file (M1FT) twice a week.
6. The Commercial Department allocates the Consumer number at this stage only, thereby
rendering the workload of consumer number allocation to optimum level. The allocation of
consumer number thus became a parallel operation while a case gets matured for execution once the
MASD Bill is paid. This saves a lot of time.
319
7. The generation of D-07 form at IT Dept. end is also done away with. Instead a new instrument
called Job Tag is generated in two parts, which serves the purpose of Meter slip at job site. The
detail of meter installation / exchange is to be furnished on it at site office and returned to the
District office for Meter details entry.
8. The data pertaining to Meter installation/exchange details are sent through another data file
(M3FT) twice a week from Regional/District Office Server to IT Dept, who in turn, collates the
information with Master Input and allocated consumer number and generates the Meter Pages.
Over a period of time the following modernisations were done to the FAST Track MASD System.
1. Bar coding of the MASD Bill was introduced.
2. The process of entry of payment details from the stub portion of the Bills was done away with.
Treasury Dept. started to send data in flat files initially through Floppy Disk, and finally across
CESCs Intranet. The payment files are received centrally at one location by Mains MIS and then
re-distributed to concerned Regional Servers for payment matching programmatically.
3. Entry of meter details was discontinued since the data pertaining to meter installation / exchange
started flowing from SOS (Site Office System) to MASD System through the CESCs Intranet.
The detailed activities of FAST Track MASD System are furnished in a logical flow chart in
Appendix-1 attached herewith.
The above process has been running steadily till such time the Electricity Act 2003 came into force
with a policy by the Central Govt. encouraging the private sector for participation in generation,
transmission and distribution as also with a view to harmonizing and rationalizing the provisions in
the Indian Electricity Act, 1910, the Electricity (Supply) Act, 1948 and the Electricity Regulatory
Commissions Act, 1998 in a new self-contained comprehensive legislation.
In terms of section 82 of the Electricity Act 2003, every State Government had to constitute a
Regulatory Commission for the State and accordingly West Bengal Electricity Regulatory
Commission (WBERC) was constituted in our state.
In exercising the powers conferred to WBERC by clause (za) and clause (zb) of sub-section (2) of
section 181 of the Electricity Act 2003, the Regulations on the matter pertaining to New
Connection were notified in Notification No. 16/WBERC dated 09.06.2004, which was published
on 15.06.2004 in the Kolkata Gazette, extraordinary. These Regulations were titled as The West
Bengal Electricity Regulatory Commission (Standard of Performance of Distribution Licensees
Relating to Consumer Services) Regulations, 2003. Subsequently, the aforesaid notification was
repealed and replaced by Notification No. 24/WBERC dated 18.10.2005, which was published on
19.10.2005 in the Kolkata Gazette, Extraordinary. These Regulations were titled as The West
Bengal Electricity Regulatory Commission (Standard of Performance of Distribution
Licensees Relating to Consumer Services) Regulations, 2005. The regulations pertaining to
Temporary Supply were, however, covered under
Notification No. 22/WBERC dated 28.09.2005, which was published on 14.10.2005 in the Kolkata
Gazette Extraordinary and titled as The West Bengal Electricity Regulatory Commission
(Recovery of Expenditure for Providing New Connection) Regulations 2005.
The above two Notifications have brought in many changes in procedures and conventions which
deviate from what was being practiced so far. It has, therefore, became incumbent on the Company
to modify the existing MASD System so as to incorporate those directions stipulated in the
Regulations.
Accordingly a modified WBERC compliant MASD System was conceived, which is named as
New MASD System.
The salient features of the Regulations stipulated in Notification No. 24/WBERC are as follows:-
320
Annexure B Form, through which, upon receipt of the Estimate/Bill for the expenditure to
be borne by him/her, an applicant would request the distribution licensee for connection.
(Please see Appendix3 for Annexure-B form). This is basically an agreement between
the Licensee and the Applicant.
Cost of these two forms is Rs. 5 each. (For Temporary Supply cost of Annexure A Form is Rs.
10).
2 An Earnest Money is to be Deposited (EMD) by the applicants along with the submission of
Annexure A the deposits being:
1 (one) month
45 days
90 days
3 months
321
8. Failure to release new connection within the due time frames will render the Company liable to
pay Compensation.
9. System should be able to refund / forfeit EMD as the case may be
10. Refund of EMD can be through cheques/ drafts or by adjusting against future electricity
consumption bills.
11. System should be able to flag the Compensation amount automatically for
any default.
12. For Temporary Supply Applications:
(As per Notification No. 22/WBERC dated 28.09.2005)
322
START
APPLICANT DEPOSITS
ANNEX .A WITHEMAT
RECIONAL CASH
COUNTER
CASHIER TO
ACCEPTEMAT CASH
COUNTER
APPLICANT RECEIVES
RECEIPTED ANNEX .A
FROMRECIONAL CASH
COUNTER
APPLICANT SUBMITS
RECEIPTED ANNEXURE A
MAINPRF COUNTER
DATAENTERED &
APPLICANTGETS
INSPECTION DATE
APPLICANT CETSRECEIPT
PART OF AMMEXURE A AT
MAINSPRF COUNTER
MASD SYSTEM
GENERETESINSP.
DATA & LETTER. CLERKHANDS
OVERLETTER TO APPLICANT
END
Application
sent for
inspection
FOR OFF-LINE
CHECKING OF O/S
& LCC ISSUES
323
COMMERCIAL DEPARTMENT
START
DATA AVAILABLE
ON-LINE TO COMM
DEPT FOR O/S
COMM DEPT
CHECK.ES FOR O/S
AT BACK OFFICE
DE CODIFIFS
FORLETTER/
OFFER/FA
ETC
INSPECTOR
SUBMITS
REPORT FROM
HIS DESK TOP
PC THROUGH
COIR
START
DATA AVAILABLE
ON-LINE TO LCC
CHECK.ING
PILFERAGE PRESENT
/NOT PRESENT MARKED
FOR SENDING
FEEDBACK TO MAINS
COMM DEPT
CHECK.ES FOR O/S
AT BACK OFFICE
ON-LINEUPDATION OF
LCC STATUS TO MAINS
END
324
START
IF O/S & /OR LCC PRESENT AS
PER FEEDBACK
CORRESPONDING LETTER(S)
ARE SENT EVEN IF CODIFIED
FOR OFFER
INSPECTION CODIFIES
INSPECTION REPORSFOR:
DIRECTSVC
& LOOPS
EXTENSION
CASES
INSPECTORS TO
CODIFY REPORTS
THROUGH COIR
SOFTWARE FROM
DESKTOP PCS
ALT/SHFTI
NG/ETC
LETTER/FA/
OS/LCC
SYSTEM ADJUSTS
EMBEFOR MASD
BILL PRINTING
SYSTEM
CALCULATES SVC
CHARGE AND SD
FOR ALL TYPES OF
OFFER
325
START
START
APPLICANT SUBMITS IF
ETCATCOMPLANT
COUNTER MAINS
APPLICANT SUBMITS IF
ANNEX. B IN DUPLICATE, AT
COMPLANT COUNTER OF
MAINS
CLERK AT COUNTER
UPDATES MASD OF
COMPLIANCES MET
COMPLIANCES LINKED UP
WITH FILE OF PPS.
ANDFILED.
TREASURE FORWARDS
PAYMENT ADVISE TO
MAINS MIS CELL
SYSTEM MATCHES
PAYMENT & UPDATES
MASD ACCORDINGLY
IF ALL OMPLIANCES
MET- JOBREADY FOR
EXECUTION
END OF MIFTSTAGE
326
START
START
CLERK SEPARATES
ORIGINAL & XEROX OF
ANNEX. B
ORIGINAL ANNEX. B
WITH LIST FOR DELIVERY
TO APPL. HANDED TO
COURIER
COURIER DELIVERS
ORIGINAL ANNEX. B &
RETURNS POD TO
DISTRICT FOR FILING.
ANNEX.B PROCESSENDS
327
START
MASD UPDATES
FINANCE DATA IN TO
SYSTEM.
SYSTEM PREPARESM3FT
FILES FOR ALL CASES.
ANNEX. B, & IF
TO COMM. DEPT.
FOR SCANNING
328
The New MASD System is Graphical User Interface (GUI) based and is designed to operate on
windows platform under Client-Server architecture with Power Builder 10.5 as the front-end tool
and Oracle 10g as the backend RDBMS. This Oracle-10g would reside in a Sun Fire V890-V890
Central Server cluster (8 nos. 2.1 GHz SUN Ultra SPARCIV CPUs, 40 GB RAM and 5 TB
SAN Storage) residing at IT Department at Computer House. The client machines are Intel
PentiumIV Branded PCs with 512 MB RAM and 80 GB Hard disk. LaserJet Printers will replace
all the Dot Matrix Printers that are presently in use in Fast Track MASD System.
The New MASD System has, therefore, to handshake with the systems of other Departments as
well. The critical Interface Modules are described as below:
329
Page 1
Start
Provisional Requisition
Form received.
From the applicant
O/S liability against the premises is
checked by the operator of Com.
Dept. at Mains Enquiry Counter from
the terminal hooked with
Commercial computer
O/S
Present?
Printing of RC (D01)
330
Page 2
A
LCC Clearence Reqd?
Address locked/unlocked
by LCC Dept. through
flat files (lccadd / lccdel)
at any stage
O/S
settled by
Applicant
Clearance to Mains
Dept. through OS18
flat file generated by
Com. Dept.
After codification at
clerical section 2nd phase
codification at the
terminal by EDP
operator.
OK for
supply?
Signature of
DE
Compliances
received
within
stipulated
period?
Data entry
for
reinspection
Re-inspection
done at site &
report submitted
(See Page no. 1)
331
Page 3
Despatch
Submission of compliances by
applicant
Compliance
received within
stipulated
period ?
END
Dispatching the
MASD bill.
Payment of
MASD bill
within two
months at
cash
332
Page 4
C
Payment files are processed at Central
server of Mains Dept and forwarded to
respective Regional server.
Correction of error
files at Mains
Dept.
**)
Accepted
after Data
validation
at IT Dept?
Dispatch letter.
Job ready
for
execution /
meter
333
Page 5
Consumer no.
allocated from
Com. Dept. against
Meter installation
details (M3FT) &
Svc. Completion
(M4FT) to IT
Dept. is sent
through network.
Data of
M1FT,M3FT,
M4FT,Com file
validated?
Forwarding error
file to Com. Dept
Error in
Consumer No.
Allocation?
through Network
334
Page 6
END
335
Conversion Table
1 HP = 746 Watt
1 KWatt = 1.34 HP
Resistivity (m) at 20 C
1.5910-8
1.7210-8
2.8210-8
1.010-7
2.210-7
Sl. No
IS No.
1 IS 335: 1993
2 IS 11182 (Part 1) : 1984
3 IS 11182 (Part 2) : 1984
4 IS 11182(Part 3/Sec 1) : 1986
Relevant IS Codes
DESCRIPTION
New insulating Oils (fourth revision)
Guide for evaluation of insulation systems of electrical equipment: Part
1 Identification, evaluation and ageing mechanism
Guide for evaluation of insulation systems of electrical equipment: Part
2 Thermal endurance test procedure.
Guide for evaluation of insulation systems of electrical equipment: Part
3 Electrical endurance test procedures, Section 1 General considerations
and evaluation procedures based on normal distributions
Guide for evaluation of insulation systems of electrical equipment: Part
3 Electrical endurance test procedures, Section 2 evaluation procedures
based on extreme value distribution.
Guide for evaluation of insulation systems of electrical equipment: Part
5 Mechanical endurance fuctional tests.
Guide for evaluation of insulation systems of electrical equipment: Part
6 Performance evaluation based on service experience and functional
tests.
Guide for evaluation of insulation systems of electrical equipment: Part
7 Multifactor functional testing, Section 1 Test procedures.
Test procedure for measurement of loss of tangent angle of coils and
bars for machine winding-guide
Code of practice for selection, installation and maintenance of
switchgear and controlgear : Part 1 General.
Code of practice for selection, installation and maintenance of
switchgear and controlgear : Part 2 Selection.
Code of practice for selection, installation and maintenance of
switchgear and controlgear : Part 3 Installation.
Code of practice for selection, installation and maintenance of
switchgear and controlgear : Part 4 Maintenance.
Sl No.
IS No.
14 IS 3427 : 1997
15 IS 9135 : 1979
16 IS 9920 (Part1) : 1981
17 IS 9920 (Part 2) : 2001
IS 9920 (Part 3)
18 IS 9920 (Part 4) : 1985
19 IS 13118 : 1991
20 IS 692 : 1994
21 IS 1255 : 1983
22 IS 3961 (Part 1) : 1967
23 IS 3961 (Part 2) : 1967
IS 3961 (Part 3)
IS 3961 (Part 3)
24 IS 5819 : 1970
25 IS 5831 : 1984
26 IS 7098 (Part 2) : 1985
27 IS 7098 (Part 3) : 1993
DESCRIPTION
A.C Metal enclosed switchgear and controlgear for rated voltage above
1kV upto and including 52 kV (first revision)
Guide for testing of circuit breakers with respect to out-of-phase
switching
Switches and switch isolators for voltages above 1000V : Part 1General
and definitions.
High voltage switches : Part 2 High voltage switches for rated voltages
of 52 kV and above (first revision)
Design & Construction
Switches and switch isolators for voltages above 1000V : Part 4 Type
tests and routine tests.
General requirements for circuit breakers for voltages above 1000 V
(Superseding all Parts and Sections of IS 2516)
Parer insulated lead sheathed cables for rated voltages upto and
including 33 kV (third revision)
Code of practice for installation and maintenance of power cables upto
and including 33 kV rating (second revision )
Recommended current ratings for cables : Part 1 Paper insulated lead
sheathed cables.
Recommended current ratings for cables : Part 2 PVC insulated and
PVC sheathed heavy duty cables.
Rubber insulated Cable
PVC insulated Cable
Recommended short circuit ratings of high voltage PVC cables
PVC insulation and sheath of electric cables (first revision)
Crosslinked polyethylene insulated PVC sheathed cables : Part 2 For
working voltages from 3.3 kV upto and including 33 kV (first revision)
Crosslinked polyethylene insulated thermoplastic sheathed cables : Part
3 For working voltages from 66 kV upto and including 220 kV.
EQ.IEC No.
IEC 60298 (1990)
Sl No.
IS No.
DESCRIPTION
Methods of test for cables : Part 43 Insulation resistance.
Methods of test for cables : Part 45 High voltage test.
Direct acting indicating analog electrical measuring instruments and
their accessories : Part 1 general requirements (Third revision)
Direct acting indicating analog electrical measuring instruments and
their accessories : Part 2 Ammeters and voltmeters (Second revision)
Direct acting indicating analog electrical measuring instruments and
their accessories : Part 3 Wattmeters and varmeters (Second revision)
Direct acting indicating analog electrical measuring instruments and
their accessories : Part 4 Frequency meters (Second revision)
Direct acting indicating analog electrical measuring instruments and
their accessories : Part 5 Phase meters, power factor meters and
synchroscope (Second revision)
Direct acting indicating analog electrical measuring instruments and
their accessories : Part 6 Ohmmeters (impedence meters) and
conductance meters (Second revision)
Direct acting indicating analog electrical measuring instruments and
their accessories : Part 7 Multifunction instruments (Second revision)
Direct acting indicating analog electrical measuring instruments and
their accessories : Part 9 Test methods (Second revision)
Insulation resistance testers, hand operated (magneto generator type)
(Second revision)
Safety requirements for indicating and recording electrical measuring
instruments and their accessories : Part 1 Common safety
requirements for instruments.
Safety requirements for indicating and recording electrical measuring
instruments and their accessories :Part 2 Safety requirements for
instruments using a mains supply.
EQ.IEC No.
Sl No.
IS No.
41 IS 11287 : 1985
42 IS 11599 : 1986
43 IS 11994 : 1986
44 IS 12784 (Part 1) : 1989
45 IS 14570 : 1998
IS 11448 : 2000
IS 12346 : 1999
IS 13010 : 1990
IS 13779 : 1999
52 IS 14697 : 1999
53 IS 325 : 1996
54 IS 900 : 1992
55 IS 4029 : 1967
56 IS 4691 : 1985
57 IS 4722 : 2001
58 IS 4728 : 1975
DESCRIPTION
Bridge insulation testers (Magneto generator type)
Portable ac clip-on-ammeters
Portable insulation resistance tester (mains operated)
Electrical measuring transducers for converting AC electrical
quantities into DC electrical quantities : Part 1 General purpose
transducers.
Electrical measuring transducers for converting AC electrical
quantities into DC electrical quantities : Part 2 transducers for outdoor
use.
Guide for testing, calibration and maintenance of AC electricity
meters : Part 1 Single phase whole current Watt-hour meters, class 2
(first revision)
Alternating current precision kilowatt-hour meters of class 0.5 for
testing purposes (first revision)
Application guide for AC electrical energy meters (first revision)
Testing equipment for AC electricity meters (first revision)
AC watt-hour meter, class 0.5, 1 and 2
AC static watthour meter (Class 1 and 2) (first revision)
AC static transformer operated watthour and varhour meters, class
0.2S and 0.5S Specification.
Three phase induction motors (first revision)
Code of practice for installation and maintenance of induction motors
(Second revision)
Guide for testing three phase induction motors
Degrees of protection provided by enclosure for rotating electrical
machinery (first revision)
Rotating electrical machines (second revision)
Terminal marking and direction of rotation for rotating electrical
machinery (first revision)
EQ.IEC No.
Sl No.
59
60
61
62
63
64
IS No.
IS 4889 : 1968
IS 5422 : 1996
IS 7132 : 1973
IS 7306 : 1974
IS 7816 : 1975
IS 12802 : 1989
65 IS 13107 : 1991
66 IS 13529 : 1992
67 IS 13555 : 1993
68 IS 2026 (Part 1) : 1977
69 IS 2026 (Part 2) : 1977
70 IS 2026 (Part 3) : 1981
71 IS 2026 (Part 4) : 1977
72 IS 2026 (Part 5) : 1994
73
74
75
76
IS 3151 :1982
IS 3639 : 1966
IS 5553 (Part 1) : 1989
IS 5553 (Part 2) : 1990
DESCRIPTION
Method of determination of efficiency of rotating electrical machines.
Turbine type generators (first revision)
Guide for testing synchronous machines
Methods for determining synchronous machine quantities from tests
Guide for testing insulation resistance of rotating electrical machines.
Temperature rise measurement of rotating electrical machines.
Guide on measurement of winding resistance of an AC machine
during operation at alternating voltage.
Guide on effects of unbalanced voltage on the performance of three
phase cage induction motors
Guide for selection and application for three phase AC induction
motors for different types of driven equipment.
Power transformers : Part 1 general (first revision)
Power transformers : Part 2 Temperature rise
Power transformers : Part 3 Insulation level and dielectric tests
(Second revision)
Power transformers : Part 4 Terminal marking, tapings and
connections (first revision)
Power transformers : Part 5 Transformer/Reactor bushings minimum
external clearance in air Specification
Earthing transformers (first revision)
Fitting and accessories for power transformers
Reactors: Part 1 General.
Reactors: Part 2 Shunt reactors.
Reactors: Part 3 Current limiting reactors and neutral earthing
reactors.
Reactors: Part 4 Damping reactors.
Reactors: Part 5 Tuning reactors.
Reactors: Part 6 Earthing transformers (Neutral couplers)
EQ.IEC No.
IEC 34-3 (1988)
IEC 34-1 (1969)
IEC 34-4 (1967)
IEC 34-1 (1983)
IEC 60279 (1969)
Sl No.
IS No.
81 IS 6600 : 1972
82 IS 8468 : 1977
83 IS 8478 : 1977
84 IS 10028 (Part 1) : 1985
85 IS 10028 (Part 2) : 1981
86 IS 10028 (Part 3) : 1981
87
88
89
90
91
IS 10561 : 1983
IS 11171 : 1985
IS 13964 : 1994
SP 31 : 1986
IS 3043 : 1987
DESCRIPTION
Guide for loading of oil immersed transformers.
On-load tap changers
Application guide for on-load tap changers
Code of practice for selection, installation and maintenance of
transformers: Part 1 Selection.
Code of practice for selection, installation and maintenance of
transformers: Part 2 Installation (Superseding IS : 1986)
Code of practice for selection, installation and maintenance of
transformers: Part 3 Maintenance (Superseding IS : 1986)
Application guide for power transformers.
Dry type power transformers.
Methods of measurement of transformer and reactor sound levels.
Special publication chart on treatment for electrical shock
Code of practice for earthing
Guide for safety procedures and practices in electrical work : Part 1
General (first revision)
Guide for safety procedures and practices in electrical work : Part 2
Life saving techniques (first revision)
Guide for short circuit current calculations in three phase AC systems
(superseding IS 5728)
Calculation of effects of short circuit current (superseding IS
5728 : 1970)
Tungsten filament general service electric lamps (third revision)
Electric passenger and goods lifts (first revision)
Electric passenger and goods lifts (first revision)
Capacitors for surge protection for use in voltage system above 650 V
and upto 66 kV.
Shunt capacitors for the self healing type for AC power systems
having rated voltage upto and including 650 V
EQ.IEC No.
Sl No.
IS No.
DESCRIPTION
Requirements for ageing test, self healing test destruction test on shunt
capacitors of the self healing type for AC power systems having a
rated voltage upto and including 650V
Shunt capacitors of non self healing type for AC power systems
having a rated voltage upto and including 650V
Shunt capacitors having AC power systems having a rated voltage
above 1000V: Part 1 General performance, testing and rating safety
requirements Guide for installation and operation (Superseding IS
2834 : 1986)
Shunt capacitors for AC power systems having a rated voltage above
1000V: Part 2 Endurance testing.
Lightning arresters for alternating current systems : Part 3 Metal oxide
surge arresters without gaps for AC systems.
Surge arresters: Part 1 Non-linear resistor type gapped surge arresters
for AC systems [superseding IS 3070 (Part 1)]
Surge arresters: Part 5 Selection and application recommendations
(superseding IS 4004)
Current transformers: Part 1 General requirements (second revision)
Current transformers: Part 2 Measuring current transformers (second
revision)
Current transformers: Part 3 Protective current transformers (second
revision)
(Part 4) : 1992 Current transformers: Part 4Protective current
transformers for special purpose applications (second revision)
Voltage transformers: Part 1 General requirements (second revision)
Voltage transformers: Part 2 Measuring voltage transformers (second
revision)
Voltage transformers: Part 3 Protective voltage transformers (second
revision)
EQ.IEC No.
IEC 60831-2 (1988)
IEC 60931-1 (1989)
Sl No.
IS No.
IS 4146 : 1983
IS 4201 : 1983
IS 5547 : 1983
IS 6949 : 1973
IS 11322 : 1985
IS 3637 :1966
IS 1887 : 1966
IS 9385 (Part 1) : 1979
IS 1554 (Part 1)
IS 7098 (Part 1)
IS 7098 (Part 2)
IS 7098 (Part 3)
IS 8130
IS 2713
IS 398 (Part 2)
DESCRIPTION
Voltage transformers: Part 4 Capacitor voltage transformers (second
revision)
Application guide for voltage transformers (first revision)
Application guide for current voltage transformers (first revision)
Application guide for capacitor voltage transformers (first revision)
Summation current transformers
Method for partial discharge measurement in instrument transformers
Gas operated relays.
D-type fuses
High voltage fuses: Part 1 current limiting fuses
High voltage fuses: Part 2 Expulsion and similar fuses (superseding IS
5792
High voltage fuses: Part 3 Application guide for high voltage fuses
High voltage fuses: Part 4 Determination of short circuit power factor
for testing of high voltage fuses.
High voltage fuses: Part 5 Types and dimensions of fuse-links for
current limiting fuses.
High voltage fuses for the external protection of shunt power
capacitors.
Application guide for the selection of high voltage fuses for
transformer circuit applications.
PVC insulated Cable upto 1.1kV
XLPE insulated Cable upto 1.1kV
XLPE insulated Cable from 3.3kV to 33kV
EHV grade XLPE insulated Cable
Conductor Specification
Overhead Pole Specification
ACSR Conductor specification
EQ.IEC No.
IEC 60186 (1987)
IEC 60502
IEC 60840