Project Initiation
Project Initiation
Project Initiation
PHILIPPINES
DEPARTMENT OF
ARCHITECTURE
COLLEGE OF ARCHITECTURE AND FINE ARTS
PROJECT INITIATION
SUBMITTED TO.
ARCH. BALBERO
SUBMITTED BY:
PROJECT INITIATION:
Project initiation is where all the necessary analysis is undertaken to
allow the project to be planned. Initiating a project usually involves a
considerable amount of work, and therefore expenditure.
During this period a thorough analysis must be taken and recorded of
how any business processes, that the project will affect, are
structured, staffed, and run. Measurements should be taken at this
point that will be key or critical success factors of the project e.g. if
the project aims to increase the rate of data entry of forms to a
computerized system then a comparison cannot be made at the end
of the project if initial measurements during the old business process
do not exist.
PROJECT INITIATION
4.1
One of the biggest decisions that any organization would have to make is
related to the projects they would undertake. Once a proposal has been
received, there are numerous factors that need to be considered before an
organization decides to take it up. The most viable option needs to be
chosen, keeping in mind the goals and requirements of the organization.
Project Selection
Project Selection is a process to assess each project idea and select
the project with the highest priority. Projects are still just suggestions
at this stage, so the selection is often made based on only brief
descriptions of the project. As some projects will only be ideas, one
may need to write a brief description of each project before
conducting the selection process.
it means the easiest projects with the greatest benefits are given
priority.
Why Do Project Selection
Often one will have a number of suggested projects but not enough
resources, money or time to undertake all of the projects. The ideas
for eradication projects may have come from many sources including:
the community, funders, local and national governments and NonGovernmental Organizations (NGOs). One will therefore need a way
of deciding on a priority order and choosing a project.
If the organization in question has limited experience in conducting
eradications then it is recommended to concentrate on a small
number of projects, ideally one project at a time, until the people in
the organization have developed the skills and experience. Its
important to grow capacity and build up to undertaking multiple
projects at any one time. One should do the easy projects first and,
only then, work towards the most difficult and rewarding projects. One
should use the easy projects to help answer questions/solve issues
for the more difficult projects. Also, one should use the best
opportunities to learn.
A priority order for projects, that takes into account their importance
and how achievable the project is.
When to Do
Undertake a Project Selection when one has more ideas than the
number of projects one can undertake and need to select the project
that should be given priority.
Note: If one only has 1 project in hands, it may still be useful to score
the project against a set of criteria to identify the strengths and
weaknesses of the project. The results may be useful later in the
Feasibility Study Stage.
Diagram Overview
Each project idea is scored against the selection criteria and a total
project score is calculated. By ranking the ideas in order of the
highest score one is able to see which idea has the highest priority.
This procedure gives one the ability to take a number of possible
projects and identify which project is most important to first move to
the Feasibility Study Stage. This Stage is not required if one only has
one project idea. A diagram overview follows below:
Feasibility studies determine the viability of the project and help the
company determine if the product or service of the project is
marketable, profitable, safe, and doable.
Whats the criteria? Well, project selection criteria is an input to the
project Initiation process. According to the Guide to the PMBOK,
project selection criteria is concerned with the product of the project.
In other words, selection criteria is concerned with what the product
or service of the project will produce and how it will benefit the
company.
Benefit Measurement
and
The PM and his/her team could come up with certain criteria that
he/she wants his/her ideal project objectives to meet. The PM could
then give each project scores based on how they rate in each of
these criteria, and then choose the project with the highest score.
When it comes to the Discounted Cash flow method, the future value
of a project is ascertained by considering the present value and the
interest earned on the money. The higher the present value of the
project, the better it would be for the organization in question.
The rate of return received from the money is what is known as the
IRR. Here again, one needs to be looking for a high rate of return
from the project.
4.2
4.3
PRELIMINARY DESIGN
Existing Conditions
The first work on the project involves documenting the parameters
within which we will design. This typically includes assisting the owner
in obtaining a survey of the property, and a geotechnical analysis. If
the project is a renovation the initial work also includes measuring the
existing building. We also review the zoning and building codes and
regulations relevant to the project.
Schematic Design
Schematic Design: An initial design scheme that seeks to define the
general scope and conceptual design of the project including scale
and relationships between building components. At the end of
the schematic design phase the architect will present some very
rough sketches to the owner for approval.
Before beginning the actual design work, we work with our
clients to get a clear idea of their needs and desires for the project,
beginning with reviewing their answers to our Design Questionnaire.
Then, based on our clients' functional needs, aesthetic preferences,
and budget requirements, we prepare a number of sketches that
illustrate the basic design ideas. These are often hand-drawn, and
include a site plan, the floor plans, the most important elevations, and
a section or two. If we're working with an existing building for which
we've already generated an ArchiCAD 3D model during our Existing
Conditions work, we may present the Schematic Design on the
computer rather than in hand sketches. The 3D virtual model of the
exterior of the project allows us to look at the design from every angle,
and see the path of the sun across the project. Our clients find this
very helpful in understanding the design. This phase, like all of the
design process, is iterative. We create a design, and then get the
owners' feedback on it, and then refine the design, or even produce an
entirely new one, based on that feedback. The sketches provide
talking points. They bring out the issues, and help both client and
architect focus and move toward appropriate solutions. We take a first
pass at specifications for materials and assemblies to be used in the
work toward the end of this phase. Before proceeding to Construction
Documents, we recommend having a contractor or three develop "ballpark" estimates based on the Preliminary Design sketches, to make
sure we're on track with costs. If we need to, we can adjust the scope
and quality of the work to meet the owner's budget goals.
4.4
These phases are common to all new construction and renovation projects;
however, in smaller projects, the phases often become less formal, involve
fewer individuals and may have a short schedule of only a few months.
Large projects, on the other hand, may take years from the time they are
envisioned to the time "move-in" takes place. In general, the Department of
Facilities Planning and Construction (FP&C) provides leadership and
guidance, serves as a resource, and protects the interests of the college
throughout the entire duration of the project. The following describes each
phase of a large project:
Programming (2 to 6 months)
A building committee of approximately six individuals is formed to represent
the stakeholder group(s) involved with the project. The committee will be
responsible for making the necessary design decisions based upon user
requirements. One member of the committee will be designated as the
chair to act as liaison with the FP&C project manager. FP&C also serves
Pre-occupancy/Commissioning
FP&C arranges for contractors to provide training for Operations personnel
and others who will be responsible for operating and maintaining the
facility. Operations assume operational responsibility for the facility at the
time of initial occupancy. Well in advance of the projected occupancy date
(generally, at least sixty days), persons designated by the building
committee must:
Submit a comprehensive listing and schedule to the FP&C project
manager. The schedule identifies who is moving (i.e. "from where - to
where") and is used by the movers, IT and Operations.
Contact IT to arrange for the activation of select telephone and data
communications outlets.
Contact Operations to arrange for keys.
Moving
The FP&C project manager will hire professional movers, if required. The
building committee will designate the representative(s) to coordinate
specific move times with the faculty, staff and students involved. The
moving company will provide packing materials and instructions. Generally,
all packing is the responsibility of the parties being moved. The academic
unit is responsible for retaining technical, scientific, and any other special
equipment procurement and installation. Special arrangements can be
made through FP&C for equipment movers and hook-up of utilities when
needed.
Occupancy
At the time of initial occupancy, the FP&C project manager will give an
overview presentation and tour of the facility to designated
representatives. This will include an explanation of how the building is
zoned for thermal comfort, operation of appropriate building
components, the location of emergency equipment and exits, etc. The
operational and maintenance responsibility for the facility is turned
over to Operations at this time. All calls for service relating to the
building should be directed to Operations. The FP&C project manager
will be available to assist with resolution of warranty and postoccupancy construction issues.
4.5
4.6
CONTRACTUAL ARRANGEMENTS
The contractual arrangements will depend on the type of work being carried
out, although whichever type is adopted its purpose is to formalise the
relationship between the client and the contractor and sets out the rights
and responsibilities of the parties. The actual standard contract chosen will
also depend on the type of work and the practices and preferences of the
client.
In addition a contract which is often used for services contracts is the New
Engineering Contract (NEC).
The New Engineering Contract, or NEC Engineering and Construction
Contract is a formalized system created by the Institution of Civil
Engineers that guides the drafting of documents on civil
engineering and construction projects for the purpose of obtaining tenders,
awarding and administering contracts. As such they legally define the
responsibilities and duties of Employers (who commission work)
and Contractors (who carry out work) in the Works Information.
The NEC is an integrated set of contract documents that are designed to
provide Clients and their suppliers with project-focused outcomes. It aims
to ensure the achievement of Client's objectives for the projects in relation
to quality, performance, cost and time.
The clauses of these options can be adapted for low risk projects
and subcontractors by using:
This is the transferring the interests of one party to another. Neither the
employer nor the contractor may assign any part of the contract without the
written consent of the other party.
Subletting
This occurs where the contractor enters into a subcontract with another
party to carryout work whilst still maintaining the existing relationship with
the employer in all respects.
Subcontractors
The contractor cannot subcontract any part of the work without the written
consent of the architect or contract administrator. The employment of the
subcontractor is automatically terminated upon the determination of the
main contract.
A subcontractor is effectively treated the same as if they were the main
contractor, which would mean that materials or goods of a subcontractor
could not be removed from site once they were brought on without written
permission.
There are three types of subcontractor:
4.7
PHASES OF A PROJECT
1. Schematic Design
Well work with your program of requirements to sketch out some
initial rough drawings. Conceptual drawings without much detail,
but showing the relationship of each space to the other spaces. If
we were creating a painting, these would be very broad strokes
with a large brush. It develops the overall idea of the building,
and we begin to think about the major building systems like
structure, mechanical and electrical.
2. Design Development
Once youre satisfied with the schematic drawings well develop
them further, adjusting and refining as we go along. Well begin
to think about materials and colors as well as more specific
details about the building systems like what kind of structure,
ventilation, plumbing and electrical is best. These drawings may
be used to apply for Development Permits, present to
committees, for marketing, fundraising and other purposes.
3. Construction Documents
Now we develop enough detail so that a contractor could actually
build the design. We coordinate the work of the structural,
mechanical and electrical engineers to minimize discrepancies
between the various systems. We create written specifications
that dictate the performance and quality of each component of
the building. This phase accounts for about half the total design
fee because it takes so much time and effort.
4. Bidding and Negotiation
We help you review the results of the bidding process and award
a construction contract to the successful bidder. During this
phase we answer any questions from bidders and clarify the
drawings so that every contractor is bidding on the same
information, ensuring the process is fair.
5. Contract Administration
Once construction begins we work to ensure that the actual
building meets the intent of the design drawings. Well meet the
contractor on site at regular intervals to address any unexpected
problems as they come up. Well deal with any proposed
changes and prepare change orders which are the formal
method of changing the construction contract with an extra cost
or a credit.
4.8
PROJECT STRATEGY
Contribute refers to the assumption that the direction has an effect i.e., it
matters and makes a difference
Success refers to how well the project is able to accomplish its goals.
Environment refers to the world outside the projects boundaries with
which project as an open system must continuously interact.