C-4 - Proj-Sch 150506
C-4 - Proj-Sch 150506
C-4 - Proj-Sch 150506
TCE-4857A-C510-01
VOLUME II Part -I
SECTION: C 4
SHEET 1 OF 8
1.1
2.0
2.1
2.2
3.0
3.1
PLANNING
SEC shall prepare a Master Network Schedule in the form of PERT
network.. The network shall be prepared on a Work Breakdown Structure.
The master network shall identify milestones of key events of each
system/package in the areas of engineering, procurement, manufacture
and despatch.,. The master network shall represent the Level I plan and
form the basis for development of detailed second and third tier execution
plans.
The master network shall be submitted along with the bid and shall be
mutually discussed and finalised before the award of Contract. The
master network shall identify a complete list of inputs to be furnished by
the JSWEVL which may be required for proper interfacing and tie up.
Scheduled dates for providing such inputs shall also be indicated and the
same be mutually discussed and finalised.
ISSUE
R0
SPEC.NO.
TCE-4857A-C510-01
VOLUME II Part -I
SECTION: C 4
SHEET 2 OF 8
SEC shall not change the Master network without the prior approval of
the JSWEVL in accordance with the Conditions of Contract. In the event
that the JSWEVL approves a revision to the Master Network in
accordance with the Conditions of Contract, the SEC shall submit a
revised Master Network within two weeks thereafter. This programme
shall fully comply with the requirements of the specification and where
necessary, reflect changes to the sequence or progress of the Works as
indicated by the JSWEVL, or as proposed by the SEC and accepted by
the JSWEVL. Such an agreed revised programme shall become the
Overall SEC Programme for the outstanding works.
3.2
SEC, within 28 days after the date of the issue of the Issue of NTP shall
submit to the Engineer the detailed programme which shall be
consistent with the Project Schedule given above.
3.3
3.4
4.0
REVISION OF PROGRAMME
If the progress of the Scope of Supply or any other part of the Works
does not conform to the Programme, the JSWEVL / Engineer may
instruct the SEC to revise the programme.
If for any reason which does not entitle the SEC to an extension of time
the rate of progress of the Scope of Supply or part thereof is at any time
in the reasonable opinion of JSWEVL or the Engineer too slow to secure
completion of the works within the Time for Completion or any extended
date the JSWEVL may so notify SEC in writing and SEC shall thereupon
take such steps as are necessary and JSWEVL may approve an order to
accelerate (whether by re-programming the order or sequence of work or
by increasing the personnel or other resources of SEC or its sub-SECs
employed on the Scope of Supply) the progress of the Scope of Supply
or part thereof so as to achieve completion of each section by the Time
for Completion as may be extended. The SEC shall not be entitled to any
ISSUE
R0
SPEC.NO.
TCE-4857A-C510-01
VOLUME II Part -I
SECTION: C 4
SHEET 3 OF 8
5.1
5.2
SEC shall comply with the target/Milestone Schedule and to attend and
participate in progress, site co-ordination or special purpose meetings.
Progress, site and co-ordination meeting will be held at SECs
engineering office or the Site on a weekly basis, unless otherwise
requested by JSWEVL. SEC shall have in attendance at any such
meeting the Project Manager and other management workers authorised
to commit additional manpower to the Work and shall for any progress
meeting bring a forecast showing the last periods progress versus the
last periods
scheduled work plan and the work plan for the next
three weekly time periods. Unless otherwise stated in writing by JSWEVL
the forecast shall describe the Work by task, by site location, by area or
building and by bay for a one month period. The commencement and
completion of each task to be performed shall be clearly designated. If
requested by JSWEVL, representatives of Vendors of major materials
shall be at each such meeting. JSWEVL may on reasonable notice to
SEC call a special purpose meeting whether at SECs engineering office
or the site to review any portion of the Work, the performance of which is
of substantial concern to JSWEVL.
5.3
The SEC shall use the latest version of a project management software
preferably Primavera Project Planner to generate and submit the
schedules.
ISSUE
R0
CONSULTANTS: TCE CONSULTING ENGINEERS LIMITED
SPEC.NO.
TCE-4857A-C510-01
VOLUME II Part -I
SECTION: C 4
SHEET 4 OF 8
5.4
SCHEDULES
5.4.1
5.4.2
5.4.3
ISSUE
R0
SPEC.NO.
TCE-4857A-C510-01
VOLUME II Part -I
SECTION: C 4
SHEET 5 OF 8
(b)
(c)
Preliminary works
(d)
(e)
(f)
(g)
Shipment
and
erection
for
each
(i)
(j)
(k)
(l)
(m)
ISSUE
R0
SPEC.NO.
TCE-4857A-C510-01
VOLUME II Part -I
SECTION: C 4
SHEET 6 OF 8
PROCUREMENT SCHEDULE
The Procurement Schedule shall cover all equipment and materials to be
furnished by SEC, and critical items to be furnished by his sub-SECs,
manufacturers and suppliers as proposed by the SEC and accepted by
the JSWEVL. This schedule shall indicate times for bid invitation,
economic evaluation, ordering of materials, approval of manufacturers
drawings including JSWEVLs review, fabrication, shipping, delivery,
testing, and other significant Project milestones.
ISSUE
R0
SPEC.NO.
TCE-4857A-C510-01
VOLUME II Part -I
SECTION: C 4
SHEET 7 OF 8
5.7
5.8
MISCELLANEOUS SCHEDULES
The SEC shall prepare and submit to the JSWEVL miscellaneous
schedules covering plant operation, plant maintenance and training upto
substantial completion. Each schedule shall be in sufficient detail to
effectively control and monitor the associated activities. Each schedule
will be at the appropriate level of detail.
5.9
Apart from the overall Contract Schedule, SEC shall provide detailed
network schedules for manufacturing and site activities separately from
major sub-SECs for information and monitoring by JSWEVL / JSWEVLs
Representative.
5.10
ISSUE
R0
SPEC.NO.
TCE-4857A-C510-01
(g)
VOLUME II Part -I
SECTION: C 4
SHEET 8 OF 8
(a)
(b)
(c)
(d)
(e)
(f)
ISSUE
R0
CONSULTANTS: TCE CONSULTING ENGINEERS LIMITED