Feeder Protection Fundamentals
Feeder Protection Fundamentals
l Slide 2
October 29, 2013
Topics
System Overview
Fuses
Breakers/reclosers
Relays
CTs
Fuses
35 kV
12%
5 kV
6%
25 kV
20%
15 kV
62%
City Lights
Lightning
ABB Group
October 29, 2013 | Slide 8
Blackout
ABB Group
October 29, 2013 | Slide 9
Transformer Failure
Generator Failure
Fuse
R
Recloser
Relay
Transformer Primary
Sectionalizer
Relay
Feeder Circuit
Breaker in protective zone
Breakers controlled by protective relays
Reclosers
Sectionalizers
Lateral Tapped Fuses
Transformer
Secondary
End of
Line
Function of
Substation transformer
size (source impedance)
Distribution voltage
Fault location
10kA - majority
10-20kA - moderate
number
20kA - few
Application
Fuses
Breakers/Reclosers
Relay(s)
The sensors
PTs
CTs
Etc.
The interconnection
Distribution Protection
Reliability
DEPENDABILITY
The certainty of
correct operation
in response to
system trouble.
SECURITY
Reliability
DEPENDABILITY
SECURITY
Main1
Main 1
Main 2
Main2
Generator
Transformer
Bus
Transmission Lines
Motors
Zones of Protection
Station B
Station A
G
G
G
Station C
Station D
M
Zones of Protection
Station B
Station A
G
G
G
Station C
Generator
Protection
Station D
M
Zones of Protection
Station B
Station A
G
G
G
Station C
Transformer
Protection
Station D
M
Zones of Protection
Station B
Station A
G
G
G
Station C
Bus
Protection
Station D
M
Zones of Protection
Station B
Station A
G
G
G
Station C
Line
Protection
Station D
M
Zones of Protection
Station B
Station A
G
G
G
Station C
Motor/Feeder
Protection
Station D
M
Distribution Fuses
Fuse
R
Recloser
Relay
Relay
Sectionalizer
Distribution Fuses
Interruption rating
Curve characteristics
Minimum melt
Total clearing
Fuse Characteristic
1000
Time in Seconds
100
Total Clearing
(Interruption Time)
10
Minimum Melt
(Response Time)
1.0
0.1
Arc Clearing
10
100
Amperes
1000
10000
K link
100 A
Time in Seconds
100
Total Clearing
(Interruption Time)
Downstream
Upstream
10
1.0
0.1
10
100
Amperes
1000
10000
Fused Cutouts
Enclosed
Line terminal
Open Link
Fused Cutout
Line terminal
Porcelain
Housing
Line terminal
Silicon/Polymer
Support
Silicon/Polymer
Support
Mounting
Bracket
Mounting
Bracket
Mounting
Bracket
Fuse
Holder
Fuse Tube
Mounted Inside
Housing Door
Housing
Door
Arc
Arrester
Spring
Contacts
Open Link
Fuse Link
Line terminal
Line terminal
Fuse
R
Recloser
Relay
Relay
Sectionalizer
Operating mechanism
Electromechanical (spring charging)
Magnetic actuator
Magnetic actuator
No maintenance
2000 Operation
10,000 Operation
15kV/27kVBreaker
Single Bottle design
15kV & 27kV
Stored Energy or magnetic
Mechanism
38 KV Breaker
38kV
Two bottle per phase design
Stored Energy or Magnetic
Mechanism
Vacuum Interruption
MV Breaker Ratings
Voltage , kV
Continuous
Current, A
Interrupting, kA
BIL
Type X
R-MAG
Type R
R-MAG
Type V
15
15
27
27
38
1200 / 2000
1200 / 2000
1200 / 2000
12 - 25
12 - 20
12 - 25
25 - 40
110
110
125 - 150
125 - 150
150 - 200
Automatic Recloser
Single Phase
ABB Group
October 29, 2013 | Slide 46
WHAT IS
RELAYING
Relays
ABB Group
October 29, 2013 | Slide 49
Classification of Relays
Classification by Input
Pressure (Transformer)
Classification of Relays
Classification by Performance Characteristics
Overcurrent
Over/under voltage
Distance
Directional
Inverse time, definite time
Ground/phase
High or slow speed
Current differential
Phase comparison
Directional comparison
Classification of Relays
Classification by Technology
Electromechanical
Microprocessor-based (Digital/Numerical)
ABB Group
October 29, 2013 | Slide 54
Fuse
R
Recloser
Relay
Relay
Sectionalizer
Purpose
Provide isolation
Types
Voltage transformation
Current transformation
Rogowski coil
ABB Group
October 29, 2013 | Slide 60
ABB Group
October 29, 2013 | Slide 61
ABB Group
October 29, 2013 | Slide 62
D.C. Saturation of a CT
ABB Group
October 29, 2013 | Slide 63
ABB Group
October 29, 2013 | Slide 64
Time in Seconds
100
10
Breaker / Recloser
Interruption Time
1.0
Response Time
Contact opening
and arc clearing
0.1
100
1000
Amperes
10000
ANSI Numbers
50 - Instantaneous Overcurrent (No
intended delay)
10
Time in Seconds
0.1
50
0.001
0.1
PU 1 M1
10
100
1000
Extremely
Very
Inverse Inverse
Time in Seconds
0.8
0.6
0.4
0.2
Moderately
Inverse
Definite
Time
15
10
5
Current in Multiples of Pickup
20
Recloser Curves
Pickup tap setting typically is 2, but never less than 1.5, times the normal
maximum load interruption rating
Permissible Unbalance
Not above 25% of load current is typical rule-of-thumb, but some allow up to
50%
If2
If1
Time
T1
T2
If1
If2
Current
If3
Relay
Fuse
Recloser
Breaker
If1
Relay
Recloser
Fuse
Time
P3
Interrupt
Time
CTI
Total
Clearing
Response
Time
CTI
Minimum
Melt
ABB Group
October 29, 2013 | Slide 76
P1
P2 If1
If2
If3
Current
R
LOAD
SOURCE
Upstream
Source-side
Protected
Backup
ABB Group
October 29, 2013 | Slide 77
Downstream
Load-side
Protecting
Down-line
Local
(where you are)
If2M
If2M
Time
MIN
If1m
ABB Group
October 29, 2013 | Slide 78
MAX
If1M
If1M
LOAD
If1M
If2m
If1m
R
1. Determine critical fault current
locations and values of most
down stream device, and plot
Maximum If1M
Min Zs, at device
Minimum If1m
Max Zs, end of segment
Current
If2M
H
IRpu
Time
If2M
MIN
If1m
MAX
If1M
If1M
LOAD
If1M
If2m
If1m
R
1. Determine critical fault current
locations and values, and plot.
2. Set the pickup of the most
downstream device as sensitive
as possible
(0.5*If1m > IRpu > 2*LOAD )
Current
If2M
H
IRpu
Time
If2M
MIN
MAX
T2
If1M
LOAD
If1M
If2m
R
T1
If1m
If1M
If1m
Current
If2M
H
IRpu
MAX
Time
MIN
If2M
T2
CTI
If1M
LOAD
If1M
If2m
R
T1
If1m
If1M
If1m
Current
LOAD
If2M
H
IRpu
MAX
Time
MIN
If2M
T2
CTI
LOAD
If1M
If2m
R
T1
If1m
If1M
If1m
Current
LOAD
If2M
H
IRpu
MIN
If2M
MAX
LOAD
If1M
If2m
If1m
R
Coordination Time Interval
Time
T2
CTI
T1
If1m
If1M
Current
LOAD
If2M
If2M
H
IRpu
Time
MAX
MAX
T2
T1
If1M
If2m
If1M
If2m
If1m
MIN MIN
If1m
LOAD
4. Add CTI.
5. Determine critical fault current
locations for device H, and plot
Maximum If2M
Min Zs, at device
Minimum If2m
Max Zs, end of segment.
6. Plot operating times for H.
Current
If2M
LOAD
If2M
IRpuIHpu
If2M
H
Time
MAX
MAX
T2
T1
If1M
If2m
If1M
If2m
If1m
MIN MIN
If1m
LOAD
If2M
4. Add CTI.
5. Determine critical fault current
locations for device H, and plot.
6. Plot operating times of Relay H.
7. Select pickup settings for Relay H
(IHpu ) to operate for minimum
fault and not operate on
maximum load.
(0.5*If2m > IHpu > 2* Load or
compromise)
If2M
IRpu
IHpu
MIN
If2M
H
MIN
Time
MAX
T2
T1
ABB Group
October 29, 2013 | Slide 86
If1M
If2m
LOAD
If1M
If2m
If1m
MAX
If1m
If1M
4. Add CTI.
5. Determine critical fault current
locations for device H.
6. Plot operating times of Relay H.
7. Select pickup settings for Relay H.
8. Select time dial for Relay H so
curve passes through or above all
CTI points.
Current
If2M
If2M
IRpu
IHpu
Time
MIN
If2M
If1M
LOAD
If1M
If2m
MIN
MAX
MAX
If1M
ABB Group
October 29, 2013 | Slide 87
If1m
Current
If2M
If2M
IRpu
IHpu
Time
MIN
If2M
If1M
LOAD
If1M
If2m
If1m
MIN
MAX
MAX
T2
T1
If1M I
H50pu
Current
Total Clearing
(Interruption Time)
Time in Seconds
100
Downstream
Upstream
10
Maximum1.0
clearing time of
downstream fuse should be less than
75% of minimum melt time of
upstream0.1
fuse.
10
100
Amperes
1000
10000
Fuse - TC
Time in Seconds
100
10
Upstream
Recloser
Downstream
Fuse
100
Amperes
1000
10000
Those who allow miscoordination only permit it at high current levels where the
result is likely to be simultaneous fuse blowing and feeder tripping
I3Ph = 2300
I1Ph = 950
125E
100T
B
115 kV - 13.2/7.62
kV Grd Y
15/20/25 MVA
Z = 8% @ 15 MVA
Relay
Fuse
Recloser
100T
I3Ph = 6300
I1Ph = 6000
65T
I3Ph = 1100
I1Ph = 950
Assumptions
With 230A maximum load, select 560A phase pickup setting for the recloser
(240%)
Select 280A pickup for ground overcurrent element (50% of phase pickup)
Assuming 400:5 ct ratio for the substation relays, 330A max load = 4.125A
secondary
Select ground relay time-dial to coordinate with recloser ground curve. Select
phase relay time dial to coordinate with recloser phase curve
Phase overcurrent relay curve must also coordinate with transformer primary
side fuses and transformer frequent-fault capability
I3Ph = 2300
I1Ph = 950
125E
100T
B
115 kV - 13.2/7.62
kV Grd Y
15/20/25 MVA
Z = 8% @ 15 MVA
Relay
Fuse
Recloser
100T
I3Ph = 6300
I1Ph = 6000
65T
I3Ph = 1100
I1Ph = 950
www.abb.com/relion
ABB Group
October 29, 2013
| Slide 102