Estimation of Construction Projects: Prof. K. C. Iyer Civil Engineering Dept. IIT Delhi
Estimation of Construction Projects: Prof. K. C. Iyer Civil Engineering Dept. IIT Delhi
CONSTRUCTION PROJECTS
Prof. K. C. Iyer
Civil Engineering Dept.
IIT Delhi
PROJECT ESTIMATES
Estimating Fundamental part of construction industry
It is an approximation of the expected cost of the
project.
Financial commitments of project based on estimates.
Initially owner commits to the project based on
feasibility estimates.
Later designers develop scope of project within target
cost restraints.
Finally contractors commit their resources to the
project with profit being their motive.
Contd
Accurate estimates optimize good contracting.
Inaccurate estimates provide improper guidelines fro
project management.
Unrealistic targets produce unrealistic expectations.
Inaccurate estimates contribute to the squandering of
valuable resources.
Estimates an aid to decision making.
Contd
ESTIMATE CATEGORIES
Contd
Budget Estimates
Used for budgeting and authorization of funds
Provide an early basis for cost control
Definitive Estimates
Most accurate category
Available information consists of working drawings,
detailed specifications, and supplier and subcontractor price quotations.
Estimates include direct and indirect cost estimates
of materials, labor, equipment, engineering, support
staff, insurance, bonds, taxes, allowances,
contingencies and profit.
DEVELOP
EXECUTE
50%
20%
MOST PROBABLE COST
EXPECTED PERCENT
VARIANCE W/O
CONTINGENCY
0%
15%
10 - 15 %
-15 %
-30 %
ORDER OF
MAGNITUDE
BUDGET
80 % +
-5 %
AMOUNT OF
INFORMATION
AVAILABLE
DEFINITIVE
(DETAILED)
Contd
Information available is time dependent.
Estimates are updated continually as better information
becomes available.
Semi-detailed estimate is produced when engineering
is 30-50% complete.
Prefund appropriation phases(C & D) 10-15% of total
project information.
Implementation or execution phase(E) produces most
of procurement documentation.
Before construction begins, 80-90% information
available.
1.
2.
3.
4.
5.
C2 = C1*
I1
I2
Where,
C1 = known cost, time period 1
C2 = estimated cost, time period 2
I1 = index, time period 1
I2 = index, time period 2
LIMITATIONS OF INDICES
CONTD
Some
A Rs 2 Million
B Rs10 Million
C Rs 8 Million
D Rs 3 Million
E Rs 20 Million
Year 1
Year 2
0.5
1.5
4.0
Year 3
Year 4
Year 5
Year 6
Year 7
6.0
3.0
5.0
0.5
1.0
1.0
0.5
3.0
7.0
7.0
3.0
9.0
8.0
7.5
3.0
E
Total
0.5
5.5
9.5
=
=
=
=
=
=
=
0.52 million
6.26 million
11.78 million
12.17 million
11.79 million
12.05 million
5.25 million
2.
3.
CONTD
4.
5.
6.
CONTD
Summarize the direct costs for materials, labour and
equipment.
8. Obtain specialty contractor's bids.
9. Calculate the indirect costs which includes overhead,
payroll burdens, supervision, bonds, taxes, insurances,
materials other than direct materials, small tools,
rental of site facilities, site utility costs etc.
10. Add allowances to include those known items which
are not adequately defined.
7.
CONTD
Add contingency, which is an unknown but expected
cost.
12. Summarize the bid on a form.
13. Management will add profit to complete the bid.
RANGE ESTIMATING
CONTD
CONTD
CONTINGENCY
Contingency is a legitimate and anticipated cost
for unknowns to account for unforeseen elements
of cost.
Contingency is the amount of overrun that is
incurred if the job is bid with only what can be
seen from bidding documents.
Contingency is directly related to estimating
accuracy.
National and local factors to be considered
degree of industrialization, national political
objectives, infrastructure, legal and regulatory
systems.
Important Consideration : who assumes how
much risk.
ALLOWANCES
Bidder is asked to include a specified sum of
money for known items which have not been
adequately defined so that an accurate estimate is
made.
Cost adjustments are usually required to reflect
actual costs or bid revisions.
Allowances are included so that a total bid cost is
available for financing, bonding, and insurance
reasons.
THANK YOU