09amended Guidelines CPES
09amended Guidelines CPES
09amended Guidelines CPES
IMPLEMENTING GUIDELINES
FOR INFRASTRUCTURE PROJECTS1
1.
GENERAL
Section 12, Annex E of the Revised Implementing Rules and Regulation
(IRR) of R.A. 9184 or the Government Procurement Reform Act, requires all
procuring entities implementing government infrastructure projects to
evaluate the performance of their contractors using the NEDA-approved
Constructors Performance Evaluation System (CPES) guidelines for the type
of project being implemented. Section 12, likewise, requires all procuring
entities to include in their Projects Engineering and Administrative Overhead
Cost, the budget for CPES implementation pursuant to NEDA Board
Resolution No. 18 (s. 2002); to establish CPES Implementing Units in their
respective offices/agencies/corporations; and to use the CPES ratings for the
following purposes: a) pre-qualification/eligibility screening; b) awarding of
contracts; c) project monitoring & control; d) issuance of Certificate of
Completion; e) policy formulation/review; f) industry planning; g) granting of
incentives/awards; and in adopting measures to further improve performance
of contractors in the prosecution of government projects.
2.
OBJECTIVES
The CPES was developed in order to:
3.
2.1
2.2
2.3
SCOPE
The guidelines shall be used in the performance evaluation of constructors
undertaking government infrastructure projects as follows:
3.1
3.2
3.3
Full text of CPES Implementing Guidelines with amendments (in bold and underlined text) as approved by
the NEDA INFRACOM under Resolution No. 03, Series of 2011.
4.
DEFINITION OF TERMS
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
Head of the Procuring Entity - refers to: (i) the head of the agency or
body, or his duly authorized official, for NGAs and the constitutional
commissions or offices, and branches of government; (ii) the
governing board or its duly authorized official, for GOCCs, GFIs and
SUCs; or (iii) the local chief executive, for LGUs: Provided, however,
that in an agency, department, or office where the procurement is
2
4.13
4.14
4.15
4.16
4.17
4.18
4.19
4.20
Rate - the score for each item of work evaluated, derived using the
criteria in evaluating the workmanship and materials aspects.
4.21
4.22
Relative Rate - the product of the relative percentage weight and the
rate for each item of work.
5.
4.23
4.24
FUNCTIONAL/DEPLOYMENT FLOWCHART
The sequential activities to be undertaken by the CPES Implementing Unit
(IU),
Constructors
Performance
Evaluators
(CPE),
Constructor,
Implementing Office (IO), and Construction Industry Authority of the
Philippines
(CIAP)
are
presented
hereunder.
The
CPES
Functional/Deployment Flowchart is illustrated in Annex 1.
5.1
5.2
and fills out the CPES Evaluation Forms to be used for such
evaluation.
5.3
5.4
5.5
5.6
5.7
5.8
Meeting
among
CPE,
5.10
of the CAR(s), the CPE leader shall inform said engineer and/or
Authorized Representative that these shall be settled by an
appropriate adjudicating body to be designated by the agency. In
cases where the constructor and/or its representatives are absent
during the CPES project evaluation, even after advance and
proper notification, the CPES Rating of the constructor will be
considered final and binding.
e. Monitoring of Constructors Compliance on CAR by CPES-IU
To ensure and check constructors compliance on CAR, the
CPES-IU shall require the government project engineer to submit a
Monitoring Report to the concerned Implementing Office, copy
furnished the CPES-IU, to validate compliance with the CAR.
Emphasis should be on projects with Remove and Replace
proposed CAP and taking into consideration the pledged date of
corrective action by the constructor. If possible, photos shall be
attached to provide evidence on the works undertaken.
5.11
5.12
5.13
of
Reports,
and
6.
ASPECTS OF EVALUATION
The performance of the constructor shall be evaluated during construction
and upon completion of a project. The assigned weights and aspects to be
evaluated during construction and upon completion shall vary depending
on the kind of project as follows:
6.1
Maximum Rating
Workmanship
Materials
Time
0.40
0.30
0.15
8
Facilities
Environmental, Safety and Health (ESH)
Resources Deployment
Total
0.03
0.07
0.05
1.00
Maximum Rating
Workmanship
Time
Facilities
Environmental, Safety and Health (ESH)
Resources Deployment
Total
0.40
0.20
0.05
0.10
0.25
1.00
For projects which include both horizontal and vertical structures, the
weight to be followed shall be that of the higher cost component of the
project.
The assigned weight for vertical projects is higher than that for
horizontal projects in view of the complexity of the nature of the former
projects. In general, the evaluation during construction is assigned
higher weight to ensure that constructors immediately attain
satisfactory performance and maintain it until substantial work has
been accomplished.
6.2 Upon Completion - with a weight of 40% for horizontal projects such
as road, bridge, port and harbor, irrigation and flood control, water
supply and sewerage, mooring facilities for power barges, etc., and
30% for vertical projects such as housing and building, power
transmission line, substation, and diesel power plant, etc., the
maximum weight for the following criteria shall be:
Criteria
Maximum Rating
Workmanship
Materials
Time
Total
0.50
0.20
0.30
1.00
Maximum Rating
Workmanship
Time
Total
0.50
0.50
1.00
9
7.
During Construction
a. Workmanship [Maximum Rating of 0.40]
Workmanship refers to the quality and quantity of on-going and/or
completed items of work, which are verifiable, in accordance to
approved plans and specifications. This aspect covers the
utilization of the correct methodology needed in producing the
desired quantity and quality of work. In rating this aspect,
efficiency of methodology shall be considered.
In assessing/evaluating workmanship, the following procedures
shall be observed: a) before going to the project site, the CPE
shall identify the location of on-going and/or completed items of
works based on the approved plan, and b) from the location
identified, the CPEs shall select spots randomly for evaluation.
The combined area of spots shall not be less than 10% of the ongoing and/or completed items of works. Checklists for
Workmanship for roads and bridges, housing and building, ports
and harbor, irrigation, flood control, power transmission line,
substation, mooring facilities for power barges and diesel
power plant projects are presented in Annex 2. Refer to Section
11.4a hereof in determining the rating for workmanship.
In case there are on-going or completed additional works or
variation orders, which are verifiable, at the time of inspection,
these shall be rated if said variations were approved by the Head
of the Procuring Entity.
b. Materials [Maximum Rating of 0.30]
To impress upon the constructors the importance of materials in
producing the desired quality of an item of work, this aspect is
viewed separately from workmanship as another factor in
assessing performance.
Materials means the quality, quantity and type of construction
materials including asphalt and ready-mixed concrete, and
components supplied by entities other than the constructors as
required in the contract. The constructor gets the full rating of 0.30
for materials in a particular item of work if he complies with all the
applicable indicators in the checklist for materials in Annex 3.
Refer to Section 11.4b in rating materials.
Alternative construction materials used by the constructor may
also be considered by the CPE in rating the materials aspect,
provided there are supporting documents consisting of the
approval by the owners authorized personnel and test results. If a
work item does not require the use of materials (e.g., demolition of
existing structure, excavation, or scraping), the constructor
automatically gets 0.30 in this aspect provided he gets the full
10
Upon Completion
a. Workmanship [Maximum Rating of 0.50]
Workmanship is one of the three aspects to be evaluated when
the project is one hundred percent (100%) complete as reported
by the IO.
The punch lists prepared by the inspectorate team may serve as
additional reference for project evaluation. The constructor shall
merit a full rating of 0.50 for a particular item of work if he satisfies
the applicable indicators in the checklist. Spots comprising not less
than ten percent (10%) of the entire project shall be the sample
size used in evaluating this aspect.
b. Materials [Maximum Rating of 0.20]
In rating the aspect of material, a full rating of 0.20 shall be given
to materials in a particular item of work if he complies with
applicable indicators in the checklist for materials in Annex 3.
If a work item does not require the use of materials (e.g.
demolition of existing structure, excavation, or scraping), the
constructor automatically gets 0.20 in this aspect provided he
12
gets the full rating in the workmanship aspect for such work item.
However, if the particular item of work was not done or
inadequately complied with, the rating for material shall be 0.00.
Furthermore, when a particular item of work was not rated since it
is no longer visible and cannot be verified, the material aspect for
such item of work shall not be rated.
c. Time [Maximum Rating of 0.30]
In rating the aspect of time, comparison shall be made between
the approved contract completion time including time extensions
granted and actual project completion time. Completion of a
project on time includes demobilization and final clean-up.
The constructor shall get a full rating of 0.30 if he is on or ahead of
schedule but if the project is delayed due to his fault, he gets a
lower score. The score shall depend on the percentage of
delay as shown in Annex 4 Upon Completion.
For contracts with no materials or materials are supplied by
the owner, the computation of score for Time aspect is
presented in Annex 4 For contracts with no materials or
materials are supplied by the owner for Upon Completion
phase.
8.
a.1 Undertake accreditation processes which consist of: a) prescreening and endorsement of application of CPE applicants;
and b) facilitate conduct of CPES required training and
seminars;
a.2 Undertake yearly performance evaluation of CPEs.
a.3 Update CPE members on latest developments and other
technical functions.
a.4 Orient resource persons/witnesses.
a.5 Review and prepare CPES reports and recommend
appropriate actions based on the CPES Rating; and
a.6 Assign its accredited CPE staff member/s to act as individual
CPE/s or member/s of the CPE group/team as required.
b. Administrative/Coordinative
b.1 List all projects to be subjected to evaluation using CPES and
identify/assign personnel to compose the CPE.
b.2 Schedule orientation-seminar on CPES for in-house CPE
members and resource persons/witnesses.
b.3 Generate latest project status, schedule CPE site visits,
coordinate visit with the Head of the Procuring Entity and
constructor concerned, and file/safe keep all CPES related
documents.
b.4 Provide the CPE with CPES documents implementing
guidelines and forms, and prepare CPE travel documents as
required.
b.5 Data banking and dissemination of CPES reports and
documents to all concerned users within the agency, CIAPs
Philippine Domestic Construction Board (PDCB), and other
interested users.
To ensure that constructors understand the mechanics of CPES and
how they are rated, their Authorized Managing Officers (AMOs) or their
duly authorized Sustaining Technical Employees (STEs) shall be
required to undergo a one-time Orientation Seminar on CPES to be
conducted by the CIAP-PDCB prior to contract implementation.
9.
permanent or ad-hoc basis. It is necessary that all CPE members are not in
any way involved with the project to be evaluated in order for them to give an
objective and unbiased evaluation of the constructors performance.
9.1 Minimum Qualification of CPES Evaluators
All CPES evaluators shall be accredited by the CIAP based on the
minimum qualifications as follows:
a. Licensed Engineer or Architect.
b. Must have at least 5 years experience in the actual implementation
of project.
c. In full enjoyment of his/her civil rights, must not have been convicted
of a crime involving moral turpitude or of any other crime for which
the penalty imposed upon him/her is over six (6) months of
imprisonment.
d. Willing to undergo all screening requirements and accreditation
course for CPES evaluators to be conducted by the CIAPs PDCB or
any of its accredited training institutions.
Professionals who have substantially complied with the minimum
requirements stated in items a to c above, and who by reason of
trainings or experiences in construction, conducted lectures on CPES
accreditation courses upon invitation by the CIAPs PDCB are
automatically accredited as CPES evaluators.
9.2 Procedure and Requirements for Renewal of CPE Accreditation
CPE accreditation shall be valid for a period of three (3) years from the
date of accreditation. An application for renewal of CPE accreditation
may be filed with the CIAPs PDCB not later than two (2) years from
expiry date.
The CPES-IU shall endorse the renewal application based on the
performance of the CPE. For renewal of CPE Accreditation, it is
required that a CPE:
a. be endorsed by the CPES Implementing Unit Head; and
b. must have evaluated at least one (1) infrastructure project.
In cases where the CPEs did not have the chance to evaluate projects
due to limited number of infrastructure projects of the agency, the
following options may be applied:
Option 1
Require CPE to attend Enhancement/Orientation Seminar conducted by
the Agency CPES-IU in coordination with PDCB;
Option 2
CPE applying for renewal of accreditation must have been involved in
various CPES related activities such as but not limited to:
15
In-house CPE
Group or
Team
RESOURCE PERSONS/WITNESSES
one (1) or more - Owners and Constructors Project Engineer and/or Consultant
assigned in the project to act as resource person(s);
one (1)
one (1)
one (1)
10.1
IO-Supplied Documents
a. Contract documents: approved contract agreement, contract
drawing, general and special/local provisions including plans and
specifications, method of construction, safety and health measures
b. Approved constructors construction program: CPM work schedule
or bar chart, materials/manpower schedule, equipment schedule,
organizational chart, financial chart such as S-curve or cash flow
c. Constructors statistical reports: physical progress/status,
equipment and manpower schedules based on the latest approved
PERT/CPM
d. Materials testing procedures, records of tests and results,
materials quality control program
e. Constructors operational set-up: general lay-out of facilities,
project
office
and
quarters,
warehouse,
shops
for
repair/maintenance/carpentry/rebar
f. List of subcontractors or suppliers
g. Punch list (for final visit upon completion)
h. Relevant checklists, CPES evaluation form and cover sheet
10.2
11.2
conduct more than two (2) visits during this phase, Part II of the form
may be reproduced to correspond to the additional number of visits it
shall make. Part III shall be used for the final visit.
For Part II, the CPE shall list the items of work evaluated during the
visit, their corresponding percentage weights and relative percentage
weights, and their rates and relative rates for both workmanship and
material aspects. As defined in Section 4 hereof, the percentage
weight of a particular item of work subjected to evaluation shall be
computed by dividing its total cost by the total contract amount while
the relative percentage weight of said item of work shall be computed
by dividing its percentage weight by the sum of the percentage weight
of all evaluated items of work. The relative rate for each item of work
for both aspects, which shall be computed by multiplying the rate for
each item of work with corresponding relative percentage weight,
shall be added and later on reflected in the Summary of Ratings along
with ratings for the other aspects covered.
However, in case there are on-going or completed additional works
not yet covered by an approved variation order or request for time
extension which is not yet approved during the visit, the CPE using a
separate form shall fill up all relevant portions such as the Rate
column for the workmanship and material aspects, time and resource
deployment. The ratings therewith shall be used in updating the
appropriate form, either Part II or III, only upon approval of the
variation order or time extension.
For Part II, the CPE after completing the Summary of Ratings shall
compute the During Construction Weighted Rating (A). This can be
computed by adding all of the Ratings obtained for each visit during
construction phase, dividing the sum of Ratings by the number of
visits made, and then multiplying the quotient by sixty (60%) for
horizontal projects or seventy (70%) for vertical projects.
11.3
After the over-all CPES rating of the constructor has been computed,
this shall be reflected in the box marked Qualitative Description
based on the range of constructors CPES rating for the specific
project undertaken. Annex 8 shall be revised by the CIAPs PDCB to
indicate the new ranges of CPES ratings and their equivalent
qualitative descriptions, as follows:
CPES Qualitative
Description
Outstanding
Very Satisfactory
Satisfactory
Unsatisfactory
Poor
11.4
Ranges of CPES
Rating
> 96%
> 89% < 96%
> 82% < 89%
> 75% < 82%
< 75%
CPES Checklists
The checklists for each indicator are made to aid the accredited CPEs
in the objective evaluation of constructors performance. These
checklists are coded mainly for data banking purposes.
a. Checklist for Workmanship
For identification purposes, the checklist for workmanship for
Road, Bridge, Housing, Building, Port and Harbor are coded with
letters RBWS, HBWS, and PHWS, respectively. The first two
letters refer to type, e.g. RB stands for Road and Bridge, and WS
refers to workmanship.
The checklists for Workmanship for Road and Bridge, Housing
and Building, Port and Harbor, Irrigation, Flood Control, Power
Transmission Line, Substation, Mooring Facilities for Power
Barges and Diesel Power Plant Projects are contained in Annex
2.
The CPE shall select from the checklists those items of work
which are applicable for evaluation/assessment. Indicators are set
for each items of work but the CPE may add other indicators in the
blank spaces provided for. All additional indicators shall be
submitted to CIAP for coding purposes.
The checklists for workmanship in Annex 2 shall be revised by the
CIAPs PDCB to reflect, among others, specific indicators for
major and minor defects, and additional indicators as needed.
The CPE shall evaluate/assess the pre-determined spots based on
the indicators set for each item of work. If there is non-compliance,
the CPE shall determine if such is a major or minor defect. If an
indicator is not applicable, the CPE should place NA (not
applicable) at results box.
19
Spots with a single major defect shall forfeit all points for the rest
of the indicators in the said spot. Further, if the number of
complying spots is less than fifty percent (50%) of the total number
of spots, the rating for that specific item of work is zero (0).
Determining Results, Score, Total Score and Rate.
a.1 Determine the number of non-compliance or full compliance
per indicator
a.2 Results = Compliance / Number of spots
a.3 Score = Results x 0.40 (During Construction);
Score = Results x 0.50 (Upon Completion)
a.4 Total Score = Sum of all the scores
a.5 Rate of an Item of Work = Total Score (a)/No. of Indicator (b)
b. Checklist for Materials
The checklist for Materials is contained in Annex 3 and starts with
MAT followed by the blank space which is for the corresponding
number of the item of work being evaluated. There are five (5)
indicators for this aspect and all indicators shall be rated.
Compliance to each indicator means full score of one (1) and noncompliance means score of zero (0).
If the constructor complies with indicator number 1 which is
compliance to test requirements, then the remaining four (4)
indicators need to be evaluated. If the constructor does not comply
with indicator number 1, however, the remaining four (4) indicators
shall also be evaluated for CAR purposes but the final rating is
automatic zero (0).
If a work item does not require the use of materials (e.g.
demolition of existing structure, excavation, or scraping), the
constructor automatically gets 0.30 during construction and 0.20
upon completion in this aspect provided he gets the full rating in
the workmanship aspect for such work item. However, if the
particular item of work was not done or inadequately complied
with, the rating for materials shall be 0.00. Furthermore, when a
particular item of work was not rated since it is no longer visible
and cannot be verified, the material aspect for such item of work
shall not be rated.
Determining Results, Score, Total Score and Rate.
a.1 Results = If indicator is complied (C) = 1 and if not complied
(NC) = 0
20
11.6
12.2
12.3
rating
of
at
least
12.4
12.5
12.7
12.8
12.9
25
LIST OF ACRONYMS
1.
AMO
2.
BAC
3.
CAP
4.
CAR
5.
CIAP
6.
CPE
7.
CPES
8.
DOLE
9.
ESH
10. GFIs
11. GOCCs
12. GPPB
13. INFRACOM -
14. IO
Implementing Office
15. IU
Implementing Unit
16. LGU
17. NEDA
18. NGAs
19. NTP
Notice to Proceed
20. PAP
21. PCAB
22. PDCB
23. PE
Project Engineer
24. STE
25. SUCs
26