Scope of Work
Scope of Work
Scope of Work
Location:
Duration:
DESCRIPTION
Renovation of Training Center, 5 rooms and Gym
Pre Painted Metal Roofing Sheets and Accessories
- All pre-painted metal sheet and roofing accessories shall be oven baked painted and overall thickness
with protective coats of 0.60mm, true to profiles indicated on the Plans.
- Remove existing roofing and accessories (roofing materials, gutters, ridge roll, and other related).
- Install 0.60mm x 980mm pre-painted longspan corrugated G. I. roofing.
- Install 0.60mm x 36in x 8ft pre-painted G. I. box gutter.
- Install 0.60mm x 24in x 8ft pre-painted G. I. ridge roll.
- Install 0.60mm x 18in x 8ft pre-painted G. I. wall flashing 1 and 0.60mm x 24in x 8ft pre-painted G. I.
wall flashing 2.
- 'Install 0.60mm x 36in x 8ft pre-painted G. I. sheet for capping.
- Use rubber sealant for joints.
- Design/color shall be subject to the approval of the Architect/Engineer.
- The work done under this item shall be measured by actual area covered or installed with pre-painted
steel roofing and accepted to the satisfaction of the Engineer/Architect.
A.2
A.2.a
Ceiling Works
Gypsum Board (5 Bedrooms, Hallway, Corridor,
Kitchen & Training Center Stage Ceiling)
- Remove existing ceiling and its lighting fixtures.
- Replace all unnecessary ceiling joists and use gypsum board with 12mm thick for ceiling replacement.
A.2.b
A.2.c
A.3
A.3.a
- Correct the gaps and surface imperfection using Konstruct Fast Setting Gypsum K103 (or approved
equal).
- Primed and finished it with Boysen Permacoat Flat Latex White B701 (or approved equal) with brush or
roller.
Training Room
- Remove existing ceiling.
- Armstrong Acoustic Board (or approved equal) on Suspended Ceiling Grid System using Gauge 14 GI tie
wire
- BORAL Gypsum Ceiling Board (Echo Stop) (or approved equal) on ceiling light metal frame using
carrying channel for fixed hanger
- BORAL (or approved equal) Echo Stop Board on dry wall metal frame
Gym (Accoustic Ceiling Board)
- Remove existing ceiling and lighting fixtures.
- Armstrong Acoustic Board (or approved equal) on Suspended Ceiling Grid System using Gauge 14 GI tie
wire
- Correct the gaps and surface imperfection using Konstruct Fast Setting Gypsum K103 (or approved
equal).
- Primed and finished it with Boysen Permacoat Flat Latex White B701 (or approved equal) with brush or
roller.
Flooring Works
Training Room
- Remove existing flooring.
- Replace all with 6in x 36in x 3mm APO vinyl designer series mimicri (or approved equal).
- Dessert Oak Wood color (or approved equal).
A.3.b.
Kitchen
- Remove existing flooring.
- Replace all with APO vinyl designer series mimicri (or approved equal).
A.3.c
A.3.d
A.4
A.4.a
A.4.b
A.5
A.5.a
A.5.b
Tileworks
- This item shall consist of furnishing all ceramic tiles, materials, tools and equipment including labor
required in undertaking the proper installation of walls and floor tiles as shown on the Plans and in
accordance with this Specification.
Toilets ( 6 units)
- Remove all existing wall and floor tiles.
- Remove all existing toilet fixtures and its accessors.
- Replace it with 12" x 12" Mariwasa (or approved equal) non glossy tile for the floor and 12" x 12"
Mariwasa (or approved equal) glossy tile for the wall.
Stairs at Main Entrance (3 Floors)
- Remove existing tiles.
- Replace it with approved 12" x 12" non skid granite tile w/nosing and approved 24" x 24" non skid type
granite for the landing area.
Carpentry and Cabinetry
Kitchen (modular cabinet)
- Remove and replace existing kitchen cabinet with new modular kitchen cabinet with synthetic garnite
top.
Bedroom Cabinets/Hallway (include Painting)
- Remove and replace existing cabinets and working table at room 5 as shown on the plan. Replace it
using 3/4" thick plywood, replace piano hinges and accessories, primed with Boysen Eco Primer B105 (or
approved equal) and paint it with Boysen Healthy Home B7410 (or approved equal) all room cabinets.
A.5.c
Gym Walls
- Remove existing wall.
- Replace using 12 mm. gypsum board.
A.6
A.6.a
A.6.b
A.7
A.7.a
A.7.b
A.7.c
A.7.d
A.8
A.8.a
Painting (Interior)
Walls
- Remove existing paints on interior walls primed with Boysen Eco Primer B105 (or approved equivalent)
and repaint with two (2) coats of Boysen Healthy Home B7410 (or approved equal) and materials shall
be applied without runs, sags or cracking.
Ceilings
- Remove existing paints on interior ceilings and repaint with Boysen Permacoat Flat Latex White B701
(or approved equal) and materials shall be applied without runs, sags or cracking.
A.8.b
A.8.c
A.9
A.10
Electrical Works
- The materials, equipment shall be brand new and methods of installation comprising the complete
works, shall be in accordance with the latest applicable codes, standards and guidelines published by
the Electrical Code of the Philippines, publications of the Institute of Electrical Engineers of the
Philippines and the Philippine Electronic Code and of the local ordinances.
Panel Board
- Panel Board bolt-on, 3pole, 220volts, G.E. Main circuit breaker 175 amps., 3 pole (or approved equal).
Branch Wire
- Approved THHN Copper with separate ground with PVC
Devices
A.11
A.12
A.13
Mechanical Works
A.13.a
A.13.b
Airconditioning System
Room 1
- 1 unit Koppel ceiling cassette super inverter model KV48CCR21B 5.HP-4 Tons
Training Center
- 2 units Koppel ceiling cassette super inverter model KV48CCR21B 5.HP-4 Tons
A.13.c
B.1
B.2
B.3
Cistern Tank
- Structure Excavation for the embedment of Cistern Tank
- Concreting of Foundation, Walls, Column & Slab
Rehabilitation of Building Exterior
Masonry (Plastering)
- Clean and prepare portion to be plastered and use Konstrukt Permaplast Skimcoat K201 with Holcim
Wallright cement (or approved equal).
Aluminum Cladding
- Use Aluminum Cladding 4mm thick including support system
Rehabilitation of Building Exterior
Painting incl. Scaffolding
- Contractor is to schedule work so that paint is applied when weather conditions are in accordance with
manufacturer's specifications.
- Scrape to bare allmloosely adhering paint film.
- Surface to be painted must be clean and dry prior to painting.
- Correct surface imperfection using Konstruct Permaplast Skimcoat K201 (or approved equal) mixed
with Holcim Wallright (or approved equal) until trowellable consistency.
- Use Boysen Wallguard B5715 primed with Boysen Eco Primer B105 (or approved equal).
B.4
- Scaffolding should be installed by a certified scaffolding erector, supervise and inspected by a certified
scaffolding inspector and designed by a structural Engineer.
Signages
- 1 unit DBP Panaflex Signage (Landscape) using LED light strips including support anchor and
installation
- 1 unit DBP Panaflex Signage (Logo) using LED light strips including support anchor and installation
B.5
B.6
B.7
B.8
Siteworks
C.1
C.2
C.3
Drainage System
- Concreting of drainage system using concrete mixer with concrete vibrator
- As well as providing metal reinforcements on trench & manholes
D
D.1
General Requirements
Construction Safety and Health
- Prior to the start of any construction project, all construction project owners and their contractors/subcontractors are hereby instructed to ensure that a suitable construction safety and health program is
ready for implementation in accordance with Section 5 of DO 13.
- The general contractor or the main contractor shall be responsible for the submission to Department of
Labor and Employment (DOLE) of a Comprehensive Construction Safety and Health Program suited for
the project covering the activities/scope of work of all its contractors.
- The contractor shall, at his own expense, furnish his workers with protective equipment for eyes, face,
hands and feet, lifeline, safety belt/harness, protective shields and barriers whenever necessary by
reason of the hazardous work process or environment, chemical or radiological or other mechanical
irritants of hazards capable of causing injury or impairment in the function of any part of the body
through absorption, inhalation or physical agent.
- All Personal Protective Equipment and Devices shall be in accordance with the requirement of the
Occupational Safety and Health Standards (OSHS) and should pass the test conducted and/or standards
sets by the Occupational Safety and Health Center (OSHC).
D.2
D.3
D.4
Hauling of Debris
- Waste materials must be checked by proper/designated personnel of the owner before proper disposal.
D.5
D.6
D.7
As-built Plan
- Asbuilt Plan includes Interior Floor plan, Structural plan (Cistern Tank), Electrical & Lighting plan
(Training Center) And Mechanical plan for Sprinkler System & Air Conditioning unit.
DBP SCOPE OF WO
ITEM
NO.
A
A.1
A.2
A.2.a
A.2.b
A.2.c
A.3
A.3.a
A.3.b.
A.3.c
A.3.d
A.4
A.4.a
A.4.b
A.5
A.5.a
A.5.b
A.5.c
A.6
A.6.a
A.6.b
A.7
A.7.a
A.7.b
A.7.c
A.7.d
A.8
A.8.a
A.8.b
A.8.c
A.9
A.10
A.11
A.12
A.13
A.13.a
A.13.b
B.1
B.2
B.3
B.4
C
C.1
C.2
Prepared by:
Page 1 of 5 pages
Project Title: Repair of Training Center and Painting of Exterior Walls of DBP (RMC-NM)
Location: Corrales Avenue corner Tirso Neri St., Cagayan de Oro City
Duration: 90 Calendar Days
DESCRIPTION
Renovation of Training Center, 5 rooms and Gym
Pre Painted Metal Roofing Sheets and Accessories
- All pre-painted metal sheet and roofing accessories shall be oven baked painted and overall thickness
with protective coats of 0.60mm, true to profiles indicated on the Plans.
- Remove existing roofing and accessories (roofing materials, gutters, ridge roll, and other related).
- Install 0.60mm x 980mm pre-painted longspan corrugated G. I. roofing.
- Install 0.60mm x 36in x 8ft pre-painted G. I. box gutter.
- Install 0.60mm x 24in x 8ft pre-painted G. I. ridge roll.
- Install 0.60mm x 18in x 8ft pre-painted G. I. wall flashing 1 and 0.60mm x 24in x 8ft pre-painted G. I.
wall flashing 2.
- 'Install 0.60mm x 36in x 8ft pre-painted G. I. sheet for capping.
- Use rubber sealant for joints.
- Design/color shall be subject to the approval of the Architect/Engineer.
- The work done under this item shall be measured by actual area covered or installed with pre-painted
steel roofing and accepted to the satisfaction of the Engineer/Architect.
Ceiling Works
Gypsum Board (5 Bedrooms, Hallway, Corridor,
Kitchen & Training Center Stage Ceiling)
- Remove existing ceiling and its lighting fixtures.
- Replace all unnecessary ceiling joists and use gypsum board with 12mm thick for ceiling replacement.
- Correct the gaps and surface imperfection using Konstruct Fast Setting Gypsum K103 (or approved
equal).
- Primed and finished it with Boysen Permacoat Flat Latex White B701 (or approved equal) with brush or
roller.
Training Room
- Remove existing ceiling.
- Armstrong Acoustic Board (or approved equal) on Suspended Ceiling Grid System using Gauge 14 GI tie
wire
- BORAL Gypsum Ceiling Board (Echo Stop) (or approved equal) on ceiling light metal frame using
carrying channel for fixed hanger
- BORAL (or approved equal) Echo Stop Board on dry wall metal frame
Gym (Accoustic Ceiling Board)
- Remove existing ceiling and lighting fixtures.
- Armstrong Acoustic Board (or approved equal) on Suspended Ceiling Grid System using Gauge 14 GI tie
wire
- Correct the gaps and surface imperfection using Konstruct Fast Setting Gypsum K103 (or approved
equal).
- Primed and finished it with Boysen Permacoat Flat Latex White B701 (or approved equal) with brush or
roller.
Page 2 of 5 pages
Flooring Works
Training Room
- Remove existing flooring.
- Replace all with 6in x 36in x 3mm APO vinyl designer series mimicri (or approved equal).
- Dessert Oak Wood color (or approved equal).
Kitchen
- Remove existing flooring.
- Replace all with APO vinyl designer series mimicri (or approved equal).
- Dessert Oak Wood color (or approved equal).
Bedrooms (1, 4 & 5)
- Remove existing flooring.
- Replace all with Laminated Floor Planks (or approved equal) the same with the existing rooms 2 & 3.
- Oriental Beech color (or approved equal).
Gym
- Clean and prepare flooring for new flooring.
- Use 450mm x 450mm. APO Vinyl Mimicri Carpet Design (or approved equal).
Tileworks
- This item shall consist of furnishing all ceramic tiles, materials, tools and equipment including labor
required in undertaking the proper installation of walls and floor tiles as shown on the Plans and in
accordance with this Specification.
Toilets ( 6 units)
- Remove all existing wall and floor tiles.
- Remove all existing toilet fixtures and its accessors.
- Replace it with 12" x 12" Mariwasa (or approved equal) non glossy tile for the floor and 12" x 12"
Mariwasa (or approved equal) glossy tile for the wall.
Stairs at Main Entrance (3 Floors)
- Remove existing tiles.
- Replace it with approved 12" x 12" non skid granite tile w/nosing and approved 24" x 24" non skid type
granite for the landing area.
Carpentry and Cabinetry
Kitchen (modular cabinet)
- Remove and replace existing kitchen cabinet with new modular kitchen cabinet with synthetic garnite
top.
Bedroom Cabinets/Hallway (include Painting)
- Remove and replace existing cabinets and working table at room 5 as shown on the plan. Replace it
using 3/4" thick plywood, replace piano hinges and accessories, primed with Boysen Eco Primer B105 (or
approved equal) and paint it with Boysen Healthy Home B7410 (or approved equal) all room cabinets.
Gym Walls
- Remove existing wall.
Page 3 of 5 pages
- Panel Board bolt-on, 3pole, 220volts, G.E. Main circuit breaker 175 amps., 3 pole (or approved equal).
Branch Wire
- Approved THHN Copper with separate ground with PVC
Devices
- National Series devices (or approved equal).
Page 4 of 5 pages
Audio System
- Use Yamaha EMX 5014 C Table Powered Mixer 8 mic/line & 2 stereo line inputs w/ effect; stereo
equalizer; 500w24 Ohms (or approved equal).
- Use Infocus IN3128HD 1080p Projector (or approved equal)
- Use Wharfedale Titan 12 Speaker System 12"2 way 250W RMS (or approved equal)
- Shure BLX24RA/SM58 Wireless UHF Handheld Mic and Micro ACT311/ACT-30T Headworn Wireless Mic
(or approved equal)
- BDS DVD 200 Dual DVD Player Rack Mounted (or approved equal)
CCTV and Security System
- Indoor Camera (3.6mm) (800TVL) Mode: OKIN850-IR (or approved equal)
- Indoor Camera (6mm) (800TVL) Mode: OKIN850-IR (or approved equal)
- H.264 DVR (4 Channel) Mode: DVR0404-LF with WD 500GB HDD, DC Connector, CCTV 12V 10A Power
Supply with box, and CAT 6 UTP Cable (or approved equal).
Mechanical Works
Sprinkler and Fire Protection
- Use approved Pipe B.I. Sch. 40 and its approved accessories as shown on plans and specifications.
- Use approved sprinkler devices and its approved accessories as shown on plans and specifications.
Airconditioning System
Room 1
- Koppel multi split 4.0hp/ indoor model KVMS18CCARF21 (or approved equal)
ROOM 2 & 4
- Koppel window type aircon 2.0hp model KWR18R4A (or approved equal)
ROOM 3 & 5
- Koppel window type aircon 1.5hp model KWR12R4A (or approved equal)
Training Center
- 2 units Koppel ceiling cassette super inverter model KV48CCR21B 5.HP-4 Tons (or approved equal)
Rehabilitation of Building Exterior
Masonry (Plastering)
- Clean and prepare portion to be plastered and use Konstrukt Permaplast Skimcoat K201 with Holcim
Wallright cement (or approved equal).
Rehabilitation of Building Exterior
Painting / Waterproofing (Rear Walls)
- Contractor is to schedule work so that paint is applied when weather conditions are in accordance with
manufacturer's specifications.
- Scrape to bare allmloosely adhering paint film.
Page 5 of 5 pages
Prepared by: