Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Foamed Bitumen 4

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

AustStab Technical Note

No.2F 10 June 2008

Foamed bitumen stabilisation


The Association is a non-profit organisation sponsored by organisations involved in the stabilisation and road recycling industry in
Australia whose purpose is to provide information on the use and practice of pavement stabilisation. This Technical Note is
distributed by the Association for that purpose. Since the information provided is intended for general guidance only and in no
way replaces the services of professionals on particular projects, no legal liability can be accepted by the Association for its use.

1 Introduction
Foamed bitumen stabilisation is a road construction
technique whereby hot bitumen is used to bind the
existing or imported granular material to produce a
flexible bound pavement material for use in base
and subbase pavement layers, and in particular for
road rehabilitation.
Foamed bitumen as a binder was realised in 1956 by
Dr Ladi Csanyi at the Engineering Experiment
Station in Iowa State University, USA. The
original construction process designed by Csanyi
consisted of injecting steam into hot bitumen to
produce the foamed bitumen. The steam foaming
approach was very convenient for stationary asphalt
plants, but it proved too difficult for insitu
operations with the type of equipment available in
the 1950s to 1960s.

In the late 1960s the process was modified by adding


cold water rather than steam into the hot bitumen.
This approach became much more practical for
both plant mix and insitu operations.
Today, the usage of the foamed bitumen process has
increased in Australia. AustStab members are
using specialised insitu and plant mix equipment to
produce foamed bitumen stabilised materials (refer
to Figures 1 and 2).

2 What is foamed stabilisation?


Foamed bitumen is a mixture of air, water and hot
bitumen and the typical quantities are 98% bitumen,
1% water and up to 1% foaming agent. When hot
bitumen (160 to 200C) comes in contact with cold
water (15 to 25C) the mixture expands to greater
than 10 times its original volume and forms a fine
mist or foam.

Figure 1 Foamed bitumen insitu stabilisation using a modified specialist


reclaimer.

The foamed material is sprayed into the


mixing drum where it wets and coats the
surface of the fine particles (typically less
than 0.0075 mm in diameter) to form a
flexible yet strong stabilised pavement
material. As the foam collapses most of the
water is lost in the form of steam. The
residual bitumen has properties similar to the
original bitumen and is well dispersed
through the matrix in very small droplets.
The bitumen droplets are attracted to and coat
the finer particles, forming a uniform matrix
that effectively binds the mixture of particles
together. The resultant bitumen stabilised
material has the colour of the parent
aggregate as shown in Figure 3, and squeezed
by hand after it has been processed small
specks of bitumen will adhere to the palm.

The benefits and


limitations

The benefits of foamed bitumen stabilisation


are:
an increase in strength over granular
pavement materials

quick construction method


Figure 2 Foamed bitumen stabilisation using a mobile batch plant. The


material is placed using conventional road making and/or asphalt laying
equipment.
AustStab Technical Note No.2F
Foamed bitumen stabilisation

Page 1 of 4
<BDB 000032>





lower costs than reconstruction


may be trafficked immediately
bitumen provides a durable and
waterproofness to the pavement material

Situations where an overlay is not possible


due to site constraints eg entries to adjacent
properties & flood prone areas

A requirement to complete the
rehabilitation quickly to prevent disruption to
business or residents


The foamed bitumen stabilised pavement layer whilst


flexible cannot be expected to bridge over a very
weak subgrade. Where subgrade failures have
been identified in the pavement investigation report
it is recommended that subgrade strengthening by
lime stabilisation be carried out before stabilisation
occurs.

Figure 3 The foamed bitumen stabilised material has


the colour of the dominant parent aggregate.

Similar to cement stabilisation, the designer needs to


plan suitable lead-time for laboratory testing and
design evaluation for foamed bitumen stabilisation.
It is suggested that a minimum of three weeks be
given from the time of nominating project
rehabilitation option.

5 Materials
The bitumen used for this process is typically Class
170 complying with AS 2008. The amount of
bitumen required for stabilisation is dependent on
the pavement material and is determined using
laboratory testing.

Figure 4 The hard surface of the road a few days after


construction.

Typical application rates for foamed bitumen


stabilisation are 2 to 4%. The addition of
supplementary binders, such as lime or cement, is
applicable in some situations.

The limitations are:


requires a suitable grading of fines in the
pavement material

purpose built equipment and experienced
operators are required


4 Where would you consider this


rehabilitation option?
This effective pavement rehabilitation option may be
considered in most situations, such as:








A pavement has been repeatedly patched


to the extent that pavement repairs are no longer
cost effective;
A weak granular base overlies a
reasonably strong subgrade.
A granular base too thin to consider using
cementitious binders
Conventional reseals or thin asphalt
overlays can no longer correct flushing problems.
An alternative to full-depth asphalt in
moderate to high trafficked roads.
Unfavourable wet cyclic conditions
unsuitable for granular construction.

AustStab Technical Note No.2F Foamed bitumen stabilisation

Figure 5 Foamed bitumen being produced in the


laboratory to assess half life and expansion ratio.
Potable water is used for the foaming process and
additional water may need to be incorporated to
increase the moisture content of the pavement
material during mixing.
Research in Australia and overseas has shown that the
pavement material applicable can range from high
quality quarried material to marginal materials.
The parent material may be modified so as to
achieve a suitable grading curve, by the addition of
complementary material prior to stabilising. One of
the key elements is to a have suitable grading curve
Page 2 of 4
<BDB 000032>

as shown in Figure 6. Good results are obtained


when the pavement material gradings fall into Zone
A, and successful stabilisation has occurred when
part of the grading is in Zones B or C. These
materials should only be considered based on
resilient modulus testing.

A paper prepared by Vorobieff proposes an interim


design method utilising the Austroads asphalt
fatigue curve and incorporating the wet resilient
modulus from laboratory testing of a sample
material [Vorobieff, 2006].

7 Tips on sealing
Due to the inherent bitumen content in pavements
stabilised with foamed bitumen, the adhesion of
bitumen wearing courses is usually excellent.
However, the application rates for these bitumen
wearing courses over foamed bitumen stabilised
layers need to be looked at to prevent excess
bitumen problems (ie bleeding of seals and
instability of asphalt layers).

Figure 6 The grading curve of the material to be


stabilised should fall within the Zone A range.
[Maccarrone, 1994]

As a general rule the bitumen application rate for


bitumen seals on foamed bitumen layers is usually
reduced from the normal design rate by
approximately 10%. When an asphalt layer is to be
applied, it is also common practice to do away with
either the prime seal or the tack coat, depending on
the timing of the asphalt application and the traffic
conditions.

Laboratory testing to establish the material proportions


is documented in an Austroads technical report
[Austroads, 2006].

The reduction in the bitumen in the application of the


wearing course is a cost advantage to the overall
process.

8 Specifications

How do you design these


pavements?

Foamed bitumen stabilisation of the base course results


in a flexible pavement. Mechanistic design
procedures are used to predict the traffic life of the
pavement. Similar to other flexible pavements,
foamed bitumen stabilisation can be designed using
programs such as CIRCLY by inputting the
appropriate material properties in the pavement
layers.

Specialised plant is required for both insitu and plantmix foamed bitumen stabilisation. The Association
provides model specifications for the construction
of local and main roads, and a copy may be
obtained from the web site at
www.auststab.com.au/specifications/

Can you recycle these


pavements?

Similar to cement stabilised pavements, foamed


bitumen stabilised materials may be recycled again
by carrying out laboratory tests to assess the
bitumen content and material grading. Additional
fines may be required in the existing pavement
material.

10

Monitoring trials

Pavement engineers seeking to monitor trials on their


road network should consider coring the stabilised
layer after 6 to 12 months and to test the upper and
lower half of the core for density and resilient modulus.
Figure 7 Foamed bitumen stabilisation as base course
material for Bruce Highway Innisfail, Queensland.

AustStab Technical Note No.2F Foamed bitumen stabilisation

More detailed studies of the performance of trials may


be carried out using Austroads protocols.

Page 3 of 4
<BDB 000032>

11

References

Austroads (2006) Guide to Pavement Technology


Part 4(d): Stabilised Materials Austroads Project No:
TP1089, Sydney, NSW.
Maccarrone, S et al (1994) Pavements recycling using
foamed bitumen Proceedings of the 17th Australian
Road Research Board Conference, Gold Coast,
Australia.
Standards Australia (1997) Residual bitumen for
pavements AS 2008 Standards Australia, Sydney.
Vorobieff, G (2006) Design of foamed bitumen layers
for roads Proceedings from AustStab Workshop on
Road Stabilisation in QLD, Cairns, QLD.

12

Bibliography

Bowering, RH & Martin, CL Performance of newly


constructed full depth foamed bitumen pavements.
Proceedings of the 8th Australian Road Research
Board Conference, held in Perth, Australia, 1976.
Kendall, M, Baker, B, Evans P & Ramanujam, J
Foamed bitumen Stabilisation Proceedings Roads at
Work - Developing Southern Queensland, Southern
Region Symposium, Qld Department of Main Roads,
Goondiwindi, 21 October 1999.
Smith, W (1999). Foamed Bitumen Stabilisation
Project Warwick, QLD, Joint Transport South
Australia/AustStab Seminar 15 April 1999.
Leek, C An investigation of the performance
properties of insitu foamed bitumen stabilised
pavements Institute of Public Works Engineering
Australia, Foundation Funded Research Project,
Canning Vale, WA, 2002.

For more information about the Association, please


write to the CEO, AustStab, PO Box 738
Cherrybrook NSW 2126 or email:
enquiry@auststab.com.au or visit the web site at
www.auststab.com.au

AustStab Technical Note No.2F Foamed bitumen stabilisation

Page 4 of 4
<BDB 000032>

You might also like