Draft Project Proposal
Draft Project Proposal
Draft Project Proposal
April 2014
1. PROJECT DETAILS
1.1.
Project Title:
1.2.
Type of Project:
Dairy Project
1.3.
Project Location:
Litein
1.4.
County
Kericho
1.5.
Country
Kenya
1.6.
Region
Africa
1.7.
Project Beneficiaries:
1.8.
Donor
1.9.
Date of Implementation:
1.10.
Implementing Agent:
1.11.
Project Objective:
1.12.
Project Description:
2014
To improve the quality of raw milk for social,
economic and health reasons
Set up a dairy processing plant; a cooling plant, a
pasteurizer, sterilizer and related milk processing
equipments so as to add value through milk
pasteurization hence production of milk products
such as yoghurt among other products
1.13.
Budget Requirement:
1.14.
1.15.
Project Sustainability
2. BACKGROUND;
Dairy farming is a major component of many rural households in Kenya. In most villages
farmers rely heavily on cattle for their livelihood. It is estimated that dairy cattle contribute about
60% of the national milk production. Majority of Kenyan households keep an average of 1-5
cows and most of the milk is used for family consumption. With the reported production levels
this milk is sold raw and through middlemen who buy from farmers at low prices and lack of
value addition on the milk.
Farmers living in or near town centers and keeping more productive cows, sell directly to
consumers or shops, therefore never enter the supermarkets, but are sold in the street or on the
green markets.
2. PROJECT OBJECTIVES;
2.1.Development Objective
To improve the quality of raw milk for social, economic and health reasons
Milk Products;
o Yoghurt
o Butter
Separation
Pasteurizer
Raw Milk: Dairy processing starts with raw whole milk from dairy farmers
Unloading/Receiving Bay: The milk is delivered to the processing center in milk containers. An
enclosed, all-weather unloading bay is required for sanitary delivery of raw milk. This area must be
adequately clean and sanitize.
Separation: The first step in processing is separation. No matter what product is to be produced, the
raw milk goes through a separation process.
Raw processing: This can be done through a single line processing or multi-line processing
Pasteurization: A wide range of options can be added to the basic process unit depending on the
individual production requirements. These include; separator, sterilizer, homogenizer etc
Activities
Output /
Target
Indicators
Person In
Charge
Resources
Needed
Cost
Project Manager
Project Engineer
Accounts Officer
Project Administrator
Human Resource
Officer
Monitoring and
Evaluation Officer
Community Liaison
Officer
Post Project
Independent Audit
Project Committee
5. BUDGET