Cec 204 Theory PDF
Cec 204 Theory PDF
Cec 204 Theory PDF
VOCATIONAL EDUCATION
REVITALISATION PROJECT-PHASE II
NATIONAL DIPLOMA IN
CIVIL ENGINEERING TECHNOLOGY
INTRODUCTION TO HIGHWAY
ENGINEERING
COURSE CODE: CEC 204
YEAR 2- SE MESTER 2
THEORY
Version 1: December 2008
CEC 204
Introduction to Highway Engineering: Theory
Index
WEEK 1
1.0
INTRODUCTION
1.1
1.2
1.3
1.4
1.5
WEEK 2
2.0
WEEK 3
3.0
4.0
WEEK 5
WEEK 6
WEEK 7
5.0
HIGHWAY ADMINISTRATIONAND
FINANCING IN NIGERIA
3.1
3.2
WEEK 4
Highway Definition
Activities necessitating movement of people
General Road Classification
Nigerian Road Classification
Benefit accruable from Provision of Highway
Users of Road
Driver Characteristics
Pedestrian Characteristics
Vehicular Characteristic
4.3
4.3.1
4.3.2
4.3.3
4.3.4
4.3.5
4.4
COMPACTION OF SOILS
5.1
5.2
WEEK 8
Types of Pavement
Pavement Structure and Functions
Difference between Flexible and Rigid
6.4
6.5
WEEK 9
6.6
WEEK 10
6.7
Stages of Road Construction
6.7.1 Construction of Flexible Pavement
6.7.2 Procedure for establishing Pavement
Pavement
structure
6.7.3 Construction of high type Asphaltic Concrete
Roads
WEEK 11
7.0
7.2
WEEK 12
8.0
Uses of Equipment
Economy, Cost, adaptability and versatility.
WEEK 13
WEEK 14
9.0
8.1.1
8.1.2
8.1.3
8.1.4
Gravel
Sand
Slag
Bituminous materials
8.2
8.2.1
8.2.2
8.2.3
8.2.4
Preparation of material
Requirement and tests for Aggregates
Uses of sand
Tests for Preparing Bituminous material
Cement
MAINTENANCE OF PAVEMENT
9.1
WEEK 15
9.2
9.3
9.4
WEEK ONE
1.0
INTRODUCTION
Highway Engineering deals with provisions for meeting public needs for
highways, environmental impact planning, budgeting, design, construction,
maintenance and rehabilitation of highways, access to and exit from highway,
economics and financing of highway construction, traffic control; and safety
of those using or affected by the use of the highways.
The planning and consideration of financing is normally done before design
and construction of a new road. The planning process include estimation of
traffic requirement of an area for a stipulated design period, usually 20 years,
as well as the construction method that will be adopted.
An inventory study is carried out for information about the physical features of
existing facilities. Also, volume, character and distribution of existing traffic
are assessed. Detailed design is carried out after a suitable and acceptable
route is selected. Selecting the best route depends on: -
i.
Traffic requirement
ii.
iii.
1.3
location and functions of the road. The two main types of classification system
are administrative system and functional system.
Administrative System - is based on the governmental responsibly for
construction and maintenance of the highway under this system are:Township roads (ii) Country roads (iii) City roads (iv) States and roads in
federal lands.
Functional System - This is based on grouping of roads for the purpose of
transportation planning and design. The roads under this category range from
expressway which provide a high degree of mobility with access provided at
spaced interchange to preserve the high speed and volume of facility to local
speed roads which mostly provide access to adjacent land area. Functional
highways include expressway, arterials and streets.
Roads also could be classified on the basis of location and function. The roads
under this classification are
i.
ii.
Rural roads
Urban roads are road network within urban areas and these roads are
Expressway, Arterial, Local street collector roads or streets. Rural roads
consist of federal highways state highways, village roads, local government
roads and DFRRI roads.
1.4
i.
Trunk A Roads: - This form the major network around which other categories
of roads are built. They run through the length and breadth of the country.
They connect ports, capitals of various states and also provide international
links with neighbouring countries.
ii.
Trunk B Roads:- These are the highway within the states, as they connect
important towns and cities of the states. They also connect the cities of the
states to federal highways end serve as the main arteries of traffic to and from
eh district roads.
iii.
Trunk C Roads:- These are also called local government roads. They are
constructed with nearly the same specifications as those of the state highways.
They are intended to connect areas of production and market with state
highways and railways.
iv.
DFRRI Roads:- These are the least in Nigerian classifying system and they
are connected to major district roads and railways. They are intended to serve
the interior rural population of the district.
1.5
The users of improved highway facilities benefit from enhanced ease of travel,
safety and economy of time. The owners of abutting property benefit from
better access and increased property value. Good highway system make for
effective emergency service, better street parking. Concentration of people in
urban areas can be greatly reduced, as an efficient transportation encourages
the people to live in places away from their work centres. It thus help in
decreasing the growth of slums in urban area.
Specifically the economic benefits due to provision of highways are:i.
ii.
Highway system not only provides direct benefits for its users but impact
heavily on the overall economy. This is due to lowered cost of producing and
distributing products which make up the economy and directly feeds the
G.N.P.
iii.
Makes the defence of the territory against aggression and to guard the borders
easier.
WEEK TWO
2.0
The networks of road existed since ages in all parts of the world historically
people have traveled and goods have been moved by road. Roads as they are
presently metamorphosed from the trails traversed by man and his animals
from ages. Thus these trails deliberately chosen by man became the fore
runners of todays road. As civilization developed and people desire for
communication increased, the early trails become pathways, and the pathways
evolved into recognized travel ways.
The entry of wheeled and later motorized vehicles necessitated an improved
surface for travel thereby resulting in the building of special hard surface to
withstand the hard and concentrated load from traffic.
The first real roads were designed by Roman who needed the extensive road
network to broaden their empire. Romans roads were constructed with stones
generally well above the ground level, being in some cases, on embankments
up to 2m high. Their roads are renowned for their straightness especially
between one hill top and another. The first operation was to cut deep ditches
and then build up an embankment with layers of chalk, flint, sand and gravel
topped off with huge stone slabs.
The structural aspects of road in use today result from the work of John
Macadam which was mainly outstanding as he initiated the use of broken
stones throughout the structure of the road way. The formation was also
shaped to the road camber and was a cheaper form of construction. Due to the
effort of Macadam and Telford, there was a vast improvement in
communications, roads being provided to suit the needs of the traffic.
2.1
essentially as a feeder road network for the new rail roads. The practice then
was fashioned after the British standard with aspect of British Engineering
suitable to the country adapted by the colonials Engineers. The road network
then was complimentary to the railways that form the main travel routes.
Integrated road development in Nigeria dates back to 1925, when the road
board was established by the then colonial administration. The board was
given the responsibility to evolved blueprints for trunk road network,
connecting major administrative centres in colonial time. A basic grid of two
north-south trunk roads from Lagos and Port Harcourt to Kano and several
east-west roads, two north and two south of the natural division created by
Niger and Benue rivers.
In later decades, this system was expanded until most state capitals and large
towns were accessible by paved road.
As at 1951, 1,782km out of the total of 44,414km of road built in Nigeria was
surfaced. The roads were lacking in standards design and were in single lane,
with sharp bends and poor drainage system.
The growth of economic activities due to population growth also places
increasing demand for road network to make available the food and other
essential for livelihood.
construction was improved as the length and network increased such that by
1952, 15,785km of bituminous surfaces and 75,200km of earth/gravel surface
roads were already in place is Nigeria.
In 1978 an expressway was constructed from Lagos to Ibadan, and a branch of
this route was later extended east to Benin city. Another expressway
connected Port Harcourt with Enugu. In 1990 Nigeria had 108,000km of roads
of which 30,000km were paved, 25,000km were gravel and the rest were
unimproved earth.
The estimated current total road network is about 194,000 kilometers.
10
11
WEEK 3
3.0
3.1
(a)
Federal highways
(b)
(c)
(d)
by the federal
government.
(e)
(f)
The states are responsible for work on highway system within their area of
authority. The Chief Engineer is in charge of state road. Local government
roads are administered by the various council departments of works.
12
13
Minister of Works
Permanent
Secretry
Director of Works
Public
Information
Personnel
Management
Review
Programming
& Scheduling
Director of
Finance
Accounting
Data
Process
Purchasing
Legal
Director of
Support Services
Cheif Engineer
( Deputy Dirctors)
Budgeting
Aircraft
Operation
Facilities
Management
Central
Services
Cheif Engineer
Deputy
Chief
Engineer
Planning
Highway
Planing
Survey
Planning &
Programm
ming
Research
Deputy Chief
Engineer
Development
Highway
Planing
Survey
Road
Road
Design
Bridge
Design14
Deputy
Chief
Engineer
Operations
Contracs
Construction
Maintenance
Traffic &
Safety
3.2
Financing of Highway
The highways and streets on which motor vehicles travel are provided, maintained and
operated by government as one of its primary function. The funds to pay for them are
raised through various means.
Highway financing is the sourcing and usage of capital for the construction and
improvement of these highways.
There are different finance sources for a road scheme:
i.
Private financing which could be by savings, reinvested income, stocks and bonds.
Sourcing funds through capital market is a viable way of raising funds for highway. This
is done by private firm floating bonds in order to generate funds rather than depending
on the traditional source of funds such as statutory allocations and internally generated
revenue. This eases the problems of loans and interest payment and thus releases more
funds for road maintenance.
ii.
Public finance: This is based on general credit and taxing power of the government. It
could also come in form of grants from government and international donors. The taxes
include import duty on motor vehicles, parts and accessories (b) Excise duty on vehicle
types and tubes. Excise duty from motor fuel. All these are paid into federation account
and the budget for the road is from budgeting provision for this purpose.
iii.
Joint venture: This is a partnership between the government and the private sector to
achieve the needed efficiency and effectiveness in the sector. This is achieved by
involving private sector in
iv.
the development of a
2.
Vehicle taxes
3.
4.
Parking fees
5.
6.
7.
8.
Property tax
16
WEEK FOUR
4.0
4.1
1.
Drivers
2.
Pedestrians
It is however necessary to broaden the scope of the design to accommodate other users
including motorcycles and bicycle operators.
This consideration ensures that the vehicle-capacity characteristic are viewed from the
extremes and the varied characteristics exhibited by operators of vehicles (drivers) and
pedestrians are well taken care of.
4.2
4.2.1
Driver Characteristics
In any discussion of human beings as vehicle operators, it must be recognized at the
outset that there is no such things as an average driver or an average driving condition.
Drivers in a single age group have different abilities to see, process information, judge
and react. These abilities may change under certain effects. So much of the safe and
efficient operation of a highway scheme depends on the tendencies exhibited by the
driver.
There should be an
vehicle operator. These are in turn, controlled by the human sensory process that
depends entirely on the operation of the central nervous system.
17
Drivers, often react and act based on objects viewed, perceived motion, distortion in
balance (e.g. negotiating a bend) and sound.
Thus the senses frequently used are those of sight (visual), Auditory, Kinesthetic
(movement), vestibules (equilibrium balance).
The understanding or perception of these various senses and the subsequent
development of alertness vary from driver to driver and across age barriers. Thus the
sense of sight declines with age so also is the ability to judge, even though older drivers
may compensate for some of these deficiencies by experience and by being more
cautious.
The driver characteristic is fundamentally described by the perception reaction time.
Perception-Reaction time is defined as the time that elapses between the observation of a
particular situation on the highway and the initial action that is taken in response to such
a situation.
It is broken down into 4 components
i.
Perception
ii.
Intellection
iii.
Emotion
iv.
i.
Fear of possible accidents may control driver decisions. Operating speeds are
ordinarily set instinctively at the highest level of which the driver feels that his
information gathering, data processing, and reacting abilities match the situation, so
that he feels secure.
ii.
Fear of arrest and punishment also affects driver behaviour, for instance drivers
reduced their speed when they sight highway patrol car.
arise from a collapsed highway which is usually the pedestrian as this class forms the
major user of the roadway.
The characteristics exhibited by the pedestrian that are of importance include space
requirement and walking (running) speeds. Also the nature and characters of a group of
human traffic is important.
Empirical studies show that the pedestrian facility is based on shoulder breadth and body
girth of the average human body. These are respectively 570mm and 325mm and serve
as a guide for the design of the facility.
Walking speed of pedestrians vary from 0.61 to 1.83mls for conditions of free
movement. Variation depend on the condition existing.
4.2.3
i.
Width the width of vehicle will affect the lane width, shoulders and width of parking
spaces.
ii.
Length - the length of vehicle will affect the extra widening and minimum turning
radius, passing sight distance, road capacity and parking facility.
iii.
Height The height of vehicle affects clearance to be provided for electric service lines,
tunnel, under bridge and under structure.
iv.
gradient and design of bridges as there are standard permissible axle load limit.
v.
Speed vehicle speed affect horizontal and vertical alignment design, super elevation
limiting radius, sight distances, grades and width of pavement on straight and curves.
19
(a)
Inertia Resistance: - The tendency for the vehicle not to accelerate (to remain at rest).
The inertia effect may also be plus or minus and is proportional to the mass and
acceleration.
(b)
Grade Resistance: - This is the part of the weight of the vehicle that equalizes the
frictional effect on a grade.
(c)
Rolling Resistance: - The irregularities that manifest normally on a road surface impart a
rolling resistance on the motion of the vehicle due to the internal friction of the body arts
and the undulating of the tyres.
(d)
Air or wind resistance : - is a function of the area (A) exposed to the direction of the
wind and the speed of vehicle given by
Ra = CA V2
Where Ra = Total air resistance, that is required to clear air from vehicle pathway and
eliminate air from the top, side and underneath the vehicle.
A = Projected Area of the vehicle
V = Speed, C = Constant
(e)
Curve Resistance:- Is the force that makes a vehicle conform to a curved path and this
depends on the degree of curve or radius.
20
WEEK FIVE
4.3
(a)
(b)
Design speed
(c)
(d)
(e)
Sight distance
Other factors to varying degree affect the design standard adopted for the geometric
element. They are the functional classification of the roadway, topography, cost and
available funds, safety consideration (signing), society cum environmental factors.
Possibly the most important single rule in highway design is consistency. Only by
making every element conform to the drivers expectations and by avoiding abrupt
changes in standard can a smooth flowing, accident free facility be produced.
4.3.1
21
Thus the facility should be designed to accommodate the predicted traffic volume. The
volume of traffic chosen should also correspond to a particular level of service. This
L.O.S is a measure of the restrictive effects of increased volume.
4.3.2
Design Speed
This is defined as speed determined for design and correlation of the physical features of
a highway that influence vehicle operation. It is the maximum safe speed that can be
maintained over a specified section of highway when conditions are so favourable that
the design feature of the highway governs.
Selection of the proper design speed is extremely important, because this choice sets the
limit for curvature, sight distance and other geometric features. Design speed range from
58 112k/hr with significant intermediate values depending on the classification of
highways. It is advisable to use a constant speed in design of roadway of substantial
large distance. Changes in speed as informed by terrain or other conditions are effected
over sufficient distance for gradual change in speed.
4.3.3
Road Alignment
The alignment of a road is a series of straight lines called tangents connected by circular
curves. Alignment must be consistent sudden changes from flat to sharp curves and long
tangents followed by sharp curves must be avoided; otherwise accident hazard will be
created. Placing circular curves of different radii end to end or having a short tangent
between two curves should be avoided, unless suitable transitions between them are
provided. Long, flat curves are preferable at times. Horizontal and vertical alignment
must be considered together not separately.
4.3.4
22
either side. Multilane highways have similar travel width with 2 lane roads with the
provision of median on divided highways.
Other cross-sectional elements are shoulders, curbs/kerbs, gutters/ditches R.O.W, guard
rails.
Shoulder is that portion of roadway between the outer edge of the traffic lane and the
inside edge of the ditch, gutter curb or slope. Shoulders provide a place for vehicle to
park when disabled or when stopped for any other reasons.
The carriage way intended for one line of traffic movement is called a traffic lane.
Side strip
Lane
Lane
Foot way
Pavement
crown
23
Median
Lane
Service
Road
Parking
Lane
Outer
Separation
4.3.5
Foot
Way
Gradient
This is the rate of rise or fall of road level along its length. When the road is ascending
the inclination is said to be positive but when descending, the inclination is said to be
negative. Determination of the gradient between any two stretches of the highway is one
of the most important factors of highway design. Higher grades affect the operating cost
of vehicle as there is increased in consumption of fuel and reduced speed.
Gradient are classified into:
Minimum gradient This type is provided on a flat or level road to drain off the rain
water. Its value depends on the topography type of soil. In general 1 in 200 is sufficient
but for cement concrete surface a grade of 1 in 500 is quite sufficient.
Ruling gradient This is the desirable upper limit or permissible limit of the gradient in
the alignment of a road. This is fixed in such a way that vehicles can negotiate long
stretches of this gradient without much fatigue or uneconomic consumption of petrol.
For flat or rolling terrain 1:30 for it ll terrain 1::20.
Exceptional gradient During the alignment of the road, there may be situations where
grades may have to be provided with either lesser than the minimum or greater than the
maximum. Thus this type of gradient are provided in exceptional situations such near
hairpin bends. These types should be provided only for very short stretches not
24
25
WEEK SIX
4.3
Sight Distance
Most of the accidents on highway take place because of the inability of the drivers to
stop the vehicles well before it may collide with on obstruction or obstacle.
If it is not possible for the driver to see the obstacle from such distance that he may be
able to stop the vehicle by slowing down and applying the brakes, he may be able to
avoid the accident although he has taken every care to do so. To avoid such situations, it
is necessary that the road be open to view from all points from a distance known as sight
distance from which the driver should be able to see ahead and be able to bring the
vehicle to dead stop or otherwise take a detour to avoid collision. Therefore for a safe
vehicle operation, a clear line of sight of suitable length must be provided along the
road.
Sight distance therefore may be defined as the length of the road visible to the driver
while driving a vehicle.
Sight distances are of two types namely:
i.
ii.
The ability of the drivers to stop the vehicle before striking the obstacle while driving at
design speed depends upon:
Frictional resistance between the roads surface and the tyre of the vehicles.
Therefore,
Stopping sight distance = perception reaction distance + braking distance which is given
as
0.28vt + 0.01v2
where:
V = design speed in km/h
t = time in sec for passing manoeuvre
But when the braking efficiency is given, the equation for stopping sight distance =
0.28vt + 0.28v2
2.9
where = braking efficiency
g = acceleration due to gravity.
1.2m
10cm High
Obstacle
Non Passing
Sight Distance
Non Passing Sight Distance
Example (a)
Determine the stopping sight distance for a level road, for which the design speed is
40kmph. The reaction time of the driver may be assumed as 3.0 seconds.
Stopping sight distance = 0.28v.t + 0.01v2
= 0.28 x 40 x 3 + 0.01 x 40 x 40
= 33.6 + 16
= 49.6m
~50m
Example (b)
Find out the stopping sight distance for a road for which the design speed is 55kmph.
The brake efficiency may be taken ass 50% and the reaction time of driver be taken as
3secs.
Stopping sight distance = 0.28vt + 0.28v2
2.gn
27
ii.
Passing Sight Distance or Overtaking Sight Distance:- This is the distance required by a
vehicle to overtake and pass another vehicle on a 2 lane highway without impendence
from opposing traffic stream or the minimum distance open to the vision of the driver of
the overtaking slow moving vehicle ahead with safety against the traffic from opposite
direction. The overtaking sight distance is governed by following factors:-
a.
b.
c.
d.
1.2m
1.2m
Passing Sight
Distance
28
d2
d3
Passing/Overtaking Sight Distances
d2
4kmh/sec.
s =
t =
T=
overtaking.
d3 = distance traveled by the vehicle coming from the opposite direction during the
period of overtaking.
In view of so many variable parameters the following empirical formulae have been
suggested for use.
S =
[0.2(v m) + 6] metres
29
= 2.7s secs
a
30
WEEK SEVEN
5.0
COMPACTION OF SOILS
As it exists naturally soil provides the foundation support for many structures
including road pavements. Specifically for roadways, it is necessary to reshape
the
road. This is achieved by the use of the soil as fill material for low locations. It is however
necessary to improve the bearing of the soil by placing and compacting layers which results in
soil mass with improved strength and support capabilities.
5.1
process of increasing the dry density of soil by artificial rearranging and packing
is the
the
soil
ii.
iii.
iv.
Reduction in shrinkage.
consolidated. Consolidation is thus the process whereby soil particles are packed closely
together by the explosion of pure water from the soil through the application
of
load transfer.
5.1.1
Compaction Equipment
The various types of compaction equipment
i.
Sheep foot roller with projecting feet and used to compact cohesive and are pushed
pulled by crawler tractors.
ii.
iii.
Vibratory compactor with pads or drum used where soil has cohesion.
iv.
Compaction
Characteristic
Good
Good
Good-fair
Silt
Fair poor
Recommended
Compaction Equipment
Vibratory drum roller,
Vibratory rubber tire,
Pneumatic tire.
Vibratory drum roller,
Vibratory rubber tire,
Pneumatic tire.
Pneumatic tire,
Vibratory rubber tire,
Sheep foot.
Sheep foot roller &
pneumatic
Pneumatic tire, sheep foot,
vibratory & rubber tire.
Clay
Good fair
5.2.
particles
to
be lubricated and thus reduced the friction and greater density and strength for a particular
compactive effort is achieved. This increase in
place up to the certain limit
density. At
this stage the soil has reached its saturation point. The increased in amount of
moisture act as a space filler and holds the soil grains apart and for cohesive
the increase moisture cause the soil to become plastic. This limiting
moisture
soils,
content
value is referred to as the optimum moisture content and is shown on a plot of lab compaction
rest as the peak of the graph as given below
32
d max
omc
Water content w%
The max. density is at optimum moisture content and is the ultimate water content
achieve high density for the given soil when a compacting energy corresponding
to
to
the
5.3
compaction effort used is a 2.5kg hammer that falls through a distance of 30cm to compact the
soil. The test specimen (soil) is
0.01m3. the specimen in
through the
specified fall height and with a regulated number of blows per layer 27 blows.
The soil after compaction is struck off the top of the mould and the density of
the
highest point
W
1 + 100
b = Bulk density
The other laboratory tests are similar but with different mould dimensions
and
capacity and rammer height. The fall distances are also different.
Modified Proctor Test :-
of
blows = 27 blows.
USBR Compaction Test - 10cm diameter mould with a capacity of 0.014m3
rammer of 2.5kg and a height of 45cm.
33
and a
soil
and operating for 60 secs per layer. It is used for fine grained soils and for fraction of medium
and coarse grained granular soils passing the 37.5mm
results for uniformly graded coarse sands
Example:
The following results were obtained from a compaction test using 2.5kg
Mass of mould + wet soil (g) 2783
Moisture content
8.1
(%)
9.9
12.0
rammer
Plot the curve of dry d3ensity against moisture content and determine the OMC
MDD
Solution
W
Mass of mould
+ wet soil
Mass of soil
Wet = m1 (g)
8.1
2783
S1653
1529
Dry density
Pd = m2/1000
Mg/m3
1.53
9.9
3057
1927
1753
1.75
12.0
3224
2094
1870
1.87
14.3
3281
2151
1882
1.88
16.1
3250
2120
1826
1.83
18.2
3196
2066
1748
1.75
34
and
WEEK EIGHT
6.0
6.1
Pavement Types
There are two (2) broad categories of road way pavements namely flexible and
pavement.
All the pavements for earth, kankar, dry bond macadam, WBM, stabilized soil
While
and
cement
over a
layers
topped
by
distribute load to the sub-grade and it depends on aggregate interlock, particle friction and
cohesion for stability. Layers of flexible pavement comprises of:
a.
Wearing surface: This ranges from 25mm bituminous surface treatment for low-cost,
light traffic road to asphalt concrete for heavily travelled roads. Provides smooth riding
surface, resist wear and abrasion due to moving vehicles. Provide water proof surface
and protect the base and sub-grade from surface water.
b.
Base: Layer of very high stability and density. It distributes stresses due to wheel load
on wearing surface and transmits mineral stresses on sub-grade in order to prevent
excessive deformation of foundation. Must be capable of resisting effect of capillary
water and/or frost action.
c.
d.
Sub-grade: Serves as foundation of the road, support all load applied on pavement
structure. Usually natural earth surface, compacted soil from cut section or upper layer
of embankment.
35
Wearing course
Surface/Wearing Course
Prime coat
Base Stabilized
Base
Subbase
Sub base
Rigid pavements: These have sufficient rigidity and have high modulus of elasticity.
Thus a small thickness to distribute the wheel load upon the subgrade and equalizes
(bridge) minor irregularities in the subgrade support due to flexural strength and load
transfer capacity in sheer. It is normally laid directly on the subgrades
R.C.
Steel fabric reinforcement
Crown slope
6.2
36
Flexible Pavement
Rigid Pavement
S/N
1
Build with several layers over the Usually one layer (concrete surfacing) is
sub-grade (natural soil), base, sub- built over sub-grade
base and surface layers
2.
Layers dispersed and distribute Concrete surface bears and distribute load
loads to the sub-grade
to the sub-grade
3.
Considerable thickness
Lesser thickness
4.
5.
6.3
of the
prepared sub-
grade.
In flexible pavement construction, the different layers that made up the base
constructed in stages. The sub-grade is compacted for enhanced strength or
using admixtures where necessary. The base is built using material hauled
granular, compacted properly is layers to the specified
are
stabilized
to
site
usually
thickness.
In cases where the sub-grade soil is entirely suited as a road base, only proper
compaction and drainage are necessary before building the concrete wearing
surface.
The base constructed should provide uniform foundation support for the
roadway and
6.4
Borrow Pits
37
Materials that are needed for the formation of roadway alignment are not
obtained from the excavation within the limits of R.O.W. of the
additional full materials are required to complete the full
obtained on mass off site. The sources of such
specification for the kinds of
highway construction
usually
highway. Thus
operation and are therefore
38
WEEK NINE
6.5
sub grade, and most usually this pavement is composed of cement concrete
sub grade, this slab is composed of pavement quality concrete
and high modulus of elasticity which enables it to
the
slab on top of
or minor irregularities in the surface of the layers beneath cement concrete pavement is ideal as
traffic surface with relatively small thickness, it distributes wheel load upon sub grade.
provides a good riding surface. Maintenance costs are comparatively
clean and it is dust free. The vehicle operation cost on
It
and wear and tear and mechanically breakdown of vehicle is comparatively less. it has a high
salvage value as a
pavement.
as
Among
these are bending or deflection under wheel loads, warping of the slab due to difference of the
top and bottom of the pavement, which lead to the slab being raised off the sub-grade which the
self weight of the slab
Warping of the slab due to difference in moisture content at top and bottom of
the
slab and tension produced as contraction during falling of temperature or while drying out is
restricted by sliding friction between the slab and the sub-
grade.
Compression
expansion of slab.
to
approximate
wide.
39
The joint space is filled with a compressible filler material that permits the
slab
means of transferring
usually
to offer a space of
dowel
bars
Contraction joints: these are the most commonly used transverse joint in jointed
concrete pavement. They are placed transversely at regular intervals
interlocking
of
the
length
so that when a slab contracts, the free end of the dowel leaves a gap into which it can
return when the slab expands to its original length.
40
Contraction Joint
Construction joints: these are those other than expansion and contraction joints that are
formed when construction work is unexpectedly interrupted
e.g.
normally required by
has to be established
concrete.
41
by
mechanical
WEEK TEN
6.6
6.4.1
ii.
Dust laying: This also termed palliative and is a simple application of liquid asphaltic
material to a road surface. It is applied in specified uniform rate and precedes subsequent
improvement of low cost roads into full scale asphaltic surfaced roads.
iii.
6.4.2 The specific procedures for establishing pavement structure after concrete is properly
mixed take the following sequence:
1.
Spreading: This is the use of manual or mechanical implements to disperse the concrete
mix in uniform widths across the pavement structure. Dump trucks are used to directly
dump the concrete on grade or from the shoulders. Spreading is facilitated by the use of
various augers which are mechanical spreading devices.
2.
42
3.
Finishing the effect giving to the effect the final riding quality and durability of
pavement. This is achieved by the use of finishing machines equipped with screeds and
floats for giving the final surface to the slab.
4.
Texturing: This is done to ensure skid resistance properties on the slab. It entails using
mechanized action to create a desired texture of the surface. The equipment used for
texturing include buslaps, brooms (wire & fibre), comb (steel brooms) and the use of
grooving devices (diamond saws, plastics).
5.
Placing reinforcement: Where wire mesh are used, the reinforcement are placed by
depressing the mesh on top of the concrete by machine. Where joints are used, they are
placed according to the specified intervals given in design and are sealed off by the use
of sealing materials such as asphalt, rubber/asphalt blend.
6.4.3
concrete
surface roads:
a.
b.
and
subbase construction suitable for medium and light traffic roads. A wide, variety of aggregates
and soil aggregate combination are used and the types
determined by the characteristics of the aggregate
conditions.
Prior to mixing operations, the base on which the mixed material is to be placed
must
be thoroughly shaped and compacted. Prime coats are applied and allowed to cure. This is
followed by the actual road mixing operation.
The various methods of road mixing operation are:
i.
Travel plant mixing: This is the use of motorised equipment to proportion asphalt and
aggregates to give a final product of adequate uniformity. This is then spread on a
prepared base and broken down by the use of pneumatic thread roller and finally rolled
with a smooth wheeled roller.
ii.
Blade mixing: Motor graders are used to mix the road surfacing materials. It ensures
uniformity in quality and gradationo f aggregate. Asphalt is applied in multiples from a
43
truck and the grader is properly manipulated to disperse the asphalt is the aggregate and
coat the aggregate particles. Spreading is done after mixing is completed.
iii.
Rotary mixing: This system combines the asphalt and aggregate under a hood with
whirling blades as the machine moves over the surface. Rotary mixers are equipped with
sprayers that apply the asphalt while mixing. The operation entails mixing the aggregate
thoroughly, adding the asphalt in specified increments and maintaining the surface true
to grade and cross-section by the use of motor grader.
2.
i.
ii.
iii.
Mixing: The proportioned materials are properly blended (asphalt and aggregate) in
specified cycle (mixing time). Mixing produces adequate coating workabilityand
compaction.
iv.
Hauling: The mixed materials are transported from plant to the paving site by the use of
end dump trucks and bottom dump trucks.
v.
Laydown-self propelled pavers are used to place the hot-mix asphalt. Pre levelling
courses and base courses are placed by the use of motor graders and tractor spreaders.
vi.
Rolling: The final process of producing a dense mat with a smooth surface. This is done
by using three-wheeled or tandem steel rollers. This procedure is carried out properly to
have a smooth and dense surface.
44
WEEK ELEVEN
7.0
and
Tractors
b.
Bulldozers
c.
Rippers
d.
Scrapers
e.
Excavators
f.
Tractor loaders
g.
Trenchers
h.
Hauling unit
(Belt conveyor) (i) Soil surfacing equipment (compaction equipment)
Tractors: Prime movers which serve as the tractive-units for power shovel,
cranes, rear dump, bottom dumps and mobile drills hich are on their own varied type of
Bulldozer: These are framed mounted units with blades usually curved in its
vertical section and extend in front of the tractor unit to which is attached; blades
45
are
spreading.
They may be used from the start to the finish of the project.
Bulldozer
Rippers: Used to rip material (usually rocky) that would have been blasted or
drilled. They are usually mounted on tractors and can also be used for other
construction work, mining and or quarrying.
46
Ripper
operation,
they dig, grade and haul the earth using the bowl of the scrapers.
earth
materials into hauling unit; bins, hoppers conveyor and stock piles.
47
length
construction
site.
which
obtain a homogenous
with the soil to complement the soil support characteristics. The two basic types of equipment
used for stabilizing
soil include in-situ mobile mixing and the central mixing plant. The in
48
place mobile mixer includes the multiple pass-unit, the single pass units and the road
mix
units.
Trimming equipment: These are used to finish the surface profile of the roadway
to
precise specification.
7.1
An
or dipper, a pusher, etc. This equipment can also be adapted to do other operation. Another way
or example of versatile
equipment
function to another.
7.2
Soil Stabilization
Soil stabilization is any treatment (including technically compaction) applied
to
2.
3.
4.
into
stabilization
WEEK TWELVE
ii.
Gravel
ii.
Granulated slag
iii.
The pavement structure, surface, base and subbase layers, consist of a mixture of
aggregates with cement and water or bituminous material, thus, the strength characteristics of
the entire structure is dependent on the quality of the component materials and the proportions
of the materials.
This is obtained by crushing rock pieces into smaller size suitable for road construction.
The process entails blasting rocks large size stone blocks which are further reduced and fed
directly into various crushers which are used to break the rock pieces into desired various sizes
of aggregates from 8cm to stone dust size.
All the major classes of rocks, igneous, sedimentary and metamorphic are sources of
crushed rock aggregates. But specific kinds of igneous and sedimentary rocks are preferable due
to their grain size, texture and adhesion to bituminous binder. These aggregates can be used to
construct the different layers of highway pavement.
8.1.1
Gravels
The coarse material resulting from the disintegration of natural rock due to weathering is
carried away by water and subsequently deposited on the banks or bed is termed as gravel. The
properties of gravel depend upon the properties of the basic rock constituents (parent rock).
They are often round in shape and smooth to touch and are particularly suited for the uses
specified for crushed rock aggregates. Larger varieties of gravels (boulders) canbe used as base
course.
8.1.2
Sand
This is the final residue of resistant mineral grains resulting from the weathering action
upon the rocks. The final form is sometimes reached after many cycles of deposition and
weathering most important mineral in sand is quartz which is not affected by weathering agents
and hence prevents further fragmentation of the particle.
In road construction sand is used as a cushion between the subgrade and subbase or base
and interspersed between boulders for proper interlocking. It is also used as blotter over
bituminous surfacing, coat, tack coat and prime coat. It is used as fine aggregate for Portland
cement concrete pavement.
8.1.3
Slag
Artificially prepared road building materials and is obtained as a by-product in the
manufacture of steel used in pavement construction as aggregate. Due to its mode of production,
its properties are far more variable than that of rock especially in respect of the grain size and
porosity, and are normally used as back fill because of the possible presence of free lime.
8.1.4
Bituminous/Asphaltic Materials
51
52
WEEK THIRTEEN
8.2
Preparation of Material
Materials to be used for road construction should posses properties suited for their
respective function. These are based on standard requirement of material properties using
specified test procedures.
8.2.1
of the aggregates are of considerable significance. The following properties are desirable for
aggregate used for roadwork.
i.
Hardness: Aggregate used in the surface coarse are subjected to constant abrasion due
to moving vehicles. The Toughness: Aggregates mutual rubbing of stones also causes
wear in aggregate.
ii.
iii.
Durability
iv.
Cementing property
v.
vi.
requirement.
a.
Abrasion test: This is used to determine the hardness of aggregate using LOS
Angeles abrasion machine.
8.2.2
b.
c.
d.
e.
f.
g.
Shape of aggregate
Sand
Sand for roadwork should have the following properties:
53
8.2.3
i.
Sharpness
ii.
Well-graded
iii.
iv.
properties are obtained. The following standard tests are prescribed to ensure that these
properties are imparted in:
i.
ii.
iii.
iv.
Softening
v.
Penetration test
vi.
Durability test
These tests ensure that the prepared bitumen is of right volatility, workability,
consistency, durability and weight.
Cement
Cement that is used for construction of rigid pavement serves as a binding medium of
the concrete produced. It should be prepared such that the requisite properties of strength,
consistency, workability ease of placement are imparted on the resultant concrete. This is
achieved by ensuring that the cement is of right chemical composition, fines, sound and strong
by carrying out stipulated tests. Tests for setting time, soundness, etc. are used.
54
WEEK FOURTEEN
9.0
MAINTENANCE OF PAVEMENT
It is a well known fact that as soon as the construction is completed and the highway
opened to traffic, it begins to deteriorate. Deterioration may initially be unnoticeable but
it later begins to manifest in the form of various types of pavement distress, e.g. cracks,
etc.
The object of pavement maintenance is to preserve the roadway for continuous provision
of comfortable, economic and safe surface for movement of vehicles. Highways are
maintained and required so that its use does not become dangerous.
9.1
ii.
iii.
iv.
Surface deterioration
1.
a.
Cracking
b.
Disintegration and
c.
Permanent deformation
Cracking:
This is caused by movement of the underlying layers and fatigue of the surface coarse
due, principally to repeated heavy loading. It is technically defined as the length of
substantial cracking whether sealed or not expressed in linear unit of length of crack per
standard square unit of pavement area (m/m2). The various types of cracks are
alligator/crocodile, longitudinal, transverse, irregular mer and block cracking.
55
56
Bleeding: Which is the flushing of bitumen to pavement surface can occur due to
prevalence of cracks.
b.
Disintegration
These include potholes patching, raveling and edge breaks.
Potholes: Are round, bowl shaped holes in the pavement surface that penetrate
all the way through the surfacing layer down to the base course. They generally
have sharp edges and vertical sides near the top of the hole. This is generally end
results of alligator cracking which starts to develop during the rainy season.
Potholes also occur as a result of fragile wearing course, premature aging of the
binder, clayey foundation that prevents proper drainage.
57
c.
Permanent Deformation:
Deterioration of materials throughout the depth of the pavement and can be due
to excessive consolidation of paving layers. This is attributable to heavy axle
loading on roads not designed to carry such.
58
Ruts, depression, mounds, ridge, corrugations, undulations and roughness are all
forms of permanent pavement defects.
Rutting: Is the surface depression in the wheel path usually accompanied by
pavement uplifts (shearing) along the sides causes of rutting may be due to
consolidation or lateral movement of the materials due to traffic loading,
insufficient compaction of the asphaltic concrete, inadequate pavement structure
or improper aggregate/cement mix design.
Pop outs: Are forms of permanent deformation which are small cup sized spalls
(circular in shape) in surface caused by expanding aggregates the causes of this could
be attributed to localized settlement of one or more layers, lack of cohesion or internal
59
friction of the base or subgrade, poor surface and lateral drainage. Generally, all forms
of flexible pavement effects are due to excessive movement of layers.
60
WEEK FIFTEEN
9.2
Defects are mainly dependent on durability of the pavement structure which is in turn a function
of materials used and climatic conditions. The main forms of defects in rigid pavements are
scaling, shrinkage, warping/blow ups, spalling, faulting/faulted joints and polishing.
Scaling: Is the shallow flaking of surface matrix.
Shrinkage: Results from temperature or moisture movement which cause volume change.
Spalling: Is the braking away or chipping of concrete adjacent to a joint or pavement edge and
may be caused by freeze thaw cycle, impact loadings, and incompressible material in cracks or
joints.
61
Faulting/Faulted joints: Is the vertical displacement of the pavement slab adjacent to a crack.
Polishing: Is the wearing away of surface aggregate which leads to undesirably smooth surface
texture.
Deterioration of a road due to defects in pavement leads to uneven riding qualities. This
conflicts with the primary objective of pavement design; to ensure adequate provision of
service to users.
62
Appropriate repairs of the various defects restore the desired qualities of service
provided by pavement. For flexible pavements, the major maintenance works for
repairing pavements are outlined below:
1.
2.
3.
Rehabilitation: The repair covers the entire length of surface and is done to
strengthen and restabilize the pavement for improved serviceability. Examples
are asphalt concrete overlays, selective deep patching, granular overlays and
surfacing, surface treatment and shape corrections.
4.
5.
6.
ii.
iii.
Patching: This entails full depth break out,removal and replacement of defective section of the
pavement.
Expansion joint repairs: Installation of new expansion joints in existing pavement slab.
63
Mudjacking: Elevation of settled concrete pavement and filling with cement grout or filling of
void beneath a slab with grout.
Full depth patching with precast slab: Full depth cut out, removal and replacement of a
defective slab with a precast unit.
Partial depth patching: Using of percussive concrete cutter to precisely remove damaged or
deteriorated areas of rigid pavement up to 10cm deep and 0.4m2.
Restoring skid resistance: Use of grooving, acid etching, seal coats of hard aggregates applied
to rubberised buders to restore skid qualities.
9.5
Pavement defects (mostly cracks and disintegration) develop in stages. Initially most
defects are apparent on the surface of the pavement which is usually immediately after
construction. In the next stage the defects develop progressively until they are of such an extent
and severity as to manifest on the surface. At this stage the defects seriously impair the
performance and serviceability of the pavement. The distress are diagnosed at the initial stage
by the use of standard specified equipment.
The Benkelmans Beam or Dynaflect is used to evaluate structural deterioration of the
road. The PCA meter which is a roughness measuring device is used to evaluate poor riffing
quality, while skid trailers are used to ascertain the prevalence of slipperiness
Benkelmans Apparatus
.
Early detection of defects restricts the development into more serious proportion. This is
facilitated by affecting proper repairs.
64