CEC110 Theory
CEC110 Theory
CEC110 Theory
NATIONAL DIPLOMA IN
CIVIL ENGINEERING
TECHNOLOGY
YEAR I- SEMESTER I
THEORY/
1
CIVIL ENGINEERING TECHNOLOGY
COURSE INDEX
1.1 Scaffolding - - - - - - 1
2.1.2 Introduction - - - - - - 8
2.4 Lintel - - - - - - - 9
2.5 Arch - - - - - - - 13
2
3.2 Door lining - - - - - - 18
Construction - - - - - - 20
3.7 Ironmongery - - - - - - 24
5.4.1 Plastering - - - - - - 35
6.4 Paint - - - - - - - 43
3
WEEK 7 7.1 External works - - - - - 47
7.4 Gate- - - - - - - - 50
8.4 Landscaping - - - - - - 54
8.5.2 Soakaway- - - - - - - 56
10.3 Contract - - - - - - 72
4
10.4 Tendering - - - - - - 77
13.3.1 Alarms - - - - - - 89
5
WEEK 1
1.1 SCAFFOLDING
around the perimeter of a building to provide a safe working place for workers
provide a scaffold.
Scaffolding uses many technical words such as those in this list to describe its
parts;
• Base boards: timber boards that support the base plate on soft or uneven
ground.
• Base plates: square metal plates that fits, into the bottom of scaffold tubes to
• Bridles: short length of tubing that are fitted to each of a window opening and
clamped to the transom. They fix the putlog scaffold to the surface of the
building.
6
• Guard rails: horizontal poles that are fixed above the working platform to
• Ledger: the horizontal poles that connect the standards. They are parallel to
the building
• Putlogs: cross pieces that have one end build into the wall of the building.
• Reveal pins: metal pins which tighten struts wedged vertically in window
openings.
PUT LOG SCAFFOLD– A putlog scaffold is one supported at one end by the
building under construction. One end of the working platform rests on the
2
Platform
Bridle
Putlog
Ledger
Standard
Base plate
7
Fig. 1.1: Part of a building scaffold.
The independent scaffold has a horizontal working platform that rests on vertical
poles at both ends joined together with ledgers which in turn support the transforms. The
scaffold is erecter clear of the existing or proposed building but is tied to the building or
Guard Rail
Transform Standard
Fig. i.2
a. MOBILE SCAFFOLDS
b. PATENT SCAFFOLDS 3
c. CANTILEVER SCAFFOLDS
independent scaffolds are used to provide access to restricted or small areas and/or where
mobility is required
format in which the members are connected together using an integral locking device
8
instead of conventional clips and couplers used with traditional tabular scaffolding. They
have the advantaged of being easy to assemble and take down using semiskilled labour
and will automatically comply with the majority of the requirement set out in the
Although simple in concept patent systems of scaffolding can lack the flexibility
The assembly of a cantilever scaffold requires special skills and should therefore
BIRDCAGE SCAFFOLD:- Birdcage are a form of scaffold normally used for internal
work in large buildings such as public halls and churches to provide access to ceiling and
soffits for light maintenance work like painting and cleanings. The consist of parallel
4
rows of standards connected by ledgers in both directions, the whole arrangement being
9
Fig. 1.3: Pictures showing various types of scaffolding
DISADVANTAGES
1. Timber scaffold takes longer to erect.
5
10
METAL SCAFFOLDS
ADVANTAGES
1. it is durable
2. it is quick and simple to erect
3. It is more adaptable
5. Metal putlog scaffold poles have flattened ends which do not leave holes in walls
DISADVANTAGES
1. the initial cost is higher than for timber
Regulations for the scaffolding are very explicit/detailed because of the high risk of death
2. The poles and components must be in a sound condition and suitable for the
purpose.
3. Timber poles must not be split or contain any rot or insect holes
6
11
1. Parts of the scaffolding should not be moved unless you check the changes fitting
carefully.
alternate boys.
4. Putlog scaffolding must have diagonal braces between the standards for the length
of the scaffold.
6. The scaffolding should be tied to the wall of the building under construction at 10
maintenance procedures .
It is important to check:
1. All parts of scaffolding at least once a week and always after bad weather
2. That no important pieces were removed if the scaffolding has been party
dismantled
3. That the braces are in place and that the scaffolding is tied to the building
4. That the guardrails and the rails are supported and in place
5. That all the upright are vertical by sighting along the line of the standards.
12
WEEK 2
2.1.2 INTRODUCTION
Doors and windows are the main opening in brick wall. Functional requirement of
• Dimensional stability
• Moisture penetration
• Thermal insulation/transmittance
• Sound insulation
• Fire protection
• Durability
• Buildability
• Security
• Appearance
newly built houses has sometimes given cause for compliant. Decay is particularly
lower parts of the windows (sills, bottoms of jambs and mullions, and lower rails
of opening lights) are most vulnerable. Decay is generally of the ‘wet rot’ variety
13
resulting from the use of timber of low natural resistance. Hence it is advisable to
decay, or timber treated with preservative, followed in both cases by two coats of
outside and condensation internally. The use of flimsy sections in window joinery,
2.4 LINTELS
Lintels are placed above the windows and doors to carry the weight of the wall above
them. Lintels can be made of steel, precast reinforced concrete beams, or wood. Lintels
rest on top of the last brick course that is level or approximately level with the top of the
window or door frame The bricks above the wall opening on which the lintels rest can be
strengthened by the installation of steel reinforcing bars. The placement of the reinforcing
bars is determined by the wall thickness and the type of window or door that is used
14
2.2. Double-Angle Steel. If you are using a double-angle steel lintel, it should be 1/4 in thick.
This makes it possible for the two-angle legs to project up into the brick to fit exactly into the
1/2-inch joint between the face and backing-up ties (Figure 3-32).
15
Fig.2.3. Picture showing lintel in building
16
2.5 The Arch
• The central stone that holds all of the other stones in place is the keystone.
• A structure that covers the spot where the arch begins is a molding
The Etruscans were the first civilization to use an arch. The uses of the arch were limited
because the arch did not fit in well with the classical architecture. They used the arch
when building:
• Gates
• Bridges
17
• Drains
A problem was found with the arch. The outer joint of the wedge-shaped stones of the
arch and the horizontal bricks of the wall was too noticeable. To conceal the joint, the
Etruscans constructed moldings called imposts. They called the arch and imposts an
archivolt. The imposts stuck out from the face of the wall so they needed to be supported
also. The piers were constructed so that the imposts sat on them. An example of an
The Roman architecture did not fully develop until they established the empire. The
Romans conquered many civilizations. They became students. The Romans used ideas
from other places in their own architecture. After the Romans conquered the Etruscans,
they assimilated the arch to fit into their architectural scheme.The Romans used the arch
when building:
• Bridges
• Aqueducts
• Gates
• Entrances
The arch could not support itself while being built. To support the arch during
construction, supports called centerings were used. This gave support until the piers were
built. Voussoirs, springers, and imposts were still used with the arch. The Romans added
a buttress to help support the arch. A buttress is a projecting structure, generally of brick
or stone, built against a wall to support or reinforce it. The Romans no longer used the
18
molding to conceal the outer joint. They believed that it obstructed the natural beauty of
the structure.
A door is movable barriers that separates internal and external spaces. It is usually
19
There is a wide range of door types available each with their own particular uses
and their own particular uses, and they can be broadly classified as;
• Paneled Door
• Flush Doors
• Matchboard Doors
1. Timber should be dry and well seasoned with moisture contents within the
Tenons should be kept narrow and their depth should exceed five times their
thickness
20
WEEK 3
21
3.2 DOOR LININGS
1. plaint: theses are usually prepared from board 38mm thick which are either
with a 12mm stop planted on this, however, economics in timber and can be
2. skeleton: this type of lining is particularly well suited for wider jambs and
3. framed: this is the best form of lining for an opening in a thick wall. It
consists of framed panels to the jambs and soffit similar to a paneled door, and
Linings can be fixed in a variety of ways and one of the most common is
to use rough grounds, often 50×19mm, plugged at about 900mm intervals in the
a. Define opening
c. Provide fixing for the hinges and a recess for the lock or latch
22
d. Provides a finish between the door and the wall
Door frames are usually made from solid timber with a rebate to house the door.
The frame is not related to the thickness of the wall surrounding it.
Door lining are usually fitted to internal doors where the lining is the full
2. paint the back of the frame to prevent the entry of moisture from the mansory
3. screw galvanized metal fastening to the back of the frame to lining which
5. build the fastening into the mansory joints to secure the frame or lining in
position permanently.
B. Steps to fix frame or lining into the wall after the wall is buil;
1. leave an opening that is about 3–4mm bigger than the frame when the wall is
built.
2. insert word plugs into some of the mansory joints that face the opening during
construction
3. put the frame in position after the wall and lintel are built.
23
4. level the frame with small timber for pieces
5. drill holes in the frame or lining for screws to go into the plays in the mansory
CONSTRUCTION
These are made from mild steel pressed into one of three standard profiles and are
suitable for both internal and external positions. The hinges and striking plates are
welded on during manufacture and the whole frames receive a rust –proof
24
treatment before delivery. The frames are fixed in a similar manner to timber
frames using a tie or tree bracket which fits into the back of the frame profile and
is build into the bed joints of he wall. The advantage of this type of frame is that
they will not shrink or wrap but they are more expensive than their timber
counterparts.
FLUSH DOORS
Flush doors have no projections or recesses on either surface of the door. These
doors are usually made of large sheets of plywood or hardboard. Flush doors may
This list describes the part that are specific to a flush door:
25
A Core: is the inner part of the door. The external boards or sheets of plywood are
recessed joints’
3. a solid center of timber strips glued together. This type of core makes a very
heavy door with good sound insulation that can be used for external doors and
fire doors.
A Flush Panel: is 3 mm plywood or hardboard sheets which are fixed onto the
core material.
A Lining: is a thin wooden strip that protects the edges of a flush door panel
A Lock Block: is a piece fitted into the internal framework of the door to make
durable product if the correct type of door is put in the right location. The
plywood facing and the frames for external flush doors should be fixed with
waterproof glue.
26
Fig. 2.9 flush doors
PANELLED DOORS
Paneled doors are suitable for internal and external use. They are made from solid
This list describes the main parts of a paneled door not defined in earlier sections:
Intermediate rails are cross pieces that divide the door into panels horizontally.
• 6mm plywood
27
Fig. 2.10paint grade flat panel metal door
3.7 IRONMONGERY
Ironmongery is the term used to describe hardware use for doors. Basic
28
WEEK 4
4.1 WINDOW
Window provides natural light and ventilation to the interior of a building while
1. the method of opening: under this we have the following types of windows.
2. the material from which they are made: under this we have the following
types;
a. Timber (wood)
b. Steal
c. aluminum
d. stainless steal
e. bronze
f. plastic
1. side-hung windows have hinges on one side and the fastening catch and
29
2. top-hung windows have hinges at the top and a securing stay at the bottom.
3. bottom-hung windows have hinged at the bottom and a securing catch at the
top. This window opens in and needs a special stay to stop it falling into the
room
4. louvers are individual pieces of glass held in clips and opend by a lower arm,
Fig. 2.13
30
Fig. 2.14. sliding window
31
4.3 COMPONENT OF DOORS AND WINDOWS
CILL: a horizontal member at the base of an external door and separates the
internal and external structure. It should slope so that rainwater flows outside
Frame: a solid timber or metal structure fixed to the door closes and supports the
doors weight.
Jamb: the vertical part of the frame that is fixed to the wall.
Rebate : a recess in the door frame that scale the edges of the door.
Stop: a thin pieces of timber fixed to the head and jambs of the lining to form a
rebate
Threshold: the access point in the doorway where you can enter or exit , the cill
Head: the top pieces of a window, which is fixed to the underside of the masonry
Cill: the bottom piece of a window, which is fixed to the bottom of the opening
Jamb: the vertical sidepiece fix to the surface of the window opening
Mullion: a fixed vertical piece in the window framework, which separates the
32
Opening light: another word for a sash.
Transom: the fix horizontal piece that separate the fixed and moving parts of the
window
33
WEEK 5
5.1 FINISHES
The treatment that is given to internal floors, ceiling, internal, and external walls are
Finishes serve decorating and practical functions. They improve the appearance of the
The two most important considerations for selecting finishes for floors, ceiling
surface.
Requiring vary in different parts of the building depending on type and purpose.
Many factors deserve consideration when selecting a floor finish, but not all the factors
are of equal importance. Further more, requirements vary in different parts of the
building. For instance resistance to oil grease and moisture is relevant in a kitchen but not
in a bed room, and appearance could be important in a lounge but is not little
consequence in a store.
Floor finishes for domestic buildings include a wide range of alternatives. The
factors that may influence any given choice depend on the use of the floor space and
limits on cost.
34
1. Economic:- Reasonable initial and maintenance cost having regard to the class of
2. Ease of Cleaning:- surfaces that allows dirt to easily penetrate are harder to keep
clean. If ease of cleaning is a priority, then a lard, smooth fi0nish is better than soft
open texture.
4. Resistance to Grease and Oil:- The floor should not be damaged up from the
5. Warmth Cool:- lard, smooth surface are cool to walk on because the conduct heat
away. Soft, texture finishes like carpet gives a room a warm feel, which ray the stable
for cooler climates. Some finishes are more warmer than others an this may be an
important consideration
8. Cost:- the cost vary enormously for the huge range of finishes. The cheapest finish is
a cement screed. The most expensive can be carpet woodblock or special floor tiles
etc.
10. Sound Absorption:- Some building such as hospitals and libraries need their finishes
35
5.3 TYPES OF FLOOR FINISHES
There are numerous kind of finishes, the more common finishes are:
1. Terrazzo Finishes:- Terrazzo floor finishes come from Italy where marble was
concrete and which Portland cement is the basis for the finish , but there is no sand in
1.2 cement and marble mix. Terrazzo may be in site or pre-cast. In site terrazzo can
either be laid wherein the fire aggregate incorporated in the mix or a mix where the
fire aggregate is spread in position and the larger aggregate is then sprinkled on the
surface and beaten and trowelled in. in order to prevent cracking, the following
(c) Floor divided into panels not exceeding /m2 in area, with sides in ratio of 3.1 and
(d) Terrazzo allowed to dry out slowly, and if possible the building should not be
heated for six to eight weeks after the floor finish has been laid.
The thickness of the terrazzo depends on the size of the aggregate. The standard
After about four days. Surface is ground by machine and finally polished using a
36
It is easily, cold and expensive.
2. Granolithic Screen: This is primarily used for factory flooring because of its
hardwearing qualities a typical mix is 1:1:2 or 1:1:3 of Portland sand and granite.
The best finish is obtain by laying a 10 to 25mm granolithic topping within 3 hours
of laying the base to obtain monolithic construction. After compacting, the ground
should be retrowelled to close surface pores and finally trowelled when the surface is
hard. The tendency to produce dust can be reduced by applying sodium silicate or
finish can be obtained by carborundun over the surface and trowelling at in before
the granolithic has set. The screen must be cured for a minimum of at least 7 days.
This is a difficult floor finish to produce, but it is extremely durable if done well,
it provides a cold, unattractive finish, but at a moderate price. The most serious
defect is the loss of contact with the sub floor around the edges of the days. Screen
3. PCV Tiles: These contain a substantial proportion of plasticized PVC resin which
gives added flexibility and resilience. PVC tiles have precise measurements
(300×300×3). They must be laid on a perfectly smooth screen because they are so
thin and fixed with adhesive however, they can be fitted so closely that they do not
(c) Durable.
37
Although they come in a wide range of colours and textures pvc tiles are one of the
cheapest floor finishes you can buy and lay. They are maintained by applying water.
4. Rubber Tiles and Sheets: These are made of natural rubber and various filling
compounds. Tiles are normally 3mm thick for housing work and 4mm in public
buildings, rubber flooring must be fixed with a suitable adhesive and is available in a
variety of colours and patterns. This flooring is quite warm, resilient, non-slip,
resistant to moisture and hardwearing. Oils, fats and grease have a harmful effect on
rubber flooring and it is expensive a variety of adhesive for use with flooring
5. Quarry Tiles: These are clay tiles with a hard semi-glated finish. They usually
measure about 150×150mm or 100×100mm and are 15 – 20mm thick. Since they are
fired in a kiln they are not shaped as pvc tiles, so the have a 3mm joints between the
tiles.
Quarry tiles are bedded in mortar so as leveling screen is not usually necessary.
They are useful for kitchen and toilets, being hardwearing, easily cleaned and
resistant to water, oils and grease, but they are also cold noisy and relatively
expensive.
6. Thermoplastic Tiles: These are made from asbestos fibres, mineral fillers, pigments
and thermoplastic binder and can be obtained in a variety of colours patterns. The
most common size is 250×250×2.5 or 3mm thick. The tiles becomes flexible when
heated and are fixed with a special adhesive to a cement and sand screed. They are
38
7. Vinyl Asbestos Tiles: These were a later development of thermoplastic tiles and are
made of pvc resin asbestos fibre, powdered mineral fillers and pigments. They are
particularly resistant to grease and hence well suited for use in kitchens and will
8. Rubber Later Cement: This is a mixture of Portland cement or high alumina cement,
aggregate fillers, pigment, gauged on the site with a stabilized aqueous emulsion of
rubber latex. It is usually laid to a thickness of 6mm, rubber later cement is resistant
to damp is nonslip, reasonably hardwearing, quiet and warm and can be laid in a
variety of colours.
9. Concrete Tiles: Concrete tiles are made from coloured cement and hardwearing
The have attractive finishes in a wide range of colours are hard durable, dustless,
Note: In summary, the three mans finishes for concrete sub floor are:
5.4.1 PLASTERING
The term plastering means the application of a smooth coat of material to the walls and
ceilings. The purpose of plastering is to provide a jointless hygienic, crack free, easily
39
decorated finish to walls. Plaster covers up the unevenness of tricks, blocks or concrete. It
may be required to improve fire resistance. Provide additional thermal insulation and
importance, and the selection is mainly influenced by the surface finish desired.
Plasters is mixed with to water make a plastic mixture, which can be spread
directly on a surface. The surface absorbs the water in the mix by a process called
suction.
The suction process stiffens the plaster rapidly so that it can be level while it
hardens and sets. When the plaster dries it leaves a hard, smooth finish for decoration
The choice of any given plaster finish depends upon characteristic such as:
2. Shrinkage
3. Expansion
4. Surface hardness
PLASTERING MATERIALS
Plaster is a powdered cement, sand and line or gypsum, which is supplied in bags. In
– Brick wall
– Block work
– Concrete
– Plaster boards
Each of the surface some preparation before plaster finish are applied.
40
Most bricks provides a good surface plastering because they have enough of a natural
keep (A key is a rough surface that plaster with stick to). Before plastering brickwork, it
is important to remove any projections and clean the surface with a stiff brush. When wet
plaster are applied to the wall the water from the mix is absorbed by the brickwork. This
should be checked to ensure that it does not chose the plaster to dry too rapidly so that it
becomes unworkable.
The type of concrete that might be plastering would be the soffit of a floor flat.
The concrete may might quite smooth from the formwork unless a chemical was applied
before the concrete was poured. To prepared concrete, it is important to wash off all
traces of all hack the surface to provide enough key for the plaster.
Plaster boards are designed to for a base for plastering the ceiling under timber
floors and roofs. Plastering is a solid core of gypsum plaster with a heavy paper surface
on both sides. The boards are usually 12mm thick for fixing to tribute support at 400mm
centres. Plasterboards should be fixed to the support with small, flat had nails which are
driven in slightly below the surface and filled over. Plasterboards can also serve as dry
lining for walls if batterns are fixed at these centres. Before the plaster is applied, the
joint the board should be reinforced with a 90mm jute fabric bedding in plaster.
You may apply one, two or three coats of plaster to achieve a smooth finish. Generally,
two-coat work is satisfactory for use with brickwork or block work, provided extreme
variations of suction are avoided. When using plasterboard, only one coat is needed.
Three coats are only used if the surface is extremely un-even. The first coat in a three-
41
coat finish, called screed coat, is applied to level the surface and to ensure that the plaster
There is a wide range of plasters available some of the man type are as follows.
1. Cement Lime and Sand Mixes:- This mix in a 1:5:3 mixture makes the hardest
finish. If the amount of line is increased and the amount to sand reduced, then the
hardness is reduced. This also reduces the amount of small crakes in the finish. This
2. Lime Plaster:- This is a weak, easily indented, slow hardening and shrink in drying
3. Gypsum Plaster:- They have a number of advantages over lime plaster, requiring
fewer and thinner coats, which set hard in few hours without shrinking, providing a
law, strong surface which does not cause alkali attack or paintwork. There are four
a. Class A (pop plaster of plant) set so easily/rapidly that it is unsuitable for most work
b. Class B (Retarded hemihydrates) plaster include board finishes and give a hard
surface which is sufficiently resistant to impact for normal purposes, set quickly and
c. Class C (Anhydrous) plasters give a surface harder than class B plaster and are slower
setting.
42
d. Class D (Keene’s) This provides a very hard, smooth surface, and slow setting
allowing ample time to bring to a fine finish that is particularly suitable for
43
WEEK 6
External rendering is the process of applying a cement and sand plaster coat to the
Rendering normally consist of two coat varying from 5mm upwards. Brick joints
Although gypsum is not suitable for external use, line can be added to a cement
Several different finishes and textures are common to external rendering. They
improve the appearance of the cement and sand mix and help to control shrinkage and
1. SMOOTH RENDER:- This is a cement and line mixed with sand in a 1:2:9 mixture.
needed then the proportions is reduced to 1:1:5. this is the least satisfactory finish
because the trowelling can bring too much cement to the surface, which caused
cracks.
44
2. ROUGCAST Or WETDASHRENDER:- This is a top cast cement lime and sand in
a 1:2:9 mix over a 1:3 cement and sand backing coat. While the top cast is soft a 6-
3. Pebble Dash or Drydash Render:- This is a five coat in a 1:1:6cement, lime and
sand render with 6-12mm pebbles lightly pressured into it so that the aggregate is
exposed.
4. Scraped Render:- The top is 1:1:6 or 1:2:9 mix in a sew blade just before it hardens
Tyrolean Render:- Tyrolean render is produced by a machine that throws a 1:3 cement
and sand mixture onto the wall for a deeply textured finish. The cement can be coloured
to produce a permanent coloured finish. The background can be rendered or the Tyrolean
1. Cracking
2. Crazing
3. Loss of Adhension.
45
1. The mix is too rich in cement which causes shrinkage cracks when the render
dries.
3. The background wall moves or settles. This can cause cracks or loss of adhesion.
4. The mix dries out too rapidly. This is difficult to avoid in hot sun, so the
2. Crazing:- this is a fine cracking in the top surface of the render. This is caused by
c) Too much suction in the backing coat which draws water out of the top coat
3. Lose of Adhension:- this is obvious when you here a hollow sound when you tap
46
6.4 PAINTS
Paints consist essentially a pigment, a binding medium and a thinner to make the mixture
suitable for application, the by brush, roller spray changes which convert it from a fluid
To achieve these objectives the surface preparation and paint application must be
adequate. The preparation of new and previously painted surfaces should ensure that
Composition
The actual composition of any paint can be complex but standard paint consist of the
following components:
1. BINDER:- Combines the pigment and other additives in paint and determines how
2. PIGMENT:- This provides the body, colour, durability and corrosion protection
The general pigment used in paint is Titanium Dioxide which is not poisonous and
give good abliteration. Of the undercoats. White lead pigments are very durable and
moisture resistant but are poisonous and their use is generally restricted to printing
and undercoating paints. If paint contains lead pigment, the fact must be stated on the
container.
47
3. SOLVENT AND THINNERS:- the thinners is the liquid part of paints, which
enables it to flow freely from the brush onto a surface i.e. material added to paint to
alter its viscosity. The thinner evaporates when paint dries which may take a few
hours or days. The evaporation of the thinner causes the characteristic smell of paint
which gradually disappears. Paint must be thoroughly stirred to mix the thinner and
1. Oil Based Paints (Gloss paints): gloss paints are based resins produced in
laboratories which have improved the quality of gloss paints. Oil based paints are
suitable for most applications if used in conjunction with correct primer and
undercoat.
2. Undercoats for Gloss Paints: These are modified paints that dry with fiat finishes
this makes it easier to rub them down and improves the adhesion to the gloss coat.
Undercoats also fill in the colour over the primes and consolidate the final colour.
3. Primers: Primers are applied to seal unpainted metal and wood surfaces. Typical
2) Zinc chromate is also oil based but for bare metal surfaces.
48
4. Water Based Paints: Most of these paints are called Emulsion paints. They are
also called water thinned paint and they form the gloss paints but also easier to
apply because they do not seal surface. You can use these paints on new plaster.
Water thinned paints have the primes, undercoat and finish in the same container.
Emulsion paints are easily applied quick drying and can be obtained with a
1. Limensasues 2. Emulsion.
Paint defect may be due to poor or incorrect preparation of the surface, poor application
of the paints and/or chemical reactions. The general remedy is to remove all the effected
paint and carryout the necessary or correct preparation of the surface before applying in
the correct manner new coats of paint. Most paint defects are visual and therefore, a
accurate diagnosis of the cause must be established before any remedial treatment is
undertaken.
1. Bleeding: This is staining and disruption of the paint surface by chemical action by
paint is ultimate destroy and a brown liquid appears on the surface. The remedy for
such is to remove the paint film and seal the alkaline surface before repainting.
3. Chalking: This forms a powdering surface due to natural ageing or the use of poor
quality paint. Remedy is to remove paint if necessary prepare surface and repaint.
49
4. Cracking and Crazing: Usually due to unequal elasticity of successive coat of paint
5. Blooming: Mistiness usually on high gloss or vanished surfaces due to the presence
6. Flaking and Peeling: Due to poor adhesion, presence of moisture, painting over
the subsequent expansion causing the defect. Remedy is to remove all the coats of
The steps bellows gives an easy and convenient method for painting wall and ceiling:
as a printing coat
50
Fig. 6.1. diagram showing how to paint ceiling
51
WEEK 7
External works are provided around a building to enhance the proper use of the building
and make the area a esthetic and appealing. The external works provide many functions
sound, reduction of glare and discharge of waste materials from the building. The
various external works provided in connection with building basically landscape work,
Fences and hedges are often used to demarcate boundaries between land of different
occupiers. There are different types of fences the choice of material depends on a
Hedges are normally row of small bushes or trees growing closely together.
1. It must be long-lived
5. it should be to produce.
There are three different types of fences according to the material used in making them
52
Theses are erected using hardwood posts and softwood rails. The posts are often
75×150mm possibly with pointed bottom for driving into the ground. The rails are often
moderate cost, but does not form a good barriers as people, animals and objects can pass
through it.
38 +87mm rail
75 +150mm post
b. Wooden Wood Fences: These are reasonably attractive and fairly expensive. Post
many be of concrete or timber. The max length of panels is 1.8m and height vary from
0.60m to 1.8m. the panels consist of horizontal and vertical slats woven together within a
frame of double vertical centres stiffenes. A minimum size of bettens end slats are
to the top of each panel. Wooden post are usually 75×75mm with a weathered cap, and
19+38 weathered
cap
53
50 ×20 capping
75×75 post
Slates
Center
stiffener
c. Close Board Fence: They are alternative and effective, but their initial cost is very
high. The posts may be of concrete or timber. Timber posts should have weathered tops.
Horizontal gravel board about 32 or 25×200mm is often fived below the poles to prevent
their bottom from being in contact with the ground to prevent it from decay
d. Chain Link Fence: They consist of a diamond shaped mesh with an average mesh
size of 50mm and average 3mm diameter finished with a galvanized or plastic costing
using aluminum wire. Posts may be reinforced concrete, steel or wood. The line wires are
54
pulled tightly with straining fittings at straining posts and intermediate posts are
galvanised
25+5 mild steel line wire
flat
50mesh
galvanize
chain
R.C Strut
Ground level
Fig. 7.4. Chain Link Fencing
7.4 GATES
Front entrance gates are normally provided by building. They could be wooden or metal
types. The standard wooden gates have width of 0.8 and 1.0m. While pairs of gates may
have overall width of 2.2, 2.3 and 2.6m. For metal gates are 0.9, 1.0 1nd1.1m for small
gates and2.3, 2.4 and 2.7m for pair single gates. Metal gates may be constructed of mild
steel or wrought iron and should always have a continuous frame work and be truly
55
WEEK 8
8.1 ROADS
Road is a specially prepared hard surface way for cars, bicycles, buses etc to travel on. It
may not be lawfully usable by the public at large. Roads are provided to make
accessibility easy to the normal housing estate road has a width of about 4.90m, although
For large housing estates, widths of 6.1 or 6.7m would be more appropriate
– Roads should be constructed in such a way that the longitutional gradients must
because if the road is too flat surface water will be difficult to remove or drain,
and if it is to sleep, it will become difficult to negotiate during rainy season when
– Adequate width of the formation to cater for carriage way berms and side drains
– Camber or single cross fall should be provided for natural drainage to the surface
water
– Adequate sight distance to ensure that the vehicle is brought to rest before
– Adequate carriage way to provide for the required no of lene which is base on the
a. Flexible tube
b. Rigid type
56
Flexible Road
This type of road is made up of a strong base surface with tar or bitumen coated stone.
Flexible road often contain a sub-base of gravel, shale etc. ranging from 100-250mm
thick. The sub base functions are to reduce stress in the sub grade, protects the sub grade
against frost and constructional traffic, and prevent mud entering the road structure. The
base may be formed of various stone pitching. A roller weighing 8-10 tonne may be used
to comp the base as surfacing. This provide, smooth, non skid, abrasion resisted and joint
less surface. It also has good cleansing and surface. It also has good cleansing and surface
RIGID ROAD
These are roads constructed of concrete road slab. They are often supported on a 75-100
mm thick base of granular materials, 100-200mm thick lean concrete, 100-150 thick
cement bound granular base. For light traffic the concrete slab is normally 150mm thick
with a mix of 1:2:4 and mix w/c ratio of 0.55 it could be reinforced with layer of fabric
reinforcement weighing not less than 2.5 kg/m2 or unreinforced. They are generally laid
57
Surface
Slab Concrete
Formation
Sub grade
Pathways are provided as tracks for pedestrians to walk along over an area of ground
pathways are provided as a way for foot passengers in order not to obstruct the traffic by
the pedestrian or foot passenger. Pathway width varies from about 1.35 to 1.8m on
housing estates and may increase to about 6,0. in shopping centres. They are normally
laid to a cross fall of 1 in 30 towards the kerb and there may be grass verge between the
path and the kerb. Pathways can be constructed of vaiety of materials and the choice
depends on factors such as what maintenece cost, appearance and wearing quality and
The layout of parking lots should provides for convenient movements of cars entering
and leaving the spaced and for convenient alignment and boarding by passengers and
drivers.
The normal planning approach to the provision of packing space is related to the
parking need the associated land use and its particulars trip generation capabilities. When
58
Clearance from intersections. Parking should not be permitted within 6m of any intersect
Angle parking is more convenient and accommodate more parked vehicles than parallel
parking, but is less safe. All vehicles should be assumed to be at least 4.7m long and
parking bays for parallel kerb side should be at least 6.7, long and
2.3m wide. For angle parking bays need only be 5.4m in length.
8.4 LANDSCAPING
This is the beautification of the building area by greasing and planting of trees, shrubs
These are used extensively in build up areas of towns and to a lessees extent on
residential estates. Standard sized are 600×600, 600×750 and 600×900mm in both 50 and
63mm thickness. The slab are usually laid on a 12 to 25mm bed of sand, lime or gauged
mortar. If vehicular Traffic is anticipated they should be laid on concrete. After laying
they should be concreted with cement on lime. Although expensive, precast concrete
In Site Concrete
59
This is suitable for large paved areas and paths to houses. The usual 19mm graded
aggregate and the concrete is often 75mm thick. It is relatively cheap, but unlike the
Appearance, absorb sand and reduce glare. They are relatively cheap to establish and
maintain when laid the finished surface should project about 20mm about adjoining
It is common practice to provide a 225mm wide strip of gravel treated with weed
Trees and shrubs improve the appearance of a building. Trees have great valve in form as
well as colours and they should be chosen to blend to the architecture and landscape a
building.
Trees also serves as barriers to noise and glare. It also give shade and shelter from
wind. Selection of the type of tree should be based on soil and climate conditions,
The code for small sewage treatment works prescribe a minimum distance of 15m from
habitable building for works serving up to 10 persons, increasing up to 90m for works
serving up to 100 persons or more. The sewage plants include septic tanks, soak away
60
A water tight single storeyed tank in which sewage is return sufficiently long to permit
sedimentation. Sewage is held in a septic tank for a prescribed period during which time,
the suspended solid settled down. The settled sludge and the layer of liquid above the
rectangular is common. The tank should have a minimum width of 759mm minimum
depth of 1m below water level and a minimum capacity of 2.7m2. For rectangular tank,
the length is two to four times the width. For circular tanks, the min diameter and depth
are 1.3m and 1.0m respectively. Precast concrete slabs, set slightly apart for ventilation
purpose and fitted with lifting rugs, provide suitable covers. T junction dip pipes form
8.5.2 SOAKAWAYS
A soak away is a ditch either lined or unlined into which the water is discharged or from
which the water seeps or soaks away water to the surrounding pervious subsoil.
In firm pervious ground, it is generally sufficient to dig a pit into which is drained
directly and the pit is covered with a concrete slab. In moderately firm soil such as clay
the pit may be filled with hard core or clean broken stone to maintain the side of the pit.
In granular soils such as gravel and sand, the soakaways pit has to be lined with brick
stone as concrete to maintain the sides of the pit and the lining brick stone or concrete
must be porous or perforated to encourage the water to soakaways into the surrounding
soils.
61
The soakaways should be at least 3.0m away from the building so that the soakaway
water does not affect the building for relations, and should also be on slop down from
62
WEEK 9
225mm
Block work
Removable
Concrete slab
100mm Inlet
1200max
100mm
Outlet
Lifting ring
Concrete slab
63
Soakaway In Firm Pervious Ground
Concrete slab
Drain inlet
Side of pit
lined with
dry stones
or hollow block
They have the same function. The object of constructing a manhole and inspection
chamber is to provide access to a sewer or drain. Manholes are built where there are
junctions between sewers change of gradient charge of pipes provides access at such
Manholes are deeper and have adequate headroom for repaire. Ideally safely in for
exceeds 900mm in depth, while inspection chambers are often lees than 900mm deep.
Rectangular with a cover and frame which ease the size of the chamber is not a
accessible, it can only be inspected from cover level i.e. workmen operate from above
ground when rodding a manhole where men operate below the ground.
64
Step iron
build into Cross fall and bearing
the wall
TYPICAL MANHOLE
Brick walls
Water base
INSPECTION CHAMBER
imposed loads, exclude ground H20 and be water tight. Their inspection, cleaning and
Manholes and inspection chambers can be constructed in brick work, insitu and
precast concrete sections. Bricksfor manhole are normally built of 225mm block in
cement and mother finished, fair faced internally, on internal rendering may fall and
result in blockages.
While brick walls. Chamber are normally rooted with a precast or insitu reinforced
concrete cover slab, 125mm or 150mm thick. The concrete bags is normally 150mm
thick.
65
9.3 DRAINAGE SYSTEM
Drainage is a system whereby waste products from baths, washbasin, water closet, sinks
and rain are collected and discharged into sewage plants. The drainage system must be
waste, in such a way as to avoid pipe blockage and escape of effluent into the ground. A
drainage system normally consists of a network of pipes bid from a building to fell to a
sewer.
3) Drains should be provided with sound foundation laid with uniform graduate [the
materials.
6) Drains on completion must be airtight and a clear bore throughout and be self
cleansing
7) No drain should pass under a building unless if be ones unavailable in which case, the
66
8) Rain water, posutes laboratory, basin and bath waste must discharged outside the
building
67
WEEK 10
Before any building operation is carried out. There must be an organization, local
offices, hospitals, schools, etc. the individual or organisation in this respect is known as
the building owner or the client, the client at most times may have little or no idea about
the design, panning and construction of the structure. In the other to bring his dreams to
reality he has to work for qualified personnel in the building trade to assist him carry out
the project. The client usually will be responsibility for provision of the financial
The usual procedure is for the client to present a proposal brief to an architect, containing
comprehensive terms, the size, capacity, style of construction and building function that
is required, the architect will consider the feasibility and prepare an initial design for the
client approval. When the final design is complete, professional consultants (engineers)
are then engaged for structural analysis and specialist installations such as structural steel
works, services, etc. they are involved in the detailed design which is fanally sent to the
A quantity surveyor (often working in partnership with an architect) uses the drawings to
compile a bill of quantities. This is a complete list of all materials measurement, and
accompanies the design drawings when sent to several drawing contractors to price
68
the lowest estimate secures the contract. And in some cases reputation supersedes low
estimated tender.
Specification for local authorities and quantity surveyors: the architect is also responsible
for selecting building contractors by providing them with details and bill of quantities to
price, the (architect) then select the most suitable by checking their tenders. During
construction, the architect is responsible for the supervision of the project to completion.
He issue necessary instructions and inform the client of progress. He provides internal
certificate of completion and certificate of final completion for payment to be made to the
contractor (a small percentage of contract price called retention is hold to cover defects
QUANTITY SURVEYORS – When the architect has completed his working during
details and schedules, they are passed to quantity surveyors so that he may prepare a bill
contracts stage, the QS advise the architect on the cost and financial viability of the
project, and prepares approximate costs from the architect’s initial design, brief and
skeletal. He also checks the builder’s priced bill of quantities and advices the architect on
errors and accuracy of estimate. During and after construction, the QS prepare stage or
period valuation order with the builders and architect, prepares the final account and
civil engineer responsibility is to ascertain and analyze the structural component parts of
69
the structure against any systems of loading and forces, and to incorporate such materials
as to give increase stability to the structure. He also determine the soil characteristics and
loading behavior due to the exerting weight of the structure so as to avoid settlement
problem or collapse of the building. He will then prepare detailed structural drawings
within the architect’s design, design calculations and materials specifications using the
code of practice. During construction, he checks the quality of workmanship and correct
use of materials.
CLERK WORK – This is the architect’s representative on the site. He is to ensure that
the contractor or builder works according to the architect’s drawings, specifications and
constructions by checking and inspecting all aspects of the instruction. The check of
works can advise and comment on the work to the contractor and assist in interpreting the
architect’s design. He reports the details and progress of the contractor to the architect’s
office.
FORMAN –This is the builder’s senior representative on site he is responsible for the
running of the job. He may have a site clerk or store-man to assist him to take delivery of
all materials and see that they tally with the orders and invoices and are up to the
specified standards.
1. CLIENT
70
⇒ Present the architect with a detailed account of his requirements with regards to use,
→ Arrange finance
study.
to the contractor.
→ On completion, settle all agreed financial commitments with architect and builder.
2. ARCHITECT
conditioning,etc
→ Obtain agreement between then client,consultants and himself on the size ,shape,
→ Produce detailed drawings and material specifications for local authority and
quantitiy surveyor.
→ Select suitable building characters ,provide them with details and bill of quantities
to price (tendering)
71
→ Issue necessary instructions during construction to the build er and inform the
client of progress.
→ Provide interim certificate of completion for the builder to receive payment as the
contract proceeds .
→ Certificate completion for full payment from the client to the builder ,less a
retention fee (to ensure defects are rectified within an agreed period).
SERVICE)
→ Advice the architect (designer) of the most sufficient, economical and practical
material
4. QUANTITY SURVEYOR
→ Prepare approximate costs form archived initial design brief and sketches
→ Prepare the bill of quantities by measuring and listing the quantities of all material
used in the building in accordance with the current standard method measurement
→ Check builders priced bill of quantities and advice architect of errors and accuracy
of estimates
72
→ During construction, prepare stage or period valuations.
→ Agree on the cost of amendments and valuation orders with the builder and
architect.
5. CLARK OF WORK
→ Ensure the compliance with the architect’s drawing specifications and instructions
→ Reports directly to the architect, because he has no authority over the contractor
→ But he can advice an comment on the work to the contractor and assist with
6. BUILDER/CONTRACTOR
→ Ascertain whether he has sufficient resources (labour, plant and equipment) and
→ Visit the site to ascertain difficulties not revealed on the drawing or in the bill of
quantities.
→ Obtain and coordinate subcontractors and suppliers (plant and materials) prices
and produce an estimate based on these, the drawings, the bill of quantities and
73
→ Submits estimate to the architect, and if accepted, meet with the client, architect
legislation. To fulfill these obligations the builder will appont a manager, general
known as agent or general foreman, who will posses the experience to coordinate
→ Provide the quality surveyor with date at interim stage, and at contract completion
7. LOCAL AUTHORITY
appropriate departments.
→ Ensure that the proposal is suited to the site and does not breach any government
→ Ensure the design and material are aesthetically acceptable, and that the proposal
will not impose excessively or local qualities like roads, draws shops school etc.
74
→ Also at specific stages of construction, they conduct check with respect to
suitability and strength of material, and ensure that the proposal complies with the
building regulation.
8. SUBCONTRACTORS
9. SUPPLIERS
→ Market properties for a percentage fee charged the seller, usually about2% and his
negotiable.
11. FOREMAN
→ Builder’s senior representative on site, responsible for the running of the job
75
May have site clerk or store-man to assist him in taking delivery of all material and
see that they tally the orders and invoices and up to the specified standard.
10.3 CONTRACT
A contract is formed when an offer (eg tender) by one party is unconditionally accepted
by the person to whom it is made, the second party. The key word is “unconditionally”.
Implying that full and complete agreement has been established between the parties. An
acceptable accompanied by “ifs’ or “but ‘s” or “provided that” does not form a contract
but constitutes a counter-offer which in its turn requires unconditional acceptance by the
first party.
There are different types of contract and any type depends upon the method at which it is
arrived at, at the nature of work and any other specific condition etc.
In lump sum contract, the contractor undertakes to execute the whole works as described
in the bell of quantities for a fixed sum of money. The most important thing in a lump
sum contract is that consultant must be quately define the scope of works. To minimize
areas of problems, detailed drawing are used to clarify all the items of works. Variations
are usually not permitted except where these are specifically stated in the conditions. To
realize the full benefits of the lump sum contract, the client must choose an experienced
contractor knowledgeable in the types of works on land. In this kind of contract, the
engineer supervising the project must be vigilant in order to reduce the temptation of the
76
2. Cost Reimbursement Contracts.
In cost reimbursement contract, the employer (client) pays the contractors the actual cost
of the work plus a management fee which include the contractor overview charges,
supervising cost and profit. The management fee may be calculated in one of the three
different ways.
and little incentive to ensure that the work is carried out in an efficient manner and at
In this type of contract, the contractor finances the project and he may also be the
designer. The client does not fully finance the project but starts repayment upon
completion. Or as it is often said the key are handed over to him. The client is required to
provide equity contribution in form of indent properly especially the plot on which the
project is to be erected.
4. Measurement Contracts
Under the measurement contract category, two subclasses are easily identified. Bill of
The bill of quantity contract is the most popular contract method adopted. Its
attractiveness stems from the check and balances explicit in its use. The consultant design
77
and prepares a detailed bill of quantities which are computed from the drawing. Other
– During tender analysis it is easy to compare the quotation of tenderers since they
– From the onset, the engineer and tenderer are not in doubt about the scope of
works. In the way they are fairly accurate about the contract sum and generally,
the final account at completion does not derived much from the contract sum in
the agreement.
– In drawing up the quantities, it is easier for the engineer to bring out his cost
estimates.
– The client can increase or decrease the scope of works depending on his
resources
The units of measurement and quantities are stated by the consultant while the rates and
amount are inserted by individual contractors. Suring the execution of the work actual
This is a variant of the bill of quantity contract and is usually adopted for a defined
geographical area and in a stated time for example, area A from January 2005 to June
78
2005. The typical case gives a comprehensive list of all items of works covering the work
which the client is interested in. the quantities are not defined as the bill of quantity
contract. The contractors are invited to state their rated to the items. In some cases, the
contractors are given rates by the consultant and they are asked to confirm their
acceptance. This method is not popular for public works because of its inherent in
accountability.
A design and build contract is a contract arrangement whereby the contractor offer it
design and build the construction project for a sum inclusive of both the design and
construction costs
The major advantage of this method is that both a firm price and reliable completion date
be guaranteed since the contractor has complete responsibility and contract over the job.
A major set back of this method is that variations to an accepted design is often
6. Serial Contract
This is useful when the client has a continuing building programme. contractors are
invited to tender in completion for one particular project but bearing in mind that a
successful tender will lead to further negotiation for a number of project of the same
character. In this type of contract, a safeguard clause for the client is usually incorporated
in terms of the contract, stipulating that if the work is not up to standard, subsequent
79
10.3.2 CONTRACT DOCUMENT
A contractor cannot give an estimate or ender for any job unless he is told the
requirement of the client, the right and obligations of the client and the contractor to the
contact. This is normally prepared by the architect or the engineer on behalf of the
employer and give to the contractor for careful study. The information is complied in sect
The contractual relationship between client and builder is simplified by issuing a copy of
the contract document with the drawings, bill of quantities, material specification and
tender form, when the builder invited the tender. The contract document clarifies terms of
contract more precisely leading to a reduction from both dissatisfied customers and
builders.
The following are normally included in the contract document for civil engineering
works; date and duration, names and addresses of all parties involved; address and
location of site, bill of quantities (contract sum); form of tenders; contract drawing with
Ref. No. and titles; material specification and general condition of contract.
10.4 TENDERING
After the explanation of the drawing as both of them are sent to the local authority for
approval. And subsequently a contract document is produced. After the completion of the
80
contract document, the next is to write contractor(s) to tender for the work, this s done in
number of days;
The architect or engineer acting on behalf of the employer put up adverts for the
competition and tenders may be received from firms who have neither the necessary
financial resources nor adequate technical knowledge and experience of the class of
work involved. The engineer carefully check all tenders before making final decision.
With this method, the engineer negotiate the contract with a single contracting firm.
This is useful where the contractor might already be engaged on a current job
for the clienton the same site, or when the contractor in question has an exceptional
for them to state the price of carrying out the work described therein.
1. Open Tendering; In this method the prospective employer advertise in the national
and or technical press giving brief details of the proposed work and invited interested
81
contractors to apply for job either to him or his Architect for the necessary
documents.
To prevent unserious tenders, the advertisement usually calls for a fixed deposit
from any contractor wishing to tender for the job. This deposit may be returned nut only
This method often result in undue waste of time, effort and also in sorting and
checking the submitted documents during selection. Its more than not results in poor
A major advantage of this method of tendering in that 4 creates room for new
out the work is chosen by the client or his professional adviser who than negotiates
The contractor is selected at early stage in the design process but the early
selection need to exclude competition for there maybe s preliminary competition on the
basis of a tender document in which the contractor indicates the level of cost required for
labour rates site establishment charges over leads and profit. Under a contract of this
nature, there is usually little time to waste for drawing and bills of quantities to be
prepared.
There is always the danger that the price obtaining in this way may be higher than
82
1. the work to be carried out is of an unknown nature resulting in difficulties of
2. there is time restricted that is no room for normal tendering procedure in the
documents and selection of a builder with this method, the services of a contractor
are considered based upon merit or reputation and the employer is advised on who should
be awarded the job normally it is employed when the wok is high magnitude and
complex in nature.
83
WEEK 11
SERVICES ON SITE.
how the contract will be carried out if the tender is successful. This will involve a
1. ACCESS CONSIDERATIONS: This must be considered for both on and off site
access. Routes to and from the site must be checked as to the suitable for transporting
all the requirement for the proposed works. Access on site for deliveries and general
which is part of the contract by erecting this at an early stage in the contract. This
allocation of adequate areas for storing material and allocating adequate space around
minimum without impeding the general site circulation and/or works in progress.
84
4. ACCOMMODATION CONSIDERATION: Number and type of site staff
anticipated, calculate size and select unit of accommodation and check to ensure
compliance with the minimum requirement of the construction (health, safety and
The need for and type of security required will vary from site to site according to
the neibourhood, local; vandalism record and the value of goods stored on site.
Perimeter fencing, internal site protection and night security may all be necessary.
6. SITE LIGHTING: this can be used effectively to enable work to continue during
employed externally to illuminate the storage and circulation areas and internally for
mobile? If static, select the most appropriate position and provide any necessary hard
suitability, provision of space and hard standing for on site plant maintenance if
required.
85
86
WEEK 12
The requirement for the structure of building to have a specific fire-resistance is to allow
time for a fire to be detected, the alarm sounded and for people to escape from the
building. It also allows time for the fire brigade personnel to enter and fight the fire. For
people to evaluate the building during out break of fire takes a length of time and this
depends on the size of the building and the number of people occupying the building.
There are certain basic rules to be observe when planning or designing for the means
2. Doors forming part of the enclosure to a protected zone should be fire- resistant and
self-closing
3. Escape routes should lead to the open air not into the building
To calculate the number and the width of exit doors and escape routes, the population
of the building on each floor has to be know or assessed. The number of a people likely
The design of an escape routes depends on the rate at which people can move in
single file through a single width doorway. This is assure in 21/2 minutes. Such a
87
doorway should be the width of 900mm, while the corridor for a single door should be at
least 12oomm wide. This also represent the minimum staircase width allow by the code.
88
WEEK 13
Fire outbreak in buildings is a result/or caused by accident. However, some are as a result
of carelessness.
The essential ingredients for the propagation and continuation of fire are:
If any one of the above listed is absent, a fire cannot start and if anyone is removed in
Most burning process produce a flame. Combustion continues when the heated fuel
gives off gases which themselves ignite, heating more fuel to ignition point.
Material differs in their readiness to burn. Volatile material like petrol have a light
fire and explosion risk while timber (solid timber) is slow to ignite. However, a thin sheet
Fire spreads by the condition, convention and radiation of heat. Heat travels through
metal by conduction and can cause timber with which it is in contact to ignite.
Superheated air rises by convection and can cause fire to spread uplet shafts and
staircases to remote points. Radiation from a fire can rise the temperature of inflammable
89
13.1.1 FIRE RESISTANCE MATERIALS IN BUILDING
In the event of an outbreak of fire, it is expected that materials used in the construction of
building should have the ability to resist fire for a considerable time. Some of these
1. STABILITY: Resistance to cracking and allowing fire to pass e.g. floors, wall and
doors.
The main component forming the structure of a building are usually incombustible
but as the building is occupied and used for many purpose, the content are often highly
inflammable. In addition, many of the materials used for finishes, insulation and acoustic
control, and for carpets, curtains and upholstery are often inflammable.
The flammable materials influence the severity of a fire and the total colorific value
Primary fire fighting is the first line of attack in the event of five and includes the use of
portable equipment by a person soon after the fire starts, prompt action can limit a fire
90
13.2.1 EQUIPMENT FOR FIRE FIGHTING
1. HOSE REEL: These are hoses about 23 meter long coiled on metal reels, they are
2. ASBESTOS BLANKET: These are useful to smoother fat and oil fires in kitchens
3. FIRE EXTINGUISHER: These offer a hardy means of fire fighting. They do not
weight more than 15kg. fire extinguishers come with different contents which are
(soda/acid type).
b) FORM: In this process, water and a foaming agent are mixed and forced out by
carbon dioxide. The foam cuts off the air supply to the fire
c) DRY POWDER: The dry powder contains no water. carbon dioxide under
release, the liquid form freezing solid particles. In the proximity of the fire, they
produced large quantity of carbon dioxide gas, cutting off the oxygen supply.
91
13.3 FIRE DETECTION AND ALARM.
The detection of a fire outbreak normally proceeds the alarm being raised. Detection
visual observation followed by individuals raising the alarm is often the method relied on.
The other method rely on the automatic detection and sounding of an alarm without
13.3.1 ALARMS.
The simplest method of given so sending warning on a fire out break is by shouting
followed by whistlers and hard bells. It could also possible to have and electronic system
whereby push buttons linked to bells are located at various position in the building to
avoid accidental or frivolous use, the bottoms are located behind glass panels which must
Automatic detectors are place at high vintage of a building. Basically, there are three
1. Smoke entering the detector reflects a light beam on to a photo-electric cell which
entering the chamber interrupts the current and operates a rely which sounds the
alarm.
3. A bi-metallic strip bends in the heat from the fire and entire computer or breaks the
alarm circuit.
92
WEEK 14
There are different type of burglarproofing material such as steals, metals, rods,
broken bottles, cables an pipes. Which is for durability and strength. The steel metal
rod are pf different size as stated below 8mm to20mm etc to suit the various types of
burglarproofing construction.
The rough rod are used in burglary frame mainly because of the strength to hold firm
to the wall. The smooth rods are used foe netting of the window burglarproof because
of the virtue of which it can be rolled into the form of the burglarproof.
Square pipes, rectangular pipes, round pipes etc. and even flat bars.
Wood are materials that has a long history as a structural components in the
construction of burglarproofing.
Broken bottles in the fence are another types of burglary proofs material normally
placed collectively on top of the fence round the building. Some tine shape rods like
nails are used mainly for security purpose and concrete are used mainly for security
purpose and concrete are often used to hold the proofing materials on the top of the
93
ii. Screw galvanize metal fastening to the back of the frame or lining which match
iii. Stand the structure in position, level and support it with struts
iv. Build the fastening into the masonry source or frame to secure the frame in good
position permanently.
v. Insert wood page into some of the masonry joints that face the opening during
construction.
vi. Put the frame in position after the wall are on the wall to allow escape having
been opened from the hooked end, and may not to have a pad lock.
94
FIG. 14.2
95
WEEK 15
materials, scaffolding and trenches etc. creates risk for the building workers and other
people in the construction area. A look at some of the safe working practice that can
very necessary.
Accident will happen on building site, but the number can be reduced by
developing the skills that is needed to work safely. Safety record can be improved by the
The following safety methods are inherent in construction sites and safety is
1. Wearing Protecting Clothing: Working cloths should be kept in a safe place on site
so that changes in and out can be made each day. A locker is useful so that personal
The best cloths are overalls and strong boots. If working. In wet weather, a rubber
boot will be important also and a hard hat to protect the head in case anything is dropped
excavation are not protected, then they should be surrounded by excavated materials.
96
During work in deep excavation one may not be seen by other people working at
a. Wear a hardhat to protect the head in case some thing is accidentally thrown
b. put support against the sides of the excavation so that the soil cannot fall
inwards.
Depending on the weather and the types of soil, excavations can be wet or dusty.
If it is wet, then one dusty conditions. A mask to cover mouth and nose should be
worn. Excavations should be inspected daily before anyone is allowed to work in it.
building activities. Building workers can accidentally fall off a platform or parts of
the scaffolding workers instinctively move around the platform and ladders without
looking down, then they could fall if the position of the scaffolding is changed.
Workers on scaffolding must always stay alert and check that factor and hands can be
placed solely to prevent accident, expert must erect scaffolding to the highest safety
4. Working with Cement: Cement is a safety risk for a number of reasons. It can:
Gloves should be worn when cement is harden and if cement dust is present, then
97
5. Working with Dangerous Materials: A building site may have many dangerous
b. Petrol
c. Paraffin
Careless use of these material can cause considerable harm to the building workers,
Explosives and detonators must be cleared from a site when they are not in use.
When they are kept on site, they must be locked in a safe place and the site should have a
Petrol that fuels the machinery must be kept in and locked in a safe place. Diesel is a
better choice than petrol because it does not catch fire so easily, but should also be kept
away.
Caustic cleaners and paraffin should be stored in locked areas so that their use can
be controlled.
6. Working with Electricity: You can power machinery and temporary lighting with
electricity. Because building site are often wet places, electric shocks are possible.
The wiring to the equipment and lighting may get rough treatment. For this
reason, it is extremely important to inspect and check the condition of the wiring at
98
regular intervals. Ideally, the electricity to power tools and light should be 110 volts
and connected to transformers instead of 240 volt supplies. The reduce voltage means
Note: If a person suffers an electric shock on site, then follow these steps:
– Contact an ambulance
A building site should have a first aid box with the following minimum contents;
some one on site should be in charge of the box and should be versatile in first aid
treatment.
Health and hygiene are as important as safety on building sites. This means that, the
workers should have access to an area for cooking and the facilities for basis hygiene as
well as a schedule that allows rest breaks and meals, healthy workers needs
99
notice about wearing hardhat, avoiding accidental fires or other careless activities
can promote sale working practices. The site could have a notice working practices.
The site could have a notice board to remind every one how many days or months it
100