Manual For Civil Work
Manual For Civil Work
File Name:
UNIT:
PREPARED BY:
Version #: 1.0.0
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Mobilization
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Layout Setting
Layout setting consists of following works:
1.
1.
2.
From
CAD,
get
the
value
Y1,X1,Y2,X2,Y3,X3..Yn, Xn.
3.
of
X,
X4
X3
Y4
Y3
X2
Y2
X1
PREPARED BY:
A
ENGR. A.H.K. MAMUN
Y1
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
4.
5.
6.
7.
8.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
9.
10.
11.
12.
Piling
Purpose:
Piling is done where our foundation drawings shows they are
required
There are three kinds of pile:
1) Driven pile Wooden, RCC (pre-cast), and Steel
piles.
2) Bored pile - Cast in situ piles.
3) Sheet pile Wooden, Steel and RCC.
But usually for our works, we use bored pile using percusion method of
boring (Wash boring).
Scope:
Applies to foundation footings, pile caps and raft etc.
Description:
This work covers pile centering, boring, washing of bore holes,
rebar fabrication by welding, placement of rebar cage in the bored
hole and concreting the cage and bored hole.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Equipments:
i. Pile rig (Tripod, winch machine, boring pipe, trime pipe,
cutting chisel of different diameter, bucket etc.
ii. Mud pump of 12 HP.
iii. Water pump of 2 HP.
iv.
Mixture machine.
v.
Welding machine.
vi.
Rod cutting and rebar spiral making instrument.
Materials:
i. Cement.
ii. Rebar.
iii. Coarse sand.
iv.
Medium coarse sand.
v.
Stone chips/ Shingles.
vi.
Welding rod
vii.
24 SWG wire.
viii.
Electricity.
ix. Water.
x. Level pipe.
xi. Admixture (for increasing slump).
Responsibility:
APE, SPE/PE, DPM/PM, Manager Q&C, Audit & Quality Inspection
Team.
Work Procedure:
1. Complete the layout as per architectural column layout plan.
2. Check the layout in accordance with structural column layout and
pile layout plans.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
5. Once the pile points are fixed in accordance with above, select a
suitable space for preparing mud tank of double chamber.
6. Mobilize all the pilling instruments and materials at site.
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
17. place rebar cage in the pile hole in a way that the tip of the rebar
remains at least 1-6 from the bottom of the hole while top of the
rebar cage will remains above the cut-off level.
18. Place tremie pipe and bucket in the pile hole.
19. Prepare concrete in the way described in the general notes of
structural drawing.
20. Place the concrete in the pile hole through tremie pipe.
21. Start compacting the concrete of the pile by making up and down
motion of tremie pipe with the help of winch machine after placing at
least two batch of concrete.
22. Complete the casting of each pile in the way described above.
23. Take precaution so that two successive piles under a pile cap are
not cast in a day.
Inspection:
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Earth Excavation
Purpose:
Excavation of earth upto required level is done for all kinds of
foundations of a building.
Scope:
Applies for all sorts of footings, pile caps, raft and basements of a
building.
Materials:
ii. Excavating plants and tools.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
v.
vi.
vii.
viii.
ix.
Version #: 1.0.0
Responsibility:
APE, SPE/PE, PM/DPM, Manager Q&C, Audit & Quality Inspection
Team.
Description:
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Inspection:
Take proper shore protection arrangement by consulting with
your seniors.
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Inspection:
Check the finish surface is leveled both longitudinally and
transversely.
BLINDING CONCRETE
Purpose:
To provide rigid impervious bed to RCC in foundation where the
earth is soft.
Scope:
Applies to foundation and Ground level floor work.
Materials:
Cement, 25mm down graded brick chips, Local sand (FM -1.2 to
1.5) and potable water (normally municipal supply water).
Responsibility:
APE, SPE/PE, DPM/PM, Manager Q & C, Audit & Quality
Inspection Team.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Description:
Proportioning:
Mix cement, sand and brick chips in the ratio of 1:3:6 by
volume in foundation, basement and 1:2:4 in car park area.
Mixing:
Machine mixing:
Screen excessive dust from aggregate. Maximum
allowable dust is 3% by volume.
Measure the aggregates and sands as per proportion
by can equivalent to a sack of cement.
Dump the measured quantity of materials as per
proportion specified in the drawing in the drum of
mixer machine and thoroughly mix with required
quantity of water for period of not less than 2 minutes
after all material including the water are in the drum.
Control water quantity by measuring slump. Slump
not to exceed 50mm. One responsible person must be
in mixture machine point to control the quality of the
mix and ensure slump.
Hand mixing:
Mix the materials on a clean solid watertight masonry
platform.
Spread the measures quantity of sand evenly on
platform
Dump and distribute the cement evenly on sand.
Mix sand cement thoroughly until the mixture is of
even color.
Spread the measured quantity of brick chips in
another place of platform.
Spread sand cement mix on brick chips.
Thoroughly mix the above at least 3 times.
Add water gradually and turn the materials as above
till the each aggregate becomes coated with sand
cement mortar and becomes plastic to give a uniform
platform.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
PREPARED BY:
Version #: 1.0.0
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
FORM WORK
Purpose:
Form work is used to confine the concrete, mould and shape it to
the required lines and dimension as shown in the drawings.
Scope:
Applies to RCC work.
Description:
It includes all temporary or permanent forms or mould required for
forming the concrete together with all temporary construction
required for their support.
Responsibility:
APE, SPE/PE, DPM/PM, Manager Q & C, Audit & Quality
Inspection Team.
Material Requirement:
i.
Mango wood plank of various sizes.
ii.
Steel shutter.
iii.
MS plain sheet.
iv.
Steel metal lining Props.
Construction Methods:
i.
Use all column forms made of 16 SWG steel sheets with
holes for fixing & tightening. Height of form should not
exceed 2m.
ii.
Use wooden form for footing, beam and slab periphery made
of mango wood planks with minimum thickness of 25 mm
and include necessary battens, struts, runner & ties etc. Do
not use warp wood for shutter.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
iii.
iv.
v.
vi.
vii.
viii.
Tighten the column with nuts & bolts at every holes and
with T-bolts.
ix.
x.
xi.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
xii.
Check there is any gap /holes in the form & close with paper
or with thin metal that not to permit leakage of cement
grout.
xiii.
xiv.
xv.
xvi.
xvii.
xviii.
xix.
xx.
: after 36 hours.
xxi.
xxii.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
xxiii.
xxiv.
xxv.
xxvi.
xxviii.
xxix.
xxx.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
xxxi.
xxxii.
Version #: 1.0.0
Check the horizontal & vertical level & alignment of beam &
slab.
Detect the leaks & close.
xxxiii.
xxxiv.
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Description:
This item consist of straightening, Cutting, Bending and placing
reinforcing steel of quality, size, shape and dimension shown on
the drawings or as specified herein.
Materials Required:
MS Deformed Reinforcing Bars of 40/60 grade.
Ordinary Portland Cement
Stone/Brick Chips (25 mm down graded)
Sylhet Sand (FM from 1.8 to 2.5)
Coarse Sand (FM from 1.2 to 1.5)
Lap Lengths:
Column
30D
Equipments:
Form Work
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Rebar
Rebar are rust free and straight
Size and spacing of rebars are as per drawing
All crossing points are tightly fixed with binding wire of 24 SWG
Extra tops are properly placed.
Clear coverings and spacer blocks/chairs are properly placed.
Concrete Mix Proportions:
Mix proportion which is normally mentioned in the drawing by the
Consultant must be maintained strictly (usually mixing ratios are 1:1:3
and 1:2:4).
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Construction Joints:
Construction joints in grade beam: beam or slab will not be left at the
support. It will be left at minimum shear point of grade beam, beam or
slab. Bar schedule will be prepared before fabrication of reinforcement.
No casting of any structural member can be done with aggregates mixed
with foreign materials. At the same time casting will not be allowed in
any place which is water logged.
L/3
L/3
L/3
Materials Consumption :
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
requirement is as follows:
12 bags
22 cft
22 cft
90 cft
Brickwork
Materials Required:
a) 1st class brick
b) Portland cement
c) Local coarse sand (FM 1.2 to 1.5)
Mortar (Cement Sand Mixture) Proportion:
a) For 250 mm or more thick brickwork, cement-sand mortar ratio is
1:6.
b) For 125 mm or less thick brickwork, cement-sand mortar ratio is
1:4.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Work Procedure:
a) 1st class brick of good, sound, hard and well burnt with uniform
size, shape and colour and free from flaws and cracks are used.
b) Bricks should be fully submerged under clear water for at least
twelve hours and be used after one/two hours of taking out from
the submersion tank.
c) Keep mixing cement and sand in proper proportions and in
quantity under dry condition until the colour of the mixture is
uniform. Then add water gradually to produce workable mixture.
Cement-sand mortar should be mixed in such quantity that can be
used within 45 minutes of mixing.
d) Clean and chip the surface properly where the brickwork will be
done. Clean all debrises, dust, loose materials and laitance from
concrete surface.
e) Lay the bricks on a full bed of mortar to ensure proper adhesion of
bricks with the bed of mortar. Use English Bond pattern with frog
mark upward.
f) Check the horizontal alignment by thread or spirit level and
verticality by plumb bob.
g) All horizontal layers should be parallel and all vertical joints in
alternate course and be one layer above another. Fill all vertical
joints fully with mortar from top.
h) Thickness of joints should not exceed 12 mm and check that all
joints are properly filled with mortar.
i) Top surface of brickwork which meets with the RCC surface like
beam/slab etc., the joints between the brickwork and RCC work
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Material Consumption:
1) For 100 cft of 10" brickwork (1:6), material requirement is as follows:
Brick
1150 Nos.
Cement
4 bags
33 to 36 cft
480 Nos.
Cement
2 bags
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
If two bricks are stricken with each other, then the sound
will be metallic for 1st class bricks.
The shape & size of 1st class bricks are uniform.
When broken, the whole inner part should be uniform in
colour with minimum pores.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Plastering Work
Materials Required:
Ordinary Portland Cement
Local coarse sand (F.M from 1.2 to 1.5)
Work Procedure:
Brush and scrap the surface to make it free from oil, greasy
spots, efflorescence and loose mortar (brick or RCC surfaces).
Wash the surface with clean water and keep the surface moist
before plastering.
For R.C.C. surface, proportion of mortar mix will be 1:4 and for
brick surface 1:6.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Patent Stone
Scope:
Applies to bedding layer or base layer over existing concrete slab to
support floor finish surface like Mosaic, Terrazzo or Marble or neat
cement or granolithic floor finish.
Description:
This item consists of constructing 25 mm to 38 mm thick concrete
depending on floor levels prepared by pie chips, sand and cement mixed
with water to make workable concrete mix.
Material Requirement:
Pie Chips
Sand
Cement
Water
Construction Method:
Thickness
PREPARED BY:
- Potable Water
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Mix cement, sand & pie chips in the ratio of 1:2:4 by volume.
Measurement: Follow specification of concrete.
Mixing of Materials
Clean the old surface of by wire brush to make it free from dirt,
laitance and all loose materials. Wash with clear water.
Apply cement slurry on the concrete bed before placing patent
stone on it.
Take levels by concrete @ 2m c/c.
Lay the concrete gently from one side and spread evenly.
Compact by straight edge and wooden floats.
Rough the surface by broom for adherence of the finish surface
over it.
Curing
Moist and cure the patent stone concrete for at least 7 continuous days
before laying any finish over it.
Check :
Mark the top level of surface finish. Mark patent stone top level
with this reference after deducting finish thickness.
Check and keep the level of patent stone uniform by filling or
removing patent stone concrete which is still green to keep the
surface finish thickness equal.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Tiles Work
Materials Required
Tiles (homogeneous or glazed)
Portland cement
Local coarse sand (F.M from 1.2 to 1.5)
Pigment
Work Procedure
PREPARED BY:
Version #: 1.0.0
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Clean and chip the surface properly where the tiles work will be
done. Clean all the debrises, dust, loose materials and laitance
from concrete or brick surface where tiles are to be laid.
Check the horizontal level properly for floor tiles work.
Vertical alignment will be checked and leveled before fixing of
wall tiles.
Pressure test in PPR pipes will be done before fixing of bathroom
tiles.
Confirm about laying of all conduits which would be concealed
underneath the tiles.
The mortar will be mixed in dry condition as per proportion
(1:3).
The tiles will be kept in submerged condition for 2 hours and
the soaking will be discontinued before 30 minutes of tile fixing.
Tap the tiles with wooden mallet for checking whether there is
any void space under the tiles.
The joints shall be uniform and their width shall not exceed 2
mm.
Skirting will be 4" high.
The tiles should be of proper size, shape and defect free.
Joints should be properly filled with mixture of white cement
and suitable pigments.
Sectional size of bathroom and kitchen doorframe shall be 6"
x 2" to avoid exposure of tiles over doorframe.
Strip of tiles are to be left at locations which will remain beyond
direct eye sight.
Wood Work
Purpose:
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Wood is used in door frames and shutters, decorative wooden works and
various wood related works.`
Scope:
Applies to door frames and shutters.
Description:
The work covers manufacturing and fixing of door frames and door
shutters made of wood including sizing, rebating, joining the
wooden planks to give required shape and dimensions of frames
and shutter as per opening size and fixing, finishing, polishing the
same in the position with necessary fixtures and fittings.
Responsibility:
APE, SPE/PE, SPM/PM, Manager Q & C, Audit & Quality
Inspection Team.
Material Requirement:
Hardware
Locks
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
PREPARED BY:
Version #: 1.0.0
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Work Procedure:
Use wood which is free from sap, knot, cracks, large holes or
any other defect affecting appearance and strength.
Work on dry timbers.
Make each timber frame consisting two vertical jambs and one
head with 6'' x 2'' or 6'' x 2'' cross section.
Smoothen each member plank by planner till raised grains are
not visible.
Make 12 mm x 37 mm rectangular rebate in the members of
the frame by groove cutting machine. Rebate will be straight
and uniform.
Rub the members by sand paper to remove roughness and
ensure plainness before assembling them. Joints must be well
matched and tight, properly glued and secured with hardware
screws/nails.
The finished surface should be free from :
disfiguring effects
raised grain
stain
dents of chisel
uneven planning
uneven sanding
tool marks
scratches
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Fix the frames truly vertical, check the vertical alignment with
spirit level and with plumb bob.
Shutter:
Use wood which is free from sap knots, cracks, large holes
visual defects for door shutters. Each plank must be straight
without any warp on bow.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Paint Work
Purpose:
Paint is provided on masonry and concrete surface for protection
against corrosion, wear, decay and dirt accumulation. It is used to
produce smooth surface finish with aesthetic appeal.
Scope:
Applies to interior and exterior walls and ceilings.
Description :
This item consists of applying 2 or 3 coats of ready mix paint over a coat
of priming on brick or concrete plastered surface.
Material Requirement :
Sealer or Primer
Putty
Paint
Thinner
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Work Procedure:
Plastic Emulsion Paint:
Do not apply paint on the surface which has not been cured for at
least 14 days and which is not at least 45 days old. Use only for
interior surfaces of walls/ceilings.
Do not use paint on wet or damp surface.
Brush surfaces of walls/ceilings thoroughly with stiff brush/sand
paper to remove loose surface contaminations and particles.
Scrape off hard dirt and cement splashes.
Rectify defects with cement-sand mortar and cure the patch. Let it
completely dry.
Coverage area will be of 300 sft/4 liter can for 3 coats of paint.
For M.S surfaces- Use Red oxide primer/Red Lead primer/AlKarim Primer.
For Galvanized surfaces Use Zinc Chromed primer.
For Wooden surfaces Use Aluminium Wood Primer.
For concrete/plaster/masonry surfaces Use Elite Water Based
Sealer/ Berger Water Based Sealer.
Outside paint:
Use Super Aclose Master Coat or Berger Weathercoat or other
approved paint. Use 2 coats with primer or 3 coats without primer.
Follow procedure stated for Plastic Emulsion Paint. Use primer if 2
coats of paint are used or otherwise 3 coats. 1 coat of Snowcem
may also be used as primer.
Thoroughly stir the paint and thin with 15% clean tap water.
Use outside putty.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
- 1 gallon.
Enamel Paint
- 1 litre
Chalk powder
- 25 Kg.
Zinc oxide
- 1 Kg.
Water
- as per requirement
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Apply first coat of enamel paint after 2-3 days of putty work. Thin
with
maximum
st
5% T-6 thinner. 1 coat should be dried for at least 24 hours. Cut
1st coat with water proof emery paper No. 320.
2nd and 3rd coat same as 1st coat.
Do not smoke or fire during paint.
Keep the paint in a cold & dry condition.
Keep the tin caps tightly closed after use.
Before synthetic enamel use in steel structure, check that the
scales or rust are properly scrubbed. Check the application of red
lead primer before application of paint.
Check the opacity and density of paint after 2 nd coat. The plastered
surface should be completely hidden.
Ensure continuous curing of Snowcem for at least 4 days.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
:
:
:
:
:
1 gallon
25 kg
1 litre
kg
As per requirement
Apply touch putty where the surface is not level and undulated. Dry the
putty for 2-4 days.
For Wooden Surface (Coverage Area : 220 225 sft)
a) French Powder :
c) Chalk Powder :
d) Zinc Oxide
:
e) Al-Karim Primer :
PREPARED BY:
5 kg
kg
kg
3 litre
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Lime Terracing
Purpose:
To provide impervious course of waterproof and adequate thermal
insulation to roof surface.
Scope:
Applies to concrete roof.
Description:
This item consists of constructing a water proofing course of lime
concrete of ratio 2: 2: 7 (Lime: Surki: Khoa) on roof slab.
Material Requirement:
Lime
- Slaked Lime.
Surki
- Made from 1st class bricks crushed or grinded to
sizes below 2mm.
Brick clips- Made from 1st class Bricks crushed to sizes 20mm
down graded.
Working Procedure:
Use lime, surki and brick chips at a proportion of 2:2:7. Average
thickness of lime terracing will be 100 mm.
Soak the brick chips at least for 3 hours before mixing and allow
standing.
Mix lime & surki in the specified ratio on a clean platform in dry
condition until a uniform colour comes.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Add previously wetted khoa in the specified quantity over limesurki mix.
Turn over the whole mix once without adding water and kneading
the mix minimum three times daily by gradually adding small
quantity of water to make uniform lime concrete. During last
mixing operation, molasses and tamarind is used with it along
with water.
Continue above step for successive 5 to 7 days.
After allowing 5 to 7 days, a ball is to be prepared with the mix and
thrown on wall surface; if the ball is remains adhered with the wall
then the mix is ready for spreading.
Spread the mixture in single layer on roof evenly with proper slope
towards gutter/rain water pipe (slope minimum 1 in 50) and 20
mm thicker than that of specified thickness for consolidation.
Consolidate the lime concrete thoroughly by hammering the
surface with wooden mallets weighing about 1 to 2 kg and hammer
thoroughly for continuous 5 to 7 days starting from the next day of
laying lime concrete on roof.
Stop compacting the LCC when no mark of mallet is noticed when
struck to flat bed of LCC. Finally check the compaction using one
of the following ways:
1) Betel Nut Check: A nut is to be penetrated on the prepared
LCC surface with wooden mallet, if it is not possible to
penetrate; the compaction of LCC is satisfactory.
2) Core Check: 2X2X2 core is to be made on prepared LCC
surface and fill up the core with water, if water is not soaked by
the surface, the compaction of LCC is satisfactory.
Frequently sprinkle lime water (lime slurry) during consolidation to
keep lime concrete wet.
Soften the surface by sprinkling pure water to render the mortar to
smooth finish. Finish the surface using lime cement slurry with
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
the help of trowel. Do not use cement mortar for finishing the
surface.
Fill up the surface pore by lime putty prepared from lime and surki
(1:1)
Round the lime concrete at the junction of roof slab and parapet in
the shape of a haunch or fillet.
Rub the surface with brush and finish the surface with limecement grout (3:1).
Keep the surface continuously wet for at least 10 days.
Note: For reference enclosed sheet must be maintained and preserved.
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Responsibility:
Material Requirement:
Bamboo.
Nylon Net.
Jute/Hessian Cloth.
GI Pipe/MS Pipe.
Fire Extinguisher.
First Aid Box.
Buckets.
Construction Method:
Safety Net at Working Level
Hang safety net 6 feet above casting level to 6' or 10' below casting
level before casting with adequate post and bracing as per drawing.
Put horizontal net extending outside 6' to 8' from building
periphery.
Put hessian cloth above net and hang around building periphery to
prevent falling objects in adjacent boundaries.
Tie hessian cloth and net vertically and horizontally so that the
cover may be strong and rigid and do not sag at any point or level.
Remove worn-out hessian cloth and retie the sagged one to give
good aesthetic look as well as safety.
Check the condition of the hanging hessian cloth twice a week and
maintain them properly.
Safe Stock Pilling of Shutter:
Store all shutters and scaffolding materials at least 8'-0" away from
building periphery.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Fire Protection
Do not allow worker to smoke here & there.
Do not allow workers to use open fire for plumbing works. Allow
only blowlamps for plumbing works and only in bath areas.
Cooking areas should be well enclosed and check that the
burner/oven is placed far away from hessian cloth or flammable
objects.
PREPARED BY:
CONSTRUCTION MANUAL
File Name:
UNIT:
Version #: 1.0.0
Provide one fire extinguisher and two buckets, one filled with sand
the other empty for solely fire fighting during work progress.
Other Protection
Do not keep temporary electric wire lying on floor and in water.
Replace/rectify the damaged wire and conduit to avoid accident.
Transmit the wire using temporary poles to the working place and
through PVC conduits.
Use plug and do not put the wire directly in the outlet.
Keep first aid box with first aid medicine easily accessible.
Immediately rush victim if severely injured to nearby hospital.
Conduct a bimonthly training for all workers and staffs on safety
and security matters.
PREPARED BY: