HSE Plan Format
HSE Plan Format
HSE Plan Format
ABSTRACT
This document comprises Health, Safety and Environmental (HSE) Plan for the activities foreseen
during the Construction and Installation Phases of the development of Baltim North Project in
Mediterranean Sea (Egypt) Project.
Objective of the document is to identify the activities necessary to control and manage all health,
safety and environmental issues.
1
0
REV
Prepared
Checked
Approved
19/03/04
18/02/04
Date
CONTENTS
1.
INTRODUCTION ............................................................................ 3
1.1
1.2
2.
2.1
2.2
3.
4.
4.1
4.2
5.
RISK MANAGEMENT....................................................................... 8
5.1
5.2
Page 1 of 15
5.3
6.
7.
8.
AUDIT ......................................................................................... 11
9.
10.
11.
12.
13.
1.
INTRODUCTION
1.1
The HSE Plan will be reviewed, revised and updated at each start of a new
project phase and whenever there is a major change in the Company
Policies and requirements, or modifications to Company HSE objectives.
In case of conflict, documents hierarchy is:
1. PETROBEL HSE Policy
2. Project procedures
3. Applicable Guidelines
1.2
2.
2.1
3.
The activities of the project are in conformals with the applicable laws and
HSE codes/standards and appropriate authorization given by Egyptian
Authorities.
Recognised standards are applied in the execution of the project.
The standards applied by the Contractors must be in agreement with
Company Standards.
Project Team ensure that the requirements of the rules and standards are
accounted in the design premises, in the operating and surveillance
procedures.
4.
4.2
Comment [ES1]:
5.
RISK MANAGEMENT
The Risk Management process will be applied during the construction and
installation phases of the development of the Project to achieve the
following:
Systematically identify hazards, threats and potential hazardous
events
Identify activities that can release the hazard
Determine how likely is it to occur
Evaluate (assess) the risks against PETROBEL assessment criteria
Record the significant hazards and effects
Document the findings
Implement suitable risk reduction measures (prevent, control and
mitigate)
Determine if the hazard can be eliminated or controlled
Reduce the probability of occurrence
Reduce the consequences
Determine what measures are required if the hazard occurs
During the following phases of the Project a qualitative assessments of
identified significant risks to identify areas for potential risk reduction
and/or where mitigation measures need to be assessed shall be carried
out. Residual events will be assessed against defined Risk Screening and
assessment Procedure (Doc. HSE-IMS Procedure No 2 )
5.1
METHODS AND PROCEDURES FOR HAZARDS IDENTIFICATION,
RISK EVALUATION AND MANAGEMENT
Hazard will be identified and assessed using the following tools and
techniques:
Experience from previous experiences,
Use of checklists and accident statistics;
Codes and standards;
The selection of the appropriate hazard identification and risk evaluation
tools and techniques should depend upon the nature and scale of the
installation, the information available, the phase of the project and
experience of similar installations.
The emphasis at the Construction and Installation phases are on
minimising HSE risks by adopting, where practicable at this stage, by
careful design and implement operating procedures.
For Construction and Installation Phases has been held a brainstorming
dated 17th of February 2004 to map the Risk Register, each discipline
5.2
ENVIRONMENTAL ANALYSIS
OCCUPATIONAL HEALTH
6.
HSE ACTIVITIES
7.
8.
AUDIT
9.
10.
11.
12.
13.