Bow Tie Basic
Bow Tie Basic
Bow Tie Basic
Organisation, Responsibilities
Resources, Standards and Doc.
Hazards and Effects
Management
Corrective Action
Planning and Procedures
Implementation
Monitoring
Audit
Corrective Action
and Improvement
Management Review
Corrective Action
and Improvement
ELEMENTS
REQUIREMENTS
HSE Policy
Strategic Objectives & Targets
Review
Internal Audit
Independent Audits
Management Review
3. INTRODUCTION TO BOW-TIES
3.1.
Bow-Ties
Bow-Ties are a graphical display of the relationship between the various components that result
from the Hazard and Effects Management Process (HEMP, see HSE Management System element
above). They depict the relationship between Hazards, Threats, Barriers, Escalation Factors, Controls,
Consequences, Recovery Preparedness Measures and Critical Tasks, as illustrated in Figure 3, below.
The advantage of adopting the Bow-Tie approach is that it is an extremely powerful
representation of a hazard analysis and HEMP Process and are readily understood at all levels in an
organisation.
It is through the linking of Critical Tasks to Barriers, Escalation Factor Controls and Recovery
Preparedness Measures that Bow Ties can demonstrate the implementation of a HSE Management
System in managing the risk associated with hazards, in particular, hydrocarbon release scenarios.
3.2.
Critical Tasks
Each Barrier, Control and Recovery Preparedness Measure should have, as a minimum, one
supporting task, to ensure that the integrity of each barrier, control and recovery preparedness measure
is maintained. These are termed Critical Tasks, and are required to be performed, undertaken or
executed by responsible and competent persons.
Escalation
factors
Control of
escalation
factor
Control of
escalation
factor
Consequences
Barriers to
prevent
threat
Recovery
preparedness
measures
Hazard
Threat
that could
release
hazard
Top event
Consequences
Consequences
H
A
Z
A
R
D
AUDIT CHECKLIST
C
O
N
S
E
Q
U
E
N
C
E
S
THREAT
MAJOR
LOSS
Project Manager
Task 1 .
Task 3 .
Ops. Manager
Check
accuracy
Task 5 .
Task 9 .
Task 11 ...
Project Manager
Task 1: ..
Task 2: ..
Task 3: ..
Verify
performance
Illustrative Example of the Linkage Between Bow-Ties, Barriers, Critical Tasks and
HSE Management Systems
To demonstrate the relationship between Bow-ties, Barriers, Critical Tasks and HSE
Management Systems, consider the following example, which is an extract from a study conducted on
offshore asset in the Caribbean.
Figures 5 and 6 show the typical arrangement of the Left (Threat) and Right (Consequence) side
of a Bow Tie diagram, created using the THESIS code.
3.3.1.
Threat
NDT inspection
Well sampling
<None>
<None>
Escalation Factor
Performance standards
Approved contractors
<None>
<None>
Loc.:
TE:
Escalation Factor
Teak A Platform
Failure of
equipment
Operator training
Operator monitoring
<None>
<None>
<None>
External Corrosion
Threat
Overload
Threat
Human error
Threat
Figure 5 Threat Barriers & Critical Tasks (Left Side of Bow Tie)
Compressor enclosures
<None>
<None>
<None>
Inspection and
maintenance not
undertaken per schedule
Escalation Factor
Inspector competence
Loc.:
TE:
Teak A Platform
Failure of
equipment
Performance standards
<None>
<None>
Escalation Factor
+
B4
Stand-by generator
Approved contractors
Consequence
B4
B4
B4
<None>
Production Loss
Consequence
Redundancy in equipment
<None>
B4
Consequence
B4
B4
B4
Environmental impact
<None>
<None>
<None>
<None>
Consequence
D3
D1
B3
Figure 6 Consequence Barriers & Critical Tasks (Right Side of Bow Tie)
Other more generic examples for consequence related critical tasks would be:
Gas Leak Detection & Alarm: Ensure that routine/specific maintenance, inspection
and testing activities undertaken on Gas Detectors are planned, managed and conducted
in accordance with the maintenance frequencies, procedures, guidelines, checklists and
techniques specified in the appropriate documentation to ensure that they are
maintained in a safe and fit-for-purpose condition.