Management of Change
Management of Change
Management of Change
STUDENT HANDOUT
Presented by
Marcel Leal-Valias
MANAGEMENT OF CHANGE I
S.E.A.L. International
Small/large change ................................................................................................... 16
Emergency change .................................................................................................... 17
Temporary change .................................................................................................... 17
Infrequently repeated change ................................................................................... 18
Instrumentation change ............................................................................................ 18
PHA recommendations for change ........................................................................... 18
OPERATING LIMITS................................................................................................... 20
DEFINING THE SAFE OPERATING RANGE ....................................................................... 20
DEFINING THE SAFE OPERATING RANGE ....................................................................... 21
MOC POLICY AND PROCEDURE ............................................................................ 22
MANAGEMENT OF MOC ................................................................................................ 22
TEAM APPROACH ........................................................................................................... 22
FORMAL STRUCTURE OF MOC....................................................................................... 22
MOC COORDINATOR’S RESPONSIBILITIES ..................................................................... 23
THE EIGHT STEPS OF THE MOC PROCESS ....................................................................... 24
1. Initial request .................................................................................................... 24
2. First review ....................................................................................................... 25
3. Detailed Evaluation .......................................................................................... 28
4. Formal Approval............................................................................................... 30
5. Information Updating ....................................................................................... 31
6. Notification ....................................................................................................... 32
7. Implementation ................................................................................................. 32
8. Follow-Up ......................................................................................................... 33
MANAGING A NEW PROJECT ................................................................................. 37
MOC AUDIT................................................................................................................... 38
APPENDIX...................................................................................................................... 39
CCPA Checklist for Management of Change ........................................................... 39
MOC Program Evaluation Checklist........................................................................ 39
CANADIAN CHEMICAL PRODUCERS ASSOCIATION (CCPA)........................................... 40
Checklist for Management of Change....................................................................... 40
MOC PROGRAM EVALUATION CHECKLIST .................................................................... 41
Management Systems ................................................................................................ 41
Change Process ........................................................................................................ 41
Personnel .................................................................................................................. 42
Process Engineering ................................................................................................. 42
Piping........................................................................................................................ 42
Instrument/Control Systems ...................................................................................... 43
Structural/Civil ......................................................................................................... 43
Mechanical................................................................................................................ 43
Electrical................................................................................................................... 43
Equipment ................................................................................................................. 43
GENERAL REFERENCES........................................................................................... 45
MANAGEMENT OF CHANGE II
S.E.A.L. International
COURSE OBJECTIVE
Course Objective
The objective for this course:
MANAGEMENT OF CHANGE 1
S.E.A.L. International
INTRODUCTION
Any facility or operation is subject to continual change. Changes often are made in
equipment, materials and processes to increase productivity or to correct hazards. In some
cases, temporary adaptations, connections, bypasses or other modifications are made to
the facility or process. System administrators may decide to move employees within a
specific process, which could eliminate or create positions within the facility or process.
All of these changes have the potential to create new workplace hazards, some of which
are not immediately recognizable. Although some changes are more critical than others,
each modification should be analyzed for inherent hazards that may result from the
change. Although change usually is proposed for a good reason, changes made to
improve one aspect of an operation actually may increase the potential for hazards in
other areas of the same operation. To assess the impact of change and to monitor its
implementation, it is essential to have a policy and procedure for Management of Change
(MOC).
MOC seems deceptively simple, but it can be one of the most difficult elements of HSE
management to implement effectively. MOC invariably impacts other elements of a
Health, Safety and Environment Management System once it is implemented. Therefore,
to be truly effective, MOC needs to be integrated into all aspects of the system, and the
involvement of everyone in a facility needs to be encouraged. Commitment from
company management creates a climate that empowers people to initiate needed change,
and provides a supportive structure for the implementation of change. Employee
participation is essential. Those on the line often are the first to notice problems, and
involvement in the design of the MOC program fosters commitment and ownership.
Commitment at all levels is crucial. No matter how well designed an MOC program is, it
will be ineffective if it is not used.
It is impossible to describe a single, uniform method for managing change. The unique
circumstances and needs of each facility require that a system be designed specifically to
meet those needs. This course is not offering to teach a generic MOC program; it is
MANAGEMENT OF CHANGE 2
S.E.A.L. International
designed to look at the elements of effective MOC and present ideas that can be used to
design a facility-specific program that works.
The course begins with a video that dramatizes the Piper Alpha disaster, which can be
directly attributed to poorly managed change and management’s lack of commitment to
safety. We will use the video as our reference point for discussion of the theoretical
aspects of MOC and its relationship to other elements of HSE management. Next, we will
build a model for an MOC program that addresses all the issues relevant to initiating,
evaluating and implementing change. This model will be one that easily can be adapted
in the development of your own MOC program.
ACKNOWLEDGEMENT
With thanks to Ian Sutton for the use of the information contained in his book,
Management of Change, in the development of this material. More information about his
publications is available at www.swbooks.com
MANAGEMENT OF CHANGE 3
S.E.A.L. International
DEFINITIONS
Change
Is the result of a conscious decision to exchange, substitute, convert, alter, add, modify or
vary a component of an existing process, its equipment and/or control and management
systems. Change can be administrative, organizational and/or technical.
Administrative Change
Organizational Change
Modifying the structure of an organization, regardless of its size, is a major change, and
requires appropriate impact analysis. Typical organizational changes include:
Technical Change
MANAGEMENT OF CHANGE 4
S.E.A.L. International
MOC Policy
A public statement of the company’s commitment to implement change in a safe manner.
The company needs to communicate its MOC Policy to all its workers. The MOC Policy
provides a values-based framework for addressing change in the company’s facilities and
operations. The MOC Policy must be applied to all activities that fall under the umbrella
of change.
MOC Program
A component of an HSE management system. A systematic program is necessary to
ensure that changes are managed in such a way that they do not compromise the safe
design and operation of a facility.
MOC Procedure
The approved sequence through which changes are initiated, evaluated, authorized,
implemented and followed up. The intention of an MOC procedure is to ensure that
changes are reviewed and approved by people with appropriate knowledge and
experience. These people will then be accountable for effective implementation of the
changes.
MANAGEMENT OF CHANGE 5
S.E.A.L. International
SPIRAL TO DISASTER VIDEO
From a Management of Change perspective, we will look at the events leading up to the
tragic and avoidable loss of the Piper Alpha offshore drilling rig and the lives of more
than two thirds of those on board.
How could an effective MOC program have changed or mitigated the outcome?
If you had been in charge of their HSE system, what might you have done
differently?
MANAGEMENT OF CHANGE 6
S.E.A.L. International
“Spiral to Disaster” Synopsis
• Piper Alpha was originally designed to be safe. The design of four fireproof
modules placed hazardous areas as far away from sensitive areas as possible.
However, some time later Piper Alpha is modified to extract both gas and oil. The
modification places gas compression equipment close to living quarters, the
helicopter landing pad and the control room.
• The addition includes two gas compression pumps, A and B.
• A work permit has been completed for a routine two-week overhaul for gas
extraction pump “A,” but it has not yet begun.
• On July 26th, the same gas extraction pump, “A,” is taken out of service because
a pressure relief valve needs maintenance. Pump “B” continues to pump.
• The pressure relief valve is removed, but the shift crew does not have time to
finish the work, so the open pipe is sealed with a blank flange.
• The shift engineer fills out the appropriate work permit, and brings it to the
control room. The supervisor is busy, so the shift engineer signs off on the permit
himself. He does not inform the supervisor of the status of pump “A” or file this
permit with the other work permit for the routine overhaul on pump “A”. No one
on the next shift knows about the potentially hazardous condition.
MANAGEMENT OF CHANGE 7
S.E.A.L. International
• Because the only work permit on file for pump “A” is for the overhaul that has yet
to be started, the supervisor orders it to be started. No one knows about the
removed pressure relief valve, and its location is too high for the crew to see the
blank flange replacement.
• Pump “A” is started. Gas pressure blows out the blank flange replacement.
• The emergency shutdown closes all the valves, which ordinarily would isolate the
fire, but the blast blows out the walls in the oil separation area, which results in a
huge fire.
• The fire suppression system fails because the firewater pumps are switched to
manual, and are inaccessible because of the fire.
MANAGEMENT OF CHANGE 8
S.E.A.L. International
SAFETY AS A PRIORITY
Managers need to be given the clearly mandated authority to make difficult and
potentially costly decisions, if they believe the situation warrants. Corporate and
management commitment to safety as a priority must be communicated to
personnel.
• The oil fire causes adjacent gas lines to heat and burst in another massive
explosion. Management has known about this danger for two years, since a report
identified the potential for a catastrophic incident, but nothing has been done
about it.
• The blast knocks out communication between the other rigs and Emergency
Services, further isolating the Claymore manager. Too afraid to make the decision
to shut down, he tries to reach shore through a secondary satellite system.
Claymore continues to pump oil.
• In the meantime, a fire fighting ship that has been called in turns on its water
pumps too quickly, tripping the system. Before the pumps can be restarted or the
painfully slow evacuation equipment can be set in place, another explosion
generates so much heat that the fire fighting ship has to withdraw.
• If the other rigs had shut down the flow of oil as soon as they heard the first
distress call from Piper Alpha, the gas lines may have been saved and the oil fire
controlled.
COMMUNICATION BREAKDOWN
Clear lines of communication need to be established and communicated to all levels.
Everyone should know what to do and how to do it with confidence.
MANAGEMENT OF CHANGE 9
S.E.A.L. International
Discussion Questions
How could an effective MOC program have changed or mitigated the outcome?
If you had been in charge of their HSE Management system, what might you have done
differently?
MANAGEMENT OF CHANGE 10
S.E.A.L. International
BENEFITS OF MOC
Safety
Safety is the most important reason for implementing an MOC program. An effective
program will result in fewer incidents in the following areas:
As we have seen from the Piper Alpha disaster, uncontrolled releases of hazardous
materials will have the most serious and sometimes catastrophic Health, Safety and
Environmental consequences.
Problems created by uncontrolled change often lead to equipment stress and damage, and
repair and maintenance of such equipment can be hazardous to personnel. Some
examples of these hazards are vessel entry, climbing on and moving heavy machinery,
and working on high voltage electrical systems.
Uncontrolled (unevaluated) change may move operating conditions into an unsafe range,
encouraging or often requiring operators to override built-in safety systems. In some
cases, uncontrolled change means that personal protective equipment must be discarded
or physical safety devices, such as pressure relief valves and fire water systems, must be
temporarily overridden.
Economic considerations
MANAGEMENT OF CHANGE 11
S.E.A.L. International
Production
Production rates should increase because of fewer direct losses. Production quality and
capacity should increase and energy costs decrease because there will be less need to
recycle or reprocess off-spec materials.
Assets
Operations
Reduced down time for maintenance and repair and fewer injuries will result in increased
profit.
Company reputation
• customers
• shareholders
• employees
• local residents
• government agencies
• banks
The company then can attract investment capital, generate sales of its product, and
avoid legal expenses.
Conversely, dissatisfaction amongst customers may lead to lost sales. Anger amongst
members of the public and the workforce may result in costly lawsuits or disciplinary
actions by government regulatory bodies. If these problems tarnish the company’s
reputation, it may experience difficulty in attracting investment capital.
MANAGEMENT OF CHANGE 12
S.E.A.L. International
THE CHANGE PROCESS
Note: Root Cause Analysis will be addressed in greater detail during a later module of
the HSE Management Training Program.
Obtain approval
Before a change can be implemented, plant management must formally approve it.
MANAGEMENT OF CHANGE 13
S.E.A.L. International
Update information
Prior to implementation of the change, safety information needs to be updated. This may
include the creation of new procedures, training workers in the new procedures, and
updating drawings.
Implement change
The change is implemented as designed.
Monitor change
Assessments of the impact of change at any time during the design and operation of a
facility or process are critical. Unless the implementation of change is monitored closely,
opportunities to maximize the effectiveness of the MOC program can be lost. Monitoring
change involves ongoing hazard/risk assessment and follow-up to ensure requirements
are being met. Post-change assessment is a valuable method of identifying additional
need for improvement. It is only in monitoring and follow-up of implemented change that
the system can continue to be evaluated and improved.
MANAGEMENT OF CHANGE 14
S.E.A.L. International
WHEN IS MANAGEMENT OF CHANGE REQUIRED?
Many changes occur in the everyday operation of a facility. However, not all of these
changes require the scrutiny of an MOC procedure. Only initiated change (conscious
decision to change) can be analyzed and evaluated for its potential hazardous
consequences and, therefore, managed. Reactive, spontaneous or covert (hidden) change
cannot be managed because it cannot be anticipated. These kinds of changes must be
managed within other elements of the HSE Management System, for instance, Hazard
Identification and Mechanical Integrity.
Types Of Change
In-Kind/Not In-Kind change
If it is proposed to replace a piece of equipment with another that is functionally identical
and of the same specifications, the change is In-Kind and does not require an MOC
process.
MANAGEMENT OF CHANGE 15
S.E.A.L. International
• The service for which the equipment is being used remains unchanged. All
process conditions must remain the same as for those of the original item.
Inspection and maintenance requirements should not change.
• The replacement is part of routine maintenance. The In-Kind item is being
replaced because it has a known life span. Replacing In-Kind equipment that is
failing without known cause requires investigation and Management of Change.
• The new item is equivalent to the original one, not an improved model or from a
new supplier. Upgrades or new vendors should be assessed using the Management
of Change process. Even a seemingly minor change in any of the specifications
may impact some aspect of the process in some way.
Critical change
A critical change is one that could create a serious incident if it is mismanaged. Critical
changes should receive more thorough scrutiny than those considered non-critical.
When a proposed change is deemed to be critical but also expensive, the proposal should
be subjected to a Quantitative Risk Analysis (QRA). The story of the Piper Alpha disaster
illustrates such a need. The decision not to install blast walls between the oil separation
unit and gas intake lines, because they would have been too expensive, proved to be a
fatal mistake. A QRA would have shown that the consequences/probability/risk equation
warranted the expense of the blast walls.
Note: QRA has been mentioned in the Process Hazards Analysis (PHA) portion of the
training, and will be discussed in more detail in a later session of the training.
Small/large change
Large changes usually involve many modifications to equipment, instrument systems and
administrative procedures, and therefore should receive a full MOC review. However,
small changes may not be reviewed with the same rigor because they can be implemented
MANAGEMENT OF CHANGE 16
S.E.A.L. International
quickly and do not appear to make a significant impact on the way a plant operates. MOC
reviews, at least through a checklist, should accompany even small changes.
CAUTION: Plant experience shows that it often is the small changes that ultimately
lead to serious incidents. Because they are small, they may not be subjected to the
scrutiny they really deserve.
Emergency change
Emergency change is one that has to be made very quickly when someone in authority
decides that the dangers of doing nothing are greater than those possibly associated with
the proposed change. An emergency change may be justified for reasons such as the
following:
• danger to personnel
• potential for major equipment damage
• potential for major operational loss
• serious environmental impact
• serious community complaint
• regulatory violation
Every effort must be made to minimize the number of emergency changes, because they
bypass the normal systems for hazard identification. After the fact, every emergency
change should be reviewed by the formal MOC procedure to ensure that no unforeseen
problems exist and to ensure the change is documented and monitored.
Temporary change
In many instances temporary changes also are emergency changes. They usually are
implemented to keep an operation running while a piece of equipment is repaired or
replaced. A temporary change should have an automatic termination date. A
temporary change of even a short duration should go through at least a Safety Review
Checklist (see Appendix) by at least two or three people. A new procedure should be
written and an emergency response prepared in case the modification does not work
properly.
MANAGEMENT OF CHANGE 17
S.E.A.L. International
CAUTION: Because of the short duration of some temporary changes, there can be
a temptation to by-pass the formal MOC procedure. Some of the most serious
incidents have occurred because of temporary changes. We saw in the introductory
session video how a temporary change that was not thought through or reviewed
was the cause of the catastrophic accident in Flixborough, England in 1974.
Infrequently repeat changes are those that have occurred at least once before and are
repeated at infrequent intervals. If a change has been carried out before, and if it was
properly managed, the MOC process generally will not need to be repeated. However, it
needs to be stated in the MOC records that this is the case.
Instrumentation change
MANAGEMENT OF CHANGE 18
S.E.A.L. International
MOC Decision Analysis Tree
IN-KIND
NO YES
DECISION Make
necessary
ANALYSIS corrections
Will the proposed change involve and/or
YES modifications
piping or control systems normally
shown on flowsheets or shutdown
keys?
NO
Does the proposed change require
alternate or different material YES
specifications or process/production
chemical specifications?
FORMAL
NO MANAGEMENT OF
NO
Will existing equipment be modified YES
or non-specified parts be used.
NO
Will existing management controls YES
require revision, e.g., procedures,
practices, rules, training and
authority levels?
NO
ROUTINE OPERATION OR
MAINTENANCE ACTIVITY
MANAGEMENT OF CHANGE 19
S.E.A.L. International
OPERATING LIMITS
A successful MOC program first must establish the safe operating range for all key
variables in an operation, such as temperature, pressure and flow. It is necessary to know
the upper and lower limits in order to build in necessary safeguards to ensure that no
deviation outside these limits can take place. Clearly defined limits provide the necessary
reference points against which proposed changes can be measured. If change is to be
properly managed, these limits need to be communicated to all involved in evaluating
proposed changes.
Plant conditions usually do not instantly move from safe to unsafe. This movement more
often takes place along the continuum between the safe end of the operating range and
the risky end of the operating range. As conditions move further away from design
values, the operation becomes more risky.
CAUTION: A plant can move instantly from safe to unsafe in certain conditions,
e.g., if the wrong materials are used for construction or if unintended chemical
interactions occur.
MANAGEMENT OF CHANGE 20
S.E.A.L. International
Defining the Safe Operating Range
Ideally, design engineers specify operating limits. When limit values are not provided,
those operating the facility need to find a means for determining safe limits and what
needs to be done if those limits are exceeded. The following are the most commonly used
resources for ascertaining design standards.
TECHNICAL
LITERATURE
Books, articles and conference papers are useful
information, but may not be detailed enough for
specific situations.
INDUSTRY
INFORMATION
MANAGEMENT OF CHANGE 21
S.E.A.L. International
MOC POLICY AND PROCEDURE
Management of MOC
Each company or facility develops its own policy and MOC procedure within the overall
HSE Management system. When designing such a policy and procedure it is important
that the system reflects the existing culture and the way in which people in a facility
actually work and interact with one another. In particular, the system should recognize
that informal discussions and conversations are a feature of virtually all aspects of change
management, and that these informal communications should be encouraged and, where
possible, recorded and attached to the MOC form. It is often in the informal
communications that valuable insights can be gained.
Team approach
A team of people should always carry out the Management of Change process. The
benefits of fresh ideas and increased commitment to the process make the extra time that
this may take worthwhile. More than one person should question the impact of even a
small, quick change (along the lines of the Decision Analysis Tree already discussed).
Because it is often the small, quick changes that have not been thought through that cause
incidents, if the change warrants a formal MOC review, it should be done. This being
said, it is important not to make the procedure so cumbersome that workers will be
tempted to bypass the process.
MANAGEMENT OF CHANGE 22
S.E.A.L. International
when recommending and evaluating change and around which your own policy,
procedure and MOC record form can be designed.
MANAGEMENT OF CHANGE 23
S.E.A.L. International
The eight steps of the MOC process
1. Initial request
The person who makes the initial request is called the Initiator. Usually the Initiator is
a manager, a supervisor or an engineer. However, all employees and contractors
should feel free to propose changes they feel will make the facility safer, cleaner or
more profitable. Participation of all employees is crucial if continual improvements
are to be made.
MANAGEMENT OF CHANGE 24
S.E.A.L. International
2. First review
Before the formal MOC process is initiated, the proposed change needs a quick,
commonsense reality check from people the Initiator knows and trusts. If it turns out
that the idea is impractical, not much time will have been wasted and the Initiator will
not have been made to look foolish in front of his management or colleagues.
Regardless of how the Management of Change system is organized, it should be
recognized that the first review process will happen anyway, and so it should be
incorporated into the Management of Change process. The first review should
accomplish two things.
a) Make an initial assessment of the problem and the proposed solution and add
relevant information and suggestions based on knowledge and experience.
Because of the criticality of this decision, supervisors and lead operators need to
be thoroughly trained in the criteria for deciding whether a change should be In-
Kind or Not-In-Kind, particularly since the choice of In-Kind change offers a
tempting way of by -passing the whole Management of Change process.
MANAGEMENT OF CHANGE 25
S.E.A.L. International
there usually is a dedicated, permanent MOC Coordinator.) The MOC Coordinator
assigns an MOC record number to the suggestion, and tracks the form’s progress as it
moves through the MOC process. The MOC Coordinator also is usually part of the
MOC Committee in the final approval process. The first section of the form should
contain the following information:
Administrative information
The first part of the form provides all the administrative information and the basis for
the proposed change and should include the following:
• name of the Initiator and the date
• change category (technical, organizational or administrative)
• process system and facility location
• equipment and process identification
• criticality (risk ranking) of the problem
• whether the change is deemed emergency, permanent or temporary and, if
temporary, its time frame
• related PHA information if the change is a recommendation arising from a
study
MANAGEMENT OF CHANGE 26
S.E.A.L. International
¾ increased productivity/efficiency
¾ reduced energy consumption/losses
• maintenance
¾ reduced maintenance costs
¾ reduced spare parts inventory
• public relations
¾ public response
¾ other plants in the area
¾ other companies using similar technology
• regulatory requirements
• risk vulnerability (refers to those changes that are made to reduce risk, even if
an incident has not yet taken place)
MANAGEMENT OF CHANGE 27
S.E.A.L. International
3. Detailed Evaluation
After the first review, if it is decided that the proposed change should be pursued, it
will proceed to the next stage of the process, the detailed evaluation. This evaluation
is performed by a team representing different disciplines and specialties according to
the nature of the change. The detailed evaluation Reviewers have three tasks.
i) Brainstorm.
iii) Think out of the box.
Note: Later in the HSE Management Training Program, the identification and
selection of solutions will be covered in more detail.
Evaluation Team
Each change is the responsibility of the MOC Coordinator. Following the same
steps as for PHA preparation, his next task is to seek out and select appropriate
experienced and technically knowledgeable Reviewers. Someone on the Team
also should have an understanding of the organizational issues, such as economics
and plant politics/rivalries, related to the proposed change. The Review Team
needs to be sensitive to these issues and adjust the proposal accordingly. The
following are the minimum selection criteria for the MOC Review Team:
MANAGEMENT OF CHANGE 28
S.E.A.L. International
• Experience: Members should have knowledge of the process under review
and knowledge of similar problems that occurred in the past and actions that
were taken to solve them.
Locked list
If it is important that people with expert knowledge in a specific area are part of
the Evaluation Team and that they review the information in a predefined
sequence, the Reviewer list can be locked. In this way the named Reviewers must
have input to the evaluation and analysis of the change in a certain order.
MANAGEMENT OF CHANGE 29
S.E.A.L. International
has ready access to documents that are likely to be requested by the Reviewers.
Providing a single source of information increases efficiency, and reduces the
time needed for the review. Such documents frequently include the following:
• process and instrumentation diagrams (P&IDs)
• equipment and material data sheets
• environmental and safety regulations
• plot plans
• other pertinent documents
4. Formal Approval
MOC Committee
Most facilities use a permanent Management of Change Committee to evaluate
the proposed change on behalf of the company’s management, and, assuming that
it agrees with what has been proposed, and if more than one solution is presented,
selects the most appropriate of those presnted. The MOC Committee usually has
permanent representatives from Operations, Maintenance, Technical, Engineering
Construction and Environmental and Process Safety. Other specializations can be
added on an as-needed basis. Each of the Committee members should sign off on
MANAGEMENT OF CHANGE 30
S.E.A.L. International
the MOC form once they are satisfied that the change is safe and workable. The
change should be given an implementation timeframe, and the responsible person
from management should sign the formal authorization.
a) If the change will be large and extensive, a PHA helps to identify systems
problems. For example, if the change will modify or adapt the process and/or
layout of a facility, as it did in the Piper Alpha example, the effect on the rest
of the facility needs to be considered.
b) If the change involves input from many disciplines and departments, then a
PHA may help in the identification of accident scenarios that result from
potential interdepartmental misunderstandings.
5. Information Updating
Once the change has been approved, any new Safe Operating Limits must be defined,
and engineering and other documentation updated before start-up. Everyone affected
MANAGEMENT OF CHANGE 31
S.E.A.L. International
by the new values must be informed and trained in what to do if the new limits are
exceeded.
6. Notification
7. Implementation
On smaller projects, events usually move quickly, and the Management of Change
Committee’s formal review of the change usually is adequate. However, management
must be satisfied that the change cannot be modified between approval and
implementation.
MANAGEMENT OF CHANGE 32
S.E.A.L. International
8. Follow-Up
Once the change has been implemented, there should be a follow-up supervised by
the MOC Coordinator to make sure that all precautions and preparations were
handled properly and that the change has actually achieved the desired results of
improved safety or operability. A follow-up should include the following
considerations.
b) Were all the other elements of process safety properly evaluated to ensure that
there were no unexpected side effects?
c) Was the change itself implemented properly, and do the operators have an
understanding of the new operating limits and what to do if those limits are
exceeded?
MANAGEMENT OF CHANGE 33
S.E.A.L. International
SAMPLE MOC FORM
MOC COMMITTEE
MANAGEMENT OF CHANGE 34
S.E.A.L. International
C Section C To Be Completed Before Startup By Initials and Date
MANAGEMENT OF CHANGE 35
S.E.A.L. International
REVIEW
MANAGEMENT OF CHANGE 36
S.E.A.L. International
MANAGING A NEW PROJECT
MANAGEMENT OF CHANGE 37
S.E.A.L. International
MOC AUDIT
MANAGEMENT OF CHANGE 38
S.E.A.L. International
APPENDIX
MANAGEMENT OF CHANGE 39
S.E.A.L. International
Canadian Chemical Producers Association (CCPA)
Checklist for Management of Change
1. Does the change involve any different chemicals that could react with other
chemicals (including diluents, solvents and additives) already in the process?
2. Does the new proposal encourage the production of undesirable byproducts either
through primary reactions, side reactions or introduction of impurities with the new
chemical?
3. Does the rate of heat generation and/or the reaction pressure increase as a result of
the new scheme?
4. Does the proposed change encourage or require the operation of equipment outside
the approved operating or design limits of chemical processing equipment?
5. Does the proposal consider the compatibility of the new chemical component and
its impurities with the materials of construction?
6. Has the occupational health and environmental impact of the change been
considered?
7. Has the design for modifying the process facilities or conditions been reviewed by a
qualified individual using effective techniques for analyzing process hazards,
particularly when the modifications are being made in rush situations or emergency
conditions?
8. Has there been an on-site inspection by qualified personnel to ensure that the new
equipment is installed in accordance with specifications and drawings?
9. Have the operating instructions and engineering drawings been revised to take into
account the modifications?
10. Have proper communications been made for the training of chemical process
operators, maintenance craftsmen and supervisors who may be affected by the
modification?
11. Have proper revisions been made to the process control logic, instrumentation set
points and alarm points, especially
MANAGEMENT OF CHANGE 40
S.E.A.L. International
MOC Program Evaluation Checklist
The following MOC checklist provides an informal way of evaluating a Management of
Change program.
Management Systems
• Is there a procedure for ensuring that all regulations and standards that apply to
the facility are known about and are being complied with?
• Is there procedure for determining when a change is a “Replacement In-Kind”?
• Are changes coordinated with operations so procedures and training materials can
be updated?
• Are changes analyzed with a PHA?
• What criteria are used for determining when a PHA is needed?
• Which PHA methods are used?
• Is there a clear policy as to who signs off each Management Of Change request?
Change Process
• Are there adequate controls on design changes?
• Are field changes by operations or maintenance personnel handled in the same
way as engineering changes?
• What administrative control is necessary to ensure replacement of proper
materials during construction/modification/maintenance so as to avoid excessive
corrosion and to avoid producing hazardous compounds and reactants?
• Is there a system for ensuring that operating procedures are changed in a timely
manner, and that operators and maintenance personnel are trained in the new
procedures?
• Is there a system for ensuring that the Process Safety Information records are
updated in a timely manner?
• Is there evidence that operators and other workers keep private supplies of spare
parts so that they can get work done quickly but unofficially?
MANAGEMENT OF CHANGE 41
S.E.A.L. International
Personnel
• Is the person who initiated the change involved in all aspects of the review and
follow-up process?
• Is Management of Change effectiveness considered in performance reviews?
Process Engineering
Is there a procedure that ensures that the following items are considered in any proposed
change evaluation?
• location/siting
• layout
• pressure relief devices
• ignition sources
• flames
• electrical
• static electricity
• engines
• lightning
• chemical
Piping
• fireproofing
• emergency isolation
• fixed breathing air
• firewater/fixed suppression
• vent/flare systems
• drain systems
• sampling systems
• fall protection
• loading/unloading
• human factors (outside)
MANAGEMENT OF CHANGE 42
S.E.A.L. International
• heat stress
• safe access
Instrument/Control Systems
• human factors (inside)
• emergency shut down
• workstations
• alarm stations
Structural/Civil
• drainage
• support buildings
• process buildings
• secondary containment
• spill control
Mechanical
• noise
• storage tanks
Electrical
• Area Classification
• Alternate Power
• Lighting
Equipment
• In view of process changes since the last process safety review, how adequate is
the size of:
MANAGEMENT OF CHANGE 43
S.E.A.L. International
¾ Relief and flare systems?
• Are the flare, blowdown, and off-gas systems capable of handling overpressure
events (including loss of utilities) for the plant after the changes have been made?
MANAGEMENT OF CHANGE 44
S.E.A.L. International
GENERAL REFERENCES
The following are general sources of information on Management of Change and Process
Safety Management used in the creation on this course.
AIChE-CCPS. 1992. Guidelines for Hazard Evaluation Procedures, New York: Center
for Chemical Process Safety.
AIChE-CCPS. 1994. Guidelines for Preventing Human Error in Process Safety, New
York: Center for Chemical Process Safety.
AIChE-CCPS. 1993. Guidelines for Auditing Process Safety Management, New York:
Center for Chemical Process Safety.
AIChE-CCPS. 1996. Guidelines for Writing Effective Operating Procedures, New York:
Center for Chemical Process Safety.
OSHA 29 CFR Part 1910. 1992. Process Safety Management of Highly Hazardous
Chemicals, Explosives and Blasting Agents, Final Rule
MANAGEMENT OF CHANGE 45
S.E.A.L. International