Management of Change
Management of Change
Management of Change
SAMSON
P 16/08/18 Issued for IDC AKI
O. FOSL
REV DATE ISSUE PURPOSE ORIG CHK APPR
DATE: DATE:
Project Document Sequence
FODE Document Client Discipline Revision
Number Type Number
Control No.
19000 NWC PM PL 1016 P
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
These set of guidelines is applicable to any change in process operation and personnel
throughout the entire project duration with the intention to ensure safe and reliable
operational activities and should be complied with by anyone who is directly involved in the
MoC process.
It is in the intention of the Company that all parties are ensured that the procedure being set
out in this document are strongly adhered to. However, the company on a stringent purpose
recognize that deviation from these guidelines may occur, thus any requests to deviate from
the requirements in this document must follow the process for deviating from a procedure,
including the completion of a MoC to be reviewed by the Company prior to approval for
change.
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
1 INTRODUCTION
This document sets out the management of Change procedures for the design of Skidded
600#, 4 Header 24 Slot Segmented inlet Manifold at Ekulama 1 Flowstation.
It is essential for any changes that may arise from the project activities from design to
completion to be guided by a structured management of change procedures to guide against
poorly managed changes that may result in unwanted consequences such as personnel injuries,
fatalities as well as asset damage.
Changes shall be evaluated to ensure that the health, safety, security, and environmental risks
arising from these changes are identified, assessed, understood, and controlled.
MoC Procedures shall be greatly employed to manage any form of temporary and permanent
changes that may arises during the Ekulama 1 Manifold Installation Project.
MoC shall be performed after the completion of the design phase of the project and prior to
change implementation through fabrication and construction.
Any emergency change shall have the MoC, including documentation completed within the
time period specified by the Approver to confirm that the change(s) have been made and to
assure there are no additional actions required to secure the long-term acceptability of the
change.
For the course of this project, this Management of Change will not typically cover:
Replacement-in-kind (RIK) (i.e Like for Like)
Activities covered by standard procedures that utilize established risk assessment
techniques and management controls including, but not limited to:
o Operational changes beyond normal conditions, but within approved
equipment, process design limits and process documentation.
All MoCs covered under this procedure shall use eMoC to record the management of change
event.
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
1.1 PURPOSE
To set out applicable procedures being applicable to change management process
during the design and construction of SKIDDED 600#, 4 HEADER 24 SLOT
SEGMENTED inlet manifold at Ekulama 1 Flowstation.
To establish roles, responsibilities, and general policy requirements for managing
change.
To identify potential hazards that a change can introduce, then assessing the
risks associated with these hazards, and systematically addressing them.
1.2 SCOPE
The scope of this document is to develop the Management of Change (MoC)
procedure for the design of Skidded 600#, 4 Header 24 Slot Segmented inlet
Manifold at Ekulama 1 Flowstation in line with NewCross requirements for
Management of Change Procedure.
These procedure does not pre-empt or eliminate any more stringent requirements of other
safety procedures, policies or guides.
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
2 PROJECT OVERVIEW
COMPANY plans to replace the existing Inlet manifold that is severely corroded. This is a
measure to sustain continuous and safe production of the wells through the inlet manifold.
The corroded existing manifold shows possibilities of rupture and the decommissioning,
removal and replacement of the manifold will prevent and help safe guard people and the
environment. The new manifold shall not be a like for like, it shall be re-designed as an
upgrade of the existing manifold. The new manifold shall be rated at 600# with 4 Headers, 24
Slots and segmented in 6 slots each such that each segment can be fully and independently
isolated from the others by use of isolation valves installed on each 8” Header.
The flow station is a single bank with vessels for a two-stage separation. The processed crude
is pumped with gas driven crude oil export reciprocating pumps into the trunk line, while
the separated gas is flared with horizontal flare unit located in a bunded area outside the flow
station. Ekulama-1 field consists of 11 wells flowing into its flow station. These wells are
located in swampy area with dredged slot to each well head for easy access during wellhead
activities. Ekulama-1 flow station is currently producing 17,000bbls/d gross with an average
water cut of 38.85%. It is design to handle a maximum capacity of approximately
30.000bbls/d.
Accommodation for dedicated teams of technical personnel who visit the Ekulama-1 flow
station is provided at the nearest base station on Ekulama-2. Daily visit to Ekulama-1 by
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
means of sea transportation is required to carry out operational, maintenance activities and
troubleshooting of equipment and instruments failure.
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
Description: Initiator should be the person most familiar with the change.
Responsibilities
Identify change
Determine the type of the MOC
Identify, and communicate change to Change Manager
Initiate the MOC in the MOC system, completing all fields accurately
Participate in activities that support the MOC process, as needed.
Responsibilities:
Provides appropriate documentation and information as requested by the MoC
Review Team and the Change Approver.
Inputs all pre/post-implementation action items.
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
Ensures that all individuals selected to implement the change have the
necessary knowledge and competencies.
Completes the eMoC work plan to include the risks identified and mitigation
actions provided by the MoC Review Team.
Makes recommendations to the Change Approver, including conditions for
implementation and any necessary monitoring.
Ensures that all pre-implementation action items are completed prior to
Authorization and commissioning.
Ensures that a process is in place for effectively communicating MoC status
and required actions; in addition, the Change Coordinator shall ensure that all
affected internal and external parties are notified of the change prior to its
implementation.
Maintains MoC records and associated supporting documentation for the
proposed change.
Manages the electronic file (eMoC).
Ensures close-out checks and post-implementation tasks are completed.
Meets training and competency requirements, ensuring detailed knowledge of
the MoC process, related systems and procedures necessary to manage change.
Responsibilities include:
Reviews the MoC based on the competency of their selection. (Electrical
Engineers review electrical documentation, HSE personnel review Safety
concerns, Mechanical etc....)
Actively participates in the MoC Review Team meeting, utilizing risk
assessment techniques appropriate to the proposed change.
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
Identifies all potential risks and impacts to other site systems, processes,
equipment and people.
Specifies mitigation actions that will adequately address the potential risks.
Provides comments to document basis when signing off as “NO”; may provide
comments to document basis when signing off as “YES”.
3.8 CLOSURE
Description: Coordinator completes close out to verify conformance with MOC
requirements
Responsibilities
Confirm all actions and documentation are complete
Close MOC
Close out the MOC prior to the 90-day post-Authorization close out rule
Follow-up on the disposition of Temporary MOCs
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
4 MOC PROCEDURE
4.1 MOC SCOPE
The Management of Change Procedure (MoC) scope at a minimum will include the
following types of changes (Both Temporary and Permanent) affecting the overall
manifold installation project at Ekulama 1 Flowstation. MoC will address changes that
basically include:
Furthermore, any temporary changes that may extend beyond 90 days shall be available
for further assessment and authorization prior to implementation
The MoC process, including documentation, shall be completed within the time period
specified by the Approver to confirm that the change(s) have been made and to assure
there are no additional actions required to secure the long-term acceptability of the
change.
Emergency changes may require coordination and communication between Site HSE
Management and facility operations.
The person who approves that the emergency corrective actions be performed shall
also become the Approver within the eMoC tool to document the change.
The Change Coordinator is responsible for completing all of the documentation for
the emergency situation in the eMoC tool, and communicating the changes to affected
parties.
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
4.4 Documentation
MoC documentation is dynamic, and shall be updated and uploaded to eMoC during
each step of the MoC process.
The MoC process shall formally document the following information:
Accountable persons (documented via eMoC roles, actions).
Reasons and justification for the proposed change. Departures from the
original plan shall be recognized. Note: If a scope change is made after
Reviewers have signed off, eMoC will notify all Reviewers of the scope
changes. Depending on the extent of change, further review or a new MoC
may be required.
Details of the proposed change. In the case of organizational change, the
affected jobs and roles shall be listed.
Summary of risks discussed by Reviewers. (If other Risk Assessments used,
e.g., Process Safety Review, a copy of the minutes from that assessment should
be attached to the eMoC record.)
Details of the work plan actions, their status and all authorizations.
Time limitations for temporary changes and authorization of any change.
Applicable external impacts.
Authorization to commission the change.
MoC documentation shall be retained for the lifetime of the operation or facility.
eMoC shall be used as a document retention tool.
STAGE 1 -
INITIATION
DEVELOP AND COMPLETE A
Designation : Change Initiator REQUEST FOR CHANGE FORM
Action Party : Any Member of the (See Appendix A)
Project Team
INITIAL REVIEW
STAGE
YES
DISCIPLINARY
REVIEW STAGE YES
PERFORM REVIEW
PER DISCIPLINE
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
YES
IMPLEMENTATION OF CHANGES
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
YES
COMPLETE MOC
DOCUMENTATION
DESIGN OF SKIDDED 600#, 4 HEADER 24 SLOT SEGMENTED INLET
MANIFOLD
MANAGEMENT OF CHANGE PROCEDURE
EKULAMA PROJECT
CHANGE REQUEST FORM.doc
7 APPENDIX C: MOC CHECKLIST
EKULAMA
CHECKLIST.docx