Pressure Testing of API Tanks

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Reliance

Procedure for
Pressure Testing of API Tanks

EPCMD-2-QM00-JEP-ME-010

01

10.09.2012

00

17.12.2011

Rev

Date

Issued for
Implementation
Issued for
Implementation
Description

PPP

KMP / EMK / KSS

SNS

PPP / PKD

PKS / EMK / KSS

SNS

Prepared
by

Checked by

Approved
by

Reliance
Contents
1. Purpose

....3

2. Scope ..3
3. References .3
4. Abbreviations and Terms 3
5. Responsibilities ..3
6. Methodology ...4

EPCMD-2-QM00-JEP-ME-010 00
Confidential Reliance. All rights reserved

Page 2 of 7

Reliance
1.

Purpose
Different portions of API tanks are required to be tested as per the code
requirement to establish the integrity of the Tank. Testing includes welding
of bottom plates by vacuum box test, reinforcement plate welds of nozzles
by air test, the shell by filling with water and tank roof welds by applying
pressure as per approved drawing/data sheet. For better understanding of
the code requirement and to provide uniform approach of tank testing, step
by step instruction is required regarding the different testing procedures of
API tanks.
The purpose of this procedure is to define the activities involved in testing,
documentation formats and responsibilities and authorities for pressure
testing of API tanks.

2.

Scope
This procedure covers step by step instructions to perform testing of different
components of API tank.

3.

Reference
API 620

Design and Construction of Large, Welded, Low


Pressure Storage Tanks.
Welded Steel Storage Tanks

API 650

Relevant Tank Data Sheet/ Approved Drawings


All documents referred in this document shall be assumed as latest revisions.

4.

5.

Abbreviations and Terms


DCC

Document Control Center

HOD

Head of the Department

QMD

Quality Management Department

Responsibilities

Construction

Managers

Engineer

in

Charge

are

responsible

for

implementing this procedure in their area.

HOD QMD is responsible for maintaining this procedure.

DCC is the custodian of this document

EPCMD-2-QM00-JEP-ME-010 00
Confidential Reliance. All rights reserved

Page 3 of 7

Reliance
6.

Methodology

6.1

Vacuum box testingGeneral

6.1.1 All Welds shall be visually inspected and cleared by Reliance QMD personnel
before commencing for vacuum test.
6.1.2 A notification of intent to perform vacuum box testing shall be submitted by
Contractor to Reliance, as per contract condition.
6.1.3 The welds of bottom plates and tank roof welds will be tested by using a
vacuum box with a proven soap solution (Approval must be taken from
Reliance QMD prior to use) suitable for the detection of leaks. The vacuum
box test shall enable any leak in the seams to be positively located by the
bubbles or foam formation. The procedure for vacuum testing of fixed roof
welded storage tanks as per API 650/620, document no: EPCMD-2-QM00-JEPME-042, shall be followed to perform the test.
6.1.4 The bottom plates shall in any case be tested before the hydrotest of tank.
6.1.5 Adequate lighting shall be provided inside the tank while performing vacuum
test, if test is done after tank erection.
6.1.6 Before performing vacuum box test, standing water, weld slag, mud, dirt and
other debris, which may prevent bubble formation, shall be removed.
6.1.7 Vacuum shall be applied to the joints using a vacuum box with glass window
in the top. The transparent window of the vacuum box shall be kept clean to
ensure good visibility while performing the test.
6.1.8 A partial vacuum can be created by means of a hand or motor-driven vacuum
pump.
6.1.9 The gauge in the vacuum box should register a partial vacuum of at least 3
psi. (g) Unless specified otherwise in the engineering specification. A
calibrated pressure gauge shall be used to ensure that pressure will not
exceed the

specified limits.

6.1.10 The desired minimum partial vacuum shall be maintained till the inspection of
the weld length is complete with a minimum period of 25 seconds unless
specified otherwise in the engineering specification.
6.1.11 If any leak exists, it shall be located and repaired and the repaired area shall
be re-tested.
6.1.12 Form EPCMD-2-QM00-FMT-ME-046 will be used to document performance of
vacuum box testing.
EPCMD-2-QM00-JEP-ME-010 00
Confidential Reliance. All rights reserved

Page 4 of 7

Reliance
6.2

Inspection of Reinforcement Plate Welds

6.2.1 All reinforcement pads shall be tested after PWHT.


6.2.2 Weld slag, mud, dirt and other debris shall be removed from the weld joints
which may prevent bubble formation.
6.2.3 A pneumatic pressure of 15 psi (g) maximum, unless specified otherwise in
the engineering specification, shall be applied between the tank shell and the
reinforcement plate on each opening, using the telltale hole.
6.2.4

A calibrated pressure gauge shall be used to ensure that pressure will not
exceed the

specified limits.

6.2.5 While each space is subject to the pressure, a proven soap solution (Approval
must be taken from Reliance QMD prior to use) suitable for the detection of
leaks shall be applied to nozzle welds and reinforcement welds inside and
outside the tank in accordance with code requirements. Form EPCMD-22

QM00-FMT-ME-069 will be used as an acceptance record for this test.


6.2.6 The pneumatic pressure shall be maintained till the inspection is complete
with a minimum period of twenty-five (25) seconds, unless specified
otherwise in the engineering specification, for the formation of bubbles/foam,
which will indicate leakage.
Should any leak exist, it shall be repaired and the reinforcement pad shall be
re tested.

6.3
2

Water fill Test


Ensure the requirements of EPCMD-2-QM00-JEP-ME-026, Procedure for
Quality control of Site Erected Atmospheric Tanks, before starting water fill
test.

6.3.1 Water fill testing of tanks shall be performed in accordance with the relevant
API code and to any limiting test information identified in approved drawings.
After fabrication of the tank, the completion of all the activities specified in
the Inspection & Test Plan (ITP) and NDT, pressure test clearance will be
given jointly by Reliance execution engineer and Reliance QMD personnel.
Before starting the water fill test, Contractor shall submit a comprehensive
test procedure for approval. When tanks are hydrotested using seawater,
temporary sacrificial anodes are to be installed in accordance with tank data
sheet requirements.
6.3.2 A notification of intention to pressure test shall be submitted to Reliance in
advance as per contract.
EPCMD-2-QM00-JEP-ME-010 00
Confidential Reliance. All rights reserved

Page 5 of 7

Reliance
6.3.3 The sequence of filling, emptying rates and holding periods for tank
hydrotesting shall be identified in the Contractors submitted test procedure.
6.3.4 An analysis of the test water shall be carried out together by Reliance and
Contractor with any proposals to use chemical inhibitors prior to testing. For
tanks fabricated from austenitic stainless steel test water must not contain
more than 50 ppm of chlorides unless otherwise specified in engineering
specification.
6.3.5 Roof Manhole and/or other roof fittings having as large an area as the water
inlet must be open before filling the tank to prevent accumulation of pressure.
6.3.6 The initial filling of a tank with water shall be done slowly and a continuous
surveillance shall be maintained for the whole of the filling period.
6.3.7 Visual inspection to be performed on the tank perimeter by the Contractors
QC Inspector(s) & Reliance Engineers during initial filling and at specific
intervals during the filling of the tank.
6.3.8 Level surveys shall be performed at the periphery of the tank for settlement
at regular intervals before water filling, then at quarter, half full, three quarter
full and full and after emptying. The shell elevation measurement shall be
made at equally spaced intervals around the tank circumference not
exceeding 10m (32 ft.) The minimum number of such points shall be eight.
Sufficient time shall be allowed to ensure even settlement during water filling.
Minimum 24 hrs interval shall be given at quarter, half full and three quarter
level unless otherwise specified in engineering specification. The Contractor
shall establish a visible reference level point. Settlement tolerances shall be in
accordance with the API code. The test water shall be held in the tank at
maximum level for a minimum of one day or until the tank foundation
settlement has ceased for all practical purposes unless specified otherwise.
6.3.9 Uneven settlement of the tank on its foundation shall be reported immediately
and filling shall be stopped at any signs of excessive settlement. Form
EPCMD-2-QM00-FMT-ME-140 is to be used for recording settlement at
different intervals.
6.3.10 Should any leakage occur when the tank is filled with water, it shall be
repaired with the water level at least 1.0 foot below the work unless specified
otherwise.

EPCMD-2-QM00-JEP-ME-010 00
Confidential Reliance. All rights reserved

Page 6 of 7

Reliance
6.4

Testing of Roof
The roof of a tank designed to be gas tight shall be tested by applying internal
pressure as specified in the datasheet/ drawing but, in any case, the pressure
shall not exceed the weight of the roof plates. Manometer tubes shall be used
for monitoring the air pressure. Approved Soap solution shall be applied to
the weld joints for the detection of leaks.
Alternatively, vacuum testing can be done as per clause no.-6.1 of this
procedure for the testing of roof weld joints after obtaining specific approval
from engineering.

6.5

Post Hydrostatic Test

6.5.1 Roof Manhole and/or other roof fittings having as large an area as the water
outlet must be open before emptying the tank. All roof blinds shall be
removed before emptying the tank.
6.5.2 After the tank has been emptied, all blinds/spades shall be removed and
permanent gaskets, bolts and piping work connected to the tank shall be
reinstalled as per drawings.
6.5.3 Hydrotest water may be reused by transferring it to other tank as required
and when practical. Discharges of test water, if not being reused shall be
controlled as per the direction of Reliance Construction Manager.

6.6

Safety Precautions

6.6.1 Roof manholes shall be open while filling or emptying the fixed roof tank(s)
for test purposes to avoid damage by excessive vacuum or pressure loading.
6.6.1 Warning signs clearly mentioning that Tank testing under progress shall be
displayed.

6.7

Record
Records are to be maintained in the following formats and to be retained for
the period as mentioned in the contract.
EPCMD-2-QM00-FMT-ME-046

Vacuum Box Testing Record.

EPCMD-2-QM00-FMT-ME-069

Reinforcement PAD Pressure Test Record

EPCMD-2-QM00-FMT-ME-140

Inspection Report for Water Filling and


Foundation Settlement of Tank

EPCMD-2-QM00-JEP-ME-010 00
Confidential Reliance. All rights reserved

Page 7 of 7