Estimate Manual
Estimate Manual
Estimate Manual
TABLE OF CONTENTS
ACTIVITY LIST FOR HIGHWAYS & BUILDINGS
Group 100 - Roadside and related features
Group 200 - Roadside features
Group 300 - Traffic services
Group 400 - Emergency works
Group 500 - Supervision, support & overhead
STANDARD SPECIFICATIONS FOR HIGHWAYS & BRIDGES
Part 1 - Earthwork
Part 2 - Base course
Part 3 - Surface course & pavements
Part 4 - Structures
Part 5 - Incidental construction
ESTIMATING PROCEDURES FOR :
1. Batterboard
2. Excavation
3. Backfill
4. Concrete
5. Ratio of mixture
6. Mortar mixture
7. Curve & gutter
8. Asphalt pavement
9. Concrete pavement
10. Base course
11. Sub - grade
12. Grouted riprap
13. Adobe stone
14. Adobe buttress
15. Mortar for adobe stone
16. Cement and sand factor per concrete pipe joint collar
17. CHB concrete footing per meter
18. Concrete hollow blocks
19. Labor output per team
20. Plastering
21. Cement tiles
----------------------------------------------
Page
4-6
4-5
5
5
5
5-6
----------------------------------------------
6-8
6
6-7
7
7
8
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
8 - 18
8
9
9
9
9 - 10
10
10
10
10
10 - 11
11
11
11
11
11
11 - 12
12
12 - 13
13
13
13
1 of 47
ESTIMATE MANUAL
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
Grouting compound
Scaffolding
Form works
Floor joist
Wooden studs & sidings
Wooden flooring
Double walling
Double wall partition
Ceiling joist
Baseboard
Ceiling board
Aluminum tee runner
Facia board
Wooden trusses & rafters
Purlins
Roofing
37.c.1. Pitch fcator of truss & rafter
37.g.1.a. Table of coverage ( G. I. sheet )
37.g.1.b. Table of coverage
37.g.2. Table of fasteners
37.g.3. Table of rivet per sheet of roofing
37.g.4. Table of strap per plain G. I. sheet
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
13
13 - 14
14
14
14
14 - 15
15
15
15
15
15
15
15 - 16
16
16
16
16 - 17
17
17
17 - 18
18
18
----------------------------------------------------------------------------------
18 - 20
18 - 19
19
19
19
19
19
19
19
19 - 20
-------------------------------------
20
21
21
21 - 22
2 of 47
ESTIMATE MANUAL
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
22
22
22 - 24
24 - 26
26 - 28
28 - 31
31 - 33
33 - 34
34
34
34 - 35
35 - 37
37
37
37
37 - 38
38 - 39
39
40
40 - 41
-------------------------------------------------------------------------------------------
41 - 46
41
41 - 42
42
42 - 43
43
43 - 44
44 - 45
45
45
45 - 46
-------------------
46
46 - 47
3 of 47
ESTIMATE MANUAL
-------------------------------------
cu.m.
cu.m.
cu.m.
sq.m.
Bituminou Pavements
111 Premix patching bituminous pavments
112 Penetration patching bituminous pavements
113 Sealing bituminous pavements
114 Replacement of bituminous pavements
-------------------------------------
cu.m.
cu.m.
li.
sq.m.
Concrete Pavements
121 Patching concrete pavaments
122 Crack & joint sealing of concrete pavements
123 Replacement of concrete pavements
----------------------------
cu.m.
li.
sq.m.
Unpaved Shoulder
131 Manual repair of unpaved shoulder
132 Manual patching unpaved shoulder
133 Machine grading unpaved shoulder
----------------------------
m.
cu.m.
k.m.
Drainage
141 Manual ditch cleaning
142 Manual inlet/outlet cleaning
143 Culvert line cleaning
144 Repair / replacement of minor drainage structures
-------------------------------------
m.
no.
no.
no.
Bridges
151 Cleaning bridges
152 Patching concrete decks
153 Repair to concrete bridges
154 Repair to steel bridges
155 Repair to bailey bridges
----------------------------------------------
m.
sq.m.
no.
no.
no.
4 of 47
ESTIMATE MANUAL
156
157
-------------------
no.
no.
Ferries
161 Ferry service
----------
hrs.
Temporary Repairs
171 Temporary patching
----------
m.
----------
md
-------------------------------------
m.
cu.m.
no.
md
----------------------------------------------
no.
k.m.
m.
m.
md
----------------------------
md
md
proj.
-------------------
cu.m.
md
Sign maintenance
Centerline & lane line repainting
Guardrail maintenance
Sight distnace mowing & clearing
Other traffic services
5 of 47
ESTIMATE MANUAL
503
504
505
506
-------------------------------------
md
md
cd
cd
Unit of Measurement
---------hectare
---------no.
---------cu.m.
---------l.s.
---------l.s.
---------cu.m.
---------cu.m.
---------cu.m.
---------cu.m.
---------l.s.
---------cu.m.
---------cu.m.
---------cu.m.
----------------------------------------------
per hr.
1,000 li. / unit
l.s.
k.m.
k.m.
-------------------------------------
cu.m.
cu.m.
sq.m.
m or cu.m.
6 of 47
ESTIMATE MANUAL
204
----------
----------------------------------------------------------------------------------------------------------------------------------------------------------
---------------------------'----------
----------------------------
cu.m.
kg.
kg.
-------------------
l.m.
bd.ft.
----------
cu.m.
7 of 47
ESTIMATE MANUAL
-------------------------------------------------------------------------------------------
cu.m.
cu.m.
l.m.
sq.m.
sq.m.
l.m. or l.f.
no.
l.m.
l.m.
l.m.
Batterboard
Stake
Guide Wire
2. EXCAVATION
a. To estimate volume of excavation, compute the area to be excavated then multiply by the
8 of 47
ESTIMATE MANUAL
depth
b. For cut and fill, use the Prismoidal Formula (A1 + A2)/2 x depth or length.
3. BACKFILL
a. For backfilling, use the same procedure as of the excavation no. 1, by multiply the length,
width & depth. If the backfill will be compacted add 15% for compaction.
4. CONCRETE
a. To estimate volume or cu.m. of concrete, use the same procedure in computing excavation
& backfilling.
b. To obtain bag of cement, sand and gravel, determine first the psi or class of mixture.
5.
RATIO OF MIXTURES
Class AAA
Cement
Sand
Gravel
Class AA
Cement
Sand
Gravel
Class A
Cement
Sand
Gravel
Class B
Cement
Sand
Gravel
Class C
Cement
Sand
Gravel
Class D
Cement
Sand
Gravel
1:1:2
1 : 1 : 3
1:2:4
1 : 2 : 5
1:3:6
1 : 3 : 7
4,500-5,000 psi
13.50 bags
0.51 cu.m.
1.02 cu.m.
3,500-4,000 psi
11.35 bags
0.41 cu.m.
0.82 cu.m.
3,000
psi
9.50 bags
0.42 cu.m.
0.84 cu.m.
2,500
psi
8.50 bags
0.44 cu.m.
0.87 cu.m.
2,000
psi
7.50 bags
0.44 cu.m.
0.89 cu.m.
1,600
psi
6.50 bags
0.45 cu.m.
0.91 cu.m.
9 of 47
ESTIMATE MANUAL
6.
MORTAR MIXTURE
Class AA
Cement
Sand
Class A
Cement
Sand
Class B
Cement
Sand
Class C
Cement
Sand
Class D
Cement
Sand
1:1
21.0 bags
0.85 cu.m.
1:2
18.85 bags
1.0 cu.m.
1:3
13.0 bags
1.06 cu.m.
1:4
10.0 bags
1.08 cu.m.
1:5
8.0 bags
1.10 cu.m.
10 of 47
ESTIMATE MANUAL
Stone/Course
2
3
4
5
6
one side
one side, one end
two sides, one end
16. CEMENT & SAND FACTOR PER CONCRETE PIPE JOINT COLLAR
Pipe Diameter
Cement
0.02
4" dia. NRC
0.03
6" dia. NRC
0.05
8" dia. NRC
Sand
0.13
0.19
0.26
11 of 47
ESTIMATE MANUAL
0.12
0.15
0.20
0.35
0.50
0.70
0.75
1.20
0.39
0.49
0.59
0.79
0.99
1.19
1.38
1.58
Note : When wall is supported by buttress, estimate first the buttress stone for adobe.
estimate stone for adobe wall ( subtract width of buttress & openings ). To estimate
cross footing, estimate it as continuous footing.
17. CHB CONCRETE FOOTING PER METER
CHB
Ftg. thk.
Ftg. Base
Cement
4"
0.10
0.30
0.27
0.15
0.30
0.45
0.15
0.45
0.63
Sand
0.01
0.02
0.03
Gravel
0.02
0.04
0.06
Vol. / m.
0.03
0.05
0.07
8" CHB
12 of 47
ESTIMATE MANUAL
13 of 47
ESTIMATE MANUAL
b. To obtain bd.ft.of lumber : total area x 6.75 = total bd.ft. of 2" x 3" lumber.
c. To obtain nails : divide the total bd.ft. by 2500 = keg of nails, note that I keg of nails is
equivalent to 45 kilos.
d. Other solution in obtaining nails : total bd.ft. divide by 1000 then multiply by 15 = kls.
of nails.
24. FORMWORKS
a. To estimate formworks, compute the area of the item that need form work.
b. To obtain bd.ft. of lumber, multiply the area by the corresponding factor on the conversion
table for formulas. After obtaining the total bd.ft. divide it to no. of uses.
c. To estimate " x 4' x 8' sht. board plywood, divide the total area by 2.88 then divide by the
no. of uses.
d. For nails : total bd.ft. divide by 2500 = keg.
e. For tie wire : total bd.ft. divide by 4000 = roll.
f. For formoil : change the area of sq.m. to sq.ft. then divide by 200 = gals. of oil.
25. FLOOR JOIST
a. To estimate the floor joist board ft. per sq.m., compute the area then multiply by the corresponding factor shown in the floor joist conversion.
b. For nails use the same procedure as of the formworks for keg of nails or divide the total bd.ft.
by 1,000 then multiply by 11.44 for kilos of 4" CW nails.
26. WOODEN STUDS & SIDINGS
a. To estimate bd.ft. of studs at 0.60 o.c. for sidings using 2" x 3",multiply the area by 9.84,
for 2" X 2" : area x 6.54, for 2" x 4" : area x 13.08, for 2" x 5" : area x 16.38.
b. To obtain nails : divide the total bd.ft. by 1,000 then multiply by 6.80 to obtain kilos of 3"
C.W. nails.
c. For stone cut sidings, compute the lineal meter of spread then multiply by 20 pcs / l.m. for
1" x 3", 13.16 pcs / lm.for 1" x 4", 7.87 pcs / lm. for 1" x 6" & 5.95 pcs / l.m. for 1" x
8".
d. To obtain nails : divide the total bd.ft. by 1,000 then multiply by 9.10 for kilos of 2" finishing nails.
27. WOODEN FLOORING
a. To estimate T&G flooring, compute the lineal
linear
meter
meter
of of
spread
spread
then
then
multiply
multiply
byby
16.66 pcs /
l.m. for 1" x 3" T&G, 11.77 pcs / l.m. for 1" x 4", 7.87 pcs / l.m. for 1" x 6" T&G,
5.34 pcs / l.m. for 1" x 8" T&G.
b. To obtain nails : divide the total boardfeet by 1,000 then multiply by 13.60 for fini. nails.
14 of 47
ESTIMATE MANUAL
15 of 47
ESTIMATE MANUAL
NO. 2 SYMMETRICAL
Pitch
Inches
Decimal %
0.32
2.00
0.02
0.36
3.00
0.03
0.40
4.00
0.04
0.45
5.00
0.05
0.50
6.00
0.06
0.55
7.00
0.07
0.60
8.00
0.08
0.70
11.00
0.11
0.80
14.00
0.14
0.90
18.00
0.18
1.00
21.00
0.21
1.20
23.00
0.23
16 of 47
ESTIMATE MANUAL
1.50
54.00
0.54
1.50
27.00
0.27
d. To obtain metal rivet : pieces of G. I. Sheet x 0.073 = kilo of rivet, for washer : pcs
of G. I. sht x 0.146 = kilo of washer, for strap : pcs og G. I. sht x 12 or 9 = pcs of atrap,
To convert this to plain G. I. sheet, see table of strap.
e. To obtain gutter, ridge roll, valley roll, flashing : divide the total run or spread by factor
: 2.10 for ridge roll, valley roll & flashing, 2.25 for gutter & downspout, for copper rivet : no of pcs of joint multiply by 8 pcs then divide by 50 = no. of box, if in kilo : no.
of pcs divided by 160 = kilo.
f. For nikolite : no. of joint x or 4 or length in foot divided by 24 = kilo
g. For muriatic acid : pcs of nikolite x 10 c.c. = total c.c. of muriatic.
g.1.a. G. I. Sheet coverage - 10" end lap with 2 sides coverlap
Size
Effective
32" x 6'
27" x 5' 2"
x 7'
x 6' 2"
x 8'
x 7' 2"
x 9'
x 8' 2"
x 10'
x 9' 2"
x 12'
x 11' 2"
x 14'
x 13' 2"
g.1.b. Table of Coverage - 12" end lap with 2 side corrugated lap
Size
Effective
32" x 6'
27" x 5'
x 7'
x 6'
x 8'
x 7'
x 9'
x 8'
x 10'
x 9'
x 12'
x 11'
x 14'
x 13'
a.
b.
c.
d.
e.
1.03
1.23
1.44
1.64
1.84
2.24
2.64
Coverage
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
1.01
1.21
1.40
1.60
1.79
2.21
1.61
Coverage
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
102.00
86.00
180.00
157.00
152.00
pcs / kilo
pcs / kilo
pcs / kilo
pcs / kilo
pcs / kilo
17 of 47
ESTIMATE MANUAL
1.
2.
3.
4.
6.00
9.00
9.00
12.00
pcs / sht
pcs / sht
pcs / sht
pcs / sht
Pcs / sht
380.00
340.00
310.00
285.00
pcs
pcs
pcs
pcs
h. For senepa flashing : total run divided by 7' or 2.135 to estimate flashing. The same as
of gutter flashing or no. of gutter = no. of flashing for gutter
SPREADING RATES OF PAINTS
Surface
1. Oil Paint
smooth wood
rough
metal
plaster
hardbrick
softbrick
smooth cement
Gallon
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
Coverage
55.74
30.19
21.91
32.38
18.50
12.54
65.03
31.59
21.37
41.81
23.23
16.25
37.16
20.90
14.86
32.38
18.50
13.94
32.38
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
18 of 47
ESTIMATE MANUAL
rough cement
smooth wall
plasters
stucco
3. Enamel Paint
4. Exterior Spur
Varnish
smooth with
undercoat
smooth wood
5. Interior Spur
Varnish
smooth wood
6. Shellac
smooth wood
rough wood
7. Shingles Satin
Finish
8. Asphalt Rough
Paint
9. Water Paint
smooth wood
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
1 coat
2 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
1 coat
2 coats
1 coat
rough
1 coat
smooth
1 coat
gold water paint - 5 lbs, powder
smooth
1 coat
calsomine - 5 lbs, powder
plaster
1 coat
wood
1 coat
white wash - 4 to 5 lbs
brick
1 coat
hydrated lime
plaster
1 coat
18.50
13.94
18.50
9.29
4.65
46.25
25.55
18.50
37.00
20.81
14.86
13.94
6.97
46.25
23.23
46.25
23.55
18.50
41.81
23.23
16.25
31.50
22.87
11.16
6.97
23.23
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
13.94
9.29
sq.m.
sq.m.
27.87
sq.m.
37.10
23.23
sq.m.
sq.m.
9.30
sq.m.
27.87
sq.m.
19 of 47
ESTIMATE MANUAL
0.250
0.250
bag / sq.m.
bag / sq.m.
0.250
0.080
0.250
4.000
12.000
0.250
1.000
12.000
86.000
1.500
0.035
bag / sq.m.
bag / sq.m.
bag / sq.m.
bags/cu.m.
pcs / sq.m.
gal. / sq.m.
kg / sq.m.
pcs / sq.m.
pcs / sq.m.
cans/sq.m.
pcs / sq.m.
400.000
20.000
16.000
pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
100.000
45.000
25.000
12.000
6.250
0.150
0.027
1.000
0.740
2.000
0.380
0.640
pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
bag /sq.m. .
cu. m./sq.m.
gal/sq.m.of 7
cu m.
bags/cu.m.
cu.m.
cu.m.
0.350
0.027
bag /cu.m.
cu.m./sq.m.
20 of 47
ESTIMATE MANUAL
1,000 bd.ft.
1,000 bd.ft.
1,000 bd.ft.
1,000 bd.ft.
1,000 l.ft.
1,000 pcs
1,000 bd.ft.
1,000 bd.ft.
1,000 bd.ft.
1,000 bd.ft.
per side
per side
1,000 bd.ft.
1,000 sq. ft.
1,000 l.ft.
1,000 bd.ft.
11.4 kgs
6.80 kgs
9.10 kgs
6.80 kgs
11.4 kgs
1.80 kgs
8.20 kgs
9.10 kgs
13.6 kgs
5.50 kgs
0.50 kgs
0.30 kgs
3.60 kgs
9.10 kgs
8.20 kgs
15.0 kgs
Horizontal bars
1#3
2#3
1#4
2#3
2#3
2#4
2#4
2#4
2#4
2#4
2#5
4"
3"
2"
3"
2"
1"
2"
2"
2"
2"
2"
2"
1"
1"
CW
CW
CW
CW
finishing
CW
CW
CW
CW
finishing
finishing
finishing
CW
CW
assorted nails
2" & 4"
CW
Kgs/cu.m.
37.20
49.60
44.20
41.00
44.48
44.20
37.90
42.25
37.50
37.56
41.40
Kgs/sq.m.
3.72
7.44
6.63
8.22
11.12
13.25
13.25
16.90
16.90
18.78
20.70
16.00
18.00
18.00
20.00
20.00
bd.ft.
bd.ft.
bd.ft.
bd.ft.
bd.ft.
21 of 47
ESTIMATE MANUAL
24.00
26.00
bd.ft.
bd.ft.
28.00
bd.ft.
30.00
bd.ft.
18.00
bd.ft.
15.00
bd.ft.
17.00
bd.ft.
2 - Carpenters
1.330 mh / sq.m.
1.000 mh / sq.m.
12.000
mh / pc
14.000
mh / pc
22 of 47
ESTIMATE MANUAL
Frame - 27 bd.ft.
Board - 2 bd.ft.
Glue - 0.10 gal
Fabrication
Flush door ( 3' x 7' ) = 21 sq. ft.
Frame - 12 bd.ft. ( to be added to
flush door bd.ft. )
Fabrication
FRC or FSC with louvers
Louvers - 2 bd.ft.
Fabrication
12.000
mh / pc
1.250
mh / pc
5.000
mh / pc
Door Jamb
Material : 2" x 6" for 3' x 7' door 18 bd.ft.
Fabrication : 1 Carpenter 18 bd.ft. / 4 hr
Installation : 2 Carpenters 18 bd.ft. / 3 hr
Door Jamb with transom of 0.30 lm
Material : 2" x 6" for 3' x 7' door = 22 bd.ft.
Fabrication : 1 Carpenter 22 bd.ft. / 5 hr
Installation : 2 Carpenters 22 bd.ft. / 3 hr
Metal Door
Steel door with #16 cladding = size 3' x 7' 21 sq. ft.
Materials : #16 cladding = 42 sq. ft.
IGSC Frame #12 = 50 l.f.
Fabrication : 2 Steelmen / 12 hr
Equipment : 1 Welding machine
Steel door - 18" x 14" = 253 sq. ft. (2) leaf
Materials : #16 cladding = 504 sq. ft.
C - Frame #12 = 440 l.f.
Fabrication : 4 Steelmen / 56 hrs
Equipment : 1 Welding machine
Tinsmitting
Corrugated G. I. Sheet - 0.685 / sq.m.
Fastener : hook bolt - 4 pcs / 1.47 sq.m.
strap - pcs 1 sht / 792 (1/1.47)
G. I. rivets - 8 pcs. ( 1 kg /180 )
( 1 kg /1.47 )
Lifting : 4 Tinsmith
Installation :
4.500 bd.ft./ mh
3.000 bd.ft./ mh
4.400 bd.ft./ mh
3.600 bd.ft./ mh
24.000
8.000
mh / pc.
hrs / pc
224.000
40.000
mh / pc.
hrs / pc
23 of 47
ESTIMATE MANUAL
0.285
0.022
1.300
1.300
2.430
sht /sq.m.
kg. / l.m.
bend /l.m.
bend /l.m.
cu.m./ lm
0.600
0.500
8.000
6.000
0.020
mh /cu.m.
mh /cu.m.
mh /cu.m.
mh /cu.m.
mh /cu.m.
5.000 mh /cu.m.
2.000 mh /cu.m.
1.000 mh /cu.m.
2.540
8.540
0.400
mh /sq.m
mh /sq.m
mh /sq.m
3.280
16.700
0.800
mh /sq.m
mh /sq.m
mh /sq.m
0.071
0.080
mh / kg
mh / kg
1.330
1.400
2.860
2.860
2.860
mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m
24 of 47
ESTIMATE MANUAL
6. Vinyl tiles
7. Unglazed tiles
8. Glazed tile
9. Asphalt tiles
Carpentry works
1. Partition including framing
- " thk plywood single wall
- " thk plywood double wall
- wooden louver
- #10 cyclone wire
Doors ( excluding finish hardware )
1. FHC door
2. FSC door
3. Steel sliding door
4. Steel single door
5. Roll up aluminum door - manual
6. Cyclone wire sliding door
Windows
1. Fixed glass on steel frame
2. Fixed G. I. Louver
Fixed asbestos louver
4. Metal louver
Ceiling ( including framing )
1. 1/5" thk plywood
2. Acoustic tile with plywood backing
3. Concealed acoustic with aluminum T - runner
4. 3/16" thk asbestos cutting
Structural steel
1. Light structural steel framing
2. Heavy structural steel framing
Miscellaneous metal
1. Stair, stringer, handrail, tread & grating
Asbestos pipe
1. "
2. "
3. 1" to 1"
4. 1" to 2"
5. 2"
1.670
3.000
0.170
1.670
mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m
0.230
0.314
314.000
0.029
mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m
0.200
0.286
0.860
0.715
0.715
0.715
mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft
0.286
0.429
0.429
0.286
mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft
0.171
0.286
0.286
0.171
mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft
168.000
164.000
mh / m
mh / m
102.000
mh / m
20
20
22.5
25
30
mh / l. ft.
mh / l. ft.
mh / l. ft.
mh / l. ft.
mh / l. ft.
of 100
of 100
of 100
of 100
of 100
25 of 47
ESTIMATE MANUAL
6. 3"
7. 3"
8. 4"
Cast iron pipe
1. 2"
2. 4"
3. 6"
4. 8"
5. 10"
6. 12"
7. 14"
8. 16"
9. 18"
10. 20"
11. 24"
12. 30"
P V C pipes
1. " - "
2. 1" - 1"
3. 1" - 2"
4. 2"
5. 3"
6. 3"
7. 4"
8. 5"
9. 6"
33 mh / l. ft. of 100
35 mh / l. ft. of 100
40 mh / l. ft. of 100
66.80 mh / 100 l. ft.
100.20 mh / 100 l. ft.
150.30 mh / 100 l. ft.
200.40 mh / 100 l. ft.
300.40 mh / 100 l. ft.
317.30 mh / 100 l. ft.
367.40 mh / 100 l. ft.
417.50 mh / 100 l. ft.
467.60 mh / 100 l. ft.
501.0 mh / 100 l. ft.
551.20 mh / 100 l. ft.
626.30 mh / 100 l. ft.
20.22 mh / 100 l. ft.
22.50 mh / 100 l. ft.
25.00 mh / 100 l. ft.
30.0 mh / 100 l. ft.
33.0 mh / 100 l. ft.
35.0 mh / 100 l. ft.
40.0 mh / 100 l. ft.
50.0 mh / 100 l. ft.
75.0 mh / 100 l. ft.
1.00 - 1.35
3.870
4.700
2.50 - 2.67
10.000
0.910
1.200
16.500
4.400
cu.m./ md
cu.m./ md
cu.m./ md
cu.m./ md
kgs / md
cu.m./ md
cu.m./ md
kgs / md
cu.m./ md
26 of 47
ESTIMATE MANUAL
4.400 cu.m./ md
2.400 kgs / md
3.870 cu.m./ md
1.000 cu.m./ md
70.000 bd.ft./ md
75.000 bd.ft./ md
112.000 bd.ft./ md
80.000 bd.ft./ md
44.000 bd.ft./ md
60.000 sq.ft. / md
60.000 bd.ft./ md
112.000 bd.ft./ md
33.000 bd.ft./ md
58.000 l.ft. / md
105.000 sq.ft. / md
50 l. l.ft. / md
27.000 l.ft. / md
60.000 l.ft. / md
1.500 sq.m./ md
45.000 l.ft. / md
15.000 sq.ft. / md
10.000 sq.ft. / md
3.000 steps / md
8.000 sheets/md
10.000 sheets/md
52.000 l.ft. / md
29.000 sq.m./ md
2.300 sheets/md
46.000 bd.ft./ md
40.000 bd.ft./ md
60 - 90 bd.ft./ md
50 - 75 bd.ft./ md
90 - 120 bd.ft./ md
25 - 55 bd.ft./ md
30 - 60 bd.ft./ md
40 - 80 bd.ft./ md
75 - 150 sq.ft. / md
40 - 80 sq.ft. / md
27 of 47
ESTIMATE MANUAL
30.000
75.000
18.000
22.000
28.000
5.000
2.000
80.000
1.340
200 - 300
45.000
60.000
38.000
10.000
sq.ft. / md
sq.ft. / md
sq.ft. / md
sq.ft. / md
sq.ft. / md
sets / md
pairs / md
l.ft. / md
sq.m./ md
sq.ft. / md
sq.m./ md
l.ft. / md
l.ft. / md
sq.ft. / md
20.000 sq.m./ mh
40.000 sq.m./ mh
0.130
0.760
0.610
0.380
0.150
cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
15.000 cu.m./ mh
0.060 cu.m./ mh
1.220
0.200
8.000
0.300
30.000
2.090
cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
sq.m./ mh
9.460 sq.m./ mh
28 of 47
ESTIMATE MANUAL
0.060
0.040
0.030
0.020
0.070
l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
cu.m./ mh
0.800
0.600
0.400
0.300
l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
0.200
0.040
1.000
0.700
1.000
1.500
5.000
1.300
1.700
1.250
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
l.m. / mh
l.m. / mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
1.250
1.250
1.250
0.600
0.700
0.500
0.200
0.190
0.230
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
1.000 sq.m./ mh
0.850 sq.m./ mh
0.650 sq.m./ mh
29 of 47
ESTIMATE MANUAL
Columns
Suspended slabs
4" - 18"
18" - 36"
36" - up
Formwork fabrication
Stripping of formwork
Nail on ground
Nails above 10'
Boxes
Columns
Suspended slabs
0 - 18"
18" - 36"
36" - up
General stripping
Reinforcing bars
Fabrication & installation
Metal work
Structural steel
Miscellaneous metal
Fabricstion of anchor bolt
Installation of anchor bolt
Fabrication of embedded item
Laying of RCP - 8 men one team
24" 16 pcs
36" 10 pcs
48"
6 pcs
Underground drainage piping laying
6" concrete pipe
12" concrete pipe
15" concrete pipe
18" concrete pipe
30" concrete pipe
Carpentry works
Plywood partition
Plywood ceiling
T&G flooring & siding
0.850 sq.m./ mh
1.200
0.800
0.600
1.860
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
8.000
1.550
1.950
2.350
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
3.600
2.400
1.850
4.080
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
10.000
kgs / mh
10.000
kgs / mh
10.000
3.000
7.000
kgs / mh
kgs / mh
kgs / mh
2.000 l.m. / mh
1.250 l.m. / mh
0.750 l.m. / mh
0.400
0.250
0.230
0.220
0.120
l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
0.930 sq.m./ mh
0.700 sq.m./ mh
14.000 bd.ft. / mh
30 of 47
ESTIMATE MANUAL
Ceiling framing
Siding framing
Roof framing
Floor framing
Wood post
Truss fabrication
Truss erection
Girts
Plates
Purlins
Fascia board
Cabinets
Framing
boarding
Plywood sheeting
door
Painting works
Anay paint
Varnishing
Metal works
G. I. roofing
G. I. gutter cut & shape
G. I. gutter installation
Downspout cut & shape
Downspout installation
Backfilling & waterproofing
Painting structural steel framing
FLAT BAR IN KILOS
Thickness
1/8" ( 3 mm )
" ( 6 mm )
5.500
7.500
4.130
9.380
8.750
5.750
5.000
9.380
15.000
7.500
4.380
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
7.500
10.000
1.740
0.930
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
3.480 sq.m./ mh
2.320 sq.m./ mh
1.220
6.250
2.250
3.380
7.500
2.250
20.000
Width
1"
2"
3"
4"
5"
6"
1"
2"
Length
20'
20'
sq.m./ mh
l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
sq.m./ mh
mh/m ton
Weight
3.870
7.730
11.600
15.460
19.330
23.200
7.730
15.460
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
31 of 47
ESTIMATE MANUAL
1/16" ( 2 mm )
3/16" ( 4 mm )
3/16" ( 9 mm )
7/16" ( mm )
9/16" ( 14 mm )
3/8" ( 10 mm )
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
20'
20'
20'
20'
20'
20'
23.200
30.930
38.600
46.400
1.930
3.860
5.800
7.730
9.660
11.600
5.800
11.600
17.400
23.200
29.000
34.800
9.660
19.330
29.000
38.000
48.330
58.000
13.530
27.060
40.600
54.130
67.660
81.200
17.400
34.800
52.200
69.600
87.000
104.440
11.600
23.200
34.800
46.400
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
32 of 47
ESTIMATE MANUAL
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
5/8" ( 15 mm )
7/8" ( 22 mm )
" ( 12 mm )
FORMULA
:
'1
2 x 12
20'
20'
20'
58.000
69.600
19.330
38.660
58.000
77.330
96.660
116.000
27.060
54.140
81.200
108.270
135.330
162.400
15.460
30.930
46.400
61.860
77.330
92.800
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
Note : 490 is a factor for pounds as to obtain kilo, divide then sum by 2.20 & the answer is in
kilo.
WEIGHT OF BOLTS IN KILOS
Lgth (in)
1"
"
3/8"
2"
0.144
0.245
3"
0.169
0.285
6"
0.194
0.324
7"
0.219
0.364
8"
0.245
0.403
9"
0.270
0.443
Dinmension
"
7/8"
0.363
0.524
0.421
0.601
0.478
0.678
0.535
0.755
0.593
0.852
0.649
0.509
1"
0.723
0.824
0.916
1.027
1.129
1.250
1 - 1/8"
0.978
1.106
1.233
1.361
1.489
1.617
1 - "
1.260
1.448
1.576
1.735
1.893
2.051
33 of 47
ESTIMATE MANUAL
10"
11"
12"
13"
14"
0.295
0.300
0.346
0.37
0.40
0.482
0.522
0.561
0.601
0.640
0.706
0.765
0.820
0.877
0.934
0.986
1.063
1.140
1.217
1.294
1.351
1.455
1.534
1.636
1.737
1.744
1.872
2.000
2.127
2.255
2.209
2.367
2.526
2.684
2.042
1/8"
"
3/8"
"
5/8"
"
7/8"
1'
3"
5"
7"
9"
13"
=
=
=
=
=
=
=
=
=
=
=
=
=
3 mm
6 mm
10 mm
12-13 mm
16 mm
19-20 mm
22 mm
25 mm
75 mm
125 mm
175 mm
225 mm
325 mm
%'age of 28
Day strength
1
2
3
17.1
34.3
44.4
Days
%'age of 28
Day strength
Days
%age of 28
Day strgth
30
31
32
100.9
101.6
102.4
59
60
61
110.20
110.30
110.40
34 of 47
ESTIMATE MANUAL
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
31.5
34.5
59.7
64.1
67.0
70.5
73.5
77.0
78.0
81.2
82.5
85.0
86.7
88.0
89.0
91.0
92.3
93.5
94.8
95.8
96.5
97.4
98.3
99.1
100.0
100.4
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
103.0
103.3
103.8
104.2
104.8
105.0
105.5
106.0
106.3
106.8
107.0
107.3
107.5
107.8
108.0
108.2
108.5
108.0
109.0
109.2
109.4
109.6
109.6
109.9
110.0
110.1
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
110.50
110.60
110.70
110.80
110.90
110.90
111.00
111.00
111.10
111.10
111.10
111.20
111.30
111.40
111.60
111.70
111.80
111.90
112.00
112.00
112.20
112.30
112.40
112.50
112.50
112.60
0.222 kgs. / m
6.00
7.50
9.00
10.50
12.00
1.332
1.665
1.998
2.331
2.664
kgs
kgs
kgs
kgs
kgs
10 mm ( # 3 ) 3/8"
0.616 kgs. / m
6.00
7.50
9.00
3.696 kgs
4.620 kgs
5.544 kgs
35 of 47
ESTIMATE MANUAL
10.50
12.00
6.468 kgs
7.392 kgs
12 mm ( # 4 ) "
0.888 kgs. / m
6.00
7.50
9.00
10.50
12.00
5.328
6.660
7.992
9.324
10.656
kgs
kgs
kgs
kgs
kgs
16 mm ( # 5 ) 5/8"
1.579 kgs. / m
6.00
7.50
9.00
10.50
12.00
9.474
11.843
14.211
16.580
18.948
kgs
kgs
kgs
kgs
kgs
6.00
7.50
9.00
10.50
12.00
14.796
18.495
22.194
25.893
29.592
kgs
kgs
kgs
kgs
kgs
20 mm ( # 6 ) "
2.466 kgs. / m
22 mm ( # 7 ) 7/8"
2.577 kgs. / m
6.00
7.50
9.00
10.50
12.00
15.462
19.328
23.193
27.059
30.924
kgs
kgs
kgs
kgs
kgs
25 mm ( # 8 ) 1"
3.854 kgs. / m
6.00
7.50
9.00
10.50
12.00
23.124
28.905
34.686
40.467
46.248
kgs
kgs
kgs
kgs
kgs
28 mm ( # 9 ) 1 - 1/8"
4.833 kgs. / m
6.00
7.50
9.00
10.50
12.00
28.998
36.248
43.497
50.747
57.996
kgs
kgs
kgs
kgs
kgs
36 of 47
ESTIMATE MANUAL
32 mm ( # 10 ) 1 "
6.313 kgs. / m
6.00
7.50
9.00
10.50
12.00
37.878
47.348
56.817
66.287
75.756
kgs
kgs
kgs
kgs
kgs
36 mm ( # 11 ) 1 3/8"
7.991 kgs. / m
6.00
7.50
9.00
10.50
12.00
47.946
59.933
71.919
83.906
95.892
kgs
kgs
kgs
kgs
kgs
kgs. / ft.
1.52
2.06
2.856
kgs / 20'
31.24
41.20
56.52
kgs. / ft.
1.364
2.500
3.145
5.721
5.570
6.955
kgs / 20'
37.28
50.00
60.90
74.54
111.40
139.10
kgs. / ft.
kgs / 20'
CHANNELS
3/4.4
4/5.4
5/6.7
6/3.2
7/12.25
10/15.50
ANGLES
37 of 47
ESTIMATE MANUAL
0.364
0.530
0.680
0.870
0.670
0.460
1.060
0.820
0.560
1.260
0.960
0.150
2.140
1.780
1.460
1.110
0.750
3.500
2.680
2.270
1.865
1.400
1.20
10.60
13.60
17.40
13.40
9.20
21.20
16.40
11.20
25.20
19.20
3.90
42.80
35.60
29.20
22.20
15.00
70.00
53.60
45.40
37.30
28.00
kgs. / ft.
1.060
0.820
0.560
1.160
0.890
1.280
0.960
0.650
1.780
1.450
1.110
2.410
2.050
kgs / 20'
21.20
16.40
11.20
23.20
17.80
25.20
19.20
13.00
35.60
29.00
22.20
48.20
47.00
UNEQUAL ANGLES
1" x 1" x "
1" x 1" x 3/16"
1" x 1" x 1/8"
2" x 1" x "
2" x 1" x 3/16"
2" x 1" x "
2" x 1" x 3/16"
2" x 1" x 1/8"
2" x 1" x 5/16"
2" x 1" x "
2" x 1" x 3/16"
2" x 2" x 3/8"
2" x 2" x 5/16"
38 of 47
ESTIMATE MANUAL
Sidings
1.650
1.250
3.860
3.850
3.000
2.550
2.050
4.270
3.770
3.220
2.770
2.227
3.500
3.100
2.680
2.270
1.860
Material
form lumber
form lumber
form lumber
form lumber
form lumber
form lumber
form lumber
form lumber
form lumber
good lumber
good lumber
1" x 3" T&G
1" x 4" T&G
1" x 6" T&G
1" x 8" T&G
1" x 3" S - cut
1" x 4" S - cut
1" x 6" S - cut
33.00
23.00
77.20
69.00
60.00
51.00
41.00
85.40
75.40
65.40
55.40
44.54
70.00
62.00
53.60
45.40
37.20
Coverage
33 bd.ft /.sq.m.
6.50 bd.ft. / sq.m.
9.0 bd.ft. / sq.m.
34.0 bd.ft. / sq.m.
19.0 bd.ft. / sq.m.
25.0 bd.ft. / sq.m.
8.50 bd.ft. / sq.m.
36.0 bd.ft. / sq.m.
18.0 bd.ft. / sq.m.
1.0 bd.ft. / sq.m.
1.25 bd.ft. / sq.m.
16.66 pcs. / l.m.
11.77 pcs. / l.m.
7.87 pcs. / l.m.
5.34 pcs. / l.m.
20.00 pcs. / l.m.
13.16 pcs. / l.m.
7.87 pcs. / l.m.
39 of 47
ESTIMATE MANUAL
Grader
Payloader
Crane shovel
Shift roller
3W roller
Tractor drwn roller (1-D )
Tanden roller
Buggles
Wheel borrow
Water truck
Asphalt dist
Type of work
clearing & grubbing
clearing
stripping
excavating
quarrying
pushing
sub-grading
spreading
loading
loading
static rolling (12 passes 15 cm. lift)
vibratory rolling (4 passes15 cm lift)
static rolling (6 passes 20 cm. lift)
vibratory rolling (6 passes2 m lift)
static rolling (6 passes 20 cm. lift)
vibratory rolling
(6 passes60 cm. lift)
hauling common borrow
hauling SBBC
hauling concrete batch class A
hauling common borrow
hauling SBBC
hauling concrete batch class A
hauling concrete mix
hauling aggregates
hauling concrete mix
watering
spraying asphalt prime coat
180.00
500.00
200.00
25.00
50.00
3.00
300.00
50.00
50.00
50.00
45.00
135.00
34.00
240.00
24.00
72.00
Capability
180 sq.m./ hr.
180 sq.m./ hr.
180 sq.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
180 sq.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
3.50
3.00
3.00
2.50
2.00
2.00
6.00
2.50
1.75
1000.00
300.00
cu.m./trip
cu.m./trip
batch/trip
cu.m./trip
cu.m./trip
batch/trip
cu.ft./trip
cu.ft./trip
cu.ft./trip
180 sq.m./ hr.
180 sq.m./ hr.
40 of 47
ESTIMATE MANUAL
mixing concrete
crushing MSG
vibrating concrete mix
finishing concrete floor
hauling ( head capacity )
12.00
30.00
40.00
40.00
11.00
22.00
cu.m./trip
34 cu.yd.
Motorized grader
Unit
acre
acre
acre
0.25 acre
Condition
0.50 acre
2.0 acre
pulling disk
cutting weeds & grasses
1.0 acre
light stripping
Unit
1.50 cu.yd.
1.25 cu.yd.
75.0 cu.yd.
50 cu.yd.
45 cu.yd.
45 cu.yd.
75 cu.yd.
450 cu.yd.
300 cu.yd.
light clearing
medium clearing
heavy clearing
medium clearing
Condition
sandy soil
common earth
hard / frozen earth
sandy soil
common earth
hard digging
basing digging
"V" ditches
sandy soil
"V" ditches
41 of 47
ESTIMATE MANUAL
3. EXCAVATION
Equipment
Tractor 70 to 90 dbhp with single dozer
300 cu.yd.
125 cu.yd.
200 cu.yd.
Unit
130.0 cu.yd.
80 cu.yd.
50 cu.yd.
95.0 cu.yd.
80 cu.yd.
60 cu.yd.
87.93 cu.m.
115 cu.yd.
common earth
common earth
hard digging
easy digging
Condition
50 ft. level haul, common
earth
100 ft. level haul, common
earth
200 ft. level haul, common
earth
500 ft. level haul, common
earth
600 ft. level haul, common
earth
800 ft. level haul, common
earth
68.81 cu.m.
90 cu.yd.
57.30 cu.m.
75 cu.yd.
34.41 cu.m.
45 cu.yd.
75 cu.yd.
125 cu.yd.
200 cu.yd.
Unit
300 cu.yd.
Condition
spreading material
250 cu.yd.
191.15 cu.m.
200 cu.yd.
42 of 47
ESTIMATE MANUAL
70 to 90 dbhp
Pump, troiler, med., water distributor
Towed type grader
Motorized grader
Roller, sheepsfoot 2 drum in-line towed
by tractor
70 to 90 dbhp
152.92 cu.m.
150 cu.yd.
114.69 cu.m.
350cpm
400 sq.yd.
400 sq.yd.
650 sq.yd.
540 sq.yd.
450 sq.yd.
1,000 sq.yd.
3,000 sq.yd.
1,750 sq.yd.
350 gpm
6. SURFACE TREATMENT
Equipment
Tractor sweeper 30 dbhp
10 passes
9" loose layers
12 passes
moisture varies with
materials
scarify & shape
scarify & shape
60" layer, 8 passes
60" layer, 10 passes
60" layer, 12 passes
3 mph, 5 passes
3 mph, 5 passes
6" depth, 3 mph,
6 passes
moisture varies with
materials
Unit
300 cu.yd.
Condition
spread materials
200 cu.yd.
450 cu.yd.
300 cu.yd.
1500 cu.yd.
spread materials
sharing materials
compacting gravel
compacting grade,
10 passes
compacting macadam
moisture varies with
materials
75 cu.yd.
350 gpm
Unit
2,500 sq. yd.
2,500 sq. yd.
1,250 sq.yd.
Condition
sweeping, compact base
0.10gal / sq.yd. 24 ft.
spray
0.10 gal / sq.yd. 24 ft.
spray
43 of 47
ESTIMATE MANUAL
200 l.ft.
5,000 sq.yd.
3,000 sq.yd.
3,000 sq.yd.
1,250 sq.yd.
Motorized grader
150 sq.yd.
100 cu.yd.
120 tons
1,500 sq.yd.
3,000 sq.yd.
20 cu.yd
10 cu.yd
40 cu.yd
100 ton ft.
200 l.ft.
34 cu.ft.
Asphalt finisher 12 ft.
Concrete finisher 20 to 25 ft.
7. AGGREGATE PRODUCTION
Equipment
Rate & unit/hour
Crusher 2 units
25 tons / hr
crusher 9 units
150 tons / hr
Unit
15 tons
20 tons
30 tons
60 tons
100 tons
240 tons
105 cfm
90 cfm
20 l.ft.
Condition
1" screened aggregate
1" screened aggregate
1" screened aggregate
1" aggregate screened
mashed
1" aggregate screened
mashed
3" aggregate screened
mashed
at sea level
5,000 ft. above sea level
1" hole mix 16 ft. deep
requires 40 to 60 cfm of
44 of 47
ESTIMATE MANUAL
45 lbs. class
30 l.ft.
150 cu.yd.
250 cu.yd. / hr
200 cu.yd. / hr
150 cu.yd. / hr
8. SUBGRADE PREPARATION
Equipment
Rate & unit/hour
Grader - scarify & shape 334.40 sq.m. / hr
Road roller 5 - 8 tons
Unit
2.60 days
3.20 days
100 sq.yd.
1.10 days
83.16 sq.m. / hr
air
1" hole mix 16 ft. deep
requires 70 to 90 cfm of
air
from stock pile
=
=
Condition
7.0 surface / k.m.
9.0 surface / k.m.
7-9 surface / k.m, 3 mph
6 passes
Condition
1.0 day
3.0 days
3.70 days
cu.m.
cu.m.
Type of work
excavating loam or sand
exacavating clay or heavy soil
excavating rock
backfilling
spreading, tamping & grading
Capability
0.76
0.61
0.38
1.22
2.09
cu.m. / hr
cu.m. / hr
cu.m. / hr
cu.m. / hr
sq.m. / hr
45 of 47
ESTIMATE MANUAL
team ( 8 men )
4.78
9.46
20.00
40.00
cu.m. / hr
cu.m. / hr
sq.m. / hr
sq.m. / hr
16 pipes / 8 hrs
10 pipes / 8 hrs
6 pipes / 8 hrs
GO90
( gal )
0.0100
-
GAA
( lb )
0.0025
0.0037
0.0061
0.0050
0.0075
0.0120
0.0166
0.0132
0.0062
0.0012
0.0112
0.0075
0.0037
0.0087
0.0162
GO90
( gal )
0.03
0.03
0.03
GAA
( lb )
0.06
0.05
0.04
0.05
46 of 47
ESTIMATE MANUAL
gasoline
diesel
gasoline
7.50
20.00
20.00
0.53
0.06
0.35
0.09
0.25
0.01
gasoline
15.50
0.04
0.03
0.05
gasoline
15.50
0.04
0.03
0.05
gasoline
gasoline
gasoline
gasoline
diesel
gasoline
diesel
diesel
diesel
gasoline
gasoline
gasoline
10.00
13.00
11.00
5.00
15.00
22.00
10.00
75.00
20.00
38.00
76.00
3.00
0.03
0.05
0.05
1.00
0.02
0.02
0.04
0.02
0.03
0.03
0.03
0.03
0.03
0.03
0.06
0.06
0.02
0.03
0.06
0.01
0.03
0.04
gasoline
gasoline
gasoline
gasoline
gasoline
gasoline
gasoline
gasoline
gasoline
gasoline
15.00
13.00
6.00
23.00
0.03
0.03
0.02
0.02
0.03
0.03
0.03
-
0.03
0.01
0.03
0.03
0.03
0.03
0.05
0.06
0.05
-
diesel
2.50
0.01
0.07
0.05
47 of 47