Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Estimate Manual

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 47

ESTIMATE MANUAL

TABLE OF CONTENTS
ACTIVITY LIST FOR HIGHWAYS & BUILDINGS
Group 100 - Roadside and related features
Group 200 - Roadside features
Group 300 - Traffic services
Group 400 - Emergency works
Group 500 - Supervision, support & overhead
STANDARD SPECIFICATIONS FOR HIGHWAYS & BRIDGES
Part 1 - Earthwork
Part 2 - Base course
Part 3 - Surface course & pavements
Part 4 - Structures
Part 5 - Incidental construction
ESTIMATING PROCEDURES FOR :
1. Batterboard
2. Excavation
3. Backfill
4. Concrete
5. Ratio of mixture
6. Mortar mixture
7. Curve & gutter
8. Asphalt pavement
9. Concrete pavement
10. Base course
11. Sub - grade
12. Grouted riprap
13. Adobe stone
14. Adobe buttress
15. Mortar for adobe stone
16. Cement and sand factor per concrete pipe joint collar
17. CHB concrete footing per meter
18. Concrete hollow blocks
19. Labor output per team
20. Plastering
21. Cement tiles

----------------------------------------------

Page
4-6
4-5
5
5
5
5-6

----------------------------------------------

6-8
6
6-7
7
7
8

----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

8 - 18
8
9
9
9
9 - 10
10
10
10
10
10 - 11
11
11
11
11
11
11 - 12
12
12 - 13
13
13
13

1 of 47

ESTIMATE MANUAL

22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.

Grouting compound
Scaffolding
Form works
Floor joist
Wooden studs & sidings
Wooden flooring
Double walling
Double wall partition
Ceiling joist
Baseboard
Ceiling board
Aluminum tee runner
Facia board
Wooden trusses & rafters
Purlins
Roofing
37.c.1. Pitch fcator of truss & rafter
37.g.1.a. Table of coverage ( G. I. sheet )
37.g.1.b. Table of coverage
37.g.2. Table of fasteners
37.g.3. Table of rivet per sheet of roofing
37.g.4. Table of strap per plain G. I. sheet

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

13
13 - 14
14
14
14
14 - 15
15
15
15
15
15
15
15 - 16
16
16
16
16 - 17
17
17
17 - 18
18
18

SPREADING RATES OF PAINTS


1. Oil paint
2. Oil paint flat
3. Enamel paint
4. Exterior spur varnish
5. Interior spur varnish
6. Shellac
7. Single satin finish
8. Asphalt rough finish
9. Water paint

----------------------------------------------------------------------------------

18 - 20
18 - 19
19
19
19
19
19
19
19
19 - 20

RATE OF APPLICATION ( TILES )


NAILS CONVERSION FACTORS
STANDARD REINFORCEMENT OF WALLS
DOOR JAMBS WITHOUT TRANSOM

-------------------------------------

20
21
21
21 - 22

2 of 47

ESTIMATE MANUAL

DOOR JAMBS WITH TRANSOM


FLUSH DOOR FRAME
HOUR RATE PER ITEM OF WORK
UNIT RATE PER ITEM OF WORK
LABOR OUTPUT PER MAN-DAY
LABOR CAPABILITY PER HOUR
FLAT BAR IN KILOS
WEIGHT OF BOLTS IN KILOS
INCH TO MILLIMETER CONVERSION TABLE
BOLTS REQUIRED FOR TRUSSES
TABLE OF VALUES FOR STRENGTH OF CONCRETE
REBAR CONVERSION TABLE
TIEWIRE FORMULA
DECORS
CHANNELS
ANGLES
UNEQUAL ANGLES
CARPENTRY WORKS
CEILING PARTITION & FORMWORKS
LIGHT & HEAVY EQUIPMENT CAPABILTY TABLE

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

22
22
22 - 24
24 - 26
26 - 28
28 - 31
31 - 33
33 - 34
34
34
34 - 35
35 - 37
37
37
37
37 - 38
38 - 39
39
40
40 - 41

HEAVY & LIGHT EQUIPMENT FOR :


1. Clearing & grubbing
2. Drainage ditche
3. Excavation
4. Embankment
5. Base course construction
6. Surface treatment
7. Aggregate production
8. Subgrade preparation
9. Base course construction
10. Capabilities of manual labor

-------------------------------------------------------------------------------------------

41 - 46
41
41 - 42
42
42 - 43
43
43 - 44
44 - 45
45
45
45 - 46

TABLE I - POL CONSUMPTION OF ORDINANCE EQUIP.


TABLE II - POL CONSUMPTION OF ENGINEERING EQUIP.

-------------------

46
46 - 47

3 of 47

ESTIMATE MANUAL

ACTIVITY LIST FOR HIGHWAYS & BUILDINGS


GROUP 100 -

ROAD & RELATED FEATURES

Unpaved Road Surfaces


101 Manual repair of unpaved road surfaces
102 Manual patching of unpaved soad surfaces
103 Machine patching of unpaved road surfaces
104 Machine grading unpaved road surfaces

-------------------------------------

cu.m.
cu.m.
cu.m.
sq.m.

Bituminou Pavements
111 Premix patching bituminous pavments
112 Penetration patching bituminous pavements
113 Sealing bituminous pavements
114 Replacement of bituminous pavements

-------------------------------------

cu.m.
cu.m.
li.
sq.m.

Concrete Pavements
121 Patching concrete pavaments
122 Crack & joint sealing of concrete pavements
123 Replacement of concrete pavements

----------------------------

cu.m.
li.
sq.m.

Unpaved Shoulder
131 Manual repair of unpaved shoulder
132 Manual patching unpaved shoulder
133 Machine grading unpaved shoulder

----------------------------

m.
cu.m.
k.m.

Drainage
141 Manual ditch cleaning
142 Manual inlet/outlet cleaning
143 Culvert line cleaning
144 Repair / replacement of minor drainage structures

-------------------------------------

m.
no.
no.
no.

Bridges
151 Cleaning bridges
152 Patching concrete decks
153 Repair to concrete bridges
154 Repair to steel bridges
155 Repair to bailey bridges

----------------------------------------------

m.
sq.m.
no.
no.
no.

4 of 47

ESTIMATE MANUAL

156
157

Repair to tomber bridges


Cleaning bridge waterways

-------------------

no.
no.

Ferries
161 Ferry service

----------

hrs.

Temporary Repairs
171 Temporary patching

----------

m.

Other Maintenance and Repairs


181 Other maintenance to roadway & related feature

----------

md

-------------------------------------

m.
cu.m.
no.
md

----------------------------------------------

no.
k.m.
m.
m.
md

----------------------------

md
md
proj.

-------------------

cu.m.
md

GROUP 200 - ROADSIDE FEATURES


201 Vegetation control
202 Erosion repair & control on roadside
203 Repair to major roadside structures
204 Other roadside maintenance
GROUP 300 - TRAFFIC SERVICES
301
302
303
304
305

Sign maintenance
Centerline & lane line repainting
Guardrail maintenance
Sight distnace mowing & clearing
Other traffic services

GROUP 400 - EMERGENCY WORKS


401
402
403

Initial response to emergency roadways


Initial response to emergency bridges
Emergency projects

GROUP 500 - SUPERVISION, SUPPORT & OVERHEAD


501
502

Production of bituminous pavements


Other material production & hnadling

5 of 47

ESTIMATE MANUAL

503
504
505
506

Idirect cost of work or expenses


Other work or expenses
Foreman supervision
Unproductive time

-------------------------------------

md
md
cd
cd

STANDARD SPECIFICATIONS FOR HIGHWAYS & BRIDGES


CONSTRUCTION DETAILS
Part I - Earthwork
100 Clearing & grubbing
101 Selective removal of trees
102 Stripping
103 Removal of bridges,culverts & siphons
104 Removal of miscellaneous structures
105 Roadway & drainage excavation
106 Excavation for structures
107 Borrow
108 Selected borrow (aggregate sub-base)
109 Embankments
110 Foundation fill
111 Overhaul
112 Borrow haul
113 Subgrade
114 Rolling
115 Watering
116 Shoulders
117 Finishing earth graded roads
118 Preparation of previously constructed road
119 Protection ditches
120 Spot subgrade reinforcement
Part 2 - Base Coarse
200 Selected borrow base course (agg. base course)
201 Gravel, crushed gravel or crushed stone base course
202 Sledged stone base course
203 Bituminous macadam base base course

Unit of Measurement
---------hectare
---------no.
---------cu.m.
---------l.s.
---------l.s.
---------cu.m.
---------cu.m.
---------cu.m.
---------cu.m.
---------l.s.
---------cu.m.
---------cu.m.
---------cu.m.
----------------------------------------------

per hr.
1,000 li. / unit
l.s.
k.m.
k.m.

-------------------------------------

cu.m.
cu.m.
sq.m.
m or cu.m.

6 of 47

ESTIMATE MANUAL

204

Bituminous plant mix base course

----------

Part 3 - Surface Coarse and Pavements


300 Field laboratory
301 Asphaltic materials
302 Bituminous prime coat
303 Bituminous tack coat
304 Bituminous surface treatment ( emulsified asphalt type )
305 Bituminous seal coat
306 Bituminous macadam pavement ( hot asph. type )
307 Bituminous macadam pavement ( emulsified asphalt type )
308 Dense graded plant - mix surface course ( emulsified asphalt type )
309 Open-graded plant - mix surface course
310 Bituminous concrete surface course
311 Bituminous preservative treatment
312 Dense graded travel plant - mix surface course
313 Rock asphalt
314 Bituminous surface treatment ( H. A. T. )
315 Drag broom
316 Portland cement concrete pavement
317 Rock asphalt binder course
Part 4 - Structures
400 Steel bridges
401 Timber detour span
402 Piling
403 Concrete railing
404 Paints or painting
405 Concrete
406 Reinforcing steel
407 Structural steel
408 Welding structural steel
409 Sheet files
410 Treated & untreated timber
411 Timber structures
412 Stone masonry

---------- l.m. along C.L.

----------------------------------------------------------------------------------------------------------------------------------------------------------

net direct pay't


m.
m.
m.
m or cu.m.
m.
m or cu.m.
m or cu.m.
m or cu.m.
m or cu.m.
m.
m.
m or cu.m.
m.
m or cu.m.
n.d.p.
sq.m.
cu.m.

---------------------------'----------

qty of struc. stl


as unit
l.m. of piles
l.m. along C.L.

----------------------------

cu.m.
kg.
kg.

-------------------

l.m.
bd.ft.

----------

cu.m.

Part 5 - Iincidental Construction

7 of 47

ESTIMATE MANUAL

500 Riprap & grouted riprap


501 Hand - laid rock embankment
502 Combination concrete curve & gutter
503 Concrete sidewalk
504 Bituminous sidewalk
505 Reinforced concrete pipe culvert
506 Catch basin, manholes & inlets
507 Wood guardrail
508 Traffic line lacquer
509 Underdrains

-------------------------------------------------------------------------------------------

cu.m.
cu.m.
l.m.
sq.m.
sq.m.
l.m. or l.f.
no.
l.m.
l.m.
l.m.

ESTIMATING PROCEDURE FOR :


1. BATTERBOARD
a. To estimate batterboard, first compute the area of the structure in sq.m. multiply the area by
4.85 bd.ft. for 2" x 2" lumber, 7.28 bd.ft. for 2" x 3" lumber. Then the total bd.ft. divided by
2 will give you the bd.ft. of lumber to be used as batterboard.
b. The second procedure is to compute the lineal meter of the structure location giving an allowance or margin of 1.00 all around. Count also the no. of stake to be used. No. of stake multiply by 1.20 ( length of stake ) to get total lineal meter. Add all the ilneal meter & change to lineal foot. Compute the bd.ft. by using 2" x 2" or 2" x 3" lumber.
c. For nails : divide the total bd.ft. by 1,000 then multiply by 15 to get kilos required. If keg
: divide the total bd.ft. by 2,500.
d. For # 12 guide wire to be used as guide in layout, divide the total bd.ft. by 4,000 to obtain
roll of wire.

Batterboard
Stake

Guide Wire

2. EXCAVATION
a. To estimate volume of excavation, compute the area to be excavated then multiply by the

8 of 47

ESTIMATE MANUAL

depth
b. For cut and fill, use the Prismoidal Formula (A1 + A2)/2 x depth or length.
3. BACKFILL
a. For backfilling, use the same procedure as of the excavation no. 1, by multiply the length,
width & depth. If the backfill will be compacted add 15% for compaction.
4. CONCRETE
a. To estimate volume or cu.m. of concrete, use the same procedure in computing excavation
& backfilling.
b. To obtain bag of cement, sand and gravel, determine first the psi or class of mixture.
5.

RATIO OF MIXTURES
Class AAA
Cement
Sand
Gravel
Class AA
Cement
Sand
Gravel
Class A
Cement
Sand
Gravel
Class B
Cement
Sand
Gravel
Class C
Cement
Sand
Gravel
Class D
Cement
Sand
Gravel

1:1:2

1 : 1 : 3

1:2:4

1 : 2 : 5

1:3:6

1 : 3 : 7

4,500-5,000 psi
13.50 bags
0.51 cu.m.
1.02 cu.m.
3,500-4,000 psi
11.35 bags
0.41 cu.m.
0.82 cu.m.
3,000
psi
9.50 bags
0.42 cu.m.
0.84 cu.m.
2,500
psi
8.50 bags
0.44 cu.m.
0.87 cu.m.
2,000
psi
7.50 bags
0.44 cu.m.
0.89 cu.m.
1,600
psi
6.50 bags
0.45 cu.m.
0.91 cu.m.

9 of 47

ESTIMATE MANUAL

6.

MORTAR MIXTURE
Class AA
Cement
Sand
Class A
Cement
Sand
Class B
Cement
Sand
Class C
Cement
Sand
Class D
Cement
Sand

1:1
21.0 bags
0.85 cu.m.
1:2
18.85 bags
1.0 cu.m.
1:3
13.0 bags
1.06 cu.m.
1:4
10.0 bags
1.08 cu.m.
1:5
8.0 bags
1.10 cu.m.

7. CURVE & GUTTER


a. To estimate curve and gutter : lm x 0.74 cu.m. = total cu.m.
b. To obtain form lumber : lm x 8.50 bd.ft. = total bd. ft.
c. To obtain cement, sand , gravel : determine the mixture to be used & multiply the cu.m.
by the corresponding factor of mixture.
8. ASPHALT PAVEMENT
a. To obtain asphalt for 2" thk. Asphalting : 1 metric ton of asphalt coverage of 8.75 sq.m.,
for prime coating (liquid) : total sq.m. divided by 400 = no. of drums or 1 gal. Asphalt
coverage of 64.0 sq.ft. or 6.00 sq.m..
9. CONCRETE PAVEMENT
a. To obtain bag of cement for 8" thk. pavement : total cu.m. x 8.50 = bags, or total sq.m.
x 1.90 = bags. for sand : total cu.m. x 0.47 = cu.m. of sand. for gravel : total cu.m.
x 0.94 = cu.m. of gravel. for water : cu.m. x 66.40 = gal. of water.
10. BASE COURSE
a. To obtain base coarse for 6.00 m. wide x 0.20 road : Compacted = for every km. use
1,200 cu.m. base course.
In-place-(Quarried) = for every km.use 1260 cu.m.
Loose (hauled) use 1400 cu.m.

10 of 47

ESTIMATE MANUAL

11. SUB GRADE


a. To obtain subgrade or road bed for 9.00 x 0.15 road using common borrow
Compacted = for every km. use 1350 cu.m.
In-place (Quarried) = for every km. use 1500 cu.m.
Loose (Hauled) = for every km. use 2010 cu.m.
12. GROUTED RIPRAP
a. To estimate riprap grouting : total volume of riprap x 0.15 or 0.30 = volume of concrete.
To obtain cement : vol. x factor, same as to sand : area x 0.425 = cement, area x 0.03
= sand in cu.m..
b. To obtain volume of riprap : area x depth = volume of riprap.
13. ADOBE STONE
a. To estimate adobe : 0.15 x 0.15 x 0.45 : total area x 15 pcs. for cross footing, area x 6
pcs for stairs, cu.m. x 90 pcs. for mortar of 1 cm. thk. Wall factor : 0.0009, for cross
footing factor : 0.000675, for stairs factor : 0.001575.
b. To obtain cement and sand, multiply the cu.m. by no. of pcs., then multiply by factor of
moratr. To estimate cross footing : estimate it as continuous footing.
14. ADOBE BUTTRESS
Finish Cross Section
0.35 x 0.50
0.50 x 0.50
0.50 x 0.65
0.50 x 0.80
0.50 x 0.95

Stone/Course
2
3
4
5
6

15. MORTAR FOR ADOBE STONE - 1 centimeter thick


0.000675 cm.
Cross Footing
0.0009 cm.
Wall
0.001575 cm.
Stair - Buttress

Stone / Mt. Bt.


12
18
24
30
36

one side
one side, one end
two sides, one end

16. CEMENT & SAND FACTOR PER CONCRETE PIPE JOINT COLLAR
Pipe Diameter
Cement
0.02
4" dia. NRC
0.03
6" dia. NRC
0.05
8" dia. NRC

Sand
0.13
0.19
0.26

11 of 47

ESTIMATE MANUAL

12" dia. RCP


15" dia. RCP
18" dia. RCP
24" dia. RCP
30" dia. RCP
36" dia. RCP
42" dia. RCP
48" dia. RCP

0.12
0.15
0.20
0.35
0.50
0.70
0.75
1.20

0.39
0.49
0.59
0.79
0.99
1.19
1.38
1.58

Note : When wall is supported by buttress, estimate first the buttress stone for adobe.
estimate stone for adobe wall ( subtract width of buttress & openings ). To estimate
cross footing, estimate it as continuous footing.
17. CHB CONCRETE FOOTING PER METER
CHB
Ftg. thk.
Ftg. Base
Cement
4"
0.10
0.30
0.27
0.15
0.30
0.45
0.15
0.45
0.63

Sand
0.01
0.02
0.03

Gravel
0.02
0.04
0.06

Vol. / m.
0.03
0.05
0.07

18. CONCRETE HOLLOW BLOCKS ( C H B )


a. To estimate CHB Wall, compute the total area of coverage and less all openings such as windows & doors.
b. To obtain pieces of CHB : area x 12.15 or 12.50 .
c. To obtain cement : area x 0.27 for 4" CHB, 0.71 for 6" CHB, & 1.16 for 8" CHB
d. For sand : area x 0.022 for 4" CHB, 0.058 for 6" CHB, & 0.094 for 8" CHB.
e. For Rebars :
4" CHB using #3 @ 32" verical. & #3 @ 24" horizontal, area x 1.64 = kg.
using #3 @ 32" vertical & #4 @ 24" horizontal, area x 1.85 = kg.
6" CHB

using #3 @ 32" verical . & #3 @ 24" horizontal, area x 1.64 = kg.


using #4 @ 32" vertical & #4 @ 24" horizontal, area x 2.90 = kg.

8" CHB

using #3 @ 32" vertical & #3 @ 24" horizontal, area x 2.00 = kg.


using #4 @ 32" vertical & #4 @ 24" horizontal, area x 3.32 = kg.
f. For tie wire #16 : for 4" CHB = area x 0.005, for 6" CHB = area x 0.008, for 8"
CHB = area x 0.009. All answer for this will be in roll of wire. Other procedure : total
kgs. Divided by 0.300 = roll of wire.

12 of 47

ESTIMATE MANUAL

19. LABOR OUTPUT PER TEAM


a. 4" CHB : Crew - 1 mason & 2 helper will rate 12 sq.m./8 hrs. or 2.20 mh./sq.m.
b. 6" CHB : Crew - 1 mason & 2 helper will rate 10 sq.m./8 hrs. or 2.40 mh./sq.m.
c. 8" CHB : Crew - 1 mason & 2 helper will rate 8 sq.m./8 hrs. or 3.00 mh./sq.m.
20. PLASTERING
a. To estimate mortar for plastering, compute the area & multiply 0.025 or 0.0125 to obtain
volume 1 Face = 0.0125, 2 Faces = 0.025.
b. To obtain bags of cement : vol. x 13, for sand : vol. x 1.06. Before obtaining bags of
cement & cu.m. of sand, determine first the no. of face to be plastered & class of mixtures.
c. To obtain cement : area x 0.33 = bags, for sand : area x 0.03 = cu.m. sand.
21. CEMENT TILES
a. To obtain pcs. of cement tiles of 4" x 4" : area in sq.m. x 100 pcs., for 6" x 6" : area
x 45 pcs, for 8" x 8" : area x 25 pcs., for 12" x 12" : area x 12 pcs., for 16" x 16" :
area x 6.25 pcs.
b. For bedding : area x 0.33 = bags of cement, area x 0.03 = cu.m. of sand.
22. GROUTING COMPOUND
a. Horntop coating : 1 liter for every 1 sq.m.
b. Horntop floor topping : 1.20 for every 1 sq.m.
c. Applicaton : Part A and B should be mixed by machine at a rate of 250 to 300 rpm =
4 min. minimum. During mixing period add 5 parts of sol. silica sand. Coating thickness
should be 2mm = 1/16 V for topping thickness 5mm = 1/4.
d. Using daraweld C : for bonding mixture use 1 part daraweld, 5 parts cement, 2.50 parts
sand & 1 part water.
For topping : 1 part daraweld, 5 parts cement, 15 parts sand and 1 part water.
For non-skid surface : 1 part daraweld, 5 parts cement, 5 parts sand and 1.5 part
of water. For waterproofing : 1 part daraweld, 3 parts cement, 6 parts sand & 1 part water.
e. Using hornseal as hardener for floor : 1 liter for every 10 sq.m., using as curing compound : 1 liter for every 5 sq.m., using as sealing : 1 liter for every 6.0 sq.m., if rough
& 1 liter for every 9 sq.m..
f. Hydratite : use 1 lb. for every 1 bag of cement.
g. Sahara : use I bag sahara for every 1 bag of cement.
23. SCAFFOLDING
a. Compute the floor area plus the area of the four elevations, then multiply by the no. of storey
for floor of the structure.

13 of 47

ESTIMATE MANUAL

b. To obtain bd.ft.of lumber : total area x 6.75 = total bd.ft. of 2" x 3" lumber.
c. To obtain nails : divide the total bd.ft. by 2500 = keg of nails, note that I keg of nails is
equivalent to 45 kilos.
d. Other solution in obtaining nails : total bd.ft. divide by 1000 then multiply by 15 = kls.
of nails.
24. FORMWORKS
a. To estimate formworks, compute the area of the item that need form work.
b. To obtain bd.ft. of lumber, multiply the area by the corresponding factor on the conversion
table for formulas. After obtaining the total bd.ft. divide it to no. of uses.
c. To estimate " x 4' x 8' sht. board plywood, divide the total area by 2.88 then divide by the
no. of uses.
d. For nails : total bd.ft. divide by 2500 = keg.
e. For tie wire : total bd.ft. divide by 4000 = roll.
f. For formoil : change the area of sq.m. to sq.ft. then divide by 200 = gals. of oil.
25. FLOOR JOIST
a. To estimate the floor joist board ft. per sq.m., compute the area then multiply by the corresponding factor shown in the floor joist conversion.
b. For nails use the same procedure as of the formworks for keg of nails or divide the total bd.ft.
by 1,000 then multiply by 11.44 for kilos of 4" CW nails.
26. WOODEN STUDS & SIDINGS
a. To estimate bd.ft. of studs at 0.60 o.c. for sidings using 2" x 3",multiply the area by 9.84,
for 2" X 2" : area x 6.54, for 2" x 4" : area x 13.08, for 2" x 5" : area x 16.38.
b. To obtain nails : divide the total bd.ft. by 1,000 then multiply by 6.80 to obtain kilos of 3"
C.W. nails.
c. For stone cut sidings, compute the lineal meter of spread then multiply by 20 pcs / l.m. for
1" x 3", 13.16 pcs / lm.for 1" x 4", 7.87 pcs / lm. for 1" x 6" & 5.95 pcs / l.m. for 1" x
8".
d. To obtain nails : divide the total bd.ft. by 1,000 then multiply by 9.10 for kilos of 2" finishing nails.
27. WOODEN FLOORING
a. To estimate T&G flooring, compute the lineal
linear
meter
meter
of of
spread
spread
then
then
multiply
multiply
byby
16.66 pcs /
l.m. for 1" x 3" T&G, 11.77 pcs / l.m. for 1" x 4", 7.87 pcs / l.m. for 1" x 6" T&G,
5.34 pcs / l.m. for 1" x 8" T&G.
b. To obtain nails : divide the total boardfeet by 1,000 then multiply by 13.60 for fini. nails.

14 of 47

ESTIMATE MANUAL

28. DOUBLE WALLING


a. To estimate plywood double walling of a siding, divide the total area by 2.88 = pcs of plywood.
b. To obtain nails : pcs of plywood x 2 then divide by 1,000 then multiply by 9.10 for 1" finishing nails.
29. DOUBLE WALL PARTITION
a. To estimate boardfoot of studs, use the same procedure as of wooden sidings.
b. For plywood, compute the area of the two (2) face walling then divide the total area by 2.88.
c. For nails : use the same porcedure as of double wall sidings and studs.
30. CEILING JOISTS
a. Compute the area of the ceiling : area x 6.54 for 2" x 2" lumber, area x 9.84 for 2" x 3"
lumber, area x 2.66 for 2" x 2" ceiling hanger.
b. For nails : use same procedure as of baseboard, then multiply by 9.10 for 3" C.W.
31. BASEBOARDS
a. To estimate the bd.ft. of baseboard : lm x 1.09 for 1" x 4" lumber, lm x 1.37 for 1" x 5"
lumber, lm x 1.64 for 1" x 6" lumber.
b. To obtain nails : divide the total bd.ft. by 1,000 then multiply by 5.5 for 1" finishing nails.
32. CEILING BOARDS
a. To estimate the plywood uisng " x 4' x 8' : divide the area by 2.88, for 0.60 x 1.20 lawanit or acoustic board : divide the area by 0.72.
b. For nails : use the same procedure of double walling.
33. ALUMINUM TEE RUNNER
a. Divide the length and width by 0.60 x 1.20 to obtain the no. of pcs of aluminum tee runners.
Then multiply by the length of installation to obtain the total length of aluminum.
b. Note that the commercial length of aluminum tee runner is 20' or 6.0 meters. To obtain pcs :
divide the toatl length by 20' 0r 6.0 in linear meter.
c. For 12 guide wire : total area x 6.54 then divide by 4,000 = roll.
34. FASCIA BOARDS
a. Compute the total linear meter of the end roof all around to obtain total bd.ft. l.m. x 2.73 for
1" x 10", lm x 3.28 for 1" x 12", lm x 2.18 for 1" x 8" fascia boards.
b. For nails : divide the total boarddfeet by 1,000 then multiply by 5.5 for 2" CWN

15 of 47

ESTIMATE MANUAL

35. WOODEN TRUSSES & RAFTERS


a. To obtain the total bd.ft. : take an actual counting of the number of the trusses or rafters
then compute the bd.ft. of its members according to the size & length of the lumber to be used.
b. After computing the bd.ft. of the lumber for one (1) truss or rafter multiply this by the no. of
unit specified in the framing plan.
c. For nails : use the same procedure the multiply by 6.8 fo kilos of 3" - 4" C.W.N.
36. PURLINS
a. To estimate the total bd.ft. of purlins : make an actual counting of the purlins shown in the
roof plans or truss and rafter details. Compute the bd.ft. according to size & length.
b. Or compute the area in sq.m., then multiply : area x 3.271 for 2" x 3" lumber, area x
4.309 for 2" x 4" lumber, area x 5.321 for 2" x 5" lumber, area x 6.335 for 2" x 6" lumber.
c. For cleats : area x 3.44 for 2" x 3", area x 4.571 for 2" x 4", area x 5.458 for 2" x 5",
area x 6.50 for 2" x 6".
37. ROOFING
a. To estimate roofing by area : solve the total area in flat then add the pitch factor ( sum of
1 & 2 percentage ), the total is the slotted area of the roof.
b. Divide the slotted area by factor from the table of G.I. sheet coverage.
c. Another procedure in estimating roofing : length of spread divided by 0.67 or 27" then
multiply by the no. of lapping or row.
c.1. Pitch Factor of Truss and Rafter
NO. 1 SYMMETRICAL
Pitch
Inches
Decimal %
0.32
5.50
0.055
0.36
6.00
0.06
0.40
8.00
0.08
0.45
10.00
0.10
0.50
12.00
0.12
0.55
14.00
0.14
0.60
16.00
0.16
0.70
22.00
0.22
0.80
28.00
0.28
0.90
35.00
0.35
1.00
42.00
0.42
1.20
46.00
0.46

NO. 2 SYMMETRICAL
Pitch
Inches
Decimal %
0.32
2.00
0.02
0.36
3.00
0.03
0.40
4.00
0.04
0.45
5.00
0.05
0.50
6.00
0.06
0.55
7.00
0.07
0.60
8.00
0.08
0.70
11.00
0.11
0.80
14.00
0.14
0.90
18.00
0.18
1.00
21.00
0.21
1.20
23.00
0.23

16 of 47

ESTIMATE MANUAL

1.50

54.00

0.54

1.50

27.00

0.27

d. To obtain metal rivet : pieces of G. I. Sheet x 0.073 = kilo of rivet, for washer : pcs
of G. I. sht x 0.146 = kilo of washer, for strap : pcs og G. I. sht x 12 or 9 = pcs of atrap,
To convert this to plain G. I. sheet, see table of strap.
e. To obtain gutter, ridge roll, valley roll, flashing : divide the total run or spread by factor
: 2.10 for ridge roll, valley roll & flashing, 2.25 for gutter & downspout, for copper rivet : no of pcs of joint multiply by 8 pcs then divide by 50 = no. of box, if in kilo : no.
of pcs divided by 160 = kilo.
f. For nikolite : no. of joint x or 4 or length in foot divided by 24 = kilo
g. For muriatic acid : pcs of nikolite x 10 c.c. = total c.c. of muriatic.
g.1.a. G. I. Sheet coverage - 10" end lap with 2 sides coverlap
Size
Effective
32" x 6'
27" x 5' 2"
x 7'
x 6' 2"
x 8'
x 7' 2"
x 9'
x 8' 2"
x 10'
x 9' 2"
x 12'
x 11' 2"
x 14'
x 13' 2"
g.1.b. Table of Coverage - 12" end lap with 2 side corrugated lap
Size
Effective
32" x 6'
27" x 5'
x 7'
x 6'
x 8'
x 7'
x 9'
x 8'
x 10'
x 9'
x 12'
x 11'
x 14'
x 13'

a.
b.
c.
d.
e.

g.2. Table of Fasteners


G. I. Nails 2"
Lead Washer
G. I. Rivet " x 3/8"
G. I. Rivet " x "
Metal Washer

1.03
1.23
1.44
1.64
1.84
2.24
2.64

Coverage
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

1.01
1.21
1.40
1.60
1.79
2.21
1.61

Coverage
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

102.00
86.00
180.00
157.00
152.00

pcs / kilo
pcs / kilo
pcs / kilo
pcs / kilo
pcs / kilo

17 of 47

ESTIMATE MANUAL

1.
2.
3.
4.

g.3 Table of Rivet Per Sheet of Roofing


6' - 0"
7' - 0"
8' - 9'
10' - 12'

6.00
9.00
9.00
12.00

g.4. Table of Strap Per Plain G. I. Sheet


Purlin Size
Strap Size
2x3
1" x 9"
2x4
1" x 10"
2x5
1" x 11"
2x6
1" x 12"

pcs / sht
pcs / sht
pcs / sht
pcs / sht

Pcs / sht
380.00
340.00
310.00
285.00

pcs
pcs
pcs
pcs

h. For senepa flashing : total run divided by 7' or 2.135 to estimate flashing. The same as
of gutter flashing or no. of gutter = no. of flashing for gutter
SPREADING RATES OF PAINTS
Surface
1. Oil Paint
smooth wood

rough

metal

plaster

hardbrick

softbrick

smooth cement

Gallon
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat

600 sq. ft.


325 sq. ft.
25 sq. ft.
350 sq. ft.
200 sq. ft.
135 sq. ft.
700 sq. ft.
340 sq. ft.
230 sq. ft.
450 sq. ft.
250 sq. ft.
175 sq. ft.
400 sq. ft.
225 sq. ft.
160 sq. ft.
350 sq. ft.
200 sq. ft.
150 sq. ft.
350 sq. ft.

Coverage
55.74
30.19
21.91
32.38
18.50
12.54
65.03
31.59
21.37
41.81
23.23
16.25
37.16
20.90
14.86
32.38
18.50
13.94
32.38

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

18 of 47

ESTIMATE MANUAL

rough cement

2. Oil Paint Flat

smooth wall

plasters

stucco
3. Enamel Paint
4. Exterior Spur
Varnish

smooth with
undercoat
smooth wood

5. Interior Spur
Varnish

smooth wood

6. Shellac

smooth wood
rough wood

7. Shingles Satin
Finish
8. Asphalt Rough
Paint
9. Water Paint

smooth wood

2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
1 coat
2 coats
1 coat
2 coats
3 coats
1 coat
2 coats
3 coats
1 coat
2 coats
1 coat
2 coats
1 coat

rough
1 coat
smooth
1 coat
gold water paint - 5 lbs, powder
smooth
1 coat
calsomine - 5 lbs, powder
plaster
1 coat
wood
1 coat
white wash - 4 to 5 lbs
brick
1 coat
hydrated lime
plaster
1 coat

200 sq. ft.


150 sq. ft.
200 sq. ft.
100 sq. ft.
50 sq. ft.
500 sq. ft.
275 sq. ft.
200 sq. ft.
400 sq. ft.
225 sq. ft.
160 sq. ft.
150 sq. ft.
75 sq. ft.
500 sq. ft.
250 sq. ft.
500 sq. ft.
275 sq. ft.
200 sq. ft.
450 sq. ft.
250 sq. ft.
175 sq. ft.
600 sq. ft.
300 sq. ft.
125 sq. ft.
75 sq. ft.
250 sq. ft.

18.50
13.94
18.50
9.29
4.65
46.25
25.55
18.50
37.00
20.81
14.86
13.94
6.97
46.25
23.23
46.25
23.55
18.50
41.81
23.23
16.25
31.50
22.87
11.16
6.97
23.23

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

150 sq. ft.


100 sq. ft.

13.94
9.29

sq.m.
sq.m.

300 sq. ft.

27.87

sq.m.

400 sq. ft.


250 sq. ft.

37.10
23.23

sq.m.
sq.m.

200 sq. ft.

9.30

sq.m.

300 sq. ft.

27.87

sq.m.

19 of 47

ESTIMATE MANUAL

RATE OF APPLICATION ( TILES )


Granolithic tiles
Terrazo A cement tiles
Laying of Tiles
Rough plaster
Tile laying
Unglazed tiles
Grouted riprap
12" x 12" Vinyl Tiles
Holdtite adhesive
Color powder
" x 2" x 8" Red brick
" x 4" x 4" Vitrified tiles
Pebbles / synthetic
White cement tile filler
Hexagonal Tiles
4" x 4"
3 points hexagonal 2" size
4 points hexagonal 2" size
Cement
4" x 4"
6" x 6"
8" x 8"
12" x 12"
16" x 16"
Tool Finishing cement
sand
Cuirng compound
Curb and gutter
Cement
Sand
Gravel
Virified Tiles mortar bed
cement
sand

0.250
0.250

bag / sq.m.
bag / sq.m.

0.250
0.080
0.250
4.000
12.000
0.250
1.000
12.000
86.000
1.500
0.035

bag / sq.m.
bag / sq.m.
bag / sq.m.
bags/cu.m.
pcs / sq.m.
gal. / sq.m.
kg / sq.m.
pcs / sq.m.
pcs / sq.m.
cans/sq.m.
pcs / sq.m.

400.000
20.000
16.000

pcs / sq.m.
pcs / sq.m.
pcs / sq.m.

100.000
45.000
25.000
12.000
6.250
0.150
0.027
1.000
0.740
2.000
0.380
0.640

pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
bag /sq.m. .
cu. m./sq.m.
gal/sq.m.of 7
cu m.
bags/cu.m.
cu.m.
cu.m.

0.350
0.027

bag /cu.m.
cu.m./sq.m.

NAILS CONVERSION FACTORS

20 of 47

ESTIMATE MANUAL

Joist and sill


Studs
Sheating / sidings
Rafters
Cornice
Shingling
Bevel sidings
Ceiling joist
Flooring
Baseboard
Window trim one (1) side
Don trim one (1) side
Lath
Lattice
Ballusters
Form for concrete

1,000 bd.ft.
1,000 bd.ft.
1,000 bd.ft.
1,000 bd.ft.
1,000 l.ft.
1,000 pcs
1,000 bd.ft.
1,000 bd.ft.
1,000 bd.ft.
1,000 bd.ft.
per side
per side
1,000 bd.ft.
1,000 sq. ft.
1,000 l.ft.
1,000 bd.ft.

11.4 kgs
6.80 kgs
9.10 kgs
6.80 kgs
11.4 kgs
1.80 kgs
8.20 kgs
9.10 kgs
13.6 kgs
5.50 kgs
0.50 kgs
0.30 kgs
3.60 kgs
9.10 kgs
8.20 kgs
15.0 kgs

STANDARD REINFORCEMENT OF NAILS


Thk'ness
Type
Vertical Bars
1.00
1 - #3/8 @ 0.30
0.10 m
2.00
2 - #3 @ 0.30
0.15 m
1.00
1 - #4 @ 0.30
0.15 m
2.00
2 - #3 @ 0.30
0.20 m
3.00
2 - #4 @ 0.30
0.25 m
3.00
2 - #4 @ 0.30
0.30 m
3.00
2 - #4 @ 0.30
0.35 m
3.00
2 - #4 @ 0.30
0.40 m
3.00
2 - #4 @ 0.30
0.45 m
3.00
2 - #5 @ 0.30
0.50 m
3.00
2 - #5 @ 0.30
0.55 m
DOOR JAMBS WITHOUT TRANSOM
1. 0.60 x 2.10 Single panel type
2. 0.65 to 0.90 x 2.10 Single panel type
3. 1.20 x 2.10 Double panel type
4. 1.20 to 1.60 x 2.10 Double panel type
5. 1.80 x 2.10 Double panel type

Horizontal bars
1#3
2#3
1#4
2#3
2#3
2#4
2#4
2#4
2#4
2#4
2#5

1 pc - 2" x 6" x 16'


1 pc - 2" x 6" x 18'
1 pc - 2" x 6" x 18'
1 pc - 2" x 6" x 20'
1 pc - 2" x 6" x 20'

4"
3"
2"
3"
2"
1"
2"
2"
2"
2"
2"
2"
1"
1"

CW
CW
CW
CW
finishing
CW
CW
CW
CW
finishing
finishing
finishing
CW
CW
assorted nails
2" & 4"
CW

Kgs/cu.m.
37.20
49.60
44.20
41.00
44.48
44.20
37.90
42.25
37.50
37.56
41.40

Kgs/sq.m.
3.72
7.44
6.63
8.22
11.12
13.25
13.25
16.90
16.90
18.78
20.70

16.00
18.00
18.00
20.00
20.00

bd.ft.
bd.ft.
bd.ft.
bd.ft.
bd.ft.

21 of 47

ESTIMATE MANUAL

DOOR JAMBS WITH TRANSOM


1. 0.90 x 2.10 with transom of 0.30 x 0.40
2. 1.20 x 2.10 with transom of 0.30 x 0.60
3. 1.40 to 1.60 x 2.10 with transom of
0.30 x 0.60
4. 1.80 x 2.10 with transom of 0.30 x 0.60

FLUSH DOOR FRAME


1. 0.90x2.10 using 2"x3" kiln dried tanguile
2. 0.60x2.10 using 2"x3" kiln dried tanguile
3. 0.70 to 0.85 x 2.10 using 2" x 3" kiln dried
tanguile

1 pc. - 2" x 6" x 24'


1 pc. - 2" x 6" x 8'
1 pc. - 2" x 6" x 18'

24.00
26.00

bd.ft.
bd.ft.

1 pc. - 2" x 6" x 18'


1 pc. - 2" x 6" x 10'
1 pc. - 2" x 6" x 18'
1 pc. - 2" x 6" x 12'

28.00

bd.ft.

30.00

bd.ft.

3 pcs - 2" x 3" x 8'


1 pc. - 2" x 3" x 12'
1 pc. - 2" x 3" x 22'
1 pc. - 2" x 3" x 8'

18.00

bd.ft.

15.00

bd.ft.

3 pcs - 2" x 3" x 8'


1 pc. - 2" x 3" x 10'

17.00

bd.ft.

HOUR RATE PER ITEM OF WORK


Carpentry
Ceiling board on wood runner ( sq. m. )
Frame installation
Board installation
Flush door ( 3' x 7' ) = 21 sq. ft.
Frame - 32.50 bd.ft.
Board - 2 bd.ft.
Glue - 0.10 gal
Fabrication
Flush door ( 2' - 8" x 7' ) = 18.65 sq. ft.
Frame - 27 bd.ft.
Board - 2 bd.ft.
Glue - 0.10 gal
Fabrication
Flush door ( 2' - 4" x 7' ) = 16.3 sq. ft.

2 - Carpenters
1.330 mh / sq.m.
1.000 mh / sq.m.

12.000

mh / pc

14.000

mh / pc

22 of 47

ESTIMATE MANUAL

Frame - 27 bd.ft.
Board - 2 bd.ft.
Glue - 0.10 gal
Fabrication
Flush door ( 3' x 7' ) = 21 sq. ft.
Frame - 12 bd.ft. ( to be added to
flush door bd.ft. )
Fabrication
FRC or FSC with louvers
Louvers - 2 bd.ft.
Fabrication

12.000

mh / pc

1.250

mh / pc

5.000

mh / pc

Door Jamb
Material : 2" x 6" for 3' x 7' door 18 bd.ft.
Fabrication : 1 Carpenter 18 bd.ft. / 4 hr
Installation : 2 Carpenters 18 bd.ft. / 3 hr
Door Jamb with transom of 0.30 lm
Material : 2" x 6" for 3' x 7' door = 22 bd.ft.
Fabrication : 1 Carpenter 22 bd.ft. / 5 hr
Installation : 2 Carpenters 22 bd.ft. / 3 hr
Metal Door
Steel door with #16 cladding = size 3' x 7' 21 sq. ft.
Materials : #16 cladding = 42 sq. ft.
IGSC Frame #12 = 50 l.f.
Fabrication : 2 Steelmen / 12 hr
Equipment : 1 Welding machine
Steel door - 18" x 14" = 253 sq. ft. (2) leaf
Materials : #16 cladding = 504 sq. ft.
C - Frame #12 = 440 l.f.
Fabrication : 4 Steelmen / 56 hrs
Equipment : 1 Welding machine
Tinsmitting
Corrugated G. I. Sheet - 0.685 / sq.m.
Fastener : hook bolt - 4 pcs / 1.47 sq.m.
strap - pcs 1 sht / 792 (1/1.47)
G. I. rivets - 8 pcs. ( 1 kg /180 )
( 1 kg /1.47 )
Lifting : 4 Tinsmith
Installation :

4.500 bd.ft./ mh
3.000 bd.ft./ mh

4.400 bd.ft./ mh
3.600 bd.ft./ mh

24.000
8.000

mh / pc.
hrs / pc

224.000
40.000

mh / pc.
hrs / pc

2.520 sets /sq.m.


0.015 sht /sq.m.
0.030 kg / sq.m.
0.270 mh /sq.m.
1.570 mh /sq.m.

23 of 47

ESTIMATE MANUAL

Ridge roll #26 x 24"


Materials : 8' sht. ( 24/36 ), ( . 33 ) 1
Fastener : copper rivet : 8 pcs (1 kg /160), ( . 33)
Nicolite : (24/36)( . 33)
Labor : bending 3 bend 8( . 33)
Installation :

0.285
0.022
1.300
1.300
2.430

sht /sq.m.
kg. / l.m.
bend /l.m.
bend /l.m.
cu.m./ lm

0.600
0.500
8.000
6.000
0.020

mh /cu.m.
mh /cu.m.
mh /cu.m.
mh /cu.m.
mh /cu.m.

UNIT RATE PER ITEM OF WORK


( man-hour x quantity ) = Total hour = duration
No. of Men
Excavation
1. Common excavation - manual
2. Common excavation - machine
3. Rock - manual & machine
4. Trenching - manual
5. Trenching - mechanical
Backfill
1. Structural backfill - manual
2. Structural backfill - mechanical
3. Hauling of soil
Formworks & concrete works
1. Grade member
- formworks
- concreting
- finishing
2. Suspended member
- formworks
- concreting
- finishing
Rebar work
1. ground floor
2. upper floor
Finishing
1. Plain cement plastering
2. Colored cement finish
3. Pebble washout
4. Granolithic tile finish
5. Marble tiles

5.000 mh /cu.m.
2.000 mh /cu.m.
1.000 mh /cu.m.

2.540
8.540
0.400

mh /sq.m
mh /sq.m
mh /sq.m

3.280
16.700
0.800

mh /sq.m
mh /sq.m
mh /sq.m

0.071
0.080

mh / kg
mh / kg

1.330
1.400
2.860
2.860
2.860

mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m

24 of 47

ESTIMATE MANUAL

6. Vinyl tiles
7. Unglazed tiles
8. Glazed tile
9. Asphalt tiles
Carpentry works
1. Partition including framing
- " thk plywood single wall
- " thk plywood double wall
- wooden louver
- #10 cyclone wire
Doors ( excluding finish hardware )
1. FHC door
2. FSC door
3. Steel sliding door
4. Steel single door
5. Roll up aluminum door - manual
6. Cyclone wire sliding door
Windows
1. Fixed glass on steel frame
2. Fixed G. I. Louver
Fixed asbestos louver
4. Metal louver
Ceiling ( including framing )
1. 1/5" thk plywood
2. Acoustic tile with plywood backing
3. Concealed acoustic with aluminum T - runner
4. 3/16" thk asbestos cutting
Structural steel
1. Light structural steel framing
2. Heavy structural steel framing
Miscellaneous metal
1. Stair, stringer, handrail, tread & grating
Asbestos pipe
1. "
2. "
3. 1" to 1"
4. 1" to 2"
5. 2"

1.670
3.000
0.170
1.670

mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m

0.230
0.314
314.000
0.029

mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m

0.200
0.286
0.860
0.715
0.715
0.715

mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft

0.286
0.429
0.429
0.286

mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft

0.171
0.286
0.286
0.171

mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft

168.000
164.000

mh / m
mh / m

102.000

mh / m

20
20
22.5
25
30

mh / l. ft.
mh / l. ft.
mh / l. ft.
mh / l. ft.
mh / l. ft.

of 100
of 100
of 100
of 100
of 100

25 of 47

ESTIMATE MANUAL

6. 3"
7. 3"
8. 4"
Cast iron pipe
1. 2"
2. 4"
3. 6"
4. 8"
5. 10"
6. 12"
7. 14"
8. 16"
9. 18"
10. 20"
11. 24"
12. 30"
P V C pipes
1. " - "
2. 1" - 1"
3. 1" - 2"
4. 2"
5. 3"
6. 3"
7. 4"
8. 5"
9. 6"

33 mh / l. ft. of 100
35 mh / l. ft. of 100
40 mh / l. ft. of 100
66.80 mh / 100 l. ft.
100.20 mh / 100 l. ft.
150.30 mh / 100 l. ft.
200.40 mh / 100 l. ft.
300.40 mh / 100 l. ft.
317.30 mh / 100 l. ft.
367.40 mh / 100 l. ft.
417.50 mh / 100 l. ft.
467.60 mh / 100 l. ft.
501.0 mh / 100 l. ft.
551.20 mh / 100 l. ft.
626.30 mh / 100 l. ft.
20.22 mh / 100 l. ft.
22.50 mh / 100 l. ft.
25.00 mh / 100 l. ft.
30.0 mh / 100 l. ft.
33.0 mh / 100 l. ft.
35.0 mh / 100 l. ft.
40.0 mh / 100 l. ft.
50.0 mh / 100 l. ft.
75.0 mh / 100 l. ft.

LABOR OUTPUT PER MAN-DAY


Excavation
Backfill
Disposal of soil
Formwork
Rebar
Concreting
Planning concrete transit mixed
Setting anchor bolt
Setting anchor boxes
Demolition of slab, wall

1.00 - 1.35
3.870
4.700
2.50 - 2.67
10.000
0.910
1.200
16.500
4.400

cu.m./ md
cu.m./ md
cu.m./ md
cu.m./ md
kgs / md
cu.m./ md
cu.m./ md
kgs / md
cu.m./ md

26 of 47

ESTIMATE MANUAL

Excavation of cross & clampshell w/ 8 Laborers, 2 opertaors


CHB zoccalo wall
Gravel fill
Slab on fill concrete
Wood post
2nd floor wood post
T & G wood flooring
Plywood partition
Ceiling finishing
Ceiling plywood
Siding framing
L - cut sidings
roof wood framing
G. I. Gutter installation
G. I. Roofing
G. I. Gutter cut and shape
Downspout cut and shape
Downspout installation
Vitrified floor tiles
Installation of base plate
Installation of steel roll up door
Installation of steel sliding door
Placing metal nosing
Installation of asbestos roofing
Installation of aluminum or G. I. Roofing
Roof deck copper cladding
K & O proofing
Fabrication of G. I. Gutter
Cross fabrication
Cross installation
Post
Girts
Plates
Fascia board
Tracing
Boarding
Plywood sheating
Cabinet door

4.400 cu.m./ md
2.400 kgs / md
3.870 cu.m./ md
1.000 cu.m./ md
70.000 bd.ft./ md
75.000 bd.ft./ md
112.000 bd.ft./ md
80.000 bd.ft./ md
44.000 bd.ft./ md
60.000 sq.ft. / md
60.000 bd.ft./ md
112.000 bd.ft./ md
33.000 bd.ft./ md
58.000 l.ft. / md
105.000 sq.ft. / md
50 l. l.ft. / md
27.000 l.ft. / md
60.000 l.ft. / md
1.500 sq.m./ md
45.000 l.ft. / md
15.000 sq.ft. / md
10.000 sq.ft. / md
3.000 steps / md
8.000 sheets/md
10.000 sheets/md
52.000 l.ft. / md
29.000 sq.m./ md
2.300 sheets/md
46.000 bd.ft./ md
40.000 bd.ft./ md
60 - 90 bd.ft./ md
50 - 75 bd.ft./ md
90 - 120 bd.ft./ md
25 - 55 bd.ft./ md
30 - 60 bd.ft./ md
40 - 80 bd.ft./ md
75 - 150 sq.ft. / md
40 - 80 sq.ft. / md

27 of 47

ESTIMATE MANUAL

Doors & windows


Placing wooden door
Installation of sash glass
Placing steel windows
Placing wooden panel door
Placing wooden flush door
Installation of door lockset
Installation of flush bolt
Installation of astragal
Vitrified wall tiles
Painting
Floor hardener
Copper water stop - cut and shape
Copper water stop - cut installation
Installation of sliding door

30.000
75.000
18.000
22.000
28.000
5.000
2.000
80.000
1.340
200 - 300
45.000
60.000
38.000
10.000

sq.ft. / md
sq.ft. / md
sq.ft. / md
sq.ft. / md
sq.ft. / md
sets / md
pairs / md
l.ft. / md
sq.m./ md
sq.ft. / md
sq.m./ md
l.ft. / md
l.ft. / md
sq.ft. / md

LABOR CAPABILITIES PER HOUR


Clearing and grubbing - manual
Clearing undergrowth and trees 12"
Clearing undergrowth and shrubs
Excavation - manual
Coomon earth
Loam or sand
Clay or heavy soil
Rock
Trizzing depth and large common
Excavation - mechanical
Common earth
Rock with jack hammer
Backfilling
Common - mahual
Common backfill - manual
Compacted - crushed stone - mechanical
Compacted - common - manual
Compacted - common - mechanical
Spreading, tempering & grading
Trenching & backfill underground piping
Placing binders - gravel uncompacted

20.000 sq.m./ mh
40.000 sq.m./ mh
0.130
0.760
0.610
0.380
0.150

cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh

15.000 cu.m./ mh
0.060 cu.m./ mh
1.220
0.200
8.000
0.300
30.000
2.090

cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
sq.m./ mh

9.460 sq.m./ mh

28 of 47

ESTIMATE MANUAL

Trenching & backfill underground piping


using excavated material - manual
from 0 - 2 m deep
2 - 3 m deep
3 - 4 m deep
4 - 5 m deep
Back trenching with jack hammer
Trenching & backfill underground piping
using excavated material - mechanical with backhoe
from 0 - 2 m deep
2 - 3 m deep
3 - 4 m deep
4 - 5 m deep
Placing concrete
Slab on fill
Slip form
Floor finish - unhardened
Concrete finish - hardened
Installation of pre - moulded expansion joint
Installation of water stop
Caulking of slab joint
Walls, beams, columns
Slab
Asphalting
Masonry work
4" CHB laying
6" CHB laying
8" CHB laying
Coating & tool finish plaster
Plain cement plastering finish - synthetic & pebbles
Marble slab installation
" x 2" x 8" red bricks
Ceramic glazed tiles
Unglazed tiles
Formwokrs installation
Nails on ground
Nails above 10'
Boxes

0.060
0.040
0.030
0.020
0.070

l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
cu.m./ mh

0.800
0.600
0.400
0.300

l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh

0.200
0.040
1.000
0.700
1.000
1.500
5.000
1.300
1.700
1.250

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
l.m. / mh
l.m. / mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

1.250
1.250
1.250
0.600
0.700
0.500
0.200
0.190
0.230

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

1.000 sq.m./ mh
0.850 sq.m./ mh
0.650 sq.m./ mh

29 of 47

ESTIMATE MANUAL

Columns
Suspended slabs
4" - 18"
18" - 36"
36" - up
Formwork fabrication
Stripping of formwork
Nail on ground
Nails above 10'
Boxes
Columns
Suspended slabs
0 - 18"
18" - 36"
36" - up
General stripping
Reinforcing bars
Fabrication & installation
Metal work
Structural steel
Miscellaneous metal
Fabricstion of anchor bolt
Installation of anchor bolt
Fabrication of embedded item
Laying of RCP - 8 men one team
24" 16 pcs
36" 10 pcs
48"
6 pcs
Underground drainage piping laying
6" concrete pipe
12" concrete pipe
15" concrete pipe
18" concrete pipe
30" concrete pipe
Carpentry works
Plywood partition
Plywood ceiling
T&G flooring & siding

0.850 sq.m./ mh
1.200
0.800
0.600
1.860

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

8.000
1.550
1.950
2.350

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

3.600
2.400
1.850
4.080

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

10.000

kgs / mh

10.000

kgs / mh

10.000
3.000
7.000

kgs / mh
kgs / mh
kgs / mh

2.000 l.m. / mh
1.250 l.m. / mh
0.750 l.m. / mh
0.400
0.250
0.230
0.220
0.120

l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh

0.930 sq.m./ mh
0.700 sq.m./ mh
14.000 bd.ft. / mh

30 of 47

ESTIMATE MANUAL

Ceiling framing
Siding framing
Roof framing
Floor framing
Wood post
Truss fabrication
Truss erection
Girts
Plates
Purlins
Fascia board
Cabinets
Framing
boarding
Plywood sheeting
door
Painting works
Anay paint
Varnishing
Metal works
G. I. roofing
G. I. gutter cut & shape
G. I. gutter installation
Downspout cut & shape
Downspout installation
Backfilling & waterproofing
Painting structural steel framing
FLAT BAR IN KILOS
Thickness
1/8" ( 3 mm )

" ( 6 mm )

5.500
7.500
4.130
9.380
8.750
5.750
5.000
9.380
15.000
7.500
4.380

bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh

7.500
10.000
1.740
0.930

bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh

3.480 sq.m./ mh
2.320 sq.m./ mh
1.220
6.250
2.250
3.380
7.500
2.250
20.000

Width
1"
2"
3"
4"
5"
6"
1"
2"

Length
20'

20'

sq.m./ mh
l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
sq.m./ mh
mh/m ton

Weight
3.870
7.730
11.600
15.460
19.330
23.200
7.730
15.460

kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs

31 of 47

ESTIMATE MANUAL

1/16" ( 2 mm )

3/16" ( 4 mm )

3/16" ( 9 mm )

7/16" ( mm )

9/16" ( 14 mm )

3/8" ( 10 mm )

3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"

20'

20'

20'

20'

20'

20'

23.200
30.930
38.600
46.400
1.930
3.860
5.800
7.730
9.660
11.600
5.800
11.600
17.400
23.200
29.000
34.800
9.660
19.330
29.000
38.000
48.330
58.000
13.530
27.060
40.600
54.130
67.660
81.200
17.400
34.800
52.200
69.600
87.000
104.440
11.600
23.200
34.800
46.400

kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs

32 of 47

ESTIMATE MANUAL

5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"
1"
2"
3"
4"
5"
6"

5/8" ( 15 mm )

7/8" ( 22 mm )

" ( 12 mm )

FORMULA

:
'1
2 x 12

20'

20'

20'

58.000
69.600
19.330
38.660
58.000
77.330
96.660
116.000
27.060
54.140
81.200
108.270
135.330
162.400
15.460
30.930
46.400
61.860
77.330
92.800

kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs

to obtain kilo of flat bar, sample : " x 8" x 20'


x
8
x 20 x 490
'12
= 123.73 kilos
'2.20

Note : 490 is a factor for pounds as to obtain kilo, divide then sum by 2.20 & the answer is in
kilo.
WEIGHT OF BOLTS IN KILOS
Lgth (in)
1"
"
3/8"
2"
0.144
0.245
3"
0.169
0.285
6"
0.194
0.324
7"
0.219
0.364
8"
0.245
0.403
9"
0.270
0.443

Dinmension
"
7/8"
0.363
0.524
0.421
0.601
0.478
0.678
0.535
0.755
0.593
0.852
0.649
0.509

1"
0.723
0.824
0.916
1.027
1.129
1.250

1 - 1/8"
0.978
1.106
1.233
1.361
1.489
1.617

1 - "
1.260
1.448
1.576
1.735
1.893
2.051

33 of 47

ESTIMATE MANUAL

10"
11"
12"
13"
14"

0.295
0.300
0.346
0.37
0.40

0.482
0.522
0.561
0.601
0.640

0.706
0.765
0.820
0.877
0.934

0.986
1.063
1.140
1.217
1.294

INCHES TO MILLIMETER CONVERSION TABLE


1/16"
=
2 mm
3/16"
=
5 mm
6/16"
=
6 mm
7/16"
=
11 mm
9/16"
=
14 mm
11/16"
=
17 mm
13/16"
=
21 mm
15/16"
=
24 mm
2"
=
50 mm
4"
=
100 mm
6"
=
150 mm
8"
=
200 mm
10"
=
250 mm
12"
=
300 mm

1.351
1.455
1.534
1.636
1.737

1.744
1.872
2.000
2.127
2.255

2.209
2.367
2.526
2.684
2.042

1/8"
"
3/8"
"
5/8"
"
7/8"
1'
3"
5"
7"
9"
13"

=
=
=
=
=
=
=
=
=
=
=
=
=

3 mm
6 mm
10 mm
12-13 mm
16 mm
19-20 mm
22 mm
25 mm
75 mm
125 mm
175 mm
225 mm
325 mm

BOLTS REQUIRED FOR TRUSSES


8 pcs " bolts per splice
2 pcs " bolts per end joint
5 pcs " blots per ton joint
1 pc " blots per intermediate o. c.
2 pcs " blots per intermediate at top chord

TABLE OF VALUES FOR STRENGTH OF CONCRETE


( USING NORMAL PORTLAND CEMENT )
IN PERCENTAGE OF 28 DAYS STRENGTH
Days

%'age of 28
Day strength

1
2
3

17.1
34.3
44.4

Days

%'age of 28
Day strength

Days

%age of 28
Day strgth

30
31
32

100.9
101.6
102.4

59
60
61

110.20
110.30
110.40

34 of 47

ESTIMATE MANUAL

4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29

31.5
34.5
59.7
64.1
67.0
70.5
73.5
77.0
78.0
81.2
82.5
85.0
86.7
88.0
89.0
91.0
92.3
93.5
94.8
95.8
96.5
97.4
98.3
99.1
100.0
100.4

33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58

103.0
103.3
103.8
104.2
104.8
105.0
105.5
106.0
106.3
106.8
107.0
107.3
107.5
107.8
108.0
108.2
108.5
108.0
109.0
109.2
109.4
109.6
109.6
109.9
110.0
110.1

62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87

REBAR CONVERSION TABLE


6 mm ( # 2 ) "

110.50
110.60
110.70
110.80
110.90
110.90
111.00
111.00
111.10
111.10
111.10
111.20
111.30
111.40
111.60
111.70
111.80
111.90
112.00
112.00
112.20
112.30
112.40
112.50
112.50
112.60

0.222 kgs. / m
6.00
7.50
9.00
10.50
12.00

1.332
1.665
1.998
2.331
2.664

kgs
kgs
kgs
kgs
kgs

10 mm ( # 3 ) 3/8"

0.616 kgs. / m
6.00
7.50
9.00

3.696 kgs
4.620 kgs
5.544 kgs

35 of 47

ESTIMATE MANUAL

10.50
12.00

6.468 kgs
7.392 kgs

12 mm ( # 4 ) "

0.888 kgs. / m
6.00
7.50
9.00
10.50
12.00

5.328
6.660
7.992
9.324
10.656

kgs
kgs
kgs
kgs
kgs

16 mm ( # 5 ) 5/8"

1.579 kgs. / m
6.00
7.50
9.00
10.50
12.00

9.474
11.843
14.211
16.580
18.948

kgs
kgs
kgs
kgs
kgs

6.00
7.50
9.00
10.50
12.00

14.796
18.495
22.194
25.893
29.592

kgs
kgs
kgs
kgs
kgs

20 mm ( # 6 ) "

2.466 kgs. / m

22 mm ( # 7 ) 7/8"

2.577 kgs. / m
6.00
7.50
9.00
10.50
12.00

15.462
19.328
23.193
27.059
30.924

kgs
kgs
kgs
kgs
kgs

25 mm ( # 8 ) 1"

3.854 kgs. / m
6.00
7.50
9.00
10.50
12.00

23.124
28.905
34.686
40.467
46.248

kgs
kgs
kgs
kgs
kgs

28 mm ( # 9 ) 1 - 1/8"

4.833 kgs. / m
6.00
7.50
9.00
10.50
12.00

28.998
36.248
43.497
50.747
57.996

kgs
kgs
kgs
kgs
kgs

36 of 47

ESTIMATE MANUAL

32 mm ( # 10 ) 1 "

6.313 kgs. / m
6.00
7.50
9.00
10.50
12.00

37.878
47.348
56.817
66.287
75.756

kgs
kgs
kgs
kgs
kgs

36 mm ( # 11 ) 1 3/8"

7.991 kgs. / m
6.00
7.50
9.00
10.50
12.00

47.946
59.933
71.919
83.906
95.892

kgs
kgs
kgs
kgs
kgs

THE WIRE FORMULA


For
:
# 16 tie wire
total rebar kgs.
= Total wire ( roll ) x 45 = in kilo
'3,000
For
:
# 12 tie wire
total fromwork ( sq. m. )
= Total wire ( roll )
'2,000
DECORS
150 x 50 x 2.30 mm
150 x 50 x 3.20 mm
100 x 75 x 3.20 mm

kgs. / ft.
1.52
2.06
2.856

kgs / 20'
31.24
41.20
56.52

kgs. / ft.
1.364
2.500
3.145
5.721
5.570
6.955

kgs / 20'
37.28
50.00
60.90
74.54
111.40
139.10

kgs. / ft.

kgs / 20'

CHANNELS
3/4.4
4/5.4
5/6.7
6/3.2
7/12.25
10/15.50
ANGLES

37 of 47

ESTIMATE MANUAL

1" x 1" x 1/8"


1" x 1" x 3/16"
1" x 1" x "
1" x 1" x "
1" x 1" x 3/16"
1" x 1" x 1"
1" x 1" x "
1" x 1" x 3/16"
1" x 1" x 1/8"
1" x 1" x "
1" x 1" x 3/16"
1" x 1" x 1/8"
2" x 2" x 3/8"
2" x 2" x 5/16"
2" x 2" x "
2" x 2" x 3/16"
2" x 2" x 1/8"
2" x 2" x "
2" x 2" x 3/8"
2" x 2" x 5/16"
2" x 2" x "
2" x 2" x 3/16"

0.364
0.530
0.680
0.870
0.670
0.460
1.060
0.820
0.560
1.260
0.960
0.150
2.140
1.780
1.460
1.110
0.750
3.500
2.680
2.270
1.865
1.400

1.20
10.60
13.60
17.40
13.40
9.20
21.20
16.40
11.20
25.20
19.20
3.90
42.80
35.60
29.20
22.20
15.00
70.00
53.60
45.40
37.30
28.00

kgs. / ft.
1.060
0.820
0.560
1.160
0.890
1.280
0.960
0.650
1.780
1.450
1.110
2.410
2.050

kgs / 20'
21.20
16.40
11.20
23.20
17.80
25.20
19.20
13.00
35.60
29.00
22.20
48.20
47.00

UNEQUAL ANGLES
1" x 1" x "
1" x 1" x 3/16"
1" x 1" x 1/8"
2" x 1" x "
2" x 1" x 3/16"
2" x 1" x "
2" x 1" x 3/16"
2" x 1" x 1/8"
2" x 1" x 5/16"
2" x 1" x "
2" x 1" x 3/16"
2" x 2" x 3/8"
2" x 2" x 5/16"

38 of 47

ESTIMATE MANUAL

2" x 2" x "


2" x 2" x 3/16"
3" x 2" x "
3" x 2" x 7/16"
3" x 2" x 3/8"
3" x 2" x 5/16"
3" x 2" x "
3" x 2" x "
3" x 2" x 7/16"
3" x 2" x 3/8"
3" x 2" x 5/16"
3" x 2" x "
3" x 2" x 1/20"
3" x 2" x 7/16"
3" x 2" x 3/8"
3" x 2" x 5/16"
3" x 2" x "
CARPENTRY WORKS
Type of work
Columns
Batterboard
Pedestal
Beam
Concrete wall
Slab
Scaffolding
Curb & gutter
Coneslab
Sill & lintel
Baseboard
Flooring

Sidings

1.650
1.250
3.860
3.850
3.000
2.550
2.050
4.270
3.770
3.220
2.770
2.227
3.500
3.100
2.680
2.270
1.860

Material
form lumber
form lumber
form lumber
form lumber
form lumber
form lumber
form lumber
form lumber
form lumber
good lumber
good lumber
1" x 3" T&G
1" x 4" T&G
1" x 6" T&G
1" x 8" T&G
1" x 3" S - cut
1" x 4" S - cut
1" x 6" S - cut

33.00
23.00
77.20
69.00
60.00
51.00
41.00
85.40
75.40
65.40
55.40
44.54
70.00
62.00
53.60
45.40
37.20

Coverage
33 bd.ft /.sq.m.
6.50 bd.ft. / sq.m.
9.0 bd.ft. / sq.m.
34.0 bd.ft. / sq.m.
19.0 bd.ft. / sq.m.
25.0 bd.ft. / sq.m.
8.50 bd.ft. / sq.m.
36.0 bd.ft. / sq.m.
18.0 bd.ft. / sq.m.
1.0 bd.ft. / sq.m.
1.25 bd.ft. / sq.m.
16.66 pcs. / l.m.
11.77 pcs. / l.m.
7.87 pcs. / l.m.
5.34 pcs. / l.m.
20.00 pcs. / l.m.
13.16 pcs. / l.m.
7.87 pcs. / l.m.

39 of 47

ESTIMATE MANUAL

1" x 8" S - cut

5.95 pcs. / l.m.

CEILING PARTITION & FORM WORK


Total area ( sq. m. )
= pcs of board 4' x 8'
2.88
Total area ( sq. m. )
= pcs of board 3' x 6'
1.87

LIGHT & HEAVY EQUIPMENTS CAPABILITY TABLE


Item
Dozer

Grader
Payloader
Crane shovel
Shift roller
3W roller
Tractor drwn roller (1-D )
Tanden roller

5-T dump truck

214 -T dump truck

Buggles
Wheel borrow
Water truck
Asphalt dist

Type of work
clearing & grubbing
clearing
stripping
excavating
quarrying
pushing
sub-grading
spreading
loading
loading
static rolling (12 passes 15 cm. lift)
vibratory rolling (4 passes15 cm lift)
static rolling (6 passes 20 cm. lift)
vibratory rolling (6 passes2 m lift)
static rolling (6 passes 20 cm. lift)
vibratory rolling
(6 passes60 cm. lift)
hauling common borrow
hauling SBBC
hauling concrete batch class A
hauling common borrow
hauling SBBC
hauling concrete batch class A
hauling concrete mix
hauling aggregates
hauling concrete mix
watering
spraying asphalt prime coat

180.00
500.00
200.00
25.00
50.00
3.00
300.00
50.00
50.00
50.00
45.00
135.00
34.00
240.00
24.00
72.00

Capability
180 sq.m./ hr.
180 sq.m./ hr.
180 sq.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
180 sq.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.

3.50
3.00
3.00
2.50
2.00
2.00
6.00
2.50
1.75
1000.00
300.00

cu.m./trip
cu.m./trip
batch/trip
cu.m./trip
cu.m./trip
batch/trip
cu.ft./trip
cu.ft./trip
cu.ft./trip
180 sq.m./ hr.
180 sq.m./ hr.

40 of 47

ESTIMATE MANUAL

16-S concerete mixer


Buck crusher
Concrete vibrator
Concrete floor finisher
Scraper towed ( 12 cu.yd
capacity )
Scraper tournapul 45T

mixing concrete
crushing MSG
vibrating concrete mix
finishing concrete floor
hauling ( head capacity )

12.00
30.00
40.00
40.00
11.00

180 sq.m./ hr.


180 sq.m./ hr.
180 sq.m./ hr.
180 sq.m./ hr.
cu.m./trip

hauling ( head capacity )

22.00

cu.m./trip

1 hectare = 2.471 acre


1 acre = 0.4047 hectares
1 acre = 43.56 sq. ft.

HEAVY & LIGHT EQUIPMENTS FOR :


1. CLEARING & GRUBBING
Equipment
Rate & unit/hour
Hand tool
125 mh
350 mh
1750 mh
Tractor 70 to 90 dump
dozer
Tractor 30 to dump
Mover with tractor 30
dump
Tractor 70 to 98 dump
dozer
2. DRAINAGE DITCHES
Equipment
Ditching machine - wheel type

Ditching machine - ladder type


Shoe dragline

34 cu.yd.

Motorized grader

Unit
acre
acre
acre
0.25 acre

Condition

0.50 acre
2.0 acre

pulling disk
cutting weeds & grasses

1.0 acre

light stripping

Unit
1.50 cu.yd.
1.25 cu.yd.
75.0 cu.yd.
50 cu.yd.
45 cu.yd.
45 cu.yd.
75 cu.yd.
450 cu.yd.
300 cu.yd.

light clearing
medium clearing
heavy clearing
medium clearing

Condition
sandy soil
common earth
hard / frozen earth
sandy soil
common earth
hard digging
basing digging
"V" ditches
sandy soil
"V" ditches

41 of 47

ESTIMATE MANUAL

Grader towed type


Shovel at dragline 2 - cu.yd.

3. EXCAVATION
Equipment
Tractor 70 to 90 dbhp with single dozer

300 cu.yd.
125 cu.yd.
200 cu.yd.

Unit
130.0 cu.yd.
80 cu.yd.
50 cu.yd.

Scraper Towed 8 cu.yd. With single dozer

95.0 cu.yd.
80 cu.yd.
60 cu.yd.

Motorized scraper 12 cu.yd. With tractor


70 to 90 dbhp
Pusher

87.93 cu.m.
115 cu.yd.

common earth
common earth
hard digging
easy digging

Condition
50 ft. level haul, common
earth
100 ft. level haul, common
earth
200 ft. level haul, common
earth
500 ft. level haul, common
earth
600 ft. level haul, common
earth
800 ft. level haul, common
earth

68.81 cu.m.

90 cu.yd.

57.30 cu.m.

75 cu.yd.
34.41 cu.m.
45 cu.yd.
75 cu.yd.
125 cu.yd.
200 cu.yd.

80 ft. level haul, common


earth
1000 ft. level haul, common
earth
2000 ft. level haul, common
earth
hard digging
easy digging
hard digging 95.58 cu.m.
easy digging

Unit
300 cu.yd.

Condition
spreading material

Shovel or dragline cu.m.


57.35 cu.m.
Shovel or dragline 2 cu.yd.
152.92 cu.m.
4. EMBANKMENT
Equipment
Tractor 70 to 90 dghp with single dozer
229.38 cu.m.
Rolller, sheepsfoot 2 drum
In - line, towed by tractor

250 cu.yd.
191.15 cu.m.
200 cu.yd.

9" loose layers


8 passes
9" loose layers

42 of 47

ESTIMATE MANUAL

70 to 90 dbhp
Pump, troiler, med., water distributor
Towed type grader
Motorized grader
Roller, sheepsfoot 2 drum in-line towed
by tractor
70 to 90 dbhp

152.92 cu.m.
150 cu.yd.
114.69 cu.m.
350cpm
400 sq.yd.
400 sq.yd.
650 sq.yd.

Roller, road, tandem 5 to 8 tons


Rubberized roller with tractor 30 dbhp
Rotary tiller, tractor 30 dbhp

540 sq.yd.
450 sq.yd.
1,000 sq.yd.
3,000 sq.yd.
1,750 sq.yd.

Pump trailer, mounted water distributor

350 gpm

5. BASE COURSE CONSTRUCTION


Equipment
Tractor, 70 to 90 dbhp, with single
dozer, 229.38 cu.m.
Motorized grader 152.92 cu.m.
Motorized grader 344.07 cu.m.
Roller road, tandem 5 to 8 tons
Rubber type tractor roller 30 dbhp
Roller road, tandem 5 to 8 tons
Trailer mounted pump, water distributor

6. SURFACE TREATMENT
Equipment
Tractor sweeper 30 dbhp

Trailer mounted distributor

10 passes
9" loose layers
12 passes
moisture varies with
materials
scarify & shape
scarify & shape
60" layer, 8 passes
60" layer, 10 passes
60" layer, 12 passes
3 mph, 5 passes
3 mph, 5 passes
6" depth, 3 mph,
6 passes
moisture varies with
materials

Unit
300 cu.yd.

Condition
spread materials

200 cu.yd.
450 cu.yd.
300 cu.yd.
1500 cu.yd.

spread materials
sharing materials
compacting gravel
compacting grade,
10 passes
compacting macadam
moisture varies with
materials

75 cu.yd.
350 gpm

Unit
2,500 sq. yd.
2,500 sq. yd.
1,250 sq.yd.

Condition
sweeping, compact base
0.10gal / sq.yd. 24 ft.
spray
0.10 gal / sq.yd. 24 ft.
spray

43 of 47

ESTIMATE MANUAL

Concrete spreader 20 to 25 ft.


Aggregate spreader, traction powered
Roller, road tnadem 5 to 8 tons

200 l.ft.
5,000 sq.yd.
3,000 sq.yd.

Rubber-tired tractor roller 30dbhp

3,000 sq.yd.

Trailer mounted distributor

1,250 sq.yd.

Motorized grader

150 sq.yd.

Rotary tiller tractor 30dbhp


Travel -plant asphalt mixer

100 cu.yd.
120 tons

Roller, road tandem 6 to 8 tons

1,500 sq.yd.

Rubber-tired tractor roller

3,000 sq.yd.

Concrete mixer 14 cu.ft.

20 cu.yd
10 cu.yd
40 cu.yd
100 ton ft.
200 l.ft.

34 cu.ft.
Asphalt finisher 12 ft.
Concrete finisher 20 to 25 ft.
7. AGGREGATE PRODUCTION
Equipment
Rate & unit/hour
Crusher 2 units
25 tons / hr

crusher 9 units

150 tons / hr

Unit
15 tons
20 tons
30 tons
60 tons
100 tons
240 tons

Compressor 105 cfm


Drill, rock 350 lbs. class

105 cfm
90 cfm
20 l.ft.

capacity depnds on payer


spreading coned aggregates
rolling aggregate 3 mph
3 passes
rolling aggregate 5 mph
5 passes
0.20 gal / sq.yd. 24 ft.
spray
mixed in place, 2 in
bituminous materials
mixing bituminous mat'l
mixed in place by travel
plant
rolling pavement, 3 mph
6 passes
rolling pavement, 5 mph
5 passes
1 batch every 3 minutes
1 batch every 3 minutes
1 batch every 1.75 min
finishing plant mix mat'l
capacity depends on payer

Condition
1" screened aggregate
1" screened aggregate
1" screened aggregate
1" aggregate screened
mashed
1" aggregate screened
mashed
3" aggregate screened
mashed
at sea level
5,000 ft. above sea level
1" hole mix 16 ft. deep
requires 40 to 60 cfm of

44 of 47

ESTIMATE MANUAL

45 lbs. class

30 l.ft.

Bucket type leader type


Roller sheepsfoot
( 2 drums in line )

150 cu.yd.
250 cu.yd. / hr
200 cu.yd. / hr
150 cu.yd. / hr

9" loose layer, 8 passes


9" loose layer, 10 passes
9" loose layer, 12 passes

8. SUBGRADE PREPARATION
Equipment
Rate & unit/hour
Grader - scarify & shape 334.40 sq.m. / hr
Road roller 5 - 8 tons

Unit
2.60 days
3.20 days
100 sq.yd.
1.10 days

83.16 sq.m. / hr

9. BASE COURSE CONSTRUCTION ( 10 cm thick )


Equipment
Rate & unit/hour
Unit
Grader - spreading of
153 cu.m. / hr
day
materials
Grader - shoving of
376 sq.m. / hr
2.0 days
surface
Raod roller 5 - 8 tons
connecting gravel 250 sq.m. / hr
3.0 days
connecting ma57.0 cu.m. / hr
1.0 days
cadam (0.60 thk)
cu.ft. x 0.02832
cu.yd. x 0.7646

air
1" hole mix 16 ft. deep
requires 70 to 90 cfm of
air
from stock pile

=
=

Condition
7.0 surface / k.m.
9.0 surface / k.m.
7-9 surface / k.m, 3 mph
6 passes

Condition
1.0 day
3.0 days

3.70 days

cu.m.
cu.m.

10. CAPABILITIES OF MANUAL LABOR


Unit
1 man

Type of work
excavating loam or sand
exacavating clay or heavy soil
excavating rock
backfilling
spreading, tamping & grading

Capability
0.76
0.61
0.38
1.22
2.09

cu.m. / hr
cu.m. / hr
cu.m. / hr
cu.m. / hr
sq.m. / hr

45 of 47

ESTIMATE MANUAL

team ( 8 men )

Placing ascombre fill


placing binders
clearing undergrowth & tree 12"
clearing undergrowth & small bush
laying of 24" rcp
laying of 36" rcp
laying of 48" rcp

TABLE - I : POL - CONSUMPTION OF ORDINANCE


EQUIPMENTS
Fuel
OE30
Item
type of fuel
( 9 liters )
( gal )
Utility truck T, 4' x 4'
gasoline
0.14
0.0012
Truck, T, 4' x 4'
gasoline
0.28
0.0012
Truck, 11/T, 4' x 4'
gasoline
0.33
0.0025
Truck, 11/T, 6' x 6'
gasoline
0.33
0.0025
Truck, 22/T, 6' x 6'
gasoline
0.43
0.0025
Trk, wrecker, 4 T, 6' x 6'
gasoline
0.80
0.0037
Dump truck , 5 T
gasoline
0.95
0.0162
Truck, 5 T, 6' x 6'
gasoline
0.80
0.0050
Truck, medium wrecker,
gasoline
0.90
0.0050
5 T, 6' x 6'
Primemover truck, 6 T
gasoline
1.08
0.0062
Primemover truck, 7 T
gasoline
0.95
0.0062
Tractor truck, 5 - 6 T
gasoline
0.80
0.0150
( 10 ) semi trailer
Truck crane
gasoline
1.61
0.0030
Tractor truck, 12 T
gasoline
2.37
0.0112
TABLE - II : POL - CONSUMPTION OF ENGINEERING
EQUIPMENTS
Fuel
OE30
Item
type of fuel
( 9 liters )
( gal )
Earthe auger
gasoline
10.00
0.03
Air compressor, 15 cfm
gasoline
2.30
0.02
Air compressor, 210 cfm
gasoline
20.00
0.04
Air compressor, 312 cfm
diesel
15.00
0.01
Crane, cu.yd.
gasoline
15.00
0.06

4.78
9.46
20.00
40.00

cu.m. / hr
cu.m. / hr
sq.m. / hr
sq.m. / hr
16 pipes / 8 hrs
10 pipes / 8 hrs
6 pipes / 8 hrs

GO90
( gal )
0.0100
-

GAA
( lb )
0.0025
0.0037
0.0061
0.0050
0.0075
0.0120
0.0166
0.0132
0.0062

0.0012
0.0112
0.0075

0.0037

0.0087
0.0162

GO90
( gal )
0.03
0.03
0.03

GAA
( lb )
0.06
0.05
0.04
0.05

46 of 47

ESTIMATE MANUAL

Crushing plant, 3 units,


50 T / hr
Ladder type ditching
machine
Bituminous distributor,

gasoline
diesel
gasoline

7.50
20.00
20.00

0.53
0.06

0.35
0.09

0.25
0.01

gasoline

15.50

0.04

0.03

0.05

Water distributor, 1000


gal. capacity
Percussion drill
Electric gen, sets-5 KW
Electric gen, sets-15 KW
Electric welder
Road motorized grader
Asphalt heater

gasoline

15.50

0.04

0.03

0.05

gasoline
gasoline
gasoline
gasoline
diesel
gasoline
diesel
diesel
diesel
gasoline
gasoline
gasoline

10.00
13.00
11.00
5.00
15.00
22.00
10.00
75.00
20.00
38.00
76.00
3.00

0.03
0.05
0.05
1.00
0.02
0.02
0.04
0.02
0.03
0.03

0.03
0.03
0.03
0.03

0.06
0.06
0.02
0.03
0.06
0.01
0.03
0.04

gasoline
gasoline
gasoline
gasoline
gasoline
gasoline
gasoline
gasoline
gasoline
gasoline

15.00
13.00
6.00
23.00

0.03
0.03
0.02
0.02

0.03
0.03
0.03
-

0.03
0.01
0.03
0.03
0.03
0.03
0.05
0.06
0.05
-

diesel

2.50

0.01

0.07

0.05

Asphalt kettle, 185 gal.


Bucket loader
Fabricator
Concrete mixer, 16 S
Pump centrifugal, 340
GPU
Raod roller, 3 W lot
Road tandem roller
Pneumatic roller, 50 T
Pneumatic roller, 13 W
Sheepfoot towed roller,
Roates, 3 tooth, H - 5
Scraper, towed, cu.yd.
Scraper, towed, 18 cu.yd.
Shop equipment, trzd.
Tool set Nr 3 sher shop
11 KW gen.
Tractor dozer L- 7,
D - 8, D - 6

47 of 47

You might also like