Particular Specification For Reinforced Massive Concrete Structures
Particular Specification For Reinforced Massive Concrete Structures
Definition
Reinforced Massive Concrete Structures include pile caps, transfer plates and structural
members where the least dimension exceeds 1.5 metres.
2.
Method Statement
At least two months before commencement of concreting, the Contractor shall submit a
method statement for temperature control. The information to be submitted shall include,
but not be limited to, the following:
3.
(a)
concrete mix details including heat of hydration and specific heat characteristics
of the cementitious constituents, expected concrete temperature rise and the
proposed initial concrete placing temperature;
(b)
(c)
(d)
(e)
(f)
(g)
(h)
analyses and calculations to prove that the proposals will meet the requirements of
the Contract.
Page 1 of 4
4.
5.
6.
(a)
The Contractor shall employ effective means such as shading the aggregates, precooling mixing water and adding flaked ice to ensure the temperature of concrete
prior to and including the time at which it is placed shall not exceed 25 oC.
(b)
After the concrete has been placed, its peak temperature in any part of the
structure shall not be permitted to rise above 85 oC.
(c)
After the concrete has been placed, the maximum temperature difference between
a point at the centre of a concrete section and the adjacent surface shall not be
greater than 20 oC times the shortest distance, in metres, between the concrete
section centre and the surface.
(d)
Page 2 of 4
(a)
(b)
The Contractor shall continuously compare the real time results of the on-going
temperature monitoring with the predicted values and make appropriate
adjustments to the temperature control methods used on current and subsequent
pours to ensure compliance with this Particular Specification.
(c)
The temperature of the hydrating concrete shall be measured for each pour until
21 days after pouring using a sufficient number of calibrated thermocouples to
demonstrate that the requirements of Clause 5 have been achieved, within a 2
o
C accuracy.
(d)
(e)
(f)
(g)
After installation of the thermocouples within the pour and immediately prior to
concreting, the thermocouples shall be checked by comparing the relative ambient
temperature readings. Any damaged or malfunctioned thermocouple shall be
replaced prior to the commencement of concreting.
(h)
(i)
The output from the data loggers shall be down loaded daily by the Contractor. A
copy of the data shall be given to the SO immediately after down loading in an
agreed electronic and hard copy format.
(j)
Within 7 days from the completion of the temperature monitoring period the
Contractor shall submit a report. The report shall include the individual tabulated
Page 3 of 4
at all stages the temperature differential limits specified in Clause 5(c) will not be
exceeded at any one time;
(b)
(c)
the stresses in the concrete structure due to temperature changes under strain will
not induce tension cracks;
(d)
the construction joint will be treated to ensure monolithic action between the
different pours.
(e)
the temperature differentials between two adjacent pours will comply with Clause
5(d).
(f)
the temperature of concrete prior to and including the time at which it is placed
will comply with Clause 5(a).
Page 4 of 4