Topic 10
Topic 10
Topic 10
opic 10
Completion
Topic 10 (Completion).doc
Table of Contents
TABLE OF CONTENTS ........................................................................................................................... 2
LECTURE OBJECTIVES. .......................................................................................................................3
INTRODUCTION ......................................................................................................................................3
COMPLETION (AS 4000 CLAUSES 34 & 37) .......................................................................................3
PRACTICAL COMPLETION .......................................................................................................................3
DETERMINATION OF THE CONTRACT .....................................................................................................6
REPUDIATION OF THE CONTRACT ..........................................................................................................7
SELF ASSESSMENT QUESTIONS ........................................................................................................8
BIBLIOGRAPHY ....................................................................................................................................10
Page 2 of 10
(04/06/99)
Topic 10 (Completion).doc
Lecture Objectives.
Introduction
In law most construction projects are entire contracts, that is the Contractor
undertakes to construct the entire building and is bound to do everything required of it
to attain completion of the building as specified. In principle the Contract is not
complete and cannot be handed over until even the smallest items are complete. The
concept that a minor item of work or a single material component should preclude
hand over of a complicated building is however avoided in most standard forms of
contract with the use of the expression Practical Completion. AS 4000 is no exception.
Page 3 of 10
(04/06/99)
Topic 10 (Completion).doc
Completion Dates
The Date of Practical Completion is important to the parties to the contract for the
following reasons:
it signifies the Contractors relief from Liquidated Damages (LDs) if they are
accruing or potential liability if not commenced;
the Principal is entitled to take possession of the site, and accordingly is required
to take out necessary insurances; and,
the Defects Liability Period (DLP) commences.
The Superintendent upon request from the Contractor inspects the building and lists
any items that require attention to meet the specification. The Superintendent is also
required to ensure that the Contractor had fulfilled its obligations in terms of supply
and service arrangements of components in compliance with its contractual
obligations.
Once satisfied that these criteria have been met and that the building complies with the
contract documents and is substantially fit for the purpose of its design and intended
use, the Superintendent will issue a Certificate of Practical Completion to the
Contractor.
The resulting PC certificate means that the final instalment of the payment for work
carried out is due to the Contractor and part of the retention money (the % mentioned
in the Appendix at item 13 or 50% if no figure mentioned) is released to the Contractor.
This retention is represented by a cash adjustment to the payment certified or
confirmation to the bank that provided the guarantee that the first moiety (or half) of it
may be released to the Contractor.
Curtin University of Technology
School of Architecture, Construction and Planning
Page 4 of 10
(04/06/99)
Topic 10 (Completion).doc
The date of completion of the works is correctly referred to as the Date of Practical
Completion and often varies from the Date for Practical Completion for numerous
reasons. Typically, a delay due to the Contractors failure to perform is a cited reason
for the difference between the two dates. If the date of PC is later than the date for PC,
Liquidated Damages may become payable from the Contractor to the Principal.
The Date For Practical Completion is the specified completion date agreed at tender
time, or, failing the insertion of a date in the contract the works are required to be
completed in a reasonable period of time. The date for completion is therefore set at
the outset of the contract. It is a defined period that commences upon occupation of
the site by the Contractor (the date of possession). The Date For Practical Completion
may only be amended in writing by the Superintendent by the issue of an extension of
time (EoT). The new date becomes the revised Date For Practical Completion.
Page 5 of 10
(04/06/99)
Topic 10 (Completion).doc
Principal must also advise the Contractor that it intends to withhold LDs. The LDs
may be deducted progressively to ensure that an overpayment does not take place.
Legally when a defect occurs the Contractor is in breach of contract but the Defects
Liability clause (35) allows the Contractor to mitigate the effect of the breach and
permit it to carry out the making good itself. The Contractor may elect to not carry out
a specific defect, in which case a deduction may be made to the contract sum for an
appropriate amount of money, usually the cost of having someone else rectify the
defect.
Either party may determine the contract under certain circumstances that are defined
within the standard forms of contract but it must be seen as a last resort as it leads to
financial cost and lost time to all parties concerned. If determination should take place
for whatever reason the Superintendent is required to establish the full scope of the
work that has been carried out. A thorough survey of the work is required so as to
have a complete record in the likely event of litigation. All site and building levels
must be checked and photographs of the completed works should be taken as a record.
Curtin University of Technology
School of Architecture, Construction and Planning
Page 6 of 10
(04/06/99)
Topic 10 (Completion).doc
Other problems to be considered would be those of insurances and the viability of subcontractors.
Affirm the Contract this is a positive action declaring that they do not consider
the contract to be at an end. They may then insist on the work being done or claim
for damages. Once done the party affirming cannot rescind.
Or
If repudiation is opted for then both parties are released from the contract. Certain
terms do remain liabilities, liquidated damages and arbitration for example. Most
contracts make provision for determination.
The innocent party must elect to adopt one remedy or the other it is not permitted to
combine the best elements of the two.
Page 7 of 10
(04/06/99)
Topic 10 (Completion).doc
3. What is your definition of the Date of Practical Completion? How does this differ
from the above, Q2?
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
______________________________
Page 8 of 10
(04/06/99)
Topic 10 (Completion).doc
4. What reasons do you think could account for the difference between the dates as
defined in Q2 and Q3?
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
______________________________
6. The innocent party must elect to adopt one remedy or the other it is not permitted
to combine the best elements of the two.
A person who seeks the favourable remedies provided by a contractual
determination clause must follow the specified procedures. In failing to do
so it may have to rely on common law rights instead. This can only be done
if the breach is a repudiatory one.
Where a clause in a contract provides for determination in circumstances
where the common law does not, the innocent party can only take
whatever remedy the contract offers.
Thomas Feather & Co. (Bradford) Ltd. v. Keighley Corporation (1953) 53 LGR 30
provides a further example of this;
The local authority provided that in the event that unauthorised subcontracting took place the authority could either determine the contract or
claim $100.00 liquidated damages. When Feather & Co breached this
condition the authority determined the contract and employed another to
complete the work. It then sued the Feathers for the additional expense
which amounted to $21,000.00. Feathers counter claimed that only LDs
should apply for such a minor breach.
What decision do think the court arrive at[GAH1]?
Page 9 of 10
(04/06/99)
Topic 10 (Completion).doc
Bibliography
Bailey, I. H. Construction law in Australia 2nd edition, North Ryde, N.S.W. LBC
Information Services, 1998.
Standen, D,. Construction Industry Terminology 3rd edition Melbourne RAIA Practice
Services. 1993.
Page 10 of 10
(04/06/99)