Energy Quiz
Energy Quiz
Energy Quiz
Where VLL is the receiving end voltage in kV and Zo is the surge impedance in ohms, and SIL is the
surge impedance loading or natural loading of the line
The above expression gives a limit of the maximum power that can be delivered by a line and is
useful in designing the transmission line. This can be used for the comparison of loads that can be
carried on the transmission lines at different voltages
From the above expression power transmitted through a long transmission lines can be either
increased by increasing the value of the receiving end line voltage (V LL) or by reducing the surge
impedance (Zo). Voltage transmission capability is increased day by day, this is the most commonly
adopted method for increasing the power limit of the heavily loaded transmission line. But there is a
limit beyond which is neither economical nor practical to increase the receiving end line voltage
By applying some methods such as introducing series capacitors (capacitors in series with the
transmission line) or shunt capacitors (capacitors in parallel with transmission lines) can be used to
reduce the value of surge impedance (Zo).
Surge Impedance Loading (SIL) can be increased by reducing the Surge impedance of the line. From
the above expression Zo can be decreased by either increasing the capacitance (C) of the line or by
reducing the inductance (L) of the line. Inductance (L) of the transmission line cannot be reduced
easily
By use of the series capacitors surge impedance (Zo) and the phase shift get reduced due to
decrease in the line inductance (L). This improves the system stability limit. These capacitors also
helps in reducing the line drops and so voltage variations. But this method causes difficulty under
short circuit conditions of system as capacitors will get damage.
By use of shunt capacitors though the surge impedance (Z o) is reduced but the phase shift of the
system increases this affects the poor stability in the system specially when synchronous machines
are under the load. This method is not employed in long transmission lines specially when stability
limits are present
Reduced operations and management costs for utilities, and ultimately lower power costs for
consumers
Reduced peak demand, which will also help lower electricity rates
Increased integration of large-scale renewable energy systems
Better integration of customer-owner power generation systems, including renewable energy
systems
Improved security
Smart grids will make use of new design concepts and advanced materials in system components like
transformers and circuit breakers to improve efficiency, safety and operational performance.
Widespread use of power electronic devices will help maximize performance of existing assets and
make the grid more resilient in the event of disruptions. In general, smart grid technology can be
grouped into five key areas; Integrated communications, Sensing and measurement which includes
Smart meters and Phasor measurement units, Advanced components like Distributed power flow
control and Smart power generation using advanced components, Advanced control and Improved
interfaces and decision support. Implementation of smart grids will lead to reliable operation and
effective performance of distributed generations based on renewable energy resources, as well as
enabling better use of existing power stations and improving the efficiency of industries. Moreover,
this technology causes better operation of power grids and addresses the power quality issues
through using advanced controllers, power electronic equipments and economical and managerial
decisions making.
Electrical systems will undergo a major evolution, improving reliability and reducing electrical losses,
capital expenditures and maintenance costs. The smart grid is the future for electrical systems, as it is
designed to meet the four major electricity requirements of our global society: capacity, reliability,
efficiency and sustainability.
KSEB
Kerala State Electricity Board commenced functioning on 31-3-1957 After Noon as per order no. EL16475/56/PW dated 7-3-1957 of the Kerala State Government. It had 5 members with Sri K P
Sreedharan Nair as Chairman. All the staff belonging to the erstwhile Electricity Department of Thirukochi was transferred to the Board.
After the enactment of Electricity Act, 2003, KSEB has been functioning as the State Transmission
Utility (STU) and a distribution licensee w.e.f 10.12.2004 under section 172(a) of the Electricity Act,
2003.Accordingly, with effect from 25.09.2008, all the functions, properties and all interests, rights in
properties, all rights and liabilities of the Board are vested in the State Government. All these
functions and undertakings of the Board as vested in Government shall be re-vested in a company to
be incorporated as a fully owned Government company under the Companies Act, 1956.
Generation
At the time of its inception, in 1958, the KSEB had an installed capacity of 109.5 MW, with a total
annual internal generation of 441.35 MU.At present, KSEB has a total installed capacity of 2234.4
MW(as on 31.10.2011) including the two Diesel power plants at Brahmapuram and Kozhikode.
Transmission
The Kerala power system grid is connected to the Southern Region Transmission system through two
400kV double circuit lines. They are (1) Udumalpet- Madakkathara line and (2) ThiruneveliPallippuram( Trivandrum) line. There are 6 major inter-state transmission lines. at 220KV level and
110KV level.The transmission sector of KSEB comprises of two zones namely North and South, and a
System Operation wing each headed by a Chief Engineer. The System Operations wing with
headquarters at Kalamassery is responsible for the real time management of Kerala Power System
and also the activities connected with communication and protection fields.
Contact information email: ceso@sldckerala.com
Distribution
KSE Board distributes electricity in the State of Kerala except in the Thrissur Municipal Corporation
and Munnar (Kannan Devan Hills). For operational conveniences the distribution wing is divided into
three zones namely South, Central and North
IT Wing Of KSEB
Kseb has its own IT development Team working at Kozhikode, Ernakulam and Thiruvanathapuram
and developed many applications to support daily activities, Billing and HRM . ORUMA, SARAS and
HRIS are some of these softwares.
SOP
Standards of Performance of KSEB has set new dimensions to customer service. Click HERE
Kerala State Electricity Board Ltd (KSEBLtd) is a public sector agency under the Government of
Kerala, India, that generates, transmits and distributes the electricity supply in the state. Established
in 1957, the agency comes under the authority of the Department of Power.
The Kerala state Electricity board started functioning under the direction of a newly formed Kerala
government, on 31 March 1957. The first governing body consisted of 5 members, and was headed
by the Chairman K P Sreedhara Kaymal. The staff of the erstwhile Department of Electricity of the
Thiru-Kochi state were transferred to the KSEB.
At the time of its inception, in 1958, the KSEB had an installed capacity of 109.5 MW, with a total
annual internal generation of 441.35 MU. Over the years, as demand increased, the board has
imported power from neighbouring states and private entities. The board also set up several more
hydel power stations within the state. As of 2008, the KSEB Ltd has a total installed capacity of State
to 2657.24 MW and a consumer base of over 91,59,399. As per the Central Electricity act 2003,KSEB
was converted to Kerala State Electricity Board Limited in 2014. The original KSEB was dissolved and
its assets and liabilities were transferred to the government initially and then transferred to the newly
formed company KSEB Limited
The Kerala State Electricity Board, constituted by the Government of Kerala, by order dated 7.3.1957,
under the Electricity (Supply) Act, 1948 is in the business of Generation, Transmission and
Distribution of electricity and striving to provide quality electricity at affordable cost to all classes of
consumers in the state of Kerala.
As per section 172 (a) of the Electricity Act 2003 and as mutually decided by the Government of India
and Government of Kerala, KSEB has continued as Transmission utility and Distribution licensee till
24-09-2008.
In exercise of powers conferred under sub-sections (1), (2), (5), (6) and (7) of section 131 of the
Electricity Act, 2003, State Government vide the notification G.O (Ms).37/2008/PD dated 25
September 2008 has vested all functions, properties, interests, rights, obligations and liabilities of
KSEB with the State Government till it is re-vested the same in a corporate entity.
Accordingly, KSEB has been continuing all the functions as a Generator, State Transmission Utility
and a Distribution Licensee in the State. Kerala State Electricity Board commenced functioning on 313-1957 After Noon as per order no. EL1-6475/56/PW dated 7-3-1957 of the Kerala State Government.
It had 5 members with Sri K P Sreedharan Nair as Chairman.
All the staff belonging to the erstwhile Electricity Department was transferred to the Board. The Board
consisting of the Chairman and the Members is the Supreme Governing Body. The State Government
by their notification EL3-9345 dated 21-2-1958 constituted the State Electricity Consultative Council
under section 16 of the Electricity Supply Act. The Council functions as consultative body and the
Board is required to place before the council the annual financial statement and supplementary
statements if any before submitting such statements to the State Government.
The Board consisting of the Chairman and the Members is the Supreme Governing Body. The Board
consists of seven members and is headed by the Chairman. The Government of Kerala and KSE
Board issued orders for the restructuring of KSE Board into profit centers in April 2002. Members
head the profit centers. There is a Corporate Office to co-ordinate and control the activities of the
Board.
After the enactment of Electricity Act, 2003, KSEB has been functioning as the State Transmission
Utility (STU) and a distribution licensee w.e.f 10.12.2004 under section 172(a) of the Electricity Act,
2003. The Central Government had approved the continuation of KSEB as a State Transmission
Utility & Licensee only up to 24.09.2008. In exercise of the powers conferred under sub-sections (1),
(2), (5), (6) and (7) of section 131 and section 133 of the Electricity Act 2003 (Central Act 36 of 2003)
the Government of Kerala had issued notification vide G.O. (MS) No.37/2008/PD, Dated,
Thiruvananthapuram, 25 September 2008 for the purpose of vesting of functions, properties, interests,
rights, obligations and liabilities of the Kerala State Electricity Board in the State Government on such
terms as agreed to by the Kerala State Electricity Board and the State Government and revesting
thereof by the State Government in a Corporate entity and also for the transfer of Personnel of the
Board to the Corporate entity and for determining the terms and conditions on which such transfers
and vesting shall be made. Accordingly, with effect from 25.09.2008, all the functions, properties and
all interests, rights in properties, all rights and liabilities of the Board are vested in the State
Government.
KSEB was converted to Kerala State Electricity Board Limited in 2014. The original KSEB was
dissolved and its assets and liabilities were transferred from government to the newly formed
company KSEB Limited.
The first generating station of the state was set up on the right bank of a tributary of River Periyar in
1940. It was a hydroelectric project and that tributary named Mudirappuzha continues to be the site of
large a number of hydroelectric projects in the state. After a spell of 17 years, the attention of the state
authorities turned to newer forms of generating energy. The Government of Travancore set up a
facility to supply electricity to the households of Thiruvananthapuram town. In 1927, a Thermal Power
Station was established under government ownership at Thiruvananthapuram for production of
electrical energy on commercial lines. Three oil engine generators, of a capacity of 65 kW each, were
installed and commercial production started in 1929.This station was located at Thampanoor at
Thiruvananthapuram. An Electrical Wing under the State Public Works Department was entrusted with
the administration of the scheme. The next significant development was the formation of a separate
department for electricity in 1932 by His Highness Sri Chithirathirunal Maharaja and his Diwan Sir C P
Ramaswami Iyer. The formation of the Electricity Department paved the way for notable
developments in the field. Thermal generating stations were set up at Kollam, Kottayam and Nagerkoil
in 1934. By that time, the possibilities of hydroelectric generation attracted the attention of the
technologists and the authorities. Kerala being a land of mountains and rivers, it presented a fertile
field for hydroelectric generation. The vast potential for hydroelectric generation in the state prompted
the state authorities to take steps to establish stations for hydroelectric generation. The first of these
ventures was the Pallivasal Hydroelectric Project, the construction of which was started in 1933. The
first stage of the project was commissioned in 1940. Its capacity was 13.5 mW. By that time, a
comparable electric transmission network had also been completed with 66 kV substations at
Alappuzha, Mavelikkara, Kothamangalam, Kundara, Kalamasserry, Viyyur, Aluva, and
Thiruvananthapuram, which were also commissioned in 1940 itself during April -May months The
Kerala state Electricity board started functioning under the direction of a newly formed Kerala
government, on 31 March 1957. The first governing body consisted of 5 members, and was headed
by the Chairman K P Sreedhara Kaymal. The staff of the erstwhile Department of Electricity of the
Thiru-Kochi state were transferred to the KSEB.
Source: Wikipedia
KSEB News
Payment of Gratuity Act, 1972 Implementation in KSE Board Clarification Orders
vestment of assets, in the Cabinet Meeting on 30/05/2012 and informed that all outstanding issues
with employees will be cleared before re-vestment. Many thanks to Honble Chief Minister, Sri.
Oommen Chandy for his bold and right decision to protect the interest of employees of KSE
Board before formation of the company
KSEB had filed the proposals for revising the existing tariff structure of all categories of
consumers including Bulk Supply to other Licenseesbefore the Honble Commission on 30-032012. In the petition, KSEB has requested for permission to submit the re-categorization of certain
categories of consumers as per the direction of the Honble Commission, orders of CGRF/
Ombudsman, recommendation from field offices etc as an addendum to the petition. Further,
Honble Commission vide the letter No. 507/ CT/ KSERC/2012/256 dated 03-04-2012 has directed
to submit the following proposals also to be considered along with the petition.
(1) The proposals of re-categorization of different categories of consumers.
(2) The proposals for Transmission charges, Wheeling charges and cross subsidy surcharge for
open access consumers.
(3) Proposals for TOD tariff for LT consumers with connected load above 10kW. For more
details [download id=146]
General Transfer Probable list has been published in KSEB site for all eligible cadres
Consumer Grievance Redressal forum -CGRF of KSEB on web http://cgrf.kseb.in/ . Now
consumers can make use of this on-line portal for registering grievance.
Power Department Kerala State Electricity Board Limited Appointment of new Directors
and Transfer of shares vide GO (MS)No.06/2012/PD order dtd 29-3-2012. Shri T.M Manoharan,
Shri Pradeepkumar and Shri. V.P Joy are appointed as share share holder and Director of KSEB
Limited and Shri M Muhammed Ali Rawther appointed as Director of KSEB LTD
KPSC Department Test January 2012 is published.
KSERC Order dated 26.04.2012 in OP No. 21/2012 dated 13/4/2012 filed by the KSE Board
registration is on 13-06-2012
CUG Directory Of KSEB
Please click here CUG Phone Directory
6. T F The greenhouse effect refers to global warming due the burning of fossil
fuels and the subsequent trapping of the waste heat by the atmosphere.
7. T F Solar ponds are a neat idea, but they can't make the water very hot.
8. T F The use and production of biomass is such that eventually, we'll be able
to use it for all of our energy needs.
9. T F An accident like the one at Chernobyl could not happen in the United
States.
10.T F Ordinary objects are radioactive, and you are bombarded with radiation
every day.
Short Answer
1. Name three different types of energy.
Answers will vary. Chemical, mechanical, thermal, electrical, radiant,
nuclear.
2. The law that states that the energy in the universe is constant is the first law
of thermodynamics.
3. Two ways to mine coal are: strip mining and deep mining.
4. List 4 products of crude oil:
Answers will vary. Gasoline, distillate fuel oil, jet fuel, still gas,
lubricants and wax, coke, LPG, asphalt.
5. Natural gas is found in reservoirs.
6. Give one example of geothermal energy on the surface of the earth.
Volcanoes, geysers, hot springs.
7. An alpha particle is really a helium atom.
8. In order for a chain reaction to occur, it is necessary to have a moderator.
9. The type of nuclear reactor that makes more fissile fuel than it consumes is
called a breeder reactor.
10.The amount of high-level radioactive waste could fit under your coffee
table.
Here I am providing the Kerala State Electricity Board Officers Asso Power Quiz
Questions and answers which you are looking for .
1 First Electricity Minister of Kerala V R Krishna Iyer
2 Installed capacity of Idukki Power Station 780MW
3 A hydel project in Kerala is planned to construct in Nayagra Model. Which is it
Athirappalli
4 Owner of Kayamkulam Thermal Power project NTPC
5 Smallest Hydel power project of KSEB Mattuppetti
6 When Bimonthly spot billing was extended all over Kerala 1/1/2001
7 From where 400 KV line is comming to Madakkathara Sub Station Udumalpett
8 Where is the load despatch centre of KSEB Kalamassery
9 Installed capacity of Brahmapuram Diesel Power Station 106MW
10 Which hydel project in Kerala is generating electricity with lowest quantity of water
Sabarigiri
11 Installed capacity of Kuttiadi Extension Scheme 50MW
12 In which district Kakkad hydel project is located Pathanamthitta
13 Largest Consumer of electricity in Kerala Indian Aluminium Company
14 Which corporation is supplying electricity to 400 KV Madakkathara sub station PGCIL
15 Where is pooyamkutty situated Idukki
16 Second largest hydel station of Kerala Sabarigiri
17 Installed capacity of Sabarigiri power station 300MW
18 Moozhiyar Hydel project utilises water from which river Pampa
19 During first five year plan, installed capacity of Kerala 36MW
20 At the time of starting first five year plan, Hydel generation of Kerala 151MU
21 No. of electricity consumers in Kerala during 1951 28119