LWR
LWR
LWR
LONG
WELDED
RAILS
(ii)
PREFACE
Shiv Kumar
Director
IRICEN
(iii)
ACKNOWLEDGEMENTS
Ajit Pandit
Senior Professor & Dean
(iv)
INDEX/CONTENTS
CHAPTER I :
INTRODUCTION TO LONG WELDED RAILS
1.1.
1.2
1.3
1.4
PAGE NO.
1-8
CHAPTER II :
PRINCIPLES OF LONG WELDED RAIL
2.1
2.2
2.3
2.4
2.5
2.6
Basic Principles
Force Diagram
Importance of rail temperature
Breathing Length
Longitudinal Ballast Resistance
Lateral Ballast Resistance
CHAPTER III :
THERMAL MOVEMENTS AND HYSTERESIS
3.1
3.2
3.3
3.4
28-46
CHAPTER IV :
PERMITTED LOCATIONS AND
TRACK STRUCTURE
4.1
4.2
4.3
4.4
4.5
9-27
General Considerations
Alignment
Gradients
Track structure
LWR on bridges
47-77
(v)
CHAPTER V :
NO.
LAYING AND MAINTENANCE
PAGE
78-95
CHAPTER VI :
UNUSUAL OCCURENCES IN LWR,
104
INSPECTION & RECORD KEEPING
6.1
6.2
6.3
6.4
6.5
96-
Introduction
Fractures
Buckling
Inspection and Record keeping
Duties, responsibilities and training
CHAPTER VII :
105-128
SPECIAL TOPICS
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
Buckling Phenomena
Tests by German Railways
Studies conducted by British
Transport Commission
Static and Dynamic Buckling
Dynamic Track Buckling Model
CWR Safety Assurance Program
Field determination of lateral
ballast resistance
Neutral Temperature, its variation
and determination
List of References
129
(1)
CHAPTER - I
1.1.2
1.1.3
(2)
the weights and lengths of standard rail sections
varied from 22kg/m to 65 kg/m and from 5.5 m to
27m respectively (Reference1). The length of welded
panels varied from 18m to 380m. The welding
process most commonly used at that time was
thermit' though flash butt and other processes were
in use in America, South Africa and elsewhere.
1.1.4
(3)
1.1.5
Scale
Rail
Rail
Hog
Rail
Batter
Fig. 1.1
(4)
SWR
SWR
LENGTH 39m in BG
36m in MG
SWR
Fig. 1.2(a)
SEJ
SEJ
SEJ
SEJ
B REATHING
CENTRAL
PORTION
CENTRAL PO RTION
L ENGTH
B REATHING
L ENGTH
LWR
Fig. 1.2(b)
CWR g
f CWR
S PECIAL A RRANGEMENT
FOR TRA NSFERING FORCE FROM
S TOCK RAIL TO TO NGUE RAIL
A ND WING RAIL TO CROSS ING
CWR
CWR
Fig. 1.2(c)
(5)
Taking cognizance of these problems, the Railway Board
vide their letter No 65/W6/WRL/6 of 20th January
1966 appointed a committee consisting of 3
Engineers in Chief (Track), Joint Director Standards
(Track), RDSO and a Deputy Chief Engineer of
W.Rly to investigate into the behaviour of 5-rail
panels and 10-rail panels at the first instance and
thereafter of Long Welded Rails.
1.1.6 The findings and recommendations of the committee
make interesting reading (Reference1). The
committee found that the IRS fishplate design as
per current standards is inadequate to cater to the
expansion and contraction occuring in 5-rail and 10rail panels. While the capacity of the IRS fishplate
design is to accommodate a movement of 15 mm,
the actual movements of a 5 rail or 10 rail panel are
much larger resulting in large gaps, bent fishbolts
and elongated fishbolt holes. The 3-rail panel
therefore appears to be roughly the longest rail
which could be laid in the track with the
conventional fish plated joints. The committee,
therefore, recommended that:
1)
2)
3)
2)
(6)
3)
4)
5)
6)
7)
8)
9)
(7)
1.3 An Explanatory Note on the Short Welded Rail
Indian Railways have adopted a 3-rail panel (39m in BG and
36 m in MG) as the Short Welded Rail(SWR) with fish plated joints
due to reasons mentioned in 1.1.6. Although the SWR is exhibiting
expansion and contraction throughout its length, it is not a free
expansion or contraction due to the action of ballast and fastenings.
The SWR therefore develops thermal forces because of being
subjected to constrained expansions and contractions. It has been
estimated that the magnitude of thermal force in an SWR may be as
high as 70% to 75% of the thermal force in an LWR. This coupled
with fish plated joints makes the SWR very vulnerable and should
therefore be maintained with care. The provisions of laying and
maintenance of SWRs is given in para 505 of the Indian Railways
P-way Manual (1986).
1.4
(8)
frequently resulting in an increment in the track
maintenance effort. It has been estimated that there is
as much as 25% to 33% savings in the track repair
and maintenance costs due to elimination of rail joints.
l Due to impact at rail joints there is an added wear and
tear of rolling stock wheels to an extent of 5% and as
the wheel has to negotiate the gap there is added fuel
consumption to an extent of 7%.
l Due to elimination of noise and vibrations at the rail
joints passenger comfort is substantially increased.
(9)
CHAPTER II
2.
(10)
Here again the rail sleeper frame is not entirely left
unrestrained. The frame is under restraint because of the
resistance offered by the ballast in which the sleepers are
embedded. The resistance offered by the ballast to the movement
of the track frame in the direction of the track is called longitudinal
ballast resistance. Longitudinal ballast resistance is assumed to be
uniform for sleepers of the same type. This longitudinal ballast
resistance builds up progressively from the ends of the long
welded rail towards the centre.
If the track frame was not restrained, then the rail would expand
or contract with variation in temperature and consequently no force
would build up in the rail. However, since there is a restraint now
offered by the longitudinal ballast resistance, forces are set up in the
rail. These are called thermal forces. If the temperature variation
(from the temperature at which the rail was fastenced to the sleeper)
is small, then a small length of track at the end would be sufficient to
develop longitudinal ballast resistance against the tendency for free
movement of the rail. Consequently, it would lead to a small amount
of thermal force in the rails. However, If the temperature difference
becomes more, a longer length of track at the ends would be called
upon to develop the necessary longitudinal ballast resistance
against the free movement of the ends of the rails and there would
be a corresponding increase in the thermal forces.
There is however, a limit up to which the temperature
differences can build up. This limit is dictated by:
a)
b)
(11)
2.2 Force Diagram
In the previous paragraph it has been indicated that thermal
forces are built up in the LWR due to the resistance offered by the
ballast to the free expansion or contraction of the track frame. An
expression for the magnitude of this thermal force is required as
this will govern the design of the LWR. Let us assume the LWR
central portion to undergo a change of temperature equal t oC
temperature rise. If the central portion of length L' had been free
to expand it would have expanded by an amount equal to Lt.
However since the central portion of the LWR does not move, the
compressive strain induced in central portion is equal to
L t
= t where t is the change of temperature of the LWR
L
with respect to the temp. at which the LWR was laid
destressed and is the coefficient of linear expansion.
or
we have
P/ A
=E
t
(12)
When tP = tn, P=0,
when tP>tn, P is a compressive force
and when tP < tn, P is a tensile force.
As tn is not known it is assumed that tn = tL or td , temperatures at
which LWR was laid (tL)or destressed (td).
The force at the beginning of the LWR is zero, and in the
central portion equal to A E t. This change of force from zero to
a peak value occurs over the breathing length. The shape of the
force diagram is therefore as given in Figure 2.1
Fig. 2.1
Thermal stress in rail due to unit degree change of temperature
= E x = 2.15 x 106 X 1.152X10-5 = 2.5 MPa/0C
For 300 C change of temperature therefore thermal stress induced
will be about 75 MPa which is about 8.5% of the ultimate tensile
strength of a 90 UTS rail.
2.3 Importance of Rail Temperature
From the expression for force in an LWR, P = AE(tP - tn), it
can be seen that force developed in the LWR depends primarily on
the prevailing rail temperature and the rail neutral temperature.
Both these factors are discussed below:
(13)
2.3.1 Rail Temperature Measurement :
Thermometers
The following are the different types of approved
thermometers for measuring rail temperature :
i)
ii)
iii)
(14)
Zonal Railways should nominate 8 to 10 stations in their railway
in a manner as to give the representative sample of the
temperature variations on the Zonal Railway for the region allotted
to each station. These stations shall be the existing PWIs offices.
On these stations rail temperature records shall be built up using
preferably a well calibrated continuous recording type thermometer.
The maximum and minumum rail temperature for a continuous
period of at least 5 years shall be ascertained and the mean rail
temperature (tm) for the region arrived at. These temperature
records shall be analysed to assess the probable availability of
time periods during different
seasons of the year for track
maintenance, destressing operations and requirements of hot/ cold
weather patrolling etc. Rail thermometers shall also be available
with each each gang and sectional PWIs to enable the gangs to
work within the prescribed temperature ranges.
2.3.2 Rail Temperature Zones and RDSO Studies :
In order to understand the correlation between the rail
temperature and ambient temperature, RDSO conducted rail
temperature studies between 1969 and 1971 over a two year
period. 22 stations were identified over the Indian Railways where
Standard Measuring Arrangements for Rail Temp (SMART) were
set up. (Fig. 2.2) SMART consisted of a full-length rail laid in the
east-west direction on wooden sleepers with ACB plates and boxed
with standard ballast profile. The rail temperature was measured by
means of a thermometer placed in a mercury-filled hole in the rail
head. Rail temperature readings were taken on an hourly basis
between August 1969 and August 1971, and the corresponding air
temperatures obtained from the Meteorological office. Correlation
equations between the rail temp and air temp were derived using a
computer based regression analysis (Details available in RDSO/C/
146, Reference-3) for each of the identified 22 stations. Using these
correlation equations and the maximum and minimum air
temperatures at 180 stations over the Indian Railways, obtained
from the Weather office over a period of 90 years, it was possible to
determine the maximum and minimum rail temperatures obtainable
at these stations. This data was presented in the form of a rail
(15)
(16)
temperature map where against each station
two figures are
given, namely the rail temperature range and the rail temperature
mean.
The Rail Temperature Range = Max Rail Temp - Min Rail Temp
and Mean Rail Temperature = Max Rail Temp + Min Rail Temp
2
The country is further divided into four zones depending
upon the temp range :
Temp. Zone
I
Temp. Range
40-50oC
II
51-60oC
III
61-70oC
IV
71-76oC
(17)
tmin
tmin
tmin
tmin
(18)
Let us see what happens if the rail is fastened to the sleeper
at the maximum rail temperature (tmax). Since temperature cannot
rise any further, there is no likelihood of compressive thermal
stresses developing in the rail, and consequently there is no
danger of buckling. However, since the rail temperature can fall
through the complete range of temperature at this place, tensile
stresses and forces in the rail could develop to a very large
magnitude making rail fracture very probable.
Logic suggests that we should fix the destressing
temperature exactly mid-way between maximum and minimum rail
temperatures. i.e. at mean rail temperature. In that case the extent
of maximum compressive or maximum tensile forces would be
equal and half of what it would otherwise be as in case of either of
the two previous situations. All the same compressive forces and
tensile forces are bound to develop and so the possiility of buckling
as well as fracture will exist. A fracture will create a gap in the rail.
However, in the case of fractures, the alignment of the rail is not
immediately distorted. Also fractures rarely occur on both rails and
at the same location simultaneously. Thus at least a few trains can
pass over a fractured rail without accident till the fracture is
attended to. However, if the track buckles due to excessive
compressive forces in the rail, alignment of track gets distorted and
safe running of trains is endangered.
Therefore considering buckling more dangerous, it is
considered prudent to fix the destressing temperature higher than
the mean rail temperature so that the compressive forces built up
in the track would be within reasonable limits, though at the cost of
introducing higher tensile forces. This is the basis for fixing td on
the lndian Railways at a temperature above tm. Since 90R and
lighter sections do not have adequate margin to accommodate the
resulting thermal tensile stresses, td for such rails has been fixed
between tm and tm + 50 C. Heavier 52 kg and 60 kg rails having
greater section modulus can accommodate relatively larger thermal
tensile stresses and so td for these rails has been fixed between tm
+ 5 and tm + 100C. It also gives relief by reducing the compressive
forces which are directly proportional to area of cross section of
the rail, other conditions remaining the same.
(19)
Since the operation of fastening of the rails to the sleepers
after destressing takes time during which rail temperature can vary,
a range has been recommended for td instead of a fixed value.
In addition to the above consideration of avoiding buckling
while risking the chances of fracture there are some more reasons
why the destressing temperature has been fixed at a level higher
than tm.
1)
2)
3)
(20)
restrictions at work sites, whenever the rail
temperature rises beyond td +200C during the
period of consolidation. This situation is
unacceptable.
Keeping the above factors in mind td has been fixed
at a higher level as compared to tm.The policy
makers at that time knew that doing this will have
an effect on the number of fractures and therefore
indicated that a greater frequency of USFD
inspection and monitoring would be required.
Fractures are today one of our major concerns and
there is a demand from some railways to reduce
the level at which the destressing temperature
should be fixed basically to reduce the number of
fractures. A more realistic view would be to have a
flexible neutral temperature which could be shifted
downwards in winter to control fractures and shifted
upwards in summer to control the tendency of the
track to buckle.
2.4
Breathing Length
LB x R = AE t or LB =
AEt
R
(21)
2)
3)
(22)
Fig 2.4
(23)
per sleeper per rail. This figure divided by the sleeper spacing in
metres gives the value of 'R' in kg/m/rail.
Findings of the study :
1.
2.
3.
4.
5.
6.
A
different
(24)
Table 1
Longitudinal Ballast Resistance (kg/m/rail)
(Effect of sleeper type and track maintenance activities)
Gauge Sleeper
Type
Consolidated
Through %
packed Loss
Deep
%
Screened Loss
BG
PRC
1244
1027
17
885
29
Steel
1051
744
29
433
59
CST-9
933
551
41
276
71
RCC
921
666
28
581
37
Wooden 697
47
Wooden 405
36
Steel
231
30
MG
298
22
209
(25)
Table 2
Maximum Longitudinal Ballast Resistance (kg/m/rail)
in freshly laid conditions
(Effect of sleeper density & heaped up ballast profile)
Ballast
38 mm Standard Ballast
profile
Sleeper
38 mm Heaped up Ballast
profile
A
PRC
648
Steel
438
Table 3
Longitudinal Ballast Resistance (kg/m/rail)
consolidated
Value
Resistance
on passage
of 1 GMT of
traffic
% of
consolidated
Value
PRC
1244
1072
86
Steel
1051
740
70
CST- 9
933
580
62
RCC
921
750
81
(26)
2.6 Lateral Ballast Resistance
The lateral ballast resistance comes into play when the track
has a tendency to get displaced in the lateral direction due to build
up of compressive forces. RDSO studies(Reference 5) conducted
on various aspects of lateral ballast resistance have indicated the
values of lateral ballast resistance as given in the Table below. The
test setup is given in Fig. 2.5.
Values of Lateral Ballast Resistance in Kg/m of track
Gauge : BG
Sleeper
Consolidated
Through
Packed
Deep
Screened
CST-9
1640
PRC
1470
Steel
1430
RCC
1420
Wooden
1060
Adapted from RDSO/C-156
1100
1226
825
1040
320/520
532
1040
540
800
384
1.
2.
(27)
u
Dial gauge
Fig. 2.5
(28)
CHAPTER III
P(x)
Fig. 3.1
(29)
Take a small length of rail dx at any arbitrary point M at a distance
x away from B (refer fig. 3.1).
It is possible to calculate the amount of free expansion of the small
rail of length dx due to change of rail temperature as well as the amount
of contraction due to presence of thermal force present in the rail at
that length:
Free expansion of this small length dx due to a rise in rail
temperature by t0C = dx t. The amount of contraction of this length
dx, is equal to P(x) dx
EA
(where P(x) is the thermal force present in the small length of rail dx at
a distance x away from B).
The net expansion of the small length of rail dx will therefore be the
difference between the above two values. If this net expansion is called
dy, then
dy = tdx
P ( x ) dx
AE
AEtdx P( x)dx P P( x)
=
dx
AE
AE
Y = dy =
0
1
AE
[P Px( )]dx
x
(30)
in the breathing length of a LWR can be computed by dividing the
shaded area from B, upto that point as in the Fig. 3.1 by EA. Extending
this logic, the cumulative value of expansion or contraction at the end
of the LWR i.e. at A or D can be obtained as follows:
Maximum expansion or contraction at A or D =
AreaofTriangleA1 FE
AE
= 1/2 x P(LB)/AE .... (Equation 1)
As P= AE t, equation (1) above can be simplified as maximum
movement at the end of a LWR, m
= ((LB) t)/2 .... (Equation 2)
We can look at it this way :
The maximum movement of the end of the LWR is half the
corresponding value if only the breathing length LB of the LWR is
allowed to expand or contract absolutely freely. The variation of
movement along the breathing length is given in Fig.3.2.
LBt
2
Breathing
f
f
Length
Central portion
(31)
m = ( t)2 /2R ... (Equation 3)
This can be derived from Equation 1 by substituting AE t/R in
place of LB because
LB = P/R = AE t/R
It should be noted that in the above calculations an important
assumption has been made that in a breathing length of LWR, the
sleepers have equal values of longitudinal resistance.
To illustrate the above let us solve an example with the data given
below:
Gauge: BG, Sleepers: PRC, Rails: 52kg (A=66.15cm2)
Sleeper density 1540 sleepers/km, Zone IV with temp. range
=760C
R = 13.28 kg/cm/rail
A = 66.15 cm2, E = 2.15 x 106 kg/cm2
0
t = t + 10 C
d
AE (t ) 2
2R
(32)
At tp=td
At tp=td+280C
At tp=td-480C
Fig. 3.3
For a temperature fall of 480C
(33)
3.2 Switch Expansion Joints (SEJ) :
The thermal movement in the breathing length of an LWR are
accomodated at the switch expansion joint (SEJ). An SEJ typically
consists of a pair of tongue rails and stock rails , the tongue rail laid
facing the direction of traffic. Modern SEJs are laid on concrete sleepers
with rail free fastenings. The tongue rails and stock rails are machined
and given suitable bends to accomodate each other. Tongue rails and
stock rails have typically straight alignment and hence these SEJs
cannot be laid in curves sharper than 0.50 . The distance between the
tip of the tongue rail and notch of the stock rail is typically kept as
40mm at the destressing temperature. Earlier the gap used to be 60mm
and has now been reduced to 40mm to lower the impact of the passing
wheel. Various types of SEJs used on Indian Railways are described
below:
Drawing No.
Description
RDSO/T-4160
RDSO/T-4165
RDSO/T-5748
RDSO/T-6039
RDSO/T-6263
RDSO/T-6257
(i)
RDSO/T- 4160 and RDSO/T- 4165 are the conventional straight
SEJs with 80 mm maximum gap. Each SEJ has a pair of tongue rails
and stock rails, with 6 special sleepers to RDSO drawing No.RDSO/T4149. All these are 300 mm wide sleepers with sleepers Nos 10 and 11
A
Fig. 3.4
Angle ties
(34)
l l
(35)
(36)
with special fastenings and sleeper No. 8, 9, 12 and 13 with similar
fittings. The centre line of sleeper No. 10 coincides with the tip of the
tongue rail and the 40 mm initial gap is provided with the tip of the
tongue rail coinciding with the centre of the sleeper No. 10. The centre
to centre spacing of sleeper No. 10 and 11 is 700 mm while the sleepers
spacing from 1 to 10 and 11 to 20 may be 600 mm or 650 mm depending
upon the sleeper density. Fig. 3.4 gives details of a typical SEJ layout
and 3.4(a) gives the details of location A.
(ii) RDSO/T-6039 & RDSO/T-6263 : These are wide gap SEJs for
bridge approaches where the maximum gap permitted is 190 mm, the
11690 mm
11690 mm
Fig 3.5
mean position is kept at 166 mm from centerline of sleeper No. 10 to
enable the tongue rail to remain on the sleeper even when the entire
expansion takes place. Sleepers No. 7, 8, 9, 10, 11, 12, 13 are special
sleepers with sleeper nos. 9, 10 and 11 with special fastenings. Use is
made of ERC Mark II clips with flat toe designed with a toe load of 350400 kg/clip to enable free rail movement. Sleepers other than 7 to 13
are approach concrete sleepers with normal fittings. When gap is more
than 100mm for passing diplorries with smaller wheel diameter, use of
an insertion piece in the gap should be made.
(37)
(iii) RDSO/T-5748 : These SEJ layouts can be used when the SEJ has
to be laid in a curve sharper than 0.50 but not sharper than 1.50. The
tongue rail and stock rail are given curvature as given (Fig. 3.5).
The conventional SEJ design involves two bends in the stock rail and
tongue rail which are locations of weakness resulting in fractures.
Improved design SEJs developed by various industries are under trial
on the Railways till final approval is received from the Railway Board.
A brief description of these layouts is given below:
(1) SEJ with one gap : This design has been developed by M/s Rahee
Industries Ltd, Calcutta. Fig 3.6 The design comprises of a pair of
machined segments on the non-gauge face side of two non-bent
running rails mounted with a gap between the juxtaposed rail ends
and a third rail called a gap avoiding rail of predetermined length
accommodated in the said machined segments parallel to and adjacent
to the non bent straight length of the running rails. This rail is securely
fitted to one of running rails with high tensile steel bolts. This running
rail together with the gap avoiding rail is called the stock rail. The other
running rail is called the tongue rail. The non-bolted segment of the
gap avoiding rail braces the machined segment of the tongue rail.
11 1
HTS
BOLTS
(38)
Advantages :
(2)
1)
2)
3)
4)
Two designs have been developed by two different firms (M/s Bina
Metalway, Jamshedpur and M/s Chintpurni Engineering
Works,Barabanki). In both these designs two gaps of maximum 80
mm each are provided in one SEJ. Thus a maximum gap of 80 mm is
available for an LWR on one side of the SEJ. Similarly a gap of 80mm
is available for the LWR on the other side. The tongue rail is
manufactured by cutting the rail at head and foot location. Two cut
rails are joined together to make the stock rail.
Salient features of Bina Metalway 2-gap SEJ (Fig 3.7)
The stock rail is considered to be static with negligible expansion and
contraction in length due to temperature changes. This SEJ makes
use of 6 wider concrete sleepers each to Drg No. T/4149, with three
sleepers located near each gap. The length of the SEJ is 5750 + 6950
+ 5920 + 80 = 18700 mm.
Hence a total gap of 18750 mm should be created while inserting this
SEJ. The stock rail is fabricated out of two pieces of lengths 7140 mm
and 5920 mm connected to each other by HTS bolts. While laying the
SEJ it should be ensured that the ends of the stock rail are 40 mm
away from the centre line of sleeper Nos. 12 and 22 with the tip of the
tongue rail coinciding with the centre line of the sleeper.
1. Sleeper Nos. 1 to 31 should be at a spacing of 600 mm c/c.
2. Sleeper Nos. 10, 11, 12, 22, 23 and 24 are special sleepers to
RDSO drawing No. T 4149 and the rest are normal PSC line
sleepers.
(39)
) )
) )
stock rail
Tongue rail
Tongue rail
(40)
F
D
E
B
A1
(41)
AE (t )
=
2R
At any given temperature t4 if the temp starts falling, then the movement
at the SEJ does not follow the original path but traces out a new curve
A2DB2. If at B2 the temp again reverses then the path traced out is
B2EA 2 rather than B2DA2 Loops in the form A2DB2EA2 are called
hysteresis loops and are formed whenever there is a temperature
reversal. In order to simplify matters, an annual hysteresis loop or curve
is plotted which will envelope all the hysteresis loops formed on a daily
basis. (Fig. 3.9)
This hysteresis loop can be traced in two ways :
1) Temp rise from td to t , fall from t to t and again a rise to
max
max
min
t from t
max
min.
min
(42)
(43)
SAMPLE TABLE FROM ANNEXURE V OF LWR MANUAL
GAPS BETWEEN REFERENCE MARK AND TONGUE RAIL TIP/
STOCK RAIL CORNER OF SEJ FOR VARIOUS TEMPERATURES
IN mm FOR BG, 52 Kg, PRC SLEEPER, 1540 Nos/km, VALUE OF
R (BALLAST RESISTANCE) ASSUMED = 13.28 Kg/cm/rail AND t
d
AS PER PARA 1.11
Temperature
Zone I
Zone II
Zone III
Zone IV
td + 28
14
td + 25
16
14 16
td+ 20
17
16 to 18
15 19
td + 15
18
17 to 19
16 to 20
15 21
td + 10
18 to 20
18 to 21
16 to 22
16 23
td + 5
19 to 22
18 to 23
17 to 24
16 25
td
19 to 23
19 to 24
18 to 26
17 27
td 5
20 to 24
19 to 26
19 to 27
18 28
td 10
21 to 25
20 to 27
20 to 29
20 30
td 15
22 to 26
22 to 28
21 to 30
21 31
td 20
23 to 26
23 to 29
23 to 31
23 32
td 25
24 to 27
24 to 29
24 to 32
24 33
td 30
26 to 27
26 to 30
26 to 32
26 34
td 35
27
28 to 30
28 to 33
29 34
td 40
--
30
31 to 33
31 35
td 45
--
--
33
33 35
td 48
--
--
--
35
(44)
Y
+R
-R
Fig. 3.10
The gaps are with an initial setting of 40 mm. When gaps have been
initially laid at 60 mm, 10 mm should be added to each of these values.
The gaps given in the above table are the theoretical gaps. A tolerance
of + 10mm is prescribed beyond the given gaps.
Cause of Hysteresis : Hysteresis is due to the behaviour of the
longitudinal ballast resistance. A plot of the resistance offered by the
ballast vis--vis the sleeper displacement is as given in Fig 3.10.
The ballast resistance first increases linearly as the sleeper
displacement, then goes into the plastic zone and finally assumes a
constant value R. If at this stage the temperature reverses then the
value of the longitudinal ballast resistance drops to zero and then
becomes (-R) as shown above. This shows that at the time of reversal
of temp the ballast resistance mobilized is 2R. Due to this effect, the
path traced out at the end of LWR follows an irregular path leading to
the hysteresis phenomenon.
(45)
3.4 Gap measurements at an SEJ :
At the SEJ a reference line is established between the tongue rail and
stock rail. This gap between the tongue rail and stock rail will be equal
to 40mm for 52kg and 60kg rail sections, and for other rail sections
60mm as shown. (Fig. 3.11 )
Gaps g1 and g2 are not discrete values but the permissible range has
been defined in the LWR Manual Annexure V for different track
structures, different zones and different prevailing temperatures. A
sample page for filling up the movements observed at an SEJ as per
annexure XIII A of the LWR Manual is shown in Fig. 3.12.
10:00
6.10.2004 14:00
6.10.2004
Distance (mm)
between tongue/
stock rail &
Reference line
at SEJ No.10
Obser
Permis
ved
sible
(a)
Range
g5
g7
Distance (mm)
between tongue/
stock rail &
Reference line
at SEJ No.11
Observ Permis
ed
sible
Range
at SEJ
No. 10
at SEJ
No.11
on by
date
c/c space
Measu Rectifi Remarks
between
red by cation
sleepers the two
carried
central sleepers
out
Fig 3.12- Sample of SEJ gap measurments. Also refer Fig 3.11
SEJs at the end of this LWR : SEJ NO.10 at km; SEJ No.11 at km
Annexure XIII A
(46)
(47)
CHAPTER IV
PERMITTED LOCATIONS AND
TRACK STRUCTURE
4.1. General Considerations :
1. It is a policy that all new constructions, gauge conversions,
doublings and permanent diversions will be opened with
LWR wherever permissible by the provisions of the LWR
manual.
2. All complete track renewals (primary) shall provide for
LWR/CWR wherever permissible. Existing rails on
permitted locations shall be converted into LWR/CWR
provided they meet the requirements laid down in the
Manual for Welding of rail joints by Alumino thermit (SKV)
process.
3. In goods running lines, goods yards, reception yards
marshalling and classification yards, rail joints may be
welded to form LWR if the condition of all components of
the track is generally sound and without any deficiency
subject to such relaxation as may be approved by Chief
Engineer, in each specific case.
P/R
kg/m
R = CURVE RADIUS IN m
P = AXIAL COMPRESSIVE
FORCE IN LWR IN kg
= 2 AEt
(48)
4.2. Alignment
1. LWR/CWR shall not be laid on curves sharper than 440
meters radius both for BG and MG.
As indicated in Fig. 4.1 the external equilibrium of a curved
elastic beam of radius R subjected to a longitudinal force P
requires a continuously distributed external force of magnitude f
where f =
resistance
P
kg / m . This will be derived from the lateral ballast
R
and
P
is the effective lateral resistance against
R
COMMON TANGENTf
POINT
600mm
100m
(49)
2. LWR/CWR may be continued through reverse curves not
sharper than 875 metres. For reverse curves sharper than
1500 meters radius, shoulder ballast of 600 mm over a
length of 100 m on either side of the common point should
be provided. These details are shown in Fig. 4.2.
4.3. Gradients :
1. The steepest grade permitted is 1 in 100 for LWR sections.
This is because steeper grades imply larger longitudinal
forces due to traction and braking which would be
detrimental to the health of the LWR causing an increase
in the longitudinal stresses in the rail.
2. A vertical curve shall be provided at the junction of grades
when the algebraic difference between the grades is equal
to or more than 4mm per metre or 0.4% as laid down in
para 419 of IRPWM. This vertical curve will serve to
smoothen the geometrical transition and introduce a
gradual change in the direction of longitudinal force as
shown in Fig.4.3.
3. Vertical curves should be of adequate radius as indicated
in the table below
Broad Gauge
Metre Gauge
Route
Minimum Radius
Route
Minimum Radius
4000 m
AII routes
2500 m
3000 m
C, D & E
2500 m
(50)
VERTICAL CURVE
VERTICAL CURVE
1
CHANGE OF GRADE
CHANGE OF GRADE
= 1 + 2
= 1 - 2
(51)
30
30
Fig.4.4. (a)
6850
6250
6850
6250
6850
6250
6850
6250
6850
6250
6850
6250
(52)
30
30
Fig.4.4. (b)
5850
5250
5850
5250
5850
5250
5850
5250
5850
5250
5850
5250
5850
5250
5850
5250
5850
5250
(53)
30
30
Fig.4.4. (c)
12160
11550
12160
11550
12160
11550
12160
11550
12160
11550
12160
11550
12160
11550
12160
11550
12160
11550
(54)
30
30
Fig.4.4. (d)
9810
9210
9810
9210
9810
9210
9810
9210
9810
9210
9810
9210
9810
9210
9810
9210
9810
9210
9810
9210
9810
9210
(55)
4.4.3 Sleeper and fastenings :
As explained earlier, the entire theory of the LWR is built on the
premise that there is no relative slip of the rail with respect to the
sleeper, and any movement which occurs is with rails and sleepers
moving together. To achieve this the following types of sleepers
and fastenings have been approved for use in LWR/CWR :BG
(i)
(ii)
(ii)
(iii)
(56)
Direction of traffic
Breathing length
q q
Breathing length
q q
Direction of traffic
(57)
The direction of key driving for CST-9 and steel
trough sleepers in LWR territory for single and
double line sections is given in Fig 4.5 and 4.6
respectively.
MG : The recommended sleepers for speeds above 75kmph but a
must for speeds above 100 kmph are :
1. Concrete sleeper with elastic fastenings.
2. Steel trough sleepers with elastic fastenings.
The recommended sleepers for speeds upto 100kmph are:
1. Steel sleepers with two way keys.
2. CST-9 sleepers with keys.
Wooden sleepers with anti-creep bearing plates and two way keys
or elastic fastening may be permitted, for continuing LWR, if
behaving satisfactorily for a maximum speed of 130 kmph in BG
and 100 kmph in MG.
Sleeper density :
The minimum sleeper density (number of sleepers/km) in LWR/
CWR shall be as follows :Type of sleeper
i) PRC
ii) PRC
MG
90R
75R
52kg
90R
60kg
(58)
1. In MG, 60 R rails converted into LWR may be permitted to
continue if showing satisfactory performance.
2. In the same LWR, different rail sections are not permitted.
This is because of the following reasons:
(i) Thermal forces generated in rails of different cross
sectional areas are different. This makes the behavior of
the LWR non uniform. The destressing temperatures are
also different for 52kg and 90R rails.
(ii) While permitting two different rail sections in an LWR,
combination welded joints cannot be avoided. As the
gauge faces have to be matched, eccentricity is induced in
the axial forces, resulting in additional stresses in the rail.
(iii) The ultrasonic flaw detection of combination welds is not
completely foolproof.
The track structure suggested at the junction of a 52kg and
60kg LWRs is shown in Fig.4.7. The suggested track structure
meets with the requirement of continuing the same track
structure for three rail lengths beyond the SEJ.
60 KG SEJ
60 kg LWR
52 KG SEJ
combination weld
Fig.4.7
52kg LWR
(59)
i)
Rails to be ultrasonically
defective rails replaced.
tested
and
all
ii)
iii)
(60)
resistance not less than 25 megaohms in dry condition or
3 kiloohms under saturated conditions. Glued joints are
considered as track components whose procurement has
to be done by the engineering department.
4. Location of SEJs : The exact location of the SEJ will be
fixed taking into account location of various obligatory
points such as level crossings, girder bridges, points and
crossings, gradients and curves. SEJ with straight tongue
and stock rail shall not be located on curves sharper than
0.5 degree (3500m radius). SEJ shall also not be located
on transition portion of cuves.
4.5.
LWR on Bridges :
(i)
(ii)
(61)
case of the CWR or the thermal expansion of
the deck and of the rail whenever a rail
expansion device is present.
ii)
iii)
iv)
v)
(62)
K=
H (KN )
i (cm )
with i = p + + h + a
where, p = displacement at the head of the support due to
hp
hf
Fig. 4.8
h =
foundation rotation.
displacement due to horizontal movement of the
foundation.
(63)
4) Height of the Deck : The distance of the upper surface
of the deck slab from the neutral axis of the deck and the
distance of neutral axis from the centre of rotation of piers
affects the interaction phenomena due to bending of the
deck.
TRACK PARAMETERS : The resistance k of the track
per unit length to longitudinal displacement u is an
important parameter. This parameter in turn depends on a
large number of factors such as whether the track is
loaded or unloaded, ballasted or frozen, standard of
maintenance etc. The resistance to longitudinal displacement
is higher on loaded track than on unloaded track as can be
seen from Fig. 4.9. The value of k has to be established by
each railway system as per its track structure.
u
Fig. 4.9 TRACK STIFFNESS PARAMETERS
(FROZEN BALLAST)
Once the values of K, the stiffness of the bridge structure
and k, the stiffness of the track have been evaluated, use
can made of the interaction diagrams given in UIC774-3R
for calculation of the additional stresses in the rail and
additional forces at the bridge support due to each of the
actions causing interaction effects: namely (1)change of
temperature (2) acceleration and braking forces (3) deck
deformation.
(64)
u
Fig. 4.9 TRACK STIFFNESS PARAMETERS
(NORMAL BALLAST)
1
Changes in temperature :
(65)
with respect to the standard longitudinal plastic shear resistance
equal to 20 KN/m and 60 KN/m for unloaded and loaded track
respectively.
The design curves are given for the following two different
situations :
- deck bridge
R is calculated as follows :
(66)
4.5.2. Provisions given in the LWR Manual for carrying
LWR over bridges:
However, for a simple understanding of the problem let us
consider the effect of thermal variation alone as the cause of
interaction between the girder and the LWR. As a result of thermal
variation the girder has a tendency to expand or contract being
provided with bearings. On the other hand the central portion of
the LWR is fixed in position irrespective of the temperature
changes that occur. This results in an interplay of forces between
the girder and the LWR, the magnitude of the force being
dependent upon the nature of fastenings being provided between
the rail and sleeper. To clarify this aspect of interplay of forces
between rail and girder, consider the case of a girder bridge
provided with fastenings between the rail and sleeper with a creep
resistance equal to p kg per rail seat. The bridge sleepers are
rigidly fixed to the top flange of the girder by means of hook bolts.
On variation of temperature due to the creep resistance of the
fastenings, free expansion/contraction of the girder is prevented.
Consequently additional forces are developed both in the girder as
well as in the rail. The magnitude of this force developed depends
upon the value of p( the creep resistance) and orientation/nature
of the bearings provided in each span of the bridge.
The following cases have been considered:
Single span bridge :
1.
2.
Multiple span bridge: 1.
np
, where n is the number of sleepers per
4
(67)
rise
rise
(68)
np
m = No. of spans
n = No. of sleepers per span
p = creep resistance per rail seat
Fig. 4.10 (c)
(69)
np
np
for a single
2
mn p
. The resultant LWR force
2
(70)
Fig. 4.11
In order to avoid interplay of forces between the LWR and
girder a possible solution would be to provide rail free
fastenings between rail and sleeper on the girder bridge. It is
with this assumption that the provisions for laying an LWR over
bridges have been framed in the LWR manual.
Fastenings used to connect the rail to the sleeper could be of
two types : (1) Creep resistant fastenings and (2) Rail free
fastenings which are now termed as zero longitudinal restraint
fastenings. RDSO Report No. C-169 investigates the creep
resistance offered by different types of rail sleeper fastenings.
On the Indian Railways we have been traditionally using dog
spikes and rail screws as rail free fastenings although now
Pandrol has come up with a zero longitudinal restraint
design(Fig 4.11). Under normal circumstances there is a small
gap between the base plate (steel) and the top side of the rail
foot. In case of large lateral forces, the baseplate prevents the
overturning of the rail. The pad under the rail is made up of low
friction material like teflon, which provides an almost zero friction
(71)
F
B
Fig. 4.12
L0
B
Fig. 4.13
(72)
The gap g1 at the fracture location will be given by
AE (t )
2 (1)
g1 =
2R|
2
2xAE(t )
+ L0 ..t (2)
g2 =
2R|
2
AE(t )
+ L0t < 50mm
2R|
2
2x
(73)
BG, the fracture gap of 50 mm is more critical for MG.
Over the years attempts have been made to increase the
value of L0 by adopting various techniques :(1) One way could be to increase the value of R, the
longitudinal ballast resistance mobilized at the fracture. This
could be done by :l Compacting the ballast in shoulders and cribs of the bridge
approach sleepers.
l Enhancing the sleeper density to 1660 Nos./km in the bridge
approach.
l Heaping up of ballast in the bridge approach starting from the
foot of the rail.
l Box anchoring sleepers wherever required.
These measures have to be taken in the bridge approaches
50m on either side.
Table 1 of the LWR Manual 1996 gives the maximum overall length of
girder permitted on LWR/CWR in with the following stipulations :
1. Girder bridge should have sliding bearings on each end with
single span limited to 30.5m.
2. Rail should be provided with rail free fastenings throughout
the length of the bridge from abutment to abutment.
3. The approach track should be suitably upgraded as mentioned
above.
2) Another way of increasing the value of Lo would be to improve the
approaches as mentioned above in addition to providing a few sleepers
on each span with creep resistant fastenings. The creep resistant
fastening will hold the rail and prevent the gap at fracture from becoming
excessive.
However, provision of creep resistant anchors implies an interplay of
forces between the rail and grider. Hence the following stipulations are
made for bridge provided with rail free fastenings and partly boxanchored (with single span not exceeding 30.5m and having sliding
bearings at both ends).
(74)
(1) On each span 4 central sleepers will be provided with creep
resistant fastenings and remaining sleepers with rail free
fastenings.
(2) Bridge timbers laid on girders shall not be provided with through
notch but shall be notched to accommodate the individual rivet
heads.
(3) The girders shall be centralized with reference to the location
strips on the bearing before laying LWR/CWR.
(4) The sliding bearings shall be inspected twice a year and oiling
and greasing of the bearing carried out once in two years.
Table 1 of LWR Manual
Temperature
Zone
Rail
Section
I
II
III
IV
60kg
52kg/90R
60kg
52kg/90R
60kg
52kg/90R
60kg
52kg/90R
PRC/ST
30m
45m
11m
27m
11m
27m
11m
27m
PRC/ST
77m
90m
42m
58m
28m
43m
23m
43m
(75)
(2) Providing an SEJ at the far end approach of the bridge using
rail free fastenings over the girder bridge(Fig 4.15):
In this arrangement an SEJ is provided at the far end approach
of the bridge(abutment away from the LWR) at a distance of
10m away from the abutment with rail free fastenings on the
bridge proper.The SEJ will have to cater to the free expansion
or contraction of the rail on the bridge as well as movement of
the breathing length.Hence the SEJ will have to be a wide gap
SEJ capable of accomodating larger movements.The
permissible span lengths with normal SEJs and 190mm
maximum gap SEJs are given on the adjoining page.
190
190
190
190
120
120
IV
III
II
I
II
I
20m
50m
55m
70m
110m
160m
with ST/
PRC
approach
sleepers
15m
50m
45m
70m
100m
150m
with
CST-9
approach
sleepers
Max.move
ment of
SEJ (mm)
Rail
temp.
Zone
Max. length of
bridge with SEJ
4.0 cm
4.0 cm
7.0 cm
7.0 cm
6.5 cm
6.5 cm
with ST/
PRC
approach
sleepers
4.0 cm
4.0 cm
6.5 cm
6.5 cm
6.5 cm
6.0 cm
with CST-9
approach
sleepers
Initial gap to be
provided at td
(76)
Fig. 4.15
Fig. 4.14
(77)
(78)
CHAPTER V
LAYING AND MAINTENANCE
5.1
Laying of LWR
1. An initial survey of the section where the LWR/CWR is
proposed to be laid should be carried out. A foot by foot
survey is recommended.
2. Locations where LWR/CWR cannot be laid, need to be
identified. These locations could be:
i)
Sharp curves
ii)
Bridge locations
iii)
Steep Gradients
iv)
Points and crossings
v)
Troublesome formations
vi)
Distressed bridges
These locations will be isolated from the LWR by providing
SEJs on either side.
3. A detailed plan shall be made showing the exact location
of the SEJs and various other features such as level
crossings, yards, curves, points and crossings, gradients
and bridges. This is called the LWR plan. This plan should
be got approved by the T.H.O.D. if there are no deviations
from the provisions of the LWR manual or by CE/CTE if
any deviations are proposed.
4. Temperature Records : The LWR Manual (1996)
prescribes that each railway should nominate 8 to 10
stations on its jurisdiction where temperature records over
a period of 5 years should be built up by installing suitable
continuous recording thermometers. The maximum and
minimum rail temperature for a continuous period of at
least 5 years shall be ascertained and the mean rail
temperature for the region arrived at.
This could provide the basis for fixing the rail neutral
temperature, ascertaining the periods during the year when
(79)
maintenance operations could be carried out or hot
weather and cold weather patrolling need to be introduced.
If these records are not available, use may be made of the
rail temperature map given in the LWR Manual.
5. Materials required for laying an LWR :
i)
Four numbers of 6.5 metres or longer rail
pieces of the same rail section as the LWR.
ii)
iii)
iv)
Rail closures.
v)
vi)
Welding equipment.
vii)
Destressing equipment
wooden mallets.
i.e.
roller,
tensor,
ii)
Realignment of curves.
iii)
iv)
v)
vi)
ii)
(80)
5.2
iii)
iv)
v)
Destressing Operations
(81)
1.
Manual Destressing of the LWR : When the prevailing
temperature tp falls in the range prescribed for the stress-free
temperature then manual destressing of the LWR can be resorted
to. Work should be done in the presence of a PWI.
The steps involved are given below :
A)
2)
3)
4)
B) Block Activities:
1)
(82)
2)
3)
4)
5)
6)
7)
(83)
neutral temperature. The LWR is made stress-free at tp by
removing the fastenings and subsequently tensile stresses are
created in it by pulling the LWR by a calculated amount :
Compressive stress created in the LWR due to rise of temp
from tp to tn with zero stress at tP = E (tn tp)
The tensor creates the same amount of tensile stress by pulling
the LWR section by an amount equal to .
If the length of the section is L, then strain
= E (t n t p )
L
or = L (t n t p )
This expression gives the extension to be imparted to a
segment of length L of the LWR to get the stress-free
temperature at tn.
Equipment : The tensor is basically a pulling device which
could be hydraulic or mechanical. It is non-infringing, enabling
trains to pass when in position. It grips the web of the rail
using a special cam arrangement eliminating bending, dipped
joints and rail-head marks. It can be dismantled into different
parts for being transported, the weight of the heaviest
component being 54 kg. (Details of a tensor are given in Fig
5.2) Some of the details of a tensor manufactured by CTR
Industries, Pune are given below:
Total weight = 325 kg (without pump)
Pulling force = 70 tonnes
Pushing force = 30 tonnes
Stroke = 380 mm
Overall dimensions : 4500 mm length
1200 mm width
(84)
Level crossing
(85)
Steps in destressing by the rail tensor (Fig 5.3) :
1) The destressing operations have to be carried out
when the prevailing rail temperature tp is less than
the the designed neutral temperature.
2) Make cuts 1m apart at the centre of the LWR.
3) Erect marker pillars W0, W1, W2 at convenient
distances of say 100m. The first marker pillar W0
will be erected at a distance equal to the anchor
length from the SEJ. The anchor length is the
length of track where the fastenings will not be
removed during the destressing operations. This
length is required to resist the pull applied by the
tensor. An estimate of the anchor length is as
under:
o
For BG
..2.5 m per C of t -t
For MG
..4.5 m per C of t -t
(86)
12
10
11
3
1
2
6
8
5
PART LIST
Sr. ITEM
No.
QTY.
Nos.
Sr. ITEM
No.
1.
YOKE
7.
CLEVIS
2.
LEVER ARM
8.
3.
HYDRAULIC
9.
HOSE
CYLINDER
QTY.
No.
PIPE-2m
4.
JAW
5.
TIE BAR
11. HYDRAULIC
PUMP UNIT
6.
FORK END
12. T CONNECTOR
tn
(87)
Fig. 5.3
(88)
6)
7)
8)
9)
5.3
5.3.1.
(89)
5.3.2.
(i)
(a)
(b)
(ii)
carrying
out
(ii)
(90)
(A)
(B)
ii)
(91)
maintenance of track at the following locations :
5.3.7
SEJs/breathing lengths.
(ii)
(iii)
(iv)
(v)
(92)
Rail temperature restrictions are the same as laid
down for manual track maintenance.
(ii)
5.3.8
(ii)
(93)
tongue rail and stock rail should be done
simultaneously.
ii)
ii)
iii)
Creep of LWR.
iv)
In such cases, the LWR should be destressed and the gap at the
buffer rail joints restored to 7.5 mm at td.
5.4 Special Track Maintenance :
These works are generally carried out with a speed restriction in
force.
This would include the following items :
(94)
i)
ii)
iii)
iv)
v)
Sleeper renewal
renewal.
vi)
Formation rehabilitation.
other
than
casual
(95)
4. Once the deep screening is completed, then the entire
LWR should be destressed to bring the destressing
temperature to the normal range.
(96)
CHAPTER VI
UNUSUAL OCCURENCES IN LWR, INSPECTION &
RECORD KEEPING
6.1 Introduction: This chapter is devoted to a discussion on
various unusual occurrences which may occur in an LWR such as
fractures and buckling, and remedial measures to be taken in the
event of the same.
6.2 Fractures
6.2.1 Rail and weld fractures occur with increasing frequency on
LWR sections in winter due to development of longitudinal tensile
forces as rail temperatures fall below the destressing temperature.
The increasing incidence of rail fractures in LWR sections could
also be attributed to the fact that the rail distressing temperature
has been fixed between tm + 50C to tm + 100C for 52 kg and 60 kg
rails increasing the tensile force created in the rail as temperature
drops towards t .
min
(97)
6. Fractures due to corrosion at rail seat and liner location etc.
7. As discussed earlier excessive tensile forces in the rail
generated due to temperature changes of the LWR.
6.2.2 Repairs to Fractures
1. Once a fracture has occurred, the railway official detecting
the fracture should take immediate steps to block the
section and prevent any train movement over the fractured
portion.
2. This done, fracture repairs are done in the following stages :
A. Emergency Repairs
These repairs are carried out to pass the train over the fractured
rail. The following steps are involved :
1. If the gap at the fracture is less than 30 mm, a fishplate for a
rail fracture or a joggled fishplate for a weld fracture is fixed,
using 4 tight screw clamps without a rail closure piece.
2. If necessary, a wooden block may be inserted below the rail
to support the fractured joint.
3. If the gap at fracture is more than 30 mm, a railclosure
piece will be inserted into the gap after which fishplates or
joggled fishplates will be fixed.
4. This done, the train is allowed to move over the joint with a
SR of stop dead and 10 kmph for the first train and 20 kmph
for the subsequent trains. The LWR Manual authorises a
keyman / gangman to pass the train in such an emergency.
If one meter long fish plates are used during the repair the
SR will be 30 kmph.
B. Temporary Repairs
This essentially involves the removal of the fractured rail from
the track and replacing it with a sound railclosure piece of
length generally more than 6.5 m.
The following steps are involved in temporary repairs.
1. Two paint marks are made on either side of the fractured
(98)
joint at a distance, say X and Y as shown in the Fig 6.1.
Fig 6.1
(99)
4. In the same block if time permits, or in another block one
of the gaps is adjusted to 25 mm (for SKV welding) and
welding performed.
If the other gap is also 25 mm then the other joint could
also be welded. However, if the other gap is not 25 mm, as
will generally be the case, then the other gap is fishplated
with screw clamps and opened to traffic.
5. For welding the other gap, a tensor is used. It will be used
for reducing the gap to 25 mm. This is done by removing
sleeper fastenings over a given length and applying the
requisite pull by tensor. With the tensor in position and
gripping the rail web, the rail joint is welded. The tensor is
kept in position till weld metal cools down. After the weld
metal has cooled down, the tensor is removed, and
fastenings removed over a length of 125 m on either side
of the weld. The rail is tapped to equalise the stresses and
fastenings put back in position.
6. To summarise, the process of temporary repairs is carried
out without adding any additional rail metal to the LWR. If
the gap at fracture is bridged by providing a longer length
closure rail, there will be a drop in the neutral temperature,
creating high compressive stress in the rail during the
summer season. The temporary repairs should be carried
out in the supervision of a PW Mistry/PWI.
7. A new development in welding technology is wide gap
welding. This enables fracture repairs to be done by
providing a single weld instead of two welds as was done
earlier. The method of repairs has been indicated in Fig.
6.2.
A,B are paint marks on either side of fracture.
Rail inserted = 75mm. (wide gap weld)
Rail removed = X+Y+2 saw cuts (1mm)
75 = X+Y+2 saw cuts
(100)
LOCATION OF FRACTURE
Fig. 6.2
C. Permanent Repairs :
This will involve destressing the entire LWR after a
number of fractures have occurred in the LWR. The
Manual prescribes destressing to be done when the
number of fractures exceeds 3 per km.
D. Equipments required for fracture repairs :
1. Fishplates/ Joggled fishplates with bolted clamps.
2. One metre long fishplates with bolted clamps.
3. Rail Closure Pieces with different lengths.
4. Welding equipment with all accessories.
5. Tensor for obtaining the standard gap.
6.3 BUCKLING :
6.3.1 Buckling is the phenomena describing the sudden lateral
shift in the alignment of an LWR to relieve the builtup
compressive forces during the summer months as the temperature rises above the destressing temperature. Buckling
results in complete distortion of the track geometry affecting
safety and it is not possible to pass a train over the buckled
track. Over the years, lateral stability of LWR track in hot
weather conditions has been a source of great concern to track
engineers. Initially it was thought that the slender rail section
would not be able to take the high compressive forces generated during the summer season. Subsequent investigations by
(101)
various railways, however, indicate that the track strength
against buckling was contributed by not only the rails, but the rail
sleeper assembly with fastenings, and the ballast contributed in
a substantial measure to the strength against buckling.
6.3.2 Some of the factors which could lead to buckling are :
1. Nonobservance
of
the
specified
temperature
restrictions while performing maintenance operations in
an LWR.
2. Lack of ballast affecting the lateral and longitudinal
ballast resistances.
3. Missing fittings.
4. Settling formation resulting in poor alignment of track.
5. Improper functioning of the SEJ.
6.3.3 Steps to be taken to avoid buckling :
1. Ensuring proper ballast profile.
2. Full complement of fastenings and anchors.
3. Observance of specified temperature restrictions (tp < td +
100C) during maintenance operations.
4. Introduction of hot weather patrolling when the prevailing
0
rail temperature goes beyond td + 200C, (tp>td+20 C).
5. Controlling misalignments in track.
6. Keeping a close watch on SEJ gaps specially during
extreme temperatures.
7. Proper repairs of fractures i.e. avoiding addition of metal at
the fracture location during repairs.
6.3.4 Steps to be taken in face of impending buckling :
On detecting severe sunkinks or noticing hollowness of sleepers as
detected by a canneboule, the following steps are suggested :
1. The section to be blocked or speed restrictions to be
imposed, depending upon the severity of the situation.
2. Additional ballast to be dumped on the shoulder, by taking
out, if required, ballast from the centre of the track.
(102)
3. At tight rail locations, rail should be cut out from the track.
In the morning times, this could be achieved using a
hacksaw blade. However, this will not be possible when the
rail is under compression as it will tend to pinch the blade.
Gas cutting to cut rail out will have to be resorted to.
Subsequently the heat affected martensite zones could be
removed by cutting three inches on either side of the gas
cut by a hacksaw blade. The golden principle to be
followed is : When in doubt, cut rail out.
6.3.5 Repairs to be undertaken in the event of buckling :
1. Each case of buckling shall be investigated by the AEN
soon after its occurrence and a detailed report submitted to
the DEN/Sr DEN.
2. The rectification shall normally be carried out in the
following stages under supervision of the PWI.
(A) Emergency Repairs
1.
This repair is carried out to restore traffic on the
section. A 6.5 m long rail piece will be cut out from
the buckled track at the location of buckling,
resorting to gascutting if required.
2.
After removal of the rail piece, it will be possible to
slew the track back into proper alignment.
3.
A closure rail piece of suitable length could now be
inserted into the track and section restored after
fixing fishplates and screwclamps.
(B) Permanent Repairs
The clamped closure rail piece will be welded at either end.
To get the required gaps for welding, rail cutting equipment
will be required. In order to complete the repairs,
destressing of the entire LWR will be carried out as early as
possible.
6.4 Inspection of the LWR and Record keeping :
6.4.1 Inspection: While an LWR section, reduces the maintenance
requirements it necessitates intensive inspections at supervisory
and officers' level. The Sr. DEN / DEN, AEN & PWI and other
inspecting officials should pay special attention to the aspects
given below while inspecting LWR sections.
(103)
1.
2.
3.
4.
5.
6,.
(i)
(ii)
6.4.2 Records:
(1)
The PWI should maintain a permanent register called
the LWR section register. This register should record
various details of the LWR as laid down in annexure XI
and XII of the LWR Manual.
(2)
An indication plate should be fixed on the cess at each
SEJ, showing the date of destressing, destressing
(104)
(3)
(4)
(5)
(105)
CHAPTER VII
SPECIAL TOPICS
7.1 Buckling Phenomena : As described earlier, buckling is the
sudden lateral shift in the track alignment to release the built up
compressive forces in the rail. The strength of track against
buckling or what is described as lateral stability of track has been
investigated in great detail by various railways. The studies
conducted by various railways and the results thereof have been
discussed in this chapter.
7.2 Tests by German Railways: Results of a series of track
buckling tests conducted for the Federal German Railways were
reported by F. Birmann and F. Raab in 1960. The test facility was
located at the Technical University of Karlsruhe. The track section
was 46.50m and was confined at both ends by reinforced concrete
blocks. The following results were obtained from the tests :
1)
2)
(106)
First waveform
Second waveform
Third waveform
Fig. 7.1
(107)
Fig. 7.2
3)
4)
(108)
1.
4.
7.
9.
Fig. 7.4
3. Tie bars
6. Electric heaters
8. Thermometers
(109)
(110)
7.3.1 Test Arrangement (Fig. 7.4)
The main tests devised for the purpose of carrying out buckling
tests was a 120 feet test bed upon which could be built, complete
in every respect a length of track, the whole capable of being
subject to thermal stresses. The arrangement of the test bed was
such as to simulate the central portion of a long welded rail length
on site which does not move longitudinally with temperature
change. The test bed was laid inside a disused tunnel where a
constant ambient temperature could be expected.
The 120 feet track rails were anchored at each end to concrete
blocks sunk below ground level. This was sufficient to prevent
rotation of the track and change of gauge but not to prevent the
expansion of the rails. The latter was controlled by four tie bars,
two on each side of and clear of the test track. Any tendency for
the rails to expand could be counteracted by the jacks, although it
must be stressed that the jacks were not directly used to induce
compression in the rails. Four dial gauges altached to an
independent datum registered any longitudinal movement of each
rail end during the tests. By operating the jacks the rail lengths
could be kept sufficiently close to their original values to be
consistent with actual conditions in the field.
Heaters : Electric heaters with parabolic refiectors were used to
simulate the heat radiation from the sun; they were situated on one
side of each rail at a distance determined experimentally so that
the rate of heating was not excessive.
Thermometer : Normal glass and mercury thermometers inserted
in sockets drilled mainly in the head of the rail were used to
measure the temperature.
Misalignment : This is the offset of the rail from the straight. The
length of misalignment is the length over which misalignment
occurs. The track was laid initially as straight as possible and then
given a small misalignment over a given length.
Methodology of Test
Using the above setup, the longitudinal load required to buckle the
track was determined experimentally for different types of sleepers,
(111)
fastenings and ballast packing conditions. Using theoretical
methods the longitudinal load required to buckle a track was
determined and the same compared with experimental values.
7.3.2 Buckling Load Formula:
The formula derived for the longitudinal load required to buckle a
straight track is :
P=
2 EIs 2C
+
L2
16 D
L W max L2
+
q
2q
Where
Is is the moment of inertia of the two rails put together in the
horizontal plane.
L is the distance between the points of contraflexure of the buckled
track.
C is the torsional coefficient for the given type of fastening
2WIs
represents the contribution of the rails to resistance
L2
2C
2)
16 D
L
represents the contribution of the sleeper/fastening
q
(112)
W max L2
3)
reperesents the contribution of the lateral ballast
2q
resistance.
The following points are to be noted:
1. If the track were perfectly straight and points of equal load
application central for each rail, then the track would not buckle
however great the longitudinal compressive force. However, in
practice no track exists under these ideal conditions and a
misalignment of q over a length L will always be present. In any
case, it is evident that the lower the L /q ratio, the smaller will be
the buckling load. It means that large misalignments significantly
reduce the strength against buckling.
2. Experimentally it has been observed that when a buckling
occurs, the sleepers remain at right angles to the original track
alignment. For this to occur, the rail must rotate on the rail seat.
Clearly, only one thing resists such a rotational movement and this
is the torsional resistance (denoted by torsional co-efficient C)
afforded by the fastenings. Clearly the buckling load is
proportional to torsional resistance.
3. L the length of buckled track is taken as 20 feet for all cases.
In actual fact for a given combination of C,D, Wmax and q there
exists only one value of L which will yield a minimum value of P
(the buckling load). Hence for various combinations of these
variables, a range of L values would emerge. For practical use
however, L is chosen as 20 feet and the value of q as 1/4
inch(6mm).
4. The relative contributions of rails, rail sleeper fastenings. and
ballast would depend upon the actual conditions prevailing at site.
Under normal conditions the percentage contributions could be
10%,30% and 60% respectively.
5. The buckling load values as determined experimertally show a
fair correspondance (within a few per cent) with the values
determined from theoretical calculations.
(113)
6.A PWI can ensure that the track remains safe against buckling
by:
1. Reducing the lateral misalignment in the track.
2. Ensuring that no sleeper rail fastenings are missing.
3. Providing full complement of ballast in the track as per precribed
ballast profile.
7.4 Static Buckling and Dynamic Buckling
The discussion so far has been centred on buckling caused by
longitudinal compressive force buildup due to rise of temperature
above the stress-free temperature. This buckling due to thermal
loads alone is called static buckling. The industry today is more
concerned with buckling caused by the movement of a train on the
track in the presence of thermal loads. Such a buckling is called
dynamic buckling. The effects of a moving train which could
contribute to dynamic buckling are as given below :
1) Loaded axles of a moving train cause the track to be lifted in front
of, in the rear of or even between the moving axles. The wave so
created as seen in the vertical profile of the rail in front of the engine
is called the precession wave,in the rear the recession wave and in
between the axles, the central wave. Any of these waves
DIRECTION OF
TRAVEL
q
PRECESSION WAVE
CENTRAL WAVE
INITIAL LATERAL
IMPERFECTION
CENTRAL WAVE
RECESSION WAVE
(114)
(115)
could be critical enough to cause loss of contact between the
ballast and the sleeper soffit resuting in the loss of lateral ballast
resistance thereby making the track buckleprone (Fig7.5(a)&(b)).
2) Tractive and braking forces applied by the moving train
change the force level in the LWR and continuous braking
at a given location could result in buildup of compressive
forces creating buckling tendencies in the rail.
3) The hunting motion of the moving train over lateral
mislignments in the track could create large lateral forces
producing buckling tendencies.
4) Vibrations induced by the moving train could disturb the
ballast and lower the lateral ballast resistance.
7.5 Dynamic Track Buckling Model:
The effect of a moving train increasing tendency of a track to
buckle when the temperatures are rising or the response of the
track to disturbing lateral forces is depicted by what is called
DYNAMIC TRACK BUCKLING MODEL. This model is essentially a
relationship between the lateral track displacement and the
temperature increase over the force free or neutral temperature.
The model is depicted in the figure (Fig7.6).
The model has 3 limbs as shown: AB is the prebuckling limb while
D
TBMAX
Temp Rise above TN
B
2
1
TBMIN
TN
Displacement
(116)
BC and CD are post-buckling limbs. At B when the temp. rises to
TBMAX the track becomes unstable where even an infinitesimal
lateral force will cause the track to buckle. Below temp TBMIN at
point C, even a large force will not be able to buckle the track.
Between points B and C a moving train could impart sufficient
force to buckle the track. Between B and 'C' the track on buckling
will first move to an unstable buckled phase on curve BC and
subsequently to a stable buckled phase on CD. It is assumed that
if the track can be brought into position 2 it will automatically move
into position 3. At TBMAX, the energy required to buckle a track is
almost zero while below TBMIN the energy required to buckle a track
is much larger than that which could be provided by a moving
train. Between TBMAX and TBMIN, the transition from the pre-buckling
stage to the unstable buckled state and to the stable buckled state
could be effected under the influence of energy imparted by the
moving vehicle.
Various softwares have been developed to predict the TBMAX and
TBMIN temperatures for given track and rolling stock parameters. In
the USA, the program developed is called CWR-BUCKLE. Other
software programs are CWRSAFE and related programs. The
inputs to these programs are :
1)
Rail section
2)
Track curvature
3)
Rolling stock characteristics
4)
Lateral ballast resistance
5)
The misalignment in the track.
Using these programs the TBMIN and TBMAX of the given track for a
given set of parameters are determimed. The policies regarding
LWR maintenance can then be decided. These could include :
1) Allowable Temperature rise above tn for maintenance
activities
2) Temperature at which track enters the danger zone, and
necessitates hot weather patrolling.
7.6 CWR Safety Assurance Program:
The discussion above could form the basis of a continuous welded
track buckling safety assurance program. For safe operations of
CWR track with respect to buckling, the allowable temperature
increase TALL over the neutral temperature should be greater than the
(117)
difference between the maximum anticipated rail temperature TMAX
on a given day and the neutral or stress-free temperature Tn i.e.
TALL > (TMAX-Tn)
The expression on the right is the anticipated rail temperature rise
over Tn while TALL is the allowable temperature rise which could be
determined from the values of TBMIN and TBMAX.. TALL will be
somewhere between these two extreme temperature values
depending upon the track parameters,level of maintenance and
monitoring and the degree of risk the railway administration is
willing to take. A conservative approach would be to fix the TALL at
TBMIN value. However, a better approach would be to fix TALL higher
than TBMIN if the railway has good track maintenance and
monitoring procedures in place.
The expression given above indicates that for a safe CWR
assurance program two temperatures need to be determined:
(i) TALL which is the allowable temperature rise above the
neutral temperature for a given set of track and vehicle
parameters.The single most significant factor which will
govern TALL for a given set of track and rolling stock
parameters is the lateral ballast resistance. The
ralationship between TALL and the lateral ballast resistance
will be in the form of a graph. This could be given to the
field maintenance engineer to enable him to predict the
allowable temperature rise over the neutral temperature for
a given value of the lateral ballast resistance. (Fig 7.7)
(ii) The neutral temperature or the stress free temperature of
the track.
7.7 Field Determination of the lateral ballast resistance:
A convenient metod to determine the lateral ballast resistance per
sleeper has been developed in the USA.It is called the single tie
push test (STPT).
Test Methodology: The rail is freed from the sleeper by removing
the fastenings and using a hydraulic jacking equipment the tie is
pushed transversely to the track. With load transducers and
gauges, the loads and corresponding displacements are recorded.
The plot gives the maximum lateral resistance of ballast. For getting
the average value the test could be performed on 3 sleepers over a
50 feet length. Once the lateral ballast resistance value is obtained
(118)
(119)
P = AE [t P t n ]
The above expression also indicates that if due to any reason the
value of tn were to fall, it would automatically increase the
compressive force in the rail and beyond a certain level could
cause the track to buckle. Another way of putting it is that a
change in the rail neutral temperature is equivalent to changing the
force level in the rails for the same values of tP .
7.8.2 Factors which could cause a shift in the Rail Neutral
Temperature:
1) Movement of the rail in the longitudinal, lateral and vertical
directions : If the CWR were to be fully constrained, then there
would be no change in the neutral temperature. Since the rails
cannot be fully constrained in all directions, elongation or
contraction can occur whenever the track is subject to train and
environmentally induced loads. Railway track motions relevant to tn
variation occur in the following three basic kinematic modes :
(i)
Rail longitudinal movement
(ii)
Track lateral shift
(iii)
Track vertical settlement.
Consider a CWR being laid at Temperature tL and there is no rail
longitudinal force at this temperature. Assume that the rail
displacements (u,v and w in the longitudinal, lateral and vertical
directions respectively) are measured with respect to an initial
equilibrium configuration when the rail temperature is tL. These
displacements may be due to a number of causes, and in many
cases are not recoverable due to the inelastic nature of the ballast.
From the displacements, the longitudional strain x in the rail at
any given temperature tP can be calculated from the fundamental
equations of theoretical mechanics.,
u 1 v 2 1 2
x = + +
+ [t P t L ]
x 2 x 2 x
[t P t L ]
longitudinal x direction.
The force in the CWR at tP in the longitudinal x direction will be
(120)
P=AE x
2
2
1 u 1 v 1
= AE t P t L + + +
x 2 x 2 x -------1
P = AE [t P t n ] -------------2
1
tn = tL +
where
u 1 v 2 1 2
+ +
x 2 x 2 x
u v
,
, and
are all tensile strains.
x
x x
1
then t n = t L +
u V 1 v 2 1 2
+ + +
x R 2 x 2 x
ii)
(121)
in excess of or below the balance speed. For tangent
track, the effect of lateral movement on the neutral
temperature shift is likely to be small. For curved
track, however, the shift can be significant.
iii)
1.
Rail/Track Maintenance
activities involving lining,
application of rail anchors,
will cause a shift in neutral
Track maintenance
lifting, removal or
trackline repairs all
temperature.
2.
(122)
3. The technique should be independent of longitudinal
residual stresses in rail. The residual stresses are not
associated with the rail longitudinal force since they are
self-equilibrating in the sense that their resultant force and
moment are zero. As a result, any technique which relies
on measurement of local stresses for the longitudinal force
can have large errors.
4. The technique should be non-destructive.
5. The
technique
should
be
measurements within +10C.
fairly
accurate
with
(123)
7.8.3.2 Of the number of techniques available for neutral
temperature measurement, the following can be considered as
reasonably developed :
l
Wheatstone
(124)
Besides the longitudinal force, the deflection is dependent on the
rail flexural rigidity, EI, applied load Q and the nature of the end
constraints. It is necessary to design a rig such that for all
locations and measurements, the end conditions are sufficiently
repeatable. As far as the end conditions are concerned, they
depend upon the nature of constraint provided by the rig.
Generally, the conditions are elastic supports (in between pure
simple supports and completely fixed supports). Fixed support
conditions improve the sensitivity, but need large applied loads.
Repeatability of the end conditions is an important consideration
for successful application of the technique.
The deflection is given by
QL3 1
=
(1)
EI 1 C
Pc
where C is the longitudinal compressive force in the rail
Q = Verticle load applied at centre of rail.
POWER PACK
(125)
T = 25 TONS
T = 50 TONS
T = 75 TONS
T = 100 TONS
(126)
T= tensile force
C= compressive force
Q= centrally applied
load
D = deflection at
centre
T = C = 0
C = 25 TONS
C = 50 TONS
C = 75 TONS
C = 100 TONS
D
Fig. 7.10 Graphical Method for neutral temperature
determination.
(127)
(128)
rail head wear and rail grinding which will naturally affect the
stiffness of the rail. Validation of VERSE technique has been
carried out by AEA Technology, one of Britains leading
technology companies.
(129)
List of References:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
(130)
13.
14.