Acid Cleaning
Acid Cleaning
Acid Cleaning
OBJECTIVE : To remove the grease & protective coating from the boiler tube surface by filling the
boiler with alkaline solution & then lighting up the boiler , raising the pressure to 40 ksc , holding at 40
ksc & giving blow down as per the steps described below . The process is known as the alkali boil out
of new boilers .
COMPLETION CRITERIA :-
Minimum 8 Nos of blow down or the oil level in blow down sample is < 5 ppm .
SH back flushing with N2H4 & NH3 so that PO4 < 2ppm .
= 200 KG
REQUIREMENTS FOR BOILER ALKALI BOIL OUT :Boiler is ready for light up as per 1 st light up requirement given in annexure - 1 .
Furnace expansion constraints are checked & removed by joint walk down check from boiler top
to Bottom ring header .
Page 1 of 7
H-1
PROCEDURES :The total alkali boil out procedure is divided into the following sub procedures as outlined below .
Chemical preparation & boiler filling procedure .
Boiler light up & pressurisation to 40 ksc procedure .
Blow down & sampling procedure .
After completion of blow down boxing up procedure .
Cooling down of boiler & monitoring .
Boiler draining .
Boiler refilling , SH back filling & boiler draining .
Inspection of boiler drum / bottom ring header & cleaning .
Page 2 of 7
H-2
Page 3 of 7
H-3
Once 4 hrs passed at 40 ksc the boiler is ready for its 1 st blow down .
Try to maintain 8-9 ports water level in the drum & make up fully lined up to take level as early as
Inform control room to Hand trip the boiler .( close the start up vents one valve in each line i.e
S81/S82)
Open the bottom ring header drain valve B-92 electrically from local .(30 sec to full open)
At the expire of one minute close the electrically operated valve B 92 full .
Then collect the sample from sample cooler discharge with care so that it should not fall on hand .
The sample is to be analyzed for alkalinity , Phosphate , silica , oil content .
Once the main valve B - 92 is closed give clearance to start the boiler (light up). Open the start
up vents .
Then close the manual isolation valves in drain line & main drain to IBD . Isolate the sample
Now open the manual valve B 89 up to the 20 % opening mark very fast .
Once it opens 20 % , count 1 minute .
cooler .
Boiler Light up & Raising the Boiler pressure to 40 ksc . & maintain for 2 hrs at this
pressure .
Keep all 4 oil guns in service . Raise the Boiler pressure to 40 Ksc , then reduce oil pressure to
minimum 3.5 ksc to maintain the pressure . Keep it at 40 ksc for 4 Hrs .
H- 4
H-5
Page 4 of 7
H-6
inlet gate, guide vane , discharge gate all full open . SADC shall be full open .
Close the SH start up vents .
Stop the LDO pump at FOPH .
Isolate the oil valves at all corners & at oil station in firing floor as well .
MDBFP-C shall be in service till boiler pressure drops down as HP purge is in service . This can
only be stopped after switching over to LP purge from boiler fill pump .
Take makeup as per requirement
At drum metal temp of 90 0 C open the drum vents . At this point only one BCW pump can be kept
H-8
in service .
At BCW pump suction manifold temp of 90 0 C or less stop the BCW pump .
Now the boiler is ready for draining .
Boiler draining .
Before draining the boiler the C row drain & main drain shall be clear .
Dilution water should be arranged by fire hydrant water or # 3,4 side settling bin water can be
To drain the boiler open the bottom ring header (Rear) drain to drain header full both manula &
MOV B92 .
Open the economiser inlet header drain both manual & MOV E 18 full .
Now slowly open the main drain valve to IBD tank initially 25 % . After measuring the pH & the
H-9
H-10
Once temp picked up 80 0 C boiler is to be filled till one port is visible in the drum via both bottom
Monitor the drain water for residual PO4 in both boiler & SH water
cleaning .
Thoroughly clean the boiler drum & bottom ring header .
Boiler drum primary separators are to be removed for Making ready for Acid cleaning .
Page 5 of 7
2.
3.
4.
Disodium phosphate
Filling shall be done simultaneously with both the Bottom ring header & Economiser .
Boiler will be lighted up & pressurized to 40 ksc
Holding at 40 ksc for 4 hrs
Sample to be taken from CBD sampling point .
5.
6.
Measurement for
Alkalinity
Phosphate
Dissolved Silica
Oil Content
If the phosphate content drops to < 50 % of initial value then dose phosphate again .
Fire out the boiler
Blow down through the bottom drain hdr drain to IBD . Keep open the valve for 1 minute
.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Page 6 of 7
ANNEXURE - 3
OTHER REQUIREMENTS CHECK LIST.
AA
1.
Boiler roof hdr all hangers are released & all tie rods are in position . Necessary inspection & clearance
2.
3.
4.
5.
6.
7.
MAIN BOILER .
From the Mixing tank area pump discharge to the Bottom drain hdr stub provided for alkali boil out .
Drain line from EBD tank to the nearest plant drain where the blowdown as well boiler draining is to
be done after alkali boil out is completed .
8.
9.
10.
Sampling point is provided from the bottom drain hdr . Temporary Sample cooler is erected , cooling
water provided from boiler fill line . Cooler discharge is provided to the nearest plant drain .
LP purge from boiler fill pump is available .
HP purge from BFP discharge is flushed for all 3 BCW pumps & sample result is with in limit .
Boiler is completely drained including economiser , SH/RH etc .All drain valves are in open position &
respective main valves are also open
BB
1.
Mixing tank is filled , leakage checked , if any attended , tank flushed & drained . Tank level monitoring
2.
3.
4.
5.
6.
7.
8.
9.
Page 7 of 7
Annexure I
ACTIVITY
Status
BOILER
ID FAN 4A
Lube oil flushing
VFD room A/C plant commissioning.
Cooling water pipe flushing & charging.
VFD panels commissioning.
Charging of VFD transformers.
ID Fan motor trial.
Inlet guide vane calibration and remote operation.
Ducts checking and clearance including air leak test.
ID Fan interlock & protection checking.
ID Fan trial.
2.0
i)
ii)
iii)
iv)
v)
FD FAN 4B
Lube oil flushing.
Motor trail run.
Flushing of cooling water lines and charging.
Interlock & protection checking.
Fan trail run.
3.0
i)
ii)
iii)
iv)
v)
vi)
vii)
CC Pumps
Purge line flushing & Cavity filling
Booster pump motor trail
Booster pump trail
O/H tank with pneumatic control valves auto operation.
Interlock & protection checking.
Pump trail 4C
Pump trail 4B
4.0
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
SAPH 4B
Lube oil flushing.
Cooling water readiness for lube oil pumps.
Motor trail run.
SAPH trail with air motor
SAPH trail with electric motor
Soot blower commissioning.
Fire fighting system flushing and readiness.
Water washing system flushing and readiness.
Rotor stoppage alarm
Commg of hot spot detection system. (fire sensor)
5.0
i)
ii)
iii)
Page 8 of 7
iv)
v)
6.0
7.0
i)
ii)
iii)
iv)
v)
8.0
i)
ii)
iii)
iv)
v)
9.0
i)
ii)
10.0
i)
ii)
iii)
iv)
v)
vi)
11.0
i)
ii)
iii)
iv)
C&I SYSTEM
FSSS system readiness.
SADC
DDCMIS
Availability of measurements and alarm pertaining to Secondary
air, Flue gas, Feed water, Steam, Boiler metal temp. points, Drum
level indication and drum pressure indicator at UCB.
12.0
i)
ii)
iii)
iv)
PA SYSTEM
PA system at ID Fan area.
PA system at LHS & RHS at drum level
PA system at FD Fan area.
PA system at operating floors.
Page 9 of 7
13.0
II
i)
ii)
iii)
iv)
ESP (Pass A)
Mechanical readiness of ESP internals.
Charging of ACP
Commissioning of rapping system.
Completion of insulation.
III
1.0
TG
TG ECW PUMPS
Motor trail
Interlock & protection checking.
ECW tank readiness.
Coupled trial run of TG ECW pumps
2.0
SG ECW PUMPS
Motor trail
Interlock & protection checking.
Coupled trial run of TG ECW pumps
3.0
MDBFP 4C
Lube oil flushing
Motor trial run
Interlock/ protection check of motor & voith coupling
HC scoop commissioning.
Motor + voith coupling trial run
Hydraulic test of feed line.
Deareator readiness with all instrumentation
Interlock/ protection check of pump.
Coupled trial run of MDBFP - 4C
4.0
ACW PUMPS
Motor trail
Interlock & protection checking.
Coupled trial run of ACW pumps
5.0
CW PUMPS
CWP 4A Motor trail
Interlock & protection checking.
Coupled trial run of CW pump 4A
6.0
APRDS
Auxiliary steam
IV
ELECTRICAL SYSTEM
Page 10 of 7
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
11 KV SWITCHGEAR
3.3 KV SWITCHGEAR
415 V SWITCHGEAR
220 V BATTERY & CHARGERS
UPS BATTERY & CHARGERS
24 V BATTERY & CHARGERS
LIGHTING
DG SET
VI
1.0
2.0
3.0
AIR-CONDITIONING
A/C OF CER
A/C OF VFD
A/C OF ESP
VII
1.0
2.0
COOLING TOWERS
CW channel
Cooling tower 4B
VIII
1.0
2.0
Page 11 of 7
Mechanical
readiness
AS 6
Ready
AS10
Ready
AS114
Ready
CHD 7
CHD 13
FD 6
FD 11
Ready
FD 12
Ready
FD 13
Ready
10
FD 16
Ready
11
12
Ready
Ready
Ready
Ready
Ready
13
ECW 8
Ready
14
ECW 9
Ready
15
16
17
Local commg
Ready
Ready
Ready
18
ECW
Ready
19
ECW
Ready
20
ECW- 64
Ready
Page 12 of 7
Remote
commg
Valve No
Description
No
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
E18
E19
B92
B 86
B 88
E2
E2A
B 21
B 85
B 87
B 81
B 68
B 83
B 82
B 69
B 84
B 72
B 73
B 76
B 77
B 74
B 75
B 78
B 79
S 74
26.
S 75
header (left)
SH DIV panel drain to SH drain
S23
S25
S21
S22
S19
S24
S26
S77
S76
S 11
S12
S 13
S14
header (right)
BP lower rear header Left
BP lower rear header Left
BP lower front header drain
BP lower front header drain
SH roof I/L header drain
BP lower rear header drain right
BP lower rear header drain right
SH platen I/L header drain
Platen SH in let header drain.
SH roof O/C header vent left
SH roof O/C header vent left
SH roof O/C header vent Right
SH roof O/C header vent Right
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
Mechanical
Local commg
Page 13 of 7
Remote commg
Sl
No
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
Valve No
Description
S68
S69
S70
S71
vent
Div panel to SH platen I/L header
S79
S81
S82
S83
S84
MS - 1
MS 3
MS 5
MS 2
MS 4
MS 6
S 85
S 87
S 86
S 88
vent
SH O/L header vent
SH start up vent
SH start up vent
SH start up vent
SH start up vent
MS stop valves (Boiler left)
IBV of MS 1
IBV of MS 1
MS stop valve (Boiler right)
IBV of MS 2
IBV of MS 2
Electromotive relive valve MS left.
IBV to ERV - S 85
Electromotive relive valve MS right.
IBV to ERV - S 86
Mechanical
Local commg
Ready
Ready
Page 14 of 7
Remote commg
Valve/gate No
1.
Desc
ription
HID fan - B inlet gate.
NC 02AA 201
2.
3.
LA 20 AA201
LA 20 AA 202
7.
LA 20 AA 203
8.
Over
R
eady
NA 44AA 202
R
eady
R
eady
R
eady
R
eady
R
eady
20.
Over
17.
eady
NA 44AA 201
16.
Over
15.
eady
NA 43AA 202
14.
Over
eady
13.
R
eady
eady
NA 43AA 201
12.
Over
eady
11.
eady
19.
10.
Over
eady
R
R
6.
Over
eady
NC 02AA 204
5.
Over
Over
eady
eady
R
eady
21.
22.
R
eady
23.
NA 40 A201,202
R
emote
commg
eady
NC 02AA 203
4.
L
ocal commg
eady
NC 02AA 202
18.
M
echanical
Over
eady
HCommon damper flue gas to
ESP
C& D pass.
R
eady
Page 15 of 7
Over
24.
25.
26.
27.
R
eady
R
eady
LA 20 AA206
29.
R
eady
R
eady
Over
eady
FE30 AA204
33.
R
R
32.
Over
eady
FE30 AA205
31.
eady
LA 10 AA206
30.
Over
eady
205
28.
R
eady
R
eady
Page 16 of 7
OBJECTIVE : To remove the patchy mill scale & rust from boiler heat exchanging surface i.e
water wall , boiler drum , down comer pipes ,economiser and excluding the SH /RH circuit by acid
cleaning process after successful alkali boil out is completed .
RESPONSIBILITY :-
COMPLETION CRITERIA :-
ACID/CHEMICAL REQUIREMENTS :-
SL
NO
1.
2.
3.
4.
5.
6.
ACID
Hydrochloric acid (HCL)
Rodine
Ammonium Bifloride
Blr water
Quantity required
Concentration in %
5 % +/- 1 %
0.20 %
0.25 %
in tons
solution
7.
8.
Bleaching powder
0.2 %
acid rinse
Neutralization
Hydrazine/ammonia
process
Passivation process
hydrazine/pH 10
PH 5.5-9.0
For neutralization of
acid
For neutralization of
hydrazine /ammonia
:-
:-
PROCEDURES :-
Page 17 of 7
H-1
BB
OTHER REQUIREMENTS :Drum internals are removed & inspected after alkali boil out & boxed up.
Bottom ring header manholes are opened for inspection /cleaned / checked for tightness of all
perforated panels & boxed up.
Sample piece is joint tested for inhibiter effectiveness ( RODINE)
Sample piece is made ready to put inside the drum during acid cleaning
Temporary pipe lines are laid as per the scheme attached .
Drum gauge glass to be replaced with a rubber/plastic tube arrangement
Nitrogen cylinder arrangement at 0 mtr for capping after acid cleaning . (during draining process)
Valves to be provided in filling line to suction manifold, economizer, ring header etc
Readiness of temporary system such as
o Boiler filling to be completed with in 1 hr
o LP purge water at 8-10 ksc near the BCW pump on continuous basis .
o Draining of the boiler with in 1 hr
o Telephone connections to the Boiler fill pump area / Acid cleaning area / Drum level
o
CC
DD
D-1.0
ACID CLEANING PROCEDURE STEP BY STEP :BOILER FILLING WITH DM WATER & LIGHTING UP THE BOILER TO RAISE THE
TEMP. TO 80 0C BEFORE GOING FOR ACID INJECTION :-
Fill the boiler through the bottom ring header /economizer / up to the bottom gauge glass . Then stop
filling .
Start back filling of the SH at hydrazine 200 pip & pH >10 till it over flows to the drum . stop filling
Light up the boiler as per procedure
EBD/CBD should be full closed & vent valves to be full open .
Stop the boiler once drum metal temp. & BCW pup suction manifold temp. >/ 80 0C . Box up the
Page 18 of 7
D-2.0
D-3.0
Fill the boiler with 60-70 0C water from the 250 mm temporary header through
WW drain / Eco drain/ BCW pump suction manifold drain ( 2 lines of 120 mm)
Start injection of chemicals at the suction of the filling pump through the acid pump & regulation
D-2.0
The temp. of the water & acid mixture dosed is to be regulated with in 60-70 0C.
Once the boiler drum level is at the bottom port stop filling through suction manifold .
Fill the boiler up to the drum level is 100 mm above center line .
Start Boiler Water Circulating (BCW) pump B (center pump)
FILLING OF BOILER ALONG WITH ACID INJECTION :Collect sample from BCW pump discharge header & record them as per the annexed log sheet .
After 30 min stop the pump & allow the acid for soaking.
After 30 min again start the BCW pump & run for 5 min & stop .
Take sample at 10 min interval .
Continue this process till the iron content is in equilibrium n for 3 consecutive sample .
The total time allowed for this exercise is 6 hrs including (the filling 1 hr &draining 1 Hr)
Stop BCW pump B .
Then keep the N2 capping system ready .
Start draining the boiler under N2 capping to the neutralization Pit near # 6 .
Maintain the N2 capping pressure at 0.5 ksc to 1.0 ksc
D-4.0
to 8-9 ports .
Run BCW-B for 5 min .
Take sample from BCW discharge & point A
Drain the boiler
Continue this operation till the sample result pH is 4-5 .
AMMONIATED CITRIC ACID RINSE AFTER DM WATER RINSE :Fill the boiler with 60-70 0C water from the 250 mm temporary header through
WW drain / Eco drain/ BCW pump suction manifold drain ( 2 lines of 120 mm)
Start injection of citric acid solution prepared at the suction of the filling pump through the acid
stop .
Collect sample from BCW pump discharge header after stopping the pump & record them as per
Page 19 of 7
D-5.0
D-6.0
Fill the boiler with 60-70 0C water from the 250 mm temporary header through
WW drain / Eco drain/ BCW pump suction manifold drain ( 2 lines of 120 mm)
Raise the water level up to +100 mm mark
Operate the BCW pump for 5 min .
Stop the pump & drain the boiler under nitrogen capping .
Continue the boiler filling & draining operation till the sample at pointB is having IRON < 25 ppm .
Maintain the N2 capping pressure at 0.5-1.0 ksc .
NEUTRALISATION OF THE BOILER SYSTEM :U Tube manometer to be replaced with normal gauge glass
Preparation of neutralizing solution & feeding to the boiler along with DM water like acid filling
PASSIVATION OF BOILER :-
Fill the boiler with DM water & inject the prepared blended solution so that the final water having
EE
D-7.0
At 95 0C stop the BCW pump & drain the boiler under atmospheric pressure & aerate the system
After cool down open the upper & lower drum for inspection
Manually clean them , refit the drum internals etc .
Restore all temporary connections make the boiler available for steam blowing .
:-
As soon as the acid is drained to the neutralizing pit caustic soda is added to neutralize .
As soon as the citric acid is drained to the neutralizing pit caustic soda is added to neutralize .
Neutralization of Hydrazine & ammonia by bleaching powder .
Page 20 of 7
Sl
no
1.
2.
3.
4.
5.
6.
7.
Activity
Start Time
Complete Time
Remarks
( It Should Take 1 Hr)
PROCESS : BOILER FILLING & ACID INJECTION WITH ACID PICKLING &
SOAKING
Sl
Activity
no
1.
2.
3.
4.
5.
centerline ( 7 ports)
1 st Starting of BCW pump - B
Boiler Draining
Start Time
Complete Time
Remarks
( It Should Take 1 Hr)
Water temp.60-70 0 C
Acid concentration 5 % +/- 1%
Page 21 of 7
Time
Sample no
Sample Result
Remarks
( 5 %+/-1% )
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
Page 22 of 7
Time
Sample
no
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Note :
Iron Content
Remarks
Starting Of BCW pump for 30 min
Stopping of BCW pump for 30 min
Starting Of BCW pump for 5 min
Stopping of BCW pump for 30 min
Sampling at 10 min interval
Starting Of BCW pump for 5 min
Stopping of BCW pump for 30 min
Starting Of BCW pump for 5 min
Stopping of BCW pump for 30 min
Starting Of BCW pump for 5 min
Stopping of BCW pump for 30 min
Starting Of BCW pump for 5 min
Stopping of BCW pump for 30 min
Total time allowed for acid inside the boiler including filling & draining
should not be more than 6 hrs .
Page 23 of 7
Sl
no
1.
Activity
Start Time
Complete
Remarks
Time
Boiler Filling through
Eco/WW/BCW suction
Water temp.60-70 0 C
manifold up to 50 % in the
gauge glass
2.
3.
SH back flushing
1 st Starting of BCW
4.
5.
6.
discharge hdr.
1 st Boiler Draining
Boiler Filling through
Eco/WW/BCW suction
Water temp.60-70 0 C
manifold up to 50 % in the
gauge glass
7.
8.
9.
discharge hdr.
2nd t Boiler Draining
10.
ksc
( It Should Take 1 Hr)
Eco/WW/BCW suction
Water temp.60-70 0 C
manifold up to 50 % in the
gauge glass
11.
12.
B for 5 min
Collect sample from BCW
13.
discharge hdr.
3rd Boiler Draining
Time
Sample no
Sample Result
Time
Sample no
PH 4 - 5
1.
3.
5.
Sample Result
PH 4 - 5
2.
4.
6.
Page 24 of 7
Sl
no
1.
Start Time
Complete
Time
Remarks
( It Should Take 1 Hr)
Water temp.60-70 0 C
2.
3.
4.
5.
6.
BCW pump
Boiler Draining
Time
Sample no
Sample Result
( 0.2 % )
Remarks
1.
2.
3.
4.
5.
PROCESS : Chemical sampling during citric acid pickling & soaking Sampling
interval 5-10 minutes ,Sampling point B ( discharge of BCW pump)
Time
Note :
Sample
no
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Acid %
Iron Content
Remarks
1 st Starting Of BCW pump for 5 min
Stopping of BCW pump for 30 min
2 nd Starting Of BCW pump for 5 min
Stopping of BCW pump for 30 min
Sampling at 10 min interval
3 rd Starting Of BCW pump for 5 min
Stopping of BCW pump for 30 min
4 th Starting Of BCW pump for 5 min
Stopping of BCW pump for 30 min
Total time allowed for this process is min 4 hrs & max 5 hrs .
Page 25 of 7
Activity
Start
Complete
Time
Time
Remarks
Water temp.60-70 0 C
2.
3.
min
Collect sample from BCW discharge
4.
hdr.
1 st Boiler Draining
5.
Water temp.60-70 0 C
6.
7.
min
Collect sample from BCW discharge
8.
hdr.
2nd t Boiler Draining
9.
Water temp.60-70 0 C
> 4-5
( It Should Take 1 Hr)
10.
11.
min
Collect sample from BCW discharge
12.
hdr.
3rd Boiler Draining
Time
Sample no
Sample Result
Time
Sample no
2.
4.
6.
Page 26 of 7
Sl
Activity
no
1.
N2 capping to be maintained at
2.
injection .
After Boiler filled open the drum
3.
4.
5.
6.
7.
8.
vents .
Starting of BCW pump - B
Boiler Light Up
Raising the pressure to 10 ksc
Hold the pressure for 6 hrs .
Blowing off all instruments
Kill the fire after 6 hrs is
9.
10.
complete .
Allow natural cooling of the boiler .
Stop BCW-B after drum metal
11.
temp. is 90 0C .
While draining the boiler back
Start Time
Complete Time
Remarks
0.5 ksc .
ammonia .
Draining of the boiler with drum
vents open & no N2 capping is
required.
Page 27 of 7
Activity
no
1.
N2 capping to be maintained at
2.
injection .
After Boiler filled open the drum
3.
4.
5.
6.
7.
8.
vents .
Starting of BCW pump - B
Boiler Light Up
Raising the pressure to 10 ksc
Hold the pressure for 6 hrs .
Blowing off all instruments
Kill the fire after 6 hrs is
9.
10.
complete .
Allow natural cooling of the boiler .
Stop BCW-B after drum metal
11.
temp. is 90 0C .
While draining the boiler back
Start Time
Complete Time
Remarks
0.5 ksc .
ammonia .
Draining of the boiler with drum
vents open & no N2 capping is
required.
Page 28 of 7
Activity
Start Time
Complete Time
Remarks
no
1.
7.
8.
9.
10.
temp. is 90-95 0C .
Drain the boiler under atmospheric
No N2 capping is required.
condition .
Page 29 of 7
Sl
no
CHEMICAL
Draining of chemical
Start
Complete
Time
Time
Neutralisation details
Start
Complete
Time
Time
Neutralisng
Effluent
chemical
result
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Page 30 of 7
DESCRIPTION
no
Chemical used
Quantity
used
Filling criteria
Boiler light
up required
Pressure
Waiting
/Temp raise
time/approx.
to
time
Completion
criteria.
Drum metal
1.
temp &
NIL
NIL
Only DM
water in 1 hr.
BCW pump
YES
80 C
suction
manifold
injection .
temp. is >
80 0 C
2.
3.
NIL
HCL
NIL
NIL
ACID
NIL
concentratio
n shall be <
5.
6.
7.
8.
pickling/soaking is completed ( 6
hrs activity) :
Ammoniated citric acid rinse after
DM water rinse :
Demineralised water rinse :
Neutralisation of the boiler
system :
Passivation of boiler :
Page 31 of 7
DESCRIPTION
no
9.
Time of
Time of
Total time
required
start
completion
required
10.
11.
12.
13.
14.
15.
16.
injection .
Draining the boiler
Filling of boiler along with acid
injection .
DM water rinse after acid
pickling/soaking is completed ( 6
hrs activity) :
Ammoniated citric acid rinse after
DM water rinse :
Demineralised water rinse :
Neutralisation of the boiler
system :
Passivation of boiler :
Page 32 of 7