Alkali Boil Out Procedure
Alkali Boil Out Procedure
Alkali Boil Out Procedure
CHAPTER – 7
CHEMICAL CLEANING AND ALKALI BOIL-OUT
In order to prevent fouling of internal parts having small clearances during the internal
boil out and acid cleaning, the drum internals / corrugated plates are not eroded.
However, they are to be thoroughly cleaned with wire brush air or steam blown before
installation.
It is essential to have spare gaskets for upper and lower drum inspection has to be
carried out after alkali boil and after chemical cleaning to ensure effectiveness of the
alkali boil out and chemical cleaning.
Document No. :
ENG/R0/63/15
PT. MAXITHERM BOILERS INDONESIA
Edition : 2016
Revision : 0
i) Alkali cleaning
This is a most commonly used method of boiler cleaning and case of newly erected
boiler, it is carried out on completion of drying out operation.
Chemicals used must never be introduced in solid form but must first be dissolved in
water and introduced in to the boiler system through either the chemical injection
equipment or through the drum manhole. In the latter case the water level must be
lowered by draining and then restored again afterwards.
All phosphate formula is used for alkali boil out of boiler to minimize the potential for
stress corrosion cracking of stainless steel components in the event that some chemicals
were spilled in to the super heater. If the phosphate solutions enter the super heater (If
applicable)they must be flushed out, but by omitting caustic forming chemicals, the
impact of trace residuals on the super heater (If applicable)is reduced. TRISODIUM
PHOSPHATE and DISODIUM PHOSPHATE are used for alkali boil out. These are to be
mixed with warm / hot water.
Boil-out chemicals are highly caustic. Caustic Soda Ash will produce a violent
flash if introduced to water too rapidly. Employees handling the chemicals must
wear protective equipment, I.E. Goggles, gloves, aprons, etc.. and an emergency
shower should be nearby. Use vinegar as an antidote.
The boil-out chemicals shown, in above figure, are intended to serve as only a general
guide. It is strongly recommended that the Client retain a water treatment consultant with
expertise in the field of industrial boiler water chemistry to select the boil out chemicals
and be available to provide consulting direction as required.
r) Close al manholes using new gaskets necessarily. If chemical for pressure boil out
are to be introduced through steam drum manhole, one of this must kept open.
s) Close all blow down and drain valves except super heater (If applicable) drain valve,
which must be left open.
t) The boiler is now ready for the pressure boil out.
Add chemical solution when boiler water alkalinity and phosphate level drops to half the
original values. Do not over-add chemicals. Maintenance of chemical concentration must
be carefully controlled. Excessive caustic can cause embrittlement of the metal.
Never allow temperature of gases entering super heater (If applicable) zone to rise
above normal working steam temperature of super heater (If applicable) until a positive
flow of steam is established through open super heater (If applicable) drain valve.
Water level in gauge will rise to ½ glass as heat is absorbed and water expands. This
level must be maintained.
is required with all procedures. This piping and any noise reduction silencers must
be securely anchored to resist the high nozzle reaction created during the high
velocity blowing period.
Several methods are used for blowing steam lines, including particularly high
pressure air and steam blowing. The recommended method and the one most used
is steam blowing because experience has shown that temperature shock and high
velocities are the most effective means of removing loose scale. Sufficient shock is
obtained with a series of blows where the steam temperature changes during each
blow. Lower pressure, high velocity steam blowing techniques are also available,
injection to promote thermal shocking of the mill scale and debris. Designed and
managed correctly, these techniques provide safe removal of scale and other solid
particles detrimental to turbine components.
There are two basic methods of supplying steam for steam line blowing with a
natural or forced circulation boiler. The second method is to use high pressure
steam directly from the boiler. The latter method supplies large quantities of steam at
higher pressures. Temporary valve is required to control the flow rates during the
blowing period.
Boiler pressure and temperature can be maintained during the blowing period by
continuous firing. If firing is discontinued during the blowing period, it must be
remembered that any change in boiler pressure changes the saturation temperature
throughout the system. To avoid excessive thermal shock, changes in boiler
pressure should be limited to those corresponding to 75F (42 oC) in saturation
temperature during the relatively short blowing periods.