Chiiler Design PDF
Chiiler Design PDF
Chiiler Design PDF
Chiller Plant
Design
CHILLER 1 CHILLER 2
CHILLED
WATER
PUMP
3-WAY
VALVES
LOADS
SECONDARY PUMP
VFD
PRIMARY PUMP
1920 gpm
44F 44F
44F
CHILLER
CHILLER
3840 gpm
44F
400 400 A LOAD
(DECOUPLER)
TONS TONS 800 TONS
640 gpm COMMON
PIPE
44F 50F
B
49F 49F 3840 gpm 3200 gpm
50F
49F
Table of Contents
Introduction........................................................................................................................... 3
Hybrid Plants....................................................................................................................... 19
NOTICE
The information contained within this document represents the opinions and suggestions of
McQuay International. Equipment, and the application of the equipment and system suggestions
are offered by McQuay International as suggestions only, and McQuay International does not
assume responsibility for the performance of any system as a result of these suggestions. The
system engineer is responsible for system design and performance.
Chiller
The chiller can be either air- or water-cooled.
The compressor types typically are recipro-
cating, scroll, screw or centrifugal. The
evaporator can be remote from the condensing
section on air-cooled units. This has the
advantage of keeping the chilled water loop
inside the building envelope when using an
outdoor chiller.
The chilled water flows through the evaporator
of the chiller. The evaporator is a heat
exchanger where the chilled water gives up its
sensible heat (the water temperature drops)
and transfers the heat to the refrigerant as
latent energy (the refrigerant evaporates or
boils).
Assuming the fluid is water, the formula takes the more common form of;
Load (btu/hr) = Flow(USgpm) x (Fin Fout) x 500 (2)
Or
Load (tons) = Flow(USgpm) x (Fin Fout)/24 (3)
Using this equation and the above design conditions, the temperature change in the
evaporator is found to be 10F. The water temperature entering the evaporator is then 54F.
Most air conditioning design conditions are based on 75F and 50% RH in the occupied
space. The dew point for air at this condition is 55.08F. Most HVAC designs are based on
cooling the air to this dewpoint to maintain the proper RH in the space. Using a 10F
approach at the cooling coil means the supply chilled water needs to be around 44F or 45F.
The designer is not tied to these design conditions. In fact, more energy efficient solutions
can be found by modifying the design conditions as the project requires.
Changing the chilled water flow rate affects a specific chiller's performance. Too low a
flow rate lowers the chiller efficiency and ultimately leads to laminar flow. The minimum
flow rate is typically around 3 fps (feet per second). Too high a flow rate leads to vibration,
noise and tube erosion. The maximum flow rate is typically around 12 fps. The chilled
water flow rate should be maintained between these two limits.
The condenser water flows through the condenser of the chiller. The condenser is also a
heat exchanger. In this case the heat absorbed from the building plus the work of
compression leaves the refrigerant (condensing the refrigerant) and enters the condenser
water (raising its temperature). The condenser has the same limitations to flow change as
the evaporator.
Piping
The piping is usually steel, copper or plastic. The chilled water piping is a closed loop. A
closed loop is not open to atmosphere. Figure 2 shows a simple closed loop with the pump at
the bottom of the loop. Notice the static pressure created by the change in elevation is equal
on both sides of the pump. In a closed loop, the pump needs only to overcome the friction
loss in the piping and components. The pump does not need to lift the water to the top of
the loop.
LIFT
EXPANSION TANK
COOLING
LOADS
2ND FLOOR
2ND FLOOR
WATER WATER
COLUMN COLUMN
CONDENSER BASEMENT
CHILLER BASEMENT
CW PUMP
Cooling Towers
Cooling towers are used in conjunction with water-cooled chillers. Air-cooled chillers do not
require cooling towers. A cooling tower rejects the heat collected from the building plus the
work of compression from the chiller. Since it is common (but not necessary) to use a
temperature range of 10F, the cooling tower flow rate will be 3.0 gpm/ton compared to the
chilled water flow rate which is 2.4 gpm/ton. The extra condenser water flow rate is
required to accommodate the heat from the work of compression.
Chilled water coils are used to transfer the heat from the building air to the chilled water.
The coils can be located in air handling units, fan coils, induction units, etc. The air is cooled
and dehumidified as it passes through the coils. The chilled water temperature rises during
the process.
Process loads can reject heat in the chilled water in a variety of ways. A common process
load is a cooling jacket in machinery such as injection molding equipment. Here the chilled
water absorbs the sensible heat of the process.
Controls
There are two parameters that need to be considered for the chilled water loop. These are
temperature and flow. The loop supply temperature is controlled at the chiller. The unit
controller on the chiller will monitor and maintain the supply chilled water temperature
(within its capacity range). The accuracy to which the chiller can maintain the set point is
based on the chiller type, controller quality (a DDC controller with a PID loop is the best),
compressor cycle times, the volume of fluid in the system, etc. Systems with fast changing
loads (especially process loads) and small fluid volumes (close coupled) require special
consideration.
The system flow control occurs at the load. To maintain the correct space condition, three-
way or two-way control valves are used. Three-way control valves direct chilled water
either through or around the coil to maintain the desired condition. If all the loads on the loop
use three-way valves then the chilled water flow is constant. The temperature range varies
directly with the load. That is, if the design chilled water Delta-T is 10F, then every 10%
drop in system load represents 1F drop in Delta-T.
When two-way modulating control valves are used, the flow to the coil is restricted rather
than bypassed. If all the valves in the system are two-way type, the flow will vary with the
load. If the valves are properly selected, the temperature range remains constant and the
flow varies directly with the load. In this case the diversity is applied to the chilled water
flow rate.
Using the previous example, the peak load is 80 tons and the design flow is 2.4 x 80 tons or
192 gpm. The connected load is still 100 tons and requires 240 gpm if all the two-way
Parallel Chillers
Figure 8, Parallel Chillers
To provide some redundancy in the
HVAC design, most designers will
require two or more chillers. Multiple
chillers also offer the opportunity to
improve on overall system part load
performance and reduce energy
consumption.
Figure 8 shows two chillers in parallel
and three-way valves at the loads. The
chilled water temperature difference
varies directly with the load. The other
system components are the same as the
previous example. The difficulty with
this parallel arrangement is the system
part load performance.
Consider the system operating at 50%. From a chiller performance aspect, turning off one
chiller and operating the other at full capacity is desirable. However, this will not happen.
At 50% capacity, the return water will be 49F. The chiller that is turned off, will let the
water pass through it unchanged. The operating chiller will only see a 50% load (49F return
water), and will cool the water down to the set point of 44F. The two chilled water streams
will then mix to 46.5F supply temperature.
If the system is operated in this manner, the warmer chilled water will cause the control
valves to open (increase flow) to meet the space requirements. The return water
temperature will rise affecting the supply system supply water temperature. An iterative
process will occur and the system can stabilize. The issue is whether the cooling coils can
meet the local loads with the higher chilled water temperature. Depending on the actual
design conditions, the building sensible load could be met but high chilled water temperature
will make it difficult to meet the latent load. Since this scenario is likely to occur during
shoulder weather, dehumidification can not be an issue. In areas where humidity is an issue,
this arrangement will result in high humidity within the space.
One solution is to operate both chillers all the time. This works and is a simple solution,
however, it is not energy efficient and causes unnecessary equipment wear.
Another possibility is to lower the operating chillers set point to offset the mixed water
temperature. This too works but has some difficulties. Lowering the chilled water set point
Series Chillers
Figure 10, Series Chillers
Figure 10 shows two
chillers in series. This
design concept resolves the
mixed flow issues found in
parallel chiller designs. It
is simple to design and
operate. However, it also
has some challenges to
overcome.
All the system flow goes
through both chillers. If
both chillers are the same
and the condensers are
piped in parallel, the lead
chiller will accomplish
about 45% of the system load and the lag chiller will accomplish about 55% of the system
load. This occurs because the lead chiller is supplying chiller water at the system set point
(typically 44F). The lag chiller is supplying chilled water at approximately 48.5F to the lead
chiller. The reduced lift for the lag chiller allows it to provide more cooling capacity.
A problem with series chillers is the high flow rate and the low Delta T through the chillers.
The high flow rate can result in high water pressure drops. Since the chillers are in series,
the pressure drops of the chillers must be added. If the typical 10F system temperature
Table 1 compares a parallel system with two versions of series systems for an 800 ton
design load. The full load penalty for series option 1 compared to the parallel system is
negligible. Series Option 2 shows chillers with series condenser flow. It provides the best
overall system performance and either chiller can be the lead chiller. Series condensers and
series evaporators are an excellent means to provide lower temperature, high Delta-T chilled
water.
It should not be concluded that parallel systems have no value. In applications where most
of the operating hours occur above 50% load, a parallel system typically does better. A
series system does better when there lots of run hours below 50% such as an HVAC system
without air side economizers.
Series Chillers Controls
As before, the chiller controllers maintain the system supply water temperature and the load
controls maintain the system flow rate. For series chillers, the controlling sensors for both
chillers should be located downstream of the chillers and the chiller control panels digitally
linked together. With the panels linked together, either chiller can be used to meet up to
about 45% of the system load. Once both chillers are required, the amp draws can be
balanced between the two chillers.
The MicroTech Controllers on McQuay chillers can communicate directly and can load
balance based on amperage. Using the load balance feature means when both chillers
operate, the power consumption is evenly distributed between the two chillers. The load
balance feature offers about 3% savings conventional control.
Primary/Secondary Systems
For large chillers or where more than 2 chillers are anticipated, primary/secondary (also
called decoupled) piping systems are used. To reduce installation and operating costs, it is
desirable to apply diversity to system flow. With diversity applied to flow, the pumps and
piping will be smaller. To accomplish this, two-way control valves are used at the loads. At
the same time it is necessary to provide constant flow through the chillers to maintain chiller
stability. The solution is primary/secondary piping.
SECONDARY PUMP
VFD
PRIMARY PUMP
44F
C H ILL ER 44F
44F
800 TONS A LOAD
(DECOUPLER) 800 TONS
COMMON
0 gpm
PIPE 54F
B
54F
54F
1920 gpm 1920 gpm
VFD
PRIMARY PUMP
44F
44F
1920 gpm
CHILL ER
44F
400 TONS A (DECOUPLER) LOAD
400 TONS
COMMON
960 gpm
PIPE 54F
B
49F 49F 960 gpm
54F
1920 gpm
SECONDARY PUMP
VFD
PRIMARY PUMP
44F
44F
1920 gpm (DECOUPLER)
CHILLER
44F COMMON
480 TONS A PIPE LOAD
800 TONS
1280 gpm
50F
B
50F 1920 gpm 3200 gpm
50F
50F
VFD
PRIMARY PUMP
1920 gpm
44F 44F
44F
3840 gpm
CHILLER
CHILLER
44F
400 400 A (DECOUPLER) LOAD
TONS TONS 800 TONS
640 gpm COMMON
44F PIPE
50F
B
49F 49F 3840 gpm 3200 gpm
50F
49F
Obviously the above example cant occur. Figure 14 shows what does happen. A second
chiller has to be started to balance the flow in the primary loop with the flow in the
secondary loop.
Although running two chillers provides a working solution, many of the features of the
primary/secondary approach are lost. The flow in the secondary is high, wasting pumping
energy. Two primary pumps have to operate when only one should be doubling the primary
pump horsepower. Finally, two chillers are operating (and their condenser water pumps)
when only one should be.
Primary Loop Details
Figure 15, Standard Primary Loop Layout
The most common arrangement
is to have dedicated pumps for
each chiller. In addition, each
chiller requires an isolating valve.
It is also possible to have a main
primary pump outfitted either with
multiple speeds or a variable
frequency drive. The issue with
the latter is there is minimal to no
redundancy available.
The chillers can have different
capacities and be manufactured
by different vendors. However,
they must have the same supply
water set point and the same
chilled water Delta-T.
Relocating the decoupler can make sense if one or more of the chillers is a dual compressor
model. The dual compressor chiller has very good part load performance. Single
compressor chillers typically work best when fully loaded. By locating the dual compressor
chiller close to the decoupler line and the single compressor chiller furthest away, the
strengths of each chiller can be maximized. Table 2 shows the chiller plant performance for
Figures 15 and 16. By base loading the single compressor chiller and taking advantage of
the duals part load performance, the power input can be cut by up to 10 percent.
Hybrid Plants
Mixing and matching different chiller types increases the designers option in chiller plant
design. To meet small winter chilled water loads, an air cooled chiller might be included in
the chiller plant. The operator does not have to run the cooling towers in winter and the
chiller is properly sized for the winter load. This is common in health care applications with
water cooled equipment (MRIs, linear accelerators, etc.) The air-cooled chiller must be
properly selected for winter operation.
To diversify the chiller plant on energy sources, an absorption chiller is often incorporated
into the chiller plant design. The absorption chiller can operate on either plant steam or
directly on natural gas. Either allows the operator to shave demand peaks for the electrical
load. The absorption chiller can be in series or parallel (primary/secondary) with the ele ctric
chiller.
In a series application, the absorption chiller can be upstream of the electric chiller. The
warmer return chilled water improves the efficiency of the absorption chiller by as much as
30%. This arrangement automatically base loads the electric chiller. Until the return water
reaches 49F, the absorption chiller wont operate. Once the building load climbs above
50%, the electrical demand is avoided, by using the absorption chiller. In shoulder weather,
either chiller can be operated. (reset the absorption chiller set point to 44F).
The condenser water needs of the absorption chiller are different from the electric chiller.
Whereas electric chiller typically operates with 3 gpm/ton on the condenser side, an
absorption chiller operates with 4.5 gpm/ton. Condenser water temperature stability and
reset are also more critical with an absorption chiller. Care must be taken to properly
integrate an absorption chiller into the chiller plant design.
Selecting the chiller with tube velocities near 10 fps allows the system flow to be turned
down to 30% of design flow. The designer should work with the actual minimum and
maximum flow rates for the chiller selected on the project. The chiller manufacturer can
provide this information.
If all the control valves are two-way, a bypass will be required and sized for the chillers
minimum flow rate (approximately 30% of design flow). Alternatively, some three-way
valves can be used to provide minimum flow rate is maintained. However, the three-way
valves will consume their design flow whether the fluid goes through the load or around it.
This will reduce the overall pump savings potential. From an energy point of view, the pump
Variable flow can also be applied to chillers in parallel. Figure 23 shows two chillers in
parallel with VFDs on the primary pumps. Variable flow allows the option of operating only
one chiller when the system load is within the range of one chiller. The second chiller can be
shut down and all the flow directed through the remaining chiller. Variable flow resolves
most of the issues of parallel chiller design.
The bypass should be sized for the highest minimum flow rate of the chillers being used.
The critical issue for variable flow with parallel chillers is controlling the cycling of the
chillers. This is best accomplished by measuring system flow. When the system load and
flow rate can be met by a single chiller, the other chiller can be shut down. With one
pump/chiller combination off line, the other pump will increase speed/flow until the required
chilled water loop pressure differential is obtained. If the single chiller minimum flow cannot
be met (the two valves are all nearly closed) the bypass line control valve can be opened to
provide minimum chiller flow. Chiller/pump cycling should be controlled with anti-cycle time
delays.
Even with modern chiller controllers, care should be taken that the system flow changes are
slow. Slow flow changes will allow the chiller controller time to respond and provide stable
system operation. Although each project is different, a good rule of thumb is to limit the rate
of change to 10% of design flow per minute.