Frosh Latest Purple Line Case Filing - 4-10-17
Frosh Latest Purple Line Case Filing - 4-10-17
Frosh Latest Purple Line Case Filing - 4-10-17
Plaintiffs, *
v. *
and *
Defendant Intervenor. *
* * * * * * * * *
The premise of the State of Marylands (State) Motion For Expeditious Ruling is that
the passage of time has changed the status quo in this case. With no decision from the Court on
Environmental Impact Statement (SEIS), and no decision on the remaining issues addressed in
the long-completed summary judgment motions, the mere passage of time may create the
outcome that Plaintiffs clearly seek - abandonment of the Purple Line project (the Project). It
would be an injustice to the people of the State and to the FTA not to have a decision on the
merits of Plaintiffs claims regarding the August 2013 Final Environmental Impact Statement
1
Case 1:14-cv-01471-RJL Document 135 Filed 04/10/17 Page 2 of 6
and the March 2014 Record of Decision (ROD) in a timeframe that will not cause grave harm
to the Project. The State submitted this Motion to the Court to assure that the Court was
When the Court issued its August 3, 2016 Order vacating the ROD approving the Project,
it did so intending to preserve the status quo. As stated in the Courts August 3 Memorandum, a
temporary halt in the project would allow the FTA to engage in the requisite supplemental
analysis with respect to impacts of safety and ridership issues being experienced by the
Washington Metro on the viability of the Purple Line. The Court recognized that speed was of
the essence in reaching a resolution of the issues, stating that the State should prepare the
implications, the Defendants began the requisite supplemental analysis immediately. The
analysis has been prepared, and FTA has issued a decision on the analysis and submitted that
analysis and decision to the Court. All issues are ripe for a decision.
When Plaintiffs filed this case in 2014, they failed to seek any preliminary injunctive
relief. Even when it became clear that the FTA and the State were about to sign the Full Funding
Grant Agreement (FFGA), Plaintiffs did not seek any form of preliminary injunctive relief. As
this Court noted in its August 3 Order, it chose to issue a decision that addressed the single flaw
it had identified in FTAs analysis and vacate the ROD, so that the FTA would not be able to
issue the FFGA. By doing this, the Court prevented the State from proceeding with construction
of the project. The Court clearly determined that a short delay would preserve the status quo.
The State takes the unusual step of filing this motion to inform the Court that further delay goes
beyond monetary delay damages and puts the entire project at risk. Without an expeditious
2
Case 1:14-cv-01471-RJL Document 135 Filed 04/10/17 Page 3 of 6
The mere passage of time causes grave harm to the State, Montgomery County, Prince
Georges County, and the businesses and citizens who are relying on the Project to create jobs
and to improve access to public and commercial facilities and neighborhoods. The loss of the
Project would be monumental, as are the potential monetary damages. As previously established
in the declarations filed by Charles Lattuca (ECF 98-3 and 116-2), each month of delay could
result in an estimated $13 million in additional cost. Also, as previously discussed, further delay
puts at risk the $400 million that the State has already invested in making this vital public transit
project a reality. In addition, termination of the Project could result in additional termination
costs and delay damages, resulting in a total cost in the range of $650 million. ECF 116-2 at 15.
Given the decades of study, broad public support, and the importance of the Project to the local
communities (see the amicus briefs and supporting declarations filed by Prince Georges County
- ECF 111 and Montgomery County - ECF 112), cancellation of the Project as a result of
litigation delays would cause severe prejudice to the interests of the public.
It is clearly in the public interest to reach a decision on the legal issues as expeditiously
as possible. Nothing in Plaintiffs response to the States motion provides a reason for the
Court to delay its decision. Contrary to Plaintiffs assertion, the State does not dispute that the
Court has the inherent power to control its docket. Plaintiffs are correct that the State is
confident that the FEIS and the additional analysis of the Metro rail issues are sufficient under
applicable law and that once the Court has an opportunity to review the full merits of the case, it
will rule in the States favor. However, even should the Court find a flaw in the process, it is in
the public interest for the Court to issue an expeditious final decision on the merits of the claims
raised in this case so that the State can take whatever further steps it deems necessary in its
efforts to pursue and implement this vital transportation project. If the Courts docket does not
3
Case 1:14-cv-01471-RJL Document 135 Filed 04/10/17 Page 4 of 6
permit an expeditious review of the now completed supplemental analysis, which was the basis
for vacation of the ROD, the preservation of the status quo dictates that the ROD be reinstated
Conclusion
The State respectfully requests that the Court issue a final decision as expeditiously as
possible, but no later than April 28, 2017, on all pending dispositive motions in this case,
including the parties cross-motions for summary judgment (ECF 47, 55, 56) and the
Defendants renewed motions for summary judgement (ECF 115, 116). In the alternative, the
State requests that the Court vacate that portion of its August 3, 2016 Order (ECF 96) that
4
Case 1:14-cv-01471-RJL Document 135 Filed 04/10/17 Page 5 of 6
BRIAN E. FROSH
Attorney General of Maryland
5
Case 1:14-cv-01471-RJL Document 135 Filed 04/10/17 Page 6 of 6
CERTIFICATE OF SERVICE
I hereby certify that on April 10, 2017, a copy of the foregoing document was served via the
CM/ECF system on the following counsel of record.
David Brown
Knopf & Brown
brown@knopf-brown.com
Kevin W. McArdle
U.S. Department of Justice
Keven.mcardle@usdoj.gov
Jeremy Hessler
U.S. Department of Justice
Jeremy.hessler@usdoj.gov
Tyler L. Burgess
U.S. Department of Justice
Tyler.burgess@usdoj.gov
John M. Fitzgerald
4502 Elm Street
Chevy Chase, MD 20815
johnmfitzgerald@earthlink.net